Professional Documents
Culture Documents
Page
B1 Model Map 18
B2 User Inputs 20
B4 Model Output 36
2
A Section 1: Industry Primer
3
A1 Energy & Solar Power Sector Overview
4
Energy Sector Overview
Sources of Energy
Oil Solar
Coal Hydro-electric
Nuclear Geo-thermal
5
Solar Power concept and evolution
Concept Evolution
6
Global Solar Power Map
Solar Power capacities are concentrated mostly in Europe, US, China and India
Source: Global Market Outlook For Solar Power / 2015 2019, SolarPower Europe
7
A1 Energy & Solar Power Sector Overview
8
Solar Power Plant
Sun
Grid
Transformer &
Inverter
Switchgear
AC DC
9
Development Process
1 2 3 4 5 6
Site Selection Feasibility Study Financial Closure Pre-Construction Construction Commissioning
Land / soil details Technical Debt Funding Approvals Site Preparation Licensing
Feasibility
Solar Resources Equity Funding Designs Materials Supply Grid connectivity
Financial
Regulations Feasibility Financial closure Selection of EPC Excavation / Testing
& other vendors infrastructure
Accessibility / Cost / Benefit Handover
Connectivity Project Timeline Mounting /
Risks Mitigation Installation
Geotechnicals strategy
Civil Works
Project Management
10
A1 Energy & Solar Power Sector Overview
11
Project Cost Components
2
Grid Connection,
Mounting Structure /
Equipment Module Invertor Installation &
Frames
Commissioning
12
Investment Sources
Sponsor
Equity
Investor
Recourse
Debt
Non Recourse
13
A1 Energy & Solar Power Sector Overview
14
Revenue drivers & considerations
1 2 3
Merchants Corporates
15
Operating Costs of a Solar Power Plant
Operations &
Solar Farm maintenance, repair, utility costs
Maintenance
Insurance Cost Asset cover, third party liability and other insurance premiums
16
B Section 2: Financial Modeling Primer
17
B1 Model Map
B2 User Inputs
B4 Model Output
18
Model Map
Rev
WC Output Tabs
Exp
Model Assumptions Ratios
Operating Costs Calculations
Capex
Capital Expenditure
Funding
19
B1 Model Map
B2 User Inputs
B4 Model Output
20
General Inputs
Select the Scenario Enter general assumptions of capacity, performance and utilization factors
from dropdown
21
Project Cost Inputs
22
Project Cost Inputs
23
Operating Inputs
24
Other Inputs
25
B1 Model Map
B2 User Inputs
B4 Model Output
26
ProjCost
I
J
K
A
B DxI
C JxK
3
AxB
AxBxC
1
L
M
N
D
DxL i
E DxM ii
F N X (1 + 2 + 3 + i + ii)
G 4
H
DxE
DxF 5
DxG 6
DxH
2 1+2+3+4+5+6
Interest on the loan during the construction
period (source tab: Funding
27
Rev
A
B
C
D
E
B x E grown annually to C x E in 10 years
C x E grown annually to D x E in 15 years
Start at B x E reduce by degradation factors
Capacity Utilization Factor x A x 365 x 24
F
G
H F grown @ G
I
J
K I grown @ J
28
Exp
A
B
C
1 A x B grown @ C
D
E
2 D grown @ E
F
G
H
3 F x G grown @ H
I
J
K
L
4 I x J grown @ L every K years
1+2+3+4
29
WC
A
1
2
B
3
4
30
Capex
A
B
AxB
C
1 A x B grown @ C
Cumulative
D
Year number
2 Equal to cost at end of life (D)
E
6 3
7
8 6/Ex7
31
Funding
1 From Capex
3 A Ax1
4 B Remaining limit
5+6
5 Minimum of 3 & 4
6 Debt Interest Capitalized
7 2-5
32
Funding
1a
1b
A
2 1a + ?
Ax2
C
7 D 1/D
8 C/7
9 11
33
Funding
7 From Financials
8 A Ax7
B Bx6
10 + 11
34
Funding
A
1 1
A-1 The macro code
pastes the values
2 From Financials in 3 which is
3 used for the
below schedules
4 3
5 If 3<0, raise equal amount of credit facility
The copying and
3 pasting continues
6 Full Cash Sweep till the sum of
B x average row 2 sum of
B row 3 becomes 0
of 4 & 7
35
Built In Macro
Objective of The objective of the macro is to ensure that any negative cash shortfall during the life of the project
the Macro is attending to by raising short term overdraft through a revolving credit facility
Algorithm of 1. The macro checks the cash balance as per the balance sheet.
the macro
2. It copies the values into a new row
3. Revolving credit facility during any negative cash balance year is taken equal to that negative amount
4. Now, the interest on the revolving credit facility leads to additional negative cash balance
5. Repeat Step 1 to four till the sum of the cash balances as per the balance sheet is equal to the new row where the macro is
copying and pasting the cash balance
3. The Red box titled Click to run macro is lined to the macro (right click and then Assign Macro
36
Activate the Developer Tab
1. Go to File
2. Click Options
3. Go To Customize Ribbon
37
B1 Model Map
B2 User Inputs
B4 Model Output
38
Output Tabs
1 2 3 4 5
Financials Ratios Returns Sensitivities Dashboard
Du Pont Analysis
39
Financials
From Rev
From Exp
From Capex
From Funding
From Funding
From Funding
From Tax
From Inputs
Profit Margin
From Funding
2 Previous Balance
3 1
2+3
40
Financials
From Capex
From WC
From Cash Flows
From Funding
From WC
From Funding
From Funding
From Funding
From Funding
From Income Statement
41
Financials
From Capex
From Funding
From Funding
From Funding
2 Previous Balance
3 1
2+3
From Funding
From Funding
42
Ratios
43
Returns
Equity IRR indicates the returns to the equity investors after the debtors have been fully repaid
Project Payback Period is the number of years it will take to cover up the total project investment
Equity Payback Period is the number of years it will take to cover up the equity investors investment
The Internal Rate of Return is calculated using the excel function =IRR(range of cashflows)
44
Scenario Analysis and Sensitivities
Optimistic All debt raised during the first year and interest capitalized only during the first year
Construction Period = 2 years and cost escalations in Year 2 increases the Project Cost
Base All debt raised during the first two years and interest capitalized during the first two years
Construction Period = 3 years and cost escalations in Year 2 & 3 increases the Project Cost
Pessimistic All debt raised during the first three years and interest capitalized during the first three year
45
Sensitivities
46
Sensitivities
Using Data Tables, the change in Project IRR is summarized in the sensitivity tables where the rows correspond to the change in the underlying factors
47
Data Tables
48