CUADRO RESUMEN DE AUDITORIO

VALORIZADO
COMPONENTES MONTO C.D. S/. MONTO P.T. S/.
MONTO C.D. S/. MONTO P.T. S/.
EXPEDIENTE TECNICO 1,285,191.63 1,468,974.04 472,791.86 540,401.10
ADICIONAL N 07 912,219.37 1,042,666.74 483,801.17 552,984.74
MAYORES METRADOS 565,266.27 646,099.35 246,807.69 282,101.19
PARTIDAS NUEVAS 346,953.10 396,567.39 236,993.49 270,883.55
DEDUCTIVO N 07 379,564.29 433,841.98
MENORES METRADOS 10,498.02 11,999.24 10,498.02
PARTIDAS NO EJECUTADAS 369,066.27 421,842.75 347,663.79
SUMATORIA EXP. TEC. + ADIC. ### ### #REF! #REF!
SUMATORIA DEDUC. 379,564.29 433,841.98
SUMATORIA EXP. TEC. - DEDUC. ### ### #REF! #REF!
VALORIZADO 956,593.03 ###
RESTANTE
MONTO C.D. S/. MONTO P.T. S/.
812,399.77 928,572.94
428,418.20 489,682.00
318,458.58 363,998.16
109,959.61 125,683.84

#REF! #REF!
#REF! #REF!
#REF! #REF!
Proyecto: Mejoramiento e Implementacin de la Infraestructura
Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui
Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegu
COMPONENTE : INFRAESTRUCTURA

SUB COMPONENTE : CONSTRUCCIN AUDITORIO

[AKSP]
la Infraestructura del
Carlos Mariategui" del
Regin Moquegua
ITORIO
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto,
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL : S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

A EXPEDIENTE TCNICO
02.00.00 OBRAS PRELIMINARES
02.04.00 LIMPIEZA DE TERRENO
02.04.04 ELIMINACION DE BASURA Y ELEMENTOS SUELTOS LIVIANOS M2 1,283.30 1,283.30
02.05.00 TRAZOS, NIVELES Y REPLANTEO
02.05.01 TRAZO Y REPLANTEO PRELIMINAR. M2 1,283.30 1,283.30
02.05.02 TRAZO DURANTE LA EJECUCION DE LA OBRA M2 1,283.30 0.00
03.00.00 MOVIMIENTO DE TIERRAS
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 533.31 264.27
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 59.67 59.67
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 55.01 0.00
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 647.99 0.00
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 81.65 0.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 165.75 165.75
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 50.81 0.00
04.03.00 BASE DE CONCRETO
04.03.01 CONCRETO f'c=100 kg/cm2 + 30% P.G. PARA BASE DE CONCRETO M2 86.48 82.84
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 99.18 99.18
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 100.49 0.00
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 16.83 0.00
04.05.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 163.29 52.28
04.08.00 FALSO PISO
04.08.01 FALSO PISO MEZCLA 1:8 e=4" M2 1,082.36 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 131.05 0.00
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 6,696.57 5,736.86
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 20.68 0.00
05.02.02 VIGAS DE CIMENTACION ENCOFRADO Y DESENCOFRADO M2 165.46 156.18
05.02.03 VIGAS DE CIMENTACION ACERO fy= 4200kg/cm2 KG 1,803.96 1,803.96
05.03.00 SOBRECIMIENTO ARMADO
05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 141.01 0.00
05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 13.18 0.00
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 105.43 67.45
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 2,245.71 943.04
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 72.53 0.00
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 658.79 376.23
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 9,692.81 9,692.81
05.06.00 COLUMNAS

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto,
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL : S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

05.06.01 CONCRETO EN COLUMNETAS DE ARRIOSTRE f'c=175 kg/cm2 M3 4.08 0.00


05.06.02 COLUMNAS, CONCRETO f'c= 210kg/cm2 M3 36.63 0.00
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 359.11 288.74
05.06.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO CARAVISTA M2 114.72 34.16
05.06.05 COLUMNAS, ACERO fy=4200 kg/cm2 KG 5,583.97 5,583.97
05.07.00 VIGAS
05.07.02 VIGAS, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 70.04 0.00
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 543.17 162.62
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 12,224.59 6,012.86
05.08.00 LOSAS
05.08.01 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 M3 37.41 0.00
05.08.02 LOSAS MACIZAS, ENCOFRADO Y DESENCOFRADO M2 187.06 0.00
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 3,912.31 1,607.15
05.08.04 LOSA ALIGERADA, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 14.71 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 168.64 168.64
05.08.06 LOSA ALIGERADA, ACERO fy= 4200kg/cm2 KG 2,401.40 1,656.86
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 1,404.77 1,404.77
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.06.00 ARMADURA PRINCIPAL VMP-01 (AUDITORIO) INC/ PINTADO Y COLOCADO PZA 8.00 0.00
06.10.00 COBERTURA METALICA VL-1 (EN AUDITORIO LOBBY) PZA 14.00 0.00
06.20.00 CORREA VL-02 (EN AUDITORIO LOBBY) INC. PINTADO Y COLOCADO PZA 52.00 0.00
06.21.00 COBERTURA METALICA EN INGRESO DE AUDITORIO PZA 1.00 0.00
06.23.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR 6 mm M2 123.33 0.00
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 416.07 328.93
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 588.13 247.07
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 208.16 0.00
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 2,036.62 92.51
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 1,387.62 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 167.03 4.35
08.05.00 TARRAJEO DE VIGAS M2 352.97 1.31
08.08.00 VESTIDURA DE DERRAMES (1:5) ML 908.20 10.55
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 527.13 13.62
09.02.00 VESTIDURA EN FONDO DE ESCALERAS M2 125.68 0.00
09.03.00 CIELO RASO DE CELOTEX (0.60 x 0.60) M2 562.56 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 634.97 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 135.13 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 66.15 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 1,465.23 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 61.06 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 368.84 0.00
10.08.00 PISO DE MADERA MACHIHEMBRADO M2 106.31 0.00
10.09.00 PISO DE PORCELANATO M2 143.82 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 610.69 0.00

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto,
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL : S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 183.32 0.00
11.02.00 CONTRAZOCALO DE PORCELANATO ML 61.48 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 204.77 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 107.15 0.00
12.04.00 ZOCALO DE PIEDRA LAJA ML 118.77 0.00
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 16.61 0.00
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 16.61 0.00
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2 407.64 0.00
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 407.64 0.00
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M 307.51 0.00
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 18.62 0.00
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X3" M2 39.16 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.01.00 PUERTA METALICA TERMOACUSTICA ANTIPANICO DE EMERGENCIA UND 3.78 0.00
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 25.13 0.00
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 12.96 0.00
16.13.00 MAMPARA DE ALUMINO M2 14.08 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 16.94 0.00
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 201.75 0.00
17.00.00 CERRAJERIA
17.02.00 BISAGRA CAPUCHINA DE ALUMINIO DE 3" X 3" PZA 87.00 0.00
17.04.00 CERRADURA DOS GOLPES EN PUERTAS PZA 9.00 0.00
17.05.00 CERRADURA PARA INTERIOR DOBLE PERILLA PZA 9.00 0.00
17.06.00 CERRADURA DE POMO PARA MAMPARA DE INGRESO PZA 2.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/ACCESOR P2 270.65 0.00
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 151.64 0.00
18.05.00 VIDRIOS BLOK INCOLORO P2 190.63 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 652.81 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 2,819.98 0.00
19.04.00 PINTURA SUPER MATE 2 MANOS EN MUROS EXT. A PARTIR DEL 2DO PISO M2 1,387.62 0.00
19.07.00 PINTURA BARNIZ 2 MANOS EN CARPINTERIA DE MADERA M2 18.62 0.00
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 45.07 0.00
20.07.00 LIMPIEZA FINAL DE LA OBRA M2 18.62 0.00
B EXPEDIENTE ADICIONAL N 07 MAYORES METRADOS - PARTIDAS NUEVAS
MAYORES METRADOS
03.00.00 MOVIMIENTO DE TIERRAS
03.03.00 CORTE DE TERRENO A MAQUINARIA M3 795.00 795.00
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 87.68 17.84
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 66.20 53.99

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto,
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL : S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 0.90 0.70


03.13.00 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES M3 1,043.60 349.00
03.16.00 ACARREO DE MATERIAL DE CORTE CON MAQUINARIA M3 210.00 210.00
03.20.00 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 1,628.60 870.00
03.24.00 RELLENO MANUAL Y COMPACTADO CON EQUIPO MATERIAL PROPIO M3 2,060.44 252.23
03.25.00 PREPARACION DE MATERIAL DE RELLENO - MATERIAL PROPIO M3 275.00 275.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 92.11 92.11
04.03.00 BASE DE CONCRETO
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 11.98 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 78.14 0.72
05.01.05 ZAPATAS, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 148.72 148.72
05.02.00 VIGAS DE CIMENTACION
05.02.04 VIGAS DE CIMENTACION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 20.68 16.53
05.04.00 MUROS DE CONTENCION
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 388.75 197.50
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 457.06 457.06
05.04.07 MUROS DE CONTENCION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 59.66 59.66
05.05.00 PLACAS
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 52.49 36.04
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 756.83 756.83
05.05.04 PLACAS, CONCRETO f'c=210 KG/CM2 CON ADITIVO M3 76.32 49.57
05.06.00 COLUMNAS
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 29.90 5.20
05.06.06 CONCRETO EN COLUMNETAS DE ARRIOSTRE, F'c= 175 KG/CM2 CON ADITIVO M3 6.76 5.03
05.06.07 COLUMNAS, CONCRETO F'c=210 KG/CM2 CON ADITIVO M3 40.96 28.33
05.07.00 VIGAS
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 77.78 6.21
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 1,442.88 155.10
05.07.05 VIGAS, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 92.89 47.69
05.07.06 CONCRETO EN VIGUETAS DE ARRIOSTRE F'c=175 KG/CM2 CON ADITIVO M3 1.97 0.00
05.08.00 LOSAS
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 119.99 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 11.67 11.67
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 104.00 100.00
05.08.08 LOSA ALIGERADA, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 15.89 15.89
05.08.09 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 CON ADITIVO M3 37.41 19.11
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 108.69 7.77
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 30.02 18.43
07.05.00 TABIQUERIA SISTEMA DRIWALL M2 5.04 0.00
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 35.89 0.00
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 138.47 109.94

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto,
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL : S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 52.49 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 52.35 0.00
08.05.00 TARRAJEO DE VIGAS M2 50.19 0.00
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 160.59 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 30.62 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 13.60 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 32.37 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 50.71 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 24.31 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 194.51 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 39.74 0.00
10.13.00 CONTRAPISO f'c = 140 KG/CM2 E=5 cm PARA BASE DE COLOCACION DE ADOQUINES M2 98.52 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 74.85 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 4.31 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 20.97 0.00
15.00.00 CARPINTERIA DE MADERA
15.14.00 PUERTA CON TABLERO REBAJADO, C/ACABADO M2 20.30 0.00
15.20.00 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM INC./MARCO CEDRO 2"x3"C/ ACABADO Y M2 41.68 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 0.54 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 1.50 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.13.00 VIDRIO SISTEMA MODUGLAS TEMPLADO INCOLORO DE 6 MM, INC./ COLOCADO Y ACCESOR P2 276.42 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 210.77 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 104.84 0.00
19.16.00 EMPASTADO DE SUPERFICIE M2 5,176.03 0.00
20.00.00 VARIOS
20.12.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 2" ML 27.80 0.00
20.13.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 1" ML 72.80 0.00
PARTIDAS NUEVAS
03.00.00 MOVIMIENTO DE TIERRAS
03.39.00 COMPACTADO Y PERFILADO EN ZONA DE EXCAVACION C/ EQUIPO M2 307.45 216.56
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUB ZAPATAS
04.02.03 SUB ZAPATA CONCRETO F'C= 140 KG/CM2 + 30% P.G. CON ADITIVO M3 67.30 46.10
04.04.00 CIMIENTOS CORRIDOS
04.04.05 CONCRETO 140 KG/CM2 +30% PG. EN CIMIENTO CORRIDO CON ADITIVO M3 100.49 41.03
04.05.00 SOBRECIMIENTOS
04.05.03 SOBRECIMIENTO, CONCRETO 140 KG/CM2 CON ADITIVO M3 16.83 4.51
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.36.00 COBERTURA METALICA EN TERRAZA DE AUDITORIO M2 108.94 8.20
06.37.00 COBERTURA METALICA SOBRE RAMPA DE AUDITORIO M2 138.85 0.00

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto,
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL : S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

06.38.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR E=8.00 MM M2 116.29 0.00


06.39.00 TECHO DE AUDITORIO CON PLANCHA TERMOACUSTICA CINDULIT 180 INC./SUMINISTRO E I GLB 1.00 0.00
06.40.00 ESTRUCTURA METALICA PARA TECHO DE AUDITORIO INC./ SUMINISTRO E INSTALACION GLB 1.00 0.00
15.00.00 CARPINTERIA DE MADERA
15.25.00 REVESTIMIENTO CON MADERA ESTRUCUTRAL EN MADERA Y DESCANSO M2 8.57 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.65.00 PASAMANO METALICO INC./ COLOCADO Y PINTADO ML 19.20 0.00
16.66.00 BARANDA METALICA INC./ COLOCADO Y PINTADO ML 188.84 0.00
16.67.00 CLARABOYA DE TUBO METALICO M2 7.35 0.00
16.68.00 ESTRUCTURA EN ESCALERA Y DESCANSO TERRAZA DE AUDITORIO (SEGN DISEO) GLB 1.00 0.00
16.69.00 ESCALERA TIPO GATO CON TAPA METALICA GLB 1.00 0.00
16.70.00 REJILLA METALICA PARA EVACIANDION DE AGUAS FLUVIALES ML 24.28 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.20.00 MAMPARA DE ALUMINIO CON VIDRIO TEMPLADO PAVONADO DE 10.00 MM M2 14.08 0.00
22.00.00 INSTALACIONES ELECTRICAS
22.03.00 SALIDAS PARA TOMACORRIENTES
22.03.06 SALIDA PARA TOMACORRIENTE TRIPLE PARA ADOSAR Pto 13.00 0.00
22.12.00 ARTEFACTOS DE ALUMBRADO
22.12.26 ARTEFACTO P/ ADOSAR DE 2 LAMPARAS FLUORECENTES DE 2x40w UND 5.00 0.00
C EXPEDIENTE DEDUCTIVO N 07 MENORES METRADOS - PARTIDAS NO EJECUTADAS
MENORES METRADOS
05.00.00 OBRAS DE CONCRETO ARMADO
05.06.00 COLUMNAS
05.06.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO CARAVISTA M2
05.08.00 LOSAS
05.08.06 LOSA ALIGERADA, ACERO fy= 4200kg/cm2 KG
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M
PARTIDAS NO EJECUTADAS
03.00.00 MOVIMIENTO DE TIERRAS
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 647.99 0.00
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 81.65 0.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 50.81 0.00
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 100.49 0.00
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 16.83 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 128.65 0.00
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 20.68 0.00
05.03.00 SOBRECIMIENTO ARMADO

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto,
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL : S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 141.01 0.00


05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 13.18 0.00
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 72.53 0.00
05.06.00 COLUMNAS
05.06.01 CONCRETO EN COLUMNETAS DE ARRIOSTRE f'c=175 kg/cm2 M3 4.08 0.00
05.06.02 COLUMNAS, CONCRETO f'c= 210kg/cm2 M3 36.63 0.00
05.07.00 VIGAS
05.07.01 CONCRETO EN VIGUETAS DE ARRIOSTRE f'c=175 KG/CM2 M3 70.04 0.00
05.08.00 LOSAS
05.08.01 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 M3 37.41 0.00
05.08.04 LOSA ALIGERADA, CONCRETO f'c=210 KG/CM2 (2 PISOS) M3 14.71 0.00
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.06.00 ARMADURA PRINCIPAL VMP-01 (AUDITORIO) INC/ PINTADO Y COLOCADO PZA 8.00 0.00
06.10.00 COBERTURA METALICA VL-1 (EN AUDITORIO LOBBY) PZA 14.00 0.00
06.20.00 CORREA VL-02 (EN AUDITORIO LOBBY) INC. PINTADO Y COLOCADO PZA 52.00 0.00
06.21.00 COBERTURA METALICA EN INGRESO DE AUDITORIO PZA 1.00 0.00
06.23.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR 6 mm M2 123.33 0.00
10.00.00 PISOS Y PAVIMENTOS
10.09.00 PISO DE PORCELANATO M2 143.82 0.00
11.00.00 CONTRAZOCALOS
11.02.00 CONTRAZOCALO DE PORCELANATO ML 61.48 0.00
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 16.61 0.00
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 16.61 0.00
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 18.62 0.00
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X3" M2 39.16 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 25.13 0.00
16.13.00 MAMPARA DE ALUMINO M2 14.08 0.00
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 201.75 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/ACCESOR P2 270.65 0.00
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 151.64 0.00
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 45.07 0.00

[AKSP]
XPEDIENTE DE ADICIONALES

Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2013

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

0.00

0.00
1,283.30

269.04
0.00
55.01
647.99
81.65

0.00

50.81

3.64
0.00

100.49

16.83
111.01

1,082.36

131.05
959.71

20.68
9.28
0.00

141.01

13.18
37.98
1,302.67

72.53
282.56
0.00

[AKSP]
XPEDIENTE DE ADICIONALES

Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2013

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

4.08
36.63
70.37
80.56
0.00

70.04
380.55
6,211.73

37.41
187.06
2,305.16
14.71
0.00
744.54
0.00

8.00
14.00
52.00
1.00
123.33

87.14
341.06

208.16
1,944.11
1,387.62
162.68
351.66
897.65

513.51
125.68
562.56

634.97
135.13
66.15
1,465.23
61.06
368.84
106.31
143.82
610.69

[AKSP]
XPEDIENTE DE ADICIONALES

Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2013

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

183.32
61.48
204.77

107.15
118.77

16.61
16.61

407.64
407.64
307.51

18.62
39.16

3.78
25.13
12.96
14.08
16.94
201.75

87.00
9.00
9.00
2.00

270.65
151.64
190.63

652.81
2,819.98
1,387.62
18.62

45.07
18.62

0.00
69.84
12.21

[AKSP]
XPEDIENTE DE ADICIONALES

Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2013

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

0.20
694.60
0.00
758.60
1,808.21
0.00

0.00

11.98

77.42
0.00

4.15

191.25
0.00
0.00

16.45
0.00
26.75

24.70
1.73
12.63

71.57
1,287.78
45.20
1.97

119.99
0.00
4.00
0.00
18.30

100.92
11.59
5.04

35.89
28.53

[AKSP]
XPEDIENTE DE ADICIONALES

Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2013

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

52.49
52.35
50.19

160.59

30.62
13.60
32.37
50.71
24.31
194.51
39.74
98.52

74.85
4.31

20.97

20.30
41.68

0.54
1.50

276.42

210.77
104.84
5,176.03

27.80
72.80

90.89

21.20

59.46

12.32

100.74
138.85

[AKSP]
XPEDIENTE DE ADICIONALES

Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2013

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

116.29
1.00
1.00

8.57

19.20
188.84
7.35
1.00
1.00
24.28

14.08

13.00

5.00

18.62

558.96

158.79
158.79
96.81

647.99
81.65

50.81

100.49

16.83

128.65

20.68

[AKSP]
XPEDIENTE DE ADICIONALES

Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2013

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

141.01

13.18

72.53

4.08
36.63

70.04

37.41
14.71

8.00
14.00
52.00
1.00
123.33

143.82

61.48

16.61
16.61

18.62
39.16

25.13
14.08
201.75

270.65
151.64

45.07

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
A EXPEDIENTE TCNICO
02.00.00 OBRAS PRELIMINARES
02.04.00 LIMPIEZA DE TERRENO
02.04.04 ELIMINACION DE BASURA Y ELEMENTOS SUELTOS LIVIANOS M2 1,283.30 1.36 1,745.29 1,283.30 1,745.29
02.05.00 TRAZOS, NIVELES Y REPLANTEO
02.05.01 TRAZO Y REPLANTEO PRELIMINAR. M2 1,283.30 1.87 2,399.77 1,283.30 2,399.77
02.05.02 TRAZO DURANTE LA EJECUCION DE LA OBRA M2 1,283.30 1.08 1,385.96 0.00 0.00
03.00.00 MOVIMIENTO DE TIERRAS
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 533.31 33.87 18,063.21 264.27 8,950.82
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 59.67 29.03 1,732.22 59.67 1,732.22
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 55.01 25.40 1,397.25 0.00 0.00
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 647.99 20.15 13,057.00 0.00 0.00
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 81.65 45.35 3,702.83 0.00 0.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 165.75 26.58 4,405.64 165.75 4,405.64
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 50.81 222.65 11,312.85 0.00 0.00
04.03.00 BASE DE CONCRETO
04.03.01 CONCRETO f'c=100 kg/cm2 + 30% P.G. PARA BASE DE CONCRETO M2 86.48 27.61 2,387.71 82.84 2,287.21
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 99.18 33.45 3,317.57 99.18 3,317.57
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 100.49 167.28 16,809.97 0.00 0.00
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 16.83 235.26 3,959.43 0.00 0.00
04.05.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 163.29 33.95 5,543.70 52.28 1,774.91
04.08.00 FALSO PISO

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
04.08.01 FALSO PISO MEZCLA 1:8 e=4" M2 1,082.36 26.63 28,823.25 0.00 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 131.05 299.23 39,214.09 0.00 0.00
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 6,696.57 4.33 28,996.15 5,736.86 24,840.60
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 20.68 311.23 6,436.24 0.00 0.00
05.02.02 VIGAS DE CIMENTACION ENCOFRADO Y DESENCOFRADO M2 165.46 45.77 7,573.10 156.18 7,148.36
05.02.03 VIGAS DE CIMENTACION ACERO fy= 4200kg/cm2 KG 1,803.96 4.33 7,811.15 1,803.96 7,811.15
05.03.00 SOBRECIMIENTO ARMADO
05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 141.01 4.33 610.57 0.00 0.00
05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 13.18 271.09 3,572.97 0.00 0.00
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 105.43 43.52 4,588.31 67.45 2,935.42
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 2,245.71 4.33 9,723.92 943.04 4,083.36
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 72.53 425.28 30,845.56 0.00 0.00
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 658.79 46.38 30,554.68 376.23 17,449.55
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 9,692.81 4.33 41,969.87 9,692.81 41,969.87
05.06.00 COLUMNAS
05.06.01 CONCRETO EN COLUMNETAS DE ARRIOSTRE f'c=175 kg/cm2 M3 4.08 395.44 1,613.40 0.00 0.00
05.06.02 COLUMNAS, CONCRETO f'c= 210kg/cm2 M3 36.63 436.79 15,999.62 0.00 0.00
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 359.11 50.14 18,005.78 288.74 14,477.42
05.06.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO CARAVISTA M2 114.72 70.35 8,070.55 34.16 2,403.16
05.06.05 COLUMNAS, ACERO fy=4200 kg/cm2 KG 5,583.97 4.33 24,178.59 5,583.97 24,178.59
05.07.00 VIGAS
05.07.02 VIGAS, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 70.04 338.49 23,707.84 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 543.17 54.75 29,738.56 162.62 8,903.45
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 12,224.59 4.33 52,932.47 6,012.86 26,035.68
05.08.00 LOSAS
05.08.01 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 M3 37.41 305.22 11,418.28 0.00 0.00
05.08.02 LOSAS MACIZAS, ENCOFRADO Y DESENCOFRADO M2 187.06 43.15 8,071.64 0.00 0.00
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 3,912.31 4.33 16,940.30 1,607.15 6,958.96
05.08.04 LOSA ALIGERADA, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 14.71 333.88 4,911.37 0.00 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 168.64 38.61 6,511.19 168.64 6,511.19
05.08.06 LOSA ALIGERADA, ACERO fy= 4200kg/cm2 KG 2,401.40 4.33 10,398.06 1,656.86 7,174.20
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 1,404.77 4.09 5,745.51 1,404.77 5,745.51
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.06.00 ARMADURA PRINCIPAL VMP-01 (AUDITORIO) INC/ PINTADO Y COLOCADO PZA 8.00 10,230.68 81,845.44 0.00 0.00
06.10.00 COBERTURA METALICA VL-1 (EN AUDITORIO LOBBY) PZA 14.00 1,362.22 19,071.08 0.00 0.00
06.20.00 CORREA VL-02 (EN AUDITORIO LOBBY) INC. PINTADO Y COLOCADO PZA 52.00 377.97 19,654.44 0.00 0.00
06.21.00 COBERTURA METALICA EN INGRESO DE AUDITORIO PZA 1.00 3,482.84 3,482.84 0.00 0.00
06.23.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR 6 mm M2 123.33 37.53 4,628.57 0.00 0.00
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 416.07 123.91 51,555.23 328.93 40,757.72
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 588.13 78.98 46,450.51 247.07 19,513.59
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 208.16 19.51 4,061.20 0.00 0.00
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 2,036.62 21.84 44,479.78 92.51 2,020.42
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 1,387.62 29.33 40,698.89 0.00 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 167.03 30.56 5,104.44 4.35 132.94
08.05.00 TARRAJEO DE VIGAS M2 352.97 42.73 15,082.41 1.31 55.98
08.08.00 VESTIDURA DE DERRAMES (1:5) ML 908.20 11.01 9,999.28 10.55 116.16
09.00.00 CIELORRASOS

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 527.13 30.01 15,819.17 13.62 408.74
09.02.00 VESTIDURA EN FONDO DE ESCALERAS M2 125.68 30.92 3,886.03 0.00 0.00
09.03.00 CIELO RASO DE CELOTEX (0.60 x 0.60) M2 562.56 140.96 79,298.46 0.00 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 634.97 26.40 16,763.21 0.00 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 135.13 21.44 2,897.19 0.00 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 66.15 56.03 3,706.38 0.00 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 1,465.23 27.11 39,722.39 0.00 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 61.06 49.18 3,002.93 0.00 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 368.84 50.10 18,478.88 0.00 0.00
10.08.00 PISO DE MADERA MACHIHEMBRADO M2 106.31 74.53 7,923.28 0.00 0.00
10.09.00 PISO DE PORCELANATO M2 143.82 56.24 8,088.44 0.00 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 610.69 24.66 15,059.62 0.00 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 183.32 15.45 2,832.29 0.00 0.00
11.02.00 CONTRAZOCALO DE PORCELANATO ML 61.48 40.25 2,474.57 0.00 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 204.77 15.67 3,208.75 0.00 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 107.15 51.17 5,482.87 0.00 0.00
12.04.00 ZOCALO DE PIEDRA LAJA ML 118.77 62.52 7,425.50 0.00 0.00
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 16.61 44.53 739.64 0.00 0.00
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 16.61 25.20 418.57 0.00 0.00
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2 407.64 34.52 14,071.73 0.00 0.00
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 407.64 5.51 2,246.10 0.00 0.00
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M 307.51 4.25 1,306.92 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 18.62 308.51 5,744.46 0.00 0.00
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X3" M2 39.16 228.28 8,939.44 0.00 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.01.00 PUERTA METALICA TERMOACUSTICA ANTIPANICO DE EMERGENCIA UND 3.78 1,729.93 6,539.14 0.00 0.00
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 25.13 100.74 2,531.60 0.00 0.00
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 12.96 261.01 3,382.69 0.00 0.00
16.13.00 MAMPARA DE ALUMINO M2 14.08 267.27 3,763.16 0.00 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 16.94 247.82 4,198.07 0.00 0.00
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 201.75 80.12 16,164.21 0.00 0.00
17.00.00 CERRAJERIA
17.02.00 BISAGRA CAPUCHINA DE ALUMINIO DE 3" X 3" PZA 87.00 13.46 1,171.02 0.00 0.00
17.04.00 CERRADURA DOS GOLPES EN PUERTAS PZA 9.00 60.70 546.30 0.00 0.00
17.05.00 CERRADURA PARA INTERIOR DOBLE PERILLA PZA 9.00 47.70 429.30 0.00 0.00
17.06.00 CERRADURA DE POMO PARA MAMPARA DE INGRESO PZA 2.00 80.70 161.40 0.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/AC P2 270.65 19.01 5,145.06 0.00 0.00
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 151.64 8.82 1,337.46 0.00 0.00
18.05.00 VIDRIOS BLOK INCOLORO P2 190.63 30.95 5,900.00 0.00 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 652.81 8.14 5,313.87 0.00 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 2,819.98 8.14 22,954.64 0.00 0.00
19.04.00 PINTURA SUPER MATE 2 MANOS EN MUROS EXT. A PARTIR DEL 2DO PISO M2 1,387.62 13.42 18,621.86 0.00 0.00
19.07.00 PINTURA BARNIZ 2 MANOS EN CARPINTERIA DE MADERA M2 18.62 15.30 284.89 0.00 0.00
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 45.07 19.72 888.78 0.00 0.00
20.07.00 LIMPIEZA FINAL DE LA OBRA M2 18.62 1.28 23.83 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
SUB TOTAL 1,285,191.63 298,245.43 0.00 0.00
B EXPEDIENTE ADICIONAL N 07 MAYORES METRADOS - PARTIDAS NUEVAS
MAYORES METRADOS
03.00.00 MOVIMIENTO DE TIERRAS
03.03.00 CORTE DE TERRENO A MAQUINARIA M3 795.00 4.72 3,752.40 795.00 3,752.40
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 87.68 33.87 2,969.72 17.84 604.24
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 66.20 29.03 1,921.79 53.99 1,567.33
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 0.90 25.40 22.86 0.70 17.78
03.13.00 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES M3 1,043.60 16.94 17,678.58 349.00 5,912.06
03.16.00 ACARREO DE MATERIAL DE CORTE CON MAQUINARIA M3 210.00 6.48 1,360.80 210.00 1,360.80
03.20.00 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 1,628.60 15.60 25,406.16 870.00 13,572.00
03.24.00 RELLENO MANUAL Y COMPACTADO CON EQUIPO MATERIAL PROPIO M3 2,060.44 62.73 129,251.40 252.23 15,822.39
03.25.00 PREPARACION DE MATERIAL DE RELLENO - MATERIAL PROPIO M3 275.00 17.11 4,705.25 275.00 4,705.25
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 92.11 26.58 2,448.28 92.11 2,448.28
04.03.00 BASE DE CONCRETO
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 11.98 33.45 400.73 0.00 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 78.14 4.33 338.35 0.72 3.12
05.01.05 ZAPATAS, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 148.72 293.09 43,588.34 148.72 43,588.34
05.02.00 VIGAS DE CIMENTACION
05.02.04 VIGAS DE CIMENTACION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 20.68 306.99 6,348.55 16.53 5,074.54
05.04.00 MUROS DE CONTENCION
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 388.75 43.52 16,918.40 197.50 8,595.20
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 457.06 4.33 1,979.07 457.06 1,979.07

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
05.04.07 MUROS DE CONTENCION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 59.66 320.48 19,119.84 59.66 19,119.84
05.05.00 PLACAS
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 52.49 46.38 2,434.49 36.04 1,671.54
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 756.83 4.33 3,277.07 756.83 3,277.07
05.05.04 PLACAS, CONCRETO f'c=210 KG/CM2 CON ADITIVO M3 76.32 407.24 31,080.56 49.57 20,186.89
05.06.00 COLUMNAS
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 29.90 50.14 1,499.19 5.20 260.73
05.06.06 CONCRETO EN COLUMNETAS DE ARRIOSTRE, F'c= 175 KG/CM2 CON ADITIVO M3 6.76 378.76 2,560.42 5.03 1,905.16
05.06.07 COLUMNAS, CONCRETO F'c=210 KG/CM2 CON ADITIVO M3 40.96 416.55 17,061.89 28.33 11,800.86
05.07.00 VIGAS
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 77.78 54.75 4,258.46 6.21 340.00
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 1,442.88 4.33 6,247.67 155.10 671.58
05.07.05 VIGAS, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 92.89 332.18 30,856.20 47.69 15,841.66
05.07.06 CONCRETO EN VIGUETAS DE ARRIOSTRE F'c=175 KG/CM2 CON ADITIVO M3 1.97 312.84 616.29 0.00 0.00
05.08.00 LOSAS
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 119.99 4.33 519.56 0.00 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 11.67 38.61 450.58 11.67 450.58
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 104.00 4.09 425.36 100.00 409.00
05.08.08 LOSA ALIGERADA, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 15.89 330.39 5,249.90 15.89 5,249.90
05.08.09 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 CON ADITIVO M3 37.41 300.43 11,239.09 19.11 5,741.22
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 108.69 123.91 13,467.78 7.77 962.78
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 30.02 78.98 2,370.98 18.43 1,455.60
07.05.00 TABIQUERIA SISTEMA DRIWALL M2 5.04 221.97 1,118.73 0.00 0.00
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 35.89 19.51 700.21 0.00 0.00
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 138.47 21.84 3,024.22 109.94 2,401.09

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 52.49 29.33 1,539.42 0.00 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 52.35 30.56 1,599.96 0.00 0.00
08.05.00 TARRAJEO DE VIGAS M2 50.19 42.73 2,144.53 0.00 0.00
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 160.59 30.01 4,819.16 0.00 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 30.62 26.40 808.37 0.00 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 13.60 21.44 291.67 0.00 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 32.37 56.03 1,813.69 0.00 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 50.71 27.11 1,374.75 0.00 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 24.31 49.18 1,195.66 0.00 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 194.51 50.10 9,745.05 0.00 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 39.74 24.66 979.99 0.00 0.00
10.13.00 CONTRAPISO f'c = 140 KG/CM2 E=5 cm PARA BASE DE COLOCACION DE ADOQUINES M2 98.52 396.62 39,076.67 0.00 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 74.85 15.45 1,156.43 0.00 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 4.31 15.67 67.54 0.00 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 20.97 51.17 1,073.03 0.00 0.00
15.00.00 CARPINTERIA DE MADERA
15.14.00 PUERTA CON TABLERO REBAJADO, C/ACABADO M2 20.30 650.38 13,202.71 0.00 0.00
15.20.00 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM INC./MARCO CEDRO 2"x3"C/ ACABA M2 41.68 355.14 14,802.24 0.00 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 0.54 261.01 140.95 0.00 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 1.50 247.82 371.73 0.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.13.00 VIDRIO SISTEMA MODUGLAS TEMPLADO INCOLORO DE 6 MM, INC./ COLOCADO Y AC P2 276.42 33.50 9,260.07 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 210.77 8.14 1,715.69 0.00 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 104.84 8.14 853.41 0.00 0.00
19.16.00 EMPASTADO DE SUPERFICIE M2 5,176.03 7.58 39,234.27 0.00 0.00
20.00.00 VARIOS
20.12.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 2" ML 27.80 18.49 514.02 0.00 0.00
20.13.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 1" ML 72.80 11.21 816.09 0.00 0.00
PARTIDAS NUEVAS
03.00.00 MOVIMIENTO DE TIERRAS
03.39.00 COMPACTADO Y PERFILADO EN ZONA DE EXCAVACION C/ EQUIPO M2 307.45 10.79 3,317.43 216.56 2,336.68
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUB ZAPATAS
04.02.03 SUB ZAPATA CONCRETO F'C= 140 KG/CM2 + 30% P.G. CON ADITIVO M3 67.30 279.27 18,794.87 46.10 12,874.35
04.04.00 CIMIENTOS CORRIDOS
04.04.05 CONCRETO 140 KG/CM2 +30% PG. EN CIMIENTO CORRIDO CON ADITIVO M3 100.49 232.44 23,357.90 41.03 9,537.01
04.05.00 SOBRECIMIENTOS
04.05.03 SOBRECIMIENTO, CONCRETO 140 KG/CM2 CON ADITIVO M3 16.83 265.99 4,476.61 4.51 1,199.61
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.36.00 COBERTURA METALICA EN TERRAZA DE AUDITORIO M2 108.94 127.54 13,893.89 8.20 1,045.83
06.37.00 COBERTURA METALICA SOBRE RAMPA DE AUDITORIO M2 138.85 155.41 21,578.68 0.00 0.00
06.38.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR E=8.00 MM M2 116.29 86.71 10,083.51 0.00 0.00
06.39.00 TECHO DE AUDITORIO CON PLANCHA TERMOACUSTICA CINDULIT 180 INC./SUMINISTR GLB 1.00 60,000.00 60,000.00 0.00 0.00
06.40.00 ESTRUCTURA METALICA PARA TECHO DE AUDITORIO INC./ SUMINISTRO E INSTALACI GLB 1.00 ### 150,000.00 0.00 0.00
15.00.00 CARPINTERIA DE MADERA
15.25.00 REVESTIMIENTO CON MADERA ESTRUCUTRAL EN MADERA Y DESCANSO M2 8.57 122.61 1,050.31 0.00 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.65.00 PASAMANO METALICO INC./ COLOCADO Y PINTADO ML 19.20 50.78 974.98 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios 859273.76
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN MEDIANTE RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
16.66.00 BARANDA METALICA INC./ COLOCADO Y PINTADO ML 188.84 89.87 16,971.05 0.00 0.00
16.67.00 CLARABOYA DE TUBO METALICO M2 7.35 163.70 1,203.20 0.00 0.00
16.68.00 ESTRUCTURA EN ESCALERA Y DESCANSO TERRAZA DE AUDITORIO (SEGN DISEO) GLB 1.00 7,180.94 7,180.94 0.00 0.00
16.69.00 ESCALERA TIPO GATO CON TAPA METALICA GLB 1.00 2,595.77 2,595.77 0.00 0.00
16.70.00 REJILLA METALICA PARA EVACIANDION DE AGUAS FLUVIALES ML 24.28 163.83 3,977.79 0.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.20.00 MAMPARA DE ALUMINIO CON VIDRIO TEMPLADO PAVONADO DE 10.00 MM M2 14.08 440.00 6,195.20 0.00 0.00
22.00.00 INSTALACIONES ELECTRICAS
22.03.00 SALIDAS PARA TOMACORRIENTES
22.03.06 SALIDA PARA TOMACORRIENTE TRIPLE PARA ADOSAR Pto 13.00 59.69 775.97 0.00 0.00
22.12.00 ARTEFACTOS DE ALUMBRADO
22.12.26 ARTEFACTO P/ ADOSAR DE 2 LAMPARAS FLUORECENTES DE 2x40w UND 5.00 105.00 525.00 0.00 0.00
SUB TOTAL 912,219.35 0.00 200,748.30 26,993.49
COSTO DIRECTO 2,197,410.98 298,245.43 200,748.30 26,993.49
GASTOS GENERALES 10% 219,741.10 29,824.54 20,074.83 2,699.35
GASTOS DE SUPERVISIN 2% 43,948.22 5,964.91 4,014.97 539.87
GASTOS DE LIQUIDACIN 0.8% 17,579.29 2,385.96 1,605.99 215.95
GASTOS ADMINISTRATIVOS 1.5% 32,961.16 4,473.68 3,011.22 404.90
PRESUPUESTO TOTAL (S/.) 2,511,640.75 340,894.52 229,455.31 30,853.56

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL

1,283.30 1,745.29

1,283.30 2,399.77
0.00 0.00

264.27 8,950.82
59.67 1,732.22
0.00 0.00
647.99 13,057.00 -647.99 0.00
81.65 3,702.83 -81.65 0.00

165.75 4,405.64

50.81 11,312.85 0.00 0.00

82.84 2,287.21
99.18 3,317.57

100.49 16,809.97 0.00 0.00

16.83 3,959.43 0.00 0.00


52.28 1,774.91

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 0.00

128.65 38,495.94 0.00 0.00


5,736.86 24,840.60

20.68 6,436.24 0.00 0.00


156.18 7,148.36
1,803.96 7,811.15

141.01 610.57 0.00 0.00

13.18 3,572.97 0.00 0.00


67.45 2,935.42
943.04 4,083.36

72.53 30,845.56 0.00 0.00


376.23 17,449.55
9,692.81 41,969.87

4.08 1,613.40 0.00 0.00


36.63 15,999.62 0.00 0.00
288.74 14,477.42
18.62 1,309.92 34.16 2,403.16
5,583.97 24,178.59

70.04 23,707.84 0.00 0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
162.62 8,903.45
6,012.86 26,035.68

37.41 11,418.28 0.00 0.00


0.00 0.00
1,607.15 6,958.96
14.71 4,911.37 0.00 0.00
168.64 6,511.19
558.96 2,420.30 1,656.86 7,174.20
1,404.77 5,745.51

8.00 81,845.44 0.00 0.00


14.00 19,071.08 0.00 0.00
52.00 19,654.44 0.00 0.00
1.00 3,482.84 0.00 0.00
123.33 4,628.57 0.00 0.00

328.93 40,757.72
247.07 19,513.59

0.00 0.00
92.51 2,020.42
0.00 0.00
4.35 132.94
1.31 55.98
10.55 116.16

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
13.62 408.74
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
143.82 8,088.44 0.00 0.00
0.00 0.00

0.00 0.00
61.48 2,474.57 0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

16.61 739.64 0.00 0.00


16.61 418.57 0.00 0.00

158.79 5,481.43 0.00 0.00


158.79 874.93 0.00 0.00
96.81 411.44 0.00 0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL

18.62 5,744.46 0.00 0.00


39.16 8,939.44 0.00 0.00

0.00 0.00
25.13 2,531.60 0.00 0.00
0.00 0.00 0.00
14.08 3,763.16 0.00 0.00
0.00 0.00 0.00
201.75 16,164.21 0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

270.65 5,145.06 0.00 0.00


151.64 1,337.46 0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

45.07 888.78 0.00 0.00


0.00 0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
10,498.02 371,371.62 298,245.43

795.00 3,752.40
17.84 604.24
53.99 1,567.33
0.70 17.78
349.00 5,912.06
210.00 1,360.80
870.00 13,572.00
252.23 15,822.39
275.00 4,705.25

92.11 2,448.28

0.00 0.00

0.72 3.12
148.72 43,588.34

16.53 5,074.54

197.50 8,595.20
457.06 1,979.07

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
59.66 19,119.84

36.04 1,671.54
756.83 3,277.07
49.57 20,186.89

5.20 260.73
5.03 1,905.16
28.33 11,800.86

6.21 340.00
155.10 671.58
47.69 15,841.66
0.00 0.00

0.00 0.00
11.67 450.58
100.00 409.00
15.89 5,249.90
19.11 5,741.22

7.77 962.78
18.43 1,455.60
0.00 0.00

0.00 0.00
109.94 2,401.09

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

0.00 0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL

0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00
0.00 0.00

216.56 2,336.68

46.10 12,874.35

41.03 9,537.01

4.51 1,199.61

8.20 1,045.83
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 VALORIZACIN FINAL DE


MENORES METRADOS PART. NO EJECUTADA OBRA - 2013
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00

0.00 0.00

0.00 0.00

0.00 0.00
0.00 0.00 227,741.79
10,498.02 371,371.62 525,987.22
1,049.80 34,766.38 52,598.72
209.96 6,953.28 10,519.74
83.98 2,781.31 4,207.90
157.47 5,214.96 7,889.81
11,999.23 397,379.72 601,203.39

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, R
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
INICIAL :
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

A EXPEDIENTE TCNICO
02.00.00 OBRAS PRELIMINARES
02.04.00 LIMPIEZA DE TERRENO
02.04.04 ELIMINACION DE BASURA Y ELEMENTOS SUELTOS LIVIANOS M2 1,283.30 1,283.30
02.05.00 TRAZOS, NIVELES Y REPLANTEO
02.05.01 TRAZO Y REPLANTEO PRELIMINAR. M2 1,283.30 1,283.30
02.05.02 TRAZO DURANTE LA EJECUCION DE LA OBRA M2 1,283.30 1,283.30
03.00.00 MOVIMIENTO DE TIERRAS
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 533.31 352.00
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 59.67 59.67
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 55.01 0.00
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 647.99 0.00
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 81.65 0.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 165.75 165.75
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 50.81 0.00
04.03.00 BASE DE CONCRETO
04.03.01 CONCRETO f'c=100 kg/cm2 + 30% P.G. PARA BASE DE CONCRETO M2 86.48 82.84
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 99.18 99.18
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 100.49 0.00
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 16.83 0.00
04.05.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 163.29 55.63
04.08.00 FALSO PISO
04.08.01 FALSO PISO MEZCLA 1:8 e=4" M2 1,082.36 488.08
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 131.05 0.00
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 6,696.57 6,027.57
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 20.68 0.00
05.02.02 VIGAS DE CIMENTACION ENCOFRADO Y DESENCOFRADO M2 165.46 156.18
05.02.03 VIGAS DE CIMENTACION ACERO fy= 4200kg/cm2 KG 1,803.96 1,803.96
05.03.00 SOBRECIMIENTO ARMADO
05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 141.01 0.00
05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 13.18 0.00
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 105.43 67.45
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 2,245.71 943.04
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 72.53 0.00
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 658.79 658.79
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 9,692.81 9,692.81
05.06.00 COLUMNAS

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, R
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
INICIAL :
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

05.06.01 CONCRETO EN COLUMNETAS DE ARRIOSTRE f'c=175 kg/cm2 M3 4.08 0.00


05.06.02 COLUMNAS, CONCRETO f'c= 210kg/cm2 M3 36.63 0.00
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 359.11 355.37
05.06.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO CARAVISTA M2 114.72 114.72
05.06.05 COLUMNAS, ACERO fy=4200 kg/cm2 KG 5,583.97 5,583.97
05.07.00 VIGAS
05.07.02 VIGAS, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 70.04 0.00
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 543.17 466.43
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 12,224.59 11,888.68
05.08.00 LOSAS
05.08.01 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 M3 37.41 0.00
05.08.02 LOSAS MACIZAS, ENCOFRADO Y DESENCOFRADO M2 187.06 0.00
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 3,912.31 3,855.87
05.08.04 LOSA ALIGERADA, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 14.71 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 168.64 168.64
05.08.06 LOSA ALIGERADA, ACERO fy= 4200kg/cm2 KG 2,401.40 1,656.86
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 1,404.77 1,404.77
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.06.00 ARMADURA PRINCIPAL VMP-01 (AUDITORIO) INC/ PINTADO Y COLOCADO PZA 8.00 0.00
06.10.00 COBERTURA METALICA VL-1 (EN AUDITORIO LOBBY) PZA 14.00 0.00
06.20.00 CORREA VL-02 (EN AUDITORIO LOBBY) INC. PINTADO Y COLOCADO PZA 52.00 0.00
06.21.00 COBERTURA METALICA EN INGRESO DE AUDITORIO PZA 1.00 0.00
06.23.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR 6 mm M2 123.33 0.00
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 416.07 394.10
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 588.13 382.26
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 208.16 152.28
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 2,036.62 1,023.29
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 1,387.62 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 167.03 167.81
08.05.00 TARRAJEO DE VIGAS M2 352.97 151.99
08.08.00 VESTIDURA DE DERRAMES (1:5) ML 908.20 93.25
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 527.13 312.97
09.02.00 VESTIDURA EN FONDO DE ESCALERAS M2 125.68 15.88
09.03.00 CIELO RASO DE CELOTEX (0.60 x 0.60) M2 562.56 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 634.97 128.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 135.13 109.97
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 66.15 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 1,465.23 452.28
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 61.06 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 368.84 0.00
10.08.00 PISO DE MADERA MACHIHEMBRADO M2 106.31 0.00
10.09.00 PISO DE PORCELANATO M2 143.82 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 610.69 0.00

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, R
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
INICIAL :
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 183.32 0.00
11.02.00 CONTRAZOCALO DE PORCELANATO ML 61.48 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 204.77 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 107.15 0.00
12.04.00 ZOCALO DE PIEDRA LAJA ML 118.77 0.00
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 16.61 0.00
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 16.61 0.00
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2 407.64 0.00
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 407.64 0.00
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M 307.51 0.00
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 18.62 0.00
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X3" M2 39.16 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.01.00 PUERTA METALICA TERMOACUSTICA ANTIPANICO DE EMERGENCIA UND 3.78 0.00
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 25.13 0.00
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 12.96 0.00
16.13.00 MAMPARA DE ALUMINO M2 14.08 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 16.94 0.00
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 201.75 0.00
17.00.00 CERRAJERIA
17.02.00 BISAGRA CAPUCHINA DE ALUMINIO DE 3" X 3" PZA 87.00 0.00
17.04.00 CERRADURA DOS GOLPES EN PUERTAS PZA 9.00 0.00
17.05.00 CERRADURA PARA INTERIOR DOBLE PERILLA PZA 9.00 0.00
17.06.00 CERRADURA DE POMO PARA MAMPARA DE INGRESO PZA 2.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/ACCESORIO P2 270.65 0.00
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 151.64 0.00
18.05.00 VIDRIOS BLOK INCOLORO P2 190.63 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 652.81 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 2,819.98 0.00
19.04.00 PINTURA SUPER MATE 2 MANOS EN MUROS EXT. A PARTIR DEL 2DO PISO M2 1,387.62 0.00
19.07.00 PINTURA BARNIZ 2 MANOS EN CARPINTERIA DE MADERA M2 18.62 0.00
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 45.07 0.00
20.07.00 LIMPIEZA FINAL DE LA OBRA M2 18.62 18.62
B EXPEDIENTE ADICIONAL N 07 MAYORES METRADOS - PARTIDAS NUEVAS
MAYORES METRADOS
03.00.00 MOVIMIENTO DE TIERRAS
03.03.00 CORTE DE TERRENO A MAQUINARIA M3 795.00 795.00
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 87.68 17.84
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 66.20 53.99

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, R
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
INICIAL :
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 0.90 0.70


03.13.00 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES M3 1,043.60 452.67
03.16.00 ACARREO DE MATERIAL DE CORTE CON MAQUINARIA M3 210.00 210.00
03.20.00 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 1,628.60 960.00
03.24.00 RELLENO MANUAL Y COMPACTADO CON EQUIPO MATERIAL PROPIO M3 2,060.44 335.11
03.25.00 PREPARACION DE MATERIAL DE RELLENO - MATERIAL PROPIO M3 275.00 275.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 92.11 92.11
04.03.00 BASE DE CONCRETO
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 11.98 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 78.14 0.72
05.01.05 ZAPATAS, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 148.72 148.72
05.02.00 VIGAS DE CIMENTACION
05.02.04 VIGAS DE CIMENTACION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 20.68 16.53
05.04.00 MUROS DE CONTENCION
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 388.75 197.50
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 457.06 457.06
05.04.07 MUROS DE CONTENCION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 59.66 59.66
05.05.00 PLACAS
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 52.49 36.04
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 756.83 756.83
05.05.04 PLACAS, CONCRETO f'c=210 KG/CM2 CON ADITIVO M3 76.32 76.32
05.06.00 COLUMNAS
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 29.90 5.23
05.06.06 CONCRETO EN COLUMNETAS DE ARRIOSTRE, F'c= 175 KG/CM2 CON ADITIVO M3 6.76 5.26
05.06.07 COLUMNAS, CONCRETO F'c=210 KG/CM2 CON ADITIVO M3 40.96 40.96
05.07.00 VIGAS
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 77.78 16.23
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 1,442.88 428.87
05.07.05 VIGAS, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 92.89 90.15
05.07.06 CONCRETO EN VIGUETAS DE ARRIOSTRE F'c=175 KG/CM2 CON ADITIVO M3 1.97 1.97
05.08.00 LOSAS
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 119.99 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 11.67 11.67
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 104.00 100.00
05.08.08 LOSA ALIGERADA, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 15.89 15.89
05.08.09 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 CON ADITIVO M3 37.41 35.76
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 108.69 7.77
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 30.02 18.43
07.05.00 TABIQUERIA SISTEMA DRIWALL M2 5.04 0.00
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 35.89 0.00
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 138.47 109.94

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, R
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
INICIAL :
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 52.49 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 52.35 0.00
08.05.00 TARRAJEO DE VIGAS M2 50.19 0.00
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 160.59 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 30.62 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 13.60 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 32.37 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 50.71 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 24.31 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 194.51 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 39.74 0.00
10.13.00 CONTRAPISO f'c = 140 KG/CM2 E=5 cm PARA BASE DE COLOCACION DE ADOQUINES M2 98.52 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 74.85 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 4.31 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 20.97 0.00
15.00.00 CARPINTERIA DE MADERA
15.14.00 PUERTA CON TABLERO REBAJADO, C/ACABADO M2 20.30 0.00
15.20.00 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM INC./MARCO CEDRO 2"x3"C/ ACABADO Y CO M2 41.68 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 0.54 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 1.50 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.13.00 VIDRIO SISTEMA MODUGLAS TEMPLADO INCOLORO DE 6 MM, INC./ COLOCADO Y ACCESORIO P2 276.42 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 210.77 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 104.84 0.00
19.16.00 EMPASTADO DE SUPERFICIE M2 5,176.03 0.00
20.00.00 VARIOS
20.12.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 2" ML 27.80 0.00
20.13.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 1" ML 72.80 0.00
PARTIDAS NUEVAS
03.00.00 MOVIMIENTO DE TIERRAS
03.39.00 COMPACTADO Y PERFILADO EN ZONA DE EXCAVACION C/ EQUIPO M2 307.45 216.56
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUB ZAPATAS
04.02.03 SUB ZAPATA CONCRETO F'C= 140 KG/CM2 + 30% P.G. CON ADITIVO M3 67.30 46.10
04.04.00 CIMIENTOS CORRIDOS
04.04.05 CONCRETO 140 KG/CM2 +30% PG. EN CIMIENTO CORRIDO CON ADITIVO M3 100.49 41.03
04.05.00 SOBRECIMIENTOS
04.05.03 SOBRECIMIENTO, CONCRETO 140 KG/CM2 CON ADITIVO M3 16.83 4.51
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.36.00 COBERTURA METALICA EN TERRAZA DE AUDITORIO M2 108.94 8.20
06.37.00 COBERTURA METALICA SOBRE RAMPA DE AUDITORIO M2 138.85 0.00

[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE

ENTIDAD : Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, R
SNIP : 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S. RESIDENTE: Arq. Carmen Prez Benavides
INICIAL :
COMPONT. : CONSTRUCCIN AUDITORIO INSPECTOR: Ing. Jhonathan Chura Yupanqui

METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO

06.38.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR E=8.00 MM M2 116.29 0.00


06.39.00 TECHO DE AUDITORIO CON PLANCHA TERMOACUSTICA CINDULIT 180 INC./SUMINISTRO E INS GLB 1.00 1.00
06.40.00 ESTRUCTURA METALICA PARA TECHO DE AUDITORIO INC./ SUMINISTRO E INSTALACION GLB 1.00 1.00
15.00.00 CARPINTERIA DE MADERA
15.25.00 REVESTIMIENTO CON MADERA ESTRUCUTRAL EN MADERA Y DESCANSO M2 8.57 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.65.00 PASAMANO METALICO INC./ COLOCADO Y PINTADO ML 19.20 0.00
16.66.00 BARANDA METALICA INC./ COLOCADO Y PINTADO ML 188.84 0.00
16.67.00 CLARABOYA DE TUBO METALICO M2 7.35 0.00
16.68.00 ESTRUCTURA EN ESCALERA Y DESCANSO TERRAZA DE AUDITORIO (SEGN DISEO) GLB 1.00 0.00
16.69.00 ESCALERA TIPO GATO CON TAPA METALICA GLB 1.00 0.00
16.70.00 REJILLA METALICA PARA EVACIANDION DE AGUAS FLUVIALES ML 24.28 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.20.00 MAMPARA DE ALUMINIO CON VIDRIO TEMPLADO PAVONADO DE 10.00 MM M2 14.08 0.00
22.00.00 INSTALACIONES ELECTRICAS
22.03.00 SALIDAS PARA TOMACORRIENTES
22.03.06 SALIDA PARA TOMACORRIENTE TRIPLE PARA ADOSAR Pto 13.00 0.00
22.12.00 ARTEFACTOS DE ALUMBRADO
22.12.26 ARTEFACTO P/ ADOSAR DE 2 LAMPARAS FLUORECENTES DE 2x40w UND 5.00 0.00

[AKSP]
XPEDIENTE DE ADICIONALES

trito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2014

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

0.00

0.00
0.00

181.31
0.00
55.01
647.99
81.65

0.00

50.81

3.64
0.00

100.49

16.83
107.66

594.28

131.05
669.00

20.68
9.28
0.00

141.01

13.18
37.98
1,302.67

72.53
0.00
0.00

[AKSP]
XPEDIENTE DE ADICIONALES

trito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2014

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

4.08
36.63
3.74
0.00
0.00

70.04
76.74
335.91

37.41
187.06
56.44
14.71
0.00
744.54
0.00

8.00
14.00
52.00
1.00
123.33

21.97
205.87

55.88
1,013.33
1,387.62
-0.78
200.98
814.95

214.16
109.80
562.56

506.97
25.16
66.15
1,012.95
61.06
368.84
106.31
143.82
610.69

[AKSP]
XPEDIENTE DE ADICIONALES

trito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2014

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

183.32
61.48
204.77

107.15
118.77

16.61
16.61

407.64
407.64
307.51

18.62
39.16

3.78
25.13
12.96
14.08
16.94
201.75

87.00
9.00
9.00
2.00

270.65
151.64
190.63

652.81
2,819.98
1,387.62
18.62

45.07
0.00

0.00
69.84
12.21

[AKSP]
XPEDIENTE DE ADICIONALES

trito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2014

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

0.20
590.93
0.00
668.60
1,725.33
0.00

0.00

11.98

77.42
0.00

4.15

191.25
0.00
0.00

16.45
0.00
0.00

24.67
1.50
0.00

61.55
1,014.01
2.74
0.00

119.99
0.00
4.00
0.00
1.65

100.92
11.59
5.04

35.89
28.53

[AKSP]
XPEDIENTE DE ADICIONALES

trito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2014

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

52.49
52.35
50.19

160.59

30.62
13.60
32.37
50.71
24.31
194.51
39.74
98.52

74.85
4.31

20.97

20.30
41.68

0.54
1.50

276.42

210.77
104.84
5,176.03

27.80
72.80

90.89

21.20

59.46

12.32

100.74
138.85

[AKSP]
XPEDIENTE DE ADICIONALES

trito de Samegua Prov. Mariscal Nieto, Regin Moquegua

Arq. Carmen Prez Benavides


Ing. Jhonathan Chura Yupanqui

METRADO - 2014

MAYOR
DIFERENCIA DEDUCTIVO
METRADO

116.29
0.00
0.00

8.57

19.20
188.84
7.35
1.00
1.00
24.28

14.08

13.00

5.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
A EXPEDIENTE TCNICO
02.00.00 OBRAS PRELIMINARES
02.04.00 LIMPIEZA DE TERRENO
02.04.04 ELIMINACION DE BASURA Y ELEMENTOS SUELTOS LIVIANOS M2 1,283.30 1.36 1,745.29 1,283.30 1,745.29
02.05.00 TRAZOS, NIVELES Y REPLANTEO
02.05.01 TRAZO Y REPLANTEO PRELIMINAR. M2 1,283.30 1.87 2,399.77 1,283.30 2,399.77
02.05.02 TRAZO DURANTE LA EJECUCION DE LA OBRA M2 1,283.30 1.08 1,385.96 1,283.30 1,385.96
03.00.00 MOVIMIENTO DE TIERRAS
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 533.31 33.87 18,063.21 352.00 11,922.24
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 59.67 29.03 1,732.22 59.67 1,732.22
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 55.01 25.40 1,397.25 0.00 0.00
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 647.99 20.15 13,057.00 0.00 0.00
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 81.65 45.35 3,702.83 0.00 0.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 165.75 26.58 4,405.64 165.75 4,405.64
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 50.81 222.65 11,312.85 0.00 0.00
04.03.00 BASE DE CONCRETO
04.03.01 CONCRETO f'c=100 kg/cm2 + 30% P.G. PARA BASE DE CONCRETO M2 86.48 27.61 2,387.71 82.84 2,287.21
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 99.18 33.45 3,317.57 99.18 3,317.57
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 100.49 167.28 16,809.97 0.00 0.00
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 16.83 235.26 3,959.43 0.00 0.00
04.05.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 163.29 33.95 5,543.70 55.63 1,888.64
04.08.00 FALSO PISO

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
04.08.01 FALSO PISO MEZCLA 1:8 e=4" M2 1,082.36 26.63 28,823.25 488.08 12,997.57
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 131.05 299.23 39,214.09 0.00 0.00
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 6,696.57 4.33 28,996.15 6,027.57 26,099.38
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 20.68 311.23 6,436.24 0.00 0.00
05.02.02 VIGAS DE CIMENTACION ENCOFRADO Y DESENCOFRADO M2 165.46 45.77 7,573.10 156.18 7,148.36
05.02.03 VIGAS DE CIMENTACION ACERO fy= 4200kg/cm2 KG 1,803.96 4.33 7,811.15 1,803.96 7,811.15
05.03.00 SOBRECIMIENTO ARMADO
05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 141.01 4.33 610.57 0.00 0.00
05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 13.18 271.09 3,572.97 0.00 0.00
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 105.43 43.52 4,588.31 67.45 2,935.42
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 2,245.71 4.33 9,723.92 943.04 4,083.36
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 72.53 425.28 30,845.56 0.00 0.00
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 658.79 46.38 30,554.68 658.79 30,554.68
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 9,692.81 4.33 41,969.87 9,692.81 41,969.87
05.06.00 COLUMNAS
05.06.01 CONCRETO EN COLUMNETAS DE ARRIOSTRE f'c=175 kg/cm2 M3 4.08 395.44 1,613.40 0.00 0.00
05.06.02 COLUMNAS, CONCRETO f'c= 210kg/cm2 M3 36.63 436.79 15,999.62 0.00 0.00
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 359.11 50.14 18,005.78 355.37 17,818.25
05.06.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO CARAVISTA M2 114.72 70.35 8,070.55 114.72 8,070.55
05.06.05 COLUMNAS, ACERO fy=4200 kg/cm2 KG 5,583.97 4.33 24,178.59 5,583.97 24,178.59
05.07.00 VIGAS
05.07.02 VIGAS, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 70.04 338.49 23,707.84 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 543.17 54.75 29,738.56 466.43 25,537.04
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 12,224.59 4.33 52,932.47 11,888.68 51,477.98
05.08.00 LOSAS
05.08.01 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 M3 37.41 305.22 11,418.28 0.00 0.00
05.08.02 LOSAS MACIZAS, ENCOFRADO Y DESENCOFRADO M2 187.06 43.15 8,071.64 0.00 0.00
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 3,912.31 4.33 16,940.30 3,855.87 16,695.92
05.08.04 LOSA ALIGERADA, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 14.71 333.88 4,911.37 0.00 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 168.64 38.61 6,511.19 168.64 6,511.19
05.08.06 LOSA ALIGERADA, ACERO fy= 4200kg/cm2 KG 2,401.40 4.33 10,398.06 1,656.86 7,174.20
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 1,404.77 4.09 5,745.51 1,404.77 5,745.51
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.06.00 ARMADURA PRINCIPAL VMP-01 (AUDITORIO) INC/ PINTADO Y COLOCADO PZA 8.00 10,230.68 81,845.44 0.00 0.00
06.10.00 COBERTURA METALICA VL-1 (EN AUDITORIO LOBBY) PZA 14.00 1,362.22 19,071.08 0.00 0.00
06.20.00 CORREA VL-02 (EN AUDITORIO LOBBY) INC. PINTADO Y COLOCADO PZA 52.00 377.97 19,654.44 0.00 0.00
06.21.00 COBERTURA METALICA EN INGRESO DE AUDITORIO PZA 1.00 3,482.84 3,482.84 0.00 0.00
06.23.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR 6 mm M2 123.33 37.53 4,628.57 0.00 0.00
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 416.07 123.91 51,555.23 394.10 48,832.93
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 588.13 78.98 46,450.51 382.26 30,190.89
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 208.16 19.51 4,061.20 152.28 2,970.98
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 2,036.62 21.84 44,479.78 1,023.29 22,348.65
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 1,387.62 29.33 40,698.89 0.00 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 167.03 30.56 5,104.44 167.81 5,128.27
08.05.00 TARRAJEO DE VIGAS M2 352.97 42.73 15,082.41 151.99 6,494.53
08.08.00 VESTIDURA DE DERRAMES (1:5) ML 908.20 11.01 9,999.28 93.25 1,026.68
09.00.00 CIELORRASOS

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 527.13 30.01 15,819.17 312.97 9,392.23
09.02.00 VESTIDURA EN FONDO DE ESCALERAS M2 125.68 30.92 3,886.03 15.88 491.01
09.03.00 CIELO RASO DE CELOTEX (0.60 x 0.60) M2 562.56 140.96 79,298.46 0.00 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 634.97 26.40 16,763.21 128.00 3,379.20
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 135.13 21.44 2,897.19 109.97 2,357.76
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 66.15 56.03 3,706.38 0.00 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 1,465.23 27.11 39,722.39 452.28 12,261.31
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 61.06 49.18 3,002.93 0.00 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 368.84 50.10 18,478.88 0.00 0.00
10.08.00 PISO DE MADERA MACHIHEMBRADO M2 106.31 74.53 7,923.28 0.00 0.00
10.09.00 PISO DE PORCELANATO M2 143.82 56.24 8,088.44 0.00 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 610.69 24.66 15,059.62 0.00 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 183.32 15.45 2,832.29 0.00 0.00
11.02.00 CONTRAZOCALO DE PORCELANATO ML 61.48 40.25 2,474.57 0.00 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 204.77 15.67 3,208.75 0.00 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 107.15 51.17 5,482.87 0.00 0.00
12.04.00 ZOCALO DE PIEDRA LAJA ML 118.77 62.52 7,425.50 0.00 0.00
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 16.61 44.53 739.64 0.00 0.00
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 16.61 25.20 418.57 0.00 0.00
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2 407.64 34.52 14,071.73 0.00 0.00
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 407.64 5.51 2,246.10 0.00 0.00
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M 307.51 4.25 1,306.92 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 18.62 308.51 5,744.46 0.00 0.00
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X M2 39.16 228.28 8,939.44 0.00 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.01.00 PUERTA METALICA TERMOACUSTICA ANTIPANICO DE EMERGENCIA UND 3.78 1,729.93 6,539.14 0.00 0.00
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 25.13 100.74 2,531.60 0.00 0.00
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 12.96 261.01 3,382.69 0.00 0.00
16.13.00 MAMPARA DE ALUMINO M2 14.08 267.27 3,763.16 0.00 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 16.94 247.82 4,198.07 0.00 0.00
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 201.75 80.12 16,164.21 0.00 0.00
17.00.00 CERRAJERIA
17.02.00 BISAGRA CAPUCHINA DE ALUMINIO DE 3" X 3" PZA 87.00 13.46 1,171.02 0.00 0.00
17.04.00 CERRADURA DOS GOLPES EN PUERTAS PZA 9.00 60.70 546.30 0.00 0.00
17.05.00 CERRADURA PARA INTERIOR DOBLE PERILLA PZA 9.00 47.70 429.30 0.00 0.00
17.06.00 CERRADURA DE POMO PARA MAMPARA DE INGRESO PZA 2.00 80.70 161.40 0.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/ P2 270.65 19.01 5,145.06 0.00 0.00
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 151.64 8.82 1,337.46 0.00 0.00
18.05.00 VIDRIOS BLOK INCOLORO P2 190.63 30.95 5,900.00 0.00 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 652.81 8.14 5,313.87 0.00 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 2,819.98 8.14 22,954.64 0.00 0.00
19.04.00 PINTURA SUPER MATE 2 MANOS EN MUROS EXT. A PARTIR DEL 2DO PISO M2 1,387.62 13.42 18,621.86 0.00 0.00
19.07.00 PINTURA BARNIZ 2 MANOS EN CARPINTERIA DE MADERA M2 18.62 15.30 284.89 0.00 0.00
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 45.07 19.72 888.78 0.00 0.00
20.07.00 LIMPIEZA FINAL DE LA OBRA M2 18.62 1.28 23.83 18.62 23.83

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
SUB TOTAL 1,285,191.63 472,791.86 0.00 0.00
B EXPEDIENTE ADICIONAL N 07 MAYORES METRADOS - PARTIDAS NUEVAS
MAYORES METRADOS
03.00.00 MOVIMIENTO DE TIERRAS
03.03.00 CORTE DE TERRENO A MAQUINARIA M3 795.00 4.72 3,752.40 795.00 3,752.40
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 87.68 33.87 2,969.72 17.84 604.24
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 66.20 29.03 1,921.79 53.99 1,567.33
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 0.90 25.40 22.86 0.70 17.78
03.13.00 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES M3 1,043.60 16.94 17,678.58 452.67 7,668.23
03.16.00 ACARREO DE MATERIAL DE CORTE CON MAQUINARIA M3 210.00 6.48 1,360.80 210.00 1,360.80
03.20.00 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 1,628.60 15.60 25,406.16 960.00 14,976.00
03.24.00 RELLENO MANUAL Y COMPACTADO CON EQUIPO MATERIAL PROPIO M3 2,060.44 62.73 129,251.40 335.11 21,021.45
03.25.00 PREPARACION DE MATERIAL DE RELLENO - MATERIAL PROPIO M3 275.00 17.11 4,705.25 275.00 4,705.25
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 92.11 26.58 2,448.28 92.11 2,448.28
04.03.00 BASE DE CONCRETO
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 11.98 33.45 400.73 0.00 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 78.14 4.33 338.35 0.72 3.12
05.01.05 ZAPATAS, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 148.72 293.09 43,588.34 148.72 43,588.34
05.02.00 VIGAS DE CIMENTACION
05.02.04 VIGAS DE CIMENTACION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 20.68 306.99 6,348.55 16.53 5,074.54
05.04.00 MUROS DE CONTENCION
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 388.75 43.52 16,918.40 197.50 8,595.20
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 457.06 4.33 1,979.07 457.06 1,979.07

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
05.04.07 MUROS DE CONTENCION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 59.66 320.48 19,119.84 59.66 19,119.84
05.05.00 PLACAS
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 52.49 46.38 2,434.49 36.04 1,671.54
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 756.83 4.33 3,277.07 756.83 3,277.07
05.05.04 PLACAS, CONCRETO f'c=210 KG/CM2 CON ADITIVO M3 76.32 407.24 31,080.56 76.32 31,080.56
05.06.00 COLUMNAS
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 29.90 50.14 1,499.19 5.23 262.23
05.06.06 CONCRETO EN COLUMNETAS DE ARRIOSTRE, F'c= 175 KG/CM2 CON ADITIVO M3 6.76 378.76 2,560.42 5.26 1,992.28
05.06.07 COLUMNAS, CONCRETO F'c=210 KG/CM2 CON ADITIVO M3 40.96 416.55 17,061.89 40.96 17,061.89
05.07.00 VIGAS
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 77.78 54.75 4,258.46 16.23 888.59
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 1,442.88 4.33 6,247.67 428.87 1,857.01
05.07.05 VIGAS, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 92.89 332.18 30,856.20 90.15 29,946.03
05.07.06 CONCRETO EN VIGUETAS DE ARRIOSTRE F'c=175 KG/CM2 CON ADITIVO M3 1.97 312.84 616.29 1.97 616.29
05.08.00 LOSAS
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 119.99 4.33 519.56 0.00 0.00
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 11.67 38.61 450.58 11.67 450.58
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 104.00 4.09 425.36 100.00 409.00
05.08.08 LOSA ALIGERADA, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 15.89 330.39 5,249.90 15.89 5,249.90
05.08.09 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 CON ADITIVO M3 37.41 300.43 11,239.09 35.76 10,743.38
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 108.69 123.91 13,467.78 7.77 962.78
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 30.02 78.98 2,370.98 18.43 1,455.60
07.05.00 TABIQUERIA SISTEMA DRIWALL M2 5.04 221.97 1,118.73 0.00 0.00
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 35.89 19.51 700.21 0.00 0.00
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 138.47 21.84 3,024.22 109.94 2,401.09

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 52.49 29.33 1,539.42 0.00 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 52.35 30.56 1,599.96 0.00 0.00
08.05.00 TARRAJEO DE VIGAS M2 50.19 42.73 2,144.53 0.00 0.00
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 160.59 30.01 4,819.16 0.00 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 30.62 26.40 808.37 0.00 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 13.60 21.44 291.67 0.00 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 32.37 56.03 1,813.69 0.00 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 50.71 27.11 1,374.75 0.00 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 24.31 49.18 1,195.66 0.00 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 194.51 50.10 9,745.05 0.00 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 39.74 24.66 979.99 0.00 0.00
10.13.00 CONTRAPISO f'c = 140 KG/CM2 E=5 cm PARA BASE DE COLOCACION DE ADOQUINE M2 98.52 396.62 39,076.67 0.00 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 74.85 15.45 1,156.43 0.00 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 4.31 15.67 67.54 0.00 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 20.97 51.17 1,073.03 0.00 0.00
15.00.00 CARPINTERIA DE MADERA
15.14.00 PUERTA CON TABLERO REBAJADO, C/ACABADO M2 20.30 650.38 13,202.71 0.00 0.00
15.20.00 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM INC./MARCO CEDRO 2"x3"C/ ACA M2 41.68 355.14 14,802.24 0.00 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 0.54 261.01 140.95 0.00 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 1.50 247.82 371.73 0.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.13.00 VIDRIO SISTEMA MODUGLAS TEMPLADO INCOLORO DE 6 MM, INC./ COLOCADO Y P2 276.42 33.50 9,260.07 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 210.77 8.14 1,715.69 0.00 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 104.84 8.14 853.41 0.00 0.00
19.16.00 EMPASTADO DE SUPERFICIE M2 5,176.03 7.58 39,234.27 0.00 0.00
20.00.00 VARIOS
20.12.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 2" ML 27.80 18.49 514.02 0.00 0.00
20.13.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 1" ML 72.80 11.21 816.09 0.00 0.00
PARTIDAS NUEVAS
03.00.00 MOVIMIENTO DE TIERRAS
03.39.00 COMPACTADO Y PERFILADO EN ZONA DE EXCAVACION C/ EQUIPO M2 307.45 10.79 3,317.43 216.56 2,336.68
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUB ZAPATAS
04.02.03 SUB ZAPATA CONCRETO F'C= 140 KG/CM2 + 30% P.G. CON ADITIVO M3 67.30 279.27 18,794.87 46.10 12,874.35
04.04.00 CIMIENTOS CORRIDOS
04.04.05 CONCRETO 140 KG/CM2 +30% PG. EN CIMIENTO CORRIDO CON ADITIVO M3 100.49 232.44 23,357.90 41.03 9,537.01
04.05.00 SOBRECIMIENTOS
04.05.03 SOBRECIMIENTO, CONCRETO 140 KG/CM2 CON ADITIVO M3 16.83 265.99 4,476.61 4.51 1,199.61
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.36.00 COBERTURA METALICA EN TERRAZA DE AUDITORIO M2 108.94 127.54 13,893.89 8.20 1,045.83
06.37.00 COBERTURA METALICA SOBRE RAMPA DE AUDITORIO M2 138.85 155.41 21,578.68 0.00 0.00
06.38.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR E=8.00 MM M2 116.29 86.71 10,083.51 0.00 0.00
06.39.00 TECHO DE AUDITORIO CON PLANCHA TERMOACUSTICA CINDULIT 180 INC./SUMINIS GLB 1.00 60,000.00 60,000.00 1.00 60,000.00
06.40.00 ESTRUCTURA METALICA PARA TECHO DE AUDITORIO INC./ SUMINISTRO E INSTALA GLB 1.00 ### 150,000.00 1.00 150,000.00
15.00.00 CARPINTERIA DE MADERA
15.25.00 REVESTIMIENTO CON MADERA ESTRUCUTRAL EN MADERA Y DESCANSO M2 8.57 122.61 1,050.31 0.00 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.65.00 PASAMANO METALICO INC./ COLOCADO Y PINTADO ML 19.20 50.78 974.98 0.00 0.00

[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO
S/. 38258,125.30 N.S.
INICIAL:
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE EJECUTADO DEL ADICIONALES


ITEM DESCRIPCIN RESOLUCIN EXPEDIENTE MAYORES METRADOS PARTIDAS NUEVAS
UND. METRADO P.U. PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
16.66.00 BARANDA METALICA INC./ COLOCADO Y PINTADO ML 188.84 89.87 16,971.05 0.00 0.00
16.67.00 CLARABOYA DE TUBO METALICO M2 7.35 163.70 1,203.20 0.00 0.00
16.68.00 ESTRUCTURA EN ESCALERA Y DESCANSO TERRAZA DE AUDITORIO (SEGN DISE GLB 1.00 7,180.94 7,180.94 0.00 0.00
16.69.00 ESCALERA TIPO GATO CON TAPA METALICA GLB 1.00 2,595.77 2,595.77 0.00 0.00
16.70.00 REJILLA METALICA PARA EVACIANDION DE AGUAS FLUVIALES ML 24.28 163.83 3,977.79 0.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.20.00 MAMPARA DE ALUMINIO CON VIDRIO TEMPLADO PAVONADO DE 10.00 MM M2 14.08 440.00 6,195.20 0.00 0.00
22.00.00 INSTALACIONES ELECTRICAS
22.03.00 SALIDAS PARA TOMACORRIENTES
22.03.06 SALIDA PARA TOMACORRIENTE TRIPLE PARA ADOSAR Pto 13.00 59.69 775.97 0.00 0.00
22.12.00 ARTEFACTOS DE ALUMBRADO
22.12.26 ARTEFACTO P/ ADOSAR DE 2 LAMPARAS FLUORECENTES DE 2x40w UND 5.00 105.00 525.00 0.00 0.00
SUB TOTAL 912,219.35 0.00 246,807.69 236,993.49
COSTO DIRECTO 2,197,410.98 472,791.86 246,807.69 236,993.49
GASTOS GENERALES 10% 219,741.10 47,279.19 24,680.77 23,699.35
GASTOS DE SUPERVISIN 2% 43,948.22 9,455.84 4,936.15 4,739.87
GASTOS DE LIQUIDACIN 0.8% 17,579.29 3,782.33 1,974.46 1,895.95
GASTOS ADMINISTRATIVOS 1.5% 32,961.16 7,091.88 3,702.12 3,554.90
PRESUPUESTO TOTAL (S/.) 2,511,640.75 540,401.10 282,101.19 270,883.56

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL

1,283.30 1,745.29 0.00 0.00%


0.00 #DIV/0!
1,283.30 2,399.77 0.00 0.00%
1,283.30 1,385.96 0.00 0.00%
0.00 #DIV/0!
352.00 11,922.24 181.31 34.00%
59.67 1,732.22 0.00 0.00%
0.00 0.00 55.01 100.00%
0.00 0.00 647.99 100.00%
0.00 0.00 81.65 100.00%
0.00 #DIV/0!
0.00 #DIV/0!
165.75 4,405.64 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 50.81 100.00%
0.00 #DIV/0!
82.84 2,287.21 3.64 4.21%
99.18 3,317.57 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 100.49 100.00%
0.00 #DIV/0!
0.00 0.00 16.83 100.00%
55.63 1,888.64 107.66 65.93%
0.00 #DIV/0!

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
488.08 12,997.57 594.28 54.91%
0.00 #DIV/0!
0.00 #DIV/0!
0.00 0.00 131.05 100.00%
6,027.57 26,099.38 669.00 9.99%
0.00 #DIV/0!
0.00 0.00 20.68 100.00%
156.18 7,148.36 9.28 5.61%
1,803.96 7,811.15 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 141.01 100.00%
0.00 #DIV/0!
0.00 0.00 13.18 100.00%
67.45 2,935.42 37.98 36.02%
943.04 4,083.36 1,302.67 58.01%
0.00 #DIV/0!
0.00 0.00 72.53 100.00%
658.79 30,554.68 0.00 0.00%
9,692.81 41,969.87 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 4.08 100.00%
0.00 0.00 36.63 100.00%
355.37 17,818.25 3.74 1.04%
114.72 8,070.55 0.00 0.00%
5,583.97 24,178.59 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 70.04 100.00%

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
466.43 25,537.04 76.74 14.13%
11,888.68 51,477.98 335.91 2.75%
0.00 #DIV/0!
0.00 0.00 37.41 100.00%
0.00 0.00 187.06 100.00%
3,855.87 16,695.92 56.44 1.44%
0.00 0.00 14.71 100.00%
168.64 6,511.19 0.00 0.00%
1,656.86 7,174.20 744.54 31.00%
1,404.77 5,745.51 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 8.00 100.00%
0.00 0.00 14.00 100.00%
0.00 0.00 52.00 100.00%
0.00 0.00 1.00 100.00%
0.00 0.00 123.33 100.00%
0.00 #DIV/0!
394.10 48,832.93 21.97 5.28%
382.26 30,190.89 205.87 35.00%
0.00 #DIV/0!
152.28 2,970.98 55.88 26.84%
1,023.29 22,348.65 1,013.33 49.76%
0.00 0.00 1,387.62 100.00%
167.81 5,128.27 -0.78 -0.47%
151.99 6,494.53 200.98 56.94%
93.25 1,026.68 814.95 89.73%
0.00 #DIV/0!

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
312.97 9,392.23 214.16 40.63%
15.88 491.01 109.80 87.36%
0.00 0.00 562.56 100.00%
0.00 #DIV/0!
128.00 3,379.20 506.97 79.84%
109.97 2,357.76 25.16 18.62%
0.00 0.00 66.15 100.00%
452.28 12,261.31 1,012.95 69.13%
0.00 0.00 61.06 100.00%
0.00 0.00 368.84 100.00%
0.00 0.00 106.31 100.00%
0.00 0.00 143.82 100.00%
0.00 0.00 610.69 100.00%
0.00 #DIV/0!
0.00 0.00 183.32 100.00%
0.00 0.00 61.48 100.00%
0.00 0.00 204.77 100.00%
0.00 #DIV/0!
0.00 0.00 107.15 100.00%
0.00 0.00 118.77 100.00%
0.00 #DIV/0!
0.00 0.00 16.61 100.00%
0.00 0.00 16.61 100.00%
0.00 #DIV/0!
0.00 0.00 407.64 100.00%
0.00 0.00 407.64 100.00%
0.00 0.00 307.51 100.00%

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 #DIV/0!
0.00 0.00 18.62 100.00%
0.00 0.00 39.16 100.00%
0.00 #DIV/0!
0.00 0.00 3.78 100.00%
0.00 0.00 25.13 100.00%
0.00 0.00 12.96 100.00%
0.00 0.00 14.08 100.00%
0.00 0.00 16.94 100.00%
0.00 0.00 201.75 100.00%
0.00 #DIV/0!
0.00 0.00 87.00 100.00%
0.00 0.00 9.00 100.00%
0.00 0.00 9.00 100.00%
0.00 0.00 2.00 100.00%
0.00 #DIV/0!
0.00 0.00 270.65 100.00%
0.00 0.00 151.64 100.00%
0.00 0.00 190.63 100.00%
0.00 #DIV/0!
0.00 0.00 652.81 100.00%
0.00 0.00 2,819.98 100.00%
0.00 0.00 1,387.62 100.00%
0.00 0.00 18.62 100.00%
0.00 #DIV/0!
0.00 0.00 45.07 100.00%
18.62 23.83 0.00 0.00%

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 0.00 0.00 472,791.86

795.00 3,752.40 0.00 0.00%


17.84 604.24 69.84 79.65%
53.99 1,567.33 12.21 18.44%
0.70 17.78 0.20 22.22%
452.67 7,668.23 590.93 56.62%
210.00 1,360.80 0.00 0.00%
960.00 14,976.00 668.60 41.05%
335.11 21,021.45 1,725.33 83.74%
275.00 4,705.25 0.00 0.00%

92.11 2,448.28 0.00 0.00%

0.00 0.00 11.98 100.00%

0.72 3.12 77.42 99.08%


148.72 43,588.34 0.00 0.00%

16.53 5,074.54 4.15 20.07%

197.50 8,595.20 191.25 49.20%


457.06 1,979.07 0.00 0.00%

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
59.66 19,119.84 0.00 0.00%
0.00 #DIV/0!
36.04 1,671.54 16.45 31.34%
756.83 3,277.07 0.00 0.00%
76.32 31,080.56 0.00 0.00%
0.00 #DIV/0!
5.23 262.23 24.67 82.51%
5.26 1,992.28 1.50 22.19%
40.96 17,061.89 0.00 0.00%
0.00 #DIV/0!
16.23 888.59 61.55 79.13%
428.87 1,857.01 1,014.01 70.28%
90.15 29,946.03 2.74 2.95%
1.97 616.29 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 119.99 100.00%
11.67 450.58 0.00 0.00%
100.00 409.00 4.00 3.85%
15.89 5,249.90 0.00 0.00%
35.76 10,743.38 1.65 4.41%
0.00 #DIV/0!
7.77 962.78 100.92 92.85%
18.43 1,455.60 11.59 38.61%
0.00 0.00 5.04 100.00%
0.00 #DIV/0!
0.00 0.00 35.89 100.00%
109.94 2,401.09 28.53 20.60%

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 0.00 52.49 100.00%
0.00 0.00 52.35 100.00%
0.00 0.00 50.19 100.00%
0.00 #DIV/0!
0.00 0.00 160.59 100.00%
0.00 #DIV/0!
0.00 0.00 30.62 100.00%
0.00 0.00 13.60 100.00%
0.00 0.00 32.37 100.00%
0.00 0.00 50.71 100.00%
0.00 0.00 24.31 100.00%
0.00 0.00 194.51 100.00%
0.00 0.00 39.74 100.00%
0.00 0.00 98.52 100.00%
0.00 #DIV/0!
0.00 0.00 74.85 100.00%
0.00 0.00 4.31 100.00%
0.00 #DIV/0!
0.00 0.00 20.97 100.00%
0.00 #DIV/0!
0.00 0.00 20.30 100.00%
0.00 0.00 41.68 100.00%
0.00 #DIV/0!
0.00 0.00 0.54 100.00%
0.00 0.00 1.50 100.00%
0.00 #DIV/0!
0.00 0.00 276.42 100.00%

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 #DIV/0!
0.00 0.00 210.77 100.00%
0.00 0.00 104.84 100.00%
0.00 0.00 5,176.03 100.00%
0.00 #DIV/0!
0.00 0.00 27.80 100.00%
0.00 0.00 72.80 100.00%
0.00 #DIV/0!
0.00 #DIV/0!
216.56 2,336.68 90.89 29.56%
0.00 #DIV/0!
0.00 #DIV/0!
46.10 12,874.35 21.20 31.50%
0.00 #DIV/0!
41.03 9,537.01 59.46 59.17%
0.00 #DIV/0!
4.51 1,199.61 12.32 73.20%
0.00 #DIV/0!
8.20 1,045.83 100.74 92.47%
0.00 0.00 138.85 100.00%
0.00 0.00 116.29 100.00%
1.00 60,000.00 0.00 0.00%
1.00 150,000.00 0.00 0.00%
0.00 #DIV/0!
0.00 0.00 8.57 100.00%
0.00 #DIV/0!
0.00 0.00 19.20 100.00%

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

DEDUCTIVO N 07 DEDUCTIVO VALORIZACIN FINAL DE


PART. NO EJECUTADAS MENORES METRADOS PART. NO EJECUTADA OBRA - 2014
METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL
0.00 0.00 188.84 100.00%
0.00 0.00 7.35 100.00%
0.00 0.00 1.00 100.00%
0.00 0.00 1.00 100.00%
0.00 0.00 24.28 100.00%
0.00 #DIV/0!
0.00 0.00 14.08 100.00%
0.00 #DIV/0!
0.00 #DIV/0!
0.00 0.00 13.00 100.00%
0.00 #DIV/0!
0.00 0.00 5.00 100.00%
0.00 0.00 0.00 483,801.17 #DIV/0!
0.00 0.00 0.00 956,593.03 #DIV/0!
0.00 0.00 0.00 95,659.30 #DIV/0!
0.00 0.00 0.00 19,131.86 #DIV/0!
0.00 0.00 0.00 7,652.74 #DIV/0!
0.00 0.00 0.00 14,348.90 #DIV/0!
0.00 0.00 0.00 1,093,385.83 #DIV/0!

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
A EXPEDIENTE TCNICO
02.00.00 OBRAS PRELIMINARES
02.04.00 LIMPIEZA DE TERRENO
02.04.04 ELIMINACION DE BASURA Y ELEMENTOS SUELTOS LIVIANOS M2 1,283.30 1.36 1,745.29 - -
02.05.00 TRAZOS, NIVELES Y REPLANTEO
02.05.01 TRAZO Y REPLANTEO PRELIMINAR. M2 1,283.30 1.87 2,399.77 - -
02.05.02 TRAZO DURANTE LA EJECUCION DE LA OBRA M2 1,283.30 1.08 1,385.96 - -
03.00.00 MOVIMIENTO DE TIERRAS
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 533.31 33.87 18,063.21 - -
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 59.67 29.03 1,732.22 - -
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 55.01 25.40 1,397.25 - -
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 0.00 20.15 0.00 - -
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 0.00 45.35 0.00 - -
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 165.75 26.58 4,405.64 - -
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 0.00 222.65 0.00 - -
04.03.00 BASE DE CONCRETO
04.03.01 CONCRETO f'c=100 kg/cm2 + 30% P.G. PARA BASE DE CONCRETO M2 86.48 27.61 2,387.71 - -
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 99.18 33.45 3,317.57 - -
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 0.00 167.28 0.00 - -
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 0.00 235.26 0.00 - -
04.05.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 163.29 33.95 5,543.70 - -
04.08.00 FALSO PISO

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
04.08.01 FALSO PISO MEZCLA 1:8 e=4" M2 1,082.36 26.63 28,823.25 - -
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 2.40 299.23 718.15 - -
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 6,696.57 4.33 28,996.15 - -
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 0.00 311.23 0.00 - -
05.02.02 VIGAS DE CIMENTACION ENCOFRADO Y DESENCOFRADO M2 165.46 45.77 7,573.10 - -
05.02.03 VIGAS DE CIMENTACION ACERO fy= 4200kg/cm2 KG 1,803.96 4.33 7,811.15 - -
05.03.00 SOBRECIMIENTO ARMADO
05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 0.00 4.33 0.00 - -
05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 0.00 271.09 0.00 - -
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 105.43 43.52 4,588.31 - -
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 2,245.71 4.33 9,723.92 - -
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 0.00 425.28 0.00 - -
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 658.79 46.38 30,554.68 - -
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 9,692.81 4.33 41,969.87 - -
05.06.00 COLUMNAS
05.06.01 CONCRETO EN COLUMNETAS DE ARRIOSTRE f'c=175 kg/cm2 M3 0.00 395.44 0.00 - -
05.06.02 COLUMNAS, CONCRETO f'c= 210kg/cm2 M3 0.00 436.79 0.00 - -
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 359.11 50.14 18,005.78 - -
05.06.04 COLUMNAS, ENCOFRADO Y DESENCOFRADO CARAVISTA M2 96.10 70.35 6,760.64 - -
05.06.05 COLUMNAS, ACERO fy=4200 kg/cm2 KG 5,583.97 4.33 24,178.59 - -
05.07.00 VIGAS
05.07.02 VIGAS, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 0.00 338.49 0.00 - -

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 543.17 54.75 29,738.56 - -
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 12,224.59 4.33 52,932.47 - -
05.08.00 LOSAS
05.08.01 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 M3 0.00 305.22 0.00 - -
05.08.02 LOSAS MACIZAS, ENCOFRADO Y DESENCOFRADO M2 187.06 43.15 8,071.64 - -
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 3,912.31 4.33 16,940.30 - -
05.08.04 LOSA ALIGERADA, CONCRETO f'c=210 kg/cm2 (2 PISOS) M3 0.00 333.88 0.00 - -
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 168.64 38.61 6,511.19 - -
05.08.06 LOSA ALIGERADA, ACERO fy= 4200kg/cm2 KG 1,842.44 4.33 7,977.77 - -
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 1,404.77 4.09 5,745.51 - -
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.06.00 ARMADURA PRINCIPAL VMP-01 (AUDITORIO) INC/ PINTADO Y COLOCADO PZA 0.00 10,230.68 0.00 - -
06.10.00 COBERTURA METALICA VL-1 (EN AUDITORIO LOBBY) PZA 0.00 1,362.22 0.00 - -
06.20.00 CORREA VL-02 (EN AUDITORIO LOBBY) INC. PINTADO Y COLOCADO PZA 0.00 377.97 0.00 - -
06.21.00 COBERTURA METALICA EN INGRESO DE AUDITORIO PZA 0.00 3,482.84 0.00 - -
06.23.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR 6 mm M2 0.00 37.53 0.00 - -
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 416.07 123.91 51,555.23 - -
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 588.13 78.98 46,450.51 - -
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 208.16 19.51 4,061.20 - -
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 2,036.62 21.84 44,479.78 - -
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 1,387.62 29.33 40,698.89 - -
08.04.00 TARRAJEO DE COLUMNAS M2 167.03 30.56 5,104.44 - -
08.05.00 TARRAJEO DE VIGAS M2 352.97 42.73 15,082.41 - -
08.08.00 VESTIDURA DE DERRAMES (1:5) ML 908.20 11.01 9,999.28 - -
09.00.00 CIELORRASOS

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 527.13 30.01 15,819.17 - -
09.02.00 VESTIDURA EN FONDO DE ESCALERAS M2 125.68 30.92 3,886.03 - -
09.03.00 CIELO RASO DE CELOTEX (0.60 x 0.60) M2 562.56 140.96 79,298.46 - -
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 634.97 26.40 16,763.21 - -
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 135.13 21.44 2,897.19 - -
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 66.15 56.03 3,706.38 - -
10.05.00 CONTRAPISO DE 48 mm. M2 1,465.23 27.11 39,722.39 - -
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 61.06 49.18 3,002.93 - -
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 368.84 50.10 18,478.88 - -
10.08.00 PISO DE MADERA MACHIHEMBRADO M2 106.31 74.53 7,923.28 - -
10.09.00 PISO DE PORCELANATO M2 0.00 56.24 0.00 - -
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 610.69 24.66 15,059.62 - -
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 183.32 15.45 2,832.29 - -
11.02.00 CONTRAZOCALO DE PORCELANATO ML 0.00 40.25 0.00 - -
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 204.77 15.67 3,208.75 - -
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 107.15 51.17 5,482.87 - -
12.04.00 ZOCALO DE PIEDRA LAJA ML 118.77 62.52 7,425.50 - -
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 0.00 44.53 0.00 - -
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 0.00 25.20 0.00 - -
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2 248.85 34.52 8,590.30 - -
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 248.85 5.51 1,371.16 - -
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M 210.70 4.25 895.48 - -

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 0.00 308.51 0.00 - -
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X3" M2 0.00 228.28 0.00 - -
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.01.00 PUERTA METALICA TERMOACUSTICA ANTIPANICO DE EMERGENCIA UND 3.78 1,729.93 6,539.14 - -
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 0.00 100.74 0.00 - -
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 12.96 261.01 3,382.69 - -
16.13.00 MAMPARA DE ALUMINO M2 0.00 267.27 0.00 - -
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 16.94 247.82 4,198.07 - -
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 0.00 80.12 0.00 - -
17.00.00 CERRAJERIA
17.02.00 BISAGRA CAPUCHINA DE ALUMINIO DE 3" X 3" PZA 87.00 13.46 1,171.02 - -
17.04.00 CERRADURA DOS GOLPES EN PUERTAS PZA 9.00 60.70 546.30 - -
17.05.00 CERRADURA PARA INTERIOR DOBLE PERILLA PZA 9.00 47.70 429.30 - -
17.06.00 CERRADURA DE POMO PARA MAMPARA DE INGRESO PZA 2.00 80.70 161.40 - -
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/ACCESORIO P2 0.00 19.01 0.00 - -
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 0.00 8.82 0.00 - -
18.05.00 VIDRIOS BLOK INCOLORO P2 190.63 30.95 5,900.00 - -
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 652.81 8.14 5,313.87 - -
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 2,819.98 8.14 22,954.64 - -
19.04.00 PINTURA SUPER MATE 2 MANOS EN MUROS EXT. A PARTIR DEL 2DO PISO M2 1,387.62 13.42 18,621.86 - -
19.07.00 PINTURA BARNIZ 2 MANOS EN CARPINTERIA DE MADERA M2 18.62 15.30 284.89 - -
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 0.00 19.72 0.00 - -
20.07.00 LIMPIEZA FINAL DE LA OBRA M2 18.62 1.28 23.83 - -

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
SUB TOTAL 903,321.99 0.00 0.00
B EXPEDIENTE ADICIONAL N 07 MAYORES METRADOS - PARTIDAS NUEVAS
MAYORES METRADOS
03.00.00 MOVIMIENTO DE TIERRAS
03.03.00 CORTE DE TERRENO A MAQUINARIA M3 795.00 4.72 3,752.40 - -
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 87.68 33.87 2,969.72 - -
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 66.20 29.03 1,921.79 - -
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 0.90 25.40 22.86 - -
03.13.00 ACARREO INTERNO, MATERIAL PROCEDENTE DE EXCAVACIONES M3 1,043.60 16.94 17,678.58 - -
03.16.00 ACARREO DE MATERIAL DE CORTE CON MAQUINARIA M3 210.00 6.48 1,360.80 - -
03.20.00 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINARIA M3 1,628.60 15.60 25,406.16 - -
03.24.00 RELLENO MANUAL Y COMPACTADO CON EQUIPO MATERIAL PROPIO M3 2,060.44 62.73 129,251.40 - -
03.25.00 PREPARACION DE MATERIAL DE RELLENO - MATERIAL PROPIO M3 275.00 17.11 4,705.25 - -
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 92.11 26.58 2,448.28 - -
04.03.00 BASE DE CONCRETO
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 11.98 33.45 400.73 - -
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 78.14 4.33 338.35 - -
05.01.05 ZAPATAS, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 148.72 293.09 43,588.34 - -
05.02.00 VIGAS DE CIMENTACION
05.02.04 VIGAS DE CIMENTACION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 20.68 306.99 6,348.55 - -
05.04.00 MUROS DE CONTENCION
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 388.75 43.52 16,918.40 - -
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 457.06 4.33 1,979.07 - -

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
05.04.07 MUROS DE CONTENCION, CONCRETO F'c= 210 KG/CM2 CON ADITIVO M3 59.66 320.48 19,119.84 - -
05.05.00 PLACAS
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 52.49 46.38 2,434.49 - -
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 756.83 4.33 3,277.07 - -
05.05.04 PLACAS, CONCRETO f'c=210 KG/CM2 CON ADITIVO M3 76.32 407.24 31,080.56 - -
05.06.00 COLUMNAS
05.06.03 COLUMNAS, ENCOFRADO Y DESENCOFRADO M2 29.90 50.14 1,499.19 - -
05.06.06 CONCRETO EN COLUMNETAS DE ARRIOSTRE, F'c= 175 KG/CM2 CON ADITIVO M3 6.76 378.76 2,560.42 - -
05.06.07 COLUMNAS, CONCRETO F'c=210 KG/CM2 CON ADITIVO M3 40.96 416.55 17,061.89 - -
05.07.00 VIGAS
05.07.03 VIGAS, ENCOFRADO Y DESENCOFRADO M2 77.78 54.75 4,258.46 - -
05.07.04 VIGAS, ACERO fy= 4200kg/cm2 KG 1,442.88 4.33 6,247.67 - -
05.07.05 VIGAS, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 92.89 332.18 30,856.20 - -
05.07.06 CONCRETO EN VIGUETAS DE ARRIOSTRE F'c=175 KG/CM2 CON ADITIVO M3 1.97 312.84 616.29 - -
05.08.00 LOSAS
05.08.03 LOSAS MACIZAS ACERO fy= 4200kg/cm2 KG 119.99 4.33 519.56 - -
05.08.05 LOSA ALIGERADA, ENCOFRADO Y DESENCOFRADO M2 11.67 38.61 450.58 - -
05.08.07 LOSA ALIGERADA, LADRILLO HUECO 15x30x30 UND 104.00 4.09 425.36 - -
05.08.08 LOSA ALIGERADA, CONCRETO 210 KG/CM2 (2 PISOS), CON ADITIVO M3 15.89 330.39 5,249.90 - -
05.08.09 LOSAS MACIZAS, CONCRETO f'c=210 kg/cm2 CON ADITIVO M3 37.41 300.43 11,239.09 - -
07.00.00 MUROS Y TABIQUES DE ALBAILERIA
07.01.00 MURO DE LADRILLO KK CABEZA M1:1:4 E=1.5 cm M2 108.69 123.91 13,467.78 - -
07.02.00 MURO DE LADRILLO KK SOGA M:1:1:4 E=1.5 cm M2 30.02 78.98 2,370.98 - -
07.05.00 TABIQUERIA SISTEMA DRIWALL M2 5.04 221.97 1,118.73 - -
08.00.00 REVOQUES ENLUCIDOS Y MOLDURAS
08.01.00 TARRAJEO PRIMARIO, MORTERO C:A 1:5 M2 35.89 19.51 700.21 - -
08.02.00 TARRAJEO EN MURO: INTERIOR Y EXTERIOR M2 138.47 21.84 3,024.22 - -

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 52.49 29.33 1,539.42 - -
08.04.00 TARRAJEO DE COLUMNAS M2 52.35 30.56 1,599.96 - -
08.05.00 TARRAJEO DE VIGAS M2 50.19 42.73 2,144.53 - -
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 160.59 30.01 4,819.16 - -
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 30.62 26.40 808.37 - -
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 13.60 21.44 291.67 - -
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 32.37 56.03 1,813.69 - -
10.05.00 CONTRAPISO DE 48 mm. M2 50.71 27.11 1,374.75 - -
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 24.31 49.18 1,195.66 - -
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 194.51 50.10 9,745.05 - -
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 39.74 24.66 979.99 - -
10.13.00 CONTRAPISO f'c = 140 KG/CM2 E=5 cm PARA BASE DE COLOCACION DE ADOQUINES M2 98.52 396.62 39,076.67 - -
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 74.85 15.45 1,156.43 - -
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 4.31 15.67 67.54 - -
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 20.97 51.17 1,073.03 - -
15.00.00 CARPINTERIA DE MADERA
15.14.00 PUERTA CON TABLERO REBAJADO, C/ACABADO M2 20.30 650.38 13,202.71 - -
15.20.00 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM INC./MARCO CEDRO 2"x3"C/ ACABADO Y C M2 41.68 355.14 14,802.24 - -
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 0.54 261.01 140.95 - -
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 1.50 247.82 371.73 - -
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.13.00 VIDRIO SISTEMA MODUGLAS TEMPLADO INCOLORO DE 6 MM, INC./ COLOCADO Y ACCESORIO P2 276.42 33.50 9,260.07 - -

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 210.77 8.14 1,715.69 - -
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 104.84 8.14 853.41 - -
19.16.00 EMPASTADO DE SUPERFICIE M2 5,176.03 7.58 39,234.27 - -
20.00.00 VARIOS
20.12.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 2" ML 27.80 18.49 514.02 - -
20.13.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 1" ML 72.80 11.21 816.09 - -
PARTIDAS NUEVAS
03.00.00 MOVIMIENTO DE TIERRAS
03.39.00 COMPACTADO Y PERFILADO EN ZONA DE EXCAVACION C/ EQUIPO M2 307.45 10.79 3,317.43 - -
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUB ZAPATAS
04.02.03 SUB ZAPATA CONCRETO F'C= 140 KG/CM2 + 30% P.G. CON ADITIVO M3 67.30 279.27 18,794.87 - -
04.04.00 CIMIENTOS CORRIDOS
04.04.05 CONCRETO 140 KG/CM2 +30% PG. EN CIMIENTO CORRIDO CON ADITIVO M3 100.49 232.44 23,357.90 - -
04.05.00 SOBRECIMIENTOS
04.05.03 SOBRECIMIENTO, CONCRETO 140 KG/CM2 CON ADITIVO M3 16.83 265.99 4,476.61 - -
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.36.00 COBERTURA METALICA EN TERRAZA DE AUDITORIO M2 108.94 127.54 13,893.89 - -
06.37.00 COBERTURA METALICA SOBRE RAMPA DE AUDITORIO M2 138.85 155.41 21,578.68 - -
06.38.00 COBERTURA TRASLUCIDA DE POLICARBONATO COLOR E=8.00 MM M2 116.29 86.71 10,083.51 - -
06.39.00 TECHO DE AUDITORIO CON PLANCHA TERMOACUSTICA CINDULIT 180 INC./SUMINISTRO E INS GLB 1.00 60,000.00 60,000.00 - -
06.40.00 ESTRUCTURA METALICA PARA TECHO DE AUDITORIO INC./ SUMINISTRO E INSTALACION GLB 1.00 ### 150,000.00 - -
15.00.00 CARPINTERIA DE MADERA
15.25.00 REVESTIMIENTO CON MADERA ESTRUCUTRAL EN MADERA Y DESCANSO M2 8.57 122.61 1,050.31 - -
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.65.00 PASAMANO METALICO INC./ COLOCADO Y PINTADO ML 19.20 50.78 974.98 - -

[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS

ENTIDAD: Gobierno Regional Moquegua


PROYECTO : Mejoramiento e Implementacin de la Infraestructura del Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui" del Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegua
SNIP: 86159
UBICACIN: Samegua / Mariscal Nieto / Moquegua
FTE. FTO.: Recursos Ordinarios
PPTO INICIAL: S/. 38258,125.30 N.S.
COMPONT. : CONSTRUCCIN AUDITORIO

PRESUPUESTO ORIGINAL APROBADO MEDIANTE


EJECUTADO AO 2010 EJECUTADO AO 2011 EJECUTADO AO 2012
ITEM DESCRIPCIN RESOLUCIN
UND. CANTIDAD P.U. PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD
16.66.00 BARANDA METALICA INC./ COLOCADO Y PINTADO ML 188.84 89.87 16,971.05 - -
16.67.00 CLARABOYA DE TUBO METALICO M2 7.35 163.70 1,203.20 - -
16.68.00 ESTRUCTURA EN ESCALERA Y DESCANSO TERRAZA DE AUDITORIO (SEGN DISEO) GLB 1.00 7,180.94 7,180.94 - -
16.69.00 ESCALERA TIPO GATO CON TAPA METALICA GLB 1.00 2,595.77 2,595.77 - -
16.70.00 REJILLA METALICA PARA EVACIANDION DE AGUAS FLUVIALES ML 24.28 163.83 3,977.79 - -
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.20.00 MAMPARA DE ALUMINIO CON VIDRIO TEMPLADO PAVONADO DE 10.00 MM M2 14.08 440.00 6,195.20 - -
22.00.00 INSTALACIONES ELECTRICAS
22.03.00 SALIDAS PARA TOMACORRIENTES
22.03.06 SALIDA PARA TOMACORRIENTE TRIPLE PARA ADOSAR Pto 13.00 59.69 775.97 - -
22.12.00 ARTEFACTOS DE ALUMBRADO
22.12.26 ARTEFACTO P/ ADOSAR DE 2 LAMPARAS FLUORECENTES DE 2x40w UND 5.00 105.00 525.00 - -
SUB TOTAL 912,219.35 0.00 0.00
COSTO DIRECTO 1,815,541.34 0.00 0.00
GASTOS GENERALES 10% 219,741.10 0.00 0.00
GASTOS DE SUPERVISIN 2% 43,948.22 0.00 0.00
GASTOS DE LIQUIDACIN 0.8% 17,579.29 0.00 0.00
GASTOS ADMINISTRATIVOS 1.5% 32,961.16 0.00 0.00
PRESUPUESTO TOTAL (S/.) 2,511,640.75 0.00 0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL

- 1,283.30 1,745.29 0.00 0.00 1,283.30 1,745.29 0.00

- 1,283.30 2,399.77 0.00 0.00 1,283.30 2,399.77 0.00


- 0.00 0.00 1,283.30 1,385.96 1,283.30 1,385.96 0.00

- 264.27 8,950.82 87.73 2,971.42 352.00 11,922.24 -181.31


- 59.67 1,732.22 0.00 0.00 59.67 1,732.22 0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -55.01
- 0.00 0.00 0.00 0.00 0.00 0.00 647.99
- 0.00 0.00 0.00 0.00 0.00 0.00 81.65
0.00
0.00
- 165.75 4,405.64 0.00 0.00 165.75 4,405.64 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 50.81
0.00
- 82.84 2,287.21 0.00 0.00 82.84 2,287.21 -3.64
- 99.18 3,317.57 0.00 0.00 99.18 3,317.57 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 100.49
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 16.83
- 52.28 1,774.91 3.35 113.73 55.63 1,888.64 -107.66
0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 0.00 0.00 488.08 12,997.57 488.08 12,997.57 -594.28
0.00
0.00
- 0.00 0.00 0.00 0.00 -128.65 -38,495.94 -131.05 128.65
- 5,736.86 24,840.60 290.71 1,258.77 6,027.57 26,099.38 -669.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.68
- 156.18 7,148.36 0.00 0.00 156.18 7,148.36 -9.28
- 1,803.96 7,811.15 0.00 0.00 1,803.96 7,811.15 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 141.01
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.18
- 67.45 2,935.42 0.00 0.00 67.45 2,935.42 -37.98
- 943.04 4,083.36 0.00 0.00 943.04 4,083.36 -1,302.67
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 72.53
- 376.23 17,449.55 282.56 13,105.13 658.79 30,554.68 0.00
- 9,692.81 41,969.87 0.00 0.00 9,692.81 41,969.87 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.08
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.63
- 288.74 14,477.42 66.63 3,340.83 355.37 17,818.25 -3.74
- 34.16 2,403.16 80.56 5,667.40 114.72 8,070.55 18.62
- 5,583.97 24,178.59 0.00 0.00 5,583.97 24,178.59 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.04

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 162.62 8,903.45 303.81 16,633.60 466.43 25,537.04 -76.74
- 6,012.86 26,035.68 5,875.82 25,442.30 11,888.68 51,477.98 -335.91
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.41
- 0.00 0.00 0.00 0.00 0.00 0.00 -187.06
- 1,607.15 6,958.96 2,248.72 9,736.96 3,855.87 16,695.92 -56.44
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.71
- 168.64 6,511.19 0.00 0.00 168.64 6,511.19 0.00
- 1,656.86 7,174.20 0.00 0.00 1,656.86 7,174.20 -185.58
- 1,404.77 5,745.51 0.00 0.00 1,404.77 5,745.51 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 52
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 123.33
0.00
- 328.93 40,757.72 65.17 8,075.21 394.10 48,832.93 -21.97
- 247.07 19,513.59 135.19 10,677.31 382.26 30,190.89 -205.87
0.00
- 0.00 0.00 152.28 2,970.98 152.28 2,970.98 -55.88
- 92.51 2,020.42 930.78 20,328.24 1,023.29 22,348.65 -1,013.33
- 0.00 0.00 0.00 0.00 0.00 0.00 -1,387.62
- 4.35 132.94 163.46 4,995.34 167.81 5,128.27 0.78
- 1.31 55.98 150.68 6,438.56 151.99 6,494.53 -200.98
- 10.55 116.16 82.70 910.53 93.25 1,026.68 -814.95
0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 13.62 408.74 299.35 8,983.49 312.97 9,392.23 -214.16
- 0.00 0.00 15.88 491.01 15.88 491.01 -109.80
- 0.00 0.00 0.00 0.00 0.00 0.00 -562.56
0.00
- 0.00 0.00 128.00 3,379.20 128.00 3,379.20 -506.97
- 0.00 0.00 109.97 2,357.76 109.97 2,357.76 -25.16
- 0.00 0.00 0.00 0.00 0.00 0.00 -66.15
- 0.00 0.00 452.28 12,261.31 452.28 12,261.31 -1,012.95
- 0.00 0.00 0.00 0.00 0.00 0.00 -61.06
- 0.00 0.00 0.00 0.00 0.00 0.00 -368.84
- 0.00 0.00 0.00 0.00 0.00 0.00 -106.31
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 143.82
- 0.00 0.00 0.00 0.00 0.00 0.00 -610.69
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -183.32
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61.48
- 0.00 0.00 0.00 0.00 0.00 0.00 -204.77
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -107.15
- 0.00 0.00 0.00 0.00 0.00 0.00 -118.77
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.61
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.61
0.00
- 0.00 0.00 0.00 0.00 -158.79 -5,481.43 -407.64
- 0.00 0.00 0.00 0.00 -158.79 -874.93 -407.64
- 0.00 0.00 0.00 0.00 -96.81 -411.44 -307.51

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.62
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.16
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -3.78
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.13
- 0.00 0.00 0.00 0.00 0.00 0.00 -12.96
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.08
- 0.00 0.00 0.00 0.00 0.00 0.00 -16.94
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201.75
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -87.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -9.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -9.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -2.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 270.65
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 151.64
- 0.00 0.00 0.00 0.00 0.00 0.00 -190.63
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -652.81
- 0.00 0.00 0.00 0.00 0.00 0.00 -2,819.98
- 0.00 0.00 0.00 0.00 0.00 0.00 -1,387.62
- 0.00 0.00 0.00 0.00 0.00 0.00 -18.62
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 45.07
- 0.00 0.00 18.62 23.83 18.62 23.83 0.00

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
0.00 298,245.43 174,546.43 472,791.86 0.00
0.00
0.00
0.00
- 795.00 3,752.40 0.00 0.00 795.00 3,752.40 0.00 0
- 17.84 604.24 0.00 0.00 17.84 604.24 -69.84 -2365.4808
- 53.99 1,567.33 0.00 0.00 53.99 1,567.33 -12.21 -354.4563
- 0.70 17.78 0.00 0.00 0.70 17.78 -0.20 -5.08
- 349.00 5,912.06 103.67 1,756.17 452.67 7,668.23 -590.93 -10010.3542
- 210.00 1,360.80 0.00 0.00 210.00 1,360.80 0.00 0
- 870.00 13,572.00 90.00 1,404.00 960.00 14,976.00 -668.60 -10430.16
- 252.23 15,822.39 82.88 5,199.06 335.11 21,021.45 -1,725.33 -108229.9509
- 275.00 4,705.25 0.00 0.00 275.00 4,705.25 0.00 0
0.00 0
0.00 0
- 92.11 2,448.28 0.00 0.00 92.11 2,448.28 0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -11.98 -400.731
0.00 0
0.00 0
- 0.72 3.12 0.00 0.00 0.72 3.12 -77.42 -335.2286
- 148.72 43,588.34 0.00 0.00 148.72 43,588.34 0.00 0
0.00 0
- 16.53 5,074.54 0.00 0.00 16.53 5,074.54 -4.15 -1274.0085
0.00 0
- 197.50 8,595.20 0.00 0.00 197.50 8,595.20 -191.25 -8323.2
- 457.06 1,979.07 0.00 0.00 457.06 1,979.07 0.00 0

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 59.66 19,119.84 0.00 0.00 59.66 19,119.84 0.00 0
0.00 0
- 36.04 1,671.54 0.00 0.00 36.04 1,671.54 -16.45 -762.951
- 756.83 3,277.07 0.00 0.00 756.83 3,277.07 0.00 0
- 49.57 20,186.89 26.75 10,893.67 76.32 31,080.56 0.00 0
0.00 0
- 5.20 260.73 0.03 1.50 5.23 262.23 -24.67 -1236.9538
- 5.03 1,905.16 0.23 87.11 5.26 1,992.28 -1.50 -568.14
- 28.33 11,800.86 12.63 5,261.03 40.96 17,061.89 0.00 0
0.00 0
- 6.21 340.00 10.02 548.60 16.23 888.59 -61.55 -3369.8625
- 155.10 671.58 273.77 1,185.42 428.87 1,857.01 -1,014.01 -4390.6633
- 47.69 15,841.66 42.46 14,104.36 90.15 29,946.03 -2.74 -910.1732
- 0.00 0.00 1.97 616.29 1.97 616.29 0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -119.99 -519.5567
- 11.67 450.58 0.00 0.00 11.67 450.58 0.00 0
- 100.00 409.00 0.00 0.00 100.00 409.00 -4.00 -16.36
- 15.89 5,249.90 0.00 0.00 15.89 5,249.90 0.00 0
- 19.11 5,741.22 16.65 5,002.16 35.76 10,743.38 -1.65 -495.7095
0.00 0
- 7.77 962.78 0.00 0.00 7.77 962.78 -100.92 -12504.9972
- 18.43 1,455.60 0.00 0.00 18.43 1,455.60 -11.59 -915.3782
- 0.00 0.00 0.00 0.00 0.00 0.00 -5.04 -1118.7288
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -35.89 -700.2139
- 109.94 2,401.09 0.00 0.00 109.94 2,401.09 -28.53 -623.1283968

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 0.00 0.00 0.00 0.00 0.00 0.00 -52.49 -1539.423179
- 0.00 0.00 0.00 0.00 0.00 0.00 -52.35 -1599.964216
- 0.00 0.00 0.00 0.00 0.00 0.00 -50.19 -2144.53324
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -160.59 -4819.15585
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -30.62 -808.368
- 0.00 0.00 0.00 0.00 0.00 0.00 -13.60 -291.66976
- 0.00 0.00 0.00 0.00 0.00 0.00 -32.37 -1813.6911
- 0.00 0.00 0.00 0.00 0.00 0.00 -50.71 -1374.7481
- 0.00 0.00 0.00 0.00 0.00 0.00 -24.31 -1195.66416
- 0.00 0.00 0.00 0.00 0.00 0.00 -194.51 -9745.0512
- 0.00 0.00 0.00 0.00 0.00 0.00 -39.74 -979.9884
- 0.00 0.00 0.00 0.00 0.00 0.00 -98.52 -39076.668204
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -74.85 -1156.4325
- 0.00 0.00 0.00 0.00 0.00 0.00 -4.31 -67.5377
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -20.97 -1073.0349
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -20.30 -13202.714
- 0.00 0.00 0.00 0.00 0.00 0.00 -41.68 -14802.2352
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -0.54 -140.9454
- 0.00 0.00 0.00 0.00 0.00 0.00 -1.50 -371.73
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -276.42 -9260.07

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
0.00 0.00 0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -210.77 -1715.69222
- 0.00 0.00 0.00 0.00 0.00 0.00 -104.84 -853.406961
- 0.00 0.00 0.00 0.00 0.00 0.00 -5,176.03 -39234.27051572
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -27.80 -514.022
- 0.00 0.00 0.00 0.00 0.00 0.00 -72.80 -816.088
0.00 0
0.00 0
- 216.56 2,336.68 0.00 0.00 216.56 2,336.68 -90.89 -980.74626
0.00 0
0.00 0
- 46.10 12,874.35 0.00 0.00 46.10 12,874.35 -21.20 -5920.524
0.00 0
- 41.03 9,537.01 0.00 0.00 41.03 9,537.01 -59.46 -13820.8824
0.00 0
- 4.51 1,199.61 0.00 0.00 4.51 1,199.61 -12.32 -3276.9968
0.00 0
- 8.20 1,045.83 0.00 0.00 8.20 1,045.83 -100.74 -12848.06075
- 0.00 0.00 0.00 0.00 0.00 0.00 -138.85 -21578.6785
- 0.00 0.00 0.00 0.00 0.00 0.00 -116.29 -10083.5059
- 0.00 0.00 1.00 60,000.00 1.00 60,000.00 0.00 0
- 0.00 0.00 1.00 150,000.00 1.00 150,000.00 0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -8.57 -1050.314043
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -19.20 -974.976

[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui

VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 0.00 0.00 0.00 0.00 0.00 0.00 -188.84 -16971.0508
- 0.00 0.00 0.00 0.00 0.00 0.00 -7.35 -1203.195
- 0.00 0.00 0.00 0.00 0.00 0.00 -1.00 -7180.94
- 0.00 0.00 0.00 0.00 0.00 0.00 -1.00 -2595.77
- 0.00 0.00 0.00 0.00 0.00 0.00 -24.28 -3977.7924
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -14.08 -6195.2
0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -13.00 -775.97
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -5.00 -525
0.00 227,741.79 256,059.38 483,801.17 428,418.17
0.00 525,987.22 430,605.82 956,593.03 858,948.30 479,384.01
0.00 52,598.72 43,060.58 95,659.30
0.00 10,519.74 8,612.12 19,131.86
0.00 4,207.90 3,444.85 7,652.74
0.00 7,889.81 6,459.09 14,348.90
0.00 601,203.39 492,182.46 1,093,385.83

[AKSP]
CUADRO COMPARATIVO DE LA SUB COMPONENTE DE
CONSTRUCCIN AUDITORIO

PRESUPUESTO DEDUCTIVO APROBADO SEGN RESOLUCIN


VALORIZADO 2014
DESCRIPCIN EJECUTIVA
S/.
S/. % DESCRIPCIN S/.
EXPEDIENTE TECNICO 1,285,191.63 472,791.86 36.79%
EXPEDIENTE DE MODIFICACIN N 08
ADICIONAL N 07 912,219.37 483,801.17 53.04% DEDUCTIVO N 07 379,564.29
MAYOR METRADO N 7 565,266.27 246,807.69 43.66% MENOR METRADO N 7 10,498.02
PARTIDA NUEVA N 7 346,953.10 236,993.49 68.31% PARTIDA NO EJECUTADA N 7 369,066.27
TOTAL (C.D.) 2,197,411.00 956,593.03 43.53% TOTAL (C.D.) 379,564.29
1,285,191.63

C ON ST R U C C I ON D EL AU D I T OR I O
1,400,000.00

912,219.37
1,200,000.00

1,000,000.00

483,801.17
472,791.86

800,000.00

600,000.00

400,000.00

200,000.00

0.00
E X P. T EC . AD I C . N 0 7
PROGRAMADO EJECUTADO