Professional Documents
Culture Documents
Fig. 3 Electrical Equipment Layout Within Enclosure Fig. 4 Electrical Equipment During FAT
B. Subsea Enclosure
Voltage: 6/10(12)kV
Current: 1600A
Frequency: 200Hz
Design life 25 years
Water depth: 2000m
Design pressure: 200 bar
Test pressure: 300 bar
Mating cycle number: 100
Operating temperature: -5C to 40C
Storage temperature: -25C to 50C
Operating temperature (compressor): 50C permanent
Fig. 6 36kV 900A 50Hz penetrator
The use of wet mate connectors allows a defective module to
be retrieved on its own while the other modules remain in D. Monitoring and Control
operation. The connectors reduce downtime for the complete
subsea station and allow the use of intervention vessels with The correct remote monitoring and control of electrical
lower rated lifting equipment since only the faulty module is distribution equipment is a key requirement for the operation of
required to be retrieved for repair. For each connection system, the subsea power distribution system. The basis for correct
interface engineering was necessary to cover the mechanical control is the availability of reliable data giving the exact
aspects, such a sealing mechanisms, mechanical interfaces condition of all the electrical equipment. Remote monitoring and
(pressure induced forces, fixation methods), assembly process, control implies a communication system that is very reliable and
as well as the electrical aspects, and especially the connection has no common mode failures. The architecture of the
toward electrical equipment inside the different modules monitoring and control system is shown in Fig. 7 and illustrates
(mechanical connection, temperature rise, electrical field, test the use of redundancy as a means to reduce the number of
philosophies and methods). The wet mate connection system common-mode failures. An important feature of the monitoring
including jumpers and penetrators underwent a complete system is self-monitoring for remote diagnosis when necessary.
qualification program as components and as a complete All failures within the monitoring and control system and
system. The interfaces were also qualified independently before communication system are signaled to the operator.
The communication system is Ethernet based and uses happen and then be forced to react quickly. Data from condition
redundant Ethernet switches and fibers to reduce the number of monitoring offers the diagnosis capability for preparing
common mode failures. The key components are the redundant intervention, and when possible, to repair the system by
controllers which are industrial computers having no moving reconfiguring it via software that are remotely uploaded.
parts (no hard disk drives). Associated with the controllers are In order to be able to predict a failure, it is necessary to have
redundant input racks and communication connections to extensive data and be able to analyze it. The amount of data
intelligent electronic devices (IEDs). These provide the that is available in a subsea compression station is enormous.
information for the monitoring function. The control of the In addition to all the analog and digital information directly
switchgear is by means of redundant hard-wired connections linked to the electrical power distribution system, there is also
from the controller outputs to the close and trip coils of the the information related to the process equipment. For example,
circuit-breakers. This allows the operator to continue production the currents and voltages of the magnetic bearings of the
even should both of the redundant protection relays of a motors and driven equipment are read several times per
particular feeder not be in service. The purpose of the second and sent onshore for analysis and storage. The
communication connections to the IEDs is to retrieve analog terabytes of data are time stamped and stored in such a
values of current, voltage, active and reactive power for each manner as to be able to retrieve them at a later date for
circuit for use by the substation operator. These connections analysis. All available data is captured and stored, even if to
also allow the modification of certain parameters such as date analysis of all data is not implemented. The idea is to have
protection settings during operation. Such work is carried out at data available for any analysis that is deemed necessary in the
a dedicated Engineering Work Station (EWS). For the LV future to provide the information necessary to predict possible
feeders the circuit-breakers provide short-circuit current failures. All condition monitoring data is accessible via the
protection only. The controllers are connected to instrument EWS.
transformers and provide the overload protection. The reason
for this is that protection settings on the LV circuit-breakers F. Assembly of HV Switchgear in Enclosure
could not be changed from a remote location via a
communication link. As described above, the complete electrical distribution
system is installed within a cylindrical enclosure. It is necessary
to design both the electrical equipment and the enclosure to
allow easy installation of the equipment without damage. All
electrical equipment is installed on racks, one rack per function.
Each rack is connected via cables or via flexible connections
thus preventing any mechanical stress and avoiding the
transmission of mechanical shocks and vibrations. The
interface between the switchgear racks and the enclosure is
very limited in order to avoid stresses due to the slight changes
in dimension of the enclosure while being installed on the
seabed.
E. Condition Monitoring
V. ENGINEERING
VI. TESTING