You are on page 1of 254

LABOUR RATES FOR CONSTRUCTION WORKS FOR

YEAR 2001/2002
Labour Rate with
Item Description Unit Rate material
Rs. Cts. Rs. Cts.

B EXCAVATION

B-01 Excavation of soil in bulk and deposited at


site as directed by the Engineer within 25m
other than rock requiring blasting m3 100.00

B-02 - do - hard soil requiring ripping m3 130.00

B-03 - do - soft rock excavation m3

B-03 Excavation for foundation to a depth not


exceeting 1.5m in any material except rock
requiring blasting part return fill including
compacting & surplus deposited within site.
m3 145.00 461.48

B-04 Approved hard earth filling inside the building


up to DPC level including spreading
,watering and ramming in 75mm layers.
(Earth available at site)
m3 180.00

C CONCRETOR

Manual Mixing
( Not for retaining walls)
C-01 1:3:6(40mm) concrete (50mm thick) m2 60.00

C-02 1:3:6(40mm) concrete (75mm thick) m2 100.00

C-03 1:3:6(40mm) mass concrete m3 800.00

C-04 1:2:4(20mm ) ct. concrete for volume up to 3


cum (Formwork and Reinforcement paid m3 1,100.00
separately)
C-05 Extra over item C04 for each lift (manual).
Measurements from floor to floor m3

C-05a - do - in upper floor m3 85.00

C-05b - do - in 2nd floor m3 170.00

C-06 1:2:4(20mm) R/F concrete for volume above


3 Cum (Formwork and Reinforcement paid
separately) m3 950.00

C-07 1:2:4(20mm ) ct. concrete for Columns


(Formwork and Reinforcement paid
separately) m3 1,100.00 #REF!
C-08 1:2:4(20mm ) ct. concrete for Slab and
beams (Formwork and Reinforcement paid
separately) volume above 15 m3 m3 1,300.00 #REF!

C - 08a 1:2:4(20mm ) ct. concrete for Slab and


beams (Formwork and Reinforcement paid
separately) volume up to 15 m3 m3 1,100.00 #REF!

C-09 1:2:4(20mm ) ct. concrete in 115x150mm


lintols including formwork ( Reinforcement
paid separately) Lm 130.00 #REF!

C-10 1:2:4(20mm ) ct. concrete in 225x150mm


lintols including formwork ( Reinforcement
paid separately) Lm 140.00 #REF!

C-11 1:2:4(20mm ) ct. concrete in 225x225mm


lintols including formwork ( Reinforcement
paid separately) Lm 160.00 #REF!

C-12 1:2:4(20mm ) ct. concrete in 300x225mm


lintols including formwork ( Reinforcement
paid separately) Lm 180.00 #REF!

C-13 Placing manualy, levelling and vibtrating the


ready mixed pumpable concrete m3 550.00

C-14 Levelling & vibrating the ready mixed


pumping concrete pumped to final location m3 120.00

D FORMWORK

D-01 Formwork for columns using plywood sheets


m2 120.00 #REF!

D-02 Formwork for slabs using plywood sheets m2 120.00 #REF!

D-03 Formwork for beams using plywood sheets


m2 140.00 #REF!

D-04 Formwork for columns using timber planks


m2 120.00

D-05 Formwork for beams using timber planks m2 150.00 #REF!

E REINFORCEMENT

E-01 Reinforcement for foundation , Kg 6.00 #REF!


beams,columns,slabs etc.
F BRICK / BLOCK MASONARY

F-01 225mm brick work in 1:5 cement mortar m3 700.00 #REF!


760.00
F-01a Extra over item F -04 for each lift (manual).
Measurements from floor to floor m3 105.00

F-02 112mm brick work in 1:5 cement mortar m2 100.00 #REF!


F-02a Extra over item F -02 for each lift (manual).
Measurements from floor to floor m2 35.00

F-03 200mm thick block works m2 120.00 #REF!

F-04 150mm thick block work in 1:5 cement mortar


m2 100.00 #REF!

F-05 100mm thick block work in 1:5 cement mortar


m2 90.00 #REF!

F-06 300mm wide 225mm to 400mm deep brick


drains in 1:5 cement mortar complete with
12mm thick1:2 cement rendering finished
smooth m 300.00 #REF!

F-07 225mm wide 150mm to 225mm deep brick


drains in 1:5 cement mortar complete with
12mm thick1:2 cement rendering finished
smooth m 250.00 #REF!

G MASONRY WORK

G-01 Random rubble masonary in 1:5 cement


mortar ( width greater than 400mm) m3 600.00 #REF!

G-02 Random rubble masonary in 1:5 cement


mortar ( width less than 400mm) m3 650.00 #REF!

G-03 Extra over item G01 for pointing exposed


rubble masonry m2 200.00

H PAVIOR

H-01 75mm thick brick paved floors set in 1: 5


cement mortar including 12mm thick 1:3
cement rendering m2 180.00 #REF!

H-02 Fixing of pressed cement tiles or Teracota


tiles including 20mm thick 1;3 cement sand
mortar m2 225.00 #REF!

H-03 Laying of Terrazo floor tiles including 12mm


thick 1:3 cement mortar levelling screed etc.
m2 200.00 #REF!

H-04 Laying of Ceramic floor tiles including 20mm


thick 1:3 cement sand bedding m2 225.00 #REF!

H-05 Laying of Ceramic tile skirting including


20mm thick 1:3 cement sand bedding m 40.00

H-06 Fixing of glazed tiles with all specials to


walls including raking , plastering and
bedding in 12mm thick 1:3 cement mortar m2 225.00 #REF!

J ROOFER
J-01 Corrugated asbestos sheet roofing including
timber frame work for single storied m2 120.00 #REF!

J-02 Corrugated asbestos sheet roofing on timber


frame work for hip roof for single storied
m2 150.00

J-03 Corrugated asbestos sheet roof on existing


frame m2 50.00 #REF!

J-04 Calicut pattern ridging bedded in 1:1:4


cement lime sand mortar coloured to match
tiles m 50.00 #REF!

J-05 Calicut pattern tiled roof on timber frame


work m2 180.00 #REF!

J-05a Calicut pattern tiled roof on timber frame


work including laying tar sheet m2 200.00

J-06 Laying half - round tiles on existing timber


roof frame work m2 30.00 #REF!

J-07 Laying half - round tiles over asbestos sheet


m2 3.00 #REF!

J-08 900mm wide valley gutters including timber


boading m 200.00 #REF!

J -09 Colour bond Zinc Alum roofing sheets on


steel frame work m2 50.00

J -10 Laying lip channel purlins m 30.00

J -11 Purlin roof m2 80.00

K CARPENTER & JOINER

K-01 Making of door frame m 60.00

K-02 Making of window frame m 70.00

K-03 Making of fully panelled door /window sash m2 1,000.00


K-04 Fixing of door /window frame Nos 260.00

K-05 Fixing of door /window sash m2 250.00

K-06 Making of glazed /panelled door/window m2 1,000.00

K-07 Flat asbestos ceiling including timber frame


work m2 200.00 #REF!

K-08 Lunumidella ceiling including timber frame


work m2 210.00 #REF!

K-09 Lunumidella ceiling underside of roof rafters m2 75.00 #REF!

K-10 Making and fixing of 20mm thick valance


board m 70.00 #REF!

K-11 Fixing of mortice or night latch lock (single) No 100.00 #REF!

K-12 Fixing of union mortice lock (double sash) No 200.00 #REF!

K-13 Fabrication and fixing mild steel purlins /


trusses. Rate included for painting. Steel and
paint supplied by the Bureau kg 22.00

K -14 Supplying & fixing of 32mm glazed and


panelled door sashes and 100mm x 75mm
frames in class1 local timber fixed complete
with brass furniture 75mm frames in class1
local timber m2 1,570.00

K15 Supplying & fixing 0f 32mm thick ordinary


sash single (Ordinary finish) plywood door
hung on 100mm x 75mm frame in class 1
timber complete with brass furniture m2 1,570.00

L PLASTERER

L-01 20mm thick, 1:2 cement sand D.P.C and


finished smooth with 2 coats of hot tar
blinded with coarse sand m2 120.00 #REF!

L-02 15mm thick ,1:1:5 cement lime plastering


finished rough m2 100.00 #REF!

L-03 15mm thick ,1:1:5 cement lime plastering and


finished smooth with lime putty m2 115.00 #REF!

L-04 15mm thick plastering,1:1:3 cement lime and


sand to R.C.C beams and slab soffit
including floating with lime putty m2 150.00 #REF!

L-04A Application of lime putty for beams and slab


soffits m2 110.00 #REF!
L-05 12mm thick, 1:3 cement rendering, including
neat cement or coloured cement floating
m2 85.00 #REF!

L-06 20mm thick, 1:3 cement rendering, including


neat cement or coloured cement floating
m2 100.00 #REF!

L-07 12mm x 100mm skirting in 1:3 projected on


flush with wall and including forming groove.
m 60.00 #REF!

L-08 Plastering to column of 225 x 225mm m 240.00 #REF!

L-09 Plastering to column of 150 x 150mm or 100


x 150mm m 200.00 #REF!

L-10 Plaster to reveals m 60.00

L-11 15mm thick plastering with 1:5 cement , sand


& febmix in walls ( external) m2 90.00 #REF!

L-12 15mm thick plastering with 1:5 cement , sand


& febmix in walls ( internal) m2 90.00 #REF!

L-13 15mm thick plastering with 1:5 cement , sand


& febmix in columns m2 192.00 #REF!

M ROOF PLUMBER

M-01 Fixing of 150mm PVC square gutters with


PVC brackets and screws at 450mm
intervals including all necessary moulded Lm 30.00 #REF!
fittings.
M-02 Fixing of 100 mm dia. PVC Down Pipes Lm 30.00 #REF!

M-03 Fixing of GI square gutters Lm 180.00 #REF!

M-04 Fixing of GI down pipes Lm. 165.00 #REF!

M-05 Supplying & fixing of 0.47 x470 mm


Zink Alum gutters Lm. 115.00 #REF!

M-06 Fixing of Zink Alum down pipes Lm. 115.00 #REF!

N PAINTER & DECORATOR

N-01 Painting one coat of Enamel Paint including


preparation of surface m2 20.00 #REF!

N-02 Painting two coats of Enamel Paint m2 50.00 #REF!

N-03 Painting new wood work with one coat of


wood primer m2 25.00 #REF!

N-04 Painting new wood work with one coat of


wood primer and two coats of Enamal paint m2 70.00 #REF!
N-05 Painting steel work with one coat of
Anticorrosive and and two coats of enamal
paint including scaling and wire brushing.
m2 70.00 #REF!

N-06a Painting wall with one primer coat and two


coats of Emulsion paint m2 55.00 #REF!

N-06b Painting wall with one primer coat and two


coats of Enamel paint (for hospital wards)
up to 1.5m height m2 50.00 #REF!

N-07 Varnishing with one coat of sanding sealer


and two coats of varnish (Rate included for
sand papering) m2 80.00 #REF!

N-08 Prepare and apply one coat of CIC putty, one


coat of primer and two coats of emulsion to
soffit of slabs (including sand papering and
preparing surface) m2 80.00 #REF!

N-09a Painting walls with one primer coat and two


coats of weathershield paint. m2 45.00 #REF!

N-10 Painting floors with one coat of floor paint


including preparing surface. m2 20.00 #REF!

N-11 Painting floors with two coats of floor paint


including preparing surface. m2 30.00 #REF!

N-12 Painting roof covering with two coats


weathershield paint. m2 30.00 #REF!

N-13 Floor polishing and waxing after washing,


cleaning and preparing surface (Polisher
provided) m2 30.00 #REF!

N-14 Painting cement grill work over doors &


windows with one coat of primer & two coats
of paint for double side. m2 125.00

P PLUMBING

P-01 Laying 20mm to 32mm PVC pipe including


trenching, back filling and making good to
walls m 35.00 #REF!

P-02 Laying 40mm to 50mm PVC pipe including


trenching, back filling and making good to
walls m 35.00 #REF!

P-03 Laying 63mm to 75mm PVC pipe including


trenching, back filling and making good to
walls m 60.00 #REF!

P-04 Laying 110mm PVC pipe including trenching,


concreting and back filling (Up to 600mm) m 125.00 #REF!
Laying 160mm PVC pipe including trenching,
concreting and back filling (Up to 600mm)
m 125.00 #REF!

P-05 Fixing of wash basin with tap No 600.00 #REF!

P-06 Fixing of commode with cistern No 700.00 #REF!

P-07 Fixing of squatting pan with cistern No 700.00 #REF!

P-08 Fixing of bidet shower No 100.00

P-09 Fixing of high level cistern No 350.00 #REF!

P-10 Fixing of stainless steel sink with tap No 450.00 #REF!

P-11 Fixing of 1/2" pillar cocks to basin No 65.00

P-12 Fixing of 150mm x 12mm PVC Shower Rose No 25.00

P-13 Fixing of urinals No 100.00 #REF!

P-14 Fixing of 1/2" - 2" gate valve/stop cock No. 50.00 #REF!

P-15 Fixing of soap tray No. 50.00 #REF!

P-16 Fixing of bath room mirror No. 50.00 #REF!

P-17 Fixing of bib tap No. 30.00 #REF!

P-18 Laying 160mm PVC pipe including trenching,


concreting and back filling (Up to 600mm)
m 150.00

P-19 600 x600 mm manhole up to 600mm deep


constructed in 225mm brick in 1:3 cement
sand mortar & 12mm cement rendered walls
and 150mm thick 1:3:6( 25mm) concrete
foundation with cover slab Nos 1,200.00 #REF!

P-20 1000 x700 mm manhole up to 600mm to


1200mm deep constructed in 225mm brick
in 1:3 cement sand mortar & 12mm cement
rendered walls and 150mm thick
1:3:6( 25mm) concrete foundation with cover
Nos 1,750.00 #REF!
slab

P-21 1000 x700 mm manhole up to 1200mm to


1800mm deep constructed in 225mm brick
in 1:3 cement sand mortar & 12mm cement
rendered walls and 150mm thick
1:3:6( 25mm) concrete foundation with cover
slab
Nos 3,000.00 #REF!

R - ROAD WORKS
R-01 Laying 4" metal m3 14.50

R-02 Laying 2" & 3/4" metal m3 13.75

R-03 Spreading 80/100 bitumen ( 1 st coat) m2 12.25

R-04 Spreading 80/100 bitumen ( 2 nd coat) m2 6.00

R-06 Casting of kerbs (600mm Long) m 40.00

R-07 Fixing of kerbs m 60.00

R-07a Surface preparation( brushing) & Applying


MC 30 m2 12.00

R-08 Casting & fixing of 450 x 450 mm walkway


slabs ( with R/F ) m2 249.00

R-09 Casting & fixing of 450 x 450 mm walkway


slabs ( with out R/F ) m2 214.50

S - CHAINLINK FENCE

S1 Casting of fence posts (Y type) Nos 240.00

S2 Erection & fixing of fence posts Nos 175.00

S3 Straining barbed wire with 7 strands m 19.50

S4 Supplying & fixing of chainlink mesh m2 28.75


Rates Applicable for works in Trincomalee August 2005

Basic rate
Rate No Description Unit with material
Amount Rs. Cts.

Earth work

Earth excavation for foundation m3 - 461.48

Earth filling under floors with available


material m3 - 282.69

C - Concretor

C01 1:3:6 (25mm) concrete ( 50mm thick) at


Ground Level m2 828.00 608.82

C02 1:3:6 (40mm) concrete ( 75mm thick) at


Ground Level m2 1,187.00 872.79

C0 3 1:3:6 (25mm) concrete at Ground Level m3 14,368.00 10,564.71

CO4 1:2:4 (20mm) concrete ( volume up to 3 m3)


at Ground Level m3 17,373.00 12,774.26

CO5 100mm thick 1:2:4 (25mm) concrete with 6"x


6" BRC mesh(6mm) m2 1,878.00 1,380.88

CO5a 1:2:4 (20mm) concrete ( volume up to 3m3)


at 1st floor level m3 17,492.00 12,861.76

CO5b 1:2:4 (20mm) concrete at 2nd floor level m3 18,443.00 13,561.03

CO6 1:2:4 (20mm) concrete for volume above 3


m3 m3 16,384.00 12,047.06

CO 7 1:2:4 (20mm) concrete in columns for volume


above 3 m3 m3 15,592.00 11,464.71

CO8 1:2:4 (20mm) concrete in slabs & beams for


volume above 15 m3 m3 17,288.00 12,711.76

C - 08a 1:2:4 (20mm) concrete in slabs & beams for


volume up to 15 m3 m3 17,624.00 12,958.82

C- 09 x 1:11/2:3 (20mm) concrete m3 18,055.00 13,275.74

C - 09 1:2:4 (20mm) concrete in 150 x 112mm lintols


(including reinforcement) m 1,031.00 758.09

C - 10 1:2:4 (20mm) concrete in 225mm x 150mm


lintols (including reinforcement) m 1,298.00 954.41

C - 11 1:2:4 (20mm) concrete in 225mm x 225mm


lintols ( including reinforcement) m 1,929.00 1,418.38

C - 12 1:2:4 (20mm) concrete in 300mm x 225mm


lintols ( excluding reinforcement) m 2,484.00 1,826.47
-
C - 13 1:2:4 (20mm) ready mixed concrete , placing
manually, levelling & vibrating m3 1,727.00 1,269.85
-
C - 14 1:2:4 (20mm) ready mixed concrete
pumping, levelling & vibrating m3 18,860.00 13,867.65
-

file:///conversion/tmp/scratch/363037749.xls
Rates Applicable for works in Trincomalee August 2005

Basic rate
Rate No Description Unit with material
Amount Rs. Cts.

D - Formwork -
-
D - 01 Formwork for columns using plywood sheets m2 1,260.00 926.47
-
D - 02 Formwork for slabs using plywood sheets m2 1,296.00 952.94
-
D -03 Formwork for beams sides , soffits using
plywood sheets m2 1,376.00 1,011.76
-
D-05 Formwork for beams using timber planks m2 1,014.00 745.59

E - Reinforcement

E -01 Reinforcement for foundation


,beams,columns,slabs etc kg 228.00 167.65

E -01 Reinforcement for foundation


,beams,columns,slabs etc kg 208.00 152.94

F - Brick Layer -

F -01
225mm brick work in 1:5 cement sand mortar m3 10,552.00 7,758.82

F-02 112mm brickwork in 1:5 cement mortar m2 1,335.00 981.62

F - 03 200mm thick block works in 1:5 cement


mortar m2 1,789.00 1,315.44

F -04 150mm thick block work in 1:5 cement


mortar m2 1,509.00 1,109.56

F - 05 100mm block work in 1:5 cement mortar m2 1,100.00 808.82

F-06 300mm wide 225mm to 400mm deep brick


drains in 1:5 cement mortar complete with
12mm thick 1:2 cement rendering finished
smooth. m 2,102.00 1,545.59

F- 07 225mm wide 150mm to 225mm deep brick


drains in 1:5 cement mortar complete with
12mm thick 1:2 cement rendering finished
smooth m 1,401.00 1,030.15

G - R/R Masonry -

G-01 Random rubble masonary in 1:5 cement


mortar ( width greater than 400mm) m3 9,651.00 7,096.32

G-02 Random rubble masonary in 1:5 cement


mortar ( width less than 400mm) m3 10,526.00 7,739.71

G-03 Pointing of rubble masonry wall surface m3 127.00 93.38


H - Pavior

H - 01 75mm thick brick paved cement rendered


floor including 12mm thick 1:3 cement
rendering m2 1,531.00 1,125.74

H - 02 Pressed cement tiles or terracotta m2 1,908.00 1,402.94

file:///conversion/tmp/scratch/363037749.xls
Rates Applicable for works in Trincomalee August 2005

Basic rate
Rate No Description Unit with material
Amount Rs. Cts.
H - 03 Terrazo floor tiles including 12mm thick 1:3
levelling screed m2 1,985.00 1,459.56

H - 04 Ceramic floor tiles including 20mm thick 1:3


levelling screed( TOILETS) m2 2,835.00 2,084.56

H - 05 Semi gloss floor tiles including 20mm thick


1:3 levelling screed m2 3,542.00 2,604.41

H - 06 Slate floor tiles including 20mm thick 1:3


levelling screed m2 3,309.00 2,433.09

H - O7 Rock finish tiling including 20mm thick 1:3


levelling screed m2 4,176.00 3,070.59

H - O8 Rock finish tiling including 20mm thick 1:3


levelling screed m2 5,067.00 3,725.74

H - 09 Glazed wall tiles including 20mm thick 1:3


raking plaster m2 4,443.00 3,266.91

H - 10 Glazed wall tiles including 20mm thick 1:3


raking plaster in toilets m2 4,442.51 3,266.55

H-11 Glazed wall tiles including 20mm thick 1:3


raking plaster in wards m2 2,829.00 2,080.15

J - Roofer -

J-01 Corrugated asbestos sheet roofing including


timber frame work for single storied m2 2,823.00 2,075.74

J-02 Corrugated asbestos sheet roofing including


timber frame work for hip roof m2 2,770.00 2,036.76

J-03 Corrugated asbestos sheet roofing on


existing frame work m2 1,277.00 938.97

J-04 Calicut pattern ridging in 1:1:4 cement lime


sand mortar coloured to match tiles m2 580.00 426.47

J-05 Calicut pattern tile roof on timber frame work


m2 6,351.00 4,669.85

J-06 Laying half round tiles on existing timber


frame work m2 2,548.00 1,873.53

J-07 Laying half round tiles on existing asbestose


sheet roof m 1,448.00 1,064.71

J-08 900mm wide valley gutters including timber


boarding m2 1,394.00 1,025.00

J-09 Colour bond Zinc Aluminium roofing sheets


on steel frame work m2 2,004.00 1,473.53

J-10 Colour bond Zinc Aluminium curved roofing


sheets on steel frame work m2 2,348.00 1,726.47

K - Carpenter & Joiner -

K-01 Flat asbestose ceiling with timber frame work


and painting m2 3,008.00 2,211.76

file:///conversion/tmp/scratch/363037749.xls
Rates Applicable for works in Trincomalee August 2005

Basic rate
Rate No Description Unit with material
Amount Rs. Cts.
K-02 Lunumidella ceiling including timber frame
work m2 2,704.00 1,988.24

K-03 Lunumidella ceiling underside of roof rafters m2 845.00 621.32

K-04 Making and fixing of 20mm thick valance


board including painting(Using Ginisapu) m2 1,548.00 1,138.24
-
K-05 Fixing of mortice or night latch door lock
( single door) No. 1,842.00 1,354.41
-
K-06 Fixing of mortice or night latch door lock
( double door) No. 2,350.00 1,727.94
-
K-07 Fabrication and fixing mild steel purlins /
trusses. Rate included for painting. Steel and
paint supplied by the Bureau kg. 193.00 141.91
-
K-08 Supplying & fixing of 32mm glazed and
panelled door sashes and 100mm x 75mm
frames in class1 local timber fixed complete
with brass furniture m2 18,141.00 13,338.97
-
K-09 Supplying & fixing of 32mm thick ordinary
sash single (Ordinary finish) plywood door
hung on 100mm x 75mm frame in class 1
timber complete with brass furniture m2 13,374.00 9,833.82
-
L - Plasterer -
-
L-01 20mm thick, 1:2 cement sand D.P.C and
finished smooth with 2 coats of hot tar
blinded with coarse sand m2 700.00 514.71
-
L-02 15mm thick ,1:1:5 cement lime plastering
finished rough m2 466.00 342.65
-
L-03 15mm thick ,1:1:5 cement lime plastering and
finished smooth with lime putty m2 505.00 371.32
-
L-04 15mm thick plastering,1:1:3 cement lime and
sand to R.C.C beams and slab soffit including
floating with lime putty m2 612.00 450.00
-
L-05 Application of lime putty to soffits of slabs &
beams m2 667.00 490.44
-
L-06 12mm thick, 1:3 cement rendering, including
neat cement or coloured cement floating m2 451.00 331.62
-
L-07 20mm thick, 1:3 cement rendering, including
neat cement or coloured cement floating m2 603.00 443.38
-
L-08 12mm x 150mm skirting in 1:3 projected on
flush with wall and including forming groove. m2 302.00 222.06
-
L-09 Plastering to column of 225 x 225mm m 952.00 700.00
-
L-10 Plastering to column of 150 x 150mm m 906.00 666.18
-
L-11 Plastering to reveals ( 100mm wide) m2 123.00 90.44
-

file:///conversion/tmp/scratch/363037749.xls
Rates Applicable for works in Trincomalee August 2005

Basic rate
Rate No Description Unit with material
Amount Rs. Cts.
L-12 15mm thick plastering with 1:5 cement , sand
& febmix in walls ( external) m2 335.00 246.32
-
L-13 15mm thick plastering with 1:5 cement , sand
& febmix in internal walls m2 541.00 397.79
-
L-14 15mm thick plastering with 1:5 cement , sand
& febmix in columns m2 904.00 664.71
-
M - Roof Plumber -
-
M-01 Fixing of 114mm PVC square gutters with
PVC brackets and screws at 450mm intervals
including all necessary moulded fittings
m 854.00 627.94
-
M-02 Fixing of 89 mm dia. PVC Down Pipes m 686.00 504.41
-
M-03 Fixing of GI gutters ( gauge 24 GI sheets) m 1,047.00 769.85
-
M-04 Fixing of GI down pipes ( gauge 24 GI
sheets) m 1,009.00 741.91
-
M-05 Supplying & fixing of 0.47 x470 mm Zink
Alum gutters m 1,330.00 977.94
-
M-06 Fixing of Zinc Alum down pipes m 1,151.00 846.32
-
N - Painter -
-
N-01 Painting one coat of Enamel Paint including
preparation of surface m2 161.00 118.38
-
N-02 Painting two coats of Enamel Paint including
preparation of surface m2 158.00 116.18
-
N-03 Painting new wood work with one coat of
wood primer m2 153.00 112.50
-
N-04 Painting new wood work with one coat of
wood primer and two coats of Enamal paint m2 358.00 263.24
-
N-05 Painting steel work with one coat of
Anticorrosive and and two coats of enamal
paint including scaling and wire brushing. of
Enamal paint m2 426.00 313.24
-
N-06a Painting Internal walls with one primer coat &
two coats of Emulsion paint m2 372.00 273.53
-
N-06b Painting Internal walls with one primer coat &
two coats of Enamel paint ( For hospital
wards) m2 413.00 303.68
-
N-07 Varnishing with one coat of sanding sealer
and two coats of varnish (Rate included for
sand papering) m2 460.00 338.24
-
N-08 Prepare and apply one coat of CIC putty, one
coat of primer and two coats of emulsion to
soffit of slabs (including sand papering and
preparing surface) m2 366.00 269.12
-
N-09 Painting External walls with one primer coat
and two coats of weathershield paint. m2 491.00 361.03
file:///conversion/tmp/scratch/363037749.xls
Rates Applicable for works in Trincomalee August 2005

Basic rate
Rate No Description Unit with material
Amount Rs. Cts.
-
N-10 Painting floors with one coat of floor paint
including preparing surface. m2 220.00 161.76
-
N-11 Painting floors with two coat of floor paint
including preparing surface. m2 266.00 195.59
-
N-12 Painting roof covering with two coats
weathershield paint. m2 437.00 321.32
-
N-13 Floor polishing and waxing after washing,
cleaning and preparing surface (Polisher
provided) m2 215.00 158.09
-
-
P - Water Supply & Sewerage -
-
P-01 Laying 20mm(type1000) PVC pipe including
trenching, back filling and making good to
walls m 133.00 97.79
-
P-02 Laying 25mm(type1000) PVC pipe including
trenching, back filling and making good to
walls m 212.00 155.88
-
P-03 Laying 32mm ( type1000)PVC pipe including
trenching, back filling and making good to
walls m 287.00 211.03
-
P-04 Laying 40mm ( type1000) PVC pipe including
trenching, back filling and making good to
walls m 413.00 303.68
-
P-05 Laying 50mm (type1000) PVC pipe including
trenching, back filling and making good to
walls m 494.62 363.69
-
P-06 Laying 63mm ( type1000) PVC pipe
including trenching, back filling and making
good to walls m 789.00 580.15
-
P-07 Laying 75mm ( type 1000) PVC pipe
including trenching, back filling and making
good to walls m 1,418.00 1,042.65
-
P-08 Laying 110mm PVC type 400 pipe including
trenching, back filling and making good to
walls m 1,040.00 764.71
-
P-09 Laying 160mm PVC type 400 pipe including
trenching, back filling and making good to
walls m 2,747.00 2,019.85
-
P-10 Laying 160mm PVC type 600 pipe including
trenching, back filling and making good to
walls m 3,922.00 2,883.82
-
P-11 Supplying and Fixing of wash basin with tap No. 19,869.00 14,609.56
-
P-12 Supplying & Fixing of Low Level Suit with
cistern No. 38,735.00 28,481.62
-
P-13 Supplying and Fixing of Squatting Pan with
high level cistern No. 11,825.00 8,694.85
file:///conversion/tmp/scratch/363037749.xls
Rates Applicable for works in Trincomalee August 2005

Basic rate
Rate No Description Unit with material
Amount Rs. Cts.
-
P-14 Supplying and Fixing of bidet shower No. 2,076.00 1,526.47
-
P-15 Supplying and Fixing of high level cistern No. 2,591.00 1,905.15
-
P-16 Supplying and Fixing of stainless steel sink
with tap No. 11,084.00 8,150.00
-
P-17 Supplying and Fixing of 1/2" pillar cocks to
basin No. 5,109.00 3,756.62
-
P-18 Supplying and Fixing of copper shower rose No. 6,883.00 5,061.03
-
P-19 Supplying and Fixing of urinals No. 19,317.00 14,203.68
-
P-20 Supplying and Fixing of gate valve / stop
cock ( 1/2") No. 1,041.00 765.44
-
P-21 Supplying and Fixing of gate valve / stop
cock ( 1") No. 2,089.00 1,536.03
-
P-22 Supplying and Fixing of gate valve / stop
cock ( 11/4") No. 2,788.00 2,050.00
-
P-23 Supplying and Fixing of gate valve / stop
cock ( 2") No. 3,042.00 2,236.76
-
P-24 Supplying and Fixing of soap tray No. 2,299.00 1,690.44
-
P-25 Supplying and Fixing of bath room mirror No. 2,946.00 2,166.18
-
P-26 Supplying and Fixing of bib tap No. 2,807.00 2,063.97
-
P-27 Construction of 600 x600 mm manhole up to
600mm deep No. 9,761.00 7,177.21
-
P-28 Construction of 1000 x 700 mm manhole
600mm to 1200mm deep No. 16,450.00 12,095.59
-
P-29 Construction of 1000 x 700 mm manhole
1200mm to 1800mm deep No. 14,717.00 10,821.32
-

file:///conversion/tmp/scratch/363037749.xls
Category Unit New rates
with VAT
Mark up 27%

Labours
Skilled Labour Hour 125.00
Semiskilled Labour 1 Hour -
Semiskilled Labour 2 Hour 112.50
Unskilled Labour Hour 100.00
Basket Item 60.00

Cement Bag 795.00


Sand m3
1,590.11
Fine Sand m3 1,590.11
20mm metal m3
3,886.93
25mm metal m3 3,621.91
40mm metal m3
3,003.53
50mm metal m3 - not changed
100mm metal m3
-
Rubble m3 1,590.11
Chips m3
1,943.46
Gravel - type1 m3 759.72
Gravel - type2 m3
424.03
Earth m3 441.70
Quarry Dust m3
1,484.10
ABC m3 2,826.86
Ready mix concrete excluding pumping m3
6,625.00
Ready mix concrete excluding pumping m3 12,000.00
Ready mix concrete including pumping m3
13,500.00

Timber
Class III, 25mm timber planks m2 325.00
Class II, 25mm timber planks m2 480.00
Class II, timber beams m3
32,000.00
Class I, timber beams m3 105,000.00
50 x 50mm reepers (Kempas) m 180.00
Plywood sheets m2 939.82 2,795.00
Plywood sheets - 6mm thick m2 420.31 1,250.00
Lunumidella 150x20mm m2 280.00
Timber planks Class I , 10" m 400.00
Ginisapu planks m 445.00
Wooden plugs m 15.00
Timber Planks(Mango) Class II , 1"x12" m2 325.00
50x50mm class1 (Kempas) m 132.00
Steel / Iron Monger
Mild Steel M/Ton 118,000.00
H/Y steel M/Ton 120,000.00
225mm x 10mm bolts & nuts kg 75.00
Binding wire kg 145.00
Wire nails kg 140.00
Mould oil Litre 65.00
Acro jacks Nos 1,820.00
Mild Steel flat kg 26.00
63 x 10mm bolt & nut Nos. 5.50
45 x 6mm bolts & nuts Nos. 1.50
20x40mm bolt 7 nuts Nos. 95.00
16x40mm bolt & nuts Nos. 55.00
12x40mm bolt & nuts Nos. 13.00
2"x2" ,3mm dia 12x7 G.I mesh ( 12'x7' per sheet m2 211.61 1,652.00
2"x2" ,3.15mm BRC mesh ( 12'x7' per sheet-135 m2 173.91 1,356.52
4"x4" ,6mm BRC mesh ( 12'x7' per sheet-2404.3 m2 462.18 3,605.00
6"x6", 5.0mm BRC mesh ( 12'x7' per sheet-1234 m2 237.18 1,850.00
6"x6", 6.0mm BRC mesh ( 12'x7' per sheet-1608 m2 310.26 2,420.00
8"x8", 5.0mm BRC mesh ( 12'x7' per sheet-910.4 m2 175.00 1,365.00
8"x8", 6.0mm BRC mesh ( 12'x7' per sheet-1239 m2 275.64 2,150.00
2"x2" GI welded mesh(12'x7') m2 211.79 1,652.00
Size 3.15,4.0,5.0 & 5.6mm wire nail(gauge 5,6, Kg. 54.20
Size 2.5mm wire nail (gauge 12) Kg. 56.95
Size 2.0 & 2.24mm wire nail (gauge 13&14) Kg. 57.60
Size 1.6 & 1.4mm wire nail (gauge 16&17) Kg. 71.78
Size 0.9 & 1.0mm wire nail (gauge 19&20) Kg. 82.19
Spring washers with flat washers Nos. 6.50
12x125 Rag bolts Nos. 165.00
12x200 ancher bolt Nos. 150.00
Size 2.5mm wire nail(gauge 12)
200x100x25kg/m UB (12m) m 1,811.67 21,740.00
175x100x20kg/m UB (6m) m 1,521.67 9,130.00
125x75x14kg/m UB (12m) m 2,173.33 26,080.00
350x175x50kg/m UB (6m) m 4,333.33 26,000.00
200x100x25kg/m UB (6m) m 2,533.33 15,200.00
125x50x2mm thick lipped channel (6m) m 366.67 2,200.00
75x75x6mm angle iron (5.8m) m 568.97 3,300.00
65x65x6mm angle iron (5.8m) m 431.03 2,500.00
50x50x6mm angle iron (5.8m) m 327.59 1,900.00
40x40x6 angle iron (5.8m) m 254.31 1,475.00
25x25x6 angle iron (5.8m) m 172.41 1,000.00
6mm thick MS plate(8'x4') m2 3,513.47 10,435.00
8mm thick MS plate m2 4,685.19 13,915.00
10mm thick MS plate m 2
5,855.89 17,392.00
12mm thick MS plate m2 702.69 2,087.00
15mm thick MS plate m 2
8,783.50 26,087.00
19mm thick MS plate m2 1,171.38 3,479.00
25mm thick MS plate m 2
16,103.37 47,827.00

Bricks, Blocks & Tiles


Bricks 1000 Nos 7,500.00
200mm cement Blocks Nos 70.00 with out transport
150mm cement Blocks -hollow Nos 55.00 Conmix
100mm cement Blocks Nos 37.00 Conmix
Pressed ct. tiles 200 x 200 Nos. 20.00
Terrazo floor tiles 300x300 Nos. 65.00
Ceramic floor tiles 300x300 Nos. 160.00
Glazed wall tiles 200x300 Nos. 80.00 70.00
semi gloss tile 300x300 Nos. 140.00
slate tile 300 x300mm Nos. 170.00
Rock finish tile 300x600mm Nos. 400.00
Non skid porcelain tile /m2 ( 250.00/ft2) Nos. 2,690.00
Glazed wall tiles 300x300 Nos. 80.00
Interlocking paving blocks 220x80mm Nos 29.00
Non skid tile 200x200 Nos 65.00
Terra cotta-200x200mm Nos 30.00
Granite slabs -20mm thick , 300x300mm Nos 950.00 (675 - 1150) per ft2
Granite tile -10mm thick , 600x300mm Nos 425.00 (350 - 425) per ft2
porcelain floor tiles 400x400 Nos. 280.00
Paint
Acrilic filler ( 10 Lit - 28kg) kg 124.18 3,477.00
Base compound kg 54.46 1,525.00
Thinner lits 214.00 856.00
Enamel paint Litrs 712.50 2,850.00
Aluminium wood primer Litrs 655.75 2,623.00
Anticorrosive paint Litrs 496.25 1,985.00
Lime putty Litrs. 35.00
Emulsion paint ( Master Palette) Litrs 490.80
Emulsion paint Litrs 571.50 2,286.00
Varnish Litrs 785.25 3,141.00
Weathershield paint ( Master palette ) Litrs 702.00
Weathershield paint Litrs 796.50 3,186.00
Floor paint Litrs 880.75 3,523.00
Floor polish Kg. 425.00
Oil Paint Litres 650.00
DPC Tar Litrs 125.00
Colour pigment for cement Kg. 475.00
80/100 bitumen Lit. 35.00
Feb mix Litres 180.00
Joint compound kg 58.93 1,650.00
Skim coat kg 34.00 850.00
sand papers No 15.00

Roofing materials
Sheets
Asbestos sheet m2 694.44 1,750.00
Zink Alum - tile effect .47mm thick m2 2,055.00
Zink Alum m2 1,169.23 1,520.00
Zink Alum curved roofing sheets m2 1,375.00 1,650.00
Tile calicut pattern Nos. 50.00
Zinc Alum flashing( 470mm girth) m 363.00
Zinc Alum facia board m 554.00
Zinc Alum facia board - 600mm wide m 600.00
Zinc Alum ridge cap m 554.00
Zinc Alum valley gutter m 554.00
Ridge tile calicut pattern Nos. 63.00
Half round tiles Nos. 30.00
GI sheet 18 BWG (Plain) m2 425.00
Gauge 24 GI sheets m2 400.00
Asbestos ceiling sheets m2 229.17 330.00

Roof plumbing
Drive screw & washers Nos. 10.00
Wood preservative Litres 146.25 585.00
Slaked Lime Kg. 10.00
Coal tar Litre 20.00
50mm iron screws Gauge 10 Nos. 2.00
PVC square gutters m 264.00
Gutter end cap Nos. 110.00
Mitre joint PVC 114mm Nos. 372.00
Gutter joiner Nos. 112.00
Gutter bracket Nos. 60.00
Running head square Nos. 131.00
Solvent cement 50 gms 264.00
Zinc Alum gutters m 575.00
Zinc Alum gutters - girth 900mm m 1,224.00
Zinc Alum gutter head Nos 785.40
Zinc Alum down pipes-100x100 m 541.00
Zinc Alum end cap Nos 160.00
Zn/Al gutter bracket Nos 115.00
Zn/Al down pipe clip Nos 22.00
Brass screws, gauge 6 Doz. 14.00
89mm dia. Down pipes m 184.43
Down pipe elbow Nos. 164.00
Down pipe joiner Nos. 138.00
Down pipe clips Nos. 29.00
Timber beadings m 30.00
Cove mouldings m 48.00
Wood plug No 6.00
Nozzle No 235.00
uPVC pipes

20mm dia. PVC pipes ( 1000) m 45.09 50.50


25mm dia. PVC pipes ( 1000) m 113.39 127.00
32mm dia. PVC pipes ( 1000) m 178.13 199.50
40mm dia. PVC pipes ( 1000) m 240.63 269.50
50mm dia. PVC pipes ( 1000) m 332.14 372.00
63mm dia. PVC pipes ( 1000) m 562.95 630.50
75mm dia. PVC pipes ( 1000) m 1,016.07 1,138.00
90mm dia. PVC pipes ( 1000) m 1,141.96 1,279.00
110mm dia. PVC pipes ( 1000) m 1,691.96 1,895.00
160mm dia. PVC pipes ( 1000) m

32mm dia. PVC pipes ( 600) m 80.80 90.50


40mm dia. PVC pipes ( 600) m 186.16 208.50
50mm dia. PVC pipes (600) m 233.93 262.00
63mm dia. PVC pipes ( 600) m 381.25 427.00
75mm dia. PVC pipes ( 600) m 708.04 793.00
90mm dia. PVC pipes ( 600) m 719.64 806.00
110mm dia. PVC pipes ( 600) m 1,167.86 1,308.00
160mm dia. PVC pipes ( 600) m 2,393.75 2,681.00

63mm dia. PVC pipes ( 400) m 225.00 378.50


75mm dia. PVC pipes ( 400) m 378.00 550.00
90mm dia. PVC pipes ( 400) m 565.00 610.50
110mm dia. PVC pipes ( 400) m 590.00 718.00
160mm dia. PVC pipes ( 400) m 1,730.00 2,011.00

Nitch latch door lock ( single) No. 1,100.00


Nitch latch door lock ( double) No. 1,250.00
Hinge butt brass 125mm x 100mm Nos. 160.00
Screws - brass 40mm x Gauge 8 Doz. 42.00
Screws - brass 50mm x Gauge 8 Doz. 48.00
Hold fasts Nos. 25.00
Bolt skelton Nos. 100.00
Bolt barrel Nos. 85.00
Sanitory fittings
American Std Rocel - Urban D
Wash basin with pedestal No. 11,500.00 7,400.00
Wash basin pedestal No.
Plugs Nos. 25.00
Low level suit Nos. 16,500.00 16,850.00
20mm brass stop cock Nos. 375.00
Fittings for cistern Nos. 400.00
Cistern bracket Pair 55.00
Low level cistern Nos. 7,020.00
Squatting pan Nos. 6,821.00
Cistern with fittings(high level) Nos.
Biddet shower - Italy Nos. 1,395.00
Shower rose, Nos. 2,650.00
Clout nails Kg. 135.00
Stainless steel sink with tap - prince Nos. 4,250.00
Elbow operated tap Nos. 2,750.00
Pillar cock Nos. 2,295.00
Urinals Nos. 3,835.00
Gate valve/stop cock ( 1/2" dia- Peglar) Nos. 750.00
Angle valve ( 1/2" dia- Peglar) Nos. 510.00
Gate valve/stop cock ( 1" dia -- English) Nos. 1,400.00
Gate valve/stop cock ( 11/4" dia -- English) Nos. 1,950.00
Gate valve/stop cock ( 3/4" dia -- peglar) Nos. 1,100.00
Gate valve/stop cock ( 2" dia -- English) Nos. 2,150.00
Bottle trap - Plastic Nos. 630.00

Soap tray Nos. 1,665.00


Bath room mirror Nos. 2,100.00
Bib tap ( 1/2" dia - pegler) Nos. 370.00
Piller tap-wash basin tap ( 1/2" dia - pegler) Nos. 560.00
High level cistern Nos. 1,100.00

Machine Rates

8 -10 ton vibrating roller hrs 2,000.00


Tractor with trailor hrs 500.00
Motor grader hrs 2,800.00
Water bowzer hrs 560.00
Concrete Mixer hrs 500.00

Precast Items

300mm dia hume pipes - 2440mm long Nos 4,750.00


450mm dia hume pipes - 2440mm long Nos 5,850.00
600mm dia hume pipes - 2440mm long Nos 6,750.00
900mm dia hume pipes - 2440mm long Nos 12,750.00
1200mm dia hume pipes - 2440mm long Nos 18,750.00
Pre cast kerbs ( 1000 mm long) m 650.00
450x450mm slabs ( RCC) m2 1,728.40 350.00

Collers
Collers - 300mm dia Nos 560.00
Collers - 450mm dia Nos 800.00
Collers - 600mm dia Nos 900.00
Collers - 900mm dia Nos 1,260.00
Collers - 1200mm dia Nos 1,200.00

Barbed wire m 9.66 2650.00 per 25kg(900ft)


Chainlink 1.2x15m roll ( gauge 10) m 2
320.00 5760.00 per 15m roll
Chainlink 1.2x15m roll ( gauge 08) m2 620.00 11,160.00
Line wire m 16.67 250.00 per 1kg
Water proofing Material

Barralastic ( 36kg) kg 220.00 7,920.00


Glascote m2 230.00

Xypex kg 458.27 12,465.00


Thoroseal kg 128.00 3,200.00

Ceiling

Wall angle m 59.06 180.00


Cross "T" m 69.72 85.00
Main "T" m 86.95 265.00
Superflex ceiling sheets m2 190.97 275.00
Concrete nails No 2.00
Rivert TAPD 625 No 2.00
Adjustable hooks No 80.00
Mineral fibre achostic tile ceiling m2 715.00 265.00

Insulation sheets
50mm thick glass fibre insulation sheets m2 214.44 3,860.00
25mm thick glass fibre insulation sheets
( density 32 kg/m3) m3 297.22 5,350.00
75x75mm galvernized mesh ( gauge 18) m2 109.63 5,920.00
8mm sisilation sheets ( single) m2 321.74 370.00
8mm sisilation sheets ( double) m2 363.48 418.00
1mm sisilation sheets ( single) m2 59.13 68.00
1mm sisilation sheets ( double) m2 95.65 110.00
10mm sisilation sheets ( single) m2 400.87 461.00
10mm sisilation sheets ( double) m2 426.96 491.00
25mm glass wool m2 136.25 3,270.00
Double side Alum foil m3 90.00 6,750.00
Day /Cube

1,000.00

900.00
800.00

764+3%
4,500.00
4,500.00
11,000.00
10,250.00
8,500.00
ot changed

4,500.00
5,500.00
2,150.00
1,200.00
1,250.00
4,200.00
8,000.00
664.2512077
1400
15,000.00 Inclusive of NBT

A 142
h out transport

39,264.00

5 - 1150) per ft2


0 - 425) per ft2
10 lit OCT. 2013
28 kg

4 LIT
28kg
25kg 150ft2 per 25 Kg.

discount
968.00 3.66m

675.00
discounted price

37.57 Oct-13
94.49
148.44
200.52
276.79
469.12
846.73
951.64
1,409.97

67.34
155.13
194.94
317.71
590.03
599.70
973.21
1,994.79
cel - Urban D
per 450 x450 slab

0.00 per 25kg(900ft)


0.00 per 15m roll

.00 per 1kg


26 kg powder
10 kg liquid

27.2kg
25kg

Actual
12ft 150
4 ft 65
12 ft 180
4' x 4'

2' x2'

1.2x15m roll
1.8x30m roll
with VAT
with VAT
with VAT
with VAT
with VAT
with VAT
with VAT
with VAT
Removal of timber from roof and timber, stacking servicible material & clearing away.

Per square

Skilled labour day hour 0.90 125.00 112.50


Unskill labour (04 labour 1/4 day hour 0.90 100.00 90.00
Allow for scaffolding 25.00
Sub Total 227.50
Add P & O H 81.90
Rate per square 309.40
Rate per m2 33.30

Rate per No m2 20.00

Removing valance barge boarding stacking material and debris cleared away.

Per Lm

Unskilled labour day hour 0.20 100.00 20.00


Allow for scaffolding 10.00
Sub Total 30.00
Add P & O H 10.80
Rate per lm 40.80

Rate per No m 30.00

Demolishing of renered floor and debris cleared away.

Per m2

Unskill labour (04 labour 1/4 day hour 0.50 100.00 50.00
Allow for scaffolding 25.00
Sub Total 75.00
Add P & O H 27.00
Rate per m2 102.00

Rate per No m2 70.00

Removing of doors including sashes from existing wall and stacked.

Per No

Unskill labour (04 labour 1/4 day hour 12.00 100.00 1,200.00
Sub Total 1,200.00
Add P & O H 432.00
Rate per No 1,632.00

Rate per No 820.00


Removing of glass panes in window and stacked.

Per m2

Skilled labour day hour 2.00 125.00 250.00


Sub Total 250.00
Add P & O H 90.00
Rate per m2 340.00

Rate per No m2 170.00

Demolishing of drains including pavement and debris cleared away from site.

Per lm

Unskilled labour day hour 6.00 100.00 600.00


Sub Total 600.00
Add P & O H 216.00
Rate per lm 816.00

Rate per No m 410.00

Demolishing of 100mm hight skirting and debris cleared away.

Per lm

Unskilled labour day hour 0.03 100.00 3.00


Sub Total 3.00
Add P & O H 1.08
Rate per lm 4.08

Rate per No m 5.00


Removing top soil - 150mm depth

Per 10 Square

Unskilled labour day 10 800.00 8,000.00


Sub Total 8,000.00
Add P & O H 2,160.00
Rate per m 10,160.00

Rate per m2 109.36

Excavation for foundation in Hard / dense soil

Per Cube

Unskilled labour day 3 1/2 800.00 2,800.00


Sub Total 2,800.00
Add P & O H 756.00
Rate per m 3,556.00

Rate per m3 1,256.54

Excavation for foundation in any material except rock requiring blasting

Per Cube

Unskilled labour day 1 5/8 800.00 1,300.00


Basket No 0.10 60.00 6.00
Sub Total 1,306.00
Add P & O H 352.62
Rate per m 1,658.62

Rate per m3 586.08

Excavation in levelling site any material except rock requiring blasting

Per Cube

Unskilled labour day 1 800.00 800.00


Transport 80.00
Basket No 0.10 60.00 6.00
Sub Total 886.00
Add P & O H 239.22
Rate per m 1,125.22
Rate per m3 397.60

Earth Work Support ( Open Planking)

(Consider 15' long 3' wide 5' depth open planking to both sides)

Per 150 ft2

Materials
17.5 cu.ft class 11 timber ( 4 uses) cu.ft 17.5 905.60 15,848.00
Add 5% on above for wedges 792.40

Labour
Carpenter day 1 1,000.00 1,000.00
Unskill Labour day 3 800.00 2,400.00
Sub Total 20,040.40
Add P & O H 5,410.91
Rate per 150 ft2 25,451.31

Rate per m2 1,825.71

Earth Work Support ( close Planking) in deep excavation

(Consider 15' long width 5.5' at top & 3.5 at bottom up to 15' depth)

Per 450 ft2

Materials
Class 11 timber ( 4 uses) cu.ft 100 905.60 90,560.00
Add 5% on above for wedges 4,528.00

Labour
Carpenter day 8 1,000.00 8,000.00
Unskill Labour day 20 800.00 16,000.00
Sub Total 119,088.00
Add P & O H 32,153.76
Rate per 150 ft2 151,241.76

Rate per m2 3,616.36


Back- filling & compaction with available earth

Per Cube

Unskilled labour day 1 800.00 800.00


Sub Total 800.00
Add P & O H 216.00
Rate per m 1,016.00

Rate per m3 359.01

Filling under floors with approved quality quarry dust including spreading,
watering and compacting in 150mm layers.

Rate per m3

Unskilled labour Hour 5.00 100.00 500.00


Quarry dust ( including transport) m3 1.10 1,484.10 1,632.51
Basket No 0.10 60.00 6.00
Allow for transport
Sub Total 2,138.51
Add P & O H 577.40
Rate per m 2,715.91

Rate per m3 Rs.2430.00

Filling under floors with approved quality quarry gravel including spreading,
watering and compacting in 150mm layers.
Rate per m3

Unskilled labour Hour 5.00 100.00 500.00


Gravel m3 1.10 759.72 835.69
Basket No 0.10 60.00 6.00
Sub Total 1,341.69
Add P & O H 362.26
Rate per m 1,703.95

Rate per m3 Rs. 800.00

ABC spreading, levelling & compacting for roads

Data for 19.82 m3


Spreading
Labour ( s/sk) hrs 44.00 - -
Blinding
Labour ( s/sk) hrs 4.00 - -
Allow 2.5% on labour for tools -

Graded aggregate 37.5mm m3 19.82 2,826.86 56,028.27


Roller charges ( 8-10 tons) vibrating hrs 8.00 2,000.00 16,000.00
Tractor & trailor hrs 2.00 500.00 1,000.00
Hire of water bouzer hrs 2.00 560.00 1,120.00
Spreading with motor grader 34.69
Sub Total 74,182.95
Add P & O H 20,029.40
Rate per m 94,212.35
4,753.40

Rate per 1 m3 ( loose volume) 4,753.40


For compacted volume 42% ( 100% compaction) 6,749.83
For compacted volume 35% ( 95% compaction) 6,417.09

Supplying & fixing Precast kerbs ( 125mm wide & 900mm long)

Data per 27m length

Materials
Excavation m3 0.50 461.48 230.74
For pre cast kerbs m 27.00 650.00 17,550.00
Cement for jointing 50 kg 0.50 795.00 397.50
Allow for transport 100.00

Labour cost
Skilled labour day 1.50 1,000.00 1,500.00
Un skilled labour day 6.00 800.00 4,800.00
Allow 2.5% for labour for tools 157.50

Sub Total 24,735.74


Add P & O H 6,678.65
Rate per 27 m 31,414.39

1,163.50
Rate per m 1,100.00

Supplying & laying 450x450x50mm pre cast concrete slabs om foot walks including average
40mm thick 1:3 cement sand mortar bedding

( a)
Data for 10 m2
( cost for mixing 6m3 of cement sand mortar)
Supplying 450x450mm slabs m2 10.00 1,728.40 17,283.95
Sand for mortar bedding m3 7.64 1,590.11 12,148.41
Cement for mortar bedding 50 kg 58.77 795.00 46,722.15
Water for mixing 150.00
Concrete mixer ( 400 lit) @ 50% efficient day 1.00 500.00 500.00

Labour cost
Skilled labour day 1.00 1,000.00 1,000.00
Un skilled labour day 6.00 800.00 4,800.00
Allow 2.5% for labour for tools 145.00

Cost for mixing 6 m3 82,749.51


Cost per 0.4 m3 ( 10m2 x 0.04m)

( b)
Allow cement for grout joints 50 kg 0.25 795.00 198.75

( c)
Labour for levelling base , placing & grouting
Skilled labour day 1.00 1,000.00 1,000.00
Un skilled labour day 4.00 800.00 3,200.00
Allow 2.5% for labour for tools 105.00
Cost for 10 m2

Total Cost ( a + b + c)
Add P & O H
Rate per 10 m2

Cost per 1 m2

Interlocking paving blocks - 220x110x80mm


Rate per m2

Labour cost including sand bedding 495.00


Paving blocks Nos 42.00 29.00 1,218.00
Transport, wastages 30.00
Sub Total 1,743.00
Add 36% P & O H 470.61
Rate per m2 2,213.61
Labour cost 46.00 per sq.ft ( including quarry dust)

GABION BOXES

Supplying & fixing gabion boxes

PVC coated gabion boxes - 1x1x1m 4,900.00


80x100mm metal m3 1 - -
-
Labour cost for packing metal/m3 1 800.00 800.00
Head transport of metal/m3 1 700.00 700.00 4,900.00
Transport 10 % material cost 490.00
Sub Total 6,890.00
Add ...% P & O H 1,860.30
Rate per m3 8,750.30

Rate per m3

PVC coated gabion boxes - 2x1x0.5m 5,965.00


80x100mm metal m3 1 - -

Labour cost for packing metal/m3 1 750.00 750.00


Head transport of metal/m3 1 700.00 700.00 5,965.00
Transport 10 % material cost 800.00
Sub Total 8,215.00
Add 30% P & O H 2,218.05
Rate per m3 10,433.05

Rate per m3 10,433.05

PVC coated gabion boxes - 3x1x0.5m 9,850.00


80x100mm metal m 3
1.5 - -

Labour cost for packing metal/m3 1.5 750.00 1,125.00


Head transport of metal/m3 1.5 700.00 1,050.00
Transport 10 % material cost 985.00
Sub Total 13,010.00
Add 30% P & O H 3,512.70
Rate per m3 16,522.70

Rate per m3 11,015.13


PVC coated gabion boxes - 3x1.5x1.0m 18,950.00
80x100mm metal m3 4.5 - -

Labour cost for packing metal/m3 4.5 750.00 3,375.00


Head transport of metal/m3 4.5 700.00 3,150.00
Transport 10 % material cost 1,895.00
Sub Total 27,370.00
Add 30% P & O H 7,389.90
Rate per m3 34,759.90

Rate per m3 7,724.42

PVC coated gabion boxes - 1x0.5x.5m 2,200.00


80x100mm metal m3
0.5 - -

Labour cost for packing metal/m3 0.5 750.00 375.00


Head transport of metal/m3 0.5 700.00 350.00
Transport 10 % material cost 220.00
Sub Total 3,145.00
Add 30% P & O H 849.15
Rate per m3 3,994.15

Rate per m3 7,988.30

PVC coated gabion metresses- 6x2x.23m 21,840.00


80x100mm metal m3
2.8 - -

Labour cost for packing metal/m3 2.8 800.00 2,240.00


Head transport of metal/m3 2.8 700.00 1,960.00
Transport 10 % material cost 218.40
Sub Total 26,258.40
Add ..% P & O H 7,089.77
Rate per m3 33,348.17

Rate per m2 2,779.01

Geotextile m2 4 180.00 720.00 per lm

Labour cost for laying hr 100.00


Removing unsuitable earth hr 2 81.25 162.50
Sub Total 982.50 245.63
Add 36% P & O H 265.28
Rate per m2 1,247.78

Rate per m2 311.94

Supplying & laying 300mm dia hume pipes

Data for 7.32m ( up to 1.8m depth)

Labour cost
Mason ( skill) hr 6 125.00 750.00
Labour ( s/sk) hr 6 100.00 600.00
Labour ( u/sk) hr 12 100.00 1,200.00
Allow 2.5% for labour for tools

Concrete pipes(2440mm long) Nos 3 4,000.00 12,000.00


Concrete pipe collars Nos 2 533.00 1,066.00
Allow for cement sand and water Joints 2 60.00 120.00

Transport ( 1 - 8 km transport)
Data for 14.64 m ( 6 pipes of 2.44m each)
Hire of vehicles ( 6 pipes per load)
6 pipes- assume 2.1 m3 m3 2.1 175.00 367.50
Idle time as above ( T1-015) u/sk day 0.055 800.00 44.00

Loading / unloading
Data for one 2.44m long pipe
Labour unskill ( 6 x 10 minutes)
Rate for 300mm dia 2.44 m long day 0.125 800.00 100.00
(1 No pipe)
Sub Total 16,247.50 19,821.95
Add 27% P & O H 4,386.83
Rate per m2 20,634.33 2,707.92

Rate per m 2,818.90

Supplying & laying 450mm dia hume pipes

Data for 7.32m ( up to 1.8m depth)

Labour cost
Mason ( skill) hr 6 125.00 750.00
Labour ( s/sk) hr 6 - -
Labour ( u/sk) hr 12 100.00 1,200.00
Allow 2.5% for labour for tools
Concrete pipes(2440mm long) Nos 3 5,850.00 17,550.00
Concrete pipe collars Nos 2 800.00 1,600.00
Allow for cement sand and water Joints 2 60.00 120.00

Transport ( 1 - 8 km transport)
Data for 14.64 m ( 6 pipes of 2.44m each)
Hire of vehicles ( 6 pipes per load)
6 pipes- assume 2.1 m3 m3 2.1 175.00 367.50
Idle time as above ( T1-015) u/sk day 0.055 800.00 44.00

Loading / unloading
Data for one 2.44m long pipe
Labour unskill ( 10 x 10 minutes)
Rate for 450mm dia 2.44 m long day 0.208 800.00 166.40
(1 No pipe)
Sub Total 21,797.90
Add 36% P & O H 7,847.24
Rate per m2 29,645.14

Rate per m 4,049.88

Supplying & laying 600mm dia hume pipes HSR - ST1-070

Data for 7.32m ( up to 1.8m depth)

Labour cost
Mason ( skill) hr 6 125.00 750.00
Labour ( s/sk) hr 6 - -
Labour ( u/sk) hr 12 100.00 1,200.00
Allow 2.5% for labour for tools

Concrete pipes(2440mm long) Nos 3 6,750.00 20,250.00


Concrete pipe collars Nos 2 900.00 1,800.00
Allow for cement sand and water Joints 2 60.00 120.00

Transport ( 1 - 8 km transport)
Data for 14.64 m ( 6 pipes of 2.44m each)
Hire of vehicles ( 6 pipes per load)
6 pipes- assume 2.1 m3 m3 2.1 175.00 367.50
Idle time as above ( T1-015) u/sk day 0.055 800.00 44.00

Loading / unloading
Data for one 2.44m long pipe
Labour unskill ( 10 x 10 minutes)
Rate for 450mm dia 2.44 m long day 0.208 800.00 166.40
(1 No pipe)
Sub Total 24,697.90
Add 36% P & O H 8,891.24
Rate per m2 33,589.14

Rate per m 4,588.68

Supplying & laying 900mm dia hume pipes HSR - ST1-071

Data for 7.32m ( up to 1.8m depth)

Labour cost
Mason ( skill) hr 6 125.00 750.00
Labour ( s/sk) hr 6 75.00 450.00
Labour ( u/sk) hr 12 100.00 1,200.00
Allow 2.5% for labour for tools

Concrete pipes(2440mm long) Nos 3 17,000.00 51,000.00


Concrete pipe collars Nos 2 900.00 1,800.00
Allow for cement sand and water Joints 2 60.00 120.00

Transport ( 1 - 8 km transport)
Data for 14.64 m ( 6 pipes of 2.44m each)
Hire of vehicles ( 6 pipes per load)
6 pipes- assume 2.1 m3 m3 2.1 175.00 367.50
Idle time as above ( T1-015) u/sk day 0.055 800.00 44.00

Loading / unloading
Data for one 2.44m long pipe
Labour unskill ( 10 x 10 minutes)
Rate for 450mm dia 2.44 m long day 0.208 800.00 166.40
(1 No pipe)
Sub Total 55,897.90
Add 20% P & O H 15,092.43
Rate per m2 70,990.33

Rate per m 9,698.13

Supplying & laying 1200mm dia hume pipes HSR - ST1-071

Data for 7.32m ( up to 1.8m depth)

Labour cost
Mason ( skill) hr 6 125.00 750.00
Labour ( s/sk) hr 6 75.00 450.00
Labour ( u/sk) hr 12 100.00 1,200.00
Allow 2.5% for labour for tools

Concrete pipes(2440mm long) Nos 3 18,750.00 56,250.00


Concrete pipe collars Nos 2 1,200.00 2,400.00
Allow for cement sand and water Joints 2 60.00 120.00

Transport ( 1 - 8 km transport)
Data for 14.64 m ( 6 pipes of 2.44m each)
Hire of vehicles ( 6 pipes per load)
6 pipes- assume 2.1 m3 m3 2.1 175.00 367.50
Idle time as above ( T1-015) u/sk day 0.055 800.00 44.00

Loading / unloading
Data for one 2.44m long pipe
Labour unskill ( 10 x 10 minutes)
Rate for 450mm dia 2.44 m long day 0.208 800.00 166.40
(1 No pipe)
Sub Total 61,747.90
Add 27% P & O H 16,671.93
Rate per m2 78,419.83

Rate per m 10,713.09

21,426.18
As per actual
Item 2.4
Supplying, spreading & compaction of borrowed approved soil Type II filling materi
(Compacted volume)
Supplying of material m3 1.00 777.39
at site (
gravel type II) @
Piling
1950.00available
per cubesoil m3 1.00 59.45
including transport &
Loading
Spreading, Watering and Compacting (210 Cu.m)

Rate per loose volume- m3


Rate per compacted volume ( * 1.35)
Add OH & P 20%
Rate per 1 Cu.m

Proposed rate/m3
Reference

ICTAD BSR

ICTAD BSR

ICTAD BSR

461.48

700

ICTAD BSR
ICTAD BSR

ICTAD BSR
ICTAD BSR
282.69

HSR - M1-012
HSR
ST1 -102
HSR
ST1 -104

5,516.63

198.75

4,305.00

10,020.38
2,705.50
12,725.89

1,272.59
-

800.00
700.00

1,500.00
-
1,500.00
716.80 (width -4m)
HSR - ST1-068

HSR(T1-022)

Tractor and trailor with driver and fuel


0.07day x 2500.00
175.00

HSR(T1-038)

HSR - ST1-069
R - ST1-070
R - ST1-071

R - ST1-071
proved soil Type II filling material.

777.39 Quotation attached

59.45 E1-021

221.00 EW -003A

1,057.84
1,428.08
285.62
1,713.69

1,700.00
CONCRETOR

C - 01
1:3:6 (25mm) concrete ( 50mm thick)
at Ground Level
Per m2

Skilled labour Hour 0.80 125.00 100.00


Unskilled labour Hour 1.13 100.00 113.00 213.00
Cement Bag 0.24 795.00 186.83
Sand m3 0.03 1,590.11 47.70
25mm metal m3 0.05 3,621.91 181.10
Basket Item 0.02 60.00 0.99
Allow for water, curing, Hire of mixer etc. 20.00
Add 25% of materials for wastage due to small quantities
Transporting cement Bag 0.24 10.00 2.35
Sub Total 651.96 847.55
Add 36% P & O H 176.03
Rate per m2 827.99

C - 02
1:3:6 (25mm) concrete ( 75mm thick)
at Ground Level
Per m2

Skilled labour Hour 0.80 125.00 100.00 100.00


Unskilled labour Hour 1.80 100.00 180.00 280.00
Cement Bag 0.35 795.00 280.24
Sand m3 0.05 1,590.11 71.55
25mm metal m3 0.08 3,621.91 271.64
Basket Item 0.02 60.00 1.49
Allow for water, curing, hire of mixer etc. 30.00
Add 25% of materials for wastage due to small quantities
Transporting cement Bag 0.35 10.00
Sub Total 934.92
Add P & O H 252.43
Rate per m2 1,187.35 15,831.32
C - 03
1:3:6 (25mm) concrete
at Ground Level
Per m3

Skilled labour Hour 2.80 125.00 350.00 800.00


Unskilled labour Hour 22.60 100.00 2,260.00 2,610.00
Cement Bag 4.24 795.00 3,371.02
Sand m3 0.60 1,590.11 954.06
25mm metal m3 1.00 3,621.91 3,621.91
Polythene gauge 1000 m2 13.33 32.00 426.56
Basket Item 0.33 60.00 19.80
Allow for water, curing, hire of Mixer etc. 310.00
Sub Total 11,313.36
Add P & O H 3,054.61
Rate per m3 14,367.96 406.61

C - 04
1:2:4 (20mm) concrete ( volume up to 3 m3)
at Ground Level
Per m3

Skilled labour Hour 3.50 125.00 437.50 1,100.00


Unskilled labour Hour 28.25 100.00 2,825.00 3,262.50
Cement Bag 6.36 795.00 5,056.54
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing, hire of Mixer etc. 500.00
Sub Total 13,679.83
Add P & O H 3,693.55
Rate per m3 17,373.38 491.67

100mm thick 1:2:4 (25mm) concrete with 6"x 6" BRC mesh(6mm)
Per m2

Labour cost per m2 150.00


Cement Bag 0.63 795.00 500.85
Sand m3 0.06 1,590.11 95.41
25mm metal m3 0.10 3,621.91 362.19
Basket Item 0.33 60.00 19.80
6"x 6" BRC mesh (6mm) m2 1.00 310.26 310.26
Allow for water, curing, hire of Mixer etc. 40.00
Sub Total 1,478.50
Add P & O H 399.20
Rate per m3 1,877.70
C - 05 a
1:2:4 (20mm) concrete ( volume up to 3m3)
at 1st floor level
Per m3

Skilled labour Hour 3.50 125.00 437.50 1,100.00


Unskilled labour Hour 28.25 100.00 2,825.00 3,262.50
Add for a lift 93.50
Cement Bag 6.36 795.00 5,056.54
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing ,hire of Mixer etc. 500.00
Sub Total 13,773.33
Add P & O H 3,718.80
Rate per m3 17,492.12

C - 05 b
1:2:4 (20mm) concrete
at 2nd floor level
Per m3

Skilled labour Hour 3.50 125.00 437.50 1,100.00


Unskilled labour Hour 36.70 100.00 3,670.00 4,107.50
Add for a lift 187.00
Cement Bag 6.36 795.00 5,056.54
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing,hire of Mixer etc. 310.00
Sub Total 14,521.83
Add P & O H 3,920.89
Rate per m3 18,442.72
C - 06
1:2:4 (20mm) concrete for volume above 3 m3
Per m3

Skilled labour Hour 2.80 125.00 350.00 1,100.00


Unskilled labour Hour 22.60 100.00 2,260.00 2,610.00
Cement Bag 6.36 795.00 5,056.54
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing hire for mixture etc. 310.00
Transporting cement Bag 6.36 10.00 63.60
Sub Total 12,900.93
Add P & O H 3,483.25
Rate per m3 16,384.18

C - 07
1:2:4 (20mm) concrete in columns for volume above 3 m3
Per m3

Skilled labour Hour 2.80 125.00 350.00 1,100.00


Unskilled labour Hour 17.00 100.00 1,700.00 2,050.00
Cement Bag 6.36 795.00 5,056.54
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing hire for mixture etc. 310.00
Sub Total 12,277.33
Add P & O H 3,314.88
Rate per m3 15,592.20

C - 08
1:2:4 (20mm) concrete in slabs & beams for volume above 15 m3
Per m3

Skilled labour Hour 6.40 125.00 800.00 1,300.00


Unskilled labour Hour 28.50 100.00 2,850.00 3,650.00
Cement Bag 6.36 795.00 5,056.54
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,621.91 3,621.91
Basket Item 0.33 60.00 19.80
Allow for water, curing hire of mixture etc. 310.00
Sub Total 13,612.31
Add P & O H 3,675.32
Rate per m3 17,287.63
C - 08a
1:2:4 (20mm) concrete in slabs & beams for volume up to 15 m3
Per m3

Skilled labour Hour 6.40 125.00 800.00 1,300.00


Unskilled labour Hour 28.50 100.00 2,850.00 3,650.00
Cement Bag 6.36 795.00 5,056.54
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing hire of mixture etc. 310.00
Sub Total 13,877.33
Add P & O H 3,746.88
Rate per m3 17,624.20

1:11/2:3 (20mm) concrete ( used 22 bags per cube, high water table)
Per m3

Skilled labour Hour 3.50 125.00 1,000.00


Unskilled labour Hour 22.60 100.00 2,500.00 2,500.00
Cement Bag 8.12 795.00 6,455.40
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing hire of mixture etc. 400.00
Sub Total 14,216.19
Add P & O H 3,838.37
Rate per m3 18,054.56 510.94

125mm thick 1:1 1/2:3 (20mm) concrete with 6"x 6" BRC mesh(6mm)

Per m2

Labour cost per m2 250.00


Cement Bag 1.02 795.00 806.93
Sand m3 0.06 1,590.11 95.41
25mm metal m3 0.13 3,621.91 452.74
Basket Item 0.33 75.00 24.75
6"x 6" BRC mesh (6mm) m2 1.00 310.26 310.26
Allow for water, curing, hire of Mixer etc. 40.00
Sub Total 1,980.08
Add P & O H 534.62
Rate per m3 2,514.70
C - 09
1:2:4 (20mm) concrete in 150 x 112mm lintols (including reinforcement)
Per m

Skilled labour Hour 1.70 125.00 300.00 130.00


Unskilled labour Hour 2.00 100.00 300.00
Cement Bag 0.10 795.00 79.50
Sand m3 0.01 1,590.11 15.90
20mm metal m3 0.02 3,886.93 77.74
Reinforcement kg 0.00180 120,000.00 216.00
Class III 25mm timber planks m2 0.30 325.00 97.50
Allow for timber props & nails, Hire of Mixer etc 25.00
Sub Total 811.64
Add P & O H 219.14
Rate per m 1,030.78

C - 10
1:2:4 (20mm) concrete in 225mm x 150mm lintols (including reinforcement)
Per m

Skilled labour Hour 1.70 125.00 400.00 130.00


Unskilled labour Hour 1.70 100.00 400.00
Cement Bag 0.20 795.00 159.00
Sand m3 0.02 2,650.00 53.00
20mm metal m3 0.03 3,886.93 116.61
Class III 25mm timber planks m2 0.30 325.00 97.50
Reinforcement kg 0.00120 120,000.00 144.00
Allow for timber props & nails, hire of Mixer etc 50.00
Transporting Cement Bag 0.20 10.00 2.00
Sub Total 1,022.11
Add P & O H 275.97
Rate per m 1,298.08
C - 11
1:2:4 (20mm) concrete in 225mm x 225mm lintols ( including reinforcement)
Per m

Skilled labour Hour 1.60 125.00 140.00


Unskilled labour Hour 1.60 100.00 400.00 400.00
Cement Bag 0.30 795.00 238.50
Sand m3 0.03 1,590.11 47.70
20mm metal m3 0.05 3,886.93 194.35
Reinforcement kg 0.00360 120,000.00 432.00
Class III 25mm timber planks m2 0.45 325.00 146.25
Allow for timber props & nails, hire of Mixer etc 60.00
Sub Total 1,518.80
Add P & O H 410.08
Rate per m 1,928.88

C - 12
1:2:4 (20mm) concrete in 300mm x 225mm lintols ( excluding reinforcement)
Per m

Skilled labour Hour 1.70 125.00 600.00 180.00


Unskilled labour Hour 2.60 100.00 600.00
Cement Bag 0.40 795.00 318.00
Sand m3 0.04 1,590.11 63.60
20mm metal m3 0.07 3,886.93 272.08
Reinforcement kg 0.00360 120,000.00 432.00
Class III 25mm timber planks m2 0.60 325.00 195.00
Allow for timber props & nails, hore of Mixer etc 75.00
Sub Total 1,955.69
Add P & O H 528.04
Rate per m 2,483.73

C - 13
1:2:4 (20mm) ready mixed concrete , placing manually, levelling & vibrating
Per m3

Labour cost per m3 550.00


Ready mix concrete m3 1.00 759.72 759.72
Allow for water, curing etc. 50.00
Sub Total 1,359.72
Add P & O H 367.12
Rate per m 1,726.84

C20 Sierra
C - 14
1:2:4 (20mm) ready mixed concrete pumping, levelling & vibrating
Per m3

Labour cost per m3 300.00


Ready mix concrete-C25 m3
1.00 13,500.00 13,500.00
Pumping of concrete m3 1.00 800.00 800.00
Allow for water, curing etc. 250.00
Sub Total 14,850.00 16,780.50
Add P & O H 4,009.50
Rate per m3 18,859.50

C25 Sierra

C25 ready mixed concrete pumping, levelling & vibrating


Per m3

Labour cost per m3 300.00


Ready mix concrete-C25 m3 1.00 14,500.00 14,500.00
Pumping of concrete m3 1.00 800.00 800.00
Allow for water, curing etc. ( 40 .00 per m2 @ 6m2) 250.00
Sub Total 15,850.00 17,910.50
Add P & O H 4,279.50
Rate per m3 20,129.50

Sun Power
C25 ready mixed concrete pumping, levelling & vibrating with BRC mesh
Per m3

Labour cost per m3 250.00


Ready mix concrete-C25 m3 1.00 15,575.00 15,575.00
Pumping of concrete m3 1.00 800.00
Allow for water, curing etc. ( 40 .00 per m2 @ 6m2) 250.00
BRC mesh 6.00 310.00 1,860.00
Sub Total 17,935.00 20,266.55
Add P & O H 2,690.25
Rate per m3 20,625.25

C20 Concrete in Slab & beams ( Ready Mix Concrete)


( 1230 ft2)
Slab Concrete m3 12.80 11,400.00 145,920.00
Beam Concrete m3 4.00 12,200.00 48,800.00 194,720.00

Labour Cost
R/F kg 1,200.00 11.00 13,200.00
Shuttering m2 170.00 300.00 51,000.00 64,200.00

Total Cost for the slab 258,920.00

210.50
C20 Concrete in Slab & beams ( Manual Mix Concrete)

Cement 50 bags 108.00 700.00 75,600.00


3/4" Cube 6.00 6,300.00 37,800.00
Sand Cube 3.50 5,500.00 19,250.00 132,650.00

Labour Cost ( including r/f and f/w)


Slab ft2 1,230.00 90.00 110,700.00
Beams ft 615.00 90.00 55,350.00 166,050.00

Total Cost for the slab 298,700.00

242.85

C30

1:1:2 (20mm) concrete ( used 31 bags per cube, high water table)
Per m3

Skilled labour Hour 3.50 125.00 1,000.00


Unskilled labour Hour 22.60 100.00 2,500.00 2,500.00
Cement Bag 11.00 795.00 8,745.00
Sand m3 0.60 1,590.11 954.06
20mm metal m3 1.00 3,886.93 3,886.93
Basket Item 0.33 60.00 19.80
Allow for water, curing hire of mixture etc. 400.00
Sub Total 16,505.79
Add P & O H 4,456.56
Rate per m3 20,962.35 593.23
17,000.00
1922.055
300.00
C20 Sun Power
C - 14
1:2:4 (20mm) ready mixed concrete pumping, levelling & vibrating
Per m3

Labour cost per m3 300.00


Ready mix m3 1.00 14,675.00 14,675.00
Pumping of m3 1.00 800.00 800.00
Allow for water, curing etc. 250.00
Sub Total 16,025.00 18,108.25
Add P & O H 4,326.75
Rate per m3 20,351.75

C25 Sun Power

C25 ready mixed concrete pumping, levelling & vibrating


Per m3

Labour cost per m3 250.00


Ready mix m3 1.00 15,575.00 15,575.00
Pumping of m 3
1.00 800.00 800.00
Allow for water, curing etc. ( 40 .00 per m2 @ 6m2) 250.00
Sub Total 16,875.00 19,068.75
Add P & O H 4,556.25
Rate per m3 21,431.25

Sun power

C25 ready mixed concrete pumping, levelling & vibrating


Per m3

Labour cost per m3 800.00 For columns, lintols etc


Ready mix m3 1.00 15,575.00 15,575.00
Pumping of m 3
1.00 800.00
Allow for water, curing etc. ( 40 .00 per m2 @ 6m2) 250.00
Sub Total 16,625.00
Add P & O H 2,493.75
Rate per m3 19,118.75
D - FORMWORK

D - 01
Formwork for columns using plywood sheets
Per m2

Skilled labour Hour 0.80 125.00


Unskilled labour Hour 2.30 100.00
Plywood sheets (03 times) m2 0.37 939.82
Class II, timber beams m3 0.00 32,000.00
225mm x 10mm bolts & nuts Kg. 0.60 75.00
Props 13ft long - acro jacks No. 0.08 1,820.00
Allow for screws, nails etc.
Sub Total
Add P & O H
Rate per m2
Jacks are used 12 times per year & for thee years

D - 02
Formwork for slabs using plywood sheets
Per m2

Skilled labour Hour 1.00 125.00


Unskilled labour Hour 2.60 100.00
Plywood sheets m2 0.37 939.82
Class II, timber beams ( 4"x2" joists) m3 0.00 32,000.00
Props 13ft long - acro jacks No. 0.03 1,820.00
Mould oil Litre 1.20 65.00
Wire nails Kg 0.20 140.00
Allow for transport of jacks & plywood ( 350 Nos jacks transport per trip)
Sub Total
Add P & O H
Rate per m2

Jacks is used 6 times per year & for thee years


D -03
Formwork for beams sides , soffits using plywood sheets
Per m2

Skilled labour Hour 1.50 125.00


Unskilled labour Hour 1.50 100.00
Plywood sheets m2 0.37 939.82
2" x 2" timber class 11 m 1.77 132.00
Props 13ft long - acro jacks No. 0.03 1,820.00
Mould oil Litre 0.30 65.00
Wire nails Kg 0.40 140.00
Allow for transport of jacks & plywood ( 350 Nos jacks transport per trip)
Sub Total
Add & P & O H
Rate per m2

D-05
Formwork for beams using timber planks

Skilled labour Hour 1.10 125.00


Unskilled labour Hour 1.10 100.00
Timber plank 25mm class iii m2 1.10 325.00
Props 13ft long - acro jacks No. 0.09 1,820.00
Bolt & nut iron 225x10mm kg 0.40 75.00
Sub Total
Add P & O H
Rate per m2

Formwork for walls in Ice storage using 6mm plywood sheets ( permanent work)
Per m2

Skilled labour Hour 0.80 125.00


Unskilled labour Hour 2.30 100.00
Plywood sheets m2 1.00 420.31
Class II, timber beams m3 0.00 32,000.00
40mm x 10mm bolts & nuts kg 0.60 75.00
Props 13ft long - acro jacks No. 0.08 1,820.00
Allow for screws, nails etc.
Sub Total
Add P & O H
Rate per m2
Jacks is used 12 times per year & for thee years
Formwork for guard wall using plywood sheets ( ht ~ 13.0m)
Per m2

Skilled labour Hour 0.80 125.00


Unskilled labour Hour 2.30 100.00
Plywood sheets m2 0.35 939.82
Class II, timber beams m3 0.00 32,000.00
225mm x 10mm bolts & nuts Kg. 0.60 75.00
Props 13ft long - acro jacks No. 0.08 1,820.00
Scaffolding - 32x20.00/9

Allow for screws, nails etc.


Sub Total
Add P & O H
Rate per m2
Jacks is used 12 times per year & for thee years
Up to DPC

Formwork for columns using plywood sheets


Per m2

100.00 120.00 Skilled labour Hour 0.800 125.00


230.00 330.00 Unskilled labour Hour 2.300 100.00
344.60 Plywood sheets- 3 times used m2 0.367 939.82
96.00 Class III, timber beams m3 0.003 16,000.00
45.00 225mm x 10mm bolts & nuts Kg. 0.600 75.00
151.67 Props 13ft long - acro jacks No. 0.083 1,820.00
25.00 Allow for screws, nails etc.
992.27 Sub Total
267.91 Add P & O H
1,260.18 Rate per m2

1,165.00

125.00 140.00
260.00 385.00
344.60
96.00
50.60
78.00
28.00
38.00
1,020.20
275.45
1,295.65
187.50 120.00
150.00 337.50
344.60
233.20
54.60
19.50
56.00
38.00
1,083.40
292.52
1,375.92

137.50 120.00
110.00 247.50
357.50
163.80
30.00
798.80
215.68
1,014.48

100.00 120.00
230.00 330.00
420.31
96.00
45.00

5.00
896.31
242.00
1,138.32
100.00 120.00
230.00 330.00
328.94
96.00
45.00
151.67
71.11

25.00
1,047.71
282.88
1,330.60

1,000.00
350.00
344.60
48.00
45.00
151.67
25.00
964.27
135.00
1,099.26

700.00
Fence

Barbed wire , 12 1/2 gauge, 4 ponts , 3" apart


Per m

For 30m

Skilled labour Hour 1.00 125.00 125.00


Unskilled labour Hour 1.00 100.00 100.00 225.00
Barbed wire m 30.00 9.35 280.47
Allow for staples & other accessories 25.00
Sub Total 530.47
Add P & O H 116.70
Rate per 30m 647.18

Rate per m 21.57

Rate for 14 strands 302.02

Say 260.00

Construction & errection of concrete fence posts 2500mm height ( corner , Intermediate)
Per No:

Casting of Post including labour


Gr 25 (20) concrete m3 0.06 18,054.56 1,119.38
Form work - 6 times used - 2.04/6 m2 0.35 1,260.18 441.06
Reinforcement kg 10.00 227.90 2,279.02
Allow for staples & other accessories 25.00
Sub Total 3,864.46

Errection of posts

Labour cost for errection 250.00


Back filling with earth m 3
0.03 466.00 14.91
Gr 15( 25) concrete m3 0.12 11,557.27 1,363.76
1,628.67
Sub Total 5,493.13

Rate per fence post 4,100.00


Construction and errection of of concrete fence posts 2500mm height ( struts)
Per No:

Casting of Post including labour


Gr 25 (20) concrete m3 0.06 12,382.88 681.06
Form work - 3 times used - 2.04/3 m2 0.75 840.01 630.00
Reinforcement kg 8.80 114.32 1,005.99
Allow for staples & other accessories 25.00
Sub Total 2,342.05

Errection of posts

Labour cost for errection 250.00


Back filling with earth m 3
0.03 466.00 14.91
Gr 15( 25) concrete m3 0.08 11,557.27 866.80 1,131.71
Sub Total 3,473.76

Rate per fence post 3,500.00

Supplying & fixing Chainlink mesh ( gauge 10) to the fence


Rate Per 36 m2 ( 30mx1.2m)

Labour cost
Skilled labour Hour 8.00 125.00 1,000.00
Unskilled labour Hour 8.00 100.00 800.00 1,800.00

Material Cost
Chainlink mesh m2 36.00 320.00 11,520.00
Line wires m 90.00 16.67 1,500.00 13,020.00
Sub Total 14,820.00
Rate per m2 411.67
Add 36% OH & P 148.20
Total 559.87

Supplying & fixing Chainlink mesh ( gauge 8) to the fence


Rate Per 36 m2 ( 30mx1.2m)

Labour cost
Skilled labour Hour 8.00 125.00 1,000.00
Unskilled labour Hour 8.00 100.00 800.00 1,800.00

Material Cost
Chainlink mesh m2 36.00 620.00 22,320.00
Line wires m 90.00 16.67 1,500.00 23,820.00
Sub Total 25,620.00
Rate per m2 711.67
Add 36% OH & P 256.20
Total 967.87

Water Proofing

Waterproofing concrete surfaces with two coats of BARRALASTIC ( Concrete & Mortar surfaces)

For 7.35 m2

Chipping & cleaning the existing concrete

Unskill labour hrs 8.00 100.00 800.00 108.84

Applying Barralastic two coats

Barralastic 2.5kg/m2 for 7.35m2 kg 18.38 220.00 4,042.50


Skill labour day 1.00 1,000.00 1,000.00
Unskill labour day 1.00 800.00 800.00 1,800.00
244.90
Applying filler coat
Glascote 230.00 per m2 m2 1.60 230.00 368.00
Skill labour day 0.50 1,000.00 500.00
Unskill labour day 0.50 800.00 400.00 400.00
54.42

Protective screed with 12mm thick 1:3 cement and sand mortar

Skill labour hrs 0.65 125.00 81.25


Unskill labour hrs 1.30 100.00 130.00
Cement Bags 0.12 795.00 91.43
Sand m3 0.02 1,590.11 23.85
Allow for water etc. 5.00

Sub Total 8,242.03


Add 36% P & O H 2,225.35
Rate per m2 10,467.37

1,424.13
Say 1,450.00

Waterproofing concrete surfaces with two coats of XYPEX ( Only for Concrete surfaces)

For 7.35 m2

Chipping & cleaning the existing concrete

Unskill labour hrs 8.00 100.00 800.00 108.84

Applying Xypex two coats

Xypex 1.6kg/m2 for 7.35m2 kg 11.76 458.27 5,389.28


Skill labour day 1.00 1,000.00 1,000.00
Unskill labour day 1.00 800.00 800.00 1,800.00
244.90
Protective screed with 20mm thick 1:3 cement and sand mortar

Skill labour hrs 0.87 125.00 108.13


Unskill labour hrs 1.73 100.00 173.00
Cement Bags 0.19 795.00 149.46
Sand m3 0.02 1,590.11 34.98
Allow for water etc. 5.00

Sub Total 8,459.85


Add 36% P & O H 2,284.16
Rate per m2 10,744.01

Rate / m2 1,461.77

Say 1,470.00

Waterproofing concrete surfaces with two coats of Thoroseal

For 7.35 m2

Chipping & cleaning the existing concrete

Unskill labour hrs 8.00 100.00 800.00 108.84

Applying Thoroseal two coats

Thoroseal 2.5kg/m2 for 7.35m2 kg 18.38 128.00 2,352.00


Skill labour day 1.00 1,000.00 1,000.00
Unskill labour day 1.00 800.00 800.00 1,800.00
244.90
Protective screed with 20mm thick 1:3 cement and sand mortar
Skill labour hrs 0.87 125.00 108.13
Unskill labour hrs 1.73 100.00 173.00
Cement Bags 0.19 795.00 149.46
Sand m3 0.02 1,590.11 34.98
Allow for water etc. 5.00

Sub Total 5,422.57


Add 36% P & O H 1,464.09
Rate per m2 6,886.66

Rate / m2 936.96

Say 800.00

Construction of chainlink fence (1.5m height) fixied to 50mm dia 3.2mm thick galvernized iron pipes
@2.4m spacing. G.I pipe will be fixed to concrete pads which will be doweled to rock with T16
reinforcement bars

For Buddhangala Temple

Data for 214.0m length ( 2.4m height)

1:2:4(20) concrete m3 2.50 13,679.83 34,199.57


Form work m2 32.40 992.27 32,149.45
Reinforcement kg 171.00 179.45 30,685.95
RRM foundation m3 50.00 9,651.35 482,567.33

Chainlink fence with Line wires ( gauge 10) m2 514.00 755.00 388,070.00
50mm dia( 3.2mm thick) G.I posts Nos 90.00 2,760.00 248,400.00

Sub Total 1,216,072.29


Add 36% P & O H 243,214.46
Rate per m2 1,459,286.75

6,819.10

Total cost for fence

For chainlink fence m 214.00 6,819.10 1,459,286.75


5,503,716.68
Antitermite pre- construction soil treatment
Per 10m2

Labour cost m2 10.00 25.00 250.00

Material cost

Chemicals ( biflex) 1% , for 10m2 chemicals Lit 0.15 3,000.00 450.00


150ml
Fuel Item Allow 60.00
Allow for transport and other Item Allow 200.00
Sub Total 960.00
Add 36% P & O H 345.60
Rate per 10 m2 1,305.60

Rate per m2 130.56

Antitermite pre- construction soil treatment

Per 10m2

Labour cost m2 10.00 25.00 250.00

Material cost

Chemicals ( chlorofyrofos) 1% , for 10m2 Lit 0.15 1,700.00 255.00


chemicals 150ml
Fuel Item Allow 60.00
Allow for transport and other Item Allow 200.00
Sub Total 765.00
Add 36% P & O H 275.40
Rate per 10 m2 1,040.40
Rate per m2 104.04

Antitermite pre- construction soil treatment

Per 10m2

Labour cost
Skilled Labour Day 1.00 750.00 750.00
Unskilled Labour Day 1.00 500.00 500.00

Material cost

Chemicals ( Biflex) - Chemicals 1% with wat Lit 4.00 125.00 500.00


Hire of drill machine Item Allow 250.00
Hire of Sprayer Item Allow 300.00
Fuel Item Allow 60.00
Allow for wastage & safety kits Item Allow 100.00
Allow for transport and other Item Allow 200.00
Sub Total 2,660.00
Add 36% P & O H 957.60
Rate per 10 m2 3,617.60

Rate per m2 361.76


Antitermite pre- construction soil treatment

Item No ..
Per 10m2

Labour cost
Skilled Labour day 1.25 750.00 937.50
Unskilled Labour day 1.25 500.00 625.00

Material cost

Chemicals ( Biflex) - Chemicals 1% with wat Lit 4.00 350.00 1,400.00


Hire of Sprayer Item Allow 300.00
Fuel Item Allow 60.00
Allow for wastage & safety kits Item Allow 100.00
Allow for transport and other Item Allow 200.00
Sub Total 3,622.50
Add 25% P & O H 905.63
Rate per 10 m2 4,528.13

Rate per m2 452.81

Proposed Rate 450.00


7.50
According
E - REINFORCEMENT

E -01
Highyield Reinforcement for foundation ,beams,columns,slabs etc
Per kg

Skilled labour Hour 0.16 125.00


Unskilled labour Hour 0.16 100.00
Tor steel M/ton 0.0011 120,000.00
Binding wire kg 0.01 145.00
Allow for wastage & transport
Sub Total
Add P & O H
Rate per kg

E - 02
Mild Reinforcement for foundation ,beams,columns,slabs etc
Per kg

Skilled labour Hour 0.10 125.00


Unskilled labour Hour 0.10 100.00
Mild steel M/ton 0.0011 118,000.00
Binding wire Kg 0.01 145.00
Allow for wastage & transport
Sub Total
Add P & O H
Rate per kg

A 142 for chip concrete ( weight 2.22 kg per m2)


Per m2

Skilled labour Hour 0.16 125.00


Unskilled labour Hour 0.16 100.00
A142 m2 1.0000 275.64
Binding wire kg 0.01 145.00
Allow for wastage & transport
Sub Total
Add P & O H
Rate per kg
20.00 6.00
16.00 36.00
132.00
1.45
10.00
179.45 197.40
48.45
227.90

12.50 6.00
10.00 22.50
129.80
1.45
10.00
163.75
44.21
207.96

labour cost

36.00 26.64
275.64
1.45
5.00
318.09
85.88
403.98
G - R/R Masonry

G-01
Random rubble masonary in 1:5 cement mortar ( width greater than 400mm)
Per m3

Skilled labour Hour 8.480 125.00


Unskilled labour Hour 16.96 100.00
Rubble 150mm to 225mm Cum 1.30 1,590.11
Cement 50 kg 2.56 795.00
Sand Cum 0.45 1,590.11
Transporting Cement 50 kg 2.56 10.00
Sub Total
Add P & O H
Rate per m2
G-02
Random rubble masonary in 1:5 cement mortar ( width less than 400mm)
Per m3

Skilled labour Hour 10.600 125.00


Unskilled labour Hour 21.20 100.00
Rubble 150mm to 225mm Cum 1.30 1,590.11
Cement 50 kg 2.56 795.00
Sand Cum 0.45 1,590.11
Transporting Cement 50 kg 2.56 10.00
Sub Total
Add P & O H
Rate per m2

G-03
Pointing of rubble masonry wall surface
Per m2

Labour for pointing m2


Allow for tools, other materials etc.
Sub Total
Add P & O H
Rate per m2

Rubble Paving / Pitching

Data for 9.29 m2

Rubble m3 1.10 1,590.11


Labour ( S/Sk) day 2.00 800.00
Allow for 2.5% for labour for tools
Sub Total
Add P & O H
Rate per 9.29 m2

Rate per m2
1,060.00 600.00 Different norm
1,696.00 2,756.00
2,067.14
2,035.20
715.55
25.60
7,599.49 9,119.38
2,051.86
9,651.35 27,313.31 273.13

1,325.00 650.00
2,120.00 3,445.00 Different norm
2,067.14
2,035.20
715.55
25.60
8,288.49
2,237.89
10,526.38

100.00
100.00
27.00
127.00

1,749.12
1,600.00
40.00
3,389.12
915.06
4,304.18

463.31
H - Pavior

H - 01
75mm thick brick paved cement rendered floor including 12mm thick 1:3 cement rendering
Per m2

Skilled labour Hour 1.490 125.00


Unskilled labour Hour 2.97 100.00
Bricks 1000 Nos 0.04 7,500.00
Sand m3 0.03 1,590.11
Cement Bag 0.49 795.00
Sub Total
Add P & O H
Rate per m2

H - 02
Pressed cement tiles or terracotta
Per m2

Skilled labour Hour 3.400 125.00


Unskilled labour Hour 3.90 93.00
Pressed ct. tiles 200 x 200 Nos. 25.00 17.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 %for wastages in cutting, transport

Sub Total
Add P & O H
Rate per m2
H - 03
Terrazo floor tiles including 12mm thick 1:3 levelling screed
Per m2

Skilled labour Hour 2.600 125.00


Unskilled labour Hour 2.80 100.00
Terrazo floor tiles 300 x 300mm Nos. 12.00 65.00
Sand m3 0.01 1,590.11
Cement Bag 0.13 795.00
Allow for tile grout
Add 5 %for wastages in cutting, transport

Sub Total
Add P & O H
Rate per m2

H - 04
Ceramic floor tiles including 20mm thick 1:3 levelling screed
Per m2

Skilled labour Hour 5.600 125.00


Unskilled labour Hour 4.00 100.00
Ceramic floor tiles 300 x300 Nos. 11.00 125.00
Sand m3 0.03 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 % for wastages
Sub Total
Add P & O H
Rate per m2

H - 05
Matt finish floor tiles including 20mm thick 1:3 levelling screed -300x300mm
Per m2

Skilled labour Hour 5.600 125.00


Unskilled labour Hour 4.00 100.00
Ceramic floor tiles 300 x300 Nos. 11.00 175.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 % for wastages
Sub Total
Add P & O H
Rate per m2

H - 06
Slate floor tiles including 20mm thick 1:3 levelling screed
Per m2

Skilled labour Hour 5.600 125.00


Unskilled labour Hour 4.00 100.00
Ceramic floor tiles 300 x300 Nos. 7.00 250.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 % for wastages
Sub Total
Add P & O H
Rate per m2
H - O7
Rock finish tiling including 20mm thick 1:3 levelling screed
Per m2

Skilled labour Hour 5.600 125.00


Unskilled labour Hour 4.00 100.00
Rock finish tile 300 x600 Nos. 6.00 400.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2

H - O8
Porcelain tiling including 20mm thick 1:3 levelling screed ( "Monalisa")
Per 1.44m2

Skilled labour Hour


Unskilled labour Hour
Porcelain finish tile 600 x600 Nos. 3.00 864.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2

H - 09
Glazed wall tiles including 20mm thick 1:3 raking plaster toilets 200x400mm
Per m2

Skilled labour Hour 2.580 125.00


Unskilled labour Hour 2.58 100.00
Glazed wall tiles 200x400 Nos. 13.00 200.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout etc.
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2
H -11
Glazed wall tiles including 20mm thick 1:3 raking plaster in wards
Per m2

Skilled labour Hour 2.580 125.00


Unskilled labour Hour 2.58 100.00
Glazed wall tiles 300x300 Nos. 11.00 135.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout etc.
Add 5 %for wastages

Sub Total
Add P & O H
Rate per m2

Ceremic floor tiling including 20mm thick 1:3 levelling screed 300x300mm
Per m2

Skilled labour Hour 3.400 125.00


Unskilled labour Hour 3.90 81.25
Ceremic tile 300 x300 Nos. 11.00 150.00
Sand m3 0.02 2,650.00
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2

H - 09
Tiling tiles including 20mm thick 1:3 raking plaster 600x600mm
Per m2

Skilled labour Hour 2.580 125.00


Unskilled labour Hour 2.58 100.00
Glazed wall tiles 600x600 Nos. 3.00 1,100.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout etc.
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2
Tiling tiles including 20mm thick 1:3 raking plaster 400x400mm
Per m2

Skilled labour Hour 2.580 125.00


Unskilled labour Hour 2.58 100.00
Glazed wall tiles 400x400 Nos. 7.00 350.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout etc.
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2

Ceremic floor tiling - 600x300mm tile

Per m2

Labour Cost ( Assume 35.00 per ft2) m2

Material cost
Ceremic tile 600 x300 including wastage Nos. 6.00 425.00
( 600x300mm tile price ~ 425.00)
Sand m3 0.02 2,650.00
Cement Bag 0.27 725.00
Allow for tile grout
Sub Total

Rate per ft2

Ceremic floor tiling - 400x400mm tile

Per m2

Labour Cost ( Assume 35.00 per ft2) m2

Material cost
Ceremic tile 400 x400 including wastage Nos. 7.00 240.00
( 400x400mm tile price ~ 240.00)
Sand m3 0.02 2,650.00
Cement Bag 0.27 725.00
Allow for tile grout
Sub Total
Rate per ft2

Ceremic floor tiling - 600x600mm tile


Per m2
Labour Cost ( Assume 35.00 per ft2) m2

Material cost
Ceremic tile 600 x600 including wastage Nos. 3.00 790.00
( 600x600mm tile price ~790.00)
Sand m3 0.02 2,650.00
Cement Bag 0.27 920.00
Allow for tile grout
Sub Total

Rate per ft2

Polished granite slab( 20mm ) paving with 1: 3 cement sand bedding

Per m2

Skilled labour Hour 3.000 125.00


Unskilled labour Hour 3.00 100.00

Granite slabs 300x300 Nos. 11.00 350.00


Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout etc.

Sub Total
Add P & O H
Rate per m2

Granite tile( 10mm ) paving with 1: 3 cement sand bedding

Per m2

Skilled labour Hour 4.000 125.00


Unskilled labour Hour 4.00 100.00

Granite tile 600x300 Nos. 6.00 425.00


Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout etc.
Allow for wastage - 5%
Sub Total
Add P & O H
Rate per m2

Granite tile( 20mm ) paving with 1: 3 cement sand bedding

Per m2

Skilled labour Hour 4.000 125.00


Unskilled labour Hour 4.00 100.00

Granite tile@1250.00 ft2 m2 1.00 13,450.00


Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout etc.
Allow for wastage - 5%
Sub Total
Add P & O H
Rate per m2

For vanity top 5.25 @ 16700.00

Ceremic floor tiling including 20mm thick 1:3 levelling screed


Per m2

Skilled labour Hour 3.400 125.00


Unskilled labour Hour 3.90 81.25
Ceremic tile 400 x400 Nos. 7.00 280.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2

Ceremic floor tiling including 20mm thick 1:3 levelling screed


Per m2

Skilled labour Hour 3.400 125.00


Unskilled labour Hour 3.90 81.25
Ceremic tile 200 x200 Nos. 25.00 65.00
Sand m3 0.02 1,590.11
Cement Bag 0.27 795.00
Allow for tile grout
Add 5 %for wastages
Sub Total
Add P & O H
Rate per m2
nt rendering

186.25 180.00
297.00 483.25
285.00
47.70
389.55 180.00
1,205.50
325.49
1,530.99

425.00 275.00
362.70 787.70
425.00
33.39
214.65
20.00
21.25

1,501.99
405.54
1,907.53

325.00 225.00
280.00 605.00
780.00
15.90
103.35
20.00
39.00
225.00
1,563.25
422.08
1,985.33
225.00
500.00 500.00
1,375.00
54.06 225.00
214.65
20.00
68.75
2,232.46
602.77
2,835.23

500.00 225.00
500.00
1,925.00
33.39
214.65
20.00
96.25
2,789.29
753.11
3,542.40 2,700.00

500.00 225.00
500.00
1,750.00
33.39
214.65
20.00
87.50
2,605.54
703.50
3,309.04
500.00 225.00
500.00
2,400.00
33.39
214.65
20.00
120.00
3,288.04
887.77
4,175.81

225.00
1,000.00 1,000.00
2,592.00
33.39
214.65
20.00
129.60
3,989.64
1,077.20
5,066.85
4,800.00

500.00 225.00
500.00
2,600.00 Prime cost
33.39
214.65
20.00
130.00
3,498.04
944.47
4,442.51 2,850.00
11.11111

400.00 225.00
400.00
1,485.00
33.39
214.65
20.00
74.25

2,227.29
601.37
2,828.66

500.00

1,650.00
55.65
214.65
20.00

2,440.30
658.88
3,099.18

500.00 225.00
500.00
3,300.00 Prime cost given
33.39
214.65
20.00
165.00
4,233.04
1,142.92
5,375.96
500.00 225.00
500.00
2,450.00 Prime cost given
33.39
214.65
20.00
122.50
3,340.54
901.95
4,242.49

375.00

2,550.00

55.65
195.75
20.00
3,196.40

297.06

375.00

1,680.00

55.65
195.75
20.00
2,326.40
216.21

400.00

2,370.00

55.65
248.40
20.00
3,094.05

287.55

375.00
300.00 675.00

3,850.00
33.39
214.65
50.00

4,823.04
1,302.22
6,125.26

500.00
400.00 900.00

2,550.00
33.39
214.65
50.00
127.50
3,875.54
1,046.40
4,921.94

500.00
400.00 900.00

13,450.00
33.39
214.65
50.00
672.50
15,320.54
4,136.55
19,457.09

87,675.00

500.00

1,960.00
33.39
214.65
20.00

2,728.04
736.57
3,464.61

500.00

1,625.00
33.39
214.65
20.00

2,393.04
646.12
3,039.16
BRICK LAYER

F -01
225mm brick work in 1:5 cement sand mortar
Per m3

Skilled labour Hour 8.50 125.00


Unskilled labour Hour 14.5 100.00
Brick 1000 Nos 0.58 7,500.00
sand Cum 0.22 1,590.11
cement 50 kg 1.30 795.00
Allow for water & scaffolding
Transporting cement 50 kg 1.30 10.00

Sub Total
Add P & O H
Rate per m3

Rate per m2

F-02
112mm brick work in 1:5 cement mortar
Per m2

Skilled labour Hour 1.61 125.00


Unskilled labour Hour 2.15 100.00
Brick 1000 Nos 0.06 7,500.00
sand Cum 0.02 1,590.11
cement 50 kg 0.14 795.00
Allow for water & scaffolding
Sub Total
Add P & O H
Rate per m2

F - 03
200mm thick block works in 1:5 cement mortar
Per m2

Skilled labour Hour 1.076 125.00


Unskilled labour Hour 1.72 100.00
Blocks Nos 13.00 70.00
sand Cum 0.01 1,590.11
cement 50 kg 0.15 795.00
Allow for water & scaffolding
Sub Total
Add P & O H
Rate per m2
F -04
150mm thick block work in 1:5 cement mortar
Per m2

Skilled labour Hour 0.860 125.00


Unskilled labour Hour 1.50 100.00
Blocks Nos 13.00 55.00
sand Cum 0.03 2,600.00
cement 50 kg 0.11 800.00
Allow for water & scaffolding
Sub Total
Add P & O H
Rate per m2
F - 05
100mm block work in 1:5 cement mortar
Per m2

Skilled labour Hour 0.800 125.00


Unskilled labour Hour 1.50 100.00
Blocks Nos 13.00 37.00
sand Cum 0.02 1,590.11
cement 50 kg 0.07 795.00
Allow for water & scaffolding
Sub Total
Add P & O H
Rate per m2

F-06
300mm wide 225mm to 400mm deep brick drains in 1:5 cement mortar complete with
12mm thick 1:2 cement rendering finished smooth.
Per m

Skilled labour Hour 3.280 125.00


Unskilled labour Hour 4.00 100.00
Bricks 1000 Nos 0.07 7,500.00
Cement 50 kg 0.33 795.00
Sand Cum 0.06 1,590.11
Sub Total
Add P & O H
Rate per m
F- 07
225mm wide 150mm to 225mm deep brick drains in 1:5 cement mortar complete with
12mm thick 1:2 cement rendering finished smooth
Per m

Skilled labour Hour 2.440 125.00


Unskilled labour Hour 3.05 100.00
Bricks 1000 Nos 0.06 7,500.00
Cement 50 kg 0.10 795.00
Sand Cum 0.01 145.00
Sub Total
Add P & O H
Rate per m
1,062.50 700.00
1,450.00 2,512.50
4,350.00
349.82
1,033.50
50.00
13.00
If the no of brick for cube 1650 nos
8,308.82
2,243.38
10,552.21

2,374.25 220.65

201.25 110.00
215.00 416.25
450.00
23.85
111.30
50.00
1,051.40
283.88
1,335.28 960.00 124.10

134.50 120.00
172.00 306.50
910.00
22.26 120
120.05
50.00
1,408.81
380.38
1,789.18
107.50 110.00
150.00 257.50
715.00
78.00
88.00
50.00
1,188.50
320.90
1,509.40

100.00 90.00
150.00 250.00
481.00
33.39
51.68
50.00
866.07
233.84
1,099.91

410.00 300.00
400.00 810.00
487.50
262.35
95.41 300.00
1,655.26
446.92
2,102.18
305.00 250.00
305.00 610.00
412.50
79.50
1.45
1,103.45
297.93
1,401.38
Supplying & fixing asbestos free cement fibre ceiling with aluminium " T " sections
(3mm thick superflex)
Per 5.76m2 ( 2.4m x2.4m)

Labour cost per m2


Skilled labour hrs 16.00 100.00 1,600.00
Unskilled labour hrs 16.00 75.00 1,200.00

Material Cost
Wall angles / m 6.00 59.06 354.35
Main T m 9.00 86.95 782.52
Cross T m 9.00 69.72 627.49
Superflex board ceiling sheet m2 6.40 6,000.00 38,400.00
Gauge 16 binding wire kg 1.00 145.00 145.00
Concrete nails Nos 32.00 2.00 64.00
Rivert TAPD 625 Nos 65.00 2.00 130.00
Emultion paint Lits 1.00 571.50 571.50
Adjustable hooks Nos 10.00 80.00 800.00
Allow for scaffolding & material transport 200.00
Sub Total 44,874.86
Add 36% P & O H 16,154.95
Rate per 5.76 m2 61,029.81
Rate per m2 10,595.45

Rate /m2 1,800.00


Supplying & fixing Mineral fibre achostic ceiling with aluminium " T " sections

Per 5.76m2 ( 2.4m x2.4m)

Labour cost per m2


Skilled labour hrs 16.00 100.00 1,600.00
Unskilled labour hrs 16.00 75.00 1,200.00

Material Cost
Wall angles m 6.00 59.06 354.35
Main T m 9.00 86.95 782.52
Cross T m 9.00 69.72 627.49
Mineral Fibre achostic ceiling m2 6.40 715.00 4,576.00
Gauge 16 binding wire kg 1.00 145.00 145.00
Concrete nails Nos 32.00 2.00 64.00
Rivert TAPD 625 Nos 65.00 2.00 130.00
Emultion paint Lits 1.00 571.50 571.50
Adjustable hooks Nos 10.00 80.00 800.00
Allow for scaffolding & material transport 200.00
Sub Total 11,050.86
Sub Total 11,050.86
Add 36% P & O H 3,978.31
Rate per 5.76 m2 15,029.17
Rate per m2 2,609.23

Rate /m2 2,600.00

Asbestos sloping ceiling underside of roof rafters for eave ( supported on steel trusses)

Per 93 m2

Labour Cost
Skilled labour day 20.00 1,000.00 20,000.00
Unskilled labour day 20.00 600.00 12,000.00

Material Cost

2"x2" Timber m 330.00 180.00 59,400.00


Asbestos ceiling sheets m2 93.00 347.00 32,271.00
Emultion paint lit 6.00 571.50 3,429.00
Beading & moulding m 275.00 12.00 3,300.00
Wire nails kg 7.00 140.00 980.00
Allow for scaffolding & transport 1,600.00
Wastage
Steel Truss for support the eave ceiling
( labour cost + Material cost) m 85.00 1,622.00
Sub Total 132,980.00
Add P & O H - 27% 35,904.60
Rate per m2 168,884.60

1,815.96
2,800.00 486.11

check qty

check qty & Price


2,800.00
1,429.89
J - Roof Work

J-01
Corrugated asbestos sheet roofing including timber frame work for single storied
Per m2

Skilled labour Hour 1.720 125.00 215.00


Unskilled labour Hour 1.10 100.00 110.00
Corrugated asbestos sheet m2 1.17 694.44 810.42
Timber beams Class 1 m3 0.01 ### 1,050.00
Drive Screws and washers Nos 3.00 10.00 30.00
Wood Preservative Lit 0.05 146.25 7.31
Sub Total 2,222.73
Add P & O H 600.14
Rate per m2 2,822.87

J-02
Corrugated asbestos sheet roofing including timber frame work for hip roof
Per m2

Skilled labour Hour 0.70 125.00 87.50


Unskilled labour Hour 0.48 100.00 48.00
Corrugated asbestos sheet m2 1.17 694.44 810.42
Timber beams Class 1 m3 0.02 95,000.00 1,425.00
Drive Screws and washers Nos 3.00 10.00 30.00
Wood Preservative Lit 0.06 146.25 8.04
Sub Total 2,408.96
Add P & O H 361.34
Rate per m2 2,770.30

800.00
Corrugated asbestos sheet roofing including timber frame work for hip roof
Per 90 m2

Labour Cost
Skilled labour day 15.00 1,000.00 15,000.00
Unskilled labour day 15.00 600.00 9,000.00

Material Cost
Corrugated asbestos sheet m2 105.30 694.44 73,125.00

Roof timber
7"x2" ridge plate m 8.20 675.00 5,535.00
6"x4" purlin m 16.80 1,325.00 22,260.00
4"x2" rafters m 115.50 470.00 54,285.00
2"x2" reepers m 105.60 65.00 6,864.00
4"x3" wall plates m 16.00 570.00 9,120.00
Drive Screws and washers Nos 270.00 10.00 2,700.00
Wood Preservative Lit 5.50 146.25 804.38
Sub Total 198,693.38
Add P & O H 53,647.21
Rate per m2 252,340.59
2,803.78

Polucarbonate sheet roofing including timber frame work for hip roof
Per 90 m2

Labour Cost
Skilled labour day 15.00 1,200.00 18,000.00
Unskilled labour day 15.00 800.00 12,000.00

Material Cost
Polycarbonate sheet m2 105.30 4,140.00 435,942.00

Roof timber
7"x2" ridge plate m 8.20 675.00 5,535.00
6"x4" purlin m 16.80 1,325.00 22,260.00
4"x2" rafters m 115.50 870.00 100,485.00
2"x2" reepers m 105.60 90.00 9,504.00
4"x3" wall plates m 16.00 960.00 15,360.00
Drive Screws and washers Nos 270.00 10.00 2,700.00
Wood Preservative Lit 5.50 146.25 804.38
Sub Total 622,590.38
Add P & O H 168,099.40
Rate per m2 790,689.78
8,785.44

Corrugated asbestos sheet roofing including timber frame work for hip roof ( with asbestos sloping sheets)
Per 110m2

Labour Cost
Skilled labour day 50.00 1,000.00 50,000.00
Unskilled labour day 50.00 600.00 30,000.00
Material Cost
Corrugated asbestos sheet m2 121.00 450.00 54,450.00
Ceiling Sheets m2 121.00 260.00 31,460.00
Insulation foil m2 110.00 500.00 55,000.00
Roof timber
7"x2" ridge plate m 12.00 675.00 8,100.00
6"x4" purlin m 8.00 1,400.00 11,200.00
4"x2" rafters m 196.00 550.00 107,800.00
2"x2" reepers m 120.00 150.00 18,000.00
4"x3" wall plates m 25.00 800.00 20,000.00
Drive Screws and washers Nos 250.00 10.00 2,500.00
Wood Preservative Lit 20.00 146.25 2,925.00
Sub Total 391,435.00
Add P & O H 105,687.45
Rate per m2 497,122.45

U/F roof - Area ~ 1600 ft2 150.000 533,775.00

Total Cost for the Roof 925,210.00

5,523.58

Calicut pattern tile roof on timber frame work


Per 93 m2
Labour Cost
Skilled labour day 20.00 1,000.00 20,000.00
Unskilled labour day 20.00 600.00 12,000.00

Material Cost
Calicut tile Nos 1,300.00 50.00 65,000.00
Ridge tile m 8.00 456.75 3,654.01

Roof timber
7"x2" ridge plate m 8.20 675.00 5,535.00
6"x4" purlin m 16.80 1,325.00 22,260.00
4"x2" rafters m 160.00 470.00 75,200.00
2"x1" reepers m 300.00 65.00 19,500.00
4"x3" wall plates m 16.00 570.00 9,120.00
Wire nails kg 7.00 140.00 980.00

Wood Preservative Lit 17.00 146.25 2,486.25

Insulation - 8mm m2 93.00 500.00 46,500.00


Asbestos sheets without timber frame work m2 93.00 350.00 32,550.00

Sub Total 314,785.26


Add P & O H 78,696.31
Rate per m2 393,481.57

4,230.98
Rate Analysis for Roof

Colourcon tile roof on timber/steel frame work


Per 51 m2

Labour Cost m2 51.00 950.000 48,450.00

Material Cost
Colourcon tile ( including 5% wastage) Nos 507.00 135.00 68,445.00
Ridge tile m 2.75 100.00 275.00
Ceiling m2 51.00 850.000 43,350.00

Roof timber
7"x2" ridge plate m 2.75 1,010.00 2,777.50
4"x2" rafters m 123.00 420.00 51,660.00
6"x4" purlins m 5.50 866.00 4,763.00
2"x1" reepers m 158.00 90.00 14,220.00
Wire nails kg 3.60 140.00 504.00

Wood Preservative Lit 12.00 146.25 1,755.00


Sub Total -1 236,199.50
Allow for transport 7,219.98
Sub Total -11 243,419.48
Add P & O H - 27% 34,078.73
Rate per m2 277,498.20

Rate per m2 on timber frame 5,441.14

Rate per m2 with steel trusses & timber frame 5,441.14


Zn /Al roof on timber frame work ( spacing of rafters 600mm)
Per 122 m2

Labour Cost
Skilled labour day 20.00 1,000.00 20,000.00
Unskilled labour day 20.00 600.00 12,000.00

Material Cost
Zn/Al roof m2 102.00 2,055.00 209,610.00
Zn/Al ridge m 7.20 554.00 3,988.80

Roof timber
6"x2" ridge plate m 7.50 675.00 5,062.50
6"x4" purlin m 15.00 1,325.00 19,875.00
5"x3" purlin m 13.00 1,025.00 13,325.00
4"x2" rafters m 120.00 460.00 55,200.00
2"x1" reepers m 440.00 65.00 28,600.00
4"x3" wall plates m 16.00 570.00 9,120.00
Wire nails kg 7.00 140.00 980.00

Wood Preservative Lit 17.00 146.25 2,486.25


Sub Total 380,247.55
Add P & O H 102,666.84
Rate per m2 482,914.39

5,192.63

Zn /Al roof on timber frame work ( spacing of rafters 600mm)


Per 93 m2

Labour Cost
Skilled labour day 20.00 1,000.00 20,000.00
Unskilled labour day 20.00 600.00 12,000.00

Material Cost
Zn/Al roof m2 102.00 2,055.00 209,610.00
Zn/Al ridge m 7.20 184.43 1,327.87
50mm glass wool m2 102.00 214.44 21,873.33
50x50 mesh m3 102.00 109.63 11,182.22
Roof timber
6"x2" ridge plate m 7.50 675.00 5,062.50
6"x4" purlin m 15.00 1,325.00 19,875.00
5"x3" purlin m 13.00 1,025.00 13,325.00
4"x2" rafters m 120.00 460.00 55,200.00
2"x1" reepers m 440.00 65.00 28,600.00
4"x3" wall plates m 16.00 570.00 9,120.00
Wire nails kg 7.00 140.00 980.00

Wood Preservative Lit 17.00 146.25 2,486.25


Sub Total 410,642.17
Add P & O H 110,873.39
Rate per m2 521,515.56

5,607.69
J- 03
Corrugated asbestos sheet roofing on existing frame work
Per m2

Skilled labour Hour 0.50 125.00 62.50


Unskilled labour Hour 0.70 100.00 70.00
Corrugated asbestos sheet m2 1.20 694.44 833.33
Drive Screws and washers Nos 2.00 10.00 20.00
Transport 20.00
Sub Total 1,005.83
Add P & O H 271.58
Rate per m2 1,277.41

J- 04
Calicut pattern ridging in 1:1:4 cement lime sand mortar coloured to match tiles
Per m

Skilled labour Hour 0.70 125.00 87.50


Unskilled labour Hour 0.70 100.00 70.00
Ridge tile calicut pattern Nos 3.00 63.00 189.00
Sand m3 0.01 1,590.11 15.90
Slaked lime Kg. 2.28 10.00 22.80
Cement Bags 0.09 795.00 71.55
Sub Total 456.75
Add P & O H 123.32
Rate per m 580.07

J- 05
Calicut pattern tile roof on timber frame work
Per m2

Skilled labour Hour 1.65 125.00 206.25


Unskilled labour Hour 1.65 100.00 165.00
Class I, timber beams m3 0.02 ### 2,100.00
25 x 50mm reepers m 3.61 180.00 649.80
Tile calicut pattern Nos. 14.00 50.00 700.00
Ridge tile calicut pattern Nos. 1.33 63.00 83.79
Binding wire Kg. 0.07 145.00 10.15
Wire nails Kg. 0.07 140.00 9.80
wood preservative Litres 0.18 146.25 26.33
Cement Bags 0.03 795.00 23.85
Lime Kg. 0.03 10.00 0.30
Sand m3 0.01 1,590.11 15.90
Insulation - 8mm m2 500.00
Asbestos sheets without timber frame work m2 500.00
Allow for colouring powder 10.00
Sub Total 5,001.17
Add P & O H 1,350.31
Rate per m 6,351.48

J- 06
Laying half round tiles on existing timber frame work
Per m2

Unskilled labour Hour 0.86 100.00 86.10


Half round tiles Nos. 64.00 30.00 1,920.00
Sub Total 2,006.10
Add P & O H 541.65
Rate per m 2,547.75

J- 07
Laying half round tiles on existing asbestose sheet roof
Per m2

Unskilled labour Hour 0.862 100.00 86.20


Half round tiles ( over asb) Nos. 38.00 30.00 1,140.00
Sub Total 1,140.00
Add P & O H 307.80
Rate per m 1,447.80

J- 08
900mm wide valley gutters including timber boarding
Per m

Skilled labour Hour 2.00 125.00 250.00


Unskilled labour Hour 3.50 100.00 350.00
GI sheet 24 BWG (Plain) m2 1.00 400.00 399.20
Class II, 25mm timber planks m2 1.00 445.00
Coal tar Litre 0.22 20.00 4.48
Cement Bags 0.03 795.00 21.47
Lime Kg. 0.80 10.00 8.00
Sand m3 0.00 1,590.11 6.36
Wire nail Kg. 0.07 140.00 9.38
Wood preservative Litres 0.34 146.25 48.99
Sub Total 1,097.88
Add P & O H 296.43
Rate per m 1,394.31
J - 09
Colour bond Zinc Aluminium roofing sheets on steel frame work
Per m2

Skilled labour Hour 0.500 125.00 120.00


Unskilled labour Hour 0.75 100.00
Zinc Alum roofing sheets m2 1.20 1,169.23 1,403.08
Drive Screws and washers Nos 2.00 10.00 20.00
Allow for transport 35.08
Sub Total 1,578.15
Add P & O H 426.10
Rate per m2 2,004.26

1,800.00

J-10
Colour bond Zinc Aluminium curved roofing sheets on steel frame work
Per m2
Skilled labour Hour 0.500 125.00 62.50
Unskilled labour Hour 0.75 100.00 75.00
Zinc Alum curved roofing sheets m2 1.20 1,375.00 1,650.00
Drive Screws and washers Nos 2.00 10.00 20.00
Allow for transport 41.25
Sub Total 1,848.75
Add 36% P & O H 499.16
Rate per m2 2,347.91

Supplying & fixing colour bond 0.47mm thick 600mm wide Zink Alum ridge cap

Per m

Labour cost per m


Skilled Labour hrs 1.00 125.00 125.00
Unskilled Labour hrs 0.70 100.00 70.00

Material Cost
Zn /Alum ridge cap m 1.10 554.00 609.40
Allow Screws 30.00
Sub Total 834.40
Add P & O H 225.29
Rate per m 1,059.69

Supplying & fixing colour bond 0.47mm thick Zn/Al valley gutter
Per m

Labour cost per m


Skilled Labour hrs 1.50 125.00
Unskilled Labour hrs 1.50 100.00 240.00

Material Cost
Zn /Alum valley gutter m 1.10 554.00 609.40
Fastners Nos 11.00 10.00 110.00
Allow for scaffolding, transport etc 40.00
Sub Total 999.40
Add 36% P & O H 269.84
Rate per m 1,269.24
1,100.00

Supplying & fixing 450mm wide 0.47mm thick Zn/Al facia board
Per m

Labour cost per m


Skilled Labour hrs 0.50 125.00 62.50
Unskilled Labour hrs 0.50 100.00 50.00

Material Cost
Zn/Alum valance board m 1.10 554.00 609.40
25x5mm flat iron m 1.40 56.00 78.40
Allow for anticorrosive paint 25.00
Sub Total 825.30
Add 36% Profit & O/H 222.83
Rate per m 1,048.13

Supplying & fixing 600mm wide 0.47mm thick Zn/Al facia board
Per m

Labour cost per m


Skilled Labour hrs 0.50 125.00 62.50
Unskilled Labour hrs 0.50 100.00 50.00

Material Cost
Zn/Alum valance board m 1.10 600.00 660.00
25x5mm flat iron m 1.40 56.00 78.40
Allow for anticorrosive paint 25.00
Sub Total 875.90
Add 36% Profit & O/H 315.32
Rate per m 1,191.22
Supplying & laying 50mm thick glass fibre insulation sheets with aluminium foil

Per m2

Labour cost per m

Skilled Labour hrs 0.50 125.00 62.50


Unskilled Labour hrs 0.25 100.00 25.00

Material Cost

50mm thick glass fibre insulation sheets m2 1.10 214.44 235.89


75x75mm gauge 18 galvernized mesh m2 1.10 109.63
Allow for scaffolding, tape etc 25.00
Sub Total 348.39
Add 36% Profit & O/H 69.68
Rate per m 418.07

Supplying & laying 25mm thick glass fibre insulation sheets with aluminium foil ( density 32 kg/m3)
for wall
Per m2

Labour cost per m

Skilled Labour hrs 0.50 125.00 62.50


Unskilled Labour hrs 0.25 100.00

Material Cost

50mm thick glass fibre insulation sheets m2 1.10 297.22 326.94


Allow for scaffolding & tapes 25.00
Sub Total 414.44
Add 36% Profit & O/H 111.90
Rate per m 526.34

Supplying & laying 8mm thick aluminium foil sisilation sheets - single

Per m2

Labour cost per m

Skilled Labour hrs 0.50 125.00 62.50


Unskilled Labour hrs 0.25 100.00 25.00

Material Cost

8mm thick insulation sheets ( single) m2 1.10 321.74 353.91


75x75mm gauge 18 galvernized mesh m2 1.10 109.63 120.59
Allow for adhesive tape & transport 25.00
Sub Total 587.01
Add 36% Profit & O/H 117.40
Rate per m 704.41

Supplying & laying 8mm thick aluminium foil sisilation sheets - double

Per m2

Labour cost per m

Skilled Labour hrs 0.50 125.00 62.50


Unskilled Labour hrs 0.25 100.00 25.00

Material Cost

8mm thick insulation sheets ( double) m2 1.10 363.48 399.83


75x75mm gauge 18 galvernized mesh m2 1.10 109.63 120.59
Allow for adhesive tape & transport 25.00
Sub Total 632.92
Add 36% Profit & O/H 126.58
Rate per m 759.50

Supplying & laying 1mm thick aluminium foil sisilation sheets - single

Per m2

Labour cost per m

Skilled Labour hrs 0.50 125.00 62.50


Unskilled Labour hrs 0.25 100.00 25.00

Material Cost

1mm thick insulation sheets ( single) m2 1.10 321.74 353.91


75x75mm gauge 18 galvernized mesh m2 1.10 109.63 120.59
Allow for adhesive tape & transport 25.00
Sub Total 587.01
Add 36% Profit & O/H 117.40
Rate per m 704.41

Supplying & laying 1mm thick aluminium foil sisilation sheets - double

Per m2

Labour cost per m

Skilled Labour hrs 0.50 125.00 62.50


Unskilled Labour hrs 0.25 100.00 25.00

Material Cost

1mm thick insulation sheets ( double) m2 1.10 363.48 399.83


75x75mm gauge 18 galvernized mesh m2 1.10 109.63 120.59
Allow for adhesive tape & transport 25.00
Sub Total 632.92
Add 36% Profit & O/H 126.58
Rate per m 759.50

J-10
Colour bond Zinc Aluminium sandwitch panel roofing sheets on steel frame work
Per m2
Skilled labour Hour 0.500 125.00 62.50
Unskilled labour Hour 0.75 100.00 75.00
Zinc Alum Sandwitch panel - 30mm thick m2 1.10 4,090.00 4,499.00
Drive Screws and washers Nos 5.00 10.00 50.00
Allow for transport 112.48
Sub Total 4,798.98
Add 36% P & O H 1,295.72
Rate per m2 6,094.70

Supplying & laying 10mm thick aluminium foil sisilation sheets - double

Per m2

Labour cost per m


Skilled Labour hrs 0.50 125.00 62.50
Unskilled Labour hrs 0.25 100.00

Material Cost

10mm thick insulation sheets ( double) m2 1.10 426.96 469.65


75x75mm gauge 18 galvernized mesh m2 1.10 100.00 110.00
Allow for adhesive tape & transport 25.00
Sub Total 667.15
Add 36% Profit & O/H 93.40
Rate per m 760.55

Supplying & laying 50x50mm mesh

Per m2

Labour cost per m

Skilled Labour hrs 0.50 125.00


Unskilled Labour hrs 0.25 100.00 25.00

Material Cost

75x75mm gauge 18 galvernized mesh m2 1.10 109.63 120.59


Allow for adhesive tape & transport 25.00
Sub Total 170.59
Add 36% Profit & O/H 34.12
Rate per m 204.71

Colour bond Zinc Aluminium roofing sheets on steel frame work 25mm thick glass wool & alumimium foil
Per m2

Skilled labour Hour 0.500 125.00 120.00


Unskilled labour Hour 0.75 100.00
Zinc Alum roofing sheets m2 1.20 1,000.00 1,200.00
Drive Screws and washers Nos 2.00 10.00 20.00

Alumimium foil & Glass wool


Labour cost per m

Skilled Labour hrs 0.50 125.00 62.50


Unskilled Labour hrs 0.25 100.00 25.00

Material Cost

25mm thick glass fibre insulation sheets m2 1.10 136.25 149.88


Double side Alumimium foil m2 1.10 90.00 99.00

Allow for scaffolding & tapes 50.00


Allow for Transport - 5% of material cost 72.44
Sub Total 1,798.82
Add P & O H 485.68
Rate per m2 2,284.50

2,000.00
50.00
325.00

50.00
135.50

24,000.00 266.67

0.16666667

0.07175 705
0.25 1390
0.58
0.26
98,064.00 0.12
1.28525 0.0142806

estos sloping sheets)

67.59 80,000.00 727.27


67.59
1,440.00
457.14

3,558.50
960.80
4,519.30
32,000.00 344.09

0.07175 705
0.25 1390
0.80
0.375
131,615.00 0.210
1.70875
32,000.00 344.09

0.065625
0.23

0.60
0.550
131,182.50 0.210
1.650625
55.00
132.50

55.00
157.50

180.00
371.25

180.00
30.00

600.00
120.00

137.50
240.00
87.50

ity 32 kg/m3)

62.50

500.00
87.50

540.00

87.50

600.00

87.50
540.00

87.50

600.00

137.50
62.50

600.00

25.00

200.00

ol & alumimium foil

120.00
J - 09
Colour bond Zinc Aluminium roofing sheets on steel frame work
Per m2

Roof covering
Skilled labour Hour 0.650 125.00
Unskilled labour Hour 1.72 100.00 120.00
Zinc Alum roofing sheets m2 1.20 1,169.23 1,403.08
Drive Screws and washers Nos 2.00 15.00 30.00
Allow for transport 35.08 1,588.15

Roof area = 181.9m2


Ridge cap length =244.5 ###

Supplying & laying 600mm wide Zinc Alume


ridge cap to match roofing sheets

Data per m

Material
Zinc Alume ridge cap m 1.1 554 609.40
drive screws and washers Nos 2 65 130.00
Transport 5.00

Labour
skilled labour Hour 1.70 125.00 212.50 ###
Cost per m = 956.90

Total cost for ridge cap 233,962.05


Cost per m2 1,286.21

Supplying & laying Aluminium foil with wire netting over existing ceiling

Data per m2

Material
2 way reinforced double
sided Aluminium foil - 8mm m2 1.2 420 504.00
Hexagon wire netting m2 1.2 100 120.00
Adhesive tape m 0.9 12 10.80
Transport 3.00

Labour
skilled labour Hour 0.25 125.00 31.25
Supplying & fixing 150x65x2mm thick galvernized lipped channel purlins

per m

Supplying 150x50x2mm m 1.00 1000.00 1,000.00 ###


thick lipped channel purlins
Cutting,fabricating kg 5.50 10 55.00
Other accessories 25.00
Loading & Unloading 5.00 ###
For painting ( Area ~ (.165+.5*2)*2 =2.33m2 ) ###

Supplying 1 coat of primer ( anticorrosive paint)


Anticorrosive paint lit 0.189 349.25 65.91
Thinner lit 0.047 130.00 6.06
Allow for brushes etc. 4.00
###
Supplying 2 coats of Enamel paint ###
Enamel paint lit 0.3728 482.50 179.88 ###
Thinner lit 0.1398 130.00 18.17
Allow for brushes etc. 4.00
Cost per m 1,363.02 1,363.02

Lipped channel length 275m Total cost 374,831.04

Cost per m2

Cost per m2 4,237.39


Add O & H profit 15% 635.61
Rate per m2 4,873.00

Zn Al roof

Colour bond Zinc Aluminium roofing sheets on steel frame work


Per 50m2

Skilled labour Hour 0.500 125.00 6,000.00


Unskilled labour Hour 0.75 100.00
Zinc Alum roofing sheets m2 60.00 1,169.23 70,153.85
Drive Screws and washers Nos 2.00 15.00 30.00
Allow for transport 1,753.85

50x50mm box bar with fabric m 60.00 1,200.00 72,000.00

Cost per m2 - 149,937.69


Add O & H profit 15% - 40,483.18
Rate per m2 - 190,420.87

3,808.42

Item D29
Supplying & fixing 100x50x2.3mm HT lipped channel

Supplying cost per m 800.00 Quotation


Cleat 200mm long, 100x75x6mm 193.00
Cutting, fabricating 35.00 per m 35.00
Painting 0.45m2 @550 247.50
Transport 25.00

Total Cost 1,300.50


Add 27% P & OH 195.08
Total cost 1,495.58

Proposed rate in BOQ/m 1,500.00

Colour bond Zinc Aluminium roofing sheets on steel frame work


Per 50m2

Skilled labour Hour 0.500 125.00 6,000.00


Unskilled labour Hour 0.75 100.00

0.47mm TCT Colour bond Zin m2 60.00 1,169.23 70,153.85


Drive Screws and washers Nos 2.00 15.00 30.00
Allow for transport 1,753.85

50x50mm box bar with fabric m 60.00 1,200.00 72,000.00

Cost per m2 - 149,937.69


Add O & H profit 15% - 40,483.18
Rate per m2 - 190,420.87

3,808.42
Carpenter & Joiner

K- 01
Flat asbestose ceiling with timber frame work and painting
Per m2

Making holes in wall and fixing joists and bearers

Class I, timber beams m3 0.013 ###


Skill labour hrs 0.66 125.00
Unskill labour hrs 0.66 100.00
Wire nail kg 0.121 140.00

Fixing joists in wall and making good holes

Mason hrs 0.11 125.00


labour hrs 0.11 100.00

Treating timber with Tarnap

Wood preservative Litres 0.031 131.00


Unskill labour hrs 0.22 100.00

Cutting & nailing sheets

Asbestose ceiling sheet m2 1.100 229.17


20mm G.I. Clout nails Kg. 0.030 135.00
Skill labour hrs 0.44 125.00
Unskill labour hrs 0.66 100.00

Fixing beading
Timber beadings m 2.100 30.00
Brass screws Doz. 0.440 14.00
Skill labour hrs 0.33 125.000
Unskill labour hrs 0.33 100.000

Fixing Cove moulding


Timber Cove Moulding m 1.010 48.00
Wood plug No 2.000 6.00
Skill labour hrs 0.11 125.00
Unskill labour hrs 0.44 100.00

Painting
Alkali resisting primer Litres 0.020 124.18
Emulsion paint Litres 0.062 571.50
Skill labour hrs 0.88 125.00
Sub Total
Add P & O H
Rate per m2
K-02
Lunumidella ceiling including timber frame work
Per m2

Skill labour hrs 1.80 125.00


Unskill labour hrs 2.26 100.00
Timber beams class 1 Cum 0.01 ###
Wire nails S.W.G 12 to 14 Kg 0.07 140.00
Wood Preservative Lit 0.16 146.25
Lunumidella 150x20mm m2 1.30 280.00
Allow for scaffolding
Sub Total
Add P & O H
Rate per m2

K-03
Lunumidella ceiling underside of roof rafters
Per m2

Skill labour hrs 1.10 125.00


Unskill labour hrs 1.10 100.00
Wire nails S.W.G 12 to 14 Kg 0.07 140.00
Wood Preservative Lit 0.16 146.25
Lunumidella 150x20mm m2 1.30 280.00
Allow for scaffolding
Sub Total
Add P & O H
Rate per m2

K-04
Making and fixing of 20mm thick valance board including painting(Using Kempas)
Per m

Skill labour hrs 3.43 125.00


Unskill labour hrs 0.86 100.00
Ginisapu planks m 1.10 445.00
50mm iron screws Gauge 10 Nos. 4.93 2.00
Wood Preservative Lit 0.05 146.25
Oil Paint Litrs 0.10 650.00
Painter Hrs. 1.08 125.00
Sub Total
Add P & O H
Rate per m

K-05
Fixing of mortice or night latch door lock ( single door)
Per No.

Skill labour hrs 2.00 125.00


Nitch latch door lock No. 1.00 1,100.00
Allow for tools etc.
Sub Total
Add P & O H
Rate per No.
K-06
Fixing of mortice or night latch door lock ( double door)
Per No.

Skill labour hrs 4.00 125.00


Nitch latch door lock ( double) No. 1.00 1,250.00
Allow for tools etc.
Sub Total
Add P & O H
Rate per No.

K-07
Fabrication and fixing mild steel purlins / trusses. Rate included for painting. Steel and
paint supplied by the Bureau
Per Kg.

Labour per Kg.


Structural Steel Kg 1.00 120.00
Allow for welding rods etc. Item
Allow for welding equipment etc Item
Sub Total
Add P & O H
Rate per kg

K-08
Supplying & fixing of 32mm glazed and panelled door sashes and 100mm x 75mm frames
in class1 local timber fixed complete with brass furniture
Per m2

Skill labour hrs 62.00 125.00


Unskill labour hrs 2.38 100.00
Timber beams class 1 Cu.m 0.03 ###
Timber planks 38mm class 1 m2 0.67 480.00
25mm thick planks of class 1 local timber m2 0.52 480.00
Hinge butt brass 125mm x 100mm Nos 1.50 160.00
Screws Butt Brass 40mm x Gauge 8 Nos 12.30 42.00
Screws Butt Brass 50mm x Gauge 8 Nos 3.00 48.00
Door lock Nos 1.00 1,250.00
Allow for machine planning and joints
Allow for spur stones rawl plugs and screws
Allow for paint
Sub Total
Add P & O H
Rate per m2

K-09
Supplying & fixing 0f 32mm thick ordinary sash single (Ordinary finish) plywood door hung on
100mm x 75mm frame in class 1 timber complete with brass furniture

Skill labour hrs 62.00 125.00


Unskill labour hrs 2.38 100.00
Hold fasts - 400 x 25 x 6 Nos 2.83 25.00
Ply wood door ordinary M.R 838 x 2060 x 32mm No 0.47 939.82
Hinge butt brass 125mm x 100mm Nos 1.42 160.00
Bolt Skeleton Brass 300mm Nos 0.47 100.00
Bolt Barrel Brass 150mm Nos 0.47 85.00
Screws Butt Brass 40mm x Gauge 8 Nos 0.48 42.00
Screws Butt Brass 25mm x Gauge 8 Nos 0.94 14.00
Screws Butt Brass 20mm x Gauge 8 Nos 0.48 14.00
Door lock Nos 1.00 1,250.00
Allow for machine planning and joints
Allow for spur stones rawl plugs and screws
Allow for paint
Sub Total
Add P & O H
Rate per m2

Aluminium framed Zn /Al door - 900x2100mm Type -D4

Per m2

Description Unit Qty Rate Amount


Rs. Cts. Rs. Cts.

Labour
Labour cost m2 1.89 1,000.00 1,890.00
Material Cost
PT -5159 nr 1 3,375.00 3,375.00
1 1/2x1 1/2 H/L nr 3 2,973.00 37.16

Accessories
1/8x3/8 Rivet nr 8 0.83 6.64
4"x3" Hinges nr 3 80.00 240.00
5/32 x3/8 CSK nr 24 1.40 33.60
Union Lock nr 1 3,580.00 3,580.00
Large felt m 5 30.00 150.00
Zn/Al sheet m2 1.89 1,200.00 2,268.00
2x8 OH nr 8 2.90 23.20
S 6 wall plug nr 8 0.70 5.60
Silicon nr 1 380.00 380.00
Door Closer ( new star) nr 1 2,950.00 2,950.00
Sub Total -1 14,939.20
Add 10 % wastage 1,493.92
Add 5 % transport 746.96
Sub Total - II 17,180.08
Add P & OH 14% 2,405.21
Rate /Nr. 19,585.29

Rate /m2 10,362.59


Proposed Rate in BOQ 10,000.00
1,365.00
82.50
66.00 1.767+0.025
16.94

13.75
11.00

4.06
22.10 22.10

252.08
4.05
55.25
66.20 121.45

63.00
6.16
41.38
33.10 74.48

48.48
12.00
13.75
44.00 57.75 for 93m2

skill 2.53 29.45


Unskill 2.42 28.18
2.48
35.43
110.00 110.00
2,368.72 363.68
639.55
3,008.27
225.00
226.00 451.00
1,260.00
10.36 210.00
23.84
364.00
20.00
2,129.20
574.88
2,704.08

137.50
110.00 247.50
10.36
23.84
364.00
20.00
665.70
179.74
845.44

428.75
86.00 514.75
489.50
9.85
7.11
62.79
135.00
1,219.00
329.13
1,548.13
250.00 250.00
1,100.00
100.00
1,450.00
391.50
1,841.50

500.00
1,250.00
100.00
1,850.00
499.50
2,349.50

22.00
120.00
5.00
5.00
152.00
41.04
193.04

5mm frames

7,750.00 7,987.50
237.50
3,150.00
321.60 1,560.00
249.60
240.00
516.60
144.00
1,250.00
150.00
75.00
200.00
14,284.30
3,856.76
18,141.06

d door hung on

7,750.00
237.50
70.75
443.59
226.56
47.20
40.12
20.16
13.20
6.72
1,250.00
150.00
75.00
200.00
10,530.81
2,843.32
13,374.12
Quotation

963.07
Plasterer

L - 01
20mm thick, 1:2 cement sand D.P.C and finished smooth with 2 coats
of hot tar blinded with coarse sand
Per m2

Skill labour hrs 1.00 125.00


Unskill labour hrs 2.00 100.00
Cement Bags 0.24 795.00
Sand m3 0.023 1,590.11
DPC Tar Lit 0.50 125.00
Allow for water etc.
Transporting Cement Bags 0.24 10.00
Sub Total
Add P & O H
Rate per m2

300mm width
Rate per m

L - 02
15mm thick ,1:1:5 cement lime plastering finished rough
Per m2

Skill labour hrs 0.65 125.00


Unskill labour hrs 1.29 100.00
Cement Bags 0.09 795.00
Slaked lime kg 2.40 10.00
Sand m3 0.02 1,590.11
Allow for water , scaffolding etc.
Transporting Cement Bags 0.09 10.00
Sub Total
Add P & O H
Rate per m2
L - 03
15mm thick ,1:1:5 cement lime plastering and finished smooth with lime putty
Per m2

Skill labour hrs 1.30 125.00


Unskill labour hrs 1.30 100.00
Cement Bags 0.09 795.00
Slaked lime kg 3.00 10.00
Sand m3 0.02 1,590.11
Allow for water etc.
Transporting Cement Bags 0.09 10.00
Sub Total
Add P & O H
Rate per m2
L - 03
15mm thick ,1:5 cement sand plastering and finished smooth with SKIM COAT & JOINT COMPOUND
Per m2

Skill labour hrs 1.30 125.00


Unskill labour hrs 1.30 100.00
Cement Bags 0.09 795.00
Febmix Lit 0.01 180.00
Sand m3 0.02 1,590.11
Skim coat Kg. 1.80 34.00
Joint compound Kg. 1.50 58.93
Allow sand Papers Nos 0.27 15.00
Allow for water etc.
Transporting Cement Bags 0.09 10.00
Sub Total
Add P & O H
Rate per m2

L - 04
15mm thick plastering,1:1:3 cement lime and sand to R.C.C beams and
slab soffit including floating with lime putty
Per m2

Skill labour hrs 1.75 125.00


Unskill labour hrs 1.75 100.00
Cement Bags 0.09 795.00
Slaked lime Kg. 3.00 10.00
Sand m3 0.02 1,590.11
Allow for water etc.,scaffolding
Sub Total
Add P & O H
Rate per m2

L - 05
Application of lime putty to soffits of slabs & beams
Per m2

Skill labour hrs 1.75 125.00


Unskill labour hrs 1.75 100.00
Slaked lime kg 1.50 110.00
Allow for water etc.,scaffolding
Sub Total
Add P & O H
Rate per m2
L - 05
Application of SKIM COAT & JOINT COMPOUND to soffits of slabs & beams
Per m2

Skill labour hrs 1.75 125.00


Unskill labour hrs 1.75 100.00
Skim coat kg 1.80 34.00
Joint compound kg 1.50 58.93
Allow for water etc.,scaffolding
Sub Total
Add P & O H
Rate per m2

L - 06
12mm thick, 1:3 cement rendering, including neat cement or coloured cement floating
Per m2

Skill labour hrs 0.65 125.00


Unskill labour hrs 1.30 100.00
Cement Bags 0.12 795.00
Sand m3 0.02 1,590.11
Cement Bags 0.03 795.00
Colour pigment for cement Kg. 0.00 475.00
Allow for water etc.
Sub Total
Add P & O H
Rate per m2

L - 07
20mm thick, 1:3 cement rendering, including neat cement or coloured
cement floating
Per m2

Skill labour hrs 0.87 125.00


Unskill labour hrs 1.73 100.00
Cement Bags 0.19 795.00
Sand m3 0.02 1,590.11
Cement Bags 0.03 795.00
Transporting Cement Bags 0.03 10.00
Colour pigment for cement kg 0.00 475.00
Allow for water etc.
Sub Total
Add P & O H
Rate per m2
L - 08
12mm x 150mm skirting in 1:3 projected on flush with wall and
including forming groove.
Per m

Skill labour hrs 1.00 125.00


Unskill labour hrs 0.80 100.00
Cement Bags 0.03 795.00
Sand m3 0.00 1,590.11
Colour pigment for cement Kg. 0.00 475.00
Transporting Cement Bags 0.03 10.00
Allow for water
Sub Total
Add P & O H
Rate per m

L - 09
Plastering to column of 225 x 225mm
Per m ( 0.9 m2)

Skill labour hrs 2.80 125.00


Unskill labour hrs 2.80 100.00
Cement Bags 0.08 795.00
Slaked lime Kg. 2.70 10.00
Sand m3 0.01 1,590.11
Allow for water etc.,scaffolding
Sub Total
Add P & O H
Rate per m
L - 10
Plastering to column of 150 x 150mm
Per m ( 0.6 m2)

Skill labour hrs 2.80 125.00


Unskill labour hrs 2.80 100.00
Cement Bags 0.05 795.00
Slaked lime Kg. 1.80 10.00
Sand m3 0.01 1,590.11
Allow for water etc.,scaffolding
Sub Total
Add P & O H
Rate per m
L - 11
Plastering to reveals ( 100mm wide)
Per m ( 0.1 m2)

Labour cost per m


Cement Bags 0.01 795.00
Slaked lime Kg. 0.30 10.00
Sand m3 0.00 1,590.11
Allow for water etc.,scaffolding
Sub Total
Add P & O H
Rate per m2

L - 12
15mm thick plastering with 1:5 cement , sand & febmix in walls ( external)
Per m2

Skill labour hrs 0.65 125.00


Unskill labour hrs 1.30 100.00
Cement Bags 0.09 795.00
Find Sand m3 0.02 1,590.11
Feb mix litre 0.11 180.00
Allow for water, scaffolding, spong sheet, regifoam ect.
Sub Total
Add P & O H
Rate per m2

L - 13
15mm thick plastering with 1:5 cement , sand & febmix in internal walls
Per m2

Skill labour hrs 1.30 125.00


Unskill labour hrs 1.30 100.00
Cement Bags 0.09 795.00
Fine Sand m3 0.02 1,590.11
Feb mix litre 0.11 180.00
Allow for water etc.,sand papers, roller brushes etc
Sub Total
Add P & O H
Rate per m2

L - 14
15mm thick plastering with 1:5 cement , sand & febmix in columns
Per m2

Skill labour hrs 2.00 125.00


Unskill labour hrs 3.00 100.00
Cement Bags 0.09 795.00
Fine Sand m3 0.04 1,590.11
Feb mix Litres 0.11 180.00
Allow for water etc.
Sub Total
Add P & O H
Rate per m2

Fair face rubble finish - (30mm thick plaster)


Per m2

Skill labour hrs


Unskill labour hrs
Cement Bags 0.17 795.00
Fine Sand m3 0.04 1,590.11
Rubble (wire cut finish) with labour m2 1.00 4,300.00
Allow for water etc.
Sub Total
Add P & O H
Rate per m2
250.00 250.00
192.39
36.57
62.50
10.00

551.46
148.89
700.36

210.11

0.08
225.00 225.00 0.16
68.37
24.00
33.39
15.00
0.86
366.62
98.99
465.61

0.16
260.00 260.00 0.16
68.37
30.00
33.39
5.00
0.86
397.62
107.36
504.98
& JOINT COMPOUND

215.00 215.00

61.20 150 ft2 for 25kg


88.39 200ft2 for 28kg
4.05
5.00
0.86
374.50
101.12
475.62

350.00 350.00
68.37
30.00
23.85
10.00
482.22
130.20
612.42

350.00
350.00
165.00
10.00
525.00
141.75
666.75
350.00 350.00
61.20
88.39
10.00
509.59
137.59
647.18

210.00 210.00
91.43
23.85
23.06
1.90
5.00
355.23
95.91
451.14

260.00 260.00
149.46
34.98
23.06
0.29
1.90
5.00
474.69
128.17
602.85
125.00
80.00 205.00
25.44
4.77
0.48
0.29
2.00
237.98
64.25
302.23

350.00 0.81
280.00 630.00
61.53
27.00
21.47
10.00
750.00
202.50
952.50

350.00
280.00 630.00
41.02
18.00
14.31
10.00
713.33
192.60
905.93

75.00
6.84
3.00
2.39
10.00
97.22
26.25
123.47

81.25
130.00 211.25
68.37
33.39
19.80
12.00
263.56
71.16
334.72

162.50
130.00 292.50
68.37
33.39
19.80
12.00
426.06
115.04
541.10

250.00
300.00 550.00
68.37
63.60
19.80
10.00
711.77
192.18
903.95

135.15
63.60
4,300.00
25.00
4,523.75
1,221.41
5,745.17
Roof Plumber

M - 01
Fixing of 114mm PVC square gutters with PVC brackets and screws at
450mm intervals including all necessary moulded fittings
Per m

Skill labour hrs 0.273 125.00


Unskill labour hrs 0.273 100.00
PVC square gutters m 1.00 264.00
Gutter end cap Nos. 0.14 110.00
Mitre joint PVC 114mm Nos. 0.07 372.00
Gutter joiner Nos. 0.21 112.00
Gutter bracket Nos. 3.10 60.00
Running head square Nos. 0.14 131.00
Solvent cement 50 gms 0.14 264.00
Brass screws, gauge 6 Doz. 0.58 14.00
Allow for scaffolding etc.
Sub Total
Add P & O H
Rate per m

M - 02
Fixing of 89 mm dia. PVC Down Pipes
Per m

Skill labour hrs 0.546 125.00


Unskill labour hrs 0.546 100.00
89mm dia. Down pipes m 1.09 184.43
Down pipe elbow Nos. 0.55 164.00
Down pipe joiner Nos. 0.14 138.00
Wooden plugs m 0.55 15.00
Down pipe clips Nos. 0.55 29.00
Brass screws, gauge 6 Doz. 0.09 14.00
Solvent cement 50 gms 0.21 264.00
Allow for scaffolding rawl plugs etc.
Sub Total
Add P & O H
Rate per m

M - 03
Fixing of GI gutters ( gauge 24 GI sheets)
Per m

Skill labour hrs 2.500 125.00


Unskill labour hrs 1.500 100.00
Gauge 24 GI sheets m2 0.35 400.00
Mild Steel flat Kg. 0.23 26.00
63 x 10mm bolt & nut Nos. 2.50 5.50
45 x 6mm bolts & nuts Nos. 1.67 1.50
Allow for painting
Sub Total
Add P & O H
Rate per m

M - 04
Fixing of GI down pipes ( gauge 24 GI sheets)
Per m

Skill labour hrs 2.500 125.00


Unskill labour hrs 1.000 100.00
Gauge 24 GI sheets m2 0.40 400.00
Mild Steel flat Kg. 0.23 26.00
63 x 10mm bolt & nut Nos. 2.50 5.50
45 x 6mm bolts & nuts Nos. 1.67 1.50
Allow for painting
Sub Total
Add P & O H
Rate per m

M - 05
Supplying & fixing of 0.47 x470 mm Zink Alum gutters

Skill labour hrs 1.000 125.00


Unskill labour hrs 1.000 100.00
Gutters 0.47 x 470mm m 1.00 575.00
Gutter end cap Nos. 0.14 160.00
Nozzle Nos. 0.14 235.00
Brass screws, gauge 6 Doz. 0.58 14.00
Brackets Nos. 2.50 45.00
Allow 10% for scaffolding & transport etc.
Sub Total
Add P & O H
Rate per m

M - 06
Fixing of Zinc Alum down pipes
Per m

Skill labour hrs 1.000 125.00


Unskill labour hrs 1.000 100.00
Zinc Alum down pipes -80 x 100 m 1.00 541.00
63 x 10mm bolt & nut Nos. 2.50 5.50
45 x 6mm bolts & nuts Nos. 1.67 1.50
Zinc Alum down pipe bracket Nos. 2.50 22.00
Allow for scaffolding & transport
Sub Total
Add P & O H
Rate per m

Supplying & fixing Zn/Al valley gutters including timber boarding


Per m

Labour cost per m


Skilled Labour hrs 1.00 125.00
Unskilled Labour hrs 0.70 100.00

Material Cost
Zn/alum valley gutter m 1.00 #REF!
Class II, 25mm timber planks m2 1.00 480.00
Coal tar Litre 0.22 #REF!
Cement Bags 0.03 #REF!
Lime kg 0.80 10.00
Sand m3 0.00 #REF!
Wire nail kg 0.07 #REF!
Wood preservative Litres 0.34 #REF!
Sub Total
Add 20% Profit & O/H
Rate per m

Supplying & fixing of 0.47 x900 mm Zink Alum gutters

Skill labour hrs 1.000 125.00


Unskill labour hrs 1.000 100.00
Gutters 0.47 x 470mm m 1.00 1,224.00
Gutter end cap Nos. 0.14 160.00
Nozzle Nos. 0.14 2,650.00
Brass screws, gauge 6 Doz. 0.58 14.00
Brackets Nos. 2.50 115.00
Allow 10% for scaffolding & transport etc.
Sub Total
Add P & O H
Rate per m
34.13
27.30 61.43
264.00
15.07
25.30
22.96
186.00
17.95
36.17
8.12
20.00
656.99
197.10
854.08
260.31

68.25
54.60 122.85
201.58
89.71
18.91
8.21
15.86
1.27
54.12
15.00
527.50
158.25
685.76
209.01

312.50
150.00 462.50
140.00
5.93
13.75
2.50
200.00
824.68
222.66
1,047.34

312.50
100.00 412.50
160.00
5.93
13.75
2.50
200.00
794.68
214.56
1,009.24

240.00 240.00
575.00
21.92
32.20
8.12
112.50
57.50
1,047.24
282.75
1,329.99

240.00 240.00
541.00
13.75
2.50
55.00
54.10
906.35
244.71
1,151.07

125.00
70.00

#REF!
480.00
#REF!
#REF!
8.00
#REF!
#REF!
#REF!
#REF!
#REF!
#REF!

125.00
100.00
1,224.00
21.92
363.05
8.12
287.50
122.40
2,251.99
608.04
2,860.03
N - Painter

N - 01
Painting one coat of Enamel Paint including preparation of surface
Per m2

Skill labour hrs 0.432 125.00


Enamel paint Litrs 0.08 712.50
Allow for brushes sand paper etc.
Sub Total
Add P & O H
Rate per m

N - 02
Painting two coats of Enamel Paint including preparation of surface
Per m2

Skill labour hrs 1.000 125.00


Enamel paint Litrs 0.16 712.50
Allow for brushes etc.
Sub Total
Add P & O H
Rate per m

N - 03
Painting new wood work with one coat of wood primer
Per m2

Skill labour hrs 0.500 125.00


Aluminium wood primer Litrs 0.08 655.75
Allow for brushes etc.
Sub Total
Add P & O H
Rate per m

N - 04
Painting new wood work with one coat of wood primer and two coats
of Enamal paint
Per m2

Skill labour hrs 1.300 125.00


Enamel paint Litrs 0.16 712.50
Allow for brushes etc.
Sub Total
Add P & O H
Rate per m2

N - 05
Painting steel work with one coat of Anticorrosive and and two coats of
enamal paint including scaling and wire brushing. of Enamal paint
Per m2

Skill labour hrs 1.300 125.00


Anticorrosive paint Litrs 0.08 655.75
Enamel paint Litrs 0.16 712.50
Allow for brushes etc.
Sub Total
Add P & O H
Rate per m2

N-06a
Painting Internal walls with one primer coat & two
coats of Emulsion paint
Per m2

Skill labour hrs 0.900 125.00


Emulsion paint Litrs 0.16 552.00
Acrilic Filler kg 0.16 124.18
Allow for brushes etc. & scaffolding
Sub Total
Add P & O H
Rate per m2

N-09
Painting External walls with one primer coat and two coats
of weathershield paint.
Per m2

Skill labour hrs 0.900 125.00


Weathershield paint Litrs 0.22 775.00
Acrilic filler kg 0.23 124.18
Allow for brushes etc. & scaffolding
Sub Total
Add P & O H
Rate per m2
Painting Internal walls with one primer coat & two
coats of Emulsion paint WITH BASE COMPOUND
Per m2

Skill labour hrs 0.900 125.00


Emulsion paint Litrs 0.16 571.50
Skim coat Kg. 1.80 34.00
Joint compound Kg. 1.50 58.93
Acrilic Filler kg 0.16 124.18
Allow for brushes etc. & scaffolding
Sub Total
Add P & O H
Rate per m2

N-10
Painting floors with one coat of floor paint including preparing surface.
Per m2

Skill labour hrs 0.250 125.000


Floor paint Litrs 0.16 855.00
Allow for brushes etc.
Sub Total
Add P & O H
Rate per m2

N - 11
Painting floors with two coat of floor paint including preparing surface.
Per m2

Skill labour hrs 0.400 125.000


Floor paint Litrs 0.16 880.75
Allow for brushes etc.
Sub Total
Add P & O H
Rate per m2
N - 12
Painting roof covering with two coats weathershield paint.
Per m2

Skill labour hrs 0.400 125.000


Weathershield paint Litrs 0.36 796.50
Allow for brushes etc.
Sub Total
Add P & O H
Rate per m2

N - 13
Floor polishing and waxing after washing, cleaning and preparing surface
(Polisher provided)
Per m2

Skill labour hrs 0.500 125.000


Floor polish Kg. 0.09 425.00
Allow for Polisher with brushes etc.
Sub Total
Add P & O H
Rate per m2

Rate Analysis - Item 1

Floor polishing and waxing after washing, cleaning and preparing surface

Per m2

Skill labour hrs 0.500 125.000


Floor polish kg 0.11 1,450.00
Polisher with brushes etc. hrs 0.50 150.00
Sub Total
Add P & O H
Rate per m2

Say
54.00 54.00
57.71 20.00
15.00
126.71
34.21
160.92

125.00 125.00
114.71
10.00
124.71
33.67
158.38

62.50 62.50
53.12
5.00
120.62
32.57
153.18

162.50 162.50
114.71
5.00
282.21
76.20
358.41

Zinc Phosphate
Painting steel work with one coat of Anticorrosive and and two coats of
enamal paint including scaling and wire brushing. of Enamal paint
Per m2

162.50 162.50 Skill labour hrs 1.300


53.12 Zn/ Phosphate Primer Litrs 0.16
114.71 Enamel paint Litrs 0.16
5.00 Allow for brushes etc.
335.33 Sub Total
90.54 Add P & O H
425.87 Rate per m2

160.00 160.00
88.32
19.87
25.00
293.19
79.16 73.30
372.35 366.49

160.00 160.00
172.83
28.56
25.00
386.39
104.32
490.71
160.00
91.44
61.20
88.39
19.87
25.00
445.90
120.39
566.29

31.25 31.25
136.80
5.00
173.05
46.72
219.77

50.00 50.00
144.44
15.00
209.44
56.55
265.99
50.00 50.00
284.19
10.00
344.19
92.93
437.12

62.50 62.50
36.55
70.00
169.05
45.64
214.69

62.50
159.50
75.00
297.00
80.19
377.19

210.00
osive and and two coats of
hing. of Enamal paint

125.00 162.50 162.50


943.00 150.88
712.50 114.71
5.00
433.09
116.93
550.03
Water Supply & Sewerage

P - 01
Laying 20mm(type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.300 125.000


Unskill labour hrs 0.300 100.000
20mm dia. PVC pipes ( 1000) m 1.10 37.57
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P- 02
Laying 25mm(type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.300 125.000


Unskill labour hrs 0.300 100.000
25mm dia. PVC pipes ( 1000) m 1.10 94.49
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P- 03
Laying 32mm ( type1000)PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000


Unskill labour hrs 0.400 100.000
32mm dia. PVC pipes ( 1000) m 1.10 148.44
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m
Skill labour hrs 0.400 125.000
Unskill labour hrs 0.400 100.000
40mm dia. PVC pipes ( 1000) m 1.10 200.52
Allow for other expenses
Sub Total
Add P & O H
Rate per m

Laying 50mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.410 125.000


Unskill labour hrs 0.410 100.000
50mm dia. PVC pipes ( 1000) m 1.10 276.79
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 06
Laying 63mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.550 125.000


Unskill labour hrs 0.550 100.000
63mm dia. PVC pipes ( 1000) m 1.10 469.12
Allow for other expenses

Sub Total
Add P & O H
Rate per m

P - 07
Laying 75mm ( type 1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.700 125.000


Unskill labour hrs 0.700 100.000
75mm dia. PVC pipes ( 1000) m 1.10 846.73
Allow for other expenses

Sub Total
Add P & O H
Rate per m

P - 07
Laying 90mm ( type 1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.700 125.000


Unskill labour hrs 0.700 100.000
90mm dia. PVC pipes ( 1000) m 1.10 951.64
Allow for other expenses

Sub Total
Add P & O H
Rate per m

P - 07
Laying 110mm ( type 1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.700 125.000


Unskill labour hrs 0.700 100.000
90mm dia. PVC pipes ( 1000) m 1.10 1,409.97
Allow for other expenses

Sub Total
Add P & O H
Rate per m

Type 400
P - 08
Laying 110mm PVC type 400 pipe including trenching, back filling and
making good to walls
Per m
Skill labour hrs 1.500 125.000
Unskill labour hrs 1.500 100.000
110mm dia. Type 400, PVC m 1.10 590.00
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 08
Laying 63mm PVC type 400 pipe including trenching, back filling and
making good to walls
Per m
Skill labour hrs 0.550 125.000
Unskill labour hrs 0.550 100.000
63mm dia. Type 400, PVC m 1.10 225.00
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 08
Laying 75mm PVC type 400 pipe including trenching, back filling and
making good to walls
Per m
Skill labour hrs 0.700 125.000
Unskill labour hrs 0.700 100.000
75mm dia. Type 400, PVC m 1.10 378.00
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 08
Laying 90mm PVC type 400 pipe including trenching, back filling and
making good to walls
Per m
Skill labour hrs 0.550 125.000
Unskill labour hrs 0.550 100.000
90mm dia. Type 400, PVC m 1.10 565.00
Allow for other expenses
Sub Total
Add P & O H
Rate per m

Laying 110mm PVC type 400 pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.550 125.000


Unskill labour hrs 0.550 100.000
90mm dia. Type 400, PVC m 1.10 590.00
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 09
Laying 160mm PVC type 400 pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 1.800 125.000


Unskill labour hrs 1.800 100.000
160mm dia. Type 400, PVC m 1.10 1,730.00
Allow for other expenses
Sub Total
Add P & O H
Rate per m

Type 600
P - 04
Laying 40mm ( type600) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000


Unskill labour hrs 0.400 100.000
40mm dia. PVC pipes ( 600) m 1.10 155.13
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 04
Laying 50mm ( type600) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000


Unskill labour hrs 0.400 100.000
50mm dia. PVC pipes ( 600) m 1.10 194.94
Allow for other expenses such as accessories
Sub Total
Add P & O H
Rate per m
Laying 63mm PVC type 600 pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 1.800 125.000


Unskill labour hrs 1.800 100.000
63mm dia. Type 600, PVC m 1.10 317.71
Allow for other expenses such as accessories
Sub Total
Add P & O H
Rate per m

Laying75mm PVC type 600 pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 1.800 125.000


Unskill labour hrs 1.800 100.000
63mm dia. Type 600, PVC m 1.10 590.03
Allow for other expenses such as accessories
Sub Total
Add P & O H
Rate per m

Laying 90mm PVC type 600 pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 1.800 125.000


Unskill labour hrs 1.800 100.000
90mm dia. Type 600, PVC m 1.10 675.00
Allow for other expenses such as accessories
Sub Total
Add P & O H
Rate per m

Laying 110mm PVC type 600 pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 1.800 125.000


Unskill labour hrs 1.800 100.000
110mm dia. Type 600, PVC m 1.10 1,167.00
Allow for other expenses such as accessories
Sub Total
Add P & O H
Rate per m

Laying 110mm PVC type 600 perforated pipe including sand filling, geotextile

Per m

Skill labour hrs 1.800 125.000


Unskill labour hrs 1.800 100.000
110mm dia. Type 600, PVC m 1.10 1,167.86
Sand filling m3 0.14 1,590.11
6-9 chips m3 0.14 1,943.46
20mm metal m3 0.14 3,886.93
Geotextile m2 1.10 245.63
Allow for other expenses
Sub Total
Add P & O H
Rate per m

P - 10
Laying 160mm PVC type 600 pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 1.800 125.000


Unskill labour hrs 1.800 100.000
160mm dia. Type 600, PVC m 1.10 2,393.75
Allow for other expenses
Sub Total
Add P & O H
Rate per m

American Standard
P - 11
Supplying and Fixing of wash basin without tap
Per No.
Skill labour hrs 8.000 125.000
Unskill labour hrs 8.000 100.000
Wash basin with pedestal No. 1.00 11,500.00
Plugs Nos. 4.00
Taps No. 1.00 2,295.00
Allow for other expenses.
Sub Total
Add P & O H
Rate per No.
P - 12
Supplying & Fixing of Low Level Suit with cistern
Per No.

Skill labour hrs 8.000 125.000


Unskill labour hrs 8.000 100.000

Low level suit with cistern & fittings Nos. 1.00 27,750.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 13
Supplying and Fixing of Squatting Pan with high level cistern

Per No.

Labour cost per No.


Skill labour hrs 8.000 125.000
Unskill labour hrs 8.000 100.000
Squatting pan Nos. 1.00 6,821.00
12mm brass stop cock Nos. 1.00 375.00
Cement Bags 0.33 795.00
Cistern with fittings Nos. 1.00 -
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 14
Supplying and Fixing of bidet shower
Per No.

Labour cost per No.


Biddet shower ( chromium plated) Nos. 1.00 1,395.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 15
Supplying and Fixing of high level cistern
Per No.
Labour cost per No.
Skill labour hrs 4.000 125.000
Unskill labour hrs 4.000 100.000
High level cistern Nos. 1.00 1,100.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 16
Supplying and Fixing of stainless steel sink with tap
Per No.

Labour cost per No.


Skill labour hrs 7.500 125.000
Unskill labour hrs 7.500 100.000
Stainless steel sink Nos. 1.00 4,250.00
Long neck tap Nos. 1.00 2,750.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 17
Supplying and Fixing of 1/2" pillar cocks to
basin
Per No.

Labour cost per No.


Skill labour hrs 7.500 125.000
Unskill labour hrs 7.500 100.000
Pillar cock Nos. 1.00 2,295.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 18
Supplying and Fixing of 1/2" pillar tap to basin

Per No.

Labour cost per No.


Skill labour hrs 7.500 125.000
Unskill labour hrs 7.500 100.000
Pillar cock Nos. 1.00 560.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 19
Supplying and Fixing of pvc shower rose
Per No.

Skilled labour hrs 0.250 125.000


Unskill labour hrs 0.250 100.000
Shower rose, PVC Nos. 1.00 2,650.00
Consealded valve Nos. 1.00 2,070.00
Mixer tap Nos. 1.00 9,995.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 20
Supplying and Fixing of urinals
Per No.

Skill labour hrs 0.500 125.000


Unskill labour hrs 1.000 100.000
Urinals Nos. 1.00
Bottletrap Nos. 1.00
Flush valve Nos. 1.00 7,000.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 20
Supplying and Fixing of angle valve ( 1/2")
Per No.

Skilled labour hrs 0.500 125.000


Unskill labour hrs 0.500 100.000
Angle valves Nos. 1.00 750.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 20
Supplying and Fixing of gate valve ( 1/2")
Per No.

Skilled labour hrs 0.500 125.000


Unskill labour hrs 0.500 100.000
gate valves Nos. 1.00 510.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 21
Supplying and Fixing of gate valve / stop cock ( 1")
Per No.

Skilled labour hrs 1.000 125.000


Unskill labour hrs 1.000 100.000
Gate valves Nos. 1.00 1,400.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 22
Supplying and Fixing of gate valve / stop cock ( 11/4")
Per No.

Skilled labour hrs 1.000 125.000


Unskill labour hrs 1.000 100.000
Gate valves Nos. 1.00 1,950.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 23
Supplying and Fixing of gate valve / stop cock ( 2")
Per No.

Skilled labour hrs 1.000 125.000


Unskill labour hrs 1.000 100.000
Gate valves Nos. 1.00 2,150.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.
P - 24
Supplying and Fixing of soap tray
Per No.

Skilled labour hrs 1.000 125.000


Soap tray Nos. 1.00 1,665.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 25
Supplying and Fixing of bath room mirror
Per No.

Skilled labour hrs 1.000 125.000


Bath room mirror Nos. 1.00 2,100.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P - 26
Supplying and Fixing of bib tap
Per No.

Skilled labour hrs 0.334 125.000


Unskill labour hrs 0.334 100.000
Bib tap Nos. 1.00 2,115.00
Brass faucet socket Nos. 1.00 100.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.

P- 27
Construction of 600 x600 mm manhole up to
600mm deep
Skilled labour hrs 8.000 125.000
Unskill labour hrs 20.000 100.000
Bricks 1000 Nos 0.26 7,500.00
Cement 50 kg 2.04 795.00
Sand Cum 0.29 1,590.11
Metal 25 mm Cum 0.17 3,886.93
Sub Total
Add P & O H
Rate per m

P- 28

Construction of 1000 x 700 mm manhole 600mm to 1200mm deep

Skilled labour hrs 12.000 125.000


Unskill labour hrs 32.000 100.000
Bricks 1000 Nos 0.50 7,500.00
Cement 50 kg 3.30 795.00
Sand Cum 0.49 1,590.11
Metal 25 mm Cum 0.29 3,886.93
Sub Total
Add P & O H
Rate per m

P - 29
Construction of 1000 x 700 mm manhole 1200mm to 1800mm deep

Skilled labour hrs 14.500 125.000


Unskill labour hrs 39.000 100.000
Labour cost per No
Bricks 1000 Nos 0.88 7,500.00
Cement 50 kg 4.85 795.00
Sand Cum 0.74 1,590.11
Metal 25 mm Cum 0.25 3,886.93
Sub Total
Add P & O H
Rate per m

Supplying and Fixing of bottle trap


Per No.

Skilled labour hrs 1.000 125.000


Bottle trap - plastic Nos. 1.00 630.00
Allow for other materials, transport etc.
Sub Total
Add P & O H
Rate per No.
60.00 60.00
41.33
3.00
104.33
28.17
132.50

60.00
60.00
103.94
3.00
166.94
45.07
212.02

60.00
60.00
163.28
3.00
226.28
61.10
287.38
75.00 75.00
220.57
30.00
325.57
87.90
413.48

75.00
304.46
10.00
389.46
105.16
494.62

85.00
85.00
516.03
20.00

621.03
167.68
788.71

85.00 85.00

931.40
100.00

1,116.40
301.43
1,417.83

160.00 160.00

1,046.80
100.00

1,306.80
352.84
1,659.64

160.00 160.00

1,550.97
100.00

1,810.97
488.96
2,299.93

160.00
160.00
649.00
10.00
819.00
221.13
1,040.13

68.75
55.00 123.75
247.50
10.00
381.25
102.94
484.19

87.50
70.00 157.50
415.80
100.00
673.30
181.79
855.09

68.75
55.00 123.75
621.50
100.00
845.25
228.22
1,073.47

68.75
55.00
649.00
10.00
782.75
211.34
994.09

250.00
250.00
1,903.00
10.00
2,163.00
584.01
2,747.01

50.00 0.400
40.00 90.00 0.400
170.65 1.10
30.00
290.65
58.13
348.78

75.00

214.43
50.00
339.43
67.89
407.32
85.00

349.48
75.00
509.48
137.56 662.32
647.04

85.00

649.03
75.00
809.03
218.44
1,027.47

160.00
742.50
100.00
1,002.50
360.90
1,363.40

200.00

1,283.70
100.00
1,583.70
427.60
2,011.30

225.00
180.00 405.00
1,284.64
214.66
262.37
524.73
270.19
10.00
2,971.60
594.32
3,565.92

225.00
180.00
2,633.13
50.00
3,088.13
833.79
3,921.92

Rocel - urban D
`
Per No.
1,000.00 Skill labour hrs 8.000 125.000
800.00 1,800.00 Unskill labour hrs 8.000 100.000
11,500.00 Wash basin with pedestal No. 1.00 7,400.00
- Tap Nos. 1.00 2,295.00
2,295.00
50.00 Allow for other expenses-- angle valve, Flexible hose
15,645.00 Sub Total
4,224.15 Add P & O H
19,869.15 Rate per No.
P - 12
Supplying & Fixing of Low Level Suit with cistern
Per No.

1,000.00 Skill labour hrs 8.000 125.000


800.00 1,800.00 Unskill labour hrs 8.000 100.000
700.00
27,750.00 Rocel Low level suit with cistern & Nos. 1.00 16,850.00
250.00 Allow for other expenses-- angle valve, Flexible hose
30,500.00 Sub Total
8,235.00 Add P & O H
38,735.00 Rate per No.

Vanity type basin


Johnsonswiss
Per No.

Skill labour hrs 8.000 125.000


Unskill labour hrs 8.000 100.000
1,000.00 Wash basin with pedestal No. 1.00 6,200.00
800.00 1,800.00 Tap Nos. 1.00 2,295.00
6,821.00
375.00 Allow for other expenses-- angle valve, Flexible hose
264.74 Sub Total
- Add P & O H
50.00 Rate per No.
9,310.74
2,513.90
11,824.63

200.00
1,395.00 American standard
40.00
1,635.00
441.45
2,076.45
500.00
400.00 900.00
1,100.00
40.00
2,040.00
550.80
2,590.80

Supplying and Fixing of stainless steel sink with tap


Per No.

Labour cost per No.


937.50 Skill labour hrs 7.500 125.000
750.00 1,687.50 Unskill labour hrs 7.500 100.000
4,250.00 Stainless steel sink - teka Nos. 1.00 22,000.00
2,750.00 Long neck tap Nos. 1.00 2,750.00
40.00 Allow for other materials, transport etc.
8,727.50 Flexible hose, angle valve
2,356.43
11,083.93

Sub Total
Add P & O H

Rate per No.

937.50
750.00
2,295.00
40.00
4,022.50
1,086.08
5,108.58

937.50
750.00
560.00
40.00
2,287.50
617.63
2,905.13

Labour 250
Bottle trap 2200
500.00 Flexible hose 500
Angle valve 1250
2,650.00 Taps 2100
2,070.00 6050
After qurry from Architect it was deleted 6957.5
200.00
5,420.00
1,463.40
6,883.40

350.00
350.00
7,840.00 johnson suisse

7,000.00
20.00
15,210.00
4,106.70
19,316.70 4174

62.50 100.00
50.00 112.50
750.00
20.00
820.00
221.40
1,041.40
62.50 100.00
50.00 112.50
510.00
20.00
580.00
156.60
736.60

125.00
100.00 225.00
1,400.00
20.00
1,645.00
444.15
2,089.15

125.00
100.00 225.00
1,950.00
20.00
2,195.00
592.65
2,787.65

125.00
100.00 225.00
2,150.00
20.00
2,395.00
646.65
3,041.65
125.00 125.00
1,665.00 American
20.00
1,810.00
488.70
2,298.70

200.00 200.00
2,100.00
20.00
2,320.00
626.40
2,946.40

41.75
33.40 75.15
2,115.00 American std

20.00
2,210.15
596.74
2,806.89

1,000.00
2,000.00 3,000.00
1,950.00
1,621.80
453.18
660.78
7,685.76
2,075.15
9,760.91

1,500.00
3,200.00 4,700.00
3,750.00
2,623.50
771.20
1,107.77
12,952.48
3,497.17
16,449.64

1,812.50
3,900.00 5,712.50

6,562.50
3,855.75
1,170.32
971.73
11,588.57
3,128.91
14,717.48

125.00 125.00
630.00
20.00
775.00
209.25
984.25
P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

125.000 50.00 Skill labour hrs 0.400 125.000


100.000 40.00 90.00 Unskill lab hrs 0.400 100.000
240.63 264.69 40mm dia. m 1.10 240.63
5.00 Allow for other expenses
359.69 Sub Total
97.12 Add P & O H
456.80 Rate per m
1,000.00
800.00 1,800.00
7,400.00
2,295.00
1,200.00
12,695.00
3,427.65
16,122.65

1,000.00
800.00 1,800.00

16,850.00 Rocel
1,200.00
19,850.00
5,359.50
25,209.50

1,000.00
800.00 1,800.00
6,200.00
2,295.00

1,200.00
11,495.00
3,103.65
14,598.65
937.50
750.00 1,687.50
22,000.00
2,750.00
40.00
1600

28,077.50
7,580.93

35,658.43
P - 04
ding trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

50.00 Skill labour hrs 0.400 125.000 50.00


40.00 90.00 Unskill lab hrs 0.400 100.000 40.00
264.69 40mm dia. m 1.10 240.63 264.69
5.00 Allow for other expenses 5.00
359.69 Sub Total 359.69
97.12 Add P & O H 97.12
456.80 Rate per m 456.80
P - 04
ing, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000 50.00


90.00 Unskill lab hrs 0.400 100.000 40.00 90.00
40mm dia. m 1.10 240.63 264.69
Allow for other expenses 5.00
Sub Total 359.69
Add P & O H 97.12
Rate per m 456.80
P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000 50.00


Unskill lab hrs 0.400 100.000 40.00 90.00
40mm dia. m 1.10 240.63 264.69
Allow for other expenses 5.00
Sub Total 359.69
Add P & O H 97.12
Rate per m 456.80
P - 04 P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC p
making good to walls making good to walls
Per m Per m

Skill labour hrs 0.400 125.000 50.00 Skill labour


Unskill lab hrs 0.400 100.000 40.00 90.00 Unskill lab
40mm dia. m 1.10 240.63 264.69 40mm dia.
Allow for other expenses 5.00 Allow for other expenses
Sub Total 359.69
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe includi
making good to walls making good to walls
Per m

hrs 0.400 125.000 50.00 Skill labour hrs


hrs 0.400 100.000 40.00 90.00 Unskill lab hrs
m 1.10 240.63 264.69 40mm dia. m
Allow for other expenses 5.00 Allow for other expenses
Sub Total 359.69 Sub Total
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
0mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenchin
ood to walls making good to walls
Per m

0.400 125.000 50.00 Skill labour hrs


0.400 100.000 40.00 90.00 Unskill lab hrs
1.10 240.63 264.69 40mm dia. m
other expenses 5.00 Allow for other expenses
359.69 Sub Total
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back fill
making good to walls
Per m

0.400 125.000 50.00 Skill labour hrs 0.400


0.400 100.000 40.00 90.00 Unskill lab hrs 0.400
1.10 240.63 264.69 40mm dia. m 1.10
5.00 Allow for other expenses
359.69 Sub Total
97.12 Add P & O H
456.80 Rate per m
P - 04
pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

125.000 50.00 Skill labour hrs 0.400 125.000


100.000 40.00 90.00 Unskill lab hrs 0.400 100.000
240.63 264.69 40mm dia. m 1.10 240.63
5.00 Allow for other expenses
359.69 Sub Total
97.12 Add P & O H
456.80 Rate per m
P - 04
ding trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

50.00 Skill labour hrs 0.400 125.000 50.00


40.00 90.00 Unskill lab hrs 0.400 100.000 40.00
264.69 40mm dia. m 1.10 240.63 264.69
5.00 Allow for other expenses 5.00
359.69 Sub Total 359.69
97.12 Add P & O H 97.12
456.80 Rate per m 456.80
P - 04
ing, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000 50.00


90.00 Unskill lab hrs 0.400 100.000 40.00 90.00
40mm dia. m 1.10 240.63 264.69
Allow for other expenses 5.00
Sub Total 359.69
Add P & O H 97.12
Rate per m 456.80
P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000 50.00


Unskill lab hrs 0.400 100.000 40.00 90.00
40mm dia. m 1.10 240.63 264.69
Allow for other expenses 5.00
Sub Total 359.69
Add P & O H 97.12
Rate per m 456.80
P - 04 P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC p
making good to walls making good to walls
Per m Per m

Skill labour hrs 0.400 125.000 50.00 Skill labour


Unskill lab hrs 0.400 100.000 40.00 90.00 Unskill lab
40mm dia. m 1.10 240.63 264.69 40mm dia.
Allow for other expenses 5.00 Allow for other expenses
Sub Total 359.69
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe includi
making good to walls making good to walls
Per m

hrs 0.400 125.000 50.00 Skill labour hrs


hrs 0.400 100.000 40.00 90.00 Unskill lab hrs
m 1.10 240.63 264.69 40mm dia. m
Allow for other expenses 5.00 Allow for other expenses
Sub Total 359.69 Sub Total
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
0mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenchin
ood to walls making good to walls
Per m

0.400 125.000 50.00 Skill labour hrs


0.400 100.000 40.00 90.00 Unskill lab hrs
1.10 240.63 264.69 40mm dia. m
other expenses 5.00 Allow for other expenses
359.69 Sub Total
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back fill
making good to walls
Per m

0.400 125.000 50.00 Skill labour hrs 0.400


0.400 100.000 40.00 90.00 Unskill lab hrs 0.400
1.10 240.63 264.69 40mm dia. m 1.10
5.00 Allow for other expenses
359.69 Sub Total
97.12 Add P & O H
456.80 Rate per m
P - 04
pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

125.000 50.00 Skill labour hrs 0.400 125.000


100.000 40.00 90.00 Unskill lab hrs 0.400 100.000
240.63 264.69 40mm dia. m 1.10 240.63
5.00 Allow for other expenses
359.69 Sub Total
97.12 Add P & O H
456.80 Rate per m
P - 04
ding trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

50.00 Skill labour hrs 0.400 125.000 50.00


40.00 90.00 Unskill lab hrs 0.400 100.000 40.00
264.69 40mm dia. m 1.10 240.63 264.69
5.00 Allow for other expenses 5.00
359.69 Sub Total 359.69
97.12 Add P & O H 97.12
456.80 Rate per m 456.80
P - 04
ing, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000 50.00


90.00 Unskill lab hrs 0.400 100.000 40.00 90.00
40mm dia. m 1.10 240.63 264.69
Allow for other expenses 5.00
Sub Total 359.69
Add P & O H 97.12
Rate per m 456.80
P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000 50.00


Unskill lab hrs 0.400 100.000 40.00 90.00
40mm dia. m 1.10 240.63 264.69
Allow for other expenses 5.00
Sub Total 359.69
Add P & O H 97.12
Rate per m 456.80
P - 04 P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC p
making good to walls making good to walls
Per m Per m

Skill labour hrs 0.400 125.000 50.00 Skill labour


Unskill lab hrs 0.400 100.000 40.00 90.00 Unskill lab
40mm dia. m 1.10 240.63 264.69 40mm dia.
Allow for other expenses 5.00 Allow for other expenses
Sub Total 359.69
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
Laying 40mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe includi
making good to walls making good to walls
Per m

hrs 0.400 125.000 50.00 Skill labour hrs


hrs 0.400 100.000 40.00 90.00 Unskill lab hrs
m 1.10 240.63 264.69 40mm dia. m
Allow for other expenses 5.00 Allow for other expenses
Sub Total 359.69 Sub Total
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
0mm ( type1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenchin
ood to walls making good to walls
Per m

0.400 125.000 50.00 Skill labour hrs


0.400 100.000 40.00 90.00 Unskill lab hrs
1.10 240.63 264.69 40mm dia. m
other expenses 5.00 Allow for other expenses
359.69 Sub Total
Add P & O H 97.12 Add P & O H
Rate per m 456.80 Rate per m
P - 04
1000) PVC pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back fill
making good to walls
Per m

0.400 125.000 50.00 Skill labour hrs 0.400


0.400 100.000 40.00 90.00 Unskill lab hrs 0.400
1.10 240.63 264.69 40mm dia. m 1.10
5.00 Allow for other expenses
359.69 Sub Total
97.12 Add P & O H
456.80 Rate per m
P - 04
pipe including trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

125.000 50.00 Skill labour hrs 0.400 125.000


100.000 40.00 90.00 Unskill lab hrs 0.400 100.000
240.63 264.69 40mm dia. m 1.10 240.63
5.00 Allow for other expenses
359.69 Sub Total
97.12 Add P & O H
456.80 Rate per m
P - 04
ding trenching, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

50.00 Skill labour hrs 0.400 125.000 50.00


40.00 90.00 Unskill lab hrs 0.400 100.000 40.00
264.69 40mm dia. m 1.10 240.63 264.69
5.00 Allow for other expenses 5.00
359.69 Sub Total 359.69
97.12 Add P & O H 97.12
456.80 Rate per m 456.80
P - 04
ing, back filling and Laying 40mm ( type1000) PVC pipe including trenching, back filling and
making good to walls
Per m

Skill labour hrs 0.400 125.000 50.00


90.00 Unskill lab hrs 0.400 100.000 40.00 90.00
40mm dia. m 1.10 240.63 264.69
Allow for other expenses 5.00
Sub Total 359.69
Add P & O H 97.12
Rate per m 456.80
Demolishing of existing buildings 03 days

Description Unit Qty Rate Amount


Rs. Cts. Rs. Cts.

Hire of machinaries
Backhoe loader Hrs 24.00 2118.00 50,832.00
3 cube tipper - 02 nos Hrs 48.00 2060.00 98,880.00

Labour
Skilled labour Days 6.00 1200.00 7,200.00
Unskilled labour -05 nos/03 days Days 15.00 800.00 12,000.00
Sub Total 168,912.00
Add over head and profit 27% 45,606.24
Total Amount 214,518.24
Reference

HSR-2011
BO- 116
BO-149
Annexure 1

You might also like