Professional Documents
Culture Documents
COLLEGE OF TECHNOLOGY
CONSTRUCTION TECHNOLOGY & MANAGEMENT DEPARTMENT
April,11/ 2017
1. Project Objective
The main objective of this semester poject is to make students more familiar with the
process of construction cost estimating with respect to project direct cost, indirect cost
and profit.
And its specific objective is to estimate the construction cost of a residential building
through a detail unit rate analysis of project activities.
A. Cost breakdown (unit rate analysis) sheet for each activity of the project
Refer the format from the attachment
Each group project progress will be strictly assessed and evaluated every week. And each
member of the group will be evaluated individually.
The final project should be done on MS-Excel and submitted both in hard copy and soft
copy.
ACTIVITY OUT PUT(Hourly)
SITE WORK
EARTHWORK
01 site clearance at the depths of 200mm
02) Bulk excavation from stripped level in Black,soft,high plastic silty clay soil to an average depth of 15
bring to a levelled surface.
02) Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a depth exceeding 150cms bu
exceeding 300cms.
03)Excavate for isolated footings in reddish to yellowish silty clay, reddish brown or reddish friable san
silty clay soil to a depth exceeding 900cms but not exceeding 1050cms.
06 ) Backfill around foundations and retaining walls with granular selected material brought from quar
material should be tested to conform with required standards and should be approved by the Engineer p
execution. Compaction should also be carried out to fulfil standard requirements.
07)Load and cart away all surplus excavated materials to a suitable pit as may be found by the contract
in the accespable range of the city adminstration.
08)Supply basaltic or equivalent stone for 25cm thick hard core on top of compacted fill materials and b
bottom basement floor slab to be well rolled, consolidated and blinded with crushed stone aggregates. L
shall be measured separately.
Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content of 150 kg/m
shall include sika or equivalent cement water proofing to be added to all foundation footings beams slab
column. b) Under grade beams
Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content of 150 kg/m
shall include sika or equivalent cement water proofing to be added to all foundation footings beams slab
column. b) Under grade beams
Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content of 150 kg/m
shall include sika or equivalent cement water proofing to be added to all foundation footings beams slab
column.c) Under floor slabs
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) a) In foundation columns and elevation columns
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column. a) In 500mm thick Mat slab
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column. b) Beams
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column.c) In footing pads
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) d) In Basemnt columns
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) g) In footing and grade beams
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) h) In suspended beams
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column.j) In staircase steps & landings
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column.j) In staircase steps & landings
03)Provide, erect or lay mild reinforcement steel S-400. It must be ensured that bars are free of any lubr
mud or any other impurities before concrete is poured onto them. Price shall include cutting, bending, p
position and tying wires.21 to 33)Rein. bar from dia =8 to 16mm
03) 20cm thick HCB wall wthin the basement floor, embedded in cement-sand mortar of 1:3 mix ratio
shall be left for plastering.
04 )15cm thick HCB block work cement sand ratio
05)10cm thick perforated HCB block work left for pointing
plastering
1. Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster or ceramic
To internal wall surface,and columns, to external wall surface, exposed beams and columns ,to roof par
2. Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster or ceramic
To RC ceiling, exposed beams,stair case soffit and sides of lift shaft walls
3. Apply one coat of gypsum finishing work on top of plastering for a) To RC ceilings, stair case soffit and
shaft walls
4. Apply one coat of gypsum finishing work on top of plastering for b)To internal wall, column, and beam
8.2) Ditto but to RC ceiling, stair case soffit and sides of lift shaft walls
steel work
1) Semi Solid Wooden Doors
A. sub structure
1. EARTH WORK
2
WORK ITEM:1.01 hourly out put 1.25 m /hr
ACTIVITY site clearance at the depths of 200mm equipment:hand tool
2 2
UNIT QUANTITY OF ACTIVITY:1m result 68.53 Birr/m
WORK ITEM:1.04
3
ACTIVITY pit excavation in reddish to yellowish silt clay,reddish brown sandy hourly out put 4.00 m /hr
clay soil to adepth of 1500 mm from reduced level EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 287.93 Birr/m
ACTIVITY: ditto as item 1.05 but depth exceeded 1500mm & not exceeding 3000mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 354.37 Birr/m
Work item:1.06
3
ACTIVITY: ditto as item 1.05 but depth exceeded 3000mm & not exceeding 4500mm hourly out put 2.50 m /hr
3
UNIT QUANTITY OF ACTIVITY:1m EQUIPMENT:HANDTOOL & EXCAVATOR
3
result 460.68 Birr/m
ACTIVITY: ditto as item no 1.05 but depth exceeded 4500mm & not exceeding 6000mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 575.85 Birr/m
3
Work item:1.08 hourly out put 1.50 m /hr
ACTIVITY: ditto as item 1.05 but depth exceeded 6000mm & not exceeding 7500mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 767.80 Birr/m
ACTIVITY: ditto as item 1.05 but depth exceeded 7500mm & not exceeding 9000mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 1151.70 Birr/m
3
Work item:1.10 labour hourly out put 0.75 m /hr
ACTIVITY: ditto as item 1.05 but depth exceeded 9000mm & not exceeding 10500mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 1535.61 Birr/m
3
Work item:1.12 hourly out put 1.25 m /hr
ACTIVITY: selected borrowed fill materials equipment:hand tool &HAND COMPACTOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 396.33 Birr/m
3
ACTIVITY: Backfill around foundations and retaining walls with granular selected material brought from quarry hourly out put 1.25 m /hr
equipment:hand tool &HAND COMPACTOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 396.33 Birr/m
3
Work item:1.14 hourly out put 4.00 m /hr
ACTIVITY: Load and cart away all surplus excavated materials to a suitable pit equipment:hand tool &DUMPTRUCK
3 3
UNIT QUANTITY OF ACTIVITY:1m result 360.03 Birr/m
B. super structure
1.CONCRETE WORK
Work item:1.01 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
ACTIVITY: of 150 kg/m3
2
under footing pads labour hourly out put 1.00 m /hr
2
UNIT QUANTITY OF ACTIVITY:1M equipment:mixer.vibrator, MIXER &hand tools
2
result 4531.05 Birr/m
2
Work item:1.03 hourly out put 1.00 m /hr
ACTIVITY:dtto as item 1.01 but under grade beams equipment:mixer.vibrator&hand tools
2 2
UNIT QUANTITY OF ACTIVITY:1M result 4531.05 Birr/m s
3
Work item:1.05 labour hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in 500mm thick mat slab equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m
3
Work item :1.07 hourly out put 0.75 m /hr
ACTIVITY: ditto as item 1.04 but in FOOTING PADS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 13431.28 Birr/m
3
Work item:1.09 hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in FOOTING & GRADE BEAMS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m
3
Work item:1.11 hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in STAIRCASE &LANDINGS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m
2
WORK ITEM: 3.03 hourly out put 0.75 M /hr
ACTIVITY:10cm thick perforated HCB block work left for pointing equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 658.83 Birr/M
5. PAINTING
2
WORK ITEM: 5.01 hourly out put 2.50 M /hr
ACTIVITY: Apply three coats of plastic emulsion paint to internal wall surfaces, columns and beams. equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 68.79 Birr/M
6 RHS WORKS
7. LATTUCE PURLIN
9. ROOF COVER
2
WORK ITEM: 9.01 hourly out put 2.00 M hr
ACTIVITY: Roof cover in EGA 400, 0.4mm thick equipment:HAND TOOLS
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 997.56 Birr/M
EARTHWORK
2
1.00 site clearance at the depths of 200mm m 68.53
2.00 Bulk excavation from stripped level in Black,soft,high plastic silty clay soil to an average
3
depth of 150cms and bring to a levelled surface. m 287.44
Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a depth exceeding 150cms but
3.00 not exceeding 300cms. 575.85
3
m
4.00
Excavate for isolated footings in reddish to yellowish silty clay, reddish brown or reddish
3
friable sandy silty or silty clay soil to a depth exceeding not exceeding 1500mm. m 287.93
3
ditto but depth exceeded 1500mm & not exceeding 3000mm m 354.37
3
ditto but depth exceeded 3000mm & not exceeding4500mm m 460.68
3
ditto but depth exceeded 4500mm & not exceeding 6000mm m 575.85
3
ditto but depth exceeded 6000mm & not exceeding 7500mm m 767.80
3
ditto but depth exceeded 7500mm & not exceeding 9000mm m 1151.70
3
ditto but depth exceeded 9000mm & not exceeding 10500mm m 1535.61
3
5.00 Trench excavation not exceeding 1.5m m 309.34
selected borrowed fill materials 3
6.00 m 396.33
7.00 Backfill around foundations and retaining walls with granular selected material brought
from quarry . Backfill material should be tested to conform with required standards and
should be approved by the Engineer prior to execution. Compaction should also be carried
3
out to fulfil standard requirements. m 396.33
8.00 Load and cart away all surplus excavated materials to a suitable pit as may be found by the
contractor and with in the accespable range of the city adminstration.
3
m 360.03
9.00
Supply basaltic or equivalent stone for 25cm thick hard core on top of compacted fill
materials and beneath the bottom basement floor slab to be well rolled, consolidated and
blinded with crushed stone aggregates. Lean concrete shall be measured separately. 3
m 956.74
Super STRUCTURE CONCRETE WORK
CONCRETE WORK IN SITU CONCRETE
10.00 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
of 150 kg/m3. Price shall include sika or equivalent cement water proofing to be added to all
foundation footings beams slab and column. a) Under footing pads
2
m 4531.05
11.00 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
of 150 kg/m3. Price shall include sika or equivalent cement water proofing to be added to all
foundation footings beams slab and column. b) Under grade beams
2
m 4353.76
12.00 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
of 150 kg/m3. Price shall include sika or equivalent cement water proofing to be added to all
foundation footings beams slab and column.c) Under floor slabs
2
m 4531.05
13.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) a) In foundation columns and elevation
columns
3
m 13145.36
14.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column. a) In
500mm thick Mat slab
3
m 12973.80
15.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column. b)
Beams
3
m 12973.80
16.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column.c) In
footing pads
3
m 13431.28
17.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) d) In Basemnt columns
3
m 13431.28
18.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) e) In footing and grade beams
3
m 12973.80
19.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) f) In suspended beams
3
m 12973.80
20.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column.g) In
staircase steps & landings
3
m 12973.80
21.00 Provide, erect or lay mild reinforcement steel S-400. It must be ensured that bars are free of
any lubricants, dirt, mud or any other impurities before concrete is poured onto them. Price
shall include cutting, bending, placing in position and tying wires. 8mm
reinforcement bar
kg 49.57
10mm reinforcement bar kg 49.57
12mm reinforcement bar kg 46.43
14mm reinforcement bar kg 48.00
16mm reinforcement bar kg 58.05
22.00 20cm thick HCB wall wthin the basement floor, embedded in cement-sand mortar of 1:3 mix
2
ratio. Both sides shall be left for plastering. m 750.64
23.00 15cm thick HCB block work cement sand ratio m
2
704.74
24.00 10cm thick perforated HCB block work left for pointing
plastering m
2
658.83
25.00 Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster
or ceramic wall tile. a) To internal wall surface,and columns, to external wall surface,
exposed beams and columns ,to roof parapet.
2
m 246.38
26.00 Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster
or ceramic wall tile. b) To RC ceiling, exposed beams,stair case soffit and sides of lift shaft
2
walls m 274.10
2
28.00 78mm thick cement sand screed m 711.37
29.00 Apply three coats of plastic emulsion paint to internal wall surfaces, columns and beams.
2
m 68.79
Ditto but to RC ceiling, stair case soffit and sides of lift shaft walls m
2
68.79
30.00 For all RHS Works of size RHS 80x80x3 mm
a) RHS 80x80x3 mm kg 467.50
b) RHS 60x60x3 mm kg 263.43
c) RHS 50x50x3 mm kg 216.34
d) RHS 40x40x3 mm kg 51.15
31.00 For all PURLIN
a) RHS 80x80x3 mm kg 467.50
b) RHS 60x60x3 mm kg 249.97
c) RHS 30x30x3 mm kg 61.78
COLLEGE OF ENGINEERING
NAME ID.NO.
1 YARED WUBSHET DBU07000691UR
GROUP 1
SETION -C
Acknowledgment
We would like to acknowledge our lecturer Admasu Bogale, B.Sc. in
construction technology and management for his unlimited support
during the out come of this project, starting form supplying the necessary
data ,and forwarding different informations .Beside this, we would like to
thank him again, for his friendly and professional approach to advise us.
It would have been impossible to have this project completed without the
help of the above mentioned person & our peergroups from major to least
help. Finally ,yet importantly, we would like to thank our families for their
constant and priceless support in different aspects.