Professional Documents
Culture Documents
2012
8.2)
AW of Initial Investment , I = 1, 000, 000( A / P,5%, 20) - 40, 000( A / F ,5%, 20) = $80, 079.2
AW of B = $220, 000
AW of C = $80, 000
$220, 000
B - C ratio = = 1.374 Ans.
$80, 079.2 + $80, 000
8.3)
I = $400, 000
C ' = $50, 000( P / A,8%,15) = $427,974
B = $85, 000( P / A,8%,15) = $727,557.5
B
BC(8%) =
I +C'
$727,557.5
=
$400, 000 + $427,974
= 0.88 < 1
Design B:
Page | 1
Fundamentals of Engineering Economics, 3rd ed. 2012
I = $300, 000
C ' = $80, 000( P / A,8%,15) = $684, 758
B = $85, 000( P / A,8%,15) = $727,557.5
B
BC(8%) =
I +C'
$727,557.5
=
$300, 000 + $684, 758
= 0.74 < 1
Incremental analysis: Fee collections in the amount of $85,000 will be the same for both
alternatives. Therefore, we will not be able to compute the BC(i ) ratio. If this happens,
we may select the best alternative based on either the least cost ( I + C ') criterion or the
incremental B'C(i ) criterion.
DB - DC '
DB'C(8%) A- B =
DI
0 - ($427,974 - $684, 758)
=
$100, 000
= 2.56 > 1
Select Design A.
Select Design A.
8.4)
Building X:
Page | 2
Fundamentals of Engineering Economics, 3rd ed. 2012
Building Y:
8.5)
Users annual cost = 22 miles $0.25 per mile 400, 000 cars
Sponsors annual cost = $21, 000, 000( A / P,10%, 40) +$140, 000
Option 2-Shortcut:
Page | 3
Fundamentals of Engineering Economics, 3rd ed. 2012
Users annual cost = 10 miles $0.25 per mile 400, 000 cars
Sponsors annual cost = $45, 000, 000( A / P,10%, 40) +$165, 000
8.6)
Proposals Incremental
8.7)
Incremental BC analysis:
Page | 4
Fundamentals of Engineering Economics, 3rd ed. 2012
Design Incremental
Select Design B.
8.8)
Alternative B:
B = ($1, 200, 000 + $350, 000 + $450, 000
+$200, 000)( P / A,10%,50)
= $21,812,592
Alternative C:
Page | 5
Fundamentals of Engineering Economics, 3rd ed. 2012
Select C.
A B C
8.9)
Page | 6
Fundamentals of Engineering Economics, 3rd ed. 2012
P1 versus P2:
11,350 - 14,350
BC(i) 2-1 = = -7.41 < 1
1,835 - 1, 430
Since the ratio is less than one, we prefer P1 over P2. Therefore, P1 becomes the current best
alternative.
P1 versus P3:
Since the ratio is greater than one, we prefer P3 over P1. Therefore, P3 becomes the current
best alternative.
P3 versus P4:
Since the ratio is greater than one, we prefer P4 over P3. With no further projects to
consider, P4 becomes the ultimate choice.
8.10)
Multiple alternatives:
PW of PW of Net B/C
Since the BC ratio for project A1 is less than 1, we eliminate it from our comparison.
Incremental Analysis: ordering (A3, A4, A2)
Page | 7
Fundamentals of Engineering Economics, 3rd ed. 2012
A3 versus A4:
$120 - $70
BC(i ) A 4- A3 =
$73 - $25
= 1.04 > 1
Select A4.
A2 versus A4:
$150 - $120
BC(i) A 2- A 4 =
$110 - $73
= 0.81 < 1
Select A4.
8.11)
(a)
Project A1:
Year CF PV@6% PV
1 $400,00 0.9434
0 $377,360
2 $340,00 0.8900
0 $302,600
3 $300,00 0.8396
0 $256,880
4 $240,00 0.7921
0 $190,104
5 $200,00 0.7473
0 $149,460
6 $150,00 0.7050
0 $105,750
Investment $900,000
NPV $477,154
Page | 8
Fundamentals of Engineering Economics, 3rd ed. 2012
$1,377,154
PI(6%) A1 = = 1.53
$900,000
Project A2:
Year CF PV@6% PV
1 $200,00 0.9434
0 $188,680
2 $300,00 0.8900
0 $267,000
3 $350,00 0.8396
0 $293,860
4 $440,00 0.7921
0 $348,524
5 $400,00 0.7473
0 $298,920
6 $350,00 0.7050
0 $246,750
Investment $1,200,000
NPV $443,734
(b)
(1) Since both profitability indexes are greater than one, we may accept both projects if
we have enough money to undertake. (2) If we could only take one due to a budget limit,
we need to conduct an incremental analysis:
Page | 9
Fundamentals of Engineering Economics, 3rd ed. 2012
8.12)
(a)
Project A1:
Year CF PV@7% PV
1 $100,00 0.935
0 $93,500
2 $100,00 0.873
0 $87,300
3 $100,00 0.816
0 $81,600
4 $240,00 0.763
0 $183,120
5 $200,00 0.713
0 $142,600
6 $180,00 0.666
0 $119,880
7 $180,00 0.623
0 $112,140
8 $180,00 0.582
0 $104,760
9 $180,00 0.544
0 $97,920
10 $180,00 0.508
0 $91,440
Investment 750,000
NPV 364,260
Page | 10
Fundamentals of Engineering Economics, 3rd ed. 2012
1,114, 260
PI(7%) A1 = = 1.49
750, 000
Project A2:
Year CF PV@7% PV
1 $200,00 0.935
0 $187,000
2 $200,00 0.873
0 $174,600
3 $200,00 0.816
0 $163,200
4 $300,00 0.763
0 $228,900
5 $300,00 0.713
0 $213,900
6 $250,00 0.666
0 $166,500
7 $250,00 0.623
0 $155,750
8 $150,00 0.582
0 $87,300
9 $100,00 0.544
0 $54,400
Investment 1,000,00
0
NPV 456,950
1, 456,950
PI(7%) A2 = = 1.46
1, 000, 000
Page | 11
Fundamentals of Engineering Economics, 3rd ed. 2012
(b)
8.13)
(a) The operating cost of the current system in terms of $/ton of solid waste:
= 109,500 tons/year
= $18.67 ton
(b) The economics of each solid-waste disposal alternative in terms of $/ton of solid waste:
Site 1:
Page | 12
Fundamentals of Engineering Economics, 3rd ed. 2012
Site 2:
AEC(8%) 2 = $4,384, 000( A / P,8%, 20)
+$480, 000( P / A1 ,10%,8%, 20)( A / P,8%, 20)
-($14, 700 + $99,300)
= $1, 417, 042.61
Site 3:
AEC(8%)3 = $4, 764, 000( A / P,8%, 20)
+$414, 000( P / A1 ,10%,8%, 20)( A / P,8%, 20)
-($15,300 + $103,500)
= $1,301,871.57
Site 4:
Page | 13
Fundamentals of Engineering Economics, 3rd ed. 2012
Present
Site1 Site2 Site3 Site4
System
Reduction in C
over the present $12,489.80 $9,430.53 $10,893.66 $11,026.67
system
Page | 14
Fundamentals of Engineering Economics, 3rd ed. 2012
8.14)
Once these values are quantified, we compute the following for each option:
Then, identify the option(s) with Users net benefits exceeding the sponsors net cost.
Select the option with the largest differential net benefits. If the initial analysis based on
the primary benefits and costs does not lead to any clear-cut choice, the analysis may be
broadened to include the secondary benefits such as the regional economic impact
studies.
Page | 15