EXCAVATION

1 | Page
Times Dimension Result Description Unit Quantity
Excavation
W.B.L.F.F
Excavate top soil
Length/breadth

5.000
Add fdn spr
0.600
5.600

5.60 Excavate top soil for preservation


5.60 average 200 mm deep
31.36 m2
Depth preserved top soil in temp. spoil
5.60 heaps average 30.00 m dist
5.60
0.20
6.27 m3
Pit excavation
Depth
Lean concrete 0.050
Footing 0.025
Stump 1.250
1.550

Less excavation
Top soil 0.200
1.350

Excavate pad footing n. e 0.25 m depth


0.60
0.60
0.25
4/ 0.36 m3

0.60 Excavate pad footing n. e 1.00 m depth


0.60
0.75
1.08
m3
0.60 Excavate pad footing n. e 2.00 m depth
0.60
0.35

2 | Page
0.52

m3
Times Dimension Result Description Unit Quantity

Ground beam excavation

Length
5.000
Less column stump
2/0.150 0.300
4.700

4/ Depth
0.200
Add
Blinding 0.050

4.70 Less excavation


0.05 Top soil 0.200
0.25 0.050
0.24 m3

3 | Page
MATERIAL
Times Dimension Result Description Unit Quantity
Blinding and Concrete

Blinding footing
Length 0.600
Breadth 0.600
Height
4/ 0.60 0.050
0.60
0.05 Concrete grade 7 blinding n. e 100 thick
0.07 laid on earth m3

Footing
Length 0.600
Breadth 0.600
4/ Height
0.60 0.250
0.60
0.25 Rein. foundation in situ concrete grade
0.36 20 in isol. foundation bases m3

Stump
Height stump below ground 1.250

Add
Slab consist of:
Hard core 0.150
Blinding 0.050
Concrete slab 0.100
1.550
4/
(continue)

Length 0.300
Breadth 0.300
1.55
0.30 Rein. in situ concrete grade 20 in isol
0.30 column stump
3
0.56 m

4 | Page
Filling soil above footing

Add soil (total space)


Length 0.600
Breadth 0.600
Height
1.250
Volume 0.450

Times Dimension Result Description Unit Quantity


(continue)

4/ Less soil (stump space)


Length 0.300
Breadth 0.300
0.45 Height
0.11 1.250
1.36 Volume 0.113 m3

Blinding ground beam


Length 4.700
Breadth 0.250
4/ Height
4.70 0.050
0.25
0.05 Concrete grade 7 blinding n. e 100 m
0.24 thick m3

Ground beam
Length 4.700
Breadth 0.250
Height
4/ 4.70 0.500
0.25
0.50 Rein. foundation in situ concrete grade
3
2.35 20 in ground beam m

Hard core
Length/Breadth 5.000

Less of stump column


4.70 2/0.150 0.300
4.70 4.700

5 | Page
0.15 Hard core thickness 150 mm
3.32 m3

Blinding slab
4.70
4.70 Concrete grade 7 blinding not
0.05 exceeding 100 mm thick
1.10 m3

Concrete slab
4.70
4.70 Concrete grade 20 for concrete slab n. e
0.10 100 mm thick
2.21 m3

Times Dimension Result Description Unit Quantity

Damp Proof Membrane (d. p. m)

4.70 Length 4.700


4.70 Width 4.700
2
22.09 m

6 | Page
FORMWORK
Times Dimension Result Description Unit Quantity

Footing
Length 0.600
4/4/
Formwork to edges & faces of
foundation exceeding 250 mm and 500
0.60 mm high
9.60 m

Footing
Length 0.600
4/4/
Formwork to edges & faces of
0.25 foundation exceeding 250 mm and 500
0.60 mm high
2
2.40 m

Stump
Length 0.300
4/4/ Height
0.30 1.550
1.55
2
7.44 Formwork to sides of isol column m
stump

7 | Page
Ground beam
Length 5.000

Less of stump column


4/2/ 2/0.150 0.300

Formwork to ground beam exceeding


4.70 250 mm and 600 high
37.60 m

Ground beam
Length 5.000

Less of stump column


4/2/ 2/0.150 0.300

0.50 Formwork to ground beam exceeding


4.70 250 mm and 600 high
18.80 m2

REINFORCEMENT
Times Dimension Result Description Unit Quantity
Footing
Length 0.600

Less
Concrete cover
2/0.040 0.080
0.520
Add
Bend
2/0.250 0.500
4/12/
Less
Concrete cover
4/0.040 0.160
0.860

20 mm diameter steel reinforcement in


0.860 straight & bend bars in foundation
41.28 m

8 | Page
Volume
r 2 h = 0.013 m3

Stump
Length
Stump + footing 1.500
Slab 0.300
Column
0.400
2.200
4/4/
Less
Concrete cover 0.040
Footing bars
2/0.020 0.040
2.120

Add
Bend 0.100
2.220

12 mm diameter steel reinforcement in


2.22 straight & bend bars in isol column
35.52 stump m

Volume
r 2 h = 0.004 m3

Times Dimension Result Description Unit Quantity

Link

Length 0.300

Less
Concrete cover
2/0/040 0.080
4/ 0.220
0.880

4/8/ Add hook


24/0.008 0.192
1.072

No of link
1.17 0.150 = 7.8

9 | Page
Approximate = 8 link

8 mm diameter steel reinforcement in


1.08 link in isol column stump
34.56 m
Volume
r 2 h = 0.002 m3

Ground beam

Length 5.000

Add
2 half column stump
2/0.150 0.300
4/4/
Less
Concrete cover
2/0.040 0.080
5.220
Add
Bend
2/0.200 0.400
5.620

16 mm diameter steel reinforcement in


5.62 straight & bend bars in ground beam
89.92 m
Volume
2 3
r h = 0.018 m

Times Dimension Result Description Unit Quantity

Stirrup ground beam

Width 0.250

Less
Concrete cover
2/0.040 0.080
0.170

Height
0.500

10 | P a g e
Less
Concrete cover
2/0.040 0.080
0.420
4/24/
2/ 0.590
1.180

Add hook
24/0.010 0.240
1.420

No of stirrup
4.70 0.200 = 23.5
Approximate = 24 stirrup

1.42 10 mm diameter steel reinforcement in


136.32 stirrup in ground beam m

Volume
r 2 h = 0.011 m3

ABSTRACT

Concrete grade 20P (1:3:6-38 mm gauge Concrete grade 15P (1:3:6-38 mm gauge
granite) as specified in foundation granite) as specified in foundation and
ground beam

0.36 (4) 0.07 (4)


0.56 (4) 0.24 (5)

11 | P a g e
2.35 (5) 0.31
3.27
2

2
=1 m
=4 m

Sawn formwork as specified to sides of Mild steel bars in reinforcement to concrete


foundation and ground beam work generally including all cutting,
bending and placing in position 10mm
diameter

2.40 (7) 0.002 (9)


7.44 (7) 0.011 (10)
18.80 (7) 0.013
28.64
=0.013
2
=29 m m3
=31.28kg
=32 kg

High tensile steel bars in reinforcement to concrete work generally including all cutting,
bending and placing in position 16 32 mm diameter

0.013 (8)
0.018 (9)
0.031

=0.031
3
m
=74.60kg
=75 kg

BILL OF QUANTITY
No Work explanation Unit Quantity Rate Amount

12 | P a g e
1 Excavate oversite average 150 mm deep to m2 32 3.60 115.20
level off formation or reduce level

2 Excavate to obtain formation level, load


and transport excavated material to m3 7 6.30 44.10
temporary spoil heap or filling area away
from site within 1 km lead

Excavate for foundation trenches, pier,


manholes, septic tanks, filter beds etc.
3
3 maximum depth not exceeding 0.25 m m 1 3.20 3.20
deep, backfill and remove surplus spoil
and deposit, spread and level on site as
specified.

Excavate for foundation trenches, pier,


manholes, septic tanks, filter beds etc.
4 maximum depth not exceeding 1.00 m m3 2 11.60 23.20
deep, backfill and remove surplus spoil
and deposit, spread and level on site as
specified.

Excavate for foundation trenches, pier,


manholes, septic tanks, filter beds etc.
5 maximum depth not exceeding 2.00 m m3 1 17.10 17.10
deep, backfill and remove surplus spoil
and deposit, spread and level on site as
specified.

Spread, level and compact excavated


3
6 earth/imported earth in layers as specified m 2 2.20 4.40
in filling areas

7 Concrete grade 15P (1:3:6-38 mm gauge m3 1 230.30 230.30


granite) as specified in foundation

3
Concrete grade 20P (1:3:6-38 mm gauge m 4 254.60 1018.40
8 granite) as specified in foundation

No Work explanation Unit Quantity Rate Amount

13 | P a g e
Concrete grade 20P (1:3:6-38 mm gauge
9 granite) as specified in ground floor slab, m3 3 262.50 787.50
aprons, kerbs, steps etc.

10 Hard core as specified m3 4 58.20 232.80

11 200 mm thick sand filling, spread and m2 23 9.60 220.80


levelled under concrete slab and floor

12 Sawn formwork as specified to sides of m2 29 35.10 1017.90


foundation and ground beam

Pabkote No. 3 or other approved


bituminous damp proof membrane applied
13 on concrete surfaces all to the approval of m2 23 15.00 345.00
the S.O and in accordance with the
manufacturers instruction.

Mild steel bars in reinforcement to


14 concrete work generally including all kg 32 3.60 115.20
cutting, bending and placing in position
10mm diameter

High tensile steel bars in reinforcement to


15 concrete work generally including all kg 10 3.70 37.00
cutting, bending and placing in position
12mm diameter

High tensile steel bars in reinforcement to


concrete work generally including all kg 75 3.40 255.00
16 cutting, bending and placing in position 16
32 mm diameter

All rate based on Schedule of Rate 2013