ACTUALPROGRES UP TO 02.05.

2017 FOR PROPOSED FOUR STORIED BUILDING PROJECT AT FACULTY OF MANAGMENT AND FINANCE,UNIVERSITY OF COLOMBO
ID Task Name Duration Start Finish %
Complete 2016 2017
November December January February March April May June July August September October November December January February March April May
25 1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30
0 Progress as programm mgt 520 days Fri 10/30/15 Thu 4/27/17 95%

1 Designing phase 30 days Fri 10/30/15 Sat 11/28/15 100%

2 Mobilization of Project 14 days Fri 10/30/15 Thu 11/12/15 100%

3 Getting approval for entrance gate from CMC 14 days Thu 11/19/15 Wed 12/2/15 100%

4 Demolishing Existing building and removing trees 10 days Mon 12/7/15Wed 12/16/15 100%

5 Substructure 62 days Thu 12/17/15 Tue 2/16/16 100%

6 Setting out of building 2 days Thu 12/17/15 Fri 12/18/15 100%

7 Excavation for ground improvement for 27 days Sat 12/19/15 Thu 1/14/16 100%
foundation

8 Quarry dust filling under strip foundation 21 days Thu 12/24/15 Wed 1/13/16 100%

9 Screed concreting for foundation & lift well base 22 days Mon 12/28/15 Mon 1/18/16 100%

10 footing r/f work 21 days Fri 1/1/16 Thu 1/21/16 100%

11 Form work of footing 18 days Mon 1/4/16 Thu 1/21/16 100%

12 Concreting of footing 15 days Wed 1/6/16 Wed 1/20/16 100%

13 Column R/F work up to ground level 8 days Sun 1/10/16 Sun 1/17/16 100%

14 Column form work up to GL 8 days Tue 1/12/16 Tue 1/19/16 100%

15 Concreting of column up to GL 8 days Wed 1/13/16 Wed 1/20/16 100%

16 Rubble work and tie beam concreting 15 days Sat 1/23/16 Sat 2/6/16 100%

17 Back filling & Filling under floors 18 days Sat 1/30/16 Tue 2/16/16 100%

18 Superstructure 199 days Sun 2/7/16 Tue 9/6/16 100%

19 Columns & Stair case GL to 1st F 14 days Sun 2/7/16 Sat 2/20/16 100%

20 Reinforcement work for Column - GFL to1st FL 10 days Sun 2/7/16 Tue 2/16/16 100%

21 Form work in Column - GFL to 1st FL 10 days Tue 2/9/16 Thu 2/18/16 100%

22 Concreting work for column GFL to 1st FL 10 days Thu 2/11/16 Sat 2/20/16 100%

23 1st Floor slab and beam 22 days Mon 2/15/16 Mon 3/7/16 100%

24 Form work 18 days Mon 2/15/16 Thu 3/3/16 100%

25 Reinforcement work 13 days Mon 2/22/16 Sat 3/5/16 100%

26 Concreting work 1 day Mon 3/7/16 Mon 3/7/16 100%

27 Column & Stair case 1FL to 2FL 16 days Thu 3/10/16 Fri 3/25/16 100%

28 Reinforcement work for Column - 1st FL to 10 days Thu 3/10/16 Sat 3/19/16 100%
2ndt FL

29 Form work in Column - 1st FL to 2nd FL 10 days Sun 3/13/16 Tue 3/22/16 100%

30 Concreting work for column - 1st FL to 2nd FL 10 days Wed 3/16/16 Fri 3/25/16 100%

31 2nd Floor slab and beam 27 days Sat 3/26/16 Thu 5/5/16 100%

32 Form work 19 days Sat 3/26/16 Wed 4/27/16 100%

33 Reinforcement work 12 days Fri 4/22/16 Tue 5/3/16 100%

34 Concreting work 1 day Thu 5/5/16 Thu 5/5/16 100%

35 Column & Stair case 2FL to 3FL 20 days Tue 5/10/16 Sun 5/29/16 100%

36 Reinforcement work for Column - 2nd FL to 3rd FL10 days Tue 5/10/16 Thu 5/19/16 100%

37 Form work in Column - 2nd FL to 3rd FL 10 days Sun 5/15/16 Tue 5/24/16 100%

38 Concreting work for column - 2nd FL to 3rd FL 10 days Fri 5/20/16 Sun 5/29/16 100%

39 3rd Floor slab and beam 23 days Tue 5/24/16 Wed 6/15/16 100%

40 Form work 20 days Tue 5/24/16 Sun 6/12/16 100%

41 Reinforcement work 13 days Wed 6/1/16 Mon 6/13/16 100%

42 Concreting work 1 day Wed 6/15/16 Wed 6/15/16 100%

43 Columns & Stair case 3FL to roof level 32 days Sun 6/19/16 Wed 7/20/16 100%

44 Reinforcement work for Column - 3rd FL to 10 days Sun 6/19/16 Tue 6/28/16 100%
roof level

45 Form work in Column - 3rd FL to roof level 10 days Thu 6/23/16 Sat 7/2/16 100%

46 Concreting work for column -3rd FL to roof 10 days Mon 6/27/16 Wed 7/6/16 100%
level

47 Roof beam r/form work and concreting 20 days Fri 7/1/16 Wed 7/20/16 100%

48 Roof work 63 days Wed 7/6/16 Tue 9/6/16 100%

49 Roof frame work fabrication work 30 days Wed 7/6/16 Thu 8/4/16 100%

50 Roof erection work 18 days Thu 7/21/16 Sun 8/7/16 100%

51 Roof covering 15 days Mon 8/8/16 Mon 8/22/16 100%

52 Roof plumbing 15 days Tue 8/23/16 Tue 9/6/16 100%

53 Brick Masonry Work 158 days Tue 3/29/16 Fri 9/16/16 100%

54 Ground floor 11 days Tue 3/29/16 Fri 4/22/16 100%

55 1st Floor 25 days Fri 5/27/16 Mon 6/20/16 100%

56 2nd Floor 25 days Thu 7/14/16 Sun 8/7/16 100%

57 3rd Floor 25 days Tue 8/23/16 Fri 9/16/16 100%

58 Wall and soffit Plastering 182 days Sun 5/8/16 Sat 11/5/16 100%

59 Internal plastering in Ground floor 20 days Sun 5/8/16 Fri 5/27/16 100%

60 Internal plastering in 1st floor 35 days Wed 7/6/16 Tue 8/9/16 100%

61 Internal plastering in 2nd floor 35 days Tue 8/23/16 Mon 9/26/16 100%

62 Internal plastering in 3rd floor 35 days Sun 10/2/16 Sat 11/5/16 100%

63 External Plastering 34 days Sat 9/17/16 Thu 10/20/16 100%

64 Wall finishes & Floor finishes 182 days Thu 6/2/16Wed 11/30/16 100%

65 Ground floor 20 days Thu 6/2/16 Tue 6/21/16 100%

66 1st Floor 20 days Mon 8/15/16 Sat 9/3/16 100%

67 2nd Floor 20 days Sun 10/2/16 Fri 10/21/16 100%

68 3rd Floor 20 days Fri 11/11/16Wed 11/30/16 100%

69 Aluminum and timber Doors & Windows 322 days Tue 3/29/16 Mon 2/27/17 86%

70 Ground floor AL 20 days Sat 10/29/16 Thu 11/17/16 100%

71 1st Floor AL 25 days Sun 11/27/16Wed 12/21/16 100%

72 2nd Floor AL 25 days Fri 12/30/16 Mon 1/23/17 100%

73 3rd Floor AL 25 days Fri 2/3/17 Mon 2/27/17 100%

74 Ground floor timber 25 days Thu 3/31/16 Sun 5/8/16 100%

75 1st floor timber 25 days Fri 5/27/16 Mon 6/20/16 100%

76 2nd floor timber 25 days Thu 7/14/16 Sun 8/7/16 100%

77 3rd floor timber 25 days Tue 8/23/16 Fri 9/16/16 100%

78 Ceiling finishes 32 days Wed 12/21/16 Sat 1/21/17 0%

79 Internal primary coat & External painting 242 days Wed 6/22/16 Sat 2/18/17 100%

80 Ground floor 20 days Wed 6/22/16 Mon 7/11/16 100%

81 1st Floor 20 days Sun 9/4/16 Fri 9/23/16 100%

82 2nd Floor 20 days Sat 10/22/16 Thu 11/10/16 100%

83 3rd Floor 20 days Thu 12/1/16 Tue 12/20/16 100%

84 External 25 days Wed 12/21/16 Sat 1/14/17 100%

85 Final painting 35 days Sun 1/15/17 Sat 2/18/17 100%

86 Plumbing work electrical and fire 252 days Sat 4/23/16 Fri 12/30/16 100%

87 Internal Plumbing and water proofing 180 days Sat 4/23/16Wed 10/19/16 100%

88 Ground floor 15 days Sat 4/23/16 Sat 5/7/16 100%

89 First Floor 15 days Tue 6/21/16 Tue 7/5/16 100%

90 2nd floor 15 days Mon 8/8/16 Mon 8/22/16 100%

91 3rd Floor 33 days Sat 9/17/16Wed 10/19/16 100%

92 External plumbing 20 days Sun 10/23/16 Fri 11/11/16 100%

93 Sanitary fittings and accessories Installation 30 days Thu 12/1/16 Fri 12/30/16 100%

94 Electrical, telephone and data wiring and 317 days Sat 3/5/16 Sun 1/29/17 90%
installation work

95 first floor conduit laying 3 days Sat 3/5/16 Mon 3/7/16 100%

96 2nd floor conduit laying 3 days Tue 5/3/16 Thu 5/5/16 100%

97 3rd floor conduit laying 3 days Mon 6/13/16 Wed 6/15/16 100%

98 electrical wiring ground floor 25 days Sat 4/23/16 Tue 5/17/16 100%

99 wiring of ground floor for electrical ,data and 25 days Tue 6/21/16 Fri 7/15/16 100%
telephone

100 wiring of 1st floor for electrical ,data and 25 days Mon 8/8/16 Thu 9/1/16 100%
telephone

101 wiring of 2nd floor for electrical ,data and 25 days Mon 8/8/16 Thu 9/1/16 80%
telephone

102 wiring of 3rd floor for electrical ,data and 25 days Sat 9/17/16 Tue 80%
telephone 10/11/16

103 fixing electrical,data,telephone fittings and 40 days Wed 12/21/16 Sun 1/29/17 80%
accessories

104 Fire installation 43 days Tue 9/20/16 Tue 11/1/16 100%

105 Fixing fire alam system and fire protection system 15 days Sun 1/22/17 Sun 2/5/17 100%

106 wiring for Public address system with multimedia 20 days Sat 9/17/16 Thu 10/6/16 100%

107 Public address system with multimedia installation 22 days Sun 1/22/17 Sun 2/12/17 100%
work

108 Lightning protection 20 days Tue 8/23/16 Sun 9/11/16 100%

109 Landscaping 40 days Sun 1/15/17 Thu 2/23/17 30%

110 Construction of underground water sump 65 days Mon 1/30/17 Tue 4/4/17 100%

111 Site clearing before handover 10 days Wed 4/5/17 Wed 4/26/17 0%

112 Handover the project 1 day Thu 4/27/17 Thu 4/27/17 0%

Project: Progress as programm mgt Task Summary Rolled Up Milestone Split Project Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Critical Split Deadline
Date: Mon 5/1/17
Milestone Rolled Up Task Rolled Up Progress External Tasks Group By Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only Critical Progress Manual Progress

KANDY CONSTRUCTIONS