VALORIZADO
COMPONENTES MONTO C.D. S/. MONTO P.T. S/.
MONTO C.D. S/. MONTO P.T. S/.
EXPEDIENTE TECNICO 1,285,191.63 1,468,974.04 472,791.86 540,401.10
ADICIONAL N 07 912,219.37 1,042,666.74 483,801.17 552,984.74
MAYORES METRADOS 565,266.27 646,099.35 246,807.69 282,101.19
PARTIDAS NUEVAS 346,953.10 396,567.39 236,993.49 270,883.55
DEDUCTIVO N 07 379,564.29 433,841.98
MENORES METRADOS 10,498.02 11,999.24 10,498.02
PARTIDAS NO EJECUTADAS 369,066.27 421,842.75 347,663.79
SUMATORIA EXP. TEC. + ADIC. ### ### #REF! #REF!
SUMATORIA DEDUC. 379,564.29 433,841.98
SUMATORIA EXP. TEC. - DEDUC. ### ### #REF! #REF!
VALORIZADO 956,593.03 ###
RESTANTE
MONTO C.D. S/. MONTO P.T. S/.
812,399.77 928,572.94
428,418.20 489,682.00
318,458.58 363,998.16
109,959.61 125,683.84
#REF! #REF!
#REF! #REF!
#REF! #REF!
Proyecto: Mejoramiento e Implementacin de la Infraestructura
Instituto Superior Tecnolgico Pblico "Jos Carlos Mariategui
Distrito de Samegua Prov. Mariscal Nieto, Regin Moquegu
COMPONENTE : INFRAESTRUCTURA
[AKSP]
la Infraestructura del
Carlos Mariategui" del
Regin Moquegua
ITORIO
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES
METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
A EXPEDIENTE TCNICO
02.00.00 OBRAS PRELIMINARES
02.04.00 LIMPIEZA DE TERRENO
02.04.04 ELIMINACION DE BASURA Y ELEMENTOS SUELTOS LIVIANOS M2 1,283.30 1,283.30
02.05.00 TRAZOS, NIVELES Y REPLANTEO
02.05.01 TRAZO Y REPLANTEO PRELIMINAR. M2 1,283.30 1,283.30
02.05.02 TRAZO DURANTE LA EJECUCION DE LA OBRA M2 1,283.30 0.00
03.00.00 MOVIMIENTO DE TIERRAS
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 533.31 264.27
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 59.67 59.67
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 55.01 0.00
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 647.99 0.00
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 81.65 0.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 165.75 165.75
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 50.81 0.00
04.03.00 BASE DE CONCRETO
04.03.01 CONCRETO f'c=100 kg/cm2 + 30% P.G. PARA BASE DE CONCRETO M2 86.48 82.84
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 99.18 99.18
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 100.49 0.00
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 16.83 0.00
04.05.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 163.29 52.28
04.08.00 FALSO PISO
04.08.01 FALSO PISO MEZCLA 1:8 e=4" M2 1,082.36 0.00
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 131.05 0.00
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 6,696.57 5,736.86
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 20.68 0.00
05.02.02 VIGAS DE CIMENTACION ENCOFRADO Y DESENCOFRADO M2 165.46 156.18
05.02.03 VIGAS DE CIMENTACION ACERO fy= 4200kg/cm2 KG 1,803.96 1,803.96
05.03.00 SOBRECIMIENTO ARMADO
05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 141.01 0.00
05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 13.18 0.00
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 105.43 67.45
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 2,245.71 943.04
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 72.53 0.00
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 658.79 376.23
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 9,692.81 9,692.81
05.06.00 COLUMNAS
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES
METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES
METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 183.32 0.00
11.02.00 CONTRAZOCALO DE PORCELANATO ML 61.48 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 204.77 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 107.15 0.00
12.04.00 ZOCALO DE PIEDRA LAJA ML 118.77 0.00
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 16.61 0.00
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 16.61 0.00
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2 407.64 0.00
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 407.64 0.00
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M 307.51 0.00
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 18.62 0.00
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X3" M2 39.16 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.01.00 PUERTA METALICA TERMOACUSTICA ANTIPANICO DE EMERGENCIA UND 3.78 0.00
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 25.13 0.00
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 12.96 0.00
16.13.00 MAMPARA DE ALUMINO M2 14.08 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 16.94 0.00
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 201.75 0.00
17.00.00 CERRAJERIA
17.02.00 BISAGRA CAPUCHINA DE ALUMINIO DE 3" X 3" PZA 87.00 0.00
17.04.00 CERRADURA DOS GOLPES EN PUERTAS PZA 9.00 0.00
17.05.00 CERRADURA PARA INTERIOR DOBLE PERILLA PZA 9.00 0.00
17.06.00 CERRADURA DE POMO PARA MAMPARA DE INGRESO PZA 2.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/ACCESOR P2 270.65 0.00
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 151.64 0.00
18.05.00 VIDRIOS BLOK INCOLORO P2 190.63 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 652.81 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 2,819.98 0.00
19.04.00 PINTURA SUPER MATE 2 MANOS EN MUROS EXT. A PARTIR DEL 2DO PISO M2 1,387.62 0.00
19.07.00 PINTURA BARNIZ 2 MANOS EN CARPINTERIA DE MADERA M2 18.62 0.00
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 45.07 0.00
20.07.00 LIMPIEZA FINAL DE LA OBRA M2 18.62 0.00
B EXPEDIENTE ADICIONAL N 07 MAYORES METRADOS - PARTIDAS NUEVAS
MAYORES METRADOS
03.00.00 MOVIMIENTO DE TIERRAS
03.03.00 CORTE DE TERRENO A MAQUINARIA M3 795.00 795.00
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 87.68 17.84
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 66.20 53.99
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES
METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES
METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 52.49 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 52.35 0.00
08.05.00 TARRAJEO DE VIGAS M2 50.19 0.00
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 160.59 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 30.62 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 13.60 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 32.37 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 50.71 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 24.31 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 194.51 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 39.74 0.00
10.13.00 CONTRAPISO f'c = 140 KG/CM2 E=5 cm PARA BASE DE COLOCACION DE ADOQUINES M2 98.52 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 74.85 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 4.31 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 20.97 0.00
15.00.00 CARPINTERIA DE MADERA
15.14.00 PUERTA CON TABLERO REBAJADO, C/ACABADO M2 20.30 0.00
15.20.00 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM INC./MARCO CEDRO 2"x3"C/ ACABADO Y M2 41.68 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 0.54 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 1.50 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.13.00 VIDRIO SISTEMA MODUGLAS TEMPLADO INCOLORO DE 6 MM, INC./ COLOCADO Y ACCESOR P2 276.42 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 210.77 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 104.84 0.00
19.16.00 EMPASTADO DE SUPERFICIE M2 5,176.03 0.00
20.00.00 VARIOS
20.12.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 2" ML 27.80 0.00
20.13.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 1" ML 72.80 0.00
PARTIDAS NUEVAS
03.00.00 MOVIMIENTO DE TIERRAS
03.39.00 COMPACTADO Y PERFILADO EN ZONA DE EXCAVACION C/ EQUIPO M2 307.45 216.56
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUB ZAPATAS
04.02.03 SUB ZAPATA CONCRETO F'C= 140 KG/CM2 + 30% P.G. CON ADITIVO M3 67.30 46.10
04.04.00 CIMIENTOS CORRIDOS
04.04.05 CONCRETO 140 KG/CM2 +30% PG. EN CIMIENTO CORRIDO CON ADITIVO M3 100.49 41.03
04.05.00 SOBRECIMIENTOS
04.05.03 SOBRECIMIENTO, CONCRETO 140 KG/CM2 CON ADITIVO M3 16.83 4.51
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.36.00 COBERTURA METALICA EN TERRAZA DE AUDITORIO M2 108.94 8.20
06.37.00 COBERTURA METALICA SOBRE RAMPA DE AUDITORIO M2 138.85 0.00
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES
METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALES
METRADO - 2013
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2013
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
0.00
0.00
1,283.30
269.04
0.00
55.01
647.99
81.65
0.00
50.81
3.64
0.00
100.49
16.83
111.01
1,082.36
131.05
959.71
20.68
9.28
0.00
141.01
13.18
37.98
1,302.67
72.53
282.56
0.00
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2013
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
4.08
36.63
70.37
80.56
0.00
70.04
380.55
6,211.73
37.41
187.06
2,305.16
14.71
0.00
744.54
0.00
8.00
14.00
52.00
1.00
123.33
87.14
341.06
208.16
1,944.11
1,387.62
162.68
351.66
897.65
513.51
125.68
562.56
634.97
135.13
66.15
1,465.23
61.06
368.84
106.31
143.82
610.69
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2013
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
183.32
61.48
204.77
107.15
118.77
16.61
16.61
407.64
407.64
307.51
18.62
39.16
3.78
25.13
12.96
14.08
16.94
201.75
87.00
9.00
9.00
2.00
270.65
151.64
190.63
652.81
2,819.98
1,387.62
18.62
45.07
18.62
0.00
69.84
12.21
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2013
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
0.20
694.60
0.00
758.60
1,808.21
0.00
0.00
11.98
77.42
0.00
4.15
191.25
0.00
0.00
16.45
0.00
26.75
24.70
1.73
12.63
71.57
1,287.78
45.20
1.97
119.99
0.00
4.00
0.00
18.30
100.92
11.59
5.04
35.89
28.53
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2013
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
52.49
52.35
50.19
160.59
30.62
13.60
32.37
50.71
24.31
194.51
39.74
98.52
74.85
4.31
20.97
20.30
41.68
0.54
1.50
276.42
210.77
104.84
5,176.03
27.80
72.80
90.89
21.20
59.46
12.32
100.74
138.85
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2013
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
116.29
1.00
1.00
8.57
19.20
188.84
7.35
1.00
1.00
24.28
14.08
13.00
5.00
18.62
558.96
158.79
158.79
96.81
647.99
81.65
50.81
100.49
16.83
128.65
20.68
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2013
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
141.01
13.18
72.53
4.08
36.63
70.04
37.41
14.71
8.00
14.00
52.00
1.00
123.33
143.82
61.48
16.61
16.61
18.62
39.16
25.13
14.08
201.75
270.65
151.64
45.07
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
1,283.30 1,745.29
1,283.30 2,399.77
0.00 0.00
264.27 8,950.82
59.67 1,732.22
0.00 0.00
647.99 13,057.00 -647.99 0.00
81.65 3,702.83 -81.65 0.00
165.75 4,405.64
82.84 2,287.21
99.18 3,317.57
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
328.93 40,757.72
247.07 19,513.59
0.00 0.00
92.51 2,020.42
0.00 0.00
4.35 132.94
1.31 55.98
10.55 116.16
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
143.82 8,088.44 0.00 0.00
0.00 0.00
0.00 0.00
61.48 2,474.57 0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
0.00 0.00
25.13 2,531.60 0.00 0.00
0.00 0.00 0.00
14.08 3,763.16 0.00 0.00
0.00 0.00 0.00
201.75 16,164.21 0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
795.00 3,752.40
17.84 604.24
53.99 1,567.33
0.70 17.78
349.00 5,912.06
210.00 1,360.80
870.00 13,572.00
252.23 15,822.39
275.00 4,705.25
92.11 2,448.28
0.00 0.00
0.72 3.12
148.72 43,588.34
16.53 5,074.54
197.50 8,595.20
457.06 1,979.07
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
36.04 1,671.54
756.83 3,277.07
49.57 20,186.89
5.20 260.73
5.03 1,905.16
28.33 11,800.86
6.21 340.00
155.10 671.58
47.69 15,841.66
0.00 0.00
0.00 0.00
11.67 450.58
100.00 409.00
15.89 5,249.90
19.11 5,741.22
7.77 962.78
18.43 1,455.60
0.00 0.00
0.00 0.00
109.94 2,401.09
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
216.56 2,336.68
46.10 12,874.35
41.03 9,537.01
4.51 1,199.61
8.20 1,045.83
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00 227,741.79
10,498.02 371,371.62 525,987.22
1,049.80 34,766.38 52,598.72
209.96 6,953.28 10,519.74
83.98 2,781.31 4,207.90
157.47 5,214.96 7,889.81
11,999.23 397,379.72 601,203.39
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE
METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
A EXPEDIENTE TCNICO
02.00.00 OBRAS PRELIMINARES
02.04.00 LIMPIEZA DE TERRENO
02.04.04 ELIMINACION DE BASURA Y ELEMENTOS SUELTOS LIVIANOS M2 1,283.30 1,283.30
02.05.00 TRAZOS, NIVELES Y REPLANTEO
02.05.01 TRAZO Y REPLANTEO PRELIMINAR. M2 1,283.30 1,283.30
02.05.02 TRAZO DURANTE LA EJECUCION DE LA OBRA M2 1,283.30 1,283.30
03.00.00 MOVIMIENTO DE TIERRAS
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 533.31 352.00
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 59.67 59.67
03.09.00 EXCAVACION DE ZANJAS PARA VIGAS DE CIMENTACION M3 55.01 0.00
03.10.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL PROPIO M3 647.99 0.00
03.11.00 RELLENO COMPACTADO CON EQUIPO, MATERIAL DE PRESTAMO M3 81.65 0.00
04.00.00 OBRAS DE CONCRETO SIMPLE
04.01.00 SOLADOS
04.01.01 SOLADOS CONCRETO f'c=100 kg/cm2 E= 10 CM M2 165.75 165.75
04.02.00 SUBAPATAS
04.02.01 CONCRETO f'c=100 kg/cm2 + 50% P.G. SUBZAPATAS M3 50.81 0.00
04.03.00 BASE DE CONCRETO
04.03.01 CONCRETO f'c=100 kg/cm2 + 30% P.G. PARA BASE DE CONCRETO M2 86.48 82.84
04.03.02 BASE DE CONCRETO, ENCOFRADO Y DESENCOFRADO M2 99.18 99.18
04.04.00 CIMIENTOS CORRIDOS
04.04.01 CONCRETO F'C=140 KG/CM2 +30% PG EN CIMIENTOS CORRIDOS M3 100.49 0.00
04.05.00 SOBRECIMIENTOS
04.05.01 CONCRETO f'c=140 kg/cm2 + 30% PM 4" EN SOBRECIMIENTOS M3 16.83 0.00
04.05.02 SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADO M2 163.29 55.63
04.08.00 FALSO PISO
04.08.01 FALSO PISO MEZCLA 1:8 e=4" M2 1,082.36 488.08
05.00.00 OBRAS DE CONCRETO ARMADO
05.01.00 ZAPATAS
05.01.03 ZAPATAS, CONCRETO 210 kg/cm2 M3 131.05 0.00
05.01.04 ZAPATAS, ACERO fy= 4200 kg/cm2 KG 6,696.57 6,027.57
05.02.00 VIGAS DE CIMENTACION
05.02.01 VIGAS DE CIMENTACION CONCRETO f'c=210 kg/cm2 M3 20.68 0.00
05.02.02 VIGAS DE CIMENTACION ENCOFRADO Y DESENCOFRADO M2 165.46 156.18
05.02.03 VIGAS DE CIMENTACION ACERO fy= 4200kg/cm2 KG 1,803.96 1,803.96
05.03.00 SOBRECIMIENTO ARMADO
05.03.04 SOBRECIMIENTO REFORZADO, ACERO fy= 4200kg/cm2 M3 141.01 0.00
05.04.00 MUROS DE CONTENCION
05.04.01 MUROS DE CONTENCION, CONCRETO f'c=140 kg/cm2 M3 13.18 0.00
05.04.04 MUROS DE CONTENCION ENCOFRADO Y DESENCOFRADO (DOS CARAS) M2 105.43 67.45
05.04.06 MUROS DE CONTENCION, ACERO fy= 4200kg/cm2 KG 2,245.71 943.04
05.05.00 PLACAS
05.05.01 PLACAS, CONCRETO f'c=210 kg/cm2 M3 72.53 0.00
05.05.02 PLACAS, ENCOFRADO Y DESENCOFRADO M2 658.79 658.79
05.05.03 PLACAS, ACERO fy= 4200kg/cm2 KG 9,692.81 9,692.81
05.06.00 COLUMNAS
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE
METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE
METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 183.32 0.00
11.02.00 CONTRAZOCALO DE PORCELANATO ML 61.48 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 204.77 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 107.15 0.00
12.04.00 ZOCALO DE PIEDRA LAJA ML 118.77 0.00
13.00.00 REVESTIMIENTO DE GRADAS Y ESCALERAS
13.01.00 REVESTIMIENTO EN ESCALERAS CON CERAMICA ANTIDESLIZANTE M2 16.61 0.00
13.02.00 REVESTIMIENTO C/CEMENTO PULIDO PASO Y CONTRAPASO M 16.61 0.00
14.00.00 CUBIERTAS
14.01.00 CUBIERTA LADRILLO PASTELERO + FRAGUA CON MORTERO 1:1/2:5 M2 407.64 0.00
14.02.00 IMPERMEAB. DE TECHOS CON PINTURA ASFALTICA M2 407.64 0.00
14.03.00 JUNTA DE DILATACION EN COB. PAST C/MORTERO ASFALTICO e=1 M 307.51 0.00
15.00.00 CARPINTERIA DE MADERA
15.01.00 PUERTA C/TABLERO REBAJADO M2 18.62 0.00
15.02.00 PUERTA CONTRAPLACADA 35 mm CON TRIPLAY 4 mm INCLUYE MARCO CEDRO 2"X3" M2 39.16 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.01.00 PUERTA METALICA TERMOACUSTICA ANTIPANICO DE EMERGENCIA UND 3.78 0.00
16.10.00 VENTANA DE ALUMINIO TIPO VITROVEN M2 25.13 0.00
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 12.96 0.00
16.13.00 MAMPARA DE ALUMINO M2 14.08 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 16.94 0.00
16.17.00 BARANDA DE TUBO METALICO DE 2 1/2" ML 201.75 0.00
17.00.00 CERRAJERIA
17.02.00 BISAGRA CAPUCHINA DE ALUMINIO DE 3" X 3" PZA 87.00 0.00
17.04.00 CERRADURA DOS GOLPES EN PUERTAS PZA 9.00 0.00
17.05.00 CERRADURA PARA INTERIOR DOBLE PERILLA PZA 9.00 0.00
17.06.00 CERRADURA DE POMO PARA MAMPARA DE INGRESO PZA 2.00 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.01.00 VIDRIO SISTEMA MODUGLAS CON VIDRIO TEMPLADO COLOR GRISS DE 6mm INC/ACCESORIO P2 270.65 0.00
18.03.00 VIDRIO SEMIDOBLE ARENADO BLANCO P2 151.64 0.00
18.05.00 VIDRIOS BLOK INCOLORO P2 190.63 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 652.81 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 2,819.98 0.00
19.04.00 PINTURA SUPER MATE 2 MANOS EN MUROS EXT. A PARTIR DEL 2DO PISO M2 1,387.62 0.00
19.07.00 PINTURA BARNIZ 2 MANOS EN CARPINTERIA DE MADERA M2 18.62 0.00
20.00.00 VARIOS
20.01.00 JUNTA DE DILATACION CON ESPUMA PLASTICA Y SELLADOR ML 45.07 0.00
20.07.00 LIMPIEZA FINAL DE LA OBRA M2 18.62 18.62
B EXPEDIENTE ADICIONAL N 07 MAYORES METRADOS - PARTIDAS NUEVAS
MAYORES METRADOS
03.00.00 MOVIMIENTO DE TIERRAS
03.03.00 CORTE DE TERRENO A MAQUINARIA M3 795.00 795.00
03.07.00 EXCAVACION DE ZANJAS Y ZAPATAS H=1.00m / MANUAL M3 87.68 17.84
03.08.00 EXCAVACION DE ZANJAS EN CIMIENTOS CORRIDOS H=1.00m / MANUAL M3 66.20 53.99
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE
METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE
METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
08.03.00 TARRAJEO EN MUROS EXTERIORES A PARTIR DEL 2do. PISO M2 52.49 0.00
08.04.00 TARRAJEO DE COLUMNAS M2 52.35 0.00
08.05.00 TARRAJEO DE VIGAS M2 50.19 0.00
09.00.00 CIELORRASOS
09.01.00 CIELO RASO CON MEZCLA C:A 1:5 M2 160.59 0.00
10.00.00 PISOS Y PAVIMENTOS
10.01.00 PISO DE CEMENTO PULIDO E=2" MEZCLA 1:4 M2 30.62 0.00
10.02.00 PISO DE CEMENTO ACABADO PULIDO Y BRUADO 2" M2 13.60 0.00
10.04.00 PISO DE ADOQUINES DE CONCRETO M2 32.37 0.00
10.05.00 CONTRAPISO DE 48 mm. M2 50.71 0.00
10.06.00 PISO CERAMICO 30x30cm - ALTO TRANSITO M2 24.31 0.00
10.07.00 PISO CERAMICO 40x40cm - ALTO TRANSITO M2 194.51 0.00
10.10.00 PISO DE ALFOMBRA TAPIZADO M2 39.74 0.00
10.13.00 CONTRAPISO f'c = 140 KG/CM2 E=5 cm PARA BASE DE COLOCACION DE ADOQUINES M2 98.52 0.00
11.00.00 CONTRAZOCALOS
11.01.00 CONTRAZOCALO DE CERAMICO H = 0.10 m. ML 74.85 0.00
11.03.00 CONTRAZOCALO DE MADERA CEDRO DE 3/4"x4" + RONDON DE 3/4" ML 4.31 0.00
12.00.00 ZOCALOS
12.01.00 ZOCALOS DE CERAMICO M2 20.97 0.00
15.00.00 CARPINTERIA DE MADERA
15.14.00 PUERTA CON TABLERO REBAJADO, C/ACABADO M2 20.30 0.00
15.20.00 PUERTA CONTRAPLACADA 35MM C/TRIPLAY 4MM INC./MARCO CEDRO 2"x3"C/ ACABADO Y CO M2 41.68 0.00
16.00.00 CARPINTERIA METALICA Y HERRERIA
16.11.00 PUERTA DE ALUMINIO EN SS.HH. M2 0.54 0.00
16.14.00 TABIQUERIA DE ALUMINIO CON ACRILICO EN SS.HH. H=1.80m ML 1.50 0.00
18.00.00 VIDRIOS, CRISTALES Y SIMILARES
18.13.00 VIDRIO SISTEMA MODUGLAS TEMPLADO INCOLORO DE 6 MM, INC./ COLOCADO Y ACCESORIO P2 276.42 0.00
19.00.00 PINTURA
19.02.00 PINTURA SUPER MATE 2 MANOS EN CIELO RASO Y VIGAS M2 210.77 0.00
19.03.00 PINTURA SUPER MATE 2 MANOS EN MUROS Y COLUMNAS M2 104.84 0.00
19.16.00 EMPASTADO DE SUPERFICIE M2 5,176.03 0.00
20.00.00 VARIOS
20.12.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 2" ML 27.80 0.00
20.13.00 JUNTA DE DILATACION CON TECKNOPORT Y SELLADOR E= 1" ML 72.80 0.00
PARTIDAS NUEVAS
03.00.00 MOVIMIENTO DE TIERRAS
03.39.00 COMPACTADO Y PERFILADO EN ZONA DE EXCAVACION C/ EQUIPO M2 307.45 216.56
04.00.00 OBRAS DE CONCRETO SIMPLE
04.02.00 SUB ZAPATAS
04.02.03 SUB ZAPATA CONCRETO F'C= 140 KG/CM2 + 30% P.G. CON ADITIVO M3 67.30 46.10
04.04.00 CIMIENTOS CORRIDOS
04.04.05 CONCRETO 140 KG/CM2 +30% PG. EN CIMIENTO CORRIDO CON ADITIVO M3 100.49 41.03
04.05.00 SOBRECIMIENTOS
04.05.03 SOBRECIMIENTO, CONCRETO 140 KG/CM2 CON ADITIVO M3 16.83 4.51
06.00.00 ESTRUCTURAS METALICAS Y COBERTURAS
06.36.00 COBERTURA METALICA EN TERRAZA DE AUDITORIO M2 108.94 8.20
06.37.00 COBERTURA METALICA SOBRE RAMPA DE AUDITORIO M2 138.85 0.00
[AKSP]
FORMATO I.F. 1
METRADOS PROGRAMADOS Y EJECUTADOS SEGN EXPEDIENTE TCNICO Y EXPEDIENTE DE ADICIONALE
METRADO - 2014
ITEM DESCRIPCIN UND
PROGRAMADO EJECUTADO
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2014
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
0.00
0.00
0.00
181.31
0.00
55.01
647.99
81.65
0.00
50.81
3.64
0.00
100.49
16.83
107.66
594.28
131.05
669.00
20.68
9.28
0.00
141.01
13.18
37.98
1,302.67
72.53
0.00
0.00
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2014
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
4.08
36.63
3.74
0.00
0.00
70.04
76.74
335.91
37.41
187.06
56.44
14.71
0.00
744.54
0.00
8.00
14.00
52.00
1.00
123.33
21.97
205.87
55.88
1,013.33
1,387.62
-0.78
200.98
814.95
214.16
109.80
562.56
506.97
25.16
66.15
1,012.95
61.06
368.84
106.31
143.82
610.69
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2014
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
183.32
61.48
204.77
107.15
118.77
16.61
16.61
407.64
407.64
307.51
18.62
39.16
3.78
25.13
12.96
14.08
16.94
201.75
87.00
9.00
9.00
2.00
270.65
151.64
190.63
652.81
2,819.98
1,387.62
18.62
45.07
0.00
0.00
69.84
12.21
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2014
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
0.20
590.93
0.00
668.60
1,725.33
0.00
0.00
11.98
77.42
0.00
4.15
191.25
0.00
0.00
16.45
0.00
0.00
24.67
1.50
0.00
61.55
1,014.01
2.74
0.00
119.99
0.00
4.00
0.00
1.65
100.92
11.59
5.04
35.89
28.53
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2014
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
52.49
52.35
50.19
160.59
30.62
13.60
32.37
50.71
24.31
194.51
39.74
98.52
74.85
4.31
20.97
20.30
41.68
0.54
1.50
276.42
210.77
104.84
5,176.03
27.80
72.80
90.89
21.20
59.46
12.32
100.74
138.85
[AKSP]
XPEDIENTE DE ADICIONALES
METRADO - 2014
MAYOR
DIFERENCIA DEDUCTIVO
METRADO
116.29
0.00
0.00
8.57
19.20
188.84
7.35
1.00
1.00
24.28
14.08
13.00
5.00
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
FORMATO I.F. 2
VALORIZACIN FINAL DE PARTIDAS EJECUTADAS EN EL PROYECTO
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
FORMATO I.F. 3
VALORIZACIN FINAL DEL PROYECTO POR AOS
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 0.00 0.00 488.08 12,997.57 488.08 12,997.57 -594.28
0.00
0.00
- 0.00 0.00 0.00 0.00 -128.65 -38,495.94 -131.05 128.65
- 5,736.86 24,840.60 290.71 1,258.77 6,027.57 26,099.38 -669.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.68
- 156.18 7,148.36 0.00 0.00 156.18 7,148.36 -9.28
- 1,803.96 7,811.15 0.00 0.00 1,803.96 7,811.15 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 141.01
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.18
- 67.45 2,935.42 0.00 0.00 67.45 2,935.42 -37.98
- 943.04 4,083.36 0.00 0.00 943.04 4,083.36 -1,302.67
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 72.53
- 376.23 17,449.55 282.56 13,105.13 658.79 30,554.68 0.00
- 9,692.81 41,969.87 0.00 0.00 9,692.81 41,969.87 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.08
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 36.63
- 288.74 14,477.42 66.63 3,340.83 355.37 17,818.25 -3.74
- 34.16 2,403.16 80.56 5,667.40 114.72 8,070.55 18.62
- 5,583.97 24,178.59 0.00 0.00 5,583.97 24,178.59 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 70.04
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 162.62 8,903.45 303.81 16,633.60 466.43 25,537.04 -76.74
- 6,012.86 26,035.68 5,875.82 25,442.30 11,888.68 51,477.98 -335.91
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 37.41
- 0.00 0.00 0.00 0.00 0.00 0.00 -187.06
- 1,607.15 6,958.96 2,248.72 9,736.96 3,855.87 16,695.92 -56.44
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.71
- 168.64 6,511.19 0.00 0.00 168.64 6,511.19 0.00
- 1,656.86 7,174.20 0.00 0.00 1,656.86 7,174.20 -185.58
- 1,404.77 5,745.51 0.00 0.00 1,404.77 5,745.51 0.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 52
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 123.33
0.00
- 328.93 40,757.72 65.17 8,075.21 394.10 48,832.93 -21.97
- 247.07 19,513.59 135.19 10,677.31 382.26 30,190.89 -205.87
0.00
- 0.00 0.00 152.28 2,970.98 152.28 2,970.98 -55.88
- 92.51 2,020.42 930.78 20,328.24 1,023.29 22,348.65 -1,013.33
- 0.00 0.00 0.00 0.00 0.00 0.00 -1,387.62
- 4.35 132.94 163.46 4,995.34 167.81 5,128.27 0.78
- 1.31 55.98 150.68 6,438.56 151.99 6,494.53 -200.98
- 10.55 116.16 82.70 910.53 93.25 1,026.68 -814.95
0.00
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 13.62 408.74 299.35 8,983.49 312.97 9,392.23 -214.16
- 0.00 0.00 15.88 491.01 15.88 491.01 -109.80
- 0.00 0.00 0.00 0.00 0.00 0.00 -562.56
0.00
- 0.00 0.00 128.00 3,379.20 128.00 3,379.20 -506.97
- 0.00 0.00 109.97 2,357.76 109.97 2,357.76 -25.16
- 0.00 0.00 0.00 0.00 0.00 0.00 -66.15
- 0.00 0.00 452.28 12,261.31 452.28 12,261.31 -1,012.95
- 0.00 0.00 0.00 0.00 0.00 0.00 -61.06
- 0.00 0.00 0.00 0.00 0.00 0.00 -368.84
- 0.00 0.00 0.00 0.00 0.00 0.00 -106.31
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 143.82
- 0.00 0.00 0.00 0.00 0.00 0.00 -610.69
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -183.32
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 61.48
- 0.00 0.00 0.00 0.00 0.00 0.00 -204.77
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -107.15
- 0.00 0.00 0.00 0.00 0.00 0.00 -118.77
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.61
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16.61
0.00
- 0.00 0.00 0.00 0.00 -158.79 -5,481.43 -407.64
- 0.00 0.00 0.00 0.00 -158.79 -874.93 -407.64
- 0.00 0.00 0.00 0.00 -96.81 -411.44 -307.51
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 18.62
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.16
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -3.78
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 25.13
- 0.00 0.00 0.00 0.00 0.00 0.00 -12.96
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.08
- 0.00 0.00 0.00 0.00 0.00 0.00 -16.94
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 201.75
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -87.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -9.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -9.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -2.00
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 270.65
- 0.00 0.00 0.00 0.00 0.00 0.00 0.00 151.64
- 0.00 0.00 0.00 0.00 0.00 0.00 -190.63
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 -652.81
- 0.00 0.00 0.00 0.00 0.00 0.00 -2,819.98
- 0.00 0.00 0.00 0.00 0.00 0.00 -1,387.62
- 0.00 0.00 0.00 0.00 0.00 0.00 -18.62
0.00
- 0.00 0.00 0.00 0.00 0.00 0.00 45.07
- 0.00 0.00 18.62 23.83 18.62 23.83 0.00
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
0.00 298,245.43 174,546.43 472,791.86 0.00
0.00
0.00
0.00
- 795.00 3,752.40 0.00 0.00 795.00 3,752.40 0.00 0
- 17.84 604.24 0.00 0.00 17.84 604.24 -69.84 -2365.4808
- 53.99 1,567.33 0.00 0.00 53.99 1,567.33 -12.21 -354.4563
- 0.70 17.78 0.00 0.00 0.70 17.78 -0.20 -5.08
- 349.00 5,912.06 103.67 1,756.17 452.67 7,668.23 -590.93 -10010.3542
- 210.00 1,360.80 0.00 0.00 210.00 1,360.80 0.00 0
- 870.00 13,572.00 90.00 1,404.00 960.00 14,976.00 -668.60 -10430.16
- 252.23 15,822.39 82.88 5,199.06 335.11 21,021.45 -1,725.33 -108229.9509
- 275.00 4,705.25 0.00 0.00 275.00 4,705.25 0.00 0
0.00 0
0.00 0
- 92.11 2,448.28 0.00 0.00 92.11 2,448.28 0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -11.98 -400.731
0.00 0
0.00 0
- 0.72 3.12 0.00 0.00 0.72 3.12 -77.42 -335.2286
- 148.72 43,588.34 0.00 0.00 148.72 43,588.34 0.00 0
0.00 0
- 16.53 5,074.54 0.00 0.00 16.53 5,074.54 -4.15 -1274.0085
0.00 0
- 197.50 8,595.20 0.00 0.00 197.50 8,595.20 -191.25 -8323.2
- 457.06 1,979.07 0.00 0.00 457.06 1,979.07 0.00 0
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 59.66 19,119.84 0.00 0.00 59.66 19,119.84 0.00 0
0.00 0
- 36.04 1,671.54 0.00 0.00 36.04 1,671.54 -16.45 -762.951
- 756.83 3,277.07 0.00 0.00 756.83 3,277.07 0.00 0
- 49.57 20,186.89 26.75 10,893.67 76.32 31,080.56 0.00 0
0.00 0
- 5.20 260.73 0.03 1.50 5.23 262.23 -24.67 -1236.9538
- 5.03 1,905.16 0.23 87.11 5.26 1,992.28 -1.50 -568.14
- 28.33 11,800.86 12.63 5,261.03 40.96 17,061.89 0.00 0
0.00 0
- 6.21 340.00 10.02 548.60 16.23 888.59 -61.55 -3369.8625
- 155.10 671.58 273.77 1,185.42 428.87 1,857.01 -1,014.01 -4390.6633
- 47.69 15,841.66 42.46 14,104.36 90.15 29,946.03 -2.74 -910.1732
- 0.00 0.00 1.97 616.29 1.97 616.29 0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -119.99 -519.5567
- 11.67 450.58 0.00 0.00 11.67 450.58 0.00 0
- 100.00 409.00 0.00 0.00 100.00 409.00 -4.00 -16.36
- 15.89 5,249.90 0.00 0.00 15.89 5,249.90 0.00 0
- 19.11 5,741.22 16.65 5,002.16 35.76 10,743.38 -1.65 -495.7095
0.00 0
- 7.77 962.78 0.00 0.00 7.77 962.78 -100.92 -12504.9972
- 18.43 1,455.60 0.00 0.00 18.43 1,455.60 -11.59 -915.3782
- 0.00 0.00 0.00 0.00 0.00 0.00 -5.04 -1118.7288
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -35.89 -700.2139
- 109.94 2,401.09 0.00 0.00 109.94 2,401.09 -28.53 -623.1283968
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 0.00 0.00 0.00 0.00 0.00 0.00 -52.49 -1539.423179
- 0.00 0.00 0.00 0.00 0.00 0.00 -52.35 -1599.964216
- 0.00 0.00 0.00 0.00 0.00 0.00 -50.19 -2144.53324
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -160.59 -4819.15585
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -30.62 -808.368
- 0.00 0.00 0.00 0.00 0.00 0.00 -13.60 -291.66976
- 0.00 0.00 0.00 0.00 0.00 0.00 -32.37 -1813.6911
- 0.00 0.00 0.00 0.00 0.00 0.00 -50.71 -1374.7481
- 0.00 0.00 0.00 0.00 0.00 0.00 -24.31 -1195.66416
- 0.00 0.00 0.00 0.00 0.00 0.00 -194.51 -9745.0512
- 0.00 0.00 0.00 0.00 0.00 0.00 -39.74 -979.9884
- 0.00 0.00 0.00 0.00 0.00 0.00 -98.52 -39076.668204
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -74.85 -1156.4325
- 0.00 0.00 0.00 0.00 0.00 0.00 -4.31 -67.5377
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -20.97 -1073.0349
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -20.30 -13202.714
- 0.00 0.00 0.00 0.00 0.00 0.00 -41.68 -14802.2352
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -0.54 -140.9454
- 0.00 0.00 0.00 0.00 0.00 0.00 -1.50 -371.73
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -276.42 -9260.07
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
0.00 0.00 0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -210.77 -1715.69222
- 0.00 0.00 0.00 0.00 0.00 0.00 -104.84 -853.406961
- 0.00 0.00 0.00 0.00 0.00 0.00 -5,176.03 -39234.27051572
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -27.80 -514.022
- 0.00 0.00 0.00 0.00 0.00 0.00 -72.80 -816.088
0.00 0
0.00 0
- 216.56 2,336.68 0.00 0.00 216.56 2,336.68 -90.89 -980.74626
0.00 0
0.00 0
- 46.10 12,874.35 0.00 0.00 46.10 12,874.35 -21.20 -5920.524
0.00 0
- 41.03 9,537.01 0.00 0.00 41.03 9,537.01 -59.46 -13820.8824
0.00 0
- 4.51 1,199.61 0.00 0.00 4.51 1,199.61 -12.32 -3276.9968
0.00 0
- 8.20 1,045.83 0.00 0.00 8.20 1,045.83 -100.74 -12848.06075
- 0.00 0.00 0.00 0.00 0.00 0.00 -138.85 -21578.6785
- 0.00 0.00 0.00 0.00 0.00 0.00 -116.29 -10083.5059
- 0.00 0.00 1.00 60,000.00 1.00 60,000.00 0.00 0
- 0.00 0.00 1.00 150,000.00 1.00 150,000.00 0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -8.57 -1050.314043
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -19.20 -974.976
[AKSP]
RESIDENTE: Arq. Carmen Prez Benavides
INSPECTOR: Ing. Jhonathan Chura Yupanqui
VALORIZACIN FINAL DE
ECUTADO AO 2012 EJECUTADO AO 2013 EJECUTADO AO 2014
OBRA
PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL CANTIDAD PARCIAL
- 0.00 0.00 0.00 0.00 0.00 0.00 -188.84 -16971.0508
- 0.00 0.00 0.00 0.00 0.00 0.00 -7.35 -1203.195
- 0.00 0.00 0.00 0.00 0.00 0.00 -1.00 -7180.94
- 0.00 0.00 0.00 0.00 0.00 0.00 -1.00 -2595.77
- 0.00 0.00 0.00 0.00 0.00 0.00 -24.28 -3977.7924
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -14.08 -6195.2
0.00 0
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -13.00 -775.97
0.00 0
- 0.00 0.00 0.00 0.00 0.00 0.00 -5.00 -525
0.00 227,741.79 256,059.38 483,801.17 428,418.17
0.00 525,987.22 430,605.82 956,593.03 858,948.30 479,384.01
0.00 52,598.72 43,060.58 95,659.30
0.00 10,519.74 8,612.12 19,131.86
0.00 4,207.90 3,444.85 7,652.74
0.00 7,889.81 6,459.09 14,348.90
0.00 601,203.39 492,182.46 1,093,385.83
[AKSP]
CUADRO COMPARATIVO DE LA SUB COMPONENTE DE
CONSTRUCCIN AUDITORIO
C ON ST R U C C I ON D EL AU D I T OR I O
1,400,000.00
912,219.37
1,200,000.00
1,000,000.00
483,801.17
472,791.86
800,000.00
600,000.00
400,000.00
200,000.00
0.00
E X P. T EC . AD I C . N 0 7
PROGRAMADO EJECUTADO
[AKSP]