You are on page 1of 8

See

discussions, stats, and author profiles for this publication at: http://www.researchgate.net/publication/280598951

PV-Diesel Hybrid Power System for a Small


Village in Nigeria

ARTICLE in INTERNATIONAL JOURNAL OF SCIENTIFIC RESEARCH JULY 2015

DOWNLOADS VIEWS

3 9

2 AUTHORS, INCLUDING:

Dr Eseosa Omorogiuwa
University of Port Harcourt
28 PUBLICATIONS 6 CITATIONS

SEE PROFILE

Available from: Dr Eseosa Omorogiuwa


Retrieved on: 17 August 2015
International Journal of Scientific Research Engineering Technology
Volume 1, Issue 4, July-2015, ISSN (Online): 2395-566X

PV-Diesel Hybrid Power System for a Small Village in


Nigeria
Omorogiuwa Eseosa Okpo Ekom Enefiok
Department of Electrical/Electronic Engineering Department of Electrical/Electronic Engineering
University of Port Harcourt, Rivers State, Nigeria Akwa Ibom State University, Mkpat Enin, Nigeira
oomorogiuwa@yahoo.com; eseosa.omorogiuwa@uniport.edu.ng

Abstract Off-grid remote electrification with the aid of Hybrid Power System (HPS) has become cost-effective and
convenient alternative for areas where grid connection is neither available nor feasible. HPS combines two or more modes of
electricity generation together; usually using renewable technologies such as Solar, Wind etc. This research focus on creating
a model for electricity generation from mix of renewable resources to satisfy the electrical needs of an off-grid remote village of
Bakpo in Eleme L.G.A. of Rivers State, Nigeria using HOMER software. The HPS selected for this village scenario comprises
of biomass, gas turbine, solar PV associated with battery and converter. Load demand pattern over different seasons was
studied and suitably modeled using HOMER. The solution obtained shows that the use of decentralized hybrid power systems
at an off-grid location is the best alternative to grid extension. More so, it is sustainable, techno-economically feasible and
environmentally friendly. Total Net Present Cost (NPC) was used as a yardstick to measure the viability and feasibility of the
project.

Keywords Hybrid,Renewable,PV-Diesel,Biomass,Nigeria

I. INTRODUCTION this problem due to enormous availability of renewable


natural energy sources to generate electricity (Balaet al,
Economic growth and development of any nation 2009).
requires energy. Nigeria as a developing country of over Against the background of electricity problems rural
one hundred and fifty million people, were majority of its communities are facing, the study will evaluate HPS with
populace lives in rural areas without access to electricity, the following objectives:
has serious challenge of supplying adequate energy to its Provide electricity to the un-electrified remote village
large population. Current energy demand of over through HPS source.
40,000MW is far less than available hovering around Improve the socialeconomic activities of the village
2,900MW-4,000MW, yet there are enormous energy This work aim to assess the benefit of HPS and using
resources (renewable) all over the nation. Before now, the village to propose the way forward and how it may be
non-renewable energy source such as fossil fuel had been introduced elsewhere in Nigeria.
the major means of generating electricity. The high
dependence on it has resulted in consequential II. REVIEW OF RELATED WORKS
implications like fuel price fluctuation environmental
hazard and global warming. (Omorogiuwa Eseosa and There have been several studies on off-grid electricity
Uhunmwangho R 2014) it is time to think alternative generation in Nigeria. Different techniques and approaches
energy source. Therefore, it is obvious that hybrid power have been used in relation to various scenarios and
is an alternative to conventional energy source (Ani, 2013) circumstances, including evaluation of Solar Photo Voltaic
most especially due to its positive impact on the (SPV), Diesel Generator (DG), and fuel cells amongst
ecosystem. Majority of rural settlements in Nigeria are others. Research on HPS combining renewable and fossil
deprived of steady electricity supply from national grid. derived electricity started 25years ago, but few have
For this reason, an isolated system is required in remote written papers about system implementation and
areas with the use of locally available energy resources. experimental data collection (Poopola et al, 2013).
HPS combines two or more means of electricity According to Ani (2013), the research describing
generation and are generally independent of large electric renewable energy hybrid systems appeared in themid-
grid systems and are used to feed loads to remote areas eighties, but literature on hybrid systems did not blossom
that are off-grid, as this pose big challenge to electric until the early1990s. Initially, this expansion in hybrid
power utilities companies. Extension of central electricity literature was driven by then eed to increase grid stability
grid to such are as is either financially not viable or and reliability as large quantities of wind power were
practically not feasible as these locations are either being added to small autonomous grid. Researchers then
geographically isolated or sparsely populated. Village used optimization techniques to model how HPS can
electrification is a vital step for improving the socio- reduce electricity generation costs over conventional fossil
economic conditions of rural areas and crucial forth fuel systems (Ashari and Nayar, 2012). Bala et al (2000)
country's overall development and better standard of living used genetic algorithms (GA) to assess optimal size of a
(Biodun et al, 2012).HPS provide formidable solution to

2015 IJSRET
71
International Journal of Scientific Research Engineering Technology
Volume 1, Issue 4, July-2015, ISSN (Online): 2395-566X

stand-alone hybrid system to minimize its costs and environmental and socio-economic factors and reached the
concluded that using wind-solar hybrid system is cheaper result that HPS is the best option in cases like this, mostly
than to rely on one of these resources individually. During because of high costs incurred when transmitting
their analysis, various technical details of the system such electricity from conventional sources to extremely remote
as PV modules tilt angle, installation height of wind locations. Anayo (2007)conducted a study on small remote
turbines etc, that were significant for the installation and villages with low load factors and found that stand-alone
maintenance costs were considered. A case study on HPS can be an attractive alternative to grid extension.
Dahran and its energy demand of 620,000 kWh/year was Several studies on stand-alone HPS showed that this
conducted (Givler and Lienthal, 2005). A hybrid SPV-DG- technology is generally not a cost-effective alternative to
battery system, with 175 kW DG and 80kW SPV was grid extension. Only where the grid would have to be
built. The authors envisaged several scenarios in their extended by more than 20km, stand-alone SPV becomes
study and examined the difficulties arising in various financially attractive. According to Ahmed (2002), rural
scenarios such as unmet load situations, emission area located in Kaduna in Northern Nigeria, where 99.5%
decrease, excess electricity and energy cost. A are of rural households and 80% of the households in
combination of SPV and a small wind turbine with fuel cities are not grid-connected. The researcher examined the
cells was used by Chiemeka and Chinekein 2003. The use of stand-alone HPS to improve this scenario and
combination with fuel cells for excess electricity was summarized that in order to make HPS readily available,
found to be well suited for remote village applications. the government policies concerning it and key market
Kassam in 2010, developed designs of solar-wind hybrid barriers hampering its fast dispersion must be eliminated.
systems to supply electricity to remote areas of Australia. The work was extended to combination of stand-alone
These hybrid RET systems were studied with different SPV with DGs. It was observed that SPV were techno-
configurations of switched, parallel, and series economically more efficient and gave an output of
connections. Also concerned with the right sizing of 15kWh/day and 68kWh/day when the economic
solar-wind hybrid system is the study by Lietzmann et al circumstances were better, making SPV market-
in 2002. A method to determine the exact demand load of competitive. Biodun et al (2013) assessed the suitability of
the location and to calculate the appropriate size of SPV stand-alone renewable energy (RE) systems to meet
array with batteries for best results was formulated. Khan energy demands of big hotels (large-scale enterprises) and
and Iqbal in 2005 investigated the feasibility of hybrid found that wind energy is more cost-efficient than SPV, as
systems with hydrogen as energy carrier in New found the latter has the disadvantage of requiring lots of space
land, Canada. The energy carrier was introduced to for large-scale energy production.
alleviate disadvantages of stand-alone system (for example
high battery costs, limited storage and low capacity). III. METHODOLOGY
Several renewable and non-renewable carriers were
discussed, comparing their environmental friendliness and Various modeling techniques are developed to model
cost-efficiency using HOMER. In the end, combination of components of HPS. General methodologies for modeling
wind turbines, Distributed Generators (DG) and batteries HPS components such as PV, turbine set, and battery used
was discovered to be the most efficient solution at the are described.
given cost. (Okedu and Uhunmwangho 2014), in their 3.1 Modeling of PV System
study used HOMER software to propose an optimization In order to achieve best performance, PV modules must
solution of hybrid system of renewable energy for remote operate at maximum power point (MPP). Power generated
areas asserted that in order to determine optimum system by DC power and PV cell temperature are calculated using
configuration that would be more energy efficient, the net equations 3.1 and 3.2 respectively
present cost should be used as the basis for selection of = N (3.1)
best operation conditions considering a system made up of
= (1 + ( ))* (3.2)
PV, wind turbine, AC diesel generator, battery and
converter system. A developed HPS model combining The temperature of PV cells is a function of weather
SPV, DG and batteries to meet the load demand of an conditions and PV cells characteristics.
electric machinery laboratory using HOMER software was 3.2 Modeling of Battery Bank
used for optimization and simulation of different Surplus power produced by PV modules is used to
combinations (James, 2010). charge the battery bank. The batteries charging current
According to Poopola (2013),HPS combine two or more (ICO) is limited by the charge controller to the maximum
modes of electricity generation together, using renewable allowable charging current I.Cmax and SOC must be equal
technologies such as Solar, Wind turbines etc. Solar to or less than S.O.Cmax. Charging current ICO is
photovoltaic configuration is one way to provide off-grid calculated as:

electricity and can be employed in a tropical country like = + 1 (3.3)

Nigeria for any kind of electrical application. More studies
Where C is charge controller efficiency (it is constant and
on the viability of HPS for remote villages have been
equal to 0.98 in the model); B1is the AC/DC converter
conducted by Ayodele et al. (2005) considering
efficiency, though it varies insignificantly with the load

2015 IJSRET
72
International Journal of Scientific Research Engineering Technology
Volume 1, Issue 4, July-2015, ISSN (Online): 2395-566X

and it is assumed to be constant at 0.9; VB is the system


=(13.3 + 59.8) 100 (3.8)
voltage and equals to 48V. In situations when power

required exceeds generated power from the battery, 3.4 Electrical Load Assessment
contributes to compensate for the shortfall power. The off-grid study was conducted in Bakpo, a remote rural
+
= (3.4) village in Eleme L.G.A near Port Harcourt, Rivers state,
1
Nigeria with a population of 100 people living in 40 houses.
The change in the battery capacity CD with a period of It has a primary school block with 4 class rooms and a health
time of t is and battery state of charge are calculated as center block with 2 rooms and located at Latitude 439N
shown in equations 3.5 and 3.6 respectively and Longitude 79E with average elevation of 460 meters
= ( )- (3.5) above sea level. It lack electricity supply due to non-
=(1) + (3.6) availability of grid network but requires power supply to
3.3 Modeling of Converter power appliances like tungsten filament bulbs, ceiling fans,
Mathematical Model of Power Converter of power security outdoor lights, television sets, etc. For the pre-
delivered by an inverter is given by: HOMER study, load requirement is calculated considering
= + (3.7) variations of season (rain and dry). Table 3.1 shows the
Mathematical relationship required by the inverter in village daily power demand.
order to fully supply power is shown in equation 3.8 where
is the discharge efficiency determined as:

Table3.1: Daily Power Demand for Bakpo Village


Components Power (W) Overall quantity Hrs/day Watt Hrs/day KwHrs/Day
Tungsten filament bulbs 40 150 9 54000 54
Ceiling fans 100 20 13 26000 26
Security outdoor light 60 30 9 16200 16.2
21 TV set 100 10 4 4000 4
Miscellaneous 100 20 20 4000 4
Total 400 104,200 104.2

3.5 HPS Components, Configuration and Operations


The proposed HPS for the village comprises PV
module, Battery, Bi-directional Power Converter,
Controller unit and turbine set as shown in figure 3.1. Its
configuration and operations using flow chart is shown in
figure 3.2. During the day, solar PV is the first choice and
only source of energy Solar (PV) which is DC power,
combines with one of the pre- stored charged batteries and
is converted to AC power by converter for the load (s) and
simultaneously charges the other batteries. During night Fig.3.1: Block Diagram of System Configuration
time, solar energy stored during daytime in battery is the
only source of energy while the turbine is off. The
converter converts DC to AC power for the load. Shortfall
can occur on any low solar- radiation day or on excessive
load demand resulting in low charging of battery and thus
system may encounter problem during end of day or night
period to meet the balance load power requirement of the
day. During shortfall, the battery reaches its maximum
discharge level and therefore, the turbine is made on.
During this period generator set serves the load as well as
charges both the batteries, one at a time or simultaneously,
till it resume full /sufficient voltage.

Fig.3.2. Flow Chart of System Operation and


Configuration during the day, night and shortfall.

2015 IJSRET
73
International Journal of Scientific Research Engineering Technology
Volume 1, Issue 4, July-2015, ISSN (Online): 2395-566X

3.6 HOMER Software under study was also computed. The process produces
HOMER (Hybrid Optimization Model for Electric biogas, which comprises methane, carbon dioxide and
Renewable), simplifies the task of evaluating designs of traces of other contaminant gases that can be used for
both off-grid and grid-connected power systems for cooking, electricity generation etc.The resulting
various applications. Various selections of different calculation from latrines wastes to produce methane gas in
components like generators, PV arrays, battery banks and Bakpo village near Port Harcourt, in Rivers State, Nigeria
other power system components via the add/remove button is as thus:
are chosen as shown in Figure 3.3. Let 1kWh = 3415btu.
With 0.34 as plant factor, gas turbine fuel consumption
of 3415/0.34 =10000Btu/kWh,
Net heating value of methane = 21433Btu/pound, then
methane consumption in a simple gas turbine is
10000/21433 =0.47pounds/kWh = 0.21kg/kWh
But, 1000litres = 1m 3; 22.4litres = 1mol; Molar mass of
methane (CH4) = 16g per mole
Then, 16mol-11000l m-31/22.4l = 714g/ m3; Volume
of human waste from each house = 5.0 m3. Total volume =
5.0 20 houses = 100m3
100 m3 0.714 =71.4 kg
If 1000 litres of village latrine waste produces 1000litres
of biogas, 71.4kg will produce 71.4m3 of biogas. Energy
produced from 71.4kg of biogas is 71.4kg /0.21kg/kWh =
Fig.3.3
340kWh
3.6.1 Load Input Recommending a 1kW biogas generator that can run for
Hourly load profile readings throughout the year for 340/24h = 14.17 i.e. approximately two weeks.
both seasons (dry and rainy) was obtained and entered as Density of human waste is approximately equal to the
shown in figure 3.4. AC load data is obtained and density of water = 1000kg/ m3.
converted via a converter to Dc voltage that is produced Mass of human waste = 1000 100 = 100000kg
by PV module and DC voltage stored in Battery system.
Let assume that the village latrines pits are evacuated
after every two years, the mass per month =2083.3kg.ass
per day = 69.44kg. The available biomass waste in tonnes
per day is given as:
3662.5/1000 = 0.0694tonnes per day.

Fig 3.4: Primary Load 1

Tungsten filament bulbs, ceiling fans, security outdoor


light and television were considered as primary load in this
study. The load type served is AC and changes during dry Fig.3.5. Biomass input in tonnes/day
and rainy seasons. The load demand is approximately
175kWh/day and 39.9 kW peak and off-peak with load 3.6.3 Solar Photovoltaic (SPV) Input
factor of 0.182. The SPV panels are connected in series- parallel. When
3.6.2 Bio-Based Renewable Fuel sunlight is incident on the surface of PV panel, it produces
Latrine waste isone of the largest source of gas electricity.
emissions and its equivalent quantity from the village

2015 IJSRET
74
International Journal of Scientific Research Engineering Technology
Volume 1, Issue 4, July-2015, ISSN (Online): 2395-566X

capacity of 200 Ah (2.4 kWh). It has a lifetime throughput


of 917kWh. Capital, replacement as well as operation and
maintenance (O&M) costs for one unit of battery were
considered as $300, $300 and $4 respectively which are
equivalent to N55500, N 55500, and N 740/year in Nigeria
currencies respectively. The batteries charging and
discharging cycles are modelled in HOMER .
3.6.5 Converter Input
A converter is an electronic power device that is
required in a hybrid system to maintain the energy flow
between AC and DC electrical components.

Fig.3.6. SPV costs and technical parameters.

The capital cost and replacement cost for a 5kW SPV is


taken as $1500 and $1500 respectively which is equivalent
to N277500, N277500 Nigeria Naira respectively.
Since solar PV require little or no maintenance, only
$130/year which equivalent to N24, 050 in Nigeria
currencies is taken for O&M costs. Figure 3.7 also shows
that the SPV is connected to a DC output with a lifetime of
20 years. The difference between capital and replacement
cost is also shown in the cost curve in figure 3.6. The
derating factor considered is 80% for each panel to
approximate the changing effects of dust and temperature Fig.3.8. Converter cost and technical parameters
on the panels.
3.6.4 Battery Input Figure 3.9 shows the capital cost, replacement cost and
Batteries are used as a backup in the system and to O&M costs for 5kW converter, as $400, $400, and
maintain a constant voltage during peak loads or a $80/year respectively which is equivalent to N74000,
shortfall in generation capacity. HOMER models a N74000 and N14800 Nigeria currencies respectively.
number of individual batteries to create a battery bank Figure 3.8 shows the cost analysis curve, the lifetime of
connected in series-parallel connections. the converter of 15 years and inverter efficiency of 85%.
3.7.1 Solar Energy Resource
Solar resource used for the village at a location of 439'
N latitude and 79' E longitude was taken from NASA
Surface Meteorology and Solar Energy.

Fig.3.7: Vision 6FM200D Batterys costand technical


parameters.

The battery chosen for this study is as shown in Figure


3.8 Vision 6FM200D. It is a 12V battery with a nominal Fig.3.9: Solar Energy Resource. (Source: NASA website)

2015 IJSRET
75
International Journal of Scientific Research Engineering Technology
Volume 1, Issue 4, July-2015, ISSN (Online): 2395-566X

Figure 3.9 shows solar resource profile considered over process are shown where the best possible combination of
a span of one year. The average clearness index and SPV, DG, converter and batteries are able to fully meet the
annual average solar radiation was found to be 0.438scaled village load demands at the lowest possible total NPC of
and 4.37114kWh/m2/Day. $1,357,033 as shown in figure 4.2. The next most
economical combination is about $23,690,664,followed by
IV. RESULTS AND DISCUSSION $33,894,256 and so on.

The economic analysis of electricity generation with V. CONCLUSION AND RECOMMENDATION


Hybrid Power System in the village of Bakpo was carried
in this study. To meet the load demands, a different types Even though the initial investment required is
of renewable energy resources were chosen, which are comparatively high, the LCC analysis shows that for a
available in the study area. remote village like Bakpo with low energy demand, HPS
can be cost-competitive due to high costs for a grid
extension. Electricity from the grid might be cheap, yet the
costs for grid extension and the transmission and
distribution losses associatedwith it sum up to to a high
cost of electricity, especially where the grid has to be
extended over a long distance.Furthermore, once the hybrid
system has been implemented, it has low operation and
maintanance cost. For these reasons, a stand-alone Hybrid
Power System can be the most financially attractive and
reliable solution in the remote village of Bakpo.
There is a considerable market for stand-alone Hybrid
Power System both in remote and highly populated areas.
To meet this markets demands, It is therefore
Recommended that policies have to be implemented to
promote the utilzation of HPS in remote areas. Moreso,
off- grid electricity generation based on HPS plays an
Fig.4.1: System Configuration in HOMER important role in addressing the issue of Nigeria energy
crisis,therefore, local governments authorities in Nigeria
For the off-grid electrification of Bakpo village, various can play important role in promoting HPS. These can be
combinations were obtained of the hybrid systems with taken into account in their decision making, planning and
SPV, Biomass, batteries and converter from the HOMER budgetingin relation to remote rural electricity
Optimization simulation as shown in figure 4.2. infrastructure.

REFERENCES
[1] Ani, A.A. Simulation and Optimization of Stand-Alone
Photovoltaic/Diesel Hybrid System for Banking
Industry. International Journal of Energy Optimization
and Engineering.Vol.5, no.3, pp.1-5, 2013.
[2] Ashari, M. and Nayar, C.V.. An Optimum Dispatch
Strategy using Set points for a Photovoltaic (PV)
DieselBattery Hybrid Power System. IJRRAS vol. 6,
no.1, pp.19, 1999.
[3] Omorogiuwa E, Uhunmwangho R Design and
Simulation of Solar Monitoring Tracking System IOSR
Journal of Electrical and Electronics Engineering (IOSR-
JEEE) e-ISSN: 2278-1676 Volume 4, Issue 5 (Jan. - Feb.
2013), PP 35-39 www.iosrjournals.orgwww.iosrjournals.
org.
[4] Bala, E.J, Ojosu, J.O. and Umar, I.H. Government
Policies and Programmes on the Development of Solar-
Fig.4.2. Optimization result details PV Sub-sector in Nigeria Nigerian Journal of
Renewable Energy. vol.8, no.1, pp. 1-6, 2000.
HOMER uses the total NPC as its main selection tool. [5] Givler, T M and Lilienthal P.O, Using HOMER
All the possible hybrid system configurations for the Software, NRELs Micro Power Optimization Model, to
Explore the Role of Gen-sets in Small Solar Power
village of Bakpo are listed in ascending order of their total
Systems; Case Study: Sri Lanka Technical Report,
NPC. Technical and economic details of all the National Renewable Energy Laboratory, USA,2005.
configurations of hybrid systems from the optimization

2015 IJSRET
76
International Journal of Scientific Research Engineering Technology
Volume 1, Issue 4, July-2015, ISSN (Online): 2395-566X

[6] Kassam, A.G HOMER Software Application for Hybrid


Power Systems IJRRAS, vol. 3, no. 2, pp. 10-1,2010.
[7] James L.L. Optimization in Renewables Applications,
IJRRAS, Vol.4, no. 3, pp. 10-14,2010.
[8] Popoola O.T. ,Ajao K.R., Oladosu O.A. Using HOMER
Power Optimization Software for Cost Benefit Analysis
of Hybrid-Solar Power Generation Relative to Utility
Cost in Nigeria IJRRAS, vol. 7, no. 1, pp. 96-100,2013.
[9] Chiemeka I.U. and Chineke T.C Evaluating the global
solar energy potential at Uturu, Nigeria, Inter. J. Physical
Sciences, Vol. 4, No. 3, pp. 115 119,2009.
[10] Ahmed, M.N Optimal Sizing of a Hybrid System of
Renewable Energy for a Reliable Load Supply without
Interruption European Journal of Scientific Research,
vol.45, no.4, pp. 20-25, 2002.
[11] Al-Karaghouli, A., Kazmerski, L.Optimization and life-
cycle cost of health clinic PV system for a rural area in
southern Iraq using HOMER software.IJRRAS, vol. 4,
no.2, pp710, 2010.
[12] Biodun T.O Ani, V.A. and Nzeako, A. N. The
Potential of Stand-Alone PV/Wind Hybrid Energy
System for Power Supply to Remote Rural Areas in
Nigeria International Journal for Clean Environment.
vol.13, no 4, pp12, 2012.
[13] Anayo S.A. "Optimised Model for Community-Based
Hybrid Energy System. International Journal of Energy
Optimization and Engineering. vol. 32, no7, pp56, 2007
[14] Bamiyo, C.D., Lawrence, T.F., Abergas, R.L., Feasibility
of Hybrid Retrofits to Off-Grid Diesel Power Plants.
IJRRAS, Vol.12, no4, pp.10-12, 2005

AUTHOR'S PROFILE

Omorogiuwa Eseosa
research interest include power system
optimization using power electronic devices
(Flexible Alternating Current Devices and
Custom Power Devices), power system
optimization, economics, marketing, renewable
energy and application of intelligent techniques to power
systems networks and machines. He hold a Ph.D. in power
systems and electric machines and currently lectures in the
university of port Harcourt, Rivers state, Nigeria.

Okpo Ekom Enefiok


research interest is in power system and electric machines. He
holds a masters degree in power systems and electric machines.
He is currently a lecturer in the Department of
Electrical/Electronic Engineering Akwa Ibom State University,
Mkpat Enin Nigeira.

2015 IJSRET
77

You might also like