Webinar:

MMC- Technologies

Presenters: Juan Carlos Garcia and Farid Mosallat


February 26 - 2015

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


1
Table of contents

1. Modular multi-level converters


2. dq decoupled vector current control
3. Half and H-bridge converters
4. Detailed equivalent models of MMC valves
5. Simulation of a two-terminal system
6. Simulation of a dc-fault and re-start process (half- and H-bridge
MMCs)
7. Setup of a three-terminal system (on-line demonstration if time
allows)
8. Questions

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


2
If you have questions during
the Webinar

Please e-mail PSCAD Support at

support@pscad.com

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


3
Grid-connected VSC:
Operation principle
0 E
jXLI
Supplying P: I
V

I V
Absorbing P:
Neglecting R: jXLI

0 E

Supplying Q: I V jXLI


E
sin
V
cos I
Absorbing Q: E jXLI
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
4
Phase Locked Loop (PLL)

fsrc f (PLL)
110

Extracting the phase angle of phase-A 100


90

voltage 80

[Hz]
70
60
50
Theta
7.0
6.0
5.0
4.0

[rad]
3.0
2.0
1.0
0.0
Vq
0.10
0.00
-0.10
-0.20
-0.30

[kV]
-0.40
-0.50
-0.60

Cos(Theta) Va
1.00
0.50
0.00
[kV]

-0.50

-1.00

t [s] 2.520 2.540 2.560 2.580 2.600 2.620 2.640 2.660 2.680 2.700

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


5
Control modes for
grid-connected operation
Vabc
PLL
Basic control modes: (P/VDC), (Q/VAC)

Rate limiter
Vabc abc vdq
P* d/dt
PI dq
-
P P controller 1: P control
Iabc abc idq
2: Vdc
Rate limiter
control dq
Vdc* d/dt
PI
- Current

Vdc * limiter
id* Decoupled vd*
id1 Vabc*
current dq Valve
VDC controller iq1* controls
controller abc
Rate limiter
iq* vq *
Q* d/dt Imax
PI id iq

- Q controller 1: Q control
Q
Rate limiter VAC droop controller
2: Vac control
Vac* d/dt
- PI
Q Vrms
Dac
VAC droop VAC controller
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
6
Decoupled current control
strategy
Current vector control with PLL locking to phase A voltage (cosine
function)
vd

x1
id* +- PI - +- ed

id L

iq L

iq* +- PI -+
+ eq
x2

vq
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
7
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00
VDC
0.50
VDC
V E VDC
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
8
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50

V E
0.00
VDC
-0.50
VAC VDC
VDC
-1.00

sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
9
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50

V E
0.00
VDC
-0.50
VAC
VDC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
10
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50

V E
0.00
VDC
-0.50
VAC VDC
VDC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
11
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50

V E
0.00
VDC
-0.50
VAC VDC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
12
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50

V E
0.00
VDC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
13
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00
VDC
0.50
VDC
V E VDC
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
14
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00
VDC
0.50
VDC
V E VDC
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
15
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00
VDC
0.50
VDC
V E VDC
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
16
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00
VDC
0.50
VDC
V E VDC
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
17
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50
VDC
V E VDC
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
18
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50

V E VDC
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
19
Modular multilevel converters

+VDC/2

: Graphs
E reference Eac MMC

1.00

0.50

V E
0.00
V
VDC
DC
-0.50
VAC VDC
V DC
VDC
DC
-1.00 VDC
sec 0.0000 0.0050 0.0100 0.0150 0.0200

-VDC/2
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
20
Types of MMC

Half-Bridge MMC 2009 Siemens diagram

Note: Filters not required

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


21
VSC Valves: MMC

Half-Bridge Cascaded 2-level converter

ABB diagram
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
22
VSC Valves: MMC

Full- or H-bridge cells

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


23
Half-bridge MMC

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


24
Half-bridge MMC

Three operating states in the half-bridge cell

State description Gates


Insert +Vc (T2)
Bypass capacitor (T1)
Blocked None
Forbidden (T1,T2)

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


25
Half-bridge MMC


2
* Vac_refT
+
Vdc 0.5 D -
F

Vac_ref

* Vac_refB
+
Vdc 0.5 D +
F

Vac_ref

Note: Half-bridge CAN NOT generate 0

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


26
Half-bridge MMC

Assuming modulating index = 1


2 2


2 0
0 2 2
2 0

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


27
Capacitor balancing: sorting
method Half-bridge cell

iac < 0 iac > 0


Inserted cell Discharges capacitor Charges capacitor

Bypassed Prevents discharging of Prevents charging of


cell capacitor capacitor

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


28
Capacitor balancing: sorting
method Half-bridge cell

Measurements
Vcapacitors,
Iac Balanced capacitor
Ordering of capacitors by voltages
voltage

Request for
IGBT firing insertion or bypass
of a cell capacitor Firing order
strategy
according to IGBT Firing
PWM, Level orders
table below
switching

Action
requested iac < 0 iac > 0
Insert cell Insert cell with highest voltage Insert cell with lowest voltage
Bypass cell Bypass cell with lowest voltage Bypass cell with highest voltage

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


29
Low Level Controls

Stages
Half-bridge cell Capacitor
balancing algorithm

Balanced
capacitor
IGBT firing voltages
Reference
strategy
voltage PWM, NLC,
waves etc.
Sinusoidal(*)
AC voltages

(*) or with harmonic content


as required

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


30
H-bridge MMC (full-bridge)

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


31
H-bridge

Four operating states


State description Gates T1 T2
Insert +Vc
Insert +Vc (T1,T4)
(T1,T4)
Insert -Vc
Insert -Vc (T3,T2)
(T3,T2) T3 T4
Bypass capacitor
Bypass capacitor (T1,T2) or
(T1,T2)
(T1,T2) or (T3,T4)
or(T3,T4)
(T3,T4)
Blocked
Blocked None
None
Forbidden
Forbidden (T1,T3) &
(T1,T3) & (T2,T4)
(T2,T4)

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


32
H-bridge


2
* Vac_refT
+
Vdc 0.5 D -
F

Vac_ref

* Vac_refB
+
Vdc 0.5 D +
F

Vac_ref

Note: H-bridge CAN generate 0

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


33
Half-bridge MMC

Assuming modulating index = 1.25

1.25
2

2 2


1.25 2 0.125 1.125
2 0
0 2 2

2 0

1.25 2 1.125 0.125

1.125
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
34
Modelling techniques:
MMC valves
Half- Half- Half-
bridge bridge bridge
Simulation of MMC VSCs can
involve hundreds of nodes. This Half- Half- Half-
Canbeinthe
significantly reduces simulation bridge bridge bridge orderofafew
hundredcells
speed. Half- Half- Half- perarm
bridge bridge bridge

Q1
Vdc

C
Q2 Half- Half- Half-
bridge bridge bridge

Half- Half- Half-


bridge bridge bridge

Half- Half- Half-


bridge bridge bridge

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


35
Modelling techniques:
MMC valves
Using Thevenin equivalent:
(detailed equivalent model)

Q1

C
Q2

U. N. Gnanarathna, A. M. Gole, and R. P.Jayasinghe, "Efficient Modeling of Modular Multilevel HVDC


Converters (MMC) on Electromagnetic Transient Simulation Programs," IEEE Transactions on Power Delivery,
vol.26, no.1, pp.316-324, Jan. 2011

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


36
Modelling techniques:
MMC valves
Using Thevenin equivalent:
(detailed equivalent model)

i1l
+

-
FP1
Vc1
Ic1
N1
+

-
FP13
Vc13
Ic13
100s of nodes into
+ FP2 + FP14

3 nodes
Vc2 Vc14
- Ic2 - Ic14

+ FP3 + FP15
Vc3 Vc15
- Ic3 - Ic15

+ FP4 + FP16
Vc4 Vc16
- Ic4 - Ic16

+ FP5 + FP17
Vc5 Vc17

Vc
- Ic5 - Ic17

+ FP6 + FP18
Vc6 Vc18
- Ic6 - Ic18

-
FP7
Vc7
Ic7
+

-
FP19
Vc19
Ic19
x10
+ FP8 + FP20

-
Vc8
Ic8 -
Vc20
Ic20
Ic
+ FP9 + FP21
Vc9 Vc21
- Ic9 - Ic21

+ FP10 + FP22
Vc10 Vc22
- Ic10 - Ic22

+ FP11 + FP23
Vc11 Vc23
- Ic11 - Ic23

+ FP12 + FP24
Vc12 Vc24
- Ic12 - Ic24
N1
n2l

This type of model is identified in CIGRE WB B4-57 as model Type-4

This model is good for system wide studies and for most DC fault simulations

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


37
Start-up sequence

Converter 1: Grid-connected mode Controls Vdc and Q (or Vac)


Converter 2: Grid-connected mode Controls P and Q (or Vac) in black start
mode
Converter 1 Converter 2
Energize transformer & Pre- After Vdc is regulated:
charge Deblock converter 2
Bypass pre-insertion resistor Regulate Vac
Deblock converter 1 Ramp-up power transfer
Regulate Vdc

V
Vdc
dc

Grid Vac AC network


in black start
Converter 1 Converter 2 mode
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.
38
Start-up sequence

Vac - onshore
VPCC-T1 Vac - Offshore VAC-T2
1.25
1.00
0.50

(p.u.)
0.00
(p.u.)

-0.50
-1.00
-1.25
Iac T - Onshore Iac - Offshore
1.00
0.40
0.75 IAC-T1 IAC-T2
0.50 0.20
0.25
0.00

(p.u.)
0.00
(p.u.)

-0.25 -0.20
-0.50
-0.75 -0.40
-1.00
Vdc at onshore terminal (P-P) Vdc at offshore terminal (P-P)
1.20 1.20
1.00 1.00
0.80 0.80
0.60

(p.u.)
0.60
(p.u.)

0.40
VDC-T1 0.40 VDC-T2
0.20 0.20
0.00 0.00

Idc (onshore -> offshore) Idc (offshore->onshore)


0.80 1.00
0.60
IDC-T1 IDC-T2
0.40 0.50
0.20
0.00
(p.u.)

0.00
(p.u.)

-0.20
-0.40 -0.50
-0.60
-0.80 -1.00
t [s] t [s] 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60
0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


39
Half-bridge DC faults performance

Sustained DC faults (unlike LCC)

Applies to conventional
2-Level VSC and
Half-bridge MMC

Most systems (except one) use cables:


No need for fast re-energization
Cables experience low occurrence of faults
Fault clearing by opening AC breaker

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


40
Half-bridge DC faults performance

Most systems use cables:


No need for fast re-energization
Cables experience low occurrence of faults
Fault clearing by opening AC breaker

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


41
Half-bridge DC faults performance

DC faults in VSC systems with Overhead Lines


(OHL)
High fault event frequency with OHL
Need fast re-energization (re-closing) (400-500 ms) to prevent
AC system movement
DC breakers are required in order to achieve fast re-
energization of DC system

DC Breaker

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


42
Half-bridge DC faults performance

DC-Breakers
Fast Low voltage
disconnect PE switch 1. Overcurrent or DC fault
under voltage front
detected

High voltage
PE switch

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


43
Half-bridge DC faults performance

DC-Breakers
Fast Low voltage
disconnect PE switch 1. Overcurrent or DC fault
under voltage front
detected
2. De-block HV PE switch

High voltage
PE switch

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


44
Half-bridge DC faults performance

DC-Breakers
Fast Low voltage
disconnect PE switch 1. Overcurrent or DC fault
under voltage front
detected
2. De-block HV PE switch
3. Open LV PE switch

High voltage
PE switch

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


45
Half-bridge DC faults performance

DC-Breakers
Fast Low voltage
disconnect PE switch 1. Overcurrent or DC fault
under voltage front
detected
2. De-block HV PE switch
3. Open LV PE switch
4. Current transferred to
HV PE switch

High voltage
PE switch

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


46
Half-bridge DC faults performance

DC-Breakers
Fast Low voltage
disconnect PE switch 1. Overcurrent or DC fault
under voltage front
detected
2. De-block HV PE switch
3. Open LV PE switch
4. Current transferred to
HV PE switch
5. Open fast disconnect

High voltage
PE switch

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


47
Half-bridge DC faults performance

DC-Breakers
Fast Low voltage
disconnect PE switch 1. Overcurrent or DC fault
under voltage front
detected
2. De-block HV PE switch
3. Open LV PE switch
4. Current transferred to
HV PE switch
5. Open fast disconnect
6. Open HV PE switch

High voltage
PE switch

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


48
Half-bridge DC faults performance

DC-Breakers
Fast Low voltage
disconnect PE switch 1. Overcurrent or DC fault
under voltage front
detected
2. De-block HV PE switch
3. Open LV PE switch
4. Current transferred to
HV PE switch
5. Open fast disconnect
6. Open HV PE switch
7. DC current
extinguished & energy
dissipated in arresters
High voltage
PE switch

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


49
Fault clearance in H-bridge
VSC systems (by blocking)

0 2

0
Therefore lac=0 after blocking since
VACLL pk m 3 Vdc
m 3 Vdc 2 Vdc
v c Vdc

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


50
Simulation of DC faults in a
two-terminal system
System description

G1
T1: P control
12.7 [m]
T2: Vdc control C1 C2

T1 & T2 in Vac control .4572 [m]


15.5 [m]

Tower: DC12
34.1 [m] Conductors: chukar
Ground_Wires: 1/2_HighStrengthSteel

0 [m]

TL Freq. dependent model

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


51
Simulation of DC faults in a
two-terminal system
DC Faults applied

At close and remote terminals


Middle of the line
Low impedance faults (0.1 ohm)

DC Faults detection
Valve overcurrent (2.7 kA level)
DC voltage drop (40% of diode rectifier voltage

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


52
Simulation of DC faults in a
two-terminal system

Converter 1 Converter 2
Edc1
Edc1 Edc2
Edc2
0.8k 0.8k
0.5k 0.5k
0.3k 0.3k
0.0
0.0 0.0
0.0
-0.3k -0.3k
The total time to restore 90% power
(kV)

(kV)
-0.5k -0.5k
-0.8k -0.8k
-1.0k
-1.3k
-1.0k
-1.3k was 450ms
IdcIdc
1->2 12 Idc Idc
2->1 21
10.0 10.0
8.0
6.0
4.0
7.5
5.0
2.5
Including 200 ms de-ionization
2.0
0.0 0.0
time
(kA)

(kA)

-2.0 -2.5
-4.0 -5.0
-6.0
-8.0 -7.5 Main : Graphs
-10.0 -10.0
Vac T1
Phase voltages T1 Vac T2
Phase voltages T2 1.2k
P1 (-) P2
300 300 0.9004k
200 200 1.0k
0.8044k
100 100 0.8k -0.0959k
0 0 0.6k
(kV)

(kV)

Min -0.0108k
-100 -100

(MW)
0.4k Max 0.9006k
-200 -200
0.2k
-300 -300
Iac T1
Iac T1 Iac T2
Iac T2 0.0
10.0 10.0
8.0 8.0 -0.2k
6.0 6.0
4.0 4.0 -0.4k
2.0 2.0 x 2.00
0.0 0.0 1.80 1.90 2.00 2.10 2.20 2.30 2.40 2.50 2.60
(kA)

(kA)

-2.0 -2.0 2.45


-4.0 -4.0 0.45
-6.0 -6.0
-8.0 -8.0
-10.0 -10.0
x 1.960 1.980 2.000 2.020 2.040 2.060 2.080 2.100 x 1.960 1.980 2.000 2.020 2.040 2.060 2.080 2.100

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


53
Three-terminal system:
Demonstration setup

Starting with the two-terminal system from CIGRE B4-57


If time allows

Manitoba HVDC Research Centre | a division of Manitoba Hydro International Ltd.


54
Questions

Please e-mail PSCAD Support at

support@pscad.com