You are on page 1of 7

APPENDIX 3B

Letters incoming from LTA / other Authorities

S/No
Date LTA Letter REF Subject Status / C&V
No. Remarks Ref. No.

1 23-Nov-10 R40.001.002 Submission of Drain Shop For Record ______


Drawings

2 25-Nov-10 R40.001.002 Submission of Monthly Progress Noted 5003


Report

3 26-Nov-10 R40.001.002 Method of Statement for Drain, Noted with 5008


Culvert & Sump Construction comments

4 26-Nov-10 R40.001.002 Proposed Material - For Record ______


Geocomposite & Geotextile

5 26-Nov-10 R40.001.002 Submission of Typical Traffic For Record ______


Arrangement Plan (rev 1)

Submission of Monthly Safety,


6 26-Nov-10 R40.001.002 Health & Environment (SHE) For Record ______
Report

Reply Letter Re. Submission for


7 29-Nov-10 R40.001.002 MOS for Drain, Culvert & Sump For Record ______
Const.

Reply Letter Re. Proposed


8 3-Dec-10 R40.001.002 Material - Non Skid Aluminium For Record ______
Rung

Reply Letter Re. Submission of


9 3-Dec-10 R40.001.002 Endorsed Typical Traffic For Record ______
Arrangement Plan

10 3-Dec-10 R40.001.002 Reply Letter Re. Proposed For Record ______


Material - UPVC Pipes

Submission of MOS for Ultimate Noted with


11 6-Dec-10 R40.001.002 Load Test of 800mm Dia Bored 5010
comments
Pile

12 8-Dec-10 R40.001.002 Proposed Material - Concrete Noted with 5011


Curing & Touch Up Products comments

13 9-Dec-10 R40.001.002 Reply Letter Re. Submission Of For Record ______


MOS For Bored Piling Works
14 7-Jan-11 R40.001.002 Reply Letter Re. Project Quality For Record ______
Plan
15 7-Jan-11 R40.001.002 Reply Letter : ULT 1 Test Report Replied with 5014
No Comments

16 7-Jan-11 R40.001.002 Commencement of Services for Noted ______


2nd RTO

Submission of Shop Drwgs for


17 10-Jan-11 R40.001.002 Cast in Situ RCU Drain at SL02 Ch Replied with 5018
No Comments
660-675

Resubmission of Proposed
18 10-Jan-11 R40.001.002 Material - Concrete Curing & Replied with 5015
Touch Up Products No Comments

Resubmission for Method of


19 10-Jan-11 R40.001.002 Statement for Drain, Culvert & Replied with 5017
Sump Construction (Rev 1) No Comments

20 10-Jan-11 R40.001.002 Resubmission for Proposed Replied with 5016


Material - Skim Coat No Comments

Submission of Temporary Slope Noted With


21 10-Jan-11 R40.001.002 Design Calculation For Bored Piles 5019
Const (Part 1) Comments

Re : Resubmission of Proposed
22 14-Jan-11 R40.001.002 Material - Concrete Curing & Noted ______
Touch Up Products

23 14-Jan-11 R40.001.002 Re : Resubmission of Proposed Noted ______


Material - Skim Coat

Re : Resubmission of MOS For


24 14-Jan-11 R40.001.002 Drain, Sump, & Culvert Const (Rev Noted ______
1)

Submission Of Method of Replied with


25 25-Jan-11 R40.001.002 Statement for Bore Pile Head 5024
No Comments
Trimming

26 25-Jan-11 R40.001.002 Assessment of Ultimate Load Test Replied with 5023


Result No Comments

27 25-Jan-11 R40.001.002 Submission of Crawler Crane & Noted ______


Piling Machine Test Certificates

25 16-Feb-11 R40.001.001 Commencement of Services for Noted ______


2nd RTO

26 22-Feb-11 R40.001.002 Proposed Material - High Ribbed Replied with 5025


Mesh No Comments

27 22-Feb-11 R40.001.002 Submission of Instrumentation Replied with 5029


Monitoring Report - 02 No Comments

28 10-Mar-11 R40.001.002 Method Of Statement for Plate For Record ____


Bearing Test

29 11-Mar-11 R40.001.002 Submission Of Intergrity Test For Record ____


Report For Bored Pile "P-17"
30 23-Mar-11 R40.001.002 Staff Changes For Record ____

31 5-Jul-11 R40.001.002 Replacement of RTO-2 For Record ____


32 5-Jul-11 R40.001.002 Replacement of RTO-2 For Record ____

33 10-Nov-11 R40.001.002 PIT Test Report For Micropile no. Replied with 5072
19 No Comments

34 10-Nov-11 R40.001.002 Method Of Statement for Replied with 5069


Manufacturing of PSPC Beam No Comments

35 10-Nov-11 R40.001.002 Construction sequence for Type Replied with 5071


1,2 Portal Frame & PSPC Bridge No Comments

36 10-Nov-11 R40.001.002 Submission of G55 & G60 Trial Replied with 5070
Mix Concrete Cube Test Results No Comments

37 10-Nov-11 R40.001.002 Cube Summary Reports (April Noted With 5076


2011 to September 2011) Comments

38 10-Nov-11 R40.001.002 Submission of Shop Drawings for Replied with 5073


PSPC Beams No Comments

39 11-Nov-11 R40.001.002 Replacement of RTO-2 For Record ____

40 14-Nov-11 R40.001.002 PIT Test Report For Bored Pile no. Replied with 5075
BP6 No Comments

41 18-Nov-11 R40.001.002 Construction Drawings for Bridge Replied with 5081


Pier Falsework No Comments

42 11-Nov-11 R40.001.002 Replacement of RTO-2 For Record ____

43 14-Nov-11 R40.001.002 PIT Test Report For Bored Pile no. Replied with 5075
BP6 No Comments

44 18-Nov-11 R40.001.002 Construction Drawings for Bridge Replied with 5081


Pier Falsework No Comments

45 15-Dec-11 R40.001.002 Cube Summary Reports (October Replied with 5077


2011) No Comments

46 15-Dec-11 R40.001.002 Cube Test Reports for Micropiles Replied with 5075
No Comments
Tensile, Ben & Rebend Test Replied with
47 15-Dec-11 R40.001.002 Reports For Rebars Samples 5079
No Comments
(Decking Works)

48 10-Dec-11 R40.001.002 Project Quality Plan For Approval For Record ___

49 19-Dec-11 R40.001.002 Bored Pile Records (Part 2 Works) Replied with 5083
No Comments

50 19-Dec-11 R40.001.002 Cube Summary Reports (April Replied with 5075


2011 to September 2011) No Comments
Tension, Load Test Report For T40 Noted With
51 15-Dec-11 R40.001.002 MCC PositionCoupler & Control 5080
Comments
Bar (Micropiling Works)

52 21-Dec-11 R40.001.002 Pot Bearing Design (Rev A) Replied with 5086


No Comments

53 21-Dec-11 R40.001.002 Method Statement for Beam Replied with 5087


Launching No Comments

54 7-Jan-12 R40-001.002 Cube Summary Reports Replied with 5084


(November 2011) No Comments

Fortnightly Interpretative
55 8-Feb-12 R40.001.002 Instrument Monitoring Report No Replied with 5091
6-11 at Part 2. Changi North No Comments
Cresent CBP Wall

56 8-Feb-12 R40.001.002 PDA Test Report For Bored Pile No Replied with 5090
BP2 Comments

57 10-Feb-12 R40.001.002 Leave of RTO - Devnani Amit For Record ___

58 10-Feb-12 R40-001.002 Proposed Rectification method Replied with 5089


for PSPC Beam Crack Edges Comments

59 1-Feb-12 R40-001.002 Shop Drawing For Grating at the Replied with no 5092
Bridge (Slip 01 L) Comments
60 28-Feb-12 R40-001.002 Method Statement for Testing of Replied with no 5093
Pot Bearing Comments

61 28-Feb-12 R40-001.002 Method Statement for Installation Replied with no 5094


of Pot Bearing Comments

62 2-Mar-12 R40-001.002 Signboard Shop Drawing Replied with no 5095


Comments
Propose to use boom lift as
63 18-Apr-12 R40-001.002 Platform for the Parapet Wall Noted with No 5096
Construction from Gridline A1 to Comments
A2

64 18-Apr-12 R40-001.002 Design Calculation of Circular Noted with 5097


Shaft Shoring for Sewer Manhole Comments

Propose to use boom lift as


Platform for the Parapet Wall Noted with No
65 27-Apr-12 R40-001.002
Construction from Gridline A1 to Comments
5100
A2

Method Statement on Temporary


shaft construction & site Replied with
66 10-May-12 R40-001.002
utilization plan at Manhole 7 &8 No Comments
5098
(Sewer Diversion)

Propose Planting of T20-150


Starter Bars with 180mm
embedment depth to replace the Noted with
67 23-May-12 R40-001.002
misaligned parapet wall starter Comments
5099
bars which were cast at SLIP01_L
CH 295.5-298

Propose Conbextra STD as the


Noted with No
68 2-Jun-12 R40-001.002 Grout Bedding Material for P1 Comments
5101
Railing

Construction Drawings For Noted with No


69 27-Jun-12 R40-001.002 Standard Details for Signboard on Comments
5102
Parapet Wall