Professional Documents
Culture Documents
DRAFT FINAL
June 2013
Return Activated Sludge Pumping
Draft Final Basis of Design Report
Contents
1.0 Introduction ........................................................................................................................................... 1
1.1 Purpose ...............................................................................................................................................................1
2.0 Background ........................................................................................................................................... 2
2.1 Plant Flows and Loads ........................................................................................................................................4
2.2 Existing Facilities ...............................................................................................................................................6
3.0 Project Elements ................................................................................................................................... 6
3.1.1 Overall Program Site Plan ...........................................................................................................................8
3.1.2 Project Site Plan ..........................................................................................................................................8
3.2 Basis of Design ................................................................................................................................................. 11
3.2.1 BioWin Model RAS Flows ....................................................................................................................... 11
3.2.2 State Point Analyses Requirements ........................................................................................................... 13
3.3 Design Criteria .................................................................................................................................................. 14
3.3.1 Pumping Station Design Criteria............................................................................................................... 14
3.3.2 Pump Selection Criteria ............................................................................................................................ 14
3.3.3 RAS Pump Turndown Range .................................................................................................................... 15
3.4 BCE Results ...................................................................................................................................................... 16
3.4.1 Advantages, Disadvantages, and Risks ..................................................................................................... 16
3.4.2 Recommendation: ..................................................................................................................................... 17
3.5 Features ............................................................................................................................................................. 17
4.0 Condition Assessment ......................................................................................................................... 18
4.1 RAS Pipe Condition.......................................................................................................................................... 19
4.2 Rehabilitation and Replacement (R&R) of RAS Pipes..................................................................................... 19
5.0 Construction Sequencing.................................................................................................................... 19
5.1 Startup and Transitioning.................................................................................................................................. 20
6.0 Site Work ............................................................................................................................................. 20
7.0 Site Utilities .......................................................................................................................................... 20
8.0 Control Strategy .................................................................................................................................. 20
8.1 Existing Control Strategy.................................................................................................................................. 20
8.2 Future Control Strategy .................................................................................................................................... 21
9.0 Site Electrical....................................................................................................................................... 21
10.0 Contractor Support Facilities and Laydown Area ........................................................................ 22
11.0 Project Coordination ........................................................................................................................ 22
11.1 RAS Piping Coordination with BNR Project .................................................................................................. 22
List of Figures
Figure 1. Process Schematic of Existing Facility ..........................................................................................................3
Figure 2. Plant Process Schematic .................................................................................................................................7
Figure 3. Overall Program Site Plan ..............................................................................................................................9
Figure 4. Overall Project Facility Site Plan ................................................................................................................. 10
Figure 5. State Point Analysis ..................................................................................................................................... 13
List of Tables
Table 1. BODR Reference Documents ..........................................................................................................................2
Table 2. SRWTP Raw Influent Flows and Loads for Year 2020...................................................................................5
Table 3. SRWTP Raw Influent Flows and Loads for 181 mgd ADWF ........................................................................5
Table 4. SRWTP Raw Influent Flows and Loads for 206 mgd ADWF ........................................................................5
Table 5. RAS Pumping Station Design Flow Criteria ................................................................................................. 11
Table 6. Required RAS Flow Rate (MGD) per SST as a Function of RAS Rate at 2020 ADWF............................... 12
Table 7. Required RAS Flow Rate (MGD) per SST as a Function of RAS Rate at 181 mgd ADWF......................... 12
Table 8. Required RAS Flow Rate (MGD) per SST as a Function of RAS Rate at 330 mgd EMDF ......................... 12
Table 9. Summary of Life Cycle Costs Analysis ......................................................................................................... 16
Table 10. RAS Alternatives Findings .......................................................................................................................... 17
Attachments
Attachment A. Return Activated Sludge Business Case Evaluation
Attachment B. Alternatives Development
Attachment C. RAS Can Drawings
Abbreviations
Acronym Description
AAF Average Annual Flow
ACC Area Control Center
ADWF Average Dry Weather Flow
AOR Acceptable Operating Range
ATTP Advanced Treatment Technologies Pilot
BCE Business Case Evaluation
BEP Best Efficiency Point
BOD Biochemical Oxygen Demand
BODR Basis of Design Report
BNR Biological Nutrient Removal
BRF Biosolids Reclamation Facility
DLDs Dedicated Land Disposal
CEP1 Phase 1 Capacity Expansion Project
CO Carbonaceous Oxygen
EMDF Equalized Maximum Daily Flow
ESBs Emergency Storage Basins
LS Lump Sum
mgd Million Gallons per Day
MM Maximum Monthly Flow
MLSS Mixed Liquor Suspended Solids
NPDES National Pollutant Discharge Elimination System
NPSH Net Positive Suction Head at 3 percent loss of head at BEP, feet of
water
NPSHmargin Net Positive Suction Head Margin Ratio
NPSHA Net Positive Suction Head Available, feet of water
NPSH3 Net Positive Suction Head at 3 percent loss of head, feet of water
Nss Suction Specific Speed
PEPS Primary Effluent Pumping Station
PCCS Process Computer Control System
PDR Preliminary Design Report
PHWWF2 Peak Hourly Wet Weather Flow For A 2-Year Storm
PMO Program Management Office
POR Preferred Operating Range
PST Primary Sedimentation Tanks
Qbep Flow at best efficiency point
RAS Return Activated Sludge
1.1 Purpose
The purpose of this Basis of Design Report (BODR) is to provide the RAS pumping system
Designer with the basic process design and preliminary equipment selection of the RAS pumps
for the project. It also provides links to key documents and information necessary for a more
complete understanding of the project.
2. The production of the PDR includes the production of several technical memoranda
(TMs) for each discipline associated with RAS pumping. During that process, focused
meetings will include District staff to continuously define the project leading to the
design submittal phases.
3. The design submittal phases will include review by PMO and District staff to confirm
that the design is following the BODR intent and updated developments regarding
Regional Board permit requirements.
The basis of design, design criteria (as distinct from the Districts Design Guidelines), the
features, and discipline-specific information has been provided. In addition, a BCE has been
developed to evaluate the number and type of pumps; the results are contained in
Attachment A.
A process schematic of the existing treatment plant is shown on Figure 1. The plant includes
the following:
Liquid Stream:
Headworks (mechanical screens and influent pumping)
Ferric
Cl2
Secondary Chlorine Sacramento
Grit Primary COTanks
Screen Clarifiers Cl Contact River
R
Removal l Cl ifi
Clarifier
Influent 2
Grit Legend
Diversion
ScreenGrit
Septage Scum RAS Scum Sludge
l d
ProcessFlow
WAS Scum
Sidestream
Disposal Polymer Chemical
Coagulant/
PS
Water
Digesters
T
FOGReceiving Sludge
MixingTanks
RF
BRF BeneficialUse
SD/SN
SN SD
FM SD
FlowMetering RASPumpingBODR
Structure
Figure1.
Z:\15.RAS(ReturnActivatedSludgeSystem)\B.Planning\BODR RASPumpStation\Figures\Figures1and2ProcessSchematicofexisting
anddesign ExistingPlantProcessSchematic
Return Activated Sludge Pumping
Draft Final Basis of Design Report
Carbonaceous Oxygen (CO) tanks and Secondary Sedimentation Tanks (SSTs) that
remove biochemical oxygen demand (BOD) and total suspended solids (TSS)
Solids Stream:
Thickeners for waste activated sludge(gravity belt thickeners and dissolved air
flotation)
Anaerobic Digestion
Dedicated Land Disposal (DLDs) for disposal of sludge harvested solids from SSBs
Refer to the PMO Facilities Plan on the Districts web site (http://srcsd.com/business-
opportunites.php) for a more detailed description of the process units and current operations. 1
The year 2020 was evaluated as it is the year that the EchoWater Project will come on-
line at SRWTP.
181-mgd average dry weather flow (ADWF) was evaluated as this is the design capacity
for the adopted NPDES permit.
206-mgd ADWF was evaluated as this is the projected flow approximately 20 years
after which 181-mgd ADWF is reached.
All the listed averaging periods (e.g., AAF, MMF, etc.) were considered for each design
condition. The raw influent flows and loads for each of the above-listed design conditions are
listed in Tables 2, 3 and 4. The loads identified for the maximum day are the result from high
sewer flows scouring solids that have settled during previously dry periods.
1
SRCSD Program Management Office (2012) Facility Plan: Sacramento Regional County Sanitation District
Advanced Wastewater Treatment Program. Program Management Office, SRWTP, Elk Grove, CA.
Table 3. SRWTP Raw Influent Flows and Loads for 181 mgd ADWF
Annual Max Max Peak
Item Unit ADWF Average Month Week Max Day Hour
Table 4. SRWTP Raw Influent Flows and Loads for 206 mgd ADWF
Annual Max Max Peak
Item Unit ADWF Average Month Week Max Day Hour
At the peak hourly wet weather flow for a 2-year storm (PHWWF2) of 332 mgd, per the CEP1
design criteria, the plant has the capacity of achieving a RAS return rate of 69 percent with all
SSTs and all RAS pumps on. At average dry weather flow (ADWF) of 181 mgd, the plant has
the capacity of achieving a RAS return rate of 126 percent with all SSTs and all RAS pumps
on. Existing operations protocol of the plant during PHWWF2 calls for a minimum of 20 SSTs
to be running at any one time with two SSTs serving as standby. PHWWF2 operations protocol
provides for each SST to have one pump operating and one as standby. In typical operation of
the plant during ADWF, a minimum of 16 SSTs are running at any one time with three SSTs
serving as standby. Each SST would have one pump operating and one as standby. The flow
rate for RAS pumps on Batteries I and II are controlled with eddy current variable speed drives
and flow rate for Battery III RAS pumps are controlled with variable frequency drives (VFDs)
for each pump. For all SSTs in service, the variable speed pumps are ramped up and down in
unison to help maintain an even sludge blanket. However, uneven flow distribution into the
SSTs does create a non-uniform sludge blanket across the existing SSTS.
SST Batteries I and II were constructed under Contract 767 in 1976 while Battery III was
constructed under Contract 2000 in 1989. Due to this difference, the SST batteries will vary in
mechanical design and electrical motor control center (MCC) location. The main difference in
the mechanical design is the difference in the RAS discharge piping. Batteries I and II
discharge piping does not prevent air entrainment in the flow meters while Battery III is
designed to remove that air entrainment by way of a U loop and an air relief valve.
Regarding the existing electrical system, Battery I RAS pumps are powered from MCCs
located in the Secondary Treatment Control Center South Building 6. Batteries II and III RAS
pumps are powered from MCCs located in the West Secondary Substation Building 12.
Filtration &
RAS Disinfection
Alkalinity Feed Filter Influent
Pump Station
Septage (FIPS)
SST
Classifying Splitter
Selector
Legend
PE Pump Diversion
Station Screen Grit
(PEPS)
Sludge
Process Flow
Scum
Sidestream
Chemical
Anoxic Aerobic Swing
Zones Zone Zones
Drain P/S
BNR Tanks
RASS BODR
Figure 2.
Z:\15. RAS (Return Activated Sludge System)\B. Planning\BODR - RAS Pump Station\Figures\Figures 1 and 2 Process Schematic of existing
and design Plant Process Schematic
Return Activated Sludge Pumping
Draft Final Basis of Design Report
3.1.1 Overall Program Site Plan
An overall site plan for the program is shown on Figure 3. The drawing shows the RAS
facilities along with the other facilities included in the program as follows:
RAS BODR
Figure 4
Return Activated Sludge Pumping
Draft Final Basis of Design Report
Replace electrical components in Batteries II & III RAS MCCs in the West Secondary
Substation Building 12.
Replace MCC 4K and MCC 4H in the Secondary Treatment Control Center South
Building 6 feeding Battery I RAS pumps.
Remove above grade piping and flow meters and replace piping to create a
configuration similar to Battery III installation. Modify below grade piping where
needed.
Add an additional isolation valve downstream of each flowmeter.
Modify the RAS pump control wiring in ACC4/11 and the West Secondary Substation
Building 12.
The relationship for flow rate per SST as a function of RAS rate at 2020 (148 mgd) and
181 mgd ADWF is shown in Table 6 and Table 7, respectively. As an example, to achieve the
low conditions established by BioWin, with the plant at ADWF and the RAS low flow
condition of a 30 percent return rate, there would be 20 SSTs in operation with a RAS flow of
approximately 2.7 mgd per SST. The tradeoff between number of clarifiers in service and RAS
Table 6. Required RAS Flow Rate (MGD) per SST as a Function of RAS Rate at 2020 ADWF
Number Percent Return Flow Overflow
of SSTs in Rate,
service 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% gpd/sqft
16 1.9 2.3 2.8 3.2 3.7 4.2 4.6 5.1 5.6 6.0 6.5 697
17 1.7 2.2 2.6 3.0 3.5 3.9 4.4 4.8 5.2 5.7 6.1 656
18 1.6 2.1 2.5 2.9 3.3 3.7 4.1 4.5 4.9 5.3 5.8 619
19 1.6 1.9 2.3 2.7 3.1 3.5 3.9 4.3 4.7 5.1 5.5 587
20 1.5 1.9 2.2 2.6 3.0 3.3 3.7 4.1 4.4 4.8 5.2 558
21 1.4 1.8 2.1 2.5 2.8 3.2 3.5 3.9 4.2 4.6 4.9 531
22 1.3 1.7 2.0 2.4 2.7 3.0 3.4 3.7 4.0 4.4 4.7 507
* Hatched numbers indicate flow below the SST RAS design low flow rate
Table 7. Required RAS Flow Rate (MGD) per SST as a Function of RAS Rate at 181 mgd ADWF
Number Percent Return Flow Overflow
of SSTs Rate,
in service 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% gpd/sqft
20 1.8 2.3 2.7 3.2 3.6 4.1 4.5 5.0 5.4 5.9 6.3 680
21 1.7 2.2 2.6 3.0 3.4 3.9 4.3 4.7 5.2 5.6 6.0 650
22 1.6 2.1 2.5 2.9 3.3 3.7 4.1 4.5 4.9 5.3 5.8 620
23 1.6 2.0 2.4 2.8 3.1 3.5 3.9 4.3 4.7 5.1 5.5 590
24 1.5 1.9 2.3 2.6 3.0 3.4 3.8 4.1 4.5 4.9 5.3 570
*Hatched numbers indicate flow below the SST RAS design low flow rate
Table 8. Required RAS Flow Rate (MGD) per SST as a Function of RAS Rate at 330 mgd EMDF
Number Percent Return Flow Overflow
of SSTs in Rate,
service 25% 30% 35% 40% 45% 50% 55% 60% 63% 65% 70% gpd/sqft
18 4.6 5.6 6.5 7.4 8.3 9.3 10.2 11.1 11.6 12.0 13.0 1380
19 4.4 5.3 6.1 7.0 7.9 8.8 9.6 10.5 11.0 11.4 12.3 1310
20 4.2 5.0 5.8 6.7 7.5 8.3 9.2 10.0 10.4 10.8 11.7 1240
21 4.0 4.8 5.6 6.3 7.1 7.9 8.7 9.5 9.9 10.3 11.1 1180
22 3.8 4.5 5.3 6.1 6.8 7.6 8.3 9.1 9.5 9.8 10.6 1130
23 3.6 4.3 5.1 5.8 6.5 7.2 8.0 8.7 9.1 9.4 10.1 1080
24 3.5 4.2 4.9 5.6 6.2 6.9 7.6 8.3 8.7 9.0 9.7 1040
*Grayed numbers indicate flow is greater than SST RAS design flow rate.
This assesses SST performance and determines the maximum MLSS concentration by locating
the state point and underflow rate line to be lower than the flux curve. If the state point or
underflow rate is higher than the flux curve then the SST is overloaded. For this analysis, a
sustained peak flow of 330 mgd (EMDF) was assumed at a SVI of 150 mL/g. The SVI of
150 mL/g represents the design assumption for the 90th percentile value. The analysis assumed
that 22 SSTs are in service and that each SST has 9.5 mgd of RAS capacity. Figure 5 presents
the results of the state point analysis.
50
RAS Underfow (ft/ft/d)
45
Derated RAS Underflow (ft/ft/d)
40
Solids Flux, lb/sf-d
30
State Point
25
20
15
Limiting Flux
10
0
0 5 10 15
Design
MLSS Solids Concentration (g/L)
1. Suction specific speed (Nss) preferred value should be 8,500 and the acceptable
value should be no greater than 10,000 where:
Nss =
(3)0.75
2. At no point should the pump operate outside of the allowable operating region
(AOR) for the flow rate and total dynamic head (TDH) range required. Per the
Hydraulic Institute (HI), the extent of the AOR is established by the pump
manufacturer.
3. During the most common flow conditions, the pump should operate well within the
preferred operating region (POR) for the flow rate and TDH range required. The
most common flow conditions should be developed by taking influent flow
frequency histogram and scaling the flow down for a 50 percent RAS return rate.
Per HI, for pumps with specific speeds greater than 4500, the POR extends from
80 percent of QBEP to 115 percent of QBEP. As the pump approaches peak flow
5. Maximum motor speed is 1800 RPM; 2-pole motors (3600 RPM) are not allowed
for pumping.
As shown in Table 7, for the low flow condition ADWF and a RAS return rate of 30 percent
there would be 20 SSTs on line each with a RAS flow rate of 2.7 mgd (1,900 gpm). The
minimum of 20 SSTs in service at ADWF is required because the overflow rates for BNR
should be between 400 to 700 gal/day/sqft for average conditions and between 1,000 to
1,600 gal/day/sqft under peak conditions (Metcalf and Eddy, 2003).
To provide sufficient flexibility to respond to influent flow changes, the RAS pumps should
have the capability to range from to 2.7 mgd (1,900 gpm) during low flow conditions and
9.5 mgd (6,600 gpm) during high flow conditions. This flow range would allow the RAS
pumping system to have a flow turn down ratio of 3.5.
Table 9 contains a summary of the capital, annual, and present value (life cycle) costs for the
three alternatives.
3.4.2 Recommendation
Alternative 3 is recommended due to low life cycle costs. This alternative has the lowest cost
due to the fewest number of pumps to purchase and maintain. In addition, these pumps have
flow capabilities ranging from 1,900 gpm to 6,600 gpm while allowing the pump to remain in
the AOR with the majority of the operating range in the POR.
During the preliminary design process, the design consultant shall perform a BCE that
compares the life cycle cost of VSDs such as magnetic drives versus VFDs.
3.5 Features
The following is a list of RAS pumping features.
Number of pumps: one per SST.
Number of pumps total: 24.
The condition assessment should include confirmation of the type of material physically
exposing portions of the pipe and chiseling into the pipe (and spot repair sample areas). Based
on the type of pipe and the condition of the lining an estimate of useful life must be developed.
If any physical improvements are reasonably provided under this project to facilitate future pipe
replacement then the required improvements should be incorporated into this project. If the
condition assessment recommends relining or in-place rehabilitation of the RAS pipe, those
improvements will be described in the contract documents.
The BODR recommends rehabilitating the SSTs during the dry season when up to an entire
battery (8 SSTs) may be temporarily taken offline for access to the pump cans. Access to the
24-inch to 42-inch discharge pipes will require shutdown of associated RAS pumps. This can
be done in conjunction with the SST shutdown for pump can access.
Replacing the electrical wiring, MCC, and VSDs do not require shutdown and draining of the
SSTs and can be done anytime during the year.
Each tank constitutes its own strategy loop, and may have sludge removed from it
automatically at a rate set independently from the other tank pumping rates. Normally, only one
pump per tank is operating and the other pump serves as a standby, but both pumps can be
manually put in service at the same time if desired.
The return sludge from each tank flows through a magnetic flow meter which can be used to
manually adjust the return from each tank or insure that the return rate is balanced between
tanks. The RAS is pumped to the RAS mixing box located at the west end of the RAS channel
above the central tunnel.
The total secondary influent flow is divided by the number of tanks in service to calculate a
flow setpoint for all tanks. Each tank has an individual operator entered ratio value. This ratio
value is then multiplied by the calculated flow setpoint value to get a flow setpoint for a given
tank. The strategy will then modulate the RAS pump speed to maintain the flow setpoint.
New control strategies will be required to maintain control of the secondary treatment process.
The following features may be required for process controls.
Addition of these process controls are not included in the scope of this project, but may be
added.
If recommended and approved, VFDs shall be located in the field per the Electrical Design
Guidelines. The existing 480V breaker buckets that feed the RAS pumps in the West Secondary
Substation shall be modified to accommodate the increased pump motor size for Battery II and
Battery III. MCC 4K and MCC 4H feeding Battery I RAS pumps shall be replaced. The RAS
pump field located VFDs shall include 3 percent line reactors and through the enclosure heat
sinks integral to the drive. Active harmonic filters shall be added to the existing switchgear
sized appropriately to reduce the harmonics to levels specified in the electrical design
guidelines.
Basis of design for contractor support facilities and laydown area include the following:
The size of the laydown area needs to be evaluated based on construction phasing and
materials delivery.
Utilities extended to the trailer area will be sized to be shared with the BNR, PEPS
pumps, and equalization basin contractor.
The trailer area will be sized to accommodate the contractor, resident engineer, field
engineer (designer), and PMO staff.
After the site preparation is complete, the general completion sequence of construction is the
RAS Pumping project first, followed in turn by the PEPS project and then the BNR project.
This sequence permits orderly testing and commissioning of these projects.
The site utilities requirements for RAS piping must also be coordinated with the BNR area
projects and with the decommissioning/repurposing of the CO Tanks
11.1 RAS Piping Coordination with BNR Project
Design consultant shall coordinate with BNR regarding the diameter of the extension of the
RAS lines to the BNR project. If the RAS pumping discharge point into the BNR reaeration
tanks is more than a 350-foot extension, transitioning to a larger diameter pipe should be
considered. The designer should consider potential savings of lower velocities in the
discharge pipe versus increased energy for pumping at the current velocities. Current
velocities range from 1 ft/s to 12.2 ft/s in the RAS system.
,
DRAFT
April 2013
Business Case Evaluation
RAS Pumping
Contents
1.0 Project Background .............................................................................................................................. 1
2.0 Problem Statement................................................................................................................................ 1
3.0 Functional Requirements ..................................................................................................................... 1
4.0 Alternatives............................................................................................................................................ 2
5.0 Findings.................................................................................................................................................. 4
6.0 Recommendation................................................................................................................................... 5
Tables
Table 1. Summary of Life Cycle Costs..........................................................................................................................4
Table 2. Advantages, Disadvantages, Risks of Preferred Alternatives ..........................................................................4
Appendices
Appendix A. Life Cycle Cost Analysis
At the peak hourly wet weather flow for a 2-year storm (PHWWF2) of 332 mgd, per the CEP1
design criteria, the plant has the capacity of achieving a RAS return rate of 69 percent with all
SSTs and all 48 RAS pumps operating. At average dry weather flow (ADWF) of 181 mgd, the
plant has the capacity of achieving a RAS return rate of 126 percent with all SSTs and all RAS
pumps on. Existing operations protocol of the plant during PHWWF2 calls for a minimum of
20 SSTs to be running at any one time with two SSTs serving as standby. PHWWF2 operations
protocol provides for each SST to have one pump operating and one as standby. In typical
operation of the plant during ADWF, a minimum of 16 SSTs are on line at any one time with
three SSTs serving as standby. Each SST would have one pump operating and one as standby.
The flow rate for RAS pumps on Batteries I and II are controlled with eddy current variable
speed drives and flow rate for Battery III RAS pumps are controlled with variable frequency
drives (VFDs) for each pump. For all SSTs in service, the variable speed pumps are ramped up
and down in unison to help maintain an even sludge blanket. However, uneven flow
distribution into the SSTs does create a non-uniform sludge blanket across the existing SSTs.
The purpose of this business case evaluation (BCE) is to evaluate RAS pump alternatives from
the existing SST to the new biological nutrient removal (BNR) structure, and provide
recommended solutions.
Below is a summary of each alternative and an explanation of whether the option was
considered viable:
Alternative 0 (Existing pumps-status quo) was not considered further because of the
higher head requirements experienced at the RAS pumps would cause the pumps to
deliver insufficient flow to the BNR process. The existing pumps are also unable to
meet the discharge requirements because 16 of the 32 Fairbanks Morse propeller pumps
in Batteries I and II are currently unavailable. As of March 2013, five of the 16
unavailable pumps would require being rebuilt before being placed back into service.
(Alternative eliminated.)
Alternative 1a (Small duty- small duty; Pump type: mixed flow; Manufacturer:
Cascade) two column pumps would be installed in the existing cans. Pump capacity
would match the existing pumps, but the pumps would be capable of pumping the same
flow rate against a greater head. The pump manufacturer Cascade does make a mixed
flow pump that can meet the space, head and flow requirements.
Alternative 1b (Small duty- small duty; Pump type: mixed flow; Manufacturer:
Fairbanks Morse) two column pumps would be installed in the existing cans. Pump
capacity would match the existing pumps, but the pumps would be capable of pumping
the same flow rate against a greater head. The pump manufacturer Fairbanks Morse may
5.0 Findings
This BCE provides a summary of cost, operations, and maintenance considerations for three
basic types of operation strategies (small duty-small duty, large duty- large standby, and large
duty only). Table 1 contains a summary of the capital, annual, and present value (life cycle)
costs for the preferred alternatives. The life cycle cost analysis can be found in Appendix A.
Table 1. Summary of Life Cycle Costs
Annual
Annual Maintenance,
Operating Non-Recurring, Life-Cycle Cost at
Alternative Capital Cost Costs Risk Costs 5% Discount Rate
Alternative 1a $20,000,000 $276,000 $394,000 $39,000,000
Alternative 2a $29,000,000 $289,000 $273,000 $47,000,000
Alternative 3 $17,000,000 $280,000 $174,000 $30,000,000
Each alternative has their own advantages, disadvantages, and risks associated. Table 2
summarizes the advantages, disadvantages, and risks to each preferred alternative.
1. Alternative 1a requires two 4.75-mgd pumps per SST to be functioning to keep the
SST in service and also requires all 48 pumps to be maintained. The large number
of duty pumps in Alternative 1a could allow for a high degree of RAS flow process
control. However, with one pump on, portions of the flow range would result in the
pump operating outside of the acceptable operating range (AOR).
2. Alternative 2a is fundamentally different from the other alternatives because two
9.5-mgd pumps are provided per SST (48 pumps total). If a pump fails, the
impacted SST may remain in service while repairs are made.
3. Alternative 3 requires installation of only 24 pumps each with a capacity of
9.5 mgd.
4. For Alternatives 1a and 3, if three pumps fail simultaneously, there is a risk that the
SSTs may not be able to return the sludge quick enough under high flows and solids
may be passed to the tertiary facilities. To manage this risk, the District may want to
have a rapid response strategy. This strategy may include purchasing a shelf standby
pump that could be rotated into service during repairs. The shelf standby pump
could be purchased as part of the project or delayed until either the flows increase
and/or when the pumps have aged 5 or 10 years.
6.0 Recommendation
Alternative 3 is recommended because of the low life-cycle costs and the lower costs of
maintaining 24 pumps instead of 48 pumps. In addition, pumps would always operate within
the AOR and the majority of the operating range would be within the pumps preferred
operating range (POR). The selection of an alternative with only 24 pumps is consistent with
selected alternative of the District BCE on RAS Unit Maintenance Strategy, February 18, 2010.
Daily Operations
Hours for all
Item and Description Batteries Days per Year Labor, $/hr Total Comment
Three times day an operator walks the SSTS. Each
walk takes approximately 40 minutes. Operators are
Daily operations check on
0.4 365 93 $ 13,578 looking for bad sounds and may observe oil
equipment and facility
reservoirs. Allocate get 45 minutes for attention to
RAS pumps
Pump Installation and pipe 20% based on meeting with D pumps 48 $ 7,750 $ 372,000
realignment Orsinelli on 7/9/01
Three new RAS MCC Substation Based on meeting with D SF 7500 $ 190 $ 1,425,000
(one per battery) Orsinelli on 7/9/2012
Daily Checks
LS 1 $ 13,578 $ 13,578
Breaker maintenance
pumps 48 $ 360 $ 17,298
0
pumps 48 $ - $ -
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Year 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Capital Costs (including soft costs and contractor costs)
Capital Costs (including contingency) $ 20,283,801
Annual Expense (including inflation) $ 20,734,674 $ 464,399 $ 478,331 $ 492,681 $ 507,461 $ 522,685 $ 538,366 $ 554,517 $ 571,152 $ 588,287 $ 654,110 $ 673,733 $ 693,945 $ 714,764 $ 736,207 $ 758,293 $ 781,042 $ 804,473 $ 828,607
Annualized Operations
Life Cycle Cost $ 212,568 $ 208,519 $ 204,547 $ 200,651 $ 196,829 $ 193,080 $ 189,402 $ 185,795 $ 182,256 $ 178,784 $ 175,379 $ 172,038 $ 168,761 $ 165,547 $ 162,394 $ 159,300 $ 156,266 $ 153,290 $ 150,370
Net Present Value $ 7,639,897
Annualized Payments $276,052
2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059
$ 372,739 $ 383,921 $ 395,439 $ 407,302 $ 419,521 $ 432,107 $ 445,070 $ 458,422 $ 472,175 $ 486,340 $ 500,930 $ 515,958 $ 531,437 $ 547,380 $ 563,802 $ 580,716 $ 598,137 $ 616,081 $ 634,564 $ 653,601 $ 673,209
$ 297,761 $ 306,693 $ 315,894 $ 325,371 $ 335,132 $ 345,186 $ 355,542 $ 366,208 $ 377,194 $ 388,510 $ 400,165 $ 412,170 $ 424,535 $ 437,271 $ 450,390 $ 463,901 $ 477,818 $ 492,153 $ 506,917 $ 522,125 $ 537,789
$ 120,108 $ 123,712 $ 127,423 $ 131,246 $ 135,183 $ 139,239 $ 143,416 $ 147,718 $ 152,150 $ 156,714 $ 161,416 $ 166,258 $ 171,246 $ 176,383 $ 181,675 $ 187,125 $ 192,739 $ 198,521 $ 204,477 $ 210,611 $ 216,929
$ 62,857 $ 64,743 $ 66,685 $ 68,686 $ 70,746 $ 72,868 $ 75,055 $ 77,306 $ 79,625 $ 82,014 $ 84,475 $ 87,009 $ 89,619 $ 92,308 $ 95,077 $ 97,929 $ 100,867 $ 103,893 $ 107,010 $ 110,220 $ 113,527
$ 129,485 $ 133,370 $ 137,371 $ 141,492 $ 145,737 $ 150,109 $ 154,612 $ 159,251 $ 164,028 $ 168,949 $ 174,018 $ 179,238 $ 184,615 $ 190,154 $ 195,858 $ 201,734 $ 207,786 $ 214,020 $ 220,440 $ 227,053
$ 853,465 $ 1,008,555 $ 1,038,811 $ 1,069,976 $ 1,102,075 $ 1,135,137 $ 1,169,191 $ 1,204,267 $ 1,240,395 $ 1,277,607 $ 1,315,935 $ 1,355,413 $ 1,396,075 $ 1,437,958 $ 1,481,096 $ 1,525,529 $ 1,571,295 $ 1,618,434 $ 1,666,987 $ 1,716,997 $ 1,768,507
$ 486,719 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412
$ 337,745 $ 380,114 $ 372,873 $ 365,771 $ 358,804 $ 351,970 $ 345,265 $ 338,689 $ 332,238 $ 325,909 $ 319,702 $ 313,612 $ 307,638 $ 301,779 $ 296,031 $ 290,392 $ 284,861 $ 279,435 $ 274,112 $ 268,891 $ 263,769
$ 235,990 $ 260,630 $ 250,887 $ 241,508 $ 232,479 $ 223,788 $ 215,423 $ 207,369 $ 199,617 $ 192,155 $ 184,972 $ 178,057 $ 171,400 $ 164,993 $ 158,825 $ 152,888 $ 147,172 $ 141,670 $ 136,374 $ 131,276 $ 126,369
$ 147,506 $ 144,696 $ 141,940 $ 139,236 $ 136,584 $ 133,983 $ 131,430 $ 128,927 $ 126,471 $ 124,062 $ 121,699 $ 119,381 $ 117,107 $ 114,877 $ 112,688 $ 110,542 $ 108,436 $ 106,371 $ 104,345 $ 102,357 $ 100,408
$ 480,726 $ 624,633 $ 643,372 $ 662,673 $ 682,553 $ 703,030 $ 724,121 $ 745,845 $ 768,220 $ 791,267 $ 815,005 $ 839,455 $ 864,638 $ 890,577 $ 917,295 $ 944,814 $ 973,158 $ 1,002,353 $ 1,032,423 $ 1,063,396 $ 1,095,298
$ 190,240 $ 235,418 $ 230,934 $ 226,535 $ 222,220 $ 217,987 $ 213,835 $ 209,762 $ 205,766 $ 201,847 $ 198,002 $ 194,231 $ 190,531 $ 186,902 $ 183,342 $ 179,850 $ 176,424 $ 173,064 $ 169,767 $ 166,534 $ 163,361
2060 2061 2062 2063 2064 2065 2066 2067 2068 2069 2070 2071 2072 2073 2074 2075 2076 2077 2078 2079
$ 693,405 $ 714,207 $ 735,633 $ 757,702 $ 780,433 $ 803,846 $ 827,962 $ 852,801 $ 878,385 $ 904,736 $ 931,878 $ 959,834 $ 988,630 $ 1,018,288 $ 1,048,837 $ 1,080,302 $ 1,112,711 $ 1,146,093 $ 1,180,475 $ 1,215,890
$ 553,922 $ 570,540 $ 587,656 $ 605,286 $ 623,445 $ 642,148 $ 661,412 $ 681,255 $ 701,692 $ 722,743 $ 744,425 $ 766,758 $ 789,761 $ 813,454 $ 837,857 $ 862,993 $ 888,883 $ 915,549 $ 943,016 $ 971,306
$ 223,437 $ 230,140 $ 237,044 $ 244,156 $ 251,480 $ 259,025 $ 266,795 $ 274,799 $ 283,043 $ 291,535 $ 300,281 $ 309,289 $ 318,568 $ 328,125 $ 337,969 $ 348,108 $ 358,551 $ 369,307 $ 380,387 $ 391,798
$ 116,933 $ 120,440 $ 124,054 $ 127,775 $ 131,609 $ 135,557 $ 139,624 $ 143,812 $ 148,127 $ 152,570 $ 157,148 $ 161,862 $ 166,718 $ 171,719 $ 176,871 $ 182,177 $ 187,642 $ 193,272 $ 199,070 $ 205,042
$ 233,865 $ 240,881 $ 248,107 $ 255,551 $ 263,217 $ 271,114 $ 279,247 $ 287,624 $ 296,253 $ 305,141 $ 314,295 $ 323,724 $ 333,436 $ 343,439 $ 353,742 $ 364,354 $ 375,285 $ 386,543 $ 398,140 $ 410,084
$ 1,821,562 $ 1,876,209 $ 1,932,495 $ 1,990,470 $ 2,050,184 $ 2,111,689 $ 2,175,040 $ 2,240,291 $ 2,307,500 $ 2,376,725 $ 2,448,027 $ 2,521,468 $ 2,597,112 $ 2,675,025 $ 2,755,276 $ 2,837,934 $ 2,923,072 $ 3,010,764 $ 3,101,087 $ 3,194,120
$ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412 $ 558,412
$ 258,745 $ 253,817 $ 248,982 $ 244,239 $ 239,587 $ 235,024 $ 230,547 $ 226,156 $ 221,848 $ 217,622 $ 213,477 $ 209,411 $ 205,422 $ 201,509 $ 197,671 $ 193,906 $ 190,212 $ 186,589 $ 183,035 $ 179,549
$ 121,645 $ 117,097 $ 112,720 $ 108,506 $ 104,450 $ 100,545 $ 96,786 $ 93,168 $ 89,685 $ 86,332 $ 83,105 $ 79,998 $ 77,008 $ 74,129 $ 71,358 $ 68,690 $ 66,122 $ 63,650 $ 61,271 $ 58,980
$ 98,495 $ 96,619 $ 94,779 $ 92,973 $ 91,202 $ 89,465 $ 87,761 $ 86,090 $ 84,450 $ 82,841 $ 81,263 $ 79,715 $ 78,197 $ 76,708 $ 75,246 $ 73,813 $ 72,407 $ 71,028 $ 69,675 $ 68,348
$ 1,128,157 $ 1,162,002 $ 1,196,862 $ 1,232,768 $ 1,269,751 $ 1,307,843 $ 1,347,078 $ 1,387,491 $ 1,429,115 $ 1,471,989 $ 1,516,149 $ 1,561,633 $ 1,608,482 $ 1,656,736 $ 1,706,439 $ 1,757,632 $ 1,810,361 $ 1,864,672 $ 1,920,612 $ 1,978,230
$ 160,250 $ 157,197 $ 154,203 $ 151,266 $ 148,385 $ 145,558 $ 142,786 $ 140,066 $ 137,398 $ 134,781 $ 132,214 $ 129,695 $ 127,225 $ 124,802 $ 122,425 $ 120,093 $ 117,805 $ 115,561 $ 113,360 $ 111,201
Daily Operations
Hours for all
Item and Description Batteries Days per Year Labor, $/hr Total Comment
Three times day an operator walks the SSTS. Each
walk takes approximately 40 minutes. Operators are
Daily operations check on
0.4 365 93 $ 13,578 looking for bad sounds and may observe oil
equipment and facility
reservoirs. Allocate get 45 minutes for attention to
RAS pumps
3%
Labor cost, $/hr = 93
Maintenance Cost Multiplier** 3.1
Loaded labor, $/hr = 288.3
Pump Installation and pipe 20% based on meeting with D pumps 48 $ 14,500 $ 696,000
realignment Orsinelli on 7/9/01
Three new RAS MCC Substation Based on meeting with D SF 7500 $ 190 $ 1,425,000
(one per battery) Orsinelli on 7/9/2012
Daily Checks
LS 1 $ 13,578 $ 13,578
Breaker maintenance
pumps 48 $ 360 $ 17,298
0
pumps 48 $ - $ -
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Year 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Capital Costs (including soft costs and contractor costs)
Capital Costs (including contingency) $ 28,746,265
Annual Expense (including inflation) $ 29,214,911 $482,706 $497,188 $512,103 $527,466 $543,290 $559,589 $576,377 $593,668 $611,478 $629,822 $648,717 $668,178 $688,224 $708,871 $793,774 $817,587 $842,115 $867,378
Annualized Operations
Life Cycle Cost $ 222,558 $ 218,319 $ 214,160 $ 210,081 $ 206,080 $ 202,154 $ 198,304 $ 194,526 $ 190,821 $ 187,187 $ 183,621 $ 180,124 $ 176,693 $ 173,327 $ 170,026 $ 166,787 $ 163,610 $ 160,494 $ 157,437
Net Present Value $ 7,998,955
Annualized Payments $289,026
2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059 2060
$ 390,257 $ 401,965 $ 414,023 $ 426,444 $ 439,237 $ 452,415 $ 465,987 $ 479,967 $ 494,366 $ 509,197 $ 524,473 $ 540,207 $ 556,413 $ 573,105 $ 590,298 $ 608,007 $ 626,248 $ 645,035 $ 664,386 $ 684,318 $ 704,847 $ 725,993
$ 311,410 $ 320,752 $ 330,375 $ 340,286 $ 350,495 $ 361,010 $ 371,840 $ 382,995 $ 394,485 $ 406,319 $ 418,509 $ 431,064 $ 443,996 $ 457,316 $ 471,036 $ 485,167 $ 499,722 $ 514,713 $ 530,155 $ 546,059 $ 562,441 $ 579,314
$ 120,108 $ 123,712 $ 127,423 $ 131,246 $ 135,183 $ 139,239 $ 143,416 $ 147,718 $ 152,150 $ 156,714 $ 161,416 $ 166,258 $ 171,246 $ 176,383 $ 181,675 $ 187,125 $ 192,739 $ 198,521 $ 204,477 $ 210,611 $ 216,929 $ 223,437
$ 71,625 $ 73,773 $ 75,986 $ 78,266 $ 80,614 $ 83,032 $ 85,523 $ 88,089 $ 90,732 $ 93,454 $ 96,257 $ 99,145 $ 102,119 $ 105,183 $ 108,339 $ 111,589 $ 114,936 $ 118,384 $ 121,936 $ 125,594 $ 129,362 $ 133,243
$ 99,145 $ 102,119 $ 105,183 $ 108,339 $ 111,589 $ 114,936 $ 118,384 $ 121,936 $ 125,594 $ 129,362 $ 133,243
$893,400 $920,202 $947,808 $976,242 $1,005,529 $1,035,695 $1,066,766 $1,098,769 $1,131,732 $1,165,684 $1,200,655 $1,335,819 $1,375,894 $1,417,171 $1,459,686 $1,503,476 $1,548,581 $1,595,038 $1,642,889 $1,692,176 $1,742,941 $1,795,229
$ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 509,493 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340
$ 353,549 $ 346,814 $ 340,208 $ 333,728 $ 327,371 $ 321,136 $ 315,019 $ 309,019 $ 303,133 $ 297,359 $ 291,695 $ 309,078 $ 303,191 $ 297,416 $ 291,751 $ 286,194 $ 280,743 $ 275,395 $ 270,150 $ 265,004 $ 259,956 $ 255,005
$ 247,032 $ 237,798 $ 228,908 $ 220,351 $ 212,113 $ 204,184 $ 196,551 $ 189,203 $ 182,130 $ 175,321 $ 168,767 $ 175,483 $ 168,923 $ 162,608 $ 156,529 $ 150,677 $ 145,045 $ 139,622 $ 134,403 $ 129,378 $ 124,542 $ 119,886
$ 154,438 $ 151,496 $ 148,611 $ 145,780 $ 143,003 $ 140,279 $ 137,607 $ 134,986 $ 132,415 $ 129,893 $ 127,419 $ 124,992 $ 122,611 $ 120,275 $ 117,984 $ 115,737 $ 113,533 $ 111,370 $ 109,249 $ 107,168 $ 105,127 $ 103,124
$ 503,143 $ 518,237 $ 533,784 $ 549,798 $ 566,292 $ 583,281 $ 600,779 $ 618,802 $ 637,366 $ 656,487 $ 676,182 $ 795,613 $ 819,481 $ 844,065 $ 869,387 $ 895,469 $ 922,333 $ 950,003 $ 978,503 $ 1,007,858 $ 1,038,094 $ 1,069,237
$ 199,111 $ 195,318 $ 191,598 $ 187,948 $ 184,368 $ 180,857 $ 177,412 $ 174,032 $ 170,718 $ 167,466 $ 164,276 $ 184,087 $ 180,580 $ 177,141 $ 173,767 $ 170,457 $ 167,210 $ 164,025 $ 160,901 $ 157,836 $ 154,830 $ 151,880
2061 2062 2063 2064 2065 2066 2067 2068 2069 2070 2071 2072 2073 2074 2075 2076 2077 2078 2079
$ 747,772 $ 770,206 $ 793,312 $ 817,111 $ 841,624 $ 866,873 $ 892,879 $ 919,666 $ 947,256 $ 975,673 $ 1,004,944 $ 1,035,092 $ 1,066,145 $ 1,098,129 $ 1,131,073 $ 1,165,005 $ 1,199,955 $ 1,235,954 $ 1,273,032
$ 596,694 $ 614,595 $ 633,033 $ 652,023 $ 671,584 $ 691,732 $ 712,484 $ 733,858 $ 755,874 $ 778,550 $ 801,907 $ 825,964 $ 850,743 $ 876,265 $ 902,553 $ 929,630 $ 957,518 $ 986,244 $ 1,015,831
$ 230,140 $ 237,044 $ 244,156 $ 251,480 $ 259,025 $ 266,795 $ 274,799 $ 283,043 $ 291,535 $ 300,281 $ 309,289 $ 318,568 $ 328,125 $ 337,969 $ 348,108 $ 358,551 $ 369,307 $ 380,387 $ 391,798
$ 137,240 $ 141,357 $ 145,598 $ 149,966 $ 154,465 $ 159,099 $ 163,872 $ 168,788 $ 173,851 $ 179,067 $ 184,439 $ 189,972 $ 195,671 $ 201,542 $ 207,588 $ 213,815 $ 220,230 $ 226,837 $ 233,642
$ 137,240 $ 141,357 $ 145,598 $ 149,966 $ 154,465 $ 159,099 $ 163,872 $ 168,788 $ 173,851 $ 179,067 $ 184,439 $ 189,972 $ 195,671 $ 201,542 $ 207,588 $ 213,815 $ 220,230 $ 226,837 $ 233,642
$1,849,086 $1,904,559 $1,961,696 $2,020,547 $2,081,163 $2,143,598 $2,207,906 $2,274,143 $2,342,367 $2,412,638 $2,485,017 $2,559,568 $2,636,355 $2,715,446 $2,796,909 $2,880,816 $2,967,241 $3,056,258 $3,147,946
$ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340 $ 550,340
$ 250,147 $ 245,383 $ 240,709 $ 236,124 $ 231,626 $ 227,214 $ 222,886 $ 218,641 $ 214,476 $ 210,391 $ 206,384 $ 202,452 $ 198,596 $ 194,813 $ 191,103 $ 187,463 $ 183,892 $ 180,389 $ 176,953
$ 115,404 $ 111,090 $ 106,937 $ 102,940 $ 99,091 $ 95,387 $ 91,821 $ 88,389 $ 85,084 $ 81,904 $ 78,842 $ 75,894 $ 73,057 $ 70,326 $ 67,697 $ 65,166 $ 62,730 $ 60,385 $ 58,128
$ 101,160 $ 99,233 $ 97,343 $ 95,489 $ 93,670 $ 91,886 $ 90,135 $ 88,419 $ 86,734 $ 85,082 $ 83,462 $ 81,872 $ 80,313 $ 78,783 $ 77,282 $ 75,810 $ 74,366 $ 72,950 $ 71,560
$ 1,101,314 $ 1,134,353 $ 1,168,384 $ 1,203,435 $ 1,239,539 $ 1,276,725 $ 1,315,026 $ 1,354,477 $ 1,395,112 $ 1,436,965 $ 1,480,074 $ 1,524,476 $ 1,570,210 $ 1,617,317 $ 1,665,836 $ 1,715,811 $ 1,767,286 $ 1,820,304 $ 1,874,913
$ 148,988 $ 146,150 $ 143,366 $ 140,635 $ 137,956 $ 135,329 $ 132,751 $ 130,222 $ 127,742 $ 125,309 $ 122,922 $ 120,580 $ 118,284 $ 116,031 $ 113,821 $ 111,653 $ 109,526 $ 107,440 $ 105,393
Daily Operations
Hours for all
Item and Description Batteries Days per Year Labor, $/hr Total Comment
Three times day an operator walks the SSTS. Each
walk takes approximately 40 minutes. Operators are
Daily operations check on
0.2 365 93 $ 6,789 looking for bad sounds and may observe oil
equipment and facility
reservoirs. Allocate get 30 minutes for attention to
RAS pumps
Check for sound, vibration and Assume 5 minutes per pump per week to check for
hrs/yr/pump 4.3 $ 288 $ 1,249
general performance. sound and vibration and general performance.
Annual PMS to oil the lower Annual PMS include 2 hours per year for each pump
hrs/yr/pump 2 $ 288 $ 577
bearings to oil the lower bearings
Electricians check motors and 3 hour per pump per year for electricians to check
hrs/yr/pump 3 $ 288 $ 865
oil the motors. motors and oil the motors.
Breaker maintenance: 2.5 hours for each pump
Breaker maintenance hrs/yr/pump 1.3 $ 288 $ 360
breaker every 2 years
Pump Installation and pipe 20% based on meeting with D pumps 24 $ 14,500 $ 348,000
realignment Orsinelli on 7/9/01
Three new RAS MCC Substation (one Based on meeting with D SF 7500 $ 190 $ 1,425,000
per battery) Orsinelli on 7/9/2012
Daily Checks
LS 1 $ 6,789 $ 6,789
Breaker maintenance
pumps 24 $ 360 $ 8,649
0
pumps 24 $ - $ -
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
Year 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038
Capital Costs (including soft costs and contractor costs)
Capital Costs (including contingency) $ 17,366,565
Annual Expense (including inflation) $ 17,689,810 $ 332,943 $ 342,931 $ 353,219 $ 363,815 $ 374,730 $ 385,972 $ 397,551 $ 409,477 $ 421,762 $ 489,309 $ 447,447 $ 519,108 $ 474,697 $ 550,721 $ 503,606 $ 584,260 $ 534,275 $ 619,842
Annualized Operations
Life Cycle Cost $ 215,769 $ 211,659 $ 207,628 $ 203,673 $ 199,793 $ 195,988 $ 192,255 $ 188,593 $ 185,000 $ 181,476 $ 178,020 $ 174,629 $ 171,303 $ 168,040 $ 164,839 $ 161,699 $ 158,619 $ 155,598 $ 152,634
Net Present Value $ 7,754,952
Annualized Payments $280,209
2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059
$ 378,352 $ 389,703 $ 401,394 $ 413,436 $ 425,839 $ 438,614 $ 451,772 $ 465,326 $ 479,285 $ 493,664 $ 508,474 $ 523,728 $ 539,440 $ 555,623 $ 572,292 $ 589,460 $ 607,144 $ 625,359 $ 644,119 $ 663,443 $ 683,346
$ 128,406 $ 132,258 $ 136,226 $ 140,313 $ 144,522 $ 148,858 $ 153,324 $ 157,923 $ 162,661 $ 167,541 $ 172,567 $ 177,744 $ 183,076 $ 188,569 $ 194,226 $ 200,053 $ 206,054 $ 212,236 $ 218,603 $ 225,161 $ 231,916
$ 60,054 $ 61,856 $ 63,712 $ 65,623 $ 67,592 $ 69,619 $ 71,708 $ 73,859 $ 76,075 $ 78,357 $ 80,708 $ 83,129 $ 85,623 $ 88,192 $ 90,837 $ 93,562 $ 96,369 $ 99,260 $ 102,238 $ 105,305 $ 108,465
$ 73,773 $ 78,266 $ 83,032 $ 88,089 $ 93,454 $ 99,145 $ 105,183 $ 111,589 $ 118,384 $ 125,594
$ 73,773 $ 78,266 $ 83,032 $ 88,089 $ 93,454 $ 99,145 $ 105,183 $ 111,589 $ 118,384 $ 125,594
$ 566,813 $ 731,363 $ 601,331 $ 775,903 $ 637,953 $ 823,156 $ 676,804 $ 873,286 $ 718,021 $ 926,469 $ 761,749 $ 982,891 $ 808,139 $ 1,042,749 $ 857,355 $ 1,106,253 $ 909,568 $ 1,173,624 $ 964,960 $ 1,245,097 $ 1,023,726
$ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245
$ 224,307 $ 275,643 $ 215,843 $ 265,242 $ 207,699 $ 255,234 $ 199,862 $ 245,604 $ 192,321 $ 236,336 $ 185,064 $ 227,419 $ 178,081 $ 218,838 $ 171,362 $ 210,581 $ 164,896 $ 202,635 $ 158,674 $ 194,989 $ 152,687
$ 156,728 $ 188,998 $ 145,229 $ 175,132 $ 134,574 $ 162,282 $ 124,701 $ 150,376 $ 115,551 $ 139,343 $ 107,074 $ 129,120 $ 99,218 $ 119,646 $ 91,938 $ 110,868 $ 85,193 $ 102,734 $ 78,942 $ 95,196 $ 73,150
$ 149,727 $ 146,875 $ 144,077 $ 141,333 $ 138,641 $ 136,000 $ 133,410 $ 130,868 $ 128,376 $ 125,931 $ 123,532 $ 121,179 $ 118,871 $ 116,606 $ 114,385 $ 112,207 $ 110,069 $ 107,973 $ 105,916 $ 103,899 $ 101,920
$ 188,460 $ 341,661 $ 199,938 $ 362,468 $ 212,114 $ 384,542 $ 225,031 $ 407,961 $ 238,736 $ 432,805 $ 253,275 $ 459,163 $ 268,699 $ 487,126 $ 285,063 $ 516,792 $ 302,423 $ 548,265 $ 320,841 $ 581,654 $ 340,380
$ 74,580 $ 128,768 $ 71,766 $ 123,910 $ 69,058 $ 119,234 $ 66,452 $ 114,735 $ 63,945 $ 110,406 $ 61,532 $ 106,240 $ 59,210 $ 102,231 $ 56,976 $ 98,374 $ 54,826 $ 94,662 $ 52,758 $ 91,090 $ 50,767
2060 2061 2062 2063 2064 2065 2066 2067 2068 2069 2070 2071 2072 2073 2074 2075 2076 2077 2078 2079
$ 703,847 $ 724,962 $ 746,711 $ 769,112 $ 792,186 $ 815,951 $ 840,430 $ 865,643 $ 891,612 $ 918,360 $ 945,911 $ 974,288 $ 1,003,517 $ 1,033,623 $ 1,064,631 $ 1,096,570 $ 1,129,467 $ 1,163,351 $ 1,198,252 $ 1,234,199
$ 238,873 $ 246,039 $ 253,421 $ 261,023 $ 268,854 $ 276,919 $ 285,227 $ 293,784 $ 302,597 $ 311,675 $ 321,026 $ 330,656 $ 340,576 $ 350,793 $ 361,317 $ 372,157 $ 383,321 $ 394,821 $ 406,666 $ 418,866
$ 111,719 $ 115,070 $ 118,522 $ 122,078 $ 125,740 $ 129,512 $ 133,398 $ 137,400 $ 141,522 $ 145,767 $ 150,140 $ 154,645 $ 159,284 $ 164,062 $ 168,984 $ 174,054 $ 179,275 $ 184,654 $ 190,193 $ 195,899
$ 133,243 $ 141,357 $ 149,966 $ 159,099 $ 168,788 $ 179,067 $ 189,972 $ 201,542 $ 213,815 $ 226,837
$ 133,243 $ 141,357 $ 149,966 $ 159,099 $ 168,788 $ 179,067 $ 189,972 $ 201,542 $ 213,815 $ 226,837
$ 1,320,924 $ 1,086,071 $ 1,401,368 $ 1,152,213 $ 1,486,711 $ 1,222,383 $ 1,577,252 $ 1,296,826 $ 1,673,307 $ 1,375,803 $ 1,775,211 $ 1,459,589 $ 1,883,321 $ 1,548,478 $ 1,998,016 $ 1,642,781 $ 2,119,695 $ 1,742,826 $ 2,248,784 $ 1,848,964
$ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245 $ 404,938 $ 323,245
$ 187,632 $ 146,925 $ 180,552 $ 141,382 $ 173,739 $ 136,047 $ 167,183 $ 130,914 $ 160,875 $ 125,974 $ 154,805 $ 121,221 $ 148,964 $ 116,647 $ 143,343 $ 112,245 $ 137,934 $ 108,010 $ 132,730 $ 103,935
$ 88,212 $ 67,783 $ 81,740 $ 62,810 $ 75,743 $ 58,202 $ 70,185 $ 53,932 $ 65,036 $ 49,975 $ 60,264 $ 46,308 $ 55,843 $ 42,911 $ 51,746 $ 39,762 $ 47,949 $ 36,845 $ 44,431 $ 34,142
$ 99,978 $ 98,074 $ 96,206 $ 94,373 $ 92,576 $ 90,813 $ 89,083 $ 87,386 $ 85,721 $ 84,089 $ 82,487 $ 80,916 $ 79,375 $ 77,863 $ 76,380 $ 74,925 $ 73,498 $ 72,098 $ 70,724 $ 69,377
$ 617,077 $ 361,109 $ 654,657 $ 383,101 $ 694,526 $ 406,432 $ 736,822 $ 431,184 $ 781,695 $ 457,443 $ 829,300 $ 485,301 $ 879,804 $ 514,856 $ 933,384 $ 546,210 $ 990,228 $ 579,475 $ 1,050,532 $ 614,765
$ 87,653 $ 48,851 $ 84,346 $ 47,008 $ 81,163 $ 45,234 $ 78,101 $ 43,528 $ 75,154 $ 41,885 $ 72,318 $ 40,305 $ 69,589 $ 38,784 $ 66,964 $ 37,321 $ 64,437 $ 35,912 $ 62,005 $ 34,557
Soft Costs
Engineering Services Through Bid 9% 9.00%
Engineering Services During Construction 4% 4.00%
PMO Support (JV) 5% 5.00%
District Staff 3% 3.00%
Construction Management 8% 8.00%
Change Order Contingency 5% 5.00%
Project Contingency 7% 7.00%
Program Contingency 0% 0.00%
Total soft cost markups 41%
Note: Values are compounding or multiplicative rather than simple
Total Markup
Goss markup 2.44
Soft Cost markups 1.41
Total markup of construction costs 3.44
Attachment B
Alternatives Development
Return Activated Sludge Business Case Evaluation Development
This attachment provides the basis regarding how each alternative in the RAS BCE was
selected. There are several options in determining how many pumps should be used and how
large each pump should be. There are several types of pump operation strategies and a wide
selection of available pumps that will work with RAS. In this document, four pump operation
strategies are paired with three pump options to develop a list of three viable alternatives.
If the 32 Fairbanks Morse propeller pumps in Batteries I and II were used with all pumps on,
the maximum flow rate would be 3,000 gpm (4.3 mgd) at 39 feet TDH per pump. The
16 Goulds mixed flow pumps in Battery III will operate at a maximum 3,100 gpm (4.5 mgd) at
40 feet TDH per pump. Both the existing Fairbanks Morse and Goulds pumps will not meet the
design flow requirements and larger pumps will be required. The existing RAS system curve
was modeled and overlaid with the existing pumps. The existing piping system trace is shown
in Appendix B along with the existing pipe system curve and pipe segment detail report. This
graphic is provided in Appendix B.
The existing pumps are unable to meet the discharge requirements because 16 of the
32 Fairbanks Morse propeller pumps in Batteries I and II are currently unavailable. As of
March 2013, five of the 16 unavailable pumps would require being rebuilt or replaced before
being placed back into service.
Existing pump curves for Batteries I and II are overlaid against the proposed system curve is
shown on Figure 1. The Battery III existing pump curves are overlaid against the proposed
system curve and are shown on Figure 2. The system curve was developed based on a detailed
analysis of each pipe segment in the existing system.
The model considers all pipes and fittings as found on the design drawings. Modeling of the
major losses is based on DarcyWeisbach equation. All piping is modeled based on DIP,
cement mortar-lined with a roughness coefficient of 0.000417 0.001083 foot. The roughness
coefficient is adapted from Pumping Station Design Manual (Garr Jones et al, 2008) and the
B-1
high value of 0.001083 foot approximates aged pipe with cement mortar lining. However,
subsequent review of original design specifications suggests that all buried piping 14 inches
and greater may be bar wrapped concrete cylinder pipe (AWWA C303). In the original design
specifications, the above grade RAS piping near the pumps is described as steel pipe
(AWWA 200) with enamel lining. Pending confirmation during the condition assessment,
coefficients should be revised based on the roughness values described in Design Guidelines.
Table 1 contains values for minor loss coefficients that are used in the model.
The maximum static lift of 6.4 feet (119.0 feet 112.6 feet) for the proposed RAS pumping
system curve is based on an assumed water surface elevation in the BNR RAS reaeration tank.
This maximum is from the provisional hydraulic profile in Appendix A and is estimated from
losses for the existing treatment train and for the future BNR treatment train. The future system
curve and segment detail report is shown in Appendix B. For reference, existing pump
documentation is contained in Appendix C.
2) Use the corrected head to establish the flow per 1) To determine the flow for each pump
pump. Use the flow per pump with the uncorrected when two pumps are running use the
pump curve to determine the head experienced by intersection of the system curve and the
the pump when two pumps are on. summed corrected pumps
B-2
Figure 2. Battery III Existing Goulds Pump Curves Overlaid against the Proposed System Curve
The large duty-large standby strategy requires the flow per can to be double the original design
requirements. However, with the increased flows, the open bottom can to horizontal header still
conforms to the requirements of the Hydraulic Institute (HI) standards 9.8.2.6, as shown in
Table 2. Because the cans conform to the requirements of HI 9.8.2.6, the design consultant will
not require a physical model; however, during design the design consultant will require the
pump manufacturers to confirm that prospective pumps are compatible with the existing cans.
B-3
Table 2. Summary of Eliminated Alternatives
Duty-
HI Requirement Standby HI Value
Value
Velocity in Can Below 4.7 5.0
Suction Bell, ft/s
Depth from header to 12 9 (3 X Suction
Suction Bell, ft Bell Diameter)
Depth of Suction Bell 11.5 2.5
Below Water Surface
Elevation, ft
A variant of this strategy would be to simply leave the existing pump in place next to the new
large pump. Depending on the large pump selection, there is a potential to extend the low flow
range of the SST by leaving the existing pump in service. This extended range could be helpful
for meeting process needs during startup.
Construction Sequencing
Construction sequencing will be a challenge for both small and large pumps. Higher head
pumps are required to supply RAS to the BNR. However, the pumps are planned to be installed
prior to cutting over from the CO tanks to the BNR tanks. Both large and small pumps can be
kept operating within their allowable operating region (AOR). At start up (to the CO tanks) the
discharge valve can be throttled and the higher end of the pump speed can be restricted. The
design engineer will have to develop the optimal strategy and sequencing plan.
B-4
Pump Selection Options
This section investigates optional pump types to be considered for replacement of the existing
pumps. Pump selection is an iterative process that is dependent on pump operating levels,
dimensions and characteristics. The process starts by developing the high and low system
curves assuming static lift conditions and then selecting a pump that matches those conditions.
Once in the detail design stage, the pumps dimensions are then used to verify that the pump
meets the standards set by the American National Standards Institute (ANSI)/Hydraulic
Institute Standards (HI). The intent of this section is to perform an initial vetting of three
classes of pumps: propeller pumps, mixed flow pumps, and vertical turbine solids handling
pumps.
Propeller Pumps
A propeller pump (i.e., axial flow pump) is a common type of pump that is essentially a
propeller in a pipe. The propeller blades push the liquid parallel to the pipe and work best under
low head and higher flow conditions. These pumps are currently being used in Batteries I
and II. While propeller pumps may be viable for the increased head of this application, they
would be operating at the edge of what this type of pump can achieve.
Manufacturers of propeller pumps include Patterson, Fairbanks Morse, and others; however,
neither manufacturer recommended using propeller pumps. Specifically, Patterson cited the fact
that their propeller pumps are more appropriate for TDH conditions lower than 20 feet and
Fairbanks Morse does not have a propeller pump that can meet these flow and head
requirements.
Mixed flow pumps are provided by all three of the contacted manufacturers (Cascade,
Fairbanks Morse, and Patterson) and were found to be the most efficient type of pumps
considered. Cascade and Fairbanks Morse each provided one mixed flow pump selection for
each strategy. Patterson provided one mixed flow pump selection for the duty-duty strategy.
B-5
Patterson Pumps does have one VTSH type pump, the Multi-Purpose Vertical Turbine Pumps
(12MPVT), that will fit in the 24-inch-diameter can. This model would only apply for the small
duty-small duty pumping strategy.
For applications that have a risk or a history of solids or stringy materials fouling pumps,
VTSH pumps are well suited. However, at SRCSD both propeller and mixed flow pumps have
performed well for approximately three decades on the RAS system. There may be limited
value to using VTSH pumps on the existing RAS system. Considering mixed flow pumps in
addition to VTSH pumps may provide access to a wider variety of pumping solutions that
provide a greater benefit for performance at a lower cost.
List of Alternatives
The list of the alternatives considered is summarized in Table 3. The table represents a
matching up of operational strategies with the list of available pump options that meet the
design requirements. The three manufacturers contacted are not the only manufacturers
providing propeller, mixed flow, or VTSH pumps. Although a complete search for all
manufacturers was not conducted, the reviewed pumps are considered representative of each
type of pump and are acceptable for the preliminary nature of this document.
1. Pumps listed in this table are a sample of pumps available. An exhaustive search for appropriate pumps was not conducted;
only these three manufacturers were contacted.
B-6
Appendix A
Hydraulic Profile
This appendix estimates the liquid train hydraulic profile through the biological process to the
SSTs. The purpose of this section is to establish the estimated water surface elevation in the
RAS reaeration tank to compute the static head loss that the RAS pumps must overcome. This
Appendix is for planning level purposes only. Once the BNR design team develops a hydraulic
profile for the Preliminary Design Report this Appendix will either be deleted or significantly
revised. The difference in water surface elevations in the SSTs and the upstream RAS
connection point determines the static head required for the RAS pumping system. In the next
section, the static head for the existing and future conditions are combined with the dynamic
losses to develop system curves. Table 1 contains the design flow criteria
A-1
Table 2. Hydraulic Losses from the Existing Settled Sewage Channel to the SSTs
Loss, ft Elevation, ft
Item PHWWF2 ADWF PHWWF2 ADWF Basis
A SSTs 112.61 112.59 From Carbonaceous Oxidation
Tank Expansion Project
B Mixed Liquor Dist. Channel 0.46 0.13 113.07 112.72 From Carbonaceous Oxidation
Tank Expansion Project
C Mixed Liquor Channel 0.13 0.03 113.20 112.75 From Carbonaceous Oxidation
Tank Expansion Project
D Oxidation Influent Channel 2.96 2.65 116.16 115.40 From Carbonaceous Oxidation
Tank Expansion Project
E Settled Sewage Channels/ 0.28 0.08 116.44 115.48 From Carbonaceous Oxidation
Junction upstream of CO Tanks Tank Expansion Project
Note: PHWWF2 approximately equals EMDF of 330 mgd and ADWF approximately equals
181 mgd.
A-2
Table 3. Hydraulic Losses from the Reaeration Tanks to the SSTs
Loss, ft Elevation, ft
Item PHWWF2 ADWF PHWWF2 ADWF Basis
A SSTs 112.61 112.59 From Carbonaceous Oxidation
Tank Expansion Project
B Mixed Liquor Dist. Channel 0.46 0.13 113.07 112.72 From Carbonaceous Oxidation
Tank Expansion Project
C Mixed Liquor Channel 0.13 0.03 113.20 112.75 From Carbonaceous Oxidation
Tank Expansion Project
D Oxidation Influent Channel 2.96 2.65 116.16 115.40 From Carbonaceous Oxidation
Tank Expansion Project
E Settled Sewage Channels/ Junction 0.28 0.08 116.44 115.48 From Carbonaceous Oxidation
upstream of CO Tanks Tank Expansion Project
F Effluent Channel at End of BNR 0.10 0.02 116.54 115.50 Two pipes each 120-inches in
Tanks diameter 400 ft from junction with
CO Tanks
G Upstream End of BNR Tanks 0.30 0.20 116.84 115.70 Submerged weir calculation from
(Through BNR Tanks Over Weir at Pilot Plant (7/14/2011)
End of BNR Tanks)
H Channel Upstream of Flow Splitting 1.00 0.30 117.84 116.00 Loss for Cut through Flume
to BNR Tanks (Cut throat flumes) (Assume 40:1 Ratio of head loss in
distribution channel)
I Channel Upstream of RAS Mixing 0.50 0.20 118.34 116.20 Use 0.5 feet for sufficient mixing
energy
J Reaeration Collector Channel 0.20 0.10 118.54 116.30 Use 0.2 ft for sufficient loss in
channel
K Reaeration tank 0.10 0.00 118.64 116.30 Use 0.1 ft for sufficient loss in tank
L Splitter Box (Cut throat flumes 0.50 0.20 119.14 116.50 Use 0.5 ft for flow splitting
upstream of Reaeration)
Note: PHWWF2 approximately equals EMDF of 330 mgd and ADWF approximately equals 181 mgd.
A-3
Appendix B
This packet contains the existing RAS system curve model and associated calculations. The
following is a list of notes and assumptions regarding RAS calculations.
1. There are 24 secondary clarifiers separated into three batteries at SRWTP. Each battery of 8
clarifiers share one 42-inch pipeline to the RAS Channel.
2. Secondary clarifier 4 is used to generate the high system curves in BC Pump Plots.
Secondary clarifier 4 is in Battery I (south east corner) and is the furthest from the RAS
Channelthus has the highest head loss. Secondary clarifier 13 is used to generate the low
system curves in BC Pump Plots. Secondary clarifier 13 is in Battery II (center North), and is
directly adjacent to the 42-inch pipelineclosest to the RAS Channel with the lowest head
loss. The main difference between these two curves is that the low curve uses the lower pipe
and minor loss coefficients and a reduce pipe length due to a different clarifier location.
3. A current condition RAS flow of 9.5 MGD (6,600 gpm) is assumed per secondary clarifier.
4. The RAS Channel water surface elevations during high and low flows are 116.2 ft and 115.4
ft (respectively). The clarifier water surface elevations during high and low flows are 112.61
ft and 112.59 ft. The water surface elevations are taken from Carollos hydraulic profile that
was done under contract 2745 in 1994.
5. The headloss due to the collectors in the clarifier is calculated based on a 1.43 ft headloss at
the manifold at 9.5 MGD. This known value was based on the submittal for the Tow Bro type
collectors in SST Battery III. This headloss was used to back calculate a reasonable minor
loss coefficient for the collector mechanism. Batteries I and II were manufactured by Walker
Process and were assumed to use similar collectors with a similar headloss.
6. The collector discharge manifold (to 30 RAS) is rectangular. An equivalent diameter analysis
was completed and found the rectangular discharge manifold to be 26 inches.
SRCSD RAS Piping Existing
Goulds - Duty
EGL Pressure
Node Description Elevation Flow into Node Flow Increament Flow out of Node
Hi Lo Hi Lo
ft ft ft psf psf mgd mgd mgd
N1 Secondary Clarifiers 112.6 112.6 0 0 0 0 0 9.5
N4 Vertical Propeller Pump 111.1 111.2 102 564 574.9 9.5 0 9.5
N4 Vertical Propeller Pump 138.6 126.3 102 2276.3 1510.5 9.5 0 9.5
N6 Add Tank 3, (2 pumps) 135.4 124.6 105 1892.9 1221.3 9.5 9.5 19.01
N7 Adds tanks 7, 8, (4 pumps) 134.1 123.9 105.4 1788.6 1153.2 19.01 19.01 38.01
N8 Adds tanks 1, 2, 5, 6 (8 126.9 123.5 106 1299 1088.6 38.01 38.01 76.03
N9 RAS Channels 116.2 115.4 0 0 0 76.03 0 0
EGL Pressure
Node Description Elevation Flow into Node Flow Increament Flow out of Node
Hi Lo Hi Lo
ft ft ft psf psf mgd mgd mgd
N1 Secondary Clarifiers 112.6 112.6 0 0 0 0 0 9.5
N4 Vertical Propeller Pump 111.1 111.2 102 564 574.9 9.5 0 9.5
N4 Vertical Propeller Pump 152.9 135.8 102 3169.7 2105 9.5 0 9.5
N6 Add Tank 3, (2 pumps) 149.7 134.2 105 2786.3 1815.8 9.5 9.5 19.01
N7 Adds tanks 7, 8, (4 pumps) 148.5 133.5 105.4 2682 1747.7 19.01 19.01 38.01
N8 Adds tanks 1, 2, 5, 6 (8 141.2 133 106 2192.5 1683.1 38.01 38.01 76.03
N9 RAS Channels 119 118.5 0 0 0 76.03 0 0
[CONSULTANT/DESIGNER ORGANIZATION]
JULY 2013
[CONSULTANT/DESIGNER ORGANIZATION]
APPROVALS
[XXXX]
ADVANCED WASTEWATER TREATMENT PLANT CONTRACT NUMBER
1 2 3 4 5
DESIGN FIRM
ADDRESS
CITY, STATE
PHONE:
CONTACT:
WWW.
REDDING
AVE
VD
D D
AVE
AME
80 S
BL
RICA
BU
N R ARDEN WAY
SUB CONSULTANT
IVE
HOWE
R
WATT
KS
OA VD
ER
SACRAMENTO BL
CITY
RIV
FAIR
CAN
OF AM
ERI
50 PRELIMINARY
SAN FRANCISCO SACRAMENTO OM
LS
FO THIS DRAWING IS NOT VALID FOR
CONSTRUCTION PURPOSES UNLESS IT
FRESNO BEARS THE SEAL AND SIGNATURE OF A
MONTEREY DULY REGISTERED PROFESSIONAL
ST
OC
KT
99
CO
JAC
KSO
ON
N
RD
FRUITRIDGE RD
LO
BRADSHAW RD
C
LOS ANGELOS YO C
101
INN RD
BLV
5 99
RD
D
GRASS FLORIN RD SACRAMENTO REGIONAL
SA
VALLEY WASTEWATER TREATMENT PLANT
POWER
FLORIN
CR
PROJECT LOCATION
RETURN ACTIVATED
AM
Sacramento Regional
SLUDGE PUMPING -
EN
GERBER RD
Wastewater MARYSVILLE
TO
BASIS OF DESIGN
Treatment Plant
80
ELK GROVE -
PATH AND FILENAME: Z:\15. RAS (Return Activated Sludge System)\B. Planning\CAD Graphics\B.20 CAD\1-MODELS\1.0 Revit\2012-AWTP-RASP-15.09-RVT-Admin.rvt
MEADOWVIEW RD
MACK RD
PROJECT LOCATION
PLACERVILLE Sacramento Regional
505 SACRAMENTO 50 Wastewater
80 CALVINE RD
Treatment Plant
BLVD
1 SANTA FREEPORT
DWIGHT RD
ROSA DAVIS
99
SHELDON RD
FAIRFIELD
101 5
B LAGUNA BLVD BOND RD
B
99
N
ST
CONCORD
FRANKLI
AT
CITY OF
ER
680
ELK GROVE
OU
SAN ELK GROVE BLVD
TE
FRANCISCO STOCKTON
RD
E
205
IN
580
TL
5 THIS IS THE ONLY MARK DATE DESCRIPTION
AN
5 ALLOWABLE PLANT ISSUE BLOCK
GR
580 ACCESS FOR DESIGNED
MODESTO CONTRACTORS PMO ENGINEERING
DRAWN
BILBY RD PMO CAD
RD
CAD User: PMO ENGINEERING
CHECKED
KLIN
160
A.G. CALCIANO
RAN
RIVE
SAN
UNION PACIFIC
D-F
HOO
APPROVED
JOSE
BRUCEVILLE RD
1 R. WILLIAMS
R
17 FILENAME
RAILROAD
CRUZ
5 CONTRACT SEQUENCE NUMBER
A DISCIPLINE
A
SALINAS GENERAL
PLOT DATE: 7/2/2013 10:12:40 AM
1 2 3 4 SCALE IN INCHES 0 1/2 1 2 4 (IF SCALE BAR IS NOT 4", SCALE ACCORDINGLY)
1 2 3 4 5
KEYNOTES:
1 EMERGENCY STORAGE BASIN A
ROCKS
ROCKS
DESIGN FIRM
ROCKS ROCKS
ROCKS
ROCKS
ROCKS
ROCKS
ROCKS
ROCKS
ROCKS
ROCKS
ADDRESS
CITY, STATE
ROCKS
ROCKS
ROCKS
3 EMERGENCY STORAGE BASIN E PHONE:
GATE
ROCKS ROCKS
ROCKS ROCKS
ROCKS
GATE
CONTACT:
4 SEPTAGE DISPOSAL AREA WWW.
ROCKS
6
CONC.
CONC.
DI
TC H
ROCKS
CONC. DI TCH
CONC. DI TCH
ROCKS
CONC. DI TCH
PI LES
CONC.
CONC.
CONC.
ASPH.
EMERGENCY STORAGE
ROCKS
ROCKS
CONC.
ROCKS
BASIN C 2 CONC.
1 4
D 6 INFLUENT JUNCTION STRUCTURE D
ROCKS
CONC.
CONC. DI TCH
ROCKS
ASPH.
3
CONC.
ROCKS
ROCKS
ROCKS
ROCKS
CONC.
ASPH.
GATE
ASPH.
CONC. CONC.
ASPH.
CONC.
ASPH.
ASPH. CONC. ASPH.
ASPH. CONC. ASPH.
CONC. CONC.
CONC.
GATE
GATE
CONC. ASPH.
ROCKS
ROCKS
CONC.
ROCKS CONC.
8 BATTERY I DIGESTERS
ASPH.
CONC. CONC.
GATE
ASPH.
CONC.
PI LES
22
ROCKS
ASPH. ASPH.
ASPH.
ASPH.
TRAI LER
CONC.
ASPH.
CONC.
ROCKS CONC.
TRAI LER
CONC. ASPH.
TRAI LER
TRAI LER
DECK
UNKNOW N SUR FACE CONC.
11
ASPH.
5
ASPH.
ASPH.
CONC.
ASPH.
CONC.
TRAI LER
DECK
TRAI LER
ASPH.
12 9 BATTERY II DIGESTERS
CONC. ROCKS
ASPH.
7
GATE
ROCKS
EMERGENCY
CONC.
ASPH.
WA
LL
ROCKS
STORAGE 47
TANK
21
ASPH. ASPH.
ASPH.
UNKNOW N SUR FACE ASPH.
OVERHANG
OVERHANG
UNKNOW N SUR FACE
ASPH. ASPH.
9
PRELIMINARY
CONC. CONC.
OVERHANG
CONC.
ASPH.
ASPH. ASPH.
ASPH. CONC.
ROCKS
CONC.
FOUNDATI ON
OVERHANG
BASIN D
TANK
CONC.
TANK
ASPH. W
OVERHANG
CONC.
TANK TANK
ASPH. ASPH.
FOUNDATI ON
PI LES ROCKS
CONC.
CONC.
CONC.
TANK
TANK
19 27 20
ASPH. GATE CONC.
OVERHANG
OVERHANG
OVERHANG
ROCKS
OVERHANG OVERHANG
ASPH.
8
CONC.
CONC.
ASPH.
CONC.
CONC. ASPH.
OVERHANG
ASPH.
CONC.
OVERHANG
ASPH.
OVERHANG
ASPH.
CONC. TANK
ASPH.
WA LL
TANK TANK
ASPH.
TANK TANK
GATE
TANK
ASPH. ASPH.
ASPH.
CONC.
CONC.
PI LES
18
CONC.
OVERHANG
ASPH. ASPH.
ASPH.
ASPH.
ASPH.
CONC.
ASPH.
ASPH.
TANK
CONC.
ASPH.
ASPH. ASPH.
CONC. CONC. CONC.
CONC.
16
TANK WALL
ASPH.
ASPH.
TANK CONC.
WALL
CONC. TANK CONC. CONC.
ASPH. TANK
ASPH.
ASPH.
GATE GATE CONC.
CONC.
GATE CONC. TRAI LER
CONC. TANK
TANK TANK
CONC.
TANK
ASPH. CONC.
CONC.
CONC.
CONC.
CONC. TANK
CONC. OVERHANG
CONC.
15
ASPH. ASPH. CONC. TRAI LER
TANK TANK TANK
ASPH.
GATE ASPH.
GATE
CONC. ASPH.
CONC. OVERHANG
CONC.
ASPH. TANK
CONC.
TANK
CONC. TANK
CONC.
PI LES
CONC.
TANK
TANK
TANK
ASPH.
ASPH. CONC.
ASPH.
ASPH. ASPH.
ASPH.
PH.
AS ASPH.
ASPH.
ASPH. OVERHANG
CONC.
CONC.
PI LES
CONC. CONC.
ASPH.
CONC.
CONC.
TANK
23
CONC.
ASPH. ASPH. CONC.
GATE CONC. CONC.
GATE GATE
ASPH.
TANK ASPH.
CONC.
CONC.
CONC. CONC.
CONC. CONC.
ASPH.
CONC. GATE ASPH.
ASPH.
CONC. CONC.
GATE
CONC.
CONC.
CONC.
CONC.
CONC.
CONC.
17
TANK
WA LL
CONC.
ASPH.
CONC. CONC.
CONC.
CONC.
ASPH.
CONC. CONC. ASPH.
CONC. ASPH.
ASPH. PI LES
CONC.
CONC.
CONC. CONC. ROCKS
CONC.
ASPH.
24 26
CONC.
ASPH. CONC.
ASPH.
CONC. CONC. CONC.
CONC.
ASPH.
PI LES
CONC.
ASPH.
30
ASPH. CONC.
ROCKS
CONC. CONC.
CONC.
CONC. ASPH.
CONC.
CONC. CONC.
ASPH. TANK
ASPH.
CONC. CONC.
TANK
TANK
TANK TANK GATE
TANK
TANK
TANK
CONC. CONC.
TANKS
TANK
WALK WAY WALK WAY WALK WAY WALK WAY WALK WAY CONC. WALK WAY CONC.
ASPH. TANK CONC. TANK
CONC. ASPH.
CONC.
TANK
TANK
GATE
CONC.
STOR AGE TANK
TANK
GATE
CONC.
TANK ASPH. ASPH.
ASPH.
CONC.
STOR AGE
CONC. ASPH.
SOLIDS
GATE
CONC.
CONC. ASPH.
ASPH.
CONC.
CONC.
CONC. CONC.
CONC. CONC. CONC.
32
CONC.
13
CONC.
PI LES
CONC. PI LES
CONC.
ASPH. CONC.
ASPH. ASPH.
PI LES PI LES
CONC. ASPH.
PI LES GATE CONC. CONC.
ASPH. TANK CONC.
ASPH. CONC. CONC. GATE
CONC.
TANK
PI LES GATE
GATE
STOR AGE
GATE
WALK WAY WALK WAY WALK WAY WALK WAY WALK WAY
STORAGE
WALK WAY
GATE
CONC.
CONC.
ASPH.
ASPH.
ASPH. ASPH.
46
ASPH.
ASPH.
CONC.
ASPH. CONC. ASPH.
CONC. ASPH.
BERM
ASPH. GATE
GATE
CONC.
CONC. ASPH.
CONC.
CONC.
PI LES
CONC. CONC. ASPH.
GATE
ASPH.
CONC.
CONC.
CONC.
CONC.
CONC.
TRAI LER
LL
PI LES
TRAI LER
WA
TANK ASPH.
25 29
CONC.
ASPH.
CONC. CONC.
CONC.
ASPH.
CONC.
ASPH.
OVERHANG
38
ASPH. WALK WAY CONC.
WALK WAY WALK WAY WALK WAY WALK WAY WALK WAY ASPH.
CONC.
CONC.
PI LES
GATE
ASPH.
ASPH. CONC.
GATE
CONC.
17 LSG GAS HOLDER TANKS
ASPH.
GATE
CONC.
CONC.
CONC.
CONC.
CONC.
WALL
PI LES
CONC.
CONC.
ASPH.
CONC.
CONC.
CONC.
CONC.
CONC.
ASPH. CONC.
WALL
PI LES
CONC.
ASPH.
CONC.
CONC.
TANK
TANK
CONC.
CONC.
36
TANK
TANK
CONC.
ASPH.
CONC.
CONC.
ROCKS
CONC.
CONC.
CONC.
CONC.
18 GROUND FLARES
CONC. CONC. CONC. CONC. CONC.
CONC. ASPH.
ASPH.
ASPH.
ASPH. CONC.
WA LL
CONC.
CONC. CONC.
ASPH.
CONC. CONC. CONC. CONC.
CONC.
GATE
PI LES
ASPH.
ASPH.
CONC.
CONC.
CONC.
CONC.
39
ASPH. ASPH.
ASPH.
ASPH.
ASPH.
ASPH.
ASPH.
TANK
TANK ASPH.
CONC. ASPH.
ROCKS
ASPH. CONC.
ASPH.
CONC.
CONC.
ASPH.
C C
TANK
CONC.
40 33
CONC.
TANK
ASPH.
ROCKS
TANK
CONC.
CONC.
WA LL
51
TANK
CONC.
ASPH. ASPH.
ASPH.
GATE
GATE
ASPH.
ASPH.
ASPH. ASPH.
ASPH.
GATE GATE
CONC. ROCKS
ASPH. ASPH.
ASPH.
ASPH.
CONC.
CONC.
49
ROCKS
ROCKS ROCKS
ROCKS GATE
ROCKS
GATE
CONC.
TANK GATE
ASPH.
CONC.
GATE
GATE GATE
48
CONC.
GATE
ASPH.
CONC.
ASPH. ASPH.
OVERHANG
ROCKS ROCKS
ROCKS
GATE GATE
GATE ASPH.
GATE
ASPH.
WA LL
21 INFLUENT/EFFLUENT BUILDING
ASPH.
GATE
CONC.
TANK
CONC.
TANK ASPH.
CONC.
ASPH.
ROCKS
TANK
ASPH. TANK
TANK CONC.
ASPH.
41 28 42 34
TANK
TANK TANK
CONC. CONC.
CONC. TANK
TANK
TANK CONC.
ASPH.
GATE
ASPH.
ASPH.
TANK
CONC.
ASPH.
CONC.
SACRAMENTO REGIONAL
TANK
ASPH.
ROCKS
TANK
GATE PI LES
CONC.
ASPH.
OVERHANG PI LES
OVERHANG
ROCKS
GATE
WA LL
ROCKS
DECK ASPH.
OVERHANG
ASPH. PI LES
PI LES
ROCKS
GATE
TRAI LER
ASPH.
43 50
ASPH.
ASPH.
ASPH. GATE
ASPH. GATE
ASPH. OVERHANG
STOR AGE
OVERHANG
STOR AGE
RETURN ACTIVATED
ASPH.
GATE
ASPH.
GATE
ASPH. ASPH.
WALL
GATE
ASPH.
TANK
ASPH.
ASPH.
ASPH. ASPH.
CONC. ASPH. ASPH.
GATE
CONC. ASPH.
SLUDGE PUMPING -
STO P STO P
ROCKS
TRAI LER
GATE
GATE
TANK
GATE
TANK
37 31 45 ASPH.
BASIS OF DESIGN
CONC.
ASPH.
ASPH.
ASPH.
GATE
GATE
LAGUNA ST
ROCKS
44 35
PATH AND FILENAME: Z:\15. RAS (Return Activated Sludge System)\B. Planning\CAD Graphics\B.20 CAD\1-MODELS\1.0 Revit\2012-AWTP-RASP-15.09-RVT-Admin.rvt
ASPH.
GATE
26 BONE YARD
52
AH EA D AH EA D
ASPH.
ASPH.
ATION ROAD
CONC.
ASPH.
ASPH.
ROCKS ROCKS
ROCKS
ROCKS
UNKNOW N SUR FACE
GATE
GATE
ROCKS
ASPH.
CONC.
GATE
ASPH.
ASPH.
CONC.
ROCKS ROCKS
ROCKS ROCKS CONC. CONC. CONC.
ROCKS
CONC.
CONC.
ROCKS
UNKNOW N SUR FACE
CONC.
ASPH.
CONC.
30 CHEMICAL STORAGE
CONC.
CONC.
BASIN ROCKS
BASIN BASIN CONC.
BASIN
II-4 II-3 II-2 II-1
ROCKS ROCKS
CONC. CONC.
CONC.
ROCKS
ROCKS
ASPH.
ROCKS
ASPH.
ROCKS
ROCKS
CONC.
CONC.
SIMS ROAD
ASPH.
CONC.
ROCKS
ROCKS ROCKS
ROCKS ROCKS
B B
ROCKS
ROCKS
ROCKS
ROCKS ROCKS
CONC. CONC. CONC.
ROCKS
BERM
CONC.
ASPH.
ROCKS
ROCKS
ROCKS
ROCKS
ASPH.
ROCKS
ROCKS
ROCKS
CONC.
ROCKS
ROCKS BASIN CONC.
BASIN BASIN BASIN ASPH.
GATE
ASPH.
CONC.
PI LES
ROCKS
CONC.
ROCKS
ROCKS
ROCKS
PI LES
ASPH.
CONC.
ROCKS
GATE
GATE
35 MAINTENANCE BUILDING
ROCKS
ROCKS ROCKS
A SPH.
36 LABORATORY BUILDING
UNKNOW N SUR FACE
ASPH.
CONC.
CONC. UNKNOW N SUR FACE UNKNOW N SUR FACE UNKNOW N SUR FACE
CONC.
CONC.
ASPH.
CONC. ROCKS
GATE
ROCKS
GATE
UNKNOW N SUR FACE
ROCKS ROCKS
ROCKS CONC.
ROCKS ROCKS
CONC.
CONC.
GATE
CONC.
SIMS ROAD
GATE
37 ADMINISTRATION BUILDING
ASPH.
CONC.
CONC.
ROCKS ROCKS
ROCKS CONC.
CONC.
GATE
ROCKS
TRA I L
TRA I L
ASPH.
ASPH.
STO P
SOLIDS
ASPH. ASPH.
TRAI L
ROCKS
ROCKS GATE
TANK CONC.
ASPH.
ISSUE BLOCK
L
TRA I
ASPH.
A IL
R
T
BASIN BASIN
CONC.
IL
TRA
ROCKS
ROCKS
GATE WITH GUARD SHACK
TRAI L
DESIGNED
III-2 III-1
UNION PACI
ROCKS
PMO ENGINEERING
CONC. CONC.
39 UV DISINFECTION FACILITY
ROCKS
ROCKS
CONC.
DRAWN
CONC.
ROCKS
ASPH.
40 EFFLUENT OBSERVATION STRUCTURE PMO CAD
CONC.
CAD User: PMO ENGINEERING
CHECKED
DLD 5
TRA
ROCKS
IL
ROCKS
ROCKS
CONC.
GATE
FIC RAILROA
CONC.
ROCKS
TRA
IL
APPROVED
R. WILLIAMS
TRA I L
TRA I L
IL
TR A GATE
TRA I L
IL
TRA
BASIN BASIN
TRA I L
ROCKS
TRA I L
FILENAME
III-4 III-3
ROCKS
GATE
CONC.
DWIGHT ROAD
A IL
R
T
[XXXX]
IL
TRA
TRA I L
TRA I L
44 BUFFERLAND OFFICE
GATE
TRA I L
TRA I L
D
ASPH. ASPH.
STO P
CONC.
ASPH.
ASPH.
ASPH.
STO P
CONC.
GATE
CONC.
WA LL
CONTRACT NUMBER
WA LL
CONC. POOL
IL
TR A
ROCKS
CONC.
ROCKS ROCKS
ROCKS
ASPH.
CONC.
TR A
IL
TRA IL
TRA I L
CONC.
TRAI L
TR
AI
L
CONC.
GENERAL
WA LL
WALL
TANK
CONC.
WA LL
CONC.
TRA I L
CONC.
CONC.
OLD CONC
POOL
OLD CONC
OLD CONC
POOL
WALL
OLD CONC
CONC.
OLD CONC
L
TR AI
TR A
IL
OLD CONC
GATE
BERM
ASPH.
PI LES
ASPH.
TANK
TANK
TANK
BERM
ASPH.
TANK
TANK
ASPH.
OVERHANG
BERM
CONC.
OVERHANG
TANK
OVERHANG
WA LL
CONC. DI TC H
51 EAST ACCESS RD GATE - SECURED DRAWING NUMBER
5
SCALE: 1" = 500'
A SPH. ASPH.
ASPH.
GI002
GATE
ROCKS
WALL ASPH.
ASPH. TANK
CONC.
ROCKS CONC.
ASPH.
CONC. DI
CONC.
OF
TC H
CONC.
A SPH.
CONC.
OVERHANG
1 2 3 4 SCALE IN INCHES 0 1/2 1 2 4 (IF SCALE BAR IS NOT 4", SCALE ACCORDINGLY)
1 2 3 4 5
ABBREVIATION DEFINITION ABBREVIATION DEFINITION ABBREVIATION DEFINITION ABBREVIATION DEFINITION
A________ CREJ CORRUGATED RUBBER EXPANSION JOINT FMH FLEXIBLE METAL HOSE L________
A AMPERE CRF CHEMICAL FEEDER FO FAIL OPEN L LENGTH DESIGN FIRM
A/C AIR CONDITIONING CRN CRANE FPC FLEXIBLE PIPE COUPLING LAM LAMINATED ADDRESS
AA ATOMIC ABSORPTION UNIT CSD CEILING SUPPLY DIFFUSER FPC-T FLEXIBLE PIPE COUPLING TO TAKE TENSION LAT LEAVING AIR TEMPERATURE, LATERAL, LATITUDE CITY, STATE
PHONE:
AB ANCHOR BOLT, AGGREGATE BASE CSP CORRUGATED STEEL PIPE FPM FEET PER MINUTE LB POUND CONTACT:
AC ASPHALT CONCRETE, ALTERNATING CURRENT, AIR CTF CENTRIFUGE FPS FEET PER SECOND LEV LEVEL WWW.
CONDITIONER CTR CONTRACTOR, CENTER FRP FIBERGLASS REINFORCED PIPE LG LONG
ACC AREA CONTROL CENTER CTS CORROSION TEST STATION FRS FREEZESTAT LOS LOCKOUT STOP
ACP ASBESTOS CEMENT PIPE CU CONTROL UNIT, COPPER, CUBIC FS FLOW SWITCH, FAR SIDE LP LOW PRESSURE, LIGHTING PANEL
D ACST ACOUSTIC CV CONTROL VALVE FSH FLOW SWITCH HIGH LS LEVEL SWITCH D
ADWF AVERAGE DRY WEATHER FLOW FSL FACULTATIVE SLUDGE LAGOON, FLOW SWITCH LOW LSH LEVEL SWITCH HIGH
AF AIR FILTER D________ FT FEET LSL LEVEL SWITCH LOW SUB CONSULTANT
AHU AIR HANDLING UNIT D DRAIN FTG FOOTING LTG LIGHTING
AL ALUMINUM DB DUCT BANK FTGS FITTINGS LVR LOUVER
ALT ALTERNATE DE DENSITY METER FUT FUTURE LWR LOWER
ALUM ALUMINUM SULPHATE DET DETAIL FZT FREEZESTAT
AMD AIR MONITORING DEVICE DF DRINKING FOUNTAIN M________
ANC ANCHOR DFD DUCT FIRE DAMPER G________ MAN MANUAL(LY)
APPROX APPROXIMATE(LY) DG DOOR GRILLE G POWER ACTUATED GATE MAX MAXIMUM
AR
AS
ALARM RELAY
AIR SUPPLY
DI
DIA
DUCTILE IRON
DIAMETER
GA
GALV
GAGE
GALVANIZED
MBH
MCC
THOUSAND BTU'S PER HOUR
MOTOR CONTROL CENTER
PRELIMINARY
ASSY ASSEMBLY DIAG DIAGRAM GB GRADE BREAK MCM THOUSAND CIRCULAR MILLS
THIS DRAWING IS NOT VALID FOR
ATM ATMOSPHERE DIFF DIFFERENTIAL GBV GLOBE VALVE MD MOTORIZED DAMPER CONSTRUCTION PURPOSES UNLESS IT
ATS ANODE TEST STATION DIP DUCTILE IRON PIPE GD GUARD MECH MECHANICAL BEARS THE SEAL AND SIGNATURE OF A
AV ANGLE VALVE DLD DEDICATED LAND DISPOSAL GDR GRINDER MEE MISCELLANEOUS ELECTRICAL EQUIPMENT DULY REGISTERED PROFESSIONAL
AVG AVERAGE DM DAMPER MOTOR GEN GENERAL, GENERATOR MFR MANUFACTURE(R)
DN DOWN GL GLASS MG/L MILLIGRAMS PER LITER
B________ DO DISSOLVED OXYGEN GPD GALLONS PER DAY MGD MILLION GALLONS PER DAY
B BLOWER DPR DAMPER GPM GALLONS PER MINUTE MH MANHOLE
BC BEGINNING OF CURVE DR DRAIN ROCK, DOOR GR GRADE MIE MISCELLANEOUS INSTRUMENTATION EQUIPMENT
BCOP BARE COPPER DT DRAIN TRAP, DRIP TRAP GRD GROUND MILSPEC MILITARY SPECIFICATION
BCR BEGINNING OF CURVE RETURN DWG DRAWING GRT GROUT MIN MINIMUM, MINUTE
BF BLIND FLANGE DWLS DOWELS GRTG GRATING MISC MISCELLANEOUS
BFV BUTTERFLY VALVE GSKT GASKET MJ MECHANICAL JOINT
BHP BRAKE HORSEPOWER E________ GSP GALVANIZED STEEL PLATE ML MILLILITER
BLDG BUILDING EA EXHAUST AIR, EACH GV GATE VALVE MME MISCELLANEOUS MECHANICAL EQUIPMENT
C BLK BLOCK EAT ENTERING AIR TEMPERATURE MOP MOTOR OPERATOR C
BM BEAM, BENCHMARK EAU ENGINE ALTERNATOR UNIT H________ MTR, M MOTOR
BOD BIOCHEMICAL OXYGEN DEMAND EC END OF CURVE, EVAPORATIVE COOLER HC HEATING COIL MUL/DIV MULTIPLY/DIVIDE
BOT BOTTOM ECC ECCENTRIC HD HEAVY DUTY MV MUD VALVE, MILLIVOLT
BSN BAR SCREEN ED EXTRACTOR DAMPER, EQUIPMENT DRAIN HDG HOT-DIPPED GALVANIZED MVU MOBILE VENTILATION UNIT
BTS BAND TEST STATION EE EACH END HDOT HEAVY DUTY OILTIGHT MW MONITORING WELL SACRAMENTO REGIONAL
BTU BRITISH THERMAL UNIT EF EACH FACE HDPE HIGH DENSITY POLYETHYLENE MX MIXER WASTEWATER TREATMENT PLANT
BV BALL VALVE EFF EFFLUENT HER HEADER
BVC BEGINNING OF VERTICAL CURVE EG EXHAUST GRILLE HEX HEAT EXCHANGER N________ RETURN ACTIVATED
EJ EXPANSION JOINT HH HANDHOLE N NEUTRAL, NORTH SLUDGE PUMPING -
C________ EL ELEVATION HOA HAND-OFF-AUTO NA NONAUTOMATIC
CAB DIRECT BURIAL CABLE ELEC ELECTRICAL HOR HORIZONTAL NAOH SODIUM HYDROXIDE BASIS OF DESIGN
CAP CAPACITY ELL ELBOW HP HIGH PRESSURE, HIGH POINT, HORSEPOWER NC NORMALLY CLOSED
PATH AND FILENAME: Z:\15. RAS (Return Activated Sludge System)\B. Planning\CAD Graphics\B.20 CAD\1-MODELS\1.0 Revit\2012-AWTP-RASP-15.09-RVT-Admin.rvt
CB CATCH BASIN EMBD EMBEDDED HR HANDRAIL, HEAT RESERVOIR, HOUR NEG NEGATIVE
CC COOLING COIL EMT ELECTRICAL METALIC TUBING HST HOIST NIC NOT IN CONTRACT
C-C CENTER TO CENTER EP EDGE OF PAVEMENT, ELECTRIC/PNEUMATIC CONVERTER HT HEIGHT, HIGH NO NORMALLY OPEN, NUMBER
CCP CONCRETE CYLINDER PIPE EPR EVAPORATOR HTR HEATER NOX NITRATES AND NITRITES
CCSP CONCRETE LINED AND COATED STEEL PIPE EPWWF EQUALIZED PEAK WET WEATHER FLOW HTV HIGH TEMPERATURE VENT NPSH NET POSITIVE SUCTION HEAD
CD CEILING DIFFUSER EQ EQUAL HV HOSE VALVE, HEATING AND VENTILATING UNIT NRS NONRISING STEM
CDR CONDUCTOR, CONDENSER EQUIP EQUIPMENT HVAC HEATING, VENTILATING, AND AIR CONDITIONING NS NEAR SIDE
CDU CONDENSING UNIT ES EXISTING SURFACE HWTR HIGH WATER NTS NOT TO SCALE
CED CEILING EXHAUST DIFFUSER EVC END OF VERTICAL CURVE HYD HYDRAULIC
CER CEILING EXHAUST REGISTER EW EACH WAY HYDT HYDRANT O________
CF CUBIC FEET EW T&B EACH WAY, TOP AND BOTTOM OA OUTSIDE AIR, OVERALL
CFH CUBIC FEET PER HOUR EWEF EACH WAY EACH FACE I________ OAI OUTSIDE AIR INTAKE
CFM CUBIC FEET PER MINUTE EWT ENTERING WATER TEMPERATURE I INTEGRAL CONTROL OC ON CENTER
CFR CODE OF FEDERAL REGULATIONS EX EXTRA IA INSTRUMENT AIR OD OUTSIDE DIAMETER
B CFS CUBIC FEET PER SECOND EXG EXHAUST GRILLE ICN INCINERATOR OF OUTSIDE FACE B
CHR CHILLER EXIST EXISTING ID INSIDE DIAMETER OL OVERLOAD
CI CAST IRON EXP EXPANSION IF INSIDE FACE OPNG OPENING
CIP CAST IRON PIPE EXT EXTERIOR IJTS INSULATED JOINT TEST STATION OPP OPPOSITE
CIRC CIRCUMFERENCE IL INDICATING LAMP ORF ODOR REMOVAL FILTER
CJ CONSTRUCTION JOINT F________ IN INCH ORP OXIDATION REDUCTION POTENTIAL
CKPL CHECKER PLATE F FAHRENHEIT, FACE, FUSE(D), FAN INF INFLUENT ORT ODOR REMOVAL TOWER
CL CLEARANCE FAB FABRICATE(D)(TION) INJ INJECTOR ORU ODOR REDUCTION UNIT
CL2 CHLORINE FAI FRESH AIR INTAKE INS INSULATE(D)(ION) OSA OUTSIDE AIR MARK DATE DESCRIPTION
CLR CLEAR, CHLORINATOR FB FLAT BAR, FLOOR BEAM INSTR INSTRUMENTATION
CM MANUAL CONTROL STATION FC FAIL CLOSED INT INTERIOR ISSUE BLOCK
CMA MANUAL-AUTO CONTROL STATION FCO FLOOR CLEANOUT INTER INTERMEDIATE (STANDARD ABBREVIATIONS P-Z ARE DESIGNED
CMC CEMENT MORTAR COATED FCR FINE CRUSHED ROCK INV INVERT LOCATED ON DRAWING GI004). PMO ENGINEERING
CML CEMENT MORTAR LINED FD FLOOR DRAIN, FIRE DAMPER IT INSTRUMENT TAP DRAWN
CMP CORRUGATED METAL PIPE FE FLOWMETER PMO CAD
CMP-AC CORRUGATED METAL PIPE ASPHALT COATED FF FAR FACE J________
CAD User: PMO ENGINEERING
CHECKED
CNTL CONTROL F-F FACE TO FACE JB JUNCTION BOX A.G. CALCIANO
CO CLEANOUT FG FLAP GATE JST JOIST APPROVED
CO2 CARBON DIOXIDE FH FIRE HYDRANT, FLATHEAD JT JOINT R. WILLIAMS
COD CHEMICAL OXYGEN DEMAND FHD FLATHEAD FILENAME
COF COOLING AIR FIN FINISHED K________
COL COLUMN FL FLOW LINE K KIP (1000 POUNDS) DESIGNER PROJECT NUMBER
COM COMMINUTOR FLEX FLEXIBLE KO KNOCK OUT [XXXX]
CONTRACT NUMBER
CONC CONCRETE FLG FLANGE(D) KV KILOVOLT
COND CONDUCTIVITY, CONDUCTOR, CONDENSATE FLP FLUID POWER UNIT KVA KILOVOLT AMPERE
CONTRACT SEQUENCE NUMBER
CONN CONNECTION FLR FLOOR KW KILOWATT
A CONT CONTINUED(OUS) FLT FILTER A
DISCIPLINE
CP COMPRESSOR FM FORCE MAIN GENERAL
CPLG COUPLING
PLOT DATE: 7/2/2013 10:13:11 AM
DRAWING NUMBER
6
GI003 OF
34
1 2 3 4 SCALE IN INCHES 0 1/2 1 2 4 (IF SCALE BAR IS NOT 4", SCALE ACCORDINGLY)
1 2 3 4 5
ABBREVIATION DEFINITION ABBREVIATION DEFINITION ABBREVIATION DEFINITION ABBREVIATION DEFINITION
CHECKED
SCD SCUPPER DRAIN VSD VARIABLE SPEED DRIVE A.G. CALCIANO
SCH SCHEDULE VTR VENT THROUGH ROOF APPROVED
SCR SCRUBBER R. WILLIAMS
SD SPLITTER DAMPER, SMOKE DETECTOR FILENAME
SECT SECTION
SEP SEPARATOR DESIGNER PROJECT NUMBER
SG SUPPLY GRILLE, SLUICE GATE-MANUAL [XXXX]
CONTRACT NUMBER
SHT SHEET
SI SPEED INCREASER CONTRACT SEQUENCE NUMBER
A DISCIPLINE
A
GENERAL
PLOT DATE: 7/2/2013 10:13:12 AM
STANDARD ABBREVIATIONS 2
DRAWING NUMBER
7
GI004 OF
34
1 2 3 4 SCALE IN INCHES 0 1/2 1 2 4 (IF SCALE BAR IS NOT 4", SCALE ACCORDINGLY)
1 2 3 4 5
GENERAL SYMBOLS MATERIALS CROSS REFERENCING SYSTEM MISCELLANEOUS
1/8" ARIAL
PROPERTY LINE
EXISTING EQUIPMENT OR MATERIALS TO PLAN TITLE 3/16" ARIAL DESIGN FIRM
MATCH LINE MATCH LINE 'A' ADDRESS
MATCH LINE BE REMOVED UNDER THIS CONTRACT
SEE DWG XX/XXX CITY, STATE
2
TOP PLAN SEE DWG XX/XXXX PHONE:
SCALE: 1" = 1'-0" CONTACT:
CENTER LINE REINFORCEMENT, IN SECTION
MATCH LINE WATER SURFACE WWW.
CL CENTER LINE
1/8" ARIAL
SECTION OUTLINE, BOUNDARY REINFORCEMENT , IN PLAN OR ELEVATION
1/8" ARIAL WITH 3/16" DIA CIRCLE
D PIPING
D
NOTE:
CONCRETE ALL ADDITIONAL PLANS, SECTIONS, LARGE SCALE PLANS, DETAILS, INTERIORS, SUB CONSULTANT
EXISTING PIPING TO BE ABANDONED OR ELEVATIONS SHALL BE SEQUECIALLY INDEXED NUMBERED FROM REFERENCED PLAN.
REMOVED UNDER THIS CONTRACT.
ABANDONED WHEN NOT IN CONFLICT WITH PRECAST CONCRETE
NEW CONSTRUCTION WORK SECTION CUTS
X X X X X FENCE
MORTAR, GROUT, OR PLASTER SECTION NUMBER, SEQUENTIALLY
2.1 2.1
HANDRAIL M-103 M-103 NUMBERED THROUGHT OUT THE
CONCRETE BLOCK FULL SECTION
REFERENCED PLAN PRELIMINARY
CONCRETE CURB AND GUTTER DRAWING WHERE SECTION IS SHOWN
NORTH ARROW THIS DRAWING IS NOT VALID FOR
2.1 SECTION NUMBER, SEQUENTIALLY CONSTRUCTION PURPOSES UNLESS IT
FUTURE EQUIPMENT, MATERIALS OR PIPING BRICK OR CAST IRON NUMBERED THROUGHT OUT THE BEARS THE SEAL AND SIGNATURE OF A
M-103
DULY REGISTERED PROFESSIONAL
REFERENCED PLAN
BURIED FACILITIES SHORT SECTION
GRATING, SPAN DRAWING WHERE SECTION IS SHOWN
BARRIER WALL
SECTION TITLE
CHECKER PLATE 3/16" ARIAL
DAYLIGHT LINE FOR GRADING REVISION CLOUD
1/8" ARIAL 1. FOR ADDITONAL SYMBOLS, SEE DRAWINGS GI006, GM001, GE001, GE002, D-001,
EL MONUMENT OR BENCH MARK
1/8" ARIAL WITH 3/16" DIA CIRCLE D- 002, D-003, AND X-001.
MARK DATE DESCRIPTION
X 10.50 SPOT ELEVATION
2. SYMBOLS ARE FOR REFEERENCE ONLY, NOT ALL SYMBOLS ARE USED IN THESE ISSUE BLOCK
PLASTIC LINING
ELEVATION STANDARD DETAIL CALLOUT CONTRACT DRAWINGS. DESIGNED
PMO ENGINEERING
S41 NOTE: 3. ITEMS SHOWN AS SCREENED ARE EXISTING. WORK UNDER THIS CONTRACT, IS DRAWN
F FIRE EXTINGUISHER AC PAVEMENT (EL) DEPICTED WITH BOLD LINES.
112 (NUMBER INDICATES EXTINGUISHER NUMBER) ALL LEADERS ARE 30 OR 60 DEGREES PMO CAD
CHECKED
4. THE NOTE IN THE TITLEBLOCK OF THIS DRAWING WHICH READS "TWO INCHES AT A.G. CALCIANO
UTILITY STATION FULL SCALE" APPEARS ON DRAWINGS FOR IDENTIFICATION OF SCALE APPROVED
NATURAL GROUND OR GRADE DISTORTIONS ON HALF SIZE DRAWINGS AND DRAWING REPRODUCTIONS. IT R. WILLIAMS
HOSE RACK STANDARD DETAIL TITLE SHALL MEAN THAT THE DRAWING IS FULL SIZE AND THE DRAWING SCALES FILENAME
ACCURATE WHEN THE LENGTH OF THIS LINE IS TWO INCHES. IF THE LENGTH IS
P51001 EQUIPMENT NUMBER ROCK S41 BOLTED COVER PLATE AND SUPPORTS OTHER THAN TWO INCHES, DRAWING SCALES MUST BE ADJUSTED DESIGNER PROJECT NUMBER
ACCORDINGLY. [XXXX]
CONTRACT NUMBER
101 DOOR NUMBER
5. EXISTING PIPING IS DESIGNATED BY SERVICE RATHER THAN MATERIAL TYPE.
JOINT FILLER KEYNOTES CONTRACT SEQUENCE NUMBER
ROOM NAME MATERIAL TYPES, IF KNOWN, APPEAR OUTSIDE THE PIPING CALLOUT BUBBLE,
A 101 ROOM NUMBER 4 AND MAY NOT BE THE SAME MATERIAL TYPES SPECIFIED FOR NEW PIPING. A
NOTE: DISCIPLINE
ALL LEADERS ARE 30 OR 60 DEGREES 6. ABBREVIATIONS USED IN THIS CONTRACT DOCUMENT CONFORM TO ANSI Y1.1, GENERAL
@ AT
PLOT DATE: 7/2/2013 10:13:13 AM
UNLESS NOTED OTHERWISE ON DRAWINGS. SEE SPEC. SECTION 01071 FOR GENERAL SYMBOLS,
ADDITIONAL ABBREVIATIONS.
& AND MATERIALS, CROSS
7. ALL STANDARD DETAILS APPLY TO ALL THE CONTRACTORS WORK WHETHER REFERENCING SYSTEM,
ROUND OR DIAMETER
SPECIFICALLY REFERENCED OR NOT. DRAWING NUMBER SYSTEM,
PL PLATE OR PROPERTY LINE AND MISCELLANEOUS
8. SEE FRONT END SHEETS FOR EACH DISCIPLINES STANDARD SYMBOLS, ETC. SYMBOLS
ANGLE DRAWING NUMBER
9. SEE ADDITIONAL GENERAL NOTES THROUGHOUT DRAWING SET. 8
GI005 OF
34
1 2 3 4 SCALE IN INCHES 0 1/2 1 2 4 (IF SCALE BAR IS NOT 4", SCALE ACCORDINGLY)
1 2 3 4 5
PIPING SYSTEMS EQUIPMENT PREFIXES PIPING DESIGNATIONS
ABBREVIATION DEFINITION ABBREVIATION DEFINITION ABBREVIATION DEFINITION ABBREVIATION DEFINITION
NEW PIPING DESIGN FIRM
ADDRESS
A________ A________ PIPE SIZE CITY, STATE
A AERATION AIR PCR PROCESS CONDENSATE RETURN AF AIR FILTER MEE MISCELLANEOUS ELECTRICAL PHONE:
AA AGITATION AIR PD PUMPED DRAINAGE AHU AIR HANDLING UNIT EQUIPMENT PIPING SYSTEM CONTACT:
WWW.
ASH ASH PNEUMATIC PE PRIMARY EFFLUENT MH MANHOLE
PF PRESSURIZED FLOW B________ MIE MISCELLANEOUS INSTRUMENTATION
B________ POL POLYELECTROLYTE B BLOWER EQUIPMENT 4" SA
BD BOILER BLOWDOWN PRS PROCESS SAMPLING BE FLAME ELEMENT MME MISCELLANEOUS MECHANICAL S= .005
D BF BOILER FEEDWATER PS PRIMARY SLUDGE BLR BOILER EQUIPMENT D
PSC PRIMARY SCUM BRN BURNER MOP MOTOR OPERATOR
SUB CONSULTANT
C________ PSCS PRIMARY SLUDGE/CIRCULATING SLUDGE BSN BAR SCREEN MVU MOBILE VENTILATION UNIT
CAA CHANNEL AERATION AIR PSG PRIMARY SLUDGE AND GRIT PIPE SLOPE
MX MIXER
CC CENTRIFUGE CAKE PSO POLYMER SOLUTION C________
CD CHEMICAL DRAIN PSR PRIMARY SLUDGE RECIRCULATION C CRANE O________ EXISTING PIPING
CEN CENTRATE PSS PROCESS STEAM SUPPLY CAF COMBUSTION AIR FAN ORF ODOR REMOVAL FILTER
CF CENTRIFUGE FEED CC COOLING COIL ORT ODOR REMOVAL TOWER
4" SA
CFE CHLORINATED FINAL EFFLUENT R________ CDU CONDENSING UNIT OSC ODOR SCRUBBER
CL LOW PRESSURE CONDENSATE RAS RETURN ACTIVATED SLUDGE CDU CONDENSING UNIT S= .005
CLG CHLORINE GAS RD ROOF DRAIN CFR CHEMICAL FEEDER P________ PRELIMINARY
CLL CHLORINE LIQUID RG REFRIGERANT GAS CHR CHILLER P PUMP
CLS CHLORINE SOLUTION RL REFRIGERANT LIQUID COF COOLING AIR FAN PB PULL BOX (ELECT) FUTURE PIPING THIS DRAWING IS NOT VALID FOR
CLV CHLORINE VACUUM RS RAW SEWAGE COM COMMINUTOR PLC PROGRAMMABLE LOGIC CONSTRUCTION PURPOSES UNLESS IT
BEARS THE SEAL AND SIGNATURE OF A
CM MEDIUM PRESSURE CONDENSATE RWL RAIN WATER LEADER CON CONVEYOR CONTROLLER DULY REGISTERED PROFESSIONAL
CPA CHEMICAL PADDING AIR RWP RAIN WATER PIPE CP COMPRESSOR PNL PANEL 4" SA
CS CIRCULATING SLUDGE CR CONTACTOR POP PNEUMATIC OPERATOR S= .005
CSO CAUSTIC SODA S________ CSN COMMINUTING SCREEN PRV PRESSURE RELIEF VALVE
CV CHEMICAL VENT S STEAM CTF CENTRIFUGE PS PRESSURE SWITCH
CWR CHILLED WATER RETURN SA SERVICE AIR CV CONTROL VALVE PSH PRESSURE SWITCH HIGH
CWS CHILLED WATER SUPPLY SCD SCUM DECANT CYL CYLINDER PSL PRESSURE SWITCH LOW NOTE:
SCLS SODIUM HYPOCHLORITE SOLUTION PSV POP SAFETY VALVE 1. SEE PIPING SYSTEM SPECIFICATIONS FOR PIPING MATERIALS LIST, VALVES, AND FITTINGS.
D________ SCO SCUM OVERFLOW D________ PTR PRINTER
D DRAIN SCR STEAM CLEAN RINSE DE DENSITY METER PVL PRESSURE VESSEL
DFE
DIZ
DECHLORINATED FINAL EFFLUENT
DEIONIZED WATER
SCS
SD
STEAM CLEAN SUPPLY
SANITARY DRAIN
DPR DAMPER PVU PANELVIEW DISPLAY EQUIPMENT DESIGNATIONS
DS DISCONNECT SWITCH
DS DIGESTED SLUDGE SE SECONDARY EFFLUENT DU DRIVE UNIT S________
C DSSG DIGESTED SLUDGE/SLUDGE GAS SG SLUDGE GAS DX DIRECT EXPANSION COIL S SILENCER
C
SME SAMPLE-EFFLUENT SBR SCRUBBER MOP90486A EQUIPMENT NO. EXAMPLE
E________ SMI SAMPLE-INFLUENT E________ SC SCREEN
ED EQUIPMENT DRAIN SMML SAMPLE MIXED LIQUOR E ENGINE SD SMOKE DETECTOR
SMO SAMPLE OXYGEN EG ENGINE ALTERNATIVE UNIT SEP SEPARATOR SACRAMENTO REGIONAL
LETTER SUFFIX
F________ SMP SAMPLE-PRIMARY EFFLUENT SG SLUICE GATE MANUAL WASTEWATER TREATMENT PLANT
FBW FILTERED BACKWASH WATER SMS SLUDGE SAMPLE-SLUDGE F________ SI SPEED INCREASER FOURTH AND FIFTH DIGITS INDICATE EQUIPMENT
FC FERRIC CHLORIDE SN SUPERNATANT FA FLAME ARRESTOR SLG SLIDE GATE NUMBER RETURN ACTIVATED
FE FINAL EFFLUENT SOG SULFUR DIOXIDE GAS FB FIRE (ALARM) BELL SMX SLURRY MIXER
FMSC FOAM SUPPRESSING CHEMICAL SOL SULFUR DIOXIDE LIQUID FC FLAME CHECK SR SPEED REDUCER THIRD DIGIT INDICATES SPECIFIC AREA IN WHICH SLUDGE PUMPING -
EQUIPMENT IS LOCATED
FOR FUEL OIL RETURN SOS SULFUR DIOXIDE SOLUTION FD FIRE DAMPER SS SPEED SELECTOR SWITCH BASIS OF DESIGN
FOS FUEL OIL SUPPLY SOV SULFUR DIOXIDE VACUUM FE FLOW METER ST STEAM TRAP SECOND DIGIT INDICATES STRUCTURE SUBDIVISION
PATH AND FILENAME: Z:\15. RAS (Return Activated Sludge System)\B. Planning\CAD Graphics\B.20 CAD\1-MODELS\1.0 Revit\2012-AWTP-RASP-15.09-RVT-Admin.rvt
FTE FILTERED EFFLUENT SR SCREENINGS FG FLAP GATE SUB SUBSTATION IN WHICH EQUIPMENT IS LOCATED
SRA SCUM REMOVAL AIR FLC FLOCCULATOR SV SOLENOID VALVE
G________ SRF SCREENINGS FEED FLP FLUID POWER UNIT SW SWITCH FIRST DIGIT INDICATES PLANT AREA STRUCTURE IN
GC GAS CIRCULATION SRO SCREENINGS OVERFLOW FLT FILTER SWB SWITCHBOARD WHICH EQUIPMENT IS LOCATED (SEE SCHEDULE)
GLY GLYCON/WATER COOLANT SSC SECONDARY SCUM FMX FLASH MIXER SWR SWITCHGEAR LETTER PREFIX INDICATES TYPE OF EQUIPMENT
GR GRIT STD STORM DRAIN FN FAN (SEE SCHEDULE)
GRC GAS RECIRCULATION COMPRESSOR SWAS SAMPLE-WASTE ACTIVATED SLUDGE FP FILTER PRESS T________
GRO GRIT OVERFLOW FRS FREEZESTAT T TANK
T________ FS FLOW SWITCH TB TERMINAL BOX (ELECT)
H________ TA THICKENER AIR FSH FLOW SWITCH HIGH TBN TURBINE
HNG HIGH PRESSURE NATURAL GAS TD TANK DRAIN FSL FLOW SWITCH LOW TCP TEMPERATURE CONTROL POINT
HOH HIGH PRESSURE HYDRAULIC OIL TE THICKENER EFFLUENT FT FREEZE TANK TFR TRANSFORMER VALVE DESIGNATIONS
HOL LOW PRESSURE HYDRAULIC OIL THS THICKENED SLUDGE TS TEMPERATURE SWITCH
HRR HEAT RESERVOIR RETURN TO THICKENED OVERFLOW G________ TSH TEMPERATURE SWITCH HIGH
B HRS HEAT RESERVOIR SUPPLY TS TRANSFER SLUDGE G POWER ACTUATED GATE TSL TEMPERATURE SWITCH LOW
39WRL03
B
HS HARVESTED SLUDGE TSC THICKENED SCUM GDR GRINDER TST THERMOSTAT
HSG HIGH PRESSURE SLUDGE GAS TWAS THICKENED WASTE ACTIVATED SLUDGE GEN GENERATOR
HSO SULFURIC ACID GRV GRAVITY RELIEF VENT U________
HTV HIGH TEMPERATURE VENT U________ UH UNIT HEATER
HWR DOMESTIC HOT WATER RETURN UA UTILITY AIR H________
HWS DOMESTIC HOT WATER SUPPLY H HOIST V________ INDICATES ARBITRARY NUMBER
V________ HC HEATING COIL V POWER ACTUATED VALVE ISOLATING
I_________ V VENT HEX HEAT EXCHANGER OR MANUAL OPERATED WITH LIMIT INDICATES PIPING SYSTEM
IA INSTRUMENT AIR VA VACUUM HH HANDHOLE (ELECT) SWITCH MARK DATE DESCRIPTION
LSG LOW PRESSURE SLUDGE GAS VS STEAM VENT HRB HEAT RECOVERY BOILER VAF VENTILATION AIR FILTER SECOND DIGIT INDICATES STRUCTURE ISSUE BLOCK
HS HAND SWITCH VDS DIGESTER SLUDGE VALVE SUBDIVISION IN WHICH VALVE IS LOCATED
DESIGNED
M________ W________ HTR HEATER VFC VARIABLE FREQUENCY CONTROLLER PMO ENGINEERING
MG MIXED GAS WAS WASTE ACTIVATED SLUDGE VFT VACUUM FILTER FIRST DIGIT INDICATES PLANT AREA
STRUCTURE IN WHICH VALVE IS LOCATED DRAWN
ML MIXED LIQUOR WFBW FILTERED BACKWASH WATER I________ VHS HARVESTED SLUDGE VALVE PMO CAD
MS MIXED SLUDGE WFP RECLAIMED WATER FIRE ICN INCINERATOR VP VACUUM PUMP
CAD User: PMO ENGINEERING
CHECKED
MSCS MIXED SLUDGE/CIRCULATING SLUDGE WFSW FILTERED SURFACE WASH WATER IND LEAK DETECTOR VSC VARIABLE SPEED COUPLING (ECC) A.G. CALCIANO
MSDS MIXED SLUDGE/DIGESTER SLUDGE WHWC WASTE HEAT COOLING WATER IR INLET RELIEF VSN SUPERNATANT VALVE
APPROVED
MSG MEDIUM PRESSURE SLUDGE GAS RETURN-COGENERATION VV VARIABLE VOLUME BOX R. WILLIAMS
WHWR WASTE HEAT COOLING WATER RETURN J________ FILENAME
N________ WHWS WASTE HEAT COOLING WATER SUPPLY JB JUNCTION BOX (ELECT) W________
NG NATURAL GAS WI WETLANDS INFLUENT WHR WASHER DESIGNER PROJECT NUMBER
WML WASTE MIXED LIQUOR L________ WKS WORKSTATION [XXXX]
O________ WN NON-POTABLE WATER LI LEVEL INDICATOR WW WIREWAY CONTRACT NUMBER
OCA ODOR CONTROL AIR WNI LANDSCAPE IRRIGATION NON-POTABLE LS LEVEL SWITCH
ODG OXYGEN DRY GAS WATER LSH LEVEL SWITCH HIGH X________ CONTRACT SEQUENCE NUMBER
OF OVERFLOW WNS NON-POTABLE WATER SOFT LSL LEVEL SWITCH LOW XSW TRANSFER SWITCH
A OFSG OVERFLOW/SLUDGE GAS WP POTABLE WATER A
OHP OXYGEN HIGH PRESSURE WPS POTABLE WATER SOFT
LV LOUVER
Z________
GENERAL NOTES DISCIPLINE
GENERAL
PLOT DATE: 7/2/2013 10:13:14 AM
OLPD OXYGEN LOW PRESSURE DISCHARGE WR RECLAIMED WATER M________ ZS POSITION SWITCH
1. FOR INSTRUMENTATION SYMBOLS AND IDENTIFICATION, SEE DRAWING XX-XXX. PIPING, EQUIPMENT, VALVE,
OLPS OXYGEN LOW PRESSURE SUCTION WRH RECLAIMED WATER HIGH PRESSURE M MOTOR
WRL RECLAIMED WATER LOW PRESSURE MC MAGNETIC CLUTCH 2. NOT ALL PIPING SYSTEMS SHOWN ARE USED IN THIS DESIGN. AND EQUIPMENT PREFIXES
P________ WRS FOAM SUPPRESSING SPRAY WATER MCC MOTOR CONTROL CENTER
PA PREAERATION AIR MD MOTORIZED DAMPER
PAS PRIMARY AND ACTIVATED SLUDGE MDM MODEM
PCH HIGH PRESSURE PROCESS
CONDENSATE
PCL LOW PRESSURE PROCESS DRAWING NUMBER
9
CONDENSATE GI006 OF
34
1 2 3 4 SCALE IN INCHES 0 1/2 1 2 4 (IF SCALE BAR IS NOT 4", SCALE ACCORDINGLY)
1 2 3 4 5
SCHEDULE OF EXISTING EQUIPMENT NUMBERS
STRUCTURES
ADMINISTRATION/ENGR.-OPS/COMMONS/
CARBONACEOUS OXIDATION STRUCTURE (CENTRAL AND
SOUTH TUNNELS, MISCELLANEOUS BUILDINGS)
SOLIDS PROCESSING STRUCTURES CONTINUED
WASTE ACTIVATED SLUDGE THICKENERS
DESIGN FIRM
ADDRESS
MAIN SUB/MAINT/LAB CENTRAL TUNNEL 42100-42199 THICKENER 1 86100-86199 CITY, STATE
ADMIN AREA @ EL. 108.00 11000-11099 SOUTH TUNNEL 42200-42299 THICKENER 2 86200-86299 PHONE:
ADMIN AREA @ EL. 120.00/134.50 12001-12219 SOUTH TUNNEL MEZZANINE 42300-42399 THICKENER 3 86300-86399 CONTACT:
WWW.
ENGR/OPS AREA 12300-12499 CONTROL BUILDING 42400-42499 THICKENER 4 86400-86499
COMMONS AREA 13500-13599 COMPRESSOR BUILDING 42500-42599 THICKENER GALLERY 86500-86599
MAIN ELECTRICAL SUBSTATION 13000-13099 DEWATERING PUMPING STATION 42600-42699 GRAVITY BELT THICKENER 86600-86999
MAINTENANCE AREA @ EL. 104.75 14101-14199 RECLAIMED WATER PUMPING STATION 42700-42789 MSG/LSG SYSTEM 87000-87999
D MAINTENANCE AREA @ EL. 120.00 15000-15099 RECLAIMED WATER SUBSTATION 42790-42799 SOLIDS PROCESSING CONTROL BUILDINGS D
ROOF AREA "MAINTENANCE" @ EL. 134.50 16020-16050 CHANNELS - ML, PE, RAS, INF 42800-42899 BASEMENT 88120-88139
SUB CONSULTANT
LAB 15100-15199 GROUND FLOOR 88220-88239
MAINTENANCE STORAGE 18000-18999 SECONDARY SEDIMENTATION STRUCTURE MANHOLE SUMPS 89100-89149
BATTERY I DIGESTER BATTERY S 89150-89399
INFLUENT-EFFLUENT PUMP BUILDING SECONDARY SEDIMENTATION TANK 1 43100-43199
BELOW ELEVATION 98.0 SECONDARY SEDIMENTATION TANK 2 43200-43299 SOLIDS STORAGE BASINS
SCREEN ROOM 21100-21199 SECONDARY SEDIMENTATION TANK 3 43300-43399 LEVEE CLOSURE 90000-90010
INFLUENT PUMP ROOM 21200-21299 SECONDARY SEDIMENTATION TANK 4 43400-43499 METERING STRUCTURE 90011-90049
EFFLUENT PUMP ROOM 21300-21399 SECONDARY SEDIMENTATION TANK 5 43500-43599 GROUNDWATER MONITORING WELLS 90050-90099
BETWEEN ELEVATION 98.0 AND 117.0 SECONDARY SEDIMENTATION TANK 6 43600-43699 BATTERY I 90100-90199 PRELIMINARY
SCREEN ROOM 22100-22199 SECONDARY SEDIMENTATION TANK 7 43700-43799 BATTERY II 90200-90299
INFLUENT PUMP ROOM 22200-22299 SECONDARY SEDIMENTATION TANK 8 43800-43899 BATTERY III 90300-90399 THIS DRAWING IS NOT VALID FOR
EFFLUENT PUMP ROOM 22300-22399 BATTERY I MIXED LIQUOR DISTRIBUTION AND 43900-43999 BATTERY IV (FUTURE) 90400-90499 CONSTRUCTION PURPOSES UNLESS IT
BEARS THE SEAL AND SIGNATURE OF A
BOILER ROOM 22400-22499 EFFLUENT CHANNELS DULY REGISTERED PROFESSIONAL
EQUIPMENT ROOM NO. 2 22500-22599 BATTERY II EMERGENCY STORAGE BASINS AND WETLANDS
MISCELLANEOUS 22600-22699 SECONDARY SEDIMENTATION TANK 9 44100-44199 EMERGENCY STORAGE BASINS A, B & C 91000-91099
UTILITY ROOMS 22700-22799 SECONDARY SEDIMENTATION TANK 10 44200-44299 WETLANDS (FISH HEAD LAKE) 91100-91199
BETWEEN ELEVATION 117.0 AND 133.0 SECONDARY SEDIMENTATION TANK 11 44300-44399 EMERGENCY STORAGE BASIN-D 91200-91269
SCREEN ROOM 23100-23199 SECONDARY SEDIMENTATION TANK 12 44400-44499
INFLUENT PUMP ROOM 23200-23299 SECONDARY SEDIMENTATION TANK 13 44500-44599 TUNNELS
EFFLUENT PUMP ROOM 22300-22399 SECONDARY SEDIMENTATION TANK 14 44600-44699 SOLIDS HANDLING TUNNEL 92000-92299
BOILER ROOM 22400-22499 SECONDARY SEDIMENTATION TANK 15 44700-44799 MAINTENANCE TUNNEL 92300-92499
MISCELLANEOUS 23600-23699 SECONDARY SEDIMENTATION TANK 16 44800-44899 CENTRAL TUNNEL 92500-92999
INCINERATOR AREA BATTERY II MIXED LIQUOR DISTRIBUTION 44900-44999
INCINERATOR NO. 1 25100-25199 EFFLUENT CHANNELS AND FILTER FEED PUMP STATION CHEMICAL HANDLING AREA
GRIT SCREENINGS SCUM DEWATERING AREAS 25500-25599 BATTERY III CHEMICAL CONTROL BUILDING 93100-93299
C ASH HANDLING AREA 25600-25699 MANHOLES 45000-45050 CHEMICAL STORAGE AND SCRUBBER AREA 93300-93399
C
ODOR REMOVAL TOWER AREA 25700-25799 SECONDARY SEDIMENTATION TANK 17 45100-45199 CHEMICAL PUMP AREA 93400-93499
CONTROL AND MCC ROOMS 25800-25899 SECONDARY SEDIMENTATION TANK 18 45200-45299 CAUSTIC STORAGE AREA 93500-93510
EQUIPMENT ROOM NO. 1 AND MISCELLANEOUS 25900-25999 SECONDARY SEDIMENTATION TANK 19 45300-45399 POLYMER AND FERRIC CHLORIDE STORAGE AREA 93511-93529
SECONDARY SEDIMENTATION TANK 20 45400-45499 FUEL STORAGE AREA 93530-93549 SACRAMENTO REGIONAL
PRIMARY TREATMENT STRUCTURE SECONDARY SEDIMENTATION TANK 21 45500-45599 SULFUR DIOXIDE STORAGE AREA 93550-93559 WASTEWATER TREATMENT PLANT
BATTERY I SECONDARY SEDIMENTATION TANK 22 45600-45699 ACTIVATED CARBON AREA 93561-93599
GRIT REMOVAL TANK 31100-31199 SECONDARY SEDIMENTATION TANK 23 45700-45799 RETURN ACTIVATED
PRIMARY EQUIPMENT GALLERY 31200-31299 SECONDARY SEDIMENTATION TANK 24 45800-45899 MISCELLANEOUS
PRIMARY SEDIMENTATION TANK 1 31300-31399 BATTERY III MIXED LIQUOR DISTRIBUTION AND 45900-45999 DECHLORINATION BUILDING 94000-94999 SLUDGE PUMPING -
PRIMARY SEDIMENTATION TANK 2 31400-31499 EFFLUENT CHANNELS BACKFLOW STRUCTURE 95000-95199 BASIS OF DESIGN
PRIMARY SEDIMENTATION TANK 3 31500-31599 X09 CLEAN ROOM 95200-95249
PATH AND FILENAME: Z:\15. RAS (Return Activated Sludge System)\B. Planning\CAD Graphics\B.20 CAD\1-MODELS\1.0 Revit\2012-AWTP-RASP-15.09-RVT-Admin.rvt
CHECKED
OXIDATION TANK 6 41600-41649 DIGESTER BATTERY II A.G. CALCIANO
OXIDATION TANK 7 41700-41749 DIGESTER 4 82100-82199
APPROVED
OXIDATION TANK 8 41800-41849 DIGESTER 5 82200-82299 R. WILLIAMS
OXIDATION TANK 9 41150-41199 DIGESTER 6 82300-82399
FILENAME
OXIDATION TANK 10 41250-41299 DIGESTER 7 82400-82499
OXIDATION TANK 11 41350-41399 EQUIPMENT GALLERY 82500-82599 DESIGNER PROJECT NUMBER
OXIDATION TANK 12 41450-41499 DIGESTER BATTERY III [XXXX]
DIGESTER 8 83100-83199 CONTRACT NUMBER
AHU'S AT NORTH CO DECK DIGESTER 9 83200-83299
DIGESTER 10 83300-83399 CONTRACT SEQUENCE NUMBER
DIGESTER 11 83400-83499
A EQUIPMENT GALLERY 83500-83599 DISCIPLINE
A
COMPRESSOR ROOM BATTERY III 83600-83649 GENERAL
PLOT DATE: 7/2/2013 10:13:15 AM
GENERAL NOTES
1. SEE DRAWING GI006 FOR MECHANICAL EQUIPMENT NUMBERING SYSTEM.
DRAWING NUMBER
10
GI601 OF
34
1 2 3 4 SCALE IN INCHES 0 1/2 1 2 4 (IF SCALE BAR IS NOT 4", SCALE ACCORDINGLY)
1 2 3 4 5
EMERGENCY
STORAGE BASIN B GENERAL NOTES:
DESIGN FIRM
ROCKS
ROCKS
ROCKS ROCKS
ROCKS
ROCKS
ROCKS
ROCKS
EMERGENCY
ROCKS
ROCKS
ROCKS
ADDRESS
STORAGE BASIN A CITY, STATE
ROCKS
ROCKS
EMERGENCY
GATE
ROCKS
GATE
WWW.
STORAGE BASIN E
ROCKS
CONC.
CONC.
LEGEND:
DI
TC H
ROCKS
CONC. DI TCH
CONC. DI TCH
ROCKS
CONC. DI TCH
PI LES
CONC.
CONC.
CONC.
GATE
ASPH.
EMERGENCY STORAGE
ROCKS
ROCKS
ROCKS
CONC.
CONTRACTOR LAYDOWN
D BASIN C CONC.
CONC.
ROCKS
D
CONC. DI TCH
ROCKS
ASPH.
CONC.
ROCKS
PROJECT AREA SUB CONSULTANT
GATE
ASPH.
CONC.
ROCKS
ROCKS
ROCKS
ASPH.
ROCKS
ROCKS
CONC. CONC.
ASPH. CONC.
ASPH. CONC.
ASPH. CONC. ASPH.
ASPH.
ASPH.
CONC. CONC.
CONC.
GATE
GATE
CONC. ASPH.
ROCKS
ROCKS
CONC.
ROCKS CONC.
ASPH.
CONC. CONC.
GATE
ASPH.
CONC.
PI LES
ROCKS
ASPH.
ASPH.
ASPH.
ASPH.
TRAI LER
CONC.
ASPH.
CONC.
ROCKS
CONC.
TRAI LER
CONC. ASPH.
TRAI LER
TRAI LER
DECK
UNKNOW N SUR FACE CONC.
ASPH.
UNKNOW N SUR FACE ASPH.
ASPH.
ASPH.
CONC.
TRAI LER
DECK
ASPH.
ASPH. TRAI LER
CONC.
CONC. ROCKS
ASPH.
GATE
ROCKS
EMERGENCY
CONC.
ASPH.
ASPH.
WA
LL
ROCKS
STORAGE
TANK
PRELIMINARY
ASPH. ASPH.
ASPH.
UNKNOW N SUR FACE ASPH.
OVERHANG
OVERHANG
UNKNOW N SUR FACE ASPH.
ASPH.
CONC. CONC.
OVERHANG
CONC.
ASPH.
ASPH. ASPH.
ASPH. CONC.
ROCKS
CONC.
FOUNDATI ON
OVERHANG
BASIN D
TANK
CONC.
TANK
ASPH. W
ALL
OVERHANG
CONC.
TANK TANK
ASPH.
ASPH.
FOUNDATI ON
PI LES ROCKS
CONC.
CONC.
CONC.
TANK
TANK
ASPH. GATE CONC.
OVERHANG
OVERHANG
OVERHANG
ROCKS
OVERHANG OVERHANG
ASPH. CONC.
CONC.
ASPH.
CONC.
CONC. ASPH.
OVERHANG
CONC. ASPH.
OVERHANG
ASPH.
OVERHANG
ASPH.
CONC. TANK
ASPH.
WA LL
TANK TANK
ASPH.
TANK TANK
GATE
TANK
ASPH. ASPH.
ASPH.
CONC.
CONC.
PI LES
CONC.
OVERHANG
ASPH. ASPH.
ASPH.
ASPH.
ASPH.
CONC.
ASPH.
ASPH.
CONC.
ASPH.
UNKNOW N SUR FACE
TANK
ASPH.
TANK CONC.
WALL
ASPH. CONC.
CONC. TANK CONC.
ASPH. TANK
ASPH.
CONC.
CONC.
CONC.
CONC. TANK
CONC. OVERHANG
CONC.
CONC.
ASPH. OVERHANG
ROCKS
TANK
TANK
CONC. TANK
CONC.
TANK
TANK
TANK
ASPH.
ASPH. CONC.
ASPH.
ASPH. CONC.
ASPH.
ASPH. CONC.
GATE ASPH.
ASPH. ASPH.
ASPH.
PH.
AS ASPH.
ASPH.
ASPH. OVERHANG
CONC.
CONC.
PI LES
CONC. CONC.
ASPH.
CONC.
CONC.
TANK
CONC.
ASPH. ASPH. CONC. CONC.
GATE CONC. GATE
GATE
ASPH.
TANK ASPH.
CONC.
CONC.
CONC. CONC.
CONC. CONC.
ASPH. ASPH.
CONC. GATE
ASPH.
CONC. CONC.
PI LES
ASPH. ASPH.
OVERHANG
CONC. GATE
ASPH.
GATE
CONC.
CONC.
UNION PACI
CONC.
CONC.
CONC.
CONC.
TANK
WA LL
CONC.
ASPH.
CONC. CONC.
CONC.
ASPH. CONC.
CONC.