Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
1 PS-01 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
2 PS-14 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
3 PS-15 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
4 PS-17 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
5 PS-5B PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
6 PS-6A PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
7 PS-5A PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
8 PS-23 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
9 PS-24 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
10 PS-33 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
11 PS-32 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Date: 25-01-2016
Total No. of Punch Items 64
18
No. of Completed Punch Items
No.of Outstanding Punch Items 46 MECHANICAL COMPLETION PUNCH LIST
Percentage Completion % 28.1%
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
12 PS-29 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
13 PS-16A PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
14 PS-13A PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
15 PS-03 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
16 PS-16B PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
17 PS-09 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
18 PS-11 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
19 PS-27 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
20 PS-20 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
21 PS-14 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
22 PS-35 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Date: 25-01-2016
Total No. of Punch Items 64
18
No. of Completed Punch Items
No.of Outstanding Punch Items 46 MECHANICAL COMPLETION PUNCH LIST
Percentage Completion % 28.1%
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
23 PS-23 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
24 PS-24 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
25 PS-25 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
26 PS-26 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
27 PS-27 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Pipe Supports welded, blasted and primed, awaits finish coat but not Water Injection Installation to start 21/01/16 once shutdown is
28 PS-28 PIP "B" BIEL 24 January 2016 Open
installed (MW-PWI-PGA-0001-01) Unit approved by MWOG
Application of Intermediate and finish coat on 2 nos welded joints and Instrument Air Project Supervisor to advise us of MWOG color
29 IAH PIP "B" MWOG 22 January 2016 Open
other instrument piping (MW-UMU-DRG-0600-004) Header specification for instrument air piping.
Valve handles for 4nos quarter turn ball valves MW-PWI-1SO- Water Injection
31 M-02 Piping B AES Open
0009A and MW-PWI-1SO-0009B Unit
2nos 4" #150 RF BL Flange to seal open ends of valves leading to Rented
Water Injection
32 M-03 Piping A filter inlet and outlet MW-PWI-1SO-0009A-02 and MW-PWI-1SO-0009A- BIEL/AES Closed Should be made available immediately
Unit
03
Rented filter inlet and outlet spools not hooked up.MW-PWI-1SO-0009A- Water Injection To be installed immediately after rented filter is
35 M-06 Piping C BIEL Closed
02 and MW-PWI-1SO-0009A-03 Unit replaced
Hot bolting on Flange & Valve on Rented Filter Suction Line before
Water Injection
36 M-07 Piping C Rented Filter Inlet Nozzle spool MW-PWI-1SO-0009A-02 and MW-PWI- BIEL/AES Closed To be carried out before Mechanical Completion
Unit
1SO-0009A-03
Application of finish coat on general firewater piping (MW-UMU-DRG- Fire water line Application of Top coat with MWOG approved red paint
37 FWM PIP "C" BIEL 20 January 2016 Ongoing
0600-005) modification in progress
Backfilling of 1 no fillet weld joint and tap wrapping required (MW-UMU- Fire water line
38 FWM PIP "C" BIEL 20 January 2016 Closed
DRG-0600-005) modification
Application of finish coat on 3 nos spool, not up to required DFT (MW- Fire water line
39 FWM PIP "C" Closed
UMU-DRG-0600-005) modification
Application of Intermediate and finish coat on 4 nos welded joints, not Fire water line
40 FWM PIP "C" Closed
up to required DFT (MW-UMU-DRG-0600-005) modification
New Pump
43 NPH PIP "C" Meter skid unit # 200 requires re-extension (MW-UMU-DRG-0600-002) BIEL Open To be installed immediately
headers
PS-32,PS-22,PS-21,PS-20, and PS-PS-19 Pipe supports not installed (MW- Open and Close
44 OCDH PIP "B" AES/BIEL 23 January 2016 Closed
UMU-DRG-0600-003) drain headers
Date: 25-01-2016
Total No. of Punch Items 64
18
No. of Completed Punch Items
No.of Outstanding Punch Items 46 MECHANICAL COMPLETION PUNCH LIST
Percentage Completion % 28.1%
Meter Skid and Awaits finish coat, 1 no. U-bolt and Neoprene
46 MSP PIP "B" PS-01, Pipe supports not installed (MW-UMU-DRG-0600-001) AES/BIEL 23 January 2016 Ongoing
Prover Area rubber
Application of finish coat on Piping connection (MW-UMU-DRG-0600- Open and Close Application of Top coat with MWOG approved red paint
48 OCDH PIP "B" BIEL 27 January 2016 Ongoing
003) drain headers in progress
Application of Intermediate and finish coat on PS-07 and PS-09 Pipe New Pump
49 NPH PIP "C" BIEL 27 January 2016 Closed
support, not up to required DFT(MW-UMU-DRG-0600-002) headers
Application of finish coat and backfilling of Drain Sump T- 500, not up to New GGF Drain Application of Top coat with MWOG approved leave
50 OCDH PIP "B" BIEL 27 January 2016 Open
required DFT(MW-UMU-GA-0800-001) Sump T-500 green paint
12'' Suction
52 SHM PIP "C" 12'' Suction header modification requires application of finish coat. header BIEL 28 January 2016 Closed
modification
Generator
12 nos side cladding removed to prevent the exhaust fumes from Awaits MWOG maintenance crew to reroute the exhaust
53 GBS SI "C" Building Shelter MWOG Open
affecting the aluminium sheets. piping connection on both generator.
Installation
MICRO TURBINE
Application of Top coat with MWOG approved Yellow
54 MTB SI "C" Application of finish coat on 1'' Gas line BUILDING Open
paint
INSTALLATION
Date: 25-01-2016
Total No. of Punch Items 64
18
No. of Completed Punch Items
No.of Outstanding Punch Items 46 MECHANICAL COMPLETION PUNCH LIST
Percentage Completion % 28.1%
GGF STORAGE
56 ST P "C" House keeping BIEL 20 January 2016 Closed
TANKS
4'' VENT HEADER Application of Top coat with MWOG approved leave
57 VHI VL "C" Installation pipe support. BIEL 30 January 2016 Open
INSTALLATION green on process piping.
Re-extension of 1 no Gusset plate upwards by 1m due to clash with the New pump
58 NPS SI "A" BIEL 30 January 2016 closed
existing booster pump and modification of 1 no diagonal brazing. shelter
Additional 3 nos Cleats to be installed on R5,R6 and R7,due to omissions New pump
60 NPS SI "A" AES/BIEL 21 January 2016 Closed
in the approved for construction drawing. shelter
New pump
64 NPS SI "B" Roofing of the new pump shelter still outstanding AES 31 January 2016 Ongoing painting in progress
shelter