Professional Documents
Culture Documents
1.0 Alignment and elevation shall be checked and referred to the topographic,
bench mark, control points and building layout plans issued for common
references.
2.2 Re-establish again and again, as necessary, knocked down grid points,
reference or offset points.
2.5 Provide reference point at center line of elevator shaft for elevator
contractor's guide.
2.6 Provide (if needed) as-built for line and grade based on existing or actual
site condition.
a. Minimum of five (5) cylinder samples shall be taken for every 50 cu.m.
and / per design strength of concrete.
/conversion/tmp/scratch/360395634.doc page 1 of 8
c.2) General Contractor shall inform DAAA schedule of demoulding
of concrete cylinder samples.
c.3) Prior to placing of cylinder into the curing tank the same should
be signed by DAAA site inspector.
c.4) Samples should not be placed on top of the other inside the tank.
2.0 FORMWORKS
2.4 For column and retaining wall, check plumbness relative to the vertical
rebar reinforcement prior to installation of any siding forms. Provide
standard rebar separator using concrete spacer block to maintain
concrete protective covering.
/conversion/tmp/scratch/360395634.doc page 2 of 8
2.6 Submit formworks enclosure request for approval by DAAA site
inspector.
Concrete floor less than Fourteen (14) days old is considered a weak
floor.
2.9 Verify requirement for inserts, keyways, water stops built-in frames for
openings, holes through the concrete and similar requirements for other
trades attached or supported by formworks.
2.10 If shoring is to be placed on top of existing soil, make sure that shoring
does not rest on unstable, loose or wet soil. Provide adequate shoring
shoes to avoid settlement.
2.12 Provide form stoppers and tie rods or snap ties to maintain required
thickness for columns/RC wall/parapet wall.
3.1 Make sure all steel bar test results shall be conforming the required
tensile strength prior to any fabrication and installation. Get three (3)
samples for every 5,000 kgs per size per supplier.
3.2 All rebar fabrication and placement shall be based on approved rebar
cutting list
/conversion/tmp/scratch/360395634.doc page 3 of 8
3.4 Bars should be examined to see that it is free from paint, loose scale,
and cement mortar, oil or grease which would reduce or prevent
bonding.
3.5 Check proper storage and handling of rebars. Rebar stockpiles should
be supported by elevated racks to avoid surface contact against any
earth materials. Similarly, a protective covering (polyethylene sheet)
must be placed during rainy season to avoid rust and corrosion.
3.7 Rebar separators, bar chairs and concrete spacers shall be provided to
maintain the required spacings and clearances.
3.8 Check provision of additional steel bars for all pipes sleeves and
blockouts.
3.9 For rebar installation, rebar intersections shall be tied with standard G.I.
tie wires:
3.9.1 Floor slab reinforcement shall be tied with tie wire at rebar
intersections alternately/ staggered.
3.9.2 All rebar intersections at column vertical bars and column
lateral ties shall be tied with the tie wire (100%). Likewise, all
rebar intersections at R-C. wall vertical and horizontal bars
shall be properly tied (100%).
3.9.3 At elevator corewall, rebar intersections shall be properly tied
with standard G.I. tire wire based on the approved
shopdrawing.
4.11 Polythylene sheet which is sufficient or more than enough to cover the
entire area for concreting in case of unexpected heavy rain that may
experience during concreting works.
/conversion/tmp/scratch/360395634.doc page 4 of 8
4.2 Use approved trial mixes/design for actual concrete batch.
4.3 Rebars, formworks, line and grade must be inspected and approved by
DAAA site inspectors prior to concrete pouring.
4.5 Check all provision of construction joints, control joints, and expansion
joints and it should conform to the specs and approved shop drawings.
Construction joints should not be located at cantilever portion of beam
or slab.
4.6 Verify if all embedded items are in place prior to concrete placement.
Get signature of electrical, plumbing, mechanical and sprinkler
contractors on standard pouring permit prior to start of concrete
placement operations.
4.8 Assign qualified concrete technician to take care of concrete mixing and
placement.
4.10 For floor finish that required a straight to finish or no required topping
the following must be observed.
4.13 If transmit mix concrete is used, check delivery receipt against actual
requirement as to:
/conversion/tmp/scratch/360395634.doc page 5 of 8
4.12.2. Slump
4.14 Is the time between mixing and placement within maximum time
allowable? Check time of departure from batching plant to avoid
overmixing of concrete. Reject all overmixed concrete.
4.15 Adding of water or cement to the transit mix concrete at jobsite should
not be allowed. Reject concrete mix wherein concrete slump as
delivered exceeds by 8 for both 4000 psi or as designated in the
delivery receipt.
4.16 Check requirements to placing fresh concrete on concrete which has set.
Unless otherwise specified, apply a slush coat or neat cement grout to
the old concrete surface prior to placing fresh concrete. Verify special
cases wherein epoxy application is required for bonding old to new
concrete.
4.17 Form ties and supports must be checked frequently and adjusted as
necessary to prevent or correct movements of the form. At least 5-7
carpenters are present during each operation to ensure safety and
continuity of concreting works. In such case where minimal volume of
concrete is to be poured ei. Isolated footings, tie beams, columns, etc
requirements of carpenters can be reduced depending on the need.
4.18 Check that a period of one to two hours is allowed for concrete in
columns, piers and walls and along side of such items as built-in
window frames, to permit the concrete settle before placing concrete
above them.
4.18.1. Do not allow initial set to take place before placing the
concrete above.
4.19.1. Insert vibrators vertically through the full length of the layer at
uniformly spaced joints such that the circles of visible
influence of the vibrators overlap.
/conversion/tmp/scratch/360395634.doc page 6 of 8
4.21 The use of form vibrators is prohibited by some specifications and
permitted by others, subject to specific approval. Do not allow their use
except as provided.
5.1. For newly concrete structure less than three (3) days old, avoid
concentrated loads such as stock pile of steel bars, cement and concrete
hollow blocks, marbles, equipment, and the like to prevent un
necessary deflections.
/conversion/tmp/scratch/360395634.doc page 7 of 8
6.1 DAAA has the authority to recommend disciplinary actions to any
Technical Personnel who seems to violate the abovementioned
proceedings or agreed guidelines.
Prepared by:
CONFORME :
_________________________________________
EEI CORPORATION
General Contractor
/conversion/tmp/scratch/360395634.doc page 8 of 8