Professional Documents
Culture Documents
Abstract Share of Non-Conventional Renewable Energy reduction, avoided cost of energy production, additional
(NCRE), small hydro, wind, solar, bio-mass etc based electricity generation capacity, distribution and capacity investment
generation in Sri Lanka at present is 10% of the total annual deferral, green pricing benefits, etc. DG causes an impact on
generation. The Government of Sri Lanka has declared a losses in the power system due to its close proximity to the
national target of 20% from NCRE by 2020[1]. Most of NCRE load centers. The main difference is that DG units cause impact
power plants have been connected to the distribution network on both active and reactive power, while capacitor banks only
and are termed as Distributed Generators (DGs). With the have impact in the reactive power component.
increase of share of DGs, it affects system reliability, power
quality and economic operation of the distribution network. Due to the geo-climatic conditions, Sri Lanka is blessed
with several forms of energy sources such as hydro power,
This paper focuses on the impact of economic operation of solar, wind and biomass. These power generating projects are
transmission and distribution network due to distributed located and connected to the power system as distributed
generation in Sri Lankan power system. Network simulation generating units. The capacities of each DG technology
studies have been carried out for transmission network and for connected to the Sri Lankan power system are summarized as
four grid substations to which many DGs have been connected. shown in Table 1. [4], [5].
The analysis revealed that transmission network losses have
reduced with increase penetration of DGs to the system while TABLE I. SUMMARY OF DGS CONNECTED TO SRI LANKA POWER SYSTEM
distribution network losses are dependent on the amount of DG (AS AT JANUARY 2015)
capacities connected to the distribution network. However, there
is a reduction of network losses when overall network is Added capacity to
Technology No. of Plants
the System (MW)
considered thereby giving financial benefit from DGs added to
Small Hydro 142 293.27
the system.
Wind 15 123.85
Solar 4 1.38
KeywordsDistributed Generation; Transmission loss;
Biomass 6 23.50
Distribution loss; Non-conventional Renewable Energy
Total 167 442.00
TABLE II. TRANSMISSION LOSS FIGURES CALCULATED USING PSSE TABLE IV. SUMMARY OF ENERGY LOSS REDUCTION IN TRANSMISSION
SOFTWARE NETWORK
From (1), Loss Load Factor of the system = 0.57 Night Peak Load
Added Capacity
Grid Substation of DGs to the
Then, of the Grid (MW)
system (MW)
Energy Loss = Peak Power Loss x Time x LLF (3) Badulla 46.7 14.6
55
A. Loss Calculation
1800
The calculated power loss figures using SynerGEE software at 1600
Ukuwela, Badulla, Kiribathkumbura and Rathnapura grid 1400
substations are graphically shown in Fig.1, Fig.2, Fig.3 and 1200
Loss (kW)
1000
Fig.4 respectively. 800
600
400
200
3,000
0
2,500
2,000
Loss (kW)
500
- Fig.4.Power Loss Vs DG % added to the system in Rathnapura GS
90%
0%
10%
20%
30%
40%
50%
60%
70%
80%
100%
It is noted that the same pattern of losses while increasing
% of DG added to the System
the DG% added to the System can be seen in Ukuwela, Badulla
Night Peak Day Peak Off Peak and Kiribathkumbura. The losses have gradually decreased and
then increased when the DG capacity is gradually added to the
Fig.1.Power Loss Vs DG % added to the system in Ukuwela GS system.
However, the distribution losses related to Rathnapura GS
show a totally different behavior from others. As shown in Fig.
3,500
4, when the DGs are gradually added to the system, the power
3,000 loss gradually increases with the added capacity of DGs. When
2,500 the DG capacity added to the system is higher than the peak
Loss (kW)
2,000 demand of the grid substation feeders, the balance or the excess
1,500
power generation should be transferred to the transmission
network. For that the flow from generation point should come
1,000
to the grid substation through a long distance. Thus, the loss is
500
higher than the other cases. However, for this case,
65%
0%
5%
10%
15%
20%
25%
30%
35%
40%
45%
50%
55%
60%
70%
75%
80%
85%
90%
95%
100%
1,500
1,000
Where, e is the load factor of the system.
500
Load factor of Ukuwela, Badulla and Kiribathkumbura GSs is
-
0.555 [8] while it is 0.450 for Rathnapura GS [9].
15%
0%
5%
10%
20%
25%
30%
35%
40%
45%
50%
55%
60%
65%
70%
75%
80%
85%
90%
95%
100%
% of DG added to the system The energy loss = Peak Power Loss* UTL
Night Peak Day Peak Off Peak Using equation (4)
UTLUkuwela = UTLBadulla= UTLKiribathkumbura = 2,952 hrs / year
Fig.3.Power Loss Vs DG % added to the system in Kiribathkumbura GS
56
TABLE VI. CALCULATED ANNUAL ENERGY LOSS OF SELECTED FOUR IV. ECONOMIC ANALYSIS OF LOSS REDUCTION
GRID SUBSTATIONS
DG
A. Cost Saving due to Transmission Loss Reduction
Annual Energy Loss (GWh)
% Kiribathku Cost saving can be calculated as a combination of Energy
Ukuwela Badula Rathnapura
mbura Cost saving and Capacity Cost saving. Marginal generation
00 7.861 10.031 6.055 0.944 cost is used for the calculation of Energy Cost saving. Marginal
05 7.649 9.688 5.922 0.859 generation cost is the unit generation cost of the next power
plant to be dispatched according to the merit order dispatch of
10 7.454 9.370 5.807 0.796 CEB.
15 7.277 9.077 5.683 0.755
Weighted average cost of the marginal generation costs has
20 7.117 8.812 5.576 0.732 been calculated for the costing of transmission energy loss
25 6.973 8.567 5.479 0.732 calculation as 23.0 LKR per kWh.
30 6.846 8.342 5.390 0.752 Energy Cost Saving = Energy Loss Reduction x Marginal
35 6.731 8.142 5.308 0.792 Generation Cost (5)
40 6.633 7.959 5.237 0.851 For the calculation of Capacity Cost saving, average capacity
45 6.548 7.796 5.172 0.929
charge of Independent Power Producers (IPPs) for year 2013
was considered and the same was found to be 2.95 LKR per
50 6.477 7.655 5.116 1.028 kWh.
55 6.421 7.528 5.069 1.143
Capacity Cost Saving = Power Loss Reduction x Average
60 6.376 7.421 5.027 1.277 Capacity cost of IPP (6)
65 6.344 7.330 4.995 1.427 Using the Equations (5), (6) and Table IV, cost saving in
70 6.326 7.256 4.971 1.595 transmission network due to the presence of DGs are calculated
75 6.320 7.197 4.953 1.766 and summarized in TABLE VII.
80 \6.323 7.156 4.942 1.970 TABLE VII. COST SAVING IN TRANSMISSION NETWORK DUE TO DGS
85 6.338 7.126 4.939 2.192 Annual Energy Annual Capacity
90 6.365 7.111 4.945 2.430 Cost Saving due to Cost Saving due to
Scenario
DGs DGs
95 6.403 7.111 4.953 2.683 (Million LKR) (Million LKR)
100 6.453 7.126 4.974 2.952 With 40% DG 598.9 76.8
8
Ce = Cost of Energy = 24.66 LKR/kWh
Cc = Capacity Cost = 18,679 LKR/kW/Year
6
Total cost of losses = Capacity Cost + Energy Cost
4
i.e.
2
Annual Cost of losses = Cc x Ploss-pk + Ce x Eloss (7)
0
0 10 20 30 40 50 60 70 80 90 100 According to Equation (7), the summary of cost saving in
% of DG added to the system distribution network due to DGs is shown in Table VIII.
Ukuwela Badula
Kiribathkumbura Rathnapura
57
TABLE VIII. COST SAVING IN DISTRIBUTION NETWORK DUE TO DGS TABLE IX. SUMMARY OF TRANSMISSION AND DISTRIBUTION LOSS
REDUCTION
Annual
Annual Annual Annual
Cost
DG Cost of Cost of Cost Saving Total
Saving in
% Energy Capacity in Capacity Loss
Energy Transmission Distribution
Loss (LKR Loss (LKR Cost (LKR Reduct
Cost (LKR Loss Reduction Loss Reduction
Million) Million) MIllion) ion per
MIllion) Scenario (LKR Million) (LKR Million)
year
00 613.81 160.09 0.00 00.0 (LKR
Million
05 594.75 154.98 19.06 5.11 Energ Capacit Energ Capacit )
y Cost y Cost y Cost y Cost
Loss Reduction
10 577.71 150.42 36.10 9.67 599 77 104 27 807
with 40% Loading
Loss Reduction
15 562.05 146.30 51.76 13.79 1,924 247 84 16 2,271
with full DG
70 496.85 131.89 116.96 28.20 [1] Democratic Socialist Republic of Sri Lanka, "The Gazette of the
Democratic Socialist Republic of Sri Lanka, EXTRAORDINARY, No.
75 499.02 132.92 114.79 27.17 1553/10-June 10", 2008.
[2] C. L.T.Borges and D. M. Falcao, "Impact of Distributed Generation
80 502.84 134.45 110.97 25.64 Allocation and Sizing on Reliability, Losses and Voltage Profile", in
IEEE Power Tech Conference, Bologna, Italy, 2003.
85 507.87 136.35 105.94 23.74 [3] M.Begovic, A. Pregelj and A. Rohatgi, "Impact of Renewable
Distributed Generation on Power Systems", in 34th Hawaii
International Conference on System Sciences, 2001.
90 514.19 138.64 99.62 21.45
[4] ]":: SRI LANKA SUSTAINABLE ENERGY AUTHORITY ::",
Energy.gov.lk, 2016. [Online]. Available:
95 521.56 141.23 92.25 18.86
http://www.energy.gov.lk/sub_pgs/energy_renewable.html. [Accessed:
12- Aug- 2015].
100 530.31 144.21 83.50 15.88
[5] ]"Do Business with Us | CEB", Ceb.lk, 2016. [Online]. Available:
http://www.ceb.lk/do-business-with-us/. [Accessed: 12- Aug- 2015].
Cost saving of both transmission and distribution network due [6] Transmission Planning Division, Ceylon Electricity Board Sri Lanka,
"Long Term Transmission Development Plan - 2013 -2022", 2013.
to DGs added to the system can be summarized in Table IX.
[7] Ceylon Electricity Board, "Statistical Digest 2013", 2014.
[8] Distribution Region 2, Ceylon Electricity Board Sri Lanka, "Medium
Voltage Distribution System Development Plan - 2013 2022", 2013.
[9] Distribution Region 3, Ceylon Electricity Board Sri Lanka, "Medium
Voltage Distribution Development Plan - 2012 2021", 2012.
58