You are on page 1of 12

LNEA DE CONDUCCIN

PROYECTO: DISEO DE ABASTECIMIETO DE AGUA POTABLE Y EL DISEO DE ALCANTARILLADO DE LA LOCALIDAD DE APA CHICO, DISTRITO DE MANC
UBICACIN: LOCALIDAD: APA CHICO
PROVINCIA: YUNGAY

ITEM DESCRIPCIN ELEMENTO

01.00.00 TRABAJOS PRELIMINARES

01.01.00 TRAZO Y REPLANTEO

TRAMO 1 : CAPTACIN A CRP1 Longitud hor.


TRAMO 2 : CRP 1 A RESERVORIO Longitud hor.

01.01.00 CINTAS SEALIZADORA

01.02.00 CERCO DE MALLA HDP DE 1 m DE ALTURA / ELEMENTOS DE SEGURIDAD

01.03.00 PUENTE DE MADERA PARA PASE PEATONAL SOBRE ZANJA

02.00.00 MOVIMIENTO DE TIERRAS

02.01.00 EXCAVACIN EN TERRENO NATURAL Longitud hor.


ZANJA: ANCHO = 0.40 m, ALTO = 1.00 m

03.00.00 REFINE Y NIVELACIN DE FONDO DE ZANJAS

03.01.00 REFINE Y NIVELACIN P/TUBERA EN TERRENO NATURAL Longitud hor.

04.00.00 CAMA DE APOYO PARA TUBERAS

04.01.00 CAMA DE APOYO PARA TUBERAS

TRAMO 1 : CAPTACIN A CRP1 Longitud hor.


TRAMO 2 : CRP 1 A RESERVORIO Longitud hor.

05.00.00 RELLENO Y COMPACTACIN INICIAL PARA TUBERAS

05.01.00 RELLENO Y COMPACTACIN INICIAL SOBRE CLAVE DEL TUBO Longitud hor.
CON MATERIAL SELECCIONADO

06.00.00 RELLENO Y COMPACTACIN FINAL PARA TUBERAS

06.01.00 RELLENO Y COMPACTACIN DE ZANJAS CON MATERIAL SELECCIONADO Longitud hor.

06.02.00 ACARREO DE MATERIAL EXCEDENTE, DP = 30 m


ZANJA: ANCHO = 0.40 m, ALTO = 1.00 m
esponjamiento = 30% y considerando un 70% de material til
V=659.46x 0.4 x 1.00 x 1.3 x 0.7 = 240.04m3

07.00.00 SUMINISTRO E INSTALACIN DE TUBERIAS NTP ISO 4435-1


LNEA DE CONDUCCIN
PROYECTO: DISEO DE ABASTECIMIETO DE AGUA POTABLE Y EL DISEO DE ALCANTARILLADO DE LA LOCALIDAD DE APA CHICO, DISTRITO DE MANC
UBICACIN: LOCALIDAD: APA CHICO
PROVINCIA: YUNGAY

ITEM DESCRIPCIN ELEMENTO

07.01.00 SUMINISTRO E INST./TUBERIA PVC-SAP =100 mm (4") CLASE 7.5 S.P

TRAMO 1 : CAPTACIN A CRP1 Longitud hor.


TRAMO 2 : CRP 1 A RESERVORIO Longitud hor.

08.00.00 SUMINISTRO E INSTALACIN DE ACCESORIOS

08.01.00 CODOS

CODOS 11.25x4"

CODOS 22.5x4"

CODOS 45x4"

09.00.00 PRUEBAS HIDRULICAS

09.01.00 DOBLE PRUEBA HIDRULICA Y DESINFECCIN EN TUBERAS =4" Longitud hor.

10.00.00 VARIOS

10.01.00 DADOS O ANCLAJE DE CONCRETO PARA FIJAR TUBERIAS D=4"

10.02.00 CMARA ROMPE PRESIN

10.04.00 VLVULA DE PURGA DE 4"


DUCCIN
APA CHICO, DISTRITO DE MANCOS PROVINCIA DE YUNGAY DEPARTAMENTO DE ANCASH.
DISTRITO MANCOS
DEPARTAMENTO ANCASH

DIMENSIONES
ELEMENTO CANT PARCIAL TOTAL UND
LARGO ANCHO ALTO

Longitud hor. 1 111.15 111.15 659.46 ml


Longitud hor. 1 548.31 548.31

2 659.46 1318.92 1318.92 ml

2 659.46 1318.92 1318.92 ml

15 15 15 und

Longitud hor. 1 659.46 659.46 659.46 ml

Longitud hor. 1 659.46 659.46 659.46 ml

Longitud hor. 1 111.15 111.15 659.46 ml


Longitud hor. 1 548.31 548.31 ml

Longitud hor. 1 659.46 659.46 659.46 ml

Longitud hor. 1 659.46 659.46 659.46 ml

1 V= 240.043 240.04 240.04 m3


DUCCIN
APA CHICO, DISTRITO DE MANCOS PROVINCIA DE YUNGAY DEPARTAMENTO DE ANCASH.
DISTRITO MANCOS
DEPARTAMENTO ANCASH

DIMENSIONES
ELEMENTO CANT PARCIAL TOTAL UND
LARGO ANCHO ALTO

Longitud hor. 1 111.15 111.15 659.46 ml


Longitud hor. 1 548.31 548.31 ml

6 6 6 und

7 7 7 und

3 3 3 und

Longitud hor. 1 659.46 659.46 659.46 ml

16 16 16 und

1 1 1 und

1 1 1 und
TUBERA LONGITUD DIMETRO =18 mm (3/4") =25 mm (1") =50 mm (2") =75 mm (3") =100 mm (4")
P-1 164.97 25 P-1 164.97
P-2 142.79 100 P-2
P-3 50.66 75 P-3 50.66
P-4 43.52 75 P-4 43.52
P-5 18.39 18 P-5 18.39
P-6 12.25 75 P-6 12.25
P-7 107.45 18 P-7 107.45
P-8 54.62 50 P-8 54.62
P-9 28.51 50 P-9 28.51
P-10 70.89 50 P-10 70.89
P-11 49.43 25 P-11 49.43
P-12 42.99 100 P-12
P-13 49.49 100 P-13
P-14 72.85 75 P-14 72.85
P-15 130.70 25 P-15 130.70
P-16 42.52 50 P-16 42.52
P-17 40.48 50 P-17 40.48
P-18 47.41 50 P-18 47.41
P-19 99.99 50 P-19 99.99
P-20 28.52 100 P-20
P-21 20.18 18 P-21 20.18
P-22 56.72 100 P-22
P-23 35.37 100 P-23
P-24 26.68 75 P-24 26.68
P-25 133.82 50 P-25 133.82
P-26 25.76 50 P-26 25.76
P-27 66.62 50 P-27 66.62
P-28 49.21 18 P-28 49.21
P-29 61.45 25 P-29 61.45
P-30 45.83 100 P-30
P-31 25.55 100 P-31
P-32 45.33 100 P-32
P-33 35.23 75 P-33 35.23
P-34 28.47 18 P-34 28.47
P-35 61.09 75 P-35 61.09
P-36 41.71 75 P-36 41.71
P-37 68.26 100 P-37
P-38 67.89 18 P-38 67.89
P-39 64.92 100 P-39
P-40 17.85 100 P-40
P-41 45.89 75 P-41 45.89
P-42 48.91 100 P-42
P-43 71.70 100 P-43
P-44 233.85 50 P-44 233.85
P-45 196.92 50 P-45 196.92
P-46 57.00 50 P-46 57.00
P-47 58.59 25 P-47 58.59
P-48 59.29 25 P-48 59.29
P-49 168.67 25 P-49 168.67
P-50 54.43 50 P-50 54.43
P-51 63.29 100 P-51
P-52 63.52 50 P-52 63.52
P-53 60.65 50 P-53 60.65
P-54 60.85 25 P-54 60.85
P-55 59.53 18 P-55 59.53
P-56 71.30 25 P-56 71.30
P-57 119.60 50 P-57 119.60
P-58 72.47 50 P-58 72.47
P-59 36.77 100 P-59
P-60 67.39 100 P-60
P-61 60.53 50 P-61 60.53
P-62 65.93 25 P-62 65.93
P-63 57.51 25 P-63 57.51
P-64 60.91 18 P-64 60.91
P-65 92.94 75 P-65 92.94
P-66 52.11 50 P-66 52.11
P-67 68.48 50 P-67 68.48
P-68 209.64 50 P-68 209.64
P-69 185.96 25 P-69 185.96
P-70 126.15 75 P-70 126.15
P-71 38.15 50 P-71 38.15
P-72 108.20 50 P-72 108.20
P-73 231.55 50 P-73 231.55
P-74 77.82 100 P-74
P-75 57.47 25 P-75 57.47
P-76 56.49 18 P-76 56.49
P-77 54.68 18 P-77 54.68
P-78 48.89 18 P-78 48.89
P-79 48.03 18 P-79 48.03
P-80 44.85 75 P-80 44.85
P-81 30.41 25 P-81 30.41
P-82 48.92 25 P-82 48.92
P-83 131.27 25 P-83 131.27
P-84 89.04 100 P-84
P-85 64.74 100 P-85
P-86 58.57 75 P-86 58.57
P-87 72.29 75 P-87 72.29
P-88 57.79 75 P-88 57.79
P-89 61.43 75 P-89 61.43
P-90 200.31 25 P-90 200.31
P-91 130.26 50 P-91 130.26
P-92 79.47 50 P-92 79.47
P-93 54.43 50 P-93 54.43
P-94 19.69 25 P-94 19.69
P-95 92.90 25 P-95 92.90
TOTAL 6884.76 620.12 1715.61 2501.88 903.90

ADUCCIN 4318.78
=100 mm (4") TERRENO TC RS RF
TC P-1 164.97
142.79 TC P-2 142.79
TC P-3 50.66
TC P-4 43.52
TC P-5 18.39
TC P-6 12.25
TC P-7 107.45
TC P-8 54.62
TC P-9 28.51
RS P-10 70.89
TC P-11 49.43
42.99 TC P-12 42.99
49.49 TC P-13 49.49
TC P-14 72.85
TC P-15 130.70
RF P-16 42.52
TC P-17 40.48
TC P-18 47.41
TC P-19 99.99
28.52 TC P-20 28.52
TC P-21 20.18
56.72 TC P-22 56.72
35.37 TC P-23 35.37
TC P-24 26.68
TC P-25 133.82
TC P-26 25.76
TC P-27 66.62
TC P-28 49.21
TC P-29 61.45
45.83 RF P-30 45.83
25.55 TC P-31 25.55
45.33 TC P-32 45.33
RS P-33 35.23
RS P-34 28.47
TC P-35 61.09
TC P-36 41.71
68.26 TC P-37 68.26
RF P-38 67.89
64.92 RS P-39 64.92
17.85 RS P-40 17.85
TC P-41 45.89
48.91 RS P-42 48.91
71.70 TC P-43 71.70
TC P-44 233.85
TC P-45 196.92
RS P-46 57.00
RS P-47 58.59
RS P-48 59.29
TC P-49 168.67
RS P-50 54.43
63.29 RF P-51 63.29
RF P-52 63.52
RF P-53 60.65
TC P-54 60.85
RS P-55 59.53
TC P-56 71.30
TC P-57 119.60
TC P-58 72.47
36.77 RS P-59 36.77
67.39 RS P-60 67.39
RF P-61 60.53
RF P-62 65.93
RF P-63 57.51
TC P-64 60.91
TC P-65 92.94
TC P-66 52.11
TC P-67 68.48
TC P-68 209.64
TC P-69 185.96
TC P-70 126.15
TC P-71 38.15
TC P-72 108.20
TC P-73 231.55
77.82 RS P-74 77.82
RS P-75 57.47
RS P-76 56.49
RS P-77 54.68
RF P-78 48.89
TC P-79 48.03
TC P-80 44.85
TC P-81 30.41
TC P-82 48.92
TC P-83 131.27
89.04 TC P-84 89.04
64.74 TC P-85 64.74
TC P-86 58.57
TC P-87 72.29
TC P-88 57.79
TC P-89 61.43
TC P-90 200.31
TC P-91 130.26
RS P-92 79.47
RS P-93 54.43
RS P-94 19.69
TC P-95 92.90
1143.26 5248.87 1059.33 576.56

TC 2159.39
RS 1295.63
RF 863.76