You are on page 1of 13

P/2014/00830

Received
27/06/2014

Construction Management Plan


Photovoltaic Solar Farm
at

Rolleston Park Farm


Tutbury
Burton on Trent
Staffordshire
DE13 9HQ

+
ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

CONTENTS

1 INTRODUCTION

2 CONSTRUCTION OPERATIONS

3 CONSTRUCTION TRAFFIC

4 CONCLUSION

APPENDICES

A Site Location Plan

B Site Layout Plan

C Construction Programme

Prepared by: C Quirk Position: Planning & Design

Approved by: J Kelly Position: Planning Director

Date Prepared: 18th June 2014

PushEnergyLtd

ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

1 INTRODUCTION

1.1 This Construction Management Plan has been prepared by Push Energy Ltd in
support of a planning application for the provision of a photovoltaic solar farm on
Rolleston Park Farm, Tutbury, Burton on Trent, Staffordshire, DE13 9HQ . The
location of the site is shown on the drawing PA001 included in Appendix A.

1.2 The proposed solar farm would comprise 1528 mounting racks, each with an array
of 48 solar panels totalling approximately 73,344 panels. The panels are arranged in
rows running East-West across an agricultural field.

1.3 The proposed solar farm is expected to generate an output of around 18.7MW of
electrical power.

1.4 This Construction Management Plan will set out the proposed access arrangements
to the site, the construction programme, construction traffic, construction worker
numbers and the construction hours.

PushEnergyLtd

ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

2 CONSTRUCTION OPERATIONS

2.1 Access

2.1.1 Vehicular access to the site will be via an existing concrete farm track that leads back
to Tutbury Road. The access is suitable for accommodating the movement of HGVs
and other construction vehicles.

2.1.2 All construction vehicles will enter and exit the site in forward gear. Banksmen will not
direct general traffic, but will indicate to heavy and large construction vehicles when it
is appropriate for them to enter and leave the site.

See Transport Statement for further information relating to access.

2.1.3 Car parking for construction workers will be provided within the site.

2.1.4 A temporary surfaced area within/adjacent to the site will provide parking, unloading,
storage of materials and manoeuvring of construction vehicles. This area will be
removed at the end of construction period.

2.2 Hours of Operation

2.2.0 Construction of the solar farm will be undertaken between 07:00 and 18:30 Monday to
Friday and between 07:00 and 12:30 on Saturdays.

2.3 Staff

2.3.1 During the construction period it is expected that between 30 and 40 staff will be on
site, depending on the phases of the construction schedule.

2.3.2 Once the solar farm is fully operational, there will be no staff based on site. It will not
generate any significant traffic movements, with security and maintenance staff the
only likely regular visitors.

2.4 Construction Programme

2.4.1 The construction of the solar farm is expected to last around 16 weeks. See Appendix
C for Construction Programme of solar farm.

2.4.2 Fig 1.1 indicates details of the approximate volumes of HGV traffic associated with the
construction of the solar farm. The expected HGV volumes are based on best
estimates at this stage and may vary due to delays in the construction programme.

PushEnergyLtd

ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

3 CONSTRUCTION TRAFFIC

3.1 Access Routes

3.1.1 The construction phase of the solar farm is expected to last 14-16 weeks.

3.1.2 It is expected that the majority of construction materials associated with the
development will be imported from Europe via the eastern ports, possibly Felixstowe.
HGV access between the port and the site would therefore be via the strategic routes
of the A12 and M1.

3.1.3 Construction staff would likely arrive from local population centres such as Leicester
and Burton Upon Trent. Push Energy management staff would be travelling from
Colchester.

3.1.4 Temporary signage will be put in place at the access junction which will direct all
vehicles associated with the construction. The signage will be put in place prior to
commencement of the construction works, will be retained in place throughout the
construction period and removed following completion of the construction.

3.1.5 In order to enforce the use of the signed construction traffic route, a clause will be
included within the contract of site contractors and suppliers directing them to use only
the signed route.

3.2 Vehicle Types

3.2.1 The vehicles will be standard Construction and use HGVs with a maximum length of
16.5m (articulated).

3.3 Vehicle Numbers

3.3.1 Fig 1.1 details the expected HGV trips associated with the construction of the solar
farm.

3.3.2 The table (Fig1.1) indicates that over the 16 week construction period a total of 100
HGV will access the site. This will result in a total of 200 HGV traffic movements (100
arrivals and 100 departures).

3.3.3 On the basis of working 6 days a week for the 16 week construction period this
equates to less than 4 HGV movements (2 arrivals and 2 departures) per day.

3.3.4 The table indicates that the peak period of construction HGV traffic would be during
week 7 of the construction programme. During that week a total of 19 HGVs would
require access to the site, resulting in 38 HGV movements (19 arrivals and 19
departures).

3.3.5 During the construction period it is expected that between 30 and 40 staff will be on
site depending on the phases of the construction programme.

PushEnergyLtd

Fig 1.1 HGV Totals

Task HGV Numbers Per Week


Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Total
Site Setup 1 1
Perimeter Fence 2 2 2 6
Piling & Earthworks 2 1 1 4
Mounting System 4 4 2 2 12
Mounting Modules 16 16 16 16 64
Cabling 2 2 1 1 6
Inverters/Transformers 3 3 6
Grid Meters 1 1
Commissioning 0
Completion 0
Totals 3 2 2 4 7 6 19 18 16 16 3 3 1 0 0 0 100
ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

3.3.6 Staff will be encouraged to car share to travel to the site, however even as a worst-
case scenario, using single occupancy for cars during the peak construction period, it
would only result in a maximum of 80 car movements to the site each day (40 arrivals
and 40 departures).

3.3.7 Push Energy will endeavour to reduce the number of car movements to the site by
encouraging to car share where practical. Alternatively, if a large number of staff are
based at one location, potential to share a minibus to the site will be considered.

4 CONCLUSION

4.1 The construction of the solar farm would result in the temporary generation of
construction and staff related traffic over a 16 week construction period.

4.2 Temporary signage will be put in place at the access junctions. In order to enforce the
use of the signed construction traffic route a clause will be included within the contract
of site contractors and suppliers directing them to use only the signed route.

4.3 The construction of the solar farm will result in a total of 200 HGV traffic movements
(100 arrivals and 100 departures) equating to an average of less than 4 HGV
movements (2 arrival and 2 departure) per day.

4.4 On the basis of the trip generation detailed above it is expected that the construction
of the solar farm would result in no real impact on the local highway network.

PushEnergyLtd

ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

Appendix A
Site Location Plan

PushEnergyLtd

ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

Appendix B
Site Layout Plan

PushEnergyLtd

Gre
e
nL
Woodside
Reservoir House

ane
(covered)

BU

(T
RT

rac
ON

k)
Proposed native hedge with Burton Road
tree planting along Northern

RO
boundary. Providing a visual
Farm
barrier from footpath

AD
74m
Falling Pit
PV Modules
Issues
See drawing PA004
Plantation Drain

Public Footpath
Fiddler's Lane

POC
NE
LA

Underground Grid Connection cable


S

ROLLEST
ER '

Caster's Bank
D DL

Plantation
FI

Gas Line
TBURY CP 88m Bleak House ON DOVE
AD
Farm
RO

Proposed native hedge Moorfield Hill


planting along Northern

ck
boundary. Providing a visual
Gas Line barrier from Burton Road

Tra
Hoblands
Farm

Switchgear /Inverter /
Transformer Enclosure
See drawing PA006

Mayfield

Northwood
Site boundary fence
See drawing PA008

k Switchgear /Inverter /
ac Transformer Enclosure
Substation/ See drawing PA006
Tr Grid Connection Cabinet/
Comms Cabinet LO
See drawings PA005 & PA007
DG
E
H
IL
L

ack Alder Moor 61m


Tr

Dra
in
Alder Moor
Issues
Plantation
Deer Park
Plantation Weirs
Spr
77m Drain
Lower Weir Weir
in

Covert
ra
D

Bushton
N
ConstructionManagementPlan
RollestonParkFarm,BurtononTrent

Appendix C
Construction Programme

PushEnergyLtd

Solar Farm

Construction Programme

ID Task Name Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16
1 Access Road Improvements
2 Perimeter Fence
3 Site Compound & Accommodation
4 Piling
5 DC Trenching
6 Inverter Bases
7 Install Mounting System
8 Install Modules
9 Install DC Strings
10 Install SSM's & Cable Connection
11 Install Inverters & Transformers
12 Complete DC Installation
13 Grid Connection Room
14 Substation Building
15 Grid Connection Trench & Cable
16 UKPN Works
17 Commissioning
18 Completion

Push Energy Ltd April 2013

You might also like