You are on page 1of 4

2016 IEEE Electrical Power and Energy Conference (EPEC)

Effect of Wind Turbine Parameters on Optimal DG


Placement in Power Distribution Systems
Majed Alotaibi, Student Member IEEE, Abdulaziz Almutairi, Student Member IEEE; M. M. A. Salama, Fellow IEEE
Department of Electrical and Computer Engineering
University of Waterloo
Waterloo, Ontario, Canada, N2L 3G1
m2alotai@uwaterloo.ca; a4almuta@uwaterloo.ca; msalama@uwaterloo.ca

Abstract The notion of the smart grid has led


stakeholders in the power industry to promote more efficient Integration of DGs in distribution systems and
technologies to the network. Distribution systems are a favorite determining proper sites and sizes has attracted a large and
place to host most of these technologies including Renewable- growing body of literature. This is, however, a challenging
based distributed generation (DG). Wind Turbine Generators optimization problem due to the involvement of different
(WTGs) in particular have proved their usefulness for objectives and sets of economic, operational, and technical
supplying a fair portion of power demand; however, the power constraints. Accordingly, a variety of models and methods
output of WTGs is mainly dependent on the stochastic nature
have recently been showcased in numerous publications [3].
of the sites wind speed in addition to the design parameters of
WTGs. Furthermore, WTGs can only be suitably utilized when
For example, the study presented in [4] focused on
their capacities and locations are optimized in such a way to determining the optimal DG locations in order to minimize
achieve certain goals. In this paper, the effect of wind power losses by using the Tabu search technique.
generator design parameters, namely cut-in, cut-out, and rated Considering multiple DGs and load levels, the multi-
wind speeds, on the problems of sizing and siting WTGs-based objective function has been mathematically modeled and
DGs is addressed. The probabilistic optimization model is used solved in [5] using mixed integer non-linear programming,
to minimize the systems annual energy losses, and the results and the cost of losses was presented among the cost
reveal that the design parameters of WTGs must be carefully functions. The work reported in [6] involved the
selected due to their strong effect on system losses and DG development of a deterministic optimization technique to
locations and capacities. identify optimum locations and sizes of DGs so that total
planning cost is minimized. It is worth mentioning that most
Keywords DG placement, energy losses, wind turbine of the optimization models have considered some practical
parameters constraints, and these constraints vary from one application
to another; they include the thermal limit of the feeders, the
voltage at each bus, the maximum reverse power, short
I. INTRODUCTION circuit level, and other elements.
Power systems have undergone major changes over the In spite of the many advantages of renewable DGs (e.g.,
recent decades in the quest to provide reliable and economic Wind Turbine Generators (WTGs), their implementation
electricity services in a way that benefits all associated into a distribution system introduces various challenges and
parties. Achieving this goal involves the consideration of makes the optimization problem further complex. This is
power industry regulations, environmental policies, mainly due to the fact that the power output of a WTG is
advancements in technology, and utilization of sustainable variable, uncertain, and non-controllable, and wind power
energies. Distributed generation (DG) is expected to be a output is extremely dependent on the characteristics of the
part of the solutions considered for the future. DG systems wind speed at a particular site. Besides this, the nonlinear
are expected to provide numerous technical, economic, and relationship between the power output of a WTG and the
environmental benefits when they are properly located and wind speed at a site is represented by the characteristics of
sized in the distribution systems [1]. From the technical the WTG when influenced by the cut-in, rated, and cut-out
point of view, DGs can help in system reliability and quality speed. Some of the earlier studies used deterministic models
improvement, power loss reduction, and voltage stability (e.g., a fixed wind profile or a capacity factor) to represent
enhancement. The economic benefits that can be gained the power output of WTGs and hence determine their
from DGs appear in, for example, deferring the required optimal locations and sizes [7, 8]. The major drawback of
investments for system expansions and reducing cost deterministic techniques is that they fail to take into account
expenditures for the fixed spinning reserve. Utilizing the stochastic nature of wind behavior, as wind speed is
renewable DGs is increasing worldwide, aimed at reducing highly variable. Alternatively, there is
carbon dioxide emissions CO2 and maintaining a safe and a growing consensus in the literature for solving the location
healthy environment [2].
The first and second authors wish to acknowledge funding support
received from the Saudi Arabian Ministry of Education to carry out this
work.

978-1-5090-1919-9/16/$31.00 2016 IEEE


2016 IEEE Electrical Power and Energy Conference (EPEC)

and size problems of wind-based DGs by using multi-state B. Optimal number of WTGs and locations formulation
probabilistic models [9]. The objective function of the probabilistic optimal power
To the best of our knowledge, few or no studies have flow model is to determine and allocate the number of
offered a critical evaluation of the effect of wind design WTGs that minimize AEL and maintain system security
parameters on wind-based DG allocation and sizing in constraints.
distribution systems. Therefore, this paper conducts several
case studies to illustrate the effect of different WTG design
parameters on the optimization of DG allocation and sizing.
A probabilistic optimization model to allocate and size , 8760 (3)
wind-based DGs while minimizing the total annual energy
losses (AEL) is used in this paper. The remainder of this
paper is structured as follows. Section II presents the where is the current flow in feeder ij, is the resistivity
probabilistic wind model along with the formulation of the of feeder ij, is the probability of occurrence of wind state
optimization model. Section III describes the case studies, s, NF is total number of feeders, and T is the total number of
and Section IV presents and compares the analyses and states.
results of the considered cases. Lastly, Section V concludes
the paper. Nodal active and reactive power constraints at each bus
II. METHODOLOGY in the system must be satisfied.

A. Probabilistic modeling of WTG output power


The probability distribution function (PDF) for the random , + , , , = , , cos + , , (4)
variable, which is wind speed in this case, will be generated
from the recorded historical data. Three successive years of
wind speed data for the site under investigation are collected
and analyzed so as to define the wind speed patterns. These , , = , , sin + , + , (5)
data are fitted to the most commonly used probabilistic
distribution function for wind speeds, the Weibull
distribution. The Weibull power density function is then where , is the rated wind power at bus i, , is the state
divided into multiple equal bands (states), where the wind output power, , is the annual average power
probability of each band is defined as follows: demand at bus i, is the magnitude of admittance matrix
element ( ), , is the state voltage magnitude of bus i,
( )= ( ). ( ) is the angle of admittance matrix element ( ), and , is
the state voltage angle of bus j.

Where are the starting and ending wind speed for All the current flowing in the feeders must be within the
such band, respectively. thermal capability of the feeder, and all the bus voltages
must be kept within standard limits. These are formulated as
After the probability of each state is calculated, per-unit follows:
wind output power for each state or band can be computed
as follows [9]: , (6)

0 0 , , (7)

( )= (2)

, = , + , 2 , , cos , , (8)

where , , are cut-in speed, rated speed, and cut-off One more constraint is added to represent the
speed of the WTG, respectively, ( ) is the output power discretization in rated WTG power. This constrains is shown
during state x, and is the average speed of state x. in (9):

It is worthwhile to note that wind speeds that have values , = (9)


lower than the cut-in speed of WTG and higher than cut-out
speed are treated as one single state, with a value equalling where M is an integer number and is the turbines rated
zero. Moreover, wind speeds that have values higher than the power.
WTG rated speed and lower than the cut-out speed are
treated as one state, with a value equal to the rated power.
2016 IEEE Electrical Power and Energy Conference (EPEC)

III. CASE STUDIES


The system used in this study is the well-known 33-bus For all of the case studies presented in this paper, a
radial distribution system presented in [10]. The WTG with a capacity of 225kW was used [12]. Based on
configuration of the system is shown in Fig. 1. This system consideration of the ultimate objectives of this research,
consists of a sub-station with the capacity of 8MW which is seven case studies have been carried out, as shown in Table
connected at Bus 1, and a typical average system load I.
estimated to be 2.6MW. In this study, all connected loads
Table I SCENARIOS UNDER STUDY
are assumed to be residential. The hourly wind speed data WTG design parameters
for three successive years for the Waterloo site located in (kilometers/hour) The purpose of the study
the province of Ontario, Canada, were used [11]. The wind Cut-in Rated Cut-out
speed mean and standard deviation at this site are 14.7 and Benchmark to compare with
Base case 12 38 80
subsequent cases
9.12 km/hour respectively, and its fitted Weibull distribution Case 1 8 38 80
function is shown in Fig. 2. To study the effect of cut-in speed
Case 2 16 38 80
Case 3 12 34 80
To study the effect of rated speed
Case 4 12 42 80
Case 5 12 38 76
To study the effect of cut-out speed
Case 6 12 38 84

IV. RESULTS AND ANALYSIS


Fig. 3 shows the AEL for the different cases under study. It
can be observed that the AEL changes significantly with the
change of cut-in wind speed (i.e. Case 1 and 2). The AEL
decreases 18.5% compared to the base case, as the cut-in
speed is reduced by 4km/h. In contrast, when the cut-in
speed is increased by 4km/h, the AEL increases by 13%.
Comparing Case 1 with Case 2, the AEL at the cut-in speed
of 8km/h is 1.4 times than at the cut-in speed of 16km/h.

425
401.3
400
Total Annual Energy Losses (MWh)

375 355 359 355 355


352.7
350

325

300 289.5

275

250

225

200
Base case case 1 case 2 case 3 case 4 case 5 case 6
Figure 1 IEEE 33 Bus System
Figure 3 The annual energy losses for different case studies

It can be seen from the results obtained for Cases 3 and 4


0.05
0.045
that the change in AEL is very small with respect to change
0.04
in rated wind speed, and that the rated wind speed has a
0.035
much smaller effect on AEL than the cut-in wind speed.
Probability f(x)

0.03
AEL decreases by 1.7% as the rated speed increases from 34
0.025
km/h to 42 km/h. These results indicate that cut-in speed
0.02 affects AEL more strongly than the rated wind speed. The
0.015 justification for these results is that most wind speed data at
0.01 this site concentrate near the cut-in speed, but they are quite
0.005 far from the rated wind speed (see Fig. 2).
0
0 10 20 30 40 50 60 70 80
The results obtained from Cases 5 and 6 reveal that the
Wind speed (km/h) cut-out speed parameter has almost no effect of AEL. The
Figure 2 Probability distribution function of the historical wind speed data cut-out speed parameter is usually designed to be quite
2016 IEEE Electrical Power and Energy Conference (EPEC)

large, and the probability of the wind speed at any particular V. CONCLUSION
site being higher than the cut-out speed is usually very low. The studies described in this paper were conducted to
illustrate the effects of WTG design parameters on the
The number and allocations of WTGs are determined problem of DG placement for loss reduction. Overall, the
based on the optimal value that can be achieved for the results show that the cut-in speed parameter is clearly a
objective function while satisfying the identified constraints. major factor that affects AEL and the number and allocation
Table III lists details about the number of WTGs and their of WTGs, followed by the rated wind speed, which has a
candidate locations. It is worth mentioning that only the less significant effect. The cut-out speed parameter has
buses selected by the optimization model as the best places almost no effect on either the annual AEL or the number or
to install WTGs are displayed in Table II. allocation of WTGs. The reason for these findings is that the
cut-out speed parameter is usually designed to be quite
From the results of Case 2, when the cut-in speed is large, and the probability of the wind speed exceeding this
reduced from 12 to 8 km/h, it can be seen that the number parameter is very small. Together, these results provide
and locations of WTGs remain unchanged from the base important insights into the need for careful selection of the
case, although the annual energy loss is significantly design parameters of WTGs (namely, cut-in and rated speed
decreased. In contrast to the previous case, the number and parameters) in order to determine the proper installation of
locations of WTGs change considerably as the cut-in is WTGs in a distribution system. Also, the same analysis
increased from 12 to 16 km/h. This is mainly due to the holds true for any other objective functions, such as
nature of the optimization problem, as well as to the strong minimization of total system cost and maximizing system
relationship between the cut-in speed parameter of the WTG reliability, and these are areas that should be considered for
and the wind speed data. Likewise, the results obtained from future investigation.
Cases 3 and 4 change accordingly with the change in rated
speed. However, the number and locations of WTGs are not REFERENCES
affected by cut-out speed variations, as seen from the results [1] El-Khattam, Walid, and M. M. A. Salama. "Distributed generation
of Cases 5 and 6. technologies, definitions and benefits." Electric power systems
research71.2 (2004): 119-128.
[2] R. Viral and D. Khatod, Optimal planning of distributed generation
systems in distribution system: A review, Renewable and
Table II. OPTIMAL WTG INSTALLATION SCHEME FOR DIFFERENT
Sustainable Energy Reviews, vol. 16, no. 7, pp. 51465165, 2012.
CASE STUDIES
[3] Georgilakis, Pavlos S., and Nikos D. Hatziargyriou. "Optimal
Cut-in Rated Cut-out distributed generation placement in power distribution networks:
models, methods, and future research." Power systems, IEEE
Buses Base case case 1 case 2 case 3 case 4 case 5 case 6 transactions on 28.3 (2013): 3420-3428.
[4] K. Nara, Y. Hayashi, K. Ikeda, and T. Ashizawa, Application of tabu
2 0 0 1 1 0 0 0 search to optimal placement of distributed generators, in Power
3 1 1 0 0 0 1 1 Engineering Society Winter Meeting, 2001. IEEE, vol. 2. IEEE, 2001,
pp. 918923.
7 1 1 1 0 0 1 1 [5] W. El-Khattam, K. Bhattacharya, Y. Hegazy, and M. Salama, Optimal
investment planning for distributed generation in a competitive
8 0 0 0 2 2 0 0
electricity market, Power Systems, IEEE Transactions on, vol. 19,
9 1 1 1 0 0 1 1 no. 3, pp. 16741684, 2004.
[6] W. El-Khattam, Y. Hegazy, and M. Salama, "An integrated distributed
13 0 0 1 1 0 0 0 generation optimization model for distribution system planning," in
14 1 1 0 0 1 1 1 Power Engineering Society General Meeting, 2005. IEEE, 2005, p.
2392 Vol. 3.
15 0 0 0 1 1 0 0 [7] Nursebo, Shemsedin, et al. "Optimizing wind power hosting capacity of
distribution systems using cost benefit analysis." Power Delivery,
16 1 1 1 0 0 1 1 IEEE Transactions on 29.3 (2014): 1436-1445.
21 0 0 1 1 1 0 0 [8] Dent, Chris J., et al. "Efficient secure AC OPF for network generation
capacity assessment." Power Systems, IEEE Transactions on 25.1
24 2 2 1 2 1 2 2 (2010): 575-583.
[9] Atwa, Y. M., et al. "Optimal renewable resources mix for distribution
25 1 1 2 1 2 1 1
system energy loss minimization." Power Systems, IEEE
27 0 0 1 0 0 0 0 Transactions on 25.1 (2010): 360-370.
[10] Baran, Mesut E., and Felix F. Wu. "Network reconfiguration in
28 1 1 0 0 0 1 1 distribution systems for loss reduction and load balancing." Power
29 0 0 0 0 1 0 0 Delivery, IEEE Transactions on 4.2 (1989): 1401-1407.
[11] Environment Canada, Historical wind speed data for Waterloo, ON
30 0 0 1 2 0 0 0 site, Available <http://climate.weather.gc.ca>.
[12] Billinton, R., and Hua Chen. "Effect of wind turbine parameters on the
31 1 1 0 0 2 1 1 capacity adequacy of generating systems using wind
32 2 2 2 2 1 2 2 energy." WESCANEX 97: Communications, Power and Computing.
Conference Proceedings., IEEE. IEEE, 1997.

You might also like