M ountainpassslopefailureretrofi
ttedwi
thhal
fvi
aductbri
dge
structure
E.
J.Kruger
South African National Road Agency Limited, Pretoria, South Africa
A.
A.Newmark& M .Smut
s
BKS Engineering & Management, Cape Town, South Africa
1107
Figure 1. Aerial view of failed slope area.
assessment of safety of these structures also formed
part of the consultants brief and in addition, record
drawings of the existing structures provided valu-
able initial information that enabled the development
of preliminary concepts by the project team. Initial
investigations and a desktop study of available infor-
mation and requirements of the client consisted of:
At least two traffic lanes (one in each direction) had
to be maintained during all construction stages.
The angle of the dip of the rock formation was
away from the mountain side at angle of 30 to
40 degrees.
The weathered rock face on the outside of the slope
under the talus could be as steep as 70 degrees
depending on the local geotechnical profiles.
Significant variations in founding depths could be
Figure 2. Failure crack with subsidence clearly evident. experienced considering the nature of the rock and
extensive weathering observed.
Any future risks which could result in future slope
2 OVERVIEW OFCONCEPTUAL failures in this area that could impact on the stabil-
ALTERNATIVES ity of the roadway had to be minimized.
Repair options would have to be combined with
An extensive information gathering exercise, topo- rock anchor and/or soil nailing systems.
graphical surveys and subsurface investigation were Considering the weathered fractured and jointed
immediately commissioned in order to establish rock, profile piling would have to be done by using
the nature of the underground strata. There are two large diameter (1000 to 1200 mm) oscillator piles.
existing half-viaduct type bridge structures in the Their ability to penetrate through rock and boulder
immediate vicinity of the failure zone to the western formations and to socket into bedrock was essential
and eastern sides of the new viaduct location. The in this application.
1108
The interaction of the roadway and possible adjacent The second design concept involved a more
structure had to be carefully assessed to limit future conventional retaining structure. This comprised of a tied
maintenance activities. mechanically stabilized embankment, constructed by
excavating to a sound founding level and the construc-
Three design concepts were selected and further
tion of a stabilized earth type backfill on an anchored-
developed by the consultants bridge specialists, Abe
back reinforced concrete footing as shown in Figure 4.
Newmark and Martin Smuts and the clients Edwin
This approach was more suited to flatter rock dip
Kruger. Ron Tluczek, the consultants geotechnical
angles and rock face profiles as detailed in Figure 4.
specialist, who had been involved in some of the pre-
Dependent on the outcome of the detailed geotechnical
vious structures on this section of the route, provided
investigation, it was considered possible to construct
critical geotechnical input.
this option without the temporary soil nail structure,
In view of initial lack of geotechnical data, vari-
in view of the reduced work space requirements.
ous rock dip angles were postulated to fast-track the
The third concept comprised a half-width viaduct
assessment of these design concepts in terms of suit-
bridge structure as shown in Figure 5.
ability and cost. From the discussion below it will
Similar to the first option, a soil nail structure
be evident that not all the concepts were suitable for
(permanent in this instance) would be constructed
some of the steep dip angles that were postulated.
adjacent to the road centre line to provide space for
This approach assisted in meeting the clients time
two-way traffic and a working platform to erect con-
constraints.
ventional piers. Longitudinal precast beams supported
The first design concept comprised a tied pile
on the pier caps and abutments would carry the via-
anchor wall and reinforced concrete cantilever shown
duct deck. The pier footings would be anchored back
in Figure 3.
by means of rock anchors. This concept was similar
The construction procedure for this concept involved
to the existing half viaduct structures in the vicinity.
the excavation to a suitable work platform by stabilizing
the existing roadway with a temporary soil nail struc-
ture to ensure accommodation of two-way traffic dur-
ing construction. This technique would allow space for
a working platform to be created to drive oscillator piles
to support a quarter roadway-width cantilever structure.
It was envisaged that the horizontal stability of the piles
would be secured by sloped rock anchors in this instance.
The main advantage of this concept was the minimiza-
tion of the risk as a result of the stabilizing effect of mul-
tiple anchored pile shafts in the rock formation.
In addition, the substantial lateral force component
minimized relevant movement between the roadway
and reinforced concrete elements of the structure.
This concept was also suited to all the various rock
dip angles that were postulated.
Figure 4. Mechanically stabilized embankment concept.
Figure 3. Tied pile anchor wall concept. Figure 5. Half viaduct bridge concept.
1109
The interaction of this structure with the adjacent
embankment would require the provision of a lon-
gitudinal joint with resulting long-term maintenance
requirements.
3 ANALYTICAL OVERVIEW
1110
Figure 7. Completed structure.
4 CONSTRUCTION ASPECTS Since this activity was on the critical path of the con-
tract, it resulted in a delay of completion.
The eight month construction period commenced in The concrete mix design was specified and care-
January 2007 and the travelling public was relatively fully monitored in view of the aggressive environment
unaffected except for the restricted lane width. The that the structure was located in. The cementitious
construction proceeded largely as planned and the binder consisted of a blend of Ordinary Portland
following aspects are considered worth noting: Cement and Corex slag, with enhanced durability
Prospective contractors, at time of tender, expressed properties and resistance to the ingress of chlorides.
some concern regarding construction activities on the The mix design, mixing, placement and compaction
partially failed slope area. It was however concluded was monitored by means of on site testing which was
that, as a result of the various investigations, the area performed on cube samples and cores extracted from
was safe for earthmoving machinery and personnel, but the structure.
that the situation would require constant monitoring
during construction. The successful contractor provided
a practical and efficient monitoring system. Based on 5 CONCLUSION
these readings and possible adverse weather conditions
such as heavy rainfall, the consultant was given the On completion, the portion of the road that once seemed
option to instruct the contractor to vacate the area. destined to slide into the Kaaimans River now has four
A contractual requirement required that none of permanent lanes. Post completion inspections con-
the temporary works related to the structure, such as cluded that the design objectives had been attained.
piling platforms, formwork for reinforced concrete The project provided the structural and geotechni-
elements, etc. were to be supported on the failed area. cal engineers with not only a challenging problem, but
After extensive monitoring and having recorded vir- also an opportunity to practice their art by restoring a
tually no further signs of further slope movement, vital transportation link and thus enhancing the lives
some variations from the original requirements were of the people and towns to whom this road serves as
allowed and some temporary support structures were an economic lifeline.
founded on the risk areas. The cost implication of this
risk was accepted by the contractor as his own. For-
tunately, the construction was completed without any ACKNOWLEDGEMENTS
further slope failures.
Unforeseen delays that were experienced during The client has kindly granted permission to publish
construction mainly related to the piling process which this paper. Vusela Construction is acknowledged as
proceeded substantially slower than anticipated. This the main contractor and Franki Africa as specialist
was mainly related to the limited work space, variable geotechnical subcontractor. Solid State Safety Con-
rock quality and the downslope dip of the rock strata. sultants performed safety audits.
1111