You are on page 1of 17

Section Title here (change colour to relevant section) Design & Access Statement for the Northern Line

ess Statement for the Northern Line Extension 15

3.0 Station Design


3.1 Introduction
3.2 Functional and Operational Requirements of Stations
3.3 Overarching Design Principles
3.4 Nine Elms Station
3.5 Battersea Station
16 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )

3.1 Introduction SITE


Figure ANALYSIS WIDER
3.1 Northern Line CONTEXT
Extension Stations - Contextual Overview (Indicative)

3.1.1 This section covers the design of the


station boxes the structures which
enclose the platforms, ventilation and
draught relief systems, emergency
intervention, ticket halls, circulation and
staff accommodation - and indicative
design of the above ground elements
of the station such as the station
entrances. The detailed design of
the station entrances, their external
appearance and associated landscaping
is reserved by planning condition.
3.1.2 It is worth noting that before the public
realm is completed at both station sites,
there is the potential that interim works
may be required during the period
when the station opens to the public
and commencement or completion of
the development at Battersea Power
Station or the over site development
(OSD) at Nine Elms. To help set out
how the designs have taken this into
account, illustrative material has also
been described in Sections 3.4 and 3.5,
demonstrating how the stations may
relate to these adjacent developments.
3.1.3 The general design principles for the
stations have been set out in Table 3.2.
This identifies the principles which have
informed the design to date and those
which will be taken into account through
subsequent design development.
NORTHERN LINE EXTENSION BATTERSEA
S e c t i o n T i t l e h e r e ( c h a n g e Sceocl toi o
unr :t o3 .r0e lSe tvaat ni ot ns eDcet si oi gnn) Design & Access Statement for the Northern Line Extension 17

3.2 Functional and Operational the LU brand, in all customer and 11. The use of line identifiers and 3.3 Overarching Design
Requirements of Stations staff environments. network identifiers must be Principles
consistent and clear. Network
4. All infrastructure design and all There are a number of common
Functional requirements identity elements will be the 3.3.1
elements of a stations design principles for the designs of the stations
principal means used to identify LU
3.2.1 The functional and operational will take account of the need for based on the requirements listed above,
environments and products.
requirements have a significant influence passengers to assimilate their as well as urban design requirements
on the design of the stations. The environment as simply as possible, 12. Only the corporate icons and which are intended to ensure that the
design of stations has been developed enabling them to move with identifiers, including the use of proposed stations integrate with their
in accordance with the London confidence through a station. graphics, as defined in Company surrounding areas. These principles
Underground Limited (LUL) Category 1 standards, shall be used. have been taken into account in the
5. All station and train design and all
Standards, which are mandatory. The station designs and will also inform the
elements of a stations and a trains Operational requirements
stations have been designed to the subsequent detailed design stages for
design, will take account of the
following standard: In terms of operational requirements, the both the external appearance of the
need to move passengers with as 3.2.3

Being structurally sound with a life little delay to them and others as stations have been designed to include: station buildings and the associated
span of up to 120 years; possible. landscaping/public realm work.
Step-free access;
Provide a ticket hall, platforms 6. Stations will always exhibit basic Intuitive way-finding; 3.3.2 Table 3.2 overleaf sets out the general
and vertical circulation elements World-class features and will principles for the stations while
Congestion free circulation;
that accommodate the projected always embrace and balance paragraphs 3.4.14 and 3.5.10 set out
passenger demand;
Staff accommodation;
in their design, functionality, specific design principles for Nine Elms
Enable passengers to evacuate
Ticketing facilities; and Battersea stations respectively.

distinctiveness, and a sense of
the station safely under emergency LUs continuing commitment to a
Gate lines;
conditions; and positive contribution to the civic Security control and communication
Providing appropriate systems scene. systems; and
for ventilation, draught relief and Evacuation facilities.
7. The concept of zoning, to
emergency intervention.
segregate and demarcate 3.2.4 Stations have be designed to
3.2.2 Stations have also been designed to unrelated activities will inform all accommodate forecast passenger
consider LUL 12 standard principles of station development activity. demand and, in accordance with
design including: relevant good practice guidance,
8. All fixtures and fittings will be
particularly London Undergrounds
1. The scope of the design should developed and installed to make a
Station Planning Standards and
encompass all aspects of the positive contribution to the overall
Guidelines and World Class Stations
Companys look and feel, not environment in which it is located.
Good Practice Guide.
just those things passengers
9. Materials and finishes will be
experience. 3.2.5 Step-free access into and out of the
consistently applied across the
stations from the public realm has
2. Infrastructure design and all whole of a station, wherever
been incorporated into the landscape
elements of infrastructure design, possible.
proposals and the public realm
will endeavour to contribute to an
10. The corporate colour palette will be immediately outside of the stations will
environment in which customers
applied in all environments in ways be designed in general accordance with
feel secure.
that enhance the LU brand and TfLs Legible London initiative, to help
3. The needs of impaired users will make the use of an environment pedestrians find their way, especially
be met in a consistent manner and easy and pleasant. when leaving Underground stations.
through designs which enhance
18 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )

Table 3.2 General Design Principles for the Stations


Project Technical requirements Urban design requirements
element
Station The station has been designed to: Details of the external appearance of the stations shall have appropriate regard to the
box be operationally independent of the OSD. following design principles:
OSD construction: Design of the station should facilitate a high quality, comprehensive
structure accommodate the appropriate scale of development of any potential OSD.

cater for a train length of 114m, to ensure that the station can accommodate longer
OSD to be built at an undefined later date.
OSD access and servicing: Station design should include or allow for the later addition
trains than those currently in use on the Northern line.
accommodate the requirements of the tunnel ventilation systems, including the
of cores for OSD and appropriate servicing and access arrangements.
OSD life span: Consider the relative predicted life span of the station and the OSD so
appropriate vertical air ducts.
take account of the necessary ducts, louvres and plant associated with the cooling and
that the structure allows for both the construction and demolition and reconstruction of
OSD without the need to interrupt the operation of the station.
ventilating of the various plant and accommodation rooms.

The ticket hall and escape cores have been designed to take account of the need for the
station to remain open during the construction and demolition of any OSD. To do this the
designs have incorporate a crash deck to provide protection to passengers and emergency
services entering and exiting the station building.

Details of the external appearance of the stations shall have appropriate regard to the
following design principle:
take account of the necessary ducts, louvres and plant associated with the cooling and

ventilating of the various plant and accommodation rooms.

Internal Stations and Premises comply with category one standards and would comply with the In defining the precise internal layout, TfL shall have regard to the following:
layout Building Regulations and relevant British standards. Where any conflicts arise between Clean and simple: Provide a clean & simple environment free of clutter, excess detail

Building Regulations and this standard, compliance with this standard shall take prec- and signage.
edence except where a breach in the Law would arise. Continuous public realm: Consider the internal space as a continuous part of the public

realm outside of the station.


Space for normal operations in stations has been planned to:
Desire lines: Provide direct, legible and easy to understand routes from the gate line to
a) minimise congestion;
b) be resilient to surges in demand and train service disruption; internal destinations and exits.
Wayfinding: Provide opportunities to integrate simple signage that complement direct
c) provide sufficient non-passenger space to enable staff to function efficiently.
and easy to understand routes through the station.
Station size has been determined by the space requirements of all required activities, e.g. Dwell spaces: Provide dwell spaces appropriately located relative to entrances, gate

emergency escape provision, access for the emergency services, ticket purchase, retailing, lines and information boards providing direct views across the station.
vending, passage through the gate-line, way-finding, access to and from platforms, waiting Commercial: Consider opportunities for commercial uses to be inserted in appropriate
for trains, boarding and alighting from trains and staff accommodation.
locations within and around the station.
Flexibility: Create flexible spaces that can be used for different purposes at different
Station design has sought to ensure that obvious routes with minimum travel distances, are
free from obstructions, have good lines of sight and avoid dead ends and hiding places. times of the day and week.
Adaptable: Be adaptable in order to accommodate future changes to the use of space

The stations have been designed to ensure that persons of reduced mobility can move and changes in technology.
between street and train via step-free routes between levels, which comprise of lifts, ramps Microclimate: Consider micro-climate created by the interface between the street
and level access between platform and trains. entrance and the underground tunnels in order to create a comfortable environment
that minimises energy consumption.
A bank of three heavy duty metro type escalators between surface level and ticket hall has
Natural light: Maximise the potential of natural day light into the ticket hall to create a
been included at each station. To achieve a minimum platform width of 3.0m these have
been located in the centre of the platforms. natural airy and light environment while minimising energy requirements.
S e c t i o n T i t l e h e r e ( c h a n g e Sceocl toi o
unr :t o3 .r0e lSe tvaat ni ot ns eDcet si oi gnn) Design & Access Statement for the Northern Line Extension 19

Project Technical requirements Urban design requirements


element
Internal Escalators to maintain an uninterrupted run off width through the ticket hall to minimise Place-making: Develop an internal character of the station that reflects and enhances
layout passenger congestion at the ticket hall level. the existing and new character and identity of the surrounding neighbourhood in a way
(continued) that creates an appropriate gateway to the area.
A designated fire lift accessible from street level have been provided at both stations.
The layouts of the station have been designed to allow for plant replacement, including ap-
propriate arrangements for vehicular access.

Station Details of the external appearance of the stations shall have appropriate regard to the Details of the external appearance of the stations shall have appropriate regard to the
entrance following design principles: following design principles:
design The entrance level should be set out in accordance with flood protection measures. Quality: Should be of a high quality and have regard to LULs ambition for World Class

The station entrance should remain open and operational during the construction, Stations.
demolition and redevelopment of any OSD. Quality: Stations should also be in keeping with its surrounding area.

Identity: Create a distinct identity, signalling the presence of the London Underground

station.
Location: The station entrance(s) should be positioned to respond to desire lines in

between the gate line and surrounding destinations and to enable good sight lines and
ease of wayfinding.
Size: the entrance should be dimensioned to allow for predicted pedestrian flows

along with any regular or extraordinary servicing requirements.


Passive capacity: Entrances should consider the need to provide additional capacity

passively to cater for future increases in demand.


Step-free access: Step-free access into and out of the station must be provided.

Station entrance structures at street level will need to include provision for louvres at

least five metres above ground to provide ventilation for the station.

Landscape Details of the landscape scheme shall have appropriate regard to the following design Details of the landscape scheme shall have appropriate regard to the following design
and principles: principles:
the station should provide public transport interchange facilities with other modes of The quality of the public realm should be of a high standard to reflect the importance
interchange
facilities transport, such as bus and bicycle of the NLE station and the VNEB regeneration.
adequate cycle parking provision and storage should be provided (further detail of The design of the public realm should provide good access to public transport.

which are provided in Section 5 on Access).


The station should be integrated with the existing and planned public realm and be
easily accessible and visible to pedestrians, bus users and cyclists at street level.
Allowance to be made at surface level for cycle parking/cycle hire facilities.
Clear pedestrian and cycle links should be provided between the station and the wider
VNEB area.
Wayfinding and signage should provide clear routes for pedestrians and cyclists
arriving at/leaving from the station, using Legible London principles (see Section 5 for
further details).
20 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )

3.4 Nine Elms Station Figure 3.3 Nine Elms Station Existing Site with Proposed Station Box (Indicative)

Location
3.4.1 The proposed site is shown in Figure
3.3 and bounded by Wandsworth Road
to the east and Pascal Street to the 1
south. The site is currently within three
separate land ownerships, Sainsburys,
Banham Security and Covent Garden
Market Authority (CGMA). 2
3.4.2 CGMA land lies immediately to the
west of the station site beyond which
is a railway viaduct, which is visually
dominant and acts as a physical barrier
3
to movement in the area.

Context
4
Surrounding land use
3.4.3 The surrounding uses currently include: 5

1. Railway viaduct 6
Sainsburys supermarket

OAD
2.

R
3. Sainsburys car park

RTH
7
4. CGMA access road

O
DSW
5. CGMA boiler house
8

WAN
6. Sainsburys petrol station
7. Proposed station box 9
8. Banham Security offices
9. CGMA offices (Covent House) 10 PAS
C AL
10. Housing (mixed tenures). STR
EET
3.4.4 Banham Security submitted a fully
detailed planning application in 2011 to
redevelop and intensify the site for office
and residential uses. The proposal did
not make any provision for the NLE at
either above or below ground levels.
Following discussions with LB Lambeth
GLA and TfL, the applicant withdrew the
application.
S e c t i o n T i t l e h e r e ( c h a n g e Sceocl toi o
unr :t o3 .r0e lSe tvaat ni ot ns eDcet si oi gnn) Design & Access Statement for the Northern Line Extension 21

Currently CGMA has no proposal for the a need for connectivity improvements Proximity to Wandsworth Road (part

Nine Elms Station


3.4.5
Covent House site and associated land. west of Wandsworth Road. of the Strategic Road Network) and
It is understood that the head office or the important CGMA access roads.
3.4.10 There are a number of key sites planned
boiler house will be relocated as part of
to the north of the Nine Elms station site Site-specific design principles
the longer term redevelopment of the
in the vicinity of Vauxhall Interchange.
wider Covent Garden Market site. In addition to principles identified in
These proposals increase in height and 3.4.14

3.4.6 LB Lambeth have resolved to grant scale towards the recently constructed Table 3.2 in Section 3.3, there are a
planning permission to Sainsburys, 50-storey Vauxhall Tower. Indeed, the number of specific design principles
subject to completion of a section106 consented scheme on the adjacent which are applicable at Nine Elms
agreement. This is a mixed use Sainsburys site includes towers up to 38 station. These are as follows:
development, including a replacement storeys in height.
retail store, residential units, and Station box
Movement
community and office space. The outline Where practicable, the external
3.4.11 The areas historic uses, notably the
element of the Sainsburys proposal appearance of the station should be
market and other warehouses with their
anticipated a station entrance located designed so that it could incorporate
large disconnected plots, have acted
on the southern edge of their site facing natural daylight from skylights and
as barriers to pedestrian, cycle and
onto Wandsworth Road. would also relate to potential future
vehicular movement.
Character
over site development (OSD).
3.4.7 The site is located adjacent to the busy 3.4.12 The railway viaduct is another major
barrier to movement in the area. The Station entrance design
Wandsworth Road in an area defined by
new development is expected to improve The station has been designed to
residential, large-scale retail and light
connectivity in line with the principles set include a single ticket hall with a
industrial uses. Residential properties
out by the respective planning policies dual/split entrance with a southern
(including a sheltered housing block)
by opening up new connections through entrance on Pascal Street and the
are located on the south side of Pascal
these sites, improving strategic links northern entrance directly opposite,
Street opposite the proposed station site
between the river, through the viaduct facing the pedestrianised street
and to the east of Wandsworth Road.
to the existing communities east of Nine adjoining the proposed Sainsburys
The immediate area is primarily urban
Elms station and the OA. This includes scheme.
in character with a range of building
typologies from large residential blocks a proposed connection from Pascal The landscape scheme should
to smaller terraces. These range from Street through the railway viaduct to retain appropriate access to the
two to four storeys in height. Ponton Road. internal street, along with access
routes to the south and east.
Constraints
3.4.8 There are no heritage assets,
3.4.13 The design of the station considers a
conservation areas, listed or locally Landscape and interchange facilities
number of physical constraints, namely:
listed buildings or registered parks and The landscape scheme should
gardens in the vicinity. The need for the station box to follow make provision for clear, coherent
the east-west orientation of the and safe pedestrian and cycle links
3.4.9 TfLs Pedestrian Environment Review
proposed NLE alignment; between the station, the Covent
System (PERS) audit of this site
The vertical alignment of the railway Garden Market site, Nine Elms Lane
highlighted that whilst the quality of the
which dictates a platform level which and the river.
walking environment is generally good
on Wandsworth Road, Pascal Street is approximately 18.5 metres below
requires significant improvements. typical ground level in the local area;
Maintenance and quality of environment The aspirations of surrounding land
were found to be very poor and identified and development proposals; and
22 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )

Design development 3.4.18 Figure 3.4 shows a number of the 3.4.20 he size of the station box also increased
T
different options for the cores and during the design development stage to
3.4.15 As set out in Section 2.6 above,
station box, based on double-ended accommodate future train lengths and as
Route 2 was the preferred route at
designs: a result of the deletion of Claylands Road
consultation and has been endorsed
shaft, which led to additional ventilation
by LB Lambeth, LB Wandsworth and facing Wandsworth Road at one end
requirements at the station.
other key stakeholders. In parallel with and the CGMA scheme at the other
work on the final route adjustment, end (Figures 3.4b); 3.4.21 A single-ended station facing
a detailed assessment of station single-ended designs with an Wandsworth Road was included in TfLs
locations was undertaken (Figure entrance off Wandsworth Road 2012 consultation, as shown in Figure
3.4a). This assessment considered: (Figure 3.4d and 3.4c); and 3.4f, showing:
local connectivity; operational single-ended design with an entrance Entrances at the corner of Wandsworth
requirements; cost implications; impact off the pedestrian street (Figure 3.4e). Road and Pascal Street;
of construction; development criteria;
All of these attempted to accommodate A lift providing step-free access to
and policy compliance.
development proposals as far as trains;
3.4.16 This highlighted that the Nine Elms practically possible. A ground-level ticket hall;
site was the most appropriate location
3.4.19 A single-ended station facing Three escalators giving access to two
for the intermediate station. TfL then
Wandsworth Road emerged as the spacious platforms; and
continued liaising with stakeholders
optimal design solution based on: Links to pedestrian and cycle networks
regarding the possible location and
orientation of the station. TfL also Forecast passenger demand which proposed for the area, including
investigated the possibility of integrating suggested that only a single ticket through the railway arches to the north.
the station with proposed developments hall would be required; 3.4.22 41% of those who responded to the
surrounding the site such as the Forecast passenger movements by questionnaire made comments on
previous Banhams proposals. direction; Nine Elms station, with 47% of those
respondents making positive comments
3.4.17 For reasons related to engineering, Facilitating appropriate interchange
(34% were neutral and 19% were
phasing and cost integration, it was between buses and the new station;
negative).
not possible, practical or feasible to Cost and staffing implications for
integrate the station with the Banham single versus double-ended station 3.4.23 The final design, as described in
proposals in particular. Instead, the layout options; the following pages incorporates all
optimum station layout was selected The need to integrate and link the the necessary TfL operating criteria
that crossed all three land ownerships, new station with the surrounding area whilst maximising the opportunity for
but allowed for comprehensive with high quality public realm, lighting a comprehensive OSD to support the
development proposals to come and signage; regeneration of the area.
forward above the station structure The need to link the station to the rest
itself (see Section 6 for further detail).
of the OA through the railway viaduct;
and
The opportunity to create active
frontages along Pascal Street and the
new internal pedestrian street to the
north of the station building.
R OA D
S e c t i o n T i t l e h e r e ( c h a n g e Sceocl toi o
unr :t o3 .r0e lSe tvaat ni ot ns eDcet si oi gnn) Design & Access Statement for the Northern Line Extension 23

N
PONTO
Figure 3.4 Nine Elms Station Design Development Options
4.3m

Nine Elms Station


28
to
30

El Sub Sta

2.7m

Depot

MP
MP0.75
0.75

143 to 161
2.7m
Sub
FB

Depot
Sta
Viaduct
Depot 22

62
uct ROAD
Viad WYVIL

62
TCB

Depot 1
9
3

1 to 16
11
7
12
8 se
13
Hou

4
Posts

14

n
into
Qu
62

6
16
El Sub
Sta

Edgar
House
1 to 16

Posts
Posts

Br L Twr
S

1 to 24
David
House

1 2 3 4
1 to 16

5 6
Chy

3.0m 7 8 9 10
Works

TRENCHOLD
Conrad

Sainsburys
House
1 to 16

E WAY
Bus Stop

FFL +3.00

LUSCOMB

House
1 to 24
1.9m

ROAD

Peter
10
L Twr Basil
House

ORTH
1 to 16

38

DSW
A

STREET
WAN
39 El Sub Sta
43 1.8m TCB
37 45
41 Posts
49 Adrian
House
47 53 1 to 16
55 3 5
51
PASC
29 AL STREE PH
31 BM 5.11m
T
13 1
3.4m 1
27
25 5.1m

an House
21 15 WILCOX ROAD

12a
23

30
17

26
2

14 to
4

1 to
6 8 10
BRAM 7 14

Charm
18 16
LEY 9
23 to 30
30 28
CRES
45 24 CENT 18

Estate
11 21 13

House nan
19 16
22 14 11
20

e
17

Charr
15

er Hous 24
12

ns Street

Locky12a 14 to
DAVIDSON GARDENS
49
43 Bus Stop

Hema

1 to
30
10 to

ound

e
1 1 to 16

Hous
Aldwyn

Playgr
House

ham
Wilbra
B

WAY

Vent.
Shaft

Vent.
Shaft
C
Retail
Retail Opportunity
Opportunity

D FFL +4.00

ROAD
WYVIL
Timber Yard
TCB

Timber Yard

BANHAM SEC
URITY
NCG 4.7m

Playground

L
11) What are your comments on proposals for the newUSCstation
OM
(a) Different locations (b) A double-ended station located on Pascal Street (c) A single-ended
NINE ELMSstation off
STATIONPascal Street BE
WA
Nine Elms? Y Fn

N
Sk-0907-NE-620 Rev-A
Route 01 Option C - Ground Floor PLAN
COLOUR KEY
1:500 at A3
Ventilation Shaft / Draft Relief
El Sub Sta

2.7m
05.12.11
Vent / Core: below surface level
23 doughty mews - bloomsbury - london wc1n 2pf t: 020 7831 5900 e: info@studiodare.com
MP
MP0.75
0.75
143 to 161

Br L Twr
Potential
Potential
FB

22
Under Platform Exhaust
62

S
uct ROAD
Viad WYVIL
62

TCB

Fire Fighters' Lift


1
9
3
1 to 16

11
7
12

FF Lift / Escape Stairs: direction of entry/exit


8
use
13 Ho

over
over site
4

Posts
14

n
into

station
Qu
62

6
16

TCBs
El Sub

Escape Stairs (2no.)


Sta

Edgar
House
1 to 16

SAINSBURY'S Passenger Lift


Posts
Posts
1 to 24

PROPOSED
David
House
1 to 16

Passenger Lift: direction of entry/exit

development
3.0m

development
Conrad
1 to 16
House Station Box: to serve 117m platform
BE WAY

Bus Stop

+1.80m
LUSCOM

Station / Passenger Access


House
1 to 24
ROAD

Peter

Basil
House
ORTH

1 to 16
DSW

Surface Level Staff Accommodation

at
at Nine
Nine Elms
WAN

El Sub Sta

3.0m
TCB
Posts
Adrian
House
1 to 16
3 5
5
PASC
AL STRE PH
ET BM 5.11m
3.4m 1
1
an House

5.1m WILCOX ROAD


12a
30
14 to

2 4
1 to

6 8 10 14
Charm

7 18 16
30 28
23 to 30
18
Estate

21 19 13
Housenan

22 16 14
20 11
e

17
Charr

15
er Hous 24

12
ns Street

14 to

DAVIDSON GARDENS
12a
Locky

Bus Stop
Hema

1 to

30
to
e

1 1 to 16
Hous

Aldwyn

1500
House
ham
Wilbra

Play
D
R OA BANHAM'S
PROPOSED
Area
1438
ON 10
NT
PO
Retail Opportunity

WAY
1194 +4.00m
00 S
TAT
ION BO

OMBE
X

1150
0

LUSC
1
2
3
4 1.9m 4300
0 ESC
ALATO
A 5 R FO
OTP Bus Stop
t
6 RINT
c 7

du

OAD
BANHAM SEC 8

Via
URITY L Twr 9
8000
10

R
B

RTH
NCG
POMs
4+2

Stair

WO
Pres.

C
Vent.
Shaft
Room
SAINSBURY'S
PROPOSED
LER

NDS
POMs
2+2

1.8m
Access GLAP
Hatch to
Concourse

WA
UMC
8

D
Posts
7
6
5

MP 2 2
4
3
Ticket hall

FFL +4.00
STR

1500
PAS
CAL
STR
EET BM 5.11m
3.4m
5.1m WILCOX RO
(d) Single entrance from Wandsworth Road (e) Single entrance from northern side of station box (f) Design included in the 2012 consultation
AD

NINE ELMS STATION


L Twr
BRA
M
NINE ELMS STATION N
GRNLEB-SDA-ST-00-SK-ARC-42613 Posts
N
Sk-0907-NE-650 Rev-
LEY
CRE Surface Level Impact: Route 5 Option G 1:500 at A3 / 1:250 at A1
Route 03 Option B - Ground Floor PLAN 1:500 at A3 Buro Happold
Consulting Engineers SCE
N 147 o'donnell court - brunswick centre - london wc1n 1nx t: 020 7278 1277 e: info@studiodare.com
10.08.12
tate

05.12.11 T
r 23 doughty mews - bloomsbury - london wc1n 2pf t: 020 7831 5900 e: info@studiodare.com
t Es

Bus Stop
e

DAVIDSON GA
Stre

RDENS TCP
Post
ans
Hem
d
oun
ygr
Pla

LB

Ps
Ps HEMANS ST
RE HEM
ANS
2.1m ET STR
EET
to 24

man House
24 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )

Proposed development Figure 3.5 Nine Elms Station General Arrangement Plan, Street Level N Location Plan
Leiceste

1
3.4.24 This TWAO application includes a N
request for a Planning Direction to grant
planning permission for all relevant
development. Full planning details
are provided for the below ground Clapham
Commo

structure and the ticket hall with the


detailed design of above ground station
entrance, external appearance and
landscaping/public realm reserved by
planning condition to be agreed with the

WANDSWORTH ROAD
respective local authority in due course.
3.4.25 he overarching station design
T

42509

42509
principles set out in Table 3.2 and

E
the site-specific principles set out in ENTRANCE

paragraph 3.4.14, have informed the +1.90m

basis of this final design. N Location Plan


Leicester Square
+4.80m 1. SAINBURYS

Charing Cross

Embankment +3.10m London


Waterloo
Amount and layout A
Bridge +4.00m

A
Borough
3.4.26 The proposed station box extends 42507

Elephant &
+4.00m 42507

0 5

over the full width of the site between +3.10m


Castle
UPPER CONCOURSE TICKET HALL
Nine Elms
Wandsworth Road and the end of
SCALE 1:250 (A1
Kennington
Battersea

Pascal Street. The alignment of the


Oval +7.60m This drawing is
subject to furth

station is broadly parallel with Pascal +1.90m


Stockwell

Street, as shown in Figure 3.5. Clapham


ENTRANCE
05 SM FM

Common Clapham 04 SM FM
North 03 SM FM

3.4.27 There are two parts to the above ground 02 SM FM


01 SM FM
elements at Nine Elms station - the
42509

42509
+3.40m
PASCAL STREET Rev By Chkd Ap
C

E
main station (east) core including the +2.50m Client

entrances and ticket hall at the eastern PASCAL STREET Tran

end nearest Wandsworth Road, and the


west core nearest the railway viaduct
WANDSWORTH ROAD

which houses emergency escape, vent Halcrow Group Ltd.


CH2M HILL COMPA

shafts and a fire fighting lift. The east


A
Elms House, 43 Brook
Hammersmith, London
TEL: 020 3479 8000
Canopy / Rooflight FAX: 020 3479 8001

core is approximately 1,200m2 and the Forecourt / Access


www.halcrow.com

west core, 270m2.


Project:
NORT
Tickethall / Entrance
PLANNIN
Paid Concourse
Drawing:
Internal Accommodation
NIN
Ducts / Risers
ENTRANCE
Lift

Emergency Lift (plant replacement)


Suitability:

Escape Route S4 FOR


Drawn by: SM
Checked by: FM
1. SAINBURYS BASEMENT CAR PARK ENTRANCE Approved by: SL
Drawing Scale: 1:25
Drawing No.:

PLANNING DIRECTION DRAWING NUMBER 28 GRNLEB-SD

+4.00m Based on Ordnance Survey Digital Data with the permission of the controller of H.M.S.O. Crown Copyright Reserved Licence No. nmlo_03735001-17

A
42507

0 5 10 15 20 25

COURSE TICKET HALL


LB
Section: 3.0 Station Design Design & Access Statement for the Northern Line Extension 25

The proposed station core includes

Nine Elms Station


3.4.28
STATION ENTRANCE/EXIT TO N
the ticket hall with a dual/split entrance INTERNAL PEDESTRIAN ROAD
onto Pascal Street to the south and AND SAINSBURYS
the internal pedestrianised street to
the north (which forms part of the STAIRS
approved Sainsburys scheme). The
area between the two cores would form
part of the OSD and would be designed
to accommodate other uses, including
entrances to residential floors above and
LIFT
retail and other active frontages.
3.4.29 The ticket hall, illustrated in Figure 3.6,
includes a bank of three heavy duty

WANDSWORTH ROAD
metro escalators in the centre of the
ESCALATORS TICKET HALL TICKET HALL VENT
station box leading down to the centre DOWN TO (PAID SIDE) (UNPAID SIDE) DUCTS
of the platform level, with a platform PLATFORMS
on either side of the escalators. A
passenger lift down to platform level
would also be provided north of the
ticket hall and would serve as a fire
fighting lift in the event of an emergency.
Stairs would also connect to platform
level for service and emergency access.
Staff accommodation is provided
south of the ticket hall on the Pascal
Street side. The main station core also
includes two vertical ventilation ducts
originating from platform level these STATION ENTRANCE/
EXIT TO PASCAL STREET
take air away from the tunnels to be
vented above the OSD and are located Figure 3.6 (above) Nine Elms Station
at the Wandsworth Road end of the Illustrative Ticket Hall Layout
station box. These vents are replicated Figure 3.7 (right) Nine Elms Station
at the western end. Illustrative Section showing Station and SKYLIGHT OSD (FOR INFORMATION WANDSWORTH
Potential OSD ONLY) ROAD
3.4.30 The west core is the emergency escape
with a lift and two sets of stairs linking to
the platform level. This is a secondary
fire intervention point with exits in
opposite directions on to Pascal Street
and the internal street to the north. This
core needs to be protected as a means TICKET HALL
of escape during an emergency and is
designed with a crash deck on top to
protect it from the OSD above.
26 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )

3.4.31 Below the ticket hall level are the Figure 3.8 Nine Elms Station Station Overview Diagram
platforms and tunnels as illustrated
in Figure 3.8. The basement levels
provide accommodation for plant rooms,
including:
an upper machine chamber at Location Plan
basement level 1; Leicester Square
Charing Cross
tunnel fans and traction sub-station at
London
basement level 2; Embankment Waterloo
Bridge
general plant rooms at basement
TICKET HALL / WEST COREBorough
level 3; and Elephant &
EAST CORE Castle
the platforms at basement level 4.
Nine Elms
Kennington
Battersea
Scale Oval
3.4.32 The detailed design of the external
appearance of the above ground Stockwell
element of the station, including scale,
Clapham
is reserved by condition for subsequent Common Clapham
determination and will follow the North

relevant design principles highlighted in


Table 3.2 and in paragraph 3.4.14. The
scale of the street level component of
the station takes into consideration the
need to enable a future comprehensive
OSD. The east and west cores are
located at either end of the station box
and will be integrated into the future
OSD.
1. OSD car park access and lightwell

1. OSD CAR 2.
PARK ACCESS
Station & traction
AHU and LIGHTWELLsubstation louvre

3. Stair
2. STATION AHU AND pressurisation
TRACTIONlouvre
SUBSTATION LOUVRE

4. Main tunnel ventilation


3. STAIR PRESSURISATION LOUVRE louvres

5. UPE louvres
4. MAIN TUNNEL VENTILATION LOUVRES
6. Attenuator
5. UPE LOUVRES
7. Dampers
6. ATTENUATOR
8. Combined tunnel ventilation
7. DAMPERS
9. Draught relief
8. COMBINED TUNNEL VENTILATION
10. Attenuator
9. DRAFT RELIEF
11. Fan
10. ATTENUATOR
12. Over track exhaust
11. FAN

12. OVER TRACK EXHAUST


Section: 3.0 Station Design Design & Access Statement for the Northern Line Extension 27

Appearance

Nine Elms Station


3.4.33 The detailed design of the external
appearance of the above ground
element of the station is reserved by
condition for subsequent determination
and will follow the relevant design
principles highlighted in Table 3.2 and in
paragraph 3.4.14.
3.4.34 The main core of the station and Figure 3.9 Nine Elms Station - Illustrative Visualisation, without potential OSD
the western core should allow for
appropriate venting/air conditioning
of the above ground areas and below
ground accommodation and venting
from the tunnel below. This may include
louvres at least five metres above
ground level.
3.4.35 The main core of the station and
western core will be visible when the
station becomes operational and prior
to any OSD having commenced or
being completed as seen in Figure 3.10.
It is anticipated that the OSD would
incorporate these station structures into
the overall design. Images in Section
6 of this document illustrate how that
transition may be treated.
Figure 3.10 Nine Elms Station - Illustrative South Elevation, without potential OSD

Station
West Core Entrance
28 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )

Landscape Figure 3.11 Nine Elms Station Landscape Masterplan (Illustrative)


3.4.36 Figure 3.11 illustrates a high quality public N Key
Key
realm around the station site, including 1. Nine Elms Station building
Pascal Street and the internal street 1. Nine
2. Elms
3.
Station
Adjacent building
development
Avenue trees
2. Adjacent development
adjacent to the Sainsburys scheme to the 5 3.
4.
Avenue
5.
Barclays cycle hire
Waytrees
finding
6
north. Feature paving is anticipated to be 5 7
4.
5.
Barclays
6.
Way
Cyclecycle
7. fiFeature
standshire
nding trees
6
provided at the station entrance area. 6. 8.
Cycle
9.
Inground lighting and artworks
stands
Pedestrian crossing
7 7 7. Feature trees
10. Paved carriageway
8. Inground lighting and artworks
3.4.37 Pascal Street is identified in both the 2
9.
11. Security bollards
Pedestrian crossing
7
VNEB OAPF and the Vauxhall SPD as a 8 10. Paved carriageway
11. Security bollards
strategic green link and a key pedestrian 2
6 8
and cycle route to the river. It also serves 8
an important function in terms of access
to existing residences and6 businesses, 8 8
as well as providing future access to the
CGMA site and Sainsburys site as shown 6

in Figure 3.13. An avenue of trees is 6


8
8
proposed on the street with high quality 5

paving to reinforce the importance of this


improved connection.
6 The landscape 11 8
5

details would be developed to the south 3 8


6
side of Pascal
5 Street and will be part of the

future details to be agreed with the local 10

authority as discussed above.


11 8
1 5

3
3

10 3

1 9
3
PAS 4
C AL S
TRE
ET
3 10

3
5

D
9

ROA
3

RTH
10
9

SWO
3

D
3

WAN
PAS 4
C AL S
TRE
ET
10

D
9

ROA
3

RTH
10

SWO
3

D
WAN
S e c t i o n T i t l e h e r e ( c h a n g e Sceocl toi o
unr :t o3 .r0e lSe tvaat ni ot ns eDcet si oi gnn) Design & Access Statement for the Northern Line Extension 29

The intention is that the internal Pascal Street would also have active

Nine Elms Station


3.4.38 3.4.39 Pascal Street
pedestrianised street between the frontages, although the intention would
station and redeveloped Sainsburys site be for it to be a quieter street because
to the north will be activated by ground of the existing residential uses opposite.
floor retail outlets and cafs, proposed Nevertheless, the broad pavements
as part of the potential OSD - further would provide the opportunity for caf
detail is provided in Section 6. Colour, uses, taking advantage of the south
in the form of lighting, seating and art facing orientation and generous space.
is envisaged for this street to provide
interest and animation - see Figure
3.12. Feature trees could be provided at
the western end of the street to create
seasonal interest.

Figure 3.12 Nine Elms Station Public Realm Precedent Images

Pedestrianised street

Viaduct
30 Design & Access Statement for the Northern Line Extension S e c t i o n : T3i t. l0e Sht ea rt ei o (nc hDaens gi ge n c o l o u r t o r e l e v a n t s e c t i o n )
Key

1. Nine Elms Station building


2. Security bollards
3. Avenue trees
4. Barclays cycle hire
3.4.40 Wayfinding signage will be provided Figure 3.13 Nine Elms Station Contextual Landscape Masterplan (Illustrative) 5. Way finding
6. Cycle stands
at the corner of Pascal Street and 7. Feature trees

Wandsworth Road, at the western end N 8. Inground lighting and artworks


9. Pedestrian crossing
Key
of Pascal Street and at both ends of 10. Adjacent development
11. Raised table for vehicle crossing point (Temporary surface)
1. Nine Elms
12. Station building
the pedestrianised street. Cycle parking 2. Security
Pedestrian
13. bollards
and cycle route (Temporary surface)
Rail arch - pedestrian cycle route with inground lighting feature
with 90 spaces will be provided at the 3. Avenue trees
4. Barclays cycle hire
western end of the station box with cycle 12 5. Way finding
hire stands on Pascal Street opposite 6.
7.
Cycle stands
Feature trees
the station entrance. Further information AD 8. Inground lighting and artworks
RO 9. Pedestrian crossing
on wayfinding and cycle parking is PO
N TO
N
10. Adjacent development
provided in Section 5. 13
11. Raised table for vehicle crossing point (Temporary surface)
12. Pedestrian and cycle route (Temporary surface)
13. Rail arch - pedestrian cycle route with inground lighting feature
3.4.41 In order to create the strategic link, 6
5

the existing wall at the western end 7


7

of Pascal Street would need to be 12 10


11
demolished and one of the railway 2
6

arches of the viaductOAopened


D up to 8
R
create a new pedestrian
TO
N and cycle
ON
link through to Pthe adjacent CGMA 12 6 8

land, Ponton Road and the Nine Elms 13 5


2 11
developments on the western side of 2 1 5
5
the viaduct. It would also connect to the 6
7
proposed River Walk northwest of the 7 3

site. This proposed link forms part of the 11


10
TWAO proposals. 2
6
8 PAS
C AL S
3.4.42 To prevent unauthorised vehicular TRE
ET
4
9

access to this new link through the

D
ROA
12
viaduct from Pascal Street, telescopic 6 83 5

RTH
bollards could be placed at the western 5

SWO
9
2
end of the street. Two existing vehicular 11

D
1 5

WAN
2
routes cross this new link (shown as 11
on Figure 3.13) and raised tables could
3
be provided to ensure pedestrian and
cyclist safety. Additional bollards could
also be placed at these intersections to
restrict vehicles using the link. PAS
C AL S
TRE 9
ET
3.4.43 Where the station becomes open to the 4

OAD
public before the OSD is completed,

R
5
a temporary surface and landscaping 3

RTH
material would be used. The material

SWO
9
palette for the permanent landscape

D
WAN
scheme will be coordinated with the
OSD proposals and in discussion with
the local authorities and surrounding
landowners.
S e c t i o n T i t l e h e r e ( c h a n g e Sceocl toi o
unr :t o3 .r0e lSe tvaat ni ot ns eDcet si oi gnn) Design & Access Statement for the Northern Line Extension 31

Refuse and servicing

Nine Elms Station


3.4.44 Station related waste would be stored
in a dedicated waste storage room on
the north face of the ticket hall building.
This storage area would be accessed
internally off the ticket hall concourse.
A set of double doors on the external
elevation allows waste to be removed
from site via the pedestrian route
immediately to the north of the station.
3.4.45 The station would require 24 hour
service access to take account of tube
and station maintenance - for example,
the replacement of plant such as fans
and traction power. Plant replacement
would be carried out via a hatch in the
floor of the ticket hall (on the unpaid
side). Plant would be lifted from the
basement levels, up into the ticket hall
through the hatch and out of the station
entrance the height of the traction
power (approximately 3.6m high x 3m
long x 3m wide) has determined the
height of the station entrances.

You might also like