You are on page 1of 20

g

GER-3954B

GE Power Systems

Generator In-Situ
Inspections

Dean T. Roney
Ronald J. Zawoyski
GE Power Systems
Schenectady, NY
Generator In-Situ Inspections

Contents

Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
In-Situ Inspection Supports Condition-Based Maintenance . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Equipment Condition Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
In-Situ Inspection A Critical Part of Generator Maintenance Cost Reduction . . . . . . . . . . . . 1
In-Situ Inspection Technologies . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
MAGIC Visual Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3
Stator Wedge Tightness Assessment . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Electromagnetic Core Imperfection Detection (EL-CID). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
Stator Clearance Measurement . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Remote Access Camera (RAC) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Remote Capacitance Probe . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
Retaining Ring NDE Scanner . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Other Testing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Qualification Efforts . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Changing an Industry Mindset . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Qualification Testing. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 10
Qualification Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
Traditional vs. In-Situ Cost Analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 11
GE Position On In-Situ Inspection . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Conclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
List of Figures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 15
List of Tables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16

GE Power Systems GER-3954B (04/03)


i
Generator In-Situ Inspections

GE Power Systems GER-3954B (04/03)


ii
Generator In-Situ Inspections

Introduction insurers review proposed plant maintenance


protocol modifications with operators and
Equipment maintenance programs are among
often require supporting recommendations
the latest budget items coming under increased
and other evidence from original equipment
fiscal scrutiny by utilities and non-utility genera-
manufacturers (OEMs) that new protocols are
tors alike as the power generation industry
functionally equivalent to the traditional.
seeks to reduce operating costs in a newly com-
petitive, deregulated market. Plant mainte- Toward that end, this paper presents GEs mod-
nance programs based on periodic disassembly ified inspection protocol for generators utiliz-
and inspection of critical turbine-generator ing new in-situ inspection tools, and compares
components, while relatively costly, have proven the results, advantages and limitations of a typi-
remarkably effective as evidenced by the cal generator in-situ inspection to those of a tra-
industrys consistently favorable plant reliability ditional inspection with the rotor removed.
and availability statistics. New bottom line reali-
ties, however, are motivating many plant opera-
In-Situ Inspection Supports Condition-
tors to reevaluate established maintenance
practices and deviate from them where they Based Maintenance
perceive net cost-to-risk advantages.
Equipment Condition Assessment
Plant operators are increasingly looking to
There are four methods to determine turbine
extend equipment running time between
planned maintenance outages, eliminate generator condition:
unnecessary outages and reduce the duration Continuous on-line assessment
of the necessary ones. GE, as the leading manu- Periodic on-line assessment
facturer of turbine-generators and a major sup-
Minor outage inspections
plier of power generation services, is assisting
operators in this objective by: Major outage inspections

Developing improved monitoring and These methods range from low impact on oper-
diagnostic instrumentation for on-line, ation and cost for continuous and periodic on-
condition-based maintenance (CBM), line assessments to medium for minor outage
rather than time-based maintenance, of inspections and high for major outage inspec-
turbine-generators tions (Figure 1). It is desirable, then, that the
CBM program make best use of the first two
Updating equipment maintenance rec-
methods while requiring the latter two methods
ommendations based on GEs fleet
as infrequently as possible. Figure 2 shows those
experience
items typically inspected on a generator and
Developing inspection tools and servic- when these inspections occur in a traditional
es that facilitate rapid off-line assess- maintenance plan.
ment of equipment condition
Industry insurers also have a vested interest in
In-Situ Inspection A Critical Part of
these objectives and are understandably reluc- Generator Maintenance Cost Reduction
tant to assume greater risks by deviating from Visual and quantitative inspection techniques
proven maintenance practices. Consequently, play an important role in assessing generator

GE Power Systems GER-3954B (04/03)


1
Generator In-Situ Inspections

GT24977
of Inspection ($)
Total Cost

On-Line Major Outage

Figure 1. Cost impact of condition assessment techniques

Continuous Periodic Minor Major


On-Line On-Line Outage Outage
STATOR
Stator Wedge Tightness X
Bar Movement X
Stator Winding Leaks X X
Core Insulation X
Stator Winding Insulation Integrity X X X
Greasing X
Cracked Connections/Integrity X
Oil Contamination X X
HV Connection Bolts X
FIELD
Blocked Vent Ducts X
RR NDT X
Field Coil Distortion X
Field Coil Loose Blocks X
Field Wedge Migration X
Field Winding Insulation Integrity X X
Thermal Sensitivity X
Rotor Surface Heating X GT25553

Figure 2. Generator inspection items

condition. On-line monitoring and diagnostic inspection supplements the capabilities of on


techniques are limited in detecting potential line monitoring and diagnostics to reduce the
problems, such as bar movement and vibration, risk of a failure.
component damage, copper dusting, coil dis-
In-situ inspection should be used during minor
tortion and foreign object damage (FOD).
Many of these conditions could lead to a major outages as a tool for assessing the generator
failure of the equipment if left unresolved for a condition. The inspection results can be used to
period of time. It is in these areas that in-situ help plan the generator maintenance at future

GE Power Systems GER-3954B (04/03)


2
Generator In-Situ Inspections

outages. This information can be used to deter- tion, it now becomes more practical to perform
mine if the field will need to be pulled and what more frequent inspections which can facilitate
components will require maintenance at this or early problem detection and resolution. As a
result the cost of maintenance and the equip-
future outages. If the generator condition is
ment reliability are both improved.
found to be acceptable, a future in-situ inspec-
tion may be planned with no maintenance nec-
essary at this time. As long as the generator con-
In-Situ Inspection Technologies
dition is found acceptable, there would be no GEs in-situ inspection capabilities were devel-
oped to address areas requiring field removal
additional need to pull the field. GEs in-situ
for inspection in the past (Figure 3). Four basic
inspection techniques can also be used with tra-
inspection systems used to provide the inspec-
ditional inspection and test techniques to pro- tion are:
vide a complete major inspection without
Miniature Air Gap Inspection Crawler
field removal.
(MAGIC)
GEs recommended standard tests for a major Remote access camera
outage are described in Technical Information
In-Situ retaining ring NDE scanner
Letter-1154 and GEK-103566.
Remote capacitance probe
In cases where known generator problems exist,
The generator in-situ inspection consists of the
periodic in-situ inspection may allow postpone-
basic MAGIC visual inspection using GEs
ment of field removal to a more convenient
patented inspection robot with the option of
time by monitoring the problem and minimiz-
adding one or more additional inspections
ing the risk of an in-service failure and resulting
based on the circumstances and customer
damage. The in-situ inspection is valuable in all
needs. Table 1 lists critical generator compo-
cases of abnormal operation where a generator
nents and the in-situ inspection techniques
suitability for service inspection is needed
used for each.
before returning to service. An in-situ inspec-
tion can be done quickly with miminal disas- MAGIC Visual Inspection
sembly of the generator, thus providing an accu-
Visual inspection of the generator stator and
rate, documented inspection and a quick
field within the bore region is performed by a
return to operation. Outage duration is less-
trained specialist using GEs exclusive MAGIC
ened by reducing the time needed to inspect
inspection robot. The robot is a precision
the generator, as well as providing condition
crawler carrying two high resolution video cam-
assessment information that can be used to plan
eras that moves through the gap between the
and perform more efficient repairs.
stator core and field. Full inspection coverage
In-situ inspection of the generator is a critical of the core ID and field surface is made possible
part of the generator maintenance program. It by the robots axial and transverse motion capa-
allows the owner to acquire high quality condi- bility. This capability also allows it to navigate
tion assessment data while minimizing the risk around the gas baffles present on many genera-
and cost. By lowering the cost of this informa- tor designs. The high resolution video scopes

GE Power Systems GER-3954B (04/03)


3
Generator In-Situ Inspections

MAGIC Visual Stator Wedge Tightness Assessment


Core Laminations
Space Blocks Electromagnetic Core
Stator Bars, Wedges Imperfection Detection (ELCID)
Field Surface, Wedges
Retaining Ring Nose Stator Insulation
Capacitance Measurement

Stator Clearance Measurement


Retaining Rings
Outside Surface:
Eddy Current
Remote Access Camera Inner Surface:
Field Coil End Turns Ultrasonic
Stator Bars
End Winding Support System
Flux Shield
Lower Frame Extension GT25678

Figure 3. Generator in-situ inspection capabilities

Component Common Problems MAGIC RAC Wedge EL-CID RR Capac- Clearance


Visual Visual Tapping NDE itance Meas.

Stator/Core

Core Laminations Foreign object damage, hot spots, evidence of movement X X


Space Blocks Migration, cooling passage blockage X X
Gas Gap Baffle Studs Cracked welds, looseness X X
Stator Wedges Looseness, loss, sparking damage X X
Stator Bars Foreign object damage, sparking, girth cracks, movement X X X
Wet groundwall insulation X
End Windings Bar movement, loose/broken ties, supports, etc., excessive X
corona activity
Copper Flux Shield Overheating, looseness, general condition X
Instrumentation RTD, thermocouple wiring ties, flux probe, general condition X

Field

Field Surface Heating, arcing, foreign object damage X


Body Weights Looseness, staking X
Field Wedges Arcing, migration, cracking X X
Retaining Ring Wedge contact, arcing, foreign object damage, material X X X
cracks, pitting
Coil End Turns Blocked ventilation, damaged insulation, coil distortion, X
contamination

General

All Excessive oil or other contamination, foreign object damage, X X


blocked cooling
Lower Frame Ext. Bus Insulation condition, connection integrity (if exposed), high X
Leads & Connections voltage bushing condition

Table 1. Inspection capabilities

GE Power Systems GER-3954B (04/03)


4
Generator In-Situ Inspections

provide the specialist with a clear view of the sta- The wedge tightness test cannot be performed
tor core laminations, stator wedges, field on asphalt insulation systems or windings held
wedges and surface on the inboard ends of the in place with camelback style wedges.
retaining rings. Figure 4 is a picture of some
The MAGIC system determines wedge tightness
repaired core damage using both the wide
by measuring the response of the wedge to a
angle and close up cameras on the MAGIC
mechanical stimulus (impact). Wedges are test-
robot.
ed in several locations along their length. The
Stator Wedge Tightness Assessment inspection data is stored in a file and provided
with the final report. The data is also used to
The Stator Wedge Tightness Test is offered as
generate a color coded wedge tightness map
an option to the MAGIC visual generator
which clearly shows the wedge tightness within
inspection. It is performed to accurately quanti-
the generator (Figure 5). Some generator
fy stator wedge tightness and is used to assess
designs limit access to all wedges and permit
the need for wedge tightening or replacement.
only a partial inspection. Wedges closest to the
This inspection is similar to that performed in
slot ends are the most critical to inspect and are
GEs factory as a quality check on new genera-
inspected in all cases. The reports data can be
tors. Loose wedges and the resulting stator bar
used for accurate trending of the winding con-
movement are major contributors to premature
dition and for determining when repairs are
stator winding damage and failure. A tight sta-
needed.
tor winding can last two or three times as long
as a winding that is not firmly held in the stator
core. The test can be performed on stator wind- Electromagnetic Core Imperfection
ings that meet the design requirements of hard Detection (EL-CID)
stator insulation (Micapal or GEGARD EL-CID is an accurate and economical means of
600) and flat or piggyback wedge systems. testing the condition of the stator core lamina-

Figure 4. View of repaired core damage taken with MAGIC robot

GE Power Systems GER-3954B (04/03)


5
Generator In-Situ Inspections

Figure 5. Generator wedge tightness

tion insulation. Damaged insulation can result although wedge tightess is a good indicator of
in circulating currents that can lead to core clearance between the top stator bar and
overheating and stator damage or even failure wedge, it can be misleading when the radial
(Figure 6). EL-CID uses a low core excitation clearance exists elsewhere in the slot. As a
level (about 4% rated flux) to establish a mag- result, GE recommends measuring the actual
netic field within the core. A highly sensitive, clearance between the stator bars and the bot-
miniaturized sensing coil, or chattock, is used tom of the core slot through a stator clearance
along the core surface to detect fault currents test. Clearance testing involves applying a force
which will result from core insulation damage. on each stator bar where it exits the core slot,
A signal processor located in the control system and accurately measuring its radial movement.
computer is used to measure, record and report GE has developed specialized tooling to per-
these faults. EL-CID has been proven to be espe- form this test which protects against stator dam-
cially valuable on machines where core loosen- age during the test. Measurements are made on
ing has been more prevalent. both ends of the stator core (Figure 7). A map of
the stator winding and each bars radial clear-
Stator Clearance Measurement ance is analyzed to determine the existence of,
Radial clearance between the stator winding or potential for bar movement.
and core permit unwanted motion of the stator
bars during operation. In some cases, radial Remote Access Camera (RAC)
motion has led to severe abrasion damage to The RAC inspection is an option to the MAGIC
the stator groundwall insulation and ultimately visual inspection. It makes use of a miniatur-
electrical failure. Wedge tightness was once ized, remotely actuated video camera to provide
thought to be the best means of detecting radi- a high resolution visual inspection of normally
al slot clearance. However, GE has found that inaccessible areas on the generator, outside of

GE Power Systems GER-3954B (04/03)


6
Generator In-Situ Inspections

Core Lamination Insulation

Core Laminations Damaged Insulation

Core Vent Duct


Stator Winding
Stator Core

Circulating Current

Figure 6. Circulating current due to damage core insulation

Field Body
Stator Clearance
Measurement System

Retaining Ring

Top Stator Bar


Stator Bottom Stator Bar
Clearance

GT25775

Figure 7. Stator winding clearance measurement

GE Power Systems GER-3954B (04/03)


7
Generator In-Situ Inspections

the bore region. These areas include the stator groundwall insulation at the location where the
endings, field coil end turns and stator terminal bar exits the core slot (Figure 9). A meter is used
connections. This information is combined to measure the capacitance across the insula-
with that provided by a MAGIC visual inspec- tion between the electrode and the stator bar
tion and the results of the standard visual and conductor. Each bar in the winding is measured
electrical exams to provide the most thorough on both ends of the core and statistical analysis
visual inspection possible with the field in place. is used to identify those bars with higher than
Figure 8 shows a picture of the stator end wind- normal expected capacitance. High capaci-
ing support system taken with the RAC system tance is a good indicator of moisture presence
during an in-situ inspection. in the insulation.
It is recommended that a capacitance test be
Remote Capacitance Probe performed at each major outage on an approx-
GE water-cooled generators manufactured imately five-year interval. This recommendation
before 1986 are susceptible to water leaks and presented a roadblock to implementing an in-
the resulting concerns as discussed in Technical situ inspection program on water-cooled gener-
Information Letter-1098. One of the periodic ators because performing the capacitance test
tests recommended in TIL-1098 is capacitance required field removal.
mapping of the stator bars. This test has proven
As part of its in-situ inspection program we have
to be very reliable in identifying stator bars with
recently developed a tool enabling the capaci-
deteriorated groundwall insulation resulting
tance test to be performed without removing
from a water leak.
the field from the stator. This tool uses an inflat-
Capacitance mapping requires placing a con- able electrode, similar to that used with the
ductive electrode on the surface of the bars field removed, and a remote actuator arm for

Figure 8. Stator end winding viewed using GEs remote access camera

GE Power Systems GER-3954B (04/03)


8
Generator In-Situ Inspections

Test
Area
Copper
Conductors

Test Groundwall
Electrode Insulation

GT25552

Figure 9. Stator bar capacitance test in process

locating the probe. GEs remote access camera access to the ID surface where eddy current test-
is also used for positioning the probe and iden- ing is used to detect very small surface indica-
tifying its location. This system is being used tions. Testing of the rings while installed on the
successfully and provides results similar to those field can also be performed, however, with less
obtained during field out inspections. sensitivity to crack detection on the ID surface.

Retaining Ring NDE Scanner Testing, similar to that performed with the field
removed from the stator, can be completed on
Stress corrosion cracking (SCC) of 18Mn-5Cr
many units without removing the field. The
generator retaining rings is a well documented
NDE test equipment has been modified by
industry-wide concern for generator mainte-
miniaturizing the scanner assembly using the
nance. SCC develops on the surface of the
same signal processing system as that used with
material in the presence of moisture and stress.
the field out. The system provides an ultrasonic
As a result of the stress concentration and
test (0.050/1.27 mm crack detection thresh-
geometry which tends to hold moisture, the
old) on the ring ID and an eddy current test
retaining ring inside diameter surface tends to
(0.005/0.127 mm crack detection threshold)
be more susceptible to this phenomena.
on the ring OD.
GE recommends replacement of 18Mn-5Cr
rings with the improved 18Mn-18Cr alloy which Other Testing
has not been susceptible to SCC. However, for There are several other tests and inspections
those customers who choose to periodically recommended during minor and major out-
inspect and repair the rings, GE offers a com- ages in addition to those discussed. They
plete inspection program. The most thorough include electrical testing of the stator and field
NDE inspection can be performed with the windings and RTDs as well as hydraulic testing
rings removed from the field. This permits of water-cooled stator windings. A complete

GE Power Systems GER-3954B (04/03)


9
Generator In-Situ Inspections

description of GE-recommended tests is provid- the results for industry use. Given acceptable
ed in Technical Information Letter-1154 and qualification results, GE expects that insurers
GEK-103566. In-situ inspection of the generator will evolve with the changing market and accept
does not change the need or importance of in-situ in place of traditional inspections.
these tests.
Qualification Testing
Qualification Efforts Qualification testing involved performing an in-
situ inspection on an actual generator and com-
Changing an Industry Mindset paring these results with those obtained
Generator inspection for years consisted of a through traditionally accepted inspection meth-
minor outage every 2 1/2 years and a major out- ods. MAGICs visual inspection system was the
age with the field removed every five years. This first to be qualified. The MAGIC inspection was
practice proved to be quite successful in main- performed on a GE generator at Georgia
taining a high level of reliability of the genera- Powers Plant Vogtle, during a scheduled major
tor fleet. Deregulation is causing the power gen- inspection outage. An inspection report was
eration industry as a whole to rethink its philos- written which documented the condition of the
ophy on equipment maintenance and OEMs, generator gas gap region as well as the collector
and utilities and insurers alike need to evolve to endwinding region which was inspected using
meet the needs of this new marketplace. In-situ the remote access camera. A thorough visual
inspection of generators is one way GE has inspection was then performed with the field
evolved to meet these demands, and GE needs out and the results were compared. GE found
to work with customers and their insurers to the in-situ inspection results were completely
properly apply this technology. In-situ inspec- satisfactory with good image resolution, thor-
tion will not be considered a complete success oughness and perspective. The field out inspec-
unless it can provide an inspection with the sim- tion found no defects which had not been
ilar accuracy, sensitivity and thoroughness of a detected with the MAGIC visual inspection.
field removed inspection. In-situ inspection
MAGICs wedge tapping capability was devel-
must not bring with it a significant increase in
oped by miniaturizing and remotely delivering
the risk of failure over traditional inspection
an industry accepted wedge tapping device.
techniques.
This direction was taken so that wedge tightness
Many GE customers with generators at nuclear- data, whether taken with the field in or out,
powered plants are required by their insurers to could be easily correlated. Data correlation is
remove the generator field at a specified inter- important to the long term trending and condi-
val to complete a major inspection. GE is cur- tion assessment. MAGICs wedge tap system was
rently working with several major insurers to qualified on a large GE generator through
reconsider this policy as a result of in-situ comparison of in-situ test results with field out
inspection technology. The first step toward wedge tapping and hammer testing tech-
replacing traditional inspections with those per- niques. As a result of its wedge tapping devel-
formed in-situ is qualification of the inspection opment, GE added the ability to listen to the tap
techniques. GE has completed several qualifica- test while in progress. This information is very
tion tests and is in the process of documenting useful in assuring the test is being performed

GE Power Systems GER-3954B (04/03)


10
Generator In-Situ Inspections

wedge tightness. The positive results with audi- inspection. This report will be made available to
ble testing of wedges has led GE to pursue this GE customers and their insurers to help sup-
as the companys primary means of wedge tight- port developing in-situ inspection programs for
ness testing on a MAGIC Jr. test system under their generators.
development.
A similar philosophy was used in the develop- Traditional vs. In-Situ Cost Analysis
ment of MAGICs EL-CID test capability. The A significant factor in comparing in-situ vs. tra-
most common and accepted EL-CID test system ditional inspection programs is the reduced
in the industry was developed by Adwel cost to the equipment owner. Cost reduction is
Industries, UK. GE currently uses Adwel systems achieved in three major areas: reduced outage
for performing field out EL-CID tests and, for duration, reduced disassembly and eliminating
the reasons stated, GE wanted to use a similar consequential damage elimination.
system for in-situ testing. This was accomplished
In-situ inspection reduces the time required to
by miniaturizing the test chattock portion of
complete a major generator inspection.
the system while making no changes to the dig-
Duration of a generator inspection includes the
ital EL-CID system. By doing so, GE can use the
time required for removal from service, disas-
same digital EL-CID test system for both field
sembly, inspection and reassembly, and prepa-
out or in-situ testing, the only difference being
ration for service. In-situ inspection significant-
the miniaturized chattock used for in-situ test-
ly reduces the time required for disassembly
ing.
and reassembly of the generator, although it
To qualify the results of the miniaturized chat- does add some time to the actual inspection
tock, GE ran comparison tests between it and process. The net time savings varies by plant
the standard chattock, including testing stator and generator design, but Table 2 provides a
cores of various design types and condition good estimate for a typical large generator at a
through use of actual in-service and laboratory nuclear plant.
test cores. The critical characteristic of the EL-
Reducing the generator inspection time is most
CID test is the electrical test signal which must
important when the generator is on the outage
be consistent between standard and in-situ tests.
critical path. Suitability for service inspections
This signal determines the cores defect magni-
are generally recommended for generators fol-
tude. Through the comparison tests, GE found
lowing an abnormal operating event that may
the test signal was very similar while testing
have caused generator damage, including
good sections of core iron as well as when sizing
breaker failures, short circuits and loss of cool-
core detects. These results demonstrated GE
ing. Each of these can cause generator damage
can expect good correlation between EL-CID
that would lead to an on-line major failure if the
tests performed using the standard or in-situ
damage is not repaired. These circumstances
methods.
provide an ideal application of in-situ inspec-
Qualification Report tion technology where every hour saved directly
affects the time spent offline.
A detailed qualification report will be prepared
to document the results and provide the data In-situ inspection can also reduce outage dura-
needed to demonstrate the validity of in-situ tion when used for advanced outage planning.

GE Power Systems GER-3954B (04/03)


11
Generator In-Situ Inspections

Visual Visual, Wedge


Type of And Wedge Tightness
Inspection Visual Tightness And EL-CID

Traditional 14 Shifts 16 Shifts 18 Shifts

In-Situ 6 Shifts 9 Shifts 12 Shifts

GT25550
Savings 8 Shifts 7 Shifts 6 Shifts

Table 2. Inspection time savings comparison

Performing an in-situ inspection during a in-situ inspection varies with the scope of the
minor outage prior to a planned major outage inspection but, generally, runs about 1/3 the
can help determine the necessity and scope of cost of complete disassembly. Table 3 compares
the major outage. The outage may be post- the cost of a traditional vs. in-situ inspection.
poned altogether if the generator is found in
Another economic benefit of in-situ inspection
good condition. If problems are found, the
is the reduction of consequential generator
information gathered during the inspection
damage as a result of the outage. Rotor removal
can be used to make preparations for repair at
requires uncoupling the turbine-generator
the next outage. These preparations include
shafts; careful disassembly of stator endshields
planning the repair, identifying labor and mate-
on both ends of the generator; removal of the
rial needs and developing contingency plans.
bearings, hydrogen seals, oil deflectors and
When it comes to generator maintenance,
exciter assemblies; and the skillful reassembly
experience has shown that preparation and
and realignment of these same components.
planning are critical to effieicntly executing an
Improper endshield reassembly may result in
outage.
oil ingestion problems, expensive and time con-
Inspection cycle through use of in-situ tech- suming oil cleanup procedures, undesirable
niques is achieved by greatly reducing the level lubrication of the armature slot and endwind-
of generator disassembly required to complete ing restraining systems, increased armature
the inspection. Reducing the level of disassem- motion, and accelerated armature insulation
bly has a number of benefits beyond reduced wear. (Refer to TIL 1098-3R2 for additional
cycle time. Cost savings result from reduced dis- information on the adverse effects of oil inges-
assembly and reassembly labor, repair and plan- tion). Rotor removal incurs risk of damage to
ning. Not removing the field from the genera- the precision components of the hydrogen seal
tor also frees up overhead crane availability for oil assemblies, and requires the heavy lifting
use on other parts of the outage. The total cost and temporary warm, dry storage of the rotor.
of field removal and reassembly is reported at The problems or damage resulting from dis-
$100,000 to $250,000 for fossil plants and assembly can lead to very costly repairs. For
$250,000 to $500,000 for nuclear plants. The this reason, the best policy is to minimize dis-
cost associated with partial disassembly to allow assembly.

GE Power Systems GER-3954B (04/03)


12
Generator In-Situ Inspections

Generator Inspection Cost Comparison Est. Cycle Est. Est. Cost


Traditional vs. In-Situ Inspection (Shifts) Craft Hrs. ($1000)

Traditional Generator Inspection


Exciter & Generator Disassembly & Field Removal 6 $125
Generator Test & Inspection 4 $20
Field Installation, Generator & Exciter Reassembly 6 $175
Lost Generation Profit (est. $20K/day, 8 days) $160
Total Cost of Inspection 1000/1500 $480

In-Situ Generator Inspection


Generator Disassembly 2 $40
Generator Test & Inspection 5 $50
Generator Reassembly 2 $60
Lost Generation Profit (est. $20K/day, 5 days) $100
Total Cost of Inspection 200/300 $250

Total Cost
Traditional Inspection ($K) $480
In-Situ Inspection ($K) $250
SAVINGS ($K) $230

Generator Inspection Cost

$500
$450
$400 Traditional Savings of $230,000
Total Cost ($1000)

$350
$300
$250
$200
In-Situ
In Situ
$150
$100
$50
$0
Traditional In-Situ Inspection
Inspection ($K) ($K)
Generator Inspection Type

Footnotes:
1. Generator Inspection Scope Included Visual and Wedge Tightness Inspection.
Electrical and Leak Testing Cost Not Included.
2. Disassembly and Test Costs Used for a Large Steam Turbine Generator
at a Nuclear Site.

Table 3. Traditional vs. in-situ inspection costs

GE Power Systems GER-3954B (04/03) 13


Generator In-Situ Inspections

GE Position On In-Situ Inspection Recommended maintenance schedules for tra-


ditional and in-situ inspection protocols are
GEs MAGIC robot provides generator compo-
compared in Table 4.
nent assessment capability comparable or supe-
rior to that routinely achieved by rotor removal
inspections for many applications. Closeup, Conclusions
detailed views of the core and rotor surfaces, The power generation industry is undergoing
stator and rotor wedges, retaining ring tips and major changes requiring power producers,
vent ducts allow a generator specialist to detect OEMs and insurers to adapt. One way GE has
and assess potential problems not generally dis- responded to these market changes is through
cernible by electrical testing or other on-line the development of tools that enable in-situ
monitoring often prior to the occurrence of inspection of generators. In-situ inspection
any significant generator damage. Periodic offers an acceptable, low cost alternative to the
MAGIC in-situ inspections, together with elec- traditional field out generator inspection in
trical testing and hydraulic checks, provide an many cases. GE has been and will continue to
acceptable alternative to many traditional OEM work within the industry to gain acceptance of
maintenance protocols. Skillful interpretation in-situ inspection techniques. GE is presently
of in-situ inspection observations and related working on enhancing the capabilities of its in-
data can provide plant operators with cost effec- situ inspection service and expanding the appli-
tive opportunities to reduce outages and outage cation to smaller generators. In-situ inspection
duration while maintaining the outstanding will play an increasing role in reducing power
reliability and availability of their generators. producers cost of generation.

Inspection Interval (Years)

First Year
Inspection
2.5 5 10
MAJOR MINOR MAJOR
Traditional Visual Visual Visual
Wedge Wedge
ELCID ELCID
IN-SITU IN-SITU IN-SITU IN-SITU
MAGIC In-Situ Visual Visual Wedge ELCID
EL-CID
Wedge
ELCID
GT25551

NOTES: Electrical and Hydraulic testing continue at recommended intervals


NDE testing and TILs may require rotor removal for completion

Table 4. Recommended generator inspection schedules

GE Power Systems GER-3954B (04/03)


14
Generator In-Situ Inspections

List of Figures
Figure 1. Cost impact of condition assessment techniques
Figure 2. Generator inspection items
Figure 3. Generator in-situ inspection capabilities
Figure 4. View of repaired core damage taken with MAGIC robot
Figure 5. Generator wedge tightness
Figure 6. Circulating current due to damage core insulation
Figure 7. Stator winding clearance measurement
Figure 8. Stator end winding viewed using GEs remote access camera
Figure 9. Stator bar capacitance test in process

GE Power Systems GER-3954B (04/03)


15
Generator In-Situ Inspections

List of Tables
Table 1. Inspection capabilities
Table 2. Inspection time savings comparison
Table 3. Generator inspection cost comparison
Table 4. Traditional vs. in-situ inspection costs

GE Power Systems GER-3954B (04/03)


16

You might also like