PENDING ISSUES

A. VCB ROOM
1. Fixing of Checkered Plate on HT Trench.
2. Fixing of Rolling shutter.
3. Fixing of Exhaust Fan for Ventilation.
4. Cleaning of Room.
5. Supply of ISI approved Rubber Mat 1-meter (Wide) suitable for 11 KV.
(Length as per Site)
6. Making Earthing-pit with cover (300mm X 300mm) for VCB body earthing.

B. TRANSFORMER YARD
1. Fixing of Checkered Plate on HT & LT Trench.
2. Fixing of Fencing.
3. Cleaning of Room.
4. Making Earthing-pit with cover (300mm X 300mm) for Transformer body &
neutral earthing.

C. MAIN LT ROOM
1. Fixing of Gate & Window.
2. Fixing of Exhaust Fan for Ventilation.
3. Fixing of Rolling shutter.
4. Cleaning & Flooring of Room.
5. Supply of ISI approved Rubber Mat 1-meter (Wide) suitable for 1.1 KV.
(Length as per Site)
6. Excavation for earthing rod & fixing or maintenance free earthing rod for
Lightning Arrester. (1-Nos.)
7. Making Earthing-pit with cover (300mm X 300mm) for Main LT Panel body
earthing.

D. TOWER-4
1. Cleaning & Flooring of Distribution Panel Area.
2. Making Earthing-pit with cover (300mm X 300mm) for Tower-4 Distribution
Panel body earthing.

E. TOWER-5
1. Cleaning & Flooring of Distribution Panel Area.
2. Making Earthing-pit with cover (300mm X 300mm) for Tower-5 Distribution
Panel body earthing.

F. LIGHTNING ARRESTER
1. Excavation for earthing rod & fixing or maintenance free earthing rod for
Lightning Arrester. (2-Nos.)
2. Making Earthing-pit with cover (300mm X 300mm) for Lightning Arrester
Earthing.
PENDING ISSUE (ELECTRICAL)
A. TRANSFORMER YARD
1. Laying & Connecting of body & neutral Earthing strip of transformer to
Earthing Rod.
2. Laying & Connecting of body Earthing strip of Servo-Stabilizer.
3. Transformer oil filtration.

B. MAIN LT ROOM
1. Laying & Connecting of Body Earthing strip of Main LT panel to Earthing
Rod.
2. Fixing of 6 Nos. 4C x 300 Sq. mm Cable of Transformer.

C. TOWER-5
1. Fixing & Connecting of Tower-5 Distribution Panel.
2. Laying & Connecting of Body Earthing strip of Tower-5 distribution panel to
Earthing Rod.

D. CLUB HOUSE
1. Fixing & Connecting of Club House Panel.
2. Fixing & Laying Cable tray for Club house.
3. Laying & Connecting Cable from Main LT panel to Club House panel.
4. Laying & Connecting of Body Earthing strip of Club House panel to
Earthing Rod.

E. CLUB HOUSE
1. Laying & Connecting of Earthing strip of Lightning arrester to Earthing
Rod.