DEBRE BERHAN UNIVERSITY

COLLEGE OF TECHNOLOGY
CONSTRUCTION TECHNOLOGY & MANAGEMENT DEPARTMENT

Cost Engineering (CoTM 3212)

GUIDLINE POINTS FOR SEMESTER PROJECT


ON
CONSTRUCTION COST ESTIMATION OF RESIDENTIAL
BUILDING

April,11/ 2017
1. Project Objective

The main objective of this semester poject is to make students more familiar with the
process of construction cost estimating with respect to project direct cost, indirect cost
and profit.

And its specific objective is to estimate the construction cost of a residential building
through a detail unit rate analysis of project activities.

2. Expected outputs from the project

A. Cost breakdown (unit rate analysis) sheet for each activity of the project
Refer the format from the attachment

B. Material price per unit sheet


Refer the format from the attachment

C. Material quantity calculation sheet for major activities of the project

D. Calculation sheet for material transport, loading and unloading costs

E. Required targated cost analysis for the project


Refer the format from the attachment

F. Direct labor indexed hourly rate sheet


Refer the format from the attachment

G. Labor benefit factor (Index factor) calculation sheet

H. Equipment hourly rental rate cost sheet


Refer the format from the attachment

I. Site overhead cost calculation sheet

J. Head office overhead cost calculation sheet

3. Project Assessment /Evaluation

Each group project progress will be strictly assessed and evaluated every week. And each
member of the group will be evaluated individually.

The final project should be done on MS-Excel and submitted both in hard copy and soft
copy.
ACTIVITY OUT PUT(Hourly)

SITE WORK
EARTHWORK
01 site clearance at the depths of 200mm

02) Bulk excavation from stripped level in Black,soft,high plastic silty clay soil to an average depth of 15
bring to a levelled surface.

02) Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a depth exceeding 150cms bu
exceeding 300cms.

03)Excavate for isolated footings in reddish to yellowish silty clay, reddish brown or reddish friable san
silty clay soil to a depth exceeding 900cms but not exceeding 1050cms.

04) Trench excavation not exceeding 1.5m

05 ) selected borrowed fill materials

06 ) Backfill around foundations and retaining walls with granular selected material brought from quar
material should be tested to conform with required standards and should be approved by the Engineer p
execution. Compaction should also be carried out to fulfil standard requirements.

07)Load and cart away all surplus excavated materials to a suitable pit as may be found by the contract
in the accespable range of the city adminstration.

08)Supply basaltic or equivalent stone for 25cm thick hard core on top of compacted fill materials and b
bottom basement floor slab to be well rolled, consolidated and blinded with crushed stone aggregates. L
shall be measured separately.

A2. SUpSTRUCTURE CONCRETE WORK


0.3 CONCRETE WORK IN SITU CONCRETE
1)Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content of 150 kg/
shall include sika or equivalent cement water proofing to be added to all foundation footings beams slab
column. a) Under footing pads

Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content of 150 kg/m
shall include sika or equivalent cement water proofing to be added to all foundation footings beams slab
column. b) Under grade beams
Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content of 150 kg/m
shall include sika or equivalent cement water proofing to be added to all foundation footings beams slab
column. b) Under grade beams

Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content of 150 kg/m
shall include sika or equivalent cement water proofing to be added to all foundation footings beams slab
column.c) Under floor slabs

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) a) In foundation columns and elevation columns

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column. a) In 500mm thick Mat slab

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column. b) Beams

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column.c) In footing pads

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) d) In Basemnt columns

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) g) In footing and grade beams

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately) h) In suspended beams

02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column.j) In staircase steps & landings
02) Produce and place reinforced concrete class C-30, with minimum OPC cement content of 400kg/m3
filled in to form work and vibrated around rod reinforcement steel. (Formwork and reinforcement measu
separately).Price shall include sika or equivalent cement water proofing to be added to all foundation foo
slab and column.j) In staircase steps & landings

03)Provide, erect or lay mild reinforcement steel S-400. It must be ensured that bars are free of any lubr
mud or any other impurities before concrete is poured onto them. Price shall include cutting, bending, p
position and tying wires.21 to 33)Rein. bar from dia =8 to 16mm

03) 20cm thick HCB wall wthin the basement floor, embedded in cement-sand mortar of 1:3 mix ratio
shall be left for plastering.
04 )15cm thick HCB block work cement sand ratio
05)10cm thick perforated HCB block work left for pointing
plastering
1. Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster or ceramic
To internal wall surface,and columns, to external wall surface, exposed beams and columns ,to roof par

2. Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster or ceramic
To RC ceiling, exposed beams,stair case soffit and sides of lift shaft walls

3. Apply one coat of gypsum finishing work on top of plastering for a) To RC ceilings, stair case soffit and
shaft walls
4. Apply one coat of gypsum finishing work on top of plastering for b)To internal wall, column, and beam

5) 78mm thick cement sand screed


A8 PAINTING
8.1) Apply three coats of plastic emulsion paint to internal wall surfaces, columns and beams.

8.2) Ditto but to RC ceiling, stair case soffit and sides of lift shaft walls

1) For all RHS Works of size RHS 80x80x3 mm


a) RHS 80x80x3 mm
b) RHS 60x60x3 mm
c) RHS 50x50x3 mm
d) RHS 40x40x3 mm
2) For all PURLIN
a) RHS 80x80x3 mm
b) RHS 60x60x3 mm
c) RHS 30x30x3 mm

3) Anchor bolt (J-Bolt) dia 16 mm development length 400 mm


1 ) Roof cover in EGA 400, 0.4mm thick

steel work
1) Semi Solid Wooden Doors

2) Fabricate or supply and fix doors made of steel-reinforced PVC Doors


2) Fabricate or supply and fix doors made of steel-reinforced PVC Doors
3)wooden frames cupboards
Benefit (index) Factor Calculation sheet
No description no of days calculation index
A basic salary 1
B index factor
working days per year 298.00
B1 annual leave 14 14/298 0.05
B2 sick leave 3 3/298 0.01
B3 mouring leave 3 3/298 0.01
B4 labor affairs 3 3/298 0.01
B5 public holiday 15 15/298 0.05
B6 Sunday 52 52/298 0.17
B8 accident 0.1
B9 iddle time pay 0.1
total index 1.50
Direct labor indexed hourly rate
Daily rate (Br) Indexed
Item Working Hourly Index
Description of labor hourly rate
No. hours/day rate (Br.) factor
(Br.)
maximum minimum average
1.00 Forman 230.00 200.00 215.00 8.00 26.88 1.50 40.37
2.00 Loader oprator 380.00 350.00 365.00 8.00 45.63 1.50 68.53
3.00 Dump truck driver 330.00 300.00 315.00 8.00 39.38 1.50 59.14
4.00 Carpenter 250.00 220.00 235.00 8.00 29.38 1.50 44.12
5.00 Mason 250.00 220.00 235.00 8.00 29.38 1.50 44.12
6.00 Welder 180.00 150.00 165.00 8.00 20.63 1.50 30.98
7.00 Plasterer 250.00 220.00 235.00 8.00 29.38 1.50 44.12
8.00 Bar Bender 180.00 150.00 165.00 8.00 20.63 1.50 30.98
9.00 bar cutter 180.00 150.00 165.00 8.00 20.63 1.50 30.98
10.00 Painter, Decorator 180.00 150.00 165.00 8.00 20.63 1.50 30.98
11.00 Mixer operator 180.00 150.00 165.00 8.00 20.63 1.50 30.98
12.00 Vibrator operator 180.00 150.00 165.00 8.00 20.63 1.50 30.98
13.00 Sledge hammer man 150.00 120.00 135.00 8.00 16.88 1.50 25.35
13.00 Jack hammer operator 380.00 350.00 365.00 8.00 45.63 1.50 68.53
14.00 Gang Chief 130.00 100.00 115.00 8.00 14.38 1.50 21.59
15.00 Daily Labourer 100.00 70.00 85.00 8.00 10.63 1.50 15.96
16.00 Electrician 150.00 120.00 135.00 8.00 16.88 1.50 25.35
17.00 Plumber 165.00 135.00 150.00 8.00 18.75 1.50 28.16
18.00 Chiseler 160.00 130.00 145.00 8.00 18.13 1.50 27.22
19.00 Chiseler &Decorator 312.00 282.00 297.00 8.00 37.13 1.50 55.76
20.00 Grinder 130.00 100.00 115.00 8.00 14.38 1.50 21.59
21.00 Tailer 250.00 220.00 235.00 8.00 29.38 1.50 44.12
22.00 Proofer 180.00 150.00 165.00 8.00 20.63 1.50 30.98
23.00 Helper 120.00 90.00 105.00 8.00 13.13 1.50 19.71
24.00 Glazer 210.00 180.00 195.00 8.00 24.38 1.50 36.61
25.00 excavatorr operator 380.00 350.00 365.00 8.00 45.63 1.50 68.53
26.00 dozer operator 380.00 350.00 365.00 8.00 45.63 1.50 68.53
Material price per unit sheet
Loading Total
Selling unit
Selling unit Transportati & mateiral
Item No. Type of material Unit price with
price (Br.) on cost (Br.) Unloading price per
VAT (Br.)
cost (Br.) unit (Br.)
1.00 Cement
PPC for others concrete except pre-cast
kg 2.40 2.76
1.10 beam 10.40 0.08 13.24
1.20 OPC for pre-cast beam kg 3.60 4.14 10.40 0.08 14.62
3
2.00 Sand m 375.00 375.00
3
3.00 Aggregate 02 for concrete m 312.50 312.50
4.00 selected material m
3
125.00 125.00
5.00 Lime kg 4.14 4.76 10.40 0.08 15.24
3
6.00 Bazaltic stone m 250.00 250.00
7.00 Reinforcement bar 0.00
7.10 a) 6mm kg 27.00 31.05 31.05
7.20 b) 8mm kg 21.00 24.15 24.15
7.30 c) 10mm kg 21.00 24.15 24.15
7.40 d) 12mm kg 19.00 21.85 21.85
7.50 e) 14mm kg 20.00 23.00 23.00
7.60 f) 16mm kg 26.40 30.36 30.36
7.70 g)20mm kg 26.40 30.36 30.36
8.00 G-28 EGA
2
8.10 G-28 EGA 300MM THICK) white colore m 165.30 190.10 190.10
2
8.20 G-28 EGA 400MM THICK) white colore m 188.00 216.20 216.20
8.20 G-28 EGA 500MM THICK) white colore m2 192.00 220.80 220.80
2
8.30 G-28 EGA 400MM THICK) colored m 196.00 225.40 225.40
9.00 Hollow block
9.10 Hollow block class C 20cm thick pcs 12.00 13.80 13.80
9.20 Hollow block class C15cm thick pcs 9.00 10.35 10.35
9.30 Hollow block class C10cm thick pcs 7.50 8.63 8.63
9.40 Hollow block class B 20cm thick pcs 17.00 19.55 19.55
9.50 Hollow block class B15cm thick pcs 14.10 16.22 16.22
9.60 Hollow block class B10cm thick pcs 12.00 13.80 13.80
9.70 Hollow block class A20cm thick pcs 20.00 23.00 23.00
9.80 Hollow block class A15cm thick pcs 16.00 18.40 18.40
9.90 Hollow block class A10cm thick pcs 12.50 14.38 14.38
10.00 oil paint lit 80.00 92.00 92.00
11.00 Plastic paint lit 40.00 46.00 46.00
12.00 stucco kgs 2.60 2.99 2.99
13.00 Gypsum kgs 4.40 5.06 5.06
14.00 Thinner lit 80.00 92.00 92.00
15.00 Vinavile Glue lit 75.00 86.25 86.25
3
16.00 Water m 0.00 0.00
17.00 Enamel paint lit 75.00 86.25 86.25
18.00 synthetic paint lit 40.00 46.00 46.00
19.00 Animal Glue kg 80.00 92.00 92.00
20.00 RHS 30*30*3mm kgs 22.60 25.99 25.99
21.00 RHS 40*40*3mm kgs 16.20 18.63 18.63
22.00 RHS 50*50*3mm kg 120.00 138.00 138.00
23.00 RHS 60*60*3mm kg 150.00 172.50 172.50
24.00 RHS 80*80*3mm kg 280.00 322.00 322.00
25.00 Tying wire 2.5mm kg 45.00 51.75 51.75
26.00 Nail kg 35.00 40.25 40.25
27.00 Anti-Rust lt 70.00 80.50 80.50
28.00 M 10 bolt no 15.00 17.25 17.25
29.00 Varnish lit 70.00 80.50 80.50
30.00 LTZ 38*0.8mm ml 31.67 36.42 36.42
31.00 LTZ 38*1mm ml 42.00 48.30 48.30
32.00 LTZ 38*1.25mm ml 50.00 57.50 57.50
33.00 LTZ 38*1.5mm ml 58.00 66.70 66.70
34.00 LTZ 28*1mm ml 26.00 29.90 29.90
35.00 LTZ 28*1.1mm ml 21.25 24.44 24.44
36.00 LTZ 28*1.25mm ml 35.00 40.25 40.25
37.00 LTZ 28*1.5mm ml 45.00 51.75 51.75
38.00 key lock & handle no 418.00 480.70 480.70
39.00 Hinges no 0.00 0.00
40.00 Door Handle no 250.00 287.50 287.50
41.00 Electrods 3.2 pcs 1.60 1.84 1.84
42.00 J-bolt(for roof)
42.10 Dia 14,L=160mm J Bolt pcs 25.00 28.75 28.75
42.20 Dia 16,L=400mm J Bolt pcs 65.00 74.75 74.75
42.30 Dia 12,L=100mm J Bolt pcs 55.00 63.25 63.25
42.40 Dia 20,L=300mm J Bolt pcs 70.00 80.50 80.50
42.50 Dia 10,L=10mm J Bolt pcs 45.00 51.75 51.75
2
42.60 play wood m 43.67 50.22 50.22
2
42.70 pvc tile m 200.00 230.00 230.00
Material quantity calculation sheet for major activities
amount
no. description description quantity unit
1 selected material 1
3
wastage 15% 1.15 m
2 bazaltic stone 1
3
wastage 20% 1.2 m
3 5cm c-15 lean concrete(1:3:6)
(w/c=0.5)
cement 1
wastage 5%
2
shirinkage 20% 1.764 qt/m
sand 1
wastage 20%
3 2
shirinkage 30% 0.468 m /m
aggregate 1
wastage 20%
3 2
shirinkage 30% 0.936 m /m
3 2
water 0.063 m /m
4 c-30 reinforced concrete(1:1.25:2)
(w/c=0.4)
cement 1
wastage 5%
3
shirinkage 20% 4.150588235 qt/m
sand 1
wastage 20%
3 3
shirinkage 30% 0.458823529 m /m
aggregate 1
wastage 20%
3 3
shirinkage 30% 10.27764706 m /m
3 3
water 0.118588235 m /m
5 reinforcement bar 1
wastage 5% 1.05 kg/kg
Tying wire 0.02 kg/kg
6 20 cm thick class a block
hcb block 12.5
2
wastage 5% 13.125 pcs/m
15mm thick mortar (1:3) 0.0225
w/c=0.45
cement 1
wastage 5%
3
shirinkage 20% 0.099225 qt/m
sand 1
wastage 20%
3 2
shirinkage 30% 0.026325 m /m
3 2
water 0.003189375 m /m
7 15 cm thick class a block 12.5
3 2
wastage 5% 13.125 m /m
15mm thick mortar (1:3) 0.016875
w/c=0.45
cement 1
wastage 5%
3
shirinkage 20% 0.07441875 qt/m
sand 1
wastage 20%
3 2
shirinkage 30% 0.01974375 m /m
3 2
water 0.002392031 m /m
8 10 cm thick class a block 12.5
3 2
wastage 5% 13.125 m /m
15 mm thick mortar (1:3) 0.01125
w/c=0.45
cement 1
wastage 5%
3
shirinkage 20% 0.0496125 qt/m
sand 1
wastage 20%
3 2
shirinkage 30% 0.0131625 m /m
3 2
water 0.022325625 m /m
9 20mm thick mortar 3 plaster(1:3) 0.02
w/c=0.45
cement 1
wastage 5%
3
shirinkage 20% 0.0882 qt/m
sand 1
wastage 20%
3 2
shirinkage 30% 0.0234 m /m
3 2
water 0.03969 m /m
10 78 MM THICK CEMENT SCREED(1:3)
W/C=0.45 0.078
cement 1
wastage 5%
2
shirinkage 20% 0.34398 qt/m
sand 1
wastage 20%
3 2
shirinkage 30% 0.09126 m /m
3 2
water 0.0110565 m /m
11 PAINTING 1
2
stucco 0.5 kg/m
2
gypsum 0.5 kg/m
2
plastic emulsion 0.2 lt/m
12 RHS
RHS 80x80x3 mm 1
WASTAGE 5% 1.05 kg/kg
ANTI RUST 0.02 lt/kg
RHS 60x60x3 mm 1
WASTAGE 5% 1.05 kg/kg
ANTI RUST 0.02 lt/kg
RHS 50x50x3 mm 1
WASTAGE 5% 1.05 kg/kg
ANTI RUST 0.02 lt/kg
RHS 40x40x3 mm 1
WASTAGE 5% 1.05 kg/kg
ANTI RUST 0.02 lt/kg
14 LATTUCE PURLIN
RHS 80x80x3 mm 1
WASTAGE 5% 1.05 kg/kg
ANTI RUST 0.02 lt/kg
RHS 60x60x3 mm 1
WASTAGE 5% 1.05 kg/kg
ANTI RUST 0.02 lt/kg
RHS 30x30x3 mm 1
WASTAGE 5% 1.05 kg/kg
ANTI RUST 0.02 lt/kg
15 ANCHOR BOLT DIA16 1 pcs
16 EGA 400mm thick 1
2 2
WASTAGE 0% 1 M /m
2
dia 10mm J BOLT 10 PCS/m
17 solid wooden doors
2
Plywood 2 m /pcs
Key/lock & handle 1 pcs/pcs
Hing 2 pcs/pcs
Handle 1 pcs/pcs
nail 0.25 kg/pcs
varnish 0.35 lt/pcs
18 steel-reinforced PVC Doors
LTZ 38*1mm 10 m/Pcs
Hinge 4 pcs/pcs
Key/lock & handle 1 pcs/pcs
anti rust 0.02 Lit/pcs
2
pvc tile 2.52 m /pcs
Handle 1 pcs/pcs
Electrod 0.25 kg/pcs
19 wooden frame cupboards
Plywood 2
2
wastage 5% 2.1 m /pcs
Key/lock & handle 1 pcs/pcs
Hing 3 pcs/pcs
Handle 1 pcs/pcs
nail 0.25 kg/pcs
varnish 0.35 lt/pcs
Equipment hourly rental rate
Item Daily rental Working
Equipment type
No. rate (Br.) hours/day
1.0 Wheel Loader mega 250III 2,000.00 8
2.0 Dump truck 7,000.00 8
3.0 Mixer 360 litter 900.00 8
4.0 Vibrator 900.00 8
5.0 Damper (16 m3 capacity ) 2,200.00 8
6.0 Jack hammer with compressor 8,800.00 8
7.0 Bar Cutter 120.00 8
8.0 Welding Machine 500.00 8
9.0 Grinder 300.00 8
10.0 Generator 800.00 8
11.0 pump 500.00 8
12.0 pick up 2,000.00 8
13.0 Excavater 6,000.00 8
14.0 Pulley 370.00 8
15.0 Hand tools 12.00 8
16.0 Dozzer 16,000.00 8
17.0 Grader 3,840.00 8
18.0 Compacter (steel roller) 3,500.00 8
18.0 Hand Compacter 300.00 8
19.0 Sledge hammer 18.00 8
20.0 Drilling machine 100.00 8
Hourly rental
rate (Br.)
250
875
112.5
112.5
275
1100
15
62.5
37.5
100
62.5
250
750
46.25
1.5
2000
480
437.5
37.5
2.25
12.5
ANALYSIS SHEET FOR DIRECT & INDIRECT UNIT COSTS

A. sub structure
1. EARTH WORK
2
WORK ITEM:1.01 hourly out put 1.25 m /hr
ACTIVITY site clearance at the depths of 200mm equipment:hand tool
2 2
UNIT QUANTITY OF ACTIVITY:1m result 68.53 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no. U.F
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 2.00 1.00 1.50 3.00
G.chief 1.00 0.50 21.59 10.80
D.Labour 2.00 1.00 15.96 31.92
Total Total 62.90 Total 3.00
2 2 2
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 50.32 Birr/m C= Equipment Unit Cost 2.40 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 52.72 Birr/m
Over head cost : 0.15 7.91 "
Profit Cost: 0.15 7.91 "
2
Total Unit Cost : 68.53 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

WORK ITEM 1.02 hourly out put 4.00


3
m /hr
ACTIVITY Bulk excavation from stripped level in Black,soft,high plastic silty clay soil to an EQUIPMENT:HANDTOOL & EXCAVATOR
3
UNIT QUANTITY OF ACTIVITY:1m average depth of 150cms and bring to a levelled surface.
3
result 287.44 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 2.00 1.00 1.50 3.00
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
D.Labour 2.00 1.00 15.96 31.92 0.00
excavator operator 1.00 1.00 68.53 68.53 0.00
Total Total 131.43 Total 753.00
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 32.86 Birr/m C= Equipment Unit Cost 188.25 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 221.11 Birr/m
Over head cost : 0.15 33.17 "
Profit Cost: 0.15 33.17 "
3
Total Unit Cost : 287.44 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
WORK ITEM:1.03 labour hourly out put 2.00 m /hr
ACTIVITY Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a depth exceeding 150cms but not exceeding 300cms. EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 575.85 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 65.71 Birr/m C= Equipment Unit Cost 377.25 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 442.96 Birr/m
Over head cost : 0.15 66.44 "
Profit Cost: 0.15 66.44 "
3
Total Unit Cost : 575.85 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

WORK ITEM:1.04
3
ACTIVITY pit excavation in reddish to yellowish silt clay,reddish brown sandy hourly out put 4.00 m /hr
clay soil to adepth of 1500 mm from reduced level EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 287.93 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53 0.00
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00Birr/m
B= Manpower Unit Cost 32.86 Birr/m C= Equipment Unit Cost 188.63 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 221.48 Birr/m
Over head cost : 0.15 33.22 "
Profit Cost: 0.15 33.22 "
3
Total Unit Cost : 287.93 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.05 hourly out put 3.25 m /hr

ACTIVITY: ditto as item 1.05 but depth exceeded 1500mm & not exceeding 3000mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 354.37 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 40.44 Birr/m C= Equipment Unit Cost 232.15 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 272.59 Birr/m
Over head cost : 0.15 40.89 "
Profit Cost: 0.15 40.89 "
Total Unit Cost : 354.37 Birr/m2
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

Work item:1.06

3
ACTIVITY: ditto as item 1.05 but depth exceeded 3000mm & not exceeding 4500mm hourly out put 2.50 m /hr
3
UNIT QUANTITY OF ACTIVITY:1m EQUIPMENT:HANDTOOL & EXCAVATOR
3
result 460.68 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 52.57 Birr/m C= Equipment Unit Cost 301.80 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 354.37 Birr/m
Over head cost : 0.15 53.16 "
Profit Cost: 0.15 53.16 "
Total Unit Cost : 460.68 Birr/m3
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.07 hourly out put 2.00 m /hr

ACTIVITY: ditto as item no 1.05 but depth exceeded 4500mm & not exceeding 6000mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 575.85 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 65.71 Birr/m C= Equipment Unit Cost 377.25 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 442.96 Birr/m
Over head cost : 0.15 66.44 "
Profit Cost: 0.15 66.44 "
3
Total Unit Cost : 575.85 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item:1.08 hourly out put 1.50 m /hr

ACTIVITY: ditto as item 1.05 but depth exceeded 6000mm & not exceeding 7500mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 767.80 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 87.62 Birr/m C= Equipment Unit Cost 503.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 590.62 Birr/m
Over head cost : 0.15 88.59 "
Profit Cost: 0.15 88.59 "
3
Total Unit Cost : 767.80 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.09 hourly out put 1.00 m /hr

ACTIVITY: ditto as item 1.05 but depth exceeded 7500mm & not exceeding 9000mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 1151.70 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 131.43 Birr/m C= Equipment Unit Cost 754.50 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 885.93 Birr/m
Over head cost : 0.15 132.89 "
Profit Cost: 0.15 132.89 "
3
Total Unit Cost : 1151.70 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item:1.10 labour hourly out put 0.75 m /hr

ACTIVITY: ditto as item 1.05 but depth exceeded 9000mm & not exceeding 10500mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 1535.61 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 3.00 1.00 1.50 4.50
G.chief 1.00 0.50 21.59 10.80 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 2.00 1.00 15.96 31.92
Total Total 131.43 Total 754.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 175.23 Birr/m C= Equipment Unit Cost 1006.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 1181.23 Birr/m
Over head cost : 0.15 177.19 "
Profit Cost: 0.15 177.19 "
3
Total Unit Cost : 1535.61 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.11 hourly out put 4.00 m /hr
ACTIVITY: trench excavation to adepth not exceeding 1500mm EQUIPMENT:HANDTOOL & EXCAVATOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 309.34 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 40.37 Hand Tools 5.00 1.00 1.50 7.50
G.chief 1.00 0.50 21.59 21.59 excavator 1.00 1.00 750.00 750.00
excavator operator 1.00 1.00 68.53 68.53
D.Labour 4.00 1.00 15.96 63.84
Total Total 194.32 Total 757.50
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 48.58 Birr/m C= Equipment Unit Cost 189.38 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 237.96 Birr/m
Over head cost : 0.15 35.69 "
Profit Cost: 0.15 35.69 "
3
Total Unit Cost : 309.34 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item:1.12 hourly out put 1.25 m /hr
ACTIVITY: selected borrowed fill materials equipment:hand tool &HAND COMPACTOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 396.33 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3 3
selected material m /m 1.15 125.00 143.75 Forman 1.00 0.50 40.37 20.18 Hand Tools 6.00 1.00 1.50 9.00
G.chief 1.00 0.50 21.59 10.80 hand compactor 1.00 1.00 37.50 37.50
D.Labour 5.00 1.00 15.96 79.79
mason 1.00 1.00 44.12 44.12
Total 143.75 Total 154.90 Total 46.50
3 3 3
A= Materials Unit Cost 143.75 Birr/m
B= Manpower Unit Cost 123.92 Birr/m C= Equipment Unit Cost 37.20 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 304.87 Birr/m
Over head cost : 0.15 45.73 "
Profit Cost: 0.15 45.73 "
3
Total Unit Cost : 396.33 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
Work item:1.13

3
ACTIVITY: Backfill around foundations and retaining walls with granular selected material brought from quarry hourly out put 1.25 m /hr
equipment:hand tool &HAND COMPACTOR
3 3
UNIT QUANTITY OF ACTIVITY:1m result 396.33 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3 3
selected material m /m 1.15 125.00 143.75 Forman 1.00 0.50 40.37 20.18 Hand Tools 6.00 1.00 1.50 9.00
G.chief 1.00 0.50 21.59 10.80 hand compactor 1.00 1.00 37.50 37.50
D.Labour 5.00 1.00 15.96 79.79
mason 1.00 1.00 44.12 44.12
Total 143.75 Total 154.90 Total 46.50
3 3 3
A= Materials Unit Cost 143.75 Birr/m
B= Manpower Unit Cost 123.92 Birr/m C= Equipment Unit Cost 37.20 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 304.87 Birr/m
Over head cost : 0.15 45.73 "
Profit Cost: 0.15 45.73 "
3
Total Unit Cost : 396.33 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item:1.14 hourly out put 4.00 m /hr
ACTIVITY: Load and cart away all surplus excavated materials to a suitable pit equipment:hand tool &DUMPTRUCK
3 3
UNIT QUANTITY OF ACTIVITY:1m result 360.03 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Forman 1.00 0.50 40.37 20.18 Hand Tools 10.00 1.00 1.50 15.00
G.chief 1.00 0.50 21.59 10.80 dump truck 1.00 1.00 875.00 875.00
D.Labour 8.00 1.00 15.96 127.67
dump truck driver 1.00 1.00 59.14 59.14
Total 0.00 217.79 Total 890.00
3 3 3
A= Materials Unit Cost 0.00 Birr/m
B= Manpower Unit Cost 54.45 Birr/m C= Equipment Unit Cost 222.50 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 276.95 Birr/m
Over head cost : 0.15 41.54 "
Profit Cost: 0.15 41.54 "
3
Total Unit Cost : 360.03 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.14 Supply basaltic or equivalent stone for 25cm thick hard core on top of compacted fill hourly out put 0.50 m /hr
ACTIVITY: materials and beneath the bottom basement floor slab equipment:hand tool
3 2
UNIT QUANTITY OF ACTIVITY:1M result 956.74 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3 3
Bazaltic stone m /m 1.20 250.00 300.00 Forman 1.00 0.50 40.37 20.18 Hand Tools 2.00 1.00 1.50 3.00
mason 2.00 1.00 44.12 88.24
G.chief 1.00 0.50 21.59 10.80
D.Labour 6.00 1.00 15.96 95.75
Total 300.00 Total 214.98 Total 3.00
3 3 3
A= Materials Unit Cost 300.00 Birr/m
B= Manpower Unit Cost 429.95 Birr/m C= Equipment Unit Cost 6.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 735.95 Birr/m
Over head cost : 0.15 110.39 "
Profit Cost: 0.15 110.39 "
3
Total Unit Cost : 956.74 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

B. super structure
1.CONCRETE WORK

Work item:1.01 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
ACTIVITY: of 150 kg/m3
2
under footing pads labour hourly out put 1.00 m /hr
2
UNIT QUANTITY OF ACTIVITY:1M equipment:mixer.vibrator, MIXER &hand tools
2
result 4531.05 Birr/m

MATERIAL COST (1.01 LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
cement qt/m 1.76 1324.00 2335.54 Forman 1.00 0.50 40.37 20.18 Hand Tools 2.00 1.00 1.50 3.00
3 2
agg m /m 0.94 312.50 292.50 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 2
sand m /m 0.47 375.00 175.50 D.Labour 15.00 1.00 15.96 239.38 MIXER 1.00 1.00 112.50 112.50
3 2
water m /m 0.06 0.00 plasterer 1.00 1.00 44.12 44.12
MIXER OPERATOR 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 2803.54 Total 453.89 Total 228.00
2 2 2
A= Materials Unit Cost 2803.54 Birr/m
B= Manpower Unit Cost 453.89 Birr/m C= Equipment Unit Cost 228.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 3485.43 Birr/m
Over head cost : 0.15 522.81 "
Profit Cost: 0.15 522.81 "
2
Total Unit Cost : 4531.05 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
2
Work item:1.-02 hourly out put 1.25 m /hr
ACTIVITY:ditto as item 1.01 but under grade beams equipment:mixer.vibrator, MIXER &hand tools
2 2
UNIT QUANTITY OF ACTIVITY:1M result 4353.76 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
cement qt/m 1.76 1324.00 2335.54 Forman 1.00 0.50 40.37 20.18 Hand Tools 2.00 1.00 1.50 3.00
3 2
agg m /m 0.94 312.50 292.50 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 2
sand m /m 0.47 375.00 175.50 D.Labour 15.00 1.00 15.96 239.38 MIXER 1.00 1.00 112.50 112.50
3 2
water m /m 0.60 0.00 plasterer 1.00 1.00 44.12 44.12
MIXER OPERATOR 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 2803.54 Total 453.89 Total 228.00
2 2 2
A= Materials Unit Cost 2803.54 Birr/m
B= Manpower Unit Cost 363.11 Birr/m C= Equipment Unit Cost 182.40 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 3349.05 Birr/m
Over head cost : 0.15 502.36 "
Profit Cost: 0.15 502.36 "
2
Total Unit Cost : 4353.76 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

2
Work item:1.03 hourly out put 1.00 m /hr
ACTIVITY:dtto as item 1.01 but under grade beams equipment:mixer.vibrator&hand tools
2 2
UNIT QUANTITY OF ACTIVITY:1M result 4531.05 Birr/m s

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
cement qt/m 1.76 1324.00 2335.54 Forman 1.00 0.50 40.37 20.18 Hand Tools 2.00 1.00 1.50 3.00
3 2
agg m /m 0.94 312.50 292.50 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 2
sand m /m 0.47 375.00 175.50 D.Labour 15.00 1.00 15.96 239.38 MIXER 1.00 1.00 112.50 112.50
3 2
water m /m 0.06 0.00 plasterer 1.00 1.00 44.12 44.12
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 2803.54 Total 453.89 Total 228.00
2 2 2
A= Materials Unit Cost 2803.54 Birr/m
B= Manpower Unit Cost 453.89 Birr/m C= Equipment Unit Cost 228.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 3485.43 Birr/m
Over head cost : 0.15 522.81 "
Profit Cost: 0.15 522.81 "
2
Total Unit Cost : 4531.05 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
Work item:1.04 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
ACTIVITY: 400kg/m3 of concrete,
3
filled in to form work and vibrated around rod reinforcement steel. hourly out put 1.00 m /hr
In foundation columns and elevation columns equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 13145.36 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 431.83 Birr/m C= Equipment Unit Cost 228.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 10111.81 Birr/m
Over head cost : 0.15 1516.77 "
Profit Cost: 0.15 1516.77 "
3
Total Unit Cost : 13145.36 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item:1.05 labour hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in 500mm thick mat slab equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 0.00 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 345.46 Birr/m C= Equipment Unit Cost 182.40 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 9979.85 Birr/m
Over head cost : 0.15 1496.98 "
Profit Cost: 0.15 1496.98 "
3
Total Unit Cost : 12973.80 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.06 hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in BEAMS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 0.00 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 345.46 Birr/m C= Equipment Unit Cost 182.40 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 9979.85 Birr/m
Over head cost : 0.15 1496.98 "
Profit Cost: 0.15 1496.98 "
3
Total Unit Cost : 12973.80 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item :1.07 hourly out put 0.75 m /hr
ACTIVITY: ditto as item 1.04 but in FOOTING PADS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 13431.28 Birr/m

MATERIAL COST (A) LABOUR COST (B) EQUIPMENT COST (C)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 0.00 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 575.77 Birr/m C= Equipment Unit Cost 304.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 10331.76 Birr/m
Over head cost : 0.15 1549.76 "
Profit Cost: 0.15 1549.76 "
3
Total Unit Cost : 13431.28 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.08 labour hourly out put 0.75 m /hr
ACTIVITY: ditto as item 1.04 but in BASEMENT COLUMNS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 13431.28 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 0.00 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 575.77 Birr/m C= Equipment Unit Cost 304.00 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 10331.76 Birr/m
Over head cost : 0.15 1549.76 "
Profit Cost: 0.15 1549.76 "
3
Total Unit Cost : 13431.28 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item:1.09 hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in FOOTING & GRADE BEAMS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1,03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 0.00 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 345.46 Birr/m C= Equipment Unit Cost 182.40 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 9979.85 Birr/m
Over head cost : 0.15 1496.98 "
Profit Cost: 0.15 1496.98 "
3
Total Unit Cost : 12973.80 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
3
Work item:1.10 hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in suspended beams equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 0.00 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 345.46 Birr/m C= Equipment Unit Cost 182.40 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 9979.85 Birr/m
Over head cost : 0.15 1496.98 "
Profit Cost: 0.15 1496.98 "
3
Total Unit Cost : 12973.80 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3
Work item:1.11 hourly out put 1.25 m /hr
ACTIVITY: ditto as item 1.04 but in STAIRCASE &LANDINGS equipment:mixer.vibrator&hand tools
3 3
UNIT QUANTITY OF ACTIVITY: 1m result 12973.80 Birr/m

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
3
cement qt/m 4.15 1462.00 6068.16 Forman 1.00 0.50 40.37 20.18 mixer 1.00 1.00 112.50 112.50
3 3
agg m /m 10.28 312.50 3211.76 mason 2.00 1.00 44.12 88.24 vibrator 1.00 1.00 112.50 112.50
3 3
sand m /m 0.46 375.00 172.06 D.Labour 15.00 1.00 15.96 239.38 hand tools 2.00 1.00 1.50 3.00
3 3
water m /m 0.12 0.00 carpenter 1.00 0.50 44.12 22.06
mixer operator 1.00 1.00 30.98 30.98
vibrator operator 1.00 1.00 30.98 30.98
Total 9451.98 Total 431.83 Total 228.00
3 3 3
A= Materials Unit Cost 9451.98 Birr/m
B= Manpower Unit Cost 345.46 Birr/m C= Equipment Unit Cost 182.40 Birr/m
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
3
Direct Cost of activity = A+B+C = 9979.85 Birr/m
Over head cost : 0.15 1496.98 "
Profit Cost: 0.15 1496.98 "
3
Total Unit Cost : 12973.80 Birr/m
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
2 .REBAR WORK
Work Item: 2.01 hourly out put 11.25 kg/hr
activity:Provide: erect or lay mild reinforcement steel S-400,8MM equipment:hand tools & BAR CUTTER
UNIT QUANTITY OF ACTIVITY: 1kg result 49.57 Birr/kg

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Reinforcement bar kg/kg 1.05 24.15 25.36 foreman 1.00 0.50 40.37 20.18 hand tools 2.00 1.00 1.50 3.00
Tying wire kg/kg 0.02 51.75 1.04 bar bender 1.00 1.00 30.98 30.98 BAR CUTTER 1.00 1.00 15.00 15.00
BAR CUTTER 1.00 1.00 30.98 30.98
D.Labour 2.00 1.00 15.96 31.92
Total 26.39 Total 114.06 Total 18.00
A= Materials Unit Cost 26.39 Birr/kg
B= Manpower Unit Cost 10.14 Birr/kg C= Equipment Unit Cost 1.60 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 38.13 Birr/kg
Over head cost : 0.15 5.72 "
Profit Cost: 0.15 5.72 "
Total Unit Cost : 49.57 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

Work Item: 2.02 labour hourly out put 11.25 kg/hr


activity:ditto AS ITEM 2.01 but 10mm equipment:hand tools & BAR CUTTER
UNIT QUANTITY OF ACTIVITY: 1kg result 49.57 Birr/kg

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Reinforcement bar kg/kg 1.05 24.15 25.36 foreman 1.00 0.50 40.37 20.18 hand tools 2.00 1.00 1.50 3.00
Tying wire kg/kg 0.02 51.75 1.04 bar bender 1.00 1.00 30.98 30.98 BAR CUTTER 1.00 1.00 15.00 15.00
BAR CUTTER 1.00 1.00 30.98 30.98
D.Labour 2.00 1.00 15.96 31.92
Total 26.39 Total 114.06 Total 18.00
A= Materials Unit Cost 26.39 Birr/kg
B= Manpower Unit Cost 10.14 Birr/kg C= Equipment Unit Cost 1.60 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 38.13 Birr/kg
Over head cost : 0.15 5.72 "
Profit Cost: 0.15 5.72 "
Total Unit Cost : 49.57 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
Work Item: 2.03 hourly out put 11.25 kg/hr
activity:ditto as item 2.01 but 12mm equipment:hand tools & BAR CUTTER
UNIT QUANTITY OF ACTIVITY: 1kg result 46.43 Birr/kg

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Reinforcement bar kg/kg 1.05 21.85 22.94 foreman 1.00 0.50 40.37 20.18 hand tools 2.00 1.00 1.50 3.00
Tying wire kg/kg 0.02 51.75 1.04 bar bender 1.00 1.00 30.98 30.98 BAR CUTTER 1.00 1.00 15.00 15.00
BAR CUTTER 1.00 1.00 30.98 30.98
D.Labour 2.00 1.00 15.96 31.92
Total 23.98 Total 114.06 Total 18.00
A= Materials Unit Cost 23.98 Birr/kg
B= Manpower Unit Cost 10.14 Birr/kg C= Equipment Unit Cost 1.60 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 35.72 Birr/kg
Over head cost : 0.15 5.36 "
Profit Cost: 0.15 5.36 "
Total Unit Cost : 46.43 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

Work Item: 2.04 hourly out put 11.25 kg/hr


activity:ditto as item 2.01 but 14mm equipment:hand tools & BAR CUTTER
UNIT QUANTITY OF ACTIVITY: 1kg result 48.00 Birr/kg

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Reinforcement bar kg/kg 1.05 23.00 24.15 foreman 1.00 0.50 40.37 20.18 hand tools 2.00 1.00 1.50 3.00
Tying wire kg/kg 0.02 51.75 1.04 bar bender 1.00 1.00 30.98 30.98 BAR CUTTER 1.00 1.00 15.00 15.00
BAR CUTTER 1.00 1.00 30.98 30.98
D.Labour 2.00 1.00 15.96 31.92
Total 25.19 Total 114.06 Total 18.00
A= Materials Unit Cost 25.19 Birr/kg
B= Manpower Unit Cost 10.14 Birr/kg C= Equipment Unit Cost 1.60 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 36.92 Birr/kg
Over head cost : 0.15 5.54 "
Profit Cost: 0.15 5.54 "
Total Unit Cost : 48.00 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
Work Item: 2.05 hourly out put 11.25 kg/hr
activity: ditto as item 2.01 but 16mm equipment:hand tools & BAR CUTTER
UNIT QUANTITY OF ACTIVITY: 1kg result 58.05 Birr/kg

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
Reinforcement bar kg/kg 1.05 30.36 31.88 foreman 1.00 0.50 40.37 20.18 hand tools 2.00 1.00 1.50 3.00
Tying wire kg/kg 0.02 51.75 1.04 bar bender 1.00 1.00 30.98 30.98 BAR CUTTER 1.00 1.00 15.00 15.00
BAR CUTTER 1.00 1.00 30.98 30.98
D.Labour 2.00 1.00 15.96 31.92
Total 32.91 Total 114.06 Total 18.00
A= Materials Unit Cost 32.91 Birr/kg
B= Manpower Unit Cost 10.14 Birr/kg C= Equipment Unit Cost 1.60 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 44.65 Birr/kg
Over head cost : 0.15 6.70 "
Profit Cost: 0.15 6.70 "
Total Unit Cost : 58.05 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

3.HALLOW CONCRETE BLOCK WORK


2
WORK ITEM: 3.01 hourly out put 0.75 M /hr
ACTIVITY:20cm thick CLASS A HCB wall wthin the basement floor, embedded in cement-sand
mortar of 1:3 mix ratio.. equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 750.64 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
HCB PCS/M 13.13 23.00 301.88 foreman 1.00 0.50 40.37 20.18 hand tools 3.00 1.00 1.50 4.50
2
CEMENT QT/M 0.10 1324.00 131.37 MASON 1.00 1.00 44.12 44.12
3 2
SAND M /M 0.03 375.00 9.87 D.Labour 2.00 1.00 15.96 31.92
3 2
water M /M 0.03 0.00
Total 443.12 Total 96.22 Total 4.50
2 2
A= Materials Unit Cost 443.12 Birr/M
B= Manpower Unit Cost 128.30 Birr/kg C= Equipment Unit Cost 6.00 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 577.42 Birr/M
Over head cost : 0.15 86.61 "
Profit Cost: 0.15 86.61 "
2
Total Unit Cost : 750.64 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
2
WORK ITEM: 3.02 labour hourly out put 0.75 M /hr
ACTIVITY:15cm thick CLASS A HCB wall wthin the basement floor, embedded in cement-sand mortar of
1:3 mix ratio.. equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 704.74 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
HCB PCS/M 13.13 23.00 301.88 foreman 1.00 0.50 40.37 20.18 hand tools 3.00 1.00 1.50 4.50
2
CEMENT QT/M 0.07 1324.00 98.53 MASON 1.00 1.00 44.12 44.12
3 2
SAND M /M 0.02 375.00 7.40 D.Labour 2.00 1.00 15.96 31.92
3 2
water M /M 0.00 0.00
Total 407.81 Total 96.22 Total 4.50
2 2
A= Materials Unit Cost 407.81 Birr/M
B= Manpower Unit Cost 128.30 Birr/kg C= Equipment Unit Cost 6.00 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 542.11 Birr/M
Over head cost : 0.15 81.32 "
Profit Cost: 0.15 81.32 "
2
Total Unit Cost : 704.74 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

2
WORK ITEM: 3.03 hourly out put 0.75 M /hr
ACTIVITY:10cm thick perforated HCB block work left for pointing equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 658.83 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
HCB PCS/M 13.13 23.00 301.88 foreman 1.00 0.50 40.37 20.18 hand tools 3.00 1.00 1.50 4.50
2
CEMENT QT/M 0.05 1324.00 65.69 MASON 1.00 1.00 44.12 44.12
3 2
SAND M /M 0.01 375.00 4.94 D.Labour 2.00 1.00 15.96 31.92
3 2
water M /M 0.02 0.00
Total 372.50 Total 96.22 Total 4.50
2 2
A= Materials Unit Cost 372.50 Birr/M
B= Manpower Unit Cost 128.30 Birr/kg C= Equipment Unit Cost 6.00 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 506.79 Birr/M
Over head cost : 0.15 76.02 "
Profit Cost: 0.15 76.02 "
2
Total Unit Cost : 658.83 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
4.PLASTERING
2
hourly out put 2.00 M /hr
WORK ITEM: 4.01
ACTIVITY:Apply three coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster
or ceramic wall tile To internal wall surface,and columns, to external wall surface, exposed beams and
columns ,to roof parapet. equipment:mixer.vibrator&hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 246.38 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
CEMENT QT/M 0.09 1324.00 116.78 foreman 1.00 0.50 40.37 20.18 hand tools 3.00 1.00 1.50 4.50
3 2
SAND M /M 0.02 375.00 8.78 PLASTERER 1.00 1.00 44.12 44.12
3 2
water M /M 0.02 0.00 D.Labour 2.00 1.00 15.96 31.92
chiesler 1.00 1.00 27.22 27.22
Total 125.55 Total 123.45 Total 4.50
2 2
A= Materials Unit Cost 125.55 Birr/M
B= Manpower Unit Cost 61.72 Birr/kg C= Equipment Unit Cost 2.25 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 189.53 Birr/M
Over head cost : 0.15 28.43 "
Profit Cost: 0.15 28.43 "
2
Total Unit Cost : 246.38 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

WORK ITEM: 4.02 hourly out put 1.50


2
M /hr
ACTIVITY:DITTO AS ITEM 4.01 BUT FOR RC ceiling, exposed beams,stair case soffit and sides of lift
shaft walls
equipment:hand tools
2
UNIT QUANTITY OF ACTIVITY; 1M 2
result 274.10 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
CEMENT QT/M 0.09 1324.00 116.78 foreman 1.00 0.50 40.37 20.18 hand tools 3.00 1.00 1.50 4.50
3 2
SAND M /M 0.02 375.00 8.78 PLASTERER 1.00 1.00 44.12 44.12
3 2
water M /M 0.02 0.00 D.Labour 2.00 1.00 15.96 31.92
chiesler 1.00 1.00 27.22 27.22
Total 125.55 Total 123.45 Total 4.50
2 2
A= Materials Unit Cost 125.55 Birr/M
B= Manpower Unit Cost 82.30 Birr/kg C= Equipment Unit Cost 3.00 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 210.85 Birr/M
Over head cost : 0.15 31.63 "
Profit Cost: 0.15 31.63 "
2
Total Unit Cost : 274.10 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
2
WORK ITEM: 4.04 hourly out put 1.75 M /hr
ACTIVITY:78mm thick cement sand screed equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 711.37 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost rental rate
2
CEMENT QT/M 0.34 1324.00 455.43 foreman 1.00 0.50 40.37 20.18 hand tools 3.00 1.00 1.50 4.50
3 2
SAND M /M 0.09 375.00 34.22 PLASTERER 1.00 1.00 44.12 44.12
3 2
WATER M /M 0.01 0.00 D.Labour 2.00 1.00 15.96 31.92
Total 489.65 Total 96.22 Total 4.50
2 2
A= Materials Unit Cost 489.65 Birr/M
B= Manpower Unit Cost 54.98 Birr/kg C= Equipment Unit Cost 2.57 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 547.21 Birr/M
Over head cost : 0.15 82.08 "
Profit Cost: 0.15 82.08 "
2
Total Unit Cost : 711.37 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

5. PAINTING
2
WORK ITEM: 5.01 hourly out put 2.50 M /hr
ACTIVITY: Apply three coats of plastic emulsion paint to internal wall surfaces, columns and beams. equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 68.79 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly hourly u.f hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
stuco kg/m 0.50 2.99 1.50 foreman 1.00 0.50 40.37 20.18 hand tools 2.00 1.50 3.00
2
gypsum kg/m 0.50 5.06 2.53 Painter 1.00 1.00 44.12 44.12
2
plastic paint lt/m 0.20 46.00 9.20 D.Labour 2.00 1.00 15.96 31.92
Total 13.23 Total 96.22 Total 3.00
2 2
A= Materials Unit Cost 13.23 Birr/M
B= Manpower Unit Cost 38.49 Birr/kg C= Equipment Unit Cost 1.20 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 52.91 Birr/M
Over head cost : 0.15 7.94 "
Profit Cost: 0.15 7.94 "
2
Total Unit Cost : 68.79 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
2
WORK ITEM:5.02 hourly out put 2.50 M /hr
ACTIVITY:Ditto as item 5.01 but to RC ceiling, stair case soffit and sides of lift shaft walls equipment:hand tools
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 68.79 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly hourly U.F hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
stuco kg/m 0.50 2.99 1.50 foreman 1.00 0.50 40.37 20.18 hand tools 2.00 1.50 1.00 3.00
2
gypsum kg/m 0.50 5.06 2.53 PLASTERER 1.00 1.00 44.12 44.12 1.00
2
plastic paint lt/m 0.20 46.00 9.20 D.Labour 2.00 1.00 15.96 31.92
Total 13.23 Total 96.22 Total 3.00
2 2
A= Materials Unit Cost 13.23 Birr/M
B= Manpower Unit Cost 38.49 Birr/kg C= Equipment Unit Cost 1.20 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 52.91 Birr/M
Over head cost : 0.15 7.94 "
Profit Cost: 0.15 7.94 "
2
Total Unit Cost : 68.79 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

6 RHS WORKS

WORK ITEM: 6.01 hourly out put 12.50 KG/hr


ACTIVITY: RHS Works of size RHS 80x80x3 mm equipment:WELDING MACHINE& GRINDER
UNIT QUANTITY OF ACTIVITY; 1KG result 467.50 Birr/KG

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
RHS 80x80x3 mm KG/kg 1.05 322.00 338.10 Forman 1.00 0.50 40.37 20.18 Welding Mac. 1.00 1.00 62.50 62.50
ANTI RUST lt/kg 0.02 80.50 1.61 Walder 1.00 1.00 30.98 30.98 Grinder 1.00 1.00 37.50 37.50
Carpenter 1.00 1.00 44.12 44.12
GRINDER 1.00 1.00 21.59 21.59
0.00 D. Labuorer 2.00 1.00 15.96 31.92
Total 339.71 Total 148.79 Total 100.00
A= Materials Unit Cost 339.71 Birr/KG
B= Manpower Unit Cost 11.90 Birr/kg C= Equipment Unit Cost 8.00 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 359.61 Birr/kg
Over head cost : 0.15 53.94 "
Profit Cost: 0.15 53.94 "
Total Unit Cost : 467.50 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
WORK ITEM: 6.02 hourly out put 12.50 KG/hr
ACTIVITY: RHS Works of size RHS 60x60x3 mm equipment:WELDING MACHINE& GRINDER
UNIT QUANTITY OF ACTIVITY; 1KG result 263.43 Birr/KG

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
RHS60x60x3 mm KG/kg 1.05 172.50 181.13 Forman 1.00 0.50 40.37 20.18 Welding Mac. 1.00 1.00 62.50 62.50
ANTI RUST lt/kg 0.02 80.50 1.61 Walder 1.00 1.00 30.98 30.98 Grinder 1.00 1.00 37.50 37.50
Carpenter 1.00 1.00 44.12 44.12
GRINDER 1.00 1.00 21.59 21.59
0.00 D. Labuorer 2.00 1.00 15.96 31.92
Total 182.74 Total 148.79 Total 100.00
A= Materials Unit Cost 182.74 Birr/KG
B= Manpower Unit Cost 11.90 Birr/kg C= Equipment Unit Cost 8.00 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 202.64 Birr/kg
Over head cost : 0.15 30.40 "
Profit Cost: 0.15 30.40 "
Total Unit Cost : 263.43 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

WORK ITEM: 6.03 hourly out put 12.50 KG/hr


ACTIVITY: RHS Works of size RHS 50x50x3 mm equipment:WELDING MACHINE& GRINDER
UNIT QUANTITY OF ACTIVITY; 1KG result 216.34 Birr/KG

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
RHS50x50x3 mm KG/kg 1.05 138.00 144.90 Forman 1.00 0.50 40.37 20.18 Welding Mac. 1.00 1.00 62.50 62.50
ANTI RUST lt/kg 0.02 80.50 1.61 Walder 1.00 1.00 30.98 30.98 Grinder 1.00 1.00 37.50 37.50
GRINDER 1.00 1.00 21.59 21.59
Carpenter 1.00 1.00 44.12 44.12
0.00 D. Labuorer 2.00 1.00 15.96 31.92
Total 146.51 Total 148.79 Total 100.00
A= Materials Unit Cost 146.51 Birr/KG
B= Manpower Unit Cost 11.90 Birr/kg C= Equipment Unit Cost 8.00 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 166.41 Birr/kg
Over head cost : 0.15 24.96 "
Profit Cost: 0.15 24.96 "
Total Unit Cost : 216.34 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
WORK ITEM: 6.04 hourly out put 12.50 KG/hr
ACTIVITY: RHS Works of size RHS 40x40x3 mm equipment:WELDING MACHINE& GRINDER
UNIT QUANTITY OF ACTIVITY; 1KG result 51.15 Birr/KG

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
RHS40x40x3 mm KG/kg 1.05 18.63 19.56 Forman 1.00 0.50 40.37 20.18 Welding Mac. 1.00 1.00 62.50 62.50
ANTI RUST lt/kg 0.02 80.50 1.61 Walder 1.00 1.00 30.98 30.98 Grinder 1.00 1.00 37.50 37.50
GRINDER 1.00 1.00 21.59
Carpenter 1.00 1.00 44.12 44.12
D. Labuorer 2.00 1.00 15.96 31.92
Total 21.17 Total 127.20 Total 100.00
A= Materials Unit Cost 21.17 Birr/KG
B= Manpower Unit Cost 10.18 Birr/kg C= Equipment Unit Cost 8.00 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 39.35 Birr/kg
Over head cost : 0.15 5.90 "
Profit Cost: 0.15 5.90 "
Total Unit Cost : 51.15 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

7. LATTUCE PURLIN

WORK ITEM:7.01 hourly out put 12.50 KG/hr


ACTIVITY: RHS Works of size RHS 80x80x3 mm equipment:WELDING MACHINE& GRINDER
UNIT QUANTITY OF ACTIVITY; 1KG result 467.50 Birr/KG

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
RHS 80x80x3 mm KG/kg 1.05 322.00 338.10 Forman 1.00 0.50 40.37 20.18 Welding Mac. 1.00 1.00 62.50 62.50
ANTI RUST lt/kg 0.02 80.50 1.61 Walder 1.00 1.00 30.98 30.98 Grinder 1.00 1.00 37.50 37.50
GRINDER 1.00 1.00 21.59 21.59
Carpenter 1.00 1.00 44.12 44.12
0.00 D. Labuorer 2.00 1.00 15.96 31.92
Total 339.71 Total 148.79 Total 100.00
A= Materials Unit Cost 339.71 Birr/KG
B= Manpower Unit Cost 11.90 Birr/kg C= Equipment Unit Cost 8.00 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 359.61 Birr/kg
Over head cost : 0.15 53.94 "
Profit Cost: 0.15 53.94 "
Total Unit Cost : 467.50 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
WORK ITEM: 7.02 hourly out put 12.50 KG/hr
ACTIVITY: RHS Works of size RHS 60x60x3 mm equipment:WELDING MACHINE& GRINDER
UNIT QUANTITY OF ACTIVITY; 1KG result 249.97 Birr/KG

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
RHS60x60x3 mm KG/kg 1.05 172.50 172.50 Forman 1.00 0.50 40.37 20.18 Welding Mac. 1.00 1.00 62.50 62.50
ANTI RUST lt/kg 0.02 80.50 1.61 Walder 1.00 1.00 30.98 30.98 Grinder 1.00 1.00 37.50 37.50
GRINDER 1.00 1.00 21.59
Carpenter 1.00 1.00 44.12 44.12
0.00 D. Labuorer 2.00 1.00 15.96 31.92
Total 174.11 Total 127.20 Total 100.00
A= Materials Unit Cost 174.11 Birr/KG
B= Manpower Unit Cost 10.18 Birr/kg C= Equipment Unit Cost 8.00 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 192.29 Birr/kg
Over head cost : 0.15 28.84 "
Profit Cost: 0.15 28.84 "
Total Unit Cost : 249.97 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

WORK ITEM: 7.03 hourly out put 12.50 KG/hr


ACTIVITY: RHS Works of size RHS30x30x3 mm equipment:WELDING MACHINE& GRINDER
UNIT QUANTITY OF ACTIVITY; 1KG result 61.78 Birr/KG

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
RHS30x30x3 mm KG/kg 1.05 25.99 27.29 Forman 1.00 0.50 40.37 20.18 Welding Mac. 1.00 1.00 62.50 62.50
ANTI RUST lt/kg 0.02 80.50 1.61 Walder 1.00 1.00 30.98 30.98 Grinder 1.00 1.00 37.50 37.50
GRINDER 1.00 1.00 21.59 21.59
Carpenter 1.00 1.00 44.12 44.12
D. Labuorer 2.00 1.00 15.96 15.96
Total 28.90 Total 132.83 Total 100.00
A= Materials Unit Cost 28.90 Birr/KG
B= Manpower Unit Cost 10.63 Birr/kg C= Equipment Unit Cost 8.00 Birr/kg
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 47.53 Birr/kg
Over head cost : 0.15 7.13 "
Profit Cost: 0.15 7.13 "
Total Unit Cost : 61.78 Birr/kg
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
8. ANCHOR BOLT
WORK ITEM: 8.01 12.50 pcs/hr
ACTIVITY: Anchor bolt (J-Bolt) dia 16 mm development length 400 mm hourly out put
equipment:handtools
UNIT QUANTITY OF ACTIVITY; 1pcs result 104.02 Birr/pcs

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
dia 16 j bolt pcs/pcs 1.00 74.75 74.75 Forman 1.00 0.50 40.37 20.18 handtools 1.00 1.00 1.50 1.50
Carpenter 1.00 1.00 44.12 44.12 0.00
D. Labuorer 1.00 1.00 15.96 0.00
Total 74.75 Total 64.30 Total 1.50
A= Materials Unit Cost 74.75 Birr/pcs B= Manpower Unit Cost 5.14 Birr/pcs C= Equipment Unit Cost 0.12 Birr/pcs
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 80.01 Birr/pcs
Over head cost : 0.15 12.00 "
Profit Cost: 0.15 12.00 "
Total Unit Cost : 104.02 Birr/pcs
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

9. ROOF COVER

2
WORK ITEM: 9.01 hourly out put 2.00 M hr
ACTIVITY: Roof cover in EGA 400, 0.4mm thick equipment:HAND TOOLS
2 2
UNIT QUANTITY OF ACTIVITY; 1M result 997.56 Birr/M

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
EGA 400mm thick M /M
2 2
1.00 216.20 216.20 Forman 1.00 0.50 40.37 20.18 HAND TOOLS 2.00 1.00 1.50 3.00
MJ BOLT dia 10mm PCS/M
2
10.00 51.75 517.50 CARPENTER 1.00 1.00 44.12 44.12 0.00
D. Labuorer 2.00 1.00 15.96 0.00
Total 733.70 Total 64.30 Total 3.00
2 2 2
A= Materials Unit Cost 733.70 Birr/M
B= Manpower Unit Cost 32.15 Birr/M C= Equipment Unit Cost 1.50 Birr/M
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
2
Direct Cost of activity = A+B+C = 767.35 Birr/M
Over head cost : 0.15 115.10 "
Profit Cost: 0.15 115.10 "
2
Total Unit Cost : 997.56 Birr/M
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
10. STEEL WORKS
WORK ITEM: 10.01 hourly out put 0.25 pcs/hr
ACTIVITY: Semi Solid Wooden Doors equipment:HAND TOOLS
UNIT QUANTITY OF ACTIVITY; 1pcs result 1113.27 Birr/pcs

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
Plywood m /pcs 2.00 50.22 100.44 Forman 1.00 0.50 40.37 20.18 HAND TOOLS 3.00 1.00 1.50 4.50
Key/lock & handle pcs/pcs 1.00 480.70 480.70 CARPENTER 1.00 1.00 44.12 44.12
Hing pcs/pcs 2.00 0.00 0.00 D. Labuorer 2.00 1.00 15.96 0.00
Handle pcs/pcs 1.00 287.50 287.50
nail kg/pcs 0.25 40.25 10.06
varnish Lt/pcs 0.35 80.50 28.18
Total 581.14 Total 64.30 Total 4.50
A= Materials Unit Cost 581.14 Birr/pcs
B= Manpower Unit Cost 257.22 Birr/pcs C= Equipment Unit Cost 18.00 Birr/pcs
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 856.36 Birr/pcs
Over head cost : 0.15 128.45 "
Profit Cost: 0.15 128.45 "
Total Unit Cost : 1113.27 Birr/pcs
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.

WORK ITEM: 10.01 hourly out put 0.25 pcs/hr


ACTIVITY: Fabricate or supply and fix doors made of steel-reinforced PVC Doors equipment:HAND TOOLS &welding machine
UNIT QUANTITY OF ACTIVITY; 1pcs result 2093.77 Birr/pcs

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
LTZ 38*1mm ml/Pcs 10.00 48.30 483.00 Forman 1.00 0.50 40.37 20.18 HAND TOOLS 2.00 1.00 1.50 3.00
Hinge pcs/pcs 4.00 0.00 0.00 CARPENTER 1.00 1.00 44.12 44.12 welding machine 1.00 1.00 62.50 62.50
Key/lock & handle pcs/pcs 1.00 480.70 480.70 D. Labuorer 2.00 1.00 15.96 31.92
anti rust Lit/pcs 0.02 80.50 1.61 welder 1.00 1.00 30.98 30.98
2
pvc tile m /Pcs 2.52 230.00 579.60
Handle pcs/pcs 1.00 287.50 287.50
Electrod kg/pcs 0.25 1.84 0.46
Total 963.70 Total 96.22 Total 65.50
A= Materials Unit Cost 963.70 Birr/pcs
B= Manpower Unit Cost 384.89 Birr/pcs C= Equipment Unit Cost 262.00 Birr/pcs
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 1610.59 Birr/pcs
Over head cost : 0.15 241.59 "
Profit Cost: 0.15 241.59 "
Total Unit Cost : 2093.77 Birr/pcs
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
WORK ITEM: 10.01 hourly out put 0.25 pcs/hr
ACTIVITY: wooden frames cupboards equipment:HAND TOOLS
UNIT QUANTITY OF ACTIVITY; 1pcs result 1285.77 Birr/pcs

MATERIAL COST (1.01) LABOUR COST (1.02) EQUIPMENT COST (1.03)


indexed hourly U.F hourly hourly cost
Type of material Unit quantity * rate cost per unit labour by trade no. u.f hourly cost type of equipment no.
cost ** rental rate
2
Plywood m /pcs 2.10 50.22 105.46 Forman 1.00 0.50 40.37 20.18 HAND TOOLS 3.00 1.00 1.50 4.50
Key/lock & handle pcs/pcs 1.00 480.70 480.70 CARPENTER 1.00 1.00 44.12 44.12
Hing pcs/pcs 3.00 0.00 0.00 D. Labuorer 2.00 1.00 15.96 31.92
Handle pcs/pcs 1.00 287.50 287.50
nail kg/pcs 0.25 40.25 10.06
varnish Lt/pcs 0.35 80.50 28.18
Total 586.16 Total 96.22 Total 4.50
A= Materials Unit Cost 586.16 Birr/pcs
B= Manpower Unit Cost 384.89 Birr/pcs C= Equipment Unit Cost 18.00 Birr/pcs
Total of (1:02) Total of (1:03)
Hourly Output: Hourly output:
Direct Cost of activity = A+B+C = 989.05 Birr/pcs
Over head cost : 0.15 148.36 "
Profit Cost: 0.15 148.36 "
Total Unit Cost : 1285.77 Birr/pcs
Remark _____________________________________________________________________________
Remark _____________________________________________________________________________
UF: UTILIZATION FACTOR
*INCLUSIVE OF WASTAGE, TRANSPORTING, HANDLING, ETC.
**INCLUSIVE OF BENEFITS, TRAVEL SUBSIDES AND COST OF OVERTIME RELATED TO TARGETED OUTPUT.
cost analysis sheet
ITEM DESCRIPTION UNIT AMOUNT RATE TOTAL

EARTHWORK
2
1.00 site clearance at the depths of 200mm m 68.53

2.00 Bulk excavation from stripped level in Black,soft,high plastic silty clay soil to an average
3
depth of 150cms and bring to a levelled surface. m 287.44

Bulk excavation to reduce level in Gray, Stiff, high plastic silty Clay to a depth exceeding 150cms but
3.00 not exceeding 300cms. 575.85
3
m

4.00
Excavate for isolated footings in reddish to yellowish silty clay, reddish brown or reddish
3
friable sandy silty or silty clay soil to a depth exceeding not exceeding 1500mm. m 287.93
3
ditto but depth exceeded 1500mm & not exceeding 3000mm m 354.37
3
ditto but depth exceeded 3000mm & not exceeding4500mm m 460.68
3
ditto but depth exceeded 4500mm & not exceeding 6000mm m 575.85
3
ditto but depth exceeded 6000mm & not exceeding 7500mm m 767.80
3
ditto but depth exceeded 7500mm & not exceeding 9000mm m 1151.70
3
ditto but depth exceeded 9000mm & not exceeding 10500mm m 1535.61

3
5.00 Trench excavation not exceeding 1.5m m 309.34
selected borrowed fill materials 3
6.00 m 396.33
7.00 Backfill around foundations and retaining walls with granular selected material brought
from quarry . Backfill material should be tested to conform with required standards and
should be approved by the Engineer prior to execution. Compaction should also be carried
3
out to fulfil standard requirements. m 396.33
8.00 Load and cart away all surplus excavated materials to a suitable pit as may be found by the
contractor and with in the accespable range of the city adminstration.

3
m 360.03
9.00
Supply basaltic or equivalent stone for 25cm thick hard core on top of compacted fill
materials and beneath the bottom basement floor slab to be well rolled, consolidated and
blinded with crushed stone aggregates. Lean concrete shall be measured separately. 3
m 956.74
Super STRUCTURE CONCRETE WORK
CONCRETE WORK IN SITU CONCRETE
10.00 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
of 150 kg/m3. Price shall include sika or equivalent cement water proofing to be added to all
foundation footings beams slab and column. a) Under footing pads
2
m 4531.05
11.00 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
of 150 kg/m3. Price shall include sika or equivalent cement water proofing to be added to all
foundation footings beams slab and column. b) Under grade beams
2
m 4353.76
12.00 Produce and place 5 cm thick lean concrete class C-15, with minimum PPCcement content
of 150 kg/m3. Price shall include sika or equivalent cement water proofing to be added to all
foundation footings beams slab and column.c) Under floor slabs
2
m 4531.05
13.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) a) In foundation columns and elevation
columns
3
m 13145.36
14.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column. a) In
500mm thick Mat slab
3
m 12973.80
15.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column. b)
Beams
3
m 12973.80
16.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column.c) In
footing pads
3
m 13431.28
17.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) d) In Basemnt columns
3
m 13431.28
18.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) e) In footing and grade beams
3
m 12973.80
19.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3 of concrete, filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately) f) In suspended beams
3
m 12973.80
20.00 Produce and place reinforced concrete class C-30, with minimum OPC cement content of
400kg/m3, of concrete filled in to form work and vibrated around rod reinforcement steel.
(Formwork and reinforcement measured separately).Price shall include sika or equivalent
cement water proofing to be added to all foundation footings beams slab and column.g) In
staircase steps & landings
3
m 12973.80
21.00 Provide, erect or lay mild reinforcement steel S-400. It must be ensured that bars are free of
any lubricants, dirt, mud or any other impurities before concrete is poured onto them. Price
shall include cutting, bending, placing in position and tying wires. 8mm
reinforcement bar
kg 49.57
10mm reinforcement bar kg 49.57
12mm reinforcement bar kg 46.43
14mm reinforcement bar kg 48.00
16mm reinforcement bar kg 58.05
22.00 20cm thick HCB wall wthin the basement floor, embedded in cement-sand mortar of 1:3 mix
2
ratio. Both sides shall be left for plastering. m 750.64
23.00 15cm thick HCB block work cement sand ratio m
2
704.74
24.00 10cm thick perforated HCB block work left for pointing
plastering m
2
658.83
25.00 Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster
or ceramic wall tile. a) To internal wall surface,and columns, to external wall surface,
exposed beams and columns ,to roof parapet.
2
m 246.38
26.00 Apply two coats of plastering of cement sand mortar (1:3) to receive either gypsum plaster
or ceramic wall tile. b) To RC ceiling, exposed beams,stair case soffit and sides of lift shaft
2
walls m 274.10
2
28.00 78mm thick cement sand screed m 711.37
29.00 Apply three coats of plastic emulsion paint to internal wall surfaces, columns and beams.
2
m 68.79
Ditto but to RC ceiling, stair case soffit and sides of lift shaft walls m
2
68.79
30.00 For all RHS Works of size RHS 80x80x3 mm
a) RHS 80x80x3 mm kg 467.50
b) RHS 60x60x3 mm kg 263.43
c) RHS 50x50x3 mm kg 216.34
d) RHS 40x40x3 mm kg 51.15
31.00 For all PURLIN
a) RHS 80x80x3 mm kg 467.50
b) RHS 60x60x3 mm kg 249.97
c) RHS 30x30x3 mm kg 61.78

32.00 Anchor bolt (J-Bolt) dia 16 mm development length 400 mm 104.02


Roof cover in EGA 400, 0.4mm thick
33.00 997.56
2
m
Semi Solid Wooden Doors
34.00 pcs 1113.27
35.00 Fabricate or supply and fix doors made of steel-reinforced PVC Doors
pcs 2093.77
36.00 wooden frames cupboards pcs 1285.77
INSTITUTE OF TECHNOLOGY

COLLEGE OF ENGINEERING

DEPARTEMENT OF CONESTRUCTION TECHNOLOGY AND


MANAGEMENT

COST ENGINEERING SEMISTER PROJECT

CONSTRUCTION COST ESTIMATION OF


RESIDENTIAL BUILDING

SUBMITTED TO:- INESTRUCTOR ADMASU BOGALE


SUBMISSION DATE:- GINBOT 28/2009 E.C
THIS IS SO DONE BY

NAME ID.NO.
1 YARED WUBSHET DBU07000691UR

2 AFOMIA ENDALAMAW DBU07001044UR

3 KALEAB GETACHEW DBU07000864UR

4 BETHELIHEM MAMUYE DBU07003434UR

5 MEKDES ASEGID DBU07000674UR

6 SAMUEL ASRAT DBU07001054UR

7 ZELEKE TEMACHEW DBU07000077UR

8 YISMAW ESKEZIYA DBU07000516UR

9 REDEAT ABERRA DBU07001276UR

10 AMANUEL BERHANE DBU07000376UR

11 ABRHET BIRHANU ENGR/928/06

GROUP 1
SETION -C
Acknowledgment
We would like to acknowledge our lecturer Admasu Bogale, B.Sc. in
construction technology and management for his unlimited support
during the out come of this project, starting form supplying the necessary
data ,and forwarding different informations .Beside this, we would like to
thank him again, for his friendly and professional approach to advise us.
It would have been impossible to have this project completed without the
help of the above mentioned person & our peergroups from major to least
help. Finally ,yet importantly, we would like to thank our families for their
constant and priceless support in different aspects.