How to Calculate Critical Path, Float, Early Start & Late Start,

and Early Finish & Late Finish

This is a part-post from Developing Project Schedule project management activity post. You will learn
how to calculate critical path, float/slack, early & late starts, and early & late finishes of a network path in
this article.
For easier understanding this post is divided into four parts that can be navigable at the bottom of each
part.

I suggest you get yourself a cup of your favorite beverage (I was going to say Coffee), this one is going to

be a long ride.

As we saw in Developing Project Schedule project management activity, Critical path is made up of
series of activities from beginning to the end, where each activity has a dependency over previous activity
in such a way that delay in any one activity causes delay in all subsequent activities, causing the project
to slip.
Click here to get my PMP exam brain-dump for free.
In other words, critical path is the longest path in your projects schedule network diagram, and is
the SHORTEST possible duration for the project.

How to Calculate Critical Path


Let us take a simpler example than Johns home construction example we saw in previous lessons. This
project involves assembling a train set (refer to the picture above).

Calculating Critical Path is a simple 4-step process.

Step 1: Find Activities


Activities for this project are as below (output from Define Activities process)

A. Assemble two-tier bridge B. Join winding tracks C. Assemble and add train station D. Place standalone
items around E. Assemble and add construction site F. Join train engine and bogies G. Place the train on
the track H. Start the engine and let it chug!

Step 2: Build Schedule Network Diagram


Sequence activities and build schedule network diagram (output from Sequence Activities process) . This
is how it looks, with individual activity duration in minutes
Figure 2: Assemble train set schedule network diagram

Step 3: Find all Possible Paths


Find all possible paths through the diagram, there are 3 in our case

A -> B -> F -> G -> H

A -> B -> C -> D -> G -> H

A -> B -> C -> E -> G -> H

Step 4: Calculate Duration for Each Path


Let us see the duration for each of these paths

A -> B -> F -> G -> H > 10+20+4+2+2 = 38 minutes

A -> B -> C -> D -> G -> H > 10+20+5+10+2+2 = 49 minutes


A -> B -> C -> E -> G -> H > 10+20+5+2+2+2= 41 minutes

The network path with longest total duration is the critical path!
Critical path is the shortest duration required to complete the project successfully.

In our example this is the second path: A -> B -> C -> D -> G -> H, which comes to 49 minutes.
Figure 3: Assemble train set Critical Path

Note that sum of durations of all activities on critical path comes 49 minutes, and sum of duration of ALL
activities on the project is much longer. If managed well, the whole project can be completed within the
critical paths duration.

Calculating Float for Activities


Now, any schedule will have some flexibility, or elbow room, called Float.

Float of an activity is the duration that it can slip by without delaying the subsequent task or completion of
the project, or violating schedule constraint.
It is the elbow room that a task has. Amount of time an activity on a network path can slip without causing
a delay in early start of any successor activity and without violating schedule constraint is called Free
Float.
Total amount of time an activity can slip from its early start date without causing delay to project
completion or violating schedule constraint is called Total Float.
Click here to get my PMP exam brain-dump for free.
The simple 3-step process to calculate float of ALL activities in your schedule network diagram

Step 1: Arrange the paths in decreasing order of their total duration, starting
with Critical path
For the above example it would be as below, the first being critical path itself

A -> B -> C -> D -> G -> H > 10+20+5+10+2+2 = 49


A -> B -> C -> E -> G -> H > 10+20+5+2+2+2= 41

A -> B -> F -> G -> H > 10+20+4+2+2 = 38

The float for each activity on the critical path is zero.

Step 2: Find float for activities on the second longest path


This would be the difference between total duration of critical path and next longest path. In our example
this would be 49-41= 8 minutes. Assign this to ALL activities on this path, which do not already have a
float. In this example that would be only activity.

Figure 4: Float for second path

Step 3: Do the same to all remaining paths, for unassigned activities


Now calculate difference between critical path and third paths total duration, and assign this to activities
on the third path excluding any which already have a float assigned in previous step. In our example
this would be 49-38 = 11 minutes.

Do this step for rest of the identified paths and you have float for all activities.
Figure 5: Float for third path

..

Early Start, Early Finish and Late Start, Late Finish


Why do we need to know the early and late number for an activity? By knowing how early an activity can
start and how late it can finish gives you the flexibility to juggle resources between other activities that can
potentially impact critical path, and hence the project completion date. The shorter a network path is in
relation to critical path, more schedule flexibility you will have on activities on that path.

Early start and Early finish


Indicates the earliest time an activity on a network path can start and earliest it can finish. If you decide to
start an activity on its early start (assuming previous activities on that network path are completed on their
early finishes), that activity can finish on its early finish (if it does not slip). And when the last activity on a
network path is completed by its early finish, you have all the resources of those activities at your disposal
to deploy on other high risk activities.
Calculating Early start and finish (take a FORWARD pass through network
path)
Remember!: Always start with the critical path and then go with paths with descending order of their total
duration.

Step 1: Early start of first activity on critical path is always 1. Write it at the top left corner of that activity
box (see the image below).
Step 2: Add its activity duration to this early start number and reduce it by one. Write the resulting number
on the top right corner of activity box.
Step 3: Take the subsequent number of this early finish and write as early start for next activity. Continue
this till you reach the end of critical path.
Step 4: Select the network path with second highest total duration, and calculate early starts and finishes.
If you find an activity with early start and finish already written do not overwrite them. Do the same for
remaining network paths.
Note: If you find two activities converging on a single activity (say, activity-G), it indicates that the activity-
G will start only AFTER converging activities finish. So, you will take the largest value amongst the early
finish of these two activities and write subsequent number as early start of the activity-G.
Why add duration to early start and then reduce by one, to get early finish? Because the duration of an
activity includes both start and finish days (or any other unit of measurement you use). So, if first activity
duration is 5 days, and early start is 1 then early finish is 1+6-1 = 6. That is 6 days including the start and
finish days.

Figure 6: Early start and finish

As you noticed, early start number is written at the top left corner of activity box, andearly finish on
the top right corner. The critical path with early start and early finish days will look like this
Figure 7: Early start and early finish for critical path

Late start and Late finish


Indicates the latest time an activity on a network path can start and latest it can finish. Knowing how late
the last activity on the network path can start and still finish within the time to not impact critical path, will
let you decide how much of flexibility you want to exercise on its schedule. However, once the last activity
on the network path starts on its late start day it should not slip, else it will impact project completion date.

Calculating Late start and finish (take BACKWARD pass through network
path)
Remember!: Start with the critical path, beginning at the last activitys late finish.

Step 1: Late finish of last activity on the critical path is same as its early finish. Write this number at the
bottom right corner.
Step 2: Calculate late start of this activity as the late finish minus activity duration plus 1. This calculation
has the same reason start and finish are both included in the duration. Write this number at the bottom
left corner.
Step 3: Write this late start of the activity minus 1, as the late finish of previous activity. Continue this way
all way till you reach the late start of first activity on the critical path.
Step 4: Select the network path with second highest total duration, and write late starts and finishes
beginning at the last activity of that path. Do the same for remaining network paths.
Notes:
If you find two activities converging on a single activity (say, activity-C), take the smallest value
amongst the late start of these activities and write previous number as late finish of the activity-C.
If you find an activity with late start and finish already written do not overwrite them.

Figure 8: Late start and Late finish

Late start number is written at the bottom left corner of activity box, and late finish on the bottom
right corner. The critical path of our example with late starts and late finishes will look like this

Figure 9: Late start, finish for the critical path


Let us go back to our example and calculate early/late start/finish for the entire schedule network
diagram.

Figure 10: Early start, finish and Late start, finish for the entire schedule network diagram

We looked at few concepts in this post

Critical path
Critical path in a network schedule diagram is the network path with longest total duration
Critical path sure is the longest network path, but this indicates Shortest Duration of the project
which means any activity slipping on this path will cause a delay in project completion
It is calculated by simply adding up duration of all activities on each network path and finding the
one with largest number
Float
Float (also known as Slack) of an activity is the duration that it can slip without delaying the next
activity or the project end date
Float for every activity on critical path is zero
Float for every activity on a network path is the difference between its total duration and that of
critical path (excluding the activities that have float calculated already)
Float is calculated for network paths in the descending order of their total duration, starting with
critical path
Calculating Early and Late Starts and Finishes
Early start and finish are calculated by forward pass through the network path, and Late start and
finish are calculated by backward pass
Both are calculated first for the critical path
Both are calculated for remaining network paths in the descending order of their total duration
During calculation if you come across any activity with duration already calculated, do not
overwrite
Heres a video explaining nicely the concept of Critical path, Float and network diagram using Forward
and Backward pass.
Note that he uses the convention of starting on day 0 and so NOT adding a day to start next activity. On
the contrary, I use the convention of starting an activity on day 1 and adding 1 to start next activity on
subsequent day, as this feels natural for our understanding.
You can use any convention you feel comfortable with, just know that the question on exam might present
scenario using any of these conventions so knowing both will help you answer them easily.