You are on page 1of 32

CHAPTER- 9

HYDRO GENERATOR, CHARACTERISTICS AND PERFORMANCE


9.1 GENERAL

The electric generator converts the mechanical energy of the turbine into electrical energy. The two major
components of the generator are the rotor and the stator. The rotor is the rotating assembly to which the
mechanical torque of the turbine shaft is applied. By magnetizing or exciting the rotor, a voltage is
induced in the stationary component, the stator. The principal control mechanism of the generator is the
exciter-regulator which sets and stabilizes the output voltage. The speed of the generator is determined by
the turbine selection, except when geared with a speed increaser. In general, for a fixed value of power, a
decrease in speed will increase the physical size and cost of the generator.

The location and orientation of the generator is influenced by factors such as turbine type and turbine
orientation. For example, the generator for a bulb type turbine is located within the bulb itself. A horizontal
generator is usually required for small turbine e.g. tube turbine and a vertical shaft generator with a thrust
bearing is appropriate for vertical turbine installations.

Conventional cooling on a generator is accomplished by passing air through the stator and rotor coils. Fan
blades on the rotating rotor assist in the air flow. For larger generator (above 5 MVA capacity) and
depending on the temperature rise limitations of the winding insulation of the machine, the cooling is
assisted by passing air through surface air coolers, which have circulated water as the cooling medium.

Large Generators interconnected with the grid should meet grid standards issued by Central Electricity
Authority (CEA) (relevant extracts are enclosed as annexure-1).

9.2 Hydro Generators Early Designs

9.2.1 Large Hydro

Large salient pole hydro generators specified for installation up to 1970 were constrained by following
considerations.

Insulation Systems for Stator and Rotor was Class B insulation with organic binding material which
permitted lower temperature rises.

Material for rotor rim punching etc. required limiting the diameter of the rotor so as to permit operation at
runaway speed.

Bearing arrangements: Top thrust and guide bearing supported on heavy brackets, capable of supporting
total generator weight was provided with a bottom guide bearing to all hydro generators including slow
speed large generator which constitutes majority of large hydro generators. This resulted in high cost of
machine and building.

Shaft mounted excitation systems were slow and unable to meet the requirements of quick response
required from large generators feeding large modern grid systems.

Stability requirements for long distance transmission lines required to feed distant load centre/grids was
achieved by manipulating reactances, excitation response ratio and flywheel effect. This resulted in larges
size of the machine.

Grids were small and there was no stringent requirement for voltage and frequency variation.

Typical section arrangement for Bhakra Left bank machines (100 MVA; 166.7 RPM) with top thrust and
guide bearing and bottom guide bearing is shown in figure 9.1 and the capability curve is shown in figure
9.2.

209
9.2.2 Small Hydro

Small hydro were a typically installed to feed remote areas and worked in isolated mode. The hydro
turbines (slow speed) were directly coupled to high cost slow speed generators. Hydro stations were
manually operated. The development of load was very poor. The small hydro became highly uneconomical
to operate because of low load factors, high installation cost and very high running cost.

9.3 Modern Large Hydro Generator

Hydraulic turbines driven generators for hydro plant above 5 MW are salient pole synchronous alternating
current machines. Large salient pole generators are relatively slow speed machines in the range 80-375 rpm
with large number of rotor poles. These generators are specifically designed.

These salient pole hydro generators interconnected with large grids have undergone considerable changes
over time which has resulted in reducing size of hydro generators considerably from the electrical and
mechanical point of view. Development in the following areas is most prominent.

i) Insulation system for stator and rotor winding


ii) Improved material
iii) Ventilation and cooling system
iv) Advanced manufacturing technology
v) Formation of large grids requires special design consideration for operation and stability.

Fig. 9.1: Bhakra Left Bank Power House


(100 MVA, 90 MW, 11 kV,0.9 pf, 3 phase, 50 Hz, 166.4 RPM, 36 Poles Vertical Wheel Water Generator
Commissioned in 1960)
Source: Notes completed for uprating the unit as member uprating committee)

210
Fig. 9.2: Bhakra Left Bank Generators Capability Curve
(Source: Notes compiled for uprating the units as member uprating committee)

9.3.1 Design Criteria

9.3.1.1 Site Operating Conditions (as per IEC: 60034, IEEE C-50-12 & IS: 4722)

Rated operation condition be specified as follows: If site operating conditions are deviating from these
values, correction may be applied.

Maximum Ambient Temperature Steady State duty: Salient-pole open ventilated air-cooled
synchronous generators operate successfully when and where the temperature of the cooling air does not
exceed 400C.

Salient-pole totally enclosed water to air cooled (water) synchronous generators operate successfully when
and where the secondary coolant temperature at the inlet to the machine or heat exchanger do not exceed
250C.

If the cooling air temperature (ambient) exceeds 400C, or cooling water temperature exceeds 250C then
maximum allowable temperature based on temperature rise on reference temperature (400/250C) of the
insulation class be specified instead of temperature.

The minimum temperature of the air at the operating site is 150C, the machine being installed and in
operation or at rest be de-energized.

Note: If temperatures different from above are expected. The manufacturer should be informed of actual
site conditions.

Generators: Generators should operate successfully at rated MVA, frequency, power factor, and terminal
voltage. Generators at other service conditions should be specified with the standards of performance
established at rated conditions.
Altitude: Height above sea level not exceeding 1000 m. For machines intended for operation on a site
where the altitude is in excess of 1000 m. should be specifically brought out.

211
9.3.1.2 Number of starts and application of load: Anticipated no. of starts and maximum MVA, power, and
reactive power loading rate of change are requirements for the manufacturer to take into account in the
machine design. The method of starting must be identified in the case of peaking stations.

9.3.1.3 Variation from rated voltage and frequency: Generators should be thermally capable of continuous
operation within the capability of their reactive capability curves over the ranges of 5 % in voltage and
2 % in frequency.

Voltage and Frequency Limits for Generators (as per IEC: 60034)

Normal Emergency
Voltage limits 5% 5% to 8%
Frequency limit 2% + 2% to + 3%;
2% to 5%
a) As the operating point moves away from rated values of voltage and frequency, the temperature rise of
total temperatures of components may progressively increase. Continuous operation at outputs near the
limits of the generators reactive capability curve (figure 9.3) may cause insulation to age thermally at
approximately two times to six times its normal rate.
b) Generators will also be capable of operation within the confines of their reactive capability curves
within the ranges of + 3 % to -5 % in frequency with further reduction of insulation life.
c) To minimize the reduction of the generators lifetime due to the effect of temperature and temperature
differentials, operation outside the above limits should be limited in extent, duration, and frequency of
occurrence. The output should be reduced or other corrective measures taken as soon as practicable.
d) The boundaries as defined result in the magnetic circuits of the generator to be over fluxed under
fluxed by no more than 5%.
e) The machine may be unstable or margins of stability may be reduced under some of the operating
conditions mentioned in a above. Excitation margins may also be reduced under these operating
conditions.
f) As the operating frequency moves away from the rated frequency, effects outside the generator may
become important and need to be considered. For example, the turbine manufacturer will specify
ranges of frequency and corresponding periods during which the turbine can operate, and the ability of
the auxiliary equipment to operate over a range of voltage and frequency should be considered.
g) Operation over a still wider range of voltage and frequency, if required, should be subject to agreement
between the purchaser and the manufacturer and need to be specifically brought out in tender
specification.
LIM ITED BY FIELD HEATING
OVEREXCITED
(LAGGING)

POWER FACTOR

RATED M V A LIM ITED BY


CAV ITATION STATOR HEATING
LIM IT
MEGAVARS

M EGAWATTS

SHAFT STRESS OR
HYDRAULIC LIM IT
UNDEREXCITED

M INIM UM
EXCITATION
(LEADING)

LIM IT

SYSTEM STABILITY
LIM IT

LINE CHARGING LIM IT

Fig. 9.3: Typical Hydro-Generator capability Curve (Typical)

212
9.3.2 Transient and Emergency Duty Requirements

A generator confirming to these guidelines will be suitable for withstanding exposure to transient event and
emergency duty imposed on a generator because of power system faults.

Sudden short circuit at the generator terminals: A generator should be capable of withstanding, without
injury, a 30 second, 3 phase short circuit at its terminals when operating at rated MVA and power factor
and at 5% over voltage, with fixed excitation. The machine shall also be capable of withstanding, without
injury, any other short circuit at its terminals of 30s duration or less in accordance with IEEE C 50. 12-
2005. Generator circuit breaker needs to be selected accordingly.

Synchronizing

a. Generators be designed to be fit for service without inspection or repair after synchronizing that is
within the limits given below:

i) Breaker closing angle 10%


ii) Generator voltage relative to system 0% to +5%
iii) Frequency difference 0.067 Hz

Additional information on synchronizing practices can be found in IEEE std. C37. 102TM- 1995.
b. Faulty synchronizing is that which is outside the limits given above. Under some system conditions,
faulty synchronizing can cause intense, short duration currents and torques that exceed those
experienced during sudden short circuits. These currents and torques may cause damage to the
generator.
c. Generators should be designed so that they are capable of coasting down from synchronous speed to a
stop after being immediately tripped off-line following a faulty synchronization. Any generator that
has been subject to a faulty synchronization should be inspected for damage and repaired as necessary
before being judged fit for service after the incident. Any loosening for stator winding bracing and
blocking and any deformation of coupling bolts, couplings, and rotor shafts should be corrected before
returning the generator to service. Even if repairs are made after a severe out-of-phase synchronization,
it should also be expected that repetition of less severe faulty synchronizations might lead to further
deterioration of the components.
d. It should be noted that the most severe faulty synchronizations, such as 1800 or 1200 out-of-phase
synchronizing to a system with low system reactance to the infinite bus, might require partial or total
rewind of the stator, or extensive or replacement of the rotor, or both.
Check synchronizing relay and auto synchronizing equipment need to be set accordingly.
Normally synchronizing closing angle is kept 7%.

Short-time volts/hertz variations: The manufacturer should provide a curve of safe short-time volts/hertz
capability. Identify the level of over flux above which the machine should never be operated, to avoid
possible machine failure. Unless otherwise specified, the curve apply for time intervals of less than 10 min.

9.3.3 Rotor Surface Heating

Continuous phase current unbalance: Generator above 5 MVA should be capable of withstanding, without
injury, the effects of a continuous phase current unbalance corresponding to a negative current of the values
in table 9.1, provided the rated MVA is not exceeded the maximum expressed as a percentage of rated
stator current.

Table 9.1 Continuous negative sequence current capability

Type of generator or generator/motor Permissible I2 (%)

Non-connected amortisseur winding 5


Connected amortisseur winding 10

213
These values also express the negative-sequence current capability at reduced generator MVA capabilities,
as a percentage of the stator current corresponding to the reduced capability.

Continuous performance with non connected amortisseur windings is not readily predictable. Therefore, if
unbalanced conditions are anticipated, machines with connected amortisseur windings should be specified.
Negative sequence relays (phase unbalance) be set accordingly.

9.3.4 Types of Generators and Configuration (Vertical or Horizontal)

Vertical shaft generators are generally used. There are two types of vertical shaft hydro generators
distinguished by bearing arrangements.

Umbrella type generators: These generators have combined bottom thrust and guide bearings and confined
to low operating speeds (up to 200 rpm) are the least expensive generator design. In semi umbrella type
generators a top guide bearing is added. Umbrella/Semi Umbrella design is being increasingly used for
slow speed vertical generator.

Conventional generators: Prior to introduction of umbrella and semi umbrella designs conventional design
comprised of top-mounted thrust and guide bearing supported on heavy brackets, capable of supporting
total weight of generator. All thrust bearing supported brackets take care the weight of generator rotating
parts. Turbine rotation parts and axial component of water thrust acting on turbine runner. A bottom guide
bearing combined with turbine shaft is usually provided. This conventional design is used for high speeds
(up to 1000 rpm) generators. Some medium size low flow turbine and tube turbine generators are horizontal
shaft. Direct driven bulb turbine generators are also horizontal shaft generators located in the bulb. Pelton
turbine coupled generators are mostly horizontal shaft.

9.3.5 Capacity and Rating

kW Rating: kW capacity is fixed by turbine rated output. In a variable head power plant the turbine output
may vary depending upon available head. In general the generator is rated for turbine output at rated head.
In peaking power plant higher generator kW rating could be specified to take care of possible higher
turbine output. Economic analysis is required for this purpose as the cost will increase and generator
capacity remains unutilized when heads are low.

The kilowatt rating of the generator should be compatible with the kW rating of the turbine. The most
common turbine types are Francis, fixed blade propeller, and adjustable blade propeller (Kaplan). Each
turbine type has different operating characteristics and imposes a different set of generator design criteria to
correctly match the generator to the turbine. For any turbine type, however, the generator should have
sufficient continuous capacity to handle the maximum kW available from the turbine at 100-percent gate
without the generator exceeding its rated nameplate temperature rise. In determining generator capacity,
any possible future changes to the project, such as raising the forebay (draw down) level and increasing
turbine output capability, should be considered. Typical hydro generator capability curve is shown in figure
9.3.

kVA Rating and power factor: kVA and power factor is fixed by consideration of interconnected
transmission system and location of the power plant with respect to load centre. These requirements include
a consideration of the anticipated load, the electrical location of the plant relative to the power system load
centers, the transmission lines, substations, and distribution facilities involved. A load flow study for
different operating condition would indicate operating power factor, which could be specified.

(Turbine output in MW) x (Generator efficiency)


Generator MVA =
Generator power factor

9.3.6 Electrical Characteristics

Electrical Characteristics e.g. voltage, short circuit ratio, reactance, line charging capacity etc. must
conform to the interconnected transmission system. Large water wheel generators are custom designed to

214
match hydraulic turbine prime over. Deviation from normal generator design parameters to meet system
stability needs can have a significant effect on cost. The system stability and other needs can be met by
modern static excitation high response systems and it is a practice to specify normal characteristics for
generators and achieve stability requirements if any by adjusting excitation system parameter (ceiling
voltage/exciter response).

9.3.6.1 Generator Terminal Voltage

Generator terminal voltage should be as high as economically feasible. Standard voltage of 11 kV or higher
is generally specified for hydro generator.

9.3.6.2 Insulation and Temperature Rise

Modern hydro units are subjected to a wide variety of operating conditions but specifications are prepared
with the intention of achieving a winding life expectancy of 35 years or more under anticipated operating
conditions. Present practice is to specify class F insulation system for the stator and rotor winding with
class B temperature rise over the ambient. Ambient temperature rise should be determined carefully from
the temperature of the cooling water etc.
If may be noted that as per IS the temperature rise specified over an ambient of 400C. Accordingly
maximum temperature for the insulation class under site conditions should be specified.
The class F system is known as thermo setting insulation system. The epoxy resins systems may be divided
into the following two major classes.
i) Resin rich system
ii) Resin poor system

Resin poor technology needs sophisticated resin storage, transfer and impregnation plants. Most of large
machines commissioned in India have class F insulation resin rich.

It is generally believed that stator insulation degradation occurs due to slot discharge as well as due to
ionization. Slot discharge is a result of poor contact between the conducting surface on generator coil and
stator iron and built up of high surface potential. Discharges of this nature can be very severe because of
the charges current involved and cause serious damage to the insulation. At some stage slot discharges
appear to or begin to increase between the surface of the insulation of the winding and laminated slot wall
and provide one of the deteriorating factor. Phenomenon of slot discharges is known since long and efforts
have been made to evolve suitable methods for monitoring the state of erosion of insulation in an
assembled machine. With adoption of epoxy mica insulation and use of increased current densities
resulting in higher electro-dynamic forces, there is an increase in the intensity of these slots discharges. Slot
discharges have been reported in water wheel generators.

Thermosetting insulation systems materials are hard and do not readily conform to the stator slot surface, so
special techniques and careful installation procedures must be used in applying these materials to avoid
possible slot discharges. Special coil fabrication techniques, installation, acceptance and maintenance
procedure are required to ensure long, trouble-free winding life.

All components of stator and rotor insulation should be of class F insulation with class B temperature rise.

9.3.6.3 Short Circuit Ratio

The short circuit ratio of a generator is the ratio of field current required to produce rated open circuit
voltage to the field current required to produce rated stator current when the generator terminals are short
circuited and is the reciprocal of saturated synchronous reactance. Normal short circuit ratios are given
below. Higher than normal short circuit ratio will increase cost and decrease efficiency.

Generator Power Factor Normal Short Circuit Ratio


0.8 1.0
0.9 1.10
0.95 1.17
215
In general, the requirement for other than nominal short-circuit ratios can be determined only from a
stability study of the system on which the generator is to operate. If the stability study shows that
generators at the electrical location of the plant in the power system are likely to experience instability
problems during system disturbances, then higher short-circuit ratio values may be determined from the
model studies and specified.

Refer Para 9.4 for more detailed discussion.

9.3.6.4 Line Charging and Synchronous Condensing Capacity

This is the capacity required to charge an unloaded line. Line charging capacity of a generator having
normal characteristics can be assumed to equal 0.75 of its normal rating multiplied by its short circuit ratio.
If the generator is to be designed to operate as synchronous condenser. The capacity when operating over
excited as condensers can be as follows:

Power Factor Condenser Capacity


0.80 65%
0.90 55%
0.95 45%

9.3.6.5 Reactance

The eight different reactances of a salient-pole generator are of interest in machine design, machine testing,
and in system stability model studies. Lower than normal reactances of the generator and step-up
transformer for system stability will increase cost and is not recommended.

Both rated voltage values of transient and subtransient reactances should be used in computations for
determining momentary rating and the interrupting ratings of circuit breakers.

Typical values of transient reactances for water wheel generators up to 25 MA are given below. Guaranteed
values of transient reactances will be approximately 10% higher.

Rated Sub-transient Reactance - xd


MVA Rating Speed RPM
100 150 300
10 - 25 0.27 0.26 0.25

9.3.6.6 Damper Winding

A short circuit grid copper conductor in face of each of the salient poles is required to prevent pulling out
of step the generator interconnected to large grid. Two types of damper windings may be connected with
each other, except through contact with the rotor metal. In the second, the pole face windings are connected
at the top and bottom to the adjacent damper windings.

The damper winding is of major importance to the stable operation of the generator. While the generator is
operating in exact synchronism with the power system, rotating field and rotor speed exactly matched, there
is no current in the damper winding and it essentially has no effect on the generator operation. If there is a
small disturbance in the power system, and the frequency tends to change slightly, the rotor speed and the
rotating field speed will be slightly different. This may result in oscillation, which can result in generator
pulling out of step with possible consequential damage.

The damper winding is of importance in all power systems, but more important to systems that tend toward
instability, i. e. systems with large loads distant from generation resources, and large intertie loads.

216
In all cases, connected damper windings are recommended. If the windings are not interconnected, the
current path between adjacent windings is through the field pole and the rotor rim. This tends to be a high
impedance path, and reduce the effectiveness of the winding, as well as resulting in heating in the current
path. Lack of interconnection leads to uneven heating of the damper windings, their deterioration, and
ultimately damage to the damper bars.

The damper winding also indirectly aids in reducing generator voltage swings under some faults conditions.
It does this by contributing to the reduction of the ratio of the quadrature reactance and the direct axis
reactance, X q / X d . This ratio can be as great as 2.5 for a salient pole generator with no damper winding,
and can be as low as 1.1 if the salient pole generator has a fully interconnected winding practice is to
provide X q / X d L 1.3.

9.3.6.7 Efficiency

As high an efficiency as possible which can be guaranteed by manufacturer should be specified. Calculated
values should be obtained from the manufacturer.

For a generator of any given speed and power factor rating, design efficiencies are reduced by the
following:

i. Higher Short-Circuit Ratio


ii. Higher WR2
iii. Above-Normal Thrust

9.3.6.8 Total Harmonic Distortion (THD)

Limits: When tested on open circuit and at rated speed and voltage, the total harmonic distortion (THD) of
the line-to-line terminal voltage, as measured according to the methods laid down in IS should not exceed
5%.

9.3.6.9 Phase Sequence

Phase sequence defines the rotor in which the phase voltages reach their positive maximum at the terminals
of the machine, and shall be agreed upon the manufacturer and purchaser. Typically this is given as a three
letter sequence, R, C, L, (right, center, left) or L, C, R (left, center, right), as defined by an observer looking
at the terminals from outside the machine. In the case of terminals on the top or bottom of the machine, the
sequence is defined looking from the end of the machine nearest the terminals toward the centerline of the
machine.

Care must be exercised to ensure that the defined phase sequence of the machine is consistent with that of
the connected equipment, particularly in situations where the plant layout requires otherwise identical
machines to have different phase sequence.

9.3.7 Mechanical Characteristics

9.3.7.1 Direction of Rotation

The direction of the rotation of the generator should suit the prime mover requirements.

9.3.7.2 Large Generator Stator

The stator frame is designed for rigidly and strength to allow it to support the clamping forces needed to
retain the stator punching in the correct core geometry. Strength is needed for the core to resist deformation
under fault conditions and system disturbances. Also, the core is subjected to magnetic forces that tend to
deform it as the rotor field rotates. In some large size machines, this flexing has been known to cause the
core to contact the rotor during operation. In one instance, the core deformed and contacted the rotor, the

217
machine was tripped by a ground fault, and intense heating caused local stator tooth iron melting, which
damaged the stator winding ground insulation.

In machines with split phase windings where the split phase currents are monitored for machine protection,
the variation in the air gap causes a corresponding variation in the split phase currents. If the variations are
significant, the machine will trip by differential relay action, or the differential relays will have to be
desensitized to prevent tripping. Desensitizing the relays will work, but it reduces their effectiveness in
protecting the machine from internal faults.

9.3.7.3 Rotor Assembly Critical Speeds

A rotor dynamic analysis of the entire shaft system should be performed. This analysis should include the
prime mover, generator, and any other rotating components. This analysis should include lateral and
torsional shaft system response to the various excitations that are possible within the operational duties
allowed by the standards. When the turbine generator is purchased as a set, it would be typical that the
manufacturer should perform this analysis. When shaft components are purchased from different
manufacturers, the purchaser should arrange to have this analysis. Critical speeds of the generator rotor
assembly should not cause unsatisfactory operation within the speed range corresponding to the frequency
range agreed in accordance with 9.3.1.4. The generator rotor assembly shall also operate satisfactorily for a
reasonable period of time at speeds between standstill and rated speed agreed upon by the prime mover and
generator designers. The turbine generator set shaft vibration at operating speed should be within limits
specified by ISO: 7919-5 for machine sets in hydraulic power generating and pumping plants.

9.3.7.4 Bearings

The allowable hydraulic thrust provided in standard generator design is satisfactory for use with a Francis
runner, but a Kaplan runner requires provision for higher-than-normal thrust loads. It is important that the
generator manufacturer have full and accurate information regarding the turbine.

Specifications for generators above 10 MW, and for generators in unmanned plants, should require
provisions for automatically pumping oil under high pressure between the shoes and the runner plate of the
thrust bearing just prior to and during machine startup, and when stopping the machine.
9.3.7.5 Noise Level and Vibration

Under all operating conditions, the noise level of generator should be less than 85-95 dB (A) at a distance
of 1 meter radialy & 1.5 m from floor of operating. In order to prevent undue and harmful vibrations, all
motors should be statically and dynamically balanced in accordance with IEEE std. C50.12-2005. Test
procedure for verification should be based on ISO 3746. Acoustic treatment may be necessary to achieve
decreasing sound pressure levels at 90 db.

9.3.7.6 Over speed withstand

It is general practice in India to specify all hydro generators to be designed for full turbine runaway
conditions (IS: 4722-2001, table 3 Clause 1). The stresses during design runaway speed should not exceed
two-thirds of the yield point.

American practice as per Army Corps Engineers Design Manual is as follows;

Generators below 360 rpm and 50,000 kVA and smaller are normally designed for 100% over speed.

9.3.7.7 Flywheel Effect

The flywheel effect (WR2) of a machine is expressed as the weight of the rotating parts multiplied by the
square of the radius of gyration. The WR2 of the generator can be increased by adding weight in the rim of
the rotor or by increasing the rotor diameter. Increasing the WR2 increases the generator cost, size and
weight, and lowers the efficiency. The need for above-normal WR2 should be analyzed from two
standpoints, the effect on power system stability, and the effect on speed regulation of the unit. Speed
regulation and governor calculation are discussed in the guidelines for selection of turbines and governors.

218
Electrical system stability considerations may in special cases require a high WR2 is only one of several
adjustable factors affecting system stability, all factors in the system design should be considered in
arriving at the minimum overall cost. Sufficient WR2 must be provided to prevent hunting and afford
stability in operation under sudden load changes. The index of the relative stability of generators used in
electrical system calculations is the inertia constant, H, which is expressed in terms of stored energy per
kVA of capacity. It is computed as:

kW s 0.231(WR 2 )(r / min)2 106


H= =
kVA kVA
The inertia constant will range from 2 to 4 for slow-speed (under 200 rpm) water wheel generators.
Transient hydraulic studies of system requirements furnish the best information concerning the optimum
inertia constant, but if data from studies are not available, the necessary WR2 can be computed or may be
estimated from knowledge of the behavior of other units on the system.

Flywheel effect is expressed as moment of inertia (GD2) (in India) as compared to flywheel effect WR2
(US/English) GD2 = weight x Diameter2 and WR2 = weight x Radius2 (lb.ft2).

GD 2
Accordingly, WR2 =
4
Conversion factor for WR2 (USA) in lb.ft2 and GD2 (India) kg. m2 is as follows:

GD2 = x 5.9 = lb. ft 2 6 x lb. ft 2

The flywheel effect of the generator can be increased by adding weight in the rim of the rotor or by
increasing the rotor diameter. Increasing the GD2 increases the generator cost, size and weight, and lowers
the efficiency. The need for above-normal WR2/ GD2 is analyzed from two standpoints, the effect on power
system stability, and the effect on speed regulation of the unit. Speed regulation and governor calculation
are discussed in guidelines for turbine selection. Power system stability considerations do not arise in small
hydro generators under considerations.

Mechanical characteristics of the generator are based on the hydraulic turbine data to which the generator
will be coupled. Characteristics regarding speed, flywheel effect have been discussed in guidelines of
turbine selection.

9.3.7.8 Cooling

Losses in a generator appear as heat which is dissipated through radiation and ventilation. The generator
rotor is normally constructed to function as an axial flow blower, or is equipped with fan blades, to
circulate air through the windings. Small-generators up to 5 MW may be partially enclosed, and heated
generator air is discharged into the generator hall, or ducted to the outside. Adequate ventilation of the
generator hall preferably thermostatically should be provided in this case.

Water to air coolers normally is provided for all modern hydro generators rated greater than 5 MVA. The
coolers are situated around the outside periphery of the stator core. Generators equipped with water-to-air
coolers can be designed with smaller physical dimensions, reducing the cost of the generator. Automatic
regulation of the cooling water flow in direct relation to the generator loading results in more uniform
machine operating temperatures, increasing the insulation life of the stator windings. Cooling of the
generator can be more easily controlled with such a system, and the stator windings and ventilating slots in
the core kept cleaner, reducing the rate of deterioration of the stator winding insulation system. The closed
systems also permits the addition of automatic fire protection systems, attenuates generator noise, and
reduce heat gains that must be accommodated by the powerhouse HVAC system.

219
Normally, generators should be furnished with one cooler than the number required for operation at rated
MVA. This allows one cooler to be removed for maintenance without affecting the unit output.

The generator cooling water normally is supplied from the penstock via a pressure reducing station or
pumped from the tailrace. In either case, automatic self-cleaning filters must be provided in the cooling
water supply lines to avoid frequent fouling or plugging of the water-to-air coolers.

9.3.7.9 Fire Extinguishing System

All hydroelectric generators greater than 25 MVA should be furnished with either a water deluge or carbon
dioxide (CO2) fire extinguishing system, to minimize the damage caused by a fire inside the machine.
Generators 25 MVA or below should be evaluated individually to ensure installation of a cost effective
system. When total thermo setting insulation system is adopted water sprinkler system may be used. This
system is safer for operating staff.

9.3.7.10 High Pressure Oil Injection System (For Thrust Bearing)

Modern Thrust Bearings have a high-pressure oil lift system, which injects oil into each shoe pad of the
bearing during starting and stopping of the unit. This helps establish a hydrodynamic oil film between the
rotating (thrust collar) and stationary (bearing shoes or pads) members of the thrust bearing.

The presence of the hydrodynamic oil film minimizes bearing wear. Consequently, during a unit start the
high pressure oil of lift system is turned on before the unit starts to rotate. It is usually shut off after the unit
speed exceeds 75 to 90% of rated speed because, at the higher rotational speeds, the hydrodynamic oil film
is self sustaining. On unit shutdown, the high pressure oil lift system is turned on when the unit speed
decreases to the 75 to 90% range and maintained until the unit is at stand still. The maximum wear on the
bearing pads occurs at slow speeds, when, due to hydrodynamic effects, the oil film is not maintained over
the entire bearing surface.

9.3.7.11 Dynamic Braking System

Modern hydroelectric generators use electrical dynamic braking in addition to the mechanical friction
braking system. The electrical dynamic braking system minimizes the wear on the mechanical brake ring
and brake pads, prolonging their life. In addition, electrical dynamic braking reduces the duration over
which the mechanical brakes are applied during a unit stop sequence, thereby minimizing the amount of
brake dust produced by the mechanical brake system. The extended life and reduced brake dust are
especially significant for units that are started and stopped several times a day; or units; such as those
connected to pelton turbines, which operate at very high rpms.

Electrical dynamic braking is initiated at a higher unit rotational speed, normally 50% of rated speed; and
maintained until the mechanical friction brakes are applied. When dynamic braking is utilized in
conjunction with the mechanical brakes, the mechanical brakes normally are applied at ten to 15% of rated
speed. Modern hydroelectric generators, especially pumped storage units, also utilize a brake dust vacuum
system to capture most of the brake dust produced when the mechanical friction brakes are applied.

9.4 Characteristics of Large Hydro Generators of Dehar Power Plant case study

Studies for fixing capacity and unit size are outlined in chapter 2 Para 2.4. Considerations involved for
fixing, Type and principal electrical and mechanical characteristics of 174 MVA Dehar Generators on Beas
-Satluj Link project are given below:

9.4.1 Introduction

Dehar Power Plant of Beas Sutlej link Project commissioned in 1976 to 1980, has six (four first stage and
two second stage) semi-umbrella type vertical generators of 0.95 pf of 165 MW each. A longitudinal
section of the scheme is shown in Figure 9.4. The 300 rpm generators are coupled to 282 m (925 ft) rated
head Francis turbines having a turbine runaway speed of 516 rpm. Unit size of 174 MVA selected for the
power plant was the largest unit size in the country at that time and is perhaps a machine with highest speed

220
with semi umbrella construction. The power plant is to be interconnected with the Northern Regional Grid
of India in the first stage by a 280 km long single circuit 420 kV line at Panipat and by a 60 km long double
circuit 245 kV line at Ganguwal. A second 420 kV line was added alongwith two second stage units. 420
kV was being introduced in the region for the first time.

The main interconnected transmission system to which Dehar power plant was to be interconnected (1st
stage) is shown in Figure 9.5and interconnection (1st stage) of the power plant with the grid is shown in
Figure 9.6.

Considerations of economy dictated the size and type of generating unit to be installed and transmission
outlets to be provided at a hydro generating site. Further in the initial stage of development of an EHV
system problems of stability of hydro generators are liable to be critical because of weak system, large
transmission angle and operation of generators at leading power factor. There is also risk of self-excitation
and problem of voltage stability due to capacitive loading of long EHV lines. Further, smaller inertia
constants of modern machines of advanced design may also jeopardize the stability of turbine governor
gear. These problems are brought out and the system and other considerations involved in fixing the
economical size, type and principal electrical and mechanical characteristics of Dehar hydro generators and
excitation system keeping in view advancement in material technology, availability of modern fast acting
static excitation equipment and methods used for analysis of system problems are discussed.

Dehar Power Station is located in the Himalayan region of India. This region and many other hilly areas
where hydro stations are located are seismic zones. Provisions made in the generator for safeguarding
against seismic forces have also been outlined.

Fig. 9.4: Longitudinal Section


(Source: Paper by Author 2nd world Congress, International Water Resources Association 1979)

221
Fig. 9.5: Dehar EHV System and Interconnected Northern regional Grid single line diagram 2200 kV and above
(Source: Paper by Author 2nd world Congress, International Water Resources Association 1979)

9.4.2 Megawatt Rating and Number of generating Units

Substantial economies in the cost of equipment and civil structure are obtained by the installation of lesser
machines of bigger size especially in a high head power plant. Further, higher efficiency is associated with
larger generating units. Limitation on the size of the unit is placed on the one hand by water turbine and on
the other hand by system considerations. With the availability of better techniques and materials, hydraulic
turbine design has undergone rapid advancement and very large sized medium and high head Francis
turbine hydraulic turbines have been made or proposed, e.g., 8,20,000 HP hydraulic turbines for third
power plant at Grand Coulee in USA. Accordingly the major constraint on unit size for medium and high
head Francis turbine driven generators is system characteristics and other limitations. As the system grows
bigger, larger size generating units can be installed. In general maximum economic unit size that can be
installed in a system can be found out by evaluating the increase in system spare generating capacity
required as a result of increase in unit size. Evaluation of system spare generating capacity for various unit
sizes is dependent upon size and characteristics of the power plants in the system and spare capacity
already available in the grid. Other considerations involved are part load operation and transportation of
heavy and big single piece packages,

The economic unit size at Dehar Power Plant was fixed keeping in view the maximum available working
capacity of 583 MW as determined by water and power studies, the system spare generating capacity
required to be provided at the power plant to meet forced outages in the system and the capacity outage
required for scheduled maintenance of power units. Seasonal variation of load and available generating
capacities was taken into consideration for fixing spare capacity. The spare generating capacity required for
forced outages was worked out by probability methods.
222
Transportation was also a consideration in fixing the maximum size of the units. Details are given in
chapter 2 (Para 2.5). Accordingly the optimum number and kilowatt rating of generating units was fixed as
four units of 165 MW each of the first stage. Two additional second stage units of equal capacity were
proposed in the power house to take care of peaking requirements of future thermal power plants in the
grid.

9.4.3 Power Factor and MVA Rating

The required MVA rating of generators is determined from the system reactive power requirements.
Growth of system network and a better understanding of its behaviour has resulted in a definite trend
towards specifying higher power factor rating especially for remotely located hydro generators,
interconnected with the grid by EHV lines, so that the improvement in performance associated with the
operation of generating unit nearer to its rated power factor can be realized.

In case of Dehar Power Plant detailed load flow studies were carried out so as to find out the VARS
(reactive power) fed into the system from Dehar generators for various interconnection alternatives. The
reactive flow, megawatt load and consequently the actual power factor at which the machines operate in the
study were found out. In the study total VARS of the system load were balanced by VARS from
generators, capacitors already installed in the system and additional capacitors at load end adjusted so as to
ensure tail end voltages at proper level. A typical study for an equivalent reduced network is shown in
Figure 9.7.

For various schedules of generation and transmission alternatives and line outage the reactive flow and
power factor of operation at Dehar machines varies from 0.96 to 0.98. Consequently the power factor of the
machines was specified as 0.95. Procurement of higher power factor machines resulted in saving in the cost
of generators.

9.4.4 Type of Generators

Savings in the cost of generators, overhead traveling crane capacities and civil structures can be made by
adopting umbrella type of construction with a combined thrust and guide bearing below the rotor. Major
conditions required to be fulfilled before umbrella type of construction can be adopted for large sized high
speed hydro generators may be summarized as below:
a) The ratio of core length to rotor diameter be kept as low as possible and at the same time ensuring
that a reasonably high output co-efficient is obtained consistent with the required winding
temperature rises and transient reactances.

b) The required flywheel effect is incorporated in the rotor rim and poles with the stresses in the rotor at
turbine runaway speed not exceeding two-third of the yield point of material.

c) The rotor overhang above the guide bearing to be reduced sufficiently, to ensure that the calculated
critical speed of the combined generator and turbine shaft system is higher than the runaway speed
by an adequate margin.

d) The radial width of air gap to be as high as possible so as to minimize the unbalanced magnetic pull
on the rotor and thereby reducing the over-turning moment on the bearing.

(e) Ample and adequate design of bearing and easy accessibility to the thrust bearing.
In order to satisfy the above conditions for umbrella construction for Dehar generators, it was
necessary that the length of the rotor core (and hence rotor overhang above the guide bearing) be
reduced. It is, therefore, obvious that umbrella generator construction would require large diameter
rotors with ratio of core length to core diameter less than about 0.29 so that critical speeds are well
above turbine runaway speeds. Large diameter rotors would mean higher speeds and consequently
higher stresses. Quality of steel available for rotor fabrication was, therefore, one of the main factors
which hitherto restricted umbrella construction to smaller sized medium and low speed Francis and
Propeller or Kaplan turbine generators. Similarly the limit curve for hydro-generator of above 100
MVA rating did not exceed 200 rpm in Japan. It was now possible to adopt umbrella type

223
construction for large high speed generators due to the advancement in material technology with
special reference to higher tensile sheet steel for rotor rim punchings so as to obtain a minimum
factor of safety of 1.5 on the yield point at turbine runaway speed.

Fig. 9.6: Interconnection of Dehar power plant with grid


(Source: Paper by Author 2nd world Congress, International Water Resources Association 1979)

Fig. 9.7: Reduced equivalent system load flow study (Max. hydro)- maximum load condition
(Source: Paper by Author 2nd world Congress, International Water Resources Association 1979)

224
For Dehar Power plant 173.8 MVA 300 rpm generators, high tensile sheet steel with a yield strength of 56
kg/sq mm (36 tons/sq in.) was used which permits its operation on a turbine runaway speed of 510 rpm at a
peripheral speed of 176 m/sec for its large diameter (6.8 m) rotors with the specified factors of safety. With
the use of this high tensile sheet steel, it was possible to reduce the length of the core (and hence the rotor
overhang above the guide bearing) sufficiently to satisfy the conditions for umbrella construction. A second
guide bearing at the top, although not considered necessary by suppliers of generators, was got provided so
as to provide better stability for the unit taking into consideration seismic zone of location. Manufacturers
intimated that the cost of the umbrella machines is about 12 to 15 percent lower than that of conventional
top thrust bearing and two guide bearing arrangement. Semi-umbrella generator actually provided was
about 10 percent cheaper. The calculated first critical speed for the combined generator and shaft system
with the proposed semi-umbrella arrangement for the generator was about 20 percent above turbine
runaway speed.

9.4.5 Generator Flywheel Effect and Stability of turbine Governor System

Large modern hydro generators have smaller inertia constant and may face problems concerning stability of
turbine governing system. This is due to the behaviour of the turbine water, which because of its inertia
gives rise to water hammer in pressure pipes when control devices are operated. This is in general
characterized by the hydraulic acceleration time constants. In isolated operation, when frequency of the
whole system is determined by turbine governor the water hammer affects the speed governing and
instability appears as hunting or frequency swinging. For interconnected operation with a large system the
frequency is essentially held constant by the later. The water hammer then effects the power fed to the
system and stability problem only arises when the power is controlled in a closed loop, i.e., in case of those
hydro generators which take part in frequency regulation.

The stability of turbine governor gear is greatly affected by the ratio of the mechanical acceleration time
constant due to the hydraulic acceleration time constant of the water masses and by the gain of the
governor. A reduction of the above ratio has a destabilizing effect and necessitates a reduction of the
governor gain, which adversely affects frequency stabilization. Accordingly a minimum flywheel effect for
rotating parts of a hydro unit is necessary which can normally only be provided in the generator.
Alternatively mechanical acceleration time constant could be reduced by the provision of a pressure relief
valve or a surge tank, etc., but it is generally very costly. An empirical criteria for the speed regulating
ability of a hydro generating unit could be based on the speed rise of the unit which may take place on the
rejection of the entire rated load of the unit operating independently. For the power units operating in large
interconnected systems and which are required to regulate system frequency, the percentage speed rise
index as computed above was considered not to exceed 45 percent. For smaller systems smaller speed rise
be provided (Refer Chapter 4).

Fig. 9.8: Longitudinal section from intake to Dehar Power Plant


(Source: Paper by Author 2nd world Congress, International Water Resources Association 1979)

225
For Dehar Power Plant, the hydraulic pressure water system connecting the balancing storage with the
power unit consisting of water intake, pressure tunnel, differential surge tank and penstock is shown in
Figure 9.8. Limiting the maximum pressure rise in the penstocks to 35 percent the estimated maximum
speed rise of the unit upon rejection of full load worked out to about 45 percent with a governor closing
time of 9.1 seconds at rated head of 282 m (925 ft) with the normal flywheel effect of the rotating parts of
the generator (i.e., fixed on temperature rise considerations only). In the first stage of operation the speed
rise was found to be not more than 43 percent. It was accordingly considered that normal flywheel effect is
adequate for regulating frequency of the system.

9.4.6 Generator Parameters and Electrical Stability

The generator parameters which have a bearing on stability are the flywheel effect, transient reactance and
short circuit ratio. In the initial stage of development of 420 kV EHV system as at Dehar problems of
stability are liable to be critical because of weak system, lower short circuit level, operation at leading
power factor, and need for economy in providing transmission outlets and fixing size and parameters of
generating units. Preliminary transient stability studies on network analyzer (using constant voltage behind
transient reactance) for Dehar EHV system also indicated that only marginal stability would be obtained.

In the early stage of design of Dehar Power Plant it was considered that specifying generators with normal
characteristics and achieving requirements of stability by optimizing parameters of other factors involved
especially those of excitation system would be economically cheaper alternative. In a study of the British
System also it was shown that changing generator parameters have comparatively much less effect on the
stability margins. Accordingly normal generator parameters as given in the appendix were specified for the
generator. The detailed stability studies carried out are given in chapter 10 in Para 10.12.

9.4.7 Line Charging Capacity and Voltage Stability

Remotely located hydro generators used to charge long unloaded EHV lines whose charging kVA is more
than the line charging capacity of the machine, the machine may become self excited and voltage rise
beyond control. The condition for self excitation is that xc < xd where, xc is capacitive load reactance and xd
the synchronous direct axis reactance. The capacity required for charging one single 420 kV unloaded line
E2/xc up to Panipat (receiving end) was about 150 MVARs at rated voltage. In second stage when a second
420 kV line of equivalent length is installed, the line charging capacity required to charge both the
unloaded lines simultaneously at rated voltage would be about 300 MVARs.
The line charging capacity available at rated voltage from Dehar generator as intimated by suppliers of the
equipment was as follows:

(i) 70 percent rated MVA, i.e., 121.8 MVAR line charging is possible with a minimum positive
excitation of 10 percent.
(ii) Up to 87 percent of rated MVA, i.e., 139 MVAR line charging capacity is possible with a
minimum positive excitation of 1 percent.
(iii) Up to 100 percent of rated MVAR, i.e., 173.8 line charging capacity can be obtained with
approximately 5 percent negative excitation and maximum line charging capacity that can be
obtained with negative excitation of 10 percent is 110 percent of rated MVA (191 MVAR)
according to BSS.
(iv) Further increase in line charging capacities is possible only by increasing the size of the machine.

In the case of (ii) and (iii) hand control of excitation is not possible and full reliance has to be placed on
continuous operation of quick acting automatic voltage regulators.

It is neither economically feasible nor desirable to increase the size of the machine for the purpose of
increasing the line charging capacities.

Accordingly taking into consideration operating conditions in the first stage of operation it was decided to
provide for a line charging capacity of 191 MVARs at rated voltage for the generators by providing
negative excitation on the generators.

226
Critical operating condition causing voltage instability may also be caused by the disconnection of load at
the receiving end. The phenomenon occurs due to capacitive loading on the machine which is further
adversely affected by the speed rise of generator. Self excitation and voltage instability may occur if.

Xc n2 (Xq + XT)

Where, Xc is capacitive load reactance, Xq is quadrature axis synchronous reactance and n is the maximum
relative over speed occurring on load rejection. This condition on the Dehar generator was proposed to be
obviated by providing a permanently connected 400 kV EHV shunt reactor (75 MVA) at the receiving end
of the line as per detailed studies carried out.

9.4.8 Damper winding

Principal function of a damper winding is its capacity to prevent excessive over-voltages in the event of
line to line faults with capacitive loads, thereby reducing over-voltage stress on the equipment. Taking into
consideration remote location and long interconnecting transmission lines fully connected damper windings
with the ratio of quadrature and direct axis reactances Xnq/ Xnd not exceeding 1.2 was specified.

9.4.9 Generator Characteristic and Excitation System

Generators with normal characteristics having been specified and preliminary studies having indicated only
marginal stability, it was decided that high speed static excitation equipment be used to improve stability
margins so as to achieve overall most economical arrangement of equipment. Detailed studies were carried
out to determine optimum characteristics of the static excitation equipment and discussed in chapter 10.

9.4.10 Seismic Considerations

Dehar Power Plant falls in seismic zone. Following provisions in the hydro generator design at Dehar were
proposed in consultation with the manufacturers of equipment and taking into consideration the seismic and
geological conditions at site and the report of the Koyna Earthquake Experts Committee constituted by
Government of India with the help of UNESCO.

Mechanical Strength
Dehar generators be designed to withstand safely the maximum earthquake acceleration force both in the
vertical and horizontal direction expected at Dehar acting at the centre of machine.

Natural Frequency
Natural frequency of the machine be kept well away (higher) from the magnetic frequency of 100 Hz
(twice the generator frequency). This natural frequency will be far removed from the earthquake frequency
and be checked for adequate margin against the predominant frequency of earthquake and critical speed of
rotating system.
Generator stator support
The generator stator and lower thrust and guide bearing foundations comprise a number of sole plates. The
sole plates be tied to foundation laterally in addition to normal vertical direction by foundation bolts.
Guide Bearing Design
Guide bearings to be of segmental type and the guide bearing parts be strengthened to withstand full
earthquake force. Manufacturers further recommended to tie up the top bracket laterally with the barrel
(generator enclosure) by means of steel girders. This would also mean that the concrete barrel in turn would
have to be strengthened.
Vibration Detection of Generators
Installation of vibration detectors or eccentricity meters on turbines and generators were recommended to
be installed for initiating shutdown and alarm in case the vibrations due to earthquake exceed a
predetermined value. This device may also be used in detecting any unusual vibrations of a unit due to
hydraulic conditions affecting the turbine.

227
Mercury Contacts
Severe shaking due to earthquake is liable to result in false tripping for initiating shutdown of a unit if
mercury contacts are used. This can be avoided by either specifying anti-vibration type mercury switches or
if found necessary by adding timing relays.

9.4.10 Conclusions

(1) Substantial economies in the cost of equipment and structure at Dehar Power Plant were obtained
by adopting large unit size keeping in view size of the grid and its influence on system spare
capacity.
(2) Cost of generators was reduced by adopting umbrella design of construction which is now
possible for large high speed hydro generators due to the development of high tensile steel for
rotor rim punchings.
(3) Procurement of natural high power factor generators after detailed studies resulted in further
savings in the cost.
(4) Normal flywheel effect of the rotating parts of the generator at the frequency regulating station at
Dehar was considered sufficient for stability of turbine governor system because of the large
interconnected system.
(5) Special parameters of remote generators feeding EHV networks for ensuring electrical stability
can be met by fast response static excitation systems.
(6) Fast acting static excitation systems can provide necessary stability margins. Such systems,
however, require stabilizing feed back signals for achieving post fault stability. Detailed studies
should be carried out.
(7) Self-excitation and voltage instability of remote generators interconnected with the grid by long
EHV lines can be prevented by increasing line charging capacity of machine by resort to negative
excitation and/or by employing permanently connected EHV shunt reactors.
(8) Provisions can be made in the design of generators and its foundations to provide safeguards
against seismic forces at small costs.
9.4.11 Main Parameters of Dehar Generators

Short Circuit Ratio = 1.06


Transient Reactance Direct Axis = 0.2
Flywheel Effect = 39.5 x 106 lb ft2
Xnq/Xnd not greater than = 1.2
9.5 Small Hydro Generator Up to & Below 5 MW

9.5.1 General

Standardized or upgraded mass-produced machine should be used where possible conforming to IS: 4722.
Most off-the-shelf or mass-produced machines are designed for lower over speed values (typically 1,25
to 1,50 times rated speed) than are experienced with hydraulic turbines. Therefore, such generator designs
should be checked for turbine runaway conditions.

Accordingly cylindrical rotor synchronous may be considered up to 3 MW capacity.

Special Design Features as per IEC 1116 conforming to IS: 4722 for these generators is as follows:

i) Designed to mechanically withstand continuous operation at runaway speed.


ii) These generators should be factory assembled that are shipped to the field as two integral
component parts, rotor and stator. So that assembled work at site is minimize.
iii) Class F insulation with class B temperature rise
iv) Self lubricated journal type maintenance -free pedestal bearing
228
v) Open ventilation
vi) Fully assembled and dynamically balanced

Standard BHEL generators confirming to the IEC standards are given in table 9.2.

9.5.2 Type of Generators

There are basically two types of alternating current generator: synchronous and asynchronous (or
induction) generators. The choice of the type to be used depends on the characteristics of the grid to which
the generator will be connected and also on the generators operational requirements.

Synchronous generators are used in the case of stand alone schemes (isolated networks). In case of weak
grids where the unit may have significant influence on the network synchronous generator are used. Salient
pole machines or cylindrical rotor machines are specified.

For grid connected schemes both types of generator can be used. In case grid is weak; Induction generators
may be used if there are two units, one of the unit can be synchronous so that in case of grid failure; supply
could still be maintained. Unit size be limited to 250 kW. In case of stronger grids induction generators up
to a 2000 kW or even higher have been used.

Before making a decision on the type of generator to be used, it is important to take the following points
into consideration:

- A synchronous generator can regulate the grid voltage and supply reactive power to the network. It
can therefore be connected to any type of network.
- An induction generator has a simpler operation, requiring only the use of a tachometer to couple it to
the grid as the machine is coupled to the grid there is a transient voltage drop, and once coupled to the
grid the generator absorbs reactive power from it. Where the power factor needs to be improved, a
capacitor bank will be necessary. The efficiency of an asynchronous generator is generally lower than
that of a synchronous one.

UNDP/World Bank Energy Sector Management Assistance Programme (ESMAP) funded a large number
of mini hydro developments on irrigation dams and canal drop in India with Induction generators.
Induction (asynchronous) generators, (essentially induction motors) which are driven at slightly above
synchronous speed, were specified for all schemes in the range 350 kW to 3500 kW. The primary function
of the irrigation based mini-hydro schemes was to provide energy to the remote sections of the grid. Hence,
induction generators, which require no separate excitation source since they draw magnetizing current from
the grid, were considered to be appropriate. The operating speed of induction generators was specified. The
difference between the rotating speeds of the turbine and generator were used to establish the specification
for speed increasing mechanisms. The goal was to keep the speed of the turbines as high as possible and to
minimize the gearbox ratio by maintaining the lowest feasible speed for the generators (See also chapter
13).

Two typical schemes 1500 kW (2 x 750 kW) at Narangwal in Punjab and proposed Lower Bhawani Project
in Tamilnadu ALT II 7000 KW (2 x 3.5 MW) (as per ESMAP Report) each with induction generators
and capacitor bank installation is shown in figure 9.9& figure 9.10.

Table 9.2 STANDARD SHP GENERATORS MANUFACTURED BY M/S BHEL INDIA Ltd. (*)

A. SHP

S. Rating Speed in RPM


No. in kW 300 333.3 375 426 500 600 750 1000 1500
1. 500 230M20 230M20 183M20 183M20 145M20 145M20 145M20 145M20 132M25
2. 1000 230M25 230M25 183M25 183M25 183M25 145M50 145M38 145M38 132M50
3. 1500 230M35 230M35 183M50 183M50 183M50 145M75 145M57 145M57 132M50
4. 2000 230M45 230M45 183M70 183M70 183M60 145M75 145M57 145M75 132M50
229
5. 2500 230M70 230M70 230M60 183M70 183M60 203M70 145M75 145M75 132M100
6. 3000 230M70 230M70 230M50 254M50 254M40 203M70 203M50 145M100 132M100
7. 3500 230M90 230M70 230M60 254M50 254M50 203M70 203M50 145M100 132M100
8. 4000 230M90 230M90 230M80 254M65 254M50 203M95 203M70 145M100 -
9. 4500 230M90 230M90 230M80 230M65 254M50 203M95 203M70 - -
10. 5000 230M90 230M90 230M80 230M65 254M50 203M95 203M70 - -

B. Mini Micro: generators 200-500 kW; speed 300 to 1500 RPM; power factor 0.67 lag.; Voltage 415 to 11
kV
(*)
A. M. Gupta BHEL, Bhopal - Small Hydro Generators International course on technology selection for
small hydro power development at Alternate Hydro Energy Centre (AHEC) during Feb. 18-28, 2003
Merits and demerits of synchronous and induction generator is given in table 9.3.

Table 9.3: Merits & Demerits Synchronous V/S Induction Generators


S. No. Item Syn. Generator Ind. Generator
1 Rotor construction Salient pole type Squirrel cage type
2 Excitation Required Not required
3 Isolated operation Possible Not possible
4 Stability To be maintained by excitation control No problem
5 Maintenance More because of excitation & control Less because of squirrel case rotor
equipments
6 Efficiency High Low
7 Inertia High Low
8 Cost High Low
9 Power factor Adjustable by excitation control Not adjustable determined by load
10 Suitability for highly Ideal Not suitable
fluctuating loads
11 Loads Highly capacitive Only inductive
12 Voltage variation Possible Not possible

Climatic conditions (ambient temperature, altitude, humidity) can affect the choice of the class of insulation
level and temperature rises.
The cooling system of the generator should be evaluated. In the case where heat from the generator is
expelled into the powerhouse sufficient power house ventilation should be provided.
If necessary, a braking system (either air or oil operated) should be considered.
9.5.3 Selection and Mechanical Characteristics

Small hydro up to 5 MW is generally category-2 generators. These generators are factory assembled that
are shipped to the field as two integral component parts, rotor and stator.

9.5.3.1 Vertical/Horizontal Configuration

With all turbines, a vertical or horizontal configuration is possible. The orientation becomes a function of
the turbine selection and of the power plant structural and equipment costs for a specific layout. As an
example, the Francis vertical unit will require a deeper excavation and higher power plant structure. A
horizontal machine will increase the width of the power plant structure yet decrease the excavation and
overall height of the unit. It becomes apparent that generator orientation and setting are governed by
compatibility with turbine selection and an analysis of overall plant costs.
230
GRID

415V 400A
400A

ACB
1250A
OUTDOOR VCB 630A

400A
OL RELAY

INDOOR VCB 630A 415V 400kVAR 415V 400kVAR

MAIN TRANSFORMER
2500kVA 415/11kV

ACB
2500A
415V 4000A

1 2 3 4 5 6 7 8
ACB
2000A CAPACITOR BANK-1 CAPACITOR BANK-2
1 CAPACITOR FEEDER 1 100kVAR 5 CAPACITOR FEEDER 5 100kVAR
2 CAPACITOR FEEDER 2 100kVAR 6 CAPACITOR FEEDER 6 100kVAR
3 CAPACITOR FEEDER 3 100kVAR 7 CAPACITOR FEEDER 7 100kVAR
4 CAPACITOR FEEDER 4 100kVAR 8 CAPACITOR FEEDER 8 100kVAR
G1 750 Kw G2
CAPACITOR

Fig, 9.9: Narangwal SHP with Induction Generators and capacitor Bank

Fig.9.10: Lower Bhavani Project ALT II (ESMAP Study)


(Source: ESMAP)

231
9.5.3.2 Speed (rpm): The speed of a generator is established by the turbine speed. The hydraulic turbines should
determine the turbine speed for maximum efficiency corresponding to an even number of generator poles.
Generator dimensions and weights vary inversely with the speed. For a fixed value of power a decrease in
speed will increase the physical size and cost of generators. Low head turbine can be connected either
directly to the generator or through a speed increaser. The speed increaser would allow the use of a higher
speed generator, typically 600, 750 or 1000 (1500) r/min, instead of a generator operating at turbine speed.
The choice to utilize a speed increaser is an economic decision. Speed increasers lower the overall plant
efficiency by about 1% for a single gear increaser and about 2% for double gear increaser. (The
manufacturer can supply exact data regarding the efficiency of speed increasers). This loss of efficiency
and the cost of the speed increaser must be compared to the reduction in cost for the smaller generator. It is
recommended that speed increaser option should not be used for unit sizes above 5 MW capacity.

9.5.3.3 Dimension

Three factors affect the size of generator. These are orientation, kVA requirements and speed. The turbine
choice dictates all three of these factors for the generator.
The size of the generator for a fixed kVA varies inversely with unit speed. This is due to the requirements
for more rotor field poles to achieve synchronous speed at lower rpm.
9.5.3.4 Over speed Withstand

In the interest of safety, units with synchronous generators are designed to withstand continuous runaway
conditions.

9.5.3.5 Guide and Thrust Bearings

The shaft system is designed to minimize the number of bearings. It is essential to study the turbine and
generator bearings as systems. The choice is between journal, ball or roller bearings, attention should be
given to their ability to withstand vibrations, eddy currents and runaway conditions.

If the unit size is small and for reasons of simplicity, the use of self-lubricating bearings should be
preferred.

9.3.5.6 Braking System

If necessary braking system (mostly oil operated) is used.

9.5.4 Ratings and Electrical Characteristics

9.5.4.1 kW Rating: The kilowatt rating of the generator should be compatible with the kW rating of the turbine.
The most common turbine types are Francis, fixed blade propeller, and adjustable blade propeller (Kaplan).
Each turbine type has different operating characteristics and imposes a different set of generator design
criteria to correctly match the generator to the turbine. For any turbine type, however, the generator should
have sufficient continuous capacity to handle the maximum kW available from the turbine at 100-percent
gate without the generator exceeding its rated nameplate temperature rise. In determining generator
capacity, any possible future changes to the project, such as raising the forebay (draw down) level and
increasing turbine output capability, should be considered.

In a variable head power plant the turbine output may vary depending upon available head. In general the
generator is rated for turbine output at rated head.

9.5.4.2 kVA Rating and power factor: kVA and power factor is fixed by consideration of location of the power
plant with respect to load centre. These requirements include a consideration of the anticipated load, the
electrical location of the plant relative to the power system load centers, the transmission lines, substations,
and distribution facilities involved.

9.5.4.3 Frequency and Number of Phases: In India standard frequency is 50 cycles, 3 phase power supply.

232
9.5.4.4 Generator Terminal Voltage: Generator terminal voltage is kept as high as economically feasible.
Generators of less than 5000 kVA are designed for 6.6 kV, 3.3 kV or 415 volts depending upon
requirement of generator WR2 or generator reactance. Economical terminal voltage for small hydro
generators recommended by CBI & P (publication no. 280 2001) and AHEC/MNRE guidelines are as
follows:

CBI & P Publication No. 280 (Economical) AHEC/MNRE Guidelines

Up to 750 kVA 415 volts Up to 400 kW (or kVA) 415 volts


751 2500 kVA 3.3 kV 401 2500 kW (or kVA) 3.3 kV
2501 5000 kVA 6.6 kV 2501 5000 kW (or kVA) 6.6 kV
Above 5000 kVA 11 kV Above 5000 kW (or kVA) 11 kV

Preferred voltage rating of generator as per IEC 60034-1 is as follows:

3.3 kV - Above 150 kW (or kVA)


6.6 kV - Above 800 kW (or kVA)
11 kV - Above 2500 kW (or kVA)

9.5.4.5 Stator Winding Connection: Star, stator winding connection are providing for both grounded or
ungrounded operation and six terminal (3 on line side and 3 on neutral side) are brought out, except for
small generators when only one neutral is brought for ground connections.
9.5.4.6 Excitation Voltage: Rated generator rotor voltage is specified by the manufacturer, based on the rotor
winding resistance and the excitation current required for full load operation at rated voltage and power
factor, including suitable margin. Ceiling voltage is as agreed upon by the manufacturer and purchaser.
Standard voltage of excitation system are 62.5, 125, 150, 250 V DC.

9.5.5 Insulation and Temperature Rise

9.5.5.1 Synchronous Generators

a) Stator:
Class F insulation level and Class B temperature rises are recommended. The American practice is
to provide Class H insulation with a temperature of not more than 80oC.

b) Rotor :
The insulation level should normally be Class-F and temperature rises Class-B.

9.5.5.2 Asynchronous (Induction) Generator

a) Stator
Class F insulation level and Class B temperature rises are recommended.

b) Rotor
Squirrel cage construction, Class F insulation and Class B temperature rises are recommended.
These units should be designed to withstand continuous runaway conditions.

9.5.6 Typical Characteristics

Typical Technical Particulars and characteristics of some SHP generators as installed in India are given in
table 9.4.

233
Table 9.4

SHP Projects Remarks


Awapan Sebari SHP Kitpi SHP
(2 x 250 kW) (2 x 500 kW) 2 x 1500 KW)
Type Salient pole Cylindrical pole Cylindrical rotor
Operation Isolated/grid connected Grid connected Grid connected Grid connected
Configuration Horizontal Vertical Horizontal Sebari SHP has siphon
intake
Rating (kW) 250 500 1500
Voltage (volts) 415 415 3.3 kV
Rated power factor 0.8 Lag 0.85 0.8
Speed rpm 1500 750 600
Runaway Speed/withstand in minutes 2700/15 min 2175/30 min 1080/15 min
Frequency (Hz) 50 50 50
SCR 1.0 0.8 1.03
Insulation Class F H F
Temp. rise Class B Class B Class B
Stator by res. 800C 1000C 800C
Rotor by res. 800C 1100C 800C
Line charging
Noise 90 dB
Vibration IS: 12065
Waveform IS: 4722
Efficiencies at rated pf. 93.40 % 95.10% 94.5%
Excitation Brushless (thyristor) static
AVR yes Automatic voltage
regulator
APFR yes Automatic power factor
regulator

9.6 Micro Hydro

Synchronous generators are generally used. Generators may be selected in accordance with quality standard
issued by AHEC extracts enclosed as Annexure 2. These generators are self excited and factory assembled
and classified as category-1 generator in American Practice. They are shipped to site completely assembled
depending on the rpm selected, unit speed/weights and method of transportation to site. In case of isolated
units, small capacity Induction generators with variable capacitor bank may be used up to a capacity of
about 50 kW especially if there is no or insignificant Induction motor load i.e. less than about 20%.

9.7 Generator Efficiencies

The efficiency of an electrical generator is defined as the ratio of output power to input power. Typical
Efficiency values for some generators are given in table 9.4. There are five major losses associated with an
electrical generator. Various test procedures are used to determine the magnitude of each loss. Two classes
of losses are fixed and therefore independent of load. These losses are (1) windage and friction (2) core
loss. The variable losses are (3) field copper loss, (4) armature copper loss and (5) stray loss or load loss.

Windage and friction loss is affected by the size and shape of rotating parts, fan design, bearing design and
the nature of the enclosure. Core loss is associated with power needed to magnetize the steel core parts of
the rotor and stator. Field copper loss represents the power losses through the dc resistance of the field.
Similarly, the armature copper loss is calculated from the dc resistance of the armature winding. Stray loss
for load loss is related to armature current and its associated flux. Typical values for efficiency range from
91 to 98%. This efficiency value is representing throughout the whole loading range of a particular
machine; i.e., the efficiency is approximately the same at load or at load. Typical efficiencies of some
SHP generators as installed is given in table 9.4.

234
CHAPTER 9: ANNEXURE-I

CENTRAL ELECTRICITY AUTHORITY (GRID STANDARDS) REGULATIONS-2006


(ABSTRACTS)

1. Short Title, Commencement and Interpretation

a) These regulations may be called the Central Electricity Authority (Grid Standards) Regulations, 2006
framed as per provisions under section 34, Section 73(d) and section 177(2) (a) of the Electricity Act,
2003.
b) These regulations shall come into force on the date of their publication in the official Gazette.
c) Grid Standards for Operation and Maintenance of Transmission Lines as prescribed by the Authority
are given in the "Schedule" appended to these Regulations.
d) These regulations shall be reviewed by the Authority in consultation with all the stake holders as and
when considered necessary.

2. Definitions

In these Regulations, unless the context otherwise requires;

a) "Act" means the Electricity Act, 2003.


b) Appropriate Load Despatch Centre" means the National Load Despatch Centre (NLDC),
Regional Load Despatch Centre (RLDC) or State Load Despatch Centre (SLDC) or Area Load
Despatch Centre as the case may be.
c) Area Load Despatch Centre" means the centre as established by the state for load Despatch &
control in a particular area of the state.
d) Bulk consumer" means a consumer who avails supply at voltage of 33 kV or above.
e) Disaster management is the mitigation of the impact of a major breakdown on the system and
bringing about restoration in the shortest possible time.
f) Emergency Restoration System" A system comprising transmission towers/ structures of modular
construction complete with associated components viz. insulators, hardware fittings, accessories,
foundation plates, guys, anchors, installation tools etc. to facilitate quick restoration of
damaged/failed transmission line towers/ sections.
g) Islanding Scheme" is a scheme for separation of the grid into two or more independent systems
as a last resort with a view to save healthy portion of the grid at the time of the grid disturbance.
h) Standards" means "Grid Standards for Operation and Maintenance of Transmission Lines" set
forth in the Schedule appended to these Regulations.
i) Transient stability" means the ability of all the elements in the network to remain in synchronism
following abrupt change in operating conditions like tripping of a feeder, tripping of generating
unit, sudden application of a load and network switching etc.
j) User" means a person such as a Generating Company including captive generating plant or
Transmission Licensee other than the Central Transmission Utility (CTU) and State Transmission
Utility (STU), Distribution Licensee or Bulk Consumer whose electrical plant is connected to the
Grid at voltage level 33kV and above.
k) "Voltage Unbalance" is defined as the deviation between highest and lowest line voltage divided
by Average line Voltage of the three phases.

The words and expressions used and not defined in these Regulations but defined in the Electricity Act,
2003 shall have the meaning assigned to them in the said Act.

235
Schedule Grid Standards for Operation and Maintenance
of Transmission Lines

1. Frequency
The standard frequency of system operation is 50 Hz and all efforts shall be made to operate at frequency
close to nominal as possible. The frequency shall not be allowed to go beyond the range 49.0 to 50.5 Hz,
except during the transient period accompanying tripping or connection of load.

2. Voltage
The steady state voltage shall be maintained within/the, limits given below:

Nominal System Voltage kV rms Voltage Variation


765 +/- 3%
400 +/- 3%
220 +/- 5%
132 and below +/- 10%

Temporary over voltage due to sudden load rejection shall be within the limits specified below:

Nominal System Voltage kVrms Phase to Neutral Voltage kV peak


765 914
400 514
220 283
132 170

For the voltage level below 132 kV, the voltage variation limits as given in (2) above shall be decided by
the State Commission in the respective State Grid Code.

3. Voltage Unbalance
The maximum permissible values of voltage unbalance shall be as under:
Nominal System Voltage kVrms Voltage Unbalance %
765 and 400 1.5%
220 2%
132 3%

i) Bulk consumers shall ensure balanced load during operation.

ii) Low Voltage Single phase loads shall be balanced periodically at the distribution transformer by
Distribution licensees.

4. Protection Standards

i) The Transmission Licensee and Users shall provide standard protection systems having the
required reliability, selectivity, speed and sensitivity to isolate the faulty equipment and protect all
components from any type of faults, within the specified fault clearance time. Protection
coordination shall be done by the RFC.

ii) Fault Clearance Time:


The maximum fault clearance times are as given below:

Nominal System Voltage kVrms Maximum Time ( in milliseconds)


765 and 400 100
220 and 132 160
iii) In the event of non clearance of the fault by a circuit breaker within the time limit prescribed in 4
(ii) above the Breaker Fail Protection shall initiate tripping of all other breakers in the concerned
bus-section to clear the fault in next 200 milliseconds.

236
5. Criteria for System Security

The following minimum security criterion shall be followed for operation and maintenance planning of the
elements of the grid:

The Grid System shall be capable of withstanding one of the following contingencies without experiencing
loss of stability:

(a) Outage of one single largest generating unit of the system or


(b) Outage of a 132 kV Double circuit line or
(c) Outage of a 220 kV Double circuit line or
(d) Outage of a 400 kV Single circuit line or
(e) Outage of a 400 kV Single circuit line with series compensation or
(f) Outage of 765 kV Single circuit line without series compensation or
(g) Outage of one pole of HVDC Bipolar line or
(h) Outage of an Interconnecting Transformer

6. Transient Stability

Under any one of the following contingencies the system shall remain stable and sustain integrity (i.e., no
generator shall lose synchronism and no part shall get isolated from the rest of the system):

a) Tripping of a single largest generating unit or


b) Transient ground fault in one phase of a 765 kV Single Circuit Line close to the bus or
c) A sustained single phase to ground fault in 400 kV single circuit line followed by 3 pole opening of
the faulted line or
d) A sustained fault in one circuit of a 400 kV Double Circuit Line when both circuits were in service
in the pre-contingency period or
e) A transient single phase to ground fault in one circuit of a 400 kV Double Circuit Line when the
second circuit is already under outage or
f) A three-phase sustained fault in a 220 kV or 132 kV or
g) A sustained fault in one pole of HVDC bipolar in a HVDC Converter Station.

7. Harmonics

The voltage wave-form quality shall be maintained at all points in the Grid.

i) In this Standard Harmonic Content limits are stipulated as follows:


Total Harmonic Distortion = VTHD (expressed as percentage)
n = 40
Vn 2
VTHD =
n =2 V1
2
x 100

'I1 refers to fundamental frequency (50 Hz)


'n' refers to the harmonic of n*1 order (corresponding frequency is 50 x n Hz)
ii) Maximum Limits of total Harmonic Distortion

System Voltage Total Harmonic Individual Harmonic of any particular


Distortion Frequency
kVrms % %
765 1.5 1.0
400 2.0 1.5
220 2.5 2.0
132 3.0 2.0

This Standard shall come into force not later than five years from the date of the publication in the official
Gazette.

237
CAPTER 9: ANNEXURE -2

Generators: Extracts from Micro Hydro Standards issued by AHEC

1. Generator Special Requirement

Description Category (Installed Capacity in kW)


Category A Category B Category C
(Up to 10 kW) (Above10kW and up (Above 50 kW
to 50 kW) and up to 100
kW)
Synchronous/ Induction - Synchronous/ Induction Synchronous
Types Single Phase/ 3 phase 3 Phase 3 Phase
Terminal Voltage, frequency 240 V, 1 phase, 415 V 3 phase, 415 V, 3 phase,
50 Hz 50 Hz 50 Hz
Generator Make and Runaway Standard / Special generators designed to withstand against continuous
withstand runaway condition.
Insulation and Temperature Class F/H insulation and Class B Temperature rise
Rise

Notes

1. For efficiency of turbine, the performance curves of similar turbines manufactured by the bidder
(tested by independent institution) will be provided.

2. Generator will conform to IS: 4722 (2001) and single-phase induction generators to IS: 996
(1979).

3. Electric load controllers shall be type tested by an independent institution for adequacy, for
performance, surge protection, waveform deviation, electromagnetic interference, emissions of
radio noise.

4. Micro hydro for power generation category B & C should have the following provisions:-

(i) Parallel operation in local grids whenever available.


(ii) Parallel operation with main grid whenever extended.

5. Micro hydropower generating station category B & C having more than 1 unit shall have
following additional provisions:-

(i) Parallel operation between units at the station


(ii) The Governor/Load Controller, AVR should have adequate provision for adjusting the
Speed Droop and Voltage Droop for facilitating the Parallel Operation of the Units.

2. Synchronous Generator and Induction Motors as Generators

i. Brand. The brand and power rating of the generator or motor should be approved by the
manufacturer of the turbines and by the purchaser.
ii. Nameplate. The original manufacturers nameplate for the generator or motor must be retained.
New nameplates can be added but must not replace the originals.
iii. Over-rating. The power rating given on the original nameplate must be at least 10% more than
the scheme rated power.
iv. Generator voltage. The power house voltage is the voltage at the generator terminals with
powerhouse-consumer isolation switch in off position. This must be between the nominal national
voltage (415 V) and +10% of 415 V.
v. Generator rotational speeds to be selected shall be 1500 rpm (+slip) or lower. In cases of direct
coupling 750 rpm or 1000 rpm generators should be preferred.
238
3. Synchronous Generator

i. Frequency. The operating frequency should be between 47.5and 52.5 Hz.


ii. Pf. The power factor rating should be 0.8 when an Electronic Load Controller (ELC) is in use
except where all loads and the ELC present a unity power factor.
iii. Brushless generators shall be supplied with regulator (AVR). The unit proposed for
interconnection with grid shall have in addition automatic power factor Regulator (APFR) with
automatic change over from AVR to APFR when grid interconnection circuit breaker.
iv. The generator shall be capable of continuous withstand against runaway speed.

4. Induction Motor

i. Frequency. The frequency should be between 50 and 52.5 Hz. The frequency should be within
this range under all operating conditions, including minimum and maximum power output, zero
consumer load and worst-case consumer load power factor.
ii. The induction generator must be over-voltage protected to avoid excessive currents to flow
through the excitation capacitors and induction machine. A protection system is required that
disconnects all or some of the capacitors, to limit the currents flowing to below the limits for the
induction machine windings and the capacitors. Provide MCBs of suitable current rating in the
series with excitation capacitors.
iii. The generator shall be capable of continuous withstand against runaway speed.

5. Turbine/generator base-frame

i. The turbine and generator should be mounted on a single steel fabrication, the base frame, which
shall be set into or fixed to the powerhouse floor (separate fixings shall be avoided in order to
avoid tension stresses occurring in the concrete floor). This shall be fabricated from angle iron or
channel section. A base frame may be omitted if the turbine and generator are close-coupled, that
is, their own frames are rigidly connected to each others.
ii. The turbine and generator should be fixed securely to the base frame in a workshop before
installation to achieve correct positioning. This should avoid problems with bearing alignment and
belt tensions during operation. The runner must be easily removable on site.

6. Bearings

i. On larger machines, bearings must be selected and maintained to provide a service life of 10 years.
On smaller machines a service life of 5 years is acceptable.
ii. Bearings must be properly aligned, either by use of self-aligning types or by adjusting of the
bearing housings. There must never be more than two bearings on one shaft. Poor alignment will
cause bearing failure and will be evident in the first year of operation of the turbine. The
mandatory one-year warranty should be given to ensure that the manufacturer covers bearing
failure costs, and to ensure that correct alignment is established.
iii. With the bearing housing open, the bearing housing should be one third full of clean grease.

239
References

A. National and International Standards and Codes

Latest edition of the following standards are applicable.

IEC-34-2A-1972 - Rotating Electrical Machines


Methods for determining losses and efficiency of electrical machinery from tests
(excluding machines for traction vehicles
IEC-34-1: 1983 Rotating Electrical Machines, Rating and Performance
IEC-85-1987 - Classification of materials for the insulation of electrical
machines
IEC-34-5-1991 Classification of degrees of protection provided by enclosures for rotating
electrical machines (IP Code)
IEC-1116: 1992 Electro-Mechanical Equipment Guide for Small Hydro-electric Installation
IS-4722 1992 Rotating electrical machines
IS-325 1996 Three phase induction motor
IS-8789 1996 Values of performance characteristics for three phase induction
motors
IS: 12824-204 Type of duty and rating assigned to electrical machines
IEEE: C50-12 IEEE std. for salient pole 50 Hz and 60 Hz synchronous generator
Micro hydro Std. AHEC IIT Roorkee
SHP std. Standards, manual and guidelines by AHEC, IIT Roorkee

B. Other References

FLOYD, G. D. and SILLS, H.R. : The evolution of the modern water wheel generators in Canada AIEE
Transaction, April 1958, pp. 6-61.

THAPAR, O. D. : Unit Size at Dehar Power Plant CBI & P 44th Annual Session, Novernber 1972,
Publication No. 114, pp. 101-108

HALL, H.E. and SHANKSHAFT, G,: Developments in the stability characteristics of power systems of
England and wales. 32.05, CIGRE 1970 Session, 24 August, 2 September.

THAPAR, O.D.: Stability for developing EHV system CBI & P. forty third annual research session, June
1973, publication no. 121, pp. 22-30.

ELLINGSEN, HANS VIDAR and OBERLANDOR JANOS: Stability problems with EHV transmission
systems with special reference to large generators. Siemens publication Extra high voltage AC
transmission pp. 18-26

AGGARWAL, R. P. and SINHA, V. P. : Over-voltages study of EHV system under Beas project part-I-
dynamic overvoltage due to sudden load rejection Report of study development of electrical engineering,
Indian Institute of Technology , Kanpur

ATEZZE, M. SCHUMM; NISHIMURA, F.; NARAYANA, RAO, H.V.; DESHMUKH, B. V.; IYENGAR.
B.R.R. and KAR, K.W. : Koyna Earthquake of 11 December 1967 Report of Experts Committee.
UNESCO Sl. No. 1489 BMS LD set, September 1969.

THAPAR O. D. Characteristics of large hydro generators of Dehar Power Plant- Proceedings 2nd world
congress, International water resources Association, New Delhi, December 1975, page 17-24.

David M. Cleman 1999 Hydro plant electrical system HCL publication

UNDP/World Bank Energy Sector Management Assistance Programme (ESMAP) Mini Hydro
Development on irrigation Dams and canal Drops Pre-investment Study Volume I & II: 1991.

240

You might also like