O.T.

: -
SERVICIO DE INSTALACION DE COBERTURAS EN SISTEMA
DE ACEITE Y MOTOR DE GENERADOR ILO 41
PROYECTO
ACTUALIZADO POR Ing. Jorge Olguin Coyla
REALIZO Ing. Jorge Olguin Coyla
CLIENTE Southern Peru Copper Corporation
FECHA DE INICIO 30 de Enero de 2017

Colocacin de Arenado Desarrollo de Avance


REFERENCIA Habilitado Armado Enderezado SP3 Pintura QA/QC Avance
Malla SP10 Planos Peso
Planos N Descripcion Cant. Peso Unit Peso Total 17% 28% 23% 3% 5% 10% 10% 2% 2% Kg %
INSTALACION DE COBERTURAS EN ENFRIADOR DE
ACEITE ,(3 UNID)
No hay un plano definido Cubertura AZ200 0.96m x 3.94m 78 37.40 2917.08 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.00 0%
No hay un plano definido Cubertura AZ200 0.96m x 6.00m 6 56.95 341.71 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.00 0%
Peso Jgo 3258.79

INSTALACION DE COBERTURAS MOTOR GENERADOR


(3 UNID)
TMT_2017_701_002 R-01 3 15.35 46.08 100% 100% 100% 100% 100% 0% 0% 50% 90% 36.31 79%
TMT_2017_701_002 R-02 3 16.46 49.43 100% 100% 100% 100% 100% 0% 0% 50% 90% 38.95 79%
TMT_2017_701_002 R-03 3 16.73 50.18 100% 100% 100% 100% 100% 0% 0% 50% 90% 39.54 79%
TMT_2017_701_002 R-04 3 22.79 68.36 100% 100% 100% 100% 100% 0% 0% 50% 90% 53.87 79%
TMT_2017_701_002 R-05 3 22.79 68.36 100% 100% 100% 100% 100% 0% 0% 50% 90% 53.87 79%
TMT_2017_701_002 R-06 3 7.21 21.63 100% 100% 100% 100% 100% 0% 0% 50% 90% 17.04 79%
TMT_2017_701_002 A 2 29.53 59.06 100% 100% 100% 100% 100% 0% 0% 50% 90% 46.54 79%
TMT_2017_701_002 B 2 29.53 59.06 100% 100% 100% 100% 100% 0% 0% 50% 90% 46.54 79%
TMT_2017_701_002 C 2 29.53 59.06 100% 100% 100% 100% 100% 0% 0% 50% 90% 46.54 79%
TMT_2017_701_002 V-01 3 50.87 152.62 100% 100% 100% 100% 100% 0% 0% 50% 90% 120.26 79%
TMT_2017_701_002 V-02 3 50.90 152.71 100% 100% 100% 100% 100% 0% 0% 50% 50% 119.11 78%
TMT_2017_701_002 TB-01 3 58.38 175.13 100% 100% 100% 100% 100% 0% 0% 50% 90% 138.00 79%
TMT_2017_701_002 TB-02 3 67.89 203.68 100% 100% 100% 100% 100% 0% 0% 50% 90% 160.50 79%
TMT_2017_701_002 TB-03 3 45.77 137.32 100% 100% 100% 100% 100% 0% 0% 50% 90% 108.21 79%
TMT_2017_701_002 R-07 30 14.18 425.37 100% 100% 100% 100% 100% 0% 0% 50% 90% 335.19 79%
TMT_2017_701_002 GT-01 3 53.57 160.71 100% 100% 100% 100% 100% 0% 0% 50% 90% 126.64 79%
TMT_2017_802_002 C-01 3 62.85 188.55 100% 100% 100% 100% 100% 100% 40% 50% 90% 174.97 93%
TMT_2017_802_002 C-02 3 55.87 167.62 100% 100% 100% 100% 100% 100% 40% 50% 90% 155.55 93%
TMT_2017_802_002 C-03 3 62.85 188.55 100% 100% 100% 100% 100% 100% 40% 50% 90% 174.97 93%
TMT_2017_802_002 C-04 3 55.87 167.62 100% 100% 100% 100% 100% 100% 40% 50% 90% 155.55 93%
TMT_2017_802_002 PL-01 12 8.25 98.96 100% 100% 100% 100% 100% 100% 40% 50% 90% 91.83 93%
TMT_2017_802_002 CN-01 24 22.58 541.92 100% 100% 100% 100% 100% 100% 40% 50% 90% 502.90 93%
TMT_2017_802_002 CN-02 9 27.06 243.57 100% 100% 100% 100% 100% 100% 40% 50% 90% 226.03 93%
TMT_2017_802_002 CH-05 6 48.38 290.25 100% 100% 100% 100% 100% 100% 40% 50% 90% 269.35 93%
TMT_2017_802_002 CH-06 6 28.80 172.81 100% 100% 100% 100% 100% 100% 40% 50% 90% 160.37 93%
TMT_2017_802_002 ANG-01 6 21.15 126.88 100% 100% 100% 100% 100% 100% 40% 50% 90% 117.74 93%
No hay un plano definido Cubertura AZ200 0.96m x 3.375m 12 32.04 384.43 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.00 0%
No hay un plano definido Cubertura AZ200 0.96m x 6.00m 6 56.95 341.71 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.00 0%
Peso Jgo 4801.63

DISEO, Y FABRICACION Y MONTAJE DE


COBERTURA EN MOTOR DE ACEITE DE CONTROL(3
UNID)
No hay un plano definido Cubertura AZ200 0.96m x 3.80m 36 36.07 1298.51 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.00 0%
No hay un plano definido Cubertura AZ200 0.96m x 3.40m 12 32.27 387.27 0% 0% 0% 0% 0% 0% 0% 0% 0% 0.00 0%
Peso Jgo 1685.78

TOTAL 297 1176.82 9746.20 TOTAL 3516.41 24.67%