METHOD STATEMENT FOR CONTRACTOR:

TESTING AND MACAIR /


COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

TABLE OF CONTENTS
Item Description

1.0 Scope.
2.0 References.
3.0 Access / Egress
4.0 Health &Safety Hazards
4.1 Safety Rules during Testing.
4.2 Safety Lighting.
4.3 Task Lighting
4.4 Emergency Arrangements.
4.5 Risk and Controls.
5.0 Abbreviations and Definitions.
6.0 Roles/Responsibilities/Competence.
7.0 Testing and Commissioning Procedures.
7.1 Attachment 1- Method of Commissioning:
8.0 Training.
9.0 Working Hours.
10.0 Manpower Requirement and Supervision.
11.0 Test Instruments Requirements.
12.0 Requirements.
12.1General Requirements.
13.0 Personnel Equipment.
14.0 Supporting Information.
15.0 Distribution
16.0 Other information

1
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

17.0 Attachments
17.1Method of Commissioning : MDBs, MCCs, EMDBs & Capacitor Banks
17.2Method of Commissioning : SMDBs, ESMDBs &DBs.
17.3Method of Commissioning: VFD Panels.
17.4Calibration Certificates.
17.5Risk Assessment.
17.6Test Reports.

2
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

1.0 SCOPE
This Procedure Covers the Testing and Commissioning of Electrical Panels in the DUCAB HV & EHV
Facility. The MDBs, EMDBs and Capacitor banks are installed at the LV rooms, while MCC Panels are at
VCV Tower roof, CCV Tower roof, EHV Test lab electrical room , Chiller plant area and mechanical plant
room. EMCCs are located at VCV Tower roof, CCV Tower roof and Administration office first Floor. ESMDBs
are installed at Factory area and VCV Tower electrical room (Ground floor). SMDBs and DBs are installed at
all areas in the project as indicated on the service drawings. This procedure will also ensure proper
workmanship and conforms to Contract documents, manufacturers instructions and standards.

2.0 REFERENCES

2.1 Approved MACAIR Shop Drawings for Power layout. (Ref: Ducab KB644/SD- 00107, 00108,
00161-00170, 00174-00176, 00187-00199, 00203, 01027,01324,01325 & 01485).
2.2 MACAIR Project Quality Plan.
2.3 MACAIR Safety Manual
2.4 Manufacturers recommendations.

3.0 ACCESS /EGRESS

The Commissioning of the System will commence only when Main Contractor clearance is given for
access to conduct the Testing and Commissioning.

4.0 HEALTH & SAFETY HAZARDS

Health and Safety procedures by Main Contractor and MACAIR will be implemented for this job. A routine
safety check will be done by the Safety Officer In-charge as per MACAIR Safety Procedure.

4.1 Safety Rules During Commissioning


In order to ensure safe conditions during testing the following rules have to be followed:
4.1.1 Persons engaged with this commissioning are experienced and have received proper and
adequate training related to procedures and test equipment utilized for the particular
testing activity.
4.1.2 Test instruments and test leads should be maintained in a safe condition and the test
methods not to create danger either for the operator or for other persons.

4.2 Safety Lighting

Safety Lights will be used in case of power failure ensuring good illumination at the working area to
aid evacuation if necessary.

3
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

4.3 Task Lighting

Adequate lighting shall be provided to ensure good illumination at the working area.

4.4 Emergency Arrangements

4.4.1 General: Site Safety procedures will be followed and in case of any emergency, Safety
Officer will administer the emergency arrangements as per the system, stop work and
report to nearest Assembly Point, etc.
Safety Officer Name : Mr. Reghupathy, (Con # 0559262923)

4.4.2 Fire Precautions: No significant fire risks associated with this activity but general fire
precaution measures will be taken.
4.4.3 Communication: Via mobile phones issued to all engineers.

4.5 Risk and Controls

4.5.1 Please refer to the Risk Assessment attached in Section 17.6


4.5.2 Environmental considerations: There are no waste materials associated with this activity.

5.0 ABBREVIATIONS & DEFINITIONS

MC - Main Contractor (MACAIR)


PM - Project Manager (MACAIR)
PE - Project Engineer (MACAIR)
PE - Project Engineer (Prime Electrical)
SO - Safety Officer (MACAIR)
QA/QC - Quality Assurance/Quality Control (MACAIR)

6.0 ROLES/RESPONSIBILTY /COMPETENCE

6.1 PM - will have the overall responsibility of the Project for execution, quality and safety, maintain
the planning and progress and coordination with Main Contractor.

6.2 PE - will be responsible for day to day activities in the Site for System Testing and
Commissioning, report preparation and demonstration of System Commissioning.

6.3 PE (Prime Electrical) - will be directly responsible for the System commissioning.
6.4 SO - will be responsible for Health and Safety aspects in the Site in line with Main Contractor
Safety requirements.
6.5 QA/QC - will oversee the quality requirements and quality control measures for the Project.

4
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

7.0 TESTING AND COMMISSIONING PROCEDURES


Please refer to the attachments as follows;
7.1 Method of Commissioning : MDBs, MCCs & EMDBs.
7.2 Method of Commissioning : Capacitor Banks
7.3 Method of Commissioning : SMDBs, ESMDBs &DBs.
7.4 Method of Commissioning: VFD Panels.
7.5 Calibration Certificates.
7.6 Risk Assessment.
7.7 Test Reports.

8.0 TRAINING
8.1 Engineers who will conduct the Commissioning shall have the experience in System
Commissioning.
8.2 Tool Box talks will provide general training and awareness for each activity and also undergo
further training by the Quality Assurance Department.

9.0 WORKING HOURS


Site Normal Working Hours.

10.0 MANPOWER REQUIREMENT & SUPERVISION


PM - Project Manager (MACAIR)
PE - Project Engineer (MACAIR)
PE - Project Engineer (Prime Electricals)
SO - Safety Officer (MACAIR)
QA/QC - Quality Assurance/Quality Control (MACAIR)

11.0 TEST INSTRUMENT REQUIREMENT


The following Test Instruments will be used for the Commissioning of the Electrical Panels. They will be
selected as having the maximum field measuring accuracy and being the best suited to the function being
measured and will be applied as recommended by the manufacturer.
11.1 Test Instruments

5
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

11.1.1 Megger.
11.1.2 High Pot Tester.
11.1.3 Torque wrench
11.1.4 Multimeter
11.2 Calibration
11.2.1 All Instruments used shall carry current calibration certificates. Calibration periods for all
instruments are recommended by the manufacturer and are in line with the requirements
of the Commissioning Specialist Association.
11.2.2 Certificates shall be available for presentation prior to commencement of commissioning.

12.0 REQUIREMENTS
12.1 General Requirements
Before commencing commissioning works, the following information /items will be made available.
12.1.1 System is fully installed and pre-tested.
12.1.2 All equipment are available at site.
13.0 PERSONNEL EQUIPMENT
13.1 All Commissioning Engineers and Technicians shall have the necessary Personnel Protective
Equipment such as Safety Shoes and Helmet.

14.0 SUPPORTING DOCUMENTATION


14.1 Approved Inspection of 1st Fix Installation.
14.2 Approved Inspection of 2nd Fix Installation.
14.3 Approved Inspection of Final Fix Installation

15.0 DISTRIBUTION
15.1 Main Contractor
15.2 Consultant.
15.3 MEP Senior Mechanical Engineer.
15.4 Health and Safety Officer.

16.0 OTHER INFORMATION


Not applicable for this activity.

6
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

17.0 ATTACHMENTS
17.1 Method of Commissioning : MDBs, MCCs & EMDBs
17.2 Method of Commissioning : Capacitor Banks
17.3 Method of Commissioning : SMDBs, ESMDBs &DBs.
17.4 Method of Commissioning: VFD Panels.
17.5 Calibration Certificates.
17.6 Risk Assessment.
17.7 Test Reports.

7
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

ATTACHMENT 17.1

Method of Commissioning: MDBs, MCCs, EMDBs

8
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

ATTACHMENT 17.2

Method of Commissioning: Capacitor Banks

9
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

ATTACHMENT 17.3

Method of Commissioning: SMDBs, ESMDBs &DBs.

10
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

ATTACHMENT 17.4

Method of Commissioning: VFD Panels

11
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

ATTACHMENT 17.5

Calibration Certificate

12
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

ATTACHMENT 17.6

Risk Assessment

13
METHOD STATEMENT FOR CONTRACTOR:
TESTING AND MACAIR /
COMMISSIONING OF DOC.NO:MS-
ELECTRICAL PANELS.
(MDBs, MCCs, CAPACITOR REV:
BANKS, EMDBS, SMDBs, DATE : 03/02/2011
ESMDBs & VFD PANELS)

ATTACHMENT 17.7

Test Reports

14