You are on page 1of 3

Figure 1. An HDD drill rig starts the drilling of a pilot hole.

NEW PRESSURES BOOST INTEREST IN HORIZONTAL


DIRECTIONAL DRILLING. TRENT MILLER,
SENIOR PROJECT MANAGER NATURAL RESOURCES,
GOLDER ASSOCIATES, USA, AND TOM BRYSKI,
ASSOCIATE AND SENIOR GEOTECHNICAL ENGINEER,
GOLDER ASSOCIATES, CANADA, DISCUSS THESE CHANGES.

GOING DEEP WITH HDD


H
orizontal directional drilling (HDD) technology include protecting the environment, minimising physical
has seen progressive and impressive intrusion and optimising lifecycle costs.
developments over the past 40 years. Advances It is just as important to understand that HDD is not
in engineering analysis and design, equipment always the best solution for pipeline installation and there
capability and contractor capacity have pushed back some are other more conventional construction techniques that
of the historic limitations of this pipeline installation may be more applicable, result in less cumulative impact
method. and provide better control of environmental and cost risk.
Pipeline operating companies are more interested
than ever in routinely considering HDD as a practical HDD versus trenchandcover
and longterm economical choice for installing pipelines Several trends are having the effect of pushing the
beneath surface obstacles. Now, several trends are helping risks associated with trenchandcover upward in many
make the use of HDD more attractive in more situations circumstances, and HDD may present a total lower risk
and this is expected to push back historic limitations even profile. These include:
further.
It is more important than ever for pipeline operators, Disturbing sensitive environments
designers, regulators and others in the oil and gas sector Rivers and streams, wetlands, rarespecies habitats, historic
to be familiar with the current state of HDD construction sites and the urban environment are becoming increasingly
practice and where this technique is applicable and will difficult to disturb through traditional trenchandcover
be successful in achieving set out objectives. These may methods. Even in places where surface disturbance is

OCTOBER 2012 | Reprinted from World Pipelines


allowed, it may well be that the longterm monitoring Even in jurisdictions and environments where local
and mitigation obligations, together with the attendant laws and regulations may permit trenching across
legal liability, means that disturbance should be avoided. a stream, corporate boards, project financiers and
Accordingly, HDD is being seen as a longterm lower risk influential third parties may apply pressure to avoid
and more costeffective solution as compared to more such disturbance. Wellfinanced and internetsavvy
traditional construction methodologies in an increasing nongovernmental organisations (NGOs) may put pressure
number of situations. on companies and their financial backers to reduce their
environmental impacts, in part by eliminating surface
disturbance in sensitive areas. In addition, by drilling
underneath these sensitive areas, the pipeline company
can avoid the need to obtain many necessary permits
that would take months to acquire, thus decreasing the
lead up times on their construction schedule.
One of the authors recently worked on an
HDD project in the western US. The pipeline was to
run under a National Wildlife refuge, including several
wetlands that were home to some endangered or
protected species. The HDD portion of the line, some
2100 m in length, cost approximately US$5 million
more than a comparable opencut construction.
However, mitigation costs associated with opencut
would have been around US$9 million for offsite
mitigation, and an additional US$1 million for longterm
Figure 2. Initial setup of a HDD trackmounted drill rig. monitoring.
The result was that despite the higher direct cost of
using HDD under the refuge, using this technology saved
the client US$5 million.

Areas of potential erosion


Increasing public concern over wellpublicised pipeline
breaks and spills, particularly when streambeds and banks
have been eroded, is putting pressure on the industry
to better manage the effects of scour and erosion.
Trenching down from surface with an open cut to reach
an appropriate depth to prevent a pipeline from being
exposed in future may be impractical. One alternative is to
go deep with HDD when geologic conditions, geometric
Figure 3. A side view of an HDD drill rig, showing the hydraulic arm
of an excavator being used to handle the drill rod. constraints and logistical considerations allow it.

Futureproofing from climate change


With the expectation that climate change will bring with
it more severe storm events, companies in all industries
are being called up on to assure the integrity of their
installations against conditions that may occur in the
future. Pipelines that are not at risk from erosion now
may be so if severe storms become more frequent.
This may mean the need to place pipelines beneath
watercourses at even greater depths than would be
required today, and extend the deep portions further
back from the current stream banks. This may be
possible in an increasing number of circumstances due
to the advances and greater capabilities associated with
HDD technology that were discussed above.

More advantages
Figure 4. A horizontal directional drill (HDD) completes a reaming
pass to widen the hole, with the reamer bit and mud pit visible in
Many of the recent advances in HDD have come from
the foreground. technology developed for horizontal directional drilling
for conventional oil and gas extraction, as well as

Reprinted from World Pipelines | OCTOBER 2012


More versatile
As well as longer, HDD technology is able to work with
a wider variety of soil types, including gravel and cobble
formations that were previously considered not feasible
due to the high potential for significant loss of drilling
fluid. Not only would this pose a financial cost, it was
an environmental hazard, particularly when the fluid
migrated to surface. One of the technologies supporting
increased versatility of HDD is the use of telescoping
surface casing, in which successively small diameter
temporary steel casings are installed inside one another
along the initial length of the planned course of the
HDD bore path prior to pilot hole drilling. The casings are
advanced sufficiently to bypass the coarse grained soils
and retain the drilling fluid as the HDD bore is conducted
Figure 5. A trackmounted HDD drill rig. inside the casings.

Deeper
Elevation differentials now allow HDD pipe installations
to greater depths underground. Until recently, 100 m of
bore path elevation differential were hard to achieve;
now, elevation differentials approaching 300 m are
possible. This allows safe installation of pipelines under
deeply incised watercourses, protecting the pipe against
exposure and possible rupture.

Bigger
Pipelines with up to 1067 mm diameter pipe, installed
using HDD methods for increasingly greater distances, are
opening up options for high capacity lines, or even single
bores containing more than one pipeline or conduit.

Not a magic bullet


While HDD has come a long way, pipeline builders and
Figure 6. Welded steel product pipe is supported on pipe cradles owners need to be aware of its limitations.
as the pipe is pulled back through the hole. Many of the more challenging, leadingedge
applications should only be carried out by highly skilled
unconventional extraction, particularly in tight formations. and experienced contractors, supported by consultants
Other improvements have come through public works with a wide range of experience in the field.
experience, including the installation of sewer lines and Use of the drill intersect method requires advanced
electrical conduits in ways that do not disturb traffic on downhole and surface survey equipment, highly skilled
busy roadways. Some examples follow. steering technicians and drill operators.
Misaligned or poorly installed telescoping surface
Longer casing may result in casing that has to be redriven or
Ten or so years ago, HDD bores over a kilometre in length abandoned. Also, since the equipment most often used
were virtually unheard of. Now, thanks partly due to the to drive the casing resembles a subhorizontal pile driver,
ability to accurately determine the position of the drill the noise level means it is most practical in remote areas.
head underground, it has become possible to use the drill Miscalculations of the forces required while pulling
intersect method to work from both sides of a crossing the pipe through the HDD bore may ovalise plastic pipe,
at the same time, and meet in between. Advancements cause excessive abrasion damage to the exterior surface
in drilling fluid engineering make it easier and faster of the pipe, or even fractures and breakages.
to remove the cuttings along these greater lengths of However, the pressures that are making cutandcover
borings, so that the cuttings remain in suspension and less practical can only help push technology ahead, and
are adequately removed from the hole. There are also increase the numbers of contractors who are familiar with
better ways to monitor and control the annular pressure HDD technology. As such, it can provide a more practical
of the drilling fluid while drilling the pilot hole. Now solution to concerns by government entities, nearby
HDD projects with bore lengths in excess of 2 km have been community members, landowners, regulators and other
achieved. stakeholders.

OCTOBER 2012 | Reprinted from World Pipelines

You might also like