Professional Documents
Culture Documents
Unforseen downward movement relative to king posts had been NLC dismissed the importance
in diaphragm walls triggered the observed on other sections of attached by the client LTA to
Nicoll Highway tunnel collapse, Singapore's Circle Line cut and the use of drained soil data in
main contractor Nishimatsu-Lum cover excavation. But there finite element analysis of
Chang jv (NLC) claimed before was no evidence of this at ground conditions on site.
the public inquiry last week. Nicoll Highway, said the It said this was appropriate as,
A sudden drop in the height contractor. "Collapse was not at shallower depths, it tends to
of the wall relative to king posts inevitable. The collapse give conservative results,
supporting the temporary struts occurred because the forced although there was no precedent
altered the angle at which struts sway mechanism dramatically for such deep excavation using
connected with the walers. This reduced the time in which it Method A in Singapore. During construction NLC
caused them to deform rapidly, developed," claimed NLC During the early stages of discovered a buried channel
leading to "sway failure", the counsel Philip Jeyaretnam. construction, NLC claimed LTA in the old alluvium base
contractor said. Although the struts were accepted that deflections strata into which the
Sway failure happens when close to the limit at which they measured on site were close to diaphragm walls were toed.
the junctions between the flanges could fail, there was no evidence those anticipated using Method A This was filled with deep,
and web of an I-beam act as that loads exceeded the ultimate finite element analysis, soft, organic clay. There was
hinges, causing the beam to capacity of the temporary works, Jeyaretnam said. also a bowl of soft estuarine
flatten under heavy loading. he added. "There was no NLC's independent clay below the marine clay
NLC coined the term evidence of a build up of loads engineer Dr Andy Pickles of which covers most of the
"forced sway failure" to before 20 April. consultant CPG had briefed site. Neither was detected
describe the violent forcing of "If the loads exceeded actual LTA on the soil analysis in during site investigation.
this mode of collapse. capacity the connections would May 2002 and LTA's The temporary works had not
Movement of diaphragm walls have failed as excavation supervising engineer had been designed for these
beneath each strut reached the described alternative conditions, and had to be
10th level, or as loads built up analysis models as over- adapted, said NLC counsel
with time after completion of cautious, he added. Philip Jeyaretnam.
excavation..
Extracted from New Civil Engineer May 2005
overloading
struts in levels
above, causing
them to buckle.
This triggered a
progressive
collapse of the
tunnel walls.
The failure was rapid. Only an
hour elapsed between failure of
the first strut-waler connection
and total collapse of the
excavation.
Overloading of the temporary
works coincided with the
excavation of a sacrificial prop
installed using jet grouting
methods just below the ninth
level struts.
NLC admitted to the inquiry that
failure of the temporary works
resulted from underdesign and
inappropriate detailing of the
strut-waler connections.
NLC's design engineers
misinterpreted building code
BS5950, said counsel for NLC
Philip Jeyarentnam.
This resulted in the adoption of
smaller than required steel
sections for the struts, reducing
redundancy in the design.