1.0 SCOPE
This Standard covers the procedures and criteria for field testing of newly installed power
cables of voltage 110kV, 115kV, 132kV, 230kV or 380kV in the system of Transmission
Buisness Unit (TBU) of Saudi Electricity Company (SEC), Kingdom of Saudi Arabia.
This does not include the maintenance testing of the power cable. This standard shall be
read in conjunction with the cable testing portion of the standard TCS-P-105.
2.0 GENERAL
2.1 The field testing of power cable along with its accessories shall ensure the capability
of the cable to fulfill Companys specific design requirements prior to normal
service and after installation. This is also to detect the shipping or installation
damages and gross cable defects or errors in workmanship in splices and
terminations.
2.2 The tests results shall be documented using the SEC Cable Acceptance Test Report
Forms, attached as Appendix I to this standard. For miscellaneous electrical tests per
clause no. 4.8, results shall be furnished by the Contractor separately for SECs
review and record.
2.4 When there is a conflict between the testing requirements of this Standard and those
of the cable manufacturer, SEC shall be the sole judge for deciding the test
procedures and sequence.
2.5 The electrical test requirements for XLPE and LPOF cables are basically the same.
For LPOF cables only DC High Voltage testing per clause 4.4 and additional testing
of oil pressure integrity, oil flow and oil impregnation coefficient shall be performed.
Instead of DC High Voltage testing, AC High Voltage testing shall be performed on
XLPE cables per clause 4.5 by the Contractor.
2.6 In case of direct buried installation, after the cable is completely pulled, cable tests
shall be performed after applying a minimum of 150 mm backfill material cover over
the cables.
2.7 All test equipments shall be calibrated properly to determine the accuracy of the
readings and their calibration certificates shall be furnished for SECs review.
3.0 SAFETY
3.1 Safety precautions/practices shall include, but are not limited to, the requirements of
the SEC Accident Prevention Manual.
3.2 Before starting cable testing operation is started, conductor under test and all cable
accessories shall be checked as being de-energized with approved method by using a
reliable voltage measuring indicator. The voltage measuring indicator should be
tested for proper operation with an independent voltage source prior to testing
operation.
3.3 While the voltage measuring indicator is still in contact with each conductor and it is
showing the conductors are de-energized, a hot-line grounded device shall be
continuously connected to all conductors under examination, except while test
equipment is being used or system is ready for re-energization.
3.4 Proper testing methods and personnel safety shall be assured before conducting the
tests. SEC Representative shall check all necessary clearances/work permits and
safety measures of the tests and shall report for any missing or insufficient safety
measures. In any case, no test shall proceed until the SEC Representative have
determined that it is safe to do so.
3.5 The test site shall have sufficient protective barriers and warning signs to conduct
specified tests safely.
All cable section ends under test shall be guarded from accidental contact. Also, the
minimum clearance from all ends or elements not being subject to test shall be 25.4
mm per 10 kV of test voltage.
3.6 All adjacent conductors in a cable circuit, not being tested, should be de-energized
and left grounded during the testing of other conductors.
To ensure the continuity and phasing of the cable conductor from terminal to
terminal, the cable conductor shall be tested using a minimum of 1000 Vdc per
Figure 08-1.
Prior to performing the high voltage test on the cable and after high voltage test,
cable insulation test by megohmmeter at 5000 Vdc shall be performed per Figure 08-
2. The test voltage shall be applied for one (1) minute between the cable conductor
and metallic shield for each cable with adjacent cables conductors and metallic
shields grounded.
The minimum insulation resistance of conductor insulation for new cables shall be
determined by the following equation:
D
R= (Eq. 08-1)
2l x loge
d
TCSP10408R0/AAG Date of Approval: December 16, 2007 PAGE NO 5 OF 24
TRANSMISSION CONSTRUCTION STANDARDS TCS-P-104.08, Rev. 0
4.3.1 Prior to performing the high voltage test on the cable, a radar test shall be
performed on each individual cable, from termination to termination with
the adjacent terminations and metallic sheaths grounded. The radar
instrument shall be suitable to give accurate results in wet and highly
conductive soil also.
4.3.2 The purpose of this test is to provide a circuit profile for each cable. This
profile will be used as a reference to locate any abnormality or any future
cable failures.
4.3.3 The radar test data shall be in the form of a calibrated strip chart printout
showing pulses for the near and far end terminals, all splices, cable sheath
grounding points and the distances between these components.
The high voltage DC test shall be applied to each individual cable phase of a 3-phase
circuit. All cable conductors and metallic shields not being tested shall be grounded.
Maximum high voltage DC test voltages are listed in Table 08-1. The test
connections shall be similar to that shown in Figure 08-2 a), b) and c).
4.4.1 The initially applied voltage shall not exceed 1.8 times the rated AC phase-
to-phase voltage of the cable. After that, the rate of increase of the test
voltages shall be approximately uniform and shall not be more than the
maximum test voltage in 10 seconds nor less than the maximum test voltage
in 60 seconds.
4.4.2 The maximum test voltage shall be maintained for 15 minutes. Leakage
current magnitude shall be recorded at 2 minutes and 15 minutes after the
maximum test voltage has been reached. No breakdown of the insulation
shall occur.
4.4.3 The high voltage DC test set shall have leakage current indicators having
resolution of 0.1A on the lowest current range. When 65% test voltage of
Table 08-1 is applied and an abnormally high leakage current (greater than
caculated by below equation) is noted; the test shall be discontinued. The
cable splices shall be checked. HV DC test shall be repeated to determine
the final acceptance or rejection of the cable.
E
IL = x10-3 (Eq. 08-2)
R
4.4.4 After the completion of the test period, the test voltage regulator dial should
be set to zero and the cable shall be discharged through the test set. For
cable length exceeding 300m a resistor of resistance not less than
10,000/kV of test voltage shall be connected between the test circuit and
ground through an insulating hook stick and a flexible grounding conductor,
not smaller than 35mm2 copper, to reduce the discharge time. The resistor
shall be designed to withstand the full test voltage without flashover and to
handle the discharge energy without overheating.
The hook stick shall be applied to the top metal part of the HV test set high
voltage output bushing after the test voltage has dropped to less than
10kVdc and shall remain connected until the conductor is completely
discharged. A retest should not be started until the cable has been grounded
for a period of at least four times the duration of the previous test.
The high voltage AC test at 20-300Hz frequency shall be applied through frequency-
tuned series resonant test set between the conductor and the metallic sheath of each
individual XLPE cable phase of a 3-phase circuit. The test voltage shall be of pure
sinusoidal-wave shape. The test voltage shall be per clause 4.5.1 or 4.5.2. The
criteria for selecting the test voltage shall be according to IEC 60840 or IEC 62067.
All cable conductors and metallic shields not being tested shall be grounded. The test
connections shall be similar to that shown in Figure 08-2 a), b) and c). No
breakdown of the insulation shall occur.
4.5.1 The maximum phase-to-phase voltage of the system shall be maintained line
to ground for 60 minutes.
AC Test set shall have adequate volt-ampere capacity to supply the required
cable charging current. The kVA capacity of the test set shall be determined
by the following:
Where,
C = cable capacitance, in microfarads per kilometer (F/km);
f = supply frequency, in hertz (Hz);
E = test voltage, in kV.
At resonance condition, the test current (I) and the test power (P) shall be
determined by the following:
C
I = Ex , in A
L
C
P = E2x , in KVA
L
Where,
L = HV Reactor Fixed Inductance (of the test set) in Henry(H).
Partial Discharge Test shall be applied on all joints and sealing ends while
conducting/after completion of HV AC Test.
Prior to 10kV DC jacket test, it is necessary to carry out shield insulation resistance
test. This shall be measured by 1000V mega-ohm meter. Each sheath section has
to be measured. If the insulation reading is found abnormally low, further physical
inspection on sheath connections and the accessories is required.
For relay setting determination, the cable zero sequence (Z0) and positive/negative
sequence (Z1/Z2) impedances shall be measured and recorded per Figure 08-3 during
the cable commissioning stage. For multiple cable circuits, mutual positive/negative
sequence (Zm1/Zm2) and zero sequence mutual (Zm0) impedances are also to be
measured and recorded per Figure 08-4.
4.9.4 Checking integrity of Cross Bonded Sheath for all cross bonded circuits.
The oil used in the cable pressurization system and reservoirs shall meet the
requirements of 54-TMSS-2.
5.2.1 After each cable section is installed but before the joints or terminations are
made, the oil pressure shall be raised so that the minimum pressure at any
2
point is 7 kg/cm . The cables shall be left at this pressure for 6 hours. No
drop in pressure shall occur.
5.2.2 After laying, jointing and terminating, the complete oil system of each phase
shall be hydraulically checked by raising the oil pressure in the system to a
2
value of 7 kg/cm at the highest point and leaving off the system for 24
hours. Any drop in hydraulic pressure not accounted for by temperature
change at the terminals shall be presumed to be an oil leak which must be
located and repaired by the Contractor.
After laying and jointing, each oil section shall be subjected to an oil-flow test per
Figure 08-5 to ensure that no abnormal obstruction is present in the cable oil duct or
joints. First with the valve closed oil pressure in the cable is taken from the pressure
gauge. Then the valve is opened and after 30 sec. the oil pressure and temperature
reading is taken. A measured quantity of oil in cubic centimeter shall be drawn off
from the oil section during this time and the resultant difference in oil pressure (dP)
2
in g/cm shall be noted. The rate of oil flow shall be calculated as follows:
dP (Eq. 08-4)
Q=
KL
5.4.1 After laying and jointing, each oil section shall be tested for efficiency of
impregnation by an impregnation test.
5.4.2 With oil feed turned off, measure the oil pressure and a measured quantity
of oil (V1) in cubic centimeter shall be drawn off from the oil section and
the resultant drop in pressure (dP) in Kg/cm2 shall be noted. The
impregnation coefficient (K1) shall be calculated as follows:
V1
K1 = (Eq. 08-5)
dP V
(Sheet 1 of 9 )
Project Title
Contract Number
Circuit Designation
Cable Type
Circuit Length(km)
Operating Voltage(kV):
2
Conductor Size(mm ):
Conductor Material
Number of Cables per Phase
Laying Formation(flat or trefoil)
Laying Condition
(direct buried or duct buried or in thurstboring)
Insulation material
Metallic sheath material:
Metallic sheath size(mm2)
Jacket material
Date of cable manufacture
Date of cable installed
Cable Manufacturer
Date of splice manufacture
Date of splice installed
Splice Manufacturer
Splice Type(heat-shrunk, pre-mould, compound
etc.)
Date of termination manufacture
Date of termination installed
Termination Manufacturer
Termination Type
(outdoor or indoor and GIS/XLPE, GIS/LPOF,
Air/XLPE, Air/LPOF etc.)
TEST INSTRUMENT
USED
MAKE/MODEL
RANGE AND
ACCURACY
CALIBRATION
VALID UP TO
SERIAL NO.
HIGH VOLTAGE DC TEST FOR LPOF CABLES: [Refer to Figure 08-2 a), b), c)]
HIGH VOLTAGE AC TEST FOR XLPE CABLES: [Refer to Clause 4.5 of TCS-P-104.08]
OIL PRESSURE INTEGRITY TEST FOR LPOF CABLE: (Refer to clause 5.2 of TCS-P-104.08)
TEST CONDITION CABLE SECTION PHASE MINIMUM OIL TEST DURATION REMARKS
NO. PRESSURE (Hrs.)
(Kg/cm2)
TEST ON SINGLE A 6
CABLE SECTIONS ON
COMPLETION OF B 6
BLINDING WORKS
BUT
PRIOR TO JOINTING C 6
AND TERMINATING
TESTS AFTER A 24
COMPLETION OF
LAYING,
JOINTING AND B 24
TERMINATING OF
EACH PHASE C 24
TEST INSTRUMENT USED
MAKE/MODEL
RANGE AND ACCURACY
CALIBRATION VALID UP TO
SERIAL NO.
PHASE A B C
Cable Length,L(m)
Oil Temperature(C)
CABLE
SECTION
NO.
Oil Pressure with valve closed(g/cm2)
Oil Pressure after 30 sec.(g/cm2)
dP(g/cm2)
Rate of oil flow,Q(cm3/sec.)
K(g.sec./cm6)
Oil Pressure with valve closed(g/cm2)
Oil Pressure after 30 sec.(g/cm2)
dP(g/cm2)
Rate of oil flow,Q(cm3/sec.)
K(g.sec./cm6)
Oil Pressure with valve closed(g/cm2)
Oil Pressure after 30 sec.(g/cm2)
dP(g/cm2)
Rate of oil flow,Q(cm3/sec.)
K(g.sec./cm6)
Oil Pressure with valve closed(g/cm2)
Oil Pressure after 30 sec.(g/cm2)
dP(g/cm2)
Rate of oil flow,Q(cm3/sec.)
K(g.sec./cm6)
TEST INSTRUMENT
USED
MAKE/MODEL
RANGE AND
ACCURACY
CALIBRATION
VALID UP TO
SERIAL NO.
PHASE A B C
Cable Length,L(m)
Oil Temperature(C)
CABLE
SECTION
NO.
Oil Pressure with oil feed turned off(Kg/cm2)
Oil Pressure after sampling(Kg/cm2)
dP(Kg/cm2)
Volume of oil withdrawn,V1(cm3)
Volume of oil in the cable section,V(cm3)
Impregnation coefficient, K1 in cm2 /Kg
Oil Pressure with oil feed turned off(Kg/cm2)
Oil Pressure after sampling(Kg/cm2)
dP(Kg/cm2)
Volume of oil withdrawn,V1(cm3)
Volume of oil in the cable section,V(cm3)
Impregnation coefficient, K1 in cm2 /Kg
Oil Pressure with oil feed turned off(Kg/cm2)
Oil Pressure after sampling(Kg/cm2)
dP(Kg/cm2)
Volume of oil withdrawn,V1(cm3)
Volume of oil in the cable section,V(cm3)
Impregnation coefficient, K1 in cm2 /Kg
TEST INSTRUMENT
USED
MAKE/MODEL
RANGE AND
ACCURACY
CALIBRATION
VALID UP TO
SERIAL NO.
WITNESSED BY:
SECs CONTRACTORs
Representative: Representative: