2B Providing and laying P.C.C. 1:4:8 of specified th. wherever specified using river sand, 40mm and down size metal including sub-grade preparation, leveling, Cft 2 4000 8000
all leads and lifts, rough finishing at the top surface, curing and shuttering if necessary etc.
2C Providing and laying P.C.C. 1:3:6 of specified thick wherever specified using river sand, 20mm and downsize metal including base Cft 5 4500 22500
preperation,Compaction,levelling, all leads and lifts, curing and shuttering if necessary etc., Complete
3A Columns
First Floor to Second Cft 200 185 37000
3B Beams
First Floor Cft 270 185 49950
3C Slabs
5 STEEL
Providing and fabricating reinforcement steel of high yield strength ribbed bars of various diameters and grade conforming to IS 1786 for reinforced
concrete work. The work includes cutting, bending, fabricating, and placing in position according to drawings. Cost to include supply and use of 18G black
annealed binding wire double fold to tie the bars in position and providing PVC cover blocks for main reinforcement to ensure specified cover.