You are on page 1of 5

TECHNICAL NOTE

Revisions to BS8006 for


reinforced soil what do
these mean for the industry?
By Stephen P Corbet, Aecom, (Chairman BSi B526/4 Reinforced
and Strengthened Soils), Chris Jenner, Tensar International UK,
Graham Horgan, Huesker UK.
Presented at the Ground Engineering Slopes Conference on 16 November 2010.

O
ver the past 15 years, the design as fills. Part 2 will be based on the ments with basal reinforcement for live loads may be set at zero to
of reinforced soil structures has CIRIA C637 Soil Nailing Best and with piles or other foundation produce a worst-case combination
evolved from the principles set Practice Guidance, but with more improvements have been addressed. for the design load.
out in the first edition of BS8006, emphasis on the design of rein- n In Annex A the derivation of par- The loads, both dead and live, are
published in 1995. The introduction forced soil slopes tial factors for polymeric reinforce- calculated in their unfactored form
of Eurocodes made a revision to ment has been updated to follow the as characteristic values, which then
BS8006:1995, essential as EN1997- The changes principles described in PD ISO CR have the appropriate partial factor
1 specifically excludes the design of The BSi committee of experts has 20432: 2007. applied to give the design load.
reinforced soil structures and slopes. reviewed the whole document and n A new Annex has been added The resisting forces in any appli-
The BSi has completed the revi- the following changes have been with seismic effects on reinforced cation are generated from the avail-
sion of BS8006 and Part 1, which made. The changes were made pub- soil structures, based on experiences able shear strength of the soil and
covers the design of reinforced fills lic in a draft for public comment, form Japan and US, with cross refer- the tensile strength of the reinforc-
was published at the end of 2010, published in July 2009, and the ence to BSEN 1998. ing elements.
while Part 2, which covers the comments received were incorpo- n Other Annexes giving test pro- The shear strength of the soil,
design of reinforced insitu soils, is rated into the final document. cedures have been reviewed and allowing for any pore pressure,
due to be published this year. n Clauses and information which removed where now described in should be a characteristic value
conflicted with BSEN1997-1, BSEN testing standards. determined as a cautious estimate
Introduction 14475 & BSEN 14490 have been n New features include: The use of the value recognising the limit
Since the publication of BS8006 in removed, but we have not revised of recycled materials is encouraged state under consideration. For walls
1995 after 10 years of drafting in all terminology to agree with BSEN using the Highways Agency docu- and slopes, the peak friction angle
committee, the design of reinforced 1997-1. ment HD35/04 as a basis; cohesive is used. In all applications, the con-
soil structures has evolved as the n The correction of some outstand- fills can benefit from inclusions sideration of external, internal and
results from research have improved ing errors found in text (at least two of drains within the soil layers to compound stability is required. For
the understanding of the behaviour found in the last published version). reduce the drainage paths for excess internal and compound stability,
reinforcement in soil. n The partial factors were reviewed. pore water pressure; new reinforce- the resistance provided by the soil is
The publication of the Eurocodes The review was to look at the pos- ments can be considered, such as supplemented by the strength of the
for design has resulted in the need sibility that the partial factors in electro-kinetic geosynthetics, used reinforcement.
to withdraw or revise all existing BS8006 could be the same or very to set up an electro osmosis system The reinforcement strength is
design codes in the UK and Europe. close to the partial factors used in for rapid drainage; low strain/high derived following a procedure
The Eurocode EN1997-1 Geotech- EN1997-1. The current situation is strength geogrids. described in an Annex of the docu-
nical Design does not include any that the partial factors in BS8006 ment.
provision for the design of rein- will remain unchanged. Sections 6 and 7 reinforced Reinforcement is defined as being
forced soil structures and the UK n A new section on reinforced mod- soil walls and steep slopes extensible if the design strength is
NAD makes a clear statement to ular block walls has been added to concepts and fundamental sustained at a total axial strain value
this effect. cover this new technology. principles (Jenner) >1%, and inextensible if the design
In particular, the factors to be n The design of facings for slopes To satisfy the requirements of a strength is sustained at a total axial
applied to the strength of the rein- and walls has been reviewed. limit state code, partial load factors strain <1%. This definition can
forcing elements cannot be deter- n All text previously included by are applied to the actions and mate- determine the actual design method
mined from the Eurocode. the Highways Agency in BD70, has rial factors are applied to the mate- adopted for a particular application.
been moved to BS8006-1 for bridge rial properties. The Code of Practice is applica-
Structure of the code abutments and bank-seats. Once the factors have been ble to all types of geosynthetic and
The standard will be published in n The construction details have applied, the requirement for stabil- steel soil reinforcement.
two parts: Part 1: Reinforced Fills been revised, with more informa- ity is that the design restoring forces
Retaining walls, slopes, basal rein- tion included for information. and moments should be greater Vertical walls and bridge
forcement and transfer platforms; n Advice on the use of vegetation on than the design disturbing forces abutments
and Part 2: Strengthened Insitu steep slopes is included. The advice and moments. In a particular appli- The principles described in the
Soils Soil nails. includes information about the best cation, the load factors applied to previous section apply to both
The two parts recognise that the methods for getting grass and other dead loads and live loads can vary reinforced soil walls and bridge
design of insitu soils reinforced with vegetation to grow and survive. depending on the load combination abutments, which are designed as
soil nails is completely different to n The problems associated with lat- under consideration; in some cir- vertical structures.
the reinforcement of soils placed eral forces at the edges of embank- cumstances, the partial load factors Other structures with facing

26 ground engineering April 2011


Effects Combinations Reinforced slopes
The design methods for reinforced
A B C slopes, generally defined as those
slopes with face angles greater than
Dead load of the structure ffs = 1.5 ffs = 1.0 ffs = 1.0 20 to the vertical, are all derived
from limit equilibrium methods,
Dead load of the fill on top of the structure ffs = 1.5 ffss = 1.0 fs = 1.0 originally derived for unreinforced
Dead load of bridge and bank seat ff = 1.2 ff = 1.0 ff = 1.0 slopes. The Code does not limit the
methods that can be used for design,
Backfill pressure behind the bank seat ffs = 1.5 ffs = 1.5 ffs = 1.0 provided that they can be adapted
to a limit state format. However,
it does describe the most common
methods in some detail.
Backfill pressure behind the structure ffs = 1.5 ffs = 1.5 ffs = 1.0
The partial factors are defined
Horizontal loads due to creep and shrinkage ff = 1.2 ff = 1.2 ff = 1.0 in Table 4 (overleaf). with only
two load cases, ULS and SLS. The
Traffic loading Over the Behind the reinforced friction angle of the fill should be
entire zone, fq = 1.5 defined as the peak value and, as
structure, with the wall design, there are par-
fq = 1.5 tial factors of safety applied to soil/
reinforcement interaction and slid-
Bridge vertical live load HA fq = 1.5 fq = 1.5 ing along the base.
The requirement for the inclusion
HA and HB fq = 1.3 fq= 1.3 of the Moment Correction Factor c
Braking dynamic load HA fq = 1.25 fq = 1.25 has been removed in the revised ver-
sion of the BS. Any potential failure
HA and HB fq = 1.1 fq = 1.1 surface that passes around the rein-
forced soil zone without cutting a
Temperature effects fq = 1.3 fq = 1.3 layer of reinforcement is now ana-
lysed using the approach defined in
Table 1: Partial load factors for walls Eurocode 7.
that varies between the at-rest For reinforced slopes where the
Soil material To be applied tan f fms = 1.0 fms = 1.0 condition in the upper zone reduc- face angle is 45 or less the need for
factors ing to active conditions deeper in a formal facing may not be required.
To be applied to c fms = 1.6 fms = 1.0 the structure with wall friction cal- In those situations the reinforce-
culated (see Figure 2). ment capacity close to the front face
To be applied to cu fms = 1.0 fms = 1.0 may be limited because of bond,
Ultimate limit state although higher shear strengths may
The appropriate partial factors are be mobilised because of the low
Soil/ Sliding across fs = 1.3 fs = 1.0 applied to the loads and materials confining stress. A check of super-
reinforcement surface of depending on the Load Case under ficial stability can be carried out to
interaction reinforcement consideration. Load Case A, with assess the stability of a free face in
factors maximum factors applied through- resistance to sliding on a plane that
Pull-out resistance fp = 1.3 fp = 1.0 out, is normally the critical condi- is very close, and parallel, to the
of reinforcement tion for reinforcement capacity and slope surface.
foundation bearing pressure and It is noted in the code that com-
Partial factors Foundation bearing fms = 1.35 n/a sometimes governs reinforcement pound stability considerations
of safety capacity: to be anchorage. where a slip surface passes partially
applied to qult Load case B, with minimum mass through the reinforced fill and par-
Sliding along base fs = 1.2 n/a of the structure but maximum over- tially through the unreinforced fill
of structure or any turning forces, is normally critical may well be the critical situation.
horizontal surface for sliding along the base of the rein-
where there is forced soil block and reinforcement Section 8 basal
soil-to-soil contact anchorage. reinforcement and load
transfer platforms (Horgan)
Table 2: Partial load factors for abutments Serviceability limit state UK BS8006-1 2009 Section 8 basal
Load Case C, with dead loads only reinforcement and basal reinforce-
angles within 20 of the vertical can Design methods for walls and partial factors of unity, is used ment over piles (aka load transfer
also be designed as vertical struc- The wall design approach is to determine the serviceability limit platforms), updates the previous
tures to the Code. Table 17 (Table 1 based on the classification of the states of foundation settlement and guidance and attempts to expand/
above) of the Code gives the partial reinforcement materials, whether reinforcement tension for internal clarify guidance considered ambigu-
load factors for load combinations the reinforcement is extensible or strains. The limit value of reinforce- ous in the previous draft and to
associated with walls and Table 18 inextensible. ment tension in the serviceabil- reflect changes in best practice since
(Table 2 above) gives the same infor- Extensible reinforcement is ity check is defined by a theoretical BS8006 was first published in 1996.
mation relating to bridge abutments. designed using the Tie-Back Wedge post-construction strain value. The main additional issues
Soil material factors can be method where the stress condition For a wall, the limit is 1% and addressed in the updates relate to:
extracted from Table 16 (Table 3 within the reinforced soil block is therefore the SLS allowable load- n Consideration of pile cap
overleaf) with a number of partial taken to be an active stress state and carrying capacity is the value at geometry;
factors of safety relating to soil/ wall friction on the back of the block which the reinforcement would n Consideration of alternative
reinforcement interaction, founda- is zero (see Figure 1). strain 1% between the end of con- arching mechanisms;
tion bearing capacity and sliding When inextensible reinforcement struction and the end of the design n More emphasis on assess-
along the base of the structure. is used, the Coherent Gravity design life (Figure 3, overleaf). For an abut- ing/controlling the settlements
The most adverse loads likely to method is used with a stress condi- ment, the limiting post-construction between piles;
occur should be considered. tion within the reinforced soil block strain is 0.5%. n Greater emphasis on collabo-

ground engineering April 2011 27


TECHNICAL NOTE
ration between geosynthetics multiple layer reinforcement such as
and pile designers; walls and slopes are deemed small, Figure 2: Coherent gravity stress state
n Time dependant consolidation of the frictional strength is represented 0 Ka Ko
soil between piles and consideration by tanp, the peak effective angle of
of partial support between piles; internal shearing resistance. Larger
n Additional guidance on anchor- strains are allowed in other scenar-
age details etc. ios, for example an embankment
subject to differential settlement.
Selection of soil parameters In these cases, the frictional
and partial factors strength is represented by large Kj J
The British standard differentiates strain values. For cohesionless soils H
between soils/fills used in slopes this is the value when the soil shears Arc tan 0.3
and walls and those used in embank- at constant volume. 6m
ments. Since the strains induced in Consideration of foundation

Ws2
Ws1
z

Soil 1: Soil 2:
c1 1 1 1 c2 2 2 2 T
hj W

Tpj
H P

L-2e b = 0 for tie back Tcs


wedge method.
b = (1.2 L/H) f2
for coherent gravity
method
Isochrone for end of construction
Isochrone for end of design life
Prescribed post-construction strain limit
L
Figure 3: Assessment of post-construction strain
Figure 1: Stressed imposed by the soils and surcharges

Partial Factors Ultimate limit state Serviceability limit soils: BS8006-1 assumes that all of
state the embankment loading will be
transferred through the piles down
Soil unit mass eg slope fill ffs = 1.5 fs = 1.0 to a firm stratum either by direct
arching on the pile caps or by the
External deal loads eg line ff= 1.2 ff = 1.0 load carried to the piles by the geo-
Load factors or point loads synthetic reinforcement.
Consequently, the characteristics
of the soft foundation soil is con-
External live loads eg traffic fq = 1.3 fq= 1.0 sidered only with regard to the type
loading of piles used and their installation.
However, the time dependant con-
Soil material To be applied tan fr fms = 1.0 fms = 1.0 solidation of soil between piles is
factors subsequently discussed.
BS 8006:1996 was one of the first
To be applied to c fms = 1.6 fms = 1.0 national codes to adopt limit state
principles and these are maintained
in the updated code.
Reinforcement To be applied to the The value of fm should be consistent
material factor reinforcement base strength with the type of reinforcement to be Consideration of pile
used and the design life over which the cap geometry
reinforcement is required (see 5.3 and The original guidance did not dif-
Annex A) ferentiate between circular or square
Soil Sliding across surface or fs = 1.3 fs = 1.0 pile caps of equal dimension yet the
reinforcement reinforcement area ratio of the square pile cap (a2)
interaction is different to that of a circular cap
factors Pull out resistance of fp = 1.3 fp = 1.0 (D2/4). Yet this dimension is used
reinforcement subsequently used to determine the
amount of arching (Marstons ratio)
Partial factors Sliding along base of fs= 1.2 NA or stress redistribution that occurs
of safety structure where there is within the piled embankment. The
soil-to-soil contact new guidance recommends reduc-
Table 3: Partial factors for reinforced slopes ing the design dimensions of cir-

28 ground engineering April 2011


Embankment Surcharge Ws
Optional geotextile separator
(dependant on embankment fill material)
Outward
shear stress
Fill: ,cv Minimum cover
Lo Reinforcement Anchor bond length 500mm to
H (varies) reinforcement
Lb Pfill

BRP layer
depth can vary
Lds
Lp
Pile
Soft foundation caps
Edge trench
option detail
Piles

Figure 4: anchorage length (Lb) at the edge of the piled area


Piles with pile caps
Partial factor Ultimate limit Serviceability (pre-cast driven, vibro concrete columns
driven/cast insitu, continuous flight auger)
state limit state
Load factors Figure 5: Reinforcement anchorage at edge of fill

Soil unit mass, ffs = 1.3 ffs = 1.0 Pile arrangement Arching coefficient
eg embankment fill
End-bearing piles Cc = 1.95H/ a -0.18
External dead loads, ff = 1.2 ff = 1.0 (unyielding)
e.g. line or point loads
Friction & other piles Cc = 1.5H/ a -0.07
External live loads, e.g. fq = 1.3 fq = 1.0
traffic loading Table 5: Arching coefficient Cc

Soil material factors mined by using Marstons formula: this limit would result in consid-
erably more design load across
To be applied to tan fms = 1.0 fms = 1.0
To be applied to c fms = 1.6 fms = 1.0
sv [ ]
Pc = Cca
H
2
the reinforcement than embank-
ment heights just above this level.
Additional criticism related to the
To be applied to cu fms = 1.0 fms = 1.0 where: fact the ratio of the vertical stress
Pc is the vertical stress on the exerted on top of the pile caps to
Soil/reinforcement interaction factors pile caps; the average vertical stress at the base
sv = (ffsH + fqws) and is the fac- of the embankment was dependant
Sliding across surface fs = 1.3 fs = 1.0 tored average vertical stress at the solely on pile type and independent
of reinforcement base of the embankment; of the type of fill used within the
Pull-out resistance of fp = 1.3 fp = 1.0 is unit weight of the embank- embankment.
reinforcement ment fill; Finally a criticism that vertical
H is the height of the embank- equilibrium is not satisfied (Eekelen,
Table 4: BS8006 Section 8 Partial factors ment; 2008). However, neither the load act-
ws is the uniformly distributed ing across the reinforcement nor the
cular pile caps to consider a square cent soil. surcharge loading; increased load acting on the pile caps
pile of an equivalent area. Where BS8006-1 identifies a minimum a is the size (or diameter) of the are calculated directly, but rather
circular pile caps are to be used, height whereby partial arching pile caps; indirectly from the ratio of increase
the diameter of the pile should be begins to develop but additional Cc is the arching coefficient. in stress concentration on the pile
reduced to produce an effective pile loads placed at the surface of the Where the value of the arching coef- caps to the average vertical stress at
cap width aequ, embankment still influence the load ficient will vary depending on the the base of the embankment.
carried by the reinforcement. This type of piles. BS8006-1 2009 Section 8 allows
aequ = (D2/4)0.5 hence aequ = 0.886D minimum height is : Several authors have studied and for an alternative theoretical solu-
compared the phenomena of soil tion which may be used to deter-
where: H 0.7(s a) arching using a variety of physical, mine the vertical load acting across
a is the size of the pile caps analytical and numerical models to the reinforcement based on work
(assuming full support can be gener- where: try to gain a better understanding presented by Hewlett and Ran-
ated at the edges of the caps); a is the size of the pile caps (or aequ and quantify the load acting across dolph, 1998, which was based on
D is the diameter of the pile cap considering circular pile caps) the reinforcement and distributing the observed failure mechanism
s is the spacing between adjacent directly to the pile caps (Alexiew from model tests and considers a
Determination of load acting piles 2002, Eekelen 2008, Kempton et al series of hemispherical domes. The
across the reinforcement BS8006-1 also identifies a criti- 1998, Love and Milligan 2003, Rog- theory determines the efficacy E as
Due to the significant differences cal height concept above which any beck 1998, Stewart and Filz, 2005). the proportion of the embankment
in deformation characteristics that additional embankment weight or One criticism of the original code weight carried by the piles, hence
exist between the piles and the sur- surcharge loading placed at the sur- is that the distributed load acting the proportion of the embankment
rounding soft foundation soil, the face of the embankment is deemed across the reinforcement was very weight carried by the geosynthetic
vertical stress distribution across the to pass directly to the pile caps and sensitive to embankment heights reinforcement may be determined
base of the embankment is assumed not influence the reinforcement. around the critical height (1 E).
to be non-uniform. Soil arching The ratio of the vertical stress The original guidance utilises
between adjacent pile caps induces exerted on top of the pile caps to H 1.4(s a) Marstons formula to determine the
greater vertical stresses on the pile the average vertical stress at the base distributed load acting across the
caps than on the surrounding adja- of the embankment may be deter- Embankment heights just under reinforcement

ground engineering April 2011 29


TECHNICAL NOTE
ffs is the partial load factor for soil This settlement can be related to References
WT =
s2 a2
[
1.4 sffsg (s a) 2 2
]
s a (p/sv) unit weight (see Table 1); an increase in stress from the instal- BS 8006:-1:2010 Code of Practice for
fq is the partial load factor for lation of the temporary working Strengthened/reinforced soils and fills,
external applied loads (see Table 1). platform or as a result of initial fill BSi London 2010.
where: placement or by external factors BS EN 1997-1:2005 Geotechnical
WT is the distributed vertical load Reinforcement details such seasonal fluctuations in the Design, BSi London 2005
acting on the reinforcement between The design approach essentially ground water level increasing the CIRIA C637 Soil Nailing best prac-
adjacent pile caps; determines the requirement for two effective stress on the insitu soil. tice guidance CIRIA 2005.
ffs is the partial load factor for soil orthogonal layers of geosynthetic Hence the time dependant con- PD ISO CR 20432 Guidelines for the
unit weight (see Table 1); reinforcement at the base of the solidation of soil between piles is derivation of the longterm strength of
fq is the partial load factor for piled embankment, one longitudinal important in reaching the assumed geosynthetics for soil reinforcement
external applied loads (see Table 1). layer parallel along the centre line of end design condition of no partial HD 35/04 Conservation and the Use
To satisfy vertical equilibrium the embankment and one transverse support between piles. of Secondary and Recycled Materials
then the remaining load must be layer perpendicular across the line Consideration can also be given AASHTO (1998), Interim Standard
carried directly by the pile caps, WP of the embankment. to the introduction of a compress- Specifications for Highway Bridges,
The longitudinal reinforcement is ible layer between the pile caps to AASHTO, Washington DC, 16th
WP= (f fsgH + fqws ) s2 WT (s2 a2) designed to resist the redistributed ensure deflection of the geosynthet- Ed
vertical load Trp. ic during the initial placement of the Alexiew, D., Piled embankment
(although this formulation is not The transverse reinforcement is overlying fill. design: Methods and case studies, Proc.
provided in BS8006 -1 2009). Once designed to resist both redistributed The maximum mid-span deflec- XV Italian Conference on Geosyn-
the distributed load WT acting across vertical load Trp and to resist the lat- tion y of extensible reinforcement, thetics, Bologna,October 2002. In:
the reinforcement is determined, eral thrust of the embankment Tds. spanning between pile caps, may be Lingegnere e larchitetto, Special Issue
then for an extensible reinforce- To mobilise these loads the rein- determined from the formulation 1-12/2002. pp. 32-39. 2002.
ment the tensile load Trp per metre forcement should achieve an ade- below (after Giroud) DIN 1054:2005-01 Baugrund; Sicher-
run, generated in the reinforcement quate bond with the adjacent soil heitsnachweise im Erdund Grundbau.
resulting from the distributed load at the extremities of the piled area y = (s a) 3 Eekelen, van SJM, Van, MA, Bezu-
WT is determined by to ensure that the maximum limit 8 ijen, A. Design of piled embankments
state tensile loads can be generated considering the basic starting point of
1
Trp = WT (s a) 1 + 6 between the outer two rows of piles. where: the British Standard BS8006. Proceed-
2a Across the width of the embank- a is the size of the pile caps; ings of the Fourth European Geo-
where: ment the reinforcement should s is the spacing between adjacent synthetics conference. Edinburgh,
Trp is the tensile load in the rein- extend a minimum distance (Lb) piles; FHWA(1996) Mechanically Stabilized
forcement; beyond the outer row of piles, (see is the strain in the reinforce- Earth Walls and Reinforced Soil Slopes
is the strain in the reinforce- Figure 4). ment. Design and Construction Guidelines
ment. The reinforcement may be The thickness of the compressible (FHWA-SA-96-071).
The above equation has two extended around the row of gabions layer can be such that it can accom- Giroud, JP, (1995). Technical Note:
unknowns Trp and , and may be and returned into the embankment modate the deflection of the geo- Determination of geosynthetic strain
solved for Trp by assuming a maxi- fill to develop the necessary bond synthetic during the early stages of due to deflection, Geosynthetics Inter-
mum allowable strain in the rein- length (see Figure 5). embankment construction, ensuring national, Vol. 2, No.3, pp.635-641
forcement and by an understanding Depending on the geometry of that the assumed design deflections Hewlett, WJ, Randolph, MA.
of the load/strain characteristics of the embankment, it may be difficult are achieved. Analysis of Piled Embankments.
the reinforcement at different load to achieve an adequate bond length Ground Engineering. April pp.12-18.
levels. Initial tensile strain in the at the extremity of the piles by Conclusions 1988
reinforcement is needed to gener- maintaining the reinforcement in a BS8006 was first published in 1995. Kempton, G.T., Russell, D., Pier-
ate a tensile load; BS8006 stipulates horizontal alignment as depicted in Section 8 of the code has been used point, N.D., Jones, C.J.F.P. Two and
that a practical upper limit of 6% Figure 4. One solution that may be to successfully design a vast number three-dimensional numerical analysis of
strain should be imposed to ensure considered is to use a row of gabi- of piled supported embankments the performance of piled embankments.
all embankment loads are trans- ons, as a thrust block along the top worldwide. Sixth international conference on
ferred to the piles. of the outer row of piles. BS8006-1 2009 updates the previ- geosynthetics, Atlanta, Georgia.
In addition to the load on the Another detail that may be con- ous guidance to reflect better indus- pp.767-772. 1998.
reinforcement generated by the sidered is the inclusion of a small try understanding of the behaviour Love J, Milligan G. Design meth-
redistributed vertical embankment periphery trench just beyond the of such complex earthworks and to ods for basally reinforced pile-supported
load, the reinforcement needs to edge piles, running parallel to the reflect changes in best practice. embankments over soft ground, Ground
resist the outward thrust from the centreline of the embankment; the Currently there is a variety of dif- Engineering, Vol. 36, No. 3. 2003.
embankment. The reinforcement trench is typically only as deep as ferent design approaches, which dif- Rogbeck, Y, Gustavsson, S,
tensile load Tds needed to resist the the piling mat or pile cap depth. The fer mainly in the amount of arching Sdergren, I Lindquist, D. Embank-
outward thrust of the embankment reinforcement can be extended into considered and the degree of sup- ment support over piles using geogrids.
may be taken as the trench and when backfilled, will port offered by the existing sub soil. Sixth international conference on
return into the embankment fill to The BS8006-1 assumption that geosynthetics, Atlanta, Georgia.
Tds = 0.5Ka (ffsH + 2fqws)H develop the necessary bond. all of the embankment loading will pp.755-762. 1998.
be transferred through the piles or Stewart, ME, Filz, GM. Influence
where: Time dependant consolidation by the geosynthetic reinforcement of Clay compressibility on Geosynthetic
Tds is the tensile load in the rein- of soil between piles onto the piles can be considered Loads in Bridging Layers for Column-
forcement per metre run needed BS8006-1 assumes that all of the conservative. Supported Embankments, GSP 131
to resist the lateral thrust of the embankment loading will be trans- However, the potential use Contemporary Issues in Foundation
embankment fill; ferred through the piles down to a of compressible layers beneath Engineering, Geofrontiers 2005,
Ka is the active earth pressure firm stratum either by direct arch- the geosynthetic reinforcement Austin
coefficient [ = tan2(45 fcv/2)]; ing on the pile caps or by the load between pile caps can ensure that
H is the height of the embank- carried to the piles by the geosyn- the end design condition of no
ment; thetic reinforcement. In reality, the partial support between piles can
is the unit weight of the embank- soil between the piles will need to be achieved during construction.
ment fill; undergo some initial degree of con- This would make consideration
ws is the surcharge intensity on solidation to enable tensile forces in of the time dependant consoli-
top of the embankment; the geosynthetic to be mobilised. dation of soil largely academic.

30 ground engineering April 2011

You might also like