ID Task Name Duration Start Finish January February March April May June July August September October

Finish January February March April May June July August September October November December January
1 PRELIMINARIES 223 days? Mon 2/1/16 Tue 12/6/16
2 Re-surveying of lot 1 day? Mon 2/1/16 Mon 2/1/16
3 Design Fee ( Architectural, Structural, Mechanical,
30 days?
Electrical and
MonPlumbing
2/1/16 ) Fri 3/11/16
4 Building and Occupancy Permits 14 days? Mon 3/14/16 Thu 3/31/16
5 Insurance (CARI) and General Liability 5 days Mon 3/7/16 Fri 3/11/16
6 Mobilization 2 days Thu 3/31/16 Fri 4/1/16
7 Clearing, cleaning & hauling of construction debris,
7 days
rubbish & Mon
the likes
4/4/16 Tue 4/12/16
8 Temporary facilities, utilities and security 14 days Mon 4/4/16 Wed 4/20/16
9 Project Management and Supervision 180 days? Thu 3/31/16 Tue 12/6/16
10 Safety / Security Officer on Site 180 days? Thu 3/31/16 Tue 12/6/16
11 Workers off-site barracks and service 180 days? Thu 3/31/16 Tue 12/6/16
12 STRUCTURAL WORKS 100 days? Mon 4/4/16 Thu 8/18/16
13 Earth Works 76 days? Mon 4/11/16 Fri 7/22/16
18 Reinforcement Bars 88 days? Mon 4/4/16 Tue 8/2/16
31 Formworks and scaffolding 79 days? Fri 4/15/16 Tue 8/2/16
44 Concreting Works 78 days? Sat 4/16/16 Tue 8/2/16
56 Steel Works 21 days Mon 6/27/16 Mon 7/25/16
59 Tinsmitry Works 7 days Mon 7/25/16 Tue 8/2/16
61 Water proofing Works 13 days Mon 8/1/16 Wed 8/17/16
64 Civil Works 26 days Thu 7/14/16 Thu 8/18/16
67 ARCHITECTURAL WORKS 85 days? Mon 7/25/16 Fri 11/18/16
68 Masonry Works 32 days Mon 7/25/16 Tue 9/6/16
71 Ceiling Finishes 80 days? Mon 8/1/16 Fri 11/18/16
72 a. 12 mm Ordinary Gypsum ceiling on metal21 framing
days system Mon( 8/1/16
Interior ceiling
Mon 8/29/16
)
73 b. 12 mm ( MR ) Moisture Resistant Gypsum7ceiling
days on metal
Mon 8/1/16
framing systemTue (8/9/16
T&B ceiling )
74 c. 150mm x 12mm thk. T&G wood on metal14 frames
days ( Roof Mon
eaves
8/8/16
) Thu 8/25/16
75 d. Ceiling paint finishes 60 days? Mon 8/29/16 Fri 11/18/16
78 Wall Finishes 80 days? Mon 8/1/16 Fri 11/18/16
79 Exterior Walls 64 days? Tue 8/23/16 Fri 11/18/16
80 a. Exterior wood cladding 30 days Tue 8/23/16 Mon 10/3/16
81 b. Stone cladding 30 days? Tue 8/23/16 Mon 10/3/16
82 c. Exterior wall paint finishes 60 days? Mon 8/29/16 Fri 11/18/16
85 Interior Walls 80 days? Mon 8/1/16 Fri 11/18/16
86 12 mm Moisture Resistant Gypsum drywall21 days
on metalMonstuds8/1/16
system (MonGeneral
8/29/16
interior walls )
87 Travertine Wall Finish 21 days? Tue 8/23/16 Tue 9/20/16
93 300 mm x 300 mm Ceramic tiles 14 days? Wed 9/21/16 Mon 10/10/16
97 Interior wall paint finishes 60 days? Mon 8/29/16 Fri 11/18/16
99 Floor Finishes 42 days? Wed 9/21/16 Thu 11/17/16
100 a. Aggromerate Marble Finish 21 days? Wed 9/21/16 Wed 10/19/16
109 b. Porcelain Floor Tiles 21 days? Wed 9/21/16 Wed 10/19/16
114 c. Natural Stones 14 days? Mon 10/31/16 Thu 11/17/16
118 d. 300 mm x 300 mm Ceramic Floor Tiles 14 days? Wed 9/21/16 Mon 10/10/16
124 f. Wood Parquet ( Narra ) Bona finish 14 days? Mon 10/31/16 Thu 11/17/16
133 g. Wood decking 14 days? Mon 10/31/16 Thu 11/17/16
138 i. Cement Finish 14 days? Wed 9/21/16 Mon 10/10/16
141 Doors 21 days Tue 8/23/16 Tue 9/20/16
155 Hardwares 7 days Mon 9/12/16 Tue 9/20/16
162 Aluminum Doors and Windows 21 days Tue 8/23/16 Tue 9/20/16
165 Iron Works 14 days Mon 9/5/16 Thu 9/22/16
168 Carpentry Works 30 days Wed 9/21/16 Tue 11/1/16
194 MECHANICAL WORKS 99 days Tue 7/5/16 Fri 11/18/16
209 ELECTRICAL WORKS 121 days Mon 4/25/16 Mon 10/10/16
213 SANITARY / PLUMBING WORKS 137 days Mon 4/25/16 Tue 11/1/16
227 SWIMMING POOL WORKS 75 days Mon 5/9/16 Fri 8/19/16
233 CISTERN TANK SYSTEM 75 days Mon 5/9/16 Fri 8/19/16
239 PUNCHLISTING 14 days Thu 11/17/16 Tue 12/6/16

Project: Cohen Bar Chart ( Constructio Task Progress Summary External Tasks Deadline
Date: Wed 1/20/16 Split Milestone Project Summary External Milestone

Cohen Residence