You are on page 1of 2

Date:

Attention :

Subject :

Location:

Dear Sir,

Please see below our detailed quotation and scope for rectification of existing elevator shaft

ITEM. SCOPE OF WORKS QTY UNIT UNIT COST AMOUNT


1.0 PRELIMINARIES PHP PHP
Mobilization / Demobilization 1.00 lot 35,000.00 35,000.00
Permits (if necessary - by Owner) 0.00 lot 0.00 0.00
Safety and PPE 1.00 lot 28,000.00 28,000.00
Temporary Facilities and Enclosure 1.00 lot 10,000.00 10,000.00
Temporary Utilities and Consumption - by Owner 0.00 lot 0.00 0.00
Site Administration and Office Support 1.00 lot 30,000.00 30,000.00
Hauling and Disposal 1.00 lot 15,000.00 15,000.00
Housekeeping 1.00 lot 10,000.00 10,000.00
Bonds and Insurances (not included) 0.00 lot 0.00 0.00

2.0 CHIPPING / DEMOLITION WORKS


Chipping Works (Elevator Shaft) 1.00 lot 45,000.00 45,000.00
Chipping Works (Elevator Call Button) 1.00 lot 2,025.00 2,025.00
Chipping Works (Elevator Rough Opening Requirement) 4.00 sets 911.25 3,645.00
Chipping works (Power Cable Inlet) 4.00 sets 202.50 810.00
Chipping works - intercom cable, LOP wirings and Conduit 9.00 sets 87.75 789.75
Chipping works (landing indicator) 4.00 sets 87.75 351.00
Removal of Existing Floor Finish - for Elevator Elevation Reqts 12.00 sqm 95.85 1,150.20
Cut-out for Controller Cabinet 1.00 lot 2,025.00 2,025.00

3.0 CIVIL WORKS


Stiffeners and Lintel Beams 1.00 lot 66,339.00 66,339.00
Zocalo at machine deck (prevent water intrusion) 1.00 lot 1,380.00 1,380.00
Plastering (rectify old elevator call button) 4.00 sets 506.25 2,025.00
Plastering (requirement for elevator opening) 4.00 sets 2,984.85 11,939.40
Provision for Power Cable Inlet (Cutout) 4.00 sets 262.50 1,050.00
Provision for Landing Indicator 4.00 sets 152.55 610.20
Provision for intercom cable, LOP wirings and Conduit 9.00 sets 152.55 1,372.95
Restoration of floor finish requirements 12.00 sqm 1,215.00 14,580.00
Plastering and Grouting of Landing Doors 1.00 lot 2,592.00 2,592.00
Pit Floor thickness requirement (not included) 0.00 lot 0.00 0.00

4.0 STEEL WORKS


Lifting Beam / Hooks with post - anchor 1.00 set 51,030.00 51,030.00

5.0 WATERPROOFING WORKS ( ELEVATOR PIT UP TO GF LEVEL ONLY )


Surface Prepartion (Elevator Pit) 9.91 sqm 101.25 1,003.29
Water Proofing (Elevator Pit) 9.91 sqm 675.00 6,688.58

6.0 ELECTRICAL WORKS


Check and verify electrical lines 1.00 lot 3,000.00 3,000.00
Shaft Lighting Fixtures (200 lux) 4.00 units 1,316.25 5,265.00
Headroom Lighting Fixture (200 lux) 1.00 unit 1,316.25 1,316.25
Wiring Devices for Lighting - Switches and COs 2.00 set 675.00 1,350.00
Shaft Ventilation - Exhaust Fan 500M x 500H (optional) 1.00 unit 16,200.00 16,200.00
Provision for Pwer Supply from Panel 15.00 lm 473.55 7,103.25
Breakers and Panels
Distribution box with Busbar 1.00 unit 1,755.00 1,755.00
Breaker for Shaft Lighting (20 AMP) 1.00 unit 1,107.00 1,107.00
Breaker for Elevator (25 AMP) 1.00 unit 1,107.00 1,107.00
Wires (THHN) 1.00 lot 11,117.25 11,117.25

Page 1 of 2
Conduits 1.00 lot 5,130.00 5,130.00

TOTAL PHP 398,857.11

*** Cost proposal is subject for clarification and discussion with Owner and other trade contractors / suppliers.

TERMS and CONDITIONS


Thirty percent (30%) downpayment, progress billing
Mobilization shall be one (2) weeks after receipt of Notice to Proceed
Completion time is estimated to be 60 calendar days
Items not mentioned in the scope of works are excluded

Prepared by:

Noted by:

Page 2 of 2