ANNEXURE - A

ACTIVITY WISE EQUIPMENT DEPLOYMENT BREAK-UP (MINIMUM) FOR MAJOR MAINLINE EQUIPMENT
FOR URAN CHAKAN LPG PIPELINE PROJECT.

Activity
Minimum No.
S.No. Equipment Description Transpor Joint Hydro-
of Equipment ROW Stringing Bending Welding NDT Trenching Lowering Backfilling Tie-in & Crossings Restoration
tation Coating Testing
1 Excavator (crawler mounted) / Backhoe
Pipe layers (Side Booms) - 572G or higher
2
capacity
3 Dozer: CAT D7 / D8 or equivalent
4 Crane (20 T)
5 Grader
6 Welding machine 400 Amp
7 Pay welder
8 Bending machine
Boring machine (suitable for casing pipe
9
size specified)
10 Internal X-Ray Crawler Machine
11 External X-Ray Machine
12 Internal line-up Clamp (Pneumatic)
13 External line-up clamp
14 Compressor (600 cfm)
Joint coating crew with compressor (300
15
cfm) and hopper assembly
16 Filling pump (250 300 m3 / hr)
17 High pressure pump (200 bar)
18 Chemical dosing pump
Complete Hydrotest kit with all instruments
(Dead Weight Tester, Pressure &
19
Temperature recorder, thermocouple etc.) &
Test cabin
20 Crane truck
21 Farm tractor
22 Low bed trailer
23 Flat bed trailer
24 Automatic Cutting & Beveling machine
25 Holiday Detector (of suitable range)
26 Voltmeter
27 Jeepmeter
HDD Rig (of adequate pull capacity & torque
28
requirement as per design)
Note 1. The above is the minimum deployment schedule of equipment in Good Working Condition and Certified by TPI. Contractor shall separately maintain adequate spare equipment to take into account break
downs so that work is not hampered on account of the same.
2. Additional equipment shall be deployed to meet construction schedule and as per instructions of Engineer-in-Charge of HPCL / MMPL.
3. A separate mobilisation plan (Inclusive of Man Power and Equipment) for the Ghat Section shall be submitted.

SIGNATURE & SEAL OF TENDERER