BUILDING COMMISSIONING

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 1

Your guide is

Former Member GPC-0


Former Member GPC-1
Corresponding Member SGPC-0
Chair GPC 1.3
Member SSPC-202
Member IESNA CX GL committee
Consultant GPC-0.2
Presenter: ASHRAE 3-hour basic CX course
Developer: ASHRAE 3-hour Standard 202 CX course

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 2


2013
Presentation
Context

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 3

What is Commissioning?

A structured quality control process


intended to ensure that a building, when
delivered, meets the
owners project requirements
immediately upon turnover.

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 4


What is Commissioning?

An ongoing process

NOT an event
NOT a short-term activity

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 5

What is
Commissioning?

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 6


What can be Commissioned?

Buildings
Building systems
Active (dynamic)
Passive (static)
Building sub-systems

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 7

Why Commissioning?

Because stuff happens


Poorly identified owner needs/wants
Poorly executed work
Design
Construction
Operation/maintenance
Ineffective communications

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 8


Why Commissioning?
stuff

stuff

stuff

stuff

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 9

Why Commissioning?

stuff

stuff

stuff

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 10


ASHRAEs CX Role Past
ASHRAE Guideline 1-1989

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 11

ASHRAEs CX Role Past


ASHRAE Guideline 1-1996

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 12


ASHRAEs CX Role Now
ASHRAE Guideline 0-2013

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 13

ASHRAEs CX Role Now


ASHRAE Guideline
1.1-2007

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 14


ASHRAEs CX Role Future
ASHRAE Guideline 0: Process
ASHRAE Guideline 1.1: HVAC&R
ASHRAE Standard 202: Process < code language >
ASHRAE Guideline 0.2: Existing CX Process
ASHRAE Guideline 1.2: Existing HVAC CX
ASHRAE Guideline 1.3: CX Training
ASHRAE Guideline 1.4: Systems Manual
ASHRAE Guideline 1.5: Smoke Control
ASHRAE Guideline 1.6: ????
Certification
Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 15

What Guideline Does What


Guideline 0 defines the process
Generic: for any system or discipline
The basis for all subsidiary guidelines

Guideline 1.1 describes how to apply the


process to HVAC&R systems
HVAC&R specifics
Lots of annexes (examples)
No changes in process, but elaboration

Other guidelines for other disciplines/issues

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 16


NIBS Guideline 3
(National Institute of Building Sciences)
about to become an ASTM document

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 17

ASHRAE Guideline 0
Title, Foreword, Purpose, Scope,
Utilization, Definitions
Project Delivery Phases
Pre-Design
Design
Construction acceptance
Occupancy and Operations
References
Annexes (many)
Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 18
The Guideline 0 Process
Communication
Documentation
Verification

Essentially describes a team effort to


assure quality that is led by an
independent party (the commissioning
provider) working on behalf of the owner

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 19

The Commissioning
Process Team
Many members
Members change from phase to phase
Guided by the commissioning provider
Team will complete various tasks
Responsibility for tasks must be clearly
allocated and contractually assigned
Roles and responsibilities will change from
project to project

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 20


Pre-Design Phase CX Activities

Hire Commissioning Provider


Develop Owners Project Requirements (OPR)
document
Intent and criteria; objectives and benchmarks;
Develop draft Commissioning Plan document
Scope, budget, schedule
Develop contractual relationships for design
professionals
Obtain owner acceptance of documents

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 21

Design Phase CX Activities


Develop Basis of Design document
Update Owners Project Requirements
Update and expand Commissioning Plan
Develop Checklists and Test Protocols
For implementation (typically) by contractor
Develop Training Plan
For implementation (to a large extent) by contractor
Obtain owner acceptance of all the above

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 22


Construction Phase CX Activities
Update Basis of Design document
Update Owners Project Requirements
Update Commissioning Plan
Implement Checklists / Test Protocols
Sampling is recommended
Implement Training Plan
Prepare Systems Manual
O&M manual plus
Attempt to minimize punchlist issues
Obtain owner acceptance of work

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 23

Occupancy and Operations


Phase CX Activities
Update Owners Project Requirements
Update Commissioning Plan
Implement deferred Checklists and tests
Implement deferred training
Complete Systems Manual
Obtain owner acceptance of work
Ideally implement ongoing commissioning
process

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 24


Keys to a Successful
Commissioning Process
Explicit expectations for all involved
Clear RFQ and contract for CX provider
Professional service contracts (especially for
the design team) that address commissioning
Construction specifications that clearly
address commissioning requirements and
provide clear statements of who and if-then

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 25

Keys to a Successful
Commissioning Process
Effective process documents
Owners Project Requirements
Basis of Design
Commissioning Plan
Construction Checklists
Test Protocols
Training Plan
Systems Manual
Commissioning Process Reports

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 26


OPR Intent/Criteria

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 27

Keys to a Successful
Commissioning Process

Ongoing informative communications


Commissioning meetings and minutes
Commissioning reports
Issues Log
Commissioning documents in general

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 28


Keys to a Successful
Commissioning Process
Verification by the commissioning team
Of OPR-influencing design decisions
Design validation
Of OPR-influencing installed equipment,
systems, assemblies
Construction validation
Using Construction Checklists
Using test protocols
Against Owners Project Requirements
(discuss)
Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 29

Keys to a Successful
Commissioning Process
Owner acceptance
Of all key deliverables/products

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 30


Key Guideline-0
Recommendations
The design team is responsible for design
and design quality
The commissioning team will verify design artifacts for
compliance with the Owners Project Requirements
using statistical sampling
The contractor is responsible for
construction and construction quality
The commissioning team will verify construction
artifacts for compliance with the Owners Project
Requirements and the Construction Documents using
statistical sampling
Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 31

Key Guideline-0
Recommendations
Start commissioning at pre-design
The Owners Project Requirements are the
validation benchmark (not just CDs)
Use an independent commissioning provider
Establish a viable commissioning team
Use statistical sampling (versus 100%)
All activities to be explicitly defined ahead of
time (no surprises)

Ball State Architecture | ENVIRONMENTAL SYSTEMS 2 | Grondzik 32