Professional Documents
Culture Documents
325
A 13
of 1.5 and excess silica above the saturation of through a second stage flashing unit, using either
about 400 ppm. The large excess of silica will the silencer or the flash vessel.
polymerize and produce hard porous deposits
along the FCDS. Normal operation requires a silencer with a
steam trap. The baffles in the silencer weirbox
Further extraction of steam in the second flash were made lower than usual, so as to have a
vessel (FV) would mean a further increase in the continuous overflow of fiesh brine. Brine aging
supersaturation of silica. The colloids in this inside the silencer can then be prevented. The
location are relatively bigger and will normally pond (TP) system serves as a back-
produce brittle to hard and porous scale under up line. The silencer discharge is then delivered
high velocity brine flow. At slow flow rate (i. e. to the The has two
in the thermal pond), the colloids form the functions in the system; 1) to trap cuttings and
structured gel network which result in the products, and 2) to break the
precipitation of soft silica gel. The gel, with turbulence and cool the brine. Cuttings and
time, will form a dense mass of thick, pasty corrosion products are major factors in the
silica at the line. At the well, this massive coagulation and deposition of silica. Once
silica, will be adsorbed and could cause trapped in the the unnecessary debris can
blockages in the porous formations. The net be removed fiom the system.
effect is detrimental reduction in the RI well
capacity, or at worst, total loss of The turbulent brine flow turns laminar at the
of the well and the formations. The brine temperature also drops to about
Thus, flashing inside the RI line is
3. FIELDSET-UP avoided. The is connected to a deaerator
pond (DP) by a cemented canal. The DP serves
The Botong FCDS and injection set-up as a catchment or reservoir during high water
schematic diagram is shown in Figure 2. The flow. The brine is then delivered to the well
GSX injection set-up is located near the OP-4D through an pipeline.
and the 3D combined two-phase line. The
combined mass flow of the two wells serves as a
vehicle for the chemical. Prior to the separator
vessel, the OP-5D and the 6D two-phase lines 4. PREDICTED GSX ACTION
meet the OP-4D and the 3D lines. Therefore the
combined fluids are already treated before they Geogard SX is an aqueous solution of organic
enter the separator vessel. The brine then passes additivebased on phosphino acid
326
OP WELLS
copolymer. It is commercially introduced as an it tends to bind with the metal surface. Once the
antiscalant. It has dispersive effect toward silica surface is coated with GSX, a layer of negative
colloids and is reactive to iron corrosion charge will be produced causing of the
products. incoming silica particles.
327
7 1
POLYMER
4
At the weirbox, where turbulence combined with is when the and corrosion products are
more evaporation occurred, particle growth was eliminated.
observed. A thin soft gel deposit was found
adsorbed on the metal and cement surface, As experienced, deposition in the line near
which can be easily removed by agitation. OP-2RD and the well itself was never a
problem. Once the brine enters the wellbore,
The serves as a catchment for the solid further heating will occur, and dissolution of
wastes. Because of the coprecipitation effect, silica will dominate the process. This condition
these materials should also be removed. Further is expected to promote the prolonged use of the
evaporation and cooling occurs in this area, RI well.
which leads to further growth of the particles.
The brine is still clear with some visible same condition at the is
particles of colloidal silica. Adsorption of silica expected to happen at the FV-main TP system.
on the cement wall was observed. However, the Build-up of cuttings and corrosion products in
build-up is slow and can be easily removed by the FV, however, will not occur due to a
simple agitation. Simply damming the brine at continuous discharge at the main-TP.
the and suddenly releasing it at the weir, is
sufficient to remove this type of deposit. Brine 5.2 GSX Treatment Efficiency
temperature at the outlet is normally
The efficiency of GSX treatment was evaluated
based on the silica concentrations at various
The brine at the DP and were similar. At points of the FCDS. Daily samples were
normal conditions, brine continuously flows in collected and analyzed for total using the
the canal built inside the DP. During yellow molybdate method.
conditions or silica gel build-up in the line,
water level at the DP rises. At times where the Figure 4 shows the total data during a
wells are at full discharge, particle growth and period of five months. The total at the
precipitationwere the dominant processes inside silencer weirbox was stable and averaged about
the DP. Massive type of gel normally build-up 1240 ppm. Initially, for about a week, the
in this area. The gel, however, can be efficiency was low primarily due to the large
completely dispersed once disturbed during amount of cuttings and corrosion products that
injection. Initially, gel built-up inside the accompanied the discharge. These materials
line, this is the worst problem in the process. reacted with the polymer and enhanced
However, this problem is reduced once the deposition. However, as these materials were
application attains its maximum efficiency, that reduced and the brine flow rate stabilized,the
328
1750
0 0
1000
0
d .
0
I-
Total Silica at
Total Silica at Pond
Total Silica at line
250
Fig. 4. Total silica data for the five-month period of GSX application
329