You are on page 1of 22

dam safety guidelines

Part 3: Performance guidelines for low, significant and high hazard dams

Introduction 2.0 Dam risk


This part of the guideline aims to promote The hazard category dictates the level of design input
appropriate levels of investigation, design and needed to ensure that the structure has an
monitoring are being applied to dams within the appropriately low risk of failure. A dam with a higher
Auckland region, in order to ensure dams in the hazard category must be designed and constructed in
region are built to and operate within acceptable a way so as to ensure a lower risk of failure than a
safety margins. Part 3 is not intended as a design dam with a lower hazard category. The concept of
manual, but rather a guideline by which the Auckland risk is discussed in Part 1 of this document.
Regional Council, as a regulator, can determine
whether adequate dam safety standards are being
3.0 Dam ownership and liability
achieved.
While this document is predominantly concerned Few dam owners are technically qualified in dam

with earth fill structures, similar principles can be engineering. Owners often play a minor role in

applied to dams made of other materials. project development, but play a very important role,
being the holder of permits and consents needed to
The performance standards in this guideline are
build and operate the dam.
mainly based on the New Zealand Society of Large
Dams (NZSOLD): Dam Safety Guidelines (Nov 1995), The owner is legally responsible for maintaining the

which provide excellent background information on dam and its associated structures in a safe condition

dam safety requirements and standards. and for operating the dam safely.

The principal topics covered in this part of the The owner usually needs help from technical advisers

guideline are: about dam design, construction, and operation.


These advisers have the responsibility to meet the
1 appropriate levels of investigation
owners requirements and also to ensure the owner
2 appropriate levels of design input is made aware of the operational and safety
3 construction monitoring and testing external limitations of the structure.
design reviews In the event of an incident, attention will first be
4 monitoring and surveillance. focussed on the owner. The owner is legally liable
Monitoring procedures, performance monitoring and for damage after a dam failure and may be culpable in
external reviews of existing dams are dealt with more the event of loss of life.
extensively in Parts 4 and 5 of this guideline.

4.0 Dam failures worldwide


1.0 Dam hazard and risk A study undertaken by the International Commission
For a proposed dam, its hazard largely determines the on Large Dams (ICOLD) 1983 examined 14,700 large
appropriate level of input into dam investigation, dams of over 15m around the world and found that
design or construction monitoring. The hazard 0.7% had failed, and 0.83% of embankment dams
category for a particular dam provides the best had failed. Failure was defined as damage sufficient
indication of this. to lead to breaching of the reservoir, or its

Dam hazard categories for use in the Auckland region abandonment or temporary removal from operation.

are outlined in Part 1 of this guideline. As well as


dam safety, the categories include historical and
environmental considerations.
Users of Part 3 of the guideline must use Part 1 to
determine the hazard category of a proposed dam.
Part 3: Performance standards for low, significant and high hazard dams 2
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Numerous studies have been conducted on dam


failure statistics. The main conclusions from these
studies are:
1 earth and rockfill dams make up the greatest
percentage of failures, but also form the largest
proportion of dams overall
2 most failures occur during reservoir filling or
shortly afterwards
3 the most frequent consequence of failure is
scheme abandonment.
Some of the statistics presented in these studies are
shown in Figures 3.1, 3.2 and 3.3.
Figure 3.1 shows that earth and rock fill dams make
Figure 3.2: Embankment Dam Incidents
up a slightly higher percentage of the number of
failures than would be expected from the proportion
of dams they represent. Although the statistics shown in Figure 3.3 would
Examination of earth dam failures in more detail is suggest that drainage should be incorporated into
thus warranted, given that they make up the greatest dam design as a matter of course, most
proportion of dams. homogeneous earthfill dams are relatively small
Figure 3.2 shows the proportions of embankment structures. The hazard posed by these structures is
dams that fail and the reason for failure. Also shown less, so the acceptable risk of failure is often higher.
is the time in the dams history when failure occurred. Larger structures have a lower acceptable risk of
These figures highlight the vulnerability of failure and constitute a greater investment. Design
embankment dams during construction and first necessities such as drainage and zoned construction
filling. are therefore justified for larger dams.
Figure 3.3 examines 65 embankment dam incidents,
including 15 failures, according to embankment type.
It highlights the value of taking a more sophisticated 5.0 Dam failures in New Zealand
approach to embankment dam design than just a
simple earthfill structure. New Zealand dam failures follow a similar pattern as
overseas ones, also being most likely to fail during
construction or within the first few months of
completion. Failures at the Ruahihi and Wheao
schemes shortly after construction and the recent
damage to the Opuha dam during construction are
some well known examples.
Natural factors that have a large influence on dam
construction method in New Zealand include the
volcanic and seismological setting, complex soil and
foundation conditions and hydrological issues. The
complex geology associated with volcanic areas has
influenced over half the recorded incidents in New
Zealand. Poor foundation conditions were a factor in
over 75% of the more serious recorded incidents.

Figure 3.1: Failures and Actual Proportions


Part 3: Performance standards for low, significant and high hazard dams 3
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.3: Embankment Dam Incidents

Of paramount importance to dam design, Deposition of eroded or landslide material has in-
construction and operation in New Zealand is the filled valleys with deep soft alluvial soils which are
adequate selection and use of materials and often inter-bedded with organic peats, gravels and
drainage. Inadequate attention to drainage has been weak clay seams.
a factor in 86% of serious dam incidents in New The successive weathering and infilling of materials,
Zealand. This includes poor drainage a-Found coupled with localised volcanic influences, mean
conduits through dams, which introduces a weak foundation conditions can change over very short
point in the dams construction. Poor understanding distances, even within the area of a dams footprint.
or insufficient consideration of difficult materials was A dam design may need to cope with varying
a factor in nearly two thirds of serious incidents. foundation conditions over relatively short distances.
Structural deficiencies influenced 50% of minor Several recent failures of irrigation dams in the
incidents. The main factors influencing incidents in Northland region have been mainly due to inattention
New Zealand are shown in Figure 3.4. to foundation conditions.
In the Auckland and Northland regions difficult soil Attention to details such as compaction and seepage
and foundation conditions pose a major challenge to control around conduits within and under the dam is
dam design and construction. The moist maritime also of crucial importance. Poor attention to conduit
climate has produced deep, often uneven, design and drainage around conduits has contributed
weathering of soils. This has in turn provided a to dam incidences in New Zealand.
setting for widespread land instability and erosion.

Figure 3.4: Factors Influencing Dam Incidents


Part 3: Performance standards for low, significant and high hazard dams 4
dam safety guidelines
Guidelines for construction, maintenance and monitoring

The Auckland Region is also subjected to more components discussed in this document and their
challenging hydrological conditions than much of the related safety considerations are discussed below:
country. The predominance of small steep 1 Reservoir The most common purpose of a
catchments gives rise to high peak flood flows. dam is to form a storage or holding area behind
Diversion planning during construction and spillway it. This storage is one of the main determinants
design are therefore of utmost importance. of a dams hazard category. The changes in water
levels caused by the reservoir can induce slope
6.0 Proposed vs existing dams instability and affect groundwater in surrounding
areas. There is also a range of environmental and
Part 3 of the guideline should mainly be used to ecological issues associated with the formation
assess the performance of proposed structures. of a reservoir.
Investigating, designing and assessing construction
2 Dam Structure The main dam structure is
standards of proposed dams is relatively straight
required to provide a barrier behind which the
forward: the critical components of the dam which
storage is retained. Safe performance depends
safeguard its existence and operation can be
on a number of components.
observed and reviewed before construction. While
this does not necessarily mean that a proposed or a A dam cannot exist in isolation from its
newly constructed dam has a lower risk of failure foundation and abutments. Sufficient

than an existing comparative structure, it does reduce investigation needs to be undertaken to

the level of uncertainty about its risk of failure. determine foundation conditions and an
appropriate type of dam structure must
Part 3 is generally applicable to existing structures,
then be selected to match these conditions.
but it is often impractical to assess the adequacy of a
Systems may also be required within the
dams design and construction once it is built. Risk
dam structure to control load stresses,
assessment of existing dams therefore needs to be
seepage flows and/or potential movements.
treated in a slightly different manner, relying more on
the monitoring, surveillance and past performance of 3 Spillways Flood flows are the most visually

the structure. Many of the components critical to obvious, and for most dams, the most frequent

safe dam operation are permanently hidden, with threat to dam safety. These flows are nearly
monitoring being the only means of determining always controlled by means of one or more

performance. spillways. The level of protection provided by


these spillways must be appropriate to the
Monitoring levels, which are too low to give an
dams hazard category.
adequate assurance of safe operation, create
possible uncertainty about the risk of particular a Spillways come in a variety of forms and
components or the structure as a whole. If there is configurations. The selection of the most

any uncertainty, performance monitoring procedures appropriate spillway or spillways depends

for existing dams dictate that a conservative approach on the characterisation of the site, proposed
to dam safety must be adopted. Monitoring and uses for the dam and economic constraints.

surveillance are discussed in Part 4. 4 Conduits Most dams have one or more
conduits passing through the main dam
structure or adjacent abutment. Conduits are the
7.0 Key dam components and safety most common method used during construction
considerations to divert streams while the dam is being built.
The term dam can describe more than just a barrier They are also used for spillways, draw-off
across a stream or river. Dams include a number of systems and power conduits for hydroelectric
key components and their nature and function can schemes.
vary depending on a dams purpose. The principal a Conduits are often a potential line of
weakness through the dam, connecting
Part 3: Performance standards for low, significant and high hazard dams 5
dam safety guidelines
Guidelines for construction, maintenance and monitoring

the storage behind the dam with the 1 Engineering geology`for investigating and
downstream toe. Care must always be assessing foundation conditions, and in the case
exercised in the design and construction of of embankment dams, the properties of the
conduits to ensure they do not cause proposed fill material.
safety problems. 2 Geotechnical engineering ` for assessing the
5 Construction A dam is usually at its most strength and stability of the foundation and
vulnerable during construction. Flood control dam. Particular attention will be placed on the
facilities, performance monitoring and external interface and interaction between man made
protection are often significantly less than for a components and natural materials, and between
completed structure. The level of risk accepted components formed from differing materials.
during construction is typically much higher than a Specific assessment of reservoir slope
during operation, creating a greater potential for stability may also be required.
an incident.
3 Hydrological engineering to assess if there is
a Careful consideration needs to be given to enough water available to make the scheme
the tolerable level of risk during viable, and to assess the size and means of
construction and whether it is consistent passing flood events.
with the hazard category of the structure at
4 Hydraulic engineering to design spillways and
various critical stages during its
associated structures.
construction.
5 Seismological engineering will be required in
6 Other Many dams include other structures
areas where earthquakes represent a possible
which, although they may not represent
threat (this includes most of New Zealand).
significant safety issues in their own right, may
6 Volcanological engineering in areas when
have importance and require a high level of
volcanic activity could represent a threat to the
protection.
dam or associated structures.
Such structures could include:-
7 Environmental engineering to identify issues
a access roading to the dam or local
and effects and design any necessary mitigation
communities
measures.
a powerstations supplying the local area
8 Structural engineering to design structural
a water supply to local communities components.
These issues can influence the required level of 9 Project management for larger projects,
design or monitoring input for a given dam. specialist project management skills are
required to ensure smooth operation and
8.0 Technical advisors and contractors integration of various components of the
development.
Technical advisors and contractors will be required
10 Construction competence a level of
during most stages of dam design and construction
construction competence appropriate for dam
for all but the smallest dams. For larger structures,
size is required. This means skill in construction
teams of specialists will probably be required to
procedures and in programming and design
investigate, design, supervise and monitor key
interpretation. Larger projects will usually have
components of the development.
several contractors undertaking a range of
The appropriate level of specialist input and design different tasks. The NZSOLD guidelines
competence depends on the dams hazard category. discuss construction competence.
Typical skills that may be called upon and their In addition to the various technical advisors and
respective roles include:- contractors, a peer reviewer or review panel is
Part 3: Performance standards for low, significant and high hazard dams 6
dam safety guidelines
Guidelines for construction, maintenance and monitoring

needed for larger projects in order to provide an Objectives:


independent overview of concepts, design issues a define physical limits and viability of scheme
and construction.
a define scheme concept or range of
concepts, and probable limitations
9.0 New dams: conception to completion a define environmental issues and concerns.

The investigation and design process needs to Methods:


address both physical and intangible considerations. a desktop study using geological/
As well as ensuring the structure can be built and topographical maps etc
operated safely, it also must be shown that the dam a walkover survey/site appraisal to assess
will not have adverse effects on the environment or need for on-site controls
the public.
a search of historical data on hydrology,
The Resource Management Act 1991 (RMA) requires climate, and values.
that the impacts from a development be kept to a
Following these, a preliminary scheme design
practical minimum and that mitigation measures be
concept or concepts would typically be
undertaken to remedy adverse effects. Consideration
produced in order to assess what level and type
of practical alternatives will typically be required to
of further investigation is required. For larger
ensure the best overall development option is
developments, these design concepts will often
adopted. This subsection looks at:
be used to begin the consultation process
investigation required under the Resource Management Act.
design Pre-design investigation
construction Pre-design investigations would be undertaken
commissioning. before full design stage. Pre-design can be
considered the main investigation phase.
9.1 Investigations Objectives

For the purpose of this guideline the term a accurately define physical limits and

investigation includes studies into both physical scheme viability

(geology, hydrology etc) and intangible a assess geological, geotechnical and


(environmental, historical) issues in three phases: hydrological controls

preliminary a define level of hazard and identify risks

Pre-design a undertake hazard assessment including

Design. seismological studies

Smaller structures may not have multiple stages a define and examine environmental,

although some preliminary investigation is almost sociological and cultural issues

always undertaken before more in-depth a define scheme concept and probable
investigations. design restrictions

Preliminary investigations a obtain cost-effective design solution

In the first stages of a projects development, the Methods


actual scheme configuration and size is normally a topographic and geological surveys and
poorly defined, and a potential hazard category mapping
would not be assigned. Initial investigations aim a surface and subsurface investigation
to define the physical viability of the scheme and
a laboratory testing etc.
will mainly be based on existing information.
a installation of specific monitoring equipment
Part 3: Performance standards for low, significant and high hazard dams 7
dam safety guidelines
Guidelines for construction, maintenance and monitoring

The investigations should be adequate to allow 3 Appropriate analyses and design methods
full design of the main scheme components. should be adopted. While most dams are
Some additional investigations, identified during unique in their setting and design, the design
the design process, may be required for specific procedures used to derive the designs are well
components. In addition to the investigations established. New technology and knowledge
examining the area in the vicinity of the dam, may allow better scheme optimisation and
consideration must also be given to the area cheaper solutions, but the process is very similar
around and within the reservoir. Slope stability from site to site.
around the reservoir perimeter can, on occasion, 4 A what if approach is required for engineering
dominate project feasibility. critical components or in areas of greatest risk.
Design investigations A backup control for a spillway gate may cost
For larger projects it is normal for the design several thousand dollars but a multi-million dollar
process to highlight potential difficulties that spillway may end up being useless in the event
may result in modifications to the design of failure of a $5 switch to open the gates.
concept. Often this process may require This conservative approach is often termed
additional investigations for new design defensive failsafe engineering.
elements or design optimisation. 5 Construction specifications, based on the design
must be clear and understandable. The
9.2 Design contractor must be made aware of design
parameters, assumptions and concepts and have
Dam design, as with most complex developments,
an understanding of design limitations.
involves an iterative process. Numerous design
a The design must also be able to withstand
options and modifications will be required before a
construction. The loadings and risk present
solution is found that meets the clients expectations,
during construction are amongst the
required safety standards, environmental constraints,
greatest the structure will ever face and
public considerations and budgetary limitations.
consideration of how the dam will be built
For large dam projects involving many specialist
is often influential on and sometime
disciplines, this iterative process will involve a series
dictates the overall design concept.
of intertwined feedback loops.
6 A degree of flexibility must be maintained in the
The design process for dams is complex and varies
design to allow for modifications that will almost
depending on dam type and purpose. It is not
certainly be required during construction to
practical in this document to cover the design
meet unforeseen conditions.
processes involved, but an understanding of the main
7 Careful consideration must be given to any
safety issues that must be addressed in the dam
stream diversion during construction and the
design phase is necessary. These are:
construction sequence as a whole. The level of
1 Evaluation of the hazard and associated risks.
risk associated with the adopted diversion
This needs to be undertaken at a early stage as it
during construction concept must be assessed.
determines the appropriate levels of
Once the final design solution is obtained, a check
investigation, design and design conservatism.
needs to be made that the parameters on which the
2 Qualifications of the design team must be
initial design concept was based are still valid. Many
adequate for the level of project complexity. The
failures have occurred due to a sequence of very
Project Manager fulfils the most important role
minor design changes which when accumulated
of ensuring that incompatibilities do not arise
together produce a design solution well outside the
between different design components and
initial design envelope on which important design
technical advisors.
assumptions were based.
Part 3: Performance standards for low, significant and high hazard dams 8
dam safety guidelines
Guidelines for construction, maintenance and monitoring

9.3 Construction 9.4 Commissioning


Dam construction involves the conversion of the Commissioning a dam involves the gradual
design in to an actual physical structure. While this application of design loadings. Formal
may seem obvious, this link between design and commissioning is usually conducted only on higher
realisation of the design is crucial to the hazard category dams. The purpose of
establishment of a safe dam. Many dam incidents commissioning is to test the dam and its associated
have resulted from lack of communication between structures under a range of loadings. Many design
construction and design personnel. Whereever loadings, such as seismic and extreme floods, can not
possible, key members of the design team should be be tested. However if expectations are realised for
involved in construction. normal load cases, confidence is gained for more
Key issues associated with the construction process extreme events.
to consider: Figure 3.2, shown previously, shows many failures
1 The contractor should be suitably experienced in and incidents occur during initial dam filling,
dam construction and in communication with highlighting the importance of careful
specialist design staff. commissioning.

2 The level of supervision and quality assurance Key components of the commissioning process
both from the contractor and the owners include:
representatives should be appropriate to the 1 Carry out testing of all key components to a pre-
scale of the project. arranged schedule
3 The owner must be made aware that 2 Give staff on the job training for monitoring
modifications during construction will nearly systems, safety, and incident response
always be required and that an allowance should 3 Repair and/or modify any components that do
be made for this when funding the scheme. not meet required performance specifications
4 Design changes should not be made without the 4 Prepare a commissioning report detailing tests
original designers approval. A dam is a undertaken, results, modifications made and
combination of interdependent components. A warning levels on monitoring equipment.
change to one component will frequently have
Preparation of an emergency action plan for higher
flow-on effects on others.
hazard dams will typically be required.
5 Observations, monitoring and design changes
The commissioning period should continue until the
during construction should be recorded and
dam and all the associated components have met the
brought together in an as-built document. This
required performance standards. Some items such
record could be crucial in the event of problems
as spillways may require review at a later date if their
that may arise later.
full design loading cannot be tested.
It is the role of Auckland Regional Council to ensure
compliance with the consents issued for the
development and the construction phase. Consents
10.0 Minimum guidelines for building new
granted for dams effectively give permission for a dams
hazard to be constructed. Council staff must ensure
Standards for the investigation, design and
they do not mistakenly assume liability for unsafe
construction of a new dam must be based on its
structures. External reviews are essential and are
hazard category. Definition of an appropriate hazard
discussed in detail in Part 5 of this guideline.
category as outlined in Part 1 of this guideline is
fundamental for establishing the required level of
design input.
Part 3: Performance standards for low, significant and high hazard dams 9
dam safety guidelines
Guidelines for construction, maintenance and monitoring

For example, it could be argued that a 7m high dam The dam must be protected from natural events that
(with a low hazard category) on soft foundations may add extra loading onto the structure or threaten
would need more than simple test pits as a means of damage to it.
site investigation. Given the potential foundation This section is mainly aimed at earthfill embankment
problems, an appropriate hazard category for this dams, but most of the broad principles also apply to
structure may well be significant, in which case a other forms of dam construction. For construction
more intense investigation is needed. This simple methods other than earthfill, designs are typically
example highlights the importance of defining an more complex and need more specialist input. For
appropriate hazard category for a dam. this reason, alternative construction types are most
The minimum standards outlined in the four flow often associated with larger structures.
charts that follow describe minimum investigation,
design and construction performance levels that
11.1 Dam foundations
could be expected for proposed dams in four hazard
categories. These are not the only appropriate The foundation of a dam, or the zone in which the
methods or the maximum level of input required. A engineered structure meets the natural ground, is
level of interpretation will be required from the crucial to the integrity of the dam. The adage that a
personnel assessing a new dam proposal as to the structure is only as secure as the foundations on
appropriateness of the proposed methods. A which it rests applies to dams. Common problems
performance assessment sheet is provided in Figure associated with foundations include:
3.11. bearing capacity failures
More detailed information on specific areas of foundation settlement
investigation and design is given in Section 12 of piping and leakage.
this Part 3. A brief checklist sub-divided by hazard
Ways of over coming these problems are outlined
category is provided in Figures 3.12 3.14 for
below:
different hazard categories.
Foundation profile and bearing capacity
The dam must be founded on material strong
11.0 Specific design details enough to bear the vertical loads imposed on it.
Dam structures and their impounded materials place It must also be able to resist the shearing force
a load on their foundations and surroundings. This produced by the structure. Assessing the soil
loading needs to be transferred to the surrounding strength profile of the foundation is the main
natural materials. The dam also needs to control purpose of the sub-surface investigations in the
seepages, not settle significantly, and serve the vicinity of the dam.
purpose for which it was built. The soil profile beneath the dam, and the
Most dams, especially embankment dams, consist of properties of this profile have the greatest
three main parts, in terms of loadings: influence on the selection of dam type and
the foundation which must provide support to profile. Some typical foundation profiles and the
the structure above and not allow excessive effect these may have on embankment dam
leakage. The connection between the dam and design are shown in Figure 3.5.
foundation must also be adequate Foundation conditions have a major influence on
the upstream portion or part of the upstream the stability of the embankment.
portion of the dam which must provide a seal Earth dams must be analysed for stability of the
against excessive leakage from the storage embankment itself, while concrete structures
the downstream portion of the embankment are more prone to sliding on the foundations or
which must provide support to the upstream toppling.
portion.
Part 3: Performance standards for low, significant and high hazard dams 10
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.5: Potential Foundation Situations

Foundation settlement 11.2 Piping and seepage control


Some settlement of the foundation materials, in
All dams leak. Classical dam engineering focussed
addition to settlement of the embankment fill (in
on trying to stop seepage flows completely. Not only
the case of earthfill dams) is likely to occur. This
were these attempts almost always unsuccessful, but
settlement can cause cracking in the fill and
they occasionally worsened the destabilising effects
stress or even dislocate conduits that pass
of seepage and water pressure. The modern
through the embankment or foundations.
approach is to limit seepages to a practical minimum,
Differential settlement, which occurs when
and then control the remaining flows by extensive
material properties change over the site or if the
targeted drainage.
valley has an unusual profile, is of particular
Losses due to seepage can be economically and
concern. Some examples of this are given in
environmentally costly and can have safety
Figure 3.6.
implications, as most dams, especially earthfill dams,
Potential settlement is another reason why softer
can be detrimentally affected by excessive or
foundation materials need to be either removed
uncontrolled seepage flows. Reducing seepage and
or designed for. Where settlement is likely to be
lowering the probability of piping failures can also
a problem, additional drainage measures are
reduce uplift pressures under the dam.
warranted to control seepages that may occur
Seepage must therefore be reduced to a practicable
through settlement cracks.
minimum.
Part 3: Performance standards for low, significant and high hazard dams 11
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.6: Differential Foundation Settlement

Seepage control focuses on two critical aspects: Seepage reduction and control
foundation and embankment seepage The purpose of most dams is to retain fluids for
seepage along conduits. use or treatment. Losses due to seepage can be
economically and environmentally costly, and
Pressurised conduits, a special case, are also
can have safety implications most dams,
discussed.
especially earthfill dams, can be detrimentally
Foundation and embankment seepage control
affected by excessive or uncontrolled seepage
As shown embankment dams without drainage flows. Seepages must therefore be reduced to a
make up a disproportionate number of the practical minimum
observed incidents. The use of homogeneous
Reducing seepage and lowering the probability
earthfill dams without drainage is only
of piping failures can also reduce uplift pressures
acceptable for minimal hazard dams in
under the dam.
uncomplicated situations.
Foundation and embankment seepage
The design of appropriate seepage control
All dams leak. Classical dam engineering
measures is site and material specific, and is
focussed on trying to stop seepage flows
therefore beyond the scope of this guideline to
completely. Not only were these attempts
describe in depth. Some typical examples of
almost always unsuccessful, but they also
drainage control measures are given in Figure
occasionally worsened the destabilising effects
3.7.
of seepage and water pressure. The modern
The most common means of reducing seepage
approach is to limit seepages to a practical
losses through dam foundations and abutments
minimum, and then control the remaining flows
is by means of a cut-off or key. The purpose of
by extensive targeted drainage.
the key is to replace a segment of the potentially
As shown in Section 4 of this part, embankment
permeable or variable foundations with
dams without drainage make up a
engineered materials. The type, location and
disproportionate number of the observed
extent of the key reflects the foundation
incidents. The use of homogeneous earthfill
materials, dam type and likely seepage rates and
dams without drainage is only acceptable for
pressures involved.
minimal hazard dams in uncomplicated
Part of the seepage control in Figure 3.7 is a key.
situations.
The size and location of the key, if one is
The design of appropriate seepage control
required, will depend on the nature of the
measures is site and material specific and as
foundation materials and the dam design. While
such is beyond the scope of this guideline to
a cutoff key will typically be incorporated into the
describe in depth. Some typical examples of
design of an earthfill dam it should not be
drainage control measures are given in Figure
assumed that this is normal. (refer to Figure 3.5
3.7. The most common means of reducing the
and Section 11.1 of this part of the guideline).
Part 3: Performance standards for low, significant and high hazard dams 12
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.7: Typical Embankment Drainage Detail

seepage losses through dam foundations and potential leakage paths along the line of the
abutments is by means of a cut-off or key. The conduit, which in the worst case will enlarge
purpose of the key is to replace a segment of with time, leading to failure. In addition, it is very
the potentially permeable on variable difficult to adequately compact around conduits,
foundations with engineered materials. The exacerbating the problem.
type, location and extent of the key reflects the Again, the classical approach was to try and stop
foundation materials, dam type and likely seepage along conduits, typically with the use of
seepage rates and pressures involved. cut-off collars. Cut-off collars along the upstream
Part of the seepage control in Figure 3.7 is a key. portion of the conduit will retard flow and
The size and location of the key, if one is provide a degree of support for the conduit, but
required, will depend on the nature of the the same problem of adequate compaction
foundation materials and the dam design. While remains for material either side of the collars.
a cutoff key will typically be incorporated into the For this reason cut-off collars should not be
design of an earthfill dam it should not be relied on as the only means of controlling
assumed that this is the norm. (Refer to Figure seepage, though they are still applicable in many
3.5 and Section 11.1 of this part of the guideline). situations. In many situations alternative
Seepage along conduits measures are more applicable such as the use of
concrete encasement or bedding. Another
Conduits through dams, especially embankment
alternative for smaller dams would be
dams, produce a discontinuity in materials.
compacted soil / bentonite mixes. The
These different material properties between the
downstream section should however always be
conduit and the surrounding fill can result in
drained in a controlled manner. This ensures
differential settlement. This will produce
Part 3: Performance standards for low, significant and high hazard dams 13
dam safety guidelines
Guidelines for construction, maintenance and monitoring

these seepage flows that will occur do not erode 11.3 Flood magnitude and control
the fill material around the conduit. A typical
Floods pose one of the greatest threats to dams.
detail using collars is shown in Figure 3.8.
Adequate control of floods is required to reduce the
Pressurised conduits
risk that potential hazard is realised.
The use of pressurised conduits through dams
Flood magnitude
should be avoided whenever possible. If their
The design flood is selected on the basis of the
use is unavoidable, their design and construction
dams hazard category, the significance of
must be considered very carefully. Because
components that may be damaged in a flood and
settlement of the dam fill or underlying
the level of understanding of the areas
foundations can cause stress or dislocations to
hydrology. Of the series of terms used to
conduits passing through the dam, in the case of
describe different types and level of design
pressurised conduits high water pressures,
floods, the most common are:
equivalent to the water level in the reservoir,
could be released into the sensitive dam interior. Diversion design flood the magnitude of the
For this reason pressurised conduits are seldom event for which the dam is protected during
used for large dams. construction.

There is no definitive rule for when pressurised Operation base flood (OBF) a moderate sized
conduits pose a significant risk. The strength of event for which no specific flood control
the foundations, type of conduit and conduit measures would be required and following
purpose all influence the suitability of which the structure could be expected to
pressurised conduits. return immediately to full operation.
Maximum design flood (MDF) the maximum
event that the structure has been designed
to safely pass. Normal operation of the
structure would probably not be possible
following the event until a full systems
check was undertaken.

Figure 3.8: Typical Conduit Seepage Control Measures


Part 3: Performance standards for low, significant and high hazard dams 14
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Bank/crest full flood (CFF) an event which The standard suggested by the Auckland
causes the reservoir to rise to the level of Regional Council is not an immovable standard.
the dam crest to the extent that there is no Flexibility should be maintained to allow the
freeboard. In some situations this may be applicant the opportunity to present an
equivalent to the MDF. alternative to the design flood suggested. Use
Probable maximum flood (PMF) the largest of external peer reviews would be an important
probable flood event that could occur at the consideration in the acceptance of alternative
site, or the theoretical upper limit to flood design standards.
magnitude. Consideration of diversion floods
Appropriate standards for design floods The selection of appropriate diversion design
Flood standards suggested by this guideline are flood needs at least as much careful
compared with some from overseas consideration as finished dam design floods.
organisations shown in Figure 3.9. The figures The applicant must justify the diversion flood
shown should not always be considered standard to be adopted.
minimum standards, as in some instances a When selecting the diversion design flood, the
lower design flood may be appropriate, applicant must consider interim hazard
particularly for dams at the lower end of their categories for the structure for the various key
hazard category. In these situations the designer stages of its development. Diversion flood
must prove that a lower level is appropriate. capacity may well also change during the period
Design floods must be adopted on a case by of construction. For larger dams, where
case basis. construction may take several seasons,
The differences in design floods selected by consideration should also be given to
various organisations, reflect these different programming construction to avoid the dams
hydrological conditions. The conservative more vulnerable stages that coincide with
design floods specified in the ANCOLD seasons when floods are more prevalent.
guidelines would not necessarily be practical in Seasonal flood frequency analysis is used to
New Zealand. identify critical times during the year. Care must

Figure 3.9: Flood Design Standards


Part 3: Performance standards for low, significant and high hazard dams 15
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.10: Effect of Different Flood Durations

be exercised to ensure that a consistent level of In many cases the maximum design flood will
protection is obtained. For instance a 1 in 10 produce a water level in the storage close to
year seasonal design flood will not give the crest full, with an allowance for wave run-up.
same level of protection as a 1 in 10 year annual Wave run-up is dependent on reservoir size,
design flood. orientation and location. Wave action is unlikely
For smaller structures where construction may to be significant in reservoirs with open water
only take a few months, selection of a smaller lengths of less than 200m.
diversion flood may be appropriate. Spillway configuration
Consideration of flood volume Many different spillway configurations are used
The introduction of a dam changes the flood for flood control. The type, number and
regime of a river. The storage behind the dam operating method of spillways reflect the dams
will slow down, attenuate the flood, reducing the size and site conditions. The main criteria for
peak flood magnitude downstream. It is very spillways or flood passing systems are:
important to consider the impact of flood events a controlled, safe passing of the operational
of different duration when designing spillways. base flood with no damage to the dam or
The critical flood event for a dam will not be the associated structures
same as that for the river in its natural state.
a safe passing of the maximum design flood
Longer duration events that contain a greater
without risk of dam failure or significant
volume of water are typically more critical. This
damage.
effect is shown in Figure 3.10.
It is often impractical to meet both of these
Freeboard and wave run-up
requirements with a single spillway or bypass
When determining the height of a dam, system. Reliance on a single spillway passing
allowance needs to be made for flood rises. flows in an extreme event is not appropriate for
Additional height should be added to allow for any except the smallest dams. If the spillway
wave run-up and to give the dam a freeboard, or suffers damage during a maximum design flood
safety margin, against flood rise. and needs extensive repairs, an alternative
Freeboard is somewhat independent of hazard means of passing smaller events should be
category, as the level of risk will already have available for use while repairs are undertaken.
been set by selecting appropriate design floods.
Part 3: Performance standards for low, significant and high hazard dams 16
dam safety guidelines
Guidelines for construction, maintenance and monitoring

In many situations the second flow-passing Energy dissipation


system may not be a spillway, but a low level Flowing water contains energy. The more
outlet, turbine or similar. pressure or head that drives the flow, the more
Two spillways are the most common energy contained within it. This energy needs to
configuration for earth dams; a service spillway be removed before the flow exits the engineered
and an extreme event spillway. The next most environment of the spillway or conduit.
common configuration is a single highly If not enough energy is dissipated by the spillway
engineered spillway, with a backup means of design, damage can occur to the river
passing flow such as a low level outlet, or a downstream of the dam, to the spillway and to
turbine. associated structures near the toe of the dam. In
For concrete dams where overtopping of the the worst case this damage may progress back
dam is less perilous a single spillway may be upstream until the dam itself is compromised.
appropriate. There are many ways of dissipating the energy
Service spillway from spillway flows. Care must be exercised to
The service spillway is required to take the ensure a system is used that is compatible with
smaller, more frequent events without damage. the spillway type, energy in the flow and the
It must also be able to be shut off or take its downstream environment.
share of the flow during extreme events and still
be useable afterwards. The capacity of the 12.0 Existing dams
service spillway is typically up to the operation
base flood event as described in Table 3.9. A dams hazard category is independent of whether
the structure is new or has been in existence for many
Common types of service spillway used include:
years. In many cases the hazard category changes
a piped spillways over the period of a dams life due to increased at-risk
a flume or chute spillways population or changes in dam use. This can result in
a conduit spillways such as bellmouth the dam becoming under-designed for the level of
spillways hazard it has come to pose as a result of these

Flood spillway changes.

The flood spillway must operate safely when The safety and performance of existing dams must

required, but may sustain some damage during therefore be gauged in terms of current standards and

extreme flood events. The capacity of the flood design methods. This can cast some existing

spillway must be sufficient to pass the maximum structures, particularly older dams, in a poor light.

design flood as described in Figure 3.9. There are a number of reasons why an existing dam
may not meet the required level of low risk
For simplicity and safety reasons, spillways
appropriate to its hazard category. The main reasons
without gates are preferable, although for
are:
economic and practical reasons, gates are often
used. Additional care is required with gated changes in design and construction technology -

spillways to ensure that the gates will open the state of the art

when most needed. They therefore need good changes in hazard category due to demographic
design with regular inspection and maintenance changes downstream
when required (see Part 4 of this guideline). modifications to the structure, its use or
Common types of flood spillway include: operation

a overflow chute spillways deterioration of all or parts of the dam

a fuse plug spillways. changes in required standards


uncertainty about the dams structural integrity.
Part 3: Performance standards for low, significant and high hazard dams 17
dam safety guidelines
Guidelines for construction, maintenance and monitoring

In most cases there is likely to be a combination of 1 Alter operations If the dam is not meeting the
the above. Uncertainty is one of the most common required safety level appropriate for its hazard
reasons why a dam may be perceived as not meeting control in just one or two specific areas (eg flood
current criteria. For this reason adequate levels of protection), changes to the dams operation may
monitoring are critical to ensure confidence can be offset the safety deficit. For example by
maintained in a structures performance. maintaining a lower operating level to increase
flood freeboard.

12.1 Safety reviews 2 Monitoring Often dams do not meet current


safety criteria because of lack of understanding
The issues listed above mean that larger dams are
of uncertainties about how the structure is
generally subjected to periodic performance and
performing. Enhanced monitoring, often in
safety reviews. These reviews range from frequent
conjunction with exploratory investigations, may
internal reviews of monitoring and surveillance data
well show that the structure does meet required
to full external reviews.
safety standards.
Internal reviews generally focus on the performance
3 Decommission In some cases it may be more
of the dam and its associated structures against a set
appropriate and economically viable to
of guidelines and criteria developed by the original
decommission the structure. While this removes
designer or peer reviewer. Should observed results
the hazard posed by the dam and reservoir,
fall outside the prescribed original limits there should
consideration must be given to the changes this
be procedures set in place to take appropriate action.
will have to the downstream environment.
External reviews are conducted to obtain a fresh,
For example, the reduced occurrence of
unbiased view of the schemes performance. The
floods downstream the dam may have
review will generally include examination of
induced, will no longer be enjoyed. This may
monitoring and surveillance results and a comparison
have implications for communities or
of its design and operation against current dam
infrastructure that have developed since the
criteria.
dam was built.
Dam reviews are discussed in detail in Part 5 of these
The type and extent of modifications to an existing
guidelines.
dam that will enable it to meet current safety criteria
are very site and structure-specific and cannot be
12.2 Meeting current criteria for existing addressed in detail in this guideline. The information
dams in Sections 9, 10 and 11 was aimed at new dams but
is still applicable for assessing existing structures.
In an ideal world it would be desirable to upgrade all
The performance assessment checklist at the end of
existing dams and associated structures to current
this part (Figure 3.11) can be used to assess potential
standards. In the real world, however, there are
safety deficiencies in a dam and when further
several reasons why this is not always practical.
information is needed.
Dam owners are very reluctant to commit finances to
upgrades, particularly when there is no guarantee
that the standards wont change again in the near
future, forcing further upgrades. Public perception of
hazard is also often less for existing structures than
new dams.
More positively however, several alternatives offer
better options than upgrading many existing dams:
Part 3: Performance standards for low, significant and high hazard dams 18
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.11: Performance Assessment Sheet for New Dams


Part 3: Performance standards for low, significant and high hazard dams 19
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.12: Minimum Guideline for the Development of Minimal and Low Hazard Dams
Part 3: Performance standards for low, significant and high hazard dams 20
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.13: Minimum Guideline for the Development of Significant Hazard Dams
Part 3: Performance standards for low, significant and high hazard dams 21
dam safety guidelines
Guidelines for construction, maintenance and monitoring
Part 3: Performance standards for low, significant and high hazard dams 22
dam safety guidelines
Guidelines for construction, maintenance and monitoring

Figure 3.14: Minimum Guideline for Development of High Hazard Dams

You might also like