August

ID TASK NAME Duration Start Finish 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28


SA S M T W Th F SA S M T W Th F SA S M T W Th F SA S
GROUND FLOOR 26 6-Aug-16 31-Aug-16
FINISHING WORKS 26 6-Aug-16 31-Aug-16
1.0 Masonry & Plastering 14 6-Aug-16 19-Aug-16 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1.1 100mm Thick Solid Block Wall Below Ground Level 2 6-Aug-16 7-Aug-16 1 1
1.2 100mm Thick Solid Block Exterior walls 5 8-Aug-16 12-Aug-16 1 1 1 1 1
1.3 Wall footing for Interior walls 2 8-Aug-16 9-Aug-16 1 1
1.4 100mm Thick Hollow Block Interior 3 10-Aug-16 12-Aug-16 1 1 1
1.5 Plastering 18mm Thick Exterior 4 13-Aug-16 16-Aug-16 1 1 1 1
1.6 Plastering 12mm Thick Interior 7 13-Aug-16 19-Aug-16 1 1 1 1 1 1 1

2.0 Floor Screed 4 20-Aug-16 23-Aug-16 1 1 1 1


2.1 75mm Thick Ground Slab 4 20-Aug-16 23-Aug-16 1 1 1 1

3.0 Tiling 4 24-Aug-16 27-Aug-16 1 1 1 1


3.1 600x600 Homogeneous Tiles on General areas 4 24-Aug-16 27-Aug-16 1 1 1 1
3.2 600x250 Ceramic Tiles on Staircase

4.0 Doors & Windows 6 24-Aug-16 29-Aug-16 1 1 1 1 1


4.1 D1 3 24-Aug-16 26-Aug-16 1 1
4.2 FG 4 24-Aug-16 27-Aug-16 1 1 1 1
4.3 RSD 3 27-Aug-16 29-Aug-16 1 1

5.0 Putty & Painting 6 24-Aug-16 29-Aug-16 1 1 1 1 1


5.1 Painting on Exterior Surfaces of Wall 2 24-Aug-16 25-Aug-16 1 1
5.2 Putty & Painting on ceiling / sofits of slab 4 24-Aug-16 27-Aug-16 1 1 1 1
5.3 Putty & Painting on interior surfaces of wall 6 24-Aug-16 29-Aug-16 1 1 1 1 1

6.0 Hydraulics & Drainage 14 6-Aug-16 19-Aug-16 1 1 1 1 1 1 1 1 1 1 1 1 1 1


6.1 Sewerage/waste water main pipeline 4 6-Aug-16 9-Aug-16 1 1 1 1
6.2 Freshwater & Groundwater pipeline 6 10-Aug-16 15-Aug-16 1 1 1 1 1 1
6.3 Inspection chamber 2 14-Aug-16 15-Aug-16 1 1
6.4 Water meter for whole building 4 15-Aug-16 18-Aug-16 1 1 1 1
6.5 Well water pump 2 18-Aug-16 19-Aug-16 1 1
ID TASK NAME Duration Start Finish 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
SA S M T W Th F SA S M T W Th F SA S M T W Th F SA S
7.0 Electrical Works 18 13-Aug-16 30-Aug-16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
7.1 Electrical wiring to Lights and Fans 3 13-Aug-16 15-Aug-16 1 1 1
7.2 Electrcal wiring to socket outlets 3 13-Aug-16 15-Aug-16 1 1 1
7.3 Electrical main connection 5 16-Aug-16 20-Aug-16 1 1 1 1
7.4 Energy Saving Lights 25W (ceiling mounted) 3 28-Aug-16 30-Aug-16
7.5 Energy Saving Lights 25W (Wall mounted) 3 28-Aug-16 30-Aug-16
7.6 One way switch (one Gang) 3 28-Aug-16 30-Aug-16
7.7 One way switch (2 Gang) 3 28-Aug-16 30-Aug-16
7.8 One way switch (4 Gang) 3 28-Aug-16 30-Aug-16
7.9 One way switch 3 28-Aug-16 30-Aug-16
7.10 13A double socket outlet 3 28-Aug-16 30-Aug-16
7.11 Distribution Board 3 28-Aug-16 30-Aug-16

8.0 Metal Works 3 29-Aug-16 31-Aug-16


8.1 Staircase Railing 3 29-Aug-16 31-Aug-16
ID TASK NAME Duration Start Finish 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
SA S M T W Th F SA S M T W Th F SA S M T W Th F SA S

144018.6 162864.18 18845.58


110556.6 110556.56 -53632.8
78228.5 24595.7 -16200
118420 102220 4650.81
43179 47829.81
31500 31500
73810 73810
18000 18000
August
29 30 31
M T W

1
29 30 31
M T W
1 1 1

1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1

1 1 1
1 1 1
AUGUST SEPTEMBER
ID TASK NAME Duration Start Finish 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4
M T W Th F SA S M T W Th F SA S M T W Th F SA S
FIRST FLOOR 24 15-Aug-16 7-Sep-16
FINISHING WORKS 24 15-Aug-16 7-Sep-16
1.0 Masonry & Plastering 17 15-Aug-16 31-Aug-16 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
1.1 100mm Thick Solid Block Exterior walls 5 15-Aug-16 19-Aug-16 1 1 1 1 1
1.2 100mm Thick Hollow Block Interior 2 20-Aug-16 21-Aug-16 1 1
1.3 Plastering 18mm Thick Exterior 4 20-Aug-16 23-Aug-16 1 1 1 1
1.4 Plastering 12mm Thick Interior 8 24-Aug-16 31-Aug-16 1 1 1 1 1 1 1 1

2.0 Floor Screed 2 26-Aug-16 27-Aug-16 1 1


2.1 Flooring 65mm thick (General) 2 26-Aug-16 27-Aug-16 1 1

3.0 Tiling
3.1 600x250 Ceramic Tiles on Staircase

4.0 Doors & Windows 7 24-Aug-16 30-Aug-16 1 1 1 1 1 1 1


4.1 RSD 7 24-Aug-16 30-Aug-16 1 1 1 1 1 1 1
4.2 D2 3 28-Aug-16 30-Aug-16 1 1 1

5.0 Putty & Painting 15 24-Aug-16 7-Sep-16 1 1 1 1 1 1 1 1 1 1 1 1


5.1 Painting on Exterior Surfaces of Wall 3 24-Aug-16 26-Aug-16 1 1 1
5.2 Putty & Painting on ceiling / sofits of slab 5 1-Sep-16 5-Sep-16 1 1 1 1
5.3 Putty & Painting on interior surfaces of wall 7 1-Sep-16 7-Sep-16 1 1 1 1
5.4 Painting on Interior surface of walls 3 5-Sep-16 7-Sep-16
5.5 Painting on ceiling / sofits of slab 3 5-Sep-16 7-Sep-16

6.0 Hydraulics & Drainage 7 22-Aug-16 28-Aug-16 1 1 1 1 1 1 1


6.1 Plumbing works internal 4 22-Aug-16 25-Aug-16 1 1 1 1
6.2 Plumbing works inc.pipe line accessories for whole building 7 22-Aug-16 28-Aug-16 1 1 1 1 1 1 1

7.0 Electrical Works 17 22-Aug-16 7-Sep-16 1 1 1 1 1 1 1 1 1 1 1 1 1 1


7.1 Electrcal wiring to socket outlets 4 22-Aug-16 25-Aug-16 1 1 1 1
7.2 Electrical wiring to Lights and Fans 7 22-Aug-16 28-Aug-16 1 1 1 1 1 1 1
7.3 Energy Saving Lights 25W (ceiling mounted) 3 5-Sep-16 7-Sep-16
7.4 Energy Saving Lights 25W (Wall mounted) 3 5-Sep-16 7-Sep-16
7.5 13A double socket outlet 3 5-Sep-16 7-Sep-16
7.6 15A socket outlet 3 5-Sep-16 7-Sep-16
7.7 One way switch (2 Gang) 3 5-Sep-16 7-Sep-16
7.8 One way switch 3 5-Sep-16 7-Sep-16
7.9 Distribution Board 3 5-Sep-16 7-Sep-16

8.0 Metal Works 3 5-Sep-16 7-Sep-16


8.1 Staircase Railing 3 5-Sep-16 7-Sep-16
SEPTEMBER
5 6 7
M T W

1 1 1

1
1 1 1
1 1 1
1 1 1

1 1 1

1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1
1 1 1

1 1 1
1 1 1
ID TASK NAME Duration Start Finish

SECOND FLOOR #REF! #REF! #REF!


CONCRETE WORKS #REF! #REF! #REF!
1.0 Column Concrete #REF! #REF! #REF!
2.0 Staircase & Liftwall Concrete #REF! #REF! #REF!
3.0 3rd Slab Concrete