Professional Documents
Culture Documents
Frequently Asked
Questions:
Risk Management
Version:1.4, November 2008
An issue is a problem or concern that may The Project Sponsor has ultimate
impede the progress of the project if not accountability for Risk Management. This
addressed. includes ensuring that there are adequate
resources for managing the project's risks
A risk is any factor (or threat) that may and that there is adequate active
adversely affect the successful completion participation in the risk management
of the project in terms of achievement of process by a wide cross-section of
its outcomes, delivery of its outputs or stakeholders. The Project Sponsor also
adverse effects upon resourcing, time, monitors the progress and effectiveness of
cost and quality. the Risk Management Plan.
If the issue cannot be resolved and The Project Manager is responsible for
becomes a threat to the successful monitoring and managing all aspects of
completion of the project, then it becomes the risk management process including:
a risk and should be added to the Risk
Register. the development of the Risk Register and
Risk Management Plan
Who is responsible for risk the continual monitoring of the project to
management? identify any new or changed risks, and
updating the Risk Register accordingly
Many people involved in a project have continual monitoring of the effectiveness
some responsibility for project risk of the Risk Management Plan
management including the Project regular reports on the status of risks to the
Manager, Steering Committee, Project Project Sponsor and Steering Committee.
Sponsor, potential Business Owners,
project Team Members and working
groups. It is important that they know that
For a medium to large project, the risks Who approves risk mitigation
are identified by, (as a minimum), the actions and/or their associated
Project Manager, Project Team members, costs?
Steering Committee members, Business
Owners and external key stakeholders by Each mitigation action needs to be costed
the use of a number of meetings or as part of the risk evaluation process. On
brainstorming sessions. the basis of the risk grading and the
associated mitigation costs, a decision will
For a small project, the Project Manager be made as to whether to undertake the
may identify risks and develop the Risk mitigation action. The Project Manager
Register, perhaps with input from the may make this decision, if it is within their
Project Sponsor/Senior Manager and level of responsibility and the cost within
colleagues or a small group of key their budget, otherwise Steering
stakeholders. Committee or Sponsor approval may be
required.
For large/complex projects, it is often
advisable to use an outside facilitator. How do I (the Project Manager)
Preparation may include an environmental report progress on risks?
scan, seeking views of key stakeholders
etc. Reference to the Risk Identification Risk Status should be reported to the
Tool may also provide some useful Steering Committee or Project
prompts. Sponsor/Senior Manager on an agreed
regular basis and form part of the Project
Who should be involved in risk Status reporting processes.
reviews?
How do I describe the risk?
For a medium to large/complex project,
the risks are reviewed by the Project Phrasing of the risk should use a
Manager, Project Team members, newspaper headline style statement
Steering Committee members and short, sharp and snappy (eg. Inadequate
external key stakeholders. funding to complete project).
The risks evaluated are then graded using the risk matrix in the following table. For the
example, above this would result in a grade of D for the loss of funding and an A for each of
the other two risks.
Seriousness
low medium high
low N D C
Likelihood
medium D C B
high C B A
In the case of larger or more complex projects, the matrix should be expanded to ensure an
A Grading is automatically assigned to any risks defined as extremely high seriousness; that
is, any risk which, if realised, will cause the project to fail or stop. An example is unexpected
legislative changes.
Seriousness
low medium high EXTREME
low N D C A
Likelihood
medium D C B A
high C B A A
Acknowledgements
This Fact Sheet contains elements of the Tasmanian Government Project Management
Guidelines prepared by the Department of Premier and Cabinet.
Elements of this FAQ have been derived from the Australian Standard AS/NZS 4360:2004.