2017 FOR PROPOSED FOUR STORIED BUILDING PROJECT AT FACULTY OF MANAGMENT AND FINANCE,UNIVERSITY OF COLOMBO
ID Task Name Duration Start Finish %
Complete 2016 2017
November December January February March April May June July August September October November December January February March April May
25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30
0 Progress as programm mgt 520 days Fri 10/30/15 Thu 4/27/17 95%
3 Getting approval for entrance gate from CMC 14 days Thu 11/19/15 Wed 12/2/15 100%
4 Demolishing Existing building and removing trees 10 days Mon 12/7/15Wed 12/16/15 100%
7 Excavation for ground improvement for 27 days Sat 12/19/15 Thu 1/14/16 100%
foundation
8 Quarry dust filling under strip foundation 21 days Thu 12/24/15 Wed 1/13/16 100%
9 Screed concreting for foundation & lift well base 22 days Mon 12/28/15 Mon 1/18/16 100%
13 Column R/F work up to ground level 8 days Sun 1/10/16 Sun 1/17/16 100%
16 Rubble work and tie beam concreting 15 days Sat 1/23/16 Sat 2/6/16 100%
17 Back filling & Filling under floors 18 days Sat 1/30/16 Tue 2/16/16 100%
19 Columns & Stair case GL to 1st F 14 days Sun 2/7/16 Sat 2/20/16 100%
20 Reinforcement work for Column - GFL to1st FL 10 days Sun 2/7/16 Tue 2/16/16 100%
21 Form work in Column - GFL to 1st FL 10 days Tue 2/9/16 Thu 2/18/16 100%
22 Concreting work for column GFL to 1st FL 10 days Thu 2/11/16 Sat 2/20/16 100%
23 1st Floor slab and beam 22 days Mon 2/15/16 Mon 3/7/16 100%
27 Column & Stair case 1FL to 2FL 16 days Thu 3/10/16 Fri 3/25/16 100%
28 Reinforcement work for Column - 1st FL to 10 days Thu 3/10/16 Sat 3/19/16 100%
2ndt FL
29 Form work in Column - 1st FL to 2nd FL 10 days Sun 3/13/16 Tue 3/22/16 100%
30 Concreting work for column - 1st FL to 2nd FL 10 days Wed 3/16/16 Fri 3/25/16 100%
31 2nd Floor slab and beam 27 days Sat 3/26/16 Thu 5/5/16 100%
35 Column & Stair case 2FL to 3FL 20 days Tue 5/10/16 Sun 5/29/16 100%
36 Reinforcement work for Column - 2nd FL to 3rd FL10 days Tue 5/10/16 Thu 5/19/16 100%
37 Form work in Column - 2nd FL to 3rd FL 10 days Sun 5/15/16 Tue 5/24/16 100%
38 Concreting work for column - 2nd FL to 3rd FL 10 days Fri 5/20/16 Sun 5/29/16 100%
39 3rd Floor slab and beam 23 days Tue 5/24/16 Wed 6/15/16 100%
43 Columns & Stair case 3FL to roof level 32 days Sun 6/19/16 Wed 7/20/16 100%
44 Reinforcement work for Column - 3rd FL to 10 days Sun 6/19/16 Tue 6/28/16 100%
roof level
45 Form work in Column - 3rd FL to roof level 10 days Thu 6/23/16 Sat 7/2/16 100%
46 Concreting work for column -3rd FL to roof 10 days Mon 6/27/16 Wed 7/6/16 100%
level
47 Roof beam r/form work and concreting 20 days Fri 7/1/16 Wed 7/20/16 100%
49 Roof frame work fabrication work 30 days Wed 7/6/16 Thu 8/4/16 100%
53 Brick Masonry Work 158 days Tue 3/29/16 Fri 9/16/16 100%
58 Wall and soffit Plastering 182 days Sun 5/8/16 Sat 11/5/16 100%
59 Internal plastering in Ground floor 20 days Sun 5/8/16 Fri 5/27/16 100%
60 Internal plastering in 1st floor 35 days Wed 7/6/16 Tue 8/9/16 100%
61 Internal plastering in 2nd floor 35 days Tue 8/23/16 Mon 9/26/16 100%
62 Internal plastering in 3rd floor 35 days Sun 10/2/16 Sat 11/5/16 100%
64 Wall finishes & Floor finishes 182 days Thu 6/2/16Wed 11/30/16 100%
69 Aluminum and timber Doors & Windows 322 days Tue 3/29/16 Mon 2/27/17 86%
79 Internal primary coat & External painting 242 days Wed 6/22/16 Sat 2/18/17 100%
86 Plumbing work electrical and fire 252 days Sat 4/23/16 Fri 12/30/16 100%
87 Internal Plumbing and water proofing 180 days Sat 4/23/16Wed 10/19/16 100%
93 Sanitary fittings and accessories Installation 30 days Thu 12/1/16 Fri 12/30/16 100%
94 Electrical, telephone and data wiring and 317 days Sat 3/5/16 Sun 1/29/17 90%
installation work
95 first floor conduit laying 3 days Sat 3/5/16 Mon 3/7/16 100%
96 2nd floor conduit laying 3 days Tue 5/3/16 Thu 5/5/16 100%
97 3rd floor conduit laying 3 days Mon 6/13/16 Wed 6/15/16 100%
98 electrical wiring ground floor 25 days Sat 4/23/16 Tue 5/17/16 100%
99 wiring of ground floor for electrical ,data and 25 days Tue 6/21/16 Fri 7/15/16 100%
telephone
100 wiring of 1st floor for electrical ,data and 25 days Mon 8/8/16 Thu 9/1/16 100%
telephone
101 wiring of 2nd floor for electrical ,data and 25 days Mon 8/8/16 Thu 9/1/16 80%
telephone
102 wiring of 3rd floor for electrical ,data and 25 days Sat 9/17/16 Tue 80%
telephone 10/11/16
103 fixing electrical,data,telephone fittings and 40 days Wed 12/21/16 Sun 1/29/17 80%
accessories
105 Fixing fire alam system and fire protection system 15 days Sun 1/22/17 Sun 2/5/17 100%
106 wiring for Public address system with multimedia 20 days Sat 9/17/16 Thu 10/6/16 100%
107 Public address system with multimedia installation 22 days Sun 1/22/17 Sun 2/12/17 100%
work
110 Construction of underground water sump 65 days Mon 1/30/17 Tue 4/4/17 100%
111 Site clearing before handover 10 days Wed 4/5/17 Wed 4/26/17 0%
Project: Progress as programm mgt Task Summary Rolled Up Milestone Split Project Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Split Deadline
Date: Mon 5/1/17
Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only Critical Progress Manual Progress
KANDY CONSTRUCTIONS