SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

QC Personnel employed by Contractor and its


Contractor and Subcontractor Quality
Schedule "Q" Schedule "Q" Subcontractors to perform the work described in this
1.1 Personnel Quality Qualification
Att. I Att. I R R Contract shall meet the minium requirement of this
Requirement.
Attachment.

Contractors shall comply with all applicable Compay


Company Standards and Procedures Schedule "Q" Schedule "Q" Material System Specfication ( SMASS) Engineering
1.2
Containing Quality Requirement. Att. II Att. II R R Standards (SAES) and procedures relationg to Quality
requirement.

RECEIVING
2.0
INSPECTION

UPS Equipment &


Weekly inspection by Contractor QC
Electrochemical Storage Battery
2.1 Storage, Handling, and Preservation SAIC-T-5001 SAIC-T-5001 W S Storage testing in accordance with manufacturer's
Visual Inspection and Testing for
instructions.
Electronic Equipment

UPS Equipment &


Weekly inspection by Contractor QC
Electrochemical Storage Battery
2.2 Storage, Handling, and Preservation SAIC-P-3002 SAIC-P-3002 W S Storage testing in accordance with manufacturer's
Visual Inspection and Testing for
instructions.
Electrical Equipment

UPS Equipment &


Weekly inspection by Contractor QC
Electrochemical Storage Battery
2.3 Storage, Handling, and Preservation SAIC-P-3101 SAIC-P-3101 W S Storage testing in accordance with manufacturer's
Visual Inspection and Testing for Vented
instructions.
Ni-Cad Wet Cell

UPS Equipment &


Weekly inspection by Contractor QC
Electrochemical Storage Battery
2.4 Storage, Handling, and Preservation SAIC-P-3102 SAIC-P-3102 W S Storage testing in accordance with manufacturer's
Visual Inspection and Testing for Vented
instructions.
Lead-Acid Wet Cell

Page 1 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment &


Weekly inspection by Contractor QC
Electrochemical Storage Battery
2.5 Storage, Handling, and Preservation SAIC-P-3103 SAIC-P-3103 W S Storage testing in accordance with manufacturer's
Visual Inspection and Testing for VRLA
instructions.
Gelatin Cell

UPS Equipment &


Weekly inspection by Contractor QC
Electrochemical Storage Battery
2.6 Storage, Handling, and Preservation SAIC-P-3104 SAIC-P-3104 W S Storage testing in accordance with manufacturer's
Visual Inspection and Testing for
instructions.
Aqueous Sulf. Acid Electrolyte

Page 2 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment &


Electrochemical Storage Battery Weekly inspection by Contractor QC
Storage, Handling, and Preservation
2.7
Visual Inspection and Testing for Dry
SAIC-P-3105 SAIC-P-3105 W S Storage testing in accordance with manufacturer's
Potassium or Sodium Hydroxide instructions.
Electrolyte

UPS Equipment &


Weekly inspection by Contractor QC
Electrochemical Storage Battery
2.8 Storage, Handling, and Preservation SATR-P-3101 SATR-P-3101 W S Storage testing in accordance with manufacturer's
Visual Inspection and Testing for
instructions.
Electrochemical Battery

Notify SA PID on receipt of shipment of each equipment


UPS Equipment &
type.
Electrochemical Storage Battery
2.9
Material Receiving
SAIC-P-3106 SAIC-P-3106 H W
QC personnel to inspect 100% of the equipment and
Visual Inspection for UPS DC/AC Inverter
accessories.

Notify SA PID on receipt of shipment of each equipment


UPS Equipment &
type.
Electrochemical Storage Battery
2.10
Material Receiving
SAIC-P-3107 SAIC-P-3107 H W
QC personnel to inspect 100% of the equipment and
Visual Inspection for UPS Static Switch
accessories.

UPS Equipment & Notify SA PID on receipt of shipment of each equipment


Electrochemical Storage Battery type.
2.11 Material Receiving SAIC-P-3108 SAIC-P-3108 H W
Visual Inspection for UPS Transfer QC personnel to inspect 100% of the equipment and
Switch accessories.

Page 3 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment & Notify SA PID on receipt of shipment of each equipment


Electrochemical Storage Battery type.
2.12 Material Receiving SAIC-P-3109 SAIC-P-3109 H W
Visual Inspection for UPS Bypass Line QC personnel to inspect 100% of the equipment and
Transformer accessories.

UPS Equipment & Notify SA PID on receipt of shipment of each equipment


Electrochemical Storage Battery type.
2.13 Material Receiving SAIC-P-3110 SAIC-P-3110 H W
Visual Inspection for UPS Maintenance QC personnel to inspect 100% of the equipment and
Bypass Switch accessories.

Page 4 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment & Notify SA PID on receipt of shipment of each equipment


Electrochemical Storage Battery type.
2.14 Material Receiving SAIC-P-3111 SAIC-P-3111 H W
Visual Inspection for UPS Panelboards / QC personnel to inspect 100% of the equipment and
CB's accessories.

UPS Equipment & Notify SA PID on receipt of shipment of each equipment


Electrochemical Storage Battery type.
2.15 Material Receiving SAIC-P-3112 SAIC-P-3112 H W
Visual Inspection for UPS/DC Battery QC personnel to inspect 100% of the equipment and
Rectifier / Charger accessories.

UPS Equipment &


Notify SA PID on receipt of shipment of storage cells and
Electrochemical Storage Battery
accessories.
2.16 Material Receiving SAIC-P-3113 SAIC-P-3113 H W
Visual Inspection for UPS/DC Vented Ni-
QC personnel to inspect 100% of the shipment.
Cad Wet Cell

UPS Equipment &


Notify SA PID on receipt of shipment of storage cells and
Electrochemical Storage Battery
accessories.
2.17 Material Receiving SAIC-P-3114 SAIC-P-3114 H W
Visual Inspection for UPS/DC Vented
QC personnel to inspect 100% of the shipment.
Lead-Acid Wet Cell

UPS Equipment &


Notify SA PID on receipt of shipment of storage cells and
Electrochemical Storage Battery
accessories.
2.18 Material Receiving SAIC-P-3115 SAIC-P-3115 H W
Visual Inspection for UPS/DC VRLA
QC personnel to inspect 100% of the shipment.
Gelatin Cell

UPS Equipment &


Electrochemical Storage Battery Notify SA PID on receipt of shipment.
2.19 Material Receiving SAIC-P-3116 SAIC-P-3116 H W
Visual Inspection for Aqueous Sulfuric QC personnel to inspect 100% of the shipment.
Acid Electrolyte

Page 5 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment &


Electrochemical Storage Battery Notify SA PID on receipt of shipment.
2.20 Material Receiving SAIC-P-3117 SAIC-P-3117 H W
Visual Inspection for Dry Potassium or QC personnel to inspect 100% of the shipment.
Sodium Hydroxide

Page 6 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment &


See GENERAL NOTES for typical accessories.
Electrochemical Storage Battery
2.21 Material Receiving SAIC-P-3118 SAIC-P-3118 H W Notify SA PID on receipt of initial shipment of each
Visual Inspection for UPS System and
accessory type.
Battery Accessories

Electrochemical Storage Cell


Jobsite Acceptance Testing
Hold point prior to installation of D.C. electrochemical
2.22 (Initial load capacity, no-load SATR-P-3102 SATR-P-3102 H W storage cells.
voltage, and specific gravity) for Vented
Ni-Cad Wet Cell

Electrochemical Storage Cell


Jobsite Acceptance Testing
Hold point prior to installation of D.C. electrochemical
2.23 (Initial load capacity, no-load SATR-P-3103 SATR-P-3103 H W storage cells.
voltage, and specific gravity) for Vented
Lead-Acid Wet Cell

Electrochemical Storage Cell


Jobsite Acceptance Testing
(Initial load capacity, no-load Hold point prior to installation of D.C. electrochemical
2.24
voltage, and specific gravity) for Valve-
SATR-P-3104 SATR-P-3104 H W storage cells.
Regulated Lead-Acid (VRLA)
Gelatin Cell

3.0 INSTALLATION

UPS Equipment / Battery Room Hold point for substantial completion of building and
3.1 Pre-Installation SAIC-P-3119 SAIC-P-3119 H H electrical room civil / structural / architectural / HVAC
Visual Inspection for Battery Room finish work (i.e., no construction dust or fumes).

UPS Equipment / Battery Room


Hold point for substantial completion of building and
Pre-Installation
3.2
Visual Inspection for Substation / Swgr
SAIC-P-3003 SAIC-P-3003 H H electrical room civil / structural / architectural / HVAC
finish work (i.e., no construction dust or fumes).
Room

UPS Equipment / Battery Rack Also see SATIP-P-111-01 Grounding & Bonding
3.3 Installation & Identification SAIC-P-3120 SAIC-P-3120 H W SA PID shall be notified on start of this activity for each
Visual Inspection UPS.

Page 7 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment & See SATIP-P-104-05 A/G Industrial Conduit


Electrochemical Storage Battery SATIP-P-104-03 Cable Tray
3.4 Conduit / Cable Tray See Remarks See Remarks SATIP-P-104-07 B/G Conduit
Installation & Identification SATIP-P-111-01 Grounding & Bonding
Visual Inspection QC hold point prior to installation of battery jars.

Page 8 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS Equipment &


Electrochemical Storage Battery SA PID to be notified on start of this activity for each UPS
3.5
Cable Pulling
SAIC-P-3207 SAIC-P-3207 H W system.
Visual Inspection

Electrochemical Storage Battery


SA PID shall be notified on start of this activity for each
3.6 Installation and Identification SAIC-P-3121 SAIC-P-3121 H W Battery.
Visual Inspection

UPS Equipment &


See SATIP-P-111-01 Grounding & Bonding
Electrochemical Storage Battery
3.7 Cable Gland Installation, SAIC-P-3207 SAIC-P-3207 H W SA PID to be notified on start of this activity for each UPS
Cable Dressing, Identification, &
system.
Termination Visual Inspection

4.0 PRE-COMMISSIONING

Cable Continuity
SA PID to be notified on start of this activity for each UPS
4.1 and Insulation Testing SATR-P-3203 SATR-P-3203 H W system.
(Installed Cable)

Power Cable Termination SA PID to be notified on start of this activity for each UPS
4.2
Torque Testing
SATR-P-3205 SATR-P-3205 H W system.

Electrochemical Storage Battery Testing


(inter-cell connector resistance, cell no- In accordance with battery manufacturer's instructions.
4.3 load voltage, battery no-load voltage, and SATR-P-3113 SATR-P-3113 H W
cell specific gravity) for UPS/DC Vented Hold point prior to UPS energization.
Ni-Cad Wet Cell

Electrochemical Storage Battery


Testing (inter-cell connector
In accordance with battery manufacturer's instructions.
resistance, cell no-load voltage,
4.4
battery no-load voltage, and cell specific
SATR-P-3114 SATR-P-3114 H W
Hold point prior to UPS energization.
gravity) for UPS/DC
Vented Lead-Acid Wet Cell

Page 9 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Electrochemical Storage Battery


Testing (inter-cell connector
In accordance with battery manufacturer's instructions.
resistance, cell no-load voltage,
4.5
battery no-load voltage, and cell specific
SATR-P-3115 SATR-P-3115 H W
Hold point prior to UPS energization.
gravity) for UPS/DC Valve-Regulated
Lead-Acid Gelatin Cell

Page 10 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

UPS System Pre-energization


In accordance with UPS manufacturer's instructions.
Visual Inspection and Testing
4.6
(for Energization Certificate) for UPS
SATR-P-3105 SATR-P-3105 H H
Hold point prior to UPS energization.
DC/AC Inverter

UPS System Pre-energization


In accordance with UPS manufacturer's instructions.
Visual Inspection and Testing
4.7
(for Energization Certificate) for UPS
SATR-P-3106 SATR-P-3106 H H
Hold point prior to UPS energization.
Static Switch

UPS System Pre-energization


In accordance with UPS manufacturer's instructions.
Visual Inspection and Testing
4.8
(for Energization Certificate) for UPS
SATR-P-3107 SATR-P-3107 H H
Hold point prior to UPS energization.
Transfer Switch

UPS System Pre-energization


In accordance with UPS manufacturer's instructions.
Visual Inspection and Testing
4.9
(for Energization Certificate) for UPS
SATR-P-3108 SATR-P-3108 H H
Hold point prior to UPS energization.
Bypass Line Transformer

UPS System Pre-energization SATR-P-3111 UPS/DC Battery Rectifier / Charger


Visual Inspection and Testing In accordance with UPS manufacturer's instructions.
4.10
(for Energization Certificate) for UPS
SATR-P-3109 SATR-P-3109 H H
Maintenance Bypass Switch Hold point prior to UPS energization.

UPS System Pre-energization


In accordance with UPS manufacturer's instructions.
Visual Inspection and Testing
4.11
(for Energization Certificate) for UPS
SATR-P-3110 SATR-P-3110 H H
Hold point prior to UPS energization.
Panelboards / CB's

UPS System Pre-energization


In accordance with UPS manufacturer's instructions.
Visual Inspection and Testing
4.12
(for Energization Certificate) for UPS/DC
SATR-P-3111 SATR-P-3111 H H
Hold point prior to UPS energization.
Battery Rectifier / Charger

UPS System Pre-energization Review EIL and all associated Quality Records.
Energization
4.13 Quality Document Review EIL
Certificate RH RH
and Energization Certificate Hold point prior to UPS energization.

Page 11 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Energized UPS System


In accordance with UPS manufacturer's instructions.
Visual Inspection and
4.14
Functional Testing for UPS DC/AC
SATR-P-3105 SATR-P-3105 H H
Hold point prior to UPS fault testing.
Inverter

Page 12 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Energized UPS System In accordance with UPS manufacturer's instructions.


4.15 Visual Inspection and SATR-P-3106 SATR-P-3106 H H
Functional Testing for UPS Static Switch Hold point prior to UPS fault testing.

Energized UPS System


In accordance with UPS manufacturer's instructions.
Visual Inspection and
4.16
Functional Testing for UPS Transfer
SATR-P-3107 SATR-P-3107 H H
Hold point prior to UPS fault testing.
Switch

Energized UPS System


In accordance with UPS manufacturer's instructions.
Visual Inspection and
4.17
Functional Testing for UPS Bypass Line
SATR-P-3108 SATR-P-3108 H H
Hold point prior to UPS fault testing.
Transformer

Energized UPS System


In accordance with UPS manufacturer's instructions.
Visual Inspection and
4.18
Functional Testing for UPS Maintenance
SATR-P-3109 SATR-P-3109 H H
Hold point prior to UPS fault testing.
Bypass Switch

Energized UPS System


In accordance with UPS manufacturer's instructions.
Visual Inspection and
4.19
Functional Testing for UPS Panelboards /
SATR-P-3110 SATR-P-3110 H H
Hold point prior to UPS fault testing.
CB's

Energized UPS System


In accordance with UPS manufacturer's instructions.
Visual Inspection and
4.20
Functional Testing for UPS/DC Battery
SATR-P-3111 SATR-P-3111 H H
Hold point prior to UPS fault testing.
Rectifier / Charger

See SATIP-J-900-01 (Instrument Loop Checking) for


Energized UPS System See
4.21
Remote Indication and Alarm Testing
See Remarks
Remarks H H additional inspection and test requirements for signal and
control loops.

Energized UPS System


4.22
Bolted-Fault Test
SATR-P-3112 SATR-P-3112 H H In accordance with UPS manufacturer's instructions.

Energized UPS System In accordance with UPS manufacturer's instructions.


4.23
Final Inspection
See Remarks EIL H H Hold point prior to UPS system certification.

Page 13 of 3005/13/2017 19:47:08


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

Energized UPS System


PMCC
4.24 Quality Document Review FEIL
MCC RH RH Review FEIL and all associated Quality Records
and Mechanical Completion Certificate

Page 14 of 3005/13/2017 19:47:09


SAUDI ARAMCO ID/PID - 18-MAY-05 - REV 0 (Standards Cutoff - Mar 2012) Rev 6 31-Mar-12

SAUDI ARAMCO TYPICAL INSPECTION PLAN SATIP No. APPROVED DATE DISCIPLINE:

AC Uninterruptible Power Supply (UPS) Systems SATIP-P-103-01 30-Apr-13 Electrical


PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM QUALITY QUALITY ASSIGNMENTS
PROJECT PHASE TASK / ACTIVITY REMARKS
NO. PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the
1
levels of Saudi Aramco participation based upon the Contractors performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
3
organization representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization
4
representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

Accessories include battery racks, battery enclosures, copper battery cable and bus bar, cable crimp terminals, battery inter-cell and inter-row connectors, stainless steel mechanical fasteners, safety
6
covers for live parts, NO-OX terminal grease, portable battery hoist, air filters, distilled water dispensers, thermometers, hydrometers, and distilled water.

LEGEND
W 100% Witness Inspection/Test R 100% Review of Documents S Surveillance
H 100% Hold Point for QC Inspection or Test RH 100% Review and Approval of Documents

Page 15 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

QC Personnel employed by Contractor and its


Subcontractors to perform the work described in this
Contract shall meet the minium requirement of this
Attachment.

Contractors shall comply with all applicable Compay


Material System Specfication ( SMASS) Engineering
Standards (SAES) and procedures relationg to Quality
requirement.

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Page 16 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Page 17 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Weekly inspection by Contractor QC

Storage testing in accordance with manufacturer's


instructions.

Notify SA PID on receipt of shipment of each equipment


type.

QC personnel to inspect 100% of the equipment and


accessories.

Notify SA PID on receipt of shipment of each equipment


type.

QC personnel to inspect 100% of the equipment and


accessories.

Notify SA PID on receipt of shipment of each equipment


type.

QC personnel to inspect 100% of the equipment and


accessories.

Page 18 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

Notify SA PID on receipt of shipment of each equipment


type.

QC personnel to inspect 100% of the equipment and


accessories.

Notify SA PID on receipt of shipment of each equipment


type.

QC personnel to inspect 100% of the equipment and


accessories.

Page 19 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

Notify SA PID on receipt of shipment of each equipment


type.

QC personnel to inspect 100% of the equipment and


accessories.

Notify SA PID on receipt of shipment of each equipment


type.

QC personnel to inspect 100% of the equipment and


accessories.

Notify SA PID on receipt of shipment of storage cells and


accessories.

QC personnel to inspect 100% of the shipment.

Notify SA PID on receipt of shipment of storage cells and


accessories.

QC personnel to inspect 100% of the shipment.

Notify SA PID on receipt of shipment of storage cells and


accessories.

QC personnel to inspect 100% of the shipment.

Notify SA PID on receipt of shipment.

QC personnel to inspect 100% of the shipment.

Page 20 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

Notify SA PID on receipt of shipment.

QC personnel to inspect 100% of the shipment.

Page 21 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

See GENERAL NOTES for typical accessories.

Notify SA PID on receipt of initial shipment of each


accessory type.

Hold point prior to installation of D.C. electrochemical


storage cells.

Hold point prior to installation of D.C. electrochemical


storage cells.

Hold point prior to installation of D.C. electrochemical


storage cells.

Hold point for substantial completion of building and


electrical room civil / structural / architectural / HVAC
finish work (i.e., no construction dust or fumes).

Hold point for substantial completion of building and


electrical room civil / structural / architectural / HVAC
finish work (i.e., no construction dust or fumes).

Also see SATIP-P-111-01 Grounding & Bonding


SA PID shall be notified on start of this activity for each
UPS.

Page 22 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

See SATIP-P-104-05 A/G Industrial Conduit


SATIP-P-104-03 Cable Tray
SATIP-P-104-07 B/G Conduit
SATIP-P-111-01 Grounding & Bonding
QC hold point prior to installation of battery jars.

Page 23 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

SA PID to be notified on start of this activity for each UPS


system.

SA PID shall be notified on start of this activity for each


Battery.

See SATIP-P-111-01 Grounding & Bonding

SA PID to be notified on start of this activity for each UPS


system.

SA PID to be notified on start of this activity for each UPS


system.

SA PID to be notified on start of this activity for each UPS


system.

In accordance with battery manufacturer's instructions.

Hold point prior to UPS energization.

In accordance with battery manufacturer's instructions.

Hold point prior to UPS energization.

Page 24 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

In accordance with battery manufacturer's instructions.

Hold point prior to UPS energization.

Page 25 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS energization.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS energization.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS energization.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS energization.

SATR-P-3111 UPS/DC Battery Rectifier / Charger


In accordance with UPS manufacturer's instructions.

Hold point prior to UPS energization.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS energization.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS energization.

Review EIL and all associated Quality Records.

Hold point prior to UPS energization.

Page 26 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS fault testing.

Page 27 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS fault testing.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS fault testing.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS fault testing.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS fault testing.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS fault testing.

In accordance with UPS manufacturer's instructions.

Hold point prior to UPS fault testing.

See SATIP-J-900-01 (Instrument Loop Checking) for


additional inspection and test requirements for signal and
control loops.

In accordance with UPS manufacturer's instructions.

In accordance with UPS manufacturer's instructions.


Hold point prior to UPS system certification.

Page 28 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

Review FEIL and all associated Quality Records

Page 29 of 3005/13/2017 19:47:09


DISCIPLINE:

Electrical
CONTRACTOR/SUBCONTRACTOR

REMARKS

GENERAL NOTES

cipation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust the

nstruction Organization
n advance. However, the inspection or test shall be performed as scheduled if the QA/QC

n advance. Inspection or test shall not be carried out without the QA/QC organization

the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

ar, cable crimp terminals, battery inter-cell and inter-row connectors, stainless steel mechanical fasteners, safety
water dispensers, thermometers, hydrometers, and distilled water.

Surveillance

Page 30 of 3005/13/2017 19:47:09

You might also like