You are on page 1of 74

SAP Production Planning Overview

A workshop that provides an overview of the


SAP R/3 Production Planning and Control (PP) module

SAP PP Overview 1
Course Contents

Introduction
Organizational Structure
Production
# Master Data
Planning
# Planning Levels
Control
# Production Orders
Integration with other modules

SAP PP Overview 2
Target Group

Audience: All departments with a fundamental knowledge of SAP

SAP PP Overview 3
Manufacturing Methods / Manufacturing
Strategies

Methods of Manufacturing
Repetitive Manufacturing
Discrete Manufacturing
Process Manufacturing
Projects

Manufacturing Strategies
Engineer to Order
Make to Order
Assemble to Order
Make to Stock

SAP PP Overview 4
Lead Times for Manufacturing Strategies

DLT Delivery Lead Time

Design Purchase Manufacture Assemble Ship ETO

DLT

Inventory Manufacture Assemble Ship MTO

DLT

Manufacture Inventory Assemble Ship ATO


DLT

Manufacture Assemble Inventory Ship MTS


DLT

Response Time to customer is shortest for MTS.

SAP PP Overview 5
Organization structure

Client 1000 SSML

Controlling Area - 1000

Company - SSML

Purchase Organizations Plants Sales Organizations

Cost Center Cost center


Profit center
Production Maintenance

SAP PP Overview 6
Production Planning and Control
Master Data

SAP PP Overview 7
Master Data in PP

Material Master
Bill of Material
Work Center
Routing
Production Resources and Tools

SAP PP Overview 8
Master Data in PP
Material Master

SAP PP Overview 9
Material Master

The material master contains information on all the materials that a


company procures, produces, stores, and sells.

The material master is used by all modules in the SAP.

Different departments in a company work with the same material, so data in


a material master record is subdivided in the form of user departments.

A minimum of five fields need to be maintained in the Material Master to


create a material Material Number, Material Type, Industry Sector, Material
Description and Base Unit of Measure.

In PP the material master is used for maintaining data relating to MRP,


Forecasting and Work Scheduling.

SAP PP Overview 10
User departments

SAP PP Overview 11
Material Types in Standard SAP

Material Type Description

FERT Finished Product


HALB Semi Finished Product
ROH Raw Material
ERSA Spare Part
HAWA Trading Goods
HIBE Operating Supply
LEER Empty Containers
NLAG Non stock Item
VERP Packaging
WETT Competitor Product
PROD Production Resources/ Tools

SAP PP Overview 12
MRP Views

MRP 1 contains data relating to MRP Type, Lot Size and MRP Controller.
MRP 2 contains data relating to Procurement Type, Special Procurement
Type, Lead Time and Scheduling Margin Key.
MRP 3 contains data relating to Planning Strategy, Consumption Mode and
Availability Check.
MRP 4 contains data relating to Production Versions, BOM Selection Method
during MRP run and Repetitive Manufacturing.
Work Scheduling contains data related to Set-up Time, Processing Time,
Delivery Tolerances, etc.
Forecasting contains data as to how the material consumption took place
during the last few periods and on the basis of certain formulae, projections
for the future are made.

SAP PP Overview 13
Material Master MRP Key Fields
Basic, General, and Lot Size Data

Procurement Type indicates if the material is externally procured,


or produced internally or both.
Special Procurement identifies special planning rules which may
be used for in-house production or external procurement
MRP Type determines how the material is planned such as MRP,
MPS, or consumption based planning
Lot Size determines which lot-sizing procedure the system uses to
calculate order quantities
MRP Controller is the person who is responsible for planning of
the material

SAP PP Overview 14
Material Master MRP Key Fields
Scheduling Parameters
Planning Time Fence: defines a period during which MRP/MPS will
not automatically add or reschedule orders
Scheduling Margin Key: controls the release period, opening period
for a material and scheduling floats for production
Release period is the number of working days taken to release a
production order
Opening period is the number of working days taken to convert
a planned order into a production order
Order floats allows for safety margin before and after production
Planned Delivery Time: lead-time for purchased material
In-house Production Time: lead-time for manufactured material
GR Processing Time: goods receipt processing time
Example: dock-to-stock time

SAP PP Overview 15
Material Master MRP Key Fields

Availability Check indicates whether the system generates individual


or summarized requirements for sales orders for this material and for
planning, which MRP items the system includes in the availability
check.

Plant Specific Material Status is used to limit the usability of materials


for certain activities such as, purchasing, bills of material, etc.

SAP PP Overview 16
Master Data in PP
Bill Of Materials (BOM)

SAP PP Overview 17
Bill of Materials

A bill of material is a complete, formally structured list of the


components required to produce the product or assembly.

The BOM contains the material number of each component,


together with the quantity , unit of measure and item category of
component.

BOMs are used in product costing and materials requirement


planning.

BOMs are also called List of Ingredients or Recipe List.

The material for which the BOM is created is called the header and
it can contain one or more items below it.

SAP PP Overview 18
BOM Structure

Assembly BOM Header

BOM Items
Component 1 Component 2 Component 3
(assembly)

Component Component Component


31 32 33

Note: BOM items are also known as BOM components.

SAP PP Overview 19
BOM Technical Types

Variant BOM
Simple BOM

Alternative 1

Alternative 2

Multiple BOM
SAP PP Overview 28
Variant BOM
Bike color T Shirt

Red color T Shirt

Black Color T Shirt

Blue Color Fabric

Red Color fabric

Black Color Fabric Buttons Labels

Qty. for variant 1


Qty. for variant 2
Blue Collar

Red Collar

Dyed yarn
Black Collar

Several similar products are represented in one bill of material

SAP PP Overview 29
Multiple BOM

Alt 1 - Lot Size 1 to 100


Alt 2 - Lot Size 101 to 500
T Shirt

Buttons Gassed
Labels Mercerized fabric

Qty. for alternative 1 alternative 1


Qty. for alternative 2

Plain Fabric

alternative 2

The same product can be manufactured using different methods of


production or with different components or component quantities

SAP PP Overview 30
Master Data in PP
Work Centers

SAP PP Overview 31
Work Centers

A work center is a place where production operations are performed.


Machines, machine groups
Employees, groups of employees

Work centers are used in task list operations (routings) and integrated with
Human Resource Management System .

A work center is always created with respect to a plant.

To each work center a work center category is assigned, that determines


which data can be maintained in the work center.

SAP PP Overview 32
Work Center Category

Machine

Person

Processing Unit
Production Line

Machine Group

Statistical Work Center


Zone

Station

SAP PP Overview 33
Work Center Views
Name and description
Basic Data Standard value key
Performance efficiency rate

Default Values Control key


Standard text key
for Task Lists
Wage data

Costing Data and Cost center


HR System Data Activity types
Formula key

Capacity category
Scheduling Data Interoperation times
Formula key

Available capacity
Capacity Data Formula key
Utilization
SAP PP Overview 35
Master Data in PP
Routings

SAP PP Overview 37
Routings
Definition:
A routing describes the processing steps required
to produce a material or provide a service .
Routings are also called task lists.
A routing is always created with reference to
material and a plant.

Examples:
Work steps - Op 10 - Pre-Assembly ...
Op 20 - Assembly ...
Op 30 - Inspection ...
Op 40 - Packaging ...
Op 50 - Delivery ...

SAP PP Overview 38
Routing Structure

A routing is composed of a header and one or more sequences.

The header contains data that are valid for the whole routing.

A sequence is a series of operations.

Operations describe individual process steps, which are carried out during
production.

SAP PP Overview 39
Operations in a Routing
Material
Operation 20
Routing Operation 10
Group
Work center
Routing Texts
Control data
Times
Material
Components

PRTs
SAP PP Overview 40
Use of Routings
Production/Assembly Scheduling

Order Times
Control data
RTG.
Texts 10 20 .... N
BOM Op 10
PRTs
Material t
Quality Start date Finish date

Capacity Planning Costing


C
Work center
a
p
Op. 10
a Manufacturing Costs
Op. 20
c Manufacturing Overheads
i
t
Machine Labor
y t t
SAP PP Overview 42
Master Data Costing Relationship

Work Center Routing

Formula Constants Standard Values

Cost
Center
Activity
Type Formula

Activity Price Actual


Time/Quantity

Costs

SAP PP Overview 43
Production Planning and Control
Planning Levels

SAP PP Overview 46
Planning Levels in SAP R/3

SAP PP Overview 47
Planning Levels
Sales and Operations Planning

SAP PP Overview 48
Sales and Operations Planning

SOP specifies sales quantities for the long and intermediate term to roughly
assess the feasibility of sales and operation plans

Sales and Operations Planning at the Product Group or F/G level


Materials may be planned together in Product Groups
Sales quantities are determined for future periods
Production quantities are then determined on the basis of sales

The data from SOP is then disaggregated and then transferred to the next
planning level i.e. Demand Management

SAP PP Overview 49
Planning Levels
Demand Management

SAP PP Overview 50
Demand Management

Copy from Copy from Copy from Copy from


Sales Plan Production Plan Forecast Original Plan

Manual Planned Sales


Independent Demand Management Demand from
Requirements Demand Program Sales Orders

MRP/MPS

SAP PP Overview 51
Demand and Supply Elements

Demand Elements Supply Elements

Sales Orders Planned Orders

Planned Independent Production Orders


Requirements
Purchase Requisitions
Dependant
Requirements Purchase Orders

Reservations Warehouse Stock

Safety Stock

Demand Elements are also called requirements or issues, while Supply Elements
are also called receipts.
SAP PP Overview 52
Requirement Types

Independent Requirements
Planned Independent Requirements:
Are used for the anonymous (Non-order-specific) planning
of production or procurement (E.g. demand forecast)
Customer Independent Requirements:
Are sales orders on the system. Sales Orders are generally
copied directly into the PP system from the SD system, but
they can also be entered manually
Dependent Requirements
Are directly related to or derived from the BOM structure for
other items or end products. They are automatically
generated during MRP

SAP PP Overview 53
Planning Strategy Make-to-Stock
Make product for stock in expectation of customer sales.
Plan using planned independent requirements for anonymous
make-to-stock production.

Use Net or Gross Requirements Planning


Net Requirements -- includes warehouse stock, planned
issues and receipts
Gross Requirements -- excludes warehouse stock. Just
includes planned and open orders

Example is a shelf stock item such as an emergency lamp.

SAP PP Overview 54
Strategy: Make-To-Stock Production

Example: Common shelf items such as a emergency lamp

Sale from stock Planning


Warehouse Stock
Finished Product

Production Push

SAP PP Overview 55
Planning Strategy Make-to-Order
Production
Sales orders trigger the production process.
Produced quantities for each sales order are managed individually.
Production and procurement costs are settled either to a sales order or a
project.

Example is a custom product with a unique structure such that it only


applies to a particular customer order.

SAP PP Overview 56
Strategy: Make-To-Order Production
Example: New machinery

Sales Order Warehouse Stock


Finished Product

Production by Lot Size Pull

SAP PP Overview 57
Consumption Logic
Customer requirements consume planned independent requirements directly before or after it.
Consumption mode is either determined in the material master record or
in the configuration menu of demand management
Consumption mode determines either --
Backward consumption requirements directly before the sales order
Forward consumption requirements directly after the sales order
Both types are allowed the system looks for the next closest planning requirements
If no consumption periods exist, then you can only consume requirements planned
on the same day.
Example -- Forward Consumption
01/07 01/14 01/21 01/28
Planned Requirements 0 0 0 100
Customer Requirements 25 -------^

Example -- Backward Consumption


01/07 01/14 01/21 01/28
Planned Requirements 0 100 0 100
Customer Requirements ^----- 25

SAP PP Overview 58
Planning Levels
Material Requirements Planning

SAP PP Overview 59
Functions of MRP

To guarantee material availability.


It is used to procure or produce the requirement quantities on time
both for internal purposes and for sales and distribution.
Monitoring of stocks, creation of order proposals for purchasing and
production.
Determines any shortages and create the appropriate procurement
elements.
Create messages that inform the MRP controller of critical parts and
exceptional situations so that the MRP controller can quickly
reprocess the results of the automatic planning run in the specific area
with problems.

SAP PP Overview 60
MRP Controller

The MRP controller is responsible for specifying the type, quantity


and time of the requirements.
He must also calculate when and for what quantity an order
proposal has to be created to cover these requirements.
He is provided with the information on stocks, stock reservation
and stock on order to calculate quantities and he needs all the
information on lead times and procurement times to calculate
dates.
The MRP controller determines a suitable MRP and lot-sizing
procedure for material to determine procurement proposals.

SAP PP Overview 61
MRP Types
VB Manual Reorder Point Planning:
MRP produces order proposals when stock falls below a reorder point.
The reorder point and safety stock levels are entered manually

VM Automatic Reorder Point Planning:


The reorder point and safety stock level are calculated based on the
forecast results

PD Deterministic Planning
MRP produces order proposal(s) to match the exact quantity of the
requirements based on independent and dependent demands

M0 Master Production Scheduling


Similar to PD but used for master schedule items

SAP PP Overview 62
MRP: Reorder Point Planning

Stock

Reorder Point

Safety Stock

Time
Order Date Delivery Date

SAP PP Overview 63
Lot Sizing

Static Periodic Optimum

Lot for Lot Daily Lot size Part period balancing

Fixed Lot size Weekly Lot size Least unit cost procedure

Replenish up to Monthly Lot size Dynamic Lot size creation


maximum stock
level Flexible period Groff reorder procedure

Lot size according


to planning
calendar.

SAP PP Overview 64
Planning File

The planning file contains a list of all materials relevant to the planning run.
This means that as soon as a material master record is created with MRP
data and a valid MRP type, this material is then automatically included in the
planning file.
Before running MRP, the MRP controller has to ensure that the planning file
has been set up and includes all materials relevant to MRP.

SAP PP Overview 65
MRP Prerequisites

PLANT LEVEL Activated for MRP

MATERIAL LEVEL Valid MRP Type

Valid Material Status

Material MRP Views


Maintained
MRP Controller
Planned Lead Time
MRP Group
Lot Size Data

SAP PP Overview 66
MRP Features
Net requirements
calculation

Lot sizing

MRP Internal production


and external
purchasing
Forecasting

Order scheduling Bill of Material


and generation Explosion

SAP PP Overview 67
MRP Control Parameters

Whether or not MRP will automatically create purchase


requisitions, planned orders or delivery schedules.

Whether an MRP list will be created or not after the MRP run.
Whether the planning data will be adopted or whether the BOM will
be re-exploded.

Whether basic date scheduling or lead time scheduling will be


carried out.

Whether or not unchanged components are to be planned.


Whether results are to be displayed before they are saved.
Whether MRP is to be run in the simulation mode.

SAP PP Overview 70
The MRP Run
Independent Requirements: BOM explosion
Sales Orders & Planned Dependent Requirements:
Independent Requirements From BOM explosion

Quantity Requirements Timings Resource Requirements


Start Finish
1 2 3 4 5 6 7 July July Raw
1 5 Labor Machinery Materials

Order Proposal
Stock Requirements
List / MRP List

SAP PP Overview 71
MRP List
MRP Order Proposals
Group of Materials and Planner Messages
Controllers MRP
MRP Controller for which controller from MRP Planning run.
Listing
is responsible
Planner can drill down
to review material
movement activity

Goods Issues Goods Receipt

SAP PP Overview 72
Production Planning and Control
Production Orders

SAP PP Overview 73
Production Order - Definition

Production orders are used to control the production activity within a


company.
A production order defines
Which material is to be produced
At which location i.e. work center.
At what time (when to produce ?)
How much work (quantity) is required.
Which resources are to be used and
How the order costs are to be settled.

SAP PP Overview 74
Functions of a Production Order

SAP PP Overview 75
The Production Cycle

1. Order Request
2. Order Creation
3. Availability Check
4. Machine Reservation
5. Order Release
6. Print Shop Floor Papers
7. Material Staging
8. Order Processing
9. Confirmations
10. Goods Receipt
11. Calculate Variances
12. Order Settlement
13. Archiving / Deletion

SAP PP Overview 76
Production Order Creation
Manual Order Proposal
Order Creation MRP Conversion

Determine
Order Type

Routing At least one operation is required


Selection
Changes are allowed
before order release
Lead Time Enter start or finish date
Scheduling depending on scheduling direction

Bill of Material Components


Selection Material Reservations
Item Categories

SAP PP Overview 78
Backward Scheduling for In-house
Production
MRP determines the basic scheduling dates using backward scheduling
If the release date lies in the past, the system automatically
switches to forward scheduling
Order Order Order
Release Start Finish
Date Date Date

Order Release In-house Goods Receipt


Process Time Production Time Process Time

Future
MRP Planning MRP Planning Lead Time Requirement
Date -- today Date

SAP PP Overview 79
Production Order Release
Production Order Order release is carried out manually
Ready for Release

Material Availability
Check Uses checking rules defined in configuration

Order or
Operation Release

Shop Paper On-line or in background


Printing Possible Pick List, Confirmation Slips,...

Material
Withdrawals Possible

SAP PP Overview 80
Material Availability Check

Stock on Reservation Planned Order Dependent


Hand for for Requirement
for
150 Units 50 Units 200 Units 200 Units

Net
Available 150 100 300 100

Requirement
for 50 Units
are Available

SAP PP Overview 81
Goods Movement for a Production
Order
Reservation

Planned Goods Issue


Material 1 Production

Unplanned Goods Issue

Material 2
Goods
Consumption of receipt of
Material 1 and 2 Material 3
Goods Issue

SAP PP Overview 82
Back flushing

A goods issue has to be posted for every material that is withdrawn


during order processing. This can occur at the following times:
Directly as the goods are issued
When the operation is confirmed, the materials allocated to the
operation have the goods issue posted. This is known as
backflushing.

Whether a material can be backflushed is decided in three different


places. These are the master records of:
The Routing
The Material Master
The Work Center

SAP PP Overview 83
Backflushing (cont..)

If the Backflush indicator is set in the routing, the material is always


backflushed regardless of what is entered in the material master
record.

If not set the indicator in the routing, whether the material is


backflushed or not depends on how you set the indicator in the
material master record.
Set indicator for backflushing in material master
Always backflush
Work Center decides whether to backflush

SAP PP Overview 84
Confirmation Data

Yield
Scrap Quantity
Quantity
Scrap Reason

Start date
Dates Finish date

Work Center
Labor Personnel Number
Qualification
Wage Group
Wage Type

SAP PP Overview 87
Production Order Status
CRT REL CNF DLV COMP

CREATED RELEASED CONFIRMED DELIVERED COMPLETE

. BOM and RTG . Completion Conf- .. Actual Production . Goods Receipt . Actual costs
selected irmation possible usage and time delivered settled to
captured cost objects
. Lead Time . Shop paper printed
Scheduling .Milestone operation
(MILE)
. Reservations . Availability Check
created for possible, at or
components before release

. Capacity Reqmts . Material issues


for Work Centers after oper release

. Planned Order
costs created (PRC)

. Settlement Rule
Determined (SETC)

SAP PP Overview 88
Order Settlement

When a production order is settled, the actual costs incurred for the order are
settled to one or more receiver cost-objects (for example, to the account for
the material produced or to a sales order). Offsetting entries are generated
automatically to credit the production order:
If the costs for the production order are settled to a material account, the
order is credited each time material is delivered to stock. The material
stock account is debited accordingly.
If the costs for the production order are settled to another receiver (for
example to a sales order), the order is credited automatically at the time
of settlement. The cost-objects are debited accordingly.

SAP PP Overview 89
Production Planning Summary

SAP PP Overview 90
Integration with other modules

SAP PP Overview 91
Integration of PP with other modules
Material Availability Check
Sales Order
Customer Shipment Sales & Transfer of Requirements

Credit Limit
Distribution Goods Issue to SO

Invoice
Sales Forecast / Plan

Production Order
Production Production Order Receipt
Materials
Planning Management
Production Cost Accounting Document

Inspection

Purchase Order

Invoice Receipt

Goods Receipt
Quality
Quality
Management

Finance & Accounts Payable


Vendor
Receivable Accounts / Cash Receipt Controlling

SAP PP Overview 92