You are on page 1of 56

FRONT END ENGINEERING DESIGN (FEED)

FOR REPLACEMENT OF OLD 3-PHASE TEST


SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

RECORD OF CHANGES

REV DATE DESCRIPTION

0 19-12-2012 ISSUED FOR COMMENTS

1 24-01-2013 ISSUED FOR APPROVAL

2 13-02-2013 RE-ISSUED FOR APPROVAL

3 05-03-2013 APPROVED FOR DETAILED DESIGN

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 2 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Table of Contents Page

1. INTRODUCTION ................................................................................................................ 5

1.1 Purpose............................................................................................................................... 5

1.2 Definitions & Abbreviations ................................................................................................. 6

1.2.1 Definitions ............................................................................................................................ 6

1.2.2 Abbreviations ....................................................................................................................... 7

1.3 CODES AND STANDARDS ............................................................................................... 9

1.3.1 American Society of Mechanical Engineers .......................................................... 9

1.3.2 National Association of Corrosion Engineers ........................................................ 9

1.3.3 British Standards .................................................................................................. 10

1.3.4 Company Specifications ...................................................................................... 10

1.3.5 Project Specifications........................................................................................... 11

1.3.6 Shell DEP ............................................................................................................. 11

1.3.7 Datasheet ............................................................................................................. 11

1.3.8 Drawings .............................................................................................................. 12

1.3.9 Others .................................................................................................................. 12

1.4 SCOPE OF WORK & SUPPLY ........................................................................................ 13

1.4.1 GENERAL ............................................................................................................ 13

1.4.2 INCLUSIONS ....................................................................................................... 13

1.4.3 EXCLUSIONS ...................................................................................................... 14

2. DESIGN DATA ................................................................................................................. 15

2.1 GENERAL ......................................................................................................................... 15

2.2 DATA SHEET FOR VESSEL............................................................................................ 15

2.3 ENVIRONMENTAL DATA ................................................................................................ 15

2.4 DESIGN LIFE ................................................................................................................... 17

3. TECHNICAL REQUIREMENTS ....................................................................................... 18

3.1 GENERAL ......................................................................................................................... 18

3.2 MATERIAL ........................................................................................................................ 18

3.3 DESIGN ............................................................................................................................ 19

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 3 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

3.4 APPURTENANCES AND ACCESSORIES ...................................................................... 24

3.5 FABRICATION .................................................................................................................. 26

3.6 REPAIRS .......................................................................................................................... 28

3.7 TOLERANCES ................................................................................................................. 28

4. INSPECTION AND TESTING........................................................................................... 29

4.1 INSPECTION .................................................................................................................... 29

4.2 TESTING .......................................................................................................................... 30

4.3 CERTIFICATION REQUIREMENTS ................................................................................ 31

5. STAMPING AND RECORDS ........................................................................................... 32

5.1 STAMPING ....................................................................................................................... 32

5.2 RECORDS ........................................................................................................................ 32

6. SPARE PARTS AND SPECIAL TOOLS .......................................................................... 34

6.1 SPARE PARTS ................................................................................................................. 34

6.2 SPECIAL TOOLS ............................................................................................................. 34

7. SURFACE PREPARATION AND PAINTING ................................................................... 35

8. ENGINEERING DESIGN PACKAGE CONTENT (DELIVERABLES) .............................. 36

8.1 GENERAL ......................................................................................................................... 36

8.2 DRAWING DOCUMENTATION........................................................................................ 36

8.3 APPROVAL PROCEDURE .............................................................................................. 37

8.4 APPROVAL OF DRAWINGS AND DOCUMENTS........................................................... 37

8.5 DISPATCH OF APPROVED DRAWINGS AND DOCUMENTS....................................... 38

8.6 SUBMISSION TIME OF DRAWINGS AND DOCUMENTS .............................................. 38

9. RESPONSIBILITY ............................................................................................................ 39

10. QUALITY ASSURANCE ................................................................................................... 40

11. GUARANTEE ................................................................................................................... 41

12. HANDLING ....................................................................................................................... 42

12.1 PACKING & SHIPPING................................................................................................ 42

12.2 PRESERVATION & STORAGE ................................................................................... 42

13. ATTACHMENTS ............................................................................................................... 43

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 4 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

1. INTRODUCTION

QP intends to replace the existing old 3-Phase Test Separators with suitably sized new 3-Phase Test
Separators for all seven degassing stations in Dukhan. Currently, two test separators, one the old
Test Separator (6,000 bpd capacity) and another a new Test Separator (10,000 bpd capacity) are
provided for assessing the composition of individual producing wells. With the implementation of this
project, the existing old Test Separators of all seven degassing stations shall be demolished and
replaced with new Test Separators.

1.1 Purpose
The purpose of this specification is to define the minimum requirements for the engineering, design,
materials, fabrication, welding, inspection, testing, cleaning, painting for the new 3-Phase Test
Separators and its necessary internals. This technical specification also summarizes the minimum
technical requirements of the necessary process internals & sand removal systems.

It is also intended to supplement the minimum requirements of the applicable international codes &
standards and project & client specifications.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 5 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

1.2 Definition s & Abbreviations

1.2.1 Definitions
For the purposes of this specification, the following definitions shall apply:

The Legal Status of any person or company authorised by QP to act on


QPs behalf on the matters specified in the agency agreement or contract.
AGENT Third parties can usually rely on the agent as an acting behalf of and with
the authority of QP, provided that the agent acts within the scope of his
apparent authority from QP.

APPROVAL Indicates agreement/sanction which shall be in writing only.


COMPANY/CLIENT Qatar Petroleum
CONSULTANT
A company awarded a contract by QP for the company to advise or give
guidance on specific subjects. The Scope of work may include instructions
to act as an agent for QP (see Agent)

CONTRACTOR
The party, which carries out all or part of the design, engineering,
procurement, construction, commissioning, or management of the Project,
also addressed as EPIC Contractor.

FEED CONTRACTOR
The party, which carries out all or part of the Front End Engineering
Design of the Project.

MAY Used where alternatives are acceptable, subject to COMPANY approval.

MANUFACTURER / The party, which manufactures and/or supplies equipment, technical


VENDOR / SUPPLIER documents/drawings and services to perform the duties specified by
COMPANY/CONTRACTOR.

MATERIALS- The equipment/materials and/or services, which are required to provide to


EQUIPMENT/SERVICES COMPANY.

MUST / SHALL A mandatory requirement

ORDER The purchase order of which these terms and conditions form a part,
including all attachments thereof, all documents, plans, drawings and the
like incorporated by reference and any additions, alternations and/or
modifications to any of them authorised by COMPANY/CONTRACTOR.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 6 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

PREFERRED Used where a provision is non-mandatory, but where compliance with the
requirements preferred by COMPANY and will be favoured during
technical bid evaluation of tenders.

Front End Engineering Design (FEED) for Replacement of Old 3-Phase


PROJECT
Test Separators at all Degassing Stations, Dukhan Field

PURCHASER The organisation responsible for performing the purchasing function.

SHOULD A recommendation, which is preferred, but the supplier may or may not
adhere to.

1.2.2 Abbreviations

Abbreviation Full Description

AFC Approved for Construction


AISC American Institute of Steel Construction
ANSI American National Standards Institute
ASME American Society of Mechanical Engineers
AWS American Welding Society
Bara Pressure in bar absolute
Barg Pressure in bar gauge
BS British Standard
CS Carbon Steel
DBM Design Basis Memorandum
DNV Det Norske Veritas
EL Elevation
EN European Standard
EPIC Engineering, Procure, Installation and Commissioning
ES Engineering Standard
HAZ Heat Affected Zone
HSE Health Safety and Environment
ID Internal Diameter
IRC Inspection Release Certificate
ISO International Organization for Standardization
M Meter
mm Millimetre

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 7 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

NACE National Association of Corrosion Engineers


NDT Non Destructive Testing
PVL Preferred Vendor List
PWHT Post Weld Heat Treatment
QP Qatar Petroleum
SI International System of Units
SPIR Spare Parts Interchangeability Record
TPC Third Party Certification
TPI Third Party Inspection Agency
GTAW Gas Tungsten Arc Welding
SAW Submerged Arc Welding
SMAW Shielded Metal Arc Welding

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 8 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

1.3 CODES AND STANDARDS

1.3.1 American Soc ie ty of Mechanica l Engineers


Document No. Title

ASME Section II Boiler and Pressure Vessel Code - Material Specifications

ASME Section V Boiler and Pressure Vessel Code - Non Destructive Examination

ASME Section VIII Boiler and Pressure Vessel Code Rules for Construction of
Div. 1 Pressure Vessels

ASME Section IX Boiler and Pressure Vessel Code-Welding and Brazing Qualification

ASME B1.1 Unified Inch Screw Threads

ASME B16.5 Pipe Flange and Flange Fittings

ANSI B 16.11 Forged Steel Fittings, Socket Welding and Threaded

ASME/ANSI B16.9 Butt Weld Fittings

Metallic Gaskets for Pipe Flanges Ring Joint, Spiral Wound and
ASME B16.20
Jacketed

ASME B16.21 Non-metallic Flat Gaskets for Pipe Flanges

ASME B 16.47 Large Diameter Steel Flanges

ASME B 18.2 Square and Hexagonal Bolts and Nuts

ASME B 31.3 Process Piping

ASME B36.10 Welded and Seamless Wrought Steel Pipe

ASME B36.19M Stainless Steel Pipe

1.3.2 National Association of Corrosion Engineers


Document No. Title

NACE MR 0175/ Materials for use in H2S containing environments in Oil and Gas
ISO 15156 production

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 9 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

1.3.3 British Standards


Document No. Title

Stresses in large horizontal cylindrical pressure vessels in two-


BS5500 Appendix G
saddled supports by L.P. Zick

BS 6399-2 Loading for Buildings - Part 2: Code of Practice for Wind Loads

BS EN 10204 / ISO
Metallic Products - Type of inspection document
10474

1.3.4 Company Spec ifications


In addition to compliance to codes/ specifications/ standards/ documents listed below, all the
requirements specified in codes/ specifications/ standards/ documents listed in document
EFS.00.08.02 latest revision shall also be fully complied. Contractor shall verify latest revision of the
document and obtain the same from the COMPANY.

Document No. Title

EFS.00.05.013 Guideline for Enforcement of Compliance with Sour Service Material


Requirements

EFS.00.05.04 Guidelines for Completion of SPIR Forms

EFS.00.08.02 List of QP Standards and Specifications

EFS.00.08.03 Standard Offshore Metocean & Environmental Conditions

EFS.00.08.04 Specification for Equipment Preservation, Protection & Packaging

ES.5.06.0001 Engineering standard Engineering of Pressure Vessels

ES.5.06.0003 Engineering standard Pressure Vessel Design and Fabrication

ES.5.06.0019 Flange Bolting Guidelines

ES.D.10 Manual Engineering Standards for Draughting

Specification for the Fabrication, Installation and Erection of Steel,


ES.S.20
Structures and Structural Steel Work

ES.S.60 Specification for the Non Destructive Testing of Welds

QP Guideline Waste Management for Offshore Operations and Halul


GD-ENV-001
Island

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 10 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Document No. Title

QP-REG-Q-001 QP Lifting Equipment Technical Regulations

QP-SPC-L-002 Specification for Painting and Wrapping for Metal Surfaces

QP-STD-Q-003 Corporate Standard for Quality Requirements for Procurement of


Materials & Equipment

QP-STD-Q-004 Corporate Standard for Quality Requirements for Projects

QP-STD-R-001 Technical Standard for Materials for Sour Service

QP-STD-R-002 Specification for the Fabrication, inspection and Installation of Carbon,


Carbon-Manganese and Low Alloy Ferritic Process Pipe work

1.3.5 Project Specifications


Document No. Title

3071-DGEN-5-14-0011 Piping Material Specification

3071-DGEN-5-14-0002 Technical Specification for Fittings

3071-DGEN-5-14-0003 Technical Specification for Flanges

3071-DGEN-5-14-0004 Technical Specification for Pipes

1.3.6 Shell DEP


Document No. Title

DEP 31.22.05.12-Gen, Liquid/Liquid and Gas/Liquid/Liquid Separators- Type Selection &


Edition-Feb 2012 Design Rules

1.3.7 Datasheet
Document No. Title

Cancelled / Deleted Cancelled / Deleted

3071-DGEN-5-13-0001 Mechanical Datasheet New 3 phase test separators

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 11 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

1.3.8 Drawings
Drawing No. Title

P&ID for New 3-Phase Test Separator (at Khatiyah Main


3071-KAHM-6-50-0306
Station)

P&ID for New 3-Phase Test Separator (at Khatiyah North


3071-KAHN-6-50-0301
Station)

P&ID for New 3-Phase Test Separator (at Khatiyah South


3071-KAHS-6-50-0009
Station)

3071-JALM-6-50-0301 P&ID for New 3-Phase Test Separator (at Jaleha Station)

3071-FAHM-6-50-0011 P&ID for New 3-Phase Test Separator (at Fahahil Main Station)

3071-FAHM-6-50-0009 P&ID for New 3-Phase Test Separator (at Fahahil North Station)

3071-FAHM-6-50-0010 P&ID for New 3-Phase Test Separator (at Fahahil South Station)

1.3.9 Others
Document No. Title

ISO 9001 Quality Systems

Welding Research Council Bulletins Nos. 107. Local Stresses on


WRC 107
spherical and cylindrical shells due to external loading

Welding Research Council Bulletins Nos. 297. Local Stresses on


WRC 297
cylindrical shells due to external loading on nozzles

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 12 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

1.4 SCOPE OF WORK & SUPPLY

1.4.1 GENERAL

VENDORs scope of work shall comprise of supply of the following vessel in accordance with this
specification, datasheets, standards and drawings attached or referred in this specification.

Tag Number Description Quantity Location


24-V-XXX1,
22-V-XXX1, 3-Phase Test Separators Seven (7) Dukhan Field
23-V-XXX1,
14-V-XXX1,
12-V-XXX1,
13-V-XXX1 &
31-V-XXX1

- Separator Internals (VTA) Dukhan Field

1.4.2 INCLUSIONS

The test separators shall be designed and fabricated complete by duly approved VENDOR (Vessel
Manufacturer) and shall include but not limited to the following items:

1) Design and Engineering of Separators as per ASME Sec. VIII Div. 1 & U1 Stamp requirement.
2) Design of steel saddles as per L.P. Zick method.
3) Material Procurement, Fabrication for complete vessel (Cylindrical Shell, Head, Saddles, Nozzles,
Manhole with blind flange, bolting & Davit, Companion flanges, reinforcement pads, all necessary
process internals (welded & removable), lifting lugs etc.) conforming to the minimum requirement
specified in this specification, & Data sheets.

4) To enhance oil/water/gas separation to improve well testing accuracy, typically below listed
internals are recommended for the 3-Phase Test Separator. However, Vendor shall recommend
his own internals based on the process conditions stated in datasheet & process guarantee
expected.

i) Feed Inlet Device

ii) Baffle Plate or Distributor Plate

iii) Mesh Pad(or other) on the vapour outlet nozzle

iv) Vortex Breakers on Oil & Water Outlet nozzles

v) Coalescer

vi) Weir Plate

vii) Sand Removal System

5) All the associated instrumentation accessories.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 13 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

6) Platforms and ladders.


7) Manufacturer & ASME Name Plate.
8) Earthing lugs.
9) Surface preparation & painting.
10) External cleats (ladder support, pipe support etc.)
11) Necessary cleats/supporting arrangement welded inside the shell to install all the process
internals.

12) Providing foundation Loading Design Data for foundation design


13) Design of foundation bolts
14) Spare parts for installation, commissioning and two-years operation
15) Special tools and lifting equipment for maintenance
16) All inspection and testing including Third Party Inspection
17) Post Weld Heat Treatment (PWHT)
18) NDT Examination
19) Preservation and packing
20) Hydro static testing
21) Submission of procedures / method statements
22) Documentation according to this specification.

1.4.3 EXCLUSIONS

The following shall not be part of VENDOR scope of work. However it shall be part of CONTRACTOR
scope of work.

1) Erection.
2) Commissioning.
3) Third Party Inspection charges.
4) Foundation design.
5) Supply of anchor bolts.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 14 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

2. DESIGN DATA

2.1 GENERAL
The new Test Separators shall be designed to handle higher capacity (10000 BPD), varied water cuts
ranging from 0% to 95% & shall be equipped with more reliable and accurate flow measuring devices
compared to the existing ones for measuring the entire range of gas, oil and water flow rates. Design
shall also include the latest technology for the internals in order to enhance oil/water/gas separation
to improve well testing accuracy. The new 3-Phase Test Separators shall be equipped with jet
nozzles to support online cleaning of the accumulated solids in the bottom of the vessel to maintain
retention volume and to prevent the formation of Sulphate Reducing Bacteria colonies within the
solids accumulated in the bottom of the vessel.

2.2 DATA SHEET F OR VESSEL


VENDOR shall follow all the requirements mentioned in the datasheets referred in Section 1.3.7.

2.3 ENVIRONMENTAL DATA


Environmental data which shall be used for the design of all equipments including piping, electrical
and instrumentation are provided below for convenience and easy reference. However, these
Environmental data specified below shall be checked and verified with latest revision of QP standard
ED.2.3071 Environmental Data.

a) Temperature and Pressure:

Average annual maximum shade temperature 49C

Maximum recorded shade temperature 52C

Average annual minimum temperature 12C

Minimum recorded temperature 0C

Maximum sun radiation temperature


(black bulb temperature) 84C

Average Monthly Soil Temperature


(0.5m to 10m depth) Max 38C
Min 22C

Average barometric pressure 0.98/1.01 Bar A

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 15 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

b) Relative Humidity:

Annual average humidity 62%

Absolute maximum humidity 100%

Absolute minimum humidity <1%

The maximum humidity of 100% is possible in any month throughout the year.

c) Rainfall:

Average annual rainfall 80 mm

Maximum recorded annual rainfall 302 mm

Minimum recorded annual rainfall <1 mm

d) Winds:

Prevailing wind direction is from North-West to North.

Design wind speed (at ground level) 135 km/h

Basic Design Wind Speed (at a height of 10m, in open 162 km/h
Country with no obstructions)

Design wind speeds in 5.2 and 5.3 above are 3 second gust wind speeds for 50year
return period, and shall be assumed to act from any direction.

Design wind speeds for other return period, terrain and/or height shall be determined in
accordance with BS CP3, Chapter V, Part 2 or other relevant code.

Wind pressures for structural design shall be calculated in accordance with BS CP3,
Chapter V, and Part 2 using Basic Wind Speed (V) of 162km/h (45m /s).

e) Lightning:

Thunderstorms and lightning are infrequent; however are more likely to occur in
winter and pre-summer seasons.

f) Sandstorms:

Severe sandstorms are common, especially in summer season. They may last for
several days with the atmosphere heavily laden with dust particles down to 2 microns.

g) Earthquakes:

Qatar is a region of low seismic risk. Earthquake load cases may be excluded, except
for high risk facilities at Ras Laffan and other locations as noted in the Basis for Design/

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 16 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Design Criteria for specific projects.

h) Special Climate Conditions:

Climate is tropical and atmosphere can be both salt- and sand-laden.

Saliferous coastal environment.

Ultra Violet (UV) radiation levels are high. All GRP and other plastics subject to direct
sunlight shall contain an UV barrier.

2.4 DESIGN L IFE

The design life of the facilities including all mechanical, associated piping, electrical,
instrumentation and civil and structural works shall be 30 years, with due note being taken of
the operating regime and of the environmental conditions. The minimum continuous period of
operation shall be 4 years for overall plant maintenance shutdown.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 17 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

3. TECHNICAL REQUIREMENTS

3.1 GENERAL
a) The vessel including all associated components shall be designed, fabricated and tested in
accordance with the requirements of this specification and the latest revision of applicable
Codes and Standards.

b) Material of construction of vessel and other associated items shall be suitable to onshore
environment.

c) Compliance of the CONTRACTOR with this specification and the referenced document shall
not release the CONTRACTOR from final guarantee for materials, equipment, workmanship
and performance of equipment supplied including its SUB-CONTRACTOR.

d) The units of measurement for drawings and design calculations shall be in SI units with the
exception of piping size identification.

e) The vessel shall be designed considering adequate safety and reasonable economy for the
proposed use.

3.2 MATERIAL
a) All materials shall be as per applicable Codes, Data sheet and QP engineering standard
ES.5.06.0003, section 6.0.

b) Pressure Parts:

i) Materials of construction for pressure parts shall be in accordance with any one of the
appropriate specifications listed in ASME SEC II-A and ASME SEC II-B, except as follows:

SA-36, SA-283, and other structural quality steel shall not be used.

Castings shall not be used for pressure parts.

Other equivalent materials meeting the requirements of this specification may be


used, with QP approval. The nomenclature and complete chemical and physical
properties of the proposed material shall be stated along with the ASME equivalent.
Any added requirements (such as fully killed, fine grain practice, and inspection
practices) for equivalency shall also be stated.

Quenched and tempered steel is limited to a maximum tensile strength of 690 MPa
and an actual yield-to-tensile strength ratio of <0.85

As equipment is under sour service, materials of construction shall be in accordance


with QP Standard QP-STD-R-001 (Materials for Sour Service), together with NACE
Standard MR-0175 / ISO 15156.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 18 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

ii) To promote good weldability, the chemical composition of carbon and carbon-manganese
steels to be used for vessels (pressure parts and attachments directly welded to the
pressure parts) shall comply with the following:

Carbon content shall not exceed 0.16% (Heat Analysis)/ 0.16% (Product Analysis),
except for forgings, where this may be relaxed to 0.25%

The carbon equivalent (CE) shall be 0.43% maximum (ladle analysis) based on the
following formula:

CE = C + Mn/6 + (Cr + Mo + V)/5 + (Ni + Cu)/15 + Si/24

Material composition shall be as per QP-STD-R-001.

In addition to the CE restrictions, SA 105 forgings shall be normalized.

iii) Materials shall be represented by test specimens that have been subjected to the same
heat treatment as the completed vessel. The term "heat treatment" shall also include any
heating above the critical range for hot forming.

iv) Substitution of material used for pressure parts requires QP approval.

v) All pipe material except man-ways for pressure retaining parts shall be seamless.
c) External attachments and Supports

Attachments that are essential to the structural integrity of the vessel, (for example, supports
and stiffening rings) as well as pipe and platform clips, shall be of material meeting the
toughness requirements of the ASME SEC II-A. Lightly loaded attachments shall meet ASME
SEC II-A requirements for minimum design metal temperatures lower than -10C.

Material of construction for external attachments directly welded to shell/head shall be in


accordance with QP Standard QP-STD-R-001 (Materials for Sour Service), together with NACE
Standard MR-0175 / ISO 15156.

d) External Bolting
External bolts and nuts for all nozzles fitted with blind flanges including manholes shall conform
to ASTM A193 Gr. B7M, A194 Gr. 2HM.
All bolting shall be cadmium plated to BS 1706.

e) Gaskets
Gaskets for nozzles fitted with blind flanges shall be provided as per applicable PMS (Piping
material specification).

3.3 DESIGN
a) Pressure Vessel shall be designed, fabricated, inspected and tested in accordance with ASME
Sec. VIII Div. 1 latest edition & U1 Stamp requirements, QP Engineering standard - Engineering
standard Pressure Vessel Design and Fabrication, ES.5.06.0003 and this specification. All
design calculations shall be carried out in corroded condition.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 19 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

b) Pressure vessels shall be designed for combined loading applicable to the erection, operation,
shutdown, and test conditions. These shall include loads due to wind, load-out, erection lift, dead
weight, static pressure and loads transmitted by piping.

c) Pressure vessel shall be self-supporting with supports designed to withstand the greatest loading
of the following cases:

i) Design wind load on an empty vessel (fully corroded).

ii) Hydrotest (new), plus 75% Design wind load.

iii) Design wind load with vessel at maximum normal operating conditions (fully corroded).

iv) Loadout accelerating conditions (new).

d) Design wind and loadout loading conditions shall be considered non-coincidental.

e) For all nozzle connections attached to piping systems the stresses in the vessel wall due to the
piping loads combined with the pressure stress intensity shall be evaluated. These local stresses
can be assessed using the method as indicated in BS5500 Appendix G.

f) Vessels of proprietary design (non-code construction), layered vessels, and vessels with
intermediate heads shall not be used without QP approval.

g) Horizontal vessels supported by two saddles shall be investigated using the Zick method for
assessing the localized stresses. One saddle shall be provided with slotted base plate to allow
expansion of vessel.

h) Basic allowable stresses for non-pressure parts are 1/3 of the ultimate tensile strength, 2/3 of the
yield strength, or that stress which produces a creep rate of 1 percent in 10,000 hours, whichever
is lowest (all stresses being taken at design metal temperature of the part).

i) Shipping Load:

i) Vessel shall be designed adequately to withstand transportation and erection loads. The
vessel fabricator shall provide lifting and tailing lugs as required, designed for an impact
load of not less than 1.5.

ii) All vessels shall be designed to withstand forces, which may be encountered during
transportation. A one-third increase in basic allowable stresses will be acceptable for this
case. In addition, all equipment shall be designed to withstand earthquake forces, which
may be encountered during the life of the facility, without catastrophic failure of the vessel
or its supports. Allowable stresses may be increased by a factor 1.7 for the earthquake
case. Design shall be based on the following minimum conditions:

Loading Condition Lateral Vertical

Transport Case 0.35g 0.50g

Earthquake Case 0.15g 0.07g

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 20 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Relaxation of these minimum requirements will require QP approval.

j) Corrosion Allowance:

i) Corrosion allowance shall be determined from the process requirements as specified in the
datasheets. Minimum corrosion allowance shall not be lesser than 3mm.

ii) The corrosion allowance shall be added to all surfaces of pressure parts, non-removable
internals, and major removable internal structural parts that are exposed to the process. For
minor removable parts, only one-half the minimum corrosion allowance shall be added to
the exposed surfaces when the specified minimum corrosion allowance exceeds 2.5mm.

iii) Internal fillet welds shall be sized to include the specified corrosion allowance on the throat
thickness.

k) Shell and Heads

i) The minimum fabricated thickness of the pressure containing shell and heads shall be the
greater of the following:

1. D/1000 + 2.5 mm, where D is the diameter in mm

2. 5 mm plus corrosion allowance

ii) Acceptable head shapes are tori-spherical or 2:1 ellipsoidal. Do not use
tori-spherical heads when any of the following conditions apply:

1. Design pressure over 690 kPag

2. Head diameters 3.6 m and larger

iii) Stresses shall be calculated in the knuckle region of tori-spherical heads with a thickness-to-
diameter ratio less than 0.002, to assure stability against buckling.

iv) In addition to the standard code requirements, all elliptical heads with D/t greater than 200 for
carbon steel must be checked for head knuckle wrinkling during hydro-test. The check is to
be performed using the methods of ASME Section VIII, Division 2, paragraph AD-204-2. The
new (un-corroded) dimensions are to be used. The pressure used in the equation is to be the
hydro-test pressure plus any applicable hydrostatic head. The allowable stress to be used is
90% of the yield stress. The AD-204-3 requirement for minimum straight flange length at the
minimum head thickness must also be followed.

v) For tori-conical transitions in vacuum service, stiffening rings in the adjacent cylindrical
sections shall be provided.

vi) Where stiffeners are required by the design code for vacuum vessels they shall be
continuous and preferably external. The rings shall be positioned at least 100mm clear of
circumferential seams, vessel branches and other permanent attachments unless otherwise
agreed by QP. Unless otherwise specified stiffeners shall be welded to shell with continuous
weld seams.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 21 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

l) Saddle Supports

i) Horizontal vessels shall be supported on two saddles covering at least 120 degrees of the
vessel circumference. The shell in contact with the saddle shall be protected from corrosion by
the use of a steel pad of material same as shell material. This pad shall be between the vessel
shell and the support surface, continuously welded to the shell and vented. Saddles and pads
shall not cover vessel shell seams. One of the saddle bearing plates shall have slotted holes to
allow for thermal expansion of the vessel.

ii) Anchor bolts shall be supplied in multiples of four. Anchor bolt to be minimum size of M20.
Allowable anchor bolt stress shall be 103 MPa calculated on the root area of the bolt.

m) Nozzles and other connections

i) All openings and branch connections shall be flanged unless otherwise specified.

ii) Branch connections NPS 2 or larger are preferred, and in no case shall the branch diameter at
the vessel wall be less than NPS 1.5. All connections NPS 2 and smaller shall be provided
with two stiffening gussets located at right angles unless the nozzle is a long weld neck type
construction.
iii) For all nozzles and connections, except man-ways and other openings intended solely for
access or inspection, the vendor shall determine the stresses in the vessel resulting from the
worst combination of any internal pressure up to the maximum operating pressure and the
externally applied forces and moments specified on the data sheet. Where the external nozzle
loads have not been specified, the vendor shall assume the forces and moments in the
following Table as per QP engineering STD.ES.5.06.0003_Rev-A acting in the worst
combination, at the nozzle to shell junction.

Nozzle Loadings:

Nozzle NPS Nozzle Rating


(inch)

150 300

Force Moment Force Moment


kN kN m kN kN m

2 1.5 0.5 1.5 0.5

3 3 1 3 1

5 3.5 2 3.5 2

6 6 6 6 6
8 7 9 7 9

10 9 13 9 13

12 12 19 12 19

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 22 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

14 13 21 13 21

16 16 26 16 29

18 17 31 20 38

20 17 32 21 40

24 22 41 29 54

iv) Where accommodation of the nozzle loads, as specified or as assumed in accordance with
above Table, would require the shell thickness of the vessel to be increased, the Vendor shall
inform the Purchaser accordingly. The Purchaser may consider reducing the nozzle loadings
by, for example, recalculating the piping loads allowing for any flexibility in the vessel nozzles.
To facilitate this, the Vendor shall provide information on the nozzle/shell flexibility.

v) On no account shall the Vendor assume nozzle loads less than those specified in above Table
without the prior agreement of the Purchaser.

vi) Vendor shall perform the local load analysis as per WRC 107. WRC 297 shall be used if
analysis can not be performed within WRC 107 limitations.

n) Reinforcement and reinforcing pads shall be as follows:

i) Reinforcement for man-ways and nozzles over NPS 2 shall be 100 percent area
replacement for the full un-corroded shell or head thickness. For example, reinforcement shall
be equal in area to the nozzle inside diameter (corroded) multiplied by the nominal un-
corroded thickness of the shell or head. No credit shall be taken for excess head or shell
material provided for factors such as corrosion allowance and joint efficiency.

ii) Integral reinforcement shall be required for multiple nozzles in heads and spheres, where the
distance between reinforcing pad edges would be less than 2.5 (Rt)1/2 (R and t being the
head or sphere radius and thickness, respectively). When integral reinforcing is provided on
nozzles 6 and greater, the ratio of nozzle wall thickness to shell wall thickness shall not be
greater than 2.

iii) Each reinforcing pad or segment thereof shall be provided with a NPT 6 mm threaded
"telltale" hole filled with grease, only after testing.

o) Flanges shall be designed for displaying the pressure and temperature on the vessel nameplate,
in accordance with the ASME SEC VIII and the following requirements:

i) Flanges in sizes of NPS 24 and smaller shall conform to the requirements of ASME B16.5.
For sizes NPS 26 through NPS 60 steel flanges dimensions and ratings shall conform to
ASME B 16.47 Series A. Lap-joint and slip-on flanges shall not be used unless otherwise
approved by QP.

ii) Flange facing shall be as per the applicable PMS (Piping material specification).

iii) Plate or forged flanges with no hub shall only be used for internal non-pressure connections.
The minimum flange thickness is 9.5 mm plus corrosion allowance.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 23 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

iv) Bolting on flanges shall clear vessel insulation by not less than the distance required to insert
and operate a box wrench.

p) Threaded connections are not allowed.

q) Nozzles and their reinforcing pads shall not be located in the knuckle region of a torispherical
head. Nor, without QP approval, closer than 2.5 (RT)1/2 (R and T being the shell radius and
thickness, respectively) from a cone-to-cylinder junction.

r) Man-ways and other inspection openings

i) Manways shall be provided with blind flange, bolting cover and davits/hinges to facilitate
handling.

ii) Flange facing for manways and hand holes shall be raised face, with a finish conforming to
ASME B16.5, unless otherwise specified.

3.4 APPURTENANCES AND ACCESSORIES


a) A list of appurtenances required for individual vessel shall be provided with purchase order,
clearly indicating components that are to be included in supply of vessel manufacturer.

b) All vessels and appurtenances shall comply with the data sheet and all attachments.

c) Vessel shall be provided complete with supports, nozzles and openings with appropriately rated
flanges, lifting lugs, ladders and platforms.

d) Vessel shall be provided with all internal piping, as required and it shall be shown in the Data
Sheet.

e) Minimum standouts for nozzles shall be in as per below table.

f) The location, size, type, and quantity of all openings, connections, including instrument
connections, and fittings shall be as shown on the Data sheet. Location, size, type, and
quantity of all openings and connections will be subject to change during engineering and
design review prior to release of the Vendor drawings for fabrication. Such changes shall be at
no further cost to the Purchaser/Buyer.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 24 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Nominal nozzle Nozzle Length X


size
NPS Flange Rating
150 300

1.5 203 203


2 203 203
3 203 203

4 203 203

6 203 203
8 203 203

10 203 203

12 254 254

14 254 254

16 254 254

18 254 254

20 254 275

24 254 275

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 25 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

g) Ladders and Platforms

Vendor shall provide ladders and platforms. Ladders, platforms, and all accessories shall be
furnished with a hot-dipped galvanized coating in accordance with ASTM A153. After fabrication,
ladders and platforms, including all bolts and nuts, shall be completely assembled to the vessel in
the shop to insure fit, then disassembled and shipped separately.

h) Grounding Lugs

Two grounding lugs shall be provided on each saddle. The grounding lugs shall not be painted or
galvanized.

3.5 FABRICATION
a) Welding

i) All welding shall be in accordance with the requirements of ASME code, this specification
and QP Engineering standard Pressure Vessels Design and Fabrication, doc. No.
ES.5.06.0003, section 7.0.

ii) All pressure containing welds shall be full fusion, full penetration butt joints. Wherever
practical, these welds should be made using double-side techniques.

iii) Fillet welds on wetted parts are not allowed.

iv) Nozzles inserted through a hole cut in the vessel shall be full penetration welded, including
the reinforcing pad. Nozzles inserted through cover plates shall be full penetration or partial
penetration double welded. ATTACHMENT BY FILLET WELDS ONLY IS NOT
PERMISSIBLE.

v) All nozzle connection shall be set-in type. Set-on connections are not permitted due to
hazardous service.

vi) Minimum weld to weld distance shall be 50 mm plus twice the thickness of the lesser thick
plate.

b) Forming of shell and heads

i) When a difference in thickness exists between shell sections or shells and heads, the inside
surfaces shall be aligned.

ii) All parts which have been cold formed by more than 5% shall be subjected to an appropriate
normalizing treatment and, if necessary, a tempering treatment.

iii) Normalizing of CS components and base materials shall be performed separately, not as part
of the hot-forming operation, unless the finishing hot-forming temperature is in the normalising
temperature range of 850 C to 960 C. In both cases, the temperature shall be recorded and
documented by a temperature recording chart.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 26 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

c) Connections

i) All man-ways and nozzles that do not extend into the vessel for internal connections shall be
finished flush with the inside of the shell. The inner edge shall be rounded to a minimum
radius of 6 mm.

ii) Where fillet welds on nozzle reinforcing pads are smaller than the pad thickness, the corner of
the pad shall be chamfered to provide a continuous surface with the face of the fillet weld.

iii) The minimum distance between the edge of any attachment weld of a pressure part (e.g. a
nozzle) to the edge of another pressure weld of the vessel shall be 50 mm or twice the
thickness of the pressure part, whichever is the greater. Similarly, the minimum distance
between the edge of a non-pressure attachment weld to the edge of a pressure weld of the
vessel shall also be 50 mm or twice the thickness of the pressure part, whichever is the
greater.

However, if this is not possible the attachment weld shall cross the pressure weld completely
by a length of at least 50 mm or twice the wall thickness (whichever is the greater) in order to
avoid stress concentration. Before the attachment weld is made, 100% NDE in accordance
with UW-11 shall be performed on the adjacent pressure weld in the area where the
attachment weld will cross.

d) Heat Treatment :

i) The complete equipment including supports shall be performed Post Weld Heat Treatment
(PWHT) as per UCS 56.

ii) Hardness of base metal, weld and HAZ shall be less than the hardness limit specified in
NACE MR 0175 with supplementary requirements presented in QP technical standard for
materials for sour service QP-STD-R-001.

iii) The complete post weld heat treating procedure, including temperature and holding time,
shall be submitted to QP for approval.

iv) The PWHT procedure shall clearly indicate the type and location of calibrated thermocouples
to be used. These details form part of the heat treatment procedure to be submitted for
approval.

v) A PWHT certificate, stating actual temperature/time parameters, shall be included in the


Manufacturer's report. The original temperature/time indicator recorder charts shall be
retained by the Manufacturer.

vi) QP or its representative will inspect all vessels duly installed with all its internal attachments
prior to heat treatment. These may be removed later for heat treatment if required.

vii) Machined surfaces shall be protected against scaling during heat treatment.

viii) No work is permitted after PWHT.

e) Non Pressure Attachments

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 27 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

i) Since the equipment is under corrosive services, welded attachments inside carbon steel
vessels shall be completely welded to prevent corrosion behind the attachment.

ii) All attachments shall be welded to vessels in the shop and prior to final post weld heat
treatment.

3.6 REPAIRS
Defects shall be removed and re-welded using qualified welding procedures. The repair weld shall be
re-examined by the original method to ensure freedom from defects. Prior QP approval is required for
the following:

i) Weld repair depth exceeding 9.5 mm or 1/2 the weld thickness

ii) Where defects in plates or forgings are observed

iii) The second and subsequent repairs in the same area

iv) Repairs after PWHT

v) All repairs in quenched and tempered material, or when the specified minimum yield strength
exceeds 360 MPA.

3.7 TOL ERANCES


a) Tolerances for vessels subject to internal and/or external pressure shall be as stated in UG-80
and UG-81. The maximum deviation of the shell from a straight line shall not exceed 0.3%, either
of the total cylindrical length or of any individual 5 m length of the vessel.

b) Tolerance on overall length measured between the tangent lines shall be in accordance with the
following table:

Length L Tolerance
(mm) (mm)

4000 < L </= 10000 +/- 8.0

NOTE: Tangent lines shall be punch-marked on the dished heads, both externally and internally at the
intersection of the knuckle with the cylindrical section.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 28 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

4. INSPECTION AND TESTING

4.1 INSPECTION

a) Vessel shall be tested and inspected as per ASME Sec. VIII Div. 1, this specification, QP Spec.
ES.S.60 & QP STD. ES.5.06.0003.

b) Radiography and Inspection of welds:

Full radiography is required for the vessel welds as per UW-11.

All long seams of fabricated nozzles shall also be fully radiographed.

100 % radiography shall be performed on all T-Joints.

Radiographs shall be taken as soon as welding of the Joint is completed. If repairs are
required, these shall be carried out before starting other welds. New radiography examination
of such repairs shall also carried out by the CONTRACTORs at his own cost.

The radiography of welds may be performed before or after PWHT. If performed before
PWHT, an additional two radiography shall be performed after PWHT.

c) Liquid penetrant/ magnetic particle/ ultrasonic examination shall be carried out as per ASME
Boiler and Pressure Vessel Code Section V and QP Spec. ES.S.60 and the acceptance criteria
shall be as per ASME Section VIII Div. 1.

d) All the temporary attachments are removed and the temporary welds, tack weld shall be ground
smooth with the surrounding shell surface and Liquid Penetrant or Magnetic Particle Inspection
shall be conducted.

e) Ultrasonic Testing shall be done at all nozzle locations to check for any laminations prior to
cutting of shell / roof plates.

f) Gaskets supplied by the Vendor shall be new and not those used for shop hydrostatic testing.
Gaskets shall be separately boxed, shipped with each vessel, and clearly identified for field
installation.

g) Hardness testing requirements shall be as per QP technical standard QP-STD-R-001, section


11.0

h) It shall be the responsibility of VENDOR to prepare a detailed inspection and test plan as per
applicable code and specifications and get the same reviewed by Client (QP) before
commencement of works.

i) CONTRACTOR shall provide mill test certificate for all materials. All the material shall be clearly
identified and the CONTRACTOR shall ensure the material traceability during the fabrication.

j) All vessel shall be offered for inspection at all stages, as desired by TPI and Clients
representative.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 29 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

k) Inspector or Clients representative shall have free access to all the CONTRACTORs shops as
well as to worksite.

l) The CONTRACTOR shall provide all facilities, such as access ladder, lighting, tools and tackles,
instruments etc. and personnel to inspectors, for proper execution of their inspection.

m) All the inspection shall be carried out in accordance with the relevant codes and requirements of
drawings and specifications.

n) Approval of the Inspector shall in no way relieve the CONTRACTOR of his responsibilities for
proper execution of work.

4.2 TESTING

a) CONTRACTOR shall submit detailed hydro-test procedure of vessel together with the procedure
for carrying out settlement checks for QP review and approval.

b) All shop fabricated vessels shall be given a shop hydrostatic test prior to any painting in
accordance with the basis set forth in ASME SEC VIII D1, Paragraph UG-99c and the following
strictures:

i) The test pressure shall be based on the as fabricated, fully reinforced, un-corroded shell and
heads, except as otherwise limited by the nozzle flange ratings.

ii) The test pressure shall be maintained for a period of not less than one hour per inch of
thickness, but not less than one hour. The thickness of the head or shell, whichever is greater,
shall be used to determine the length of the test period.

iii) The minimum metal temperature during initial pressure testing of ferritic vessels with
shell or head thicknesses greater than 13 mm shall not be lower than the following:
Where base metal impact tests have been conducted, the impact test temperature plus
17C
Where base metal impact tests have not been conducted, both the test water and the
metal temperature shall be a minimum of +15o C, however the test temperature shall not
exceed 49C

iv) Fresh water shall be used for hydro-testing vessels. The chloride content of water shall not
exceed 50 ppm for testing the vessels.

c) Pneumatic or hydro-pneumatic tests are not permitted.

d) All reinforcing pad welds shall be tested to 103 kPag minimum, with dry air or light oil, before
PWHT.

e) Vessels shall be hydro-tested prior to coating of the interior and exterior surfaces.

f) Vessels shall be completely dried up with dry air after the hydro-test.

g) The CONTRACTOR shall be responsible for all labour, supervision, equipment, and
instrumentation required for testing.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 30 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

h) Any defect pointed out any time during the progress of the Test shall be rectified and re-tested by
CONTRACTOR at no additional cost to the QP.

i) When required by purchase order, CONTRACTOR shall submit the procedure for carrying out
vessel measurements and calibration.

Copies of calibration charts and data, together with records of checks carried out are to be
provided for record purposes.

4.3 CERTIFICATION REQUIREMENTS

i) Vessel plates, part directly welded to shell/head, Nozzle parts shall be certified in accordance
with EN 10204 3.2.

ii) External attachments like platform, ladders, saddles etc. shall also be certified in accordance
with EN 10204 Type 3.1.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 31 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

5. STAMPING AND RECORDS

5.1 ST AMPING

Manufacturer shall securely fasten a stainless steel name plate to a bracket that is seal
welded to the vessel. The bracket material shall be of similar metallurgy as that of the vessel
pressure part. The name plate shall bear the following, as a minimum:

i) All applicable code symbols

ii) Manufacturer's name

iii) Manufacturer's serial number

iv) Date of manufacture

v) Maximum allowable working pressure and corresponding temperature


(corroded condition)

vi) Corrosion allowance, and shell and head thickness

vii) Hydrostatic test pressure

viii) QP purchase order number and QP equipment number

ix) Vessel size - OD x T/T length

x) Minimum design metal temperature

xi) Capacity

xii) Erection weight

xiii) PWHT

xiv) Radiography

Steel stamping of vessels with a minimum design metal temperature below 15C shall be
done with low stress stamps.

5.2 RECORDS

Records to confirm compliance of materials and fabrication with the requirements of this
guide shall be retained by the fabricator for review by QP. Upon completion of fabrication,
the fabricator shall supply QP with copies of final drawings and data as specified, including:

i) Assembly and detail drawings showing as-built dimensions, weights, and details

ii) ASME Code Form U-1 Manufacturer's Data Report

iii) Certified record showing location, heat numbers, chemical and physical properties of all
materials used

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 32 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

iv) Copy of post weld heat treatment recording charts

v) Copy of hydrostatic test chart

vi) Copy of non-destructive examination test results.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 33 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

6. SPARE PARTS AND SPECIAL TOOLS

6.1 SPARE P ART S

VENDOR shall provide Commissioning, Start-up, one-year initial spare parts and list of two-years of
operation spares. VENDOR shall also provide all insurance spares deemed required which shall be
identified in the bid document.

VENDOR shall provide a detailed list of spare parts by completing the SPIR Forms. SPIR shall cover
all the spares required for all routine inspections, major overhauls and breakdowns but not limited to
initial 2 years.

Unless otherwise proven by cost-benefit evaluation each vessel shall be provided with identical spare.

6.2 SPECI AL TOOLS

All special tools that are required for installation, commissioning, operation and maintenance of vessel
shall be provided by the VENDOR with a detailed list. This shall include any special lifting facilities for
any major sub-component of the vessel. One complete set of special tools is to be supplied as above,
for each vessel.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 34 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

7. SURFACE PREPARATION AND PAINTING

CONTRACTOR shall carry out surface preparation and painting as per Specification for painting and
wrapping of metal surfaces, Document No. QP-SPC-L-002, latest revision.

The surface preparation and painting shall be applied as per the following coating schedule:

COATING
DESCRIPTION OF AREA
SCHEDULE NO.

General Exposure to Atmosphere (External surface of vessel) New


1Un
Construction of Uninsulated Items

8 Internal Surfaces of Vessel

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 35 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

8. ENGINEERI NG DESIGN PACKAGE CONTENT


(DELIVERABLES)

8.1 GENER AL

This section is intended to define the minimum requirements for CONTRACTOR documents, to be
prepared and issued for QP Review and Approval.

CONTRACTOR shall submit drawings and other documentation as specified and outlined under
Attachment 1. The lists in this schedule outline the minimum requirements. Any document
requirement within the framework of this Specification, necessary for the execution of the WORK,
shall be identified and prepared by CONTRACTOR and is made available for QP review if requested.

CONTRACTOR shall keep records of all technical and commercial correspondence involving
CONTRACTOR, QP, etc. together with data and drawings related to the WORK. These records shall
be issued to QP or any party designated by QP, when so required.

8.2 DRAWING DOCUM ENTATION

All drawings/documents shall be project specific and shall be prepared in accordance with ES-D-10.

All drawings shall be prepared in AutoCAD version as specified in ES-D-10 and documents shall be
prepared using Microsoft Office 2000 and applicable design software. English language shall be used
in all documentation and drawings.

CONTRACTOR shall prepare all the necessary project specific drawings, design, etc. giving full and
complete information to enable QP to property consider CONTRACTORs WORK.

Drawings prepared by SUB-CONTRACTORS shall be checked thoroughly by CONTRACTOR who


shall ensure that they conform to the requirements of this Specification. Drawings found to be
inaccurate or otherwise in error will be returned to the SUB-CONTRACTOR for correction before
being submitted to QP for review or approval.

QP approval of CONTRACTORs and any SUB-CONTRACTORs drawings shall not relieve


CONTRACTOR from his responsibility for error or omissions which may exist.

Where such errors or omissions are discovered later, they shall be made good by CONTRACTOR at
his own irrespective of any approval by QP.

In addition to their standard drawings numbering system, CONTRACTOR shall incorporate in all
deliverables QP project number which will be advised to CONTRACTOR. All drawings shall consists
of QP title block, name of the project, contract no., location of site, etc.

All drawings prepared or furnished by CONTRACTOR/SUB-CONTRACTORs shall be marked with


the correct title of the project and shall be transmitted to QP in as many copies as specified.

Each transmittal of drawings shall be accompanied by a Transmittal Form giving the drawings
numbers and titles and numbers of prints enclosed.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 36 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Revised drawings shall be resubmitted for approval, unless otherwise directed by QP.

Revised drawings shall have a revision letter added to the drawing number and the nature of the
revision and date shall be noted.

A triangle containing the revision letter shall be placed on the drawing adjacent to the modification:
the modification shall be highlighted by a cloud around it.

8.3 APPRO VAL PROC EDU RE

Specifications/procedures, drawings, reports, design calculations and data will be reviewed or


approved, as necessary, by QP within ten (10) working days of their receipt. The Detailed
Engineering Dossiers will be reviewed / approved by QP within fifteen (15) working days of their
receipt.

CONTRACTOR shall be responsible for any discrepancy, errors or omissions in the drawings and
documents supplied by him, whether such drawings and documents have been approved by QP or
not.

Each copy of a drawing or document sent for approval shall be clearly marked For Approval in a
visible place. Each drawing or document for which no approval is required shall be clearly marked
For Information only in a visible place. The original and copies of each approved drawing or
document shall clearly be marked Approved in a visible place. The marking shall include QP
approval date.

At monthly intervals, CONTRACTOR shall submit copies for approval of the Drawing schedule
showing the percentage completion.

Any drawing or document for approval or information shall be submitted to QP via courier service at
CONTRACTORs cost. CONTRACTOR shall supply further copies as and when requested by QP.

8.4 APPRO VAL OF DR AWINGS AND DOCUMENT S

Within the period mentioned, QP will inform CONTRACTOR by returning one copy marked with one
of the following categories:

Category A: Reviewed and accepted as final and certified. CONTRACTOR may proceed.

Category B: Reviewed and accepted as noted. Revise and resubmit. CONTRACTOR may proceed

Category C: Reviewed and returned Correct and resubmit. CONTRACTOR shall not proceed until
resubmitted and accepted either as Category A or B.

Category D: Review not required. For information only. CONTRACTOR may proceed.

All drawings / documentation incorporated in the Operating Manual, Instruction Manual, Maintenance
Manual and Design Manual shall be the final certified document and shall be stamped AS BUILT.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 37 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

8.5 DIS PAT CH OF APPROVED DR AWINGS AND DOCUMENTS

When CONTRACTOR receives the advice that a drawing or document is approved by QP, he shall
immediately enter the mark Approved on the original and distribute the required number of copies to
QP.

8.6 SUBMISSION TIME OF DRAWINGS AND DOCUMENTS

CONTRACTOR shall submit to QP the following documentation within the indicated below:

a) A general program showing all pertinent activities that require QP approval during the design
and engineering phase, and indicating durations and completion dates shall be submitted
within two weeks from the EFFECTIVE DATE OF THE CONTRACT.

b) Detailed design drawings and documentation shall be submitted according to a schedule


prepared by CONTRACTOR compatible with the project development and approved by QP.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 38 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

9. RESPONSIBIL ITY

This specification is prepared mainly for (EPIC) CONTRACTOR. But equipment supply and
installation may be carried out by Vendor / Supplier or SUB-CONTRACTOR; hence some of the
requirements are indicated for Vendor / Supplier or SUB-CONTRACTOR. However responsibility
remains on CONTRACTOR to ensure the compliance with this specification and reference
documents.

CONTRACTOR shall be responsible for ensuring that the equipment is complete for its safe and
efficient operation. Components not mentioned in this specification which are necessary for the
operation of the equipment or required by certifying agency, regulatory bodies or by law, shall be
CONTRACTOR standard components. Compliance to this Specification does not relieve
CONTRACTOR from this responsibility to meet the specified operating conditions and duties.

It shall be understood that when drawings are approved by QP or his representative for construction,
this does not relieve CONTRACTOR from the responsibility of ensuring the equipment is to
specification or complete for safe and normal operation.

CONTRACTOR shall be responsible for the co-ordination of SUB-CONTRACTORs equipment supply


and installation and ensuring that the equipment complies with this specification.

It is CONTRACTORs responsibility to bring promptly to QPs attention any discrepancies which are
found to exist between this specification and the individual Data Sheets. Also applicable for any
outstanding information required from QP.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 39 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

10. QUAL ITY ASSURANCE

The CONTRACTOR shall operate a Quality System meeting the requirements of the relevant Part of
ISO 9001. Guidance for the Manufacturers conformance requirements to ISO 9001 is given in QP
Standard Specification No. QP-STD-Q-004.

The CONTRACTOR shall ensure that his sub-suppliers operate a quality system meeting the
specified conformance criteria to ISO 9001. The Manufacturers quality system shall be subject to the
Purchaser approval prior to commitment to the Purchase Order. Major sub-suppliers shall be subject
to identical approvals. The Purchaser reserves the right to conduct a Quality Audit at the
Manufacturers/sub-suppliers facilities at any stage during manufacture.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 40 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

11. GUARANTEE

CONTRACTOR shall guarantee the mechanical design of the vessel & its components, in accordance
with the design conditions given in the data sheets.

The equipment shall be guaranteed against defective materials, poor workmanship and improper
design for a period of one year after the vessel has been placed in regular operation.

CONTRACTOR shall repair or make good, at his own expense, any defects noted during the
guarantee period. All repair work must be completed within a reasonable period to full satisfaction.

Coating Works - Externally: CONTRACTOR shall guarantee the protective coating applied by him on
the vessel against defective materials and workmanship for a period of three (3) years from the
CONTRACT COMPLETION DATE (no worse than Ri2 as per ISO 4828/3 Part 3).

Coating Works - Internally: CONTRACTOR shall provide a product performance warranty for the
internal lining system against defective materials and workmanship for a period of 10 years from the
CONTRACT COMPLETION DATE.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 41 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

12. HANDLING

12.1 PACKING & SHIP PING

a. Before shipment all vessels shall be dried, perfectly cleaned and free from all foreign matters.

b. All equipment shall be suitably protected for shipment and securely anchored during transit.

c. Vessel shall be clearly identified by painting or stencilling in a conspicuous place, the vessel
description and the purchase order number.

d. Separate or loose parts shall be completely boxed with identification tag.

12.2 PRESE RVATION & STORAGE

a. The equipment shall be suitably preserved under N2 blanket to maintain in good condition
throughout the phases of storage until ready to be operated.

b. Equipment components and materials shall be protected to withstand transit and extended
period of storage at the offshore jobsite for a minimum period of twelve (12) months.
Equipment shall be protected to safeguard against all harsh environments, such as: humidity,
moisture, rain, dust, dirt, sand, mud, salt air. Consideration shall be given to extremes of
ambient temperature, which maybe experienced during shipment and storage.

c. All equipment shall be properly protected from damage for sea / road freight and long-term
outdoor storage. Each item shall be clearly identified with Purchasers name, Purchase order
number and Tag number.

d. Exposed machinery surfaces shall be coated with easily removable rust preventive. Items
vulnerable to damage shall be packed separately for installation at site. Any such items shall
be properly tagged for ready identification and correct installation. The content of all boxes or
packages shall be recorded in detail on the packing list.

e. The transported equipment shall have the necessary fastenings protection and lifting facilities to
satisfy lifting and sea fastening loads and restraints. Lifting and fastening procedures shall
accompany each package.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 42 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

13. ATTACHMENTS
Attachment 1 Drawings and Documentation Requirements
Attachment 2 Vendor Document List

Attachment 3 Datasheet New 3-phase Test Separators

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 43 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Attachment 1 Drawings and Documentation Requirements

CONTRACTOR shall submit the drawings/ documents as per the following table:

EQUIPMENT NEW 3-PHASE TEST SEPARATORS

REQUIRED NO. FOR CLIENT SUBMISSION

COMMENT/APPROVAL AS BUILT
DRAWINGS/DOCUMENTS
WITH BID (1)

PRINT PRINTS

Progress Reports (Monthly)

List of Drawings and Documents 6 6

List of each and all exceptions from 4


specification

Method statement 4

Procurement, Fabrication, Installation and 4 6


testing schedule

Mechanical Design calculation report 6 6


including wind, seismic and local load
analysis

General arrangement drawings c/w wgts & 4 6 6


including nozzle orientation

Nozzle Detail drawings with Bill of Material 6 6

Internals drawings with Bill of Material 6 6

Saddle drawings with Bill of Material 6 6

Platform and ladder drawings 6 6

Details of support cleats with Bill of Material 6 6

Foundation loading (with details of anchor 6 6


bolts)

Cathodic Protection design report 6 6

Cathodic protection manual, material 6 6


schedules, installation procedure,
commissioning procedure etc.

Surface preparation and Painting Procedure 6 6

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 44 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Welding procedures, procedure 6 6


qualifications and weld maps

Preservation Procedures 6 6

Packing and Transport Procedures 6 6

Inspection & Testing Procedure 6 6

Heat treatment procedure, as applicable 6 6

Hydrostatic test procedure 6 6

Certificate of compliance with PO & 6 6


Specification

Shipping Information (units, weights, size, 4


etc.)

Installation & Erection Procedure 6 6

Maintenance Manual of appurtenances 3 6

List of special tools req. for Maint. & 4 6


Operations

Quality Plan 4 4 4

Country of Origin (Material and 4


Components)

Manufacturing, Inspection & Test Plan (ITP) 6 6

Manufacturing report and data books 6

Inspection & Testing Report 6 6

Nameplate 6 6

Completed SPIR Forms 6 6

Commissioning, Insurance and Two year 4


operation spare part list

NOTE (1) Fabrication not to commence until review and acceptance

(2) Vendor shall also submit Electronic copy of all the documents/drawings during each
submission to QP.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 45 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

ADDITIONAL REQUIREMENTS/INFORMATION

All as built drawing/documentations shall be issued in Electronic Format (Native) in accordance with
ES.D.10, Issue 6.0. Electronic copies of all drawing templates and sample drawings conforming to
ES.D.10 must be submitted to QP and approved prior to commencement of design activities.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 46 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Attachment 2 Vendor Document List

The Vendor shall submit the following document for review and approval by Company prior to the start
of fabrication and must be submitted within four (4) weeks from the placement of order.

1. Drawings:

i) General arrangement drawings, with vessel dimensions, weights (empty, operating &
hydrotest condition), location and sizes of all connections, supports, and accessories shall be
submitted for approval. The Engineering contractor will use these drawings to indicate final
nozzle and instrumentation port orientation, as well as the locations of ladders, stairs,
platforms, etc.

ii) details of welding,

iii) Saddle drawing with bill of material,

iv) Nozzles and manholes drawings with bill of material,

v) Platform and ladder drawings,

vi) External and internal support detail drawings,

vii) Internals drawing with bill of material,

viii) Drawings detailing foundation loadings and requirements including moments, dead loads,
seismic loads, live loads, size, and location of anchor bolts; clearance requirements, fastening
torque requirements; and all required mounting details.

ix) Drawings required for a complete installation.

x) Isometric sketches showing maximum allowable nozzle loadings.

2. Mechanical design calculation for shell, head, stiffening rings, nozzles with local load analysis,
manways, pump nozzles & flanges with local load analysis, anchoring, complying to the
requirement of ASME Sec. VIII Div. 1.

3. Complete manufacturing sequence schedule showing the dates of all major fabricating operations
and tests.

4. List of Spares Commissioning, Operation and Insurance spares,

5. Completed SPIR forms

6. Surface preparation and Painting procedure

7. A complete description of the methods and procedures for each test required including acceptance
criteria.

8. Records and Reports:

i) Test reports for all tests specified.

ii) Certificate of compliance for materials.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 47 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

9. As Built Drawings

i) After commissioning of the system, issue as-built revision for all project drawings. During the
construction and commissioning period any variation from the CERTIFIED or APPROVED FOR
CONSTRUCTION drawings shall be agreed between the CONTRACTOR and QP site
representative & documented by the CONTRACTOR.

ii) Within six weeks after completion of the work, the SUPPLIER shall submit all final revisions of
all original drawings and six sets of the "AS-BUILT" drawings. This shall also include the
modification of the existing drawings and O & M Manuals to include the new operation facilities.

Note:

1. The Vendor shall produce all drawings in accordance with ES.D.10, Issue 6.0. Electronic copies of
all drawing templates and sample drawings conforming to ES.D.10 must be submitted to QP and
approved prior to commencement of design activities. The drawings shall be created using QPs
approved version of AutoCAD software.

2. All design documentation shall be provided in electronic format


3. The Vendor shall use the following engineering software for the preparation of deliverables:
i) AutoCAD for drawings
ii) MS Office for reports
iii) Approved software for vessel design i.e. PV-Elite latest version.

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 48 of 49


FRONT END ENGINEERING DESIGN (FEED)
FOR REPLACEMENT OF OLD 3-PHASE TEST
SEPARATORS AT ALL DEGASSING
STATIONS, DUKHAN FIELD

TECHNICAL SPECIFICATION FOR NEW


3-PHASE TEST SEPARATORS

Attachment 3 DATASHEET NEW 3-PHASE TEST SEPARATORS

DOC. NO.: 3071-DGEN-5-14-0001 REV. 3 Sheet 49 of 49


QP REF. LC12102200

VN
M DATA SHEET PLANT Degassing Stations
NEW 3-PHASE TEST SEPARATORS LOCATION Dukhan Field

24-V-XXX1,22-V-XXX1,23-V-XXX1,14-V-XXX1,12-V-XXX1,
1 Tag No. : Client: Qatar Petroleum
13-V-XXX1 & 31-V-XXX1 (Note-36)
2 Title: New 3-Phase Test Separator Plant Location: Degassing Stations-Dukhan
3 P & ID No. : Refer Note-39 Manufacturer: -
4 Purchase Order No. : -
5 Number of Units: 7
6 Operation (Continuous / Intermittent): Continuous (Note 4)
7 Cyclic Service (Yes / No): No
8 Location (Indoors / Outdoors): Outdoors
9 SEPARATOR CONFIGURATION
10 Orientation (Horizontal / Vertical): Horizontal
11 Phase Separation (2-Phase / 3-Phase): 3-Phase
12 FLUID PROPERTIES UNITS CASE 1 CASE 2 CASE 3 CASE 4
13 Fluid: Crude Oil (Well Fluid)
14 Flammable / Explosive / Toxic:
15 Corrosive / Erosive due to: Water, CO2 , H2S
16 Foaming Tendency (Nil / Moderate / Severe): Nil
17 Other:
18 DESIGN CONDITIONS
19 Design Pressure: Barg 17.7 / FV
20 Design Temperature: C -10 / 93
21 Design K Factor: m/s 0.1
22 Slug Volume Requirement: m 2
23 OPERATING CASES Maximum Oil Maximum Gas Maximum water All Maximum
24 Pressure: Barg 12.73 12.73 12.73 12.73
25 Temperature: C 10 / 49 10 / 49 10 / 49 10 / 49
26 Vapour:
27 Mass Flowrate: kg/h 4342 10360 174 10360
28 Density: kg/m3 15.3 13.7 13.9 13.7
29 Viscosity: cP 0.01 0.01 0.01 0.01
30 Molecular weight:
31 Liquid Hydrocarbon:
32 Mass Flow rate: kg/h 55060 51770 2738 55060
33 Density: kg/m3 831.12 781.29 826.52 831.12
34 Viscosity: cP 4.12 1.6 4.14 4.12
35 Liquid Aqueous:
36 Mass Flow rate: (Note-2) kg/h 2753 2588.5 64130 64130
37 Density: kg/m3 1019 989.5 1019 1019
38 Viscosity: cP 1.3 0.55 1.3 1.3
39 PERFORMANCE
40 Allowable Entrainment:
41 Hydrocarbon liquids in water: 200ppm and Oil Droplet size of 80 microns & above
42 Water in Hydrocarbons: Max. 2% by Volume
0.1 USG / MMscf with a demisting effeciency of 98% for a fine mist with liquid
43 Liquid in Vapour:
droplet of 10 micron
44 VESSEL INTERNALS
45 Inlet Distributor: Note-3 Yes No Type:
46 Mist Eliminator: Note-3 No Mesh Pad Vane Pack

47 Hydrocarbon Outlet Vortex Breaker: Yes No

48 Aqueous Outlet Vortex Breaker: Yes No

49 Weirs: Yes No

50 Calming Baffle: Yes No

51 Sand Removal: Note-5 Yes No

52 Plate Pack Coalescer: Yes No

53 Internal Heating / Cooling: Yes No

54 External Heating / Cooling: Yes No

55 Other Internals: Note-3


56
57
58
59
60
61
62

FRONT END ENGINEERING DESIGN (FEED)


FOR REPLACEMENT OF OLD 3-PHASE TEST SEPARATORS AT ALL
DEGASSING STATIONS, DUKHAN FIELD
Contract No: LC12102200 sh: 2 of 7

Document No: 3071-DGEN-5-13-0001 Rev: 5


QP Ref: LC12102200
DATA SHEET PLANT Degassing Stations
NEW 3-PHASE TEST SEPARATORS LOCATION Dukhan Field

1
2 = TO BE FILLED BY SUPPLIER DURING BIDDING STAGE (AND TO UPDATE AT DESIGN STAGE)
24-V-XXX1, 22-V-XXX1, 23-V-XXX1,
3 NAME OF EQUIPMENT: New 3-Phase Test Separators EQUIPMENT NO. & QTY.: 14-V-XXX1, 12-V-XXX1, 13-V-XXX1 &
31-V-XXX1
4 JOB / TECHNICAL SPECIFICATION DOCUMENT NO.: : 3071-DGEN-5-14-0001 QP REQUISITION NO.: *
5 MANUFACTURER / SUPPLIER NAME AND DETAILS: *
6 DESIGN DATA OPERATING CONDITIONS
7 CODE (SEE NOTE-9) ASME Sec VIII Div. 1, U1 code stamp SERVICE SOUR SERVICE
8 Q.P. ENGINEERING STANDARDS ES.5.06.0001 & ES.5.06.0003 CONTENTS CRUDE OIL (WELL FLUID)
9 CRITICALITY RATING 1 SPECIFIC GRAVITY OF CONTENTS 1.019
10 DESIGN PRESSURE, INTERNAL 17.7 barg @ 93 C OPERATING PRESSURE (max / nor / min) - / 12.73 / - barg
11 DESIGN PRESSURE, EXTERNAL FV (Steam Out) @ 107 C P.S.V. SIZE & SET PRESSURE TBA
12 DESIGN TEMPERATURE 93 C OPERATING TEMPERATURE (Min./Max.) 10 / 49 C
13 M.D.M.T. FOR IMPACT TESTING ETC. -10 @ 12.73 barg. C LEVEL INSTRUMENT SET VOL. FOR ALARM Refer Page 5 of 7 m3
14 INTENDED No. OF OPERATING CYCLES Nil LEVEL INSTRUMENT SET VOL. FOR TRIP Refer Page 5 of 7 m3
15 CORROSION ALLOWANCE 3.0 mm MATERIALS (SEE NOTE-21)
16 JOINT EFFICIENCY SHELL: 1.0 HEADS: 1.0 SHELL A 516 GR 60N + HIC (Note-41)
17 WIND LOADS PER 3071-DGEN-5-14-0001,Section 2.2 HEADS 5 A 516 GR 60N + HIC (Note-41)
18 SEISMIC LOADS PER 3071-DGEN-5-14-0001,Section 2.2 INTERNAL CLADDING / LINING / COATING Coating Schedule 8 (Note-42)
19 SHIPPING LOADS PER 3071-DGEN-5-14-0001,Section 3.3 EXT. JACKETTING (IF ANY) -
20 NOZZLE LOADS PER 3071-DGEN-5-14-0001,Sec-3.3 (n) REINFORCEMENT PADS 5 A 516 GR 60N + HIC (Note-41)
21 LENGTH (TAN-TAN) (Note-35) 7000 mm EXT. NOZZLE NECKS A 106 GR B / A 516 GR 60N
22 INTERNAL DIAMETER (Note-35) 2200 mm EXT. FLANGES A105N
23 SHELL THICKNESS 20* mm EXT. FLANGE BOLTING A 193 GR B7M / A 194 GR 2HM
24 HEAD THICKNESS (SEE NOTE-10) 20* (MIN AFTER FORMING) mm INT. NOZZLE NECKS SS 316
25 SUPPORT TYPE 2 SADDLES (@ 5100 mm CL to CL) INT. FLANGES SS 316
26 INSULATION (HOT / COLD / PP) YES / NO THK. mm EXTERNAL GASKETS (CONFINED DIMENSIONS) SS Spiral Wound Gasket
27 PASSIVE FIRE PROTECTION YES / NO INT. BOLTING & INT. GASKETS Duplex Stainless Steel
28 LADDERS & PLATFORMS (SEE NOTE-14) YES / NO INT. ATTACHMENTS (WELDED) SS 316L
29 CLIPS FOR LADDERS/PLATFORMS (SEE NOTE-14) YES / NO EXT. ATTACHMENTS (SEE NOTE-21) A 516 GR 60N / A 285 GR C
30 CLIPS FOR PIPE SUPPORTS (SEE NOTE-14) YES / NO INTERNALS (SEE NOTE-15) SS 316L
31 INSULATION SUPPORTS YES / NO SADDLE SUPPORTS A 285 GR C
32 LIFTING LUGS YES SADDLE WRAPPER PLATES A 516 GR 60N
33 EARTHING BOSS ASSEMBLY (1 PER SADDLE) YES FRICTION PLATE BELOW THE SLIDING SADDLE *
34 ANY SHELL FLANGE / DAVIT ARRANGEMENT NO ANCHOR BOLTING REQUIREMENT, SIZE, QTY, MATERIAL (Supply by Others)
35 MANWAY COVER HINGED / WITH DAVIT NAMEPLATE SS 316
36 FABRICATION, INSPECTION, TESTING & CERTIFICATION PROTECTIVE COATING / LINING
37 INSPECTION AUTHORITY SEE NOTE-11 SURFACE PREPARATION (EXTERNAL) PER QP-SPC-L-002
38 HEAT TREATMENT Yes (SEE NOTE-19 & 20) COATING (EXTERNAL) PER QP-SPC-L-002, Schedule 1Un
39 SPECIAL HEAT TREATMENT - SURFACE PREPARATION (INTERNAL) PER QP-SPC-L-002
40 MATERIAL IMPACT TESTS PER CODE & SPECS.(Note-38) COATING (INTERNAL) PER QP-SPC-L-002, Schedule 8
41 MATERIAL TENSILE TEST PER CODE & SPECS.(Note-38) PICKLING AND PASSIVATION *
42 MATERIAL MICROSTRUCTURE EXAM. PER CODE & SPECS.(Note-38) VESSEL PRESERVATION DESSICANT / NITROGEN FILL (SEE NOTE-16)
43 MATERIAL CERTIFICATES 5 EN 10024 - 3.1B WEIGHTS & LIQUID VOLUMES
44 WELDING PROCEDURE SEQUENCE PER CODE & SPECS.(Note-38) EMPTY (ERECTED) CONDITION 10,750 * kg
45 WELDING PROCEDURE QUALIFICATION PER CODE & SPECS.(Note-38) OPERATING CONDITIONS 35,350 * kg
46 WELDER PERFORMANCE QUAL. TESTING PER CODE & SPECS.(Note-38) HYDROTEST CONIDITION 37,750 * kg
47 CORROSION TEST PER CODE & SPECS.(Note-38) LOOSE INTERNALS * kg
48 HARDNESS TEST PER CODE & SPECS.(Note-38) TOTAL CAPACITY 27 m3
49 RADIOGRAPHY PER CODE & SPECS.(Note-38) LIQUID CAPACITY @ L.A.H.H. VTA based on liquid levels in p.no 5 of 7 m3
50 DYE PEN EXAM. / MAGNETIC PARTICLE EXAM PER CODE & SPECS.(Note-38) LIQUID CAPACITY @ L.A.H. VTA based on liquid levels in p.no 5 of 7 m3
51 ULTRASONIC TESTING PER CODE & SPECS.(Note-38) LIQUID CAPACITY @ N.L.L. VTA based on liquid levels in p.no 5 of 7 m3
3
52 PNEUMATIC TESTING (For Reinforcement Pads) Yes (SEE NOTE-28) LIQUID CAPACITY @ L.A.L. VTA based on liquid levels in p.no 5 of 7 m
53 HYDROSTATIC TEST PER 3071-DGEN-5-14-0001,Sec-4.2 LIQUID CAPACITY @ L.A.L.L. VTA based on liquid levels in p.no 5 of 7 m3
54 VENTING DATA
55 MAX. BREATHING RATE TBA Nm3/h RELIEVING TEMPERATURE TBA 0
C
56 MAX. OUTBREATHING RATE TBA Nm3/h MAX. RELIEVING PRESSURE TBA bar (a) PCV failure
57 EMERGENCY RELIEF FLUID TBA
58 FLOW TBA kg/h
59 MW TBA
60
61
62

FRONT END ENGINEERING DESIGN (FEED)


FOR REPLACEMENT OF OLD 3-PHASE TEST SEPARATORS
AT ALL DEGASSING STATIONS, DUKHAN FIELD
Contract No: LC12102200 sh: 3 of 7
Document No: 3071-DGEN-5-13-0001 Rev: 5
QP Ref: LC12102200
DATA SHEET PLANT Degassing Stations
NEW 3-PHASE TEST SEPARATORS LOCATION Dukhan Field

1 NOZZLES TABLE
2 MARK No. Off SIZE FLANGE RATING / TYPE NOZZLE NOZZLE RF PAD DIMs. SERVICE REMARKS

3 No. Nozzles (NB) ASME B 16.5 FACE SCH. NECK SCH. ORIENTN. O.D. THK.
4 N1 1 10" # 150, WN RF * * * * * Feed Inlet Nozzle
5 N2 1 8" # 150, WN RF * * * * * Gas outlet Nozzle SEE NOTE-31
6 N3 1 6" # 150, WN RF * * * * * Oil Outlet Nozzle SEE NOTE-7
7 N4 1 6" # 150, WN RF * * * * * Water Outlet Nozzle SEE NOTE-7
8 N5 1 6" # 150, WN RF * * * * * PSV line
9 N6 1 2" # 150, WN RF * * * * * Vent Connection
10 N7 A/B 2 2" # 150, WN RF * * * * * Drain Connection
11 N8 & N18 2 2" # 150, WN RF * * * * * Utility Connection
12 N9 & N10 2 2" # 300, WN RF * * * * * TI
14 N11 A/B 2 2" # 300, WN RF * * * * * PT
15 N12 A/B/C 3 4" # 300, WN RF * * * * * LT (Water Level) (SEE NOTE-40) Nozz @ water phase side of vessel
16 N13 A/B/C 3 2" # 300, WN RF * * * * * LT (LALL- Water) (SEE NOTE-40) Nozz @ water phase side of vessel
17 5 Deleted
18 N15A/B 2 4" # 300, WN RF * * * * * LT (Oil Level) Nozz @ Oil phase side of vessel
17 Deleted
18 N17 1 3" # 150, WN RF * * * * * Sand Jetting (Note-8)

19 M1 & M3 2 24" # 150, WN RF * * * * * Manhole (Note-6) C/W BF, BOLT, NUT, GASKET & Davit

20 M2 1 6" # 150, WN RF * * * * * Hand Hole (Note-6) C/W BF, BOLT, NUT, GASKET & Davit

21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
55
53
54
55
56
57
58

FRONT END ENGINEERING DESIGN (FEED)


FOR REPLACEMENT OF OLD 3-PHASE TEST SEPARATORS
AT ALL DEGASSING STATIONS, DUKHAN FIELD
Contract No: LC12102200 sh: 4 of 7
Document No: 3071-DGEN-5-13-0001 Rev: 5
Data Sheet for New 3-Phase Test Separator
24-V-XXX1, 22-V-XXX1, 23-V-XXX1,
1 Tag No. 14-V-XXX1, 12-V-XXX1, 13-V-XXX1 & Client: Qatar Petroleum
31-V-XXX1
2 Title: 3-Phase Test Separator Plant Location: Degassing Stations-Dukhan
3
4
5 VESSEL SKETCH
6
7 5
8
2:1 Ellipsoidal D'end Head (Typ.)
9
10 20mm Thk.(Min.) after forming 7,000 TL/TL
11
N1 M2 N6 N5 N12A N11A N11B N16A
12 N13A
Thk. 20mm N2 N15A

13 (Min.)
T.L T.L
14
15
16 N10
N18

ID = 2,200
17
N9 WEIR PLATE
18
M3 M1
19 N12C
N13C

1100
20
N12B
21 N13B

22 N8

1400
23
N15B
24
N7A N17 N4 N3 N7B
25
26
27 950 Slope 2% 1100
28 (Typ.) 5100 C/L to C/L
29
30 FIXED SADDLE SLIDING SADDLE

31
32
33
34 3 PHASE TEST SEPARATOR
35 OPERATING LEVELS SETTINGS

36 1675 mm LAHH (OVERALL)


37 1575 mm LAH (OVERALL)
38 1375 mm NL NORMAL (OVERALL)
39 1175 mm LAL (OVERALL)
40 825 mm LIAH (INTERFACE)
41 650mm NIL NORMAL (INTERFACE)
42 400 mm LIAL (INTERFACE)
5
43 300 mm LIALL (INTERFACE)
44
45
46
47
48 1.All Dimensions are in mm.
49
50
51
52
53
54

FEED FOR REPLACEMENT OF OLD 3-PHASE TEST


SEPARATORS AT ALL DEGASSING STATIONS,
DUKHAN FIELD
Project No: 3071 Sh. 5 of 7
3071-DGEN-5-13-0001 Rev. 5
QP Ref: LC12102200
DATA SHEET PLANT Degassing Stations
NEW 3-PHASE TEST SEPARATORS LOCATION Dukhan Field

1 GENERAL NOTES
2

3 1 All data marked as '*' shall be furnished and confirmed by vendor / supplier.

3 2 The water cut for maximum oil and maximum gas case is 0%. However 5% WC has been considered for sizing calculation.
New Test Separator design shall include the latest technology for the internals in order to enhance oil/water/gas separation to improve well testing
3 3
accuracy.

3 4 At any given time one of the well shall always be online to the Test Separator.

Separators should be equipped with jet nozzles to support online cleaning of the accumulated solids in the bottom of the vessel to maintain
3 5 retention volume and to prevent the formation of sulphate reducing bacteria colonies within the solids accumulated in the bottom of vessel.The
new test separators shall have the provision for sand jetting facility.
3 6 No.of Manhole & Handhole to be confirmed by vendor.
3 7 Vortex breaker to be added on the water outlet and oil outlet nozzles.
3 8 Vendor shall advise/confirm the sand jetting nozzle size.

The vessel shall be designed and manufactured per ASME Sec VIII Div-1 & U1 stamp requirements. Vendor shall also follow the requirements of
Technical specification - New 3phase test separators, doc. no. 3071-DGEN-5-14-0001 & QP Engineering standard - Pressure Vessels Design
4 9
and Fabrication, doc. no. ES.5.06.0003. Latest revision of code and specifications shall be followed for the design, fabrication, inspection and
testing of the equipment.

Heads shall be normally 2:1 semi-ellipsoidal type, unless otherwise specifically agreed upon with QP in-writing. Minimum thickness after forming
5 10 & Nominal Plate thickness as well as the Forming / Heat treatment procedures shall be provided by the Supplier & discussed during the quotation
stage.

Supplier shall engage a recognized inspection authority to certify compliance with appropriate QP Stanadards, Design Codes, Project & other
related Specifications - to include as a minimum - Design Appraisal, Validate all the Design and Project Specification requirements, Fabrication
6 11
Survey and Endorsement of Supplier MDR. Recognized design verification and certification agencies are normally DNV, Lloyds, ABS, BV, TUV
which shall be assigned by QP.

Nozzle outstands are measured from vessel CL or the dished head T.L. upto the flange face, unless otherwise stated. All flange bolt holes to
7 12
straddle vessel center lines.

Hydrotest gaskets shall be same as Service Gaskets while performing Vessel hydrostatic testing at the shop floor. These shall be replaced with
8 13
the actual designed (new) gaskets after the test.

Ladders and Platforms shall be supplied by Vessel Manufacturer. The welded clips that are required for installation of these and for any piping
9 14 connections / supporting shall also be provided by the Vessel Manufacturer. The location, details and any special design shall be developed
during detail engineering review stage.

All the removable internals shall be designed and fabricated for installation / removal through the manholes, without perfoming any cutting
operations. All these internals shall be 100% fitted and certified checked for accuracy per approved drawings by the Third Party Inspectorate,
10 15
unless otherwise agreed upon in-writing with QP. Supplier shall perform and provide a proper design for all the removable internals, to ensure that
they are in-tact even during road / sea transportation, and during any process upset conditions.

Unless otherwise specified the Internal surfaces of the Vessel shall be cleaned completely and a calculated quantity of dessicant / vapour phase
inhibitor shall be placed inside before closing and sealing the nozzles for shipment. Lables, Warning the presence of inhibitor to be displayed on
11 16
the vessel before crating for shipment. Since the Vessels shall be supplied with internal coating, the shipment details shall be discussed
separately with QP during the bidding stage.

The Vessel Manufacturer/Supplier shall furnish details of the loading on each saddle, anchor bolt requirements, moments on anchor bolting, and
12 17 the CG location of the Vessel while lifting in the Erection Condition. Preliminary data shall be furnished during the bid stage, which shall be
verified and certified during the as-built drawing stages.

13 18 All horizontal vessels shall be hydrostatic tested at shop along with the saddles in place, and shall be design checked accordingly.

14 19 Complete equipment including supports shall be undergone Post Weld Heat Treatment (PWHT).

Hardness of base metal, weld and HAZ shall be less than the hardness limit specified in NACE MR 0175 with supplementary requirements
15 20
presentated in QP technical standard for materials for sour service QP-STD-R-001.

As equipment is under sour service, materials of construction shall comply the requirements of QP Standard QP-STD-R-001 (Materials for Sour
16 21 Service), together with NACE Standard MR-0175 / ISO 15156. Material of construction for external attachments directly welded to shell/head shall
be same as shell material.
17 22 For nozzle with blind flange, Vendor shall supply companion flanges along with nut, bolts, gaskets etc.

FRONT END ENGINEERING DESIGN (FEED)


FOR REPLACEMENT OF OLD 3-PHASE TEST SEPARATORS

AT ALL DEGASSING STATIONS, DUKHAN FIELD


Contract No: LC12102200 sh: 6 of 7
Document No: 3071-DGEN-5-13-0001 Rev: 5
QP Ref: LC12102200
DATA SHEET PLANT Degassing Stations
NEW 3-PHASE TEST SEPARATORS LOCATION Dukhan Field

1 GENERAL NOTES (Continuation)

2 23 Surface preparation and painting shall be as per QP specification QP-SPC-L-002.

3 24 Vendor shall perform 100% radiography for all the welds including nozzle to flange joints.

Flanges in sizes of DN 600 and smaller shall conform to the requirements of ASME B16.5. For sizes DN 650 through DN 1500 steel flanges
4 25
dimensions and ratings shall conform to ASME B 16.47 Series A. All flange bolt holes to straddle vessel center lines.

All connections DN 50 and smaller shall be provided with two stiffening gussets located at right angles unless the nozzle is a long weld neck type
5 26
construction.

All welding shall be in accordance with the requirements of ASME code, specification 3071-DGEN-5-14-0001 and QP Engineering standard
6 27
Pressure Vessels Design and Fabrication, doc. No. ES.5.06.0003, section 7.0.

7 28 All reinforcing pad welds shall be tested to 103 kPag minimum, with dry air or light oil, before PWHT.

8 29 Vessel shall be hydrotested prior to coating of the interior and exterior surfaces.

9 30 Manway shall be provided with internal ladders for access.

10 31 Gas outlet nozzle to be provided with mist eliminator.

11 32 Weir stability shall be verified by vendor considering the liquid head (with specific gravity =1) by one side only.

12 33 The internals arrangement and size should be Proposed by vendor.

13 34 Baffle stability shall be verified by vendor considering the liquid head (with specific gravity =1) by one side only.
14 35 Vendor to review and verify/confirm the equipment size.
15 36 One test separator at each station KM (24-V-XXX1), KN (22-V-XXX1), KS (23-V-XXX1), FM (14-V-XXX1), FN (12-V-XXX1), FS (13-V-XXX1)
16 and Jaleha (31-V-XXX1) will be installed.
17 37 Refer to 'Simulation and H&MB Report' for fluid compositions, Doc. No. 3071-DGEN-6-17-0001.
18 38 All these information will be updated after interpreting the Codes,Standards and Specifications by the Vessel Designer (Vendor)
19 during EPIC stage.
20 39 Tag No : 24-V-XXX1 P&ID Number : 3071-KAHM-6-50-0306
21 Tag No : 22-V-XXX1 P&ID Number : 3071-KAHN-6-50-0301
22 Tag No : 23-V-XXX1 P&ID Number : 3071-KAHS-6-50-0009
23 Tag No : 31-V-XXX1 P&ID Number : 3071-JALM-6-50-0301
24 Tag No : 14-V-XXX1 P&ID Number : 3071-FAHM-6-50-0011
25 Tag No : 12-V-XXX1 P&ID Number : 3071-FAHN-6-50-0009
26 Tag No : 13-V-XXX1 P&ID Number : 3071-FAHS-6-50-0010
27 40 Nozzles N12A and N13A will be set at top of Vessel & Nozzles 12C and N13C will be set at 850mm. 5
28 41 Plate material shall be HIC tested as per QP Std:QP-STD-R-001.
29 42 Internal coating shall be as per Schedule-8 (Vynil Ester Glass Flake reinforced resin) of QP Spec. (QP-SPC-L-002). 5
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46

FRONT END ENGINEERING DESIGN (FEED)


FOR REPLACEMENT OF OLD 3-PHASE TEST SEPARATORS

AT ALL DEGASSING STATIONS, DUKHAN FIELD


Contract No: LC12102200 sh: 7 of 7
Document No: 3071-DGEN-5-13-0001 Rev: 5

You might also like