You are on page 1of 176

1

THIRD DIVISION [G.R. No. 141833. March 26, 2003] arbitrable the issue of whether respondents take-over of some
work items had been intended to be a termination of the original
contract under Letter K of the Subcontract. It ruled likewise on
LM POWER ENGINEERING CORPORATION, petitioner,
two other issues: whether petitioner was liable under the
vs. CAPITOL INDUSTRIAL CONSTRUCTION GROUPS,
warranty clause of the Agreement, and whether it should
INC., respondent.
reimburse respondent for the work the latter had taken over. [15]

PANGANIBAN, J.:
Hence, this Petition.[16]

Alternative dispute resolution methods or ADRs -- like


The Issues
arbitration, mediation, negotiation and conciliation -- are
encouraged by the Supreme Court. By enabling parties to
resolve their disputes amicably, they provide solutions that are In its Memorandum, petitioner raises the following issues
less time-consuming, less tedious, less confrontational, and for the Courts consideration:
more productive of goodwill and lasting relationships. [1]
A
The Case
Whether or not there exist[s] a controversy/dispute between
Before us is a Petition for Review on Certiorari[2] under Rule petitioner and respondent regarding the interpretation and
45 of the Rules of Court, seeking to set aside the January 28, implementation of the Sub-Contract Agreement dated February
2000 Decision of the Court of Appeals[3] (CA) in CA-GR CV No. 22, 1983 that requires prior recourse to voluntary arbitration;
54232. The dispositive portion of the Decision reads as follows:
B
WHEREFORE, the judgment appealed from is REVERSED and SET
ASIDE. The parties are ORDERED to present their dispute to In the affirmative, whether or not the requirements provided in
arbitration in accordance with their Sub-contract Article III [1] of CIAC Arbitration Rules regarding request for
Agreement. The surety bond posted by [respondent] is arbitration ha[ve] been complied with[.] [17]
[d]ischarged.[4]

The Courts Ruling


The Facts

The Petition is unmeritorious.


On February 22, 1983, Petitioner LM Power Engineering
Corporation and Respondent Capitol Industrial Construction
Groups Inc. entered into a Subcontract Agreement involving First Issue: Whether Dispute Is Arbitrable
electrical work at the Third Port of Zamboanga.[5]
Petitioner claims that there is no conflict regarding the
On April 25, 1985, respondent took over some of the work interpretation or the implementation of the Agreement. Thus,
contracted to petitioner.[6] Allegedly, the latter had failed to without having to resort to prior arbitration, it is entitled to
finish it because of its inability to procure materials.[7] collect the value of the services it rendered through an ordinary
action for the collection of a sum of money from respondent. On
the other hand, the latter contends that there is a need for prior
Upon completing its task under the Contract, petitioner arbitration as provided in the Agreement. This is because there
billed respondent in the amount of P6,711,813.90.[8] Contesting are some disparities between the parties positions regarding the
the accuracy of the amount of advances and billable extent of the work done, the amount of advances and billable
accomplishments listed by the former, the latter refused to accomplishments, and the set off of expenses incurred by
pay. Respondent also took refuge in the termination clause of respondent in its take-over of petitioners work.
the Agreement.[9] That clause allowed it to set off the cost of the
work that petitioner had failed to undertake -- due to
termination or take-over -- against the amount it owed the latter. We side with respondent. Essentially, the dispute arose
from the parties ncongruent positions on whether certain
provisions of their Agreement could be applied to the facts. The
Because of the dispute, petitioner filed with the Regional instant case involves technical discrepancies that are better left
Trial Court (RTC) of Makati (Branch 141) a Complaint [10] for the to an arbitral body that has expertise in those areas. In any
collection of the amount representing the alleged balance due it event, the inclusion of an arbitration clause in a contract does
under the Subcontract. Instead of submitting an Answer, not ipso facto divest the courts of jurisdiction to pass upon the
respondent filed a Motion to Dismiss, [11]alleging that the findings of arbitral bodies, because the awards are still judicially
Complaint was premature, because there was no prior recourse reviewable under certain conditions.[18]
to arbitration.

In the case before us, the Subcontract has the following


In its Order[12] dated September 15, 1987, the RTC denied arbitral clause:
the Motion on the ground that the dispute did not involve the
interpretation or the implementation of the Agreement and was,
therefore, not covered by the arbitral clause.[13] 6. The Parties hereto agree that any dispute or
conflict as regards to interpretation and
implementation of this Agreement which cannot be
After trial on the merits, the RTC [14] ruled that the take-over settled between [respondent] and [petitioner]
of some work items by respondent was not equivalent to a amicably shall be settled by means of arbitration x x
termination, but a mere modification, of the Subcontract. The x.[19]
latter was ordered to give full payment for the work completed
by petitioner.
Clearly, the resolution of the dispute between the parties
herein requires a referral to the provisions of their
Ruling of the Court of Appeals Agreement. Within the scope of the arbitration clause are
discrepancies as to the amount of advances and billable
On appeal, the CA reversed the RTC and ordered the accomplishments, the application of the provision on
referral of the case to arbitration. The appellate court held as termination, and the consequent set-off of expenses.
2
A review of the factual allegations of the parties reveals percent (10%) of the value of the approved
that they differ on the following questions: (1) Did a take- quantities. Any claims by [respondent] on [petitioner]
over/termination occur? (2) May the expenses incurred by may be deducted by [respondent] from the progress
respondent in the take-over be set off against the amounts it payments and/or retained amount. Any excess from
owed petitioner? (3) How much were the advances and billable the retained amount after deducting [respondents]
accomplishments? claims shall be released by [respondent] to
[petitioner] after the issuance of [the Ministry of Public
Works and Highways] of the Certificate of Completion
The resolution of the foregoing issues lies in the
and final acceptance of the WORK by [the Ministry of
interpretation of the provisions of the Agreement. According to
Public Works and Highways].
respondent, the take-over was caused by petitioners delay in
completing the work. Such delay was in violation of the
provision in the Agreement as to time schedule: xxxxxxxxx

G. TIME SCHEDULE D. IMPORTED MATERIALS AND EQUIPMENT

[Petitioner] shall adhere strictly to the schedule [Respondent shall open the letters of credit for the
related to the WORK and complete the WORK within importation of equipment and materials listed in
the period set forth in Annex C hereof. NO time Annex E hereof after the drawings, brochures, and
extension shall be granted by [respondent] to other technical data of each items in the list have
[petitioner] unless a corresponding time extension is been formally approved by [the Ministry of Public
granted by [the Ministry of Public Works and Works and Highways]. However, petitioner will still be
Highways] to the CONSORTIUM.[20] fully responsible for all imported materials and
equipment.
Because of the delay, respondent alleges that it took over
some of the work contracted to petitioner, pursuant to the All expenses incurred by [respondent], both in foreign
following provision in the Agreement: and local currencies in connection with the opening
of the letters of credit shall be deducted from the
Contract Prices.
K. TERMINATION OF AGREEMENT

xxxxxxxxx
[Respondent] has the right to terminate and/or take
over this Agreement for any of the following causes:
N. OTHER CONDITIONS
xxxxxxxxx
xxxxxxxxx
6. If despite previous warnings by [respondent],
[petitioner] does not execute the WORK in 2. All customs duties, import duties, contractors
accordance with this Agreement, or persistently taxes, income taxes, and other taxes that may be
or flagrantly neglects to carry out [its] required by any government agencies in connection
obligations under this Agreement.[21] with this Agreement shall be for the sole account of
[petitioner].[23]
Supposedly, as a result of the take-over, respondent
incurred expenses in excess of the contracted price. It sought to Being an inexpensive, speedy and amicable method of
set off those expenses against the amount claimed by petitioner settling disputes,[24] arbitration -- along with mediation,
for the work the latter accomplished, pursuant to the following conciliation and negotiation -- is encouraged by the Supreme
provision: Court. Aside from unclogging judicial dockets, arbitration also
hastens the resolution of disputes, especially of the commercial
kind.[25] It is thus regarded as the wave of the future in
If the total direct and indirect cost of completing the remaining
international civil and commercial disputes. [26] Brushing aside a
part of the WORK exceed the sum which would have been
contractual agreement calling for arbitration between the
payable to [petitioner] had it completed the WORK, the amount
parties would be a step backward.[27]
of such excess [may be] claimed by [respondent] from either of
the following:
Consistent with the above-mentioned policy of
encouraging alternative dispute resolution methods, courts
1. Any amount due [petitioner] from [respondent] at the time of
should liberally construe arbitration clauses. Provided such
the termination of this Agreement.[22]
clause is susceptible of an interpretation that covers the
asserted dispute, an order to arbitrate should be granted. [28] Any
The issue as to the correct amount of petitioners advances doubt should be resolved in favor of arbitration.[29]
and billable accomplishments involves an evaluation of the
manner in which the parties completed the work, the extent to
Second Issue:
which they did it, and the expenses each of them incurred in
connection therewith. Arbitrators also need to look into the
computation of foreign and local costs of materials, foreign and Prior Request for Arbitration
local advances, retention fees and letters of credit, and taxes
and duties as set forth in the Agreement. These data can be According to petitioner, assuming arguendo that the
gathered from a review of the Agreement, pertinent portions of dispute is arbitrable, the failure to file a formal request for
which are reproduced hereunder: arbitration with the Construction Industry Arbitration
Commission (CIAC) precluded the latter from acquiring
C. CONTRACT PRICE AND TERMS OF PAYMENT jurisdiction over the question. To bolster its position, petitioner
even cites our ruling in Tesco Services Incorporated v. Vera.
[30]
We are not persuaded.
xxxxxxxxx

Section 1 of Article II of the old Rules of Procedure


All progress payments to be made by [respondent] to
Governing Construction Arbitration indeed required the
[petitioner] shall be subject to a retention sum of ten
submission of a request for arbitration, as follows:
3
SECTION. 1. Submission to Arbitration -- Any party to a SO ORDERED.
construction contract wishing to have recourse to arbitration by
the Construction Industry Arbitration Commission (CIAC) shall THIRD DIVISION [G.R. No. 121171. December 29, 1998]
submit its Request for Arbitration in sufficient copies to the
Secretariat of the CIAC; PROVIDED, that in the case of ASSET PRIVATIZATION TRUST, petitioner, vs., COURT OF
government construction contracts, all administrative remedies APPEALS, JESUS S. CABARRUS, SR., JESUS S.
available to the parties must have been exhausted within 90 CABARRUS, JR., JAIME T. CABARRUS, JOSE MIGUEL
days from the time the dispute arose. CABARRUS, ALEJANDRO S. PASTOR, JR., ANTONIO
U. MIRANDA, and MIGUEL M. ANTONIO, as
Minority Stock Holders of Marinduque Mining and
Tesco was promulgated by this Court, using the foregoing Industrial Corporation, respondents.
provision as reference.
KAPUNAN, J.:
On the other hand, Section 1 of Article III of the new Rules
of Procedure Governing Construction Arbitration has dispensed The petition for review on certiorari before us seeks us to
with this requirement and recourse to the CIAC may now be reverse and set aside the decision of the Court of Appeals which
availed of whenever a contract contains a clause for the denied due course to the petition for certiorari filed by the Asset
submission of a future controversy to arbitration, in this wise: Privatization Trust (APT) assailing the order of the Regional Trial
Court (RTC) Branch 62, Makati City. The Makati RTCs order
upheld and confirmed the award made by the Arbitration
SECTION 1. Submission to CIAC Jurisdiction An arbitration clause Committee in favor of Marinduque Mining and Industrial
in a construction contract or a submission to arbitration of a Corporation (MMIC) and against the Government, represented
construction dispute shall be deemed an agreement to submit by herein petitioner APT for damages in the amount of P2.5
an existing or future controversy to CIAC jurisdiction, BILLION (or approximately P4.5 BILLION, including interest).
notwithstanding the reference to a different arbitration
Ironically, the staggering amount of damages was imposed
institution or arbitral body in such contract or submission. When
on the Government for exercising its legitimate right of
a contract contains a clause for the submission of a future
foreclosure as creditor against the debtor MMIC as a
controversy to arbitration, it is not necessary for the parties to consequence of the latters failure to pay its overdue and unpaid
enter into a submission agreement before the claimant may obligation of P22 billion to the Philippine National Bank (PNB)
invoke the jurisdiction of CIAC. and the Development Bank of the Philippines (DBP).

The foregoing amendments in the Rules were formalized


by CIAC Resolution Nos. 2-91 and 3-93.[31] The antecedent facts of the case

The difference in the two provisions was clearly explained


in China Chang Jiang Energy Corporation (Philippines) v. Rosal The development, exploration and utilization of the mineral
Infrastructure Builders et al.[32] (an extended unsigned deposits in the Surigao Mineral Reservation have been
Resolution) and reiterated in National Irrigation Administration v. authorized by Republic Act No. 1828, as amended by Republic
Court of Appeals,[33] from which we quote thus: Acts No. 2077 and 4167, by virtue of which laws, a
Memorandum of Agreement was drawn on July 3, 1968, whereby
Under the present Rules of Procedure, for a particular the Republic of the Philippines thru the Surigao Mineral
Reservation Board, granted MMIC the exclusive right to explore,
construction contract to fall within the jurisdiction of CIAC, it is
develop and exploit nickel, cobalt and other minerals in the
merely required that the parties agree to submit the same to
Surigao mineral reservation.[1] MMIC is a domestic corporation
voluntary arbitration Unlike in the original version of Section 1, engaged in mining with respondents Jesus S. Cabarrus, Sr. as
as applied in the Tesco case, the law as it now stands does not President and among its original stockholders.
provide that the parties should agree to submit disputes arising
from their agreement specifically to the CIAC for the latter to The Philippine Government undertook to support the
acquire jurisdiction over the same. Rather, it is plain and clear financing of MMIC by purchase of MMIC debenture and extension
that as long as the parties agree to submit to voluntary of guarantees. Further, the Philippine Government obtained a
arbitration, regardless of what forum they may choose, their firm, commitment from the DBP and/or other government
agreement will fall within the jurisdiction of the CIAC, such that, financing institutions to subscribed in MMIC and issue
even if they specifically choose another forum, the parties will guarantee/s for foreign loans or deferred payment arrangements
secured from the US Eximbank, Asian Development Bank, Kobe
not be precluded from electing to submit their dispute before
Steel, of amount not exceeding US$100 Million.[2]
the CIAC because this right has been vested upon each party by
law, i.e., E.O. No. 1008.[34] DBP approved guarantees in favor of MMIC and subsequent
requests for guarantees were based on the unutilized portion of
Clearly, there is no more need to file a request with the the Government commitment.Thereafter, the Government
extended accommodations to MMIC in various amounts.
CIAC in order to vest it with jurisdiction to decide a construction
dispute. On July 13, 1981, MMIC, PNB and DBP executed a Mortgage
Trust Agreement[3] whereby MMIC, as mortgagor, agreed to
The arbitral clause in the Agreement is a commitment on constitute a mortgage in favor of PNB and DBP as mortgagees,
the part of the parties to submit to arbitration the disputes over all MMICs assets, subject of real estate and chattel
mortgage executed by the mortgagor, and additional assets
covered therein. Because that clause is binding, they are
described and identified, including assets of whatever kind,
expected to abide by it in good faith. [35] And because it covers
nature or description, which the mortgagor may acquire whether
the dispute between the parties in the present case, either of in substitution of, in replenishment, or in addition thereto.
them may compel the other to arbitrate.[36]
Article IV of the Mortgage Trust Agreement provides for
Events of Default, which expressly includes the event that the
Since petitioner has already filed a Complaint with the RTC
MORTGAGOR shall fail to pay any amount secured by this
without prior recourse to arbitration, the proper procedure to enable
Mortgage Trust Agreement when due.[4]
the CIAC to decide on the dispute is to request the stay or
suspension of such action, as provided under RA 876 [the Article V of the Mortgage Trust Agreement prescribes in
Arbitration Law].[37] detail, and in addition to the enumerated events of defaults,
circumstances by which the mortgagor may be declared in
default, the procedure therefor, waiver of period to foreclose,
WHEREFORE, the Petition is DENIED and the assailed
authority of Trustee before, during and after foreclosure,
Decision AFFIRMED. Costs against petitioner. including taking possession of the mortgaged properties.[5]
4
In various request for advances/remittances of loans of 2. Submission. The parties hereby agree that (a) the controversy
huge amounts, Deeds of Undertakings, Promissory Notes, Loans in Civil Case No. 9900 shall be submitted instead to arbitration
Documents, Deeds of Real Estate Mortgages, MMIC invariably under RA 876 and (b) the reliefs prayed for in Civil Case No.
committed to pay either on demand or under certain terms the 9900 shall, with the approval of the Trial Court of this
loans and accommodations secured from or guaranteed by both Compromise and Arbitration Agreement, be transferred and
DBP and PNB. reduced to pure pecuniary/money claims with the parties
waiving and foregoing all other forms of reliefs which they
By 1984, DBP and PNBs financial exposure both in loans prayed for or should have payed for in Civil Case No. 9900.[13]
and in equity in MMIC had reached tremendous proportions, and
MMIC was having a difficult time meeting its financial
obligations. MMIC had an outstanding loan with DBP in the The Compromise and Arbitration Agreement limited the
amount of P13,792,607,565.92 as of August 31, 1984 and in the issues to the following:
amount of P8,789,028,249.38 as of July 15, 1984 or a total
Government exposure of Twenty Two Billion Six Hundred Sixty- 5. Issues. The issues to be submitted for the Committees
Eight Million Five Hundred Thirty-Seven Thousand Seven resolution shall be: (a) Whether PLAINTIFFS have the capacity or
Hundred Seventy and 05/100 (P22,668,537,770.05), Philippine the personality to institute this derivative suit in behalf of the
Currency.[6] Thus, a financial restructuring plan (FRP) designed to MMIC or its directors; (b) Whether or not the actions leading to,
reduce MMIC' interest expense through debt conversion to and including, the PNB-DBP foreclosure of the MMIC assets were
equity was drafted by the Sycip Gorres Velayo accounting firm. proper, valid and in good faith.[14]
[7]
On April 30, 1984, the FRP was approved by the Board of
Directors of the MMIC.[8] However, the proposed FRP had never
been formally adopted, approved or ratified by either PNB or This agreement was presented for approval to the trial
DBP.[9] court. On October 14, 1992, the Makati RTC, Branch 62, issued
an order, to wit:
In August and September 1984, as the various loans and
advances made by DBP and PNB to MMIC had become overdue
WHEREFORE, this Court orders:
and since any restructuring program relative to the loans was no
longer feasible, and in compliance with the directive of
Presidential Decree No. 385, DBP and PNB as mortgagees of 1. Substituting PNB and DBP with the Asset
MMIC assets, decided to exercise their right to extrajudicially Privatization Trust as party defendant.
foreclose the mortgages in accordance with the Mortgage Trust
Agreement.[10]
2. Approving the Compromise and Arbitration
The foreclosed assets were sold to PNB as the lone bidder Agreement dated October 6, 1992, attached
and were assigned to three newly formed corporations, namely, as Annex C of the Omnibus Motion.
Nonoc Mining Corporation, Maricalum Mining and Industrial
Corporation, and Island Cement Corporation. In 1986, these 3. Approving the Transformation of the reliefs prayed
assets were transferred to the Asset Privatization Trust (APT). [11] for [by] the plaintiffs in this case into pure
money claims; and
On February 28, 1985, Jesus S. Cabarrus, Sr., together with
the other stockholders of MMIC, filed a derivative suit against
DBP and PNB before the RTC of Makati, Branch 62, for 4. The Complaint is hereby DISMISSED.[15]
Annulment of Foreclosures, Specific Performance and Damages.
[12]
The suit, docketed as Civil Case No. 9900, prayed that the The Arbitration Committee was composed of retired
court: (1) annul the foreclosure, restore the foreclosed assets to Supreme Court Justice Abraham Sarmiento as Chairman, Atty.
MMIC, and require the banks to account for their use and Jose C. Sison and former Court of Appeals Justice Magdangal
operation in the interim; (2) direct the banks to honor and Elma as Members. On November 24, 1993, after conducting
perform their commitments under the alleged FRP; and (3) pay several hearings, the Arbitration Committee rendered a majority
moral and exemplary damages, attorneys fees, litigation decision in favor of MMIC, the pertinent portions of which read
expenses and costs. as follows:
In the course of the trial, private respondents and
petitioner APT, as successor of the DBP and PNBs interest in Since, as this Committee finds, there is no foreclosure at all was
MMIC, mutually agreed to submit the case to arbitration by not legally and validly done, the Committee holds and so
entering into a Compromise and Arbitration Agreement, declares that the loans of PNB and DBP to MMIC, for the
stipulating, inter alia: payment and recovery of which the void foreclosure sales were
undertaken, continue to remain outstanding and
NOW, THEREFORE, for and in consideration of the foregoing unpaid. Defendant APT as the successor-in-interest of PNB and
premises and the mutual covenants contain herein, the parties DBP to the said loans is therefore entitled and retains the right,
agreed as follows: to collect the same from MMIC pursuant to and based on the
loan documents signed by MMIC, subject to the legal and valid
defenses that the latter may duly and seasonably
1. Withdrawal and Compromise. The parties have agreed to interpose. Such loans shall, however, be reduced by the amount
withdraw their respective claims from the Trial Court and to which APT may have realized from the sale of the seized assets
resolve their dispute through arbitration by praying to the Trial of MMIC which by agreement should no longer be returned even
Court to issue a Compromise Judgment based on this if the foreclosure were found to be null and void.
Compromise and Arbitration Agreement.
The documentary evidence submitted and adopted by both
In withdrawing their dispute form the court and in choosing to parties (Exhibits 3, 3-B; Exhibits 100; and also Exhibit ZZZ) as
resolve it through arbitration, the parties have agreed that: their exhibits would show that the total outstanding obligation
due to DBP and PNB as of the date of foreclosure
(a) their respective money claims shall be reduced to purely is P22,668,537,770.05, more or less.
money claims; and
Therefore, defendant APT can, and is still entitled to, collect the
(b) as successor and assignee of the PNB and DBP interest in outstanding obligations of MMIC to PNB and DBP amounting
MMIC and the MMIC accounts, APT shall likewise succeed to the to P22,668.537,770.05, more or less, with interest thereon as
rights and obligations of PNB and DBP in respect of the stipulated in the loan documents from the date of foreclosure up
controversy subject of Civil Case No. 9900 to be transferred to to the time they are fully paid less the proportionate liability of
arbitration and any arbitral award/order against either PNB DBP as owner of 87% of the total capitalization of MMIC under
and/or DBP shall be the responsibility of, be discharged by and the FRP. Simply put, DBP shall share in the award of damages to,
be enforceable against APT, the partied having agreed to drop and in obligations of MMIC in proportion to its 87% equity in the
PNB and DBP from the arbitration. total capital stock of MMIC.
5
x x x. to the court having jurisdiction, (not necessarily with this
Honorable Court) for an order confirming the award;
As this Committee holds that the FRP is valid, DBPs equity in
MMIC is raised to 87%. So pursuant to the above provision of the 3. The issues submitted for arbitration have been limited to two:
Compromise and Arbitration Agreement, the 87% equity of DBP (1) propriety of the plaintiffs filing the derivative suit and (2) the
is hereby deducted from the actual damages regularity of the foreclosure proceedings. The arbitration award
of P19,486,118,654.00 resulting in the net actual damages sought to be confirmed herein far exceeded the issues
of P2,531,635,425.02 plus interest. submitted and even granted moral damages to one of the
herein plaintiffs;
DISPOSITION
4. Under Section 24 of Rep. Act 876, the Court must make an
order vacating the award where the arbitrators exceeded their
WHEREFORE, premises considered, judgment is hereby
powers, or so imperfectly executed them, that a mutual final
rendered:
and definite award upon the subject matter submitted to them
was not made.[17]
1. Ordering the defendant to pay to the Marinduque Mining and
Industrial Corporation, except the DBP, the sum
Private respondents filed a REPLY AND OPPOSITION dated
of P2,531,635,425.02 with interest thereon at the legal rate of
November 10, 1984, arguing that a dismissal of Civil case No.
six per cent (6%) per annum reckoned from August 3, 9, and 24,
9900 was merely a qualified dismissal to pave the way for the
1984, pari passu, as and for actual damages. Payment of these
submission of the controversy to arbitration, and operated
actual damages shall be offset by APT from the outstanding and
simply as a mere suspension of the proceedings. They denied
unpaid loans of the MMIC with DBP and PNB, which have not
that the Arbitration Committee had exceeded its powers.
been converted into equity. Should there be any balance due to
the MMIC after the offsetting, the same shall be satisfied from In an Order dated November 28, 1994, the trial court
the funds representing the purchase price of the sale of the confirmed the award of the Arbitration Committee. The
shares of Island Cement Corporation in the amount dispositive portion of said order reads:
of P503,000,000.00 held under escrow pursuant to the Escrow
Agreement dated April 22, 1988 or to such subsequent escrow
agreement that would supercede [sic] it pursuant to paragraph WHEREFORE, premises considered, and in the light of the
(9) of the Compromise and Arbitration Agreement; parties [sic] Compromise and Arbitration Agreement dated
October 6, 1992, the Decision of the Arbitration Committee
promulgated on November 24, 1993, as affirmed in a Resolution
2. Ordering the defendant to pay to the Marinduque Mining and dated July 26, 1994, and finally settled and clarified in the
Industrial Corporation, except the DBP, the sum Separate Opinion dated September 2, 1994 of Committee
of P13,000,000.00 as and for moral and exemplary Member Elma, and the pertinent provisions of RA 876,also
damages. Payment of these moral and exemplary damages shall known as the Arbitration Law, this Court GRANTS PLAINTIFFS
be offset by APT from the outstanding and unpaid loans of MMIC APPLICATION AND THUS CONFIRMS THE ARBITRATION AWARD,
with DBP and PNB, which have not been converted into AND JUDGMENT IS HEREBY RENDERED:
equity. Should there be any balance due to MMIC after the
offsetting, the same shall be satisfied from the funds
representing the purchase price of the sale of the shares of (a) Ordering the defendant APT to the Marinduque Mining and
Island Cement Corporation in the of P503,000,000.00 held under Industrial Corporation (MMIC, except the DBP, the sum
escrow pursuant to the Escrow Agreement dated April 22, 1988 of P3,811,757,425.00, as and for actual damages, which shall be
or to such subsequent escrow agreement that would supercede partially satisfied from the funds held under escrow in the
[sic] it pursuant to paragraph (9) of the Compromise and amount of P503,000,000.00 pursuant to the Escrow Agreement
Arbitration Agreement; dated April 22, 1988. The Balance of the award, after the escrow
funds are fully applied, shall be executed against the APT;

3. Ordering the defendant to pay to the plaintiff, Jesus Cabarrus,


Sr., the sum of P10,000,000.00, to be satisfied likewise from the (b) Ordering the defendant to pay to the MMIC, except the DBP,
funds held under escrow pursuant to the Escrow Agreement the sum of P13,000,000.00 as and moral and exemplary
dated April 22, 1988 or to such subsequent escrow agreement damages;
that would supercede it, pursuant to paragraph (9) of the
Compromise and Arbitration Agreement, as and for moral (c) Ordering the defendant to pay to Jesus S. Cabarrus, Sr., the
damages; and sum of P10,000,000.00 as and for moral damages; and

4. Ordering the defendant to pay arbitration costs. (d) Ordering the defendant to pay the herein
plaintiffs/applicants/movants the sum of P1,705,410.22 as
This Decision is FINAL and EXECUTORY. arbitration costs.

IT IS SO ORDERED.[16] In reiteration of the mandates of Stipulation No. 10 and


Stipulation No. 8 paragraph 2 of the Compromise and Arbitration
Agreement, and the final edict of the Arbitration Committees
Motions for reconsiderations were filed by both parties, but decision, and with this Courts Confirmation, the issuance of the
the same were denied. Arbitration Committees Award shall henceforth be final and
executory.
On October 17, 1994, private respondents filed in the same
Civil Case No. 9900 an Application/Motion for Confirmation of
Arbitration Award. Petitioner countered with an Opposition and SO ORDERED.[18]
Motion to Vacate Judgment raising the following grounds:
On December 27, 1994, petitioner filed its motion for
1. The plaintiffs Application/Motion is improperly filed with this reconsideration of the Order dated November 28, 1994. Private
branch of the Court, considering that the said motion is neither respondents, in turn, submitted their reply and opposition
a part nor the continuation of the proceedings in Civil Case No. thereto.
9900 which was dismissed upon motion of the parties. In fact,
the defendants in the said Civil Case No. 9900 were the On January 18, 1995, the trial court handed down its order
Development Bank of the Philippines and the Philippine National denying APTs motion for reconsideration for lack of merit and for
Bank (PNB); having been filed out of time.The trial court declared that
considering that the defendant APT through counsel, officially
and actually received a copy of the Order of this Court dated
2. Under Section 22 of Rep. Act 876, an arbitration under a November 28, 1994 on December 6, 1994, the Motion for
contract or submission shall be deemed a special proceedings Reconsideration thereof filed by the defendant APT on
and a party to the controversy which was arbitrated may apply December 27, 1994, or after the lapse of 21 days, was clearly
6
filed beyond the 15-day reglementary period prescribed or THE COURT OF APPEALS ERRED IN NOT TREATING
provided for by law for the filing of an appeal from final orders, PETITIONER APTS PETITION FOR CERTIORARI AS AN
resolutions, awards, judgments or decisions of any court in all APPEAL TAKEN FROM THE ORDER CONFIRMING THE
cases, and by necessary implication for the filling of a motion for AWARD
reconsideration thereof.

On February 7, 1995, petitioner received private V


respondents motion for Execution and Appointment of Custodian
of Proceeds of Execution dated February 6, 1995. THE COURT OF APPEALS ERRED IN NOT RULING ON THE
LEGAL ISSUE OF WHEN TO RECKON THE COUNTING OF THE
Petitioner thereafter filed with the Court of Appeals a
PERIOD TO FILE A MOTION FOR RECONSIDERATION.[21]
special civil action for certiorari with temporary restraining order
and/or preliminary injunction dated February 13, 1996 to annul
and declare as void the Orders of the RTC-Makati dated The petition is impressed with merit.
November 28, 1994 and January 18, 1995 for having been
issued without or in excess of jurisdiction and/or with grave I
abuse of discretion.[19] As ground therefor, petitioner alleged The RTC of Makati, Branch 62, did not have jurisdiction to confirm the arbitral award
that:
The use of the term dismissed is not a mere semantic
I THE RESPONDENT JUDGE HAS NOT VALIDLY ACQUIRED
imperfection. The dispositive portion of the Order of the trial
JURISDICTION MUCH LESS, HAS THE COURT AUTHORITY, TO
court dated October 14, 1992 stated in no uncertain terms:
CONFIRM THE ARBITRAL AWARD CONSIDERING THAT THE
ORIGINAL CASE, CIVIL CASE NO. 9900, HAD PREVIOUSLY BEEN 4. The Complaint is hereby DISMISSED.[22]
DISMISSED.
The term dismiss has a precise definition in law. To dispose of an
II THE RESPONDENT JUDGE COMMITTED GRAVE ABUSE OF action suit, or motion without trial on the issues
DISCRETION AND ACTED WITHOUT OR IN EXCESS OF involved. Conclude, discontinue, terminate, quash.[23]
JURISDICTION, IN ISSUING THE QUESTIONED ORDERS
CONFIRMING THE ARBITRAL AWARD AND DENYING THE MOTION Admittedly the correct procedure was for the parties to go
FOR RECONSIDERATION OF ORDER OF AWARD. back to the court where the case was pending to have the award
confirmed by said court.However, Branch 62 made
III THE RESPONDENT JUDGE GROSSLY ABUSED HIS DISCRETION the fatal mistake of issuing a final order dismissing the
AND ACTED WITHOUT OR IN EXCESS OF AND WITHOUT case. While Branch 62 should have merely suspended the case
JURISDICTION IN RECKONING THE COUNTING OF THE PERIOD TO and not dismissed it,[24] neither of the parties questioned said
FILE MOTION FOR RECONSIDERATION, NOT FROM THE DATE OF dismissal. Thus, both parties as well as said court are bound by
SERVICE OF THE COURTS COPY CONFIRMING THE AWARD, BUT such error.
FROM RECEIPT OF A XEROX COPY OF WHAT PRESUMABLY IS THE
OPPOSING COUNSELS COPY THEREOF.[20] It is erroneous then to argue, as private respondents do,
that petitioner APT was charged with the knowledge that the
On July 12, 1995, the Court of Appeals, through its fifth case was merely stayed until arbitration finished, as again, the
Division denied due course and dismissed the petition order of Branch 62 in very clear terms stated that the complaint
for certiorari. was dismissed. By its own action, Branch 62 had lost jurisdiction
over the vase. It could not have validly reacquired jurisdiction
Hence, the instant petition for review
over the said case on mere motion of one of the parties. The
on certiorari imputing to the Court of Appeals the following
Rules of Court is specific on how a new case may be initiated
errors.
and such is not done by mere motion in a particular branch of
the RTC. Consequently, as there was no pending action to speak
ASSIGNMENT OF ERRORS of, the petition to confirm the arbitral award should have been
filed as a new case and raffled accordingly to one of the
branches of the Regional Trial Court.
I
II
THE COURT OF APPEALS ERRED IN NOT HOLDING THAT Petitioner was not estopped from questioning the jurisdiction of Branch 62 of the RTC of Makati.
THE MAKATI REGIONAL TRIAL COURT, BRANCH 62 WHICH
HAS PREVIOULSY DISMISSED CIVIL CASE NO. 9900 HAD The Court of Appeals ruled that APT was already estopped
LOST JURISDICTION TO CONFIRM THE ARBITRAL AWARD to question the jurisdiction of the RTC to confirm the arbitral
UNDER THE SAME CIVIL CASE AND IN NOT RULING THAT award because it sought affirmative relief in said court by asking
THE APPLICATION FOR CONFIRMATION SHOULD HAVE BEEN that the arbitral award be vacated.
FILED AS A NEW CASE TO BE RAFFLED OFF AMONG THE
DIFFERENT BRANCHES OF THE RTC. The rule is that Where the court itself clearly has no
jurisdiction over the subject matter or the nature of the action,
II the invocation of this defense may de done at any time. It is
neither for the courts nor for the parties to violate or disregard
that rule, let alone to confer that jurisdiction, this matter being
THE COURT OF APPEALS LIKEWISE ERRED IN HOLDING legislative in character.[25] As a rule the, neither waiver nor
THAT PETITIONER WAS ESTOPPED FROM QUESTIONING estoppel shall apply to confer jurisdiction upon a court barring
THE ARBITRATION AWARD, WHEN PETITIONER highly meritorious and exceptional circumstances.[26] One such
QUESTIONED THE JURISDICTION OF THE RTC-MAKATI, exception was enunciated in Tijam vs. Sibonghanoy,[27] where it
BRANCH 62 AND AT THE SAME TIME MOVED TO VACATE was held that after voluntarily submitting a cause and
THE ARBITRAL AWARD. encountering an adverse decision on the merits, it is too late for
the loser to question the jurisdiction or power of the court."
III Petitioners situation is different because from the outset, it
has consistently held the position that the RTC, Branch 62 had
THE COURT OF APPEALS ERRED IN NOT HOLDING THAT no jurisdiction to confirm the arbitral award; consequently, it
THE RESPONDENT TRIAL COURT SHOULD HAVE EITHER cannot be said that it was estopped from questioning the RTCs
DISMISSED/DENIED PRIVATE RESPONDENTS jurisdiction. Petitioners prayer for the setting aside of the
MOTION/PETITION FOR CONFIRMATION OF ARBITRATION arbitral award was not inconsistent with its disavowal of the
AWARD AND/OR SHOULD HAVE CONSIDERED THE MERITS courts jurisdiction.
OF THE MOTION TO VACATE ARBITRAL AWARD.
III
Appeal of petitioner to the Court of Appeals thru certiorari under Rule 65 was proper.
IV
The Court of Appeals in dismissing APTs petition
for certiorari upheld the trial courts denial of APTs motion for
7
reconsideration of the trial courts order confirming the arbitral rescinded. Additionally, under Sections 24 and 25, of the
award, on the ground that said motion was filed beyond the 15- Arbitration Law, there are grounds for vacating, modifying or
day reglementary period; consequently, the petition rescinding an arbitrators award. Thus, if and when the factual
for certiorari could not be resorted to as substitute to the lost circumstances referred to in the above-cited provisions are
right of appeal. present, judicial review of the award is properly warranted.

We do not agree.
Accordingly, Section 20 of R.A. 876 provides:
Section 29 of Republic Act No. 876,[28] provides that:
SEC. 20. Form and contents of award. The award must be made
x x x An appeal may be taken from an order made in a in writing and signed and acknowledged by a majority of the
proceeding under this Act, or from a judgment entered arbitrators, if more than one; and by the sole arbitrator, if there
upon an award through certiorari proceedings, but such is only one. Each party shall be furnished with a copy of the
appeals shall be limited to question of law. x x x. award. The arbitrators in their award may grant any remedy or
relief which they deem just and equitable and within the scope
of the agreement of the parties, which shall include, but not be
The aforequoted provision, however, does not preclude a
limited to, the specific performance of a contract.
party aggrieved by the arbitral award from resorting to the
extraordinary remedy of certiorariunder Rule 65 of the Rules of
Court where, as in this case, the Regional Trial Court to which xxx
the award was submitted for confirmation has acted without
jurisdiction, or with grave abuse of discretion and there is no
The arbitrators shall have the power to decide only those
appeal, nor any plain, speedy remedy in the course of law.
matters which have been submitted to them. The terms of the
Thus, Section 1 of Rule 65 provides: award shall be confined to such disputes.(Underscoring ours).

SEC 1. Petition for Certiorari: - When any tribunal, board or xxx.


officer exercising judicial functions, has acted without or in
Section 24 of the same law enumerating the grounds for
excess of its or his jurisdiction, or with grave abuse of discretion
vacating an award states:
and there is no appeal, nor any plain, speedy, and adequate
remedy in the ordinary course of law, a person aggrieved
thereby may file a verified petition in the proper court alleging SEC. 24. Grounds for vacating award. In any one of the following
the facts with certainty and praying that judgment be rendered cases, the court must make an order vacating the award upon
annulling or modifying the proceedings, as the law requires, of the petition of any party to the controversy when such party
such tribunal, board or officer. proves affirmatively that in the arbitration proceedings:

In the instant case, the respondent court erred in (a) The award was procured by corruption, fraud, or other undue
dismissing the special civil action for certiorari, it being from the means; or
pleadings and the evidence that the trial court lacked
jurisdiction and/or committed grave abuse of discretion in taking
(b) That there was evident partiality or corruption in arbitrators
cognizance of private respondent motion to confirm the arbitral
or any of them; or
award and, worse, in confirming said award which is grossly and
patently not in accord with the arbitration agreement, as will be
hereinafter demonstrated. (c) That the arbitrators were guilty of misconduct in refusing to
postpone the hearing upon sufficient cause shown, or in refusing
IV to hear evidence pertinent and material to the controversy; that
The nature and limits of the Arbitrators powers. one or more of the arbitrators was disqualified to act as such
under section nine hereof, and willfully refrained from disclosing
As a rule, the award of an arbitrator cannot be set aside for such disqualifications or any other misbehavior by which the
mere errors of judgment either as to the law or as to the facts. rights of any party have been materially prejudiced; or
[29]
Courts are without power to amend or overrule merely
because of disagreement with matters of law or facts (d) That the arbitrators exceeded their powers, or so imperfectly
determined by the arbitrators.[30] They will not review the executed them, that a mutual, final and definite award upon the
findings of law and fact contained in an award, and will not subject matter submitted to them was not made. (Underscoring
undertake to substitute their judgment for that of the ours).
arbitrators, since any other rule would make an award the
commencement, not the end, of litigation. [31] Errors of law and
fact, or an erroneous decision of matters submitted to the xxx.
judgment of the arbitrators, are insufficient to invalidate an Section 25 which enumerates the grounds for modifying
award fairly and honestly made. [32] Judicial review of an the award provides:
arbitration is, thus, more limited than judicial review of a trial.[33]

Nonetheless, the arbitrators awards is not absolute and SEC. 25. Grounds for modifying or correcting award In anyone of
without exceptions. The arbitrators cannot resolve issues the following cases, the court must make an order modifying or
beyond the scope of the submission agreement. [34] The parties correcting the award, upon the application of any party to the
to such an agreement are bound by the arbitrators award only controversy which was arbitrated:
to the extent and in the manner prescribed by the contract and
only if the award is rendered in conformity thereto. [35] Thus,
Sections 24 and 25 of the Arbitration Law provide grounds for (a) Where there was an evident miscalculation of figures, or an
vacating, rescinding or modifying an arbitration award. Where evident mistake in the description of any person, thing or
the conditions described in Articles 2038, [36] 2039[37] and property referred to in the award; or
2040[38] of the Civil Code applicable to compromises and
arbitration are attendant, the arbitration award may also be (b) Where the arbitrators have awarded upon a matter not
annulled. submitted to them, not affecting the merits of the decision upon
the matter submitted; or
In Chung Fu Industries (Phils.) vs. Court of Appeals, [39] we
held:
(c) Where the award is imperfect in a matter of form not
affecting the merits of the controversy, and if it had been a
x x x. It is stated explicitly under Art. 2044 of the Civil Code that commissioners report, the defect could have been amended or
the finality of the arbitrators awards is not absolute and without disregarded by the court.
exceptions. Where the conditions described in Articles 2038,
2039, and 2040 applicable to both compromises and arbitration
are obtaining, the arbitrators' award may be annulled or x x x.
8
Finally, it should be stressed that while a court is precluded A : Yes.
from overturning an award for errors in determination of factual
issues, nevertheless, if an examination of the record reveals no xxx
support whatever for the arbitrators determinations, their award
must be vacated.[40] In the same manner, an award must be Which brings me to my last point in this separate opinion. Was
vacated if it was made in manifest disregard of the law.[41] PNB and DBP absolutely unjustified in foreclosing the
mortgages?
Against the backdrop of the foregoing provisions and
principles, we find that the arbitrators came out with an award
in excess of their powers and palpably devoid of factual and In this connection, it can readily be seen and it cannot quite be
legal basis. denied that MMIC accounts in PNB-DBP were past due. The
drawing up of the FRP is the best proof of this. When MMIC
V adopted a restructuring program for its loan, it only meant that
There was no financial structuring program; foreclosure of mortgage was fully justified. these loans were already due and unpaid. If these loans were
restructurable because they were already due and unpaid, they
The point need not be belabored that PNB and DBP had the are likewise forecloseable. The option is with the PNB-DBP on
legitimate right to foreclose of the mortgages of MMIC whose what steps to take.
obligations were past due. The foreclosure was not a wrongful
act of the banks and, therefore, could not be the basis of any The mere fact that MMIC adopted the FRP does not mean that
award of damages. There was no financial restructuring DBP-PNB lost the option to foreclose. Neither does it mean that
agreement to speak of that could have constituted an the FRP is legally binding and implementable. It must be pointed
impediment to the exercise of the banks right to foreclose. that said FRP will, in effect, supersede the existing and past due
loans of MMIC with PNB-DBP. It will become the new loan
As correctly stated by Mr. Jose C. Sison, a member of the agreement between the lenders and the borrowers. As in all
Arbitration Committee who wrote a separate opinion: other contracts, there must therefore be a meeting of minds of
the parties; the PNB and DBP must have to validly adopt and
1. The various loans and advances made by DBP and PNB to ratify such FRP before they can be bound by it; before it can be
MMIC have become overdue and remain unpaid. The fact that a implemented. In this case, not an iota of proof has been
FRP was drawn up is enough to establish that MMIC has not presented by the PLAINTIFFS showing that PNB and DBP ratified
been complying with the terms of the loan and adopted the FRP. PLAINTIFFS simply relied on a legal
agreement. Restructuring simply connotes that the obligations doctrine of promissory estoppel to support its allegation in this
are past due that is why it is restructurable; regard.[42]

2. When MMIC thru its board and the stockholders agreed and Moreover, PNB and DBP had to initiate foreclosure
adopted the FRP, it only means that MMIC had been informed or proceedings as mandated by P.D. No. 385, which took effect on
notified that its obligations were past due and that foreclosure is January 31, 1974. The decree requires government financial
forthcoming; institutions to foreclose collaterals for loans where the
arrearages amount to 20% of the total outstanding
obligations. The pertinent provisions of said decree read as
3. At that stage, MMIC also knew that PNB-DBP had the option of follows:
either approving the FRP or proceeding with the
foreclosure. Cabarrus, who filed this case supposedly in behalf of
MMIC should have insisted on the FRP. Yet Cabarrus himself SEC. 1. It shall be mandatory for government financial
opposed the FRP; institutions, after the lapse of sixty (60) days from the issuance
of this Decree to foreclose the collaterals and/or securities for
any loan, credit, accommodations, and/or guarantees granted
4. So when PNB-DBP proceeded with the foreclosure, it was done by them whenever the arrearages on such account, including
without bad faith but with honest and sincere belief that accrued interest and other charges, amount to at least twenty
foreclosure was the only alternative; a decision further explained percent (20%) of the total outstanding obligations, including
by Dr. Placido Mapa who testified that foreclosure was, in the interest and other charges, as appearing in the books of account
judgment of PNB, the best move to save MMIC itself. and/or related records of the financial institutions
concerned. This shall be without prejudice to the exercise by the
Q : Now in this portion of Exh. L which was marked as Exh. L- government financial institutions of such rights and/or remedies
1, and we adopted as Exh. 37-A for the respondent, available to them under their respective contracts with their
may I know from you, Dr. Mapa what you meant by that debtor, including the right to foreclosure on loans, credits,
the decision to foreclose was neither precipitate nor accommodations and/or guarantees on which the arrearages are
arbitrary? less than twenty percent (20%).

A : Well, it is not a whimsical decision but rather decision


arrived at after weighty considerations of the SEC. 2. No restraining order, temporary or permanent injunction
information that we have received, and listening to the shall be issued by the court against any government financial
prospects which reported to us that we had assumed institution in any action taken by such institution in compliance
would be the premises of the financial rehabilitation with the mandatory foreclosure provided in Section 1 hereof,
plan was not materialized nor expected to materialized. whether such restraining order, temporary or permanent
injunction is sought by the borrower(s) or any third party or
Q : And this statement that it was premised upon the known parties, except after due hearing in which it is established by the
fact that means, it was referring to the decision to borrower and admitted by the government financial institution
foreclose, was premised upon the known fact that the concerned that twenty percent (20%) of the outstanding
rehabilitation plan earlier approved by the stockholders arrearages has been paid after the filing of foreclosure
was no longer feasible, just what is meant by no longer proceedings. (Underscoring supplied.)
feasible?

A : Because the revenue that they were counting on to make Private respondents thesis that the foreclosure proceedings
the rehabilitation plan possible, was not anymore were null and void because of lack of publication in the
expected to be forthcoming because it will result in a newspaper is nothing more than a mere unsubstantiated
short fall compared to the prices that were actually allegation not borne out by the evidence. In any case, a
taking place in the market. disputable presumption exists in favor of petitioner that official
duty has been regularly performed and ordinary course of
Q : And I supposed that was you were referring to when you business has been followed.[43]
stated that the production targets and assumed prices
of MMICs products, among other projections, used in VI
the financial reorganization program that will make it Not only was the foreclosure rightfully exercised by the
viable were not met nor expected to be met? PNB and DBP, but also, from the facts of the case, the
9
arbitrators in making the award went beyond the arbitration was not a party to the derivative suit; and (c) in awarding moral
agreement. damages to Jesus S. Cabarrus, Sr.
The arbiters overstepped their powers by declaring as valid proposed Financial Restructuring Program.
In their complaint filed before the trial court, private
respondent Cabarrus, et al. prayed for judgment in their favor:
The Arbitration Committee went beyond its mandate and
thus acted in excess of its powers when it ruled on the validity
1. Declaring the foreclosure effected by the defendants DBP and of, and gave effect to, the proposed FRP.
PNB on the assets of MMIC null and void and directing said
defendants to restore the foreclosed assets to the possession of In submitting the case to arbitration, the parties had
MMIC, to render an accounting of their use and/or operation of mutually agreed to limit the issue to the validity of the
said assets and to indemnify MMIC for the loss occasioned by its foreclosure and to transform the reliefs prayed for therein into
dispossession or the deterioration thereof; pure money claims.

There is absolutely no evidence that the DBP and PNB


2. Directing the defendants DBP and PNB to honor and perform agreed, expressly or impliedly, to the proposed FRP. It cannot be
their commitments under the financial reorganization plan which overemphasized that a FRP, as a contract, requires the consent
was approved at the annual stockholders meeting of MMIC on 30 of the parties thereto.[47] The contract must bind both
April 1984; contracting parties.[48] Private respondents even by their own
admission recognized that the FRP had yet not been carried out
3. Condemning the defendants DBP and PNB, jointly and and that the loans of MMIC had not yet been converted into
severally to pay the plaintiffs actual damages consisting of the equity.[49]
loss of value of their investment amounting to not less
than P80,000,000.00, the damnum emerges and lucrum cessans However, the arbitration Committee not only declared the
in such amount as may be establish during the trial, moral FRP valid and effective, but also converted the loans of MMIC
damages in such amount as this Honorable Court may deem just into equity raising the equity of DBP to 87%.[50]
and equitable in the premises, exemplary damages in such The Arbitration Committee ruled that there was a
amount as this Honorable Court may consider appropriate for commitment to carry out the FRP[51] on the ground of promissory
the purpose of setting an example for the public good, attorneys estoppel.
fees and litigation expenses in such amounts as may be proven
during the trial, and the costs legally taxable in this litigation.
Similarly, the principle of promissory estoppel applies in the
present case considering as we observed, the fact that the
Further, Plaintiffs pray for such other reliefs as may be just and government (that is Alfredo Velayo) was the FRPs
equitable in the premises.[44] proponent. Although the plaintiffs are agreed that the
government executed no formal agreement, the fact remains
Upon submission for arbitration, the Compromise and that the DBP itself which made representations that the FRP
Arbitration Agreement of the parties clearly and explicitly constituted a way out for MMIC. The Committee believes that
defined and limited the issues to the following: although the DBP did not formally agree (assuming that the
board and stockholders approvals were not formal enough), it is
(a) whether PLAINTIFFS have the capacity or the bound nonetheless if only for its conspicuous representations.
personality to institute this derivative suit in behalf of the
MMIC or its directors;
Although the DBP sat in the board in a dual capacity-as holder of
(b) whether or not the actions leading to, and including, 36% of MMICs equity (at that time) and as MMICs creditor-the
the PNB-DBP foreclosure of the MMIC assets were proper, DBP can not validly renege on its commitments simply because
valid and in good faith.[45] at the same time, it held interest against the MMIC.

Item No. 8 of the Agreement provides for the period by


The fact, of course, is that as APT itself asserted, the FRP was
which the Committee was to render its decision, as well as the
being carried out although apparently, it would supposedly fall
nature thereof:
short of its targets. Assuming that the FRP would fail to meet its
8. Decision. The committee shall issue a decision on the targets, the DBP-and so this Committee holds-can not, in any
controversy not later than six (6) months from the date of its event, brook any denial that it was bound to begin with, and the
constitution. fact is that adequate or not (the FRP), the government is still
bound by virtue of its acts.

In the event the committee finds that PLAINTIFFS have the


personality to file this suit and extra-judicial foreclosure of the The FRP, of course, did not itself promise a resounding success,
MMIC assets wrongful, it shall make an award in favor of the although it raised DBPs equity in MMIC to 87%. It is not excuse,
PLAINTIFFS (excluding DBP), in an amount as may be however, for the government to deny its commitments.[52]
established or warranted by the evidence which shall be payable
in Philippine Pesos at the time of the award. Such award shall be Atty. Sison, however, did not agree and correctly observed
paid by the APT or its successor-in-interest within sixty (60) days that:
from the date of the award in accordance with the provisions of
par. 9 hereunder. x x x. The PLAINTIFFS remedies under this
Section shall be in addition to other remedies that may be But the doctrine of promissory estoppel can hardly find
available to the PLAINTIFFS, all such remedies being cumulative application here. The nearest that there can be said of any
and not exclusive of each other. estoppel being present in this case is the fact that the board of
MMIC was, at the time the FRP was adopted, mostly composed
of PNB and DBP representatives. But those representatives,
On the other hand, in case the arbitration committee finds that singly or collectively, are not themselves PNB or DBP. They are
PLAINTIFFS have no capacity to sue and/or that the extra-judicial individuals with personalities separate and distinct from the
foreclosure is valid and legal, it shall also make an award in banks they represent. PNB and DBP have different boards with
favor of APT based on the counterclaims of DBP and PNB in an different members who may have different decisions. It is unfair
amount as may be established or warranted by the to impose upon them the decision of the board of another
evidence. This decision of the arbitration committee in favor of company and thus pin them down on the equitable principle of
APT shall likewise finally settle all issues regarding the estoppel. Estoppel is a principle based on equity and it is
foreclosure of the MMIC assets so that the funds held in escrow certainly not equitable to apply it in this particular
mentioned in par. 9 hereunder will thus be released in full in situation. Otherwise the rights of entirely separate, distinct and
favor of APT.[46] autonomous legal entities like PNB and DBP with thousands of
stockholders will be suppressed and rendered nugatory.[53]
The clear and explicit terms of the submission
notwithstanding, the Arbitration Committee clearly exceeded its As a rule, a corporation exercises its powers, including the
powers or so imperfectly executed them: (a) in ruling on and power to enter into contracts, through its board of
declaring valid the FRP; (b) in awarding damages to MMIC which directors. While a corporation may appoint agents to enter into
10
a contract in its behalf, the agent, should not exceed his of Evangelista v. Santos, that the stockholders may not directly
authority.[54] In the case at bar, there was no showing that the claim those damages for themselves for that would result in the
representatives of PNB and DBP in MMIC even had the requisite appropriation by, and the distribution among them of part of the
authority to enter into a debt-for-equity swap. And if they had corporate assets before the dissolution of the corporation and
such authority, there was no showing that the banks, through the liquidation of its debts and liabilities, something which
their board of directors, had ratified the FRP. cannot be legally done in view of section 16 of the Corporation
Law xxx;
Further, how could the MMIC be entitled to a big amount of
moral damages when its credit reputation was not exactly
something to be considered sound and wholesome. Under (3) the filing of such suits would conflict with the duty of the
Article 2217 of the Civil Code, moral damages include management to sue for the protection of all concerned;
besmirched reputation which a corporation may possibly
suffer. A corporation whose overdue and unpaid debts to the (4) it would produce wasteful multiplicity of suits; and
Government alone reached a tremendous amount of P22 Billion
Pesos cannot certainly have a solid business reputation to brag
about. As Atty. Sison in his separate opinion persuasively put it: (5) it would involve confusion in a ascertaining the effect of
partial recovery by an individual on the damages recoverable by
the corporation for the same act.[58]
Besides, it is not yet a well settled jurisprudence that
corporations are entitled to moral damages. While the Supreme
Court may have awarded moral damages to a corporation for If at all an award was due MMIC, which it was not, the
besmirched reputation in Mambulao vs. PNB 22 SCRA 359, such same should have been given sans deduction, regardless of
ruling cannot find application in this case. It must be pointed out whether or not the party liable had equity in the corporation, in
that when the supposed wrongful act of foreclosure was done, view of the doctrine that a corporation has a personality
MMICs credit reputation was no longer a desirable one. The separate and distinct from its individual stockholders or
company then was already suffering from serious financial crisis members. DBPs alleged equity, even if it were indeed 87%, did
which definitely projects an image not compatible with good and not give it ownership over any corporate property, including the
wholesome reputation. So it could not be said that there was a monetary award, its right over said corporate property being a
reputation besmirches by the act of foreclosure.[55] mere expectancy or inchoate right.[59]Notably, the stipulation
even had the effect of prejudicing the other creditors of MMIC.
The arbiters, likewise, exceeded their authority in awarding moral damages to Jesus Cabarrus, Sr.

The arbiters exceeded their authority in awarding damages to MMIC, which is not impleaded as a
It is perplexing how the Arbitration Committee can in one
party to the derivative suit.
breath rule that the case before it is a derivative suit, in which
the aggrieved party or the real party in interest is supposedly
the MMIC, and at the same time award moral damages to an
Civil Code No. 9900 filed before the RTC being a derivative individual stockholder, to wit:
suit, MMIC should have been impleaded as a party. It was not
joined as a party plaintiff or party defendant at any stage of the WHEREFORE, premises considered, judgment is hereby
proceedings. As it is, the award of damages to MMIC, which was rendered:
not a party before the Arbitration Committee, is a complete
nullity.
xxx.
Settled is the doctrine that in a derivative suit, the
corporation is the real party in interest while the stockholder
filing suit for the corporations behalf is only nominal party. The 3. Ordering the defendant to pay to the plaintiff, Jesus S.
corporation should be included as a party in the suit. Cabarrus, Sr., the sum of P10,000,000.00, to be satisfied
likewise from the funds held under escrow pursuant to the
Escrow Agreement dated April 22, 1988 or to such subsequent
An individual stockholder is permitted to institute a derivative escrow agreement that would supersede it, pursuant to
suit on behalf of the corporation wherein he holds stock in order paragraph (9), Compromise and Arbitration Agreement, as and
to protect or vindicate corporate rights, whenever the officials of for moral damages; x x x[60]
the corporation refuse to sue, or are the ones to be sued or hold
the control of the corporation. In such actions, the suing
stockholder is regarded as a nominal party, with the corporation The majority decision of the Arbitration Committee sought
as the real party in interest. x x x.[56] to justify its award of moral damages to Jesus S. Cabarrus, Sr. by
pointing to the fact that among the assets seized by the
government were assets belonging to Industrial Enterprise Inc.
It is a condition sine qua non that the corporation be (IEI), of which Cabarrus is the majority stockholder. It then
impleaded as a party because- acknowledge that Cabarrus had already recovered said assets in
the RTC, but that he won no more than actual damages. While
x x x. Not only is the corporation an indispensible party, but it is the Committee cannot possibly speak for the RTC, there is no
also the present rule that it must be served with process. The doubt that Jesus S. Cabarrus, Sr., suffered moral damages on
reason given is that the judgment must be made binding upon account of that specific foreclosure, damages the Committee
the corporation and in order that the corporation may get the believes and so holds, he Jesus S. Cabarrus, Sr., may be awarded
benefit of the suit and may not bring a subsequent suit against in this proceeding.[61]
the same defendants for the same cause of action. In other Cabarrus cause of action for the seizure of the assets
words the corporations must be joined as party because it is its belonging to IEI, of which he is the majority stockholder, having
cause of action that is being litigated and because judgment been ventilated in a complaint he previously filed with the RTC,
must be a res ajudicata against it.[57] from which he obtained actual damages, he was barred res
judicata from filing a similar case in another court, this time
The reasons given for not allowing direct individual suit asking for moral damages which he failed to get from the earlier
are: case.[62] Worse, private respondents violated the rule against
non-forum shopping.
(1) x x x the universally recognized doctrine that a stockholder It is a basic postulate that s corporation has a personality
in a corporation has no title legal or equitable to the corporate separate and distinct from its stockholders. [63] The properties
property; that both of these are in the corporation itself for the foreclosed belonged to MMIC, not to its stockholders. Hence, if
benefit of the stockholders. In other words, to allow wrong was committed in the foreclosure, it was done against the
shareholders to sue separately would conflict with the separate corporation. Another reason is that Jesus S. Cabarrus, Sr. cannot
corporate entity principle; directly claim those damages for himself that would result in the
appropriation by, and the distribution to, him part of the
(2) x x x that the prior rights of the creditors may be corporations assets before the dissolution of the corporation and
prejudiced. Thus, our Supreme Court held in the case the liquidation of its debts and liabilities. The Arbitration
Committee, therefore, passed upon matters not submitted to
11
it.Moreover, said cause of action had already been decided in a there is no showing that the case at bar constitutes an
separate case. It is thus quite patent that the arbitration exception. Nevertheless, we gave due course to the petition to
committee exceeded the authority granted to it by the parties enable the Court to reiterate and clarify the jurisdictional
Compromise and Arbitration Agreement by awarding moral boundaries between Labor Arbiters and Voluntary Arbitrator or
damages to Jesus S. Cabarrus, Sr. Panel of Voluntary Arbitrators over money claims, and to render
Atty. Sison, in his separate opinion, likewise expressed substantial and speedy justice to subject aged stevedore retiree
befuddlement to the award of moral damages to Jesus S. who first presented his claim for retirement benefit in April 1991,
Cabarrus, Sr.: or seven years ago.

It is clear and it cannot be disputed therefore that based on Labor law practitioners and all lawyers, for that
these stipulated issues, the parties themselves have agreed that matter, should be fully conversant with the requirements for the
the basic ingredient of the causes of action in this case is the institution of certiorari proceedings under Rule 65 of the Revised
wrong committed on the corporation (MMIC) for the alleged Rules of Court. For instance, it is necessary that a Motion for
illegal foreclosure of its assets. By agreeing to this Reconsideration of the Decision of the National Labor Relations
stipulation, PLAINTIFFS themselves (Cabarrus, et al.) admit that Commission must first be resorted to. The ruling in Corazon
the cause of action pertains only to the corporation (MMIC) and Jamer v. National Labor Relations Commission, G.R. No. 112630,
that they are filing this for and in behalf of MMIC. September 5, 1997, comes to the fore and should be well
understood and observed. An ordinary allegation ... and there is
Perforce this has to be so because it is the basic rule in no appeal, nor any plain, speedy, and adequate remedy in the
Corporation Law that the shareholders have no title, legal or ordinary course of law (Rule 65, Sec. 1, Revised Rules of Court)
equitable to the property which is owned by the corporation (13 is not a foolproof substitute for a Motion for Reconsideration,
Am. Jur. 165; Pascual vs. Oresco, 14 Phil. 83). In Ganzon & Sons absence of which can be fatal to a Petition
vs. Register of Deeds, 6 SCRA 373, the rule has been reiterated for Certiorari. Petitioner cannot and should not rely on the
that a stockholder is not the co-owner of corporate liberality of the Court simply because he is a working man.
property. Since the property or assets foreclosed belongs [sic] to
MMIC, the wrong committed, if any, is done against the
corporation. There is therefore no direct injury or direct violation In the Jamer case, this court said:
of the rights of Cabarrus et al. There is no way, legal or
equitable, by which Cabarrus et al. could recover damages in ... This premature action of petitioners constitutes a fatal
their personal capacities even assuming or just because the
infirmity as ruled in a long line of decisions, most recently is the
foreclosure is improper or invalid. The Compromise and
case of Building Care Corporation v. National Labor Relations
Arbitration Agreement itself and the elementary principles of
Corporation Law say so. Therefore, I am constrained to dissent Commission
from the award of moral damages to Cabarrus.[64]
The filing of such motion is intended to afford public respondent
From the foregoing discussions, it is evident that, not only an opportunity to correct any actual or fancied error attributed
did the arbitration committee exceed its powers or so to it by way of a re-examination of the legal and factual aspects
imperfectly execute them, but also, its findings and conclusions of the case. Petitioners inaction or negligence under the
are palpably devoid of any factual basis and in manifest circumstances is tantamount to a deprivation of the right and
disregard of the law. opportunity of the respondent commission to cleanse itself of an
error unwittingly committed or to vindicate itself of an act
We do not find it necessary to remand this case to the RTC unfairly imputed...
for appropriate action. The pleadings and memoranda filed with
this Court, as well as in the Court of Appeals, raised and
extensively discussed the issues on the merits. Such being the Likewise, a motion for reconsideration is an adequate remedy;
case, there is sufficient basis for us to resolve the controversy hence certiorari proceedings, as in this case, will not prosper.
between the parties anchored on the records and the pleadings
before us.[65]
As stated in the Decision of the Labor Arbiter in NLRC-NCR-
WHEREFORE, the Decision of the Court of Appeals dated Case No. 00-03-0201-93, dated January 19, 1994, the facts of
July 17, 1995, as well as the Orders of the Regional Trial Court of this case are undisputed. The Labor Arbiter reported, thus:
Makati, Branch 62, dated November 28, 1994 and January 19,
1995, is hereby REVERSED and SET ASIDE, and the decision of
Complainant, in his position paper (Record, pages 11 to
the Arbitration Committee is hereby VACATED.
14) states that he was hired sometime in July 1980 as a
SO ORDERED stevedore continuously until he was advised in April 1991 to
retire from service considering that he already reached 65 years
old (sic); that accordingly, he did apply for retirement and was
THIRD DIVISION[G.R. No. 121227. August 17, 1998]
paid P3,156.39 for retirement pay... (Rollo, pp. 15, 26-27, 58-
59).
VICENTE SAN JOSE, petitioner, vs. NATIONAL LABOR
RELATIONS COMMISSION and OCEAN TERMINAL
Decision of the Labor Arbiter in NLRC-NCR-Case No. 00-03-
SERVICES, INC., respondents.
02101-93, January 9, 1994 (Rollo, pp. 15017, at pp. 16-17).

PURISIMA, J.:
The Labor Arbiter decided the case solely on the merits of
the complaint. Nowhere in the Decision is made mention of or
Before the Court is a Petition for Certiorari seeking to annul reference to the issue of jurisdiction of the Labor Arbiter (Rollo,
a Decision of the National Labor Relations Commission dated pp. 15-17). But the issue of jurisdiction is the bedrock of the
April 20, 1995 in NLRC-NCR-CA-No. 00671-94 which reversed, on Petition because, as earlier intimated, the Decision of the
jurisdictional ground, a Decision of the Labor Arbiter dated National Labor Relations Commission, hereinbelow quoted,
January 19, 1994 in NLRC-NCR Case No. 00-03-02101-93 a case reversed the Labor Arbiters Decision on the issue of
for a money claim - underpayment of retirement jurisdiction. Reads subject Decision of the Labor Arbiter:
benefit. Records do not show that petitioner presented a Motion
for Reconsideration of subject Decision of the National Labor
Respondents, in their Reply to complainants position paper,
Relations Commission, which motion is, generally required
allege (Record, pages 18 to 21) that complainants latest basic
before the filing of Petition for Certiorari.
salary was P120.34 per day; that he only worked on rotation
basis and not seven days a week due to numerous stevedores
While the rule prescribing the requisite motion for who can not all be given assignments at the same time; that all
reconsideration is not absolute and recognizes some exceptions, stevedores only for paid every time they were assigned or
12
actually performed stevedoring; that the computation used in xxx The company agrees that in case of casual employees
arriving at the amount of P3,156.30 was the same computation and/or workers who work on rotation basis the criterion for
applied to the other stevedores; that the use of divisor 303 is determining their retirement pay shall be 303 rotation calls or
not applicable because complainant performed stevedoring job work days as equivalent to one (1) year and shall be paid their
only on call, so while he was connected with the company for retirement pay equivalent to one half (1/2) month for every year
the past 11 years, he did not actually render 11 years of service; of service.
that the burden of proving that complainants latest salary
was P200.00 rests upon him; that he already voluntarily signed xxx
a waiver of quitclaim; that if indeed respondent took advantage
of his illiteracy into signing his quitclaim, he would have
immediately filed this complaint but nay, for it took him Since the instant case arises from interpretation or
two (2) years to do so. implementation of a collective bargaining agreement, the Labor
Arbiter should have dismissed it for lack of jurisdiction in
accordance with Article 217 (c) of the Labor Code, which
The issue therefore is whether or not complainant is entitled to reads: (Underscoring supplied)
the claimed differential of separation pay.

Art. 217. Jurisdiction of Labor Arbiter and the Commission.


We find for the complainant. He is entitled to differential.

xxx
We cannot sustain a computation of length of service based on
the ECC contribution records. Likewise, the allegation that
complainant rendered service for only five days a month for the (c) Cases arising from the interpretation or implementation of
past 11 years is statistically improbable, aside from the fact that collective bargaining agreement and those arising from the
the best evidence thereof are complainants daily time records interpretation or enforcement of company procedure/policies
which respondent are (sic) duty bound to keep and make shall be disposed of by the Labor Arbiter by referring the same
available anytime in case of this. to the grievance machinery and voluntary arbitrator as may be
provided in said agreements.

The late filing has no bearing. The prescription period is three


years. It is suffice (sic) that the filing falls within the period. Petitioner contends that:

Whether or not complainant worked on rotation basis is a I. THE PUBLIC RESPONDENT NLRC GRAVELY ABUSED ITS
burden which lies upon the employer. The presumption is that DISCRETION IN GIVING DUE COURSE TO THE APPEAL
the normal working period is eight (8)hours a day and DESPITE THE FACT 4 (SIC) THAT IT WAS FILED OUT OF
six (6) days a week, or 26 days a month, unless proven TIME AND THERE IS NO SHOWING THAT A SURETY BOND
otherwise. WAS POSTED.

Also, the burden of proving the amount of salaries paid to II. THE PUBLIC RESPONDENT NLRC GRAVELY ABUSED ITS
employees rests upon the employer not on the employee. It can DISCRETION N SETTING ASIDE THE DECISION OF XXX
be easily proven by payrolls, vouchers, etc. which the employers DATED 19 JANUARY 1994 AND DISMISSING THE CASE ON
are likewise duty bound to keep and present. There being non, THE GROUND OF LACK OF JURISDICTION WHEN THE
we have to sustain complainants assertion that his latest salary ISSUE DOES NOT INVOLVE ANY PROVISION OF THE
rate was P200 a day or P5,200 a month. Therefore, his COLLECTIVE BARGAINING AGREEMENT. (Rollo, pp. 7-8)
retrenchment pay differential is P25,443.70 broken down as
follows: The Manifestation and Motion (In Lieu of Comment) sent in
on December 6, 1995 by the Office of the Solicitor General
P200 x 26 days = P5,200 x 11 years support the second issue, re: jurisdiction raised by the Petitioner
(Rollo, pp. 26-33, at pp. 38-32).

2
Labor Arbiter Decision

= (P2,600 x 11 years) - P3,156.30


Labor Arbiters should exert all efforts to cite statutory
provisions and/or judicial decision to buttress their
= P28,600 - P3,156.30 dispositions. An Arbiter cannot rely on simplistic statements,
generalizations, and assumptions. These are not substitutes for
= P25,443.70 reasoned judgment. Had the Labor Arbiter exerted more
research efforts, support for the Decision could have been found
in pertinent provisions of the Labor Code, its Implementing
The Decision of the National Labor Relations Commission in
Rules, and germane decisions of the Supreme Court. As this
NLRC-NCR-CA No. 06701-94, April 20, 1995 (Rollo, pp. 18-21).
Court said in Juan Saballa, et al. v. NLRC, G.R. No. 102472-84,
August 22, 1996:
The National Labor Relations Commission reversed on
jurisdictional ground the aforesaid Decision of the Labor Arbiter;
xxx This Court has previously held that judges and arbiters
ruling, as follows:
should draw up their decisions and resolutions with due care,
and make certain that they truly and accurately reflect their
... His claim for separation pay differential is based on the conclusions and their final dispositions. A decision should
Collective Bargaining Agreement (CBA) between his union and faithfully comply with Section 14, Article VIII of the Constitution
the respondent company, the pertinent portion of which reads: which provides that no decision shall be rendered by any court
without expressing therein clearly and distinctly the facts of the
xxx ANY UNION member shall be compulsory retired (sic) by the case and the law on which it is based. If such decision had to be
company upon reaching the age of sixty (60) years, unless completely overturned or set aside, upon the modified decision,
otherwise extended by the company for justifiable reason. He such resolution or decision should likewise state the factual and
shall be paid his retirement pay equivalent to one- legal foundation relied upon. The reason for this is
half (1/2) month salary for every year of service, a fraction of at obvious: aside from being required by the Constitution, the court
least six months being considered as one (1) whole year. should be able to justify such a sudden change of course; it
must be able to convincingly explain the taking back of its
13
solemn conclusions and pronouncements in the earlier The jurisdiction of Labor Arbiters and Voluntary Arbitrator or
decision. The same thing goes for the findings of fact made by Panel of Voluntary Arbitrators is clearly defined and specifically
the NLRC, as it is a settled rule that such findings are entitled to delineated in the Labor Code.The pertinent provisions of the
great respect and even finality when supported by substantial Labor Code, read:
evidence; otherwise, they shall be struck down for being
whimsical and capricious and arrived at with grave abuse of A. Jurisdiction of Labor Arbiters
discretion. It is a requirement of due process and fair play that
the parties to a litigation be informed of how it was decided,
with an explanation of the factual and legal reasons that led to Art. 217. Jurisdiction of Labor Arbiter and the Commission. -- (a)
the conclusions of the court.A decision that does not clearly and Except as otherwise provided under this Code the Labor Arbiter
distinctly state the facts and the law on which it is based leaves shall have original and exclusive jurisdiction to hear and decide,
the parties in the dark as to how it was reached and is especially within thirty (30) calendar days after the submission of the case
prejudicial to the losing party, who is unable to pinpoint the by the parties for decision without extension, even in the
possible errors of the court for review by a higher tribunal. xxx absence of stenographic notes, the following cases involving all
workers, whether agricultural or non-agricultural:

This is not an admonition but rather, advice and a critique


to stress that both have obligations to the Courts and students 1. Unfair labor practice cases;
of the law. Decisions of the Labor Arbiters, the National Labor
Relations Commission, and the Supreme Court serve not only to 2. Termination disputes;
adjudicate disputes, but also as an educational tool to
practitioners, executives, labor leaders and law students. They
3. If accompanied with a claim for reinstatement, those cases
all have a keen interest in methods of analysis and the
that workers may file involving wages, rates of pay, hours of
reasoning processes employed in labor dispute adjudication and
work and other terms and conditions of employment;
resolution. In fact, decisions rise or fall on the basis of the
analysis and reasoning processes of decision makers or
adjudicators. 4. claims for actual, moral, exemplary and other forms of
damages arising from the employer-employee relations;
On the issues raised by the Petitioner, we rule:
5. Cases arising from any violation of Article 264 of this Code,
I. Timeliness of Appeal And Filing of Appeal Bond including questions involving the legality of strikes and lockouts;
and,

The Court rules that the appeal of the respondent


6. Except claims for Employees Compensation, Social Security,
corporation was interposed within the reglementary period, in
Medicare and maternity benefits, all other claims, arising from
accordance with the Rules of the National Labor Relations
employer-employee relations, including those of persons in
Commission, and an appeal bond was duly posted. We adopt the
domestic or household service, involving an amount exceeding
following Comment dated August 14, 1996, submitted by the
five thousand pesos (P5,000) regardless of whether
National Labor Relations Commission, to wit:
accompanied with a claim for reinstatement.

xxx While it is true that private respondent company received a


xxx
copy of the decision dated January 19, 1994 of the Labor Arbiter
xxx and filed its appeal on February 14, 1994, it is undisputed
that the tenth day within which to file an appeal fell on a (c) Cases arising from the interpretation or implementation of
Saturday, the last day to perfect an appeal shall be the next collective bargaining agreement and those arising from the
working day. interpretation or enforcement of company procedure/policies
shall be disposed of by the Labor Arbiter by referring the same
to the grievance machinery and voluntary arbitrator so maybe
Thus, the amendments to the New Rules of Procedure of the
provided in said agreement.
NLRC, Resolution No. 11-01-91 which took effect on January 14,
1992, provides in part:
B. Jurisdiction of Voluntary Arbitrator or Panel of Voluntary
Arbitrators
xxx

Art. 261. Jurisdiction of Voluntary Arbitrators or panel of


1. Rule VI, Sections 1 and 6 are hereby amended to read as
Voluntary Arbitrators. The Voluntary Arbitrator or panel of
follows:
Voluntary Arbitrators shall have original and exclusive
jurisdiction to hear and decide all unresolved grievances arising
Section 1. Period of Appeal Decisions, awards or orders of the from the interpretation or implementation of the Collective
Labor Arbiter ... shall be final and executory unless appealed to Bargaining Agreement and those arising from the interpretation
the Commission by any or both parties within ten (10) calendar or enforcement of company personnel policies referred to in the
days from receipt of such decisions, awards or orders of the immediately preceding article. Accordingly, violations of a
Labor Arbiter xxx ... If the 10th day ... falls on a Saturday, Sunday Collective Bargaining Agreement, except those which are gross
or a Holiday, the last day to perfect the decision shall be the in character, shall no longer be treated as unfair labor practice
next working day. (Underscoring supplied) and shall be resolved as grievances under the collective
bargaining agreement. For purposes of this Article, gross
Hence, it is crystal clear that the appeal was filed within the violations of Collective Bargaining Agreement shall mean
prescriptive period to perfect an appeal. Likewise, the flagrant and/or malicious refusal to comply with the economic
petitioners contention that private respondent did not post the provisions of such agreement.
required surety bond, deserves scant consideration, for the
simple reason that a surety bond was issued by BF General The Commission, its Regional Offices and the Regional Directors
Insurance Company, Inc., in the amount of P25, 443.70 (Rollo, of the Department of Labor and Employment shall not entertain
pp. 63-64). disputes, grievances or matters under the exclusive and original
jurisdiction of the Voluntary Arbitrator or panel of Voluntary
2. Jurisdictional Issue Arbitrators and shall immediately dispose and refer the same to
the Grievance Machinery or Voluntary Arbitration provided in the
Collective Bargaining Agreement.
14
Art. 262. Jurisdiction over other labor disputes. The Voluntary shall be resolved as grievances under the Collective Bargaining
Arbitrator or panel of Voluntary Arbitrators, upon agreement of Agreement. xxx.
the parties, shall also hear and decide all other labor disputes
including unfair labor practices and bargaining deadlocks. 2. Voluntary Arbitrators or Panel of Voluntary Arbitrators,
however, can exercise jurisdiction over any and all disputes
The aforecited provisions of law cannot be read in isolation between an employer and a union and/or individual worker as
or separately. They must be read as a whole and each Article of provided for in Article 262.
the Code reconciled one with the other. An analysis of the
provisions of Articles 217, 261, and 262 indicates, that: Art. 262. Jurisdiction over other labor disputes. - The voluntary
arbitrator or panel of voluntary arbitrators, upon agreement of
1. The jurisdiction of the Labor Arbiter and Voluntary the parties, shall also hear and decide all other labor disputes
Arbitrator or Panel of Voluntary Arbitrators over the including unfair labor practices and bargaining deadlocks.
cases enumerated in Articles 217, 261 and 262, can
possibly include money claims in one form or another. It must be emphasized that the jurisdiction of the Voluntary
Arbitrator or Panel of Voluntary Arbitrators under Article 262
2. The cases where the Labor Arbiters have original and must be voluntarily conferred upon by both labor and
exclusive jurisdiction are enumerated in Article 217, management. The labor disputes referred to in the same Article
and that of the Voluntary Arbitrator or Panel of 262 can include all those disputes mentioned in Article 217 over
Voluntary Arbitrators in Article 261. which the Labor Arbiter has original and exclusive jurisdiction.

3. The original and exclusive jurisdiction of Labor Arbiters As shown in the above contextual and wholistic analysis of
is qualified by an exception as indicated in the Articles 217, 261, and 262 of the Labor Code, the National Labor
introductory sentence of Article 217 (a), to wit: Relations Commission correctly ruled that the Labor Arbiter had
no jurisdiction to hear and decide petitioners money-
claim underpayment of retirement benefits, as the
Art. 217. Jurisdiction of Labor Arbiters ... (a) Except as otherwise
controversy between the parties involved an issue arising from
provided under this Code the Labor Arbiter shall have original
the interpretation or implementation of a provision of the
and exclusive jurisdiction to hear and decide ... the following
collective bargaining agreement. The Voluntary Arbitrator or
cases involving all workers...
Panel of Voluntary Arbitrators has original and exclusive
jurisdiction over the controversy under Article 261 of the Labor
The phrase Except as otherwise provided under this Code Code, and not the Labor Arbiter.
refers to the following exceptions:

3. Merits of the Case


A. Art. 217. Jurisdiction of Labor Arbiters ...

The Court will not remand the case to the Voluntary


xxx Arbitrator or Panel of Voluntary Arbitrators for hearing. This case
has dragged on far too long - eight (8) years. Any further delay
(c) Cases arising from the interpretation or implementation of would be a denial of speedy justice to an aged retired
collective bargaining agreement and those arising from the stevedore. There is further the possibility that any Decision by
interpretation or enforcement of company procedure/policies the Voluntary Arbitrator or Panel of Voluntary Arbitrators will be
shall be disposed of by the Labor Arbiter by referring the same appealed to the Court of Appeals, and finally to this
to the grievance machinery and voluntary arbitrator as may be Court. Hence, the Court will rule on the merits of the case.
provided in said agreement.
We adopt as our own the retirement benefit computation
B. Art. 262. Jurisdiction over other labor disputes. - The formula of the Labor Arbiter, and the reasons therefor as stated
Voluntary Arbitrator or panel of Voluntary Arbitrators, upon in the decision abovequoted.
agreement of the parties, shall also hear and decide all other
labor disputes including unfair labor practices and bargaining The simple statement of the Labor Arbiter that we cannot
deadlocks. sustain a computation of length of service based on ECC
contribution records, was not amply explained by the Labor
Parenthetically, the original and exclusive jurisdiction of the Arbiter; however, there is legal and factual basis for the same. It
Labor Arbiter under Article 217 (c), for money claims is limited is unrealistic to expect a lowly stevedore to know what reports
only to those arising from statutes or contracts other than a his employer submits to the Employees Compensation
Collective Bargaining Agreement. The Voluntary Arbitrator or Commission under Book IV, Health, Safety and Welfare Benefits,
Panel of Voluntary Arbitrators will have original and exclusive Title II, Employees Compensation and State Insurance Fund, of
jurisdiction over money claims arising from the interpretation or the Labor Code, simply because the insurance fund is solely
implementation of the Collective Bargaining Agreement and, funded by the employer and the rate of employers contribution
those arising from the interpretation or enforcement of company varies according to time and actuarial
personnel policies, under Article 261. computations. (See Articles 183-184; Labor Code). The worker
has no ready access to this employers record. In fact, it is
farthest from his mind to inquire into the amount of employers
4. The jurisdiction of Voluntary Arbitrator or Panel of contribution, much less whether the employer remits the
Voluntary Arbitrators is provided for in Arts. 261 and contributions. The worker is at all times entitled to benefits upon
262 of the Labor Code as indicated above. the occurrence of the defined contingency even when the
employer fails to remit the contributions. (See Article 196 (b),
1. A close reading of Article 261 indicates that the original Labor Code).
and exclusive jurisdiction of Voluntary Arbitrator or Panel of
Voluntary Arbitrators is limited only to: All employers are likewise required to keep an employment
record of all their employees, namely: payrolls; and time
... unresolved grievances arising from the interpretation or records. (See Book III, Rule X, specifically Secs. 6,7,8, 1 and
implementation of the Collective Bargaining Agreement and 12, Omnibus Rules - Implementing the Labor Code).
those arising from the interpretation or enforcement of company
personnel policies... Accordingly, violations of a collective The respondent-employer was afforded the opportunity to
bargaining agreement, except those which are gross in show proof of the petitioners length of service and pay
character, shall no longer be treated as unfair labor practice and
15
records. In both instances, the respondent-employer failed. By as of the close of business hours on November 2, 1990. Private
its own folly, it must therefore suffer the consequences of such respondents were in fact purged on the date aforesaid.
failure. (South Motorists Enterprises v. Tosoc, 181 SCRA 386,
[1990]) From the very beginning - by the provision of the Thus, on February 25, 1991, private respondents filed a
retirement provision of the Collective Bargaining Agreement, complaint against petitioners for Illegal Dismissal and Unfair
i.e., the length of service as requirement for retirement, and Labor Practices, with a prayer for damages and attorneys fees,
salary as a basis for benefit computation - the employer was with the Arbitration Branch of respondent National Labor
forewarned of the need for accurate record keeping. This is Relations Commission. The complaint[1] was assigned to Labor
precisely the basis of retirement, and the computation of Arbiter Eduardo F. Carpio for hearing and proper disposition.
benefits based on years of service and monthly wage.

On April 15, 1991, petitioners filed a motion to dismiss the


To recapitulate; the Court hereby rules - complaint, alleging that respondent Labor Arbiter had no
jurisdiction over the subject matter of the complaint, and that
1. That the National Labor Relations Commission correctly respondent Labor Arbiter must defer consideration of the unfair
ruled that the Labor Arbiter had no jurisdiction over the labor practice complaint until after the parties have gone
case, because the case involved an issue arising from through the grievance procedure provided for in the existing
the interpretation or implementation of a Collective Collective Bargaining Agreement (CBA). Respondent Labor
Bargaining Agreement; Arbiter denied this motion in a Resolution, dated September 23,
1991.
2. That the appeal to the National Labor Relations
Commission was filed within the reglementary period The petitioners appealed the denial to respondent
and that the appeal bond was filed; and Commission on November 8, 1991. Unimpressed by the grounds
therefor, respondent Commission dismissed the appeal in its
assailed Resolution, dated August 11, 1992. Petitioners promptly
3. That we adopt the computation formula for the
filed a Motion for Reconsideration which, however, was denied
retirement benefits by the Labor Arbiter, and the basis
through the likewise assailed Resolution, dated October 29,
thereof. The respondent must therefore pay the
1992.
petitioner the additional amount of Twenty-Five
Thousand Four Hundred Forty-Three and Seventy
Centavos P25,443.70) Pesos. Hence, the instant petition for certiorari alleging the
following grounds was filed by the petitioners:
In view of the long delay in the disposition of the case, this
decision is immediately executory. I.

SO ORDERED. RESPONDENT LABOR ARBITER CANNOT EXERCISE JURISDICTION


OVER THE ALLEGED ILLEGAL TERMINATION AND ALLEGED ULP
CASES WITHOUT PRIOR RESORT TO GRIEVANCE AND
FIRST DIVISION[G.R. No. 108001. March 15, 1996]
ARBITRATION PROVIDED UNDER THE CBA.

SAN MIGUEL CORPORATION, ANGEL G. ROA and MELINDA


II
MACARAIG, petitioners, vs. NATIONAL LABOR
RELATIONS COMMISSION (Second Division),
LABOR ARBITER EDUARDO J. CARPIO, ILAW AT THE STRONG STATE POLICY ON THE PROMOTION OF VOLUNTARY
BUKLOD NG MANGGAWA (IBM), ET MODES OF SETTLEMENT OF LABOR DISPUTES CRAFTED IN THE
AL., respondents. CONSTITUTION AND THE LABOR CODE DICTATES THE
SUBMISSION OF THE CBA DISPUTE TO GRIEVANCE AND
ARBITRATION.[2]
HERMOSISIMA, JR., J.:

Petitioners posit the basic principle that a collective


In the herein petition for certiorari under
bargaining agreement is a contract between management and
Rule 65, petitioners question the jurisdiction of the Labor Arbiter
labor that must bind and be enforced in the first instance as
to hear a complaint for unfair labor practice, illegal dismissal,
between the parties thereto. In this case, the CBA between the
and damages, notwithstanding the provision for grievance and
petitioners and respondent union provides, under Section 1,
arbitration in the Collective Bargaining Agreement.
Article V entitled ARBITRATION, that wages, hours of work,
conditions of employment and/or employer-employee relations
Let us unfurl the facts. shall be settled by arbitration. Petitioners thesis is that the
dispute as to the termination of the union members and the
Private respondents, employed by petitioner San Miguel unfair labor practice should first be settled by arbitration, and
Corporation (SMC) as mechanics, machinists, and carpenters, not directly by the labor arbiter, following the above provision of
were and still are, bona fide officers and members of private the CBA, which ought to be treated as the law between the
respondent Ilaw at Buklod ng Manggagawa. parties thereto.

On or about July 31, 1990, private respondents were The argument is unmeritorious. The law in point is Article
served a Memorandum from petitioner Angel G. Roa, Vice- 217 (a) of the Labor Code. It is elementary that this law is
President and Manager of SMCs Business Logistics Division deemed written into the CBA. In fact, the law speaks in plain and
(BLD), to the effect that they had to be seperated from the unambiguous terms that termination disputes, together with
service effective October 31, 1990 on the ground of redundancy unfair labor practices, are matters falling under the original and
or excesss personnel. Respondent union, in behalf of private exclusive jurisdiction of the Labor Arbiter, to wit:
respondents, opposed the intended dismissal and asked for a
dialogue with management. Article 217. Jurisdiction of Labor Arbiters and the Commission -
(a) Except as otherwise provided under this Code, the Labor
Accordingly, a series of dialogues were held between Arbiters shall have original and exclusive jurisdiction to hear and
petitioners and private respondents. Even before the conclusion decide x x x the following cases involving all workers, whether
of said dialogues, the aforesaid petitioner Angel Roa issued agricultural or non-agricultural:
another Memorandum on October 1, 1990 informing private
respondents that they would be dismissed from work effective
16
(1) Unfair labor practice cases: ART. 217(c). Cases arising from the interpretation or
implementation of collective bargaining agreements and those
arising from the interpretation or enforcement of company
(2) Termination disputes;
personnel policies shall be disposed of by the Labor Arbiter by
referring the same to the grievance machinery and voluntary
x x x x x x x x x. arbitration as may be provided in said agreements. (As
amended by R.A. 6715).
The sole exception to the above rule can be found under Article
262 of the same Code, which provides: Petitioners theorize that since respondents questioned the
discharges, the main question for resolution is whether SMC had
Aricle 262. Jurisdiction over other labor disputes - The voluntary the management right or prerogative to effect the discharges on
arbitrator or panel of voluntary arbitrators, upon agreement of the ground of redundancy, and this necessarily calls for the
the parties, shall also hear and decide all other labor disputes interpretation or implementation of Article III (Job Security) in
including unfair labor practices and bargaining deadlocks. (As relation to Article IV (Grievance Machinery)of the CBA.[4]
added by R.A. 6715)
Petitioners theory does not hold water. There is no
We subjected the records of this case, particularly the CBA, to connection whatsoever between SMCs management prerogative
meticulous scrutiny and we find no agreement between SMC to effect the discharges and the interpretation or
and the respondent union that would state in unequivocal implementation of Articles III and IV of the CBA. The only
language that petitioners and the respondent union conform to relevant provision under Article III that may need interpretation
the submission of termination disputes and unfair labor or implementation is Section 2 which was cited herein. However,
practices to voluntary arbitration. Section 1, Article V of the as patiently pointed out by this court, said provision does not
CBA, cited by the herein petitioners, certainly does not provide come into play considering that the union never exercised its
so. Hence, consistent with the general rule under Article 217 (a) right to seek reconsideration of the discharges effected by the
of the Labor Code, the Labor Arbiter properly has jurisdiction company. It would have been different had the union sought
over the complaint filed by the respondent union on February reconsideration. Such recourse under Section 2 would have
25, 1991 for illegal dismissal and unfair labor practice. been treated as a grievance under Article IV (Grievance
Machinery) of the CBA, thus calling for the possible
interpretation or implementation of the entire provision on
Petitioners point however to Section 2, Article III of the Grievance Machinery as agreed upon by the parties. This was
CBA, under the heading Job Security, to show that the dispute is not the case however. The union brought the termination
a proper subject of the grievance procedure, viz: dispute directly to the Labor Arbiter rendering Articles III and IV
of the CBA inapplicable for the resolution of this case.
x x x The UNION, however, shall have the right to seek
reconsideration of any discharge, lay-off or disciplinary action, The discharges, petitioners also contend, call for the
and such requests for reconsideration shall be considered a interpretation or enforcement of company personnel policies,
dispute or grievance to be dealt with in accordance with the particulary SMCs personnel policies on lay-offs arising from
procedure outlined in Article IV hereof [on Grievance Machinery] redundacy, and so, they may be considered grievable and
x x x[3] (Emphasis ours) arbitrable by virtue of Article 2 17(c). Not necessarily
so. Company personnel policies are guiding principles stated in
Petitioners allege that respondent union requested management broad, long-range terms that express the philosophy or beliefs
for a reconsideration and review of the companys decision to of an organizations top authority regarding personnel
terminate the employment of the union members. By this act, matters. They deal with matters affecting efficiency and well-
petitioners argue, respondent union recognized that the being of employees and include, among others, the procedure in
questioned dismissal is a grievable dispute by virtue of Section the administration of wages, benefits, promotions, transfer and
2, Article III of the CBA. This allegation was strongly denied by other personnel movements which are usually not spelled out in
the respondent union. In a Memorandum filed for the public the collective agreement. The usual source of grievances,
respondent NLRC, the Solicitor General supported the position of however, is the rules and regulations governing disciplinary
the respondent union that it did not seek reconsideration from actions.[5] Judging therefrom, the questioned discharges due to
the SMC management in regard to the dismissal of the alleged redundancy can hardly be cosidered company personnel
employees. policies and therefore need not directly be subject to the
grievance machinery nor to voluntary arbitration.
Petitioners fail miserably to prove that, indeed, the
respondent union requested for a reconsideration or review of Third. Petitioners would like to persuade us that
the management decision to dismiss the private respondents. A respondents ULP claims are merely conclusory and cannot serve
punctilious examination of the records indubitably reveals that to vest jurisdiction to the Labor Arbiters. Petitioners argue with
at no time did the respondent union exercise its right to seek passion: How was the discharges (sic) right to self-organization
reconsideration of the companys move to terminate the restrained by their termination? Respondent did not show..
employment of the union members, which request for There is no allegation of the existence of anti-union animus or of
reconsideration would have triggered the application of Section the ultimate facts showing how the discharges affected the
2, Article III of the CBA, thus resulting in the treatment of the rights to self-organization of individual respondents. [6] In short,
dispute as a grievance to be dealt with in accordance with the petitioners maintain that respondents complaint does not allege
Grievance Machinery laid down in Article IV of, the CBA. Stated a genuine case for ULP.
differently, the filing of a request. for reconsideration by the
respondent union, which is the condition sine qua non to The Court is not convinced.
categorize the termination dispute and the ULP complaint as a
grievable dispute, was decidedly absent in the case at
bench. Hence, the respondent union acted well within their The complaint alleges that:
rights in filing their complaint for illegal dismissal and ULP
directly with the Labor Arbiter under Article 217 (a) of the Labor 5. Individual complainants are bona fide officers and members
Code. of complainant Ilaw at Buklod ng Manggagawa (IBM). They are
active and militant in the affairs and activities of the union.
Second. Petitioners insist that involved in the controversy
is the interpretation and implementation of the CBA which is xxx xxx xxx
grievable and arbitrable by law under Article 217(c) of the Labor
Code, viz:
17
23. The dismissal or lock-out from work of the individual redundancy. The important fact is that in all of these cases,
complainants clearly constitutes an act of unfair labor practices including the one at bar, all of the dismissed employees were
in the light of the fact that the work being performed by the officers and members of their respective unions, and their
individual complainants are being contracted out by the employers failed to give a satisfactory explanation as to why
respondent company, and, therefore, deprives individual this group of employees was singled out.
complainants of their right to work and it constitutes a criminal
violation of existing laws. It may be the case that employees other than union
members may have been terminated also by petitioner SMC on
xxx xxx xxx account of its redundancy program. If that is true, the
discharges may really be for a bona fide authorized cause under
Article 283[11] of the Labor Code. On the other hand, it is also
25. The acts of the respondent company in economically
possible that such may only be a clever scheme of the petitioner
coercing employees to accept payment of seperation and/or
company to camouflage its real intention of discriminating
retirement benefits, pending final resolution of the labor
against union members particularly the private respondents. In
disputes between the parties constitute acts of unfair labor
any case, these matters will be best ventilated in a hearing
practice in the light of the fact that there is undue interference,
before the Labor Arbiter.
restraint, and coercion of employees in the exercise of their right
to self-organization and collective bargaining.[7]
It is for the above reason that we cannot hold the
petitioners guilty of the ULP charge. This will be the task of the
Short of pre-empting the proceedings before the Labor
Labor Arbiter. We however find that based on the cicumstances
Arbiter, the above complaint, makes Out a genuine case for ULP.
surrounding this case and settled jurisprudence on the subject,
the complaint filed by the private respondents on
In Manila Pencil Co. v. CIR,[8] This Court had occasion to February 25, 1991 alleges facts sufficient to costitute a bona
observe that even where business conditions justified a lay-off of fide case of ULP, and therefore properly cognizable by the Labor
employees, unfair labor practices were committed in the form of Arbiter under Article 2 17(a) of the Labor Code. This is
discriminatory dismissal where only unionists were permanently consistent with the rule that jurisdictioin over the subject matter
dismissed. This was despite the valid excuse given by the Manila is determined by the allegations of the complaint. [12]
Pencil Company that the dismissal of the employees was due to
the reduction of the companys dollar allocations for importation
Finally, petitioners try to impress on this Court the strong
and that both union members and non-union members were
State policy on the promotion of voluntary modes of settlement
laid-off. The Court, thru Justice Makalintal, rebuffed the
of labor disputes crafted in the Constitution and the Labor Code
petitioner Company and said:
which dictate the submission of the CBA dispute to grievance
and arbitration.[13]
x x x The explanation, however, does not by any means account
for the permanent dismissal of five of the unionists, where it
In this regard, the response of the Solicitor General is apt:
does not appear that non-unionists were similarly dismissed.

Petitioners deserve commendation for divulging and bringing to


xxx xxx xxx
public respondents attention the noble legislative intent behind
the law mandating the inclusion of grievance and voluntary
And the discrimination shown by the Company strongly is arbitration provisions in the CBA. However, in the absence of an
confirmed by the fact that during the period from October 1958 express legal conferment thereof, jurisdiction cannot be
to August 17, 1959 it hired from fifteen to twenty new appropriated by an official or tribunal (sic) no matter how well-
employees and ten apprentices. It says these employees were intentioned it is, even in the pursuit of the clearest substantial
for its new lead factory, but is (sic) not shown that the five who right (Concurring Opinion of Justice Barredo,
had been permanently dismissed were not suitable for work in Estanislao v. Honrado, 114 SCRA 748, 29 June 1982).[14]
that new factory.

In the same manner, petitioners cannot arrogate into the powers


A similar ruling was made by this Court in Peoples Bank of voluntary arbitrators the original and exclusive jurisdiction of
and Trust Co. v. Peoples Bank and Trust Co. Employees Labor Arbiters over unfair labor practices, termination disputes,
Union[9] involving the lay-off by a bank of sixty- and claims for damages, in the absence of an express
five (65) employees who were active union members allegedly agreement between the parties in order for Article 262 [15] of the
by reason of retrechment. The Court likewise found the Labor Law to apply in the case at bar.[16]
employer in that case to have committed ULP in effecting the
discharges.
WHEREFORE, the instant petition is DISMISSED for lack of
merit and the resolutions of the National Labor Relations
This Court was more emphatic however in Bataan Shipyard Commission dated August 11, 1992 and October 29, 1992 are
and Engineering Co., Inc. v. NLRC, et al.:[10] hereby AFFIRMED.

Under the circumstances obtaining in this case, We are inclined SO ORDERED


to believe that the company had indeed been discriminatory in
selecting the employees who were to be retrenched. All of the
THIRD DIVISION[G. R. No. 138094. May 29, 2003]
retrenched employees are officers and members of the
NAFLU.The record of the case is bereft of any satisfactory
explanation from the Company regarding this situation. As such, MARILOU GUANZON APALISOK, petitioner, vs. RADIO
the action taken by the firm becomes highly suspect. It leads PHILIPPINES NETWORK RADIO STATION DYKC and
Us to conclude that the firm had been discriminating STATION MANAGER GEORGE SUAZO, respondents.
against membership in the NAFLU, an act which amounts
to interference in the employees exercise of their right DECISION
of self-organization. Under Art. 249 (now Art. 248) of the
Labor Code of the Philippines, such interference is considered an
act of unfair labor practice on the part of the Company x x x. CARPIO-MORALES, J.:
(Emphasis ours)
Before this Court is a petition for review on certiorari under
It matters not that the cause of termination in the above Rule 45 assailing the Court of Appeals Decision [1] of October 30,
cited cases was retrenchment while that in the instant case was 1998 and Resolution[2] of February 26, 1999.
18
On May 15, 1995, Marilou Gaunzon Apalisok (petitioner), 2. BACKWAGES (P14,600 X 6
then Production Chief of Radio Philippines Network (RPN) Station
DYKC, received a Memorandum[3] from Branches Operations months) ................................ P 88,817.00
Manager Gilito Datoc asking her to submit a written explanation
why no disciplinary action should be taken against her for
performance of acts hostile to RPN, and arrogant, disrespectful 3. MORAL AND EXEMPLARY
and defiant behavior towards her superior Station Manager
George Suazo. DAMAGES .................................. P100,000.00

Complying, petitioner submitted on May 16, 1995 her 4. SERVICE INCENTIVE LEAVES
Answer[4] to the memorandum.

(P14,600 divide by 30 days =


On May 31, 1995, petitioner received another
memorandum from the Administrative Manager of RPN,
P486.67 x 5 days = P2,433.35 x
informing her of the termination of her services effective the
close of regular office hours of June 15, 1995.
19 years ........................................ P 46,233.65
By letter of June 5, 1995, petitioner informed RPN, by letter
of June 5, 1995, of her decision to waive her right to resolve her 5. ATTORNEYS FEES (10%) .... P 37,375.16
case through the grievance machinery of RPN as provided for in
the Collective Bargaining Agreement (CBA) and to lodge her All other claims are hereby denied.
case before the proper government forum. She thereafter filed a
complaint against RPN DYKC and Suazo (respondents) for illegal
dismissal before the National labor Relations Commission, SO ORDERED. (Emphasis supplied)
Regional Arbitration Branch of Region 7 which referred it to the
National Conciliation and Mediation Board. Respondents motion for reconsideration[9] of the Award
having been denied by the voluntary arbitrator by Order of
By Submission Agreement[5] dated June 20, 1995 signed by November 21, 1995, they filed a petition for certiorari before
their respective counsels, petitioner and respondents agreed to this Court, docketed as G. R. No. 122841.
submit for voluntary arbitration the issue of whether petitioners
dismissal was valid and to abide by the decision of the voluntary By Resolution[10] of December 13, 1995, the Third Division
arbitrator. of this Court referred G. R. No. 122841 to the Court of Appeals,
following the case of Luzon Development Bank v. Association of
In her position paper[6] submitted before the voluntary Luzon Development Bank Employees, et al.[11]holding that
arbitrator, petitioner prayed that her dismissal be declared decisions or awards of a voluntary arbitrator or panel of
invalid and that she be awarded separation pay, backwages and arbitrators in labor cases are reviewable by the Court of
other benefits granted to her by the Labor Code since Appeals.
reinstatement is no longer feasible due to strained relations. She
also prayed that she be awarded P2,000,000.00 for moral The Court of Appeals, finding that the option of petitioner
damages and P500,000.00 for exemplary damages. not to subject the dispute to the grievance machinery provided
for in the CBA was tantamount to relinquishing her right to avail
Respondents on the other hand prayed for the dismissal of of the aid of a voluntary arbitrator in settling the dispute which
the complaint, arguing that the voluntary arbitrator had no likewise converted an unresolved grievance into a resolved one,
jurisdiction over the case and, assuming that he had, the held that the voluntary arbitrator did not have jurisdiction over
complaint is dismissible for lack of merit as petitioner was not petitioners complaint and accordingly nullified and set aside, by
illegally dismissed.[7] Decision of October 30, 1998, the voluntary arbitration award.

On October 18, 1995, the voluntary arbitrator rendered an Petitioners Motion for Reconsideration [12] of the Court of
Award[8] in favor of petitioner, the dispositive portion of which Appeals Decision having been denied by Resolution [13] of
reads: February 26, 1999, the present petition was filed which raises
the following issues:

WHEREFORE, above premises considered, this Voluntary


Arbitrator rules that the dismissal of complainant was 1. Whether or not the Voluntary Arbitrator had jurisdiction over
invalid. petitioners complaint, and

However, considering the impracticality of reinstatement 2. Whether or not respondents are guilty of estoppel.[14]
because of proven strained relation between the parties,
respondents, instead shall pay complainant the amount of FOUR Petitioner, citing Article 262 of the Labor Code of the
HUNDRED ELEVEN THOUSAND ONE HUNDRED TWENTY SIX Philippines, as amended which reads:
PESOS & SEVENTY-SIX CENTAVOS (P411,126.76) itemized as
follows:
ARTICLE 262. JURISDICTION OVER OTHER LABOR DISPUTES. The
Voluntary Arbitrator or panel of Voluntary
In summary, the total award is hereunder itemized: Arbitrators, upon agreement of the parties, shall hear and
decide all other labor disputes including unfair labor
1. SEPARATION PAY (P14,600.00 practices and bargaining deadlocks. (Emphasis and
underscoring supplied),

divide by 30 days multiplied by


contends that her option not to subject the dispute to the
grievance machinery of RPN did not amount to her relinquishing
15 days per year of service x 19 of her right to avail of voluntary arbitration as a mode of settling
it for she and respondents in fact agreed to have the dispute
years) ......................................... P138,700.95 settled by a voluntary arbitrator when they freely executed the
above-said Submission Agreement. She thus concludes that the
voluntary arbitrator has jurisdiction over the controversy. [15]
19
Petitioner contends in any event that even assuming that according to the length of service rendered by the availing
the voluntary arbitrator had no jurisdiction over the case, it employee.
would not be in keeping with settled jurisprudence to allow a
losing party to question the authority of the voluntary arbitrator Thereafter, the union requested LUDO to include in its
after it had freely submitted itself to its authority.[16] members period of service the time during which they rendered
arrastre services to LUDO through the CLAS so that they could
The petition is impressed with merit. get higher benefits. LUDO failed to act on the request. Thus, the
matter was submitted for voluntary arbitration.
The above-quoted Article 262 of the Labor Code provides
that upon agreement of the parties, the voluntary arbitrator The parties accordingly executed a submission agreement
can hear and decide all other labor disputes. raising the sole issue of the date of regularization of the workers
for resolution by the Voluntary Arbitrator.
Contrary to the finding of the Court of Appeals, voluntary
arbitration as a mode of settling the dispute was not forced In its decision dated April 18, 1997, the Voluntary
upon respondents. Both parties indeed agreed to submit the Arbitrator ruled that: (1) the respondent employees were
issue of validity of the dismissal of petitioner to the jurisdiction engaged in activities necessary and desirable to the business of
of the voluntary arbitrator by the Submission Agreement duly petitioner, and (2) CLAS is a labor-only contractor of petitioner.
[2]
signed by their respective counsels. It disposed of the case thus:

As the voluntary arbitrator had jurisdiction over the parties WHEREFORE, in view of the foregoing, this Voluntary Arbitrator
controversy, discussion of the second issue is no longer finds the claims of the complainants meritorious and so hold
necessary. that:

WHEREFORE, the Court of Appeals Decision of October a. the 214 complainants, as listed in the Annex A, shall be
30, 1998 is hereby SET ASIDE and the voluntary arbitration considered regular employees of the respondents six (6) months
Award of October 18, 1995 is hereby REINSTATED. from the first day of service at CLAS;

SO ORDERED. b. the said complainants, being entitled to the CBA benefits


during the regular employment, are awarded a) sick leave, b)
vacation leave & c) annual wage and salary increases during
SECOND DIVISION[G.R. No. 140960. January 20, 2003]
such period in the amount of FIVE MILLION SEVEN HUNDRED
SEVEN THOUSAND TWO HUNDRED SIXTY ONE PESOS AND SIXTY
LUDO & LUYM CORPORATION, petitioner, vs. FERDINAND ONE CENTAVOS (P5,707,261.61) as computed in Annex A;
SAORNIDO as voluntary arbitrator and
LUDO EMPLOYEES UNION (LEU) representing 214
c. the respondents shall pay attorneys fees of ten (10) percent
of its officers and members, respondents.
of the total award;

DECISION
d. an interest of twelve (12) percent per annum or one (1)
percent per month shall be imposed to the award from the date
QUISUMBING, J.: of promulgation until fully paid if only to speed up the payment
of these long over due CBA benefits deprived of the complaining
This petition for review on certiorari seeks to annul and set workers.
aside the decision[1] of the Court of Appeals promulgated on July
6, 1999 and its Order denying petitioners motion for Accordingly, all separation and/or retirement benefits shall be
reconsideration in CA-G.R. SP No. 44341. construed from the date of regularization aforementioned
subject only to the appropriate government laws and other
The relevant facts as substantially recited by the Court of social legislation.
Appeals in its decision are as follows:
SO ORDERED.[3]
Petitioner LUDO & LUYM CORPORATION (LUDO for brevity)
is a domestic corporation engaged in the manufacture of coconut In due time, LUDO filed a motion for reconsideration, which
oil, corn starch, glucose and related products. It operates a was denied. On appeal, the Court of Appeals affirmed in toto the
manufacturing plant located at Tupas Street, Cebu City and a decision of the Voluntary Arbitrator, thus:
wharf where raw materials and finished products are shipped
out.
WHEREFORE, finding no reversible error committed by
respondent voluntary arbitrator, the instant petition is hereby
In the course of its business operations, LUDO engaged the DISMISSED.
arrastre services of Cresencio Lu Arrastre Services (CLAS) for the
loading and unloading of its finished products at the
SO ORDERED.[4]
wharf. Accordingly, several arrastre workers were deployed by
CLAS to perform the services needed by LUDO.
Hence this petition. Before us, petitioner raises the
following issues:
These arrastre workers were subsequently hired, on
different dates, as regular rank-and-file employees of LUDO
every time the latter needed additional manpower services. Said I
employees thereafter joined respondent union, the LUDO
Employees Union (LEU), which acted as the exclusive bargaining WHETHER OR NOT BENEFITS CONSISTING OF SALARY
agent of the rank-and-file employees. INCREASES, VACATION LEAVE AND SICK LEAVE BENEFITS FOR
THE YEARS 1977 TO 1987 ARE ALREADY BARRED BY
On April 13, 1992, respondent union entered into a PRESCRIPTION WHEN PRIVATE RESPONDENTS FILED THEIR CASE
collective bargaining agreement with LUDO which provides IN JANUARY 1995;
certain benefits to the employees, the amount of which vary
20
II The Commission, its Regional Offices and the Regional Directors
of the Department of Labor and Employment shall not entertain
disputes, grievances or matters under the exclusive and original
WHETHER OR NOT A VOLUNTARY ARBITRATOR CAN AWARD
jurisdiction of the Voluntary Arbitrator or panel of Voluntary
BENEFITS NOT CLAIMED IN THE SUBMISSION AGREEMENT. [5]
Arbitrators and shall immediately dispose and refer the same to
the Grievance Machinery or Voluntary Arbitration provided in the
Petitioner contends that the appellate court gravely erred Collective Bargaining Agreement.
when it upheld the award of benefits which were beyond the
terms of submission agreement. Petitioner asserts that the
Art. 262. Jurisdiction over other labor disputes. The
arbitrator must confine its adjudication to those issues
Voluntary Arbitrator or panel of Voluntary Arbitrators, upon
submitted by the parties for arbitration, which in this case is the
agreement of the parties, shall also hear and decide all other
sole issue of the date of regularization of the workers.Hence, the
labor disputes including unfair labor practices and bargaining
award of benefits by the arbitrator was done in excess of
deadlocks.
jurisdiction.[6]

In construing the above provisions, we held in San Jose vs.


Respondents, for their part, aver that the three-year
NLRC, [9] that the jurisdiction of the Labor Arbiter and the
prescriptive period is reckoned only from the time the obligor
Voluntary Arbitrator or Panel of Voluntary Arbitrators over the
declares his refusal to comply with his obligation in clear and
cases enumerated in the Labor Code, Articles 217, 261 and
unequivocal terms. In this case, respondents maintain that
262, can possibly include money claims in one form or another.
LUDO merely promised to review the company records in [10]
Comparatively, in Reformist Union of R.B. Liner, Inc. vs.
response to respondents demand for adjustment in the date of
NLRC,[11] compulsory arbitration has been defined both as the
their regularization without making a categorical statement of
process of settlement of labor disputes by a government
refusal.[7] On the matter of the benefits, respondents argue that
agency which has the authority to investigate and to make an
the arbitrator is empowered to award the assailed benefits
award which is binding on all the parties, and as a mode of
because notwithstanding the sole issue of the date of
arbitration where the parties are compelled to accept the
regularization, standard companion issues on reliefs and
resolution of their dispute through arbitration by a third party
remedies are deemed incorporated. Otherwise, the whole
(emphasis supplied).[12] While a voluntary arbitrator is not part
arbitration process would be rendered purely academic and the
of the governmental unit or labor departments personnel, said
law creating it inutile.[8]
arbitrator renders arbitration services provided for under labor
laws.
The jurisdiction of Voluntary Arbitrator or Panel of Voluntary
Arbitrators and Labor Arbiters is clearly defined and specifically
Generally, the arbitrator is expected to decide only those
delineated in the Labor Code. The pertinent provisions of the
questions expressly delineated by the submission
Labor Code, read:
agreement. Nevertheless, the arbitrator can assume that he has
the necessary power to make a final settlement since arbitration
Art. 217. Jurisdiction of Labor Arbiters and the is the final resort for the adjudication of disputes. [13] The
Commission. --- (a) Except as otherwise provided under this succinct reasoning enunciated by the CA in support of its
Code the Labor Arbiters shall have original and exclusive holding, that the Voluntary Arbitrator in a labor controversy has
jurisdiction to hear and decide, within thirty (30) calendar days jurisdiction to render the questioned arbitral awards, deserves
after the submission of the case by the parties for decision our concurrence, thus:
without extension, even in the absence of stenographic notes,
the following cases involving all workers, whether agricultural or
In general, the arbitrator is expected to decide those questions
non-agricultural:
expressly stated and limited in the submission
agreement. However, since arbitration is the final resort for the
1. Unfair labor practice cases: adjudication of disputes, the arbitrator can assume that he has
the power to make a final settlement. Thus, assuming that the
2. Termination disputes; submission empowers the arbitrator to decide whether an
employee was discharged for just cause, the arbitrator in this
instance can reasonable assume that his powers extended
3. If accompanied with a claim for reinstatement, those cases beyond giving a yes-or-no answer and included the power to
that workers may file involving wage, rates of pay, hours of work reinstate him with or without back pay.
and other terms and conditions of employment;

In one case, the Supreme Court stressed that xxx the Voluntary
4. Claims for actual, moral, exemplary and other forms of Arbitrator had plenary jurisdiction and authority to interpret the
damages arising from the employer-employee relations; agreement to arbitrate and to determine the scope of his own
authority subject only, in a proper case, to the certiorari
xxx jurisdiction of this Court. The Arbitrator, as already indicated,
viewed his authority as embracing not merely the determination
of the abstract question of whether or not a performance bonus
Art. 261. Jurisdiction of Voluntary Arbitrators or panel of
was to be granted but also, in the affirmative case, the amount
Voluntary Arbitrators. The Voluntary Arbitrator or panel of
thereof.
Voluntary Arbitrators shall have original and exclusive
jurisdiction to hear and decide all unresolved grievances arising
from the interpretation or implementation of the Collective By the same token, the issue of regularization should be viewed
Bargaining Agreement and those arising from the interpretation as two-tiered issue. While the submission agreement mentioned
or enforcement of company personnel policies referred to in the only the determination of the date or regularization, law and
immediately preceding article. Accordingly, violations of a jurisprudence give the voluntary arbitrator enough leeway of
Collective Bargaining Agreement, except those which are gross authority as well as adequate prerogative to accomplish the
in character, shall no longer be treated as unfair labor practice reason for which the law on voluntary arbitration was created
and shall be resolved as grievances under the Collective speedy labor justice. It bears stressing that the underlying
Bargaining Agreement. For purposes of this article, gross reason why this case arose is to settle, once and for all, the
violations of Collective Bargaining Agreement shall mean ultimate question of whether respondent employees are entitled
flagrant and/or malicious refusal to comply with the economic to higher benefits. To require them to file another action for
provisions of such agreement. payment of such benefits would certainly undermine labor
proceedings and contravene the constitutional mandate
providing full protection to labor.[14]
21
As regards petitioners contention that the money claim in BELLOSILLO, J.:
this case is barred by prescription, we hold that this contention
is without merit. So is petitioners stance that the benefits CELESTINO VIVERO, in this petition for review, seeks the
claimed by the respondents, i.e., sick leave, vacation leave and reversal of the Decision of the Court of Appeals of 26 May 1999
13th-month pay, had already prescribed, considering the three- setting aside the Decision of the National Labor Relations
year period for the institution of monetary claims. [15] Such Commission of 28 May 1998 as well as its Resolution of 23 July
determination is a question of fact which must be ascertained 1998 denying his motion for its reconsideration, and reinstating
based on the evidence, both oral and documentary, presented the decision of the Labor Arbiter of 21 January 1997.
by the parties before the Voluntary Arbitrator. In this case, the
Voluntary Arbitrator found that prescription has not as yet set in
to bar the respondents claims for the monetary benefits Petitioner Vivero, a licensed seaman, is a member of the
awarded to them. Basic is the rule that findings of fact of Associated Marine Officers and Seamen's Union of the
administrative and quasi-judicial bodies, which have acquired Philippines (AMOSUP). The Collective Bargaining Agreement
expertise because their jurisdiction is confined to specific entered into by AMOSUP and private respondents provides,
matters, are generally accorded not only great respect but even among others -
finality.[16] Here, the Voluntary Arbitrator received the evidence
of the parties first-hand. No compelling reason has been shown ARTICLE XII
for us to diverge from the findings of the Voluntary Arbitrator,
especially since the appellate court affirmed his findings, that it
GRIEVANCE PROCEDURE
took some time for respondent employees to ventilate their
claims because of the repeated assurances made by the
petitioner that it would review the company records and xxxx
determine therefrom the validity of the claims, without
expressing a categorical denial of their claims. As elucidated by Sec. 3. A dispute or grievance arising in connection with the
the Voluntary Arbitrator: terms and provisions of this Agreement shall be adjusted in
accordance with the following procedure:
The respondents had raised prescription as defense. The
controlling law, as ruled by the High Court, is: 1. Any seaman who feels that he has been unjustly treated or
even subjected to an unfair consideration shall endeavor to
The cause of action accrues until the party obligated refuses xxx have said grievance adjusted by the designated representative
to comply with his duty. Being warded off by promises, the of the unlicensed department abroad the vessel in the following
workers not having decided to assert [their] right[s], [their] manner:
causes of action had not accrued (Citation omitted.)
A. Presentation of the complaint to his immediate superior.
Since the parties had continued their negotiations even after the
matter was raised before the Grievance Procedure and the B. Appeal to the head of the department in which the seaman
voluntary arbitration, the respondents had not refused to involved shall be employed.
comply with their duty. They just wanted the complainants to
present some proofs. The complainants cause of action had not
therefore accrued yet. Besides, in the earlier voluntary C. Appeal directly to the Master.
arbitration case aforementioned involving exactly the same
issue and employees similarly situated as the complainants, the Sec. 4. If the grievance cannnot be resolved under the provision
same defense was raised and dismissed by Honorable Thelma of Section 3, the decision of the Master shall govern at sea x x x
Jordan, Voluntary Arbitrator. x in foreign ports and until the vessel arrives at a port where the
Master shall refer such dispute to either the COMPANY or the
In fact, the respondents promised to correct their length of UNION in order to resolve such dispute. It is understood,
service and grant them the back CBA benefits if the however, if the dispute could not be resolved then both parties
complainants can prove they are entitled rendered the former in shall avail of the grievance procedure.
estoppel, barring them from raising the defense of laches or
prescription. To hold otherwise amounts to rewarding the Sec. 5. In furtherance of the foregoing principle, there is hereby
respondents for their duplicitous representation and abet them created a GRIEVANCE COMMITTEE to be composed of two
in a dishonest scheme against their workers.[17] COMPANY REPRESENTATIVES to be designated by the COMPANY
and two LABOR REPRESENTATIVES to be designated by the
Indeed, as the Court of Appeals concluded, under the UNION.
equitable principle of estoppel, it will be the height of injustice if
we will brush aside the employees claims on a mere Sec. 6. Any grievance, dispute or misunderstanding concerning
technicality, especially when it is petitioners own action that any ruling, practice, wages or working conditions in the
prevented them from interposing the claims within the COMPANY, or any breach of the Employment Contract, or any
prescribed period. dispute arising from the meaning or the application of the
provision of this Agreement or a claim of violation thereof or any
WHEREFORE, the petition is DENIED. The appealed complaint that any such crewmembers may have against the
decision of the Court of Appeals in CA-G.R. SP No. 44341 and the COMPANY, as well as complaint which the COMPANY may have
resolution denying petitioners motion for reconsideration, against such crewmembers shall be brought to the attention of
are AFFIRMED. Costs against petitioner. the GRIEVANCE COMMITTEE before either party takes any
action, legal or otherwise.

SO ORDERED.
Sec. 7. The COMMITTEE shall resolve any dispute within seven
(7) days from and after the same is submitted to it for resolution
SECOND DIVISION[G.R. No. 138938. October 24, 2000] and if the same cannot be settled by the COMMITTEE or if the
COMMITTEE fails to act on the dispute within the 7-day period
CELESTINO VIVIERO, petitioner, vs. COURT OF APPEALS, herein provided, the same shall be referred to a VOLUNTARY
HAMMONIA MARINE SERVICES, and HANSEATIC ARBITRATION COMMITTEE.
SHIPPING CO., LTD. respondents.
An "impartial arbitrator" will be appointed by mutual choice and
DECISION consent of the UNION and the COMPANY who shall hear and
22
decide the dispute or issue presented to him and his decision file his Complaint originally with POEA, then the Labor Arbiter to
shall be final and unappealable x x x x[1] whom the case was transferred would have to take cognizance
of the case.[7]
As found by the Labor Arbiter -
The NLRC then remanded the case to the Labor Arbiter for
further proceedings. On 3 July 1998 respondents filed a Motion
Complainant was hired by respondent as Chief Officer of the
for Reconsideration which was denied by the NLRC on 23 July
vessel "M.V. Sunny Prince" on 10 June 1994 under the terms and
1998.
conditions, to wit:

Thus, private respondents raised the case to the Court of


Duration of Contract - - - - 10 months
Appeals contending that the provision in the CBA requiring a
dispute which remained unresolved by the Grievance Committee
Basic Monthly Salary - - - - US $1,100.00 to be referred to a Voluntary Arbitration Committee, was
mandatory in character in view of the CBA between the
Hours of Work - - - - 44 hrs./week parties. They stressed that "since it is a policy of the state to
promote voluntary arbitration as a mode of settling labor
disputes, it is clear that the public respondent gravely abused its
Overtime - - - - 495 lump O.T. discretion in taking cognizance of a case which was still within
the mantle of the Voluntary Arbitration Commitees
Vacation leave with pay - - - - US $220.00/mo. jurisdiction."[8]

On grounds of very poor performance and conduct, refusal to On the other hand, petitioner argued -
perform his job, refusal to report to the Captain or the vessels
Engineers or cooperate with other ship officers about the (A)s strongly suggested by its very title, referral of cases of this
problem in cleaning the cargo holds or of the shipping pump and nature to the Voluntary Arbitration Committee is voluntary in
his dismal relations with the Captain of the vessel, complainant nature.Otherwise, the committee would not have been called
was repatriated on 15 July 1994. Voluntary Arbitration Committee but rather, a Compulsory
Arbitration Committee. Moreover, if the referral of cases of
On 01 August 1994, complainant filed a complaint for illegal similar nature to the Voluntary Arbitration Committee would be
dismissal at Associated Marine Officers and Seamans Union of deemed mandatory by virtue of the provisions in the CBA, the
the Philippines (AMOSUP) of which complainant was a [NLRC] would then be effectively deprived of its jurisdiction to
member. Pursuant to Article XII of the Collective Bargaining try, hear and decide termination disputes, as provided for under
Agreement, grievance proceedings were conducted; however, Article 217 of the Labor Code. Lastly, [respondents] ought to be
parties failed to reach and settle the dispute amicably, thus, on deemed to have waived their right to question the procedure
28 November 1994, complainant filed [a] complaint with the followed by [petitioner], considering that they have already filed
Philippine Overseas Employment Administration (POEA). [2] their Position Paper beforebelatedly filing a Motion to Dismiss x x
x x [9]
The law in force at the time petitioner filed his Complaint with
the POEA was EO No. 247.[3] But the Court of Appeals ruled in favor of private
respondents. It held that the CBA "is the law between the
parties and compliance therewith is mandated by the express
While the case was pending before the POEA, private
policy of the law."[10] Hence, petitioner should have followed the
respondents filed a Motion to Dismiss on the ground that the
provision in the CBA requiring the submission of the dispute to
POEA had no jurisdiction over the case considering petitioner
the Voluntary Arbitration Committee once the Grievance
Vivero's failure to refer it to a Voluntary Arbitration Committee in
Committee failed to settle the controversy.[11] According to the
accordance with the CBA between the parties. Upon the
Court of Appeals, the parties did not have the choice to
enactment of RA 8042, the Migrant Workers and Overseas
"volunteer" to refer the dispute to the Voluntary Arbitrator or a
Filipinos Act of 1995, the case was transferred to the
Panel of Arbitrators when there was already an agreement
Adjudication Branch of the National Labor Relations Commission.
requiring them to do so. "Voluntary Arbitration" means that it is
binding because of a prior agreement or contract, while
On 21 January 1997 Labor Arbiter Jovencio Ll. Mayor Jr., on "Compulsory Arbitration" is when the law declares the dispute
the basis of the pleadings and documents available on record, subject to arbitration, regardless of the consent or desire of the
rendered a decision dismissing the Complaint for want of parties.[12]
jurisdiction.[4] According to the Labor Arbiter, since the CBA of
the parties provided for the referral to a Voluntary Arbitration
The Court of Appeals further held that the Labor Code itself
Committee should the Grievance Committee fail to settle the
enumerates the original and exclusive jurisdiction of the
dispute, and considering the mandate of Art. 261 of the Labor
Voluntary Arbitrator or Panel of Voluntary Arbitrators, and
Code on the original and exclusive jurisdiction of Voluntary
prohibits the NLRC and the Regional Directors of the Department
Arbitrators, the Labor Arbiter clearly had no jurisdiction over the
of Labor and Employment (DOLE) from entertaining cases falling
case.[5]
under the same.[13] Thus, the fact that private respondents filed
their Position Paper first before filing their Motion to
Petitioner (complainant before the Labor Arbiter) appealed Dismiss was immaterial and did not operate to confer
the dismissal of his petition to the NLRC. On 28 May 1998 the jurisdiction upon the Labor Arbiter, following the well-settled
NLRC set aside the decision of the Labor Arbiter on the ground rule that jurisdiction is determined by law and not by consent or
that the record was clear that petitioner had exhausted his agreement of the parties or by estoppel.[14]
remedy by submitting his case to the Grievance Committee of
AMOSUP. Considering however that he could not obtain any
Finally, the appellate court ruled that a case falling under
settlement he had to ventilate his case before the proper
the jurisdiction of the Labor Arbiter as provided under Art. 217 of
forum, i.e., the Philippine Overseas Employment Administration.
[6] the Labor Code may be lodged instead with a Voluntary
The NLRC further held that the contested portion in the CBA
Arbitrator because the law prefers, or gives primacy, to
providing for the intercession of a Voluntary Arbitrator was not
voluntary arbitration instead of compulsory arbitration.
binding upon petitioner since both petitioner and private [15]
Consequently, the contention that the NLRC would be
respondents had to agree voluntarily to submit the case before
deprived of its jurisdiction to try, hear and decide termination
a Voluntary Arbitrator or Panel of Voluntary Arbitrators. This
disputes under Art. 217 of the Labor Code, should the instant
would entail expenses as the Voluntary Arbitrator chosen by the
dispute be referred to the Voluntary Arbitration Committee, is
parties had to be paid. Inasmuch however as petitioner chose to
23
clearly bereft of merit.[16] Besides, the Voluntary Arbitrator, any violation of Article 264 of this Code, including questions
whether acting solely or in a panel, enjoys in law the status of a involving the legality of strikes and lockouts; and, (6) Except
quasi-judicial agency independent of, and apart from, the NLRC claims for Employees Compensation, Social Security, Medicare
since his decisions are not appealable to the latter.[17] and maternity benefits, all other claims arising from employer-
employee relations, including those of persons in domestic or
household service, involving an amount exceeding five thousand
Celestino Vivero, in his petition for review assailing the
pesos (P5,000.00) regardless of whether accompanied with a
Decision of the Court of Appeals, alleges that the appellate court
claim for reinstatement.
committed grave abuse of discretion in holding that a Voluntary
Arbitrator or Panel of Voluntary Arbitrators, and not the
Adjudication Branch of the NLRC, has jurisdiction over his (b) The Commission shall have exclusive appellate jurisdiction
complaint for illegal dismissal. He claims that his complaintfor over all cases decided by Labor Arbiters.
illegal dismissal was undeniably a termination dispute and did
not, in any way, involve an "interpretation or implementation of (c) Cases arising from the interpretation of collective bargaining
collective bargaining agreement" or "interpretation" or agreements and those arising from the interpretation or
"enforcement" of company personnel policies.Thus, it should fall enforcement of company personnel policies shall be disposed of
within the original and exclusive jurisdiction of the NLRC and its by the Labor Arbiter by referring the same to the grievance
Labor Arbiter, and not with a Voluntary Arbitrator, in accordance machinery and voluntary arbitration as may be provided in said
with Art. 217 of the Labor Code. agreements (emphasis supplied).

Private respondents, on the other hand, allege that the However, any or all of these cases may, by agreement of
case is clearly one "involving the the parties, be submitted to a Voluntary Arbitrator or Panel of
proper interpretation and implementation of the Grievance Voluntary Arbitrators for adjudication. Articles 261 and 262 of
Procedure found in the Collective Bargaining Agreement (CBA) the Labor Code provide -
between the parties"[18]because of petitioners allegation in his
claim/assistance request form submitted to the Union, to wit:
Art. 261. Jurisdiction of Voluntary Arbitrators or Panel of
Voluntary Arbitrators. - The Voluntary Arbitrator or panel of
NATURE OF COMPLAINT Voluntary Arbitrators shall have original and exclusive
jurisdiction to hear and decide all unresolved grievances arising
3. Illegal Dismissal - Reason: (1) That in this case it was the from the interpretation or implementation of the Collective
master of M.V. SUNNY PRINCE Capt. Andersen who created the Bargaining Agreement and those arising from the interpretation
trouble with physical injury and stating false allegation; (2) That or enforcement of company personnel policies referred to in the
there was no proper procedure of grievance; (3) No proper immediately preceding article. Accordingly, violations of a
notice of dismissal. Collective Bargaining Agreement, except those which are gross
in character, shall no longer be treated as unfair labor practice
and shall be resolved as grievances under the Collective
Is there a Notice of dismissal? _x_ Yes or ____ No
Bargaining Agreement. For purposes of this article, gross
violations of Collective Bargaining Agreement shall mean
What date? 11 July 1994 flagrant and/or malicious refusal to comply with the economic
provisions of such agreement.
Is there a Grievance Procedure observed? ____ Yes or _x_ No[19]
The Commission, its Regional Offices and the Regional Directors
Private respondents further allege that the fact that of the Department of Labor and Employment shall not entertain
petitioner sought the assistance of his Union evidently shows disputes, grievances or matters under the exclusive and original
that he himself was convinced that his Complaint was within the jurisdiction of the Voluntary Arbitrator or panel of Voluntary
ambit of the jurisdiction of the grievance machinery and Arbitrators and shall immediately dispose and refer the same to
subsequently by a Panel of Voluntary Arbitrators as provided for the Grievance Machinery or Voluntary Arbitration provided in the
in their CBA, and as explicitly mandated by Art. 261 of the Labor Collective Bargaining Agreement.
Code.[20]
Art. 262. Jurisdiction Over Other Labor Disputes. - The Voluntary
Thus, the issue is whether the NLRC is deprived of Arbitrator or panel of Voluntary Arbitrators, upon agreement of
jurisdiction over illegal dismissal cases whenever a CBA provides the parties, shall also hear and decide all other labor disputes
for grievance machinery and voluntary arbitration including unfair labor practices and bargaining deadlocks
proceedings. Or, phrased in another way, does the dismissal of (emphasis supplied).
an employee constitute a "grievance between the parties," as
defined under the provisions of the CBA, and consequently, Private respondents attempt to justify the conferment of
within the exclusive original jurisdiction of the Voluntary jurisdiction over the case on the Voluntary Arbitrator on the
Arbitrators, thereby rendering the NLRC without jurisdiction to ground that the issue involves the proper interpretation and
decide the case? implementation of the Grievance Procedure found in the
CBA. They point out that when petitioner sought the assistance
On the original and exclusive jurisdiction of Labor Arbiters, of his Union to avail of the grievance machinery, he in effect
Art. 217 of the Labor Code provides - submitted himself to the procedure set forth in the CBA
regarding submission of unresolved grievances to a Voluntary
Arbitrator.
Art. 217. Jurisdiction of Labor Arbiters and the Commission.
- (a) Except as otherwise provided under this Code, the Labor
Arbiters shall have original and exclusive jurisdiction to hear and The argument is untenable. The case is primarily a
decide within thirty (30) calendar days after the submission of termination dispute. It is clear from the claim/assistance request
the case by the parties for decision without extension, even in form submitted by petitioner to AMOSUP that he was
the absence of stenographic notes, the following cases involving challenging the legality of his dismissal for lack of cause and
all workers, whether agricultural or non-agricultural: (1) Unfair lack of due process. The issue of whether there was proper
labor practice cases; (2) Termination disputes; (3) If interpretation and implementation of the CBA provisions comes
accompanied with a claim for reinstatement, those cases that into play only because the grievance procedure provided for in
workers may file involving wages, rates of pay, hours of work the CBA was not observed after he sought his Unions assistance
and other terms and conditions of employment; (4) Claims for in contesting his termination. Thus, the question to be resolved
actual, moral, exemplary and other forms of damages arising necessarily springs from the primary issue of whether there was
from the employer-employee relations; (5) Cases arising from a valid termination; without this, then there would be no reason
24
to invoke the need to interpret and implement the CBA legal conferment. In the same manner, petitioner cannot
provisions properly. arrogate into the powers of Voluntary Arbitrators the original
and exclusive jurisdiction of Labor Arbiters over unfair labor
practices, termination disputes, and claims for damages, in the
In San Miguel Corp. v. National Labor Relations
absence of an express agreement between the parties in order
Commission[21] this Court held that the phrase "all other labor
for Art. 262 of the Labor Code to apply in the case at bar. In
disputes" may include termination disputes provided that the
other words, the Court of Appeals is correct in holding that
agreement between the Union and the Company states "in
Voluntary Arbitration is mandatory in character if there is a
unequivocal language that [the parties] conform to the
specific agreement between the parties to that effect. It must be
submission of termination disputes and unfair labor practices to
stressed however that, in the case at bar, the use of the word
voluntary arbitration."[22] Ergo, it is not sufficient to merely say
"may" shows the intention of the parties to reserve the right of
that parties to the CBA agree on the principle that "all disputes"
recourse to Labor Arbiters.
should first be submitted to a Voluntary Arbitrator. There is a
need for an express stipulation in the CBA that illegal
termination disputes should be resolved by a Voluntary The CBA clarifies the proper procedure to be followed in
Arbitrator or Panel of Voluntary Arbitrators, since the same fall situations where the parties expressly stipulate to submit
within a special class of disputes that are generally within the termination disputes to the jurisdiction of a Voluntary Arbitrator
exclusive original jurisdiction of Labor Arbiters by express or Panel of Voluntary Arbitrators. For when the parties have
provision of law. Absent such express stipulation, the phrase "all validly agreed on a procedure for resolving grievances and to
disputes" should be construed as limited to the areas of conflict submit a dispute to voluntary arbitration then that procedure
traditionally within the jurisdiction of Voluntary Arbitrators, i.e., should be strictly observed. Non-compliance therewith cannot
disputes relating to contract-interpretation, contract- be excused, as petitioner suggests, by the fact that he is not
implementation, or interpretation or enforcement of company well-versed with the "fine prints" of the CBA. It was his
personnel policies. Illegal termination disputes - not falling responsibility to find out, through his Union, what the provisions
within any of these categories - should then be considered as a of the CBA were and how they could affect his rights. As
special area of interest governed by a specific provision of law. provided in Art. 241, par. (p), of the Labor Code -

In this case, however, while the parties did agree to make (p) It shall be the duty of any labor organization and its officers
termination disputes the proper subject of voluntary arbitration, to inform its members on the provisions of its constitution and
such submission remains discretionary upon the parties. A by-laws, collective bargaining agreement, the prevailing labor
perusal of the CBA provisions shows that Sec. 6, Art. XII relations system and all their rights and obligations under
(Grievance Procedure) of the CBA is the general agreement of existing labor laws.
the parties to refer grievances, disputes or misunderstandings
to a grievance committee, and henceforth, to a voluntary In fact, any violation of the rights and conditions of union
arbitration committee. The requirement of specificity is fulfilled membership is a "ground for cancellation of union registration or
by Art. XVII (Job Security) where the parties agreed - expulsion of officer from office, whichever is appropriate. At
least thirty percent (30%) of all the members of a union or any
Sec. 1. Promotion, demotion, suspension, dismissal or member or members especially concerned may report such
disciplinary action of the seaman shall be left to the discretion of violation to the Bureau [of Labor Relations] x x x x" [29]
the Master, upon consultation with the Company and notification
to the Union. This notwithstanding, any and all disciplinary It may be observed that under Policy Instruction No. 56 of
action taken on board the vessel shall be provided for in the Secretary of Labor, dated 6 April 1993, "Clarifying the
Appendix B of this Agreement x x x x [23] Jurisdiction Between Voluntary Arbitrators and Labor Arbiters
Over Termination Cases and Providing Guidelines for the
Sec. 4. x x x x Transfer, lay-off or discipline of seamen for Referral of Said Cases Originally Filed with the NLRC to the
incompetence, inefficiency, neglect of work, bad behavior, NCMB," termination cases arising in or resulting from the
perpetration of crime, drunkenness, insubordination, desertion, interpretation and implementation of collective bargaining
violation of x x x regulations of any port touched by the agreements and interpretation and enforcement of company
Companys vessel/s and other just and proper causes shall be at personnel policies which were initially processed at the various
Masters discretion x x x in the high seas or foreign ports. The steps of the plant-level Grievance Procedures under the parties'
Master shall refer the case/dispute upon reaching port and if not collective bargaining agreements fall within the original and
satisfactorily settled, the case/dispute may be referred to the exclusive jurisdiction of the voluntary arbitrator pursuant to Art.
grievance machinery or procedure hereinafter provided 217 (c) and Art. 261 of the Labor Code; and, if filed before the
(emphasis supplied).[24] Labor Arbiter, these cases shall be dismissed by the Labor
Arbiter for lack of jurisdiction and referred to the concerned
NCMB Regional Branch for appropriate action towards an
The use of the word "may" shows the intention of the
expeditious selection by the parties of a Voluntary Arbitrator or
parties to reserve the right to submit the illegal termination
Panel of Arbitrators based on the procedures agreed upon in the
dispute to the jurisdiction of the Labor Arbiter, rather than to a
CBA.
Voluntary Arbitrator. Petitioner validly exercised his option to
submit his case to a Labor Arbiter when he filed
his Complaint before the proper government agency. As earlier stated, the instant case is a termination dispute
falling under the original and exclusive jurisdiction of the Labor
Arbiter, and does not specifically involve the application,
Private respondents invoke Navarro III v.
implementation or enforcement of company personnel policies
Damasco[25] wherein the Court held that "it is the policy of the
contemplated in Policy Instruction No. 56. Consequently, Policy
state to promote voluntary arbitration as a mode of
Instruction No. 56 does not apply in the case at bar. In any case,
settling disputes."[26] It should be noted, however, that
private respondents never invoked the application of Policy
in Navarro III all the parties voluntarily submitted to the
Instruction No. 56 in their Position Papers, neither did they raise
jurisdiction of the Voluntary Arbitrator when they filed their
the question in their Motion to Dismiss which they filed nine (9)
respective position papers and submitted documentary
months after the filing of their Position Papers. At this late stage
evidence before him. Furthermore, they manifested during the
of the proceedings, it would not serve the ends of justice if this
initial conference that they were not questioning the authority of
case is referred back to a Voluntary Arbitrator considering that
the Voluntary Arbitrator.[27] In the case at bar, the dispute was
both the AMOSUP and private respondents have submitted to
never brought to a Voluntary Arbitrator for resolution; in fact,
the jurisdiction of the Labor Arbiter by filing their
petitioner precisely requested the Court to recognize the
respective Position Papers and ignoring the grievance procedure
jurisdiction of the Labor Arbiter over the case. The Court had
set forth in their CBA.
held in San Miguel Corp. v. NLRC[28] that neither officials nor
tribunals can assume jurisdiction in the absence of an express
25
After the grievance proceedings have failed to bring about voltage/pole who are team
a resolution, AMOSUP, as agent of petitioner, should have not exposed to the
informed him of his option to settle the case through voluntary risk
arbitration. Private respondents, on their part, should have
timely invoked the provision of their CBA requiring the referral of Collectors - no need for cash
their unresolved disputes to a Voluntary Arbitrator once it bond, no
became apparent that the grievance machinery failed to resolve need to reduce quota
it prior to the filing of the case before the proper tribunal. The and MAPL
private respondents should not have waited for nine (9) months
exclude confidential
from the filing of their Position Paper with the POEA before it CBU - include
employees
moved to dismiss the case purportedly for lack of jurisdiction. As
it is, private respondents are deemed to have waived their right maintenance of
Union security - closed shop
to question the procedure followed by petitioner, assuming that membership
they have the right to do so. Under their CBA, both Union and
respondent companies are responsible for selecting an impartial Contracting no need to consult
- consult first
out union
arbitrator or for convening an arbitration committee; [30] yet, it is
apparent that neither made a move towards this existing terms and
end. Consequently, petitioner should not be deprived of his All benefits - all terms
conditions
legitimate recourse because of the refusal of both Union and
respondent companies to follow the grievance procedure. Dec. 28, 1996-Dec. from Dec. 1,
Retroactivity -
27, 199(9) 1995
WHEREFORE, the Decision of the Court of Appeals is SET
ASIDE and the case is remanded to the Labor Arbiter to dispose Dissatisfied with the Decision, some alleged members of private
of the case with dispatch until terminated considering the undue respondent union (Union for brevity) filed a motion for
delay already incurred.SO ORDERED. intervention and a motion for reconsideration of the said
Decision. A separate intervention was likewise made by the
supervisor's union (FLAMES2) of petitioner corporation alleging
SPECIAL FIRST DIVISIONG.R. No. 127598 February 22,
that it has bona fide legal interest in the outcome of the
2000
case.3 The Court required the "proper parties" to file a comment
to the three motions for reconsideration but the Solicitor-
MANILA ELECTRIC COMPANY, petitioner, General asked that he be excused from filing the comment
vs. because the "petition filed in the instant case was granted" by
Hon. SECRETARY OF LABOR LEONARDO QUISUMBING and the Court.4 Consequently, petitioner filed its own consolidated
MERALCO EMPLOYEES and WORKERS ASSOCIATION comment. An "Appeal Seeking Immediate Reconsideration" was
(MEWA), respondent. also filed by the alleged newly elected president of the
Union.5 Other subsequent pleadings were filed by the parties
and intervenors.
YNARES-SANTIAGO, J.:

The issues raised in the motions for reconsideration had already


In the Decision promulgated on January 27, 1999, the Court
been passed upon by the Court in the January 27, 1999 decision.
disposed of the case as follows:
No new arguments were presented for consideration of the
Court. Nonetheless, certain matters will be considered herein,
WHEREFORE, the petition is granted and the orders of particularly those involving the amount of wages and the
public respondent Secretary of Labor dated August 19, retroactivity of the Collective Bargaining Agreement (CBA)
1996 and December 28, 1996 are set aside to the arbitral awards.
extent set forth above. The parties are directed to
execute a Collective Bargaining Agreement
Petitioner warns that if the wage increase of P2,200.00 per
incorporating the terms and conditions contained in the
month as ordered by the Secretary is allowed, it would simply
unaffected portions of the Secretary of Labor's orders
pass the cost covering such increase to the consumers through
of August 19, 1996 and December 28, 1996, and the
an increase in the rate of electricity. This is a non sequitur. The
modifications set forth above. The retirement fund
Court cannot be threatened with such a misleading argument.
issue is remanded to the Secretary of Labor for
An increase in the prices of electric current needs the approval
reception of evidence and determination of the legal
of the appropriate regulatory government agency and does not
personality of the MERALCO retirement fund.1
automatically result from a mere increase in the wages of
petitioner's employees. Besides, this argument presupposes that
The modifications of the public respondent's resolutions include petitioner is capable of meeting a wage increase. The All Asia
the following: Capital report upon which the Union relies to support its position
regarding the wage issue cannot be an accurate basis and
conclusive determinant of the rate of wage increase. Section 45
Secretary's of Rule 130 Rules of Evidence provides:
January 27, 1999 decision
resolution

P1,900.00 for 1995- Commercial lists and the like. Evidence of


Wages - P2,200.00 statements of matters of interest to persons engaged
96
in an occupation contained in a list, register, periodical,
modified to one or other published compilation is admissible as tending
X'mas bonus - 2 months
month to prove the truth of any relevant matter so stated if
that compilation is published for use by persons
remanded to the engaged in that occupation and is generally used and
Retirees - granted
Secretary relied upon by them therein.
Loan to coops - denied granted
Under the afore-quoted rule, statement of matters contained in
GHSIP, HMP a periodical, may be admitted only "if that compilation is
and granted up to published for use by persons engaged in that occupation and is
Housing loans - P60,000.00 granted generally used and relied upon by them therein." As correctly
held in our Decision dated January 27, 1999, the cited report is a
Signing bonus - denied granted mere newspaper account and not even a commercial list. At
most, it is but an analysis or opinion which carries no persuasive
Union leave - 40 days (typo error) 30 days
weight for purposes of this case as no sufficient figures to
High - not apply to those members of support
a it were presented. Neither did anybody testify to its
accuracy. It cannot be said that businessmen generally rely on
26
news items such as this in their occupation. Besides, no stated by public respondent in his assailed Order of
evidence was presented that the publication was regularly April 12, 1991 dismissing petitioner's Motion for
prepared by a person in touch with the market and that it is Reconsideration
generally regarded as trustworthy and reliable. Absent extrinsic
proof of their accuracy, these reports are not admissible. 6 In the
Anent the alleged lack of basis for the
same manner, newspapers containing stock quotations are not
retroactivity provisions awarded; we would
admissible in evidence when the source of the reports is
stress that the provision of law invoked by the
available.7 With more reason, mere analyses or projections of
Hospital, Article 253-A of the Labor Code,
such reports cannot be admitted. In particular, the source of the
speaks of agreements by and between the
report in this case can be easily made available considering that
parties, and not arbitral awards . . .
the same is necessary for compliance with certain governmental
requirements.
Therefore, in the absence of a specific provision of law
prohibiting retroactivity of the effectivity of arbitral
Nonetheless, by petitioner's own allegations, its actual total net
awards issued by the Secretary of Labor pursuant to
income for 1996 was P5.1 billion. 8 An estimate by the All Asia
Article 263(g) of the Labor Code, such as herein
financial analyst stated that petitioner's net operating income
involved, public respondent is deemed vested with
for the same year was about P5.7 billion, a figure which the
plenary and discretionary powers to determine the
Union relies on to support its claim. Assuming without admitting
effectivity thereof.
the truth thereof, the figure is higher than the P4.171 billion
allegedly suggested by petitioner as its projected net operating
income. The P5.7 billion which was the Secretary's basis for In the 1997 case of Mindanao Terminal, 17 the Court applied the
granting the P2,200.00 is higher than the actual net income of St. Luke's doctrine and ruled that:
P5.1 billion admitted by petitioner. It would be proper then to
increase this Court's award of P1,900.00 to P2,000.00 for the
In St. Luke's Medical Center v. Torres, a deadlock also
two years of the CBA award. For 1992, the agreed CBA wage
developed during the CBA negotiations between
increase for rank-and-file was P1,400.00 and was reduced to
management and the union. The Secretary of Labor
P1,350.00; for 1993; further reduced to P1,150.00 for 1994. For
assumed jurisdiction and ordered the retroaction of the
supervisory employees, the agreed wage increase for the years
CBA to the date of expiration of the previous CBA. As in
1992-1994 are P1,742.50, P1,682.50 and P1,442.50,
this case, it was alleged that the Secretary of Labor
respectively. Based on the foregoing figures, the P2,000.00
gravely abused its discretion in making his award
increase for the two-year period awarded to the rank-and-file is
retroactive. In dismissing this contention this Court
much higher than the highest increase granted to supervisory
held:
employees.9 As mentioned in the January 27, 1999 Decision, the
Court does "not seek to enumerate in this decision the factors
that should affect wage determination" because collective Therefore, in the absence of a specific
bargaining disputes particularly those affecting the national provision of law prohibiting retroactive of the
interest and public service "requires due consideration and effectivity of arbitral awards issued by the
proper balancing of the interests of the parties to the dispute Secretary of Labor pursuant to Article 263(g)
and of those who might be affected by the dispute." 10 The Court of the Labor Code, such as herein involved,
takes judicial notice that the new amounts granted herein are public respondent is deemed vested with
significantly higher than the weighted average salary currently plenary and discretionary powers to determine
enjoyed by other rank-and-file employees within the community. the effectivity thereof.
It should be noted that the relations between labor and capital is
impressed with public interest which must yield to the common
The Court in the January 27, 1999 Decision, stated that the CBA
good.11 Neither party should act oppressively against the other
shall be "effective for a period of 2 years counted from
or impair the interest or convenience of the public. 12 Besides,
December 28, 1996 up to December 27, 1999." Parenthetically,
matters of salary increases are part of management
this actually covers a three-year period. Labor laws are silent as
prerogative.13
to when an arbitral award in a labor dispute where the Secretary
had assumed jurisdiction by virtue of Article 263 (g) of the Labor
On the retroactivity of the CBA arbitral award, it is well to recall Code shall retroact. In general, a CBA negotiated within six
that this petition had its origin in the renegotiation of the months after the expiration of the existing CBA retroacts to the
parties' 1992-1997 CBA insofar as the last two-year period day immediately following such date and if agreed thereafter,
thereof is concerned. When the Secretary of Labor assumed the effectivity depends on the agreement of the parties. 18 On
jurisdiction and granted the arbitral awards, there was no the other hand, the law is silent as to the retroactivity of a CBA
question that these arbitral awards were to be given retroactive arbitral award or that granted not by virtue of the mutual
effect. However, the parties dispute the reckoning period when agreement of the parties but by intervention of the government.
retroaction shall commence. Petitioner claims that the award Despite the silence of the law, the Court rules herein that CBA
should retroact only from such time that the Secretary of Labor arbitral awards granted after six months from the expiration of
rendered the award, invoking the 1995 decision in Pier 8 the last CBA shall retroact to such time agreed upon by both
case14 where the Court, citing Union of Filipino Employees v. employer and the employees or their union. Absent such an
NLRC,15 said: agreement as to retroactivity, the award shall retroact to the
first day after the six-month period following the expiration of
the last day of the CBA should there be one. In the absence of a
The assailed resolution which incorporated the CBA to
CBA, the Secretary's determination of the date of retroactivity as
be signed by the parties was promulgated on June 5,
part of his discretionary powers over arbitral awards shall
1989, the expiry date of the past CBA. Based on the
control.
provision of Section 253-A, its retroactivity should be
agreed upon by the parties. But since no agreement to
that effect was made, public respondent did not abuse It is true that an arbitral award cannot per se be categorized as
its discretion in giving the said CBA a prospective an agreement voluntarily entered into by the parties because it
effect. The action of the public respondent is within the requires the interference and imposing power of the State thru
ambit of its authority vested by existing law. the Secretary of Labor when he assumes jurisdiction. However,
the arbitral award can be considered as an approximation of a
collective bargaining agreement which would otherwise have
On the other hand, the Union argues that the award should
been entered into by the parties. 19 The terms or periods set forth
retroact to such time granted by the Secretary, citing the 1993
in Article 253-A pertains explicitly to a CBA. But there is nothing
decision of St. Luke's.16
that would prevent its application by analogy to an arbitral
award by the Secretary considering the absence of an applicable
Finally, the effectivity of the Order of January 28, 1991, law. Under Article 253-A: "(I)f any such agreement is entered
must retroact to the date of the expiration of the into beyond six months, the parties shall agree on the duration
previous CBA, contrary to the position of petitioner. of retroactivity thereof." In other words, the law contemplates
Under the circumstances of the case, Article 253-A retroactivity whether the agreement be entered into before or
cannot be properly applied to herein case. As correctly after the said six-month period. The agreement of the parties
27
need not be categorically stated for their acts may be actually been distributed to them. The assailed Decision is
considered in determining the duration of retroactivity. In this AFFIRMED in all other respects.1wphi1.ntSO ORDERED.
connection, the Court considers the letter of petitioner's
Chairman of the Board and its President addressed to their
THIRD DIVISIONG.R. No. 80774 May 31, 1988
stockholders, which states that the CBA "for the rank-and-file
employees covering the period December 1, 1995 to November
30, 1997 is still with the Supreme Court," 20 as indicative of SAN MIGUEL CORPORATION, petitioner,
petitioner's recognition that the CBA award covers the said vs.
period. Earlier, petitioner's negotiating panel transmitted to the NATIONAL LABOR RELATIONS COMMISSION and RUSTICO
Union a copy of its proposed CBA covering the same period VEGA, respondents.
inclusive.21 In addition, petitioner does not dispute the allegation
that in the past CBA arbitral awards, the Secretary granted
retroactivity commencing from the period immediately following FELICIANO, J.:
the last day of the expired CBA. Thus, by petitioner's own
actions, the Court sees no reason to retroact the subject CBA In line with an Innovation Program sponsored by petitioner San
awards to a different date. The period is herein set at two (2)
Miguel Corporation ("Corporation;" "SMC") and under which
years from December 1, 1995 to November 30, 1997.
management undertook to grant cash awards to "all SMC
employees ... except [ED-HO staff, Division Managers and
On the allegation concerning the grant of loan to a cooperative, higher-ranked personnel" who submit to the Corporation Ideas
there is no merit in the union's claim that it is no different from and suggestions found to be beneficial to the Corporation,
housing loans granted by the employer. The award of loans for private respondent Rustico Vega submitted on 23 September
housing is justified because it pertains to a basic necessity of 1980 an innovation proposal. Mr. Vega's proposal was entitled
life. It is part of a privilege recognized by the employer and
"Modified Grande Pasteurization Process," and was supposed to
allowed by law. In contrast, providing seed money for the
eliminate certain alleged defects in the quality and taste of the
establishment of the employee's cooperative is a matter in
which the employer has no business interest or legal obligation. product "San Miguel Beer Grande:"
Courts should not be utilized as a tool to compel any person to
grant loans to another nor to force parties to undertake an Title of Proposal
obligation without justification. On the contrary, it is the
government that has the obligation to render financial
assistance to cooperatives and the Cooperative Code does not Modified Grande Pasteurization Process
make it an obligation of the employer or any private individual.22
Present Condition or Procedure
Anent the 40-day union leave, the Court finds that the same is a
typographical error. In order to avoid any confusion, it is herein At the early stage of beer grande production, several cases of
declared that the union leave is only thirty (30) days as granted
beer grande full goods were received by MB as returned beer
by the Secretary of Labor and affirmed in the Decision of this
fulls (RBF). The RBF's were found to have sediments and their
Court.
contents were hazy. These effects are usually caused by
underpasteurization time and the pasteurzation units for beer
The added requirement of consultation imposed by the grande were almost similar to those of the steinie.
Secretary in cases of contracting out for six (6) months or more
has been rejected by the Court. Suffice it to say that the
employer is allowed to contract out services for six months or Proposed lnnovation (Attach necessary information)
more. However, a line must be drawn between management
prerogatives regarding business operations per se and those In order to minimize if not elienate underpasteurization of
which affect the rights of employees, and in treating the latter, beer grande, reduce the speed of the beer grande pasteurizer
the employer should see to it that its employees are at least
thereby, increasing the pasteurization time and the
properly informed of its decision or modes of action in order to
pasteurization acts for grande beer. In this way, the self-life
attain a harmonious labor-management relationship and
enlighten the workers concerning their rights.23 Hiring of workers (sic) of beer grande will also be increased. 1
is within the employer's inherent freedom to regulate and is a
valid exercise of its management prerogative subject only to Mr. Vega at that time had been in the employ of petitioner
special laws and agreements on the matter and the fair Corporation for thirteen (1 3) years and was then holding the
standards of justice.24 The management cannot be denied the position of "mechanic in the Bottling Department of the SMC
faculty of promoting efficiency and attaining economy by a Plant Brewery situated in Tipolo, Mandaue City.
study of what units are essential for its operation. It has the
ultimate determination of whether services should be performed
by its personnel or contracted to outside agencies. While there Petitioner Corporation, however, did not find the aforequoted
should be mutual consultation, eventually deference is to be proposal acceptable and consequently refused Mr. Vega's
paid to what management decides.25 Contracting out of services subsequent demands for a cash award under the Innovation
is an exercise of business judgment or management Program. On 22 February 1983., a Complaint 2 (docketed as
prerogative.26 Absent proof that management acted in a Case No. RAB-VII-0170-83) was filed against petitioner
malicious or arbitrary manner, the Court will not interfere with Corporation with Regional Arbitration Branch No. VII (Cebu City)
the exercise of judgment by an employer.27 As mentioned in the of the then.", Ministry of Labor and Employment. Frivate
January 27, 1999 Decision, the law already sufficiently regulates
respondent Vega alleged there that his proposal "[had] been
this matter.28 Jurisprudence also provides adequate limitations,
accepted by the methods analyst and implemented by the
such that the employer must be motivated by good faith and the
contracting out should not be resorted to circumvent the law or Corporation [in] October 1980," and that the same "ultimately
must not have been the result of malicious or arbitrary and finally solved the problem of the Corporation in the
actions.29 These are matters that may be categorically production of Beer Grande." Private respondent thus claimed
determined only when an actual suit on the matter arises. entitlement to a cash prize of P60,000.00 (the maximum award
per proposal offered under the Innovation Program) and
attorney's fees.
WHEREFORE, the motion for reconsideration is PARTIALLY
GRANTED and the assailed Decision is MODIFIED as follows: (1)
the arbitral award shall retroact from December 1, 1995 to In an Answer With Counterclaim and Position Paper, 3 petitioner
November 30, 1997; and (2) the award of wage is increased Corporation alleged that private respondent had no cause of
from the original amount of One Thousand Nine Hundred Pesos action. It denied ever having approved or adopted Mr. Vega's
(P1,900.00) to Two Thousand Pesos (P2,000.00) for the years proposal as part of the Corporation's brewing procedure in the
1995 and 1996. This Resolution is subject to the monetary production of San Miguel Beer Grande. Among other things,
advances granted by petitioner to its rank-and-file employees petitioner stated that Mr. Vega's proposal was tumed down by
during the pendency of this case assuming such advances had
the company "for lack of originality" and that the same, "even if
28
implemented [could not] achieve the desired result." Petitioner While paragraph 3 above refers to "all money claims of
further alleged that the Labor Arbiter had no jurisdiction, Mr. workers," it is not necessary to suppose that the entire universe
Vega having improperly bypassed the grievance machinery of money claims that might be asserted by workers against their
procedure prescribed under a then existing collective bargaining employers has been absorbed into the original and exclusive
agreement between management and employees, and available jurisdiction of Labor Arbiters. In the first place, paragraph 3
administrative remedies provided under the rules of the should be read not in isolation from but rather within the context
Innovation Program. A counterclaim for moral and exemplary formed by paragraph 1 related to unfair labor practices),
damages, attorney's fees, and litigation expenses closed out paragraph 2 (relating to claims concerning terms and conditions
petitioner's pleading. of employment), paragraph 4 (claims relating to household
services, a particular species of employer-employee relations),
and paragraph 5 (relating to certain activities prohibited to
In an Order 4 dated 30 April 1986, the Labor Arbiter, noting that
employees or to employers).<re||an1w> It is evident that
the money claim of complainant Vega in this case is "not a
there is a unifying element which runs through paragraphs 1 to
necessary incident of his employment" and that said claim is not
5 and that is, that they all refer to cases or disputes arising out
among those mentioned in Article 217 of the Labor Code,
of or in connection with an employer-employee relationship. This
dismissed the complaint for lack of jurisdiction. However, in a
is, in other words, a situation where the rule of noscitur a sociis
gesture of "compassion and to show the government's concern
may be usefully invoked in clarifying the scope of paragraph 3,
for the workingman," the Labor Arbiter also directed petitioner
and any other paragraph of Article 217 of the Labor Code, as
to pay Mr. Vega the sum of P2,000.00 as "financial assistance."
amended. We reach the above conclusion from an examination
of the terms themselves of Article 217, as last amended by B.P.
The Labor Arbiter's order was subsequently appealed by both Blg. 227, and even though earlier versions of Article 217 of the
parties, private respondent Vega assailing the dismissal of his Labor Code expressly brought within the jurisdiction of the Labor
complaint for lack of jurisdiction and petitioner Corporation Arbiters and the NLRC "cases arising from employer employee
questioning the propriety of the award of "financial assistance" relations," 6 which clause was not expressly carried over, in
to Mr. Vega. Acting on the appeals, the public respondent printer's ink, in Article 217 as it exists today. For it cannot be
National Labor Relations Commission, on 4 September 1987, presumed that money claims of workers which do not arise out
rendered a Decision, 5 the dispositive portion of which reads: of or in connection with their employer-employee relationship,
and which would therefore fall within the general jurisdiction of
WHEREFORE, the appealed Order is hereby set aside and the regular courts of justice, were intended by the legislative
another udgment entered, order the respondent to pay the authority to be taken away from the jurisdiction of the courts
complainant the amount of P60,000.00 as explained above. and lodged with Labor Arbiters on an exclusive basis. The Court,
therefore, believes and so holds that the money claims of
workers" referred to in paragraph 3 of Article 217 embraces
SO ORDERED. money claims which arise out of or in connection with the
employer-employee relationship, or some aspect or incident of
In the present Petition for certiorari filed on 4 December 1987, such relationship. Put a little differently, that money claims of
petitioner Corporation, invoking Article 217 of the Labor Code, workers which now fall within the original and exclusive
seeks to annul the Decision of public respondent Commission in jurisdiction of Labor Arbiters are those money claims which have
Case No. RAB-VII-01 70-83 upon the ground that the Labor some reasonable causal connection with the employer-employee
Arbiter and the Commission have no jurisdiction over the subject relationship.
matter of the case.
Applying the foregoing reading to the present case, we note that
The jurisdiction of Labor Arbiters and the National Labor petitioner's Innovation Program is an employee incentive
Relations Commission is outlined in Article 217 of the Labor scheme offered and open only to employees of petitioner
Code, as last amended by Batas Pambansa Blg. 227 which took Corporation, more specifically to employees below the rank of
effect on 1 June 1982: manager. Without the existing employer-employee relationship
between the parties here, there would have been no occasion to
consider the petitioner's Innovation Program or the submission
ART. 217. Jurisdiction of Labor Arbiters and the commission.
by Mr. Vega of his proposal concerning beer grande; without that
(a) The Labor Arbiters shall have the original and exclusive
relationship, private respondent Vega's suit against petitioner
jurisdiction to hear and decide within thirty (30) working days
Corporation would never have arisen. The money claim of
after submission of the case by the parties for decision, the
private respondent Vega in this case, therefore, arose out of or
following cases involving are workers, whether agricultural or
in connection with his employment relationship with petitioner.
non-agricultural:

The next issue that must logically be confronted is whether the


1. Unfair labor practice cases;
fact that the money claim of private respondent Vega arose out
of or in connection with his employment relation" with petitioner
2. Those that workers may file involving wages, hours of work Corporation, is enough to bring such money claim within the
and other terms and conditions of employment; original and exclusive jurisdiction of Labor Arbiters.

3. All money claims of workers, including those based on non- In Molave Motor Sales, Inc. v. Laron, 7 the petitioner was a
payment or underpayment of wages, overtime compensation, corporation engaged in the sale and repair of motor vehicles,
separation pay and other benefits provided by law or while private respondent was the sales Manager of petitioner.
appropriate agreement, except claims for employees' Petitioner had sued private respondent for non-payment of
compensation, social security, medicare and maternity accounts which had arisen from private respondent's own
benefits; purchases of vehicles and parts, repair jobs on cars personally
owned by him, and cash advances from the corporation. At the
4. Cases involving household services; and pre-trial in the lower court, private respondent raised the
question of lack of jurisdiction of the court, stating that because
petitioner's complaint arose out of the employer-employee
5. Cases arising from any violation of Article 265 of this; Code, relationship, it fell outside the jurisdiction of the court and
including questions involving the legality of strikes and consequently should be dismissed. Respondent Judge did
lockouts. dismiss the case, holding that the sum of money and damages
sued for by the employer arose from the employer-employee
(b) The Commission shall have exclusive appellate jurisdiction relationship and, hence, fell within the jurisdiction of the Labor
over all cases decided by Labor Arbiters. (Emphasis supplied) Arbiter and the NLRC. In reversing the order of dismissal and
requiring respondent Judge to take cognizance of the case
29
below, this Court, speaking through Mme. Justice Melencio- terms and conditions of employment, but rather in the
Herrera, said: application of the general civil law. Clearly, such claims fall
outside the area of competence or expertise ordinarily ascribed
to Labor Arbiters and the NLRC and the rationale for granting
Before the enactment of BP Blg. 227 on June 1, 1982,
jurisdiction over such claims to these agencies disappears.
Labor Arbiters, under paragraph 5 of Article 217 of the
Labor Code had jurisdiction over" all other cases arising
from employer-employee relation, unless, expressly Applying the foregoing to the instant case, the Court notes that
excluded by this Code." Even then, the principle followed the SMC Innovation Program was essentially an invitation from
by this Court was that, although a controversy is between petitioner Corporation to its employees to submit innovation
an employer and an employee, the Labor Arbiters have no proposals, and that petitioner Corporation undertook to grant
jurisdiction if the Labor Code is not involved. In Medina vs. cash awards to employees who accept such invitation and
Castro-Bartolome, 11 SCRA 597, 604, in negating whose innovation suggestions, in the judgment of the
jurisdiction of the Labor Arbiter, although the parties were Corporation's officials, satisfied the standards and requirements
an employer and two employees, Mr. Justice Abad Santos of the Innovation Program 10 and which, therefore, could be
stated: translated into some substantial benefit to the Corporation.
Such undertaking, though unilateral in origin, could nonetheless
ripen into an enforceable contractual (facio ut des) 11 obligation
The pivotal question to Our mind is whether or not the
on the part of petitioner Corporation under certain
Labor Code has any relevance to the reliefs sought by the
circumstances. Thus, whether or not an enforceable contract,
plaintiffs. For if the Labor Code has no relevance, any
albeit implied arid innominate, had arisen between petitioner
discussion concerning the statutes amending it and
Corporation and private respondent Vega in the circumstances
whether or not they have retroactive effect is unnecessary.
of this case, and if so, whether or not it had been breached, are
preeminently legal questions, questions not to be resolved by
It is obvious from the complaint that the plaintiffs have not referring to labor legislation and having nothing to do with
alleged any unfair labor practice. Theirs is a simple action wages or other terms and conditions of employment, but rather
for damages for tortious acts allegedly committed by the having recourse to our law on contracts.
defendants. Such being the case, the governing statute is
the Civil Code and not the Labor Code. It results that the
WEREFORE, the Petition for certiorari is GRANTED. The decision
orders under review are based on a wrong premise.
dated 4 September 1987 of public respondent National Labor
Relations Commission is SET ASIDE and the complaint in Case
And in Singapore Airlines Limited v. Pao, 122 SCRA 671, No. RAB-VII-0170-83 is hereby DISMISSED, without prejudice to
677, the following was said: the right of private respondent Vega to file a suit before the
proper court, if he so desires. No pronouncement as to costs.SO
Stated differently, petitioner seeks protection under the ORDERED.
civil laws and claims no benefits under the Labor Code.
The primary relief sought is for liquidated damages for SECOND DIVISION February 13, 2008 G.R. No. 163101
breach of a contractual obligation. The other items
demanded are not labor benefits demanded by workers BENGUET CORPORATION, Petitioner,- versus - DEPARTMENT
generally taken cognizance of in labor disputes, such as OF ENVIRONMENT AND NATURAL RESOURCES-MINES
payment of wages, overtime compensation or separation ADJUDICATION BOARD and J.G. REALTY AND
pay. The items claimed are the natural consequences MINING CORPORATION,Respondents.
flowing from breach of an obligation, intrinsically a civil x----------------------------------------------------------------------------------------
dispute. -x
VELASCO, JR., J.:

In the case below, PLAINTIFF had sued for monies loaned The instant petition under Rule 65 of the Rules of Court seeks
to DEFENDANT, the cost of repair jobs made on his the annulment of the December 2, 2002 Decision [1]and March
personal cars, and for the purchase price of vehicles and 17, 2004 Resolution[2] of the Department of Environment and
parts sold to him. Those accounts have no relevance to Natural Resources-Mining Adjudication Board (DENR-MAB) in
the Labor Code. The cause of action was one under the MAB Case No. 0124-01 (Mines Administrative Case No. R-M-
civil laws, and it does not breach any provision of the 2000-01) entitled Benguet Corporation (Benguet) v. J.G. Realty
Labor Code or the contract of employment of DEFENDANT. and Mining Corporation (J.G. Realty). The December 2, 2002
Hence the civil courts, not the Labor Arbiters and the NLRC Decision upheld the March 19, 2001 Decision[3] of the MAB Panel
should have jurisdiction. 8 of Arbitrators (POA) which canceled the Royalty Agreement with
Option to Purchase (RAWOP) dated June 1, 1987[4] between
Benguet and J.G. Realty, and excluded Benguet from the joint
It seems worth noting that Medina v. Castro-Bartolome, referred Mineral Production Sharing Agreement (MPSA) application over
to in the above excerpt, involved a claim for damages by two (2) four mining claims. The March 17, 2004 Resolution denied
employees against the employer company and the General Benguets Motion for Reconsideration.
Manager thereof, arising from the use of slanderous language on
the occasion when the General Manager fired the two (2) The Facts
employees (the Plant General Manager and the Plant
Comptroller). The Court treated the claim for damages as "a On June 1, 1987, Benguet and J.G. Realty entered into a RAWOP,
wherein J.G. Realty was acknowledged as the owner of four
simple action for damages for tortious acts" allegedly committed
mining claims respectively named as Bonito-I, Bonito-II, Bonito-
by private respondents, clearly if impliedly suggesting that the
III, and Bonito-IV, with a total area of 288.8656 hectares,
claim for damages did not necessarily arise out of or in situated in Barangay Luklukam, Sitio Bagong
connection with the employer-employee relationship. Singapore Bayan, Municipality of Jose Panganiban, Camarines Norte. The
Airlines Limited v. Pao, also cited in Molave, involved a claim parties also executed a Supplemental Agreement [5] dated June 1,
for liquidated damages not by a worker but by the employer 1987. The mining claims were covered by MPSA Application No.
company, unlike Medina. The important principle that runs APSA-V-0009 jointly filed by J.G. Realty as claimowner and
through these three (3) cases is that where the claim to the Benguet as operator.
principal relief sought 9 is to be resolved not by reference to the
Labor Code or other labor relations statute or a collective In the RAWOP, Benguet obligated itself to perfect the rights to
bargaining agreement but by the general civil law, the the mining claims and/or otherwise acquire the mining rights to
jurisdiction over the dispute belongs to the regular courts of the mineral claims. Within 24 months from the execution of the
justice and not to the Labor Arbiter and the NLRC. In such RAWOP, Benguet should also cause the examination of the
situations, resolution of the dispute requires expertise, not in mining claims for the purpose of determining whether or not
they are worth developing with reasonable probability of
labor management relations nor in wage structures and other
profitable production. Benguet undertook also to furnish J.G.
30
Realty with a report on the examination, within a reasonable Therefrom, Benguet filed a Notice of Appeal [11] with the MAB on
time after the completion of the examination. Moreover, also April 23, 2001, docketed as Mines Administrative Case No. R-M-
within the examination period, Benguet shall conduct all 2000-01. Thereafter, the MAB issued the assailed December 2,
necessary exploration in accordance with a prepared exploration 2002 Decision. Benguet then filed a Motion for Reconsideration
program. If it chooses to do so and before the expiration of the of the assailed Decision which was denied in the March 17,
examination period, Benguet may undertake to develop the 2004Resolution of the MAB. Hence, Benguet filed the instant
mining claims upon written notice to J.G. Realty. Benguet must petition.
then place the mining claims into commercial productive stage
within 24 months from the written notice. [6] It is also provided in The Issues
the RAWOP that if the mining claims were placed in commercial
production by Benguet, J.G. Realty should be entitled to a royalty
of five percent (5%) of net realizable value, and to royalty for 1. There was serious and palpable error
any production done by Benguet whether during the when the Honorable Board failed to rule that the
examination or development periods. contractual obligation of the parties to arbitrate under
the Royalty Agreement is mandatory.
Thus, on August 9, 1989, the Executive Vice-President of
Benguet, Antonio N. Tachuling, issued a letter informing J.G. 2. The Honorable Board exceeded its
Realty of its intention to develop the mining claims. However, on jurisdiction when it sustained the cancellation of the
February 9, 1999, J.G. Realty, through its President, Johnny L. Royalty Agreement for alleged breach of contract
Tan, then sent a letter to the President of Benguet informing the despite the absence of evidence.
latter that it was terminating the RAWOP on the following
grounds: 3. The Questioned Decision of the
Honorable Board in cancelling the RAWOP prejudice[d]
a. The fact that your company has failed to the substantial rights of Benguet under the contract to
perform the obligations set forth in the RAWOP, i.e., to the unjust enrichment of JG Realty.[12]
undertake development works within 2 years from the
execution of the Agreement;
Restated, the issues are: (1) Should the controversy have first
b. Violation of the Contract by allowing high been submitted to arbitration before the POA took cognizance of
graders to operate on our claim. the case?; (2) Was the cancellation of the RAWOP supported by
evidence?; and (3) Did the cancellation of the RAWOP amount to
c. No stipulation was provided with respect unjust enrichment of J.G. Realty at the expense of Benguet?
to the term limit of the RAWOP. The Courts Ruling

d. Non-payment of the royalties thereon as Before we dwell on the substantive issues, we find that
provided in the RAWOP.[7] the instant petition can be denied outright as Benguet resorted
to an improper remedy.
The last paragraph of Section 79 of Republic Act No. (RA) 7942
In response, Benguets Manager for Legal Services, or the Philippine Mining Act of 1995 states, A petition for review
Reynaldo P. Mendoza, wrote J.G. Realty a letter dated March 8, by certiorari and question of law may be filed by the aggrieved
1999,[8] therein alleging that Benguet complied with its party with the Supreme Court within thirty (30) days from
obligations under the RAWOP by investing PhP 42.4 million to receipt of the order or decision of the [MAB].
rehabilitate the mines, and that the commercial operation was
hampered by the non-issuance of a Mines Temporary Permit by However, this Court has already invalidated such provision
the Mines and Geosciences Bureau (MGB) which must be in Carpio v. Sulu Resources Development Corp.,[13]ruling that a
considered as force majeure, entitling Benguet to an extension decision of the MAB must first be appealed to the Court of
of time to prosecute such permit. Benguet further claimed that Appeals (CA) under Rule 43 of the Rules of Court, before
the high graders mentioned by J.G. Realty were already recourse to this Court may be had. We held, thus:
operating prior to Benguets taking over of the premises, and
that J.G. Realty had the obligation of ejecting such small scale To summarize, there are sufficient legal
miners. Benguet also alleged that the nature of the mining footings authorizing a review of the MAB Decision
business made it difficult to specify a time limit for the RAWOP. under Rule 43 of the Rules of Court. First, Section 30 of
Benguet then argued that the royalties due to J.G. Realty were in Article VI of the 1987 Constitution, mandates that [n]o
fact in its office and ready to be picked up at any time. It law shall be passed increasing the appellate jurisdiction
appeared that, previously, the practice by J.G. Realty was to of the Supreme Court as provided in this Constitution
pick-up checks from Benguet representing such royalties. without its advice and consent. On the other hand,
However, starting August 1994, J.G. Realty allegedly refused to Section 79 of RA No. 7942 provides that decisions of
collect such checks from Benguet. Thus, Benguet posited that the MAB may be reviewed by this Court on a petition
there was no valid ground for the termination of the RAWOP. It for review by certiorari. This provision is obviously an
also reminded J.G. Realty that it should submit the disagreement expansion of the Courts appellate jurisdiction, an
to arbitration rather than unilaterally terminating the RAWOP. expansion to which this Court has not consented.
Indiscriminate enactment of legislation enlarging the
On June 7, 2000, J.G. Realty filed a Petition for appellate jurisdiction of this Court would unnecessarily
Declaration of Nullity/Cancellation of the RAWOP [9] with the burden it.
Legaspi City POA, Region V, docketed as DENR Case No. 2000- Second, when the Supreme Court, in the
01 and entitled J.G. Realty v. Benguet. exercise of its rule-making power, transfers to the CA
pending cases involving a review of a quasi-judicial
On March 19, 2001, the POA issued a Decision, [10] dwelling upon bodys decisions, such transfer relates only to
the issues of (1) whether the arbitrators had jurisdiction over the procedure; hence, it does not impair the substantive
case; and (2) whether Benguet violated the RAWOP justifying and vested rights of the parties. The aggrieved partys
the unilateral cancellation of the RAWOP by J.G. Realty. The right to appeal is preserved; what is changed is only
dispositive portion stated: the procedure by which the appeal is to be made or
decided. The parties still have a remedy and a
WHEREFORE, premises considered, the June competent tribunal to grant this remedy.
01, 1987 [RAWOP] and its Supplemental Agreement is
hereby declared cancelled and without effect. BENGUET Third, the Revised Rules of Civil Procedure
is hereby excluded from the joint MPSA Application over included Rule 43 to provide a uniform rule on appeals
the mineral claims denominated as BONITO-I, BONITO- from quasi-judicial agencies. Under the rule, appeals
II, BONITO-III and BONITO-IV. from their judgments and final orders are now required
to be brought to the CA on a verified petition for review.
SO ORDERED. A quasi-judicial agency or body has been defined as an
organ of government, other than a court or legislature,
which affects the rights of private parties through
either adjudication or rule-making. MAB falls under this
31
definition; hence, it is no different from the other quasi- Thus, Benguet argues that the POA should have first referred the
judicial bodies enumerated under Rule 43. Besides, the case to voluntary arbitration before taking cognizance of the
introductory words in Section 1 of Circular No. 1- case, citing Sec. 2 of RA 876 on persons and matters subject to
91among these agencies areindicate that the arbitration.
enumeration is not exclusive or conclusive and
acknowledge the existence of other quasi-judicial On the other hand, in denying such argument, the POA ruled
agencies which, though not expressly listed, should be that:
deemed included therein.
While the parties may establish such stipulations
Fourth, the Court realizes that under Batas clauses, terms and conditions as they may deem
Pambansa (BP) Blg. 129 as amended by RA No. 7902, convenient, the same must not be contrary to law and
factual controversies are usually involved in decisions public policy. At a glance, there is nothing wrong with
of quasi-judicial bodies; and the CA, which is likewise the terms and conditions of the agreement. But to state
tasked to resolve questions of fact, has more elbow that an aggrieved party cannot initiate an action
room to resolve them. By including questions of fact without going to arbitration would be tying ones hand
among the issues that may be raised in an appeal from even if there is a law which allows him to do so. [17]
quasi-judicial agencies to the CA, Section 3 of Revised
Administrative Circular No. 1-95 and Section 3 of Rule
43 explicitly expanded the list of such issues. The MAB, meanwhile, denied Benguets contention on the
ground of estoppel, stating:
According to Section 3 of Rule 43, [a]n appeal
under this Rule may be taken to the Court of Appeals Besides, by its own act, Benguet is already estopped in
within the period and in the manner herein provided questioning the jurisdiction of the Panel of Arbitrators
whether the appeal involves questions of fact, of law, to hear and decide the case. As pointed out in the
or mixed questions of fact and law. Hence, appeals appealed Decision, Benguet initiated and filed an
from quasi-judicial agencies even only on questions of Adverse Claim docketed as MAC-R-M-2000-02 over the
law may be brought to the CA. same mining claims without undergoing contractual
arbitration. In this particular case (MAC-R-M-2000-02)
Fifth, the judicial policy of observing the now subject of the appeal, Benguet is likewise in
hierarchy of courts dictates that direct resort from estoppel from questioning the competence of the Panel
administrative agencies to this Court will not be of Arbitrators to hear and decide in the summary
entertained, unless the redress desired cannot be proceedings J.G. Realtys petition, when Benguet itself
obtained from the appropriate lower tribunals, or unless did not merely move for the dismissal of the case but
exceptional and compelling circumstances justify also filed an Answer with counterclaim seeking
availment of a remedy falling within and calling for the affirmative reliefs from the Panel of Arbitrators.[18]
exercise of our primary jurisdiction.[14]

Moreover, the MAB ruled that the contractual provision on


The above principle was reiterated in Asaphil Construction and arbitration merely provides for an additional forum or venue and
Development Corporation v. Tuason, Jr. (Asaphil).[15] However, does not divest the POA of the jurisdiction to hear the case. [19]
the Carpio ruling was not applied to Asaphil as the petition in
the latter case was filed in 1999 or three years before the In its July 20, 2004 Comment, [20] J.G. Realty reiterated the above
promulgation of Carpio in 2002. Here, the petition was filed on rulings of the POA and MAB. It argued that RA 7942 or the
April 28, 2004 when the Carpio decision was already applicable, Philippine Mining Act of 1995 is a special law which should
thus Benguet should have filed the appeal with the CA. prevail over the stipulations of the parties and over a general
law, such as RA 876. It also argued that the POA cannot be
Petitioner having failed to properly appeal to the CA considered as a court under the contemplation of RA 876 and
under Rule 43, the decision of the MAB has become final and that jurisprudence saying that there must be prior resort to
executory. On this ground alone, the instant petition must be arbitration before filing a case with the courts is inapplicable to
denied. the instant case as the POA is itself already engaged in
arbitration.
Even if we entertain the petition although Benguet
skirted the appeal to the CA via Rule 43, still, the December 2, On this issue, we rule for Benguet.
2002 Decision and March 17, 2004 Resolution of the DENR-MAB Sec. 2 of RA 876 elucidates the scope of arbitration:
in MAB Case No. 0124-01 should be maintained.
Section 2. Persons and matters subject to
First Issue: The case should have first been brought to arbitration.Two or more persons or parties may
voluntary arbitration before the POA submit to the arbitration of one or more
arbitrators any controversy existing between
Secs. 11.01 and 11.02 of the RAWOP pertinently provide: them at the time of the submission and which
may be the subject of an action, or the parties to
11.01 Arbitration any contract may in such contract agree to settle
by arbitration a controversy thereafter arising
Any disputes, differences or disagreements between between them. Such submission or contract shall
BENGUET and the OWNER with reference to anything be valid, enforceable and irrevocable, save upon
whatsoever pertaining to this Agreement that cannot such grounds as exist at law for the revocation of
be amicably settled by them shall not be cause of any any contract.
action of any kind whatsoever in any court or
administrative agency but shall, upon notice of one Such submission or contract may include
party to the other, be referred to a Board of Arbitrators question[s] arising out of valuations, appraisals or other
consisting of three (3) members, one to be selected by controversies which may be collateral, incidental,
BENGUET, another to be selected by the OWNER and precedent or subsequent to any issue between the
the third to be selected by the aforementioned two parties. (Emphasis supplied.)
arbitrators so appointed.

xxxx In RA 9285 or the Alternative Dispute Resolution Act of 2004, the


11.02 Court Action Congress reiterated the efficacy of arbitration as an alternative
mode of dispute resolution by stating in Sec. 32 thereof that
No action shall be instituted in court as to any matter in domestic arbitration shall still be governed by RA 876. Clearly, a
dispute as hereinabove stated, except to enforce the contractual stipulation that requires prior resort to voluntary
decision of the majority of the Arbitrators.[16] arbitration before the parties can go directly to court is not
illegal and is in fact promoted by the State. Thus, petitioner
correctly cites several cases whereby arbitration clauses have
been upheld by this Court.[21]
32
governmental unit or labor departments
Moreover, the contention that RA 7942 prevails over RA 876 personnel, said arbitrator renders arbitration services
presupposes a conflict between the two laws. Such is not the provided for under labor laws.[23] (Emphasis supplied.)
case here. To reiterate, availment of voluntary arbitration before
resort is made to the courts or quasi-judicial agencies of the
government is a valid contractual stipulation that must be There is a clear distinction between compulsory and voluntary
adhered to by the parties. As stated in Secs. 6 and 7 of RA 876: arbitration. The arbitration provided by the POA is compulsory,
while the nature of the arbitration provision in the RAWOP is
Section 6. Hearing by court.A party voluntary, not involving any government agency. Thus, J.G.
aggrieved by the failure, neglect or refusal of Realtys argument on this matter must fail.
another to perform under an agreement in As to J.G. Realtys contention that the provisions of RA 876
writing providing for arbitration may petition the cannot apply to the instant case which involves an
court for an order directing that such arbitration administrative agency, it must be pointed out that Section 11.01
proceed in the manner provided for in such of the RAWOP states that:
agreement. Five days notice in writing of the hearing
of such application shall be served either personally or [Any controversy with regard to the contract] shall not
by registered mail upon the party in default. The court be cause of any action of any kind whatsoever in any
shall hear the parties, and upon being satisfied court or administrative agency but shall, upon notice
that the making of the agreement or such failure of one party to the other, be referred to a Board of
to comply therewith is not in issue, shall make an Arbitrators consisting of three (3) members, one to be
order directing the parties to proceed to selected by BENGUET, another to be selected by the
arbitration in accordance with the terms of the OWNER and the third to be selected by the
agreement. If the making of the agreement or aforementioned two arbiters so appointed.
[24]
default be in issue the court shall proceed to (Emphasis supplied.)
summarily hear such issue. If the finding be that
no agreement in writing providing for arbitration There can be no quibbling that POA is a quasi-judicial body
was made, or that there is no default in the which forms part of the DENR, an administrative agency. Hence,
proceeding thereunder, the proceeding shall be the provision on mandatory resort to arbitration, freely entered
dismissed. If the finding be that a written into by the parties, must be held binding against them. [25]
provision for arbitration was made and there is a
default in proceeding thereunder, an order shall In sum, on the issue of whether POA should have referred the
be made summarily directing the parties to case to voluntary arbitration, we find that, indeed, POA has no
proceed with the arbitration in accordance with jurisdiction over the dispute which is governed by RA 876, the
the terms thereof. arbitration law.

xxxx However, we find that Benguet is already estopped from


questioning the POAs jurisdiction. As it were, when J.G. Realty
Section 7. Stay of civil action.If any suit or filed DENR Case No. 2000-01, Benguet filed its answer and
proceeding be brought upon an issue arising out of an participated in the proceedings before the POA, Region
agreement providing for the arbitration thereof, the V. Secondly, when the adverse March 19, 2001 POA Decision
court in which such suit or proceeding is pending, upon was rendered, it filed an appeal with the MAB in Mines
being satisfied that the issue involved in such suit or Administrative Case No. R-M-2000-01 and again participated in
proceeding is referable to arbitration, shall stay the the MAB proceedings. When the adverse December 2, 2002 MAB
action or proceeding until an arbitration has been had Decision was promulgated, it filed a motion for reconsideration
in accordance with the terms of the agreement: with the MAB. When the adverse March 17, 2004 MAB
Provided, That the applicant, for the stay is not in Resolution was issued, Benguet filed a petition with this Court
default in proceeding with such arbitration. (Emphasis pursuant to Sec. 79 of RA 7942 impliedly recognizing MABs
supplied.) jurisdiction. In this factual milieu, the Court rules that the
jurisdiction of POA and that of MAB can no longer be questioned
by Benguet at this late hour. What Benguet should have done
In other words, in the event a case that should properly be the was to immediately challenge the POAs jurisdiction by a special
subject of voluntary arbitration is erroneously filed with the civil action for certiorari when POA ruled that it has jurisdiction
courts or quasi-judicial agencies, on motion of the defendant, over the dispute. To redo the proceedings fully participated in by
the court or quasi-judicial agency shall determine whether such the parties after the lapse of seven years from date of institution
contractual provision for arbitration is sufficient and effective. If of the original action with the POA would be anathema to the
in affirmative, the court or quasi-judicial agency shall then order speedy and efficient administration of justice.
the enforcement of said provision. Besides, in BF Corporation v. Second Issue: The cancellation of the RAWOP
Court of Appeals, we already ruled: was supported by evidence

In this connection, it bears stressing that the The cancellation of the RAWOP by the POA was based
lower court has not lost its jurisdiction over the case. on two grounds: (1) Benguets failure to pay J.G. Realtys royalties
Section 7 of Republic Act No. 876 provides that for the mining claims; and (2) Benguets failure to seriously
proceedings therein have only been stayed. After the pursue MPSA Application No. APSA-V-0009 over the mining
special proceeding of arbitration has been pursued and claims.
completed, then the lower court may confirm the award As to the royalties, Benguet claims that the checks
made by the arbitrator.[22] representing payments for the royalties of J.G. Realty were
available for pick-up in its office and it is the latter which refused
to claim them. Benguet then thus concludes that it did not
J.G. Realtys contention, that prior resort to arbitration is violate the RAWOP for nonpayment of royalties. Further,
unavailing in the instant case because the POAs mandate is to Benguet reasons that J.G. Realty has the burden of proving that
arbitrate disputes involving mineral agreements, is misplaced. A the former did not pay such royalties following the principle that
distinction must be made between voluntary and compulsory the complainants must prove their affirmative allegations.
arbitration. In Ludo and Luym Corporation v. Saordino, the Court
had the occasion to distinguish between the two types of With regard to the failure to pursue the MPSA
arbitrations: application, Benguet claims that the lengthy time of approval of
Comparatively, in Reformist Union of R.B. Liner, Inc. vs. the application is due to the failure of the MGB to approve it. In
NLRC, compulsory arbitration has been defined both as other words, Benguet argues that the approval of the application
the process of settlement of labor disputes by is solely in the hands of the MGB.
a government agency which has the authority to
investigate and to make an award which is binding Benguets arguments are bereft of merit.
on all the parties, and as a mode of arbitration where
the parties are compelled to accept the resolution of Sec. 14.05 of the RAWOP provides:
their dispute through arbitration by a third party. While
a voluntary arbitrator is not part of the 14.05 Bank Account
33
equity and good conscience. Article 22 of the Civil Code
OWNER shall maintain a bank account at ___________ or provides that [e]very person who through an act of
any other bank from time to time selected by OWNER performance by another, or any other means, acquires
with notice in writing to BENGUET where BENGUET or comes into possession of something at the expense
shall deposit to the OWNERs credit any and all of the latter without just or legal ground, shall return
advances and payments which may become due the the same to him. The principle of unjust enrichment
OWNER under this Agreement as well as the purchase under Article 22 requires two conditions: (1) that a
price herein agreed upon in the event that BENGUET person is benefited without a valid basis or justification,
shall exercise the option to purchase provided for in the and (2) that such benefit is derived at anothers
Agreement. Any and all deposits so made by expense or damage.
BENGUET shall be a full and complete
acquittance and release to [sic] BENGUET from There is no unjust enrichment when the
any further liability to the OWNER of the person who will benefit has a valid claim to such
amounts represented by such deposits. (Emphasis benefit.[28](Emphasis supplied.)
supplied.)

Clearly, there is no unjust enrichment in the instant case as the


Evidently, the RAWOP itself provides for the mode of royalty cancellation of the RAWOP, which left Benguet without any legal
payment by Benguet. The fact that there was the previous right to participate in further developing the mining claims, was
practice whereby J.G. Realty picked-up the checks from Benguet brought about by its violation of the RAWOP. Hence, Benguet has
is unavailing. The mode of payment is embodied in a contract no one to blame but itself for its predicament.
between the parties. As such, the contract must be considered
as the law between the parties and binding on both.[26] Thus, WHEREFORE, we DISMISS the petition, and AFFIRM the
after J.G. Realty informed Benguet of the bank account where December 2, 2002 Decision and March 17, 2004 Resolution of
deposits of its royalties may be made, Benguet had the the DENR-MAB in MAB Case No. 0124-01 upholding the
obligation to deposit the checks. J.G. Realty had no obligation to cancellation of the June 1, 1987 RAWOP. No costs.
furnish Benguet with a Board Resolution considering that the SO ORDERED.
RAWOP itself provided for such payment scheme. THIRD DIVISIONG.R. No. 180640 April 24, 2009

Notably, Benguets claim that J.G. Realty must prove


HUTAMA-RSEA JOINT OPERATIONS, INC., Petitioner,
nonpayment of its royalties is both illogical and unsupported by
law and jurisprudence. vs.
CITRA METRO MANILA TOLLWAYS
The allegation of nonpayment is not a positive CORPORATION, Respondent.
allegation as claimed by Benguet. Rather, such is a negative
allegation that does not require proof and in fact transfers the DECISION
burden of proof to Benguet. Thus, this Court ruled in Jimenez
v. National Labor Relations Commission:
CHICO-NAZARIO, J.:
As a general rule, one who pleads payment
has the burden of proving it. Even where the plaintiff
Before Us is a Petition1 for Review on Certiorari under Rule 45 of
must allege non-payment, the general rule is that the
the Rules of Court seeking to set aside the Decision 2 dated 23
burden rests on the defendant to prove payment,
rather than on the plaintiff to prove non-payment. The May 2007 and Resolution3 dated 16 November 2007 of the Court
debtor has the burden of showing with legal of Appeals in CA-G.R. SP No. 92504.
certainty that the obligation has been discharged
by payment.[27] (Emphasis supplied.) The facts, culled from the records, are as follows:

In the instant case, the obligation of Benguet to pay Petitioner HUTAMA-RSEA Joint Operations Incorporation and
royalties to J.G. Realty has been admitted and supported by the respondent Citra Metro Manila Tollways Corporation are
provisions of the RAWOP. Thus, the burden to prove such corporations organized and existing under Philippine laws.
obligation rests on Benguet. Petitioner is a sub-contractor engaged in engineering and
construction works. Respondent, on the other hand, is the
It should also be borne in mind that MPSA Application No. APSA- general contractor and operator of the South Metro Manila
V-0009 has been pending with the MGB for a considerable Skyway Project (Skyway Project).
length of time. Benguet, in the RAWOP, obligated itself to
perfect the rights to the mining claims and/or otherwise acquire
the mining rights to the mineral claims but failed to present any On 25 September 1996, petitioner and respondent entered into
evidence showing that it exerted efforts to speed up and have an Engineering Procurement Construction Contract (EPCC)
the application approved. In fact, Benguet never even alleged whereby petitioner would undertake the construction of Stage 1
that it continuously followed-up the application with the MGB of the Skyway Project, which stretched from the junction of
and that it was in constant communication with the government Buendia Avenue, Makati City, up to Bicutan Interchange, Taguig
agency for the expeditious resolution of the application. Such City. As consideration for petitioners undertaking, respondent
allegations would show that, indeed, Benguet was remiss in obliged itself under the EPCC to pay the former a total amount
prosecuting the MPSA application and clearly failed to comply of US$369,510,304.00.4
with its obligation in the RAWOP.

Third Issue: There is no unjust enrichment in the instant During the construction of the Skyway Project, petitioner wrote
case respondent on several occasions requesting payment of the
formers interim billings, pursuant to the provisions of the EPCC.
Based on the foregoing discussion, the cancellation of the Respondent only partially paid the said interim billings, thus,
RAWOP was based on valid grounds and is, therefore, justified. prompting petitioner to demand that respondent pay the
The necessary implication of the cancellation is the cessation of outstanding balance thereon, but respondent still failed to do
Benguets right to prosecute MPSA Application No. APSA-V-0009 so.5
and to further develop such mining claims.

In Car Cool Philippines, Inc. v. Ushio Realty and Development The Skyway Project was opened on 15 December 1999 for public
Corporation, we defined unjust enrichment, as follows: use, and toll fees were accordingly collected. After informing
respondent that the construction of the Skyway Project was
We have held that [t]here is unjust enrichment already complete, petitioner reiterated its demand that
when a person unjustly retains a benefit to the loss of respondent pay the outstanding balance on the interim billings,
another, or when a person retains money or property of as well as the "Early Completion Bonus" agreed upon in the
another against the fundamental principles of justice,
34
EPCC. Respondent refused to comply with petitioners CIAC.12 Respondents Urgent Motion was denied by the CIAC in
demands.6 its Order dated 6 December 2005.13

On 24 May 2004, petitioner, through counsel, sent a letter to Respondent filed a Motion for Reconsideration of the CIAC Order
respondent demanding payment of the following: (1) the dated 6 December 2005.14 The CIAC issued, on 12 December
outstanding balance on the interim billings; (2) the amount of 2005, an Order denying respondents Motion for
petitioners final billing; (3) early completion bonus; and (4) Reconsideration.15 It held that prior resort by the parties to DAB
interest charges on the delayed payment. Thereafter, petitioner was not a condition precedent for it to assume jurisdiction over
and respondent, through their respective officers and CIAC Case No. 17-2005. Aggrieved, respondent assailed the
representatives, held several meetings to discuss the possibility CIAC Order dated 12 December 2005 by filing a special civil
of amicably settling the dispute. Despite several meetings and action for certiorari and prohibition with the Court of
continuous negotiations, lasting for a period of almost one year, Appeals,16 docketed as CA-G.R. SP No. 92504.
petitioner and respondent failed to reach an amicable
settlement.7 On 23 May 2007, the Court of Appeals rendered its Decision in
CA-G.R. SP No. 92504, annulling the 12 December 2005 Order of
Petitioner finally filed with the Construction Industry Arbitration the CIAC, and enjoining the said Commission from proceeding
Commission (CIAC) a Request for Arbitration, seeking to enforce with CIAC Case No. 17-2005 until the dispute between petitioner
its money claims against respondent.8 Petitioners Request was and respondent had been referred to and decided by the DAB, to
docketed as CIAC Case No. 17-2005. be constituted by the parties pursuant to Clause 20.4 of the
EPCC. The appellate court, thus, found that the CIAC exceeded
its jurisdiction in taking cognizance of petitioners Request for
In its Answer ad cautelam with Motion to Dismiss, respondent
Arbitration in CIAC Case No. 17-2005 despite the latters failure
averred that the CIAC had no jurisdiction over CIAC Case No. 17-
to initially refer its dispute with respondent to the DAB, as
2005. Respondent argued that the filing by petitioner of said
directed by Clause 20.4 of the EPCC.
case was premature because a condition precedent, i.e., prior
referral by the parties of their dispute to the Dispute
Adjudication Board (DAB), required by Clause 20.4 of the EPCC, The dispositive portion of the 23 May 2007 Decision of the Court
had not been satisfied or complied with. Respondent asked the of Appeals reads:
CIAC to dismiss petitioners Request for Arbitration in CIAC Case
No. 17-2005 and to direct the parties to comply first with Clause WHEREFORE, the instant petition is GRANTED and the order of
20.4 of the EPCC.9 the Arbitration Tribunal of the Construction Industry Arbitration
Commission dated December 12, 2005 is hereby ANNULED and
After submission by the parties of the necessary pleadings on SET ASIDE and, instead, [CIAC, members of the Arbitral
the matter of jurisdiction, the CIAC issued on 30 August 2005, Tribunal,17 and herein petitioner], their agents or anybody acting
an Order in CIAC Case No. 17-2005, favoring petitioner. The CIAC in their behalf, are enjoined from further proceeding with CIAC
ruled that it had jurisdiction over CIAC Case No. 17-2005, and Case No. 17-2005, promulgating a decision therein, executing
that the determination of whether petitioner had complied with the same if one has already been promulgated or otherwise
Clause 20.4 of the EPCC was a factual issue that may be enforcing said order of December 12, 2005 until the dispute has
resolved during the trial. It then ordered respondent to file an been referred to and decided by the Dispute Adjudication Board
Answer to petitioners Request for Arbitration.10 to be constituted by the parties in accordance with Sub-Clause
20.4 of the Engineering Procurement Construction Contract
dated September 25, 1996.
After respondent and petitioner filed an Answer and a Reply,
respectively, in CIAC Case No. 17-2005, the CIAC conducted a
preliminary conference, wherein petitioner and respondent Petitioner filed a Motion for Reconsideration of the afore-
signed the "Terms of Reference" outlining the issues to be mentioned Decision but this was denied by the Court of Appeals
resolved, viz: in a Resolution dated 16 November 2007.

(1) Is prior resort to the DAB a precondition to Hence, petitioner filed the instant Petition for Review before us
submission of the dispute to arbitration considering raising the sole issue of whether CIAC has jurisdiction over CIAC
that the DAB was not constituted?; Case No. 17-2005.

(2) Is [herein petitioner] entitled to the balance of the Section 4 of Executive Order No. 1008 18 defines the jurisdiction
principal amount of the contract? If so, how much?; of CIAC, thus:

(3) Is [petitioner] entitled to the early compensation SECTION 4. Jurisdiction. - The CIAC shall have original and
bonus net of VAT due thereon? If so, how much?; exclusive jurisdiction over disputes arising from, or connected
with, contracts entered into by parties involved in construction
in the Philippines, whether the disputes arises before or after
(4) Was there delay in the completion of the project? If
the completion of the contract, or after the abandonment or
so, is [herein respondent] entitled to its counterclaim
breach thereof. These disputes may involve government or
for liquidated damages?;
private contracts. For the Board to acquire jurisdiction, the
parties to a dispute must agree to submit the same to voluntary
(5) Is [petitioner] entitled to payment of interest on the arbitration.
amounts of its claims for unpaid billings and early
completion bonus? If so, at what rate and for what
The jurisdiction of the CIAC may include but is not limited to
period?;
violation of specifications for materials and workmanship;
violation of the terms of agreement; interpretation and/or
(6) Which of the parties is entitled to reimbursement of application of contractual provisions; amount of damages and
the arbitration costs incurred? 11 penalties; commencement time and delays; maintenance and
defects; payment default of employer or contractor and changes
Respondent, however, subsequently filed an Urgent Motion in contract cost.
requesting that CIAC refrain from proceeding with the trial
proper of CIAC Case No. 17-2005 until it had resolved the issue Excluded from the coverage of this law are disputes arising from
of whether prior resort by the parties to DAB was a condition employer-employee relationships which shall continue to be
precedent to the submission of the dispute to covered by the Labor Code of the Philippines. (Emphasis ours.)
35
Further, Section 1, Article III of the CIAC Rules of Procedure contract arising out of their appointment; the parties
Governing Construction Arbitration19 (CIAC Rules), provides: shall indemnify the members against such claims.

SECTION 1. Submission to CIAC Jurisdiction. An arbitration The terms of the remuneration of the Dispute Adjudication
clause in a construction contract or a submission to arbitration Board, including the remuneration of each member and of any
of a construction dispute shall be deemed an agreement to specialist from whom the Dispute Adjudication Board may
submit an existing or future controversy to CIAC jurisdiction, require to seek advice, shall be mutually agreed upon by the
notwithstanding the reference to a different arbitration Employer, the Contractor and each member of the Dispute
institution or arbitral body in such contract or submission. When Adjudication Board when agreeing such terms of appointment.
a contract contains a clause for the submission of a future In the event of disagreement, the remuneration of each member
controversy to arbitration, it is not necessary for the parties to shall include reimbursement for reasonable expenses, a daily
enter into a submission agreement before the claimant may fee in accordance with the daily fee established from time to
invoke the jurisdiction of CIAC. time for arbitrators under the administrative and financial
regulations of the International Centre for Settlement of
Investment Disputes, and a retainer fee per calendar month
An arbitration agreement or a submission to arbitration shall be
equivalent to three times such daily fee.
in writing, but it need not be signed by the parties, as long as
the intent is clear that the parties agree to submit a present or
future controversy arising from a construction contract to The Employer and the Contractor shall each pay one-half of the
arbitration. Dispute Adjudication Boards remuneration in accordance with
its terms of remuneration. If, at any time, either party shall fail
to pay its due proportion of such remuneration, the other party
It may be in the form of exchange of letters sent by post or by
shall be entitled to make payment on his behalf and recover if
telefax, telexes, telegrams or any other modes of
from the party in default.
communication. (Emphasis ours.)

The Dispute Adjudication Boards appointment may be


Based on the foregoing provisions, the CIAC shall have
terminated only by mutual agreement of the Employer and the
jurisdiction over a dispute involving a construction contract if
Contractor. The Dispute Adjudication Boards appointment shall
said contract contains an arbitration clause (nothwithstanding
expire when the discharge referred to in Sub-Clause 13.12 shall
any reference by the same contract to another arbitration
have become effective, or at such other time as the parties may
institution or arbitral body); or, even in the absence of such a
mutually agree.
clause in the construction contract, the parties still agree to
submit their dispute to arbitration.
It, at any time, the parties so agree, they may appoint a suitably
qualified person to replace (or to be available to replace) any or
It is undisputed that in the case at bar, the EPCC contains an
all members of the Dispute Adjudication Board. The
arbitration clause in which the petitioner and respondent
appointment will come into effect if a member of the Dispute
explicitly agree to submit to arbitration any dispute between
Adjudication Board declines to act or is unable to act as a result
them arising from or connected with the EPCC, under the
of death, disability, resignation or termination of appointment. If
following terms and conditions20 :
a member so declines or is unable to act, and no such
replacement is available to act, the member shall be replaced in
CLAIMS, DISPUTES and ARBITRATION the same manner as such member was to have been
nominated.
xxxx
If any of the following conditions apply, namely:
20.3 Unless the member or members of the Dispute
Adjudication Board have been previously mutually agreed upon (a) the parties fail to agree upon the appointment of
by the parties and named in the Contract, the parties shall, the sole member of a one-person Dispute Adjudication
within 28 days of the Effective Date, jointly ensure the Board within 28 days of the Effective Date,
appointment of a Dispute Adjudication Board. Such Dispute
Adjudication Board shall comprise suitably qualified persons as
(b) either party fails to nominate an acceptable
members, the number of members being either one or three, as
member, for the Dispute Adjudication Board of three
stated in the Appendix to Tender. If the Dispute Adjudication
members, within 28 days of the Effective Date,
Board is to comprise three members, each party shall nominate
one member for the approval of the other party, and the parties
shall mutually agree upon and appoint the third member (who (c) the parties fail to agree upon the appointment of
shall act as chairman). the third member (to act as chairman) within 28 days
of the Effective Date, or
The terms of appointment of the Dispute Adjudication Board
shall: (d) the parties fail to agree upon the appointment of a
replacement member of the Dispute Adjudication Board
within 28 days of the date on which a member of the
(a) incorporate the model terms published by the
Dispute Adjudication Board declines to act or is unable
Fdration Internationale des Ingnieurs-Conseils
to act as a result of death, disability, resignation or
(FIDIC),
termination of appointment,

(b) require each member of the Dispute Adjudication


then the person or administration named in the Appendix to the
Board to be, and to remain throughout the
Tender shall, after due consultation with the parties, nominate
appointment, independent of the parties,
such member of the Dispute Adjudication Board, and such
nomination shall be final and conclusive.
(c) require the Dispute Adjudication Board to act
impartially and in accordance with the Contract, and
20.4 If a dispute arises between the Employer and the
Contractor in connection with, or arising out of, the Contract or
(d) include undertakings by the parties (to each other the execution of the Works, including any dispute as to any
and to the Dispute Adjudication Board) that the opinion, instruction, determination, certification or valuation of
members of the Dispute Adjudication Board shall in no the Employers Representative, the dispute shall initially be
circumstances be liable for breach of duty or of referred in writing to the Dispute Adjudication Board for its
36
decision, with a copy to the other party. Such reference shall Adjudication Board shall not be altered by reason of the
state that it is made under this Sub-Clause. The parties shall arbitration being conducted during the progress of the Works.
promptly make available to the Dispute Adjudication Board all
such information, access to the Site, and appropriate facilities, 20.7 Where neither party has given notice of dissatisfaction
as the Dispute Adjudication Board may require for the purposes within the period stated in Sub-Clause 20.4 and the Dispute
of rendering its decision. No later than the fifty-sixth day after Adjudication Boards related decision, if any, has become final
the day on which it received such reference, the Dispute and binding, either party may, if the other party fails to comply
Adjudication Board, acting as a panel of expert(s) and not as with such decision, and without prejudice to any other rights it
arbitrator(s), shall give notice of its decision to the parties. Such may have, refer the failure itself to arbitration under Sub-Clause
notice shall include reasons and shall state that it is given under 20.6. The provisions of Sub-Clauses 20.4 and 20.5 shall not
this Sub-Clause.1awphi1.zw+ apply to any such reference.

Unless the Contract has already been repudiated or terminated, 20.8 When the appointment of the Dispute Adjudication Board
the Contractor shall, in every case, continue to proceed with the and of any replacement has expired, any such dispute referred
Works with all due diligence, and the Contractor and the to in Sub-Clause 20.4 shall be finally settled by arbitration
Employer shall give effect forthwith to every decision of the pursuant to Sub-Clause 20.6. The provisions of Sub-Clauses 20.4
Dispute Adjudication Board, unless and until the same shall be and 20.5 shall not apply to any such reference. (Emphasis ours.)
revised, as hereinafter provided, in an amicable settlement or an
arbitral award.
Despite the presence of the afore-quoted arbitration clause in
the EPCC, it is respondents position, upheld by the Court of
If either party is dissatisfied with the Dispute Adjudication Appeals, that the CIAC still cannot assume jurisdiction over CIAC
Boards decision, then either party, on or before the twenty- Case No. 17-2005 (petitioners Request for Arbitration) because
eighth day after the day on which it received notice of such petitioner has not yet referred its dispute with respondent to the
decision, may notify the other party of its dissatisfaction. If the DAB, as directed by Clause 20.4 of the EPCC. Prior resort of the
Dispute Adjudication Board fails to give notice of its decision on dispute to DAB is a condition precedent and an indispensable
or before the fifty-sixth day after the day on which it received requirement for the CIAC to acquire jurisdiction over CIAC Case
the reference, then either party, on or before the twenty-eighth No. 17-2005.21
day after the day on which the said period of fifty-six days has
expired, may notify the other party of its dissatisfaction. In
either event, such notice of dissatisfaction shall state that it is It is true that Clause 20.4 of the EPCC states that a dispute
given under this Sub-Clause, such notice shall set out the between petitioner and respondent as regards the EPCC shall be
matters in dispute and the reason(s) for dissatisfaction and, initially referred to the DAB for decision, and only when the
subject to Sub-Clauses 20.7 and 20.8, no arbitration in respect parties are dissatisfied with the decision of the DAB should
of such dispute may be commenced unless such notice is given. arbitration commence. This does not mean, however, that the
CIAC is barred from assuming jurisdiction over the dispute if
such clause was not complied with.
If the Dispute Adjudication Board has given notice of its decision
as to a matter in dispute to the Employer and the Contractor
and no notice of dissatisfaction has been given by either party Under Section 1, Article III of the CIAC Rules, an arbitration
on or before the twenty-eighth day after the day on which the clause in a construction contract shall be deemed as an
parties received the Dispute Adjudication Boards decision, then agreement to submit an existing or future controversy to CIAC
the Dispute Adjudication Boards decision shall become final and jurisdiction, "notwithstanding the reference to a different
binding upon the Employer and the Contractor. arbitration institution or arbitral body in such contract x x x."
Elementary is the rule that when laws or rules are clear, it is
incumbent on the court to apply them. When the law (or rule) is
20.5 Where notice of dissatisfaction has been given under Sub- unambiguous and unequivocal, application, not interpretation
Clause 20.4, the parties shall attempt to settle such dispute thereof, is imperative.22
amicably before the commencement of arbitration. Provided
that unless the parties agree otherwise, arbitration may be
commenced on or after the fifty-sixth day after the day on which Hence, the bare fact that the parties herein incorporated an
notice of dissatisfaction was given, even if no attempt at arbitration clause in the EPCC is sufficient to vest the CIAC with
amicable settlement has been made. jurisdiction over any construction controversy or claim between
the parties.23 The arbitration clause in the construction contract
ipso facto vested the CIAC with jurisdiction.24 This rule applies,
20.6 Any dispute in respect of which: regardless of whether the parties specifically choose another
forum or make reference to another arbitral body. 25 Since the
(a) the decision, if any, of the Dispute Adjudication jurisdiction of CIAC is conferred by law, it cannot be subjected to
Board has not become final and binding pursuant to any condition; nor can it be waived or diminished by the
Sub-Clause 20.4, and stipulation, act or omission of the parties, as long as the parties
agreed to submit their construction contract dispute to
arbitration, or if there is an arbitration clause in the construction
(b) amicable settlement has not been reached, shall be
contract.26 The parties will not be precluded from electing to
finally decided by international arbitration. The
submit their dispute to CIAC, because this right has been vested
arbitration rules under which the arbitration is
in each party by law.27
conducted, the institution to nominate the arbitrator(s)
or to administer the arbitration rules (unless named
therein), the number of arbitrators, and the language In China Chang Jiang Energy Corporation (Philippines) v. Rosal
and place of such arbitration shall be as set out in the Infrastructure Builders,28 we elucidated thus:
Appendix to Tender. The arbitrator(s) shall have full
power to open up, review and revise any decision of the What the law merely requires for a particular construction
Dispute Adjudication Board. contract to fall within the jurisdiction of CIAC is for the parties to
agree to submit the same to voluntary arbitration. Unlike in the
Neither party shall be limited, in the proceedings before such original version of Section 1, as applied in the Tesco case, the
arbitrator(s), to the evidence or arguments previously put before law does not mention that the parties should agree to submit
the Dispute Adjudication Board to obtain its decision. disputes arising from their agreement specifically to the CIAC for
the latter to acquire jurisdiction over such disputes. Rather, it is
plain and clear that as long as the parties agree to submit to
Arbitration may be commenced prior to or after completion of
voluntary arbitration, regardless of what forum they may
the Works. The obligations of the parties and the Dispute
choose, their agreement will fall within the jurisdiction of the
37
CIAC, such that, even if they specially choose another forum, the with, contracts entered into by the parties involved in
parties will not be precluded from electing to submit their construction in the Philippines.30
dispute before the CIAC because this right has been vested upon
each party by law, i.e., E.O. No. 1008. The dispute between petitioner and respondent has been
lingering for almost five years now. Despite numerous meetings
xxxx and negotiations between the parties, which took place prior to
petitioners filing with the CIAC of its Request for Arbitration, no
amicable settlement was reached. A ruling requiring the parties
Now that Section 1, Article III [CIAC Rules of Procedure
to still appoint a DAB, to which they should first refer their
Governing Construction Arbitration], as amended, is submitted
dispute before the same could be submitted to the CIAC, would
to test in the present petition, we rule to uphold its validity with
merely be circuitous and dilatory at this point. It would entail
full certainty. However, this should not be understood to mean
unnecessary delays and expenses on both parties, which
that the parties may no longer stipulate to submit their disputes
Executive Order No. 1008 precisely seeks to prevent. It would,
to a different forum or arbitral body. Parties may continue to
indeed, defeat the purpose for which the CIAC was created.
stipulate as regards their preferred forum in case of voluntary
arbitration, but in so doing, they may not divest the CIAC of
jurisdiction as provided by law. Under the elementary principle WHEREFORE, the Petition is hereby GRANTED. The Decision,
on the law on contracts that laws obtaining in a jurisdiction form dated 23 May 2007, and Resolution, dated 16 November 2007,
part of all agreements, when the law provides that the Board of the Court of Appeals in CA-G.R. SP No. 92504 are hereby
acquires jurisdiction when the parties to the contract agree to REVERSED and SET ASIDE. The instant case is hereby
submit the same to voluntary arbitration, the law in effect, REMANDED for further proceedings to the CIAC which is
automatically gives the parties an alternative forum before DIRECTED to resolve the same with dispatch.
whom they may submit their disputes. That alternative forum is
the CIAC. This, to the mind of the Court, is the real spirit of E.O. SO ORDERED.
No. 1008, as implemented by Section 1, Article III of the CIAC
Rules. (Emphases ours.)
FIRST DIVISION [G.R. No. 129169. November 17, 1999]

Likewise, in National Irrigation Administration v. Court of


Appeals,29 we pronounced that: NATIONAL IRRIGATION ADMINISTRATION (NIA), petitioner,
vs. HONORABLE COURT OF APPEALS (4th
Division), CONSTRUCTION INDUSTRY
Under the present Rules of Procedure [CIAC Rules of Procedure ARBITRATION COMMISSION, and HYDRO
Governing Construction Arbitration], for a particular construction RESOURCES CONTRACTORS
contract to fall within the jurisdiction of CIAC, it is merely CORPORATION, respondents.
required that the parties agree to submit the same to voluntary
arbitration. Unlike in the original version of Section 1, as applied
in the Tesco case, the law as it now stands does not provide that DECISION
the parties should agree to submit disputes arising from their
agreement specifically to the CIAC for the latter to acquire DAVIDE, JR., C.J.:
jurisdiction over the same. Rather, it is plain and clear that as
long as the parties agree to submit to voluntary arbitration,
In this special civil action for certiorari under Rule 65 of the
regardless of what forum they may choose, their agreement will
Rules of Court, the National Irrigation Administration (hereafter
fall within the jurisdiction of the CIAC, such that, even if they
NIA), seeks to annul and set aside the Resolutions [1]of the Court
specifically choose another forum, the parties will not be
of Appeals in CA-GR. SP No. 37180 dated 28 June 1996 and 24
precluded from electing to submit their dispute before the CIAC
February 1997, which dismissed respectively NIAs petition
because this right has been vested upon each party by law, i.e.,
for certiorari and prohibition against the Construction Industry
E.O. No. 1008.
Arbitration Commission (hereafter CIAC), and the motion for
reconsideration thereafter filed.
We note that this is not a case wherein the arbitration clause in
the construction contract named another forum, not the CIAC,
Records show that in a competitive bidding held by NIA in
which shall have jurisdiction over the dispute between the
August 1978, Hydro Resources Contractors Corporation
parties; rather, the said clause requires prior referral of the
(hereafter HYDRO) was awarded Contract MPI-C-2 for the
dispute to the DAB. Nonetheless, we still hold that this condition
construction of the main civil works of the Magat River Multi-
precedent, or more appropriately, non-compliance therewith,
Purpose Project. The contract provided that HYDRO would be
should not deprive CIAC of its jurisdiction over the dispute
paid partly in Philippine pesos and partly in U.S. dollars. HYDRO
between the parties.
substantially completed the works under the contract in 1982
and final acceptance by NIA was made in 1984. HYDRO
It bears to emphasize that the mere existence of an arbitration thereafter determined that it still had an account receivable
clause in the construction contract is considered by law as an from NIA representing the dollar rate differential of the price
agreement by the parties to submit existing or future escalation for the contract.[2]
controversies between them to CIAC jurisdiction, without any
qualification or condition precedent. To affirm a condition
After unsuccessfully pursuing its case with NIA, HYDRO, on
precedent in the construction contract, which would effectively
7 December 1994, filed with the CIAC a Request for Adjudication
suspend the jurisdiction of the CIAC until compliance therewith,
of the aforesaid claim. HYDRO nominated six arbitrators for the
would be in conflict with the recognized intention of the law and
arbitration panel, from among whom CIAC appointed Engr. Lauro
rules to automatically vest CIAC with jurisdiction over a dispute
M. Cruz. On 6 January 1995, NIA filed its Answer wherein it
should the construction contract contain an arbitration clause.
questioned the jurisdiction of the CIAC alleging lack of cause of
action, laches and estoppel in view of HYDROs alleged failure to
Moreover, the CIAC was created in recognition of the avail of its right to submit the dispute to arbitration within the
contribution of the construction industry to national prescribed period as provided in the contract. On the same date,
development goals. Realizing that delays in the resolution of NIA filed a Compliance wherein it nominated six arbitrators, from
construction industry disputes would also hold up the among whom CIAC appointed Atty. Custodio O. Parlade, and
development of the country, Executive Order No. 1008 expressly made a counterclaim for P1,000,000 as moral damages; at
mandates the CIAC to expeditiously settle construction industry least P100,000 as exemplary damages; P100,000 as attorneys
disputes and, for this purpose, vests in the CIAC original and fees; and the costs of the arbitration.[3]
exclusive jurisdiction over disputes arising from, or connected
38
The two designated arbitrators appointed Certified Public E.O. NO. 1008 IS A SUBSTANTIVE LAW, NOT MERELY
Accountant Joven B. Joaquin as Chairman of the Arbitration PROCEDURAL AS RULED BY THE CIAC.
Panel.The parties were required to submit copies of the evidence
they intended to present during the proceedings and were D
provided the draft Terms of Reference.[4]

AN INDORSEMENT OF THE AUDITOR GENERAL DECIDING A


At the preliminary conference, NIA through its counsel Atty. CONTROVERSY IS A DECISION BECAUSE ALL THE ELEMENTS FOR
Joy C. Legaspi of the Office of the Government Corporate JUDGMENT ARE THERE; THE CONTROVERSY, THE AUTHORITY TO
Counsel, manifested that it could not admit the genuineness of DECIDE AND THE DECISION.IF IT IS NOT APPEALED SEASONABLY,
HYDROs evidence since NIAs records had already been THE SAME BECOMES FINAL.
destroyed. NIA requested an opportunity to examine the
originals of the documents which HYDRO agreed to provide. [5]
E

After reaching an accord on the issues to be considered by


the arbitration panel, the parties scheduled the dates of NIA HAS TIMELY RAISED THE ISSUE OF JURISDICTION. IT DID NOT
hearings and of submission of simultaneous memoranda.[6] WAIVE NOR IS IT ESTOPPED FROM ASSAILING THE SAME.

On 13 March 1995, NIA filed a Motion to Dismiss [7]alleging F


lack of jurisdiction over the disputes. NIA contended that there
was no agreement with HYDRO to submit the dispute to CIAC for THE LEGAL DOCTRINE THAT JURISDICTION IS DETERMINED BY
arbitration considering that the construction contract was THE STATUTE IN FORCE AT THE TIME OF THE COMMENCEMENT
executed in 1978 and the project completed in 1982, whereas OF THE ACTION DOES NOT ONLY APPLY TO THE INSTANT CASE. [11]
the Construction Industry Arbitration Law creating CIAC was
signed only in 1985; and that while they have agreed to
The Court of Appeals, after finding that there was no grave
arbitration as a mode of settlement of disputes, they could not
abuse of discretion on the part of the CIAC in issuing the
have contemplated submission of their disputes to CIAC. NIA
aforesaid Orders, dismissed the petition in its Resolution dated
further argued that records show that it had not voluntarily
28 June 1996. NIAs motion for reconsideration of the said
submitted itself to arbitration by CIAC citing TESCO Services,
Inc. v. Hon. Abraham Vera, et al.,[8] wherein it was ruled: decision was likewise denied by the Court of Appeals on 26
February 1997.

CIAC did not acquire jurisdiction over the dispute arising from
On 2 June 1997, NIA filed before us an original action
the sub-contract agreement between petitioner TESCO and
for certiorari and prohibition with urgent prayer for temporary
private respondent LAROSA. The records do not show that the
restraining order and writ of preliminary injunction, praying for
parties agreed to submit the disputes to arbitration by the CIAC
the annulment of the Resolutions of the Court of Appeals dated
xxxx. While both parties in the sub-contract had agreed to
28 June 1996 and 24 February 1997. In the said special civil
submit the matter to arbitration, this was only between
action, NIA merely reiterates the issues it raised before the
themselves, no request having been made by both with the
Court of Appeals. [12]
CIAC. Hence, as already stated, the CIAC, has no jurisdiction
over the dispute. xxxx. Nowhere in the said article (sub-
contract) does it mention the CIAC, much less, vest jurisdiction We take judicial notice that on 10 June 1997, CIAC
with the CIAC. rendered a decision in the main case in favor of HYDRO. [13] NIA
assailed the said decision with the Court of Appeals. In view of
the pendency of the present petitions before us the appellate
On 11 April 1995, the arbitral body issued an order [9] which
court issued a resolution dated 26 March 1998 holding in
deferred the determination of the motion to dismiss and
abeyance the resolution of the same until after the instant
resolved to proceed with the hearing of the case on the merits
petitions have been finally decided.[14]
as the grounds cited by NIA did not seem to be indubitable. NIA
filed a motion for reconsideration of the aforesaid Order. CIAC in
denying the motion for reconsideration ruled that it has At the outset, we note that the petition suffers from a
jurisdiction over the HYDROs claim over NIA pursuant to E.O procedural defect that warrants its outright dismissal. The
1008 and that the hearing should proceed as scheduled. [10] questioned resolutions of the Court of Appeals have already
become final and executory by reason of the failure of NIA to
appeal therefrom.Instead of filing this petition
On 26 May 1996, NIA filed with the Court of Appeals an
for certiorari under Rule 65 of the Rules of Court, NIA should
original action of certiorari and prohibition with prayer for
have filed a timely petition for review under Rule 45.
restraining order and/or injunction, seeking to annul the Orders
of the CIAC for having been issued without or in excess of
jurisdiction. In support of its petition NIA alleged that: There is no doubt that the Court of Appeals has jurisdiction
over the special civil action for certiorari under Rule 65 filed
before it by NIA. The original jurisdiction of the Court of Appeals
A
over special civil actions for certiorari is vested upon it under
Section 9(1) of B.P. 129. This jurisdiction is concurrent with the
RESPONDENT CIAC HAS NO AUTHORITY OR JURIDICTION TO Supreme Court[15] and with the Regional Trial Court.[16]
HEAR AND TRY THIS DISPUTE BETWEEN THE HEREIN PARTIES AS
E.O. NO. 1008 HAD NO RETROACTIVE EFFECT.
Thus, since the Court of Appeals had jurisdiction over the
petition under Rule 65, any alleged errors committed by it in the
B exercise of its jurisdiction would be errors of judgment which are
reviewable by timely appeal and not by a special civil action
THE DISPUTE BETWEEN THE PARTIES SHOULD BE SETTLED IN of certiorari.[17] If the aggrieved party fails to do so within the
ACCORDANCE WITH GC NO. 25, ART. 2046 OF THE CIVIL CODE reglementary period, and the decision accordingly becomes final
AND R.A. NO. 876 THE GOVERNING LAWS AT THE TIME and executory, he cannot avail himself of the writ of certiorari,
CONTRACT WAS EXECUTED AND TERMINATED. his predicament being the effect of his deliberate inaction. [18]

C The appeal from a final disposition of the Court of Appeals


is a petition for review under Rule 45 and not a special civil
action under Rule 65 of the Rules of Court, now Rule 45 and Rule
65, respectively, of the 1997 Rules of Civil Procedure.[19] Rule 45
39
is clear that decisions, final orders or resolutions of the Court of NIAs argument that CIAC had no jurisdiction to arbitrate on
Appeals in any case, i.e., regardless of the nature of the action contract which preceded its existence is untenable. E.O. 1008 is
or proceedings involved, may be appealed to this Court by filing clear that the CIAC has jurisdiction over all disputes arising from
a petition for review, which would be but a continuation of the or connected with construction contract whether the dispute
appellate process over the original case. [20] Under Rule 45 the arises before or after the completion of the contract. Thus, the
reglementary period to appeal is fifteen (15) days from notice of date the parties entered into a contract and the date of
judgment or denial of motion for reconsideration.[21] completion of the same, even if these occurred before the
constitution of the CIAC, did not automatically divest the CIAC of
jurisdiction as long as the dispute submitted for arbitration arose
In the instant case the Resolution of the Court of Appeals
after the constitution of the CIAC. Stated differently, the
dated 24 February 1997 denying the motion for reconsideration
jurisdiction of CIAC is over the dispute, not the contract; and the
of its Resolution dated 28 June 1997 was received by NIA on 4
instant dispute having arisen when CIAC was already
March1997. Thus, it had until 19 March 1997 within which to
constituted, the arbitral board was actually exercising current,
perfect its appeal. NIA did not appeal. What it did was to file an
not retroactive, jurisdiction. As such, there is no need to pass
original action for certiorari before this Court, reiterating the
upon the issue of whether E.O. No. 1008 is a substantive or
issues and arguments it raised before the Court of Appeals.
procedural statute.

For the writ of certiorari under Rule 65 of the Rules of Court


NIA also contended that the CIAC did not acquire
to issue, a petitioner must show that he has no plain, speedy
jurisdiction over the dispute since it was only HYDRO that
and adequate remedy in the ordinary course of law against its
requested for arbitration. It asserts that to acquire jurisdiction
perceived grievance.[22] A remedy is considered plain, speedy
over a case, as provided under E.O. 1008, the request for
and adequate if it will promptly relieve the petitioner from the
arbitration filed with CIAC should be made by both parties, and
injurious effects of the judgment and the acts of the lower court
hence the request by one party is not enough.
or agency.[23] In this case, appeal was not only available but also
a speedy and adequate remedy.
It is undisputed that the contracts between HYDRO and NIA
contained an arbitration clause wherein they agreed to submit
Obviously, NIA interposed the present special civil action
to arbitration any dispute between them that may arise before
of certiorari not because it is the speedy and adequate remedy
or after the termination of the agreement. Consequently, the
but to make up for the loss, through omission or oversight, of
the right of ordinary appeal. It is elementary that the special claim of HYDRO having arisen from the contract is
arbitrable. NIAs reliance with the ruling on the case of Tesco
civil action of certiorari is not and cannot be a substitute for an
Services Incorporated v. Vera,[30] is misplaced.
appeal, where the latter remedy is available, as it was in this
case. A special civil action under Rule 65 of the Rules of Court
will not be a cure for failure to timely file a petition for review The 1988 CIAC Rules of Procedure which were applied by
on certiorari under Rule 45 of the Rules of Court. [24] Rule 65 is this Court in Tesco case had been duly amended by CIAC
an independent action that cannot be availed of as a substitute Resolutions No. 2-91 and 3-93, Section 1 of Article III of which
for the lost remedy of an ordinary appeal, including that under read as follows:
Rule 45,[25] especially if such loss or lapse was occasioned by
ones own neglect or error in the choice of remedies.[26] Submission to CIAC Jurisdiction - An arbitration clause in a
construction contract or a submission to arbitration of a
For obvious reasons the rules forbid recourse to a special construction contract or a submission to arbitration of a
civil action for certiorari if appeal is available, as the remedies of construction dispute shall be deemed an agreement to submit
appeal and certiorari are mutually exclusive and not alternative an existing or future controversy to CIAC jurisdiction,
or successive.[27] Although there are exceptions to the rules, notwithstanding the reference to a different arbitration
none is present in the case at bar. NIA failed to show institution or arbitral body in such contract or submission. When
circumstances that will justify a deviation from the general rule a contract contains a clause for the submission of a future
as to make available a petition for certiorari in lieu of taking an controversy to arbitration, it is not necessary for the parties to
appropriate appeal. enter into a submission agreement before the claimant may
invoke the jurisdiction of CIAC.
Based on the foregoing, the instant petition should be
dismissed. Under the present Rules of Procedure, for a particular
construction contract to fall within the jurisdiction of CIAC, it is
merely required that the parties agree to submit the same to
In any case, even if the issue of technicality is disregarded
voluntary arbitration. Unlike in the original version of Section 1,
and recourse under Rule 65 is allowed, the same result would be
as applied in the Tesco case, the law as it now stands does not
reached since a review of the questioned resolutions of the CIAC
provide that the parties should agree to submit disputes arising
shows that it committed no grave abuse of discretion.
from their agreement specifically to the CIAC for the latter to
acquire jurisdiction over the same. Rather, it is plain and clear
Contrary to the claim of NIA, the CIAC has jurisdiction over that as long as the parties agree to submit to voluntary
the controversy. Executive Order No.1008, otherwise known as arbitration, regardless of what forum they may choose, their
the Construction Industry Arbitration Law which was agreement will fall within the jurisdiction of the CIAC, such that,
promulgated on 4 February 1985, vests upon CIAC original and even if they specifically choose another forum, the parties will
exclusive jurisdiction over disputes arising from, or connected not be precluded from electing to submit their dispute before
with contracts entered into by parties involved in construction in the CIAC because this right has been vested upon each party by
the Philippines, whether the dispute arises before or after the law, i.e., E.O. No. 1008.[31]
completion of the contract, or after the abandonment or breach
thereof. The disputes may involve government or private
Moreover, it is undeniable that NIA agreed to submit the
contracts. For the Board to acquire jurisdiction, the parties to a
dispute for arbitration to the CIAC. NIA through its counsel
dispute must agree to submit the same to voluntary arbitration.
[28] actively participated in the arbitration proceedings by filing an
answer with counterclaim, as well as its compliance wherein it
nominated arbitrators to the proposed panel, participating in the
The complaint of HYDRO against NIA on the basis of the deliberations on, and the formulation of, the Terms of Reference
contract executed between them was filed on 7 December 1994, of the arbitration proceeding, and examining the documents
during the effectivity of E.O. No. 1008. Hence, it is well within submitted by HYDRO after NIA asked for the originals of the said
the jurisdiction of CIAC. The jurisdiction of a court is determined documents.[32]
by the law in force at the time of the commencement of the
action.[29]
40
As to the defenses of laches and prescription, they are After summing up the award to both parties this TRIBUNAL
evidentiary in nature which could not be established by mere hereby awards the amount of THREE MILLION NINE HUNDRED
allegations in the pleadings and must not be resolved in a SIXTY-FOUR THOUSAND SIX HUNDRED SEVENTY[-]ONE PESOS
motion to dismiss. Those issues must be resolved at the trial of AND SIXTEEN CENTAVOS (P3,964,671.16) to CLAIMANT
the case on the merits wherein both parties will be given ample Philippine Commercial Industrial Bank. Respondent William
opportunity to prove their respective claims and defenses. Golangco Construction is hereby ordered to pay the stated
[33]
Under the rule[34] the deferment of the resolution of the said amount with legal interest of six (6%) percent from date of this
issues was, thus, in order. An allegation of prescription can decision until fully paid.[2]
effectively be used in a motion to dismiss only when the
complaint on its face shows that indeed the action has already PCIB filed on June 28, 1996 a Motion for Partial
prescribed.[35] In the instant case, the issue of prescription and Reconsideration[3] of the CIAC Decision which is not
laches cannot be resolved on the basis solely of the complaint. It allowed under Section 9, Article XV of the CIAC Rules of
must, however, be pointed that under the new rules,
[36]
Procedure. It subsequently filed on July 12, 1996 before the CA a
deferment of the resolution is no longer permitted. The court petition for Certiorari and/or Partial Review [4] which may be
may either grant the motion to dismiss, deny it, or order the treated as an original action for certiorari under Rule 65 of the
amendment of the pleading. Rules of Court or as a petition for review under Circular 1-95 of
the Supreme Court, alleging that the CIAC acted in excess of its
WHEREFORE, the instant petition is DISMISSED for lack of jurisdiction and contrary to law in awarding, without basis, an
merit. The Court of Appeals is hereby DIRECTED to proceed with amount in favor of WGCC.
reasonable dispatch in the disposition of C.A. G.R. No. 44527
and include in the resolution thereof the issue of laches and To PCIBs petition filed before the CA WGCC filed a Motion to
prescription. Dismiss with Motion to Cite PCIB Counsel for Contempt[5] on the
ground that it was filed beyond the 15-day reglementary period
SO ORDERED. for filing an appeal, in support of which it alleged that, contrary
to the allegation of counsel for PCIB that he acquired actual
knowledge of the CIAC decision on June 28, 1996, PCIB actually
THIRD DIVISION[G.R. No. 127275. June 20, 2003]
received a copy thereof on June 24, 1996, hence, it had only
until July 9, 1996 within which to file before the CA a petition
PHILIPPINE COMMERCIAL INTERNATIONAL for review. Since PCIB filed before the CA its petition for
BANK, petitioner, vs. COURT OF APPEALS, Certiorari and/or Partial Review on July 12, 1996, WGCC
WILLIAM GOLANGCO CONSTRUCTION CORP., concluded that it was late by 3 days. WGCC attached to its
Chairman ERNESTO S. DE CASTRO, and members motion a certified photocopy[6] of the pertinent entry in the CIAC
LAURO M. CRUZ and VICTOR P. LAZATIN of the logbook showing that Engineer Bong Nuno received a copy of
ARBITRAL TRIBUNAL of the CONSTRUCTION the decision for PCIB on June 24, 1996.
INDUSTRY ARBITRATION
COMMISSION, respondents.
By its assailed Resolution,[7] the CA granted WGCCs Motion
to Dismiss PCIBs petition upon a finding that indeed PCIB
CARPIO-MORALES, J.: received a copy of the CIAC decision on June 24, 1996 and,
therefore, its petition was belatedly filed. On the nature of the
Petitioner Philippine Commercial Industrial Bank (PCIB) petition, the CA held that an original action for certiorari under
assails, by the present Petition for Certiorari and Mandamus, the Rule 65 and a petition for review under Circular 1-95 of the
September 25, 1996 Resolution of the Court of Appeals (CA) Supreme Court cannot be the subject of a single pleading.
dismissing its petition for Certiorari and/or Partial Review of CIAC
Case No. 07-95, on motion of private respondent William PCIBs Motion for Reconsideration having been denied by
Golangco Construction Corporation (WGCC). the CA, it comes to this Court by the present petition for
Certiorari and Mandamus upon the following grounds:
PCIB contracted WGCC to construct the 5th to 21st floors
of PCIB Tower II in Makati. Alleging that the granite finish [of the I
tower] proved to be defective such that after all efforts at
negotiations proved futile it hired another contractor to redo the
THE RESPONDENT COURT GRAVELY ABUSED ITS DISCRETION TO
defective finish, but that WGCC refused to pay it actual
THE GRAVE AND IRREPARABLE DAMAGE TO THE PETITIONER
damages incurred in the process, PCIB filed a request for
AND FAILED OR UNLAWFULLY NEGLECTED TO DO AN ACT WHICH
arbitration with the Construction Industry Arbitration
THE LAW ENJOINS IT TO DO WHEN IT DISMISSED THE PETITION
Commission (CIAC), which docketed it as CIAC Case No. 07-95,
IN CA G.R. SP NO. 41227.
praying that WGCC be held liable for construction deficiencies.

II
WGCC denied PCIBs claim, it alleging that it accomplished
the project faithfully and in accordance with the specifications-
requirements of PCIB which accepted it after due inspection. It THE RESPONDENT COURT GRAVELY ABUSED ITS DISCRETION TO
counterclaimed that PCIB was actually indebted to it for material THE GRAVE AND IRREPARABLE DAMAGE AND INJURY TO THE
cost adjustment since the cost of materials substantially PETITIONER AND FAILED OR UNLAWFULLY NEGLECTED TO DO AN
increased in the course of the construction of the project. ACT WHICH THE LAW ENJOINS IT TO DO WHEN IT REFUSED TO
ALLOW THE PETITIONERS ALTERNATIVE RELIEFS FOR REVIEW
AND/OR FOR CERTIORARI. (Underscoring supplied)
The CIAC, by Decision[1] of June 21, 1996, found that PCIB
was entitled to recover from WGCC the sum of P9,741,829.00
representing cost of repairs done by another contractor on the PCIBs counsel disclaims that Engineer Bong Nuno is his
project. On WGCCs counterclaim, finding that under the parties employee but submits anyway that he was not authorized to
contract, increase for labor and materials under certain receive the CIAC decision for him in his (counsels) capacity as,
conditions was allowed but that PCIB presented no strong, or at by his claim, the authorized representative of PCIB.
best, token opposition to the evidence presented by WGCC for
the escalated cost of materials, the CIAC awarded WGCC the The present petition fails.
amount of P5,777,157.84. The CIAC accordingly disposed as
follows:
In the petition for Certiorari and/or Partial Review of CIAC
Case No. 07-95[8] filed before the CA by PCIB, its counsel alleged,
inter alia, as follows, quoted verbatim:
41
Inasmuch as the undersigned counsel ha[s] not officially 1996, it was only on June 27 (sic), 1996 that [he] had actual
received its copy of the Decision sought to be reviewed knowledge of the content of the decision. (Emphasis
because the Arbitral Tribunal had such copy served only on supplied). PCIBs counsels latest position may not be entertained
[PCIB], the reglementary period should be reckoned from the given his glaring admission that copy of the CIAC decision was
date when the undersigned counsel actually acquired knowledge duly served on June 24 1996 on PCIB, a party to the case which,
thereof which was on 28 June 1996 when it filed [PCIBs] Motion as will now be discussed, CIAC Rules mandates should be the
for Partial Reconsideration.Accordingly, treated as a Petition for one to be notified of the text of the decision.
Review, pursuant to resolution No. 2-95, this petition is
seasonable. The CIAC Rules of Procedure does not contain a provision
similar to Section 2, Rule 13 of the Revised Rules of Court,
A copy of the Decision as served upon [PCIB] itself is attached reiterated in the 1997 Rules of Civil Procedure, which provides
marked as Annex A and made a part thereof.[9] (Underscoring that service to any party represented by counsel should be
supplied) made upon his counsel, unless service upon the party himself is
ordered by the court. Instead, Section 7, Article XV of the CIAC
Rules of Procedure provides:
The copy of the CIAC decision attached to PCIBs petition
before the CA is a computer print-out bearing
the originalsignatures of the Chairman and two members of Section 7. Notification of Award to Parties Once an award has
the Arbitral Tribunal.[10] When PCIB received that copy of the been made, provided that the costs of the arbitration have been
CIAC decision, the petition filed before the CA did not state. fully paid to the Secretariat by the parties or by one of them, the
Secretariat shall notify the parties of the text signed by the
Arbitrator or Arbitral Tribunal.
As earlier stated, WGCC filed before the CA a Motion to
Dismiss with Motion to Cite PCIB Counsel for Contempt, [11]on the
grounds that: Additional copies certified true by the Executive Director of the
Secretariat shall be made available, on request and at any time,
to the parties or their counsel but to no one else. (Emphasis
THE . . . PETITION HAS BEEN FILED BEYOND THE REGLEMENTARY
and underscoring supplied)
PERIOD OF FIFTEEN DAYS FROM PETITIONERS RECEIPT OF THE
ASSAILED DECISION.
From the immediately-quoted provision of the CIAC Rules,
it is the parties who are to be notified of the text of the CIAC
PETITIONERS COUNSEL IS GUILTY OF MISREPRESENTING FACTS IN
decision. This answers PCIBs counsels jarring complaint that he
A BLATANT ATTEMPT TO HIDE THE BELATED FILING OF THE . . .
was not officially served with a copy of the CIAC decision.
PETITION;

In fine, copy of the CIAC decision having admittedly been


and in said Motion to Dismiss, WGCC alleged that per CIAC
served on and received by PCIB on June 24, 1996, PCIBs
records, petitioner received its copy of the CIAC decision on June
counsel cannot assail the validity of such service by now
24, 1996, hence, the petition filed before the CA on July 12,
claiming that the same was ineffective as it was not served on
1996 was late by 3 days.
him (counsel) as the duly authorized representative of PCIB.

In its Opposition [to WGCCs Motion to Dismiss], and


It is an elementary rule of procedure that perfection of an
Countermotion for Contempt,[12] PCIBs counsel admitted that
appeal within the reglementary period is not
PCIB was indeed served copy of the CIAC decision through
only mandatory but also jurisdictional so that failure to do so
Engineer Nuno but that it was only on June 28, 1996 that PCIB
renders the questioned decision final and executory, and
sent him a copy thereof. Thus PCIBs counsel alleged:
deprives an appellate court of jurisdiction to alter the final
judgment, much less to entertain the appeal.[13]
In its petition filed with this Honorable Court [of Appeals], the
petitioner was candid in alleging that although it received a copy
PCIB having filed its petition for Certiorari and/or Partial
of a decision of the Arbitral Tribunal, no actual service thereof
Review after the CIAC decision had become final and executory,
was made on the undersigned counsel. Receipt by the
the CA correctly granted WGCCs Motion to Dismiss the
petitioner itself of the decision did not start the running of the
same. This leaves it unnecessary to pass upon PCIBs plaint
period to appeal. It is basic that:
about the CAs refus[al] to allow [its] alternative reliefs for review
and/or certiorari. Suffice it to state that the following ruling of
xxx. The moment an attorney appears for any party, notice this Court instructs:
should be given to the furnished. xxx where a party appears by
attorney in an action or proving in a court of record all notices
We have time and again reminded members of the bench and
thereafter requires to be given in the action or providing must
bar that a special civil action for certiorari under Rule 65 lies
be given to the attorney and not to the client; and a notice given
only when there is no appeal nor plain, speedy and adequate
to the client and not to his attorney is not a notice in law (Palad
remedy in the ordinary course of law. Certiorari cannot be
vs. Cui, et al., 28 Phil. 44). In legal contemplation, therefore, and
allowed when a party to a case fails to appeal a judgment
under the fact, the present case, there was no legal service of
despite the availability of that remedy, certiorari not being a
the notice, and the defendants creed not be in default. (Elli, et
substitute for lost appeal. The remedies of appeal and
al. vs. Ditan, et al., 5 SCRA 503, 506).
certiorari are mutually exclusive and not alternative or
successive (Emphasis supplied, citations omitted.) [14]
When, therefore, the undersigned submitted in the petition
that it had actual knowledge of the decision on 28 June
PCIB, at all events, appeals for a relaxation of the Rules
1996 when the petitioner sent it a copy thereof, it was
given the [substantial] issues and amounts involved. But even
not only being candid, but was also admitting that it
its present petition for certiorari and mandamus is not the
already had actual notice of the decision as of then, hence,
proper remedy from the CA Resolution. What it should have filed
the running of the period to appeal must commence as of
was a petition for review under Rule 45 of the Rules of
then. (Emphasis supplied, underscoring by petitioner)
Court. But even if, in accordance with the liberal spirit pervading
the Rules of Court and in the interest of justice, this Court, in the
In the present petition before this Court, PCIBs exercise of its discretion, treats the present petition for certiorari
counsel now alleges that in the CIAC decision, he was as one for review under Rule 45, petitioner has failed to proffer
specifically named as the representative and counsel for [PCIB], meritorious reasons or arguments for its allowance.
but since the decision was not served on him as the authorized
representative of PCIB but to an employee of [PCIB] on June 24,
42
WHEREFORE, the present petition is hereby DISMISSED. pay the amount stated in the third progress billing, claiming that
it still had to evaluate the works accomplished by HRCC.
SO ORDERED. On November 25, 2004, HRCC submitted to FFCCI its
fourth progress billing in the amount of P1,527,112.95 for the
SECOND DIVISION March 14, 2012 G.R. No. 187521 works it had completed from October 26 to November 25, 2004.

F.F. CRUZ & CO., INC., Petitioner,- versus - HR Subsequently, FFCCI, after it had evaluated the
CONSTRUCTION CORP., completed works of HRCC from September 26 to November 25,
Respondent. 2004, approved the payment of the gross amount
of P1,505,570.99 to HRCC. FFCCI deducted
REYES, J.: therefrom P150,557.10 for retention and P27,374.02 for
expanded withholding tax leaving a net payment
This is a petition for review on certiorari under Rule 45 of P1,327,639.87, which amount was paid to HRCC on March 11,
of the Rules of Court filed by petitioner F.F. Cruz & Co., Inc. 2005.[9]
(FFCCI) assailing the Decision[1] dated February 6, 2009 and
Resolution[2] dated April 13, 2009 issued by the Court of Appeals Meanwhile, HRCC sent FFCCI a letter [10] dated
(CA) in CA-G.R. SP No. 91860. December 13, 2004 demanding the payment of its progress
billings in the total amount of P7,340,046.09, plus interests,
within three days from receipt thereof. Subsequently, HRCC
completely halted the construction of the subcontracted project
The Antecedent Facts after taking its Christmas break on December 18, 2004.

Sometime in 2004, FFCCI entered into a contract with On March 7, 2005, HRCC, pursuant to the arbitration
the Department of Public Works and Highways (DPWH) for the clause in the Subcontract Agreement, filed with the Construction
construction of the Magsaysay Viaduct, known as the Lower Industry Arbitration Commission (CIAC) a Complaint [11] against
Agusan Development Project. On August 9, 2004, FFCCI, in turn, FFCCI praying for the payment of the following: (1) overdue
entered into a Subcontract Agreement [3] with HR Construction obligation in the reduced amount of P4,096,656.53 as of
Corporation (HRCC) for the supply of materials, labor, December 15, 2004 plus legal interest; (2) P1,500,000.00 as
equipment, tools and supervision for the construction of a attorneys fees; (3) P80,000.00 as acceptance fee and
portion of the said project called the East Bank Levee and Cut- representation expenses; and (4) costs of litigation.
Off Channel in accordance with the specifications of the main
contract. In its Answer,[12] FFCCI claimed that it no longer has any
liability on the Subcontract Agreement as the three payments it
The subcontract price agreed upon by the parties made to HRCC, which amounted to P3,472,521.86, already
amounted to P31,293,532.72. Pursuant to the Subcontract represented the amount due to the latter in view of the works
Agreement, HRCC would submit to FFCCI a monthly progress actually completed by HRCC as shown by the survey it
billing which the latter would then pay, subject to stipulated conducted jointly with the DPWH. FFCCI further asserted that
deductions, within 30 days from receipt thereof. the delay in the payment processing was primarily attributable
to HRCC inasmuch as it presented unverified work
The parties agreed that the requests of HRCC for accomplishments contrary to the stipulation in the Subcontract
payment should include progress accomplishment of its Agreement regarding requests for payment.
completed works as approved by FFCCI. Additionally, they
agreed to conduct a joint measurement of the completed works Likewise, FFCCI maintained that HRCC failed to comply
of HRCC together with the representative of DPWH and with the condition stated under the Subcontract Agreement for
consultants to arrive at a common quantity. the payment of the latters progress billings, i.e. joint
measurement of the completed works, and, hence, it was
Thereafter, HRCC commenced the construction of the justified in not paying the amount stated in HRCCs progress
works pursuant to the Subcontract Agreement. billings.

On September 17, 2004, HRCC submitted to FFCCI its On June 16, 2005, an Arbitral Tribunal was created
first progress billing in the amount of P2,029,081.59 covering composed of Engineer Ricardo B. San Juan, Joven B. Joaquin and
the construction works it completed from August 16 to Attorney Alfredo F. Tadiar, with the latter being appointed as the
September 15, 2004.[4] However, FFCCI asserted that the DPWH Chairman.
was then able to evaluate the completed works of HRCC only
until July 25, 2004. Thus, FFCCI only approved the gross amount In a Preliminary Conference held on July 5, 2005, the
of P423,502.88 for payment. Pursuant to the Subcontract parties defined the issues to be resolved in the proceedings
Agreement, FFCCI deducted from the said gross before the CIAC as follows:
amount P42,350.29 for retention and P7,700.05 for expanded
withholding tax leaving a net payment in the amount 1. What is the correct amount of [HRCCs] unpaid
of P373,452.54. This amount was paid by FFCCI to HRCC on progress billing?
December 3, 2004.[5]
2. Did [HRCC] comply with the conditions set forth in
FFCCI and the DPWH then jointly evaluated the subparagraph 4.3 of the Subcontract Agreement
completed works of HRCC for the period of July 26 to September for the submission, evaluation/processing and
25, 2004. FFCCI claimed that the gross amount due for the release of payment of its progress billings?
completed works during the said period was P2,008,837.52.
From the said gross amount due, FFCCI deducted 3. Did [HRCC] stop work on the project?
therefrom P200,883.75 for retention and P36,524.07 for
expanded withholding tax leaving amount of P1,771,429.45 as 3.1 If so, is the work stoppage justified?
the approved net payment for the said period. FFCCI paid this
amount on December 21, 2004.[6] 3.2 If so, what was the percentage and value
of [HRCCs] work accomplishment at the
On October 29, 2004, HRCC submitted to FFCCI its time it stopped work on the project?
second progress billing in the amount of P1,587,760.23 covering
its completed works from September 18 to 25, 2004. [7] FFCCI did 4. Who between the parties should bear the cost of
not pay the amount stated in the second progress billing, arbitration or in what proportion should it be
claiming that it had already paid HRCC for the completed works shared by the parties?[13]
for the period stated therein.

On even date, HRCC submitted its third progress billing Likewise, during the said Preliminary Conference, HRCC
in the amount of P2,569,543.57 for its completed works from further reduced the amount of overdue obligation it claimed
September 26 to October 25, 2004. [8] FFCCI did not immediately from FFCCI to P2,768,916.66. During the course of the
proceedings before the CIAC, HRCC further reduced the said
43
amount to P2,635,397.77 the exact difference between the total
amount of HRCCs progress billings (P6,107,919.63) and FFCCIs
total payments in favor of the latter (P3,472,521.86). Further, the CIAC ruled that FFCCI had already waived
its right under the Subcontract Agreement to require a joint
The CIAC Decision measurement of HRCCs completed works as a condition
precedent to the payment of the latters progress billings. Hence:
On September 6, 2005, after due proceedings, the CIAC
rendered a Decision[14] in favor of HRCC, the decretal portion of [FFCCI] admits that in all three instances
which reads: where it paid [HRCC] for its progress billings, it never
required compliance with the aforequoted contractual
WHEREFORE, judgment is hereby rendered in provision of a prior joint quantification. Such repeated
favor of the Claimant HR CONSTRUCTION omission may reasonably be construed as
CORPORATION and AWARD made on its monetary a waiver by [FFCCI] of its contractual right to require
claim against Respondent F.F. CRUZ & CO., INC., as compliance of said condition and it is now too late in
follows: the day to so impose it. Article 6 of the Civil Code
expressly provides that rights may be waived unless
[P]2,239,452.63 as the balance of its unpaid the waiver is contrary to law, public order, public
billings and policy, morals or good customs. The tribunal cannot
see any such violation in this case.
101,161.57 as reimbursement of the
arbitration costs. xxx

[P]2,340,614.20 Total due the Claimant [FFCCIs] omission to enforce the contractually
required condition of payment, has led [HRCC] to
Interest on the foregoing believe it to be true that indeed [FFCCI] has waived the
amount [P]2,239,452.63 shall be paid at the rate of condition of joint quantification and, therefore, [FFCCI]
6% per annum from the date of this Decision. After may not be permitted to falsify such resulting position.
[17]
finality of this Decision, interest at the rate of 12% per
annum shall be paid thereon until full payment of the
awarded amount shall have been made x x x.
Likewise, the CIAC held that FFCCIs non-payment of the
SO ORDERED.[15] progress billings submitted by HRCC gave the latter the right to
rescind the Subcontract Agreement and, accordingly, HRCCs
work stoppage was justified. It further opined that, in effect,
The CIAC held that the payment method adopted by FFCCI had ratified the right of HRCC to stop the construction
FFCCI is actually what is known as the back-to-back payment works as it did not file any counterclaim against HRCC for
scheme which was not agreed upon under the Subcontract liquidated damages arising therefrom.
Agreement. As such, the CIAC ruled that FFCCI could not impose
upon HRCC its valuation of the works completed by the latter. FFCCI then filed a petition for review with CA assailing
The CIAC gave credence to HRCCs valuation of its completed the foregoing disposition by the CIAC.
works as stated in its progress billings. Thus:
The CA Decision
During the trial, [FFCCIs] Aganon admitted
that [HRCCs] accomplishments are included in its own On February 6, 2009, the CA rendered the herein
billings to the DPWH together with a substantial mark- assailed Decision[18] denying the petition for review filed by
up to cover overhead costs and profit. He further FFCCI. The CA agreed with the CIAC that FFCCI had waived its
admitted that it is only when DPWH approves its right under the Subcontract Agreement to require a joint
(Respondents) billings covering [HRCCs] scope of work quantification of HRCCs completed works.
and pays for them, that [FFCCI] will in turn pay [HRCC]
for its billings on the sub-contracted works. The CA further held that the amount due to HRCC as
claimed by FFCCI could not be given credence since the same
On clarificatory questioning by the Tribunal, was based on a survey of the completed works conducted
[FFCCI] admitted that there is no back-to- without the participation of HRCC. Likewise, being the main
back provision in the sub-contract as basis for contractor, it ruled that it was the responsibility of FFCCI to
this sequential payment arrangement and, include HRCC in the joint measurement of the completed works.
therefore, [FFCCIs] imposition thereof by withholding Furthermore, the CA held that HRCC was justified in stopping its
payment to [HRCC] until it is first paid by the project construction works on the project as the failure of FFCCI to pay
owner on the Main Contract, clearly violates said sub- its progress billings gave the former the right to rescind the
contract. It [is] this unauthorized implementation of a Subcontract Agreement.
back-to-back payment scheme that is seen to be the
reason for [FFCCIs] non-payment of the third progress FFCCI sought a reconsideration[19] of the said February
billings. 6, 2009 Decision but it was denied by the CA in its
Resolution[20] dated April 13, 2009.
It is accordingly the holding of this Arbitral
Tribunal that [FFCCI] is not justified in withholding Issues
payment of [HRCCs] third progress billing for this
scheme that [HRCC] has not agreed to in the sub- In the instant petition, FFCCI submits the following
contract agreement x x x. issues for this Courts resolution:

xxx [I.]

The total retention money deducted by [FFCCI] x x x First, [d]oes the act of [FFCCI] in
from [HRCCs] three progress billings, amounts conducting a verification survey of [HRCCs] billings in
to [P]395,945.14 x x x. The retention money is part of the latters presence amount to a waiver of the right of
[HRCCs] progress billings and must, therefore, be [FFCCI] to verify and approve said billings? What, if any,
credited to this account. The two amounts (deductions is the legal significance of said act?
and net payments) total [P]3,868,467.00 x x x. This
represents the total gross payments that should be [II.]
credited and deducted from the total gross billings to
arrive at what has not been paid to the [HRCC]. This x x x Second, [d]oes the payment of [FFCCI] to
results in the amount [HRCC] based on the results of the above mentioned
of [P]2,239,452.63 ([P]6,107,919.63 - verification survey result in the former being obliged to
[P]3,868,467.00) as the correct balance of [HRCCs] accept whatever accomplishment was reported by the
unpaid billings.[16] latter?
44
Aware of the objective of voluntary arbitration
[III.] in the labor field, in the construction industry, and in
any other area for that matter, the Court will not assist
x x x Third, [d]oes the mere comparison of the one or the other or even both parties in any effort to
payments made by [FFCCI] with the contested progress subvert or defeat that objective for their private
billings of [HRCC] amount to an adjudication of the purposes. The Court will not review the factual findings
controversy between the parties? of an arbitral tribunal upon the artful allegation that
such body had "misapprehended the facts" and will not
[IV.] pass upon issues which are, at bottom, issues of fact,
no matter how cleverly disguised they might be as
x x x Fourth, [d]oes the failure of [FFCCI] to "legal questions." The parties here had recourse to
interpose a counterclaim against [HRCC] for liquidated arbitration and chose the arbitrators themselves; they
damages due to the latters work stoppage, amount to a must have had confidence in such arbitrators. x x
ratification of such work stoppage? x[25] (Citation omitted)

[V.]
Thus, in cases assailing the arbitral award rendered by
x x x Fifth, [d]id the [CA] disregard or overlook the CIAC, this Court may only pass upon questions of
significant and material facts which would affect the law. Factual findings of construction arbitrators are final and
result of the litigation?[21] conclusive and not reviewable by this Court on appeal. This rule,
however, admits of certain exceptions.

In sum, the crucial issues for this Courts resolution In Spouses David v. Construction Industry and Arbitration
are: first, what is the effect of FFCCIs non-compliance with the Commission,[26] we laid down the instances when this Court may
stipulation in the Subcontract Agreement requiring a joint pass upon the factual findings of the CIAC, thus:
quantification of the works completed by HRCC on the payment
of the progress billings submitted by the latter; and second, We reiterate the rule that factual findings of
whether there was a valid rescission of the Subcontract construction arbitrators are final and conclusive and
Agreement by HRCC. not reviewable by this Court on appeal, except when
the petitioner proves affirmatively that: (1) the award
The Courts Ruling was procured by corruption, fraud or other undue
means; (2) there was evident partiality or corruption of
The petition is not meritorious. the arbitrators or of any of them; (3) the arbitrators
were guilty of misconduct in refusing to postpone the
hearing upon sufficient cause shown, or in refusing to
Procedural Issue: hear evidence pertinent and material to the
Finality and Conclusiveness of the CIACs Factual Findings controversy; (4) one or more of the arbitrators were
disqualified to act as such under section nine of
Before we delve into the substantial issues raised by FFCCI, we Republic Act No. 876 and willfully refrained from
shall first address the procedural issue raised by HRCC. disclosing such disqualifications or of any other
According to HRCC, the instant petition merely assails the misbehavior by which the rights of any party have been
factual findings of the CIAC as affirmed by the CA and, materially prejudiced; or (5) the arbitrators exceeded
accordingly, not proper subjects of an appeal under Rule 45 of their powers, or so imperfectly executed them, that a
the Rules of Court. It likewise pointed out that factual findings of mutual, final and definite award upon the subject
the CIAC, when affirmed by the CA, are final and conclusive matter submitted to them was not made. x x
upon this Court. x[27] (Citation omitted)

Generally, the arbitral award of CIAC is final and may not


be appealed except on questions of law. Issues on the proper interpretation of the terms of the
Subcontract Agreement involve questions of law.

Executive Order (E.O.) No. 1008 [22] vests upon the CIAC original
and exclusive jurisdiction over disputes arising from, or A question of law arises when there is doubt as to what the law
connected with, contracts entered into by parties involved in is on a certain state of facts, while there is a question of fact
construction in the Philippines. Under Section 19 of E.O. No. when the doubt arises as to the truth or falsity of the alleged
1008, the arbitral award of CIAC "shall be final and inappealable facts. For a question to be one of law, the same must not involve
except on questions of law which shall be appealable to the an examination of the probative value of the evidence presented
Supreme Court."[23] by the litigants or any of them. The resolution of the issue must
rest solely on what the law provides on the given set of
In Hi-Precision Steel Center, Inc. v. Lim Kim Steel Builders, Inc., circumstances. Once it is clear that the issue invites a review of
[24]
we explained raison d etre for the rule on finality of the CIACs the evidence presented, the question posed is one of fact.[28]
arbitral award in this wise:
On the surface, the instant petition appears to merely
Voluntary arbitration involves the reference of raise factual questions as it mainly puts in issue the appropriate
a dispute to an impartial body, the members of which amount that is due to HRCC. However, a more thorough analysis
are chosen by the parties themselves, which parties of the issues raised by FFCCI would show that it actually asserts
freely consent in advance to abide by the arbitral questions of law.
award issued after proceedings where both parties had
the opportunity to be heard. The basic objective is to FFCCI primarily seeks from this Court a determination
provide a speedy and inexpensive method of settling of whether amount claimed by HRCC in its progress billing may
disputes by allowing the parties to avoid the be enforced against it in the absence of a joint measurement of
formalities, delay, expense and aggravation which the formers completed works. Otherwise stated, the main
commonly accompany ordinary litigation, especially question advanced by FFCCI is this: in the absence of the joint
litigation which goes through the entire hierarchy of measurement agreed upon in the Subcontract Agreement, how
courts. Executive Order No. 1008 created an arbitration will the completed works of HRCC be verified and the amount
facility to which the construction industry in due thereon be computed?
the Philippines can have recourse. The Executive Order
was enacted to encourage the early and expeditious The determination of the foregoing question entails an
settlement of disputes in the construction industry, a interpretation of the terms of the Subcontract Agreement vis--
public policy the implementation of which is necessary vis the respective rights of the parties herein. On this point, it
and important for the realization of national should be stressed that where an interpretation of the true
development goals. agreement between the parties is involved in an appeal, the
appeal is in effect an inquiry of the law between the parties, its
interpretation necessarily involves a question of law. [29]
45
a common/agreed quantity.[33] (Emphasis
Moreover, we are not called upon to examine the supplied)
probative value of the evidence presented before the CIAC.
Rather, what is actually sought from this Court is an
interpretation of the terms of the Subcontract Agreement as it Pursuant to the terms of payment agreed upon by the
relates to the dispute between the parties. parties, FFCCI obliged itself to pay the monthly progress billings
of HRCC within 30 days from receipt of the same. Additionally,
First Substantive Issue: Effect of Non-compliance with the monthly progress billings of HRCC should indicate the extent
the Joint Quantification Requirement on the of the works completed by it, the same being essential to the
Progress Billings of HRCC valuation of the amount that FFCCI would pay to HRCC.

Basically, the instant issue calls for a determination as to which The parties further agreed that the extent of HRCCs
of the parties respective valuation of accomplished works should completed works that would be indicated in the monthly
be given credence. FFCCI claims that its valuation should be progress billings should be determined through a joint
upheld since the same was the result of a measurement of the measurement conducted by FFCCI and HRCC together with the
completed works conducted by it and the DPWH. On the other representative of DPWH and the consultants.
hand, HRCC maintains that its valuation should be upheld on
account of FFCCIs failure to observe the joint measurement It is the responsibility of FFCCI to call for the joint
requirement in ascertaining the extent of its completed works. measurement of HRCCs completed works.

The terms of the Subcontract Agreement should prevail.


It bears stressing that the joint measurement contemplated
under the Subcontract Agreement should be conducted by the
In resolving the dispute as to the proper valuation of the works parties herein together with the representative of the DPWH and
accomplished by HRCC, the primordial consideration should be the consultants. Indubitably, FFCCI, being the main contractor of
the terms of the Subcontract Agreement. It is basic that if the DPWH, has the responsibility to request the representative of
terms of a contract are clear and leave no doubt upon the DPWH to conduct the said joint measurement.
intention of the contracting parties, the literal meaning of its
stipulations shall control.[30] On this score, the testimony of Engineer Antonio M.
Aganon, Jr., project manager of FFCCI, during the reception of
In Abad v. Goldloop Properties, Inc.,[31] we stressed that: evidence before the CIAC is telling, thus:

A courts purpose in examining a contract is to MR. J. B. JOAQUIN:


interpret the intent of the contracting parties, as
objectively manifested by them. The process of Engr. Aganon, earlier there was a stipulation that in all
interpreting a contract requires the court to make a the four billings, there never was a joint quantification.
preliminary inquiry as to whether the contract before it
is ambiguous. A contract provision is ambiguous if it is PROF. A. F. TADIAR:
susceptible of two reasonable alternative
interpretations. Where the written terms of the He admitted that earlier. Pinabasa ko sa kanya.
contract are not ambiguous and can only be read
one way, the court will interpret the contract as a ENGR. R. B. SAN JUAN:
matter of law. If the contract is determined to be
ambiguous, then the interpretation of the contract is The joint quantification was done only between them
left to the court, to resolve the ambiguity in the light of and DPWH.
the intrinsic evidence.[32](Emphasis supplied and
citation omitted) xxxx

ENGR. AGANON:
Article 4 of the Subcontract Agreement, in part, contained the
following stipulations: Puwede ko po bang i-explain sandali lang po regarding
lang po doon sa quantification na iyon? Basically po as
ARTICLE 4 main contractor of DPWH, we are the ones who
[are] requesting for joint survey quantification
SUBCONTRACT PRICE with the owner, DPWH. Ngayon po, although wala sa
4.1 The total SUBCONTRACT Price shall be THIRTY ONE papel na nag-witness and [HRCC] still the same po,
MILLION nandoon din po sila during that time, kaya lang ho . . .
TWO HUNDRED NINETY THREE THOUSAND FIVE
HUNDRED THIRTY TWO PESOS & 72/100 ONLY MR. J. B. JOAQUIN:
([P]31,293,532.72) inclusive of Value Added
Tax x x x. Hindi pumirma?

xxx ENGR. AGANON:

4.3 Terms of Payment Hindi sila puwede pumirma kasi ho kami po ang
contractor ng DPWH hindi sila.[34] (Emphasis supplied)
FFCCI shall pay [HRCC] within thirty (30)
days upon receipt of the [HRCCs] Monthly
Progress Billingssubject to deductions due to FFCCI had waived its right to demand for a joint
ten percent (10%) retention, and any other sums measurement of HRCCs completed works under the
that may be due and recoverable by FFCCI from Subcontract Agreement.
[HRCC] under this SUBCONTRACT. In all cases,
however, two percent (2%) expanded
withholding tax on the [HRCCs] income will be The CIAC held that FFCCI, on account of its failure to demand
deducted from the monthly payments. the joint measurement of HRCCs completed works, had
effectively waived its right to ask for the conduct of the same as
Requests for the payment by the [HRCC] a condition sine qua non to HRCCs submission of its monthly
shall include progress accomplishment of progress billings.
completed works (unit of work accomplished x
unit cost) as approved by [FFCCI]. Cut-off We agree.
date of monthly billings shall be every 25 thof the
month and joint measurement shall be In People of the Philippines v. Donato,[35] this Court explained the
conducted with the DPWHs representative, doctrine of waiver in this wise:
Consultants, FFCCI and [HRCC] to arrive at
46
Waiver is defined as "a voluntary and FFCCI insist on the conduct of a joint measurement to verify the
intentional relinquishment or abandonment of a known extent of HRCCs completed works despite its receipt of the four
existing legal right, advantage, benefit, claim or monthly progress billings submitted by the latter.
privilege, which except for such waiver the party would
have enjoyed; the voluntary abandonment or FFCCI is already barred from contesting HRCCs valuation
surrender, by a capable person, of a right known by of the completed works having waived its right to
him to exist, with the intent that such right shall be demand the joint measurement requirement.
surrendered and such person forever deprived of its
benefit; or such conduct as warrants an inference
of the relinquishment of such right; or the In view of FFCCIs waiver of the joint measurement
intentional doing of an act inconsistent with requirement, the CA, essentially echoing the CIACs disposition,
claiming it." found that FFCCI is obliged to pay the amount claimed by HRCC
in its monthly progress billings. The CA reasoned thus:
As to what rights and privileges may be
waived, the authority is settled: Verily, the joint measurement that [FFCCI]
claims it conducted without the participation of [HRCC],
x x x the doctrine of waiver extends to rights to which [FFCCI] anchors its claim of full payment of its
and privileges of any character, and, since the obligations to [HRCC], cannot be applied, nor imposed,
word waiver covers every conceivable right, it on [HRCC]. In other words, [HRCC] cannot be made to
is the general rule that a person may accept a quantification of its works when the said
waive any matter which affects his quantification was made without its participation. As a
property, and any alienable right or consequence, [FFCCIs] claim of full payment cannot be
privilege of which he is the owner or upheld as this is a result of a quantification that was
which belongs to him or to which he is made contrary to the express provisions of the
legally entitled, whether secured by Subcontract Agreement.
contract, conferred with statute, or
guaranteed by constitution, provided such The Court is aware that by ruling so, [FFCCI]
rights and privileges rest in the would seem to be placed at a disadvantage because it
individual, are intended for his sole would result in [FFCCI] having to pay exactly what
benefit, do not infringe on the rights of [HRCC] was billing the former. If, on the other hand, the
others, and further provided the waiver Court were to rule otherwise[,] then [HRCC] would be
of the right or privilege is not forbidden the one at a disadvantage because it would be made to
by law, and does not contravene public accept payment that is less than what it was billing.
policy; and the principle is recognized that
everyone has a right to waive, and agree to Circumstances considered, however, the Court
waive, the advantage of a law or rule made deems it proper to rule in favor of [HRCC] because of
solely for the benefit and protection of the the explicit provision of the Subcontract Agreement
individual in his private capacity, if it can be that requires the participation of the latter in the joint
dispensed with and relinquished without measurement. If the Court were to rule otherwise, then
infringing on any public right, and without the Court would, in effect, be disregarding the explicit
detriment to the community at large. x x agreement of the parties in their contract. [43]
x[36] (Emphasis supplied and citations omitted)

Essentially, the question that should be resolved is this: In view


Here, it is undisputed that the joint measurement of HRCCs of FFCCIs waiver of its right to demand a joint measurement of
completed works contemplated by the parties in the HRCCs completed works, is FFCCI now barred from disputing the
Subcontract Agreement never materialized. Indeed, HRCC, on claim of HRCC in its monthly progress billings?
separate occasions, submitted its monthly progress billings
indicating the extent of the works it had completed sans prior We rule in the affirmative.
joint measurement. Thus:
As intimated earlier, the joint measurement requirement is a
Progress Billing Period Covered mechanism essentially granting FFCCI the opportunity to verify
1st Progress Billing dated and, if necessary, contest HRCCs valuation of its completed
August 16 to September 15, 2004
September 17, 2004[37] works prior to the submission of the latters monthly progress
2nd Progress Billing dated October billings.
September 18 to 25, 2004
29, 2004[38]
3rd Progress Billing dated October In the final analysis, the joint measurement
September 26 to October 25, 2004
29, 2004[39] requirement seeks to limit the dispute between the parties with
4th Progress Billing dated November regard to the valuation of HRCCs completed works. Accordingly,
October 26 to November 25, 2004
25, 2004 any issue which FFCCI may have with regard to HRCCs valuation
of the works it had completed should be raised and resolved
FFCCI did not contest the said progress billings submitted by during the said joint measurement instead of raising the same
HRCC despite the lack of a joint measurement of the latters after HRCC had submitted its monthly progress billings. Thus,
completed works as required under the Subcontract Agreement. having relinquished its right to ask for a joint measurement of
Instead, FFCCI proceeded to conduct its own verification of the HRCCs completed works, FFCCI had necessarily waived its right
works actually completed by HRCC and, on separate dates, to dispute HRCCs valuation of the works it had accomplished.
made the following payments to HRCC:

Date of Payment Period Covered Second Substantive Issue:


[40]
Validity of HRCCs Rescission of the Subcontract
December 3, 2004 April 2 to July 25, 2004 Agreement
December 21, 2004[41] July 26 to September 25, 2004 Both the CA and the CIAC held that the work stoppage of HRCC
[42] was justified as the same is but an exercise of its right to rescind
March 11, 2005 September 26 to November 25, 2004
the Subcontract Agreement in view of FFCCIs failure to pay the
formers monthly progress billings. Further, the CIAC stated that
FFCCIs voluntary payment in favor of HRCC, albeit in amounts FFCCI could no longer assail the work stoppage of HRCC as it
substantially different from those claimed by the latter, is a failed to file any counterclaim against HRCC pursuant to the
glaring indication that it had effectively waived its right to terms of the Subcontract Agreement.
demand for the joint measurement of the completed works.
FFCCIs failure to demand a joint measurement of HRCCs For its part, FFCCI asserted that the work stoppage of
completed works reasonably justified the inference that it had HRCC was not justified and, in any case, its failure to raise a
already relinquished its right to do so. Indeed, not once did counterclaim against HRCC for liquidated damages before the
47
CIAC does not amount to a ratification of the latters work Section 1, Rule 142 of the Rules of Court provides:
stoppage.
Section 1. Costs ordinarily follow results of
The determination of the validity of HRCCs work stoppage suit. Unless otherwise provided in these rules, costs
depends on a determination of the following: first,whether HRCC shall be allowed to the prevailing party as a matter of
has the right to extrajudicially rescind the Subcontract course, but the court shall have power, for special
Agreement; and second, whether FFCCI is already barred from reasons, to adjudge that either party shall pay the
disputing the work stoppage of HRCC. costs of an action, or that the same be divided, as
may be equitable. No costs shall be allowed against
HRCC had waived its right to rescind the Subcontract the Republic of the Philippines unless otherwise
Agreement. provided by law. (Emphasis supplied)

The right of rescission is statutorily recognized in Although, generally, costs are adjudged against the
reciprocal obligations. Article 1191 of the Civil Code pertinently losing party, courts nevertheless have discretion, for special
reads: reasons, to decree otherwise.

Art. 1191. The power to rescind obligations is Here, considering that the work stoppage of HRCC is
implied in reciprocal ones, in case one of the obligors not justified, it is only fitting that both parties should share in
should not comply with what is incumbent upon him. the burden of the cost of arbitration equally. HRCC had a valid
reason to institute the complaint against FFCCI in view of the
The injured party may choose between the latters failure to pay the full amount of its monthly progress
fulfillment and the rescission of the obligation, with the billings. However, we disagree with the CIAC and the CA that
payment of damages in either case. He may also seek only FFCCI should shoulder the arbitration costs. The arbitration
rescission, even after he has chosen fulfillment, if the costs should be shared equally by FFCCI and HRCC in view of the
latter should become impossible. latters unjustified work stoppage.

The court shall decree the rescission claimed, WHEREFORE, in consideration of the foregoing
unless there be just cause authorizing the fixing of a disquisitions, the Decision dated February 6, 2009 and
period. Resolution dated April 13, 2009 of the Court of Appeals in CA-
G.R. SP No. 91860 are
This is understood to be without prejudice to hereby AFFIRMED with MODIFICATION that the arbitration
the rights of third persons who have acquired the thing, costs shall be shared equally by the parties herein.SO
in accordance with Articles 1385 and 1388 and the ORDERED.
Mortgage Law.
FIRST DIVISIONG.R. No. 141897 September 24, 2001
The rescission referred to in this article, more appropriately
referred to as resolution is on the breach of faith by the METRO CONSTRUCTION, INC., petitioner,
defendant which is violative of the reciprocity between the vs.
parties.[44] The right to rescind, however, may be waived, CHATHAM PROPERTIES, INC., respondent.
expressly or impliedly.[45]
DAVIDE, JR., C.J.:
While the right to rescind reciprocal obligations is implied, that
is, that such right need not be expressly provided in the
contract, nevertheless the contracting parties may waive the The core issue in this case is whether under existing law and
same.[46] rules the Court of Appeals can also review findings of facts of
the Construction Industry Arbitration Commission (CIAC).
Contrary to the respective dispositions of the CIAC and the CA,
we find that HRCC had no right to rescind the Subcontract
Respondent Chatham Properties, Inc. (CHATHAM) and petitioner
Agreement in the guise of a work stoppage, the latter having
Metro Construction, Inc. (MCI) entered into a contract for the
waived such right. Apropos is Article 11.2 of the Subcontract
construction of a multi-storey building known as the Chatham
Agreement, which reads:
House located at the corner of Herrera and Valero Streets,
Salcedo Village, Makati City, Metro Manila. In April 1998, MCI
11.2 Effects of Disputes and Continuing
sought to collect from CHATHAM a sum of money for unpaid
Obligations
progress billings and other charges and instituted a request for
adjudication of its claims with the CIAC. The case was docketed
Notwithstanding any dispute,
as CIAC Case No. 10-98. The arbitral tribunal was composed of
controversy, differences or arbitration
Joven B. Joaquin as Chairman, and Beda G. Fajardo and Loreto C.
proceedings relating directly or indirectly
Aquino as members.
to this SUBCONTRACT Agreement and
without prejudice to the eventual outcome
thereof, [HRCC] shall at all times proceed The preliminary conference before the CIAC started in June 1998
with the prompt performance of the and was concluded a month after with the signing of the Terms
Works in accordance with the directives of Reference (TOR) of the Case.1 The hearings immediately
of FFCCI and this SUBCONTRACT started with the presentation of MCI's witnesses, namely: Ms.
Agreement.[47] (Emphasis supplied) Ma. Suzette S. Nucum, Chief Accountant; Ms. Isabela Redito,
Office Engineer; Mr. John Romulo, Field Manager; and Dr. John Y.
Lai, President. CHATHAM's witnesses were: Engr. Ruperto
Hence, in spite of the existence of dispute or Kapunan III, Managing Director of RK Development and
controversy between the parties during the course of the Construction Co., Inc. (RKDCCI), which was the Construction
Subcontract Agreement, HRCC had agreed to continue the Manager firm hired by CHATHAM to oversee the construction
performance of its obligations pursuant to the Subcontract work of the Chatham House; Engr. Alex Bautista, Area Manager
Agreement. In view of the provision of the Subcontract of RKDCCI; Mr. Avelino M. Mercado, CHATHAM's Project Manager;
Agreement quoted above, HRCC is deemed to have effectively and Engr. Jose T. Infante.
waived its right to effect extrajudicial rescission of its contract
with FFCCI. Accordingly, HRCC, in the guise of rescinding the
In the meantime, the TOR was amended and finalized on 19
Subcontract Agreement, was not justified in implementing a
August 1998.2
work stoppage.

The costs of arbitration should be shared by the parties The facts, as admitted by the parties before the CIAC and
equally. incorporated in the original TOR, are as follows:
48
1. On 21 April 1994, the parties formally entered into 10. Whether or not CHATHAM is entitled to claim x x x
a . . . contract for the construction of the "Chatham actual damages? If so, to what extent and how much?
House" . . . for the contract price of price of
P50,000,000.00 inclusive of value-added tax, subject to
11. Whether or not CHATHAM is entitled to x x x
adjustments in accordance with Article 9 of the
additional counterclaims as follows:
contract. Construction of the project, however,
commenced on 15 April 1994 upon the release by
CHATHAM of the down payment 11.1. Core testing expenses and penalty for
concrete strength failure P3,630,587.38.
2. On 12 July 1994, a Supplemental Contract was
executed by and between the parties whereby 11.2. Expenses to rectify structural steel works
CHATHAM authorized MCI to procure in behalf of the for the foundation P1,331,139.74.
former materials, equipment, tools, fixtures,
refurbishing, furniture, and accessories necessary for
11.3. Cost of additional materials (concrete &
the completion of the project.
rebars) supplied by CPI P5,761,457.91.

3. Under Section I.04 of the Supplemental Contract, the


12. Are the parties entitled to their respective claims
total amount of procurement and transportation cost[s]
for attorney's fees and cost of litigation? If so, how
and expenses which may be reimbursed by MCI from
much?3
CHATHAM shall not exceed the amount of P75,
000,000.00.
In the resolution of these issues, the CIAC discovered significant
data, which were not evident or explicit in the documents and
4. In the course of the construction, Change Orders No.
records but otherwise revealed or elicited during the hearings,
1, 4, 8A, 11, 12 and 13 were implemented, payment of
which the CIAC deemed material and relevant to the complete
which were recommended by x x x RKDCCI and
adjudication of the case. In its decision of 19 October 1998, 4
approved by one of CHATHAM's Project Managers,
the CIAC made the following findings and conclusions:
Romulo F. Sugay.

It was established during the hearing that the contract was


5. On 15 September 1995, CHATHAM through its Project
awarded to MCI through negotiation as no bidding was
Manager, Romulo F. Sugay, agreed to give P20,000 per
conducted, x x x It was also revealed that two agreements
floor for five (5) floors, or a total of P100,000.00 as
were entered into, one is labeled Construction Contract for the
bonus/incentive pay to MCI's construction workers for
total fixed amount of P50,000,000.00 and the other a
the completion of each floor on schedule. CHATHAM
Supplemental Contract for an amount not to exceed
reimbursed MCI the amount of P60,000.00
P75,000,000.00. The latter is supposed to cover the
corresponding to bonuses advanced to its workers by
procurement of materials for the project. The Construction
the latter for the 14th, 16th, and 17th floors.
Contract provides for monthly progress billings and payments
based on actual accomplishments of the various phases of
6. CHATHAM's payments to MCI totaled work. The Supplemental Contract provides for; reimbursement
P104,875,792.37, representing payments for portions of [the] total amount of procurement and transportation costs
of MCI's progress billings and x x x additional charges. and expenses, upon MCI's presentation of suppliers'
invoices/receipts.
The parties then stipulated on the following issues, again, as set
forth in the TOR: However, from testimonies of witnesses from both parties, it
was revealed that the two distinct manner(s) of payment to
MCI was set aside. The earlier attempt by CHATHAM to prove
1. Is MCI entitled to its claims for unpaid progress
that MCI was remiss in submitting suppliers' invoices and/or
billings amounting to P21,062,339.76?
receipts in support of its billings against the Supplemental
Contract was in fact later on abandoned when CHATHAM's
2. Were the approved Change Orders 1, 4, 8a, 11, 12 witness Mercado admitted that the matter of adherence to the
and 13 fully paid by CHATHAM? If not, is MCI entitled to payment provision of the Supplemental Contract is a 'non-
its claim for the unpaid balance? issue.' This was borne out by the fact that progress billings
and payments under both contracts were made on the basis
of percentage of project completion.
3. Is CHATHAM liable for Change Orders 7a, 7b, 10, 14,
15, 16, 17, 19 and 20?
Both documentary and testimonial evidence prove that,
effectively, the construction contract and supplemental
4. Were the CHB works from the 8th to the 31st floors
contract is but one agreement for a lump sum contract
part of the original contract or in the nature of
amount of P125,000,000.00.
extra/additional works? Is CHATHAM liable for the
same? If so, how much?
xxx xxx xxx
5. Is MCI entitled to an additional reimbursement of
P40,000.00 for bonuses granted to workers as an There was also the admitted fact that the contract was
incentive for the early completion of each floor? negotiated and awarded in the absence of a complete
construction plan. In any case, in support of the total contract
amount of P125 million, is a Cost Breakdown (Exh. 17-L),
6. Were the deductions in the amount of P1,393,458.84
where the estimated quantities of owner furnished materials
made by CHATHAM in MCI's progress billing
(OFM) are indicated. It is however, understood that these
reasonable?
quantities are estimates, based on (an) incomplete set of
construction plans. It is likewise understood that except for
7. Is MCI's claim of P1,646,502.00 for labor escalation the OFM, all the other costs in the Cost Breakdown form the
valid? basis for the lump-sum agreement under the contract, subject
to adjustment only if there are any significant changes in the
contract plans.
8. Is MCI entitled to payment of attendance fee? To
what extent and how much?
RKDCCI in its letter to MCI dated 15 Feb. 1995 (Exh. 4),
informed MCI that it was confirming the agreement allegedly
9. Did MCI fail to complete and/or deliver the project
accepted by Dr. Lai that the Building Committee will take over
within the approved completion period? If so, is MCI
the management of the construction operations (of the
liable for liquidated damages and how much?
project) albeit under certain conditions. Specifically, the take
49
over was for an interim period and will extend only after 1. That indeed 'special friendly relations' were present
concreting of up to basement level 5 or up to 30 May 1995 between the parties in this case, although decisions by either
whichever is later. The letter also stated that the Building party on any particular issue were made not purely on the
Committee . . . will be responsible for management and basis of such special relations. For example, this Tribunal
direction including management of MCI engineers at the site, believes that, contrary to the allegation of (CHATHAM's)
sequencing of work, additional labor, additional equipment witnesses, the decision not to terminate the contract was not
and management of the yard and staging area. The letter, due to the admitted 'special relations' only, but also due to
however, emphasized that the intent is not a take over of the the greater problems the project would be faced with by
contract or take over of the entire work and in fact, it was terminating the MCI contract and mobilizing another
mentioned that MCI will still be responsible for earth contractor.
anchoring and steel fabrication work.
2. That while there was no official termination of the contract,
CHATHAM claims that the interim take-over was necessitated the manner by which CHATHAM had taken upon themselves
by MCI's delay in the progress of its work, due allegedly to the procurement of materials, the fielding of labor, the control
MCI's lack of manpower and equipment. During the hearings over MCI's engineers, and the subcontracting of various
of this case, this claim of MCI's lack of manpower, necessary phases of work on its own, is considered by this Tribunal as
equipment, qualified engineers and inefficient construction implied termination of the contract. The idea of allowing MCI
management was testified to by both Mr. Mercado [of to remain on the project in spite of what CHATHAM claims. (to
CHATHAM] and Engr. Kapunan of RKDCCI. CHATHAM's be) MCI's shortcomings, and MCI's agreement to stay on the
witnesses, however, testified that in spite of these alleged project under conditions set by CHATHAM, is believed a
deficiencies, MCI was nevertheless allowed to continue to take matter of mutual benefit to both parties.
full control of the operations. When asked why termination of
the contract was not resorted to if truly, MCI was not
3. That CHATHAM's invoking its rights under the provisions of
performing its contracted obligations, witnesses Mercado and
Article 27 of the construction contract is believed out of place,
Kapunan cited "special relations" between the owner of MCI
as it failed to observe the required antecedent acts before it
(Dr. John Lai) and the president of CHATHAM (Mr. Lamberto
can exercise its prerogative under the said contract provision.
Ocampo) as the reason.

4. That there is no reason to believe, either party was in any


On the other hand, Dr. Lai contends that, as explained in his
way guilty of bad faith in acting as it did on certain relevant
letter to CHATHAM dated 17 February 1995, (Exh. 4-A) MCI's
matters. However, this Tribunal is of the belief that due
work was on schedule. During the hearings, Dr. Lai also
perhaps to the eagerness on the part particularly of
insisted that beginning 15 February 1995, MCI was relieved of
CHATHAM's representatives to take such steps it considered
full control of the construction operations, that it was
necessary to insure completion of the project within the
relegated to (be) a mere supplier of labor, materials and
period desired by CHATHAM, it deviated from some generally
equipment, and that the alleged interim takeover actually
accepted procedures in the construction industry in dealing
extended through the completion of the project. Dr. Lai cited
with MCI. One example was not giving MCI the opportunity to
CHATHAM's purchases of materials, fielding labor force and
rectify some of what CHATHAM considered as construction
sub-contracting works allegedly for the project without his
deficiencies and instead engaging the services of other
knowledge and consent as proof that CHATHAM had taken full
parties to undertake the corrective works and later on
control of the project.
charging the costs thereof to MCI.

To the above allegation of MCI that CHATHAM went ahead and


In addition to the above conclusions resulting from what this
procured materials, hired labor and entered into sub-contract
Tribunal considered peculiar of circumstances surrounding the
agreements with the intention of eventually charging the
implementation of the project that were revealed during the
costs thereof to MCI, witness Mercado countered, that
proceedings of this case, this Tribunal finds the necessity of
CHATHAM has the right to do this under the provisions of
establishing a cut-off date with regard to the fiscal liability of
Article 27 of the contract, dealing with 'Recision, Cancellation,
one party towards the other.
Termination of Contract.'

Mr. Avelino Mercado of CHATHAM presented a list of what he


By way of responding to the various counterclaims of
claims as its Payments to MCI (Exhibit 7) summarized as
CHATHAM, MCI referred to a letter of the former addressed to
follows:
MCI dated 18 January 1997 (Exhibit E-1) the first paragraph of
which reads as follows:

After evaluating all the documents issued and received from


both Chatham Properties Inc. and Metro Construction, Inc., the a. Down payment (Paid in two equal trances
Building Committee of Chatham Properties, Inc. evaluated
them. The Building Committee finds the total receivable of
Metro Construction is in the amount of EIGHT MILLION PESOS
(P8,000,000.00) only.
b. Cash Advance for Mobilization

When queried by the Tribunal if the said amount already took


into account the costs and expenses, (Chatham) claims to
have incurred for the account of MCI, Mr. Mercado answered in
the affirmative. When queried further how the amount was c. Payments of Progress Billings up to Billing No. 19
arrived at, Mr. Mercado replied that it was the sum the
Building Committee figured it was willing to pay MCI simply to
close the issue.
d. Other Payments (Mar 1994 to Apr. 1996)
Mr. Mercado even added that while MCI is not actually entitled
to this amount, it was out of a friendship" that CHATHAM
offered this sum to MCI as final settlement under the contract.
e. Advances on MCI Payrolls (April 1996 to March
It is with the above attendant circumstances that this Tribunal 1997)
will be guided in the resolution of issues brought before it for
adjudication. From what this Tribunal finds as peculiar
circumstances surrounding the contracting and
implementation of the CHATHAM House Project. it arrived at Total
the following fundamental conclusions:
50
In consideration of the above facts, this Tribunal's conclusion
that there was in fact an implied take over of the project is
further confirmed. Furthermore, this Tribunal additionally
concludes that the cut-off date for purposes of delineating the
financial obligations of the parties between them should be 23
May 1996, the date when CHATHAM evaluated MCI's
The records of this case show that the last progress payment accomplishment at 94.10% but nevertheless suspended all
to MCI was in January 1996 representing payment of Progress further progress payments to MCI.
Billing No. 19 for the period ending 31 December 1995. The
percentage of completion claimed then by MCI was 80.02%,
MCI presented further documentary evidence (Exhibit E-6) the
the amount evaluated and eventually paid to MCI was the
subject of which is a PUNCHLISTING-CIVIL STRUCTURAL." In
equivalent of 77.15% work accomplishment. No further
this particular document which bears the signatures of
progress payments were made thereafter, other than for
representatives of both MCI and RKDCCI, MCI tried to prove
advances to cover MCI payrolls from April 1996 to March 1997
that as of 30 August 1996 it had actually attained 99.16%
in the amount of P8,196,755.51 and for various advances and
work accomplishment. While it may be true that as of that
payments of approved change orders in the amount of
date the project had reached 99.16% completion, there is no
P5,474,419.67.
incontrovertible evidence showing that MCI was responsible
for such accomplishment. This was in fact actually testified to
In the meantime, up to Billing No. 23 for the period ending 30 by Engr. Alex Bautista of RKDCCI, when he said that it was an
April 1996, MCI billed CHATHAM a total accomplishment of evaluation of the project's completion stage, not necessarily
95.29%. This billing was however, evaluated by CHATHAM, MCI's work accomplishment. This Tribunal therefore stands
and in its letter to MCI dated 27 May 1996 (Exhibit E) it firm on its conclusion that MCI's accomplishment is only up to
confirmed that MCI's remaining balance of work stands at the extent of 94.10%.5
P7,374,201.15 as of 23 May 1996. This amount, percentage-
wise, equals roughly 5.88% of the contract amount as testified
With those findings, the CIAC disposed of the specific money
to by Engr. Jose Infante. (Exhibit 22-B). Therefore, what was
claims by either granting or reducing them. On Issue No. 9, i.e.,
computed as MCI's work accomplishment as of 23 May 1996
whether CHATHAM failed to complete and/or deliver the project
was 94.12% and it is this evaluation which this Tribunal
within the approved completion period and, if so, whether
believes MCI is entitled to as of said date.
CHATHAM is liable for liquidated damages and how much, the
CIAC ruled in this wise:
Applying this percentage of completion of 94.12% to the
P125,000,000.00 contract amount gives a total
This Tribunal holds that the provision of the contract insofar as
accomplishment equivalent to P117,650,000.00 as of 23 May
the Overall Schedule is concerned cannot justifiably be
1996. Add to this amount the sum of P5,353,091.08
applied in the instant case in view of the implied take-over of
representing the total of approved Change Orders as of 31
the Chatham House project by CHATHAM. Accordingly, this
December 1995 gives a total MCI accomplishment of
Tribunal finds no necessity to resolve whether or not MCI
P123,003,091.08, as CHATHAM saw it. Of this amount,
complete[d] and/or deliver[ed] the project within the
CHATHAM admitted having paid MCI the total sum of
approved completion period. In fact, Mr. Mercado testified that
P104,752,358.42 only (Exhibit 7) up to March 15, 1997,
it was CHATHAM who ultimately completed the project, with
leaving a balance of P18,250,732.66. It should be noted that
assistance of the construction managers.
of the total payment of P104,752,358.42, the sum of
P5,750,000.00 was paid after May 1996 so that as of 25 May
1996, CHATHAM's total payment to MCI was P99,002,358.42. In any case, this Tribunal finds merit in RKDCCI's claim that
MCI was in delay in the concreting milestone and that [it] is
liable for liquidated damages therefor. This, notwithstanding
Effectively, therefore, the amount due MCI as of 23 May 1996
MCI's invoking that Chatham is estopped from claiming
amounted to P24,005,732.66 computed as follows:
liquidated damages after it failed to deduct the alleged
liquidated damages from MCI's progress billings. This Tribunal
holds that such failure to deduct, which CHATHAM claims it did
in order not to hamper progress of work in the project, is an
Total accomplishment as of 23 May 1996 at option which [it] may or may not exercise.
94.12%

However, this Tribunal finds that CHATHAM's Exh. 11-A where


the liquidated damages on delays in concreting milestone was
applied is not consistent with [its] own Exhibit 3-I. This
Add approved change orders Tribunal notes that in Exh. 11-A, CHATHAM included a
projected delay of 85 days for the Helipad Concreting works,
while no such projected delay was included in Exh. 3-I as it
should be.
Total
This Tribunal holds that Exh. 3-I showing a delay of 294 days
in concreting milestones should rightfully be used in
computing liquidated damages. Accordingly, this Tribunal
Less payments up to 23 May 1996 holds that MCI is liable for liquidated damages in the amount
of P3,062,498.78 as follows:

1/4 x 1/3[(1/10 x P125,000,000.00) 1%] x 294 =


Balance due MCI as of 23 May 1996 P3,062,498.78.6

The CIAC then decreed:

Of the above balance of P24,005,732.66 as of 23 May 1996,


the only payments made by CHATHAM to MCI is the sum of Accordingly, as presented below, all the amounts due MCI are
P5,750,000.00 from June 1996 onwards, allegedly to cover first listed and added up and the total payment is deducted
MCI payrolls. It is of course noted that CHATHAM's suspension therefrom. The admitted total payment figure as reflected in
of further payments to MCI was because it had been the Terms of Reference is the amount applied instead of the
undertaking on its own, the further procurement of materials total reflected in CHATHAM's Summary of Payments which
and sub-contracting of various phases of works on the project. incidentally reflected a lesser amount. From the 'Balance Due
MCI' the 'Amounts CPI is Held Entitled To' is deducted and the
'Net Amount Due MCI' is arrived at.
51

A. AMOUNTS HELD CPI IS ENTITLED TO: C. NET AMOUNT DUE MCI (A minus B)

A.1. From the original contract: WHEREFORE, judgment is hereby rendered in favor of the
94.12% of P125,000,000.00 Claimant [MCI] directing Respondent [CHATHAM] to pay
Claimant [MCI] the net sum of SIXTEEN MILLION ONE
HUNDRED TWENTY SIX THOUSAND NINE HUNDRED TWENTY
TWO & 91/100 (16,126,922.91) PESOS.

A.2. Approved Change Orders


SO ORDERED.7

Impugning the decision of the CIAC, CHATHAM instituted a


A.3 Pending Change Orders petition for review with the Court of Appeals, which was
docketed as CA-G.R. SP No. 49429. In its petition, CHATHAM
alleged that:

A.4 CHB Works The Arbitral Tribunal grossly erred in failing to indicate
specific reference to the evidence presented or to the
transcript of stenographic notes in arriving at its
questioned Decision, in violation of the cardinal rule
under Section 1, Rule 36 of the Revised Rules of Civil
A.5 Workers Bonus Procedure that a judgment must state clearly and
definitely the facts and the law on which it is based.

The Tribunal's conclusions are grounded entirely on


A.6 Disputed Deductions speculations, surmises and conjectures.

The Arbitral Tribunal grossly erred in failing to consider


the evidence presented by CHATHAM and the
A.7 Labor Escalation testimony of its witnesses.

The Arbitral Tribunal gravely abused its discretion in


considering arbitrarily that there was an implied
A.8 Attendance Fee takeover contrary to the facts and evidence submitted.

The Arbitral Tribunal committed grave error and gross


misapprehension of facts in holding that CHATHAM is
Total
not entitled to liquidated damages despite failure of
MCI to meet the over-all schedule of completion.

The Arbitral Tribunal manifestly erred in holding that


Less: Total payments - Item 11-6 of TOR
MCI is entitled to its claim for unpaid progress billings.

The Arbitral Tribunal committed gross and reversible


error in equating the percentage of MCI's work
Balance Due MCI
accomplishment with the entire work in place, despite
evidence to the contrary.

The Arbitral Tribunal gravely erred in making 23 May


B. AMOUNTS HELD CPI IS ENTITLED TO:
1996 as the cut-off date for purposes of delineating the
financial obligations of the parties.

The Arbitral Tribunal erred in denying CHATHAM its


B.1. liquidated Damages
claim for actual damages pursuant to Article 27.8 of the
Construction Contract.

The facts set forth in CHATHAM's Answer with


B.2. Actual Damages
Compulsory Counterclaim as well as its documentary
and testamentary evidence were not overturned or
controverted by any contrary evidence.8

B.3. Penalties
In its decision of 30 September 1999, 9 the Court of Appeals
simplified the assigned errors into one core issue, namely, the
"propriety" of the CIAC's factual findings and conclusions. In
upholding the decision of the CIAC, the Court of Appeals
B.4. Cash Payments in Behalf of MCI confirmed the jurisprudential principle that absent any showing
of arbitrariness, the CIAC's findings as an administrative agency
and quasi judicial body should not only be accorded great
respect but also given the stamp of finality. However, the Court
Total Amount Due CPI of Appeals found exception in the CIAC's disquisition of Issue
No.9on the matter of liquidated damages.

The Court of Appeals disagreed with the CIAC's finding that


there was an implied takeover by CHATHAM of the project and
52
that it was unnecessary for the CIAC to rule on whether MCI Exhibit "4-D" Letter dated 4 January 1996
completed and/or delivered the project within the approved indicating that Mr. H.T. Go offered Dr Lai an
completion schedule of the project since CHATHAM failed to incentive of P1,800,000 on the condition that
observe the antecedent acts required for the termination of the MCI meets the new schedule/milestones. MCI's
contract, as set forth in the Construction Agreement. acceptance of the incentive offer likewise
shows that MCI was in control of the Project.
The Court of Appeals ascertained that the evidence
overwhelmingly proved that there was no takeover by CHATHAM Exhibits "5," "3-1," "3-M," "3-N," "3-W-1," 3-X,"
and that MCI exercised complete control, authority and "3-Y," and "3-Z" among others containing
responsibility over the construction. In support of this reminders to MCI of its duties and
conclusion, the appellate court pointed to the following shortcomings, likewise attest to the fact that
evidentiary bases:10 MCI was in control (of) and responsible for the
Project, although markedly deficient.
1. Testimony of CHATHAM's Engr. Kapunan that the
interim takeover for the works on the basement was Exhibits "5," "5-A," "5-B," "5-C," "5-D," "5-E,"
triggered by lack of manpower and delays as early as "5-F," "5-O," "C-7," and "E-9" evidencing
February 1995, as evidenced by their assessment 11and that MCI continued to manage other works on
that the interim takeover was only with respect to the the project even during the time of the interim
direction or management of the field operations and takeover of the basement works, as seen in
was limited only to works on the basement and the series of communications between
intended to assist MCI to catch up with the schedule of CHATHAM or RKDCCI and MCI within the period
completion, since at that time the project was very beginning February 1995 to 30 May 1995.
much delayed; thereafter, the MCI was back in full
control of the project.12
5. Respondent's Request for Adjudication, Annex G,
Records, Folder No. 6 which incorporated Change
2. Testimony of Engr. Bautista that the takeover was Order No. 12, among others, dated 28 August 1995,
only partial and temporary and limited to the recommended by the RKDCCI and accepted by Dr. Lai,
management portion on the basement only and that and which request for an extension of 25 days readily
MCI was always in control of the project.13 showed that even after 30 May 1995, after the close of
the supposed takeover period, MCI was still the
contractor in complete control of the project for it
3. Testimony of Engr. Infante that MCI personnel were
would not have otherwise accepted the said change
constantly present in the project and the "intervention"
order if it (were) no longer the Contractor of the project
(not takeover) by CHATHAM was justified to ensure
due to the termination of the Construction agreement
completion of the project on time.14
as of said date on account of the alleged takeover.

4. Documentary exhibits evincing the nature and


6. Exhibits "3-J," "3-M," "3-Q," "3-R," "3-V," "3- W-1," "3-
extent of MCI's work during the takeover period which
W-2," "5-F," "5-1," "6," "12-II," "12-JJ," "12-MM," and
belied its claims that it was not in control of the project
"12-NN" tending to prove that RKDCCI monitored the
because of the takeover thus:
work from start to finish and had zealously pointed out
to MCI the defects or improper execution of the
Exhibit "4" Letter dated 15 February 1995 of construction works, and gave MCI all the opportunity to
Engr. Kapunan of RKDCCI to John Lai of MCI rectify the construction deficiencies and complete the
stating that the takeover of directions or works of the project.
management of the field operations is interim,
i.e. while the takeover is effective immediately
The Court of Appeals concluded that the interim takeover was
it will extend only after concreting Level B-1 or
necessitated by CHATHAM's insistence to meet its own turnover
approximately until 30 May 1995 which ever is
dates with the buyers of the project's units. Thus, CHATHAM was
later.
constrained to hire subcontractors with sufficient manpower and
supervision and incur various expenses to facilitate the
Exhibit "4-A" Letter dated 17 February 1995 completion of the project and/or assist MCI in making up for its
written by Dr. Lai of MCI to Engr. Kapunan in delay.
response to the latter's 15 February 1995
letter stating that "[Also we were assured that
The Court of Appeals then considered it imperative to determine
we will not be responsible for any errors or
whether MCI failed to complete the project on time for which it
accidents that may occur during this INTERIM
may be held liable for liquidated damages based on the delays
period," indicating that Dr. Lai was very much
in the overall schedule of completion pursuant to Art. 13.5 of the
aware of the interim period.
Construction Agreement, to wit:

Exhibit "4-C" Letter dated 18 February 1995


13.5. Over-All Schedule For not meeting the final
written by Engr. Ben C. Ruiz of RKDCCI to Dr.
completion date of the PROJECT, the OWNER will
Lai containing the reasons for the takeover.
deduct from the Contract Sum or amounts due the
CONTRACTOR, the amount equivalent to 1/10 of 1% of
Exhibit "8A" Letter dated 5 September 1995 the Contract Sum for every calendar day of delay,
written by Dr. E.G. Tabujara to Dr. Lai/Romy provided, however, that the maximum penalty should
Laron (Project Manager of MCI) requesting for not exceed 25% of the fee payable to the CONTRACTOR
an engineer of MCI to accompany the as stipulated in the Bill of Quantities. Penalties from
inspector of RKDCCI to witness batching concreting milestones shall be deducted from the
procedures. By so doing, Dr. E.G. Tabujara penalty of Over-All Schedule.15
acknowledged that Dr. Lai was in control of the
project.
The Court of Appeals disposed of the controversy in this wise:

Exhibit "8" Letter dated 4 September 1995


As is extant from the records, the completion date of
by Engr. Romulo R Sugay to Dr. Lai offering an
the Project under the Construction Contract or under
incentive to the workers of MCI to exert (their)
the revised construction schedule was never met by
best effort for topping off by the end of
reason of [MCI's] lack of manpower, necessary
December; another clear indication that Dr. Lai
equipment, qualified engineers and inefficient
was in control of the project.
management of construction works on the Project.
Thus, under the Contract (Exhibit '1'), [MCI] had 780
53
days, or until 22 January 1996, from starting date, or
April 12, 1994, to finish the project. The completion
date, however, was not followed and was revised as
early as December 17, 1994, extending the milestone
dates up to March 15, 1996 (Exhibits '3-G' and '3-H').
As of December 25, 1995, the number of days delayed
was already 294 days. Thus, on February 22, 1996, the
contract milestones were again revised, inclusive of 53 A.7 Labor Escalation
days extension, to May 23, 1996 (Exhibits '3-I' and '3-
O'). The May 23, 1996 turnover milestone nor the July
22, 1996 turnover of the whole project were neither
met (Exhibits '3-P', '3-R', '3-S' and '3-T' but [CHATHAM] A.8 Attendance Fee
was again constrained to allow [MCI] to continue
working on the Project to complete the balance of the
works (Exhibit 'M'). And all throughout the construction
of the Project, [CHATHAM] had to assist [MCI] along the
Total
way to expedite the execution and completion of the
Project (Exhibits '3-K' and '3-V').

From the foregoing disquisitions, it is clear that [MCI] is


Less: Total payments-item 11-6 of TOR
liable for liquidated damages, as per Article 13.5 of the
Construction Contract, for its failure to complete the
project within the period stipulated in the Construction
Contract and even despite an extension of 53 days
from the original schedule or of the overall schedule of Balance Due Respondent
completion. [MCI] should therefore pay [CHATHAM] the
amount of liquidated damages equivalent to
P24,125,000.00 for 193 days of delay in the overall
schedule of completion counted from overall
B. AMOUNTS [CHATHAM] IS ENTITLED TO:
completion date on July 22, 1996 up to the date of
completion on February 15, 1997, as stated in the
Certificate of Occupancy, computed as follows, to wit:

B.1. liquidated Damages


1/10[1%(P125,000,000.00)] per day x 193
days

= [1/10 (P1,250,000.00)] per day x 193 days B.2. Actual Damages

= P125,000.00 per day x 193 days

= P24,125,000.00 B.3. Penalties

IN VIEW OF ALL THE FOREGOING, judgment is hereby


rendered partially granting [CHATHAM's] claim for
liquidated damages. The Tribunal's Decision dated 19 B.4. Cash Payments in behalf of MCI
October 1998 is hereby AFFIRMED with the modification
on [MCI's] liability for liquidated damages in the
amount of P24,125,000.00. Thus,
Total Amount Due CPI

A. AMOUNT [MCI] IS ENTITLED TO:


C. NET AMOUNT DUE [CHATHAM] (B minus A)

A.1. From the original contract:


94.12% of P125,000,000.00 Correspondingly, Respondent [MCI] is hereby directed
to pay the Petitioner [CHATHAM] the net sum of FOUR
MILLION NINE HUNDRED THIRTY-FIVE THOUSAND FIVE
HUNDRED SEVENTY-EIGHT & 31/100 (P4,935,578.31)
A.2 Approved Change Orders PESOS.16

MCI promptly filed on 25 October 1999 a motion for


reconsideration. In its Resolution of 4 February 2000, the Court
A.3 Pending Change Orders of Appeals denied MCI's motion for reconsideration for lack of
merit, as well as CHATHAM's Motion to Lift Garnishment and
Levy Pending Appeal, filed on 13 October 1999, for being
premature.17
A.4 CHB Works
Thus, MCI filed the instant petition for review to challenge the
decision of the Court of Appeals. MCI alleges that the Court of
Appeals erred in reviewing and reversing the CIAC's factual
findings, that there was an implied takeover by CHATHAM of the
A.5 Workers Bonus
project, and that MCI was not in delay in the overall schedule. In
so doing, the Court of Appeals contravened Section 19 of
Executive Order (E.O.) No. 1008,18 which limits the review of an
Arbitral Award to only questions of law, thus:
A.6 Disputed Deductions
54
SECTION 19. Finality of Awards The arbitral award in Section 19 of E.O. No. 1008 and vested the same in the Court
shall be binding upon the parties. It shall be final and of Appeals, and whether appeals from CISC awards are no
inappealable (sic), except on questions of law which longer confined to questions of law.
shall be appealable to the Supreme Court.
On 27 February 1991, this Court issued Circular No. 1-91, which
MCI then asserts that as signatories to the contract, it and prescribes the Rules Governing Appeals to the Court of Appeals
CHATHAM complied with this legal provision when they included from Final Orders or Decisions of the Court of Tax Appeals and
as part of their TOR the stipulation that "[t]he decision of the Quasi-Judicial Agencies. Pertinent portions thereof read as
Arbitral Tribunal shall be final and non-appealable except on follows:
questions of law." Accordingly, the binding character of this
provision upon the parties is conclusive and final.
1. Scope. These rules shall apply to appeals from
final orders or decisions of the Court of Tax Appeals.
MCI also contends that while it may be argued that recent (1) They shall also apply to appeals from final orders or
issuances by the Supreme Court, specifically, Circular No. 1-91, decisions of any quasi-judicial agency from which an
which eventually became Revised Administrative Circular No. 1- appeal is now allowed by statute to the Court of
95; (2) legislation in particular, Republic Act No. 7902, which Appeals or the Supreme Court. Among these agencies
amended Batas Pambansa Blg. 129; and (3) amendments to the are the Securities and Exchange Commission, Land
Rules on Civil Procedure, modifying E.O. No. 1008 in the sense Registration Authority, Social Security Commission,
that "questions of facts, of law, or mixed questions of facts and Civil Aeronautics Board, Bureau of Patents, Trademarks
law may be the subject of an appeal of the CIAC's decision to and Technology Transfer, National Electrification
the Court of Appeals," it is still E.O. No. 1008 which remains to Administration, Energy Regulatory Board, National
be the fundamental and substantive law that endows parties to Telecommunications Commission, Secretary of Agrarian
an arbitral controversy the right to appeal. Hence, the provisions Reform and Special Agrarian Courts under RA. No.
on appeal of E.O. No. 1008 should be controlling, i.e., only 6657, Government Service Insurance System,
questions of law should be entertained. Therefore, the only Employees Compensation Commission, Agricultural
effect of these rules on E.O. No. 1008 is the transfer of the Inventions Board, Insurance Commission and Philippine
appeal forum from the Supreme Court to the Court of Appeals. Atomic Energy Commission.

MCI further asserts that, even assuming that the CIAC's findings 2. Cases not Covered. These rules shall not apply to
of facts are reviewable on appeal, the Court of Appeals gravely decisions and interlocutory orders of the National Labor
abused its discretion when it accepted "hook, line and sinker" Relations Commission or the Secretary of Labor and
CHATHAM's contention that MCI was in delay, and ignored Employment under the Labor Code of the Philippines,
competent, clear and substantial evidence that prove the the Central Board of Assessment Appeals, and other
contrary, and that CHATHAM is not entitled to liquidated quasi-judicial agencies from which no appeal to the
damages. courts is prescribed or allowed by statute.

For its part, CHATHAM avers that the evolution on the rules 3. Who may appeal and where to appeal. The appeal
governing appeals from judgments, decisions, resolutions, of a party affected by a final order, decision, or
orders or awards of the CIAC convincingly discloses that E.O. No. judgment of the Court of Tax Appeals or a quasi judicial
1008 has already been superseded. With the power of the agency shall be taken to the Court of Appeals within
Supreme Court to promulgate rules concerning the protection the period and in the manner herein provided, whether
and enforcement of constitutional rights, pleadings, practice, the appeal involves questions of fact or of law or mixed
and procedure in all courts, its issuances and amendments to questions of fact and law. From final judgments or
the Rules on Civil Procedure, not to mention R A. No. 7902, as decisions of the Court of Appeals, the aggrieved party
enacted by Congress, effectively modified E.O. No. 1008. may appeal by certiorari to the Supreme Court as
Accordingly, the judgments, awards, decisions, resolutions, provided in Rule 45 of the Rules of Court.
orders or awards of the CIAC are now appealable to the Court of
Appeals on questions of facts, mixed questions of facts and law,
Subsequently, on 23 February 1995, RA. No. 7902 was enacted.
and questions of law, and no longer with the Supreme Court on
It expanded the jurisdiction of the Court of Appeals and
exclusively questions of law. Further, the TOR cannot limit the
amended for that purpose Section 9 of B.P. Blg. 129, otherwise
expanded jurisdiction of the Court of Appeals based on the
known as the Judiciary Reorganization Act of 1980.20
latest rules. Thus, the Court of Appeals did not err in reviewing
the factual findings of the CIAC.
Section 9(3) thereof reads:
CHATHAM also contends that, even if the Court of Appeals can
only review questions of law, said court did not err in rendering SECTION 9. Jurisdiction. The Court of Appeals shall
the questioned decision as the conclusions therein, drawn as exercise:
they were from factual determinations, can be considered
questions of law. .
xxx xxx xxx

Finally, CHATHAM asseverates that the Court of Appeals did not


(3) Exclusive appellate jurisdiction over all final
commit grave abuse of discretion in reversing the CIAC's
judgments, decisions, resolutions, orders or awards of
ascertainment on the implied take-over and liquidated damages.
Regional Trial Courts and quasi-judicial agencies,
instrumentalities, boards or commissions, including the
This Court shall now resolve the primary issue raised in this Securities and Exchange Commission, the Social
case. Security Commission, the Employees Compensation
Commission and the Civil Service Commission, except
those falling within the appellate jurisdiction of the
EO. No. 1008 vest upon the CIAC original and exclusive
Supreme Court in accordance with the Constitution, the
jurisdiction over disputes arising from, or connected with,
Labor Code of the Philippines under Presidential Decree
contracts entered into by parties involved in construction in the
No. 442, as amended, the provisions of this Act, and of
Philippines, whether the dispute arises before or after the
subparagraph (1) of the third paragraph and
completion of the contract, or after the abandonment or breach
subparagraph (4) of the fourth paragraph of Section 17
thereof.19 By express provision of Section 19 thereof, the arbitral
of the Judiciary Act of 1948.
award of the CIAC is final and unappealable, except on questions
of law, which are appealable to the Supreme Court.
The Court of Appeals shall have the power to try cases
and conduct hearings, receive evidence and perform
The parties, however, disagree on whether the subsequent
any and all acts necessary to resolve factual issues
Supreme Court issuances on appellate procedure and R.A. No.
raised in cases falling within its original and appellate
7902 removed from the Supreme Court its appellate jurisdiction
55
jurisdiction, including the power to grant and conduct the reviewing body to resolve questions of fact or of law or
new trials or further proceedings. x x x mixed questions of fact and law.

Then this Court issued Administrative Circular No. 1-95, 21 which It is clear that Circular No. 1-91 covers the CIAC. In the first
revised Circular No. 1-91. Relevant portions of the former reads place, it is a quasi judicial agency. A quasi-judicial agency or
as follows: body has been defined as an organ of government other than a
court and other than a legislature, which affects the rights of
private parties through either adjudication or rule-making. 22 The
1. Scope. These rules shall apply to appeals from
very definition of an administrative agency includes its being
judgments or final orders of the Court of Tax Appeals
vested with quasi judicial powers. The ever increasing variety of
and from awards, judgments, final orders or resolutions
powers and functions given to administrative agencies
of any quasi-judicial agency from which an appeal is
recognizes the need for the active intervention of administrative
authorized to be taken to the Court of Appeals or the
agencies in matters calling for technical knowledge and speed in
Supreme Court. Among these agencies are the
countless controversies which cannot possibly be handled by
Securities and Exchange Commission, Land
regular courts.23 The CIAC's primary function is that of a quasi-
Registration Authority, Social Security Commission,
judicial agency, which is to adjudicate claims and/or determine
Civil Aeronautics Board, Bureau of Patents, Trademarks
rights in accordance with procedures set forth in E.O. No. 1008.
and Technology Transfer, National Electrification
Administration, Energy Regulatory Board, National
Telecommunication Commission, Department of In the second place, the language of Section 1 of Circular No. 1-
Agrarian Reform under Republic Act No. 6657, 91 emphasizes the obvious inclusion of the CIAC even if it is not
Government Service Insurance System, Employees named in the enumeration of quasi-judicial agencies. The
Compensation Commission, Agricultural Inventions introductory words "[a] among these agencies are" preceding
Board, Insurance Commission, Philippine Atomic Energy the enumeration of specific quasi-judicial agencies only highlight
Commission, Board of Investments, and Construction the fact that the list is not exclusive or conclusive. Further, the
Industry Arbitration Commission. overture stresses and acknowledges the existence of other
quasi-judicial agencies not included in the enumeration but
should be deemed included. In addition, the CIAC is obviously
SECTION 2. Cases Not Covered. These rules shall not
excluded in the catalogue of cases not covered by the Circular
apply to judgments or final orders issued under the
and mentioned in Section 2 thereof for the reason that at the
Labor Code of the Philippines, Central Board of
time the Circular took effect, E.O. No. 1008 allows appeals to the
Assessment Appeals, and by other quasi-judicial
Supreme Court on questions of law.
agencies from which no appeal to the court is
prescribed or allowed.
In sum, under Circular No. 1-91, appeals from the arbitral
awards of the CIAC may be brought to the Court of Appeals, and
SECTION 3. Where to Appeal. An appeal under these
not to the Supreme Court alone. The grounds for the appeal are
rules may be taken to the Court of Appeals within the
likewise broadened to include appeals on questions of facts and
period and in the manner herein provided, whether the
appeals involving mixed questions of fact and law.
appeal involves questions of fact, of law, or mixed
questions of fact and law.
The jurisdiction of the Court of Appeals over appeals from final
orders or decisions of the CIAC is further fortified by the
Thereafter, this Court promulgated the 1997 Rules on Civil
amendments to B.P. Blg. 129, as introduced by RA. No. 7902.
Procedure. Sections 1, 2 and 3 of Rule 43 thereof provides:
With the amendments, the Court of Appeals is vested with
appellate jurisdiction over all final judgments, decisions,
SECTION 1. Scope. This Rule shall apply to appeals resolutions, orders or awards of Regional Trial Courts and quasi-
from judgments or final orders of the Court of Tax judicial agencies, instrumentalities, boards or commissions,
Appeals and from awards, judgments, final orders or except "those within the appellate jurisdiction of the Supreme
resolutions of or authorized by any quasi-judicial Court in accordance with the Constitution, the Labor Code of the
agency in the exercise of its quasi-judicial functions. Philippines under Presidential Decree No. 442, as amended, the
Among these agencies are the Civil Service provisions of this Act, and of subparagraph (1) of the third
Commission, Central Board of Assessment Appeals, paragraph and subparagraph (4) of the fourth paragraph of
Securities and Exchange Commission, Office of the Section 17 of the Judiciary Act of 1948."
President, Land Registration Authority, Social Security
Commission, Civil Aeronautics Board, Bureau of
While, again, the CIAC was not specifically named in said
Patents, Trademarks and Technology Transfer, National
provision, its inclusion therein is irrefutable. The CIAC was not
Electrification Administration, Energy Regulatory Board,
expressly covered in the exclusion. Further, it is a quasi-judicial
National Telecommunications Commission, Department
agency or instrumentality. The decision in Luzon Development
of Agrarian Reform under Republic Act No. 6657,
Bank v. Luzon Development Bank Employees 24 sheds light on
Government Service Insurance System, Employees
the matter, thus:
Compensation Commission, Agricultural Inventions
Board, Insurance Commission, Philippine Atomic Energy
Commission, Board of Investments, Construction Assuming arguendo that the voluntary arbitrator or the
Industry Arbitration Commission, and voluntary panel of voluntary arbitrators may not strictly be
arbitrators authorized by law. considered as a quasi-judicial agency, board or
commission, still both he and the panel are
comprehended within the concept of a 'quasi-judicial
SECTION 2. Cases Not Covered. This Rule shall not
instrumentality.' It may even be stated that it was to
apply to judgments or final orders issued under the
meet the very situation presented by the quasi-judicial
Labor Code of the Philippines.
functions of the voluntary arbitrators here, as well as
the subsequent arbitrator/arbitral tribunal operating
SECTION 3. Were to Appeal. An appeal under this under the Construction Industry Arbitration
Rule may be taken to the Court of Appeals within the Commission, that the broader term 'instrumentalities'
period and in the manner herein provided, whether the was purposely included in [Section 9 of B.P. Blg. 129 as
appeal involves question of fact, of law, or mixed amended by RA. No. 7902].
questions of fact and law.
An instrumentality' is anything used as a means or
Through Circular No. 1-91, the Supreme Court intended to agency. Thus, the terms governmental 'agency' or
establish a uniform procedure for the review of the final orders 'instrumentality' are synonymous in the sense that
or decisions of the Court of Tax Appeals and other quasi judicial either of them is a means by which a government acts,
agencies provided that an appeal therefrom is then allowed or by which a certain government act or function is
under existing statutes to either the Court of Appeals or the performed. The word 'instrumentality,' with respect to a
Supreme Court. The Circular designated the Court of Appeals as state, contemplates an authority to which the state
56
delegates governmental power for the performance of The CIAC is certain that the evidence overwhelmingly tended to
a state function. prove that the manner by which CHATHAM took charge in the
procurement of materials, fielding of labor, control of MCI
engineers and the subcontracting of various phases of the work,
Any remaining doubt on the procedural mutation of the
constituted an implied takeover of the project. The CIAC then
provisions on appeal in E.O. No. 1008, vis-a-vis Circular No. 1-91
concludes that the cut-off date for delineating the fiscal
and R A. No. 7902, was completely removed with the issuance
liabilities of the parties is 23 May 1996 when CHATHAM
by the Supreme Court of Revised Administrative Circular No. 1-
evaluated MCI's work accomplishment at 94.12% and then
95 and the 1997 Rules of Civil Procedure. Both categorically
suspended all further progress payments to MCI. For these
include the CIAC in the enumeration of quasi-judicial agencies
reasons, the CIAC found it trifling to determine whether MCI was
comprehended therein. Section 3 of the former and Section 3,
in delay based on the Overall Schedule. However, the CIAC
Rule 43 of the latter, explicitly expand the issues that may be
discovered that MCI was in delay for 294 days in the concreting
raised in an appeal from quasi judicial agencies or
milestone and held the latter liable for liquidated damages in
instrumentalities to the Court of Appeals within the period and in
the amount of P3,062,498.78.
the manner therein provided. Indisputably, the review of the
CIAC award may involve either questions of fact, of law, or of
fact and law. The Court of Appeals made a contrary conclusion and declared
that MCI was in delay for 193 days based on the overall
schedule of completion of the project and should incur
In view of all the foregoing, we reject MCI's submission that
liquidated damages in the amount of P24,125,000.00.
Circular No. 1-91, B.P. Blg. 129, as amended by RA. 7902,
Revised Administrative Circular 1-95, and Rule 43 of the 1997
Rules of Civil Procedure failed to efficaciously modify the It is undisputed that the CIAC and the Court of Appeals found
provision on appeals in E.O. No. 1008. We further discard MCI's MCI liable for liquidated damages but on different premises.
claim that these amendments have the effect of merely Based on the CIAC's assessment, MCI's responsibility was
changing the forum for appeal from the Supreme Court to the anchored on its delay in the concreting milestone, while the
Court of Appeals. Court of Appeal's evaluation concentrated on MCI's delay in
completing the project based on the overall schedule of work.
The variance in the evaluation spells a staggering difference in
There is no controversy on the principle that the right to appeal
the party who should ultimately be held liable and the net
is statutory. However, the mode or manner by which this right
amount involved.
may be exercised is a question of procedure which may be
altered and modified provided that vested rights are not
impaired. The Supreme Court is bestowed by the Constitution A study of the final computation of the net amount due in both
with the power and prerogative, inter alia, to promulgate rules the final disquisition of the CIAC and the Court of Appeals shows
concerning pleadings, practice and procedure in all courts, as that all the other figures therein are constant, save for the
well as to review rules of procedure of special courts and quasi- amount of liquidated damages for which MCI should be
judicial bodies, which, however, shall remain in force until accountable. If this Court concurs with the CIAC's conclusions,
disapproved by the Supreme Court. 25 This power is MCI's responsibility for liquidated damages is, as already stated,
constitutionally enshrined to enhance the independence of the P3,062,498.78. Setting this off against CHATHAM's overall fiscal
26
Supreme Court. accountability would bring the latter's total liability to MCI to
P16,126,922.91. If the Court of Appeals is correct, MCI would be
held liable for a much higher P24,125,000 liquidated damages.
The right to appeal from judgments, awards, or final orders of
Setting this off against CHATHAM's monetary responsibilities,
the CIAC is granted in E.O. No. 1008. The procedure for the
MCI would still have to pay CHATHAM P4,935,578.31.
exercise or application of this right was initially outlined in E.O.
No. 1008. While R. A. No. 7902 and circulars subsequently
issued by the Supreme Court and its amendments to the 1997 After painstakingly combing through the voluminous records, we
Rules on Procedure effectively modified the manner by which affirm the findings of the CIAC. The evidence taken as a whole or
the right to appeal ought to be exercised, nothing in these in their totality reveals that there was an implied takeover by
changes impaired vested rights. The new rules do not take away CHATHAM on the completion of the project. The evidence that
the right to appeal allowed in E.O. No. 1008. They only prescribe appears to accentuate the Court of Appeals' decision ironically
a new procedure to enforce the right. 27 No litigant has a vested bolstered the CIAC's conclusion. The testimonies of Engr.
right in a particular remedy, which may be changed by Kapunan, Engr. Bautista, Dr. Lai, and the letter of Engr.
substitution without impairing vested rights; hence, he can have Ruiz,31acknowledging the "temporary takeover" by CHATHAM of
none in rules of procedure which relate to remedy."28 the project, underscore the palpable fact that there was indeed
a takeover. We confer particular credit to Dr. Lai's testimony that
as of 15 February 1995, MCI was relieved of full control of the
The foregoing discussion renders academic MCI's assertion on
construction operations, that it was relegated to a mere supplier
the binding effect of its stipulation with CHATHAM in the TOR
of labor, materials and equipment, and that the alleged interim
that the decision of the CIAC shall be final and non-appealable
takeover actually extended through the completion of the
except on questions of law. The agreement merely adopted
project. Even CHATHAM admits the takeover but sugarcoated
Section 19 of E.O. No. 1008, which, as shown above, had been
the same with words like "interim" did "charging the costs to
modified.
MCI." With these glaring admissions, we can even consider that
the takeover was not implied but blatant.
The TOR, any contract or agreement of the parties cannot
amend, modify, limit, restrict or circumscribe legal remedies or
Exhibits "4," "4-A," "4-C," "8A," "8," "4-D," '43," "3-I," "3-M," "3-
the jurisdiction of courts. Rules of procedure are matters of
N," "3-W-1," "3-X," "3-Y," "3-Z," "5,""5-A," "5-B," "5-C," "5-D," "5-
public order and interest and unless the rules themselves so
E," "5-F," "5-O," "C-7," "E-9," etc., 32 relied upon by the Court of
allow, they cannot be altered, changed or regulated by
Appeals when considered by themselves and singly, seemingly
agreements between or stipulations of the parties for their
and initially evince MCI's control over the project. However, they
singular convenience.29
eventually lose evidentiary puissance to support the Court of
Appeals' conclusion when reckoned against the totality of the
Having resolved the existence of the authority of the Court of evidence that CHATHAM took charge of the completion of the
Appeals to review the decisions, awards, or final orders of the project, particularly, the fact that CHATHAM suspended all
CIAC, the Court shall now determine whether the Court of progress billing payments to MCI. The continued presence and
Appeals erred in rendering the questioned decision participation of MCI in the project was, as found by the CIAC, a
of30 September 1999. matter of mutual benefit to and convenience of the parties.

Settled is the general rule that the findings of facts of the Court WHEREFORE, IN VIEW OF ALL THE FOREGOING, the assailed 30
of Appeals are binding on us. There are recognized exceptions to September 1999 decision of the Court of Appeals in CA-G.R SP
the rule, such as when the findings are contrary to those of the No. 49429 is hereby PARTIALLY MODIFIED by setting aside the
trial court 30 as in this case. Hence, we have to take a closer order directing Metro Construction, Inc. to pay Chatham
reexamination of this case. Properties, Inc. the amount of P4,935,578.31. The arbitral award
of the Construction Industry Arbitration Commission in CIAC
57
Case 10-98, promulgated on 19 October 1998, directing was appointed by the CIAC as a common nominee of the two (2)
Chatham Properties, Inc. to pay Metro Construction, Inc. the sum parties. On the Chairman was a lawyer. After the arbitration
of SIXTEEN MILLION ONE HUNDRED TWENTY-SIX THOUSAND proceeding, the Arbitral Tribunal rendered a unanimous Award
NINE HUNDRED TWENTY-TWO & 91/100 (P16,126,922.91) dated 13 November 1992, the dispositive portion of which reads
PESOS, is accordingly REINSTATED. as follows:

No pronouncement as to costs.SO ORDERED. WHEREFORE, premises considered, the Owner


[petitioner Hi-Precision] is ordered to pay the
THIRD DIVISION.R. No. 110434 December 13, 1993 Contractor [private respondent Steel Builders]
the amount of P6,400,717.83 and all other
claims of the parties against each other are
HI-PRECISION STEEL CENTER, INC., petitioner,
deemed compensated and offset. No
vs.
pronouncement as to costs.
LIM KIM STEEL BUILDERS, INC., and CONSTRUCTION
INDUSTRY ARBITRATION COMMISSION, respondents.
The Parties are enjoined to abide by the
award. 11
FELICIANO, J.:

Upon motions for reconsideration filed, respectively, by


On 18 June 1993, a "Petition for Extension to File Petition for
Hi-Precision and Steel Builders, the Arbitral Tribunal
Review" 1 was filed before the Court, petitioner Hi-Precision Steel
issued an Order dated 13 May 1993 which reduced the
Center, Inc. ("Hi-Precision") stating that it intended to file a
net amount due to contractor Steel Builders to
Petition for Review on Certiorari in respect of the 13 November
P6,115,285.83. 12
1992 Award 2 and 13 May 1993 Order 3 of public respondent
Construction Industry Arbitration Commission ("CIAC") in
Arbitration Case No. 13-90. The Petition (really a Motion) prayed In its Award, the Arbitral Tribunal stated that it was guided by
for an extension of thirty (30) days or until 21 July 1993 within Articles 1169, 1192 and 2215 of the Civil Code. With such
which to file a Petition for Review. guidance, the arbitrators concluded that (a) both parties were at
fault, though the Tribunal could not point out which of the
parties was the first infractor; and (b) the breaches by one party
An opposition 4 to the Motion was filed by private respondent
affected the discharge of the reciprocal obligations of the other
Lim Kim Steel Builders, Inc. ("Steel Builders") on 5 July 1993. On
party. With mutual fault as a principal premise, the Arbitral
the same day, however, the Court issued a Resolution 5 granting
Tribunal denied (a) petitioner's claims for the additional costs
the Motion with a warning that no further extension would be
allegedly incurred to complete the project; and (b) private
given.
respondent's claim for profit it had failed to earn because of
petitioner's take over of the project.
The Opposition, the subsequent Reply 6 of petitioner filed on 20
July 1993 and the Petition for Review 7 dated 21 July 1993, were
The Tribunal then proceeded to resolve the remaining specific
noted by the Court in its Resolution 8 of 28 July 1993. The Court
claims of the parties. In disposing of these multiple, detailed
also required private respondent Steel Builders to file a
claims the Arbitral Tribunal, in respect of one or more of the
Comment on the Petition for Review and Steel Builders
respective claims of the parties: (a) averaged out the conflicting
complied.
amounts and percentages claimed by the parties; 13 (b) found
neither basis nor justification for a particular claim; 14 (c) found
The Petition prays for issuance of a temporary restraining the evidence submitted in support of particular claims either
order 9 to stay the execution of the assailed Order and Award in weak or non-existent; 15 (d) took account of the admissions of
favor of Steel Builders, which application the Court merely liability in respect of particular claims; 16 (e) relied on its own
noted, as it did subsequent Urgent Motions for a temporary expertise in resolving particular claims; 17 and (f) applied a
restraining order. 10 "principle of equity" in requiring each party to bear its own loss
resulting or arising from mutual fault or delay (compensation
Petitioner Hi-Precision entered into a contract with private morae). 18
respondent Steel Builders under which the latter as Contractor
was to complete a P21 Million construction project owned by the Petitioner Hi-Precision now asks this Court to set aside the
former within a period of 153 days, i.e. from 8 May 1990 to 8 Award, contending basically that it was the contractor Steel
October 1990. The project completion date was first moved to 4 Builders who had defaulted on its contractual undertakings and
November 1990. On that date, however, only 75.8674% of the so could not be the injured party and should not be allowed to
project was actually completed. Petitioner attributed this non- recover any losses it may have incurred in the project. Petitioner
completion to Steel Builders which allegedly had frequently Hi-Precision insists it is still entitled to damages, and claims that
incurred delays during the the Arbitral Tribunal committed grave abuse of discretion when
original contract period and the extension period. Upon the it allowed certain claims by Steel Builders and offset them
other hand, Steel Builders insisted that the delays in the project against claims of Hi-Precision.
were either excusable or due to Hi-Precision's own fault and
issuance of change orders. The project was taken over on 7
A preliminary point needs to be made. We note that the Arbitral
November 1990, and eventually completed on February 1991,
Tribunal has not been impleaded as a respondent in the Petition
by Hi-Precision.
at bar. The CIAC has indeed been impleaded; however, the
Arbitral Award was not rendered by the CIAC, but rather by the
Steel Builders filed a "Request for Adjudication" with public Arbitral Tribunal. Moreover, under Section 20 of Executive Order
respondent CIAC. In its Complaint filed with the CIAC, Steel No. 1008, dated 4 February 1985, as amended, it is the Arbitral
Builders sought payment of its unpaid progress buildings, Tribunal, or the single Arbitrator, with the concurrence of the
alleged unearned profits and other receivables. Hi-Precision, CIAC, which issues the writ of execution requiring any sheriff or
upon the other hand, in its Answer and Amended Answer, other proper officer to execute the award. We consider that the
claimed actual and liquidated damages, reimbursement of Arbitral Tribunal which rendered the Award sought to be
alleged additional costs it had incurred in order to complete the reviewed and set aside, should be impleaded even though the
project and attorney's fees. defense of its Award would presumably have to be carried by
the prevailing party.
The CIAC formed an Arbitral Tribunal with three (3) members,
two (2) being appointed upon nomination of Hi-Precision and Petitioner Hi-Precision apparently seeks review of both under
Steel Builders, respectively; the third member (the Chairman) Rule 45 and Rule 65 of the Rules of Court. 19 We do not find it
58
necessary to rule which of the two: a petition for review under From the foregoing, petitioner Hi-Precision may be seen to be
Rule 45 or a petition for certiorari under Rule 65 is necessary making two (2) basic arguments:
under Executive Order No. 1008, as amended; this issue was, in
any case, not squarely raised by either party and has not been (a) Petitioner asks this Court to correct legal errors committed
properly and adequately litigated. by the Arbitral Tribunal, which at the same time constitute
grave abuse of discretion amounting to lack of jurisdiction on
In its Petition, Hi-Precision purports to raise "legal issues," and in the part of the Arbitral Tribunal; and
presenting these issues, prefaced each with a creative formula:
(b) Should the supposed errors petitioner asks us to correct be
(1) characterized as errors of fact, such factual errors should
nonetheless be reviewed because there was "grave abuse of
discretion" in the misapprehension of facts on the part of the
The public respondent [should be the "Arbitral
Arbitral Tribunal.
Tribunal'] committed serious error in law, if not grave abuse of
discretion, when it failed to strictly apply Article 1191, New
Civil Code, against the Executive Order No. 1008, as amended, provides, in its
contractor . . .; Section 19, as follows:

(2) Sec. 19. Finality of Awards. The arbitral award shall be


binding upon the parties. It shall be final and inappealable
except on questions of law which shall be appealable to the
The public respondent committee serious error in law, if not
Supreme Court.
grave abuse of discretion, when it failed to rule in favor of the
owner, now petitioner herein, all the awards it claimed on
arbitration, and when it nonetheless persisted in its awards of Section 19 makes it crystal clear that questions of fact cannot
damages in favor of the be raised in proceedings before the Supreme Court which is
respondent. . . .; not a trier of facts in respect of an arbitral award rendered
under the aegis of the CIAC. Consideration of the animating
purpose of voluntary arbitration in general, and arbitration
(3)
under the aegis of the CIAC in particular, requires us to apply
rigorously the above principle embodied in Section 19 that the
The public respondent committed serious error in law, if not Arbitral Tribunal's findings of fact shall be final and
grave abuse of discretion, for its abject failure to apply the inappealable.
doctrine of waiver, estoppel against the contractor, the
private respondent herein, when it agreed on November 16,
Voluntary arbitration involves the reference of a dispute to an
1990 to award termination of the contract and the owner's
impartial body, the members of which are chosen by the parties
takeover of the project . . .;
themselves, which parties freely consent in advance to abide by
the arbitral award issued after proceedings where both parties
(4) had the opportunity to be heard. The basic objective is to
provide a speedy and inexpensive method of settling disputes
The public respondent committed serious error in law, if not by allowing the parties to avoid the formalities, delay, expense
grave abuse of discretion, when it did not enforce the law and aggravation which commonly accompany ordinary litigation,
between the parties, the "technical specification[s]" which is especially litigation which goes through the entire hierarchy of
one of the contract documents, particularly to par. (a), sub- courts. Executive Order No. 1008 created an arbitration facility
part 3.01, part 3, Sec. 2b, which expressly requires that major to which the construction industry in the Philippines can have
site work activities like stripping, removal and stockpiling of recourse. The Executive Order was enacted to encourage the
top soil shall be done "prior to the start of regular excavation early and expeditious settlement of disputes in the construction
or backfiling work", the principal issue in arbitration being industry, a public policy the implementation of which is
non-compliance with the contract documents; necessary and important for the realization of national
development goals. 21

(5)
Aware of the objective of voluntary arbitration in the labor field,
in the construction industry, and in any other area for that
The public respondent committed serious error in law, if not matter, the Court will not assist one or the other or even both
grave abuse of discretion, when it found, in the May 13, 1993 parties in any effort to subvert or defeat that objective for their
Order, the petitioner "guilty of estoppel" although it is claimed private purposes. The Court will not review the factual findings
that the legal doctrine of estoppel does not apply with respect of an arbitral tribunal upon the artful allegation that such body
to the required written formalities in the issuance of change had "misapprehended the facts" and will not pass upon issues
order . . .; which are, at bottom, issues of fact, no matter how cleverly
disguised they might be as "legal questions." The parties here
(6) had recourse to arbitration and chose the arbitrators
themselves; they must have had confidence in such arbitrators.
The Court will not, therefore, permit the parties to relitigate
The exceptional circumstances in Remalante vs. Tibe, 158
before it the issues of facts previously presented and argued
SCRA 138, where the Honorable Supreme Court may review
before the Arbitral Tribunal, save only where a very clear
findings of facts, are present in the instant case, namely; (a)
showing is made that, in reaching its factual conclusions, the
when the inference made is manifestly absurd, mistaken or
Arbitral Tribunal committed an error so egregious and hurtful to
impossible (Luna vs. Linatoc, 74 Phil. 15); (2) when there is
one party as to constitute a grave abuse of discretion resulting
grave abuse of discretion in the appreciation of facts (Buyco
in lack or loss of jurisdiction. 22 Prototypical examples would be
vs. People, 95 Phil. 253); (3) when the judgment is premised
factual conclusions of the Tribunal which resulted in deprivation
on a misapprehension of facts (De la Cruz v. Sosing, 94 Phil.
of one or the other party of a fair opportunity to present its
26 and Castillo vs. CA, 124 SCRA 808); (4) when the findings
position before the Arbitral Tribunal, and an award obtained
of fact are conflicting (Casica v. Villaseca, 101 Phil. 1205); (5)
through fraud or the corruption of arbitrators. 23 Any other, more
when the findings are contrary to the admissions of the
relaxed, rule would result in setting at naught the basic
parties (Evangelista v. Alto Surety, 103 Phil. 401), and
objective of a voluntary arbitration and would reduce arbitration
therefore, the findings of facts of the public respondent in the
to a largely inutile institution.
instant case may be reviewed by the Honorable Supreme
Court. 20 (Emphasis partly applied and partly in the original)
59
Examination of the Petition at bar reveals that it is essentially an Conditions of Contract forming part of the Contract Documents.
attempt to re-assert and re-litigate before this Court the detailed Petitioner Hi-Precision's argument is that a written Agreement
or itemized factual claims made before the Arbitral Tribunal dated 16 November 1990 with Steel Builders concerning the
under a general averment that the Arbitral Tribunal had take over of the project by Hi-Precision, constituted waiver on
"misapprehended the facts" submitted to it. In the present the part of the latter of its right to a 15-day notice of contract
Petition, too, Hi-Precision claims that the Arbitral Tribunal had termination. Whether or not that Agreement dated 16 November
committed grave abuse of discretion amounting to lack of 1990 (a document not submitted to this Court) is properly
jurisdiction in reaching its factual and legal conclusions. characterized as constituting waiver on the part of Steel
Builders, may be conceded to be prima facie a question of law;
but, if it is, and assuming arguendo that the Arbitral Tribunal had
The first "legal issue" submitted by the Petition is the claimed
erred in resolving it, that error clearly did not constitute a grave
misapplication by the Arbitral Tribunal of the first and second
abuse of discretion resulting in lack or loss of jurisdiction on the
paragraphs of Article 1911 of the Civil Code. 24 Article 1191
part of the Tribunal.
reads:

A third "legal issue" posed by Hi-Precision relates to the


Art. 1191. The power to rescind obligations is implied in
supposed failure on the part of the Arbitral Tribunal "to uphold
reciprocal ones, in case one of the obligors should not comply
the supremacy of 'the
with what is incumbent upon him.
law between the parties' and enforce it against private
respondent [Steel Builders]." 27 The "law between that parties"
The injured party may choose between the fulfillment and the here involved is the "Technical Specifications" forming part of
rescission of the obligation, with the payment of damages in the Contract Documents. Hi-Precision asserts that the Arbitral
either case. He may also seek rescission, even after he has Tribunal did not uphold the "law between the parties," but
chosen fulfillment, if the latter should become impossible. instead substituted the same with "its [own] absurd inference
and 'opinion' on mud." Here again, petitioner is merely
The court shall decree the rescission claimed, unless there be disguising a factual question as a "legal issue," since petitioner
just cause authorizing the fixing of a period. is in reality asking this Court to review the physical operations
relating, e.g., to site preparation carried out by the contractor
Steel Builders and to determine whether such operations were in
This is understood to be without prejudice to the rights of third accordance with the Technical Specifications of the project. The
persons who have acquired the thing, in accordance with Arbitral Tribunal resolved Hi-Precision's claim by finding that
articles 1385 and 1388 and the Mortgage Law. Steel Builders had complied substantially with the Technical
Specifications. This Court will not pretend that it has the
Hi-Precision contends energetically that it is the injured party technical and engineering capability to review the resolution of
and that Steel Builders was the obligor who did not comply with that factual issue by the Arbitral Tribunal.
what was incumbent upon it, such that Steel Builders was the
party in default and the entity guilty of negligence and delay. As Finally, the Petition asks this Court to "review serious errors in
the injured party, Hi-Precision maintains that it may choose the findings of fact of the [Arbitral Tribunal]." 28 In this section of
between the fulfillment or rescission of the obligation in its Petition,
accordance with Article 1191, and is entitled to damages in Hi-Precision asks us to examine each item of its own claims
either case. Thus, Hi-Precision continues, when the contractor which the Arbitral Tribunal had rejected in its Award, and each
Steel Builders defaulted on the 153rd day of the original claim of the contractor Steel Builders which the Tribunal had
contract period, Hi-Precision opted for specific performance and granted. In respect of each item of the owner's claims and each
gave Steel Builders a 30-day extension period with which to item of the contractor's claims, Hi-Precision sets out its
complete the project. arguments, to all appearances the same arguments it had raised
before the Tribunal. As summarized in the Arbitral Award,
What petitioner Hi-Precision, in its above argument, disregards is Contractor's Claims were as follows:
that the determination of whether Hi-Precision or Steel Builders
was the "injured party" is not to be resolved by an application of 12.1. Unpaid Progress Billing 1,812,706.95
Article 1191. That determination is eminently a question of fact,
for it requires ascertainment and identification of which the two
(2) contending parties had first failed to comply with what is 12.2. Change Order 1 0.00
incumbent upon it. In other words, the supposed misapplication 12.3. -do- 2 10,014.00
of Article 1191, while ostensibly a "legal issue," is ultimately a 12.4. -do- 3 320,000.00
question of fact, i.e., the determination of the existence or non- 12.5. -do- 4 112,300.70
existence of a fact or set of facts in respect of which Article 1191 12.6. -do- 5 398,398.00
may be properly applied. Thus, to ask this Court to correct a 12.7. -do- 6 353,050.38
claimed misapplication or non-application of Article 1191 is to 12.8. -do- 7 503,836.53
compel this Court to determine which of the two (2) contending 12.9. -do- 8 216,138.75
parties was the "injured party" or the "first infractor." As noted 12.10. -do- 9 101,621.40
earlier, the Arbitral Tribunal after the prolonged arbitration 12.11. -do- 10 7,200.00
proceeding, was unable to make that factual determination and 12.12. -do- 11 0.00
instead concluded that both parties had committed breaches of 12.13. -do- 12 7,800.00
their respective obligations. We will not review, and much less 12.14. -do- 13 49,250.00
reverse, that basic factual finding of the Arbitral Tribunal. 12.15. -do- 14 167,952.00
12.16. -do- 15 445,600.00
12.17. -do- 16 92,457.30
A second "legal issue" sought to be raised by petitioner Hi- 12.18. -do- 17 1,500.00
Precision relates to the supposed failure of the Arbitral Tribunal 12.19. 20,240.00
to apply the doctrines of estoppel and waiver as against Steel 12.20. 63,518.00
Builders. 25 The Arbitral Tribunal, after declaring that the parties 12.21. 0.00
were mutually at fault, proceeded to enumerate the faults of 12.22. 0.00
each of the parties. One of the faults attributed to petitioner Hi- 12.23. 0.00
Precision is that it had failed to give the contractor Steel 12.24. 0.00
Builders the required 15-day notice for termination of the 12.25. 0.00
contract. 26 This was clearly a finding of fact on the part of the 12.26. 730,201.57
Tribunal, supported by the circumstance that per the record, 12.27. 1,130,722.70
petitioner had offered no proof that it had complied with such 12.28. 0.00
15-day notice required under Article 28.01 of the General
60
12.29. 273,991.00 a. Foreign exchange loss 4,155,982.18
12.30. 0.00 b. Cost of money (a) 821,242.72
c. Additional import levy of 5% 886,513.33
d. Cost of money (c) 170,284.44

e. Cost of money on marginal


deposit on Letter of Credit 561,195.25
29
12.31. 7,318,499.28

IF Cost of money on holding to CRC INTY 3,319,609.63


=============

Total Actual Damages 35,295,927.32


Upon the other hand, the petitioner's claims we are asked to
review and grant are summarized as follows:
2. Liquidated Damages 2,436,000.00

1. Actual Damages
3. Attorney's Fees 500,000.00

Advance Downpayment

[at] signing of Contract
which is subject to 40%
deduction every progress P38,231,927.32 30
billing (40% of Contract Price) P8,406,000.00
=============
Progress Billings 5,582,585.55
We consider that in asking this Court to go over each individual
Advances made to Lim Kim claim submitted by it and each individual countering claim
submitted by Steel Builders to the Arbitral Tribunal, petitioner Hi-
Precision is asking this Court to pass upon claims which are
a) prior to take-over 392,781.45
either clearly and directly factual in nature or require previous
b) after the take-over
determination of factual issues. This upon the one hand. Upon
the other hand, the Court considers that petitioner Hi-Precision
Civil Works 1,158,513.88 has failed to show any serious errors of law amounting to grave
Materials 4,213,318.72 abuse of discretion resulting in lack of jurisdiction on the part of
Labor 2,155,774.79 the Arbitral Tribunal, in either the methods employed or the
Equipment Rental 1,448,208.90 results reached by the Arbitral Tribunal, in disposing of the
detailed claims of the respective parties.

WHEREFORE, for all the foregoing, the Petition is hereby


P8,974,816.45 DISMISSED for lack of merit. Costs against petitioner.SO
ORDERED.

Total Amount Paid for Construction 23,650,183.00


Less: Contract Price (21,000,000.00) SECOND DIVISION G.R. No. 175404 January 31, 2011
CARGILL PHILIPPINES, INC.,Petitioner, - versus - SAN
FERNANDO REGALA TRADING, INC., Respondent.
IA Excess of amount paid
over contract price 2,650,163.29 PERALTA, J.:

Before us is a petition for review on certiorari seeking to reverse


IB Other items due from Lim and set aside the Decision [1] dated July 31, 2006and the
Kim Steel Builders Resolution[2] dated November 13, 2006 of the Court of Appeals
(CA) in CA G.R. SP No. 50304.
a. Amount not yet deducted
The factual antecedents are as follows:
from Downpayment due
to non-completion of Project
(P24.1326%) 2,027,138.40

b. Due to Huey Commercial On June 18, 1998, respondent San Fernando Regala Trading, Inc.
used for HSCI Project 51,110.40 filed with the Regional Trial Court (RTC) of Makati City a
Complaint for Rescission of Contract with Damages [3] against
IC Additional construction expenses petitioner Cargill Philippines, Inc. In its Complaint, respondent
alleged that it was engaged in buying and selling of molasses
and petitioner was one of its various sources from whom it
a. Increases in prices since Oct. 5,272,096.81 purchased molasses. Respondent alleged that it entered into a
contract dated July 11, 1996 with petitioner, wherein it was
agreed upon that respondent would purchase from petitioner
b. Cost of money of (a) 873,535.49
12,000 metric tons of Thailand origin cane blackstrap molasses
at the price of US$192 per metric ton; that the delivery of the
ID Installation of machinery molasses was to be made in January/February 1997 and
payment was to be made by means of an Irrevocable Letter of
Credit payable at sight, to be opened by September 15, 1996;
a. Foreign exchange loss 11,565,048.37 that sometime prior to September 15, 1996, the parties agreed
that instead of January/February 1997, the delivery would be
b. Cost of money (a) 2,871,987.01 made in April/May 1997 and that payment would be by an
Irrevocable Letter of Credit payable at sight, to be opened upon
petitioner's advice. Petitioner, as seller, failed to comply with its
I[E] Raw Materials obligations under the contract, despite demands from
respondent, thus, the latter prayed for rescission of the contract
and payment of damages.
61
On July 24, 1998, petitioner filed a Motion to Dismiss/Suspend suspension of the proceedings warranted, since the Arbitration
Proceedings and To Refer Controversy to Voluntary Arbitration, Law contemplates an arbitration proceeding that must be
[4]
wherein it argued that the alleged contract between the conducted in the Philippines under the jurisdiction and control of
parties, dated July 11, 1996, was never consummated because the RTC; and before an arbitrator who resides in the country;
respondent never returned the proposed agreement bearing its and that the arbitral award is subject to court approval,
written acceptance or conformity nor did respondent open the disapproval and modification, and that there must be an appeal
Irrevocable Letter of Credit at sight. Petitioner contended that from the judgment of the RTC. The RTC found that the arbitration
the controversy between the parties was whether or not the clause in question contravened these procedures, i.e., the
alleged contract between the parties was legally in existence arbitration clause contemplated an arbitration proceeding
and the RTC was not the proper forum to ventilate such issue. It in New York before a non-resident arbitrator (American
claimed that the contract contained an arbitration clause, to wit: Arbitration Association); that the arbitral award shall be final and
binding on both parties. The RTC said that to apply Section 7 of
the Arbitration Law to such an agreement would result in
disregarding the other sections of the same law and rendered
them useless and mere surplusages.

Petitioner filed its Motion for Reconsideration, which the RTC


ARBITRATION denied in an Order[10] dated November 25, 1998.

Petitioner filed a petition for certiorari with the CA raising the


sole issue that the RTC acted in excess of jurisdiction or with
Any dispute which the Buyer and Seller may not be grave abuse of discretion in refusing to dismiss or at least
able to settle by mutual agreement shall be settled by suspend the proceedings a quo, despite the fact that the party's
arbitration in the City of New York before the American agreement to arbitrate had not been complied with.
Arbitration Association. The Arbitration Award shall be
final and binding on both parties.[5] Respondent filed its Comment and Reply. The parties were then
required to file their respective Memoranda.
that respondent must first comply with the arbitration clause
before resorting to court, thus, the RTC must either dismiss the On July 31, 2006, the CA rendered its assailed Decision denying
case or suspend the proceedings and direct the parties to the petition and affirming the RTC Orders.
proceed with arbitration, pursuant to Sections 6 [6] and
7[7] of Republic Act (R.A.) No. 876, or the Arbitration Law. In denying the petition, the CA found that stipulation providing
for arbitration in contractual obligation is both valid and
constitutional; that arbitration as an alternative mode of dispute
resolution has long been accepted in our jurisdiction and
Respondent filed an Opposition, wherein it argued that the RTC expressly provided for in the Civil Code; that R.A. No. 876 (the
has jurisdiction over the action for rescission of contract and Arbitration Law) also expressly authorized the arbitration of
could not be changed by the subject arbitration clause. It cited domestic disputes. The CA found error in the RTC's holding that
cases wherein arbitration clauses, such as the subject clause in Section 7 of R.A. No. 876 was inapplicable to arbitration clause
the contract, had been struck down as void for being contrary to simply because the clause failed to comply with the
public policy since it provided that the arbitration award shall be requirements prescribed by the law. The CA found that there
final and binding on both parties, thus, ousting the courts of was nothing in the Civil Code, or R.A. No. 876, that require that
jurisdiction. arbitration proceedings must be conducted only in
the Philippines and the arbitrators should be Philippine
In its Reply, petitioner maintained that the cited decisions were residents. It also found that the RTC ruling effectively invalidated
already inapplicable, having been rendered prior to the not only the disputed arbitration clause, but all other
effectivity of the New Civil Code in 1950 and the Arbitration Law agreements which provide for foreign arbitration. The CA did not
in 1953. find illegal or against public policy the arbitration clause so as to
render it null and void or ineffectual.
In its Rejoinder, respondent argued that the arbitration clause
relied upon by petitioner is invalid and unenforceable, Notwithstanding such findings, the CA still held that the case
considering that the requirements imposed by the provisions of cannot be brought under the Arbitration Law for the purpose of
the Arbitration Law had not been complied with. suspending the proceedings before the RTC, since in its Motion
to Dismiss/Suspend proceedings, petitioner alleged, as one of
the grounds thereof, that the subject contract between the
parties did not exist or it was invalid; that the said contract
By way of Sur-Rejoinder, petitioner contended that respondent
bearing the arbitration clause was never consummated by the
had even clarified that the issue boiled down to whether the
parties, thus, it was proper that such issue be first resolved by
arbitration clause contained in the contract subject of the
the court through an appropriate trial; that the issue involved a
complaint is valid and enforceable; that the arbitration clause
question of fact that the RTC should first resolve. Arbitration is
did not violate any of the cited provisions of the Arbitration Law.
not proper when one of the parties repudiated the existence or
On September 17, 1998, the RTC rendered an Order, [8] the validity of the contract.
dispositive portion of which reads:

Petitioner's motion for reconsideration was denied in a


Resolution dated November 13, 2006.

Premises considered, defendant's Motion To


Dismiss/Suspend Proceedings and To Refer Controversy
Hence, this petition.
To Voluntary Arbitration is hereby DENIED. Defendant is
directed to file its answer within ten (10) days from
receipt of a copy of this order.[9]
Petitioner alleges that the CA committed an error of law
in ruling that arbitration cannot proceed despite the fact that:
(a) it had ruled, in its assailed decision, that the arbitration
clause is valid, enforceable and binding on the parties; (b) the
In denying the motion, the RTC found that there was no clear case of Gonzales v. Climax Mining Ltd. [11] is inapplicable here; (c)
basis for petitioner's plea to dismiss the case, pursuant to parties are generally allowed, under the Rules of Court, to adopt
Section 7 of the Arbitration Law. The RTC said that the provision several defenses, alternatively or hypothetically, even if such
directed the court concerned only to stay the action or
proceeding brought upon an issue arising out of an agreement
providing for the arbitration thereof, but did not impose the
sanction of dismissal. However, the RTC did not find the
62
defenses are inconsistent with each other; and (d) the complaint In its Reply, petitioner insists that respondent filed an action for
filed by respondent with the trial court is premature. rescission and damages on the basis of the contract, thus,
respondent admitted the existence of all the provisions
contained thereunder, including the arbitration clause; that if
respondent relies on said contract for its cause of action against
Petitioner alleges that the CA adopted inconsistent positions petitioner, it must also consider itself bound by the rest of the
when it found the arbitration clause between the parties as valid terms and conditions contained thereunder notwithstanding that
and enforceable and yet in the same breath decreed that the respondent may find some provisions to be adverse to its
arbitration cannot proceed because petitioner assailed the position; that respondents citation of the Gonzales case, decided
existence of the entire agreement containing the arbitration in 2005, to show that the validity of the contract cannot be the
clause. Petitioner claims the inapplicability of the subject of the arbitration proceeding and that it is the RTC which
cited Gonzales case decided in 2005, because in the present has the jurisdiction to resolve the situation between the parties
case, it was respondent who had filed the complaint for herein, is not correct since in the resolution of the Gonzales'
rescission and damages with the RTC, which based its cause of motion for reconsideration in 2007, it had been ruled that an
action against petitioner on the alleged agreement dated July arbitration agreement is effective notwithstanding the fact that
11, 2006 between the parties; and that the same agreement one of the parties thereto repudiated the main contract which
contained the arbitration clause sought to be enforced by contained it.
petitioner in this case. Thus, whether petitioner assails the
genuineness and due execution of the agreement, the fact We first address the procedural issue raised by respondent that
remains that the agreement sued upon provides for an petitioners petition for certiorari under Rule 65 filed in the CA
arbitration clause; that respondent cannot use the provisions against an RTC Order denying a Motion to Dismiss/Suspend
favorable to him and completely disregard those that are Proceedings and to Refer Controversy to Voluntary Arbitration
unfavorable, such as the arbitration clause. was a wrong remedy invoking Section 29 of R.A. No. 876, which
provides:

Petitioner contends that as the defendant in the RTC, it


presented two alternative defenses, i.e., the parties had not
entered into any agreement upon which respondent as plaintiff Section 29.
can sue upon; and, assuming that such agreement existed,
there was an arbitration clause that should be enforced, thus,
the dispute must first be submitted to arbitration before an
action can be instituted in court. Petitioner argues that under
Section 1(j) of Rule 16 of the Rules of Court, included as a x x x An appeal may be taken from an order made in a
ground to dismiss a complaint is when a condition precedent for proceeding under this Act, or from a judgment entered
filing the complaint has not been complied with; and that upon an award through certiorari proceedings, but such
submission to arbitration when such has been agreed upon is appeals shall be limited to question of law. x x x.
one such condition precedent. Petitioner submits that the
proceedings in the RTC must be dismissed, or at least
suspended, and the parties be ordered to proceed with
arbitration.

On March 12, 2007, petitioner filed a Manifestation [12] saying


that the CA's rationale in declining to order arbitration based on
the 2005 Gonzales ruling had been modified upon a motion for
reconsideration decided in 2007; that the CA decision lost its
legal basis, because it had been ruled that the arbitration
agreement can be implemented notwithstanding that one of the
parties thereto repudiated the contract which contained such
agreement based on the doctrine of separability. To support its argument, respondent cites the case of Gonzales
v. Climax Mining Ltd.[13] (Gonzales case), wherein we ruled the
In its Comment, respondent argues that certiorari under
impropriety of a petition for certiorari under Rule 65 as a mode
Rule 65 is not the remedy against an order denying a Motion to
of appeal from an RTC Order directing the parties to arbitration.
Dismiss/Suspend Proceedings and To Refer Controversy to
Voluntary Arbitration. It claims that the Arbitration Law which We find the cited case not in point.
petitioner invoked as basis for its Motion prescribed, under its
Section 29, a remedy, i.e., appeal by a petition for review
on certiorari under Rule 45. Respondent contends that
the Gonzales case, which was decided in 2007, is inapplicable in In the Gonzales case, Climax-Arimco filed before the RTC of
this case, especially as to the doctrine of separability enunciated Makati a petition to compel arbitration under R.A. No. 876,
therein.Respondent argues that even if the existence of the pursuant to the arbitration clause found in the Addendum
contract and the arbitration clause is conceded, the decisions of Contract it entered with Gonzales. Judge Oscar Pimentel of the
the RTC and the CA declining referral of the dispute between the RTC of Makati then directed the parties to arbitration
parties to arbitration would still be correct. This is so because proceedings. Gonzales filed a petition for certiorari with
respondent's complaint filed in Civil Case No. 98-1376 presents Us contending that Judge Pimentel acted with grave abuse of
the principal issue of whether under the facts alleged in the discretion in immediately ordering the parties to proceed with
complaint, respondent is entitled to rescind its contract with arbitration despite the proper, valid and timely raised argument
petitioner and for the latter to pay damages; that such issue in his Answer with counterclaim that the Addendum Contract
constitutes a judicial question or one that requires the exercise containing the arbitration clause was null and void. Climax-
of judicial function and cannot be the subject of arbitration. Arimco assailed the mode of review availed of by Gonzales,
citing Section 29 of R.A. No. 876 contending that certiorariunder
Rule 65 can be availed of only if there was no appeal or any
adequate remedy in the ordinary course of law; that R.A. No.
Respondent contends that Section 8 of the Rules of Court, which 876 provides for an appeal from such order. We then ruled that
allowed a defendant to adopt in the same action several Gonzales' petition for certiorarishould be dismissed as it was
defenses, alternatively or hypothetically, even if such defenses filed in lieu of an appeal by certiorari which was the prescribed
are inconsistent with each other refers to allegations in the remedy under R.A. No. 876 and the petition was filed far beyond
pleadings, such as complaint, counterclaim, cross-claim, third- the reglementary period.
party complaint, answer, but not to a motion to dismiss. Finally,
respondent claims that petitioner's argument is premised on the We found that Gonzales petition for certiorari raises a question
existence of a contract with respondent containing a provision of law, but not a question of jurisdiction; that Judge Pimentel
for arbitration. However, its reliance on the contract, which it acted in accordance with the procedure prescribed in R.A. No.
repudiates, is inappropriate. 876 when he ordered Gonzales to proceed with arbitration and
appointed a sole arbitrator after making the determination that
there was indeed an arbitration agreement. It had been held
63
that as long as a court acts within its jurisdiction and does not The CA ruled that arbitration cannot be ordered in this case,
gravely abuse its discretion in the exercise thereof, any since petitioner alleged that the contract between the parties
supposed error committed by it will amount to nothing more did not exist or was invalid and arbitration is not proper when
than an error of judgment reviewable by a timely appeal and not one of the parties repudiates the existence or validity of the
assailable by a special civil action of certiorari.[14] contract. Thus, said the CA:

In this case, petitioner raises before the CA the issue that the Notwithstanding our ruling on the validity and
respondent Judge acted in excess of jurisdiction or with grave enforceability of the assailed arbitration clause
abuse of discretion in refusing to dismiss, or at least suspend, providing for foreign arbitration, it is our considered
the proceedings a quo, despite the fact that the partys opinion that the case at bench still cannot be brought
agreement to arbitrate had not been complied with. Notably, the under the Arbitration Law for the purpose of
RTC found the existence of the arbitration clause, since it said in suspending the proceedings before the trial court. We
its decision that hardly disputed is the fact that the arbitration note that in its Motion to Dismiss/Suspend Proceedings,
clause in question contravenes several provisions of the etc, petitioner Cargill alleged, as one of the grounds
Arbitration Law x x x and to apply Section 7 of the Arbitration thereof, that the alleged contract between the parties
Law to such an agreement would result in the disregard of the do not legally exist or is invalid. As posited by
afore-cited sections of the Arbitration Law and render them petitioner, it is their contention that the said contract,
useless and mere surplusages. However, notwithstanding the bearing the arbitration clause, was never consummated
finding that an arbitration agreement existed, the RTC denied by the parties. That being the case, it is but proper that
petitioner's motion and directed petitioner to file an answer. such issue be first resolved by the court through an
appropriate trial. The issue involves a question of fact
In La Naval Drug Corporation v. Court of Appeals,[15] it that the trial court should first resolve.
was held that R.A. No. 876 explicitly confines the courts
authority only to the determination of whether or not there is an
agreement in writing providing for arbitration. In the affirmative,
the statute ordains that the court shall issue an order summarily Arbitration is not proper when one of the parties
directing the parties to proceed with the arbitration in repudiates the existence or validity of the contract.
accordance with the terms thereof. If the court, upon the other Apropos is Gonzales v. Climax Mining Ltd., 452 SCRA
hand, finds that no such agreement exists, the proceedings shall 607, (G.R.No.161957), where the Supreme Court held
be dismissed. that:

In issuing the Order which denied petitioner's Motion to


Dismiss/Suspend Proceedings and to Refer Controversy to
Voluntary Arbitration, the RTC went beyond its authority of The question of validity of the
determining only the issue of whether or not there is an contract containing the agreement to
agreement in writing providing for arbitration by directing submit to arbitration will affect the
petitioner to file an answer, instead of ordering the parties to applicability of the arbitration clause
proceed to arbitration. In so doing, it acted in excess of its itself. A party cannot rely on the contract
jurisdiction and since there is no plain, speedy, and adequate and claim rights or obligations under it
remedy in the ordinary course of law, petitioners resort to a and at the same time impugn its
petition for certiorari is the proper remedy. existence or validity. Indeed, litigants are
enjoined from taking inconsistent
We now proceed to the substantive issue of whether positions....
the CA erred in finding that this case cannot be brought under
the arbitration law for the purpose of suspending the
proceedings in the RTC.
Consequently, the petitioner herein cannot claim that
We find merit in the petition. the contract was never consummated and, at the same
time, invokes the arbitration clause provided for under
Arbitration, as an alternative mode of settling disputes, the contract which it alleges to be non-existent or
has long been recognized and accepted in our jurisdiction. invalid. Petitioner claims that private respondent's
[16]
R.A. No. 876[17] authorizes arbitration of domestic complaint lacks a cause of action due to the absence of
disputes. Foreign arbitration, as a system of settling commercial any valid contract between the parties. Apparently, the
disputes of an international character, is likewise recognized. arbitration clause is being invoked merely as a fallback
[18]
The enactment of R.A. No. 9285 on April 2, 2004 further position. The petitioner must first adduce evidence in
institutionalized the use of alternative dispute resolution support of its claim that there is no valid contract
systems, including arbitration, in the settlement of disputes.[19] between them and should the court a quo find the
claim to be meritorious, the parties may then be spared
the rigors and expenses that arbitration in a foreign
land would surely entail.[24]
A contract is required for arbitration to take place and
to be binding.[20] Submission to arbitration is a contract [21] and a
clause in a contract providing that all matters in dispute
between the parties shall be referred to arbitration is a contract.
[22]
The provision to submit to arbitration any dispute arising
therefrom and the relationship of the parties is part of the However, the Gonzales case,[25] which the CA relied upon for not
contract and is itself a contract.[23] ordering arbitration, had been modified upon a motion for
reconsideration in this wise:
In this case, the contract sued upon by respondent
provides for an arbitration clause, to wit:
x x x The adjudication of the petition in G.R. No.
167994 effectively modifies part of the Decision
dated 28 February 2005 in G.R. No. 161957.
Hence, we now hold that the validity of the
ARBITRATION contract containing the agreement to submit to
arbitration does not affect the applicability of the
arbitration clause itself. A contrary ruling would
suggest that a party's mere repudiation of the
Any dispute which the Buyer and Seller may not be main contract is sufficient to avoid arbitration.
able to settle by mutual agreement shall be settled by That is exactly the situation that the separability
arbitration in the City of New York before the American doctrine, as well as jurisprudence applying it,
Arbitration Association, The Arbitration Award shall be seeks to avoid. We add that when it was declared in
final and binding on both parties. G.R. No. 161957 that the case should not be brought
for arbitration, it should be clarified that the case
64
referred to is the case actually filed by Gonzales before the contract with damages; and that issue constitutes a judicial
the DENR Panel of Arbitrators, which was for the question or one that requires the exercise of judicial function
nullification of the main contract on the ground of and cannot be the subject of an arbitration proceeding.
fraud, as it had already been determined that the case Respondent cites our ruling in Gonzales, wherein we held that a
should have been brought before the regular courts panel of arbitrator is bereft of jurisdiction over the complaint for
involving as it did judicial issues.[26] declaration of nullity/or termination of the subject contracts on
the grounds of fraud and oppression attendant to the execution
of the addendum contract and the other contracts emanating
from it, and that the complaint should have been filed with the
In so ruling that the validity of the contract containing the regular courts as it involved issues which are judicial in nature.
arbitration agreement does not affect the applicability of the
arbitration clause itself, we then applied the doctrine of Such argument is misplaced and respondent cannot rely on
separability, thus: the Gonzales case to support its argument.

In Gonzales, petitioner Gonzales filed a complaint before the


The doctrine of separability, or severability as
Panel of Arbitrators, Region II, Mines and Geosciences Bureau, of
other writers call it, enunciates that an arbitration
the Department of Environment and Natural Resources (DENR)
agreement is independent of the main contract. The against respondents Climax- Mining Ltd, Climax-Arimco and
arbitration agreement is to be treated as a separate Australasian Philippines Mining Inc, seeking the declaration of
agreement and the arbitration agreement does not nullity or termination of the addendum contract and the other
automatically terminate when the contract of which it is contracts emanating from it on the grounds of fraud and
a part comes to an end. oppression. The Panel dismissed the complaint for lack of
jurisdiction. However, the Panel, upon petitioner's motion for
The separability of the arbitration agreement is reconsideration, ruled that it had jurisdiction over the dispute
especially significant to the determination of whether maintaining that it was a mining dispute, since the subject
the invalidity of the main contract also nullifies the complaint arose from a contract between the parties which
arbitration clause. Indeed, the doctrine denotes that involved the exploration and exploitation of minerals over the
the invalidity of the main contract, also referred to as disputed area. Respondents assailed the order of the Panel of
the "container" contract, does not affect the validity of Arbitrators via a petition for certiorari before the CA. The CA
granted the petition and declared that the Panel of Arbitrators
the arbitration agreement. Irrespective of the fact that
did not have jurisdiction over the complaint, since its jurisdiction
the main contract is invalid, the arbitration
was limited to the resolution of mining disputes, such as those
clause/agreement still remains valid and enforceable. [27] which raised a question of fact or matter requiring the technical
knowledge and experience of mining authorities and not when
the complaint alleged fraud and oppression which called for the
interpretation and application of laws. The CA further ruled that
the petition should have been settled through arbitration under
Respondent argues that the separability doctrine is not R.A. No. 876 the Arbitration Law as provided under the
applicable in petitioner's case, since in the Gonzalescase, addendum contract.
Climax-Arimco sought to enforce the arbitration clause of its
contract with Gonzales and the former's move was premised on On a review on certiorari, we affirmed the CAs finding that the
the existence of a valid contract; while Gonzales, who resisted Panel of Arbitrators who, under R.A. No. 7942 of the Philippine
the move of Climax-Arimco for arbitration, did not deny the Mining Act of 1995, has exclusive and original jurisdiction to
existence of the contract but merely assailed the validity thereof hear and decide mining disputes, such as mining areas, mineral
on the ground of fraud and oppression. Respondent claims that agreements, FTAAs or permits and surface owners, occupants
in the case before Us, petitioner who is the party insistent on and claimholders/concessionaires, is bereft of jurisdiction over
arbitration also claimed in their Motion to Dismiss/Suspend the complaint for declaration of nullity of the addendum
Proceedings that the contract sought by respondent to be contract; thus, the Panels' jurisdiction is limited only to those
rescinded did not exist or was not consummated; thus, there is mining disputes which raised question of facts or matters
no room for the application of the separability doctrine, since requiring the technical knowledge and experience of mining
there is no container or main contract or an arbitration clause to authorities. We then said:
speak of.
In Pearson v. Intermediate Appellate Court, this
We are not persuaded. Court observed that the trend has been to make the
adjudication of mining cases a purely administrative
Applying the Gonzales ruling, an arbitration agreement matter. Decisions of the Supreme Court on mining
which forms part of the main contract shall not be regarded as disputes have recognized a distinction between (1) the
invalid or non-existent just because the main contract is invalid primary powers granted by pertinent provisions of law
or did not come into existence, since the arbitration agreement to the then Secretary of Agriculture and Natural
shall be treated as a separate agreement independent of the Resources (and the bureau directors) of an executive or
main contract. To reiterate. a contrary ruling would suggest that administrative nature, such as granting of license,
a party's mere repudiation of the main contract is sufficient to permits, lease and contracts, or approving, rejecting,
avoid arbitration and that is exactly the situation that the reinstating or canceling applications, or deciding
separability doctrine sought to avoid. Thus, we find that even conflicting applications, and (2) controversies or
the party who has repudiated the main contract is not prevented disagreements of civil or contractual nature between
from enforcing its arbitration clause. litigants which are questions of a judicial nature that
may be adjudicated only by the courts of justice. This
Moreover, it is worthy to note that respondent filed a distinction is carried on even in Rep. Act No. 7942. [28]
complaint for rescission of contract and damages with the RTC.
In so doing, respondent alleged that a contract exists between
respondent and petitioner. It is that contract which provides for
an arbitration clause which states that any dispute which the We found that since the complaint filed before the
Buyer and Seller may not be able to settle by mutual agreement DENR Panel of Arbitrators charged respondents with
shall be settled before the City of New York by the American disregarding and ignoring the addendum contract, and acting in
Arbitration Association. The arbitration agreement clearly a fraudulent and oppressive manner against petitioner, the
expressed the parties' intention that any dispute between them complaint filed before the Panel was not a dispute involving
as buyer and seller should be referred to arbitration. It is for the rights to mining areas, or was it a dispute involving claimholders
arbitrator and not the courts to decide whether a contract or concessionaires, but essentially judicial issues. We then said
between the parties exists or is valid. that the Panel of Arbitrators did not have jurisdiction over such
issue, since it does not involve the application of technical
Respondent contends that assuming that the existence of the knowledge and expertise relating to mining. It is in this context
contract and the arbitration clause is conceded, the CA's that we said that:
decision declining referral of the parties' dispute to arbitration is
still correct. It claims that its complaint in the RTC presents the
issue of whether under the facts alleged, it is entitled to rescind
65
Arbitration before the Panel of Arbitrators is proper only had fully mobilized its manpower and equipment, and had
when there is a disagreement between the parties as to ordered the delivery of steel bars. FSI also asked for the
some provisions of the contract between them, which payment of accomplished work amounting to P3,627,818.00.[7] A
needs the interpretation and the application of that series of correspondence between LICOMCEN and FSI then
particular knowledge and expertise possessed by followed.
members of that Panel. It is not proper when one of the
parties repudiates the existence or validity of such ESCA wrote FSI on January 6, 1998, stating that the revised
contract or agreement on the ground of fraud or design necessitated a change in the bored piles requirement
oppression as in this case. The validity of the contract and a substantial reduction in the number of piles. Thus, ESCA
cannot be subject of arbitration proceedings. proposed to FSI that only 50% of the steel bars be delivered to
Allegations of fraud and duress in the execution of a the jobsite and the rest be shipped back to Manila.
[8]
contract are matters within the jurisdiction of the Notwithstanding this instruction, all the ordered steel bars
ordinary courts of law. These questions are legal in arrived in Legaspi City on January 14, 1998.[9]
nature and require the application and interpretation of
laws and jurisprudence which is necessarily a judicial On January 15, 1998, LICOMCEN instructed FSI to hold all
function.[29] construction activities on the project, [10] in view of a pending
administrative case against the officials of the City Government
of Legaspi and LICOMCEN filed before the Ombudsman (OMB-
ADM-1-97-0622).[11] On January 19, 1998, ESCA formalized the
In fact, We even clarified in our resolution on Gonzales motion suspension of construction activities and ordered the
for reconsideration that when we declared that the case should constructions demobilization until the case was resolved. [12] In
not be brought for arbitration, it should be clarified that the case response, FSI sent ESCA a letter, dated February 3, 1998,
referred to is the case actually filed by Gonzales before the requesting payment of costs incurred on account of the
DENR Panel of Arbitrators, which was for the nullification of the suspension which totaled P22,667,026.97.[13] FSI repeated its
main contract on the ground of fraud, as it had already been demand for payment on March 3, 1998.[14]
determined that the case should have been brought before the
regular courts involving as it did judicial issues. We made such ESCA replied to FSIs demands for payment on March 24,
clarification in our resolution of the motion for reconsideration 1998, objecting to some of the claims. [15] It denied the claim
after ruling that the parties in that case can proceed to for the cost of the steel bars that were delivered, since the
arbitration under the Arbitration Law, as provided under the delivery was done in complete disregard of its instructions. It
Arbitration Clause in their Addendum Contract. further disclaimed liability for the other FSI claims based on the
suspension, as its cause was not due to LICOMCENs fault. FSI
rejected ESCAs evaluation of its claims in its April 15,
1998 letter.[16]
WHEREFORE, the petition is GRANTED. The Decision
dated July 31, 2006 and the Resolution dated November 13,
On March 14, 2001, FSI sent a final demand
2006 of the Court of Appeals in CA-G.R. SP No. 50304
are REVERSED and SET ASIDE. The parties are letter to LICOMCEN for payment of P29,232,672.83.
[17]
Since LICOMCEN took no positive action on FSIs demand for
hereby ORDERED to SUBMIT themselves to the arbitration of
their dispute, pursuant to their July 11, 1996 agreement. payment,[18] FSI filed a petition for arbitration with the
Construction Industry Arbitration Commission (CIAC) on October
SO ORDERED. a. Unpaid accomplished work billings. P 1,264,404.12
b. Material costs at site.. 15,143,638.51
THIRD DIVISION April c. Equipment and labor standby costs.. 3,058,984.34
4, 2011 G.R. d. Unrealized gross profit.. 9,023,575.29
No. 167022 e. Attorneys fees.. 300,000.00
f. Interest expenses ... equivalent to 15% of the total claim
LICOMCEN
INCORPORATED,Petitioner,- versus -FOUNDATION 2, 2002, docketed as CIAC Case No. 37-2002. [19] In the
SPECIALISTS, INC.,Respondent. arbitration petition, FSI demanded payment of the following
amounts:

THE FACTS LICOMCEN again denied liability for the amounts


claimed by FSI. It justified its decision to indefinitely suspend the
Citimall project due to the cases filed against it involving its
The petitioner, LICOMCEN Incorporated (LICOMCEN), is a Lease Contract with the City Government of Legaspi. LICOMCEN
domestic corporation engaged in the business of operating also assailed the CIACs jurisdiction, contending that FSIs claims
shopping malls in the country. were matters not subject to arbitration under GC-61 of the GCC,
but one that should have been filed before the regular courts
In March 1997, the City Government of Legaspi awarded to of Legaspi City pursuant to GC-05.[20]
LICOMCEN, after a public bidding, a lease contract over a lot
located in the central business district of the city. Under the During the preliminary conference of January 28, 2003,
contract, LICOMCEN was obliged to finance the construction of a LICOMCEN reiterated its objections to the CIACs jurisdiction,
commercial complex/mall to be known as the LCC Citimall which the arbitrators simply noted. Both FSI and LICOMCEN then
(Citimall). It was also granted the right to operate and manage proceeded to draft the Terms of Reference. [21]
Citimall for 50 years, and was, thereafter, required to turn over
the ownership and operation to the City Government.[1] On February 4, 2003, LICOMCEN, through a collaborating
counsel, filed its Ex Abundati Ad Cautela Omnibus Motion,
For the Citimall project, LICOMCEN hired E.S. de Castro and insisting that FSIs petition before the CIAC should be dismissed
Associates (ESCA) to act as its engineering consultant. Since the for lack of jurisdiction; thus, it prayed for the suspension of the
Citimall was envisioned to be a high-rise structure, LICOMCEN arbitration proceedings until the issue of jurisdiction was finally
contracted respondent Foundation Specialists, Inc. (FSI) to do settled. The CIAC denied LICOMCENs motion in its February 20,
initial construction works, specifically, the construction and 2003 order,[22] finding that the question of jurisdiction depends
installation of bored piles foundation. [2] LICOMCEN and FSI on certain factual conditions that have yet to be established by
signed the Construction Agreement,[3] and the accompanying ample evidence. As the CIACs February 20, 2003order stood
Bid Documents[4] and General Conditions of Contract [5] (GCC) uncontested, the arbitration proceedings continued, with both
on September 1, 1997. Immediately thereafter, FSI purchased parties actively participating.
the materials needed for the Citimall[6] project and began
working in order to meet the 90-day deadline set by LICOMCEN. The CIAC issued its decision on July 7, 2003,[23] ruling in favor of
FSI and awarding the following amounts:
On December 16, 1997, LICOMCEN sent word to FSI that it was
considering major design revisions and the suspension of work
on the Citimall project. FSI replied on December 18, 1997,
expressing concern over the revisions and the suspension, as it
66
a. Unpaid accomplished work billings. P 1,264,404.12 with the
b. Material costs at site 14,643,638.51 Contract, or
c. Equipment and labor standby costs 2,957,989.94 breach
d. Unrealized gross profit 5,120,000.00 thereof,
shall be litigated in the courts of Legaspi City except
LICOMCEN was also required to bear the costs of arbitration in where otherwise specifically stated or except when
the total amount of P474,407.95. such question is submitted for settlement thru
arbitration as provided herein.[28]
LICOMCEN appealed the CIACs decision before the
Court of Appeals (CA). On November 23, 2004, the CA upheld
the CIACs decision, modifying only the amounts awarded by (a) LICOMCEN also contends that FSI failed to comply with the
reducing LICOMCENs liability for material costs at site condition precedent for arbitration laid down in GC-61 of the
to P5,694,939.87, and (b) deleting its liability for equipment and GCC. An arbitrable dispute under GC-61 must first be referred to
labor standby costs and unrealized gross profit; all the other and settled by LICOMCEN, which has 30 days to resolve it. If
awards were affirmed.[24] Both parties moved for the within a period of 30 days from receipt of LICOMCENs decision
reconsideration of the CAs Decision; LICOMCENs motion was on the dispute, either party does not officially give notice to
denied in the CAs February 4, 2005 Resolution, while FSIs contest such decision through arbitration, the said decision shall
motion was denied in the CAs September 13, remain final and binding. However, should any party, within 30
2005 Resolution. Hence, the parties filed their own petition for days from receipt of LICOMCENs decision, contest said decision,
review on certiorari before the Court.[25] the dispute shall be submitted for arbitration under the
Construction Industry Arbitration Law.

LICOMCEN considers its March 24, 1998 letter as its final


LICOMCENs Arguments decision on FSIs claims, but declares that FSIs reply letter
of April 15, 1998 is not the notice to contest required by GC-61
LICOMCEM principally raises the question of the CIACs that authorizes resort to arbitration before the CIAC. It posits
jurisdiction, insisting that FSIs claims are non-arbitrable. In that nothing in FSIs April 15, 1998 letter states that FSI will avail
support of its position, LICOMCEN cites GC-61 of the GCC: of arbitration as a mode to settle its dispute with
LICOMCEN. While FSIs final demand letter of March 14,
GC-61. DISPUTES AND ARBITRATION 2001 mentioned its intention to refer the matter to arbitration,
LICOMCEN declares that the letter was made three years after
Should any dispute of any kind arise its March 24, 1998letter, hence, long after the 30-day period
between the LICOMCEN INCORPORATED and the provided in GC-61. Indeed, FSI filed the petition for arbitration
Contractor [referring to FSI] or the Engineer [referring with the CIAC only on October 2, 2002.[29] Considering FSIs
to ESCA] and the Contractor in connection with, or delays in asserting its claims, LICOMCEN also contends that FSIs
arising out of the execution of the Works, such action is barred by laches.
dispute shall first be referred to and settled by the
LICOMCEN, INCORPORATED who shall within a period of With respect to the monetary claims of FSI, LICOMCEM alleges
thirty (30) days after being formally requested by that the CA erred in upholding its liability for material costs at
either party to resolve the dispute, issue a written site for the reinforcing steel bars in the amount
decision to the Engineer and Contractor. of P5,694,939.87, computed as follows[30]:

Such decision shall be final and binding upon 2nd initial rebar requirements purchased from Pag-Asa Steel Wo
the parties and the Contractor shall proceed with the Inc..
execution of the Works with due diligence Reinforcing steel bars purchased from ARCA Industrial Sales (t
notwithstanding any Contractor's objection to the net weight of 744,197.66 kilograms) 50% of net amount due.
decision of the Engineer. If within a period of thirty (30)
days from receipt of the LICOMCEN, INCORPORATED's Subtotal.
decision on the dispute, either party does not officially Less
give notice to contest such decision through arbitration, Purchase cost of steel bars by Ramon Quinquileria..
the said decision shall remain final and binding.
However, should any party, within thirty (30) days from TOTAL LIABILITY OF LICOMCEN TO FSI FOR MATER
receipt of the LICOMCEN, INCORPORATED's decision, COSTS AT SITE...
contest said decision, the dispute shall be submitted for
arbitration under the Construction Industry Arbitration Citing GC-42(2) of the GCC, LICOMCEN says it shall be liable to
Law, Executive Order 1008. The arbitrators appointed pay FSI [t]he cost of materials or goods reasonably ordered
under said rules and regulations shall have full power for the Permanent or Temporary Works which have
to open up, revise and review any decision, opinion, been delivered to the Contractor but not yet used, and which
direction, certificate or valuation of the LICOMCEN, delivery has been certified by the Engineer.[31] None of these
INCORPORATED. Neither party shall be limited to the requisites were allegedly complied with. It contends that FSI
evidence or arguments put before the LICOMCEN, failed to establish that the steel bars delivered in Legaspi City,
INCORPORATED for the purpose of obtaining his said on January 14, 1998, were for the Citimall project. In fact, the
decision. No decision given by the LICOMCEN, steel bars were delivered not at the site of the Citimall project,
INCORPORATED shall disqualify him from being called but at FSIs batching plant called Tuanzon compound, a few
as a witness and giving evidence in the arbitration. It is hundred meters from the site. Even if delivery to Tuanzon was
understood that the obligations of the LICOMCEN, allowed, the delivery was done in violation of ESCAs instruction
INCORPORATED, the Engineer and the Contractor shall to ship only 50% of the materials. Advised as early as December
not be altered by reason of the arbitration being 1997 to suspend the works, FSI proceeded with the delivery of
conducted during the progress of the Works.[26] the steel bars in January 1998. LICOMCEN declared that it should
not be made to pay for costs that FSI willingly incurred for itself.
LICOMCEN posits that only disputes in connection with or arising [32]

out of the execution of the Works are subject to


arbitration. LICOMCEN construes the phrase execution of the Assuming that LICOMCEN is liable for the costs of the
Works as referring to the physical construction activities, since steel bars, it argues that its liability should be minimized by the
Works under the GCC specifically refer to the structures and fact that FSI incurred no actual damage from the purchase and
facilities required to be constructed and completed for the delivery of the steel bars. During the suspension of the works,
Citimall project.[27] It considers FSIs claims as mere contractual FSI sold 125,000 kg of steel bars for P500,000.00 to a third
monetary claims that should be litigated before the courts person (a certain Ramon Quinquileria). LICOMCEN alleges that
of Legaspi City, as provided in GC-05 of the GCC: FSI sold the steel bars for a ridiculously low price of P 4.00/kilo,
when the prevailing rate was P20.00/kilo. The sale could have
GC-05. JURISDICTION garnered a higher price that would offset LICOMCENs
liability. LICOMCEN also wants FSI to account for and deliver to it
Any question between the contracting the remaining 744 metric tons of steel bars not sold. Otherwise,
parties that may arise out of or in connection
67
FSI would be unjustly enriched at LICOMCENs expense, receiving The CIAC was created through Executive Order No.
payment for materials not delivered to LICOMCEN.[33] 1008 (E.O. 1008), in recognition of the need to establish an
arbitral machinery that would expeditiously settle construction
LICOMCEN also disagrees with the CA ruling that declared it industry disputes. The prompt resolution of problems arising
solely liable to pay the costs of arbitration. The ruling was from or connected with the construction industry was
apparently based on the finding that LICOMCENs failure or considered of necessary and vital for the fulfillment of national
refusal to meet its obligations, legal, financial, and moral, development goals, as the construction industry provides
caused FSI to bring the dispute to arbitration. [34] LICOMCEN employment to a large segment of the national labor force and
asserts that it was FSIs decision to proceed with the delivery of is a leading contributor to the gross national product. [43] Section
the steel bars that actually caused the dispute; it insists that it is 4 of E.O. 1008 states:
not the party at fault which should bear the arbitration costs. [35]
FSIs Arguments Sec. 4. Jurisdiction. The CIAC shall have
original and exclusive jurisdiction over disputes
FSI takes exception to the CA ruling that modified the arising from, or connected with, contracts
amount for material costs at site, and deleted the awards for entered into by parties involved in
equipment and labor standby costs and unrealized profits. construction in the Philippines, whether the
dispute arises before or after the completion of
Proof of damage to FSI is not required for LICOMCEN to the contract, or after the abandonment or breach
be liable for the material costs of the steel bars. Under GC-42, it thereof. These disputes may involve government or
is enough that the materials were delivered to the contractor, private contracts. For the Board to acquire jurisdiction,
although not used. FSI said that the 744 metric tons of steel the parties to a dispute must agree to submit the same
bars were ordered and paid for by it for the Citimall project as to voluntary arbitration.
early as November 1997. If LICOMCEN contends that these were
procured for other projects FSI also had in Legaspi City, it should The jurisdiction of the CIAC may include but is
have presented proof of this claim, but it failed to do so. [36] not limited to violation of specifications for materials
and workmanship; violation of the terms of agreement;
ESCAs January 6, 1998 letter simply suggested that interpretation and/or application of contractual time
only 50% of the steel bars be shipped to Legaspi City; it was not and delays; maintenance and defects; payment, default
a clear and specific directive. Even if it was, the steel bars were of employer or contractor and changes in contract cost.
ordered and paid for long before the notice to suspend was
given; by then, it was too late to stop the delivery. FSI also Excluded from the coverage of this law are
claims that since it believed in good faith that the Citimall disputes arising from employer-employee relationships
project was simply suspended, it expected work to resume soon which shall continue to be covered by the Labor Code
after and decided to proceed with the shipment.[37] of the Philippines.

Contrary to LICOMCENs arguments, GC-42 of the GCC The jurisdiction of courts and quasi-judicial bodies is determined
does not require delivery of the materials at the site of the by the Constitution and the law.[44] It cannot be fixed by the will
Citimall project; it only requires delivery to the contractor, which of the parties to a dispute;[45] the parties can neither expand nor
is FSI. Moreover, the Tuanzon compound, where the steel bars diminish a tribunals jurisdiction by stipulation or agreement. The
were actually delivered, is very close to the Citimall project text of Section 4 of E.O. 1008 is broad enough to cover any
site. FSI contends that it is a normal construction practice for dispute arising from, or connected with construction contracts,
contractors to set up a staging site, to prepare the materials and whether these involve mere contractual money claims or
equipment to be used, rather than stock them in the crowded execution of the works.[46] Considering the intent behind the law
job/project site. FSI also asserts that it was useless to have the and the broad language adopted, LICOMCEN erred in insisting on
delivery certified by ESCA because by then the Citimall project its restrictive interpretation of GC-61. The CIACs jurisdiction
had been suspended. It would be unfair to demand FSI to cannot be limited by the parties stipulation that only disputes in
perform an act that ESCA and LICOMCEN themselves had connection with or arising out of the physical construction
prevented from happening.[38] activities (execution of the works) are arbitrable before it.

The CA deleted the awards for equipment and labor In fact, all that is required for the CIAC to acquire
standby costs on the ground that FSIs documentary evidence jurisdiction is for the parties to a construction contract
was inadequate. FSI finds the ruling erroneous, since LICOMCEN to agree to submit their dispute to arbitration. Section 1,
never questioned the list of employees and equipments Article III of the 1988 CIAC Rules of Procedure (as amended by
employed and rented by FSI for the duration of the suspension. CIAC Resolution Nos. 2-91 and 3-93) states:
[39]

Section 1. Submission to CIAC Jurisdiction. An


FSI also alleges that LICOMCEN maliciously and arbitration clause in a construction contract or a
unlawfully suspended the Citimall project. While LICOMCEN cited submission to arbitration of a construction
several other cases in its petition for review on certiorari as dispute shall be deemed an agreement to submit
grounds for suspending the works, its letters/notices of an existing or future controversy to CIAC
suspension only referred to one case, OMB-ADM-1-97-0622, an jurisdiction, notwithstanding the reference to a
administrative case before the Ombudsman that was dismissed different arbitration institution or arbitral body
as early as October 12, 1998. LICOMCEN never notified FSI of in such contract or submission. When a contract
the dismissal of this case. More importantly, no restraining order contains a clause for the submission of a future
or injunction was issued in any of these cases to justify the controversy to arbitration, it is not necessary for the
suspension of the Citimall project.[40] FSI posits that LICOMCENs parties to enter into a submission agreement before
true intent was to terminate its contract with it, but, to avoid the claimant may invoke the jurisdiction of CIAC.
paying damages for breach of contract, simply declared it as
indefinitely suspended. That LICOMCEN conducted another An arbitration agreement or a submission to arbitration
public bidding for the new designs is a telling indication of shall be in writing, but it need not be signed by the
LICOMCENs intent to ease out FSI.[41] Thus, FSI states that parties, as long as the intent is clear that the parties
LICOMCENs bad faith in indefinitely suspending the Citimall agree to submit a present or future controversy arising
project entitles it to claim unrealized profit. The restriction under from a construction contract to arbitration.
GC-41 that [t]he contractor shall have no claim for anticipated
profits on the work thus terminated,[42] will not apply because
the stipulation refers to a contract lawfully and properly In HUTAMA-RSEA Joint Operations, Inc. v. Citra Metro Manila
terminated. FSI seeks to recover unrealized profits under Articles Tollways Corporation,[47] the Court declared that the bare fact
1170 and 2201 of the Civil Code. that the parties x x x incorporated an arbitration clause in [their
contract] is sufficient to vest the CIAC with jurisdiction over any
THE COURTS RULING construction controversy or claim between the parties. The
arbitration clause in the construction contract ipso
The jurisdiction of the CIAC facto vested the CIAC with jurisdiction.
68
Under GC-61 and GC-05 of the GCC, read singly and in relation
with one another, the Court sees no intent to limit resort to
arbitration only to disputes relating to the physical construction Before the Court rules on each of FSIs contractual
activities. monetary claims, we deem it important to discuss the validity of
LICOMCENs indefinite suspension of the works on the Citimall
First, consistent with the intent of the law, an project. We quote below two contractual stipulations relevant to
arbitration clause pursuant to E.O. 1008 should be interpreted at this issue:
its widest signification. Under GC-61, the voluntary arbitration
clause covers any dispute of any kind, not only arising of out the GC-38. SUSPENSION OF WORKS
execution of the works but also in connection therewith. The
payments, demand and disputed issues in this case namely, The Engineer [ESCA] through the
work billings, material costs, equipment and labor standby LICOMCEN, INCORPORATED shall have the
costs, unrealized profits all arose because of the construction authority to suspend the Works wholly or partly
activities and/or are connected or related to these activities. In by written order for such period as may be
other words, they are there because of the construction deemed necessary, due to unfavorable weather or
activities. Attorneys fees and interests payment, on the other other conditions considered unfavorable for the
hand, are costs directly incidental to the dispute. Hence, the prosecution of the Works, or for failure on the part of
scope of the arbitration clause, as worded, covers all the the Contractor to correct work conditions which are
disputed items. unsafe for workers or the general public, or failure or
refusal to carry out valid orders, or due to change of
Second and more importantly, in insisting that plans to suit field conditions as found necessary during
contractual money claims can be resolved only through court construction, or to other factors or causes which,
action, LICOMCEN deliberately ignores one of the exceptions to in the opinion of the Engineer, is necessary in the
the general rule stated in GC-05: interest of the Works and to the LICOMCEN,
INCORPORATED. The Contractor [FSI] shall
immediately comply with such order to suspend
GC-05. JURISDICTION the work wholly or partly directed.

Any question between the contracting parties In case of total suspension or suspension of
that may arise out of or in connection with the activities along the critical path of the approved
Contract, or breach thereof, shall be litigated in the PERT/CPM network and the cause of which is not due to
courts of Legaspi City except where otherwise any fault of the Contractor, the elapsed time
specifically stated or except when such question is between the effective order for suspending work
submitted for settlement thru arbitration as and the order to resume work shall be allowed
provided herein. the Contractor by adjusting the time allowed for
his execution of the Contract Works.
The second exception clause authorizes the submission to
arbitration of any dispute between LICOMCEM and FSI, even if The Engineer through LICOMCEN,
the dispute does not directly involve the execution of physical INCORPORATED shall issue the order lifting the
construction works. This was precisely the avenue taken by FSI suspension of work when conditions to resume work
when it filed its petition for arbitration with the CIAC. shall have become favorable or the reasons for the
suspension have been duly corrected.[50]
If the CIACs jurisdiction can neither be enlarged nor diminished
by the parties, it also cannot be subjected to a condition
precedent. GC-61 requires a party disagreeing with LICOMCENs GC-41 LICOMCEN, INCORPORATED's RIGHT TO
decision to officially give notice to contest such SUSPEND WORK OR TERMINATE THE CONTRACT
decision through arbitration within 30 days from receipt of
the decision. However, FSIs April 15, 1998 letter is not the notice xxxx
contemplated by GC-61; it never mentioned FSIs plan to submit
the dispute to arbitration and instead requested LICOMCEN to 2. For Convenience of LICOMCEN,
reevaluate its claims. Notwithstanding FSIs failure to make a INCORPORATED
proper and timely notice, LICOMCENs decision (embodied in
its March 24, 1998 letter) cannot become final and binding so as If any time before completion of work
to preclude resort to the CIAC arbitration. To reiterate, all that is under the Contract it shall be found by the
required for the CIAC to acquire jurisdiction is for the parties to LICOMCEN, INCORPORATED that reasons beyond
agree to submit their dispute to voluntary arbitration: the control of the parties render it impossible
or against the interest of the LICOMCEN,
[T]he mere existence of an arbitration clause in INCORPORATED to complete the work, the
the construction contract is considered by law as LICOMCEN, INCORPORATED at any time, by
an agreement by the parties to submit existing written notice to the Contractor, may discontinue
or future controversies between them to CIAC the work and terminate the Contract in whole or in
jurisdiction, without any qualification or part. Upon the issuance of such notice of termination,
condition precedent. To affirm a condition precedent the Contractor shall discontinue to work in such
in the construction contract, which would effectively manner, sequence and at such time as the LICOMCEN,
suspend the jurisdiction of the CIAC until compliance INCORPORATED/Engineer may direct, continuing and
therewith, would be in conflict with the recognized doing after said notice only such work and only until
intention of the law and rules to automatically vest such time or times as the LICOMCEN,
CIAC with jurisdiction over a dispute should the INCORPORATED/Engineer may direct.[51]
construction contract contain an arbitration clause.[48]

The CIAC is given the original and exclusive Under these stipulations, we consider LICOMCENs initial
jurisdiction over disputes arising from, or connected with, suspension of the works valid. GC-38 authorizes the
contracts entered into by parties involved in construction in suspension of the works for factors or causes which ESCA deems
the Philippines.[49] This jurisdiction cannot be altered by necessary in the interests of the works and LICOMCEN. The
stipulations restricting the nature of construction disputes, factors or causes of suspension may pertain to a change or
appointing another arbitral body, or making that bodys decision revision of works, as cited in the December 16, 1997 and
final and binding. January 6, 1998 letters of ESCA, or to the pendency of a case
before the Ombudsman (OMB-ADM-1-97-0622), as cited in
The jurisdiction of the CIAC to resolve the dispute LICOMCENs January 15, 1998 letter and ESCAs January 19, 1998
between LICOMCEN and FSI is, therefore, affirmed. and February 17, 1998 letters. It was not necessary for
ESCA/LICOMCEN to wait for a restraining or injunctive order to
The validity of the indefinite be issued in any of the cases filed against LICOMCEN before it
suspension of the works on the can suspend the works. The language of GC-38 gives
Citimall project ESCA/LICOMCEN sufficient discretion to determine whether the
69
existence of a particular situation or condition necessitates the shall deduct any outstanding balance due from the
suspension of the works and serves the interests of LICOMCEN. Contractor for advances in respect to mobilization and
materials, and any other sum the LICOMCEN,
Although we consider the initial suspension of the works INCORPORATED is entitled to be credited.[56]
as valid, we find that LICOMCEN wrongfully prolonged
the suspension of the works (or indefinite suspension as For LICOMCEN to be liable for the cost of materials or goods,
LICOMCEN calls it). GC-38 requires ESCA/LICOMCEN to issue an item two of GC-42 requires that
order lifting the suspension of work when conditions to resume
work shall have become favorable or the reasons for the a. the materials or goods were reasonably ordered for the
suspension have been duly corrected. The Ombudsman case Permanent or Temporary Works;
(OMB-ADM-1-97-0622), which ESCA and LICOMCEN cited in their b. the materials or goods were delivered to the
letters to FSI as a ground for the suspension, was dismissed as Contractor but not yet used; and
early as October 12, 1998, but neither ESCA nor LICOMCEN c. the delivery was certified by the Engineer.
informed FSI of this development.The pendency of the other
cases[52] may justify the continued suspension of the works, but Both the CIAC and the CA agreed that these requisites were met
LICOMCEN never bothered to inform FSI of the existence of by FSI to make LICOMCEN liable for the cost of the steel bars
these cases until the arbitration proceedings ordered for the Citimall project; the two tribunals differed only to
commenced. By May 28, 2002, the City Government of Legaspi the extent of LICOMCENs liability because the CA opined that it
sent LICOMCEN a notice instructing it to proceed with the should be limited only to 50% of the cost of the steel bars. A
Citimall project;[53] again, LICOMCEN failed to relay this review of the records compels us to uphold the CAs finding.
information to FSI. Instead, LICOMCEN conducted a rebidding of
the Citimall project based on the new design. [54] LICOMCENs Prior to the delivery of the steel bars, ESCA informed
claim that the rebidding was conducted merely to get cost FSI of the suspension of the works; ESCAs January 6, 1998 letter
estimates for the new design goes against the established reads:
practice in the construction industry. We find the CIACs
discussion on this matter relevant: As per our information to you on December 16,
1997, a major revision in the design of the Legaspi
But what is more appalling and disgusting is the Citimall necessitated a change in the bored piles
allegation x x x that the x x x invitation to bid was requirement of the project. The change involved a
issued x x x solely to gather cost estimates on the substantial reduction in the number and length
redesigned [Citimall project] x x x. This Arbitral Tribunal of piles.
finds said act of asking for bids, without any
intention of awarding the project to the lowest We expected that you would have suspended the
and qualified bidder, if true, to be extremely deliveries of the steel bars until the new design
irresponsible and highly unprofessional. It might has been approved.
even be branded as fraudulent x x x [since] the invited
bidders [were required] to pay P2,000.00 each for a set According to you[,] the steel bars had already
of the new plans, which amount was non- been paid and loaded and out of Manila on said
refundable. The presence of x x x deceit makes the date.
whole story repugnant and unacceptable.[55]
In order to avoid double handling, storage,
LICOMCENs omissions and the imprudent rebidding of security problems, we suggest that only 50% of
the Citimall project are telling indications of LICOMCENs the total requirement of steel bars be delivered
intent to ease out FSI and terminate their contract. As at jobsite. The balance should be returned
with GC-31, GC-42(2) grants LICOMCEN ample discretion to to Manila where storage and security is better.
determine what reasons render it against its interest to
complete the work in this case, the pendency of the other cases In order for us to consider additional cost due to the shi
and the revised designs for the Citimall project. Given this pping of the excess steel bars, we need to know the
authority, the Court fails to the see the logic why LICOMCEN had actual dates of purchase, payments and loading of the
to resort to an indefinite suspension of the works, instead of steel bars. Obviously, we cannot consider the additional
outrightly terminating the contract in exercise of its rights under cost if you have had the chance to delay the shipping
GC-42(2). of the steel bars.[57]

We now proceed to discuss the effects of these findings with From the above, it appears that FSI was informed of the
regard to FSIs monetary claims against LICOMCEN. necessity of suspending the works as early as December 16,
1997. Pursuant to GC-38 of the GCC, FSI was expected
The claim for material costs at site to immediately comply with the order to suspend the work.
[58]
Though ESCAs December 16, 1997 notice may not have been
GC-42 of the GCC states: categorical in ordering the suspension of the works, FSIs reply
GC-42 PAYMENT FOR TERMINATED CONTRACT letter of December 18, 1997 indicated that it actually complied
with the notice to suspend, as it said, We hope for the early
If the Contract is terminated as aforesaid, the resolution of the new foundation plan and the resumption of
Contractor will be paid for all items of work executed, work.[59] Despite the suspension, FSI claimed that it could not
satisfactorily completed and accepted by the stop the delivery of the steel bars (nor found the need to do so)
LICOMCEN, INCORPORATED up to the date of because (a) the steel bars were ordered as early as November
termination, at the rates and prices provided for in the 1997 and were already loaded in Manila and expected to arrive
Contract and in addition: in Legaspi City by December 23, 1997, and (b) it expected
immediate resumption of work to meet the 90-day deadline.[60]
1. The cost of partially accomplished items of
additional or extra work agreed upon by the Records, however, disclose that these claims are not
LICOMCEN, INCORPORATED and the entirely accurate. The memorandum of agreement and sale
Contractor. covering the steel bars specifically stated that these would be
withdrawn from the Cagayan de Oro depot, not Manila[61];
2. The cost of materials or goods indeed, the bill of lading stated that the steel bars were loaded
reasonably ordered for the Permanent or in Cagayan de Oro on January 11, 1998, and arrived
Temporary Works which have been in Legaspi City within three days, on January 14, 1998.[62] The
delivered to the Contractor but not yet loading and delivery of the steel bar thus happened after FSI
used and which delivery has been received ESCAs December 16, 1997 and January 6, 1998 letters
certified by the Engineer. days after the instruction to suspend the works. Also, the same
stipulation that authorizes LICOMCEN to suspend the works
3. The reasonable cost of demobilization allows the extension of the period to complete the works. The
relevant portion of
For any payment due the Contractor under the above GC-38 states:
conditions, the LICOMCEN, INCORPORATED, however,
70
In case of total suspension x x x and the cause nor differentiated the two terms. [A] contract must be
of which is not due to any fault of the Contractor interpreted from the language of the contract itself, according to
[FSI], the elapsed time between the effective its plain and ordinary meaning. [66] If the terms of a contract are
order for suspending work and the order to clear and leave no doubt upon the intention of the contracting
resume work shall be allowed the Contractor by parties, the literal meaning of the stipulations shall control. [67]
adjusting the time allowed for his execution of Nonetheless, on account of our earlier discussion of
the Contract Works.[63] LICOMCENs failure to observe the proper procedure in
terminating the contract by declaring that it was merely
The above stipulation, coupled indefinitely suspended, we deem that FSI is entitled to the
with the short period it took to ship the payment of nominal damages. Nominal damages may be
steel bars from Cagayan de Oro to Legaspi City, thus negates awarded to a plaintiff whose right has been violated or invaded
both FSIs by the defendant, for the purpose of vindicating or recognizing
argument and the CIACs ruling[64] that there was no necessity to that right, and not for indemnifying the plaintiff for any loss
stop the shipment so as to meet the 90-day deadline. These suffered by him.[68] Its award is, thus, not for the purpose of
circumstances prove that FSI acted imprudently in proceeding indemnification for a loss but for the recognition and vindication
with the delivery, contrary to LICOMCENs instructions. The CA of a right. A violation of the plaintiffs right, even if only
was correct in holding LICOMCEN liable for only 50% of the costs technical, is sufficient to support an award of nominal damages.
[69]
of the steel bars delivered. FSI is entitled to recover the amount of P100,000.00 as
nominal damages.
The claim for equipment and
labor standby costs The liability for costs of arbitration

The Court upholds the CAs ruling deleting the award for Under the parties Terms of Reference, executed before the CIAC,
equipment and labor standby costs. We quote in agreement the costs of arbitration shall be equally divided between them,
pertinent portions of the CA decision: subject to the CIACs determination of which of the parties shall
eventually shoulder the amount. [70] The CIAC eventually ruled
The CIAC relied solely on the list of 37 pieces that since LICOMCEN was the party at fault, it should bear the
of equipment respondent allegedly rented and costs. As the CA did, we agree with this finding. Ultimately, it
maintained at the construction site during the was LICOMCENs imprudent declaration of indefinitely
suspension of the project with the prorated rentals suspending the works that caused the dispute between it and
incurred x x x. To the mind of this Court, these lists FSI. LICOMCEN should bear the costs of arbitration.
are not sufficient to establish the fact that
indeed [FSI] incurred the said expenses. Reliance WHEREFORE, premises considered, the petition for review
on said lists is purely speculative x x x the list of on certiorari of LICOMCEN INCORPORATED, docketed as G.R. No.
equipments is a mere index or catalog of the 167022, and the petition for review on certiorari of FOUNDATION
equipments, which may be utilized at the SPECIALISTS, INC., docketed as G.R. No. 169678, are DENIED.
construction site. It is not the best evidence to The November 23, 2004 Decision of the Court of Appeals in CA-
prove that said equipment were in fact G.R. SP No. 78218 is MODIFIED to include the award of
rented and maintained at the construction site during nominal damages in favor of FOUNDATION SPECIALISTS, INC.
the suspension of the work. x x x [FSI] should have Thus, LICOMCEN INCORPORATED is ordered to pay FOUNDATION
presented the lease contracts or any similar SPECIALISTS, INC. the following amounts:
documents such as receipts of payments x x
x. Likewise, the list of employees does not in a. P1,264,404.12 for unpaid balance on FOUNDATION
anyway prove that those employees in the list SPECIALISTS, INC. billings;
were indeed at the construction site or were required to b. P5,694,939.87 for material costs at site; and
be on call should their services be needed and were c. P100,000.00 for nominal damages.
being paid their salaries during the suspension
of the project.Thus, in the absence of sufficient LICOMCEN INCORPORATED is also ordered to pay the costs of
evidence, We deny the claim for equipment and arbitration. No costs.SO ORDERED.
labor standby costs.[65] THIRD DIVISION July 4, 2012 G.R. No. 172438
METROPOLITAN CEBU WATER DISTRICT,Petitioner,- versus
-MACTAN ROCK INDUSTRIES, INC.,Respondent.
The claim for unrealized profit

FSI contends that it is not barred from recovering unrealized MENDOZA, J.:
profit under GC-41(2), which states:
GC-41. LICOMCEN, INCORPORATEDs RIGHT TO
SUSPEND WORK OR TERMINATE THE CONTRACT This is a petition for review on certiorari under Rule 45
xxxx assailing the February 20, 2006 Decision[1] and the March 30,
2006 Resolution[2] of the Court of Appeals (CA) in CAG.R. CEB SP.
2. For Convenience of the LICOMCEN, INCORPORATED No. 00623.

x x x. The Contractor [FSI] shall not claim


damages for such discontinuance or termination
of the Contract, but the Contractor shall receive THE FACTS
compensation for reasonable expenses incurred in
good faith for the performance of the Contract and for Petitioner Metropolitan Cebu Water District (MCWD) is a
reasonable expenses associated with termination of the government-owned and controlled corporation (GOCC) created
Contract. The LICOMCEN, INCORPORATED will pursuant to Presidential Decree (PD) No. 198,[3] as amended,
determine the reasonableness of such expenses. The with its principal office address at the MCWD Building,
Contractor [FSI] shall have no claim for Magallanes corner Lapu-Lapu Streets, Cebu City. [4] It is
anticipated profits on the work thus terminated, mandated to supply water within its service area in the cities
nor any other claim, except for the work actually of Cebu, Talisay, Mandaue, and Lapu-Lapu and the municipalities
performed at the time of complete discontinuance, of Compostela, Liloan, Consolacion, and Cordova in
including any variations authorized by the LICOMCEN, the Province of Cebu.[5]
INCORPORATED/Engineer to be done.
Respondent Metro Rock Industries, Inc. (MRII) is a
The prohibition, FSI posits, applies only where the contract was domestic corporation with principal office address at the
properly and lawfully terminated, which was not the case at 2nd Level of the Waterfront Cebu Hotel and Casino,
bar. FSI also took pains in differentiating its claim for unrealized Lahug, Cebu City.[6]
profit from the prohibited claim for anticipated profits;
supposedly, unrealized profit is one that is built-in in the On May 19, 1997, MCWD entered into a Water Supply
contract price, while anticipated profit is not. We fail to see the Contract[7] (the Contract) with MRII wherein it was agreed that
distinction, considering that the contract itself neither defined the latter would supply MCWD with potable water, in accordance
71
with the World Health Organization (WHO) standard or the Exchange Rate and the Base Power Rate shall be the
Philippine national standard, with a minimum guaranteed annual prevailing rate in January 1999, while the Base Selling Price
volume.[8] of water shall mean the 1996 rate per cubic meter of water
as provided for in the Water Supply Contract.
On March 15, 2004, MRII filed a Complaint[9] against
MCWD with the Construction Industry Arbitration 2. Ordering Respondent Metropolitan Cebu Water
Commission (CIAC), citing the arbitration clause (Clause 18) [10] of District to pay Claimant, Mactan Rock Industries, Inc[.] under
the Contract. The case was docketed as CIAC Case No. 12-2004. the reformed Clause 17 of the Water Supply Contract, the net
In the said complaint, MRII sought the reformation of Clause 17 amount of Php12,126,296.70 plus legal interest of six
of the Contract, or the Price Escalation/De-Escalation Clause, in percent (6%) per annum from the (sic) March 15, 2004, the
order to include Capital Cost Recovery in the price escalation date of filling (sic) of the case with the Construction Industry
formula, and to have such revised formula applied from 1996 Arbitration Commission, the rate increased to twelve percent
when the bidding was conducted, instead of from the first day (12%) per annum from the date the herein Decision have
when MRII started selling water to MCWD. It also sought the (sic) become final and executory until the foregoing amounts
payment of the unpaid price escalation/adjustment, and the shall have been fully paid[.]
payment of unpaid variation/extra work order and interest/cost
of money up to December 31, 2003.[11] 3. Claimant Mactan Rock Industries, Inc. and
Metropolitan Cebu Water District shall share equally the cost
On May 7, 2002, MCWD filed its Answer [12] dated April of arbitration.
27, 2004, which included a motion to dismiss the complaint on
the ground that the CIAC had no jurisdiction over the case, as SO ORDERED.[19]
the Contract was not one for construction or infrastructure.
Decision of the CA in CA-G.R. SP No. 85579 - Petition for
The CIAC thereafter issued an order [13] denying MCWDs certiorari under Rule 65 with the Court of Appeals questioning
motion to dismiss, and calling the parties to a preliminary the jurisdiction of the CIAC
conference for the review and signing of the Terms of Reference.
[14]
Meanwhile, on October 28, 2005, the CA in its
decision[20] in the First Petition upheld the jurisdiction of the CIAC
MCWD, thus, filed a petition for certiorari[15] under Rule over the case. The CA held that when parties agree to settle
65 with the CA, questioning the jurisdiction of the CIAC. The their disputes arising from or connected with construction
petition was docketed as CA-G.R. SP. No. 85579 (First Petition). contracts, the CIAC acquires primary jurisdiction.
[21]
Citing Philrock Inc. v. Construction Industry Arbitration
Meanwhile, the CIAC proceeded with the preliminary Commission,[22] the CA stated that the CIAC may resolve not only
conference scheduled on June 10 and July 22, 2004 which MWCD the merits of such controversies, but may also award damages,
opted not to attend. MRII and the CIAC both signed the Terms of interest, attorneys fees, and expenses of litigation, when
Reference. Pursuant to the Terms of Reference and the CIAC appropriate.[23]
Order dated July 22, 2004, MRII submitted its documentary
evidence and affidavits of its witnesses.[16]
Second, the CA held that the claims in question fall
under the jurisdiction of the CIAC. Thus:
On August 27, 2004, MRII submitted its Formal Offer of
Evidence and its memorandum of arguments in the form of a Xxx Section 4 of Executive Order No. 1008,
proposed/draft decision. MCWD did not attend the hearings. It otherwise known as the Construction Industry
did not submit evidence other than those annexed to its Answer. Arbitration Law delineates CIACs jurisdiction as original
Neither did it file a formal offer of evidence, or a memorandum and exclusive jurisdiction over disputes arising from, or
of legal arguments.[17] connected with, contracts entered into by parties
involved in construction in the Philippines, whether the
Decision of the CIAC disputes arise before or after the completion of the
contract, or after abandonment thereof. Moreover,
The CIAC promulgated its Decision [18] on April 14, 2005, Section 5 (k) of Republic Act No. 9184 otherwise known
the dispositive portion of which reads: as [the] Government Procurement Reform Act expressly
defines infrastructure project as including water
WHEREFORE[,] premises considered, judgment is hereby supply[,] construction, rehabilitation[,] demolition,
rendered as follows: repair, restoration and maintenance.

1. Ordering the reformation of Clause 17 of the Consistent with the above-mentioned policy of
Water Supply Contract to read: encouraging alternative dispute resolution methods,
courts should liberally construe arbitration clauses.
17[.] Price Escalation and/or De-Escalation shall be based on Provided such clause is susceptible of an interpretation
the parametric formula: that covers the asserted dispute, an order to arbitrate
should be granted. Any doubt should be resolved in
17.1 Power Rate Price Adjustment/Power Cost favor of arbitration. It is to be highlighted that the
Adjustment dispute in the case at bar arose from the parties
incongruent positions with regard to clause 17 of the
Current Power Rate - Base Power Rate x 30% of base selling Water Supply Contract[,] specifically the price
price of water escalation/adjustment. The instant case involves
Base Power Rate technical discrepancies that are better left to an arbitral
body that has expertise in those areas. Nevertheless, in
17.2 Consumer Price Index (CPI) Adjustment/Operating Cost any event, the inclusion of an arbitration clause in a
Adjustment: contract does not ipso facto divest the courts of
jurisdiction to pass upon the findings of arbitral bodies,
Current CPI Base CPI x 40% of base selling price of water because the awards are still judicially reviewable under
Base CPI certain conditions.[24] (Citations omitted.)

17.3 Capital Cost Recovery Adjustment: MCWDs motion for reconsideration of the decision in the First
Petition was still pending when it filed the petition for
Current Peso to Base Peso to US$ review[25] under Rule 43 (Second Petition) appealing the decision
US$ Exchange Rate Exchange Rate x 30% of base selling of the CIAC. The motion for reconsideration was eventually
price of water denied in a Resolution[26] dated May 3, 2006. MCWD did not
Base Peso to US $ Exchange Rate appeal from the denial of the motion. It, thus, became final and
executory.[27]
Price escalation shall be reckoned from January 1999 when
the water was first delivered by Mactan Rock Industries, Inc.
to the MCWD facilities in Mactan. The base CPI, base US$
72
The Construction Industry Arbitration
Decision of the CA in CA-G.R. CEB SP. No. 00623 Petition Commission (CIAC) was created in 1985 under Executive
for review under Rule 43 appealing the decision of the CIAC Order (E.O.) No. 1008 (Creating an Arbitration Machinery for the
Philippine Construction Industry), in recognition of the need to
Aggrieved by the CIAC Decision, MCWD filed a petition establish an arbitral machinery that would expeditiously settle
for review under Rule 43 with the CA which was docketed as CA- construction industry disputes. The prompt resolution of
G.R. CEB SP. No. 00623. problems arising from, or connected to, the construction
industry was considered necessary and vital for the fulfillment of
The CA, however, dismissed the petition in its Decision national development goals, as the construction industry
dated February 20, 2006. The Court therein stated that the issue provided employment to a large segment of the national labor
of jurisdiction had already been resolved by the 18 th Division in force, and was a leading contributor to the gross national
the First Petition, where the CA upheld the jurisdiction of the product. [31]
CIAC over Arbitration Case No. 12-2004.
Under Section 4 of E.O. No. 1008, the CIACs jurisdiction
Citing jurisprudence, the CA also ruled that there being was specifically delineated as follows:
an arbitration clause in the Contract, the action for reformation
of contract instituted by MRII in this case fell squarely within the SECTION 4. Jurisdiction - The CIAC shall
jurisdiction of the CIAC, not the courts. In relation to this, the CA have original and exclusive jurisdiction over disputes
noted that the present rule is that courts will look with favor arising from, or connected with, contracts entered into
upon amicable agreements to settle disputes through by parties involved in construction in the Philippines,
arbitration, and will only interfere with great reluctance to whether the disputes arise before or after the
anticipate or nullify the action of the arbitrator. MCWD being a completion of the contract, or after the abandonment
signatory and a party to the Water Supply Contract, it cannot or breach thereof. These disputes may involve
escape its obligation under the arbitration clause. [28] government or private contracts. For the Board to
acquire jurisdiction, the parties to a dispute must agree
The CA also held that the CIAC did not err in finding to submit the same to voluntary arbitration.
that the Water Supply Contract is clear on the matter of the
reckoning period for the computation of the escalation cost The jurisdiction of the CIAC may include but is
from January 9, 1999, or the first day of delivery of water. not limited to violation of specifications for materials
Moreover, the CA found that the CIAC did not err in ruling that and workmanship; violation of the terms of agreement;
the contract be reformed to include Capital Cost Recovery in the interpretation and/or application of contractual
parametric formula for price escalation. Neither did it err in provisions; amount of damages and penalties;
holding that the Capital Cost Recovery shall be 30% of the Base commencement time and delays; maintenance and
Selling Price of water as a consequence of the reformation of defects; payment default of employer or contractor and
Clause 17. changes in contract cost.

Finally, the CA stressed that factual findings of


administrative agencies which are deemed to have acquired
expertise in matters within their respective jurisdictions are
generally accorded not only respect but even finality when
supported by substantial evidence.[29]
Excluded from the coverage of this law are
MCWD filed a motion for reconsideration but it was disputes arising from employer-employee relationships
denied in the CA Resolution dated March 30, 2006. which shall continue to be covered by the Labor Code
of the Philippines. (Underscoring supplied)
Thus, this petition.
The jurisdiction of the CIAC as a quasi-judicial body is
ISSUES confined to construction disputes,[32] that is, those arising from,
or connected to, contracts involving all on-site works on
MCWD raises the following issues in its petition for buildings or altering structures from land clearance through
review: completion including excavation, erection and assembly and
installation of components and equipment.[33] The CIAC has
MAY THE CONSTRUCTION INDUSTRY jurisdiction over all such disputes whether the dispute arises
[ARBITRATION] COMMISSION EXERCISE before or after the completion of the contract.[34]
JURISDICTION OVER DISPUTES ARISING FROM A
WATER SUPPLY CONTRACT? Whether the CIAC has jurisdiction over the dispute

MAY A PARTY, WHO IS A SIGNATORY TO THE As earlier stated, following the denial of its motion to dismiss by
WATER SUPPLY CONTRACT[,] IN EFFECT CIAC, MCWD filed the First Petition with the CA, which decided in
SUBMITTING ITSELF TO THE JURISDICTION OF favor of MRII and upheld the jurisdiction of the CIAC.
THE CONSTRUCTION INDUSTRY ARBITRATION
COMMISSION, QUESTION THE JURISDICTION OF Not being in conformity, MCWD filed a motion for
[THE] CIAC? reconsideration.

DOES THE CONSTRUCTION INDUSTRY While the said motion was pending with the CA, MCWD filed the
ARBITRATION COMMISSION HAVE THE (SIC) Second Petition with the same court. Eventually, the motion was
JURISDICTION OVER A COMPLAINT PRAYING FOR denied, and MCWD never appealed the case. Thus, the decision
A REFORMATION OF A WATER SUPPLY CONTRACT? of the CA in the First Petition became final and executory.

MAY THE COURT OF APPEALS REFUSE TO RENDER


A [SIC] JUDGMENT ON AN ISSUE BECAUSE THIS The question now is whether such final and executory
HAS BEEN ALREADY SETTLED IN A DECISION decision is binding such that courts are generally precluded from
RENDERED BY ANOTHER DIVISION OF THE COURT passing judgment on the issue of jurisdiction in the present
OF APPEALS IN A PETITION FOR CERTIORARI, petition.
EVEN IF THE SAID DECISION HAS NOT YET BEEN
(SIC) FINAL DUE TO A TIMELY FILING OF A The Court finds in the affirmative.
MOTION FOR RECONSIDERATION?[30] This Court has held time and again that a final and
executory judgment, no matter how erroneous, cannot be
changed, even by this Court. Nothing is more settled in law than
RULING OF THE COURT that once a judgment attains finality, it thereby becomes
immutable and unalterable. It may no longer be modified in any
Creation of the CIAC respect, even if such modification is meant to correct what is
perceived to be an erroneous conclusion of fact or law, and
73
regardless of whether the modification is attempted to be made from the Water Supply Contract between the petitioner and
by the court rendering it or by the highest court of the land.[35] respondent.

In its Decision in the First Petition, the CA affirmed the arbitral To determine whether there is identity of the rights
bodys finding in CIAC Case No. 12-2004 that the case was within asserted and reliefs prayed for, grounded on the same facts and
its jurisdiction. Such decision having become final, it is beyond bases, the following tests may be utilized: (1) whether the same
the jurisdiction of this Court, or any court or body, for that evidence would support and sustain both the first and the
matter, to review or modify, even supposing for the sake of second causes of action, also known as the same evidence test;
argument, that it is indeed erroneous. or (2) whether the defenses in one case may be used to
substantiate the complaint in the other.[39] Also fundamental is
Also, the parties apparently characterized the Contract the test of determiningwhether the cause of action in the
as one involving construction, as its arbitration clause second case existed at the time of the filing of the first case. [40]
specifically refers disputes, controversies or claims arising out of
or relating to the Contract or the breach, termination or validity In the First Petition, MCWD argued that the CIACs
thereof, if the same cannot be settled amicably, to an arbitration issuance of its Order[41] dated May 28, 2004 was tainted with
tribunal, in accordance with E.O. No. 1008, or the Construction grave abuse of discretion amounting to excess or lack of
Industry Arbitration Law: jurisdiction. Thus, MCWD stated in its prayer:

WHEREFORE, in light of the premises laid


down, petitioner most respectfully prays:
V. DISPUTES AND JURISDICTION:
1. Upon the filing of this Petition, a Writ of
18. Any dispute, controversy or claim arising Preliminary Injunction or restraining order be
out of or relating to this contract or the breach, issued forthwith, enjoining the respondent
termination or invalidity thereof, if the same cannot be from proceeding with the hearing of the case
settled amicably, may be submitted for arbitration to until further orders from the Honorable Court
an Arbitration Tribunal in accordance with Executive of Appeals;
Order No. 1008 dated 4 February 1985, otherwise
known as the Construction Industry Arbitration Law and 2. After consideration, petitioner also prays
the place of arbitration shall be the City of Cebu, that the Order dated May 28, 2004, denying
Philippines, otherwise said dispute or controversy petitioners motion to dismiss be declared
arising out of the contract or breach thereof shall be without force and effect;
submitted to the court of law having jurisdiction thereof
in the city where MCWD is located.[36] 3. Petitioner also prays that the Construction
Industry Arbitration Commission be barred
Had the parties been of the mutual understanding that from hearing the case filed by Mactan Rock
the Contract was not of construction, they could have instead Industries, Inc., private respondent herein.
referred the matter to arbitration citing Republic Act (R.A.) No.
876, or The Arbitration Law. Having been passed into law in Other measures of relief, which are just and
1953, the said statute was already in existence at the time the equitable under the foregoing premise are also prayed
contract was entered into, and could have been applied to for.[42]
arbitration proceedings other than those specifically within the
arbitral jurisdiction of the CIAC. The Second Petition, on the other hand, raised the
following issues:
Whether the CA erred in refusing to render judgment on
the issue of jurisdiction ___________ a. Whether or not the Arbitral Tribunal of CIAC gravely
erred in taking and exercising jurisdiction over the
On a related matter, MWCD also raises the issue of complaint filed by the respondent;
whether the 19th Division of the CA, Cebu City, erred in refusing
to render judgment on the issue of jurisdiction raised in the b. Whether or not the Arbitral
Second Petition on the ground that it had already been settled Tribunal of CIAC gravely erred in reforming Clause 17 of
by the 18th Division in its decision in the First Petition, even if the the Contract;
18th Division decision had not yet become final due to a timely
filing of a motion for reconsideration. c. Whether or not the same
tribunal gravely committed an error in considering
The Court rules in the negative. Capital Cost Recovery Adjustment in awarding in favor
of the complainant, when the same is extraneous to the
The 19th Division was correct in refusing to render provisions of the contract;[43]
judgment on the issue of jurisdiction as, at that time, the issue
was still pending before another division of the CA. Thus, it prayed:

Litis pendentia is predicated on the principle that a WHEREFORE, PREMISES CONSIDERED, it is


party should not be allowed to vex another more than once most respectfully prayed of the Honorable Court that a
regarding the same subject matter and for the same cause of Judgment be issued reversing the findings of the
action. It is founded on the public policy that the same subject Arbitral Tribunal of the Construction Industry Arbitration
matter should not be the subject of controversy in courts more Commission in its Decision dated April 14, 2005, as far
than once, in order that possible conflicting judgments may be as the order of reformation of the water supply contract
avoided for the sake of the stability of the rights and status of and in granting the monetary award.
persons, and also to avoid the costs and expenses incident to
numerous suits. [37] It is further prayed that the decision rendered
by the Arbitral Tribunal be declared invalid for want of
With the two petitions then pending before the CA, all jurisdiction to arbitrate and to order the reformation of
the elements of litis pendentia were present, that is, identity of the water supply contract;
the parties in the two actions, substantial identity in the causes
of action and in the reliefs sought by the parties, and identity It is also prayed that the decision awarding
between the two actions such that any judgment that may be money to the respondent be strike (sic) down as
rendered in one case, regardless of which party is successful, erroneous and without legal basis for lack of jurisdiction
would amount to res judicata in the other.[38] by the Arbitral Tribunal, which rendered the Decision.

In both cases, MCWD was the petitioner and MRII, the It is also prayed that a Temporary Restraining
respondent. Although they differ in form, in essence, the two Order and a Writ of Preliminary Injunction be issued at
cases involved a common issue, that is, MCWDs challenge to the the outset, ordering the stay of execution pending the
jurisdiction of the CIAC over the arbitration proceedings arising resolution of the issues raised in the Petition.
74
Other measures of relief, which are just and Whether the CIAC had jurisdiction to order the
equitable, are also prayed for.[44] reformation of the Water Supply Contract
The jurisdiction of courts and quasi-judicial bodies is
In both cases, the parties also necessarily relied on the determined by the Constitution and the law.[50] It cannot be fixed
same laws and arguments in support of their respective by the will of the parties to the dispute, nor can it be expanded
positions on the matter of jurisdiction. or diminished by stipulation or agreement. [51] The text of Section
4 of E.O. No. 1008 is broad enough to cover any dispute arising
In the First Petition, in support of its argument, that the from, or connected with, construction contracts, whether these
CIAC had no jurisdiction to arbitrate the causes of action raised involve mere contractual money claims or execution of the
by MRII, MCWD cited the portions of the Contract on the works. This jurisdiction cannot be altered by stipulations
obligations of the water supplier, E.O. No. 1008 (specifically restricting the nature of construction disputes, appointing
Section 4 on jurisdiction), the Rules of Procedure Governing another arbitral body, or making that bodys decision final and
Construction Arbitration (Section 1, Article III). It also alleged binding.[52]
that in issuing the order denying its motion to dismiss, the CIAC
misread the provisions of LOI No. 1186 and R.A. No. 9184 on the Thus, unless specifically excluded, all incidents and
definition of an infrastructure project.[45] matters relating to construction contracts are deemed to be
within the jurisdiction of the CIAC. Based on the previously cited
MRII, however, opined that the CIAC had jurisdiction provision outlining the CIACs jurisdiction, it is clear that with
over the complaint and, therefore, correctly denied petitioners regard to contracts over which it has jurisdiction, the only
motion to dismiss. MRII argued that certiorari was not a proper matters that have been excluded by law are disputes arising
remedy in case of denial of a motion to dismiss and that the from employer-employee relationships, which continue to be
claims fell squarely under CIACs original and exclusive governed by the Labor Code of the Philippines. Moreover, this is
jurisdiction. MRII, in support of its position, cited Section 1 of LOI consistent with the policy against split jurisdiction.
No. 1186 and Section 5(k) of R.A. No. 9184. MRII further
proposed that, as shown by MCWDs pro-forma Water Supply In fact, in National Irrigation Administration v. Court of
Contract, Specifications, Invitation to Submit Proposal, Pre-Bid Appeals,[53] it was held that the CIAC had jurisdiction over the
Conference minutes, Addendum No. 1, and MRIIs Technical and dispute, and not the contract. Therefore, even if the contract
Financial Proposals, the undertaking contemplated by the preceded the existence of the CIAC, since the dispute arose
parties is one of infrastructure and of works, rather than one of when the CIAC had already been constituted, the arbitral board
supply or mere services.[46] was exercising current, and not retroactive, jurisdiction. In the
same case, it was held that as long as the parties agree to
In the Second Petition, in support of the issue of submit to voluntary arbitration, regardless of what forum they
jurisdiction, MCWD again relied on Section 4 of E.O. No. 1008 may choose, their agreement will fall within the jurisdiction of
and Section 1, Article III of the Rules of Procedure Governing the CIAC, such that, even if they specifically choose another
Construction Arbitration. It also brought to fore the alleged forum, the parties will not be precluded from electing to submit
faulty conclusion of MRII that a water supply contract is their dispute to the CIAC because this right has been vested
subsumed under the definition of an infrastructure project under upon each party by law.
LOI 1186.[47]
This is consistent with the principle that when an
In its Comment, MRII reiterated and adopted its administrative agency or body is conferred quasi-judicial
arguments before the CIAC, and insisted that the undertaking functions, all controversies relating to the subject matter
contemplated by the parties was one of infrastructure and of pertaining to its specialization are deemed to be included within
works, as distinguished from mere supply from off-the-shelf or its jurisdiction since the law does not sanction a split of
from mere services.[48] Section 1 of LOI No. 1186, to define jurisdiction, as stated in Pea v. Government Service Insurance
infrastructure and Section 5(k) of R.A. No. 9184 to include water System.[54]
supply, were again cited. In support of its arguments, MRII cited
anew MCWDs pro-forma Water Supply Contract, Specifications In Pea, the Court held that although the complaint for
(in its Invitation to Submit Proposal), pronouncements at the Pre- specific performance, annulment of mortgage, and damages
Bid Conference, Addendum No. 1, and MRIIs Technical and filed by the petitioner against the respondent included title to,
Financial Proposals. MRII further extensively reproduced the possession of, or interest in, real estate, it was well within the
content of the joint affidavit of Messrs. Antonio P. Tompar and jurisdiction of the Housing and Land Use Regulatory
Lito R. Maderazo, MRIIs President/CEO and Financial Manager, Board (HLURB), a quasi-judicial body, as it involved a claim
respectively.[49] against the subdivision developer, Queens Row Subdivision, Inc.,
as well as the Government Service Insurance System (GSIS).
Given that the same arguments were raised on the
matter of CIAC jurisdiction, the parties thus relied on This case was later cited in Badillo v. Court of Appeals,[55] where
substantially the same evidence in both petitions. MCWD the Court concluded that the HLURB had jurisdiction over
annexed to both petitions copies of the Water Supply Contract, complaints for annulment of title. The Court also held that courts
the complaint filed by MRII with the CIAC, and its Answer to the will not determine a controversy where the issues for resolution
said complaint. On the other hand, MRII presented Addendum demand the exercise of sound administrative discretion, such as
No. 1 to the Water Supply Contract and its Technical and that of the HLURB, the sole regulatory body for housing and land
Financial Proposals. development. It was further pointed out that the extent to which
an administrative agency may exercise its powers depends on
Moreover, the first cause of action in the Second the provisions of the statute creating such agency.
Petition, that is, the CIACs having assumed jurisdiction, allegedly The ponencia further quoted from C.T. Torres
unlawfully, over the dispute arising from the Water Supply Enterprises, Inc. v. Hibionada:[56]
Contract, obviously existed at the time the First Petition was The argument that only courts of justice can adjudicate
filed, as the latter case dealt with the jurisdiction of the CIAC claims resoluble under the provisions of the Civil Code
over the complaint filed. is out of step with the fast-changing times. There are
hundreds of administrative bodies now performing this
Finally, any judgment that may be rendered in the First function by virtue of a valid authorization from the
Petition on the matter of whether the CIAC has jurisdiction over legislature. This quasi-judicial function, as it is called, is
the arbitration proceedings, regardless of which party was exercised by them as an incident of the principal power
successful, would amount to res judicata in the Second Petition, entrusted to them of regulating certain activities falling
insofar as the issue of jurisdiction is concerned. In fact, what under their particular expertise.
MCWD should have done was to appeal to the Court after the
denial of its motion for reconsideration in the First Petition. For In the Solid Homes case for example the Court affirmed
not having done so, the decision therein became final and, the competence of the Housing and Land Use
therefore, immutable. Regulatory Board to award damages although this is an
essentially judicial power exercisable ordinarily only by
Thus, following the above discussion, the 19th Division the courts of justice. This departure from the traditional
was correct in refusing to render judgment on the issue of allocation of governmental powers is justified by
jurisdiction in the Second Petition. expediency, or the need of the government to respond
75
swiftly and competently to the pressing problems of Thus, under the CIAC Rules, even without the
the modern world. participation of one of the parties in the proceedings, the CIAC is
still required to proceed with the hearing of the construction
In Bagunu v. Spouses Aggabao,[57] the Court ruled dispute.[61]
that the RTC must defer the exercise of its jurisdiction on related
issues involving the same subject matter properly within its This Court has held that the CIAC has jurisdiction over a
jurisdiction, such as the distinct cause of action for reformation dispute arising from a construction contract even though only
of contracts involving the same property, since the DENR one of the parties requested for arbitration. [62] In fact,
assumed jurisdiction over the lot in question, pursuant to its in Philrock, Inc. v. Construction Industry Arbitration Commission,
[63]
mandate. the Court held that the CIAC retained jurisdiction even if both
parties had withdrawn their consent to arbitrate.
In National Housing Authority v. First United Constructors
Corporation,[58] the Court held that there was no basis for the In this case, there being a valid arbitration clause
exclusion of claims for business losses from the jurisdiction of mutually stipulated
the CIAC because E.O. No. 1008 excludes from the coverage of by the parties, they are bothcontractually bound to settle their d
the law only those disputes arising from employer-employee ispute
relationships which are covered by the Labor Code, conveying through arbitration before the CIAC. MCWD refused to
an intention to encompass a broad range of arbitrable issues participate, but this should not affect the authority of the CIAC
within the jurisdiction of CIAC.[59] Section 4 provides that (t)he to conduct the proceedings, and, thereafter, issue an arbitral
jurisdiction of the CIAC may include but is not limited to xx x, award.
underscoring the expansive character of the CIACs jurisdiction.
Very clearly, the CIAC has jurisdiction over a broad range of Now, with the CIAC decision being questioned by
issues and claims arising from construction disputes, including MCWD, the Court takes a cursory reading of the said decision. It
but not limited to claims for unrealized profits and opportunity reveals that the conclusions arrived at by CIAC are supported by
or business losses. What E.O. No. 1008 emphatically excludes is facts and the law. Article 1359 of the Civil Code states that when
only disputes arising from employer-employee relationships.[60] there has been a meeting of the minds of the parties to a
contract, but their true intention is not expressed in the
Where the law does not delineate, neither should we. instrument purporting to embody the agreement by reason of
Neither the provisions of the Civil Code on reformation of mistake, fraud, inequitable conduct or accident, one of the
contracts nor the law creating the CIAC exclude the reformation parties may ask for the reformation of the instrument to the end
of contracts from its jurisdiction. Jurisprudence further dictates that such true intention may be expressed. The CIAC, in this
that the grant of jurisdiction over related and incidental matters case, found that the parametric formula for price escalation
is implied by law. Therefore, because the CIAC has been held to reflected in the Water Supply Contract involved two items:
have jurisdiction over the Contract, it follows that it has Power Rate Price Adjustment (30% of the base selling price of
jurisdiction to order the reformation of the Contract as well. water) and Consumer Price Index Adjustment (40% of the base
selling price of water). The remaining 30% of the selling price of
Whether MCWD can validly refuse to participate in the water, which should have been for Capital Cost Recovery, was
arbitration proceedings inadvertently left out in this parametric formula. Thus, the
Contract should be reformed accordingly to reflect the intention
In light of the finality of the CA decision on the matter of of the parties to include in the price escalation formula the
jurisdiction, the only remaining issue to be disposed of is Capital Cost Recovery Adjustment. These conclusions were
whether the CIAC could proceed with the case even if the MCWD affirmed by the CA in the assailed decision of February 20, 2006.
refused to participate in the arbitration proceedings.
As noted by MCWD in its reply, however, the dispositive
The Court rules in the affirmative. Though one party portion of the CIAC decision reforming the price escalation
can refuse to participate in the arbitration proceedings, formula is inconsistent with what was stated in the body of the
this cannot prevent the CIAC from proceeding with the case and decision. The formula contained in the body of the decision is as
issuing an award in favor of one of the parties. follows:

Section 4.2 of the Revised Rules of Procedure PRICE ADJUSTMENT COMPUTATION


Governing Construction Arbitration (CIAC Rules) specifically Based on Reformed Clause 17 of the Water
provides that where the jurisdiction of the CIAC is properly Supply Contract
invoked by the filing of a Request for Arbitration in accordance
with CIAC Rules, the failure of a respondent to appear, which 1. Power Cost Adjustment:
amounts to refusal to arbitrate, will not stay the proceedings, xxx
notwithstanding the absence of the respondent or the lack of
participation of such party. In such cases, the CIAC is mandated Current Power Rate Base Power Rate x 30% of Base Selling
to appoint the arbitrator/s in accordance with the Rules, and the Price of water
arbitration proceedings shall continue. The award shall then be Base Power Rate
made after receiving the evidence of the claimant.
xxx
In such a case, all is not lost for the party who did not
participate. Even after failing to appear, a respondent is still 2. Operating Cost Adjustment - Local
given the opportunity, under the CIAC Rules, to have the
proceedings reopened and be allowed to present evidence, xxx
although with the qualification that this is done before an award
is issued: Current CPI Base CPI x 30% of 40% of Base Selling Price of
Water
4.2.1 In the event that, before award, the Base CPI
Respondent who had not earlier questioned the
jurisdiction of the Tribunal, appears and offers to xxx
present his evidence, the Arbitral Tribunal may, for
reasons that justifies (sic) the failure to appear, reopen 3. Operating Cost Adjustment Foreign
the proceedings, require him to file his answer with or
without counterclaims, pay the fees, where required xxx
under these Rules, and allow him to present his
evidence, with limited right to cross examine witnesses Current Forex Base Forex x 70% of 40% of Base Selling Price
already in the discretion of the Tribunal. Evidence of Water
already admitted shall remain. The Tribunal shall decide Base Forex
the effect of such controverting evidence presented by
the Respondent on evidence already admitted prior to xxx
such belated appearance.
Capital Cost Adjustment Local
76
xxx water, and not just 70% of the Capital Cost Recovery
Adjustment. The omission of the marked portions of the formula
Current CPI Base CPI x 30% of 30% of Base Selling as stated in the body of the CIAC decision represents substantial
Price of Water changes to the formula for price escalation. It is thus clear that
Base CPI the formula as stated in the body of the decision should govern.

xxx WHEREFORE, the petition is DENIED. The Decision


and Resolution of the Court of Appeals in C.A.-G.R. CEB SP. No.
Capital Cost Adjustment Foreign 00623 are AFFIRMED with the modification that the formula for
the computation of the Capital Cost Recovery Adjustment in the
xxx fallo of the CIAC decision should be amended to read as follows:

Current Forex Base Forex x 70% of 30% of Base WHEREFORE, premises considered, judgment is hereby
Selling Price of Water rendered as follows:
Base Forex
1. Ordering the reformation of Clause 17 of the Water
xxx[64] Supply Contract to read:

The dispositive portion of the decision, however, 17. Price Escalation and/or De-Escalation shall be based on
reads: the parametric formula:
WHEREFORE[,] premises considered, judgment is
hereby rendered as follows: 17.1. Power Rate Price Adjustment/Power Cost
Adjustment
1. Ordering the reformation of Clause 17 of the Water Supply
Contract to read:
Current Power Rate - Base Power Rate x 30% of base selling
17[.] Price Escalation and/or De-Escalation shall be based on price of water
the parametric formula: Base Power Rate

17.1 Power Rate Price Adjustment/Power Cost 17.2 Consumer Price Index (CPI) Adjustment/Operating Cost
Adjustment Adjustment:

Current Power Rate Base Power Rate x 30% of Base Selling Current CPI Base CPI x 30% of 40% of base selling price of
Price of water water
Base Power Rate Base CPI

17.2 Consumer Price Index (CPI) Adjustment/Operatiing 17.3 Capital Cost Recovery Adjustment:
(sic) Cost Adjustment:
Current Peso to Base Peso to US$
Current CPI Base CPI x 40% of Base Selling Price of Water US$ Exchange Rate Exchange Rate x 70% of 30% of base
Base CPI selling price of water
Base Peso to US $ Exchange Rate
17.3 Capital Cost Recovery Adjustment:
Price escalation shall be reckoned from January 1999 when
Current Peso to Base Peso to US$ the water was first delivered by Mactan Rock Industries, Inc.
US$ Exchange Rate Exchange Rate x 30% of base selling price to the MCWD facilities in Mactan. The base CPI, base US$
of water Exchange Rate and the Base Power Rate shall be the
Base Peso to US $ Exchange Rate prevailing rate in January 1999, while the Base Selling Price
of water shall mean the 1996 rate per cubic meter of water
The general rule is that where there is a conflict as provided for in the Water Supply Contract.
between the fallo, or the dispositive part, and the body of the
decision or order, the fallo prevails on the theory that the fallo is 2. Ordering Respondent Metropolitan Cebu Water District
the final order and becomes the subject of execution, while the to pay Claimant, Mactan Rock Industries, Inc. under the
body of the decision merely contains the reasons or conclusions reformed Clause 17 of the Water Supply Contract, the net
of the court ordering nothing. However, where one can clearly amount of Php12,126,296.70 plus legal interest of six
and unquestionably conclude from the body of the decision that percent (6%) per annum from March 15, 2004, the date of
there was a mistake in the dispositive portion, the body of the filing of the case with the Construction Industry Arbitration
decision will prevail.[65] Commission, and twelve percent (12%) per annum from the
date this Decision becomes final and executory, until the
Following the reasoning of the CIAC in this case, there foregoing amounts shall have been fully paid.
are three components to price adjustment: (1) Power Cost
Adjustment (30% of the base selling price of water); (2) 3. Claimant Mactan Rock Industries, Inc. and Metropolitan
Operating Cost Adjustment (40% of the base selling price of Cebu Water District shall share the cost of arbitration equally.
water); and (3) Capital Cost Adjustment (30% of the base selling
price of water). SO ORDERED.
SECOND DIVISIONG.R. No. 179628 January 16,
In turn, the second componentOperating Cost 2013
Adjustmentis computed based on Local Operating Cost
Adjustment (30%), and Foreign Operating Cost Adjustment
(70%). THE MANILA INSURANCE COMPANY, INC., Petitioner,
vs.
Capital Cost Adjustment, on the other hand, is SPOUSES ROBERTO and AIDA AMURAO, Respondents.
composed of Local Capital Cost Adjustment (30%), and Foreign
Capital Cost Adjustment (70%). DEL CASTILLO, J.:
This is consistent with the formula set forth in the body
of the CIAC decision. If the formula in the dispositive portion The jurisdiction of the Construction Industry Arbitration
were to be followed, Operating Cost Adjustment would be Commission (CIAC) is conferred by law. Section 4 1 of Executive
computed with the Local Operating Cost Adjustment Order (E.O.) No. I 008, otherwise known as the Construction
representing the entire 40% of the base selling price of water Industry Arbitration Law, "is broad enough to cover any dispute
instead of just 30% of the Operating Cost Adjustment. Moreover, arising from, or connected with construction contracts, whether
if the Capital Cost Recovery Adjustment were to be computed these involve mere contractual money claims or execution of
based solely on Foreign Capital Cost Recovery Adjustment, it the works."2
would represent the entire 30% of the base selling price of
77
This Petition for Review on Certiorari 3 under Rule 45 of the Rules each contract becomes completed at the same time, and the
of Court assails the Decision 4 dated June 7, 2007 and the consideration which supports the principal contract likewise
Resolution5 dated September 7, 2007 of the Court of Appeals supports the subsidiary one." 30 The CA likewise said that,
(CA) in CA-G.R. SP No. 96815. although the contract of surety is only an accessory to the
principal contract, the suretys liability is direct, primary and
absolute.31 Thus:
Factual Antecedents

WHEREFORE, we resolve to DISMISS the petition as we find that


On March 7, 2000, respondent-spouses Roberto and Aida
no grave abuse of discretion attended the issuance of the order
Amurao entered into a Construction Contract Agreement
of the public respondent denying the petitioners motion to
(CCA)6 with Aegean Construction and Development Corporation
dismiss.
(Aegean) for the construction of a six-storey commercial building
in Tomas Morato corner E. Rodriguez Avenue, Quezon City.7 To
guarantee its full and faithful compliance with the terms and IT IS SO ORDERED.32
conditions of the CCA, Aegean posted performance bonds
secured by petitioner The Manila Insurance Company, Petitioner moved for reconsideration but the CA denied the
Inc.8 (petitioner) and Intra Strata Assurance Corporation (Intra same in a Resolution33 dated September 7, 2007.
Strata).9

Issues
On November 15, 2001, due to the failure of Aegean to
complete the project, respondent spouses filed with the Regional
Trial Court (RTC) of Quezon City, Branch 217, a Hence, this petition raising the following issues:
Complaint,10 docketed as Civil Case No. Q-01-45573, against
petitioner and Intra Strata to collect on the performance bonds A.THE HONORABLE CA ERRED WHEN IT HELD THAT IT IS ONLY
they issued in the amounts of P2,760,000.00 WHEN THERE ARE DIFFERENCES IN THE INTERPRETATION OF
and P4,440,000.00, respectively.11 ARTICLE I OF THE CONSTRUCTION AGREEMENT THAT THE
PARTIES MAY RESORT TO ARBITRATION BY THE CIAC.
Intra Strata, for its part, filed an Answer 12 and later, a Motion to
Admit Third Party Complaint,13 with attached Third Party B.THE HONORABLE CA ERRED IN TREATING PETITIONER AS A
Complaint14 against Aegean, Ronald D. Nicdao, and Arnel A. SOLIDARY DEBTOR INSTEAD OF A SOLIDARY GUARANTOR.
Mariano.

C.THE HONORABLE [CA] OVERLOOKED AND FAILED TO


Petitioner, on the other hand, filed a Motion to Dismiss 15 on the CONSIDER THE FACT THAT THERE WAS NO ACTUAL AND
grounds that the Complaint states no cause of action 16 and that EXISTING CONSTRUCTION AGREEMENT AT THE TIME THE
the filing of the Complaint is premature due to the failure of MANILA INSURANCE BOND NO. G (13) 2082 WAS ISSUED ON
respondent-spouses to implead the principal contractor, FEBRUARY 29, 2000.34
Aegean.17 The RTC, however, denied the motion in an
Order18 dated May 8, 2002. Thus, petitioner filed an Answer with
Petitioners Arguments
Counterclaim and Cross-claim,19 followed by a Third Party
Complaint20 against Aegean and spouses Ronald and Susana
Nicdao. Petitioner contends that the CA erred in ruling that the parties
may resort to arbitration only when there is difference in the
interpretation of the contract documents stated in Article I of the
During the pre-trial, petitioner and Intra Strata discovered that
CCA.35 Petitioner insists that under Section 4 of E.O. No. 1008, it
the CCA entered into by respondent-spouses and Aegean
is the CIAC that has original and exclusive jurisdiction over
contained an arbitration clause.21
construction disputes, such as the instant case.36

Hence, they filed separate Motions to Dismiss 22 on the grounds


Petitioner likewise imputes error on the part of the CA in treating
of lack of cause of action and lack of jurisdiction.
petitioner as a solidary debtor instead of a solidary
guarantor.37 Petitioner argues that while a surety is bound
Ruling of the Regional Trial Court solidarily with the obligor, this does not make the surety a
solidary co-debtor.38 A surety or guarantor is liable only if the
On May 5, 2006, the RTC denied both motions. 23 Petitioner and debtor is himself liable.39 In this case, since respondent-spouses
Intra Strata separately moved for reconsideration but their and Aegean agreed to submit any dispute for arbitration before
motions were denied by the RTC in its subsequent Order 24 dated the CIAC, it is imperative that the dispute between respondent-
September 11, 2006. spouses and Aegean must first be referred to arbitration in order
to establish the liability of Aegean.40 In other words, unless the
liability of Aegean is determined, the filing of the instant case is
Aggrieved, petitioner elevated the case to the CA by way of premature.41
special civil action for certiorari.25

Finally, petitioner puts in issue the fact that the performance


Ruling of the Court of Appeals bond was issued prior to the execution of the CCA. 42Petitioner
claims that since there was no existing contract at the time the
On June 7, 2007, the CA rendered a Decision 26 dismissing the performance bond was executed, respondent-spouses have no
petition. The CA ruled that the presence of an arbitration clause cause of action against petitioner.43 Thus, the complaint should
in the CCA does not merit a dismissal of the case because under be dismissed.44
the CCA, it is only when there are differences in the
interpretation of Article I of the construction agreement that the Respondent spouses Arguments
parties can resort to arbitration.27 The CA also found no grave
abuse of discretion on the part of the RTC when it disregarded
the fact that the CCA was not yet signed at the time petitioner Respondent-spouses, on the other hand, maintain that the CIAC
issued the performance bond on February 29, 2000.28 The CA has no jurisdiction over the case because there is no ambiguity
explained that the performance bond was intended to be in the provisions of the CCA. 45 Besides, petitioner is not a party
coterminous with the construction of the building. 29 It pointed to the CCA.46 Hence, it cannot invoke Article XVII of the CCA,
out that "if the delivery of the original contract is which provides for arbitration proceedings. 47 Respondent-
contemporaneous with the delivery of the suretys obligation, spouses also insist that petitioner as a surety is directly and
equally bound with the principal.48 The fact that the performance
78
bond was issued prior to the execution of the CCA also does not Based on the foregoing, in order for the CIAC to acquire
affect the latters validity because the performance bond is jurisdiction two requisites must concur: "first, the dispute must
coterminous with the construction of the building. 49 be somehow connected to a construction contract; and second,
the parties must have agreed to submit the dispute to
arbitration proceedings."54
Our Ruling

In this case, both requisites are present.


The petition has merit.

The parties agreed to submit to arbitration proceedings "any


Nature of the liability of the surety
dispute arising in the course of the execution and performance
of the CCA by reason of difference in interpretation of the
A contract of suretyship is defined as "an agreement whereby a Contract Documents x x x which the parties are unable to
party, called the surety, guarantees the performance by another resolve amicably between themselves."55 Article XVII of the CCA
party, called the principal or obligor, of an obligation or reads:
undertaking in favor of a third party, called the obligee. It
includes official recognizances, stipulations, bonds or
ARTICLE XVII ARBITRATION
undertakings issued by any company by virtue of and under the
provisions of Act No. 536, as amended by Act No. 2206." 50 We
have consistently held that a suretys liability is joint and 17.1 Any dispute arising in the course of the execution and
several, limited to the amount of the bond, and determined performance of this Agreement by reason of difference in
strictly by the terms of contract of suretyship in relation to the interpretation of the Contract Documents set forth in Article I
principal contract between the obligor and the obligee. 51 It bears which the OWNER and the CONTRACTOR are unable to resolve
stressing, however, that although the contract of suretyship is amicably between themselves shall be submitted by either party
secondary to the principal contract, the suretys liability to the to a board of arbitrators composed of Three (3) members
obligee is nevertheless direct, primary, and absolute.52 chosen as follows: One (1) member shall be chosen by the
CONTRACTOR AND One (1) member shall be chosen by the
OWNER. The said Two (2) members, in turn, shall select a third
In this case, respondent-spouses (obligee) filed with the RTC a
member acceptable to both of them. The decision of the Board
Complaint against petitioner (surety) to collect on the
of Arbitrators shall be rendered within Ten (10) days from the
performance bond it issued. Petitioner, however, seeks the
first meeting of the board, which decision when reached through
dismissal of the Complaint on the grounds of lack of cause of
the affirmative vote of at least Two (2) members of the board
action and lack of jurisdiction.
shall be final and binding upon the OWNER and
CONTRACTOR.1wphi1
The respondent-spouses have cause of action against the
petitioner; the performance bond is coterminous with the CCA
17.2 Matters not otherwise provided for in this Contract or by
Special Agreement of the parties shall be governed by the
Petitioner claims that respondent-spouses have no cause of provisions of the Arbitration Law, Executive Order No. 1008. 56
action against it because at the time it issued the performance
bond, the CCA was not yet signed by respondent-spouses and
In William Golangco Construction Corporation v. Ray Burton
Aegean.
Development Corporation,57 we declared that monetary claims
under a construction contract are disputes arising from
We do not agree. "differences in interpretation of the contract" because "the
matter of ascertaining the duties and obligations of the parties
A careful reading of the Performance Bond reveals that the under their contract all involve interpretation of the provisions of
"bond is coterminous with the final acceptance of the the contract."58 Following our reasoning in that case, we find
project."53 Thus, the fact that it was issued prior to the execution that the issue of whether respondent-spouses are entitled to
of the CCA does not affect its validity or effectivity. collect on the performance bond issued by petitioner is a
"dispute arising in the course of the execution and performance
of the CCA by reason of difference in the interpretation of the
But while there is a cause of action against petitioner, the contract documents."
complaint must still be dismissed for lack of jurisdiction.

The fact that petitioner is not a party to the CCA cannot remove
The CIAC has jurisdiction over the case the dispute from the jurisdiction of the CIAC because the issue
of whether respondent-spouses are entitled to collect on the
Section 4 of E.O. No. 1008 provides that: performance bond, as we have said, is a dispute arising from or
connected to the CCA.
SEC. 4. Jurisdiction. The CIAC shall have original and exclusive
jurisdiction over disputes arising from, or connected with, In fact, in Prudential Guarantee and Assurance, Inc. v. Anscor
contracts entered into by parties involved in construction in the Land, Inc.,59 we rejected the argument that the jurisdiction of
Philippines, whether the dispute arises before or after the CIAC is limited to the construction industry, and thus, cannot
completion of the contract, or after the abandonment or breach extend to surety contracts. In that case, we declared that
thereof. These disputes may involve government or private "although not the construction contract itself, the performance
contracts. For the Board to acquire jurisdiction, the parties to a bond is deemed as an associate of the main construction
dispute must agree to submit the same to voluntary arbitration. contract that it cannot be separated or severed from its
principal. The Performance Bond is significantly and
substantially connected to the construction contract that there
The jurisdiction of the CIAC may include but is not limited to
can be no doubt it is the CIAC, under Section 4 of E.O. No. 1008,
violation of specifications for materials and workmanship,
which has jurisdiction over any dispute arising from or
violation of the terms of agreement, interpretation and/or
connected with it."60
application of contractual time and delays, maintenance and
defects, payment, default of employer or contractor, and
changes in contract cost. In view of the foregoing, we agree with the petitioner that
juriisdiction over the instant case lies with the CIAC, and not
with the RTC. Thus, the Complaint filed by respondent-spouses
Excluded from the coverage of the law are disputes arising from
with the RTC must be dismissed.
employer-employee relationships which shall continue to be
covered by the Labor Code of the Philippines.
79
WHEREFORE, the petition is hereby GRANTED. The Decision and 2) that the cause of action of the third party plaintiff ha[d]
dated June 7, 2007 and the Resolution dated September 7, 2007 already prescribed.
of the Court of Appeals in CA-G.R. SP No. 96815 are hereby
ANNULLED and SET ASIDE. The Presiding Judge of the Regional On September 16, 1991, the trial court issued an order
Trial Court of Quezon City, Branch 217 1s DIRECTED to dismiss dismissing the third party complaint. Defendant-third party
Civil Case No. Q-01-45573 for lack of jurisdiction.SO ORDERED. plaintiffs motion for reconsideration of this order was
subsequently denied.[3]
FIRST DIVISION[G.R. No. 123871. August 31, 1998]
Respondent Courts Ruling

ALLIED BANKING CORPORATION, petitioner, vs. COURT OF


APPEALS and BANK OF THE PHILIPPINE ISLANDS, Respondent Court affirmed the trial court thus:
INC., respondents.

x x x Appellants submission that the cause of action of the third


DECISION party plaintiff against the third party defendant accrued only
when the complaint in the original case was filed on March 17,
PANGANIBAN, J.: 1981 is untenable. As earlier discussed, the defendant has a
separate cause of action (in respect of plaintiffs complaint)
against a third party in the original and principal
As a general rule, a trial court that has established
case. Reviewing the third-party complaint below, that cause of
jurisdiction over the main action also acquires jurisdiction over a
action is the supposed erroneous endorsement made by
third-party complaint, even if it could not have done so had the
COMTRUST for which ALLIED BANK is being held liable for
latter been filed as an independent action. This rule, however,
damages by the payee-appellee. Without COMTRUSTs warranties
does not apply to banks that have agreed to submit their
as a general endorser, ALLIED BANK allegedly would not have
disputes over check clearings to arbitration under the rules of
paid on the checks. Should such warranties prove to be false
the Philippine Clearing House Corporation. In that event, primary
and inaccurate, COMTRUST may be held liable for any damage
recourse should be to the PCHC Arbitration Committee, without
arising out of the falsity of its representation.
prejudice to an appeal to the trial courts. In other words, without
first resorting to the PCHC, the third-party complaint would be
premature. Based on the records the subject endorsement of COMTRUST
was made in August 1980[;] and in the same period, ALLIED
The Case BANK paid on the subject checks. From that moment, ALLIED
BANK could have instituted an action against COMTRUST. It is
the legal possibility of bringing the action which determines the
Before us is a petition for review on certiorari under Rule starting point for the computation of the period (Tolentino, Civil
45, assailing the Decision dated February 12, 1996 promulgated Code of the Philippines, Vol. IV, p. 41, citing Manresa). This is the
by the Court of Appeals[1] in CA-GR CV No. 44804; which moment when a cause of action may be deemed to
affirmed the trial courts Order dated September 16, 1991, accrue. Thus, considering that the third party complaint was
dismissing petitioners third-party complaint against private filed more than ten years from August 1980, specifically on
respondent.[2] January 10, 1991, the same can no longer be entertained.

Facts of the Case


Even granting arguendo that the lower court had jurisdiction
over the third party complaint and the cause of action thereof
The facts are undisputed. Reproduced hereunder is had not yet prescribed, the filing of the third party complaint
Respondent Courts narration: should nevertheless be disallowed considering that defendant
has already presented several witnesses and is about ready to
rest its case because, then, the allowance of the third party
Hyatt Terraces Baguio issued two crossed checks drawn against complaint would only delay the resolution of the original
Allied Banking Corp. (hereinafter, ALLIED) in favor of appellee case. (Firestone Tire and Rubber Co. of the Phil. vs.
Meszellen Commodities Services, Inc. (hereinafter, Tempengko, supra, p. 423).
MESZELLEN). Said checks were deposited on August 5, 1980 and
August 18, 1980, respectively, with the now defunct Commercial
Bank and Trust Company (hereinafter, COMTRUST). Upon receipt A final word. We have noted the curious situation here where,
of the above checks, COMTRUST stamped at the back thereof instead of the payee suing its bank, i.e., the collecting bank
the warranty All prior endorsements and/or lack of (which is COMTRUST), it opted to sue the drawee bank (ALLIED
endorsements guaranteed. After the checks were cleared BANK). It is, however, up to the trial court to rule on the
through the Philippine Clearing House Corporation (hereinafter, propriety of the latter complaint.[4]
PCHC), ALLIED BANK paid the proceeds of said checks to
COMTRUST as the collecting bank. Not satisfied with the above ruling, petitioner filed the
present petition before this Court.[5]
On March 17, 1981, the payee, MESZELLEN, sued the drawee,
ALLIED BANK, for damages which it allegedly suffered when the The Issues

value[s] of the checks were paid not to it but to some other


person.
Petitioner raises the following issues:[6]

Almost ten years later, or on January 10, 1991, before defendant


I. The Respondent Honorable Court of Appeals erred in holding
ALLIED BANK could finish presenting its evidence, it filed a third
that the cause of action of the third-party complaint ha[d]
party complaint against Bank of the Philippine Islands
already prescribed.
(hereinafter, BPI, appellee herein) as successor-in-interest of
COMTRUST, for reimbursement in the event that it would be
adjudged liable in the main case to pay plaintiff, II. The Respondent Honorable Court of Appeals erred in holding
MESZELLEN. The third party complaint was admitted [in] an that the filing of the third party complaint should be disallowed
Order dated May 16, 1991 issued by the Regional Trial Court of as it would only delay the resolution of the case.
Pasig, Branch 162. On July 16, 1991, BPI filed a motion to
dismiss said third party complaint grounded on the following: 1) On the other hand, private respondent argues that the trial
that the court ha[d] no jurisdiction over the nature of the action; court had no authority to admit a third-party claim that was filed
by one bank against another and involved a check cleared
80
through the Philippine Clearing House Corporation (PCHC). To concerned in its operations in effect amounts to a manifestation
the mind of the Court, this is the critical issue. of agreement by the parties to abide by its rules and
regulations. As a consequence of such participation, a party
The Courts Ruling cannot invoke the jurisdiction of the courts over disputes and
controversies which fall under the PCHC Rules and Regulations
without first going through the arbitration processes laid out by
The petition is bereft of merit. the body. Since claims relating to the regularity of checks
cleared by banking institutions are among those claims which
Critical Issue: Mandatory Recourse to PCHC should first be submitted for resolution by the PCHCs Arbitration
Committee, petitioner Associated Bank, having voluntarily
bound itself to abide by such rules and regulations, is estopped
To buttress its claim, private respondent contends that
from seeking relief from the Regional Trial Court on the coattails
petitioners remedy rests with the PCHC, of which both Allied and
of a private claim and in the guise of a third party complaint
BPI are members, in consonance with the Clearing House Rules
without first having obtained a decision adverse to its claim
and Regulations which, in part, states:
from the said body. It cannot bypass the arbitration process on
the basis of its averment that its third party complaint is
Sec. 38 - Arbitration inextricably linked to the original complaint in the Regional Trial
Court.
Any dispute or controversy between two or more clearing
participants involving any check/item cleared thru PCHC shall be xxxxxxxxx
submitted to the Arbitration Committee, upon written complaint
of any involved participant by filing the same with the PCHC
Clearly therefore, petitioner Associated Bank, by its voluntary
serving the same upon the other party or parties, who shall
participation and its consent to the arbitration rules cannot go
within fifteen (15) days after receipt thereof file with the
directly to the Regional Trial Court when it finds it convenient to
Arbitration Committee its written answer to such written
do so. The jurisdiction of the PCHC under the rules and
complaint and also within the same period serve the same upon
regulations is clear, undeniable and is particularly applicable to
the complaining participant, xxx.
all the parties in the third party complaint under their obligation
to first seek redress of their disputes and grievances [from] the
Private respondent cites Banco de Oro Savings and PCHC before going to the trial court.
Mortgage Bank v. Equitable Banking
Corporation[7] andAssociated Bank v. Court of Appeals,[8] which
Finally, the contention that the third party complaint should not
upheld the right of the PCHC to settle and adjudicate disputes
have been dismissed for being a necessary and inseparable
between member banks. In Banco de Oro, the Court ruled:
offshoot of the main case over which the court a quo had
already exercised jurisdiction misses the fundamental point
The participation of the two banks, petitioner and private about such pleading. A third party complaint is a mere
respondent, in the clearing operations of PCHC is a procedural device which under the Rules of Court is allowed only
manifestation of their submission to its jurisdiction. Secs. 3 and with the courts permission. It is an action actually independent
36.6 of the PCHC-CHRR clearing rules and regulations provide: of, separate and distinct from the plaintiffs complaint (s)uch
that, were it not for the Rules of Court, it would be necessary to
Sec. 3. AGREEMENT TO THESE RULES. - It is the general file the action separately from the original complaint by the
agreement and understanding that any participant in the defendant against the third party. (Italics supplied.)
Philippine Clearing House Corporation, MICR clearing
operations[,] by the mere fact of their participation, thereby Banco de Oro and Associated Bank are clear and
manifests its agreement to these Rules and Regulations and its unequivocal: a third-party complaint of one bank against
subsequent amendments. another involving a check cleared through the PCHC is
unavailing, unless the third-party claimant has first exhausted
Sec. 36.6. (ARBITRATION) - The fact that a bank participates in the arbitral authority of the PCHC Arbitration Committee and
the clearing operations of the PCHC shall be deemed its written obtained a decision from said body adverse to its claim.
and subscribed consent to the binding effect of this arbitration
agreement as if it had done so in accordance with section 4 of Recognizing the role of the PCHC in the arbitration of
(the) Republic Act. No. 876, otherwise known as the Arbitration disputes between participating banks, the Court in Associated
Law. Bank further held: Pursuant to its function involving the clearing
of checks and other clearing items, the PCHC has adopted rules
Further[,] Section 2 of the Arbitration Law mandates: and regulations designed to provide member banks with a
procedure whereby disputes involving the clearance of checks
and other negotiable instruments undergo a process of
Two or more persons or parties may submit to the arbitration of arbitration prior to submission to the courts below. This
one or more arbitrators any controversy existing between them procedure not only ensures a uniformity of rulings relating to
at the time of the submission and which may be the subject of factual disputes involving checks and other negotiable
any action, or the parties of any contract may in such contract instruments but also provides a mechanism for settling minor
agree to settle by arbitration a controversy thereafter arising disputes among participating and member banks which would
between them. Such submission or contract shall be valid and otherwise go directly to the trial courts.
irrevocable, save upon grounds as exist at law for the revocation
of any contract.
We defer to the primary authority of PCHC over the present
dispute, because its technical expertise in this field enables it to
Such submission or contract may include question arising out of better resolve questions of this nature. This is not prejudicial to
valuations, appraisals or other controversies which may be the interest of any party, since primary recourse to the PCHC
collateral, incidental, precedent or subsequent to any issue does not preclude an appeal to the regional trial courts on
between the parties. (Italics supplied.) questions of law. Section 13 of the PCHC Rules reads:

Associated Bank also disallowed a similar third-party Sec. 13. The findings of facts of the decision or award rendered
complaint, ruling thus: by the Arbitration Committee or by the sole Arbitrator as the
case may be shall be final and conclusive upon all the parties in
Under the rules and regulations of the Philippine Clearing House said arbitration dispute. The decision or award of the Arbitration
Corporation (PCHC), the mere act of participation of the parties Committee or of the Sole Arbitrator shall be appealable only on
81
questions of law to any of the Regional Trial Courts in the on October 18, 1991 as "Drawn Against Insufficient Funds."
National Capital Judicial Region where the Head Office of any of HBSTC received the notice of dishonor on October 21, 1991 but
the parties is located. The appellant shall perfect his appeal by refused to accept the checks and on October 22, 1991, returned
filing a notice of appeal to the Arbitration Secretariat and filing a them to FEBTC through the PCHC for the reason "Beyond
Petition with the Regional Trial Court of the National Capital Reglementary Period," implying that HBSTC already treated the
Region xxx. three (3) FEBTC checks as cleared and allowed the proceeds
thereof to be withdrawn. 4 FEBTC demanded reimbursement for
the returned checks and inquired from HBSTC whether it had
Furthermore, when the error is so patent, gross and
permitted any withdrawal of funds against the unfunded checks
prejudicial as to constitute grave abuse of discretion, courts may
and if so, on what date. HBSTC, however, refused to make any
address questions of fact already decided by the arbitrator.[9]
reimbursement and to provide FEBTC with the needed
information.
We are not unaware of the rule that a trial court, which has
jurisdiction over the main action, also has jurisdiction over the
Thus, on December 12, 1991, FEBTC submitted the dispute for
third party complaint, even if the said court would have had no
arbitration before the PCHC Arbitration Committee, 5 under the
jurisdiction over it had it been filed as an independent action.
[10] PCHC's Supplementary Rules on Regional Clearing to which
However, this doctrine does not apply in the case of banks,
FEBTC and HBSTC are bound as participants in the regional
which have given written and subscribed consentto arbitration
clearing operations administered by the PCHC. 6
under the auspices of the PCHC.

On January 17, 1992, while the arbitration proceeding was still


By participating in the clearing operations of the PCHC,
pending, FEBTC filed an action for sum of money and damages
petitioner agreed to submit disputes of this nature to
with preliminary
arbitration. Accordingly, it cannot invoke the jurisdiction of the
attachment 7 against HBSTC, Robert Young, Victor Tancuan and
trial courts without a prior recourse to the PCHC Arbitration
Eugene Arriesgado with the Regional Trial Court of Makati,
Committee. Having given its free and voluntary consent to the
Branch 133. A motion to dismiss was filed by HBSTC claiming
arbitration clause, petitioner cannot unilaterally take it back
that the complaint stated no cause of action and accordingly
according to its whim. In the world of commerce, especially in
". . . should be dismissed because it seeks to enforce an arbitral
the field of banking, the promised word is crucial. Once given, it
award which as yet does not exist." 8 The trial court issued an
may no longer be broken.
omnibus order dated April 30, 1992 denying the motion to
dismiss and an order dated October 1, 1992 denying the motion
Upon the other hand, arbitration as an alternative method for reconsideration.
of dispute-resolution is encouraged by this Court. Aside from
unclogging judicial dockets, it also hastens solutions especially
On December 16, 1992, HBSTC filed a petition for certiorari with
of commercial disputes.
the respondent Court of Appeals contending that the trial court
acted with grave abuse of discretion amounting to lack of
In view of the foregoing, a discussion of the issues raised jurisdiction in denying the motion to dismiss filed by HBSTC.
by the petitioners is unnecessary.

In a Decision 9 dated January 21, 1994, the respondent court


WHEREFORE, the petition is DENIED for lack of dismissed the petition for lack of merit and held that "FEBTC can
merit. Costs against petitioner.SO ORDERED. reiterate its cause of action before the courts which it had
already raised in the arbitration case" 10 after finding that the
SECOND DIVISIONG.R. No. 115412 November 19, 1999 complaint filed by FEBTC ". . . seeks to collect a sum of money
from HBT [HBSTC] and not to enforce or confirm an arbitral
award." 11 The respondent court observed that "[i]n the
HOME BANKERS SAVINGS AND TRUST Complaint, FEBTC applied for the issuance of a writ of
COMPANY, petitioner, preliminary attachment over HBT's [HBSTC] property" 12 and
vs.
citing section 14 of Republic Act No. 876, otherwise known as
COURT OF APPEALS and FAR EAST BANK & TRUST CO., the Arbitration Law, maintained that "[n]ecessarily, it has to
INC. respondents. reiterate its main cause of action for sum of money against HBT
[HBSTC]," 13 and that "[t]his prayer for conservatory relief [writ
BUENA, J.: of preliminary attachment] satisfies the requirement of a cause
of action which FEBTC may pursue in the courts." 14
This appeal by certiorari under Rule 45 of the Rules of Court
seeks to annul and set aside the decision 1 of the Court of Furthermore, the respondent court ruled that based on section 7
Appeals 2 dated January 21, 1994 in CA-G.R. SP No. 29725, of the Arbitration Law and the cases of National Union Fire
dismissing the petition for certiorari filed by petitioner to annul Insurance Company of Pittsburg vs. Stolt-Nielsen Philippines,
the two (2) orders issued by the Regional Trial Court of Inc., 15 and Bengson vs. Chan, 16 ". . . when there is a condition
Makati 3 in Civil Case No. 92-145, the first, dated April 30, 1992, requiring prior submission to arbitration before the institution of
denying petitioner's motion to dismiss and the second, dated a court action, the complaint is not to be dismissed but should
October 1, 1992 denying petitioner's motion for reconsideration be suspended for arbitration." 17 Finding no merit in HBSTC's
thereof. contention that section 7 of the Arbitration Law ". . .
contemplates a situation in which a party to an arbitration
agreement has filed a court action without first resorting to
The pertinent facts may be briefly stated as follows: Victor
arbitration, while in the case at bar, FEBTC has initiated
Tancuan, one of the defendants in Civil Case No. 92-145, issued
arbitration proceedings before filing a court action," the
Home Bankers Savings and Trust Company (HBSTC) check No.
respondent court held that ". . . if the absence of a prior
193498 for P25,250,000.00 while Eugene Arriesgado issued Far
arbitration may stay court action, so too and with more reason,
East Bank and Trust Company (FEBTC) check Nos. 464264,
should an arbitration already pending as obtains in this case
464272 and 464271 for P8,600,000.00, P8,500,000.00 and
stay the court action. A party to a pending arbitral proceeding
P8,100,000.00, respectively, the three checks amounting to
may go to court to obtain conservatory reliefs in connection with
P25,200,000.00. Tancuan and Arriesgado exchanged each
his cause of action although the disposal of that action on the
other's checks and deposited them with their respective banks
merits cannot as yet be obtained." 18 The respondent court
for collection. When FEBTC presented Tancuan's HBSTC check for
discarded Puromines, Inc. vs. Court of Appeals, 19 stating that ". .
clearing, HBSTC dishonored it for being "Drawn Against
. perhaps Puromines may have been decided on a different
Insufficient Funds." On October 15, 1991, HBSTC sent
factual basis." 20
Arriesgado's three (3) FEBTC checks through the Philippine
Clearing House Corporation (PCHC) to FEBTC but was returned
82
In the instant petition, 21 petitioner contends that first, "no party WHETHER OR NOT PRIVATE RESPONDENT WHICH COMMENCED
litigant can file a non-existent complaint," 22 arguing that ". . . AN ARBITRATION PROCEEDING UNDER THE AUSPICES OF THE
one cannot file a complaint in court over a subject that is PHILIPPINE CLEARING HOUSE CORPORATION (PCHC) MAY
undergoing arbitration." 23 Second, petitioner submits that SUBSEQUENTLY FILE A SEPARATE CASE IN COURT OVER THE
"[s]ince arbitration is a special proceeding by a clear provision of SAME SUBJECT MATTER OF ARBITRATION DESPITE THE
law, 24 the civil suit filed below is, without a shadow of doubt, PENDENCY OF THAT ARBITRATION, SIMPLY TO OBTAIN THE
barred by litis pendentia and should be dismissed de PROVISIONAL REMEDY OF ATTACHMENT AGAINST THE BANK THE
plano insofar as HBSTC is concerned." 25 Third, petitioner insists ADVERSE PARTY IN THE ARBITRATION PROCEEDING. 42
that "[w]hen arbitration is agreed upon and suit is filed without
arbitration having been held and terminated, the case that is We find no merit in the petition. Section 14 of Republic Act 876,
filed should be dismissed," 26 citing Associated Bank vs. Court of otherwise known as the Arbitration Law, allows any party to the
Appeals, 27 Puromines, Inc. vs. Court of Appeals, 28 as arbitration proceeding to petition the court to take measures to
and Ledesma vs. Court of Appeals. 29 Petitioner demurs that safeguard and/or conserve any matter which is the subject of
the Puromines ruling was deliberately not followed by the the dispute in arbitration, thus:
respondent court which claimed that:

Sec. 14. Subpoena and subpoena duces tecum.


xxx xxx xxx Arbitrators shall have the power to require any person to attend
a hearing as a witness. They shall have the power to subpoena
It would really be much easier for Us to rule to witnesses and documents when the relevancy of the testimony
dismiss the complaint as the petitioner here and the materiality thereof has been demonstrated to the
seeks to do, following Puromines. But with arbitrators. Arbitrators may also require the retirement of any
utmost deference to the Honorable Supreme witness during the testimony of any other witness. All of the
Court, perhaps Puromines may have been arbitrators appointed in any controversy must attend all the
decided on a different factual basis. hearings in that matter and hear all the allegations and proofs of
the parties; but an award by the majority of them is valid unless
30 the concurrence of all of them is expressly required in the
xxx xxx xxx
submission or contract to arbitrate. The arbitrator or arbitrators
shall have the power at any time, before rendering the award,
Petitioner takes exception to FEBTC's contention without prejudice to the rights of any party to petition the court
that Puromines cannot modify or reverse the rulings to take measures to safeguard and/or conserve any matter
in National Union Fire Insurance Company of Pittsburg which is the subject of the dispute in arbitration. (emphasis
vs. Stolt-Nielsen Philippines, Inc., 31 and Bengson supplied)
vs. Chan, 32 where this Court suspended the action filed
pending arbitration, and argues that "[s]ound policy
Petitioner's exposition of the foregoing provision deserves scant
requires that the conclusion of whether a Supreme
consideration. Section 14 simply grants an arbitrator the power
Court decision has or has not reversed or modified [a]
to issue subpoena and subpoena duces tecum at any time
previous doctrine, should be left to the Supreme Court
before rendering the award. The exercise of such power is
itself; until then, the latest pronouncement should
without prejudice to the right of a party to file a petition in court
prevail." 33 Fourth, petitioner alleges that the writ of
to safeguard any matter which is the subject of the dispute in
preliminary attachment issued by the trial court is void
arbitration. In the case at bar, private respondent filed an action
considering that the case filed before it "is a separate
for a sum of money with prayer for a writ of preliminary
action which cannot exist," 34 and ". . . there is even no
attachment. Undoubtedly, such action involved the same
need for the attachment as far as HBSTC is concerned
subject matter as that in arbitration, i.e., the sum of
because such automatic debit/credit procedure 35 may
P25,200,000.00 which was allegedly deprived from private
be regarded as a security for the transactions involved
respondent in what is known in banking as a "kiting scheme."
and, as jurisprudence confirms, one requirement in the
However, the civil action was not a simple case of a money
issuance of an attachment [writ of preliminary
claim since private respondent has included a prayer for a writ
attachment] is that the debtor has no sufficient
of preliminary attachment, which is sanctioned by section 14 of
security." 36 Petitioner asserts further that a writ of
the Arbitration Law.
preliminary attachment is unwarranted because no
ground exists for its issuance. According to petitioner,
". . . the only allegations against it [HBSTC] are that it Petitioner cites the cases of Associated Bank vs. Court of
refused to refund the amounts of the checks of FEBTC Appeals, 43 Puromines, Inc. vs. Court of Appeals, 44 and Ledesma
and that it knew about the fraud perpetrated by the vs. Court of Appeals 45 in contending that "[w]hen arbitration is
other defendants," 37 which, at best, constitute only agreed upon and suit is filed without arbitration having been
"incidental fraud" and not causal fraud which justifies held and terminated, the case that is filed should be
the issuance of the writ of preliminary attachment. dismissed." 46 However, the said cases are not in point.
In Associated Bank, we affirmed the dismissal of the third-party
complaint filed by Associated Bank against Philippine
Private respondent FEBTC, on the other hand, contends that ". . .
Commercial International Bank, Far East Bank & Trust Company,
the cause of action for collection [of a sum of money] can
Security Bank and Trust Company, and Citytrust Banking
coexist in the civil suit and the arbitration [proceeding]" 38 citing
Corporation for lack of jurisdiction, it being shown that the said
section 7 of the Arbitration Law which provides for the stay of
parties were bound by the Clearing House Rules and Regulations
the civil action until an arbitration has been had in accordance
on Arbitration of the Philippine Clearing House Corporation.
with the terms of the agreement providing for arbitration.
In Associated Bank, we declared that:
Private respondent further asserts that following section 4(3),
article VIII 39 of the 1987 Constitution, the subsequent case
of Puromines does not overturn the ruling in the earlier cases . . . . . .. Under the rules and regulations of the Philippine
of National Union Fire Insurance Company of Pittsburg vs. Stolt- Clearing House Corporation (PCHC), the mere act of
Nielsen Philippines, Inc., 40 and Bengson vs. Chan, 41 hence, participation of the parties concerned in its operations in
private respondent concludes that the prevailing doctrine is that effect amounts to a manifestation of agreement by the
the civil action must be stayed rather than dismissed pending parties to abide by its rules and regulations. As a
arbitration. consequence of such participation, a party cannot invoke
the jurisdiction of the courts over disputes and
controversies which fall under the PCHC Rules and
In this petition, the lone issue presented for the consideration of
Regulations without first going through the arbitration
this Court is:
processes laid out by the body. 47 (emphasis supplied)
83
And thus we concluded: been or is being committed and that it is necessary to look into
the deposit to establish such fraud or irregularity,
Clearly therefore, petitioner Associated Bank, by its
voluntary participation and its consent to the arbitration (2) In an examination made by an independent auditor
rules cannot go directly to the Regional Trial Court when it hired by the bank to conduct its regular audit provided that the
finds it convenient to do so. The jurisdiction of the PCHC examination is for audit purposes only and the results thereof
under the rules and regulations is clear, undeniable and is shall be for the exclusive use of the bank,
particularly applicable to all the parties in the third party
complaint under their obligation to first seek redress of their (3) Upon written permission of the depositor,
disputes and grievances with the PCHC before going to the
trial court. 48 (emphasis supplied)
(4) In cases of impeachment,

Simply put, participants in the regional clearing operations of


the Philippine Clearing House Corporation cannot bypass the (5) Upon order of a competent court in cases of bribery or
arbitration process laid out by the body and seek relief directly dereliction of duty of public officials, or
from the courts. In the case at bar, undeniably, private
respondent has initiated arbitration proceedings as required by (6) In cases where the money deposited or invested in the
the PCHC rules and regulations, and pending arbitration has subject matter of the litigation.
sought relief from the trial court for measures to safeguard
and/or conserve the subject of the dispute under arbitration, as
Whether or not the case at bar falls under the last
sanctioned by section 14 of the Arbitration Law, and otherwise
exception is the issue in the instant petition.
not shown to be contrary to the PCHC rules and regulations.

The facts are not disputed.


Likewise, in the case of Puromines, Inc. vs. Court of
Appeals, 49 we have ruled that:
On March 21, 1990, a check (Check No. 11669677) dated
March 31, 1990 in the amount of One Million Pesos
In any case, whether the liability of respondent should be
(P1,000,000.00) was drawn against Account No. 0111-01854-8
based on the sales contract or that of the bill of lading,
with private respondent Allied Bank payable to the order of one
the parties are nevertheless obligated to respect the
Jose Ch. Alvarez. The payee deposited the check with petitioner
arbitration provisions on the sales contract and/or bill of
Union Bank who credited the P1,000,000.00 to the account of
lading. Petitioner being a signatory and party to the sales
Mr. Alvarez. On May 21, 1990, petitioner sent the check for
contract cannot escape from his obligation under the
clearing through the Philippine Clearing House Corporation
arbitration clause as stated therein.
(PCHC). When the check was presented for payment, a clearing
discrepancy was committed by Union Banks clearing staff when
In Puromines, we found the arbitration clause stated in the amount of One Million Pesos (P1,000,000.00) was
the sales contract to be valid and applicable, thus, we erroneously under-encoded to One Thousand Pesos (P1,000.00)
ruled that the parties, being signatories to the sales only.
contract, are obligated to respect the arbitration
provisions on the contract and cannot escape from
Petitioner only discovered the under-encoding almost a
such obligation by filing an action for breach of contract
year later. Thus, on May 7, 1991, Union Bank Notified Allied
in court without resorting first to arbitration, as agreed
Bank of the discrepancy by way of a charge slip for Nine
upon by the parties.
Hundred Ninety-Nine Thousand Pesos (P999,000.00) for
automatic debiting against the account of Allied Bank. The
At this point, we emphasize that arbitration, as an alternative latter, however, refused to accept the charge slip since [the]
method of dispute resolution, is encouraged by this Court. Aside transaction was completed per your [Union Banks] original
from unclogging judicial dockets, it also hastens solutions instruction and clients account is now insufficiently funded.
especially of commercial disputes. 50 The Court looks with favor
upon such amicable arrangement and will only interfere with
Subsequently, Union Bank filed a complaint against Allied
great reluctance to anticipate or nullify the action of the
Bank before the PCHC Arbitration Committee (Arbicom), praying
arbitrator. 51
that:

WHEREFORE, premises considered, the petition is hereby


judgment be rendered in favor of plaintiff against defendant
DISMISSED and the decision of the court a quo is AFFIRMED.SO
sentencing it to pay plaintiff:
ORDERED.

1. The sum of NINE HUNDRED NINETY-NINE THOUSAND PESOS


FIRST DIVISION[G.R. No. 134699. December 23, 1999]
(P999,000.00);

UNION BANK OF THE PHILIPPINES, petitioner, vs. COURT


2. The sum of THREE HUNDRED SIXTY-ONE AND FOUR HUNDRED
OF APPEALS and ALLIED BANK
EIGHTY AND 20/XX P361,480.20 as of October 9, 1991
CORPORATION, respondents.
representing reimbursements for opportunity losses and interest
at the rate of 24% per annum arising from actual losses
DECISION sustained by plaintiff as of May 21, 1990;

KAPUNAN, J.: 3. The amount for attorneys fees at the rate of 25% of any and
all sums due;
Section 2 of the Law on Secrecy of Bank Deposits, [1] as
amended, declares bank deposits to be absolutely confidential 4. Penalty Charges at the rate of 1/8 of 1% of P999,000.00 from
except: May 22, 1990 until payment thereof.

(1) In an examination made in the course of a special or 5. Exemplary and punitive damages against the defendant in
general examination of a bank that is specifically authorized by such amounts as may be awarded by this Tribunal in order to
the Monetary Board after being satisfied that there is reasonable serve a lesson to all member-Banks under the PCHC umbrella to
ground to believe that a bank fraud or serious irregularity has striclty comply with the provisions thereof;
84
6. The costs of suit which includes filing fee in addition to result of its own employees admitted error in encoding the
litigation expenses which shall be proven in the course of check.
arbitration.
The money depositied in Account No. 0111-018548 is not the
7. Such other damages thay may be awarded by this Tribunal.[2] subject matter of the litigation in the Arbicom case for as clearly
stated by petitioner itself, it is the alleged violation by
respondent of the rules and regulations of the PCHC.[4]
Thereafter, Union Bank filed in the Regional Trial court
(RTC) of Makati a petition for the examination of Account No.
111-01854-8. Judgment on the arbitration case was held in Union Bank is now before this Court insisting that the
abeyance pending the resolution of said petition. money deposited in Account No. 0111-01854-8 is the subject
matter of the litigation Petitioner cites the case of Mathay vs.
Consolidated Bank and Trust Company,[5] where we defined
Upon motion of private respondent, the RTC dismissed
subject matter of the action, thus:
Union Banks petition. The RTC held that:

xxx By the phrase subject matter of the action is meant the


The case of the herein petitioner does not fall under any of the
physical facts, the things real or personal, the money, lands,
foregoing exceptions to warrant a disclosure of or inquiry into
chattels, and the like, in relation to which the suit is prosecuted,
the ledgers/books of account of Allied Checking Account No.
and not the delict or wrong committed by the defendant.
111-01854-8. Needless to say, the complaint filed by herein
petitioner against Allied Banking Corporation before the
Philippine Clearing House Corporation (PCHC) Arbitration Petitioner contends that the Court of Appeals confuses the cause
Committee and docketed therein as Arb[i]com Case No. 91-068 of action with the subject of the action. In Yusingco vs. Ong Hing
(Annex A, petition) is not one for bribery or dereliction of duty of Lian,[6] petitioner points out, this Court distinguished the two
public officials much less is there any showing that the subject concepts.
matter thereof is the money deposited in the account in
question. Petitioners complaint primarily hing[e]s on the alleged xxx The cause of action is the legal wrong threatened or
deliberate violation by Allied Bank Corporation of the provisions committed, while the object of the action is to prevent or
of the PCHC Rule Book, Sec. 25[.]3, and as principal reliefs, it redress the wrong by obtaining some legal relief; but the subject
seeks for [sic] the recovery of amounts of money as a of the action is neither of these since it is not the wrong or the
consequence of an alleged under-coding of check amount to relief demanded, the subject of the action is the matter or thing
P1,000,000.00 and damage[s] by way of loss of interest income.
[3]
with respect to which the controversy has arisen, concerning
which the wrong has been done, and this ordinarily is the
property, or the contract and its subject matter, or the thing in
The Court of Appeals affirmed the dismissal of the petition, dispute.
ruling that the case was not one where the money deposited is
the subject matter of the litigation. The argument is well taken. We note with approval the
difference between the subject of the action from the cause of
Petitioner collecting bank itself in its complaint filed before the action. We also find petitioners definition of the phrase subject
PCHC, Arbicom Case No. 91-068, clearly stated that its cause of matter of the action is consistent with the term subject matter
action against defendant arose from defendants deliberate of the litigation, as the latter is used in the Bank Deposits
violation of the provisions of the PCHC Rule Book, Sec. 25.3, Secrecy Act.
specifically on Under-Encoding of check amouting to
P1,000,000.00 drawn upon defendants Tondo Branch which was In Mellon Bank, N.A. vs. Magsino,[7] where the petitioner
deposited with plaintiff herein on May 20, 1990, xxx which was bank inadvertently caused the transfer of the amount of
erroneously encoded at P1,000.00 which defendant as the US$1,000,000.00 instead of only US$1,000.00, the Court
receiving bank thereof, never called nor notified the plaintiff of sanctioned the examination of the bank accounts where part of
the error committed thus causing actual losses to plaintiff in the the money was subsequently caused to be deposited:
principal amount of P999,000.00 exclusive of opportunity losses
and interest.
Section 2 of [Republic Act No. 1405] allows the disclosure of
bank deposits in cases where the money deposited is the
Furthermore, a reading of petitioner collecting banks complaint subject matter of the litigation. Inasmuch as Civil Case No.
in the Arbicom case shows that its thrust is directed against 26899 is aimed at recovering the amount converted by the
respondent drawee banks alleged failure to inform the former of Javiers for their own benefit, necessarily, an inquiry into the
the under-encoding when Sec. 25.3 of the PCHC Rule Book is wherabouts of the illegally acquired amount extends to
clear that it is receiving banks (respondent drawee bank herein) whatever is concealed by being held or recorded in the name of
duty and obligation to notify the erring bank (petitioner persons other than the one responsible for the illegal
collecting bank herein) of any such under-encoding of any check acquisition.
amount submitted for clearing within the member banks of the
PCHC not later than 10:00 a.m. of the following clearing day and
prays that respondent drawee bank be held liable to petitioner Clearly, Mellon Bank involved a case where the money
collecting bank for penalties in view of the latters violation of deposited was the subject matter of the litigation since the
the notification requirement. money so deposited was the very thing in dispute. This,
however, is not the case here.

Prescinding from the above, we see no cogent reason to depart


from the time-honored general banking rule that all deposits of Petitioners theory is that private respondent Allied Bank
whatever nature with banks are considered of absolutely should have informed petitioner of the under-encoding pursuant
confidential nature and may not be examined, inquired or looked to the provisions of Section 25.3.1 of the PCHC Handbook, which
into by any person, government official, bureau or office and states:
corollarily, that it is unlawful for any official or employee of a
bank to disclose to any person any information concerning 25.3.1. The Receiving Bank should inform the erring Bank about
deposits. the under-encoding of amount not later than 10:00 A.M. of the
following clearing day.
Nowhere in petitioner collecting banks complaint filed before the
PCHC does it mention of the amount it seeks to recover from Failing in that duty, petitioner holds private
Account No. 0111-018548 itself, but speaks of P999,000.00 only respondent directly liable for the P999,000.00 and other
as an incident of its alleged opportunity losses and interest as a
85
damages. It does not appear that petitioner is seeking Since the provisions of the PCHC Rule Book has so imposed upon
reimbursement from the account of the drawer. This much is the defendant being the Receiving Bank of a discrepant check
evident in petitioners complaint before the Arbicom. item to give that timely notification and defendant failing to
comply with such requirement, then it can be said that
defendant is guilty of negligence. He who is guilty of negligence
xxx plaintiffs cause of action against defendant arose from
in the performance of its [sic] duty is liable for damages. (Art.
defendants deliberate violation of the provisions of the PCHC
1170, New Civil Code.)
Rule Book, Sec. 25.3, specifically on Under-Encoding of check
amounting to P1,000,000.00 drawn upon defendants Tondo
Branch which was deposited with plaintiff herein sometime on Art. 1172 of the Civil Code provides that:
May 20, 1990. From the check amount of P1,000,000.00, it was
instead erroneously encoded at P1,000.00 which defendant as Responsibility arising from negligence in the performance of
the receiving bank thereof, never called nor notified the plaintiff every kind of obligation is also demandable, but such liability
of the error committed thus causing actual losses to plaintiff in may be regulated by the courts, according to the circumstances.
the principal amount of P999,000.00 exclusive of opportunity [][12]
losses and interest thereon whatsoever. xxx[8]

Petitioner points to its prayer in its complaint to show that


Petitioner even requested private respondents Branch Manager it sought reimbursement from the drawers account. The prayer,
for reimbursement from private respondents account through however, does not specifically state that it was seeking recovery
the automatic debiting system. of the amount from the depositors account. Petitioner merely
asked that judgment be rendered in favor of plaintiff against
2.7. On May 6, 1991, plaintiffs Senior Vice-President, Ms. defendant sentencing it to pay plaintiff: 1. The sum of NINE
ERLINDA V. VALENTON wrote defendants Tondo Branch Manager, HUNDRED NINETY-NINE THOUSAND PESOS (P999,000.00).[13]
Mr. RODOLFO JOSE on the incident and requested assistance in
facilitating correction of the erroneous coding with request for On the other hand, the petition before this court reveals
reimbursement thru the industrys automatic debiting of that the true purpose for the examination is to aid petitioner in
defendants account.[9] proving the extent of Allied Banks liability:

Further, petitioner rejected private respondents proposal that Hence, the amount actually debited from the subject account
the drawer issue postdated checks in favor of petitioner since becomes very material and germane to petitioners claim for
the identity and credit standing of the depositor were unknown reimbursement as it is only upon examination of subject account
to petitioner. can it be proved that indeed a discrepancy in the amount
credited to petitioner was committed, thereby, rendering
2.9. On May 23, 1991, defendants Branch Manager, the same respondent Allied Bank liable to petitioner for the deficiency. The
Mr. Rodolfo Jose wrote plaintiffs Ms. Erlinda Valenton again money deposited in aforesaid account is undeniably the subject
insisting on the execution of the Quitclaim and Release in favor matter of the litigation since the issue in the Arbicom case is
of defendant as the Branch has endeavored to negotiate with its whether respondent Bank should be held liable to petitioner for
client for the collection of such amount. Upon a reading of the reimbursement of the amount of money constituting the
terms of the Quitclaim and Release being proposed by difference between the amount of the check and the amount
defendant, the unmistakable fact lies that again defendant credited to petitioner, that is, P999,000.00, which has remained
attempts for the second time to take advantage of plaintiffs deposited in aforesaid account.
plight by indicating that the terms of the payment of the
principal amount of P999,000.00 is by way of several personal On top of the allegations in the complaint, which can be verified
postdated checks up to March 21, 1992 from a person whose only by examining the subject bank account, the defense of
identity is not even disclosed to plaintiff. respondent Allied Bank that the reimbursement cannot be made
since clients account is not sufficiently funded at the time
To an ordinary person aggrieved already by having been taken petitioner sent its Charge Slip, bolsters petitioners contention
advantage of for 620 days more or less, the proposal of that the money in subject account is the very subject matter of
defendant could not be acceptable for the reason that aside the pending Arbicom case.
from the interest lost already for the use of its money by
another party, no assurance is made as to the actual collection Indeed, to prove the allegations in its Complaint before the
thereof from a party whose credit standing, the recipient is not PCHC Arbitration Committee, and to rebut private respondents
at all aware of.[10] defense on the matter, petitioner needs to determine:

Petitioner also believed that it had no privity with the depositor: 1. how long respondent Allied Bank had willfully or negligently
allowed the difference of P999,000.00 to be maintained in the
2.12. Plaintiff then replied to defendants letter by requesting subject account without remitting the same to petitioner;
that in lieu of the post-dated checks from defendants client with
whom plaintiff has no privity whatsoever, if the defendant could 2. whether indeed the subject account was no longer sufficiently
tender the full payment of the amount of P999,000.00 in funded when petitioner sent its charge slip for reimbursement to
defendants own Managers check and that plaintiff is willing to respondent bank on May 7, 1991; and
forego its further claims for interest and losses for a period of
620 days, more or less.[11]
3. whether or not respondent Allied Banks actuations in refusing
to immediately reimburse the discrepancy was attended by
The following argument adduced by petitioner in the good or bad faith.
Arbicom case leaves no doubt that petitioner is holding private
respondent itself liable for the discrepancy:
In other words, only a disclosure of the pertinent details and
information relating to the transactions involving subject
Defendant by its acceptance thru the clearing exchange of the account will enable petitioner to prove its allegations in the
check deposit from its client cannot be said to be free from any pending Arbicom case. xxx[14]
liability for the unpaid portion of the check amount considering
that defendant as the drawee bank, is remiss in its duty of
verifying possible technicalities on the face of the check. In short, petitioner is fishing for information so it can
determine the culpability of private respondent and the amount
of damages it can recover from the latter. It does not seek
86
recovery of the very money contained in the deposit. The denied in the second assailed order dated July
subject matter of the dispute may be the amount of 20, 1994 (Emphasis and words in bracket added).
P999,000.00 that petitioner seeks from private respondent as a
result of the latters alleged failure to inform the former of the
discrepancy; but it is not the P999,000.00 deposited in the From the order denying its motion to discharge attachment by
drawers account. By the terms of R.A. No. 1405, the money counter-bond, petitioner went to the Court of Appeals on a
deposited itself should be the subject matter of the litigation. petition for certiorari thereat docketed as CA-G.R. SP No. 34876,
ascribing on the trial court the commission of grave abuse of
discretion amounting to lack of jurisdiction.
That petitioner feels a need for such information in order to
establish its case against private respondent does not, by itself, While acknowledging that [R]espondent Judge may have erred
warrant the examination of the bank deposits. The necessity of in his Order of June 13, 1994 that the counter-bond should be in
the inquiry, or the lack thereof, is immaterial since the case the amount of P27,237,700.00, in that he erroneously factored
does not come under any of the exceptions allowed by the Bank in, in arriving at such amount, unliquidated claim items, such as
Deposits Secrecy Act. actual and exemplary damages, legal interest, attorneys fees
and expenses of litigation, the CA, in the herein
assailed decision dated October 9, 1995, nonetheless denied
WHEREFORE, the petition is DENIED. due course to and dismissed the petition. For, according to the
appellate court, the RTCs order may be defended by, among
others, the provision of Section 12 of Rule 57 of the Rules of
SO ORDERED. G.R. NO. 123638 June 15, 2005
Court, infra. The CA added that, assuming that the RTC erred on
THIRD DIVISION
the matter of computing the amount of the discharging counter-
INSULAR SAVINGS BANK,Petitioner,- versus -COURT OF
bond, its error does not amount to grave abuse of discretion.
APPEALS, JUDGE OMAR U. AMIN, in his capacity as
Presiding Judge of Branch 135 of the Regional Trial Court
With its motion for reconsideration having been similarly denied,
of Makati, and FAR EAST BANK AND TRUST COMPANY,
petitioner is now with us, faulting the appellate court, as follows:
Respondents.
I. THE COURT OF APPEALS ERRED IN NOT RULING THAT
THE PRINCIPAL AMOUNT CLAIMED BY
RESPONDENT BANK SHOULD BE THE BASIS
GARCIA, J.:
FOR COMPUTING THE AMOUNT OF THE
COUNTER-BOND, FOR THE PRELIMINARY
Thru this appeal via a petition for review on certiorari under Rule
ATTACHMENT WAS ISSUED FOR THE SAID
45 of the Rules of Court, petitioner Insular Savings
AMOUNT ONLY.
Bank seeks to set aside the decision[1] dated October 9,
1995 of the Court of Appeals in CA-G.R. SP No. 34876 and
II. THE COURT OF APPEALS ERRED IN NOT RULING THAT
its resolution dated January 24, 1996, [2] denying petitioners
THE ARGUMENT THAT THE AMOUNT OF THE
motion for reconsideration.
COUNTER-BOND SHOULD BE BASED ON THE
VALUE OF THE PROPERTY ATTACHED CANNOT
The assailed decision of October 9, 1995 cleared the Regional
BE RAISED FOR THE FIRST TIME IN THE COURT
Trial Court (RTC) at Makati, Branch 135, of committing, as
OF APPEALS.
petitioner alleged, grave abuse of discretion in denying
petitioners motion to discharge attachment by counter-bond in
III. THE COURT OF APPEALS ERRED IN RULING THAT THE
Civil Case No. 92-145, while the equally assailed resolution of
AMOUNT OF THE COUNTER-BOND SHOULD BE
January 24, 1996 denied petitioners motion for reconsideration.
BASED ON THE VALUE OF THE PROPERTY
ATTACHED EVEN IF IT WILL RESULT IN MAKING
The undisputed facts are summarized in the appellate courts
THE AMOUNT OF THE COUNTER-BOND EXCEED
decision[3] under review, as follows:
THE AMOUNT FOR WHICH PRELIMINARY
ATTACHMENT WAS ISSUED.
On December 11, 1991, respondent Bank [Far East
Bank and Trust Company] instituted Arbitration Case
Simply put, the issue is whether or not the CA erred in not ruling
No. 91-069 against petitioner [Insular Savings Bank]
that the trial court committed grave abuse of discretion in
before the Arbitration Committee of the Philippine
denying petitioners motion to discharge attachment by counter-
Clearing House Corporation [PCHC]. The dispute
bond in the amount of P12,600,000.00.
between the parties involved three [unfunded] checks
with a total value of P25,200,000.00. The checks were
Says the trial court in its Order of June 13, 1994:
drawn against respondent Bank and were presented by
xxx (T)he counter-bond posted by [petitioner] Insular
petitioner for clearing. As respondent Bank returned
Savings Bank should include the unsecured portion of
the checks beyond the reglementary period, [but after
[respondents] claim of P12,600,000.00 as agreed by
petitioners account with PCHC was credited with the
means of arbitration between [respondent] and
amount of P25,200,000.00] petitioner refused to refund
[petitioner]; Actual damages at 25% percent per
the money to respondent Bank. While the dispute was
annum of unsecured amount of claim from October 21,
pending arbitration, on January 17, 1992, respondent
1991 in the amount of P7,827,500.00; Legal interest of
Bank instituted Civil Case No. 92-145 in the Regional
12% percent per annum from October 21, 1991 in the
Trial Court of Makati and prayed for the issuance of a
amount of P3,805,200.00; Exemplary damages in the
writ of preliminary attachment. On January 22, 1992,
amount of P2,000,000.00; and attorneys fees and
Branch 133 of the Regional Trial Court of Makati issued
expenses of litigation in the amount of P1,000,000.00
an Order granting the application for preliminary
with a total amount of P27,237,700.00 (Adlawan vs.
attachment upon posting by respondent Bank of an
Tomol, 184 SCRA 31 (1990).
attachment bond in the amount of P6,000,000.00.
On January 27, 1992, Branch 133 of the Regional Trial
Court of Makati issued a writ of preliminary attachment
Petitioner, on the other hand, argues that the starting point in
for the amount of P25,200,000.00. During the hearing
computing the amount of counter-bond is the amount of the
on February 11, 1992 before the Arbitration Committee
respondents demand or claim only, in this case P25,200,000.00,
of the Philippine Clearing House Corporation, petitioner
excluding contingent expenses and unliquidated amount of
and respondent Bank agreed to temporarily divide
damages. And since there was a mutual agreement between the
between them the disputed amount of P25,200,000.00
parties to temporarily, but equally, divide between themselves
while the dispute has not yet been resolved. As a
the said amount pending and subject to the final outcome of the
result, the sum of P12,600,000.00 is in the possession
arbitration, the amount of P12,600,000.00 should, so petitioner
of respondent Bank. On March 9, 1994, petitioner filed
argues, be the basis for computing the amount of the counter-
a motion to discharge attachment by counter-bond in
bond.
the amount of P12,600,000.00. On June 13, 1994,
respondent Judge issued the first assailed order
The Court rules for the petitioner.
denying the motion. On June 27, 1994, petitioner
filed a motion for reconsideration which was
87
The then pertinent provision of Rule 57 (Preliminary Attachment) writ of attachment issued on January 27, 1992, in turn, expressly
of the Rules of Court under which the appellate court issued its indicated that petitioner is justly indebted to respondent in the
assailed decision and resolution, provides as follows: amount of P25,200,000.00.[8] On February 11, 1992, before the
Arbitration Committee of the Philippine Clearing House
SEC. 12. Discharge of attachment upon giving counter- Corporation, petitioner and respondent, however, agreed to
bond. At any time after an order of attachment has equally divide between themselves, albeit on a temporary basis,
been granted, the party whose property has been the disputed amount of P25,200,000.00, subject to the outcome
attached, . . . may upon reasonable notice to the of the arbitration proceedings. Thus, the release by petitioner of
applicant, apply to the judge who granted the order or the amount of P12,600,000.00 to respondent. On March 7, 1994,
to the judge of the court which the action is pending, petitioner filed a motion to discharge attachment by counter-
for an order discharging the attachment wholly or in bond in the amount of P12,600,000.00[9] which, to petitioner, is
part on the security given. The judge shall, after the extent that respondent may actually be prejudiced in the
hearing, order the discharge of the attachment if a event its basic complaint for recovery of money against
cash deposit is made, or a counter-bond executed to petitioner prospers.
the attaching creditor is filed, on behalf of the adverse
party, with the clerk or judge of the court where the As things stood, therefore, respondents principal claim against
application is made in an amount equal to the petitioner immediately prior to the filing of the motion to
value of the property attached as determined by discharge attachment has effectively been pruned down
the judge, to secure the payment of any to P12,600,000.00. The trial court was fully aware of this reality.
judgment that the attaching creditor may Accordingly, it should have allowed a total discharge of the
recover in the action. x x x . Should such counter- attachment on a counter-bond based on the reduced claim of
bond for any reason be found to be, or become respondent. If a portion of the claim is already secured, we see
insufficient, and the party furnishing the same fail to no justifiable reason why such portion should still be subject of
file an additional counter-bond, the attaching party counter-bond. It may be that a counter-bond is intended to
may apply for a new order of attachment 4 (Emphasis secure the payment of any judgment that the attaching party
supplied).[4] may recover in the main action. Simple common sense, if not
consideration of fair play, however, dictates that a part of a
possible judgment that has veritably been preemptively
As may be noted, the amount of the counter-attachment bond satisfied or secured need not be covered by the counter-bond.
is, under the terms of the aforequoted Section 12, to be
measured against the value of the attached property, as With the view we take of this case, the trial court, in
determined by the judge to secure the payment of any requiring petitioner to post a counter-bond in the amount
judgment that the attaching creditor may recover in the action. of P27,237,700.00,
Albeit not explicitly stated in the same section and without obviously glossed over one certain fundamental. We refer to the
necessarily diminishing the sound discretion of the issuing judge fact that the attachment respondent applied for and the
on matters of bond approval, there can be no serious objection, corresponding writ issued was only for the amount of P25.2
in turn, to the proposition that the attached property - and Million. Respondent, it bears to stress, did not pray for
logically the counter-bond necessary to discharge the lien on attachment on its other claims, contingent and unliquidated as
such property - should as much as possible correspond in value they were. Then, too, the attaching writ rightly excluded such
to, or approximately match the attaching creditors principal claims. While the records do not indicate, let alone provide a
claim. Else, excessive attachment, which ought to be avoided at clear answer as to the actual value of the property levied upon,
all times, shall ensue. As we held in Asuncion vs. Court of it may reasonably be assumed that it is equal to respondents
Appeals:[5] principal claim. Be that as it may, it was simply unjust for the
trial court to base the amount of the counter-bond on a figure
We, however, find the counter-attachment bond in the beyond the P25,200,000.00 threshold, as later reduced
amount of P301,935.41 required of the private to P12,600,200.00.
respondent by the trial court as rather excessive under
the circumstances. Considering that the principal The trial court, therefore, committed grave abuse of discretion
amounts claimed by the petitioner . . . total only when it denied petitioners motion to discharge attachment by
P185,685.00, and that he had posted a bond of only counter-bond in the amount of P12,600,000.00, an amount more
P80,000.00 for the issuance of the writ of preliminary than double the attachment bond required of, and given by,
attachment, we deem it reasonable to lower the respondent. As a necessary consequence, the Court of Appeals
amount of the counter-attachment bond to be posted committed reversible error when it dismissed petitioners
by the private respondent . . . to the sum of recourse thereto in CA-G.R. SP No. 34876.
P185,685.00.
It bears to stress, as a final consideration, that the certiorari
proceedings before the appellate court and the denial of the
The following excerpts from Herrera, REMEDIAL LAW, Vol. VII, motion to discharge attachment subject of such proceedings,
1997 ed., p. 61, citing retired Justice Jose Y. Feria, drive home transpired under the old rules on preliminary attachment which
the same point articulated in Asuncion: has since been revised.[10] And unlike the former Section 12 of
Rule 57 of the Rules of Court where the value of the property
The sheriff is required to attach only so much attached shall be the defining measure in the computation of
of the property of the party against whom the order is the discharging counter-attachment bond, the present less
issued as may be sufficient to satisfy the applicants stringent Section 12 of Rule 57 provides that the court shall
demand, the amount of which is stated in the order the discharge of attachment if the movant makes a cash
order, unless a deposit is made or a counter-bond deposit, or files a counter-bond . . . in an amount equal to that
is given equal to said amount. However, if the value fixed by the court in the order of attachment, exclusive of costs.
of the property to be attached is less than the amount Not being in the nature of a penal statute, the Rules of Court
of the demand, the amount of the applicants bond may cannot be given retroactive effect.[11]
be equal to the value of said property, and the
amount of the adverse partys deposit or counter- This disposition should be taken in the light of then Section 12,
bond may be equal to the applicants bond. The Rule 57 of the Rules of Court.
writ of preliminary attachment is issued upon approval
of the requisite bond. (Emphasis supplied). WHEREFORE, the instant petition is GRANTED. Accordingly,
Turning to the case at bar, the records show that the principal the assailed decision and resolution of the Courts of Appeals are
claim of respondent, as plaintiff a quo, is in the amount hereby REVERSED and SET ASIDE, along with the orders
of P25,200,000.00,[6] representing the three (3) unfunded checks dated June 13, 1994 and July 20, 1994 of the Regional Trial Court
drawn against, and presented for clearing to, respondent bank. at Makati, Branch 135, in Civil Case No. 92-145insofar they
Jurisprudence teaches that a writ of attachment cannot be denied petitioners motion to discharge attachment by counter-
issued for moral and exemplary damages, and other bond in the amount of P12,600,000.00, and a new one
unliquidated or contingent claim.[7] entered GRANTING such motion upon the reposting of the
same counter-bond.
The order of attachment dated January 22, 1992 fixed the bond
to be posted by respondent, as applicant, at P6,000,000.00. The SO ORDERED.
88
FIRST DIVISION June 22, 2006 G.R. No. 141818 SO ORDERED.[9] (Emphasis supplied)

INSULAR SAVINGS BANK, Petitioner,- versus - FAR EAST


BANK ANDTRUST COMPANY, Respondent.

The above Omnibus Order was amended by the trial


YNARES-SANTIAGO, J.: court in its October 1, 1992 Order,[10] the dispositive portion of
which reads as follows:

This petition for review on certiorari [1] assails the November 9,


1999 Order[2] of the Regional Trial Court of Makati City, Branch WHEREFORE, the Omnibus Order dated 30
135, in Civil Case No. 92-145 which dismissed the petition for April 1992 is hereby reconsidered by deleting the
review for lack of jurisdiction and its February 1, 2000 phrase since the complaint also seeks exemplary
Order[3] denying reconsideration thereof. damages, attorneys fees, litigation expenses and costs
of suit against HBT, on page 4 thereof and par. C of its
dispositive portion is amended to read:

The antecedent facts are as follows:

On December 11, 1991, Far East Bank and Trust Company (c) Procedings against Home Bankers and
(Respondent) filed a complaint against Home Bankers Trust and Trust Co. are suspended pending award/decision in the
Company (HBTC)[4] with the Philippine Clearing House arbitration proceedings while those against individual
Corporations (PCHC) Arbitration Committee docketed as defendants be immediately reinstated and continued.
Arbicom Case No. 91-069.[5] Respondent sought to recover from
the petitioner, the sum of P25,200,000.00 representing the total
amount of the three checks drawn and debited against its
clearing account.HBTC sent these checks to respondent for
clearing by operation of the PCHC clearing system. Thereafter, HBT and Tancuans separate Motions for
respondent dishonored the checks for insufficiency of funds and Reconsiderations are hereby denied, for lack of merit.
returned the checks to HBTC. However, the latter refused to
accept them since the checks were returned by respondent after
the reglementary regional clearing period.[6]
SO ORDERED.[11]

Meanwhile, on January 17, 1992, before the termination


of the arbitration proceedings, respondent filed another
On February 2, 1998, the PCHC Arbitration Committee rendered
complaint but this time with the Regional Trial Court (RTC)
its decision in favor of respondent,[12] thus:
in Makati City docketed as Civil Case No. 92-145 for Sum of
Money and Damages with Preliminary Attachment. The
complaint was filed not only against HBTC but also against
Robert Young, Eugene Arriesgado and Victor Tancuan
(collectively known as Defendants), who were the president and IN VIEW OF ALL THE FOREGOING, judgment is hereby
depositors of HBTC respectively. [7] Aware of the arbitration rendered in favor of the plaintiff and against the
proceedings between respondent and petitioner, the RTC, in an defendant sentencing the latter to pay the plaintiff the
Omnibus Order dated April 30, 1992,[8] suspended the sum of P25.2 million as principal. In view of the fact,
proceedings in the case against all the defendants pending the however, that this amount was split between the
decision of the Arbitration Committee, to wit: plaintiff and the defendant in the course of the
proceedings, the amount to be paid by the defendant
to the plaintiff should only be P12,600,000.00 plus
interest on this latter amount at the rate of 12% per
annum from February 11, 1992, the date when the total
WHEREFORE, the Court hereby orders:
amount of P25.2 Million was split between plaintiff and
defendant up to the date of payment.

(a) Home Bankers & Trust Co. to produce and


permit plaintiff to inspect, copy and/or photograph the
In view of the facts found by the committee, no
checking account deposit ledger of Victor Tancuans
attorneys fees nor other damages are awarded.
Account No. 1803-00605-3;

SO ORDERED.[13]
(b) The Motions to Dismiss filed by all
defendants denied, for lack of merit; and

(c) Proceedings in this case against all


defendants be suspended pending The motion for reconsideration filed by petitioner was denied by
award/decision in the arbitration proceedings the Arbitration Committee.[14] Consequently, to appeal the
against Home Bankers and Trust Co. decision of the Arbitration Committee in Arbicom Case No. 91-
069, petitioner filed a petition for review in the earlier case
filed by respondent in Branch 135 of the RTC
of Makati and docketed as Civil Case No. 92-145.[15] In an
89
order dated January 20, 1999, the RTC directed both petitioner there was already a pending original action, i.e., Civil Case No.
and respondent to file their respective memoranda, after which, 92-145.
said petition would be deemed submitted for resolution. [16]

The petition lacks merit.


Both parties filed several pleadings. On February 8, 1999,
respondent filed a Motion to Dismiss Petition for Review for Lack
of Jurisdiction,[17] which was opposed by the petitioner.
[18]
Respondent then filed its Reply to the opposition, [19] to which
petitioner filed a Rejoinder.[20] On August 16, 1999, respondent The Philippine Clearing House Corporation was created
submitted its Surrejoinder.[21] to facilitate the clearing of checks of member banks. Among
these member banks exists a compromissoire,[25] or an
arbitration agreement embedded in their contract wherein they
consent that any future dispute or controversy between its PCHC
participants involving any check would be submitted to the
On November 9, 1999, the RTC rendered the assailed Order Arbitration Committee for arbitration. Petitioner and respondent
which held, thus: are members of PCHC, thus they underwent arbitration
proceedings.

Acting on plaintiff Far East Bank and Trust Companys


Motion To Dismiss Petition For Review For Lack Of
Jurisdiction, considering that the petition for review is a
separate and distinct case, the same must comply with
all the requirements for filing initiatory pleadings for
civil actions before this Court so that since the The PCHC has its own Rules of Procedure for Arbitration
commencement of the subject petition lacks the (PCHC Rules). However, this is governed by Republic Act No.
mandatory requirements provided for, except the 876, also known as The Arbitration Law[26] and supplemented by
payment of docket fees, for lack of jurisdiction, the the Rules of Court.[27] Thus, we first thresh out the remedy of
petition for review is hereby dismissed. petition for review availed of by the petitioner to appeal the
order of the Arbitration Committee.

SO ORDERED.[22]
Sections 23, 24 and 29 of The Arbitration Law, and
Section 13 of the PCHC Rules, provide:

The RTC denied petitioners motion for reconsideration, [23] hence,


this petition on the sole ground, to wit:
SEC. 23. Confirmation of award. At any time within one
month after the award is made, any party to the
controversy which was arbitrated may apply to the
court having jurisdiction, as provided in Section 28, for
THE REGIONAL TRIAL COURT ERRED IN DISMISSING THE an order confirming the award; and thereupon the
PETITION OF PETITIONER FOR LACK OF JURISDICTION court must grant such order unless the award is
ON THE GROUND THAT IT SHOULD HAVE BEEN vacated, modified or corrected, as prescribed
DOCKETED AS A SEPARATE CASE.[24] herein. Notice of such motion must be served upon the
adverse party or his attorney as prescribed by law for the
service of such notice upon an attorney in action in the
same court.

Petitioner contends that Civil Case No. 92-145 was merely


suspended to await the outcome of the arbitration case pending
before the PCHC. Thus, any petition questioning the decision of
the Arbitration Committee must be filed in Civil Case No. 92-145 SEC. 24. Grounds for vacating award. In any one of the
and should not be docketed as a separate action. Likewise, following cases, the court must make an order vacating
petitioner avers that had it filed a separate action, this would the award upon the petition of any party to the
have resulted in a multiplicity of suits, which is abhorred in controversy when such party proves affirmatively that in
procedure. the arbitration proceedings:

Meanwhile respondent avers that the RTC correctly (a) The award was procured by corruption, fraud
dismissed the appeal from the award of private arbitrators since or other undue means; or
there is no statutory basis for such appeal. Respondent argues
that petitioners claim that the parties by agreement had (b) That there was evident partiality or corruption
conferred on the RTC appellate jurisdiction over decisions of in the arbitrators or any of them; or
private arbitrators is erroneous because they cannot confer a
non-existent jurisdiction on the RTC or any court. Furthermore,
the petition for review filed by petitioner violated the rule on (c) That the arbitrators were guilty of misconduct
commencing an original action under Section 5, Rule 1, and the in refusing to postpone the hearing upon sufficient cause
raffle of cases under Section 2, Rule 20 of the Rules of Court, shown, or in refusing to hear evidence pertinent and
when it filed the same in Branch 135 of the RTC of Makati where material to the controversy; that one or more of the
arbitrators was disqualified to act as such under section
90
nine hereof, and willfully refrained from disclosing such committee or sole arbitrator or of the Board of Directors,
disqualification or of any other misbehavior by which the as the case may be, within a non-extendible period of
rights of any party have been materially prejudiced; or fifteen (15) days from and after its receipt of the order
denying or granting said motion for reconsideration or new
trial had been filed, within a non-extendible period of
(d) That the arbitrators exceeded their powers, or
fifteen (15) days from and after its receipt of the order
so imperfectly executed them, that a mutual, final and
denying or granting said motion for reconsideration or of
definite award upon the subject matter submitted to them
the decision rendered after the new trial if one had been
was not made.
granted.

xxxx
x x x x. (Emphasis supplied)

SEC. 25. Grounds for modifying or correcting award. In any


As provided in the PCHC Rules, the findings of facts of
one of the following cases, the court must make an order
the decision or award rendered by the Arbitration Committee
modifying or correcting the award, upon the application of
shall be final and conclusive upon all the parties in said
any party to the controversy which was arbitrated:
arbitration dispute.[28] Under Article 2044[29] of the New Civil
Code, the validity of any stipulation on the finality of the
arbitrators award or decision is recognized. However, where the
conditions described in Articles 2038, [30] 2039[31] and
(a) Where there was an evident miscalculation of 2040[32] applicable to both compromises and arbitrations are
figures, or an evident mistake in the description of any obtaining, the arbitrators award may be annulled or rescinded.
[33]
person, thing or property referred to in the award; or Consequently, the decision of the Arbitration Committee is
subject to judicial review.
(b) Where the arbitrators have awarded upon a
matter not submitted to them, not affecting the merits of
the decision upon the matter submitted; or
Furthermore, petitioner had several judicial remedies
(c) Where the award is imperfect in a matter of available at its disposal after the Arbitration Committee denied
form not affecting the merits of the controversy, and if it its Motion for Reconsideration. It may petition the proper RTC to
had been a commissioners report, the defect could have issue an order vacating the award on the grounds provided for
been amended or disregarded by the court. under Section 24 of the Arbitration Law.[34] Petitioner likewise has
the option to file a petition for review under Rule 43 of the Rules
of Court with the Court of Appeals on questions of fact, of law, or
mixed questions of fact and law.[35] Lastly, petitioner may file a
petition for certiorari under Rule 65 of the Rules of Court on the
The order may modify and correct the award so ground that the Arbitrator Committee acted without or in excess
as to effect the intent thereof and promote justice between of its jurisdiction or with grave abuse of discretion amounting to
the parties. lack or excess of jurisdiction. Since this case involves acts or
omissions of a quasi-judicial agency, the petition should be filed
in and cognizable only by the Court of Appeals. [36]

SEC. 29. Appeals. An appeal may be taken from an


order made in a proceeding under this Act, or from
judgment entered upon an award through certiorari In this instance, petitioner did not avail of any of the
proceedings, but such appeals shall be limited to abovementioned remedies available to it. Instead it filed a
questions of law. The proceedings upon such an appeal, petition for review with the RTC where Civil Case No. 92-145 is
including the judgment thereon shall be governed by the pending pursuant to Section 13 of the PCHC Rules to sustain its
Rules of Court insofar as they are applicable. action. Clearly, it erred in the procedure it chose for judicial
review of the arbitral award.

AMENDED ARBITRATION RULES OF PROCEDURE OF PCHC


Having established that petitioner failed to avail of the
abovementioned remedies, we now discuss the issue of the
jurisdiction of the trial court with respect to the petition for
review filed by petitioner.
Sec. 13. The findings of facts of the decision or
award rendered by the Arbitration Committee or by
the sole Arbitrator as the case may be shall be final
and conclusive upon all the parties in said
arbitration dispute. The decision or award of the Jurisdiction is the authority to hear and determine a
Arbitration Committee or of the Sole Arbitrator or of the cause - the right to act in a case. [37] Jurisdiction over the subject
Board of Directors, as the case may be, shall matter is the power to hear and determine the general class to
be appealable only on questions of law to any of the which the proceedings in question belong. Jurisdiction over the
Regional Trial Courts in the National Capital Region subject matter is conferred by law and not by the consent or
where the Head Office of any of the parties is acquiescence of any or all of the parties or by erroneous belief
located. The appellant shall perfect his appeal by filing a of the court that it exists.[38]
notice of appeal to the Arbitration Secretariat and filing a
Petition with the Regional Trial Court of the National Capital
Region for the review of the decision or award of the
91
In the instant case, petitioner and respondent have CAPELLAN, and the REGISTER OF DEEDS FOR LIPA
agreed that the PCHC Rules would govern in case of CITY, respondents.
controversy. However, since the PCHC Rules came about only as
a result of an agreement between and among member banks of DE LEON, JR., J.:
PCHC and not by law, it cannot confer jurisdiction to the
RTC. Thus, the portion of the PCHC Rules granting jurisdiction to
the RTC to review arbitral awards, only on questions of law, Before us is a petition for review on certiorari of the
cannot be given effect. Order[1] of Branch 85 of the Regional Trial Court of Lipa
City[2] dismissing petitioners complaint[3] for rescission of several
sale transactions involving land owned by Augusto L. Salas, Jr.,
their predecessor-in-interest, on the ground that they failed to
first resort to arbitration.
Consequently, the proper recourse of petitioner from
the denial of its motion for reconsideration by the Arbitration Salas, Jr. was the registered owner of a vast tract of land in
Committee is to file either a motion to vacate the arbitral award Lipa City, Batangas spanning 1,484,354 square meters.
with the RTC, a petition for review with the Court of Appeals
under Rule 43 of the Rules of Court, or a petition for certiorari
under Rule 65 of the Rules of Court. In the case at bar, petitioner On May 15, 1987, he entered into an Owner-Contractor
filed a petition for review with the RTC when the same should Agreement[4] (hereinafter referred to as the Agreement) with
have been filed with the Court of Appeals under Rule 43 of the respondent Laperal Realty Corporation (hereinafter referred to
Rules of Court. Thus, the RTC of Makati did not err in dismissing as Laperal Realty) to render and provide complete (horizontal)
the petition for review for lack of jurisdiction but not on the construction services on his land.
ground that petitioner should have filed a separate case from
Civil Case No. 92-145 but on the necessity of filing the correct On September 23, 1988, Salas, Jr. executed a Special
petition in the proper court. It is immaterial whether petitioner Power of Attorney in favor of respondent Laperal Realty to
filed the petition for review in Civil Case No. 92-145 as an appeal exercise general control, supervision and management of the
of the arbitral award or whether it filed a separate case in the sale of his land, for cash or on installment basis.
RTC, considering that the RTC will only have jurisdiction over an
arbitral award in cases of motions to vacate the
On June 10, 1989, Salas, Jr. left his home in the morning for
same. Otherwise, as elucidated herein, the Court of Appeals
a business trip to Nueva Ecija. He never returned.
retains jurisdiction in petitions for review or in petitions for
certiorari. Consequently, petitioners arguments, with respect to
the filing of separate action from Civil Case No. 92-145 resulting On August 6, 1996, Teresita Diaz Salas filed with the
in a multiplicity of suits, cannot be given due course. Regional Trial Court of Makati City a verified petition for the
declaration of presumptive death of her husband, Salas, Jr., who
had then been missing for more than seven (7) years. It was
granted on December 12, 1996.[5]

Alternative dispute resolution methods or ADRs like


Meantime, respondent Laperal Realty subdivided the land
arbitration, mediation, negotiation and conciliation are
of Salas, Jr. and sold subdivided portions thereof to respondents
encouraged by the Supreme Court. By enabling parties to
Rockway Real Estate Corporation and South Ridge Village, Inc.
resolve their disputes amicably, they provide solutions that are
on February 22, 1990; to respondent spouses Abrajano and Lava
less time-consuming, less tedious, less confrontational, and
and Oscar Dacillo on June 27, 1991; and to respondents Eduardo
more productive of goodwill and lasting relationships. [39] It must
Vacuna, Florante de la Cruz and Jesus Vicente Capalan on June
be borne in mind that arbitration proceedings are mainly
4, 1996 (all of whom are hereinafter referred to as respondent
governed by the Arbitration Law and suppletorily by the Rules of
lot buyers).
Court.

On February 3, 1998, petitioners as heirs of Salas, Jr. filed


in the Regional Trial Court of Lipa City a Complaint [6] for
declaration of nullity of sale, reconveyance, cancellation of
WHEREFORE, in light of the foregoing, the petition contract, accounting and damages against herein respondents
is DENIED. The November 9, 1999 Order of the Regional Trial which was docketed as Civil Case No. 98-0047.
Court of Makati City, Branch 135, in Civil Case No. 92-145 which
dismissed the petition for review for lack of jurisdiction and the
On April 24, 1998, respondent Laperal Realty filed a Motion
February 1, 2000 Order denying its reconsideration,
to Dismiss[7]on the ground that petitioners failed to submit their
are AFFIRMED.
grievance to arbitration as required under Article VI of the
Agreement which provides:

ARTICLE VI. ARBITRATION.


SO ORDERED.

All cases of dispute between CONTRACTOR and OWNERS


SECOND DIVISION[G.R. NO. 135362. December 13, 1999] representative shall be referred to the committee represented
by:
HEIRS OF AUGUSTO L. SALAS, JR., namely: TERESITA D.
SALAS for herself and as legal guardian of the a. One representative of the OWNER;
minor FABRICE CYRILL D. SALAS, MA. CRISTINA S.
LESACA, and KARINA TERESA D.
b. One representative of the CONTRACTOR;
SALAS, petitioners, vs. LAPERAL REALTY
CORPORATION, ROCKWAY REAL ESTATE
CORPORATION, SOUTH RIDGE VILLAGE, INC., c. One representative acceptable to both OWNER and
MAHARAMI DEVELOPMENT CORPORATION, CONTRACTOR.[8]
Spouses THELMA D. ABRAJANO and GREGORIO
ABRAJANO, OSCAR DACILLO, Spouses VIRGINIA D. On May 5, 1998, respondent spouses Abrajano and Lava
LAVA and RODEL LAVA, EDUARDO A. VACUNA, and respondent Dacillo filed a Joint Answer with Counterclaim
FLORANTE DE LA CRUZ, JESUS VICENTE B. and Crossclaim[9] praying for dismissal of petitioners Complaint
for the same reason.
92
On August 9, 1998, the trial court issued the herein in Article VI of the Agreement was never vested in respondent
assailed Order dismissing petitioners Complaint for non- lot buyers.
compliance with the foregoing arbitration clause.
Respondent Laperal Realty, as a contracting party to the
Hence this petition. Agreement, has the right to compel petitioners to first arbitrate
before seeking judicial relief. However, to split the proceedings
into arbitration for respondent Laperal Realty and trial for the
Petitioners argue, thus:
respondent lot buyers, or to hold trial in abeyance pending
arbitration between petitioners and respondent Laperal Realty,
The petitioners causes of action did not emanate from the would in effect result in multiplicity of suits, duplicitous
Owner-Contractor Agreement. procedure and unnecessary delay. On the other hand, it would
be in the interest of justice if the trial court hears the complaint
The petitioners causes of action for cancellation of contract and against all herein respondents and adjudicates petitioners rights
accounting are covered by the exception under the Arbitration as against theirs in a single and complete proceeding.
Law.
WHEREFORE, the instant petition is hereby GRANTED. The
Failure to arbitrate is not a ground for dismissal. [10] Order dated August 19, 1998 of Branch 85 of the Regional Trial
Court of Lipa City is hereby NULLIFIED and SET ASIDE. Said court
is hereby ordered to proceed with the hearing of Civil Case No.
In a catena of cases [11] inspired by Justice Malcolms 98-0047.
provocative dissent in Vega v. San Carlos Milling Co.[12], this
Court has recognized arbitration agreements as valid, binding,
enforceable and not contrary to public policy so much so that Costs against private respondents.
when there obtains a written provision for arbitration which is
not complied with, the trial court should suspend the SO ORDERED.
proceedings and order the parties to proceed to arbitration in
accordance with the terms of their agreement[13] Arbitration is
THIRD DIVISION[G.R. No. 120105. March 27, 1998]
the wave of the future in dispute resolution.[14] To brush aside a
contractual agreement calling for arbitration in case of
disagreement between parties would be a step backward.[15] BF CORPORATION, petitioner, vs. COURT OF APPEALS,
SHANGRI-LA PROPERTIES, COLAYCO, ALFREDO C.
RAMOS, INC., RUFO B.
Nonetheless, we grant the petition.
MAXIMO G. LICAUCO III and BENJAMIN C.
RAMOS, respondents.
A submission to arbitration is a contract. [16] As such, the
Agreement, containing the stipulation on arbitration, binds the
ROMERO, J.:
parties thereto, as well as their assigns and heirs. [17] But only
they. Petitioners, as heirs of Salas, Jr., and respondent Laperal
Realty are certainly bound by the Agreement. If respondent The basic issue in this petition for review on certiorari is
Laperal Realty, had assigned its rights under the Agreement to a whether or not the contract for the construction of the EDSA
third party, making the former, the assignor, and the latter, the Plaza between petitioner BF Corporation and respondent
assignee, such assignee would also be bound by the arbitration Shangri-la Properties, Inc. embodies an arbitration clause in case
provision since assignment involves such transfer of rights as to of disagreement between the parties in the implementation of
vest in the assignee the power to enforce them to the same contractual provisions.
extent as the assignor could have enforced them against the
debtor[18] or in this case, against the heirs of the original party to Petitioner and respondent Shangri-la Properties, Inc. (SPI)
the Agreement. However, respondents Rockway Real Estate entered into an agreement whereby the latter engaged the
Corporation, South Ridge Village, Inc., Maharami Development
former to construct the main structure of the EDSA Plaza Project,
Corporation, spouses Abrajano, spouses Lava, Oscar Dacillo, a shopping mall complex in the City of Mandaluyong.
Eduardo Vacuna, Florante de la Cruz and Jesus Vicente Capellan
are not assignees of the rights of respondent Laperal Realty
under the Agreement to develop Salas, Jr.s land and sell the The construction work was in progress when SPI decided to
same. They are, rather, buyers of the land that respondent expand the project by engaging the services of petitioner
Laperal Realty was given the authority to develop and sell under again. Thus, the parties entered into an agreement for the main
the Agreement. As such, they are not assigns contemplated in contract works after which construction work began.
Art. 1311 of the New Civil Code which provides that contracts
take effect only between the parties, their assigns and heirs. However, petitioner incurred delay in the construction work
that SPI considered as serious and substantial. [1] On the other
Petitioners claim that they suffered lesion of more than hand, according to petitioner, the construction works progressed
one-fourth (1/4) of the value of Salas, Jr.s land when respondent in faithful compliance with the First Agreement until a fire broke
Laperal Realty subdivided it and sold portions thereof to out on November 30, 1990 damaging Phase I of the Project.
[2]
respondent lot buyers. Thus, they instituted action [19]against Hence, SPI proposed the re-negotiation of the agreement
both respondent Laperal Realty and respondent lot buyers for between them.
rescission of the sale transactions and reconveyance to them of
the subdivided lots. They argue that rescission, being their Consequently, on May 30, 1991, petitioner and SPI entered
cause of action, falls under the exception clause in Sec. 2 of into a written agreement denominated as Agreement for the
Republic Act No. 876 which provides that such submission [to] or Execution of Builders Work for the EDSA Plaza Project. Said
contract [of arbitration] shall be valid, enforceable and agreement would cover the construction work on said project as
irrevocable, save upon such grounds as exist at law for the of May 1, 1991 until its eventual completion.
revocation of any contract.

According to SPI, petitioner failed to complete the


The petitioners contention is without merit. For while construction works and abandoned the project. [3] This resulted in
rescission, as a general rule, is an arbitrable issue, disagreements between the parties as regards their respective
[20]
they impleaded in the suit for rescission the respondent lot liabilities under the contract. On July 12, 1993, upon SPIs
buyers who are neither parties to the Agreement nor the latters initiative, the parties respective representatives met in
assigns or heirs.Consequently, the right to arbitrate as provided conference but they failed to come to an agreement.[4]
93
Barely two days later or on July 14, 1993, petitioner filed Manila on November 15, 1991. The said Articles of
with the Regional Trial Court of Pasig a complaint for collection Agreement also provides that the `Contract Documents'
of the balance due under the construction agreement. Named therein listed `shall be deemed an integral part of this
defendants therein were SPI and members of its board of Agreement, and one of the said documents is the
directors namely, Alfredo C. Ramos, Rufo B. Colayco, Antonio B. `Conditions of Contract which contains the Arbitration
Olbes, Gerardo O. Lanuza, Jr., Maximo G. Licauco III and Clause relied upon by the defendants in their Motion to
Benjamin C. Ramos. Suspend Proceedings.

On August 3, 1993, SPI and its co-defendants filed a This Court notes, however, that the `Conditions of Contract
motion to suspend proceedings instead of filing an answer. The referred to, contains the following provisions:
motion was anchored on defendants allegation that the formal
trade contract for the construction of the project provided for a `3. Contract Document.
clause requiring prior resort to arbitration before judicial
intervention could be invoked in any dispute arising from the
contract. The following day, SPI submitted a copy of the Three copies of the Contract Documents
conditions of the contract containing the arbitration clause that referred to in the Articles of
it failed to append to its motion to suspend proceedings. Agreement shall be signed by the parties
to the contract and distributed to the
Owner and the Contractor for their safe
Petitioner opposed said motion claiming that there was no keeping. (underscoring supplied)
formal contract between the parties although they entered into
an agreement defining their rights and obligations in
undertaking the project. It emphasized that the agreement did And it is significant to note further that the said
not provide for arbitration and therefore the court could not be `Conditions of Contract is not duly signed by the parties on
deprived of jurisdiction conferred by law by the mere allegation any page thereof --- although it bears the initials of BFs
of the existence of an arbitration clause in the agreement representatives (Bayani F. Fernando and Reynaldo M. de la
between the parties. Cruz) without the initials thereon of any representative of
Shangri-La Properties, Inc.

In reply to said opposition, SPI insisted that there was such


an arbitration clause in the existing contract between petitioner Considering the insistence of the plaintiff that the said
and SPI. It alleged that suspension of proceedings would not Conditions of Contract was not duly executed or signed by
necessarily deprive the court of its jurisdiction over the case and the parties, and the failure of the defendants to submit any
that arbitration would expedite rather than delay the settlement signed copy of the said document, this Court entertains
of the parties respective claims against each other. serious doubt whether or not the arbitration clause found
in the said Conditions of Contract is binding upon the
parties to the Articles of Agreement. (Underscoring
In a rejoinder to SPIs reply, petitioner reiterated that there supplied.)
was no arbitration clause in the contract between the parties. It
averred that granting that such a clause indeed formed part of
the contract, suspension of the proceedings was no longer The lower court then ruled that, assuming that the
proper. It added that defendants should be declared in default arbitration clause was valid and binding, still, it was too late in
for failure to file their answer within the reglementary period. the day for defendants to invoke arbitration. It quoted the
following provision of the arbitration clause:

In its sur-rejoinder, SPI pointed out the significance of


petitioners admission of the due execution of the Articles of Notice of the demand for arbitration of a dispute shall be
Agreement. Thus, on page D/6 thereof, the signatures of Rufo B. filed in writing with the other party to the contract and a
Colayco, SPI president, and Bayani Fernando, president of copy filed with the Project Manager. The demand for
petitioner appear, while page D/7 shows that the agreement is a arbitration shall be made within a reasonable time after
public document duly notarized on November 15, 1991 by the dispute has arisen and attempts to settle amicably
Notary Public Nilberto R. Briones as document No. 345, page 70, have failed; in no case, however, shall the demand he
book No. LXX, Series of 1991 of his notarial register.[5] made be later than the time of final payment except as
otherwise expressly stipulated in the contract.

Thereafter, upon a finding that an arbitration clause indeed


exists, the lower court[6] denied the motion to suspend Against the above backdrop, the lower court found that per
proceedings, thus: the May 30, 1991 agreement, the project was to be completed
by October 31, 1991. Thereafter, the contractor would
pay P80,000 for each day of delay counted from November 1,
It appears from the said document that in the letter- 1991 with liquified (sic) damages up to a maximum of 5% of the
agreement dated May 30, 1991 (Annex C, Complaint), total contract price.
plaintiff BF and defendant Shangri-La Properties, Inc.
agreed upon the terms and conditions of the Builders Work
for the EDSA Plaza Project (Phases I, II and Carpark), The lower court also found that after the project was
subject to the execution by the parties of a formal trade completed in accordance with the agreement that contained a
contract. Defendants have submitted a copy of the alleged provision on progress payment billing, SPI took possession and
trade contract, which is entitled `Contract Documents For started operations thereof by opening the same to the public in
Builders Work Trade Contractor dated 01 May 1991, page 2 November, 1991. SPI, having failed to pay for the works,
of which is entitled `Contents of Contract Documents with petitioner billed SPI in the total amount of P110,883,101.52,
a list of the documents therein contained, and Section A contained in a demand letter sent by it to SPI on February 17,
thereof consists of the abovementioned Letter-Agreement 1993. Instead of paying the amount demanded, SPI set up its
dated May 30, 1991. Section C of the said Contract own claim of P220,000,000.00 and scheduled a conference on
Documents is entitled `Articles of Agreement and that claim for July 12, 1993. The conference took place but it
Conditions of Contract which, per its Index, consists of Part proved futile.
A (Articles of Agreement) and B (Conditions of
Contract). The said Articles of Agreement appears to have Upon the above facts, the lower court concluded:
been duly signed by President Rufo B. Colayco of Shangri-
La Properties, Inc. and President Bayani F. Fernando of BF
Considering the fact that under the supposed Arbitration
and their witnesses, and was thereafter acknowledged
Clause invoked by defendants, it is required that `Notice of
before Notary Public Nilberto R. Briones of Makati, Metro
the demand for arbitration of a dispute shall be filed in
94
writing with the other party x x x x in no case x x x x later is required that Notice of the demand for arbitration of a dispute
than the time of final payment x x x x which apparently, shall be filed in writing with the other party x x x in no case x x x
had elapsed, not only because defendants had taken later than the time of final payment, which apparently, had
possession of the finished works and the plaintiffs billings elapsed, not only because defendants had taken possession of
for the payment thereof had remained pending since the finished works and the plaintiffs billings for the payment
November, 1991 up to the filing of this case on July 14, thereof had remained pending since November, 1991 up to the
1993, but also for the reason that defendants have failed filing of this case on July 14, 1993, but also for the reason that
to file any written notice of any demand for arbitration defendants have failed to file any written notice of any demand
during the said long period of one year and eight months, for arbitration during the said long period of one year and eight
this Court finds that it cannot stay the proceedings in this months, x x x.
case as required by Sec. 7 of Republic Act No. 876,
because defendants are in default in proceeding with such Respondent Court has overlooked the fact that under the
arbitration. arbitration clause

The lower court denied SPIs motion for reconsideration for Notice of the demand for arbitration dispute shall be filed in
lack of merit and directed it and the other defendants to file writing with the other party to the contract and a copy filed with
their responsive pleading or answer within fifteen (15) days from the Project Manager. The demand for arbitration shall be made
notice. within a reasonable time after the dispute has arisen and
attempts to settle amicably had failed; in no case, however,
Instead of filing an answer to the complaint, SPI filed a shall the demand be made later than the time of final payment
petition for certiorari under Rule 65 of the Rules of Court before except as otherwise expressly stipulated in the contract
the Court of Appeals. Said appellate court granted the petition, (underscoring supplied)
annulled and set aside the orders and stayed the proceedings in
the lower court. In so ruling, the Court of Appeals held: quoted in its order (Annex A, petition). As the respondent Court
there said, after the final demand to pay the amount
The reasons given by the respondent Court in denying of P110,883,101.52, instead of paying, petitioners set up its own
petitioners motion to suspend proceedings are untenable. claim against respondent Corporation in the amount
of P220,000,000.00 and set a conference thereon on July 12,
1993. Said conference proved futile. The next day, July 14, 1993,
1. The notarized copy of the articles of agreement attached as
respondent Corporation filed its complaint against petitioners.
Annex A to petitioners reply dated August 26, 1993, has been
On August 13, 1993, petitioners wrote to respondent
submitted by them to the respondent Court (Annex G, petition).
Corporation requesting arbitration. Under the circumstances, it
It bears the signature of petitioner Rufo B. Colayco, president of
cannot be said that petitioners resort to arbitration was made
petitioner Shangri-La Properties, Inc., and of Bayani Fernando,
beyond reasonable time. Neither can they be considered in
president of respondent Corporation (Annex G-1, petition). At
default of their obligation to respondent Corporation.
page D/4 of said articles of agreement it is expressly provided
that the conditions of contract are `deemed an integral part
thereof (page 188, rollo). And it is at pages D/42 to D/44 of the Hence, this petition before this Court. Petitioner assigns
conditions of contract that the provisions for arbitration are the following errors:
found (Annexes G-3 to G-5, petition, pp. 227-229). Clause No. 35
on arbitration specifically provides: A.

Provided always that in case any dispute or difference shall arise THE COURT OF APPEALS ERRED IN ISSUING THE
between the Owner or the Project Manager on his behalf and the EXTRAORDINARY WRIT OF CERTIORARIALTHOUGH
Contractor, either during the progress or after the completion or THE REMEDY OF APPEAL WAS AVAILABLE TO
abandonment of the Works as to the construction of this RESPONDENTS.
Contract or as to any matter or thing of whatsoever nature
arising thereunder or in connection therewith (including any
matter or being left by this Contract to the discretion of the B.
Project Manager or the withholding by the Project Manager of
any certificate to which the Contractor may claim to be entitled THE COURT OF APPEALS ERRED IN FINDING GRAVE
or the measurement and valuation mentioned in clause 30 (5) ABUSE OF DISCRETION IN THE FACTUAL FINDINGS OF
(a) of these Conditions or the rights and liabilities of the parties THE TRIAL COURT THAT:
under clauses 25, 26, 32 or 33 of these Conditions), the Owner
and the Contractor hereby agree to exert all efforts to settle
(i) THE PARTIES DID NOT ENTER INTO AN
their differences or dispute amicably. Failing these efforts then
AGREEMENT TO ARBITRATE.
such dispute or difference shall be referred to Arbitration in
accordance with the rules and procedures of the Philippine
Arbitration Law. (ii) ASSUMING THAT THE PARTIES DID ENTER
INTO THE AGREEMENT TO
ARBITRATE, RESPONDENTS ARE
The fact that said conditions of contract containing the
ALREADY IN DEFAULT IN INVOKING
arbitration clause bear only the initials of respondent
THE AGREEMENT TO ARBITRATE.
Corporations representatives, Bayani Fernando and Reynaldo de
la Cruz, without that of the representative of petitioner Shangri-
La Properties, Inc. does not militate against its effectivity. Said On the first assigned error, petitioner contends that the
petitioner having categorically admitted that the document, Order of the lower court denying the motion to suspend
Annex A to its reply dated August 26, 1993 (Annex G, petition), proceedings is a resolution of an incident on the merits. As such,
is the agreement between the parties, the initial or signature of upon the continuation of the proceedings, the lower court would
said petitioners representative to signify conformity to appreciate the evidence adduced in their totality and thereafter
arbitration is no longer necessary. The parties, therefore, should render a decision on the merits that may or may not sustain the
be allowed to submit their dispute to arbitration in accordance existence of an arbitration clause. A decision containing a
with their agreement. finding that the contract has no arbitration clause can then be
elevated to a higher court in an ordinary appeal where an
adequate remedy could be obtained.Hence, to petitioner, the
2. The respondent Court held that petitioners `are in default in
Court of Appeals should have dismissed the petition
proceeding with such arbitration. It took note of `the fact that
for certiorari because the remedy of appeal would still be
under the supposed Arbitration Clause invoked by defendants, it
available to private respondents at the proper time. [7]
95
The above contention is without merit. incidentally, is a question of law, then it has to answer the core
issue of whether there exists an Arbitration Clause which,
admittedly, is a question of fact.
The rule that the special civil action of certiorari may not
be invoked as a substitute for the remedy of appeal is succinctly
reiterated in Ongsitco v. Court of Appeals[8] as follows: Moreover, where a rigid application of the rule
that certiorari cannot be a substitute for appeal will result in a
manifest failure or miscarriage of justice, the provisions of the
x x x. Countless times in the past, this Court has held that
Rules of Court which are technical rules may be relaxed. [10] As
`where appeal is the proper remedy, certiorari will not lie. The
we shall show hereunder, had the Court of Appeals dismissed
writs of certiorari and prohibition are remedies to correct lack or
the petition for certiorari, the issue of whether or not an
excess of jurisdiction or grave abuse of discretion equivalent to
arbitration clause exists in the contract would not have been
lack of jurisdiction committed by a lower court. `Where the
resolved in accordance with evidence extant in the record of the
proper remedy is appeal, the action for certiorari will not be
case. Consequently, this would have resulted in a judicial
entertained. x x x. Certiorari is not a remedy for errors of
rejection of a contractual provision agreed by the parties to the
judgment. Errors of judgment are correctible by appeal, errors of
contract.
jurisdiction are reviewable by certiorari.

In the same vein, this Court holds that the question of the
Rule 65 is very clear. The extraordinary remedies of certiorari,
existence of the arbitration clause in the contract between
prohibition and mandamus are available only when `there is no
petitioner and private respondents is a legal issue that must be
appeal or any plain, speedy and adequate remedy in the
determined in this petition for review on certiorari.
ordinary course of law x x x. That is why they are referred to as
`extraordinary. x x x.
Petitioner, while not denying that there exists an
arbitration clause in the contract in question, asserts that in
The Court has likewise ruled that certiorari will not be
contemplation of law there could not have been one considering
issued to cure errors in proceedings or correct erroneous
the following points. First, the trial court found that the
conclusions of law or fact. As long as a court acts within its
conditions of contract embodying the arbitration clause is not
jurisdiction, any alleged errors committed in the exercise of its
duly signed by the parties. Second, private respondents
jurisdiction will amount to nothing more than errors of judgment
misrepresented before the Court of Appeals that they produced
which are reviewable by timely appeal and not by a special civil
in the trial court a notarized duplicate original copy of the
action of certiorari.[9]v. Court of Appeals, 327 Phil. 1, 41-42
construction agreement because what were submitted were
(1996).9
mere photocopies thereof. The contract(s) introduced in court by
private respondents were therefore of dubious authenticity
This is not exactly so in the instant case. While this Court because: (a) the Agreement for the Execution of Builders Work
does not deny the eventual jurisdiction of the lower court over for the EDSA Plaza Project does not contain an arbitration
the controversy, the issue posed basically is whether the lower clause, (b) private respondents surreptitiously attached as
court prematurely assumed jurisdiction over it. If the lower court Annexes `G-3 to `G-5 to their petition before the Court of
indeed prematurely assumed jurisdiction over the case, then it Appeals but these documents are not parts of the Agreement of
becomes an error of jurisdiction which is a proper subject of a the parties as there was no formal trade contract executed, (c) if
petition for certiorari before the Court of Appeals. And if the the entire compilation of documents is indeed a formal trade
lower court does not have jurisdiction over the controversy, then contract, then it should have been duly notarized, (d) the
any decision or order it may render may be annulled and set certification from the Records Management and Archives Office
aside by the appellate court. dated August 26, 1993 merely states that the notarial record of
Nilberto Briones x x x is available in the files of (said) office
However, the question of jurisdiction, which is a question as Notarial Registry Entry only, (e) the same certification attests
of law depends on the determination of the existence of the that the document entered in the notarial registry pertains to
arbitration clause, which is a question of fact. In the instant the Articles of Agreement only without any other accompanying
case, the lower court found that there exists an arbitration documents, and therefore, it is not a formal trade contract, and
clause. However, it ruled that in contemplation of law, said (f) the compilation submitted by respondents are a mere hodge-
arbitration clause does not exist. podge of documents and do not constitute a single intelligible
agreement.

The issue, therefore, posed before the Court of Appeals in


a petition for certiorari is whether the Arbitration Clause does In other words, petitioner denies the existence of the
not in fact exist. On its face, the question is one of fact which is arbitration clause primarily on the ground that the
not proper in a petition for certiorari. representatives of the contracting corporations did not sign the
Conditions of Contract that contained the said clause. Its other
contentions, specifically that insinuating fraud as regards the
The Court of Appeals found that an Arbitration Clause does alleged insertion of the arbitration clause, are questions of fact
in fact exist. In resolving said question of fact, the Court of that should have been threshed out below.
Appeals interpreted the construction of the subject contract
documents containing the Arbitration Clause in accordance with
Republic Act No. 876 (Arbitration Law) and existing This Court may as well proceed to determine whether the
jurisprudence which will be extensively discussed hereunder. In arbitration clause does exist in the parties contract.Republic Act
effect, the issue posed before the Court of Appeals was likewise No. 876 provides for the formal requisites of an arbitration
a question of law. Being a question of law, the private agreement as follows:
respondents rightfully invoked the special civil action
of certiorari. Section 4. Form of arbitration agreement. A contract to arbitrate
a controversy thereafter arising between the parties, as well as
It is that mode of appeal taken by private respondents a submission to arbitrate an existing controversy, shall be in
before the Court of Appeals that is being questioned by the writing and subscribed by the party sought to be charged, or by
petitioners before this Court. But at the heart of said issue is the his lawful agent.
question of whether there exists an Arbitration Clausebecause if
an Arbitration Clause does not exist, then private respondents The making of a contract or submission for arbitration described
took the wrong mode of appeal before the Court of Appeals. in section two hereof, providing for arbitration of any
controversy, shall be deemed a consent of the parties of the
For this Court to be able to resolve the question of whether province or city where any of the parties resides, to enforce such
private respondents took the proper mode of appeal, which, contract of submission. (Underscoring supplied.)
96
The formal requirements of an agreement to arbitrate are act hastily in order to resolve the controversy through the
therefore the following: (a) it must be in writing and (b) it must courts.
be subscribed by the parties or their representatives. There is no
denying that the parties entered into a written contract that was The arbitration clause provides for a reasonable time
submitted in evidence before the lower court. To subscribe within which the parties may avail of the relief under that
means to write underneath, as ones name; to sign at the end of clause. Reasonableness is a relative term and the question of
a document.[11] That word may sometimes be construed to mean whether the time within which an act has to be done is
to give consent to or to attest.[12] reasonable depends on attendant circumstances. [15] This Court
finds that under the circumstances obtaining in this case, a one-
The Court finds that, upon a scrutiny of the records of this month period from the time the parties held a conference on
case, these requisites were complied with in the contract in July 12, 1993 until private respondent SPI notified petitioner that
question. The Articles of Agreement, which incorporates all the it was invoking the arbitration clause, is a reasonable time.
other contracts and agreements between the parties, was Indeed, petitioner may not be faulted for resorting to the court
signed by representatives of both parties and duly to claim what was due it under the contract. However, we find
notarized. The failure of the private respondents representative its denial of the existence of the arbitration clause as an attempt
to initial the `Conditions of Contract would therefor not affect to cover up its misstep in hurriedly filing the complaint before
compliance with the formal requirements for arbitration the lower court.
agreements because that particular portion of the covenants
between the parties was included by reference in the Articles of In this connection, it bears stressing that the lower court
Agreement. has not lost its jurisdiction over the case. Section 7 of Republic
Act No. 876 provides that proceedings therein have only been
Petitioners contention that there was no arbitration clause stayed. After the special proceeding of arbitration [16] has been
because the contract incorporating said provision is part of a pursued and completed, then the lower court may confirm the
hodge-podge document, is therefore untenable. A contract need award[17] made by the arbitrator.
not be contained in a single writing. It may be collected from
several different writings which do not conflict with each other It should be noted that in this jurisdiction, arbitration has
and which, when connected, show the parties, subject matter, been held valid and constitutional. Even before the approval on
terms and consideration, as in contracts entered into by June 19, 1953 of Republic Act No. 876, this Court has
correspondence.[13] A contract may be encompassed in several countenanced the settlement of disputes through arbitration.
instruments even though every instrument is not signed by the [18]
Republic Act No. 876 was adopted to supplement the New
parties, since it is sufficient if the unsigned instruments are Civil Codes provisions on arbitration.[19] Its potentials as one of
clearly identified or referred to and made part of the signed the alternative dispute resolution methods that are now
instrument or instruments. Similarly, a written agreement of rightfully vaunted as the wave of the future in international
which there are two copies, one signed by each of the parties, is relations, is recognized worldwide. To brush aside a contractual
binding on both to the same extent as though there had been agreement calling for arbitration in case of disagreement
only one copy of the agreement and both had signed it. [14] between the parties would therefore be a step backward.

The flaw in petitioners contentions therefore lies in its WHEREFORE, the questioned Decision of the Court of
having segmented the various components of the whole Appeals is hereby AFFIRMED and the petition
contract between the parties into several parts. This for certiorariDENIED. This Decision is immediately
notwithstanding, petitioner ironically admits the execution of the executory. Costs against petitioner.
Articles of Agreement. Notably, too, the lower court found that
the said Articles of Agreement also provides that the `Contract
Documents therein listed `shall be deemed an integral part of SO ORDERED.
this Agreement, and one of the said documents is the
`Conditions of Contract which contains the Arbitration Clause. It EN BANCG.R. No. L-27010 April 30, 1969
is this Articles of Agreement that was duly signed by Rufo B.
Colayco, president of private respondent SPI, and Bayani F.
MARLENE DAUDEN-HERNAEZ, petitioner,
Fernando, president of petitioner corporation. The same
vs.
agreement was duly subscribed before notary public Nilberto R.
HON. WALFRIDO DE LOS ANGELES, Judge of the Court of
Briones. In other words, the subscription of the principal
First Instance of Quezon City, HOLLYWOOD FAR EAST
agreement effectively covered the other documents
PRODUCTIONS, INC., and RAMON
incorporated by reference therein.
VALENZUELA, respondents.

This Court likewise does not find that the Court of Appeals
REYES, J.B.L., Acting C.J.:
erred in ruling that private respondents were not in default in
invoking the provisions of the arbitration clause which states
that (t)he demand for arbitration shall be made within a Petition for a writ of certiorari to set aside certain orders of the
reasonable time after the dispute has arisen and attempts to Court of First Instance of Quezon City (Branch IV), in its Civil
settle amicably had failed. Under the factual milieu, private Case No. Q-10288, dismissing a complaint for breach of contract
respondent SPI should have paid its liabilities under the contract and damages, denying reconsideration, refusing to admit an
in accordance with its terms. However, misunderstandings amended complaint, and declaring the dismissal final and
appeared to have cropped up between the parties ostensibly unappealable.
brought about by either delay in the completion of the
construction work or by force majeure or the fire that partially The essential facts are the following:
gutted the project. The almost two-year delay in paying its
liabilities may not therefore be wholly ascribed to private
respondent SPI. Petitioner Marlene Dauden-Hernaez, a motion picture actress,
had filed a complaint against herein private respondents,
Hollywood Far East Productions, Inc., and its President and
Besides, private respondent SPIs initiative in calling for a General Manager, Ramon Valenzuela, to recover P14,700.00
conference between the parties was a step towards the agreed representing a balance allegedly due said petitioner for her
resort to arbitration. However, petitioner posthaste filed the services as leading actress in two motion pictures produced by
complaint before the lower court. Thus, while private respondent the company, and to recover damages. Upon motion of
SPIs request for arbitration on August 13, 1993 might appear an defendants, the respondent court (Judge Walfrido de los Angeles
afterthought as it was made after it had filed the motion to presiding) ordered the complaint dismissed, mainly because the
suspend proceedings, it was because petitioner also appeared to "claim of plaintiff was not evidenced by any written document,
97
either public or private", and the complaint "was defective on its pleading once as a matter of course, that is, without
face" for violating Articles 1356 and 1358 of the Civil, Code of leave of court, at any time before a responsive pleading
the Philippines, as well as for containing defective allege, is served. A motion to dismiss is not a "responsive
petitions. Plaintiff sought reconsideration of the dismissal and pleading". (Moran on the Rules of Court, vol. 1, 1952,
for admission of an amended complaint, attached to the motion. ed., p. 376). As plaintiffs amended their complaint
The court denied reconsideration and the leave to amend; before it was answered, the motion to admit the
whereupon, a second motion for reconsideration was filed. amendment should not have been denied. It is true
Nevertheless, the court also denied it for being pro forma, as its that the amendment was presented after the original
allegations "are, more or less, the same as the first motion", and complaint had been ordered dismissed. But that order
for not being accompanied by an affidavit of merits, and further was not yet final for it was still under reconsideration.
declared the dismissal final and unappealable. In view of the
attitude of the Court of First Instance, plaintiff resorted to this The foregoing observations leave this Court free to discuss the
Court. main issue in this petition. Did the court below abuse its
discretion in ruling that a contract for personal services
The answer sets up the defense that "the proposed amended involving more than P500.00 was either invalid of unenforceable
complaint did not vary in any material respect from the original under the last paragraph of Article 1358 of the Civil Code of the
complaint except in minor details, and suffers from the same Philippines?
vital defect of the original complaint", which is the violation of
Article 1356 of the Civil Code, in that the contract sued upon We hold that there was abuse, since the ruling herein contested
was not alleged to be in writing; that by Article 1358 the writing betrays a basic and lamentable misunderstanding of the role of
was absolute and indispensable, because the amount involved the written form in contracts, as ordained in the present Civil
exceeds five hundred pesos; and that the second motion for Code.
reconsideration did not interrupt the period for appeal, because
it was not served on three days' notice.
In the matter of formalities, the contractual system of our Civil
Code still follows that of the Spanish Civil Code of 1889 and of
We shall take up first the procedural question. It is a well the "Ordenamiento de Alcala" 2 of upholding the spirit and intent
established rule in our jurisprudence that when a court sustains of the parties over formalities: hence, in general, contracts are
a demurrer or motion to dismiss it is error for the court to valid and binding from their perfection regardless of form
dismiss the complaint without giving the party plaintiff an whether they be oral or written. This is plain from Articles 1315
opportunity to amend his complaint if he so chooses. 1 Insofar as and 1356 of the present Civil Code. Thus, the first cited
the first order of dismissal (Annex D, Petition) did not provide provision prescribes:
that the same was without prejudice to amendment of the
complaint, or reserve to the plaintiff the right to amend his
complaint, the said order was erroneous; and this error was ART. 1315. Contracts are perfected by mere consent,
compounded when the motion to accept the amended complaint and from that moment the parties are bound not only
was denied in the subsequent order of 3 October 1966 (Annex F, to the fulfillment of what has been expressly stipulated
Petition). Hence, the petitioner-plaintiff was within her rights in but also to all the consequences which, according to
filing her so-called second motion for reconsideration, which was their nature, may be in keeping with good faith, usage
actually a first motion against the refusal to admit the amended and law. (Emphasis supplied)
complaint.
Concordantly, the first part of Article 1356 of the Code Provides:
It is contended that the second motion for reconsideration was
merely pro forma and did not suspend the period to appeal from ART. 1356. Contracts shall be obligatory in whatever
the first order of dismissal (Annex D) because (1) it merely form they may have been entered into, provided all the
reiterated the first motion for reconsideration and (2) it was filed essential requisites for their validity are present....
without giving the counsel for defendant-appellee the 3 days' (Emphasis supplied)
notice provided by the rules. This argument is not tenable, for
the reason that the second motion for reconsideration was
These essential requisites last mentioned are normally (1)
addressed to the court' refusal to allow an amendment to the
consent (2) proper subject matter, and (3) consideration
original complaint, and this was a ground not invoked in the first
or causa for the obligation assumed (Article 1318). 3 So that once
motion for reconsideration. Thus, the second motion to
the three elements exist, the contract is generally valid and
reconsider was really not pro forma, as it was based on a
obligatory, regardless of the form, oral or written, in which they
different ground, even if in its first part it set forth in greater
are couched.lawphi1.nt
detail the arguments against the correctness of the first order to
dismiss. And as to the lack of 3 days' notice, the record shows
that appellees had filed their opposition (in detail) to the second To this general rule, the Code admits exceptions, set forth in the
motion to reconsider (Answer, Annex 4); so that even if it were second portion of Article 1356:
true that respondents were not given the full 3 days' notice they
were not deprived of any substantial right. Therefore, the claim However, when the law requires that a contract be in
that the first order of dismissal had become final and some form in order that it may be valid or enforceable,
unappealable must be overruled. or that a contract be proved in a certain way, that
requirement is absolute and indispensable....
It is well to observe in this regard that since a motion to dismiss
is not a responsive pleading, the plaintiff-petitioner was entitled It is thus seen that to the general rule that the form (oral or
as of right to amend the original dismissed complaint. In Paeste written) is irrelevant to the binding effect inter partes of a
vs. Jaurigue 94 Phil. 179, 181, this Court ruled as follows: contract that possesses the three validating elements of
consent, subject matter, and causa, Article 1356 of the Code
Appellants contend that the lower court erred in not establishes only two exceptions, to wit:
admitting their amended complaint and in holding that
their action had already prescribed. Appellants are right (a) Contracts for which the law itself requires that they be in
on both counts. some particular form (writing) in order to make them valid and
enforceable (the so-called solemn contracts). Of these the
Amendments to pleadings are favored and should be typical example is the donation of immovable property that the
liberally allowed in the furtherance of justice. (Torres vs. law (Article 749) requires to be embodied in a public instrument
Tomacruz, 49 Phil. 913). Moreover, under section 1 of in order "that the donation may be valid", i.e., existing or
Rule 17, Rules of Court, a party may amend his binding. Other instances are the donation of movables worth
98
more than P5,000.00 which must be in writing, "otherwise the installation of Liquefied Petroleum Gas (LPG) Cylinder
donation shall be void" (Article 748); contracts to pay interest on manufacturing plants, while private respondent Pacific General
loans (mutuum) that must be "expressly stipulated in writing" Steel Manufacturing Corp. (PGSMC) is a domestic corporation.
(Article 1956); and the agreements contemplated by Article
1744, 1773, 1874 and 2134 of the present Civil Code. On March 5, 1997, PGSMC and KOGIES executed a
Contract[1] whereby KOGIES would set up an LPG Cylinder
Manufacturing Plant in Carmona, Cavite. The contract was
(b) Contracts that the law requires to be proved by some writing executed in the Philippines. On April 7, 1997, the parties
(memorandum) of its terms, as in those covered by the old executed, in Korea, an Amendment for Contract No. KLP-970301
Statute of Frauds, now Article 1403(2) of the Civil Code. Their dated March 5, 1997[2]amending the terms of payment. The
existence not being provable by mere oral testimony (unless contract and its amendment stipulated that KOGIES will ship the
wholly or partly executed), these contracts are exceptional in machinery and facilities necessary for manufacturing LPG
requiring a writing embodying the terms thereof for their cylinders for which PGSMC would pay USD 1,224,000. KOGIES
enforceability by action in court. would install and initiate the operation of the plant for which
PGSMC bound itself to pay USD 306,000 upon the plants
production of the 11-kg. LPG cylinder samples. Thus, the total
The contract sued upon by petitioner herein (compensation for contract price amounted to USD 1,530,000.
services) does not come under either exception. It is true that it
appears included in Article 1358, last clause, providing that "all On October 14, 1997, PGSMC entered into a Contract of
other contracts where the amount involved exceeds five Lease[3] with Worth Properties, Inc. (Worth) for use of Worths
hundred pesos must appear in writing, even a private one." But 5,079-square meter property with a 4,032-square meter
Article 1358 nowhere provides that the absence of written form warehouse building to house the LPG manufacturing plant. The
in this case will make the agreement invalid or unenforceable. monthly rental was PhP 322,560 commencing on January 1,
On the contrary, Article 1357 clearly indicates that contracts 1998 with a 10% annual increment clause. Subsequently, the
covered by Article 1358 are binding and enforceable by action or machineries, equipment, and facilities for the manufacture of
LPG cylinders were shipped, delivered, and installed in the
suit despite the absence of writing.
Carmona plant. PGSMC paid KOGIES USD 1,224,000.

ART. 1357. If the law requires a document or other However, gleaned from the Certificate[4] executed by
special form, as in the acts and contracts enumerated the parties on January 22, 1998, after the installation of the
in the following article, the contracting parties may plant, the initial operation could not be conducted as PGSMC
compel each other to observe that form, once the encountered financial difficulties affecting the supply of
contract has been perfected. This right may be materials, thus forcing the parties to agree that KOGIES would
exercised simultaneously with the action the contract. be deemed to have completely complied with the terms and
conditions of the March 5, 1997 contract.
(Emphasis supplied) .
For the remaining balance of USD306,000 for the
It thus becomes inevitable to conclude that both the court a installation and initial operation of the plant, PGSMC issued two
quo as well as the private respondents herein were grossly postdated checks: (1) BPI Check No. 0316412 dated January 30,
mistaken in holding that because petitioner Dauden's contract 1998 for PhP 4,500,000; and (2) BPI Check No. 0316413 dated
for services was not in writing the same could not be sued upon, March 30, 1998 for PhP 4,500,000.[5]
or that her complaint should be dismissed for failure to state a
cause of action because it did not plead any written agreement. When KOGIES deposited the checks, these were
dishonored for the reason PAYMENT STOPPED. Thus, on May 8,
1998, KOGIES sent a demand letter [6] to PGSMC threatening
The basic error in the court's decision lies in overlooking that in criminal action for violation of Batas Pambansa Blg. 22 in case of
our contractual system it is not enough that the law should nonpayment. On the same date, the wife of PGSMCs President
require that the contract be in writing, as it does in Article 1358. faxed a letter dated May 7, 1998 to KOGIES President who was
The law must further prescribe that without the writing the then staying at a Makati City hotel. She complained that not
contract is not valid or not enforceable by action. only did KOGIES deliver a different brand of hydraulic press from
that agreed upon but it had not delivered several equipment
parts already paid for.
WHEREFORE, the order dismissing the complaint is set aside,
and the case is ordered remanded to the court of origin for On May 14, 1998, PGSMC replied that the two checks it
further proceedings not at variance with this decision. issued KOGIES were fully funded but the payments were stopped
for reasons previously made known to KOGIES.[7]
Costs to be solidarity paid by private respondents Hollywood Far
On June 1, 1998, PGSMC informed KOGIES that PGSMC
East Productions, Inc., and Ramon Valenzuela.
was canceling their Contract dated March 5, 1997 on the ground
SECOND DIVISION G.R. No. 143581 January 7, 2008 that KOGIES had altered the quantity and lowered the quality of
the machineries and equipment it delivered to PGSMC, and that
KOREA TECHNOLOGIES CO., Petitioner,- versus - HON. PGSMC would dismantle and transfer the machineries,
ALBERTO A. LERMA, his capacity as Presiding Judge equipment, and facilities installed in the Carmona plant. Five
of Branch 256 of Regional Trial days later, PGSMC filed before the Office of the Public Prosecutor
Court of Muntinlupa City, andPACIFIC GENERAL STEEL an Affidavit-Complaint for Estafa docketed as I.S. No. 98-03813
MANUFACTURINGCORPORATION,Respondents. against Mr. Dae Hyun Kang, President of KOGIES.

On June 15, 1998, KOGIES wrote PGSMC informing the


VELASCO, JR., J.: latter that PGSMC could not unilaterally rescind their contract
nor dismantle and transfer the machineries and equipment on
In our jurisdiction, the policy is to favor alternative methods of mere imagined violations by KOGIES.It also insisted that their
resolving disputes, particularly in civil and commercial disputes should be settled by arbitration as agreed upon in
disputes. Arbitration along with mediation, conciliation, and Article 15, the arbitration clause of their contract.
negotiation, being inexpensive, speedy and less hostile methods
have long been favored by this Court. The petition before us On June 23, 1998, PGSMC again wrote KOGIES
puts at issue an arbitration clause in a contract mutually agreed reiterating the contents of its June 1, 1998 letter threatening
upon by the parties stipulating that they would submit that the machineries, equipment, and facilities installed in the
themselves to arbitration in a foreign country. Regrettably, plant would be dismantled and transferred on July 4, 1998. Thus,
instead of hastening the resolution of their dispute, the parties on July 1, 1998, KOGIES instituted an Application for Arbitration
wittingly or unwittingly prolonged the controversy. before the Korean Commercial Arbitration Board (KCAB)
in Seoul, Korea pursuant to Art. 15 of the Contract as amended.
Petitioner Korea Technologies Co., Ltd. (KOGIES) is a
Korean corporation which is engaged in the supply and On July 3, 1998, KOGIES filed a Complaint for Specific
Performance, docketed as Civil Case No. 98-117[8] against
99
PGSMC before the Muntinlupa City Regional Trial Court supply of all the machinery and facilities and transfer of
(RTC). The RTC granted a temporary restraining order (TRO) technology for a total contract price of USD 1,530,000 such that
on July 4, 1998, which was subsequently extended until July 22, the dismantling and transfer of the machinery and facilities
1998. In its complaint, KOGIES alleged that PGSMC had initially would result in the dismantling and transfer of the very plant
admitted that the checks that were stopped were not funded but itself to the great prejudice of KOGIES as the still unpaid
later on claimed that it stopped payment of the checks for the owner/seller of the plant. Moreover, KOGIES points out that the
reason that their value was not received as the former allegedly arbitration clause under Art. 15 of the Contract as amended was
breached their contract by altering the quantity and lowering a valid arbitration stipulation under Art. 2044 of the Civil Code
the quality of the machinery and equipment installed in the and as held by this Court in Chung Fu Industries (Phils.), Inc.[15]
plant and failed to make the plant operational although it earlier
certified to the contrary as shown in a January 22, 1998 In the meantime, PGSMC filed a Motion for Inspection of
Certificate. Likewise, KOGIES averred that PGSMC violated Art. Things[16] to determine whether there was indeed alteration of
15 of their Contract, as amended, by unilaterally rescinding the the quantity and lowering of quality of the machineries and
contract without resorting to arbitration. KOGIES also asked that equipment, and whether these were properly installed. KOGIES
PGSMC be restrained from dismantling and transferring the opposed the motion positing that the queries and issues raised
machinery and equipment installed in the plant which the latter in the motion for inspection fell under the coverage of the
threatened to do on July 4, 1998. arbitration clause in their contract.

On July 9, 1998, PGSMC filed an opposition to the TRO On September 21, 1998, the trial court issued an Order
arguing that KOGIES was not entitled to the TRO since Art. 15, (1) granting PGSMCs motion for inspection; (2) denying KOGIES
the arbitration clause, was null and void for being against public motion for reconsideration of the July 23, 1998 RTC Order; and
policy as it ousts the local courts of jurisdiction over the instant (3) denying KOGIES motion to dismiss PGSMCs compulsory
controversy. counterclaims as these counterclaims fell within the requisites of
compulsory counterclaims.
On July 17, 1998, PGSMC filed its Answer with
Compulsory Counterclaim[9] asserting that it had the full right to On October 2, 1998, KOGIES filed an Urgent Motion for
dismantle and transfer the machineries and equipment because Reconsideration[17] of the September 21, 1998 RTC Order
it had paid for them in full as stipulated in the contract; that granting inspection of the plant and denying dismissal of
KOGIES was not entitled to the PhP 9,000,000 covered by the PGSMCs compulsory counterclaims.
checks for failing to completely install and make the plant
operational; and that KOGIES was liable for damages amounting Ten days after, on October 12, 1998, without waiting for
to PhP 4,500,000 for altering the quantity and lowering the the resolution of its October 2, 1998 urgent motion for
quality of the machineries and equipment. Moreover, PGSMC reconsideration, KOGIES filed before the Court of Appeals (CA) a
averred that it has already paid PhP 2,257,920 in rent (covering petition for certiorari[18] docketed as CA-G.R. SP No. 49249,
January to July 1998) to Worth and it was not willing to further seeking annulment of the July 23, 1998 and September 21, 1998
shoulder the cost of renting the premises of the plant RTC Orders and praying for the issuance of writs of prohibition,
considering that the LPG cylinder manufacturing plant never mandamus, and preliminary injunction to enjoin the RTC and
became operational. PGSMC from inspecting, dismantling, and transferring the
machineries and equipment in the Carmona plant, and to direct
After the parties submitted their Memoranda, on July the RTC to enforce the specific agreement on arbitration to
23, 1998, the RTC issued an Order denying the application for a resolve the dispute.
writ of preliminary injunction, reasoning that PGSMC had paid
KOGIES USD 1,224,000, the value of the machineries and In the meantime, on October 19, 1998, the RTC denied
equipment as shown in the contract such that KOGIES no longer KOGIES urgent motion for reconsideration and directed the
had proprietary rights over them. And finally, the RTC held that Branch Sheriff to proceed with the inspection of the machineries
Art. 15 of the Contract as amended was invalid as it tended to and equipment in the plant on October 28, 1998.[19]
oust the trial court or any other court jurisdiction over any
dispute that may arise between the parties. KOGIES prayer for Thereafter, KOGIES filed a Supplement to the
an injunctive writ was denied. [10] The dispositive portion of the Petition[20] in CA-G.R. SP No. 49249 informing the CA about
Order stated: the October 19, 1998 RTC Order. It also reiterated its prayer for
the issuance of the writs of prohibition, mandamus and
preliminary injunction which was not acted upon by the
WHEREFORE, in view of the foregoing consideration, CA. KOGIES asserted that the Branch Sheriff did not have the
this Court believes and so holds that no cogent reason technical expertise to ascertain whether or not the machineries
exists for this Court to grant the writ of preliminary and equipment conformed to the specifications in the contract
injunction to restrain and refrain defendant from and were properly installed.
dismantling the machineries and facilities at the lot and
building of Worth Properties, Incorporated at Carmona, On November 11, 1998, the Branch Sheriff filed his
Cavite and transfer the same to another site: and Sheriffs Report[21] finding that the enumerated machineries and
therefore denies plaintiffs application for a writ of equipment were not fully and properly installed.
preliminary injunction.
The Court of Appeals affirmed the trial court and
declared
the arbitration clause against public policy
On July 29, 1998, KOGIES filed its Reply to Answer and
Answer to Counterclaim.[11] KOGIES denied it had altered the
quantity and lowered the quality of the machinery, equipment, On May 30, 2000, the CA rendered the assailed
and facilities it delivered to the plant. It claimed that it had Decision[22] affirming the RTC Orders and dismissing the petition
performed all the undertakings under the contract and had for certiorari filed by KOGIES. The CA found that the RTC did not
already produced certified samples of LPG cylinders. It averred gravely abuse its discretion in issuing the assailed July 23,
that whatever was unfinished was PGSMCs fault since it failed to 1998 and September 21, 1998 Orders. Moreover, the CA
procure raw materials due to lack of funds. KOGIES, relying reasoned that KOGIES contention that the total contract price for
on Chung Fu Industries (Phils.), Inc. v. Court of Appeals, USD 1,530,000 was for the whole plant and had not been fully
[12]
insisted that the arbitration clause was without question paid was contrary to the finding of the RTC that PGSMC fully paid
valid. the price of USD 1,224,000, which was for all the machineries
and equipment. According to the CA, this determination by the
After KOGIES filed a Supplemental Memorandum with RTC was a factual finding beyond the ambit of a petition for
Motion to Dismiss[13] answering PGSMCs memorandum of July certiorari.
22, 1998 and seeking dismissal of PGSMCs counterclaims,
KOGIES, on August 4, 1998,filed its Motion for On the issue of the validity of the arbitration clause, the
Reconsideration[14] of the July 23, 1998 Order denying its CA agreed with the lower court that an arbitration clause which
application for an injunctive writ claiming that the contract was provided for a final determination of the legal rights of the
not merely for machinery and facilities worth USD 1,224,000 but parties to the contract by arbitration was against public policy.
was for the sale of an LPG manufacturing plant consisting of
100
On the issue of nonpayment of docket fees and non- dated July 17, 1998 in accordance with Section 8 of Rule 11,
attachment of a certificate of non-forum shopping by PGSMC, 1997 Revised Rules of Civil Procedure, the rule that was
the CA held that the counterclaims of PGSMC were compulsory effective at the time the Answer with Counterclaim was
ones and payment of docket fees was not required since the filed. Sec. 8 on existing counterclaim or cross-claim states, A
Answer with counterclaim was not an initiatory pleading. For the compulsory counterclaim or a cross-claim that a defending party
same reason, the CA said a certificate of non-forum shopping has at the time he files his answer shall be contained therein.
was also not required.

Furthermore, the CA held that the petition for certiorari On July 17, 1998, at the time PGSMC filed its Answer
had been filed prematurely since KOGIES did not wait for the incorporating its counterclaims against KOGIES, it was not liable
resolution of its urgent motion for reconsideration of the to pay filing fees for said counterclaims being compulsory in
September 21, 1998 RTC Order which was the plain, speedy, and nature. We stress, however, that effective August 16,
adequate remedy available. According to the CA, the RTC must 2004 under Sec. 7, Rule 141, as amended by A.M. No. 04-2-04-
be given the opportunity to correct any alleged error it has SC, docket fees are now required to be paid in compulsory
committed, and that since the assailed orders were counterclaim or cross-claims.
interlocutory, these cannot be the subject of a petition for
certiorari. As to the failure to submit a certificate of forum
shopping, PGSMCs Answer is not an initiatory pleading which
Hence, we have this Petition for Review on Certiorari requires a certification against forum shopping under Sec. 5 [24] of
under Rule 45. Rule 7, 1997 Revised Rules of Civil Procedure. It is a responsive
pleading, hence, the courts a quo did not commit reversible
The Issues error in denying KOGIES motion to dismiss PGSMCs compulsory
counterclaims.
Petitioner posits that the appellate court committed the
following errors: Interlocutory orders proper subject of certiorari
a. PRONOUNCING THE QUESTION OF OWNERSHIP OVER
THE MACHINERY AND FACILITIES AS A QUESTION OF Citing Gamboa v. Cruz,[25] the CA also pronounced that
FACT BEYOND THE AMBIT OF A PETITION FOR certiorari and Prohibition are neither the remedies to question
CERTIORARI INTENDED ONLY FOR CORRECTION OF the propriety of an interlocutory order of the trial court. [26] The
ERRORS OF JURISDICTION OR GRAVE ABUSE OF CA erred on its reliance on Gamboa.Gamboa involved the denial
DISCRETION AMOUNTING TO LACK OF (SIC) EXCESS OF of a motion to acquit in a criminal case which was not assailable
JURISDICTION, AND CONCLUDING THAT THE TRIAL in an action for certiorari since the denial of a motion to quash
COURTS FINDING ON THE SAME QUESTION WAS required the accused to plead and to continue with the trial, and
IMPROPERLY RAISED IN THE PETITION BELOW; whatever objections the accused had in his motion to quash can
then be used as part of his defense and subsequently can be
b. DECLARING AS NULL AND VOID THE ARBITRATION raised as errors on his appeal if the judgment of the trial court is
CLAUSE IN ARTICLE 15 OF THE CONTRACT BETWEEN adverse to him. The general rule is that interlocutory orders
THE PARTIES FOR BEING CONTRARY TO PUBLIC POLICY cannot be challenged by an appeal. [27] Thus, in Yamaoka v.
AND FOR OUSTING THE COURTS OF JURISDICTION; Pescarich Manufacturing Corporation, we held:

c. DECREEING PRIVATE RESPONDENTS The proper remedy in such cases is an


COUNTERCLAIMS TO BE ALL COMPULSORY NOT ordinary appeal from an adverse
NECESSITATING PAYMENT OF DOCKET FEES AND judgment on the merits, incorporating in said appeal
CERTIFICATION OF NON-FORUM SHOPPING; the grounds for assailing the interlocutory
orders. Allowing appeals from interlocutory orders
d. RULING THAT THE PETITION WAS FILED would result in the sorry spectacle of a case being
PREMATURELY WITHOUT WAITING FOR THE subject of a counterproductive ping-pong to and from
RESOLUTION OF THE MOTION FOR RECONSIDERATION the appellate court as often as a trial court is perceived
OF THE ORDER DATED SEPTEMBER 21, 1998 OR to have made an error in any of its interlocutory
WITHOUT GIVING THE TRIAL COURT AN OPPORTUNITY rulings. However, where the assailed interlocutory
TO CORRECT ITSELF; order was issued with grave abuse of discretion or
patently erroneous and the remedy of appeal would not
e. PROCLAIMING THE TWO ORDERS DATED afford adequate and expeditious relief, the Court allows
JULY 23 AND SEPTEMBER 21, 1998 NOT TO BE PROPER certiorari as a mode of redress.[28]
SUBJECTS OF CERTIORARI AND PROHIBITION FOR BEING
INTERLOCUTORY IN NATURE;
Also, appeals from interlocutory orders would open the
f. NOT GRANTING THE RELIEFS AND floodgates to endless occasions for dilatory motions. Thus,
REMEDIES PRAYED FOR IN HE (SIC) PETITION AND, where the interlocutory order was issued without or in excess of
INSTEAD, DISMISSING THE SAME FOR ALLEGEDLY jurisdiction or with grave abuse of discretion, the remedy is
WITHOUT MERIT.[23] certiorari.[29]

The alleged grave abuse of discretion of the respondent


The Courts Ruling court equivalent to lack of jurisdiction in the issuance of the two
assailed orders coupled with the fact that there is no plain,
The petition is partly meritorious. speedy, and adequate remedy in the ordinary course of law
amply provides the basis for allowing the resort to a petition for
Before we delve into the substantive issues, we shall certiorari under Rule 65.
first tackle the procedural issues.
Prematurity of the petition before the CA
The rules on the payment of docket fees for
counterclaims Neither do we think that KOGIES was guilty of forum
and cross claims were amended effective August 16, shopping in filing the petition for certiorari. Note that KOGIES
2004 motion for reconsideration of the July 23, 1998 RTC Order which
denied the issuance of the injunctive writ had already been
KOGIES strongly argues that when PGSMC filed the denied. Thus, KOGIES only remedy was to assail the RTCs
counterclaims, it should have paid docket fees and filed a interlocutory order via a petition for certiorari under Rule 65.
certificate of non-forum shopping, and that its failure to do so
was a fatal defect. While the October 2, 1998 motion for reconsideration of
KOGIES of the September 21, 1998 RTC Order relating to the
We disagree with KOGIES. inspection of things, and the allowance of the compulsory
counterclaims has not yet been resolved, the circumstances in
As aptly ruled by the CA, the counterclaims of PGSMC this case would allow an exception to the rule that before
were incorporated in its Answer with Compulsory Counterclaim certiorari may be availed of, the petitioner must have filed a
101
motion for reconsideration and said motion should have been Court of Appeals, we held that [i]n this jurisdiction, arbitration
first resolved by the court a quo. The reason behind the rule is has been held valid and constitutional. Even before the approval
to enable the lower court, in the first instance, to pass upon and on June 19, 1953 of Republic Act No. 876, this Court has
correct its mistakes without the intervention of the higher court. countenanced the settlement of disputes through
[30]
arbitration. Republic Act No. 876 was adopted to supplement the
New Civil Codes provisions on arbitration. [39] And in LM Power
The September 21, 1998 RTC Order directing the Engineering Corporation v. Capitol Industrial Construction
branch sheriff to inspect the plant, equipment, and facilities Groups, Inc., we declared that:
when he is not competent and knowledgeable on said matters is
evidently flawed and devoid of any legal support. Moreover, Being an inexpensive, speedy and amicable
there is an urgent necessity to resolve the issue on the method of settling disputes, arbitrationalong with
dismantling of the facilities and any further delay would mediation, conciliation and negotiationis encouraged
prejudice the interests of KOGIES. Indeed, there is real and by the Supreme Court. Aside from unclogging judicial
imminent threat of irreparable destruction or substantial dockets, arbitration also hastens the resolution of
damage to KOGIES equipment and machineries. We find the disputes, especially of the commercial kind. It is thus
resort to certiorari based on the gravely abusive orders of the regarded as the wave of the future in international civil
trial court sans the ruling on the October 2, 1998 motion for and commercial disputes. Brushing aside a contractual
reconsideration to be proper. agreement calling for arbitration between the parties
would be a step backward.
The Core Issue: Article 15 of the Contract
Consistent with the above-mentioned policy of
We now go to the core issue of the validity of Art. 15 of encouraging alternative dispute resolution methods,
the Contract, the arbitration clause. It provides: courts should liberally construe arbitration clauses.
Provided such clause is susceptible of an interpretation
Article 15. Arbitration.All disputes, that covers the asserted dispute, an order to arbitrate
controversies, or differences which may arise between should be granted. Any doubt should be resolved in
the parties, out of or in relation to or in connection with favor of arbitration.[40]
this Contract or for the breach thereof, shall finally be
settled by arbitration in Seoul, Korea in accordance with
the Commercial Arbitration Rules of the Korean Having said that the instant arbitration clause is not
Commercial Arbitration Board. The award rendered against public policy, we come to the question on what governs
by the arbitration(s) shall be final and an arbitration clause specifying that in case of any dispute
binding upon both parties concerned. (Emphasis arising from the contract, an arbitral panel will be constituted in
supplied.) a foreign country and the arbitration rules of the foreign country
would govern and its award shall be final and binding.

Petitioner claims the RTC and the CA erred in ruling that RA 9285 incorporated the UNCITRAL Model law
the arbitration clause is null and void. to which we are a signatory

Petitioner is correct.
For domestic arbitration proceedings, we have
Established in this jurisdiction is the rule that the law of particular agencies to arbitrate disputes arising from contractual
the place where the contract is made governs. Lex loci relations. In case a foreign arbitral body is chosen by the parties,
contractus. The contract in this case was perfected here in the arbitration rules of our domestic arbitration bodies would not
the Philippines. Therefore, our laws ought to be applied. As signatory to the Arbitration Rules of the UNCITRAL
govern. Nonetheless, Art. 2044 of the Civil Code sanctions the Model Law on International Commercial Arbitration [41] of
validity of mutually agreed arbitral clause or the finality and the United Nations Commission on International Trade Law
binding effect of an arbitral award. Art. 2044 provides, Any (UNCITRAL) in the New York Convention on June 21, 1985,
stipulation that the arbitrators award or decision shall be the Philippines committed itself to be bound by the Model
final, is valid, without prejudice to Articles 2038, 2039 and Law. We have even incorporated the Model Law in Republic Act
2040. (Emphasis supplied.) No. (RA) 9285, otherwise known as the Alternative Dispute
Resolution Act of 2004 entitled An Act to Institutionalize the Use
Arts. 2038,[31] 2039,[32] and 2040[33] abovecited refer to of an Alternative Dispute Resolution System in the Philippines
instances where a compromise or an arbitral award, as applied and to Establish the Office for Alternative Dispute Resolution,
to Art. 2044 pursuant to Art. 2043,[34] may be voided, rescinded, and for Other Purposes, promulgated on April 2, 2004. Secs. 19
or annulled, but these would not denigrate the finality of the and 20 of Chapter 4 of the Model Law are the pertinent
arbitral award. provisions:

The arbitration clause was mutually and voluntarily CHAPTER 4 - INTERNATIONAL COMMERCIAL
agreed upon by the parties. It has not been shown to be ARBITRATION
contrary to any law, or against morals, good customs, public
order, or public policy. There has been no showing that the SEC. 19. Adoption of the Model Law on
parties have not dealt with each other on equal footing. We find International Commercial Arbitration.International
no reason why the arbitration clause should not be respected commercial arbitration shall be governed by the Model
and complied with by both parties. In Gonzales v. Climax Mining Law on International Commercial Arbitration (the Model
Ltd.,[35] we held that submission to arbitration is a contract and Law) adopted by the United Nations Commission on
that a clause in a contract providing that all matters in dispute International Trade Law on June 21, 1985 (United
between the parties shall be referred to arbitration is a contract. Nations Document A/40/17) and recommended for
[36]
Again in Del Monte Corporation-USA v. Court of Appeals, we enactment by the General Assembly in Resolution No.
likewise ruled that [t]he provision to submit to arbitration any 40/72 approved on December 11, 1985, copy of which
dispute arising therefrom and the relationship of the parties is is hereto attached as Appendix A.
part of that contract and is itself a contract. [37]
SEC. 20. Interpretation of Model Law.In
Arbitration clause not contrary to public policy interpreting the Model Law, regard shall be had to its
international origin and to the need for uniformity in its
The arbitration clause which stipulates that the interpretation and resort may be made to the travaux
arbitration must be done in Seoul, Korea in accordance with the preparatories and the report of the Secretary General
Commercial Arbitration Rules of the KCAB, and that the arbitral of the United Nations Commission on International
award is final and binding, is not contrary to public policy. This Trade Law dated March 25, 1985 entitled, International
Court has sanctioned the validity of arbitration clauses in Commercial Arbitration: Analytical Commentary on
a catena of cases. In the 1957 case of Eastboard Navigation Ltd. Draft Trade identified by reference number A/CN. 9/264.
v. Juan Ysmael and Co., Inc.,[38] this Court had occasion to rule
that an arbitration clause to resolve differences and breaches of
mutually agreed contractual terms is valid. In BF Corporation v.
102
While RA 9285 was passed only in 2004, it nonetheless A foreign arbitral award, when confirmed by the Regional Trial
applies in the instant case since it is a procedural law which has Court, shall be enforced in the same manner as final and
a retroactive effect. Likewise, KOGIES filed its application for executory decisions of courts of law of the Philippines
arbitration before the KCAB on July 1, 1998 and it is still pending
because no arbitral award has yet been rendered. Thus, RA 9285 xxxx
is applicable to the instant case. Well-settled is the rule that
procedural laws are construed to be applicable to actions SEC. 47. Venue and Jurisdiction.Proceedings for recognition
pending and undetermined at the time of their passage, and are and enforcement of an arbitration agreement or for vacations,
deemed retroactive in that sense and to that extent. As a setting aside, correction or modification of an arbitral award,
general rule, the retroactive application of procedural laws does and any application with a court for arbitration assistance and
not violate any personal rights because no vested right has yet supervision shall be deemed as special proceedings and shall
attached nor arisen from them.[42] be filed with the Regional Trial Court (i) where arbitration
proceedings are conducted; (ii) where the asset to be
Among the pertinent features of RA 9285 applying and attached or levied upon, or the act to be enjoined is located;
incorporating the UNCITRAL Model Law are the following: (iii) where any of the parties to the dispute resides or has his
place of business; or (iv) in the National Judicial Capital
(1) The RTC must refer to arbitration in proper cases Region, at the option of the applicant.

Under Sec. 24, the RTC does not have jurisdiction over SEC. 48. Notice of Proceeding to Parties.In a special
disputes that are properly the subject of arbitration pursuant to proceeding for recognition and enforcement of an arbitral
an arbitration clause, and mandates the referral to arbitration in award, the Court shall send notice to the parties at their
such cases, thus: address of record in the arbitration, or if any part cannot be
served notice at such address, at such partys last known
SEC. 24. Referral to Arbitration.A court before address. The notice shall be sent al least fifteen (15) days
which an action is brought in a matter which is the before the date set for the initial hearing of the application.
subject matter of an arbitration agreement shall, if at
least one party so requests not later than the pre-trial
conference, or upon the request of both parties It is now clear that foreign arbitral awards when
thereafter, refer the parties to arbitration unless it finds confirmed by the RTC are deemed not as a judgment of a foreign
that the arbitration agreement is null and void, court but as a foreign arbitral award, and when confirmed, are
inoperative or incapable of being performed. enforced as final and executory decisions of our courts of law.

Thus, it can be gleaned that the concept of a final and


binding arbitral award is similar to judgments or awards given
by some of our quasi-judicial bodies, like the National Labor
(2) Foreign arbitral awards must be confirmed by the RTC Relations Commission and Mines Adjudication Board, whose final
judgments are stipulated to be final and binding, but not
Foreign arbitral awards while mutually stipulated by the immediately executory in the sense that they may still be
parties in the arbitration clause to be final and binding are not judicially reviewed, upon the instance of any party. Therefore,
immediately enforceable or cannot be implemented the final foreign arbitral awards are similarly situated in that
immediately. Sec. 35[43] of the UNCITRAL Model Law stipulates they need first to be confirmed by the RTC.
the requirement for the arbitral award to be recognized by a
competent court for enforcement, which court under Sec. 36 of (3) The RTC has jurisdiction to review foreign arbitral
the UNCITRAL Model Law may refuse recognition or enforcement awards
on the grounds provided for. RA 9285 incorporated these
provisos to Secs. 42, 43, and 44 relative to Secs. 47 and 48, Sec. 42 in relation to Sec. 45 of RA 9285 designated
thus: and vested the RTC with specific authority and jurisdiction to set
aside, reject, or vacate a foreign arbitral award on grounds
SEC. 42. Application of the New York Convention.The New York provided under Art. 34(2) of the UNCITRAL Model Law. Secs. 42
Convention shall govern the recognition and enforcement of and 45 provide:
arbitral awards covered by said Convention.
SEC. 42. Application of the New York Convention.The New
The recognition and enforcement of such arbitral awards shall York Convention shall govern the recognition and enforcement
be filed with the Regional Trial Court in accordance with the of arbitral awards covered by said Convention.
rules of procedure to be promulgated by the Supreme Court.
Said procedural rules shall provide that the party relying on The recognition and enforcement of such arbitral awards
the award or applying for its enforcement shall file with the shall be filed with the Regional Trial Court in accordance with
court the original or authenticated copy of the award and the the rules of procedure to be promulgated by the Supreme
arbitration agreement. If the award or agreement is not made Court. Said procedural rules shall provide that the party relying
in any of the official languages, the party shall supply a duly on the award or applying for its enforcement shall file with the
certified translation thereof into any of such languages. court the original or authenticated copy of the award and the
arbitration agreement. If the award or agreement is not made
The applicant shall establish that the country in which foreign in any of the official languages, the party shall supply a duly
arbitration award was made in party to the New York certified translation thereof into any of such languages.
Convention.
The applicant shall establish that the country in which
xxxx foreign arbitration award was made is party to the New York
Convention.
SEC. 43. Recognition and Enforcement of Foreign Arbitral
Awards Not Covered by the New York Convention.The If the application for rejection or suspension of
recognition and enforcement of foreign arbitral awards not enforcement of an award has been made, the Regional Trial
covered by the New York Convention shall be done in Court may, if it considers it proper, vacate its decision and may
accordance with procedural rules to be promulgated by the also, on the application of the party claiming recognition or
Supreme Court. The Court may, on grounds of comity and enforcement of the award, order the party to provide
reciprocity, recognize and enforce a non-convention award as appropriate security.
a convention award.
xxxx
SEC. 44. Foreign Arbitral Award Not Foreign Judgment.A
foreign arbitral award when confirmed by a court of a foreign SEC. 45. Rejection of a Foreign Arbitral Award.A party to a
country, shall be recognized and enforced as a foreign arbitral foreign arbitration proceeding may oppose an application for
award and not as a judgment of a foreign court. recognition and enforcement of the arbitral award in
accordance with the procedures and rules to be promulgated
by the Supreme Court only on those grounds enumerated
103
under Article V of the New York Convention. Any other ground Finally, it must be noted that there is nothing in the
raised shall be disregarded by the Regional Trial Court. subject Contract which provides that the parties may dispense
with the arbitration clause.

Unilateral rescission improper and illegal


Thus, while the RTC does not have jurisdiction over
disputes governed by arbitration mutually agreed upon by the Having ruled that the arbitration clause of the subject
parties, still the foreign arbitral award is subject to judicial contract is valid and binding on the parties, and not contrary to
review by the RTC which can set aside, reject, or vacate it. In public policy; consequently, being bound to the contract of
this sense, what this Court held in Chung Fu Industries (Phils.), arbitration, a party may not unilaterally rescind or terminate the
Inc. relied upon by KOGIES is applicable insofar as the foreign contract for whatever cause without first resorting to arbitration.
arbitral awards, while final and binding, do not oust courts of What this Court held in University of the Philippines v.
jurisdiction since these arbitral awards are not absolute and De Los Angeles[47] and reiterated in succeeding cases,[48] that the
without exceptions as they are still judicially reviewable. Chapter act of treating a contract as rescinded on account of infractions
7 of RA 9285 has made it clear that all arbitral awards, whether by the other contracting party is valid albeit provisional as it can
domestic or foreign, are subject to judicial review on specific be judicially assailed, is not applicable to the instant case on
grounds provided for. account of a valid stipulation on arbitration. Where an
(4) Grounds for judicial review different in domestic and arbitration clause in a contract is availing, neither of the parties
foreign arbitral awards can unilaterally treat the contract as rescinded since whatever
infractions or breaches by a party or differences arising from the
The differences between a final arbitral award from an contract must be brought first and resolved by arbitration, and
international or foreign arbitral tribunal and an award given by a not through an extrajudicial rescission or judicial action.
local arbitral tribunal are the specific grounds or conditions that
vest jurisdiction over our courts to review the awards. The issues arising from the contract between PGSMC
and KOGIES on whether the equipment and machineries
For foreign or international arbitral awards which must delivered and installed were properly installed and
first be confirmed by the RTC, the grounds for setting aside, operational in the plant in Carmona, Cavite; the ownership of
rejecting or vacating the award by the RTC are provided under equipment and payment of the contract price; and whether
Art. 34(2) of the UNCITRAL Model Law. there was substantial compliance by KOGIES in the production of
the samples, given the alleged fact that PGSMC could not supply
For final domestic arbitral awards, which also need the raw materials required to produce the sample LPG cylinders,
confirmation by the RTC pursuant to Sec. 23 of RA 876[44] and are matters proper for arbitration. Indeed, we note that on July
shall be recognized as final and executory decisions of the RTC, 1, 1998, KOGIES instituted an Application for Arbitration before
[45]
they may only be assailed before the RTC and vacated on the the KCAB in Seoul, Korea pursuant to Art. 15 of the Contract as
grounds provided under Sec. 25 of RA 876.[46] amended. Thus, it is incumbent upon PGSMC to abide by its
commitment to arbitrate.
(5) RTC decision of assailed foreign arbitral award
appealable Corollarily, the trial court gravely abused its discretion
in granting PGSMCs Motion for Inspection of Things
Sec. 46 of RA 9285 provides for an appeal before the on September 21, 1998, as the subject matter of the motion is
CA as the remedy of an aggrieved party in cases where the RTC under the primary jurisdiction of the mutually agreed arbitral
sets aside, rejects, vacates, modifies, or corrects an arbitral body, the KCAB in Korea.
award, thus: In addition, whatever findings and conclusions made by
the RTC Branch Sheriff from the inspection made on October 28,
1998, as ordered by the trial court on October 19, 1998, is of no
SEC. 46. Appeal from Court Decision or worth as said Sheriff is not technically competent to ascertain
Arbitral Awards.A decision of the Regional Trial Court the actual status of the equipment and machineries as installed
confirming, vacating, setting aside, modifying or in the plant.
correcting an arbitral award may be appealed to the
Court of Appeals in accordance with the rules and For these reasons, the September 21, 1998 and
procedure to be promulgated by the Supreme Court. October 19, 1998 RTC Orders pertaining to the grant of the
inspection of the equipment and machineries have to be
The losing party who appeals from the recalled and nullified.
judgment of the court confirming an arbitral award
shall be required by the appellate court to post a Issue on ownership of plant proper for arbitration
counterbond executed in favor of the prevailing party
equal to the amount of the award in accordance with Petitioner assails the CA ruling that the issue petitioner raised on
the rules to be promulgated by the Supreme Court. whether the total contract price of USD 1,530,000 was for the
whole plant and its installation is beyond the ambit of a Petition
Thereafter, the CA decision may further be appealed or for Certiorari.
reviewed before this Court through a petition for review under
Rule 45 of the Rules of Court. Petitioners position is untenable.
PGSMC has remedies to protect its interests
It is settled that questions of fact cannot be raised in an original
Thus, based on the foregoing features of RA 9285, action for certiorari.[49] Whether or not there was full payment for
PGSMC must submit to the foreign arbitration as it bound itself the machineries and equipment and installation is indeed a
through the subject contract. While it may have misgivings on factual issue prohibited by Rule 65.
the foreign arbitration done in Koreaby the KCAB, it has
available remedies under RA 9285. Its interests are duly However, what appears to constitute a grave abuse of discretion
protected by the law which requires that the arbitral award that is the order of the RTC in resolving the issue on the ownership of
may be rendered by KCAB must be confirmed here by the RTC the plant when it is the arbitral body (KCAB) and not the RTC
before it can be enforced. which has jurisdiction and authority over the said issue. The
RTCs determination of such factual issue constitutes grave
With our disquisition above, petitioner is correct in its abuse of discretion and must be reversed and set aside.
contention that an arbitration clause, stipulating that the arbitral
award is final and binding, does not oust our courts of
jurisdiction as the international arbitral award, the award of
which is not absolute and without exceptions, is still judicially RTC has interim jurisdiction to protect the rights of the
reviewable under certain conditions provided for by parties
the UNCITRAL Model Law on ICA as applied and incorporated
in RA 9285. Anent the July 23, 1998 Order denying the issuance of
the injunctive writ paving the way for PGSMC to dismantle and
transfer the equipment and machineries, we find it to be in
order considering the factual milieu of the instant case.
104
Firstly, while the issue of the proper installation of the
equipment and machineries might well be under the primary Art. 17 J of UNCITRAL Model Law on ICA also grants courts
jurisdiction of the arbitral body to decide, yet the RTC under Sec. power and jurisdiction to issue interim measures:
28 of RA 9285 has jurisdiction to hear and grant interim
measures to protect vested rights of the parties. Sec. 28 Article 17 J. Court-ordered interim measures
pertinently provides:
A court shall have the same power of issuing an interim
SEC. 28. Grant of interim Measure of Protection.(a) It is not measure in relation to arbitration proceedings, irrespective of
incompatible with an arbitration agreement for a party whether their place is in the territory of this State, as it has in
to request, before constitution of the tribunal, from a relation to proceedings in courts. The court shall exercise such
Court to grant such measure. After constitution of the power in accordance with its own procedures in consideration
arbitral tribunal and during arbitral proceedings, a request for of the specific features of international arbitration.
an interim measure of protection, or modification thereof, may
be made with the arbitral or to the extent that the arbitral
tribunal has no power to act or is unable to act In the recent 2006 case of Transfield Philippines, Inc. v. Luzon
effectivity, the request may be made with the Hydro Corporation, we were explicit that even the pendency
Court. The arbitral tribunal is deemed constituted when the of an arbitral proceeding does not foreclose resort to the
sole arbitrator or the third arbitrator, who has been courts for provisional reliefs. We explicated this way:
nominated, has accepted the nomination and written
communication of said nomination and acceptance has been As a fundamental point, the pendency of arbitral proceedings
received by the party making the request. does not foreclose resort to the courts for provisional reliefs.
The Rules of the ICC, which governs the parties arbitral
(b) The following rules on interim or provisional relief shall be dispute, allows the application of a party to a judicial authority
observed: for interim or conservatory measures. Likewise, Section 14 of
Republic Act (R.A.) No. 876 (The Arbitration Law) recognizes
Any party may request that provisional relief be granted the rights of any party to petition the court to take measures
against the adverse party. to safeguard and/or conserve any matter which is the subject
of the dispute in arbitration. In addition, R.A. 9285, otherwise
Such relief may be granted: known as the Alternative Dispute Resolution Act of 2004,
allows the filing of provisional or interim measures with the
(i) to prevent irreparable loss or injury; regular courts whenever the arbitral tribunal has no power to
(ii) to provide security for the performance of any obligation; act or to act effectively.[50]
(iii) to produce or preserve any evidence; or
(iv) to compel any other appropriate act or omission.
It is thus beyond cavil that the RTC has authority and
(c) The order granting provisional relief may be conditioned jurisdiction to grant interim measures of protection.
upon the provision of security or any act or omission specified
in the order. Secondly, considering that the equipment and
machineries are in the possession of PGSMC, it has the right to
(d) Interim or provisional relief is requested by written protect and preserve the equipment and machineries in the best
application transmitted by reasonable means to the Court or way it can. Considering that the LPG plant was non-operational,
arbitral tribunal as the case may be and the party against PGSMC has the right to dismantle and transfer the equipment
whom the relief is sought, describing in appropriate detail the and machineries either for their protection and preservation or
precise relief, the party against whom the relief is requested, for the better way to make good use of them which is
the grounds for the relief, and the evidence supporting the ineluctably within the management discretion of PGSMC.
request.
Thirdly, and of greater import is the reason that
(e) The order shall be binding upon the parties. maintaining the equipment and machineries in Worths property
is not to the best interest of PGSMC due to the prohibitive rent
(f) Either party may apply with the Court for assistance in while the LPG plant as set-up is not operational. PGSMC was
implementing or enforcing an interim measure ordered by an losing PhP322,560 as monthly rentals or PhP3.87M for 1998
arbitral tribunal. alone without considering the 10% annual rent increment in
maintaining the plant.
(g) A party who does not comply with the order shall be liable
for all damages resulting from noncompliance, including all Fourthly, and corollarily, while the KCAB can rule on
expenses, and reasonable attorney's fees, paid in obtaining motions or petitions relating to the preservation or transfer of
the orders judicial enforcement. (Emphasis ours.) the equipment and machineries as an interim measure, yet on
hindsight, the July 23, 1998 Order of the RTC allowing the
transfer of the equipment and machineries given the non-
Art. 17(2) of the UNCITRAL Model Law on ICA defines an recognition by the lower courts of the arbitral clause, has
interim measure of protection as: accorded an interim measure of protection to PGSMC which
would otherwise been irreparably damaged.
Article 17. Power of arbitral tribunal to order interim measures
Fifth, KOGIES is not unjustly prejudiced as it has already
xxx xxx xxx been paid a substantial amount based on the
contract. Moreover, KOGIES is amply protected by the arbitral
(2) An interim measure is any temporary measure, whether action it has instituted before the KCAB, the award of which can
in the form of an award or in another form, by which, at any be enforced in our jurisdiction through the RTC. Besides, by our
time prior to the issuance of the award by which the dispute is decision, PGSMC is compelled to submit to arbitration pursuant
finally decided, the arbitral tribunal orders a party to: to the valid arbitration clause of its contract with KOGIES.

(a) Maintain or restore the status quo pending determination PGSMC to preserve the subject equipment and
of the dispute; machineries

(b) Take action that would prevent, or refrain from taking Finally, while PGSMC may have been granted the right
action that is likely to cause, current or imminent harm or to dismantle and transfer the subject equipment and
prejudice to the arbitral process itself; machineries, it does not have the right to convey or dispose of
the same considering the pending arbitral proceedings to settle
(c) Provide a means of preserving assets out of which a the differences of the parties. PGSMC therefore must preserve
subsequent award may be satisfied; or and maintain the subject equipment and machineries with the
diligence of a good father of a family[51] until final resolution of
(d) Preserve evidence that may be relevant and material to the arbitral proceedings and enforcement of the award, if any.
the resolution of the dispute.
105
On 17 April 1986, the Lopez family, through counsel, ex-Senator
Lorenzo Tanada, requested President Aquino to order the return
WHEREFORE, this petition is PARTLY GRANTED, in to the Lopez family of TV Stations 2 and 4. 1
that:

(1) The May 30, 2000 CA Decision in CA-G.R. SP No. On 13 June 1986, the Lopez family made a written request to
49249 is REVERSED and SET ASIDE; the PCGG for the return of TV Station Channel 2. On 18 June
1986, the PCGG approved the return of TV Station Channel 2 to
(2) The September 21, 1998 and October 19, 1998 RTC the Lopez family. 2 The return was made on 18 October 1986.
Orders in Civil Case No. 98-117 are REVERSED and SET ASIDE;
Thereafter, the Lopez family requested for the return of TV
(3) The parties are hereby ORDERED to submit
Station Channel 4. Acting upon the request, respondent
themselves to the arbitration of their dispute and differences
arising from the subject Contract before the KCAB; and Executive Secretary, by authority of the President, entered into
with the ABS-CBN Broadcasting Corporation, represented by its
(4) PGSMC is hereby ALLOWED to dismantle and President, Eugenio Lopez, Jr., an "Agreement to
transfer the equipment and machineries, if it had not done so, Arbitrate", 3 pursuant to which an Arbitration Committee was
and ORDERED to preserve and maintain them until the finality created, composed of Atty. Catalino Macaraig, Jr., for the
of whatever arbitral award is given in the arbitration Republic of the Philippines, Atty. Pastor del Rosario, for ABS-CBN,
proceedings. and retired Justice Vicente Abad Santos, as Chairman.

No pronouncement as to costs.SO ORDERED.


EN BANCG.R. No. 78389 October 16, 1989 Thereupon, petitioners,as taxpayers, filed the instant petition.

JOSE LUIS MARTIN C. GASCON, FAUSTINO "BONG" L. Before discussing the issues raised in the present petition, the
LAPIRA, and SPOUSES ALBERTO and KARLA Court will first resolve the question of whether or not the herein
LIM, petitioners, petitioners have the legal personality or standing to the the
vs. instant case.
The Hon. JOKER T. ARROYO, in his official capacity as
Executive Secretary to the President, Hon. TEODORO C. There have been several cases wherein the Court recognized
BENIGNO, as Press Secretary, Hon. REINERIO REYES, as the right of a taxpayer to file an action questioning the validity
the Secretary of Transportation and Communication, or constitutionality of a statute or law, on the theory that the
Hon. JOSE ALCUAZ, as Chairman of the National expenditure of public funds by an officer of the government for
Telecommunications Commission, Hon. CONRADO A. the purpose of administering or implementing an
LIMCAOCO, JR., as the Officer-in-Charge of the People's unconstitutional or invalid law, constitutes a misapplication of
Television 4, ABS-CBN BROADCASTING CORPORATION, such funds. 4
and MESSRS. VICENTE ABAD SANTOS, PASTOR DEL
ROSARIO and CATALINO MACARAIG, JR., in their
The present case, however, is not an action to question the
respective capacities as Chairman and Members of the
constitutionality or validity of a statute or law. It is an action to
"Arbitration Committee", respondents.
annul and set aside the "Agreement to Arbitrate", which, as
between the parties, is contractual in character. Petitioners have
not shown that they have a legal interest in TV Station Channel
4 and that they will be adversely affected if and when the said
PADILLA, J.: television station is returned to the Lopez family. Petitioners,
therefore, have no legal standing to file the present petition.

In this petition for certiorari and prohibition, with prayer for


issuance of writ of preliminary injunction or temporary In addition, the petition is devoid of merit.
restraining order, petitioners seek to annul and set aside the
"Agreement to Arbitrate" entered into by and between the Under the Provisional Constitution of the Republic of the
Republic of the Philippines, represented by Executive Secretary Philippines also known as the Freedom Constitution), which was
Joker T. Arroyo, and ABS-CBN Broadcasting Corporation, in force and effect when the "Agreement to Arbitrate" was
represented by its President, Eugenio Lopez, Jr., dated 6 January signed by the parties thereto on 6 January 1987, the President
1987, to settle the claims of ABS-CBN for the return of radio and exercised both the legislative and executive powers of the
television stations (TV Station Channel 4), and to enjoin the Government. As Chief Executive, the President was (and even
Arbitration Committee created under the aforesaid agreement now) "assisted by a Cabinet" composed of Ministers (now
from adjudicating the claims of ABS-CBN. Secretaries), who were appointed by and accountable to the
President. 5 In other words, the Members of the cabinet, as
The record discloses the following facts: heads of the various departments, are the assistants and agents
of the Chief Executive, and, except in cases where the Chief
Executive is required by the Constitution or the law to act in
The Lopez family is the owner of two (2) television stations, person, or where the exigencies of the situation demand that he
namely: Channels 2 and 4 which they have operated through the act personally, the multifarious executive and administrative
ABS-CBN Broadcasting Corporation. functions of the Chief Executive are performed by and through
the executive departments, and the acts of the heads of such
When martial law was declared on 21 September 1972, TV departments performed in the regular course of business, are,
Channel 4 was closed by the military; thereafter, its facilities unless disapproved or reprobated by the Chief Executive,
were taken over by the Kanlaon Broadcasting System which presumptively the acts of the Chief Executive. 6
operated it as a commercial TV station.
Respondent Executive Secretary had, therefore, the power and
In 1978, the said TV station and its facilities were taken over by authority to enter into the "Agreement to Arbitrate" with the
the National Media Production Center (NMPC), which operated it ABS- CBN Broadcasting Corporation, as he acted for and in
as the Maharlika Broadcasting System TV 4 (MBS-4). behalf of the President when he signed it; hence, the aforesaid
agreement is valid and binding upon the Republic of the
Philippines, as a party thereto.
After the February 1986 EDSA revolution, the Presidential
Commission on Good Government (PCGG) sequestered the
aforementioned TV Stations, and, thereafter, the Office of Media Moreover, the settlement of controversies is not vested in the
Affairs took over the operation of TV Channel 4. courts of justice alone to the exclusion of other agencies or
106
bodies. Whenever a controversy arises, either or both parties to In October 1994 the appointment of private respondent
the controversy may file the proper action in court. However, MMI as the sole and exclusive distributor of Del Monte products
the parties may also resort to arbitration under RA 876 which is in the Philippines was published in several newspapers in the
a much faster way of settling their controversy, compared to country. Immediately after its appointment, private respondent
how long it would take if they were to go to court. In entering MMI appointed Sabrosa Foods, Inc. (SFI), with the approval of
into the "Agreement to Arbitrate", the Executive branch of the petitioner DMC-USA, as MMIs marketing arm to concentrate on
government merely opted to avail itself of an alternative mode its marketing and selling function as well as to manage its
of settling the claim of the private respondent ABS-CBN critical relationship with the trade.
Broadcasting Corporation for the return of TV Station Channel 4.
Court held that where the government takes property from a On 3 October 1996 private respondents MMI, SFI and MMIs
private landowner for public use without going through the legal Managing Director Liong Liong C. Sy (LILY SY) filed a
process of expropriation or negotiated sale, the aggrieved party Complaint[5] against petitioners DMC-USA, Paul E. Derby, Jr.,
may properly maintain a suit against the government without [6]
Daniel Collins[7] and Luis Hidalgo,[8] and Dewey Ltd.[9] before
thereby violating the doctrine of governmental immunity from the Regional Trial Court of Malabon, Metro Manila. Private
suit without its consent. That is, as it should be, for the doctrine respondents predicated their complaint on the alleged violations
of governmental immunity from suit cannot serve as an by petitioners of Arts. 20,[10] 21[11] and 23[12] of the Civil
instrument for perpetrating an injustice to a citizen. 8 Code. According to private respondents, DMC-USA products
continued to be brought into the country by parallel importers
Finally, neither the "convening of Congress" nor the "recent despite the appointment of private respondent MMI as the sole
declaration of the President that PTV-4 shall remain as the and exclusive distributor of Del Monte products thereby causing
information arm of the government" can render "ineffective and them great embarrassment and substantial damage. They
unenforceable" the "Agreement to Arbitrate" because at the alleged that the products brought into the country by these
time of the signing of the said agreement, the President was importers were aged, damaged, fake or counterfeit, so that in
exercising both the legislative and executive powers of the March 1995 they had to cause, after prior consultation with
Government, and since the "Agreement to Arbitrate" is valid, it Antonio Ongpin, Market Director for Special Markets of Del
is "enforceable and irrevocable, save upon such grounds as exist Monte Philippines, Inc., the publication of a "warning to the
at law for the revocation of any contract." 9 trade" paid advertisement in leading newspapers. Petitioners
DMC-USA and Paul E. Derby, Jr., apparently upset with the
publication, instructed private respondent MMI to stop
WHEREFORE, the petition is DISMISSED.SO ORDERED.
coordinating with Antonio Ongpin and to communicate directly
instead with petitioner DMC-USA through Paul E. Derby, Jr.
SECOND DIVISION[G.R. No. 136154. February 7, 2001]

Private respondents further averred that petitioners


DEL MONTE CORPORATION-USA, PAUL E. DERBY, JR., knowingly and surreptitiously continued to deal with the former
DANIEL COLLINS and LUIS HIDALGO, petitioners, in bad faith by involving disinterested third parties and by
vs. COURT OF APPEALS, JUDGE BIENVENIDO L. proposing solutions which were entirely out of their
REYES in his capacity as Presiding Judge, RTC-Br. control. Private respondents claimed that they had exhausted all
74, Malabon, Metro Manila, MONTEBUENO possible avenues for an amicable resolution and settlement of
MARKETING, INC., LIONG LIONG C. SY and their grievances; that as a result of the fraud, bad faith, malice
SABROSA FOODS, INC., respondents. and wanton attitude of petitioners, they should be held
responsible for all the actual expenses incurred by private
BELLOSILLO, J.: respondents in the delayed shipment of orders which resulted in
the extra handling thereof, the actual expenses and cost of
money for the unused Letters of Credit (LCs) and the substantial
This Petition for Review on certiorari assails the 17 July opportunity losses due to created out-of-stock situations and
1998 Decision[1] of the Court of Appeals affirming the 11 unauthorized shipments of Del Monte-USA products to the
November 1997 Order[2] of the Regional Trial Court which denied Philippine Duty Free Area and Economic Zone; that the bad faith,
petitioners Motion to Suspend Proceedings in Civil Case No. fraudulent acts and willful negligence of petitioners, motivated
2637-MN. It also questions the appellate courts Resolution[3] of by their determination to squeeze private respondents out of the
30 October 1998 which denied petitioners Motion for outstanding and ongoing Distributorship Agreement in favor of
Reconsideration. another party, had placed private respondent LILY SY on
tenterhooks since then; and, that the shrewd and subtle manner
On 1 July 1994, in a Distributorship Agreement, petitioner with which petitioners concocted imaginary violations by private
Del Monte Corporation-USA (DMC-USA) appointed private respondent MMI of the Distributorship Agreement in order to
respondent Montebueno Marketing, Inc. (MMI) as the sole and justify the untimely termination thereof was a subterfuge. For
exclusive distributor of its Del Monte products in the Philippines the foregoing, private respondents claimed, among other reliefs,
for a period of five (5) years, renewable for two (2) consecutive the payment of actual damages, exemplary damages, attorneys
five (5) year periods with the consent of the parties. The fees and litigation expenses.
Agreement provided, among others, for an arbitration clause
which states - On 21 October 1996 petitioners filed a Motion to Suspend
Proceedings[13] invoking the arbitration clause in their
12. GOVERNING LAW AND ARBITRATION[4] Agreement with private respondents.

This Agreement shall be governed by the laws of the State of In a Resolution[14] dated 23 December 1996 the trial court
California and/or, if applicable, the United States of America. All deferred consideration of petitioners Motion to Suspend
disputes arising out of or relating to this Agreement or the Proceedingsas the grounds alleged therein did not constitute the
parties relationship, including the termination thereof, shall be suspension of the proceedings considering that the action was
resolved by arbitration in the City of San Francisco, State of for damages with prayer for the issuance of Writ of Preliminary
California, under the Rules of the American Arbitration Attachment and not on the Distributorship Agreement.
Association. The arbitration panel shall consist of three
members, one of whom shall be selected by DMC-USA, one of On 15 January 1997 petitioners filed a Motion for
whom shall be selected by MMI, and third of whom shall be Reconsideration to which private respondents filed
selected by the other two members and shall have relevant their Comment/Opposition.On 31 January 1997 petitioners filed
experience in the industry x x x x their Reply. Subsequently, private respondents filed an Urgent
Motion for Leave to Admit Supplemental Pleading dated 2 April
107
1997. This Motion was admitted, over petitioners opposition, in the petition to compel arbitration in the United States made the
an Order of the trial court dated 27 June 1997. petition filed before this Court an alternative remedy and, in a
way, an abandonment of the cause they are fighting for here in
the Philippines, thus warranting the dismissal of the present
As a result of the admission of the Supplemental
petition before this Court.
Complaint, petitioners filed on 22 July 1997
a Manifestation adopting their Motion to Suspend Proceedings of
17 October 1996 and Motion for Reconsideration of 14 January There is no doubt that arbitration is valid and constitutional
1997. in our jurisdiction.[21] Even before the enactment of RA 876, this
Court has countenanced the settlement of disputes through
arbitration. Unless the agreement is such as absolutely to close
On 11 November 1997 the Motion to Suspend
the doors of the courts against the parties, which agreement
Proceedings was denied by the trial court on the ground that
would be void, the courts will look with favor upon such
it "will not serve the ends of justice and to allow said suspension
amicable arrangement and will only interfere with great
will only delay the determination of the issues, frustrate the
reluctance to anticipate or nullify the action of the arbitrator.
quest of the parties for a judicious determination of their [22]
Moreover, as RA 876 expressly authorizes arbitration of
respective claims, and/or deprive and delay their rights to seek
domestic disputes, foreign arbitration as a system of settling
redress."[15]
commercial disputes was likewise recognized when the
Philippines adhered to the United Nations "Convention on the
On appeal, the Court of Appeals affirmed the decision of Recognition and the Enforcement of Foreign Arbitral Awards of
the trial court. It held that the alleged damaging acts recited in 1958" under the 10 May 1965 Resolution No. 71 of the Philippine
the Complaint, constituting petitioners causes of action, required Senate, giving reciprocal recognition and allowing enforcement
the interpretation of Art. 21 of the Civil Code [16] and that in of international arbitration agreements between parties of
determining whether petitioners had violated it "would require a different nationalities within a contracting state.[23]
full blown trial" making arbitration "out of the
question."[17]Petitioners Motion for Reconsideration of the
A careful examination of the instant case shows that the
affirmation was denied. Hence, this Petition for Review.
arbitration clause in the Distributorship Agreement between
petitioner DMC-USA and private respondent MMI is valid and the
The crux of the controversy boils down to whether the dispute between the parties is arbitrable. However, this Court
dispute between the parties warrants an order compelling them must deny the petition.
to submit to arbitration.

The Agreement between petitioner DMC-USA and private


Petitioners contend that the subject matter of private respondent MMI is a contract. The provision to submit to
respondents causes of action arises out of or relates to the arbitration any dispute arising therefrom and the relationship of
Agreement between petitioners and private respondents. Thus, the parties is part of that contract and is itself a contract. As a
considering that the arbitration clause of the Agreement rule, contracts are respected as the law between the contracting
provides that all disputes arising out of or relating to the parties and produce effect as between them, their assigns and
Agreement or the parties relationship, including the termination heirs.[24] Clearly, only parties to the Agreement, i.e., petitioners
thereof, shall be resolved by arbitration, they insist on the DMC-USA and its Managing Director for Export Sales Paul E.
suspension of the proceedings in Civil Case No. 2637-MN as Derby, Jr., and private respondents MMI and its Managing
mandated by Sec. 7 of RA 876[18] - Director LILY SY are bound by the Agreement and its arbitration
clause as they are the only signatories thereto. Petitioners
Sec. 7. Stay of Civil Action. If any suit or proceeding be brought Daniel Collins and Luis Hidalgo, and private respondent SFI, not
upon an issue arising out of an agreement providing for parties to the Agreement and cannot even be considered
arbitration thereof, the court in which such suit or proceeding is assigns or heirs of the parties, are not bound by the Agreement
pending, upon being satisfied that the issue involved in such and the arbitration clause therein. Consequently, referral to
suit or proceeding is referable to arbitration, shall stay the arbitration in the State of California pursuant to the arbitration
action or proceeding until an arbitration has been had in clause and the suspension of the proceedings in Civil Case No.
accordance with the terms of the agreement. Provided, That the 2637-MN pending the return of the arbitral award could be
applicant for the stay is not in default in proceeding with such called for[25] but only as to petitioners DMC-USA and Paul E.
arbitration. Derby, Jr., and private respondents MMI and LILY SY, and not as
to the other parties in this case, in accordance with the recent
case of Heirs of Augusto L. Salas, Jr. v. Laperal Realty
Private respondents claim, on the other hand, that their Corporation,[26] which superseded that of Toyota Motor
causes of action are rooted in Arts. 20, 21 and 23 of the Civil Philippines Corp. v. Court of Appeals.[27]
Code,[19]the determination of which demands a full blown trial,
as correctly held by the Court of Appeals. Moreover, they claim
that the issues before the trial court were not joined so that the In Toyota, the Court ruled that "[t]he contention that the
Honorable Judge was not given the opportunity to satisfy himself arbitration clause has become dysfunctional because of the
that the issue involved in the case was referable to presence of third parties is untenable ratiocinating that
arbitration. They submit that, apparently, petitioners filed a "[c]ontracts are respected as the law between the contracting
motion to suspend proceedings instead of sending a written parties"[28] and that "[a]s such, the parties are thereby expected
demand to private respondents to arbitrate because petitioners to abide with good faith in their contractual
were not sure whether the case could be a subject of commitments."[29] However, in Salas, Jr., only parties to the
arbitration. They maintain that had petitioners done so and Agreement, their assigns or heirs have the right to arbitrate or
private respondents failed to answer the demand, petitioners could be compelled to arbitrate. The Court went further by
could have filed with the trial court their demand for arbitration declaring that in recognizing the right of the contracting parties
that would warrant a determination by the judge whether to to arbitrate or to compel arbitration, the splitting of the
refer the case to arbitration. Accordingly, private respondents proceedings to arbitration as to some of the parties on one hand
assert that arbitration is out of the question. and trial for the others on the other hand, or the suspension of
trial pending arbitration between some of the parties, should not
be allowed as it would, in effect, result in multiplicity of suits,
Private respondents further contend that the arbitration duplicitous procedure and unnecessary delay.[30]
clause centers more on venue rather than on arbitration. They
finally allege that petitioners filed their motion for extension of
time to file this petition on the same date [20] petitioner DMC-USA The object of arbitration is to allow the expeditious
filed a petition to compel private respondent MMI to arbitrate determination of a dispute.[31] Clearly, the issue before us could
before the United States District Court in Northern California, not be speedily and efficiently resolved in its entirety if we allow
docketed as Case No. C-98-4446. They insist that the filing of simultaneous arbitration proceedings and trial, or suspension of
108
trial pending arbitration. Accordingly, the interest of justice
would only be served if the trial court hears and adjudicates the
case in a single and complete proceeding.[32] TOYOTA CASE (Civil Case No. 91-2504)

WHEREFORE, the petition is DENIED. The Decision of the On September 11, 1991, Toyota filed a case against APT and Sun
Court of Appeals affirming the Order of the Regional Trial Court Valley docketed as Civil Case No. 91-2504 with the Regional Trial
of Malabon, Metro Manila, in Civil Case No. 2637-MN, which Court of Makati, Branch 146 presided by Judge Salvador
denied petitioners Motion to Suspend Proceedings, is Tensuan. The complaint was for the reformation of the Deed of
AFFIRMED.The Regional Trial Court concerned is directed to Sale executed between Toyota and APT. Toyota alleges that the
proceed with the hearing of Civil Case No. 2637-MN with instrument failed to reflect the true intention of the parties, as
dispatch. No costs.SO ORDERED. evidenced by the failure of the title to include the 723 square
meters strip of land.
THIRD DIVISIONG.R. No. 102881 December 7, 1992
Toyota alleges that the discrepancy came about because of the
TOYOTA MOTOR PHILIPPINES CORPORATION, petitioner, serious flaw in the classification/cataloguing of properties bidded
vs. out for sale by APT. Toyota was made to understand that
THE COURT OF APPEALS, HON. FERNANDO V. GOROSPE, included in its perimeter fence is the disputed strip of land.
JR. and SUN VALLEY MANUFACTURING & DEVELOPMENT Thus, Toyota sought the resurvey of the property to correct this
CORPORATION, respondents. error in the title. Sun Valley was impleaded considering that it
purchased the adjoining land whose title allegedly included the
723 square meters property.
GUTIERREZ, JR., J.:

On September 11, 1991, upon Toyota's application, Judge


This case involves a boundary dispute between Toyota Motor
Tensuan issued a temporary restraining order (TRO) enjoining
Phil. Corporation (Toyota) and Sun Valley Manufacturing and
Sun Valley and APT from any act of destruction and removal of
Development Corporation (Sun Valley).
Toyota's walls and structures. Sun Valley and APT were
respectively served summons on the following day.
Both Toyota and Sun Valley are the registered owners of two (2)
adjoining parcels of land situated in La Huerta, Paraaque, Metro
On September 16, 1991, Sun Valley filed a motion to dismiss, on
Manila which they purchased from the Asset Privatization Trust
the ground that the Toyota complaint failed to state a cause of
(APT).
action against it (1) since it was not a party to the contract of
the deed of sale between Toyota and APT, and (2) the complaint
The properties in question formerly belonged to Delta Motors was in effect a collateral attack on its title.
Corporation (DMC). They were foreclosed by the Philippine
National Bank (PNB) and later transferred to the national
On September 27, 1991, Judge Tensuan initially denied Toyota's
government through the APT for disposition.
application for preliminary injunction on the finding that there
was no evidence of any threatened destruction, removal or
APT then proceeded to classify the DMC properties according to dispossession of Toyota's property.
the existing improvements, i.e., buildings, driveways, parking
areas, perimeter fence, walls and gates and the land on which
On October 10, 1991, Judge Tensuan denied Sun Valley's motion
the improvements stood. The entire DMC property is called GC
to dismiss.
III-Delta Motors Corporation, divided into Delta I, Delta II, and
Delta III. Further subdivisions for the separate catalogues were
made for each division e.g. Delta I into Lots 1, 2 and 3. After this Both Toyota and Sun Valley filed their respective motions for
classification, APT parcelled out and catalogued the properties reconsideration. Toyota moved to reconsider the denial of its
for bidding and sale. injunctive application while Sun Valley moved to reconsider the
denial of its motion to dismiss.
Part of the duly parcelled Delta I property (Lot 2) was sold to
Toyota through public bidding on May 12, 1988 for the amount On October 30, 1991, APT filed its answer with affirmative
of P95,385,000.00. After its purchase, Toyota constructed a defenses alleging that the complaint must be dismissed on the
concrete hollow block (CHB) perimeter fence around its alleged ground that Toyota and APT should first have resorted to
property. arbitration as provided in Toyota's deed of sale with APT. On
December 4, 1991, Toyota filed a motion alleging that Sun
Valley's long threatened destruction and removal of Toyota's
On October 5, 1990, another part of the parcelled Delta I (Lot 1)
walls and structures were actually being implemented to which
covering an area of 55,236 square meters was purchased by
Judge Tensuan issued another TRO enjoining acts of destruction
Sun Valley from APT for the bid price of P124,349,767.00.
and removal of the perimeter walls and structures on the
Relying upon the title description of its property and the surveys
contested area.
it had commissioned, Sun Valley claimed that Toyota's perimeter
fence overlaps Sun Valley's property along corners 11 to 15 by
322 square meters and corners 19 to 1 by 401 square meters Consequently, on December 17, 1991, Judge Tensuan
for a total of 723 square meters. (Rollo, p. 841) reconsidered his earlier denial of Toyota's application for
injunction and granted a writ of preliminary injunction enjoining
Sun Valley from proceeding with its threatened destruction and
Negotiations between the two (2) corporations for a possible
removal of Toyota's walls and directed Sun Valley to restore the
settlement of the dispute bogged down. Court battles ensued,
premises to the status quo ante.
grounded on purely procedural issues. In pursuing the resolution
of the dispute, both Toyota and Sun Valley opted to file separate
actions. Much of the complications that arose and are now On December 11, 1991, Judge Tensuan denied Sun Valley's
before us can be traced to the two separate cases pursued by motion for reconsideration of its motion to dismiss. Sun Valley
both parties. There are other cases arising from the same elevated this denial to the Court of Appeals. The case was
dispute but which are not before us. docketed as CA-G.R. Sp. No. 26942 and raffled to the Eleventh
(11th) Division.
Culled from the records, these are the antecedents of the two
cases which transpired below. Judge Tensuan's jurisdiction to act considering the defense of
prematurity of action for failure to arbitrate the validity of the
109
TRO issued on December 4, 1991 and the order granting Consequently, Toyota filed the present petition for certiorari on
injunctive reliefs were challenged in a petition for certiorari filed December 9, 1991.
with the Court of Appeals and docketed as CA-G.R. No. 26813,
assigned to the Second (2nd) Division. Earlier, upon an ex-parte motion to clarify filed by Sun Valley on
October 25, 1991, Judge Gorospe issued another order dated
December 2, 1991 which followed Sun Valley to break open and
demolish a portion of the Toyota perimeter walls, and eventually
to secure possession of the disputed area. Toyota was
SUN VALLEY CASE (Civil Case No. 91-2550)
constrained to come to this Court for relief.

On September 16, 1991, Sun Valley, on the other hand, filed a


On December 11, 1991, we issued a TRO enjoining the
case for recovery of possession of the disputed 723 square
implementation of Judge Gorospe's injunction and break-open
meters boundary with the Regional Trial Court (RTC) Makati,
orders dated October 1, 1991 and December 2, 1991
Branch 61 presided by Judge Fernando Gorospe, Jr.
respectively as well as further proceedings in Civil Case No. 91-
2550.
On the same day, Judge Gorospe issued a TRO enjoining Toyota
from committing further acts of dispossession against Sun
Meanwhile, the Court of Appeals' Second Division issued a TRO
Valley.
ordering respondent Judge Tensuan and all other persons acting
in his behalf to cease and desist from further proceeding with
On September 19, 1991, Toyota moved to lift the TRO and Civil Case No. 91-2504 and from enforcing the Order dated
opposed Sun Valley's application for injunction. December 17, 1991 and the writ of preliminary mandatory
injunction dated December 19, 1991.
On September 23, 1991, Toyota filed a motion to dismiss on the
ground that the RTC has no jurisdiction over the case since the This prompted Toyota to file a motion to quash the TRO and file
complaint was a simple ejectment case cognizable by the a supplemental petition with this Court impleading the Court of
Metropolitan Trial Court (MTC). The motion to dismiss was set for Appeals' Second Division.
hearing on September 27, 1991.

On January 13, 1992, we admitted the supplemental petition.


On September 27, 1991, Sun Valley filed an amended complaint
to incorporate an allegation that Toyota's possession of the
On January 10, 1992, the Court of Appeals' Second Division
alleged disputed area began in September, 1988 when Toyota
issued the Resolution granting Sun Valley's application for
purchased the property.
preliminary injunction which enjoined Judge Tensuan in the
Toyota case from implementing his injunction Order and from
Ruling that the amendment was a matter of right, Judge Gorospe proceeding with the case before him (Civil Case No. 91-2504).
admitted the amended complaint. Toyota adopted its motion to
dismiss the original complaint as its motion to dismiss the
Thus, Toyota filed its Second Supplemental Petition with this
amended complaint. After the arguments to Toyota's motion to
Court challenging the validity of the injunction writ issued by the
dismiss, the same was submitted for resolution. Sun Valley's
Court of Appeals' Second Division.
application for prohibitory and mandatory injunction contained
in its complaint was set for hearing on October 1, 1991.
This Second Supplemental Petition was admitted on February
10, 1992.
Protesting the admission of the amended complaint, Toyota went
to the Court of Appeals, on certiorari on October 1, 1991. This
petition was docketed as CA-G.R. No. 26152 raffled to the Tenth On February 10, 1992, we gave due course to Toyota's petition.
(10th) Division.
Subsequently, through a manifestation dated April 29, 1992,
Toyota was later prompted to file two supplemental petitions, Toyota informed the Court that on April 15, 1992, the Court of
before the Court of Appeals as a result of Judge Gorospe's Appeals' 11th Division (Sun Valley case) rendered a decision
alleged hasty issuance of four (4) Orders, all dated October 1, dismissing the case before it for lack of merit. The Court of
1992. These are: Appeals ruled that the Toyota complaint was not a collateral
attack on Sun Valley's title and that misjoinder of parties is not a
ground for dismissal.
(1) First supplemental petition dated October 4, 1991 which
sought to nullify the Order denying Toyota's motion to dismiss
the amended complaint. A subsequent motion for reconsideration was denied in a
resolution dated August 10, 1992.
(2) Second supplemental petition dated October 23, 1991 which
sought the nullification of the orders granting Sun Valley's In the instant petition Toyota raises the following issues, to wit:
application for preliminary prohibitory and mandatory injunction
and denying Toyota's motion to cross-examine Sun Valley's 1. The Court of Appeals' 10th Division gravely abused its
witnesses on the latter's injunction application. discretion when it ignored or pretended to ignore Toyota's
protests against Judge Gorospe's injunction orders.
On November 27, 1991, respondent Court of Appeals' Tenth
Division promulgated its questioned decision which is primarily 2. Sun Valley is guilty of forum-shopping and Judge Gorospe of
the subject matter of the present petition before us. case-grabbing.

The respondent court denied due course to the Toyota petition Sun Valley, on the other hand raises the following:
on the finding that the amendment of Sun Valley's complaint
was a valid one as Sun Valley's action was not for unlawful
detainer but an accion publiciana. Furthermore, the 1. Whether or not the petitioner availed of the proper mode of
supplemental petitions filed by Toyota assailing the prohibitory elevating the case to this Court.
and mandatory injunctive writ were not ruled upon as they were
expunged from the records because of Toyota's failure to attach
a motion to admit these supplemental petitions.
110
2. Whether or not the Court of Appeals committed grave abuse dismiss was sustained, correctly ruled that misjoinder of parties
of discretion in refusing to act upon petitioner's supplemental is not a ground for dismissal.
petitions for certiorari.
American jurisprudence from where provisions on reformation of
3. Whether or not the complaint filed in the court below is instruments were taken discloses that suits to reform written
an accion publiciana which is within the jurisdiction of the RTC. instruments are subject to the general rule in equity that all
persons interested in the subject matter of the litigation,
whether it is a legal or an equitable interest should be made
4. Whether or not Judge Salvador S. Tensuan had jurisdiction to
parties, so that the court may settle all their rights at once and
take cognizance of Civil Case No. 2504 for reformation of
thus prevent the necessity of a multiplicity of suits (Bevis
instrument.
Construction Co. v. Grace [Fla App] 115 So 2d 84; Green v.
Stone, 54 N.J.E. 387, 34 A 1099). As a general rule, therefore, all
5. Whether or not respondent Judge Gorospe, Jr. committed persons to be affected by the proposed reformation must be
grave abuse of discretion in granting private respondent's made parties (American Fidelity & Casualty Co. v. Elder, 189 Ga
application for a writ of preliminary prohibitory/mandatory 229, 5 SE 2d 668; Kemp v. Funderburk, 224 NC 353, 30 SE 2d
injunction. 155). In an action to reform a deed, all parties claiming an
interest in the land or any part thereof purportedly conveyed by
6. Whether or not Judge Tensuan committed grave abuse of the instrument sought to be reformed, and whose interests will
discretion in issuing the writ of mandatory injunction dated be affected by the reformation of the instrument are necessary
December 19, 1991. parties to the action (Kemp v. Funderburk, 224 NC 353, 30 SE 2d
155).

This case is far from settlement on the merits. Through legal


maneuverings, the parties have succeeded in muddling up the From the foregoing jurisprudence, it would appear that Toyota
vital issues of the case and getting the lower courts embroiled in was correct in impleading Sun Valley as party defendant.
numerous appeals over technicalities. As it is now, there are However, these principles are not applicable under the
three appellate decisions/resolutions before us for review and particular circumstances of this case. Under the facts of the
conflicting orders issued by lower courts as a result of the present case, Toyota's action for reformation is dismissible as
separate cases filed by the parties. As in the case against Sun Valley.
of Consolidated Bank and Trust Corp. v. Court of Appeal,s 193
SCRA 158 [1991], the Court is explicit in stating that: Attention must first be brought to the fact that the contract of
sale executed between APT and Toyota provides an arbitration
xxx xxx xxx clause which states that:

Where there are conflicting but inextricably interconnected xxx xxx xxx
issues in one and the same complicated case, it is best that
these be resolved in one integrated proceeding where an overall 5. In case of disagreement or conflict arising out of this
picture of the entirety of the case can be presented and Contract, the parties hereby undertake to submit the matter for
examined. Piecemeal determinations by several trial courts on determination by a committee of experts, acting as arbitrators,
segments of the basic issue and disconnected appeals to the composition of which shall be as follows:
different Divisions of the Court of Appeals resulting in separate
decisions each dealing with only part of the problem are
a) One member to be appointed by the VENDOR;
discouraged. Needless multiplicity of suits is something which is
frowned upon.
b) One member to be appointed by the VENDEE;
xxx xxx xxx
c) One member, who shall be a lawyer, to be appointed by both
of the aforesaid parties;
Amid the clutter of extraneous materials which have certainly
bloated the records of this case, we find only two (2) issues vital
to the disposition of the petition: first, is the matter of The members of the Arbitration Committee shall be appointed
jurisdiction, who as between Judge Tensuan or Judge Gorospe not later than three (3) working days from receipt of a written
has jurisdiction over the dispute; and second, who as between notice from either or both parties. The Arbitration Committee
the parties has the rightful possession of the land. shall convene not later than three (3) weeks after all its
members have been appointed and proceed with the
arbitration of the dispute within three (3) calendar months
Anent the issue on jurisdiction, we examine the two actions filed
counted therefrom. By written mutual agreement by the parties
by the parties.
hereto, such time limit for the arbitration may be extended for
another calendar month. The decision of the Arbitration
Toyota filed an action for reformation on September 11, 1991, Committee by majority vote of at least two (2) members shall
before Judge Tensuan alleging that the true intentions of the be final and binding upon both the VENDOR and the VENDEE;
parties were not expressed in the instrument (Art. 1359 Civil (Rollo, pp. 816-817)
Code). The instrument sought to be reformed is the deed of sale
executed by APT in favor of Toyota. Toyota alleges that there
xxx xxx xxx
was a mistake in the designation of the real properties subject
matter of the contract. Sun Valley was impleaded in order to
obtain complete relief since it was the owner of the adjacent lot. The contention that the arbitration clause has become
disfunctional because of the presence of third parties is
untenable.
Sun Valley, however, argues that the complaint for reformation
states no cause of action against it since an action for
reformation is basically one strictly between the parties to the Contracts are respected as the law between the contracting
contract itself. Third persons who are not parties to the contract parties (Mercantile Ins. Co. Inc. v. Felipe Ysmael, Jr. & Co., Inc.,
cannot and should not be involved. Thus, Sun Valley contends 169 SCRA 66 [1989]). As such, the parties are thereby expected
that it should not have been impleaded as a defendant. to abide with good faith in their contractual commitments
(Quillan v. CA, 169 SCRA 279 [1989]). Toyota is therefore bound
to respect the provisions of the contract it entered into with APT.
The Court of Appeals' 11th Division, in its decision promulgated
on April 15, 1992 where the denial of Sun Valley's motion to
111
Toyota filed an action for reformation of its contract with APT, long standing principle that equity follows the law. It is applied in
the purpose of which is to look into the real the abscence of and never against statutory law (Zabat v. Court
intentions/agreement of the parties to the contract and to of Appeals, 142 SCRA 587 [1986]). Courts are bound by rules of
determine if there was really a mistake in the designation of the law and have no arbitrary discretion to disregard them. (See
boundaries of the property as alleged by Toyota. Such questions Arsenal v. Intermediate Appellate Court, 143 SCRA 40 [1986].)
can only be answered by the parties to the contract themselves. Courts of equity must proceed with utmost caution especially
This is a controversy which clearly arose from the contract when rights of third parties may intervene. Thus in the instant
entered into by APT and Toyota. Inasmuch as this concerns more case, vis-a-vis well-settled principles or rules in land registration,
importantly the parties APT and Toyota themselves, the the equitable relief of reformation may not come into play in
arbitration committee is therefore the proper and convenient order to transfer or appropriate a piece of land that one claims
forum to settle the matter as clearly provided in the deed of to own but which is titled in the name of a third party.
sale.
On the other hand, Sun Valley filed an action for reconveyance
Having been apprised of the presence of the arbitration clause against Toyota to recover possession of the strip of land
in the motion to dismiss filed by APT, Judge Tensuan should have encroached upon and occupied by the latter. What Sun Valley
at least suspended the proceedings and directed the parties to seeks in its complaint is the recovery of possession de jure and
settle their dispute by arbitration (Bengson v. Chan, 78 SCRA not merely possession de facto. Toyota moved to dismiss on the
113 [1977], Sec. 7, RA 876). Judge Tensuan should have not assumption that the complaint was one for unlawful detainer
taken cognizance of the case. cognizable by the MTC.

But the more apparent reason which warrants the dismissal of We do not find any reversible error in the decision of the Court
the action as against Sun Valley is the fact that the complaint for of Appeals' 10th Division where it upheld Judge Gorospe's order
reformation amounts to a collateral attack on Sun Valley's title, denying Toyota's motion to dismiss. An amendment to a
contrary to the finding of the Court of Appeals' 11th Division. complaint before a responsive pleading is filed, is a matter of
right (Rule 10, Sec. 2). Whether or not the complaint was
amended, Sun Valley's complaint was one for accion
It is disputed that Sun Valley has a Torrens title registered in its
publiciana cognizable by the RTC. Its right over the land is
name by virtue of its purchase of the land from APT.
premised on the certificate of title registered in its name after it
had purchased said land from APT. As the registered owner it
Toyota contends that the 723 square meters strip of land which had the right of possession of said land illegally occupied by
it understood to be included in its purchase from APT was another (Ybaez v. IAC, 194 SCRA 743 [1991]). The case
erroneously included in Sun Valley's title. This is the reason why of Banayos v. Susana Realty, Inc. (71 SCRA 557 [1976]) is quite
reformation was sought to correct the mistake. instructive:

Well-settled is the rule that a certificate of title can not be xxx xxx xxx
altered, modified, or cancelled except in a direct proceeding in
accordance with law (Section 48, P.D. No. 1529).
We deem it advisable, at this point, to reiterate the essential
differences between three kinds of actions for the recovery of
In the case of Domingo v. Santos Ongsiako, Lim y Sia (55 Phil. possession of real property, namely: (1) the summary action
361 [1930]), the Court held that: for forcible entry and unlawful detainer; (2) the accion
publiciana; and (3) the accion de reivindicacion.
. . . The fact should not be overlooked that we are here
confronted with what is really a collateral attack upon a The action for forcible entry may be brought where
Torrens title. The circumstance that the action was directly dispossession of real property had taken place by any of the
brought to recover a parcel of land does not alter the truth means provided for in Section 1 of Rule 70 of the Revised
that the proceeding involves a collateral attack upon a Rules of Court, and in the case of unlawful detainer, where
Torrens title, because as we have found, the land in the possession is withheld after the expiration or termination
controversy lies within the boundaries determined by that of the right to hold possession, by virtue of any contract
title. The Land Registration Law defines the methods under express or implied. These two actions must be filed within
which a wrongful adjudication of title to land under the one (1) year after such unlawful deprivation or withholding of
Torrens system may be corrected . . . possession with the municipal or city court. These actions in
their essence are mere quieting processes by virtue of which
While reformation may often be had to correct mistakes in a party in possession of land may not be, by force,
defining the boundary of lands conveyed so as to identify the dispossessed of that land, the law restoring to him such
lands, it may not be used to pass other lands from those possession in a summary manner, until the right of
intended to be bought and sold, notwithstanding a mistake in ownership can be tried in due course of law. They are,
pointing out the lines, since reformation under these therefore, intended to provide an expeditious means of
circumstances would be inequitable and unjust. (McCay v. protecting actual possession or right to possession of
Jenkins, 244 Ala 650, 15 So 2d 409, 149 ALR 746) property. The aforesaid Rule 70 does not, however, cover all
of the cases of dispossession of lands. Thus, "whenever the
owner is dispossessed by any other means than those
Assuming that Toyota is afforded the relief prayed for in the mentioned he may maintain his action in the Court of First
Tensuan court, the latter can not validly order the contested Instance, and it is not necessary for him to wait until the
portion to be taken out from the Sun Valley's TCT and award it in expiration of twelve months before commencing an action to
favor of Toyota. be repossessed or declared to be owner of land." (Gumiran v.
Gumiran, 21 Phil. 174, 179. Cf. Medina, et al. v. Valdellon, 63
An action for reformation is in personam, not in rem (Cohen v. SCRA 278) Courts of First Instance have jurisdiction over
Hellman Commercial Trust & Savings Bank, 133 Cal App 758, 24 actions to recover possession of real property illegally
P2d 960; Edwards v. New York Life Ins. Co. 173 Tenn 102, 114 detained, together with rents due and damages, even though
SW 2d 808) even when real estate is involved (Agurs v. Holt, 232 one (1) year has not expired from the beginning of such
La 1026, 95 So 2d 644; Vallee v. Vallee (La App) 180 So 2d 570). illegal detention, provided the question of ownership of such
It is merely an equitable relief granted to the parties where property is also involved. In other words, if the party illegal
through mistake or fraud, the instrument failed to express the dispossessed desires to raise the question of illegal
real agreement or intention of the parties. While it is a dispossession as well as that of the ownership over the
recognized remedy afforded by courts of equity it may not be property, he may commence such action in the Court of First
applied if it is contrary to well-settled principles or rules. It is a Instance immediately or at any time after such illegal
112
dispossession. If he decides to raise the question of illegal As early as September, 1988 prior to the construction of the
dispossession only, and the action is filed more than one (1) perimeter fence, Toyota was already aware of the discrepancies
year after such deprivation or withholding of possession, in the property's description in the title and the actual survey.
then the Court of First Instance will have original jurisdiction
over the case. (Bishop of Cebu v. Mangoron, 6 Phil. 286; The letter of its surveyor company, Summa Kumagai thus
Catholic Church v. Tarlac and Victoria, 9 Phil. 450; Ledesma v. reveals:
Marcos, 9 Phil. 618; Medina, et al. v. Valdellon, supra) The
former is an accion de reivindicacion which seeks the
recovery of ownership as well as possession, while the latter 09 September, 1988
refers to an accion publiciana, which is the recovery of the
right to possess and is a plenary action in an ordinary TOYOTA MOTOR PHILIPPINES CORPORATION
proceeding in the Court of First Instance. (Sec. 88, Rep. Act 10th Floor, Metrobank Plaza
No. 296; Rule 70, Rules of Court; Manila Railroad Co. v. Sen. Gil J. Puyat Ave.
Attorney General, 20 Phil. 523; Lim Cay v. Del, 55 Phil. 692; Makati, Metro Manila
Central Azucarera de Tarlac v. De Leon, 56 Phil. 169; Navarro
v. Aguila, 66 Phil. 604; Luna v. Carandang, 26 SCRA 306;
ATTENTION: MR. FLORENCIO JURADO
Medina, et al. v. Valdellon, supra; Pasaqui, et al. v.
Finance Officer
Villablanca, et al., supra).

SUBJECT: PHASE I RENOVATION WORK


With the finding that Toyota's action for reformation is
PERIMETER FENCE
dismissable as it is in effect a collateral attack on Sun Valley's
title, Sun Valley's action for recovery of possession filed before
Judge Gorospe now stands to be the proper forum where the GENTLEMEN:
following dispute may be tried or heard.
This is in connection with the construction of the Perimeter
We now come to the issue as to which of the parties has a legal Fence for the Toyota Motor Plant Facilities which to this date
right over the property to warrant the issuance of the we have not started yet due to the following reasons:
preliminary mandatory/prohibitory injunction.
1. Lack of fencing permit which can only be applied to and
In actions involving realty, preliminary injunction will lie only issued by the Paraaque Building Official upon receipt of the
after the plaintiff has fully established his title or right thereto by transfer certificate to title and tax declaration.
a proper action for the purpose. To authorize a temporary
injunction, the complainant must make out at least a prima 2. Although the Building Official has verbally instructed us
facie showing of a right to the final relief. Preliminary injunction to proceed with the renovation work and construction of
will not issue to protect a right not in esse (Buayan Cattle Co. fence, we could not execute the fencing work due to
Inc. v. Quintillan, 128 SCRA 286-287 [1984]; Ortigas & Company, discrepancies on the consolidation plan and the existing
Limited Partnership v. Ruiz, 148 SCRA 326 [1987]). property monuments. These discrepancies was (sic)
confirmed with the representatives of the Geodetic
Two requisites are necessary if a preliminary injunction is to Engineer.
issue, namely, the existence of the right to be protected, and
the facts against which the injunction is to be directed, are Kindly expedite the immediate confirmation with the
violative of said right. In particular, for a writ of preliminary Geodetic Engineer on the final descriptions of the property
injunction to issue, the existence of the right and the violation lines.
must appear in the allegations of the complaint and an
injunction is proper also when the plaintiff appears to be entitled
to the relief demanded in his complaint. Furthermore, the We would appreciate your usual prompt attention regarding
complaint for injunctive relief must be construed strictly against this matter.
the pleader (Ortigas & Company, Limited Partnership v.
Ruiz, supra). Very truly yours,

In the instant case the existence of a "clear positive right" CESAR D. ELE
especially calling for judicial protection has been shown by Sun Project Manager (Emphasis supplied, Rollo, p. 811)
Valley.

Despite such notification, Toyota continued to build the


Toyota's claim over the disputed property is anchored on the perimeter fence. It is highly doubtful whether Toyota may be
fact of its purchase of the property from APT, that from the considered a builder in good faith to be entitled to protection
circumstances of the purchase and the intention of the parties, under Article 448 of the Civil Code.
the property including the disputed area was sold to it.

The records also reveal that Toyota's own surveyor, the Certeza
Sun Valley, on the other hand has TCT No. 49019 of the Registry Surveying & Acrophoto Systems, Inc. confirmed in its reports
of Deeds of Paraaque embracing the aforesaid property in its dated April 1 and April 5, 1991 that Toyota's perimeter fence
name, having been validly acquired also from APT by virtue of a overlaps the boundaries of Sun Valley's lot (Rollo, pp. 833-383).
Deed of Sale executed in its favor on December 5, 1990 (Rollo,
pp. 823-825; 826-827).
Even communication exchanges between and among APT,
Toyota & Sun Valley show that the parties are certainly aware
There are other circumstances in the case which militate against that the ownership of the disputed property more properly
Toyota's claim for legal possession over the disputed area. pertains to Sun Valley. Among these are the following:91

The fact that Toyota has filed a suit for reformation seeking the MR. JOSE CH. ALVAREZ
inclusion of the 723 square meters strip of land is sufficient to President
deduce that it is not entitled to take over the piece of property it Sun Valley Manufacturing &
now attempts to appropriate for itself. Development Corp. (SVMDC)
Cor. Aurora Blvd. and Andrews Ave.
Pasay City, Metro Manila
113
Dear Mr. Alvarez: TOYOTA MOTOR PHILIPPINES CORPORATION
Rm. 15, South Superhighway
Paraaque, Metro Manila
Thank you for honoring our invitation to a luncheon meeting
held at noon time today at Sugi Restaurant.
ATTENTION: MR. MASAO MITAKE
President
As per our understanding, we would like to propose as a
package the settlement of differences between your property
and ours as follows: Gentlemen:

1. Boundary Issue between TMP Main Office & Factory and the This refers to our several meetings regarding the property
recently acquired property of SVMDC. problems at "Lot 6" and your encroachment of SVMD LOT I.

The boundary lines to our property lines bidded early 1988 We wish to thank you for finally acknowledging the legitimacy
were determined after making full payment in August 1988 of our demands on both properties. In order to start a good
jointly by representatives of TMP/Metrobank Messrs. Mitake, business relationship, we propose that the property problem
Pedrosa, Alonzo and Jurado, APT Mr. Bince together with at "LOT 6" which consists of the perimeter fence, water
representatives of Geo-Resources who installed the reservoir, water pump and systems be settled first, in the
monuments and prepared the technical description of the amount of P3,500,000.00 payable to CMANC.
property. The construction of the fence utilized existing fence
marked yellow on Exhibit 1 and made sure that the new fence We also would like to request you to allow us to continue
to set boundaries were on top of the monuments set by Geo- usage of the MERALCO posts and lines connecting to SVMD
Resources. The replacement of existing wire fence were power station which passes thru your property and allow entry
affected by setting concrete walls on exactly the same of MERALCO linemen from time to time.
position.

Upon acceptance of these requests, I will confer which our


This is the reason why we are surprised top be informed that Japanese partners to consider the selling of the 723 sq. m. of
our fence goes beyond the boundary lines set forth in the land adjacent to your Assembly Plant which you continue to
Technical Description on the Transfer Certificate of Title (TCT) use even after said property has been legally transferred to
to our property. This occurs even on fence already existing us from last quarter of 1990.
and should have been maintained in the TCT.

In view of your present good behavior, we are hoping that this


Since we have manifested our intention when we set first problem be settled not later than July 15, 1991,
boundaries to our property, we propose the following in otherwise, we will consider the whole matter as unacceptable
relation to the excess area occupied by TMP. to you and we, therefore, proceed as earlier demanded to
immediately demolish the CHB fence that prevents us from
1. We offer to give way to an access road 5 m. wide more or using our property.
less from point 15 to 16 of Lot 2 (14.65 m. in length) at the
back of our Paint Storage Building (Exhibit 2). We hope for your immediate action to start the resolution of
these unwanted problems.
2. We propose to pay for the balance of excess land inside
TMP fence (contested areas) at a price mutually agreed upon. Ver)

II. Question of ownership of certain permanent improvements Moreover, Sun Valley puts forth evidence that Toyota has altered
(underground water reservoir and perimeter walls/fences) the boundaries of its own property by moving the monuments
located at Lot 6 which we won by bidding from APT on erected thereon by APT's surveyor Geo-Resources and
October 5, 1990. Consultancy, Inc. when Lot 2 was initially surveyed in August
1988:
We have made our position to APT that these permanent
improvements are part of Lot 6 on "as is where is" bid basis The Asset Privitalization Trust
(See explanatory map Exhibit 3). However, since you have 10th Floor, BA-Lepanto Building
relayed to us that the underground water reservoir is of no 9847 Paseo de Roxas Building
use to you, as part of the total package we are proposing to Metro Manila
pay for the underground water reservoir, the applicable
perimeter walls/fences and the water pump/pipings at a price
mutually agreed upon. Attention: Mr. Felipe B. Bince, Jr.
Associate Executive Trustee

We hope that through this proposal we would settle our


differences and look forward to a more cooperative Dear Sirs:
relationship between good neighbors.
This has reference to our letter to your office dated April 8,
We will appreciate your favorable consideration and 1991, a copy of which is attached, regarding the check
immediate attention on the matter. survey of Delta I. After asking some of the field men who
participated in the various surveys of Delta I from the
consolidation to subdivision surveys, we found out that
Very truly yours, some more of the present corner points are not the same
points shown to them during the surveys. We shall show
MASAO MITAKE this during a meeting with the representatives of the
President owners of Lots 1 and 2.

We hope this will clarify the discrepancies.

July 4, 1991 (Emphasis supplied; Rollo, p. 839)


114
There is therefore sufficient and convincing proof that Sun Valley proposed master plans and development plans; and
has a clear legal right to possession in its favor to warrant the second, presentation of the preliminary design of the
issuance of a writ of preliminary/mandatory injunction. Sun passenger terminal building. The ADP submitted a Draft
Valley's TCT gives it that right to possession. On the other hand, Final Report to the DOTC in December 1989.
Toyota has not established its right over the said property
except for the assertion that there was a mistake in an Some time in 1993, six business leaders consisting of
instrument which purportedly should have included the John Gokongwei, Andrew Gotianun, Henry Sy, Sr., Lucio
questioned strip of land. Tan, George Ty and Alfonso Yuchengco met with then
President Fidel V. Ramos to explore the possibility of
investing in the construction and operation of a new
As between the two (2) parties, Sun Valley has a better right.
international airport terminal. To signify their
Under the circumstances, therefore, and considering that the commitment to pursue the project, they formed the
clear legal right of Toyota to possession of the disputed area has Asia's Emerging Dragon Corp. (AEDC) which was
not been established sufficient to grant the prayed for relief, a registered with the Securities and Exchange
writ of preliminary mandatory injunction may be Commission (SEC) on September 15, 1993.
issued pendente lite. (See Mara, Inc. v. Estrella, 65 SCRA 471
[1975]; De Gracia v. Santos, 79 Phil. 365 [1947]; Rodulfa v.
On October 5, 1994, AEDC submitted an unsolicited
Alfonso, 76 Phil. 225 [1946] and Torre v. Querubin, 101 Phil. 53
proposal to the Government through the DOTC/MIAA for
[1957]) the development of NAIA International Passenger
Terminal III (NAIA IPT III) under a build-operate-and-
In view of all the foregoing, the petition is hereby DISMISSED for transfer arrangement pursuant to RA 6957 as amended
failure to show reversible error, much less grave abuse of by RA 7718 (BOT Law).1
discretion, on the part of the respondent court.
On December 2, 1994, the DOTC issued Dept. Order No. 94-832
EN BANC constituting the Prequalification Bids and Awards Committee
(PBAC) for the implementation of the NAIA IPT III project.

G.R. No. 155001 May 5, 2003


On March 27, 1995, then DOTC Secretary Jose Garcia endorsed
the proposal of AEDC to the National Economic and
DEMOSTHENES P. AGAN, JR., JOSEPH B. CATAHAN, JOSE Development Authority (NEDA). A revised proposal, however,
MARI B. REUNILLA, MANUEL ANTONIO B. BOE, was forwarded by the DOTC to NEDA on December 13, 1995. On
MAMERTO S. CLARA, REUEL E. DIMALANTA, MORY V. January 5, 1996, the NEDA Investment Coordinating Council
DOMALAON, CONRADO G. DIMAANO, LOLITA R. HIZON, (NEDA ICC) Technical Board favorably endorsed the project to
REMEDIOS P. ADOLFO, BIENVENIDO C. HILARIO, MIASCOR the ICC Cabinet Committee which approved the same, subject
WORKERS UNION - NATIONAL LABOR UNION (MWU-NLU), to certain conditions, on January 19, 1996. On February 13,
and PHILIPPINE AIRLINES EMPLOYEES ASSOCIATION 1996, the NEDA passed Board Resolution No. 2 which approved
(PALEA), petitioners, the NAIA IPT III project.
vs.
PHILIPPINE INTERNATIONAL AIR TERMINALS CO., INC.,
MANILA INTERNATIONAL AIRPORT AUTHORITY, On June 7, 14, and 21, 1996, DOTC/MIAA caused the publication
DEPARTMENT OF TRANSPORTATION AND in two daily newspapers of an invitation for competitive or
COMMUNICATIONS and SECRETARY LEANDRO M. comparative proposals on AEDC's unsolicited proposal, in
MENDOZA, in his capacity as Head of the Department of accordance with Sec. 4-A of RA 6957, as amended. The
Transportation and Communications, respondents, alternative bidders were required to submit three (3) sealed
MIASCOR GROUNDHANDLING CORPORATION, DNATA- envelopes on or before 5:00 p.m. of September 20, 1996. The
WINGS AVIATION SYSTEMS CORPORATION, MACROASIA- first envelope should contain the Prequalification Documents,
EUREST SERVICES, INC., MACROASIA-MENZIES AIRPORT the second envelope the Technical Proposal, and the third
SERVICES CORPORATION, MIASCOR CATERING SERVICES envelope the Financial Proposal of the proponent.
CORPORATION, MIASCOR AIRCRAFT MAINTENANCE
CORPORATION, and MIASCOR LOGISTICS On June 20, 1996, PBAC Bulletin No. 1 was issued, postponing
CORPORATION, petitioners-in-intervention, the availment of the Bid Documents and the submission of the
comparative bid proposals. Interested firms were permitted to
PUNO, J.: obtain the Request for Proposal Documents beginning June 28,
1996, upon submission of a written application and payment of
a non-refundable fee of P50,000.00 (US$2,000).
Petitioners and petitioners-in-intervention filed the instant
petitions for prohibition under Rule 65 of the Revised Rules of
Court seeking to prohibit the Manila International Airport The Bid Documents issued by the PBAC provided among others
Authority (MIAA) and the Department of Transportation and that the proponent must have adequate capability to sustain the
Communications (DOTC) and its Secretary from implementing financing requirement for the detailed engineering, design,
the following agreements executed by the Philippine construction, operation, and maintenance phases of the project.
Government through the DOTC and the MIAA and the Philippine The proponent would be evaluated based on its ability to
International Air Terminals Co., Inc. (PIATCO): (1) the Concession provide a minimum amount of equity to the project, and its
Agreement signed on July 12, 1997, (2) the Amended and capacity to secure external financing for the project.
Restated Concession Agreement dated November 26, 1999, (3)
the First Supplement to the Amended and Restated Concession On July 23, 1996, the PBAC issued PBAC Bulletin No. 2 inviting all
Agreement dated August 27, 1999, (4) the Second Supplement bidders to a pre-bid conference on July 29, 1996.
to the Amended and Restated Concession Agreement dated
September 4, 2000, and (5) the Third Supplement to the
Amended and Restated Concession Agreement dated June 22, On August 16, 1996, the PBAC issued PBAC Bulletin No. 3
2001 (collectively, the PIATCO Contracts). amending the Bid Documents. The following amendments were
made on the Bid Documents:

The facts are as follows:


a. Aside from the fixed Annual Guaranteed Payment,
the proponent shall include in its financial proposal an
In August 1989, the DOTC engaged the services of additional percentage of gross revenue share of the
Aeroport de Paris (ADP) to conduct a comprehensive Government, as follows:
study of the Ninoy Aquino International Airport (NAIA)
and determine whether the present airport can cope
with the traffic development up to the year 2010. The
study consisted of two parts: first, traffic forecasts, i. First 5 years 5.0%
capacity of existing facilities, NAIA future requirements,
115
structured to meet the requirements and needs of their
current respective business undertaking/activities. In
order to comply with this equity requirement, Paircargo
is requesting PBAC to just allow each member of (sic)
corporation of the Joint Venture to just execute an
agreement that embodies a commitment to infuse the
required capital in case the project is awarded to the
ii. Next 10 years 7.5% Joint Venture instead of increasing each corporation's
current authorized capital stock just for prequalification
purposes.

iii. Next 10 years 10.0%


In prequalification, the agency is interested in one's
financial capability at the time of prequalification, not
future or potential capability.

b. The amount of the fixed Annual Guaranteed Payment


shall be subject of the price challenge. Proponent may A commitment to put up equity once awarded the
offer an Annual Guaranteed Payment which need not project is not enough to establish that "present"
be of equal amount, but payment of which shall start financial capability. However, total financial capability
upon site possession. of all member companies of the Consortium, to be
established by submitting the respective companies'
audited financial statements, shall be acceptable.
c. The project proponent must have adequate
capability to sustain the financing requirement for the
detailed engineering, design, construction, and/or 2. At present, Paircargo is negotiating with banks and
operation and maintenance phases of the project as other institutions for the extension of a Performance
the case may be. For purposes of pre-qualification, this Security to the joint venture in the event that the
capability shall be measured in terms of: Concessions Agreement (sic) is awarded to them.
However, Paircargo is being required to submit a copy
of the draft concession as one of the documentary
i. Proof of the availability of the project requirements. Therefore, Paircargo is requesting that
proponent and/or the consortium to provide they'd (sic) be furnished copy of the approved
the minimum amount of equity for the project; negotiated agreement between the PBAC and the
and AEDC at the soonest possible time.

ii. a letter testimonial from reputable banks A copy of the draft Concession Agreement is included in
attesting that the project proponent and/or the the Bid Documents. Any material changes would be
members of the consortium are banking with made known to prospective challengers through bid
them, that the project proponent and/or the bulletins. However, a final version will be issued before
members are of good financial standing, and the award of contract.
have adequate resources.
The PBAC also stated that it would require AEDC to sign
d. The basis for the prequalification shall be the Supplement C of the Bid Documents (Acceptance of Criteria and
proponent's compliance with the minimum technical Waiver of Rights to Enjoin Project) and to submit the same with
and financial requirements provided in the Bid the required Bid Security.
Documents and the IRR of the BOT Law. The minimum
amount of equity shall be 30% of the Project Cost.
On September 20, 1996, the consortium composed of People's
Air Cargo and Warehousing Co., Inc. (Paircargo), Phil. Air and
e. Amendments to the draft Concession Agreement Grounds Services, Inc. (PAGS) and Security Bank Corp. (Security
shall be issued from time to time. Said amendments Bank) (collectively, Paircargo Consortium) submitted their
shall only cover items that would not materially affect competitive proposal to the PBAC. On September 23, 1996, the
the preparation of the proponent's proposal. PBAC opened the first envelope containing the prequalification
documents of the Paircargo Consortium. On the following day,
On August 29, 1996, the Second Pre-Bid Conference was held September 24, 1996, the PBAC prequalified the Paircargo
where certain clarifications were made. Upon the request of Consortium.
prospective bidder People's Air Cargo & Warehousing Co., Inc
(Paircargo), the PBAC warranted that based on Sec. 11.6, Rule On September 26, 1996, AEDC informed the PBAC in writing of
11 of the Implementing Rules and Regulations of the BOT Law, its reservations as regards the Paircargo Consortium, which
only the proposed Annual Guaranteed Payment submitted by include:
the challengers would be revealed to AEDC, and that the
challengers' technical and financial proposals would remain
confidential. The PBAC also clarified that the list of revenue a. The lack of corporate approvals and financial
sources contained in Annex 4.2a of the Bid Documents was capability of PAIRCARGO;
merely indicative and that other revenue sources may be
included by the proponent, subject to approval by DOTC/MIAA. b. The lack of corporate approvals and financial
Furthermore, the PBAC clarified that only those fees and charges capability of PAGS;
denominated as Public Utility Fees would be subject to
regulation, and those charges which would be actually deemed
Public Utility Fees could still be revised, depending on the c. The prohibition imposed by RA 337, as amended (the
outcome of PBAC's query on the matter with the Department of General Banking Act) on the amount that Security Bank
Justice. could legally invest in the project;

In September 1996, the PBAC issued Bid Bulletin No. 5, entitled d. The inclusion of Siemens as a contractor of the
"Answers to the Queries of PAIRCARGO as Per Letter Dated PAIRCARGO Joint Venture, for prequalification purposes;
September 3 and 10, 1996." Paircargo's queries and the PBAC's and
responses were as follows:
e. The appointment of Lufthansa as the facility
1. It is difficult for Paircargo and Associates to meet the operator, in view of the Philippine requirement in the
required minimum equity requirement as prescribed in operation of a public utility.
Section 8.3.4 of the Bid Documents considering that
the capitalization of each member company is so
116
The PBAC gave its reply on October 2, 1996, informing AEDC Government granted PIATCO the franchise to operate and
that it had considered the issues raised by the latter, and that maintain the said terminal during the concession period and to
based on the documents submitted by Paircargo and the collect the fees, rentals and other charges in accordance with
established prequalification criteria, the PBAC had found that the rates or schedules stipulated in the 1997 Concession
the challenger, Paircargo, had prequalified to undertake the Agreement. The Agreement provided that the concession period
project. The Secretary of the DOTC approved the finding of the shall be for twenty-five (25) years commencing from the in-
PBAC. service date, and may be renewed at the option of the
Government for a period not exceeding twenty-five (25) years.
At the end of the concession period, PIATCO shall transfer the
The PBAC then proceeded with the opening of the second
development facility to MIAA.
envelope of the Paircargo Consortium which contained its
Technical Proposal.
On November 26, 1998, the Government and PIATCO signed an
Amended and Restated Concession Agreement (ARCA). Among
On October 3, 1996, AEDC reiterated its objections, particularly
the provisions of the 1997 Concession Agreement that were
with respect to Paircargo's financial capability, in view of the
amended by the ARCA were: Sec. 1.11 pertaining to the
restrictions imposed by Section 21-B of the General Banking Act
definition of "certificate of completion"; Sec. 2.05 pertaining to
and Sections 1380 and 1381 of the Manual Regulations for
the Special Obligations of GRP; Sec. 3.02 (a) dealing with the
Banks and Other Financial Intermediaries. On October 7, 1996,
exclusivity of the franchise given to the Concessionaire; Sec.
AEDC again manifested its objections and requested that it be
4.04 concerning the assignment by Concessionaire of its interest
furnished with excerpts of the PBAC meeting and the
in the Development Facility; Sec. 5.08 (c) dealing with the
accompanying technical evaluation report where each of the
proceeds of Concessionaire's insurance; Sec. 5.10 with respect
issues they raised were addressed.
to the temporary take-over of operations by GRP; Sec. 5.16
pertaining to the taxes, duties and other imposts that may be
On October 16, 1996, the PBAC opened the third envelope levied on the Concessionaire; Sec. 6.03 as regards the periodic
submitted by AEDC and the Paircargo Consortium containing adjustment of public utility fees and charges; the entire Article
their respective financial proposals. Both proponents offered to VIII concerning the provisions on the termination of the contract;
build the NAIA Passenger Terminal III for at least $350 million at and Sec. 10.02 providing for the venue of the arbitration
no cost to the government and to pay the government: 5% proceedings in case a dispute or controversy arises between the
share in gross revenues for the first five years of operation, parties to the agreement.
7.5% share in gross revenues for the next ten years of
operation, and 10% share in gross revenues for the last ten
Subsequently, the Government and PIATCO signed three
years of operation, in accordance with the Bid Documents.
Supplements to the ARCA. The First Supplement was signed on
However, in addition to the foregoing, AEDC offered to pay the
August 27, 1999; the Second Supplement on September 4,
government a total of P135 million as guaranteed payment for
2000; and the Third Supplement on June 22, 2001 (collectively,
27 years while Paircargo Consortium offered to pay the
Supplements).
government a total of P17.75 billion for the same period.

The First Supplement to the ARCA amended Sec. 1.36 of the


Thus, the PBAC formally informed AEDC that it had accepted the
ARCA defining "Revenues" or "Gross Revenues"; Sec. 2.05 (d) of
price proposal submitted by the Paircargo Consortium, and gave
the ARCA referring to the obligation of MIAA to provide sufficient
AEDC 30 working days or until November 28, 1996 within which
funds for the upkeep, maintenance, repair and/or replacement
to match the said bid, otherwise, the project would be awarded
of all airport facilities and equipment which are owned or
to Paircargo.
operated by MIAA; and further providing additional special
obligations on the part of GRP aside from those already
As AEDC failed to match the proposal within the 30-day period, enumerated in Sec. 2.05 of the ARCA. The First Supplement also
then DOTC Secretary Amado Lagdameo, on December 11, 1996, provided a stipulation as regards the construction of a surface
issued a notice to Paircargo Consortium regarding AEDC's failure road to connect NAIA Terminal II and Terminal III in lieu of the
to match the proposal. proposed access tunnel crossing Runway 13/31; the swapping of
obligations between GRP and PIATCO regarding the
improvement of Sales Road; and the changes in the timetable. It
On February 27, 1997, Paircargo Consortium incorporated into
also amended Sec. 6.01 (c) of the ARCA pertaining to the
Philippine International Airport Terminals Co., Inc. (PIATCO).
Disposition of Terminal Fees; Sec. 6.02 of the ARCA by inserting
an introductory paragraph; and Sec. 6.02 (a) (iii) of the ARCA
AEDC subsequently protested the alleged undue preference referring to the Payments of Percentage Share in Gross
given to PIATCO and reiterated its objections as regards the Revenues.
prequalification of PIATCO.
The Second Supplement to the ARCA contained provisions
On April 11, 1997, the DOTC submitted the concession concerning the clearing, removal, demolition or disposal of
agreement for the second-pass approval of the NEDA-ICC. subterranean structures uncovered or discovered at the site of
the construction of the terminal by the Concessionaire. It
defined the scope of works; it provided for the procedure for the
On April 16, 1997, AEDC filed with the Regional Trial Court of
demolition of the said structures and the consideration for the
Pasig a Petition for Declaration of Nullity of the Proceedings,
same which the GRP shall pay PIATCO; it provided for time
Mandamus and Injunction against the Secretary of the DOTC,
extensions, incremental and consequential costs and losses
the Chairman of the PBAC, the voting members of the PBAC and
consequent to the existence of such structures; and it provided
Pantaleon D. Alvarez, in his capacity as Chairman of the PBAC
for some additional obligations on the part of PIATCO as regards
Technical Committee.
the said structures.

On April 17, 1997, the NEDA-ICC conducted an ad referendum to


Finally, the Third Supplement provided for the obligations of the
facilitate the approval, on a no-objection basis, of the BOT
Concessionaire as regards the construction of the surface road
agreement between the DOTC and PIATCO. As the ad
connecting Terminals II and III.
referendum gathered only four (4) of the required six (6)
signatures, the NEDA merely noted the agreement.
Meanwhile, the MIAA which is charged with the maintenance
and operation of the NAIA Terminals I and II, had existing
On July 9, 1997, the DOTC issued the notice of award for the
concession contracts with various service providers to offer
project to PIATCO.
international airline airport services, such as in-flight catering,
passenger handling, ramp and ground support, aircraft
On July 12, 1997, the Government, through then DOTC Secretary maintenance and provisions, cargo handling and warehousing,
Arturo T. Enrile, and PIATCO, through its President, Henry T. Go, and other services, to several international airlines at the NAIA.
signed the "Concession Agreement for the Build-Operate-and- Some of these service providers are the Miascor Group, DNATA-
Transfer Arrangement of the Ninoy Aquino International Airport Wings Aviation Systems Corp., and the MacroAsia Group.
Passenger Terminal III" (1997 Concession Agreement). The Miascor, DNATA and MacroAsia, together with Philippine Airlines
117
(PAL), are the dominant players in the industry with an Petitioners' Legal Standing to File the present Petitions
aggregate market share of 70%.
a. G.R. Nos. 155001 and 155661
On September 17, 2002, the workers of the international airline
service providers, claiming that they stand to lose their
In G.R. No. 155001 individual petitioners are employees of
employment upon the implementation of the questioned
various service providers7 having separate concession contracts
agreements, filed before this Court a petition for prohibition to
with MIAA and continuing service agreements with various
enjoin the enforcement of said agreements.2
international airlines to provide in-flight catering, passenger
handling, ramp and ground support, aircraft maintenance and
On October 15, 2002, the service providers, joining the cause of provisions, cargo handling and warehousing and other services.
the petitioning workers, filed a motion for intervention and a Also included as petitioners are labor unions MIASCOR Workers
petition-in-intervention. Union-National Labor Union and Philippine Airlines Employees
Association. These petitioners filed the instant action for
prohibition as taxpayers and as parties whose rights and
On October 24, 2002, Congressmen Salacnib Baterina, Clavel
interests stand to be violated by the implementation of the
Martinez and Constantino Jaraula filed a similar petition with this
PIATCO Contracts.
Court.3

Petitioners-Intervenors in the same case are all corporations


On November 6, 2002, several employees of the MIAA likewise
organized and existing under Philippine laws engaged in the
filed a petition assailing the legality of the various agreements. 4
business of providing in-flight catering, passenger handling,
ramp and ground support, aircraft maintenance and provisions,
On December 11, 2002. another group of Congressmen, Hon. cargo handling and warehousing and other services to several
Jacinto V. Paras, Rafael P. Nantes, Eduardo C. Zialcita, Willie B. international airlines at the Ninoy Aquino International Airport.
Villarama, Prospero C. Nograles, Prospero A. Pichay, Jr., Harlin Petitioners-Intervenors allege that as tax-paying international
Cast Abayon and Benasing O. Macaranbon, moved to intervene airline and airport-related service operators, each one of them
in the case as Respondents-Intervenors. They filed their stands to be irreparably injured by the implementation of the
Comment-In-Intervention defending the validity of the assailed PIATCO Contracts. Each of the petitioners-intervenors have
agreements and praying for the dismissal of the petitions. separate and subsisting concession agreements with MIAA and
with various international airlines which they allege are being
interfered with and violated by respondent PIATCO.
During the pendency of the case before this Court, President
Gloria Macapagal Arroyo, on November 29, 2002, in her speech
at the 2002 Golden Shell Export Awards at Malacaang Palace, In G.R. No. 155661, petitioners constitute employees of MIAA
stated that she will not "honor (PIATCO) contracts which the and Samahang Manggagawa sa Paliparan ng Pilipinas - a
Executive Branch's legal offices have concluded (as) null and legitimate labor union and accredited as the sole and exclusive
void."5 bargaining agent of all the employees in MIAA. Petitioners
anchor their petition for prohibition on the nullity of the
contracts entered into by the Government and PIATCO regarding
Respondent PIATCO filed its Comments to the present petitions
the build-operate-and-transfer of the NAIA IPT III. They filed the
on November 7 and 27, 2002. The Office of the Solicitor General
petition as taxpayers and persons who have a legitimate
and the Office of the Government Corporate Counsel filed their
interest to protect in the implementation of the PIATCO
respective Comments in behalf of the public respondents.
Contracts.

On December 10, 2002, the Court heard the case on oral


Petitioners in both cases raise the argument that the PIATCO
argument. After the oral argument, the Court then resolved in
Contracts contain stipulations which directly contravene
open court to require the parties to file simultaneously their
numerous provisions of the Constitution, specific provisions of
respective Memoranda in amplification of the issues heard in the
the BOT Law and its Implementing Rules and Regulations, and
oral arguments within 30 days and to explore the possibility of
public policy. Petitioners contend that the DOTC and the MIAA,
arbitration or mediation as provided in the challenged contracts.
by entering into said contracts, have committed grave abuse of
discretion amounting to lack or excess of jurisdiction which can
In their consolidated Memorandum, the Office of the Solicitor be remedied only by a writ of prohibition, there being no plain,
General and the Office of the Government Corporate Counsel speedy or adequate remedy in the ordinary course of law.
prayed that the present petitions be given due course and that
judgment be rendered declaring the 1997 Concession
In particular, petitioners assail the provisions in the 1997
Agreement, the ARCA and the Supplements thereto void for
Concession Agreement and the ARCA which grant PIATCO the
being contrary to the Constitution, the BOT Law and its
exclusive right to operate a commercial international passenger
Implementing Rules and Regulations.
terminal within the Island of Luzon, except those international
airports already existing at the time of the execution of the
On March 6, 2003, respondent PIATCO informed the Court that agreement. The contracts further provide that upon the
on March 4, 2003 PIATCO commenced arbitration proceedings commencement of operations at the NAIA IPT III, the
before the International Chamber of Commerce, International Government shall cause the closure of Ninoy Aquino
Court of Arbitration (ICC) by filing a Request for Arbitration with International Airport Passenger Terminals I and II as international
the Secretariat of the ICC against the Government of the passenger terminals. With respect to existing concession
Republic of the Philippines acting through the DOTC and MIAA. agreements between MIAA and international airport service
providers regarding certain services or operations, the 1997
Concession Agreement and the ARCA uniformly provide that
In the present cases, the Court is again faced with the task of
such services or operations will not be carried over to the NAIA
resolving complicated issues made difficult by their intersecting
IPT III and PIATCO is under no obligation to permit such carry
legal and economic implications. The Court is aware of the far
over except through a separate agreement duly entered into
reaching fall out effects of the ruling which it makes today. For
with PIATCO.8
more than a century and whenever the exigencies of the times
demand it, this Court has never shirked from its solemn duty to
dispense justice and resolve "actual controversies involving With respect to the petitioning service providers and their
rights which are legally demandable and enforceable, and to employees, upon the commencement of operations of the NAIA
determine whether or not there has been grave abuse of IPT III, they allege that they will be effectively barred from
discretion amounting to lack or excess of jurisdiction." 6 To be providing international airline airport services at the NAIA
sure, this Court will not begin to do otherwise today. Terminals I and II as all international airlines and passengers will
be diverted to the NAIA IPT III. The petitioning service providers
will thus be compelled to contract with PIATCO alone for such
We shall first dispose of the procedural issues raised by
services, with no assurance that subsisting contracts with MIAA
respondent PIATCO which they allege will bar the resolution of
and other international airlines will be respected. Petitioning
the instant controversy.
service providers stress that despite the very competitive
118
market, the substantial capital investments required and the agencies or instrumentalities." 16 Further, "insofar as taxpayers'
high rate of fees, they entered into their respective contracts suits are concerned . . . (this Court) is not devoid of
with the MIAA with the understanding that the said contracts will discretion as to whether or not it should be entertained." 17 As
be in force for the stipulated period, and thereafter, renewed so such ". . . even if, strictly speaking, they [the petitioners] are not
as to allow each of the petitioning service providers to recoup covered by the definition, it is still within the wide discretion of
their investments and obtain a reasonable return thereon. the Court to waive the requirement and so remove the
impediment to its addressing and resolving the serious
constitutional questions raised." 18 In view of the serious legal
Petitioning employees of various service providers at the NAIA
questions involved and their impact on public interest, we
Terminals I and II and of MIAA on the other hand allege that with
resolve to grant standing to the petitioners.
the closure of the NAIA Terminals I and II as international
passenger terminals under the PIATCO Contracts, they stand to
lose employment. Other Procedural Matters

The question on legal standing is whether such parties have Respondent PIATCO further alleges that this Court is without
"alleged such a personal stake in the outcome of the jurisdiction to review the instant cases as factual issues are
controversy as to assure that concrete adverseness which involved which this Court is ill-equipped to resolve. Moreover,
sharpens the presentation of issues upon which the court so PIATCO alleges that submission of this controversy to this Court
largely depends for illumination of difficult constitutional at the first instance is a violation of the rule on hierarchy of
questions."9 Accordingly, it has been held that the interest of a courts. They contend that trial courts have concurrent
person assailing the constitutionality of a statute must be direct jurisdiction with this Court with respect to a special civil action
and personal. He must be able to show, not only that the law or for prohibition and hence, following the rule on hierarchy of
any government act is invalid, but also that he sustained or is in courts, resort must first be had before the trial courts.
imminent danger of sustaining some direct injury as a result of
its enforcement, and not merely that he suffers thereby in some
After a thorough study and careful evaluation of the issues
indefinite way. It must appear that the person complaining has
involved, this Court is of the view that the crux of the instant
been or is about to be denied some right or privilege to which he
controversy involves significant legal questions. The facts
is lawfully entitled or that he is about to be subjected to some
necessary to resolve these legal questions are well established
burdens or penalties by reason of the statute or act complained
and, hence, need not be determined by a trial court.
of.10

The rule on hierarchy of courts will not also prevent this Court
We hold that petitioners have the requisite standing. In the
from assuming jurisdiction over the cases at bar. The said rule
above-mentioned cases, petitioners have a direct and
may be relaxed when the redress desired cannot be obtained in
substantial interest to protect by reason of the implementation
the appropriate courts or where exceptional and compelling
of the PIATCO Contracts. They stand to lose their source of
circumstances justify availment of a remedy within and calling
livelihood, a property right which is zealously protected by the
for the exercise of this Court's primary jurisdiction.19
Constitution. Moreover, subsisting concession agreements
between MIAA and petitioners-intervenors and service contracts
between international airlines and petitioners-intervenors stand It is easy to discern that exceptional circumstances exist in
to be nullified or terminated by the operation of the NAIA IPT III the cases at bar that call for the relaxation of the rule. Both
under the PIATCO Contracts. The financial prejudice brought petitioners and respondents agree that these cases are
about by the PIATCO Contracts on petitioners and petitioners- of transcendental importance as they involve the
intervenors in these cases are legitimate interests sufficient to construction and operation of the country's premier international
confer on them the requisite standing to file the instant airport. Moreover, the crucial issues submitted for resolution are
petitions. of first impression and they entail the proper legal interpretation
of key provisions of the Constitution, the BOT Law and its
Implementing Rules and Regulations. Thus, considering the
b. G.R. No. 155547
nature of the controversy before the Court, procedural bars may
be lowered to give way for the speedy disposition of the instant
In G.R. No. 155547, petitioners filed the petition for prohibition cases.
as members of the House of Representatives, citizens and
taxpayers. They allege that as members of the House of
Legal Effect of the Commencement of Arbitration
Representatives, they are especially interested in the PIATCO
Proceedings by
Contracts, because the contracts compel the Government
and/or the House of Representatives to appropriate funds
necessary to comply with the provisions therein. 11 They cite PIATCO
provisions of the PIATCO Contracts which require disbursement
of unappropriated amounts in compliance with the contractual
There is one more procedural obstacle which must be overcome.
obligations of the Government. They allege that the Government
The Court is aware that arbitration proceedings pursuant to
obligations in the PIATCO Contracts which compel government
Section 10.02 of the ARCA have been filed at the instance of
expenditure without appropriation is a curtailment of their
respondent PIATCO. Again, we hold that the arbitration step
prerogatives as legislators, contrary to the mandate of the
taken by PIATCO will not oust this Court of its jurisdiction over
Constitution that "[n]o money shall be paid out of the treasury
the cases at bar.
except in pursuance of an appropriation made by law." 12

In Del Monte Corporation-USA v. Court of Appeals, 20 even after


Standing is a peculiar concept in constitutional law because in
finding that the arbitration clause in the Distributorship
some cases, suits are not brought by parties who have been
Agreement in question is valid and the dispute between the
personally injured by the operation of a law or any other
parties is arbitrable, this Court affirmed the trial court's decision
government act but by concerned citizens, taxpayers or voters
denying petitioner's Motion to Suspend Proceedings pursuant to
who actually sue in the public interest. Although we are not
the arbitration clause under the contract. In so ruling, this Court
unmindful of the cases of Imus Electric Co. v. Municipality of
held that as contracts produce legal effect between the parties,
Imus13 and Gonzales v. Raquiza14 wherein this Court held that
their assigns and heirs, only the parties to the Distributorship
appropriation must be made only on amounts immediately
Agreement are bound by its terms, including the arbitration
demandable, public interest demands that we take a more
clause stipulated therein. This Court ruled that arbitration
liberal view in determining whether the petitioners suing
proceedings could be called for but only with respect to the
as legislators, taxpayers and citizens have locus standi
parties to the contract in question. Considering that there are
to file the instant petition. In Kilosbayan, Inc. v.
parties to the case who are neither parties to the Distributorship
Guingona,15 this Court held "[i]n line with the liberal policy of
Agreement nor heirs or assigns of the parties thereto, this Court,
this Court on locus standi, ordinary taxpayers, members of
citing its previous ruling in Salas, Jr. v. Laperal Realty
Congress, and even association of planters, and non-profit civic
Corporation,21 held that to tolerate the splitting of proceedings
organizations were allowed to initiate and prosecute actions
by allowing arbitration as to some of the parties on the one
before this Court to question the constitutionality or validity of
hand and trial for the others on the other hand would, in effect,
laws, acts, decisions, rulings, or orders of various government
119
result in multiplicity of suits, duplicitous procedure and not for pre-qualification (Section 5.4 of the same
unnecessary delay.22 Thus, we ruled that the interest of justice document).23
would best be served if the trial court hears and adjudicates the
case in a single and complete proceeding.
Under the BOT Law, in case of a build-operate-and-transfer
arrangement, the contract shall be awarded to the bidder
It is established that petitioners in the present cases who "who, having satisfied the minimum financial, technical,
have presented legitimate interests in the resolution of the organizational and legal standards" required by the law,
controversy are not parties to the PIATCO Contracts. has submitted the lowest bid and most favorable terms of
Accordingly, they cannot be bound by the arbitration clause the project.24 Further, the 1994 Implementing Rules and
provided for in the ARCA and hence, cannot be compelled to Regulations of the BOT Law provide:
submit to arbitration proceedings. A speedy and decisive
resolution of all the critical issues in the present
Section 5.4 Pre-qualification Requirements.
controversy, including those raised by petitioners,
cannot be made before an arbitral tribunal. The object of
arbitration is precisely to allow an expeditious determination of xxx xxx xxx
a dispute. This objective would not be met if this Court were to
allow the parties to settle the cases by arbitration as there are
c. Financial Capability: The project proponent must have
certain issues involving non-parties to the PIATCO Contracts
adequate capability to sustain the financing requirements for
which the arbitral tribunal will not be equipped to resolve.
the detailed engineering design, construction and/or
operation and maintenance phases of the project, as the
Now, to the merits of the instant controversy. case may be. For purposes of pre-qualification, this capability
shall be measured in terms of (i) proof of the ability of
the project proponent and/or the consortium to
I
provide a minimum amount of equity to the project,
and (ii) a letter testimonial from reputable banks
Is PIATCO a qualified bidder? attesting that the project proponent and/or members
of the consortium are banking with them, that they
are in good financial standing, and that they have
Public respondents argue that the Paircargo Consortium,
adequate resources. The government agency/LGU
PIATCO's predecessor, was not a duly pre-qualified bidder on the
concerned shall determine on a project-to-project basis and
unsolicited proposal submitted by AEDC as the Paircargo
before pre-qualification, the minimum amount of equity
Consortium failed to meet the financial capability required under
needed. (emphasis supplied)
the BOT Law and the Bid Documents. They allege that in
computing the ability of the Paircargo Consortium to meet the
minimum equity requirements for the project, the entire net Pursuant to this provision, the PBAC issued PBAC Bulletin No.
worth of Security Bank, a member of the consortium, 3 dated August 16, 1996 amending the financial capability
should not be considered. requirements for pre-qualification of the project proponent as
follows:
PIATCO relies, on the other hand, on the strength of the
Memorandum dated October 14, 1996 issued by the DOTC 6. Basis of Pre-qualification
Undersecretary Primitivo C. Cal stating that the Paircargo
Consortium is found to have a combined net worth of
The basis for the pre-qualification shall be on the compliance
P3,900,000,000.00, sufficient to meet the equity requirements
of the proponent to the minimum technical and financial
of the project. The said Memorandum was in response to a letter
requirements provided in the Bid Documents and in the IRR
from Mr. Antonio Henson of AEDC to President Fidel V. Ramos
of the BOT Law, R.A. No. 6957, as amended by R.A. 7718.
questioning the financial capability of the Paircargo Consortium
on the ground that it does not have the financial resources to
put up the required minimum equity of P2,700,000,000.00. This The minimum amount of equity to which the proponent's
contention is based on the restriction under R.A. No. 337, as financial capability will be based shall be thirty percent
amended or the General Banking Act that a commercial bank (30%) of the project cost instead of the twenty
cannot invest in any single enterprise in an amount more than percent (20%) specified in Section 3.6.4 of the Bid
15% of its net worth. In the said Memorandum, Undersecretary Documents. This is to correlate with the required debt-to-
Cal opined: equity ratio of 70:30 in Section 2.01a of the draft concession
agreement. The debt portion of the project financing should
not exceed 70% of the actual project cost.
The Bid Documents, as clarified through Bid Bulletin
Nos. 3 and 5, require that financial capability will be
evaluated based on total financial capability of all the Accordingly, based on the above provisions of law, the Paircargo
member companies of the [Paircargo] Consortium. In Consortium or any challenger to the unsolicited proposal of
this connection, the Challenger was found to have a AEDC has to show that it possesses the requisite financial
combined net worth of P3,926,421,242.00 that could capability to undertake the project in the minimum
support a project costing approximately P13 Billion. amount of 30% of the project cost through (i) proof of the
ability to provide a minimum amount of equity to the project,
and (ii) a letter testimonial from reputable banks attesting that
It is not a requirement that the net worth must be
the project proponent or members of the consortium are
"unrestricted." To impose that as a requirement now
banking with them, that they are in good financial standing, and
will be nothing less than unfair.
that they have adequate resources.

The financial statement or the net worth is not the sole


As the minimum project cost was estimated to be
basis in establishing financial capability. As stated in
US$350,000,000.00 or roughly P9,183,650,000.00,25 the
Bid Bulletin No. 3, financial capability may also be
Paircargo Consortium had to show to the satisfaction of the
established by testimonial letters issued by reputable
PBAC that it had the ability to provide the minimum equity for
banks. The Challenger has complied with this
the project in the amount of at least P2,755,095,000.00.
requirement.

Paircargo's Audited Financial Statements as of 1993 and 1994


To recap, net worth reflected in the Financial Statement
indicated that it had a net worth of P2,783,592.00 and
should not be taken as the amount of the money to be
P3,123,515.00 respectively.26 PAGS' Audited Financial
used to answer the required thirty percent (30%) equity
Statements as of 1995 indicate that it has approximately
of the challenger but rather to be used in establishing if
P26,735,700.00 to invest as its equity for the project. 27 Security
there is enough basis to believe that the challenger can
Bank's Audited Financial Statements as of 1995 show that it has
comply with the required 30% equity. In fact, proof of
a net worth equivalent to its capital funds in the amount of
sufficient equity is required as one of the conditions for
P3,523,504,377.00.28
award of contract (Section 12.1 IRR of the BOT Law) but
120
We agree with public respondents that with respect to Security qualification. With respect to Security Bank, the maximum
Bank, the entire amount of its net worth could not be invested amount which may be invested by it would only be 15% of its
in a single undertaking or enterprise, whether allied or non- net worth in view of the restrictions imposed by the General
allied in accordance with the provisions of R.A. No. 337, as Banking Act. Disregarding the investment ceilings provided by
amended or the General Banking Act: applicable law would not result in a proper evaluation of whether
or not a bidder is pre-qualified to undertake the project as for all
intents and purposes, such ceiling or legal restriction determines
Sec. 21-B. The provisions in this or in any other Act to
the true maximum amount which a bidder may invest in the
the contrary notwithstanding, the Monetary Board,
project.
whenever it shall deem appropriate and necessary to
further national development objectives or support
national priority projects, may authorize a Further, the determination of whether or not a bidder is pre-
commercial bank, a bank authorized to provide qualified to undertake the project requires an evaluation of the
commercial banking services, as well as a financial capacity of the said bidder at the time the bid is
government-owned and controlled bank, to submitted based on the required documents presented by the
operate under an expanded commercial banking bidder. The PBAC should not be allowed to speculate on
authority and by virtue thereof exercise, in the future financial ability of the bidder to undertake the
addition to powers authorized for commercial project on the basis of documents submitted. This would open
banks, the powers of an Investment House as doors to abuse and defeat the very purpose of a public bidding.
provided in Presidential Decree No. 129, invest in This is especially true in the case at bar which involves the
the equity of a non-allied undertaking, or own a investment of billions of pesos by the project proponent. The
majority or all of the equity in a financial intermediary relevant government authority is duty-bound to ensure that the
other than a commercial bank or a bank authorized to awardee of the contract possesses the minimum required
provide commercial banking services: Provided, financial capability to complete the project. To allow the PBAC to
That (a) the total investment in equities shall not estimate the bidder's future financial capability would not
exceed fifty percent (50%) of the net worth of the secure the viability and integrity of the project. A restrictive and
bank; (b) the equity investment in any one conservative application of the rules and procedures of public
enterprise whether allied or non-allied shall not bidding is necessary not only to protect the impartiality and
exceed fifteen percent (15%) of the net worth of regularity of the proceedings but also to ensure the financial and
the bank; (c) the equity investment of the bank, or of technical reliability of the project. It has been held that:
its wholly or majority-owned subsidiary, in a single non-
allied undertaking shall not exceed thirty-five percent
The basic rule in public bidding is that bids should be
(35%) of the total equity in the enterprise nor shall it
evaluated based on the required documents submitted
exceed thirty-five percent (35%) of the voting stock in
before and not after the opening of bids. Otherwise, the
that enterprise; and (d) the equity investment in other
foundation of a fair and competitive public bidding
banks shall be deducted from the investing bank's net
would be defeated. Strict observance of the rules,
worth for purposes of computing the prescribed ratio of
regulations, and guidelines of the bidding
net worth to risk assets.
process is the only safeguard to a fair, honest
and competitive public bidding.30
xxx xxx xxx
Thus, if the maximum amount of equity that a bidder may
Further, the 1993 Manual of Regulations for Banks provides: invest in the project at the time the bids are submitted falls
short of the minimum amounts required to be put up by the
bidder, said bidder should be properly disqualified. Considering
SECTION X383. Other Limitations and Restrictions.
that at the pre-qualification stage, the maximum amounts which
The following limitations and restrictions shall also
the Paircargo Consortium may invest in the project fell short of
apply regarding equity investments of banks.
the minimum amounts prescribed by the PBAC, we hold that
Paircargo Consortium was not a qualified bidder. Thus the award
a. In any single enterprise. The equity investments of of the contract by the PBAC to the Paircargo Consortium, a
banks in any single enterprise shall not exceed at any disqualified bidder, is null and void.
time fifteen percent (15%) of the net worth of the
investing bank as defined in Sec. X106 and Subsec.
While it would be proper at this juncture to end the resolution of
X121.5.
the instant controversy, as the legal effects of the
disqualification of respondent PIATCO's predecessor would come
Thus, the maximum amount that Security Bank could validly into play and necessarily result in the nullity of all the
invest in the Paircargo Consortium is only P528,525,656.55, subsequent contracts entered by it in pursuance of the project,
representing 15% of its entire net worth. The total net worth the Court feels that it is necessary to discuss in full the pressing
therefore of the Paircargo Consortium, after considering issues of the present controversy for a complete resolution
the maximum amounts that may be validly invested by each thereof.
of its members is P558,384,871.55 or only 6.08% of the
project cost,29 an amount substantially less than the
II
prescribed minimum equity investment required for the project
in the amount of P2,755,095,000.00 or 30% of the project cost.
Is the 1997 Concession Agreement valid?
The purpose of pre-qualification in any public bidding is to
determine, at the earliest opportunity, the ability of the bidder Petitioners and public respondents contend that the 1997
to undertake the project. Thus, with respect to the bidder's Concession Agreement is invalid as it contains provisions that
financial capacity at the pre-qualification stage, the law requires substantially depart from the draft Concession Agreement
the government agency to examine and determine the ability of included in the Bid Documents. They maintain that a substantial
the bidder to fund the entire cost of the project by considering departure from the draft Concession Agreement is a violation of
the maximum amounts that each bidder may invest in public policy and renders the 1997 Concession Agreement null
the project at the time of pre-qualification. and void.

The PBAC has determined that any prospective bidder for the PIATCO maintains, however, that the Concession Agreement
construction, operation and maintenance of the NAIA IPT III attached to the Bid Documents is intended to be a draft, i.e.,
project should prove that it has the ability to provide equity in subject to change, alteration or modification, and that this
the minimum amount of 30% of the project cost, in accordance intention was clear to all participants, including AEDC, and
with the 70:30 debt-to-equity ratio prescribed in the Bid DOTC/MIAA. It argued further that said intention is expressed in
Documents. Thus, in the case of Paircargo Consortium, the PBAC Part C (6) of Bid Bulletin No. 3 issued by the PBAC which states:
should determine the maximum amounts that each member
of the consortium may commit for the construction, operation
6. Amendments to the Draft Concessions Agreement
and maintenance of the NAIA IPT III project at the time of pre-
121
Amendments to the Draft Concessions Agreement shall through public bidding, when such subsequent amendment was
be issued from time to time. Said amendments shall made without a new public bidding, is null and void:
only cover items that would not materially affect the
preparation of the proponent's proposal.
The Court agrees with the contention of counsel for the
plaintiffs that the due execution of a contract after
By its very nature, public bidding aims to protect the public public bidding is a limitation upon the right of the
interest by giving the public the best possible advantages contracting parties to alter or amend it without another
through open competition. Thus: public bidding, for otherwise what would a public
bidding be good for if after the execution of a
contract after public bidding, the contracting
Competition must be legitimate, fair and honest. In the
parties may alter or amend the contract, or even
field of government contract law, competition requires,
cancel it, at their will? Public biddings are held for
not only `bidding upon a common standard, a common
the protection of the public, and to give the public the
basis, upon the same thing, the same subject matter,
best possible advantages by means of open
the same undertaking,' but also that it be
competition between the bidders. He who bids or offers
legitimate, fair and honest; and not designed to
the best terms is awarded the contract subject of the
injure or defraud the government.31
bid, and it is obvious that such protection and best
possible advantages to the public will disappear if the
An essential element of a publicly bidded contract is that all parties to a contract executed after public bidding may
bidders must be on equal footing. Not simply in terms of alter or amend it without another previous public
application of the procedural rules and regulations imposed by bidding.35
the relevant government agency, but more importantly, on the
contract bidded upon. Each bidder must be able to bid on the
Hence, the question that comes to fore is this: is the 1997
same thing. The rationale is obvious. If the winning bidder is
Concession Agreement the same agreement that was offered for
allowed to later include or modify certain provisions in the
public bidding, i.e., the draft Concession Agreement attached to
contract awarded such that the contract is altered in any
the Bid Documents? A close comparison of the draft Concession
material respect, then the essence of fair competition in the
Agreement attached to the Bid Documents and the 1997
public bidding is destroyed. A public bidding would indeed be a
Concession Agreement reveals that the documents differ in at
farce if after the contract is awarded, the winning bidder may
least two material respects:
modify the contract and include provisions which are favorable
to it that were not previously made available to the other
bidders. Thus: a. Modification on the Public

It is inherent in public biddings that there shall be a fair Utility Revenues and Non-Public
competition among the bidders. The specifications in
such biddings provide the common ground or basis for
Utility Revenues that may be
the bidders. The specifications should, accordingly,
operate equally or indiscriminately upon all bidders.32
collected by PIATCO
The same rule was restated by Chief Justice Stuart of the
Supreme Court of Minnesota: The fees that may be imposed and collected by PIATCO under
the draft Concession Agreement and the 1997 Concession
Agreement may be classified into three distinct categories: (1)
The law is well settled that where, as in this case,
fees which are subject to periodic adjustment of once every two
municipal authorities can only let a contract for public
years in accordance with a prescribed parametric formula and
work to the lowest responsible bidder, the proposals
adjustments are made effective only upon written approval by
and specifications therefore must be so framed as to
MIAA; (2) fees other than those included in the first category
permit free and full competition. Nor can they enter
which maybe adjusted by PIATCO whenever it deems necessary
into a contract with the best bidder containing
without need for consent of DOTC/MIAA; and (3) new fees and
substantial provisions beneficial to him, not
charges that may be imposed by PIATCO which have not been
included or contemplated in the terms and
previously imposed or collected at the Ninoy Aquino
specifications upon which the bids were invited.33
International Airport Passenger Terminal I, pursuant to
Administrative Order No. 1, Series of 1993, as amended. The
In fact, in the PBAC Bid Bulletin No. 3 cited by PIATCO to support glaring distinctions between the draft Concession Agreement
its argument that the draft concession agreement is subject to and the 1997 Concession Agreement lie in the types of fees
amendment, the pertinent portion of which was quoted above, included in each category and the extent of the supervision and
the PBAC also clarified that "[s]aid amendments shall only regulation which MIAA is allowed to exercise in relation thereto.
cover items that would not materially affect the
preparation of the proponent's proposal."
For fees under the first category, i.e., those which are subject
to periodic adjustment in accordance with a prescribed
While we concede that a winning bidder is not precluded from parametric formula and effective only upon written approval by
modifying or amending certain provisions of the contract bidded MIAA, the draft Concession Agreement includes the
upon, such changes must not constitute substantial or following:36
material amendments that would alter the basic
parameters of the contract and would constitute a denial
(1) aircraft parking fees;
to the other bidders of the opportunity to bid on the
same terms. Hence, the determination of whether or not a
modification or amendment of a contract bidded out constitutes (2) aircraft tacking fees;
a substantial amendment rests on whether the contract, when
taken as a whole, would contain substantially different terms
(3) groundhandling fees;
and conditions that would have the effect of altering the
technical and/or financial proposals previously submitted by
other bidders. The alterations and modifications in the contract (4) rentals and airline offices;
executed between the government and the winning bidder must
be such as to render such executed contract to be an entirely
(5) check-in counter rentals; and
different contract from the one that was bidded upon.

(6) porterage fees.


In the case of Caltex (Philippines), Inc. v. Delgado
Brothers, Inc.,34 this Court quoted with approval the ruling of
the trial court that an amendment to a contract awarded
122
Under the 1997 Concession Agreement, fees which are Agreement, vehicular parking fee is subject to MIAA regulation
subject to adjustment and effective upon MIAA approval are and approval under the second paragraph of Section 6.03
classified as "Public Utility Revenues" and include:37 thereof while porterage fee is covered by the first paragraph of
the same provision. There is an obvious relaxation of the extent
of control and regulation by MIAA with respect to the particular
(1) aircraft parking fees;
fees that may be charged by PIATCO.

(2) aircraft tacking fees;


Moreover, with respect to the third category of fees that may
be imposed and collected by PIATCO, i.e., new fees and charges
(3) check-in counter fees; and that may be imposed by PIATCO which have not been previously
imposed or collected at the Ninoy Aquino International Airport
Passenger Terminal I, under Section 6.03 of the draft
(4) Terminal Fees.
Concession Agreement MIAA has reserved the right to
regulate the same under the same conditions that MIAA may
The implication of the reduced number of fees that are subject regulate fees under the first category, i.e., periodic adjustment
to MIAA approval is best appreciated in relation to fees included of once every two years in accordance with a prescribed
in the second category identified above. Under the 1997 parametric formula and effective only upon written approval by
Concession Agreement, fees which PIATCO may adjust MIAA. However, under the 1997 Concession
whenever it deems necessary without need for consent of Agreement, adjustment of fees under the third category is not
DOTC/MIAA are "Non-Public Utility Revenues" and is defined as subject to MIAA regulation.
"all other income not classified as Public Utility Revenues
derived from operations of the Terminal and the Terminal
With respect to terminal fees that may be charged by
Complex."38 Thus, under the 1997 Concession Agreement,
PIATCO,41 as shown earlier, this was included within the category
ground handling fees, rentals from airline offices and porterage
of "Public Utility Revenues" under the 1997 Concession
fees are no longer subject to MIAA regulation.
Agreement. This classification is significant because under
the 1997 Concession Agreement, "Public Utility Revenues"
Further, under Section 6.03 of the draft Concession are subject to an "Interim Adjustment" of fees upon the
Agreement, MIAA reserves the right to regulate (1) lobby and occurrence of certain extraordinary events specified in the
vehicular parking fees and (2) other new fees and charges that agreement.42 However, under the draft Concession
may be imposed by PIATCO. Such regulation may be made by Agreement, terminal fees are not included in the types of fees
periodic adjustment and is effective only upon written approval that may be subject to "Interim Adjustment." 43
of MIAA. The full text of said provision is quoted below:
Finally, under the 1997 Concession Agreement, "Public Utility
Section 6.03. Periodic Adjustment in Fees and Charges. Revenues," except terminal fees, are denominated in US
Adjustments in the aircraft parking fees, aircraft tacking Dollars44 while payments to the Government are in Philippine
fees, groundhandling fees, rentals and airline offices, Pesos. In the draft Concession Agreement, no such
check-in-counter rentals and porterage fees shall be stipulation was included. By stipulating that "Public Utility
allowed only once every two years and in accordance Revenues" will be paid to PIATCO in US Dollars while payments
with the Parametric Formula attached hereto as Annex by PIATCO to the Government are in Philippine currency under
F. Provided that adjustments shall be made effective the 1997 Concession Agreement, PIATCO is able to enjoy the
only after the written express approval of the MIAA. benefits of depreciations of the Philippine Peso, while being
Provided, further, that such approval of the MIAA, shall effectively insulated from the detrimental effects of exchange
be contingent only on the conformity of the rate fluctuations.
adjustments with the above said parametric formula.
The first adjustment shall be made prior to the In-
When taken as a whole, the changes under the 1997 Concession
Service Date of the Terminal.
Agreement with respect to reduction in the types of fees that
are subject to MIAA regulation and the relaxation of such
The MIAA reserves the right to regulate under regulation with respect to other fees are significant amendments
the foregoing terms and conditions the lobby and that substantially distinguish the draft Concession Agreement
vehicular parking fees and other new fees and from the 1997 Concession Agreement. The 1997 Concession
charges as contemplated in paragraph 2 of Agreement, in this respect, clearly gives PIATCO more
Section 6.01 if in its judgment the users of the favorable terms than what was available to other bidders
airport shall be deprived of a free option for the at the time the contract was bidded out. It is not very
services they cover.39 difficult to see that the changes in the 1997 Concession
Agreement translate to direct and concrete financial
advantages for PIATCO which were not available at the time
On the other hand, the equivalent provision under the 1997
the contract was offered for bidding. It cannot be denied that
Concession Agreement reads:
under the 1997 Concession Agreement only "Public Utility
Revenues" are subject to MIAA regulation. Adjustments of all
Section 6.03 Periodic Adjustment in Fees and Charges. other fees imposed and collected by PIATCO are entirely within
its control. Moreover, with respect to terminal fees, under the
1997 Concession Agreement, the same is further subject to
xxx xxx xxx
"Interim Adjustments" not previously stipulated in the draft
Concession Agreement. Finally, the change in the currency
(c) Concessionaire shall at all times be judicious in stipulated for "Public Utility Revenues" under the 1997
fixing fees and charges constituting Non-Public Utility Concession Agreement, except terminal fees, gives PIATCO an
Revenues in order to ensure that End Users are not added benefit which was not available at the time of bidding.
unreasonably deprived of services. While the
vehicular parking fee, porterage fee and
b. Assumption by the Government of the liabilities of
greeter/well wisher fee constitute Non-Public
PIATCO in the event of the latter's default thereof
Utility Revenues of Concessionaire, GRP may
intervene and require Concessionaire to explain
and justify the fee it may set from time to time, if Under the draft Concession Agreement, default by PIATCO of
in the reasonable opinion of GRP the said fees have any of its obligations to creditors who have provided, loaned or
become exorbitant resulting in the unreasonable advanced funds for the NAIA IPT III project does not result in the
deprivation of End Users of such services.40 assumption by the Government of these liabilities. In fact,
nowhere in the said contract does default of PIATCO's loans
figure in the agreement. Such default does not directly result in
Thus, under the 1997 Concession Agreement, with respect to
any concomitant right or obligation in favor of the Government.
(1) vehicular parking fee, (2) porterage fee and (3) greeter/well
wisher fee, all that MIAA can do is to require PIATCO to explain
and justify the fees set by PIATCO. In the draft Concession However, the 1997 Concession Agreement provides:
123
Section 4.04 Assignment. modification that translates to better terms and conditions for
PIATCO.
xxx xxx xxx
PIATCO, however, argues that the parties to the bidding
procedure acknowledge that the draft Concession Agreement is
(b) In the event Concessionaire should default in the
subject to amendment because the Bid Documents permit
payment of an Attendant Liability, and the default has
financing or borrowing. They claim that it was the lenders who
resulted in the acceleration of the payment due date of
proposed the amendments to the draft Concession Agreement
the Attendant Liability prior to its stated date of
which resulted in the 1997 Concession Agreement.
maturity, the Unpaid Creditors and Concessionaire shall
immediately inform GRP in writing of such default. GRP
shall, within one hundred eighty (180) Days from We agree that it is not inconsistent with the rationale and
receipt of the joint written notice of the Unpaid purpose of the BOT Law to allow the project proponent or the
Creditors and Concessionaire, either (i) take over the winning bidder to obtain financing for the project, especially in
Development Facility and assume the Attendant this case which involves the construction, operation and
Liabilities, or (ii) allow the Unpaid Creditors, if qualified, maintenance of the NAIA IPT III. Expectedly, compliance by the
to be substituted as concessionaire and operator of the project proponent of its undertakings therein would involve a
Development Facility in accordance with the terms and substantial amount of investment. It is therefore inevitable for
conditions hereof, or designate a qualified operator the awardee of the contract to seek alternate sources of funds
acceptable to GRP to operate the Development Facility, to support the project. Be that as it may, this Court maintains
likewise under the terms and conditions of this that amendments to the contract bidded upon should always
Agreement; Provided that if at the end of the 180-day conform to the general policy on public bidding if such
period GRP shall not have served the Unpaid Creditors procedure is to be faithful to its real nature and purpose. By its
and Concessionaire written notice of its choice, GRP very nature and characteristic, competitive public bidding aims
shall be deemed to have elected to take over the to protect the public interest by giving the public the best
Development Facility with the concomitant assumption possible advantages through open competition. 45 It has been
of Attendant Liabilities. held that the three principles in public bidding are (1) the offer
to the public; (2) opportunity for competition; and (3) a basis for
the exact comparison of bids. A regulation of the matter which
(c) If GRP should, by written notice, allow the Unpaid
excludes any of these factors destroys the distinctive character
Creditors to be substituted as concessionaire, the latter
of the system and thwarts the purpose of its adoption. 46 These
shall form and organize a concession company qualified
are the basic parameters which every awardee of a contract
to take over the operation of the Development Facility.
bidded out must conform to, requirements of financing and
If the concession company should elect to designate an
borrowing notwithstanding. Thus, upon a concrete showing that,
operator for the Development Facility, the concession
as in this case, the contract signed by the government and the
company shall in good faith identify and designate a
contract-awardee is an entirely different contract from the
qualified operator acceptable to GRP within one
contract bidded, courts should not hesitate to strike down said
hundred eighty (180) days from receipt of GRP's written
contract in its entirety for violation of public policy on public
notice. If the concession company, acting in good faith
bidding. A strict adherence on the principles, rules and
and with due diligence, is unable to designate a
regulations on public bidding must be sustained if only to
qualified operator within the aforesaid period, then GRP
preserve the integrity and the faith of the general public on the
shall at the end of the 180-day period take over the
procedure.
Development Facility and assume Attendant Liabilities.

Public bidding is a standard practice for procuring government


The term "Attendant Liabilities" under the 1997 Concession
contracts for public service and for furnishing supplies and other
Agreement is defined as:
materials. It aims to secure for the government the lowest
possible price under the most favorable terms and conditions, to
Attendant Liabilities refer to all amounts recorded and curtail favoritism in the award of government contracts and
from time to time outstanding in the books of the avoid suspicion of anomalies and it places all bidders in equal
Concessionaire as owing to Unpaid Creditors who footing.47 Any government action which permits any
have provided, loaned or advanced funds substantial variance between the conditions under which
actually used for the Project, including all interests, the bids are invited and the contract executed after the
penalties, associated fees, charges, surcharges, award thereof is a grave abuse of discretion amounting
indemnities, reimbursements and other related to lack or excess of jurisdiction which warrants proper
expenses, and further including amounts owed by judicial action.
Concessionaire to its suppliers, contractors and sub-
contractors.
In view of the above discussion, the fact that the foregoing
substantial amendments were made on the 1997 Concession
Under the above quoted portions of Section 4.04 in relation to Agreement renders the same null and void for being contrary
the definition of "Attendant Liabilities," default by PIATCO of to public policy. These amendments convert the 1997
its loans used to finance the NAIA IPT III project triggers Concession Agreement to an entirely different
the occurrence of certain events that leads to the agreement from the contract bidded out or the draft
assumption by the Government of the liability for the Concession Agreement. It is not difficult to see that the
loans. Only in one instance may the Government escape the amendments on (1) the types of fees or charges that are subject
assumption of PIATCO's liabilities, i.e., when the Government so to MIAA regulation or control and the extent thereof and (2) the
elects and allows a qualified operator to take over as assumption by the Government, under certain conditions, of the
Concessionaire. However, this circumstance is dependent liabilities of PIATCO directly translates concrete financial
on the existence and availability of a qualified operator advantages to PIATCO that were previously not available
who is willing to take over the rights and obligations of during the bidding process. These amendments cannot be
PIATCO under the contract, a circumstance that is not taken as merely supplements to or implementing provisions of
entirely within the control of the Government. those already existing in the draft Concession Agreement. The
amendments discussed above present new terms and conditions
which provide financial benefit to PIATCO which may have
Without going into the validity of this provision at this juncture,
altered the technical and financial parameters of other bidders
suffice it to state that Section 4.04 of the 1997 Concession
had they known that such terms were available.
Agreement may be considered a form of security for the loans
PIATCO has obtained to finance the project, an option that was
not made available in the draft Concession Agreement. Section III
4.04 is an important amendment to the 1997 Concession
Agreement because it grants PIATCO a financial advantage or
Direct Government Guarantee
benefit which was not previously made available during
the bidding process. This financial advantage is a significant
124
Article IV, Section 4.04(b) and (c), in relation to Article 1.06, of out of its control. The Government under the circumstances
the 1997 Concession Agreement provides: provided for in the 1997 Concession Agreement is at the mercy
of the existence, availability and willingness of a qualified
operator. The above contractual provisions constitute a direct
Section 4.04 Assignment
government guarantee which is prohibited by law.

xxx xxx xxx


One of the main impetus for the enactment of the BOT Law is
the lack of government funds to construct the infrastructure and
(b) In the event Concessionaire should default in the development projects necessary for economic growth and
payment of an Attendant Liability, and the default development. This is why private sector resources are being
resulted in the acceleration of the payment due date of the tapped in order to finance these projects. The BOT law allows
Attendant Liability prior to its stated date of maturity, the the private sector to participate, and is in fact encouraged to do
Unpaid Creditors and Concessionaire shall immediately so by way of incentives, such as minimizing the unstable flow of
inform GRP in writing of such default. GRP shall within one returns,52 provided that the government would not have to
hundred eighty (180) days from receipt of the joint written unnecessarily expend scarcely available funds for the project
notice of the Unpaid Creditors and Concessionaire, either (i) itself. As such, direct guarantee, subsidy and equity by the
take over the Development Facility and assume the government in these projects are strictly prohibited. 53 This is
Attendant Liabilities, or (ii) allow the Unpaid Creditors, if but logical for if the government would in the end still be
qualified to be substituted as concessionaire and operator at a risk of paying the debts incurred by the private
of the Development facility in accordance with the terms entity in the BOT projects, then the purpose of the law is
and conditions hereof, or designate a qualified operator subverted.
acceptable to GRP to operate the Development Facility,
likewise under the terms and conditions of this Agreement;
Section 2(n) of the BOT Law defines direct guarantee as follows:
Provided, that if at the end of the 180-day period GRP shall
not have served the Unpaid Creditors and Concessionaire
written notice of its choice, GRP shall be deemed to (n) Direct government guarantee An agreement
have elected to take over the Development Facility whereby the government or any of its agencies or local
with the concomitant assumption of Attendant government units assume responsibility for
Liabilities. the repayment of debt directly incurred by the
project proponent in implementing the project in
case of a loan default.
(c) If GRP, by written notice, allow the Unpaid Creditors to be
substituted as concessionaire, the latter shall form and
organize a concession company qualified to takeover the Clearly by providing that the Government "assumes" the
operation of the Development Facility. If the concession attendant liabilities, which consists of PIATCO's unpaid debts,
company should elect to designate an operator for the the 1997 Concession Agreement provided for a direct
Development Facility, the concession company shall in good government guarantee for the debts incurred by PIATCO in the
faith identify and designate a qualified operator acceptable implementation of the NAIA IPT III project. It is of no moment
to GRP within one hundred eighty (180) days from receipt of that the relevant sections are subsumed under the title of
GRP's written notice. If the concession company, acting in "assignment". The provisions providing for direct government
good faith and with due diligence, is unable to designate a guarantee which is prohibited by law is clear from the terms
qualified operator within the aforesaid period, then thereof.
GRP shall at the end of the 180-day period take over the
Development Facility and assume Attendant
The fact that the ARCA superseded the 1997 Concession
Liabilities.
Agreement did not cure this fatal defect. Article IV, Section
4.04(c), in relation to Article I, Section 1.06, of the ARCA
. provides:

Section 1.06. Attendant Liabilities Section 4.04 Security

Attendant Liabilities refer to all amounts recorded and xxx xxx xxx
from time to time outstanding in the books of the
Concessionaire as owing to Unpaid Creditors who
(c) GRP agrees with Concessionaire (PIATCO) that it shall
have provided, loaned or advanced funds actually used for
negotiate in good faith and enter into direct
the Project, including all interests, penalties, associated
agreement with the Senior Lenders, or with an agent of
fees, charges, surcharges, indemnities, reimbursements and
such Senior Lenders (which agreement shall be subject to
other related expenses, and further including amounts
the approval of the Bangko Sentral ng Pilipinas), in such
owed by Concessionaire to its suppliers, contractors and
form as may be reasonably acceptable to both GRP and
sub-contractors.48
Senior Lenders, with regard, inter alia, to the following
parameters:
It is clear from the above-quoted provisions that Government,
in the event that PIATCO defaults in its loan obligations,
xxx xxx xxx
is obligated to pay "all amounts recorded and from time to
time outstanding from the books" of PIATCO which the latter
owes to its creditors.49 These amounts include "all interests, (iv) If the Concessionaire [PIATCO] is in default under a
penalties, associated fees, charges, surcharges, indemnities, payment obligation owed to the Senior Lenders, and
reimbursements and other related expenses."50 This obligation as a result thereof the Senior Lenders have become entitled
of the Government to pay PIATCO's creditors upon PIATCO's to accelerate the Senior Loans, the Senior Lenders shall
default would arise if the Government opts to take over NAIA IPT have the right to notify GRP of the same, and without
III. It should be noted, however, that even if the Government prejudice to any other rights of the Senior Lenders or any
chooses the second option, which is to allow PIATCO's unpaid Senior Lenders' agent may have (including without
creditors operate NAIA IPT III, the Government is still at a risk of limitation under security interests granted in favor of the
being liable to PIATCO's creditors should the latter be unable to Senior Lenders), to either in good faith identify and
designate a qualified operator within the prescribed period. 51 In designate a nominee which is qualified under sub-clause
effect, whatever option the Government chooses to take (viii)(y) below to operate the Development Facility [NAIA
in the event of PIATCO's failure to fulfill its loan Terminal 3] or transfer the Concessionaire's [PIATCO] rights
obligations, the Government is still at a risk of assuming and obligations under this Agreement to a transferee which
PIATCO's outstanding loans. This is due to the fact that the is qualified under sub-clause (viii) below;
Government would only be free from assuming PIATCO's debts if
the unpaid creditors would be able to designate a qualified
xxx xxx xxx
operator within the period provided for in the contract.
Thus, the Government's assumption of liability is virtually
125
(vi) if the Senior Lenders, acting in good faith and using pay any and all amounts owed by PIATCO to its lenders in
reasonable efforts, are unable to designate a nominee or connection with NAIA IPT III. Worse, the conditions that would
effect a transfer in terms and conditions satisfactory to the make the Government liable for PIATCO's debts is triggered by
Senior Lenders within one hundred eighty (180) days after PIATCO's own default of its loan obligations to its Senior Lenders
giving GRP notice as referred to respectively in (iv) or (v) to which loan contracts the Government was never a party to.
above, then GRP and the Senior Lenders shall endeavor in The Government was not even given an option as to what
good faith to enter into any other arrangement relating to course of action it should take in case PIATCO defaulted in the
the Development Facility [NAIA Terminal 3] (other than a payment of its senior loans. The Government, upon PIATCO's
turnover of the Development Facility [NAIA Terminal 3] to default, would be merely notified by the Senior Lenders of the
GRP) within the following one hundred eighty (180) days. If same and it is the Senior Lenders who are authorized to appoint
no agreement relating to the Development Facility [NAIA a qualified nominee or transferee. Should the Senior Lenders fail
Terminal 3] is arrived at by GRP and the Senior Lenders to make such an appointment, the Government is then
within the said 180-day period, then at the end thereof automatically obligated to "directly deal and negotiate" with the
the Development Facility [NAIA Terminal 3] shall be Senior Lenders regarding NAIA IPT III. The only way the
transferred by the Concessionaire [PIATCO] to GRP or Government would not be liable for PIATCO's debt is for a
its designee and GRP shall make a termination qualified nominee or transferee to be appointed in place of
payment to Concessionaire [PIATCO] equal to the PIATCO to continue the construction, operation and maintenance
Appraised Value (as hereinafter defined) of the of NAIA IPT III. This "pre-condition", however, will not take the
Development Facility [NAIA Terminal 3] or the sum of contract out of the ambit of a direct guarantee by the
the Attendant Liabilities, if greater. Notwithstanding government as the existence, availability and willingness of a
Section 8.01(c) hereof, this Agreement shall be deemed qualified nominee or transferee is totally out of the
terminated upon the transfer of the Development Facility government's control. As such the Government is virtually at
[NAIA Terminal 3] to GRP pursuant hereto; the mercy of PIATCO (that it would not default on its loan
obligations to its Senior Lenders), the Senior Lenders (that they
would appoint a qualified nominee or transferee or agree to
xxx xxx xxx
some other arrangement with the Government) and the
existence of a qualified nominee or transferee who is able and
Section 1.06. Attendant Liabilities willing to take the place of PIATCO in NAIA IPT III.

Attendant Liabilities refer to all amounts in each case The proscription against government guarantee in any
supported by verifiable evidence from time to time owed form is one of the policy considerations behind the BOT
or which may become owing by Concessionaire Law. Clearly, in the present case, the ARCA obligates the
[PIATCO] to Senior Lenders or any other persons or Government to pay for all loans, advances and obligations
entities who have provided, loaned, or advanced funds arising out of financial facilities extended to PIATCO for the
or provided financial facilities to Concessionaire implementation of the NAIA IPT III project should PIATCO default
[PIATCO] for the Project [NAIA Terminal 3], including, in its loan obligations to its Senior Lenders and the latter fails to
without limitation, all principal, interest, associated appoint a qualified nominee or transferee. This in effect would
fees, charges, reimbursements, and other related make the Government liable for PIATCO's loans should the
expenses (including the fees, charges and expenses of any conditions as set forth in the ARCA arise. This is a form of direct
agents or trustees of such persons or entities), whether government guarantee.
payable at maturity, by acceleration or otherwise, and
further including amounts owed by Concessionaire [PIATCO]
The BOT Law and its implementing rules provide that in order for
to its professional consultants and advisers, suppliers,
an unsolicited proposal for a BOT project may be accepted, the
contractors and sub-contractors.54
following conditions must first be met: (1) the project involves a
new concept in technology and/or is not part of the list of
It is clear from the foregoing contractual provisions that in the priority projects, (2) no direct government guarantee,
event that PIATCO fails to fulfill its loan obligations to its Senior subsidy or equity is required, and (3) the government
Lenders, the Government is obligated to directly negotiate and agency or local government unit has invited by publication other
enter into an agreement relating to NAIA IPT III with the Senior interested parties to a public bidding and conducted the
Lenders, should the latter fail to appoint a qualified nominee or same.56 The failure to meet any of the above conditions will
transferee who will take the place of PIATCO. If the Senior result in the denial of the proposal. It is further provided that the
Lenders and the Government are unable to enter into an presence of direct government guarantee, subsidy or equity will
agreement after the prescribed period, the Government must "necessarily disqualify a proposal from being treated and
then pay PIATCO, upon transfer of NAIA IPT III to the accepted as an unsolicited proposal." 57 The BOT Law clearly and
Government, termination payment equal to the appraised value strictly prohibits direct government guarantee, subsidy and
of the project or the value of the attendant liabilities equity in unsolicited proposals that the mere inclusion of a
whichever is greater. Attendant liabilities as defined in the provision to that effect is fatal and is sufficient to deny the
ARCA includes all amounts owed or thereafter may be owed by proposal. It stands to reason therefore that if a proposal can be
PIATCO not only to the Senior Lenders with whom PIATCO has denied by reason of the existence of direct government
defaulted in its loan obligations but to all other persons who guarantee, then its inclusion in the contract executed after the
may have loaned, advanced funds or provided any other type of said proposal has been accepted is likewise sufficient to
financial facilities to PIATCO for NAIA IPT III. The amount of invalidate the contract itself. A prohibited provision, the
PIATCO's debt that the Government would have to pay as a inclusion of which would result in the denial of a proposal
result of PIATCO's default in its loan obligations -- in case no cannot, and should not, be allowed to later on be inserted in the
qualified nominee or transferee is appointed by the Senior contract resulting from the said proposal. The basic rules of
Lenders and no other agreement relating to NAIA IPT III has justice and fair play alone militate against such an occurrence
been reached between the Government and the Senior Lenders and must not, therefore, be countenanced particularly in this
-- includes, but is not limited to, "all principal, interest, instance where the government is exposed to the risk of
associated fees, charges, reimbursements, and other related shouldering hundreds of million of dollars in debt.
expenses . . . whether payable at maturity, by acceleration or
otherwise."55
This Court has long and consistently adhered to the legal maxim
that those that cannot be done directly cannot be done
It is clear from the foregoing that the ARCA provides for indirectly.58 To declare the PIATCO contracts valid despite
a direct guarantee by the government to pay PIATCO's the clear statutory prohibition against a direct
loans not only to its Senior Lenders but all other entities government guarantee would not only make a mockery
who provided PIATCO funds or services upon PIATCO's of what the BOT Law seeks to prevent -- which is to
default in its loan obligation with its Senior Lenders. The expose the government to the risk of incurring a
fact that the Government's obligation to pay PIATCO's lenders monetary obligation resulting from a contract of loan
for the latter's obligation would only arise after the Senior between the project proponent and its lenders and to
Lenders fail to appoint a qualified nominee or transferee does which the Government is not a party to -- but would also
not detract from the fact that, should the conditions as stated in render the BOT Law useless for what it seeks to achieve
the contract occur, the ARCA still obligates the Government to - to make use of the resources of the private sector in
126
the "financing, operation and maintenance of shall be offset from the amount next payable by
infrastructure and development projects"59 which are Concessionaire to GRP.62
necessary for national growth and development but
which the government, unfortunately, could ill-afford to
PIATCO cannot, by mere contractual stipulation,
finance at this point in time.
contravene the Constitutional provision on temporary
government takeover and obligate the government to
IV pay "reasonable cost for the use of the Terminal and/or
Terminal Complex."63 Article XII, section 17 of the 1987
Constitution envisions a situation wherein the exigencies of the
Temporary takeover of business affected with public
times necessitate the government to "temporarily take over or
interest
direct the operation of any privately owned public utility or
business affected with public interest." It is the welfare and
Article XII, Section 17 of the 1987 Constitution provides: interest of the public which is the paramount consideration in
determining whether or not to temporarily take over a particular
business. Clearly, the State in effecting the temporary takeover
Section 17. In times of national emergency, when the
is exercising its police power. Police power is the "most
public interest so requires, the State may, during the
essential, insistent, and illimitable of powers." 64 Its exercise
emergency and under reasonable terms prescribed by
therefore must not be unreasonably hampered nor its exercise
it, temporarily take over or direct the operation of any
be a source of obligation by the government in the absence of
privately owned public utility or business affected with
damage due to arbitrariness of its exercise. 65 Thus, requiring the
public interest.
government to pay reasonable compensation for the reasonable
use of the property pursuant to the operation of the business
The above provision pertains to the right of the State in times of contravenes the Constitution.
national emergency, and in the exercise of its police power, to
temporarily take over the operation of any business affected
V
with public interest. In the 1986 Constitutional Commission, the
term "national emergency" was defined to include threat from
external aggression, calamities or national disasters, but not Regulation of Monopolies
strikes "unless it is of such proportion that would paralyze
government service."60 The duration of the emergency itself is
A monopoly is "a privilege or peculiar advantage vested in one
the determining factor as to how long the temporary takeover
or more persons or companies, consisting in the exclusive right
by the government would last.61 The temporary takeover by the
(or power) to carry on a particular business or trade,
government extends only to the operation of the business and
manufacture a particular article, or control the sale of a
not to the ownership thereof. As such the government is not
particular commodity."66 The 1987 Constitution strictly
required to compensate the private entity-owner of the
regulates monopolies, whether private or public, and even
said business as there is no transfer of
provides for their prohibition if public interest so requires. Article
ownership, whether permanent or temporary. The private
XII, Section 19 of the 1987 Constitution states:
entity-owner affected by the temporary takeover cannot,
likewise, claim just compensation for the use of the said
business and its properties as the temporary takeover by the Sec. 19. The state shall regulate or prohibit monopolies
government is in exercise of its police power and not of its when the public interest so requires. No combinations
power of eminent domain. in restraint of trade or unfair competition shall be
allowed.
Article V, Section 5.10 (c) of the 1997 Concession Agreement
provides: Clearly, monopolies are not per se prohibited by the Constitution
but may be permitted to exist to aid the government in carrying
on an enterprise or to aid in the performance of various services
Section 5.10 Temporary Take-over of operations by GRP.
and functions in the interest of the public.67 Nonetheless, a
determination must first be made as to whether public interest
. requires a monopoly. As monopolies are subject to abuses that
can inflict severe prejudice to the public, they are subject to a
higher level of State regulation than an ordinary business
(c) In the event the development Facility or any part
undertaking.
thereof and/or the operations of Concessionaire or any
part thereof, become the subject matter of or be
included in any notice, notification, or declaration In the cases at bar, PIATCO, under the 1997 Concession
concerning or relating to acquisition, seizure or Agreement and the ARCA, is granted the "exclusive right to
appropriation by GRP in times of war or national operate a commercial international passenger terminal within
emergency, GRP shall, by written notice to the Island of Luzon" at the NAIA IPT III. 68This is with the
Concessionaire, immediately take over the operations exception of already existing international airports in Luzon such
of the Terminal and/or the Terminal Complex. During as those located in the Subic Bay Freeport Special Economic
such take over by GRP, the Concession Period shall be Zone ("SBFSEZ"), Clark Special Economic Zone ("CSEZ") and in
suspended; provided, that upon termination of war, Laoag City.69 As such, upon commencement of PIATCO's
hostilities or national emergency, the operations shall operation of NAIA IPT III, Terminals 1 and 2 of NAIA would cease
be returned to Concessionaire, at which time, the to function as international passenger terminals. This, however,
Concession period shall commence to run does not prevent MIAA to use Terminals 1 and 2 as domestic
again.Concessionaire shall be entitled to passenger terminals or in any other manner as it may deem
reasonable compensation for the duration of the appropriate except those activities that would compete with
temporary take over by GRP, which compensation NAIA IPT III in the latter's operation as an international
shall take into account the reasonable cost for passenger terminal.70 The right granted to PIATCO
the use of the Terminal and/or Terminal Complex, to exclusively operate NAIA IPT III would be for a period of
(which is in the amount at least equal to the debt twenty-five (25) years from the In-Service Date 71 and renewable
service requirements of Concessionaire, if the for another twenty-five (25) years at the option of the
temporary take over should occur at the time when government.72 Both the 1997 Concession Agreement and
Concessionaire is still servicing debts owed to project the ARCA further provide that, in view of the exclusive
lenders), any loss or damage to the Development right granted to PIATCO, the concession contracts of the
Facility, and other consequential damages. If the service providers currently servicing Terminals 1 and 2
parties cannot agree on the reasonable compensation would no longer be renewed and those concession
of Concessionaire, or on the liability of GRP as contracts whose expiration are subsequent to the In-
aforesaid, the matter shall be resolved in accordance Service Date would cease to be effective on the said
with Section 10.01 [Arbitration]. Any amount date.73
determined to be payable by GRP to Concessionaire
127
The operation of an international passenger airport terminal is bar, have a valid and binding contract with the Government,
no doubt an undertaking imbued with public interest. In entering through MIAA, whose period of effectivity, as well as the other
into a BuildOperate-and-Transfer contract for the construction, terms and conditions thereof, cannot be violated.
operation and maintenance of NAIA IPT III, the government has
determined that public interest would be served better if private
In fine, the efficient functioning of NAIA IPT III is imbued with
sector resources were used in its construction and an exclusive
public interest. The provisions of the 1997 Concession
right to operate be granted to the private entity undertaking the
Agreement and the ARCA did not strip government, thru the
said project, in this case PIATCO. Nonetheless, the privilege
MIAA, of its right to supervise the operation of the whole NAIA
given to PIATCO is subject to reasonable regulation and
complex, including NAIA IPT III. As the primary government
supervision by the Government through the MIAA, which is the
agency tasked with the job, 79 it is MIAA's responsibility to ensure
government agency authorized to operate the NAIA complex, as
that whoever by contract is given the right to operate NAIA IPT
well as DOTC, the department to which MIAA is attached. 74
III will do so within the bounds of the law and with due regard to
the rights of third parties and above all, the interest of the
This is in accord with the Constitutional mandate that a public.
monopoly which is not prohibited must be regulated. 75While it is
the declared policy of the BOT Law to encourage private sector
VI
participation by "providing a climate of minimum government
regulations,"76 the same does not mean that Government must
completely surrender its sovereign power to protect public CONCLUSION
interest in the operation of a public utility as a monopoly. The
operation of said public utility can not be done in an arbitrary
In sum, this Court rules that in view of the absence of the
manner to the detriment of the public which it seeks to serve.
requisite financial capacity of the Paircargo Consortium,
The right granted to the public utility may be exclusive but the
predecessor of respondent PIATCO, the award by the PBAC of
exercise of the right cannot run riot. Thus, while PIATCO may be
the contract for the construction, operation and maintenance of
authorized to exclusively operate NAIA IPT III as an international
the NAIA IPT III is null and void. Further, considering that the
passenger terminal, the Government, through the MIAA, has the
1997 Concession Agreement contains material and substantial
right and the duty to ensure that it is done in accord with public
amendments, which amendments had the effect of converting
interest. PIATCO's right to operate NAIA IPT III cannot also violate
the 1997 Concession Agreement into an entirely different
the rights of third parties.
agreement from the contract bidded upon, the 1997 Concession
Agreement is similarly null and void for being contrary to public
Section 3.01(e) of the 1997 Concession Agreement and the policy. The provisions under Sections 4.04(b) and (c) in relation
ARCA provide: to Section 1.06 of the 1997 Concession Agreement and Section
4.04(c) in relation to Section 1.06 of the ARCA, which constitute
a direct government guarantee expressly prohibited by, among
3.01 Concession Period
others, the BOT Law and its Implementing Rules and Regulations
are also null and void. The Supplements, being accessory
xxx xxx xxx contracts to the ARCA, are likewise null and void.

(e) GRP confirms that certain concession WHEREFORE, the 1997 Concession Agreement, the Amended
agreements relative to certain services and and Restated Concession Agreement and the Supplements
operations currently being undertaken at the Ninoy thereto are set aside for being null and void. SO ORDERED.
Aquino International Airport passenger Terminal I have
a validity period extending beyond the In-Service
SECOND DIVISION G.R. No. L-47207 September 25, 1980
Date. GRP through DOTC/MIAA, confirms that these
services and operations shall not be carried over to
the Terminal and the Concessionaire is under no legal JOSE F. ESCANO, JESUS F. ESCANO, VICENTA F. ESCANO,
obligation to permit such carry-over except PILAR ESCANO-BERNAD, SAMUEL F. ESCANO, ANA MA. N.
through a separate agreement duly entered into with ILANO, MARIA LOURDES E. NOEL, PILAR VICTORIA E.
Concessionaire. In the event Concessionaire becomes NOEL and GABRIEL NOEL, for himself and the minor heirs
involved in any litigation initiated by any such of his deceased wife LOURDES ESCANO, petitioners-
concessionaire or operator, GRP undertakes and hereby appellants,
holds Concessionaire free and harmless on full
vs.
indemnity basis from and against any loss and/or any
COURT OF APPEALS and REPUBLIC OF THE
liability resulting from any such litigation, including the
cost of litigation and the reasonable fees paid or PHILIPPINES, respondents-appellees.
payable to Concessionaire's counsel of choice, all such
amounts shall be fully deductible by way of an offset
from any amount which the Concessionaire is bound to
pay GRP under this Agreement.
AQUINO, J.:

During the oral arguments on December 10, 2002, the


counsel for the petitioners-in-intervention for G.R. No. The petitioners complain about the judgment of the Court of
155001 stated that there are two service providers Appeals, engrafting conditions on their repurchase of ten lots,
whose contracts are still existing and whose validity which were expropriated to form part of the Lahug Airport in
extends beyond the In-Service Date. One contract Cebu City, as well as the failure of the Appellate Court to grant
remains valid until 2008 and the other until 2010.77 them compensation for the use of the lots by the Civil
Aeronautics Administration (CAA) from the time that they
We hold that while the service providers presently operating at tendered the redemption price (Escano vs. Republic of the
NAIA Terminal 1 do not have an absolute right for the renewal or Philippines, CA-G.R. No. 57188-R, March 17, 1977).
the extension of their respective contracts, those contracts
whose duration extends beyond NAIA IPT III's In-Service-Date In 1964, those ten lots with a total area of 10,639 square meters
should not be unduly prejudiced. These contracts must be
were sold for P31,977 by Mamerto Escano, Inc. to the Republic
respected not just by the parties thereto but also by third
for use by the CAA.
parties. PIATCO cannot, by law and certainly not by contract,
render a valid and binding contract nugatory. PIATCO, by the
mere expedient of claiming an exclusive right to operate, cannot The sale was subject to the resolutory condition that when the
require the Government to break its contractual obligations to CAA would no longer use the lots as part of the airport, then the
the service providers. In contrast to the arrastre and stevedoring title thereto would revert to the seller upon reimbursement of
service providers in the case of Anglo-Fil Trading the price of P31,977 without interest. That condition was
Corporation v. Lazaro78 whose contracts consist of temporary annotated on the title issued to the Republic of the Philippines.
hold-over permits, the affected service providers in the cases at
128
In 1966, by means of two deeds of assignment and other The petitioners appealed to this Court. The Government did not
documents, the petitioners became the successors of Mamerto appeal.
Escano, Inc. to the reversionary right or the right to repurchase
the lots from the Republic of the Philippines. We hold that the Court of Appeals erred in imposing the said
conditions on the reconveyance of the ten lots to the petitioners,
In the meantime, or on April 27, 1966, the Mactan Airport a matter which was not raised in the pleadings.
commenced its operation and the Philippine Airlines stopped
using the Lahug Airport. Filipinas Airways and Air Manila ceased The propriety of imposing those conditions was not in issue in
to use the Lahug Airport at the end of 1966 and thereafter used the trial court and in the Court of Appeals. It was an immaterial
the Mactan Airport. (pp. 28-29, Record on Appeal p. 38, Rollo). point in the case. It was not included in any assignment of errors
in the Government's brief.
On the premise that the above-mentioned resolutory condition
had already been fulfilled, meaning that the ten lots were no When the petitioners filed in the Court of Appeals their motion
longer being used as part of the Lahug Airport because of the for reconsideration, the Solicitor General did not oppose their
operation of the Mactan Airport, the petitioners, through prayer that the imposition of the conditions be deleted from the
counsel, made on October 2, 1972 a written tender to the CAA decision. The Solicitor General confined his opposition to
of the repurchase price of P31,977 (Exh. G). petitioners prayer that the CAA be adjudged liable to pay
compensation for the use of the lots.
The Director of Civil Aviation rejected the tender in his reply of
October 4, 1972. He reasoned out that because the Lahug The Court of Appeals ignored the rule that the questions to be
Airport was still being utilized for general aviation, the ten lots raised on appeal are those raised in the court below and within
could not yet be released and returned to the reversionary the issues framed by the parties (Sec. 18, Rule 46, Rules of
owners (Exh. H). Court).

On November 29, 1972, the petitioners sued the Republic of the It also disregarded the rule that "no error which does not affect
Philippines (CAA) in the Court of First Instance of Cebu for the the jurisdiction over the subject matter will be considered unless
reconveyance of the ten lots (Civil Case No. L-13078). stated in the assignment of errors and properly argued in the
brief, save as the court, at its option, may notice plain errors not
After hearing, the trial court rendered a decision on October 30, specified, and also clerical errors" (Sec. 7, Rule 51, Rules of
1974, ordering the CAA to reconvey to the petitioners the ten Court).
lots after payment of the repurchase price of P31,977.
It departed from the accepted and usual course of an appeal by
The trial court found that the lots were no longer needed for the adjudicating a point which was not raised by the parties.
airport and that since 1964 they were never used for any Airport
facility. The 1964 contract of sale between the petitioners'
predecessors-in-interest and the Government is the law between
The petitioners (plaintiffs) appealed because the lower court did them. Had they intended that the conditions imposed in the
not award to them the reasonable compensation for the use and resale of General Campo's lots in 1961 should likewise be
occupation of the lots from the time that they tendered the imposed in the resale to the reversionary owners of the ten lots,
redemption price. they could have easily made a stipulation to that effect in the
1964 deed of sale.
The Government appealed because it believed that the
resolutory condition for the repurchase had not yet materialized. The fact that the contract of sale does not mention those
conditions means that they were never within the contemplation
of the parties. The Court of Appeals, in gratuitously imposing
The Court of Appeals affirmed the trial court's judgment allowing
those conditions, made a new contract for them.
the repurchase but it went farther. The Appellate Court ruled
that the repurchase should be subject to the same five
conditions which were imposed in 1961 on the resale made by In fact, the second condition "that the repurchases allow the
the CAA to General Isagani Campo of his two lots which are in CAA to continue using the property repurchased for airfield
proximity to petitioners' ten lots. Those conditions were as purposes, until such time as the airport operation is finally
follows (Exh. J-3): transferred to Mactan Airport" nullifies the reversion or
resolutory condition and negatives the trial court's findings that
the Lahug Aiport had ceased to be operational and that it had
(a) That all taxes imposed on the property
been replaced by the Mactan Airport.
from the time the property is repossessed by
the said spouses shall be paid by them.
The other point is that the Court of Appeals denied petitioners'
claim for reasonable compensation for the CAA's alleged use
(b) That the repurchasers shall allow the CAA
and occupancy of the lots from October 2, 1972 when the tender
to continue the property repurchased for
of the redemption price was made.
airfield purposes, until such time as the airport
operations are finally transferred to Mactan
Airport. The trial court disallowed that claim because (1) the
compensation was not stipulated by the parties in the contract
of sale; (2) the claim is inconsistent with petitioners' theory that
(c) That the CAA shall not pay any rents or
the CAA never used their lots for aviation purposes; (3) the
other charges for its continued use of the
Government, as owner, should not be required to pay rentals for
property.
the lots registered in its name, and (4) the petitioners'
predecessors-in-interest were able to use the price of P31,977.
(d) That the repurchase price of the property
in question shall be based on the price paid by
To those grounds, the Solicitor General adds that the CAA, as
the CAA for the acquisition.
owner, should not answer for the compensation for the use of
the lots before the issuance of a judicial declaration that the
(e) That the property shall not be resold by the resolutory condition had been fulfilled.
repurchasers until , the Lahug landing field is
finally transferred to Mactan Airport.
129
We hold that, while petitioners' claim for compensation may be the issue of performance bonus to voluntary arbitration" and
justified on the ground that the CAA should have reconveyed the that "the decision/award of the voluntary arbitrator shall be
ten lots upon the tender of the redemption price, nevertheless, respected and implemented by the parties as final and
it would seem to be inequitable to require the CAA to pay executory, in accordance with the law." 1
compensation when it had not derived any benefit from the lots.
On 14 August 1989, petitioner filed its position paper which
And, on the other hand, it is undeniable that during all the time aimed to show that the performance of the members of
that the reconveyance has not been effected the petitioners respondent union during the year was below the production
have been able to use the redemption price of P31,977 for their goals or targets set by Sime Darby for 1988-1989 and below
own purposes. previous years' levels for which reason the performance bonus
could not be granted. Petitioner there referred to the following
performance indicators: a) number of tires produced; b) degree
If any damage had been suffered by the petitioners due to the
of wastage of production materials; and c) number of pounds of
delay in the reconveyance, that damage might be equivalent to
tires produced per man hour. On that same day, 14 August
damnum absque injuria which is damage without injury or
1989, petitioner manifested before the Voluntary Arbitrator that
damage or injury inflicted without injustice, or loss or damage
it would file a Reply to the union's Position Paper submitted on
without violation of a legal right, or a wrong done to a man for
10 August 1989 not later than 18 August 1989.
which the law provides no remedy (1 Bouvier's Law Dictionary,
3rd Ed., p. 754).
However, before petitioner could submit its Reply to the union's
Position Paper, the Voluntary Arbitrator on 17 August 1989
The petitioners have been dealing with a governmental entity
issued an award which declared respondent union entitled to a
whose activities are presumably dictated by policy
performance bonus equivalent to 75% of the monthly basic pay
considerations and the public interest.
of its members. In that award, the Voluntary Arbitrator held that
a reading of the CBA provision on the performance bonus would
WHEREFORE, the decision of the Court of Appeals is modified by show that said provision was mandatory hence the only issue to
deleting therefrom the five conditions for the reconveyance of be resolved was the amount of performance bonus. The
the ten lots to the petitioners. The trial court's judgment is Voluntary Arbitrator further stated that petitioner company's
affirmed. No costs. SO ORDERED. financial statements as of 30 June 1988 revealed retained
earnings in the amount of P 324,370,372.32. From the foregoing,
THIRD DIVISION G.R. No. 90426 December 15, 1989 the Voluntary Arbitrator concluded that petitioner company
could well afford to give members of respondent union a
substantial performance bonus. The Voluntary Arbitrator also
SIME DARBY PILIPINAS, INC., petitioners, stated that there was evidence to show that the company has
vs. given performance bonuses to its managerial and non-unionized
DEPUTY ADMINISTRATOR BUENAVENTURA C. MAGSALIN employees as well as to monthly paid workers of the year 1988-
as Voluntary Arbitrator and the SIME DARBY EMPLOYEES 1989.
ASSOCIATION, respondents.

Petitioner filed a motion for reconsideration which motion was


FELICIANO, J.: not entertained by the Voluntary Arbitrator upon the ground that
under the ruling of this Court in Solidbank v. Bureau of Labor
The Petition for certiorari before us assails the award of Relations, (G.R. No. 64926, promulgated 8 October 1984;
Voluntary Arbitrator Buenaventura Magsalin dated 17 August unpublished) he, the Voluntary Arbitrator, had automatically lost
1989 which directed petitioner Sime Darby Pilipinas, Inc. (Sime jurisdiction over the arbitration case upon the issuance of the
Darby) to pay the members of private respondent Sime Darby award.
Employees Association (SDEA) a performance bonus equivalent
to seventy-five percent (75%) of their monthly basic pay for the In this Petition for Certiorari, petitioner mainly argues that
year 1988-1989.
respondent Voluntary Arbitrator gravely abused his discretion in
holding that the grant of performance bonus was mandatory and
On 13 June 1989, petitioner Sime Darby and private respondent that the only issue before him was the amount of the bonus. It is
SDEA executed a Collective Bargaining Agreement (CBA) contended that since a performance bonus is a "gift" based on
providing, among others, that: the company's performance, the same is not justified when the
company's performance has been poor. Petitioner claims that
during the fiscal year of 1988-1989, the company performed
Article X, Section 1. A performance bonus shall
poorly as shown by the decline in tire production for the said
be granted, the amount of which [is] to be
year as well as the increase of the rate of wastage of production
determined by the Company depending on the
materials, and also by the decrease in the number of tires
return of [sic] capital investment as reflected
produced per man hour. Petitioner also argues that even if a
in the annual financial statement.
performance bonus were justified, the Voluntary Arbitrator
gravely abused his discretion in giving an award of 75% of the
On 31 July 1989, the Sime Darby Salaried Employees monthly basic rate without any evidence of the basis used in
Association- ALU (SDSEA-ALU) wrote petitioner demanding the arriving at such an award. It is insisted that under the relevant
implementation of a provision Identical to the above contained CBA provision, the company determines the amount of the
in their own CBA with petitioner. Subsequently, petitioner called bonus if the same be justified. Petitioner also alleged that
both respondent SDEA and SDEA-ALU to a meeting wherein the respondent Arbitrator gravely erred when he based the award
former explained that it was unable to grant the performance on the company's retained earnings the level of which
bonus corresponding to the fiscal year 1988-1989 on the ground represents earnings accumulated during prior years and not
that the workers' performance during said period did not justify merely during the fiscal year 1988-1989.
the award of such bonus. On 27 July 1989, private respondent
SDEA filed with the National Conciliation and Mediation Board
On 8 November 1989, the Court temporarily restrained the
(NCMB) an urgent request for preventive conciliation between
enforcement of the Voluntary Arbitrator's award to prevent the
private respondent and petitioner.
petition at bar becoming moot and academic.

On 1 August 1989, the parties were called to a conciliation


We are not persuaded by petitioner's arguments.
meeting and in such meeting, both parties agreed to submit
their dispute to voluntary arbitration. Their agreement to
arbitrate stated, among other things, that they were "submitting
130
One point needs to be stressed at the outset: the award of a includes not only the determination of the existence of the
Voluntary Arbitrator is final and executory after ten (10) right of the union to this benefit but also the amount thereof.
calendar days from receipt of the award by the parties. 2 There This conclusion arises from a perusal of the terms of the
was a time when the award of a Voluntary Arbitrator relating to submission agreement entered into by Sime Darby Pilipinas,
money claims amounting to more than P 100,000.00 or forty Inc. and Sime Darby Employees Association which limited the
percent (40%) of the paid-up capital of the employer (whichever voluntary arbitration only with regard to submission of
was lower), could be appealed to the National Labor Relations position papers of the parties, disposition and rendition of the
Commission upon the grounds of (a) abuse of discretion; or (b) award. Nary (sic) a trace of qualification as to the sole issue of
gross incompetence, presumably of the arbitrator. 3 This is no performance bonus may be gleaned from a review of said
longer so today although, of course, certiorari will lie in agreement.
appropriate cases. A petition for certiorari under Rule 65 of the
Revised Rules of Court will lie only where a grave abuse of With that as a timely reminder, this Arbitrator now proceeds
discretion or an act without or in excess of jurisdiction on the to resolve the issues herein submitted for resolution. Without
part of the Voluntary Arbitrator is clearly shown. It must be doubt, the Sime Darby Employees Association is entitled to
borne in mind that the writ of certiorari is an extraordinary performance bonus. This conclusion arises from an analysis of
remedy and that certiorari jurisdiction is not to be equated with the imperative terms of the CBA provision on production
appellate jurisdiction. In a special civil action of certiorari, the bonus, hereinunder reproduced, to wit:
Court will not engage in a review of the facts found nor even of
the law as interpreted or applied by the Arbitrator unless the
supposed errors of fact or of law are so patent and gross and A performance bonus shall be granted the amount of which to
prejudicial as to amount to a grave abuse of discretion or an be determined by the Company depending on the return of
excess de pouvoir on the part of the Arbitrator. 4 The Labor Code capital investment as reflected in the annual financial
and its Implementing Rules thus clearly reflect the important statements. 5(Emphasis supplied)
public policy of encouraging recourse to voluntary arbitration
and of shortening the arbitration process by rendering the Analysis of the relevant provisions of the CBA between the
arbitral award non- appealable to the NLRC. The result is that a parties and examination of the record of the instant case lead us
voluntary arbitral award may be modified and set aside only to the conclusion that the Arbitrator's reading of the scope of his
upon the same grounds on which a decision of the NLRC itself own authority must be sustained.
may be modified or set aside, by this Court.
Article X, Section 1 of the CBA is, grammatically speaking, cast
Examination of the pleadings in the instant Petition shows that in mandatory terms: "A performance bonus shall be granted ..."
two (2) principal issues are raised: The first is whether or not the The CBA provision goes on, however, immediately to say that
Voluntary Arbitrator acted with grave abuse of discretion or the amount of the performance bonus "[is] to be determined by
without or in excess of jurisdiction in passing upon both the the Company." Thus, notwithstanding the literal or grammatical
question of whether or not a performance bonus is to be granted tenor of Article X, Section 1, as a practical matter, only the issue
by petitioner Sime Darby to the private respondents and the relating to the amount of the bonus to be declared appears
further question of the amount thereof. The second is whether or important. Not much reflection is needed to show that the
not the award by the Arbitrator of a performance bonus critical issue is the scope of authority of the company to
amounting to seventy five percent (75%) of the basic monthly determine the amount of any bonus to be granted. If the
salary of members of private respondent union itself constituted company's discretionary authority were to be regarded as
a grave abuse of discretion or an act without or in excess of unlimited and if the company may declare in any event a merely
jurisdiction. We consider these issues seriatim nominal bonus, the use of mandatory language in Article X,
Section 1, would seem largely illusory and cosmetic in effect.
1. In respect of the first issue, petitioner Sime Darby urges Alternatively, even if one were to disregard the use of "shall"
that the Arbitrator gravely abused his discretion in passing rather than "may" in Article X, Section 1, the question of
upon not only the question of whether or not a performance whether or not a performance bonus is to be granted, still
bonus is to be granted but also, in the affirmative case, the cannot realistically be dissociated from the intensely practical
matter of the amount thereof. The position of petitioner, to the issue of the amount of the bonus to be granted. It is noteworthy
extent we can understand it, is that the Arbitrator was that petitioner Sime Darby itself did not spend much time
authorized to determine only the question of whether or not a discussing as an abstract question whether or not the grant of a
performance bonus was to be granted, the second question performance bonus is per se obligatory upon the company.
being reserved for determination by the employer Sime Darby. Petitioner instead focused upon the production performance of
We noted earlier that in their agreement to arbitrate, the the company's employees as bearing upon the appropriateness
parties submitted to the Voluntary Arbitrator "the issue of of any amount of bonus. Further, if petitioner Sime Darby's
performance bonus." The language of the agreement to argument were to be taken seriously, one must conclude that
arbitrate may be seen to be quite cryptic. There is no the parties to the arbitration agreement intended to refer only a
indication at all that the parties to the arbitration agreement theoretical and practically meaningless issue to the Voluntary
regarded "the issue of performance bonus" as a two-tiered Arbitrator, a conclusion that we find thoroughly unacceptable.
issue, only one tier of which was being submitted to
arbitration. Possibly, Sime Darby's counsel considered that 2. We turn then to the issue of whether or not
issue as having dual aspects and intended in his own mind to the Voluntary Arbitrator gravely abused his discretion
submit only one of those aspects to the Arbitrator; if he did, or acted without or in excess of jurisdiction in awarding
however, he failed to reflect his thinking and intent in the an amount equivalent to seventy-five percent (75%) of
arbitration agreement. the basic monthly pay of members of respondent
union. Petitioner Sime Darby contends that that award
It is thus essential to stress that the Voluntary Arbitrator had is devoid of factual basis. We understand this
plenary jurisdiction and authority to interpret the agreement contention to be that the Arbitrator did not apply the
to arbitrate and to determine the scope of his own authority relevant CBA provision.
subject only, in a proper case, to the certiorari jurisdiction of
this Court. The Arbitrator, as already indicated, viewed his Once more, we are not persuaded by petitioner's contention.
authority as embracing not merely the determination of the
abstract question of whether or not a performance bonus was
Article X, Section 1 of the CBA does not in express terms identify
to be granted but also, in the affirmative case, the amount
whose performance is to appraised in determining an
thereof. The Arbitrator said in his award:
appropriate amount to be awarded as performance bonus. The
Court considers that it is the performance of the company as a
At this juncture, it would not be amiss to emphasize to the whole, and not merely the production or manufacturing
parties that the matter of performance bonus necessarily
131
performance of its employees, which is relevant in that WESTERN MINOLCO CORPORATION, petitioner,
determination. The CBA provision refers to the return on vs.
investment of the company (ROI). The return on the COURT OF APPEALS and GREGORIAN MINING
stockholders' investment, as we understand it, relates basically COMPANY, respondents.
to the net profits shown by the company and therefore to many
more factors than simply the extent to which production targets NARVASA, J.:
were achieved or the rise and fall of the manufacturing
efficiency ratios. Among those factors would be the cost of
production, the quality of the products, the cost of money, the A series of contracts was entered into between Western Minolco
debt-equity ratio, the cost of sales, the level of taxes due and Corporation and Gregorian Mining Company, basically for the
payable, the gross revenues realized, and so forth. operation by the former of the latter's mining claims. 1 One of
the stipulations in the contracts (a) declared certain particular
disputes to be subject to arbitration and (b) specified the
We note upon the other hand, that petitioner's counsel failed to manner of enforcement by court action of the resulting
discuss at all before the Voluntary Arbitrator the rate of return arbitration awards. 2 The stipulation reads as follows:
on stockholders' investment achieved by Sime Darby for the
year 1988- 1989; as earlier noted, counsel confined his
argument and the evidence submitted by him to the number of Article XII
tires produced, the decrease in the rate of wastage of
manufacturing materials, and the productivity of the work force 12.01. Should any dispute, difference or
measured in terms of the number of tires produced per man disagreement arise between the CLAIM-OWNER and the
hour. COMPANY regarding the meaning, application or effect
of this Agreement or of any clause thereof, or in regard
The Voluntary Arbitrator, upon the other hand, explicitly to the amount and computation of the royalties,
considered the net earnings of petitioner Sime Darby in 1988 (P deductions, or other item of expense hereinabove
100,000,000.00) and in the first semester of 1989 (P provided, such dispute, difference or disagreement
95,377,507.00) as well as the increase in the company's shall be referred to a board of arbitration to be
retained earnings from P 265,729,826.00 in 1988 to P 324, composed of one arbitrator to be appointed by the
370,372.00 as of 30 June 1989. Thus, the Arbitrator impliedly or COMPANY, another to be appointed by the CLAIM-
indirectly took into account the return on stockholders' OWNER, and a third to be selected by the two
investment realized for the fiscal year 1988-1989. It should also aforementioned arbitrators, the decision of a majority
be noted that the relevant CBA provision does not specify a of the said arbitrators to be binding upon the parties,
minimum rate of return on investment (ROI) which must be insofar as the same is permitted by law. No action shall
realized before any particular amount of bonus may or should be be instituted in any Court by either party hereto, unless
declared by the company. the dispute, difference or disagreement, shall have
been first submitted to and received by said board of
arbitrators, and any such action shall be based upon
The Voluntary Arbitrator also took into account, again in an the award as obtained.
indirect manner, the performance of Sime Darby's employees by
referring in his award to "the total labor cost incurred by the
Company": 12.02The parties stipulate that the venue of
the actions referred to in Section 12.01 shall
be in the City of Manila.
This Arbitrator, however, is well aware that
any effort in this regard must be tempered and
balanced as against the need to sustain the continued There are, it will be noted, only two (2) classes of disputes or
viability of Sime Darby Pilipinas, Inc. in accordance with disagreements governed by these provisions:
the constitutional provision which recognizes the 'right
of enterprise to reasonable returns on investment and 1) those "regarding the meaning, application or effect of the
to expansion and growth.' Furthermore, any award to agreement(s) or any clause thereof," and
be rendered must likewise take into account the total
labor cost incurred by the Company. It should not
2) those "in regard to the amount and computation of the
merely be confined to those pertaining to the members
royalties, deductions, or other item of expense" provided in the
of the Sime Darby Employees Association but
agreement.
necessarily include that which shall be paid and
granted to all other employees of Sime Darby this
year. 6 (Emphasis supplied) It is made quite clear that these two (2) classes of disputes are
to be "referred to a board of arbitration." It is made equally clear
that no action concerning them may be instituted in any court
On balance, we believe and so hold that the award of the
by either party (1) unless the controversy be "first submitted to
Voluntary Arbitrator of a bonus amounting to seventy-five
and received by said board of arbitrators," and (2) only if the
percent (75%) of the basic monthly salary cannot be said to be
action "be based upon the award as obtained. " In the event of
merely arbitrary or capricious or to constitute an excess de
such an action, the venue thereof "shall be in the City of
pouvoir.
Manila."

The remaining assertions of petitioner Sime Darby relating to


Now, it appears that Western Minolco Corporation subsequently
denial of procedural due process by the Voluntary Arbitrator,
executed another agreement with another firm, the Dreamers
consisting of failure to wait for petitioner's announced Reply
Mining Association, for the validation of 36 mineral lode claims
(basically reiterative and amplificatory in nature) to the union's
in the latter's favor. As it happened, those 36 claims were
Position Paper and of alleged failure to consider evidence
believed by Gregorian Mining Company to be in conflict with,
submitted by petitioner, do not require extended consideration;
and had been superimposed on its own claims, which it had
they are evidently bereft of merit.
earlier located and which were in fact subject of the series of
agreements signed by it and Western Minolco Corporation.
WHEREFORE, the Petition for Certiorari is DISMISSED for lack of Gregorian Mining Company consequently brought suit against
merit. The Temporary Restraining Order issued on 8 November Western Minolco Corporation in the Court of First Instance of
1989 is hereby LIFTED. This Decision is immediately executory. Baguio and Benguet, for the rescission of their agreements and
Costs against petitioner.SO ORDERED. damages. 3

FIRST DIVISIONG.R. No. L-51996 November 23, 1988


132
Western Minolco moved to dismiss the complaint, theorizing that a third party the selfsame claims which it had earlier
(a) venue had been improperly laid, and (b) the complaint undertaken to operate for Gregorian. Clearly, such a controversy
stated no cause of action. 4 Gregorian opposed the motion, does not fall within either of the two categories of disputes
arguing that (a) the stipulation regarding venue in the parties' which must first be submitted for arbitration. The stipulation in
agreements was merely permissive and did not preclude the question (for arbitration to be first had) did not therefore
filing of an action conformably with the general rules of venue in constitute an impediment or a bar to the institution of the action
Section 2, Rule 4 of the Rules of Court, and (b) there was a commenced by Gregorian against Western Minolco, for
cause of action set forth in the complaint within the Trial Court's rescission and damages.
jurisdiction because the action involved a dispute which was not
arbitrable in accordance with their contracts. 5 Western Minolco Even if, for the sake of argument, some measure of tenability be
filed a reply. 6 The Trial Court 7 denied Western Minolco's conceded to the opposite view: that the controversy subject of
motion to dismiss and required it to file its responsive pleading Civil Case No. 2272 (220) might be considered as dealing with
within the prescribed period. 8 The Court also denied Western the "meaning, application or effect" of the agreement
Minolco's motion for reconsideration. 9 specifically, whether the claims therein described are the very
same mining claims subject of Western Minolco's subsequent
In the meantime, and while it was seeking reconsideration of the agreement with a third partyand therefore should first be
Baguio Court's adverse order, Western Minolco filed a petition submitted to and resolved by a board of arbitrators, the worst
with the Court of First Instance of Manila to compel arbitration, that could then be said of the orders of the Trial Court, affirmed
in line with its agreement with Gregorian, and for recovery of by the Court of Appeals, is that they are attended by an error in
damages against the latter. 10 After an exchange of pleadings, the analysis and interpretation of the language and import of
the petition was granted. 11 Gregorian sought to take an appeal the stipulation in question, but certainly not by that whimsical,
to the Court of Appeals; 12 but the Manila Court ruled that the capricious, or totally groundless or tangential exercise of
appeal should more properly be taken to this Court. 13 adjudgment or discretion as would justify the issuance of the
extraordinary writ of certiorari or prohibition. 17 In no sense
may it be said that power has been exercised by either the
Gregorian decided to forego the appeal, and to await instead the
Appellate Court or the Trial Court in so arbitrary or despotic a
decision of the Court of Appeals on the petition for certiorari and
manner, as by reason of passion, prejudice or personal hostility,
prohibition which Western Minolco had in the meantime filed to
or in so patently and grossly mistaken a manner as to amount to
assail the Orders of the CFI of Baguio and Benguet (refusing to
an evasion of positive duty or a virtual refusal to perform a duty
dismiss the action [Case No. 2272 (220)] brought against it by
enjoined or to act at all in contemplation of law, so as to make
Gregorian). 14 The Court of Appeals was not persuaded by
needful the extension of this Court's correcting hand by the
Western Minolco's arguments, and dismissed its petition, by
peremptory writ of certiorari or prohibition. 18
decision dated August 29, 1979. 15 It later denied Western
Minolco's motion for reconsideration. 16 This decision of August
29, 1979, and the order denying reconsideration, are challenged Since the stipulation as to venue becomes relevant only when
in the instant appeal. The verdict must go against the petitioner, an action has to be instituted "based upon the award as
Western Minolco Corporation. obtained" (from the board of arbitrators) (i.e., as the mode of
enforcement of the award); and since there is here no such
award because no controversy subject to arbitration existed and
It is Western Minolco's thesis that it was reversible error for the
was ever submitted to arbitration, no error can possibly be
Court of Appeals to find and declare that
imputed to the Trial Court in not applying the stipulation to the
action a quo. In any event, it is not entirely amiss to restate the
a) the venue of the action instituted against it by Gregorian doctrine that stipulations in a contract, which specify a definite
Mining Co. was improperly laid; place for the institution of an action arising in connection
therewith, do not, as a rule, supersede the general rules on the
b) the action could not be instituted until and unless the matter set out in Rule 4 of the Rules of Court, but should be
dispute subject thereof had first been resolved by construed merely as an agreement on an additional forum, not
arbitration, as covenanted by the parties; as limiting venue to the specified place. 19

c) public policy encourages arbitration and arbitration WHEREFORE, the petition is DENIED, and the decision of the
agreements are to be liberally construed; Court of Appeals subject of the appeal is AFFIRMED. Costs
against petitioner.

d) the Trial Court had no business interpreting the


provisions of the agreement the terms of which were SO ORDERED.
otherwise clear, unambiguous and unequivocal.
SECOND DIVISION[G.R. No. 115412. November 19, 1999]
The terms of the applicable provision of the parties' agreements
are indeed "clear, unambiguous, and unequivocal." As pointed HOME BANKERS SAVINGS AND TRUST
out in the opening paragraphs of this opinion, only two (2) kinds COMPANY, petitioner vs. COURT OF APPEALS and
of "disputes, differences or disagreements" have been made FAR EAST BANK & TRUST COMPANY, respondents.
subject of arbitration:

BUENA , J.:
1) those "regarding the meaning, application or effect of the
agreement(s) or any clause thereof;" and
This appeal by certiorari under Rule 45 of the Rules of
Court seeks to annul and set aside the decision [1] of the Court of
2) those "in regard to the amount and computation of the Appeals[2] dated January 21, 1994 in CA-G.R. SP No. 29725,
royalties, deduction, or other item of expense" provided in the dismissing the petition for certiorari filed by petitioner to annul
agreement. the two (2) orders issued by the Regional Trial Court of
Makati[3] in Civil Case No. 92-145, the first, dated April 30, 1992,
The controversy involved in the action brought by Gregorian denying petitioner's motion to dismiss and the second, dated
against Western Minolco was the alleged violation by the latter October 1, 1992 denying petitioner's motion for reconsideration
of its agreements with the former, consisting of its entering into thereof.
a contract with a third party for the validation of mining claims
which it knew had already been located by Gregorian. What was The pertinent facts may be briefly stated as follows: Victor
involved, in other words, was the breach of faith, or the double Tancuan, one of the defendants in Civil Case No. 92-145, 0issued
dealing of Western Minolco in undertaking to validate in favor of Home Bankers Savings and Trust Company (HBSTC) check No.
133
193498 for P25,250,000.00 while Eugene Arriesgado issued Far respondent court held that "if the absence of a prior arbitration
East Bank and Trust Company (FEBTC) check Nos. 464264, may stay court action, so too and with more reason, should an
464272 and 464271 for P8,600,000.00, P8,500,000.00 arbitration already pending as obtains in this case stay the court
and P8,100,000.00, respectively, the three checks amounting action. A party to a pending arbitral proceeding may go to court
to P25,200,000.00. Tancuan and Arriesgado exchanged each to obtain conservatory reliefs in connection with his cause of
other's checks and deposited them with their respective banks action although the disposal of that action on the merits cannot
for collection. When FEBTC presented Tancuan's HBSTC check for as yet be obtained."[18] The respondent court
clearing, HBSTC dishonored it for being "Drawn Against discarded Puromines, Inc. vs. Court of Appeals,[19] stating that
Insufficient Funds." On October 15, 1991, HBSTC sent "perhaps Puromines may have been decided on a different
Arriesgado's three (3) FEBTC checks through the Philippine factual basis."[20]
Clearing House Corporation (PCHC) to FEBTC but was returned
on October 18, 1991 as "Drawn Against Insufficient Funds." In the instant petition,[21] petitioner contends that first, "no
HBSTC received the notice of dishonor on October 21, 1991 but party litigant can file a non-existent complaint," [22] arguing that
refused to accept the checks and on October 22, 1991, returned "one cannot file a complaint in court over a subject that is
them to FEBTC through the PCHC for the reason "Beyond undergoing arbitration."[23] Second, petitioner submits that
Reglementary Period," implying that HBSTC already treated the "[s]ince arbitration is a special proceeding by a clear provision of
three (3) FEBTC checks as cleared and allowed the proceeds law,[24] the civil suit filed below is, without a shadow of doubt,
thereof to be withdrawn.[4] FEBTC demanded reimbursement for barred by litis pendencia and should be dismissed de
the returned checks and inquired from HBSTC whether it had plano insofar as HBSTC is concerned." [25] Third, petitioner insists
permitted any withdrawal of funds against the unfunded checks that "[w]hen arbitration is agreed upon and suit is filed without
and if so, on what date. HBSTC, however, refused to make any arbitration having been held and terminated, the case that is
reimbursement and to provide FEBTC with the needed filed should be dismissed,"[26] citing Associated Bank vs. Court of
information. Appeals,[27] Puromines, Inc. vs. Court of Appeals, [28] and Ledesma
vs. Court of Appeals.[29] Petitioner demurs that
Thus, on December 12, 1991, FEBTC submitted the dispute the Puromines ruling was deliberately not followed by the
for arbitration before the PCHC Arbitration Committee, [5] under respondent court which claimed that:
the PCHC's Supplementary Rules on Regional Clearing to which
FEBTC and HBSTC are bound as participants in the regional "xxx xxx.
clearing operations administered by the PCHC. [6]

It would really be much easier for Us to rule to dismiss the


On January 17, 1992, while the arbitration proceedings was complainant as the petitioners here seeks to do, following
still pending, FEBTC filed an action for sum of money and Puromines. But with utmost deference to the Honorable
damages with preliminary attachment[7] against HBSTC, Robert Supreme Court, perhaps Puromines may have been decided on
Young, Victor Tancuan and Eugene Arriesgado with the Regional a different factual basis.
Trial Court of Makati, Branch 133. A motion to dismiss was filed
by HBSTC claiming that the complaint stated no cause of action
and accordingly should be dismissed because it seeks to enforce xxx xxx."[30]
an arbitral award which as yet does not exist. [8] The trial court
issued an omnibus order dated April 30, 1992 denying the Petitioner takes exception to FEBTC's contention
motion to dismiss and an order dated October 1, 1992 denying that Puromines cannot modify or reverse the rulings in National
the motion for reconsideration. Union Fire Insurance Company of Pittsburg vs. Stolt-Nielsen
Philippines, Inc.,[31] and Bengson vs. Chan,[32] where this Court
On December 16, 1992, HBSTC filed a petition suspended the action filed pending arbitration, and argues that
for certiorari with the respondent Court of Appeals contending "[s]ound policy requires that the conclusion of whether a
that the trial court acted with grave abuse of discretion Supreme Court decision has or has not reversed or modified [a]
amounting to lack of jurisdiction in denying the motion to previous doctrine, should be left to the Supreme Court itself;
dismiss filed by HBSTC. until then, the latest pronouncement should prevail." [33] Fourth,
petitioner alleges that the writ of preliminary attachment issued
by the trial court is void considering that the case filed before it
In a Decision[9] dated January 21, 1994, the respondent "is a separate action which cannot exist,"[34] and "there is even
court dismissed the petition for lack of merit and held that no need for the attachment as far as HBSTC is concerned
"FEBTC can reiterate its cause of action before the courts which because such automatic debit/credit procedure [35] may be
it had already raised in the arbitration case" [10] after finding that regarded as a security for the transactions involved and, as
the complaint filed by FEBTC "seeks to collect a sum of money jurisprudence confirms, one requirement in the issuance of an
from HBT [HBSTC] and not to enforce or confirm an arbitral attachment [writ of preliminary attachment] is that the debtor
award."[11] The respondent court observed that "[i]n the has no sufficient security." [36] Petitioner asserts further that a
Complaint, FEBTC applied for the issuance of a writ of writ of preliminary attachment is unwarranted because no
preliminary attachment over HBT's [HBSTC] property" [12] and ground exists for its issuance. According to petitioner, "the only
citing section 14 of Republic Act No. 876, otherwise known as allegations against it [HBSTC] are that it refused to refund the
the Arbitration Law, maintained that "[n]ecessarily, it has to amounts of the checks of FEBTC and that it knew about the
reiterate its main cause of action for sum of money against HBT fraud perpetrated by the other defendants,"[37] which, at best,
[HBSTC],"[13] and that "[t]his prayer for conservatory relief [writ constitute only "incidental fraud" and not causal fraud which
of preliminary attachment] satisfies the requirement of a cause justifies the issuance of the writ of preliminary attachment.
of action which FEBTC may pursue in the courts."[14]

Private respondent FEBTC, on the other hand, contends


Furthermore, the respondent court ruled that based on that "the cause of action for collection [of a sum of money] can
section 7 of the Arbitration Law and the cases of National coexist in the civil suit and the arbitration [proceeding]" [38] citing
Union Fire Insurance Company of Pittsburg vs. Slolt- section 7 of the Arbitration Law which provides for the stay of
Nielsen Philippines, Inc.,[15] and Bengson vs. Chan,[16] "when the civil action until an arbitration has been had in accordance
there is a condition requiring prior submission to arbitration with the terms of the agreement providing for
before the institution of a court action, the complaint is not to be arbitration. Private respondent further asserts that following
dismissed but should be suspended for arbitration."[17] Finding no section 4(3), article VIII [39]of the 1987 Constitution, the
merit in HBSTC's contention that section 7 of the Arbitration Law subsequent case of Puromines does not overturn the ruling in
"contemplates a situation in which a party to an arbitration the earlier cases of National Union Fire Insurance Company of
agreement has filed a court action without first resorting to Pittsburg vs. Stolt-Nielsen Philippines, Inc.
arbitration, while in the case at bar, FEBTC has initiated [40]
and Bengson vs. Chan,[41] hence, private respondents
arbitration proceedings before filing a court action," the
134
concludes that the prevailing doctrine is that the civil action act of participation of the parties concerned in its
must be stayed rather than dismissed pending arbitration. operations in effect amounts to a manifestation of
agreement by the parties to abide by its rules and
regulations. As a consequence of such
In this petition, the lone issue presented for the
participation, a party cannot invoke the
consideration of this Court is:
jurisdiction of the courts over disputes and
controversies which fall under the PCHC Rules
WHETHER OR NOT PRIVATE RESPONDENT WHICH and Regulations without first going through the
COMMENCED AN ARBITRATION PROCEEDING UNDER arbitration processes laid out by the
THE AUSPICES OF THE PHILIPPINE CLEARING HOUSE body."[47] (emphasis supplied)
CORPORATION (PCHC) MAY SUBSEQUENTLY FILE A
SEPARATE CASE IN COURT OVER THE SAME SUBJECT
And thus we concluded:
MATTER OF ARBITRATION DESPITE THE PENDENCY OF
THAT ARBITRATION, SIMPLY TO OBTAIN THE
PROVISIONAL REMEDY OF ATTACHMENT AGAINST THE "Clearly therefore, petitioner Associated Bank,
BANK, THE ADVERSE PARTY IN THE ARBITRATION by its voluntary participation and its consent to
PROCEEDINGS."[42] the arbitration rules cannot go directly to the
Regional Trial Court when it finds it convenient to
do so. The jurisdiction of the PCHC under the rules and
We find no merit in the petition. Section 14 of Republic Act
regulations is clear, undeniable and is particularly
876, otherwise known as the Arbitration Law, allows any party to
applicable to all the parties in the third party complaint
the arbitration proceeding to petition the court to take measures
under their obligation to first seek redress of their
to safeguard and/or conserve any matter which is the subject of
disputes and grievances with the PCHC before going to
the dispute in arbitration, thus:
the trial court."[48](emphasis supplied)

Section 14. Subpoena and subpoena duces tecum. - Arbitrators


Simply put, participants in the regional clearing operations
shall have the power to require any person to attend a hearing
of the Philippine Clearing House Corporation cannot bypass
as a witness. They shall have the power to subpoena witnesses
the arbitration process laid out by the body and seek
and documents when the relevancy of the testimony and the
relief directly from the courts. In the case at bar,
materiality thereof has been demonstrated to the
undeniably, private respondent has initiated arbitration
arbitrators. Arbitrators may also require the retirement of any
proceedings as required by the PCHC rules and regulations, and
witness during the testimony of any other witness. All of the
pending arbitration has sought relief from the trial court for
arbitrators appointed in any controversy must attend all the
measures to safeguard and/or conserve the subject of the
hearings in that matter and hear all the allegations and proofs of
dispute under arbitration, as sanctioned by section 14 of the
the parties; but an award by the majority of them is valid unless
Arbitration Law, and otherwise not shown to be contrary to the
the concurrence of all of them is expressly required in the
PCHC rules and regulations.
submission or contract to arbitrate. The arbitrator or
arbitrators shall have the power at any time, before
rendering the award, without prejudice to the rights of Likewise, in the case of Puromines, Inc. vs. Court of
any party to petition the court to take measures to Appeals,[49] we have ruled that:
safeguard and/or conserve any matter which is the
subject of the dispute in arbitration. (emphasis supplied) "In any case, whether the liability of respondent should
be based on the sales contract or that of the bill of
Petitioner's exposition of the foregoing provision deserves lading, the parties are nevertheless obligated to
scant consideration. Section 14 simply grants an arbitrator the respect the arbitration provisions on the sales contract
power to issue subpoena and subpoena duces tecum at any and/or bill of lading. Petitioner being a signatory and
time before rendering the award. The exercise of such power is party to the sales contract cannot escape from his
without prejudice to the right of a party to file a petition in court obligation under the arbitration clause as stated
to safeguard any matter which is the subject of the dispute in therein."
arbitration. In the case at bar, private respondent filed an action
for a sum of money with prayer for a writ of preliminary In Puromines, we found the arbitration clause stated in
attachment. Undoubtedly, such action involved the same the sales contract to be valid and applicable, thus, we ruled that
subject matter as that in arbitration, i.e., the sum the parties, being signatories to the sales contract, are obligated
of P25,200,000.00 which was allegedly deprived from private to respect the arbitration provisions on the contract and cannot
respondent in what is known in banking as a "kiting scheme." escape from such obligation by filing an action for breach of
However, the civil action was not a simple case of a money contract in court without resorting first to arbitration, as agreed
claim since private respondent has included a prayer for a writ upon by the parties.
of preliminary attachment, which is sanctioned by section 14 of
the Arbitration Law.
At this point, we emphasize that arbitration, as an
alternative method of dispute resolution, is encouraged by this
Petitioner cites the cases of Associated Bank vs. Court of Court. Aside from unclogging judicial dockets, it also hastens
Appeals,[43] Puromines, Inc. vs. Court of Appeals, [44] and Ledesma solutions especially of commercial disputes. [50] The Court looks
vs. Court of Appeals[45] in contending that "[w]hen arbitration is with favor upon such amicable arrangement and will only
agreed upon and suit is filed without arbitration having been interfere with great reluctance to anticipate or nullify the action
held and terminated, the case that is filed should be of the arbitrator.[51]
dismissed."[46] However, the said cases are not in
point. In Associated Bank, we affirmed the dismissal of the
third-party complaint filed by Associated Bank against Philippine WHEREFORE, premises considered, the petition is hereby
Commercial International Bank, Far East Bank & Trust Company, DISMISSED and the decision of the court a quo is AFFIRMED.
Security Bank and Trust Company and Citytrust Banking
Corporation for lack of jurisdiction, it being shown that the said SO ORDERED.
parties were bound by the Clearing House Rules and Regulations
on Arbitration of the Philippine Clearing House
SECOND DIVISIONG.R. No. 129916 March 26, 2001
Corporation. In Associated Bank, we declared that:

MAGELLAN CAPITAL MANAGEMENT CORPORATION and


"xxx xxx. Under the rules and regulations of the
MAGELLAN CAPITAL HOLDINGS CORPORATION, petitioners,
Philippine Clearing House Corporation (PCHC), the mere
vs.
135
ROLANDO M. ZOSA and HON. JOSE P. SOBERANO, JR., in having jurisdiction thereof, with costs of the arbitration
his capacity as Presiding Judge of Branch 58 of the to be borne equally by the parties, except that each
Regional Trial Court of Cebu, 7th Judicial party shall pay the fees and expenses of its own
Region, respondents. counsel in the arbitration."

BUENA, J.: On November 10, 1995, respondent Zosa designated his


brother, Atty. Francis Zosa, as his representative in the
arbitration panel9 while MCHC designated Atty. Inigo S.
Under a management agreement entered into on March 18,
Fojas10 and MCMC nominated Atty. Enrique I. Quiason 11as their
1994, Magellan Capital Holdings Corporation [MCHC] appointed
respective representatives in the arbitration panel. However,
Magellan Capital Management Corporation [MCMC] as manager
instead of submitting the dispute to arbitration, respondent
for the operation of its business and affairs. 1 Pursuant thereto,
Zosa, on April 17, 1996, filed an action for damages against
on the same month, MCHC, MCMC, and private respondent
petitioners before the Regional Trial Court of Cebu 12 to enforce
Rolando M. Zosa entered into an "Employment Agreement"
his benefits under the Employment Agreement.
designating Zosa as President and Chief Executive Officer of
MCHC.
On July 3, 1996, petitioners filed a motion to dismiss 13 arguing
that (1) the trial court has no jurisdiction over the instant case
Under the "Employment Agreement", the term of respondent
since respondent Zosa's claims should be resolved through
Zosa's employment shall be co-terminous with the management
arbitration pursuant to Section 23 of the Employment
agreement, or until March 1996,2 unless sooner terminated
Agreement with petitioners; and (2) the venue is improperly laid
pursuant to the provisions of the Employment Agreement. 3 The
since respondent Zosa, like the petitioners, is a resident of Pasig
grounds for termination of employment are also provided in the
City and thus, the venue of this case, granting without admitting
Employment Agreement.
that the respondent has a cause of action against the petitioners
cognizable by the RTC, should be limited only to RTC-Pasig City. 14
On May 10, 1995, the majority of MCHC's Board of Directors
decided not to re-elect respondent Zosa as President and Chief
Meanwhile, respondent Zosa filed an amended complaint dated
Executive Officer of MCHC on account of loss of trust and
July 5, 1996.
confidence4 arising from alleged violation of the resolution
issued by MCHC's board of directors and of the non-competition
clause of the Employment Agreement.5 Nevertheless, On August 1, 1996, the RTC Branch 58 of Cebu City issued an
respondent Zosa was elected to a new position as MCHC's Vice- Order denying petitioners motion to dismiss upon the findings
Chairman/Chairman for New Ventures Development. 6 that (1) the validity and legality of the arbitration provision can
only be determined after trial on the merits; and (2) the amount
of damages claimed, which is over P100,000.00, falls within the
On September 26, 1995, respondent Zosa communicated his
jurisdiction of the RTC.15 Petitioners filed a motion for
resignation for good reason from the position of Vice-Chairman
reconsideration which was denied by the RTC in an order
under paragraph 7 of the Employment Agreement on the ground
dated September 5, 1996.16
that said position had less responsibility and scope than
President and Chief Executive Officer. He demanded that he be
given termination benefits as provided for in Section 8 (c) (i) (ii) In the interim, on August 22, 1996, in compliance with the
and (iii) of the Employment Agreement.7 earlier order of the court directing petitioners to file responsive
pleading to the amended complaint, petitioners filed their
Answer Ad Cautelam with counterclaim reiterating their position
In a letter dated October 20, 1995, MCHC communicated its
that the dispute should be settled through arbitration and the
non-acceptance of respondent Zosa's resignation for good
court had no jurisdiction over the nature of the action.17
reason, but instead informed him that the Employment
Agreement is terminated for cause, effective November 19,
1995, in accordance with Section 7 (a) (v) of the said On October 21, 1996, the trial court issued its pre-trial order
agreement, on account of his breach of Section 12 thereof. declaring the pre-trial stage terminated and setting the case for
Respondent Zosa was further advised that he shall have no hearing. The order states:
further rights under the said Agreement or any claims against
the Manager or the Corporation except the right to receive "ISSUES:
within thirty (30) days from November 19, 1995, the amounts
stated in Section 8 (a) (i) (ii) of the Agreement.8
"The Court will only resolve one issue in so far as this
case is concerned, to wit:
Disagreeing with the position taken by petitioners, respondent
Zosa invoked the Arbitration Clause of the Employment
Agreement, to wit: "Whether or not the Arbitration Clause contained in
Sec. 23 of the Employment Agreement is void and of no
effect: and, if it is void and of no effect, whether or not
"23. Arbitration. In the event that any dispute, the plaintiff is entitled to damages in accordance with
controversy or claim arises out of or under any his complaint and the defendants in accordance with
provisions of this Agreement, then the parties hereto their counterclaim.
agree to submit such dispute, controversy or claim to
arbitration as set forth in this Section and the
determination to be made in such arbitration shall be "It is understood, that in the event the arbitration
final and binding. Arbitration shall be effected by a clause is valid and binding between the parties, the
panel of three arbitrators. The Manager, Employee and parties shall submit their respective claim to the
Corporation shall designate one (1) arbitrator who Arbitration Committee in accordance with the said
shall, in turn, nominate and elect who among them arbitration clause, in which event, this case shall be
shall be the chairman of the committee. Any such deemed dismissed."18
arbitration, including the rendering of an arbitration
award, shall take place in Metro Manila. The arbitrators On November 18, 1996, petitioners filed their Motion Ad
shall interpret this Agreement in accordance with the Cautelam for the Correction, Addition and Clarification of the
substantive laws of the Republic of the Philippines. The Pre-trial Order dated November 15, 1996, 19 which was denied by
arbitrators shall have no power to add to, subtract from the court in an order dated November 28, 1996.20
or otherwise modify the terms of Agreement or to grant
injunctive relief of any nature. Any judgment upon the
award of the arbitrators may be entered in any court
136
Thereafter, petitioners MCMC and MCHC filed a Motion Ad proper that each party be represented in the
Cautelam for the parties to file their Memoranda to support their arbitration panel.
respective stand on the issue of the validity of the "arbitration
clause" contained in the Employment Agreement. In an order "C. The trial court grievously erred in its
dated December 13, 1996, the trial court denied the motion of conclusion that petitioners MCMC and MCHC
petitioners MCMC and MCHC. represent the same interest.

On January 17, 1997, petitioners MCMC and MCHC filed a "D. Respondent Zosa is estopped from
petition for certiorari and prohibition under Rule 65 of the Rules questioning the validity of the arbitration
of Court with the Court of Appeals, questioning the trial court clause, including the right of petitioner MCMC
orders dated August 1, 1996, September 5, 1996, and to nominate its own arbitrator, which he
December 13, 1996.21 himself has invoked.

On March 21, 1997, the Court of Appeals rendered a decision, "II. In any event, the trial court acted without
giving due course to the petition, the decretal portion of which jurisdiction in hearing the case below, considering that
reads: it has no jurisdiction over the nature of the action or
suit since controversies in the election or appointment
"WHEREFORE, the petition is GIVEN DUE COURSE. The of officers or managers of a corporation, such as the
respondent court is directed to resolve the issue on the action brought by respondent Zosa, fall within the
validity or effectivity of the arbitration clause in the original and exclusive jurisdiction of the Securities and
Employment Agreement, and to suspend further Exchange Commission.
proceedings in the trial on the merits until the said
issue is resolved. The questioned orders are set aside "III. Contrary to respondent Zosa's allegation, the issue
insofar as they contravene this Court's resolution of the of the trial court's jurisdiction over the case below has
issues raised as herein pronounced. not yet been resolved with finality considering that
petitioners have expressly reserved their right to raise
"The petitioner is required to remit to this Court the said issue in the instant petition. Moreover, the
sum of P81.80 for cost within five (5) days from notice. principle of the law of the case is not applicable in the
instant case.
"SO ORDERED."22
"IV. Contrary to respondent Zosa's allegation,
petitioners MCMC and MCHC are not guilty of forum
Petitioners filed a motions for partial reconsideration of the CA
shopping.
decision praying (1) for the dismissal of the case in the trial
court, on the ground of lack of jurisdiction, and (2) that the
parties be directed to submit their dispute to arbitration in "V. Contrary to respondent Zosa's allegation, the
accordance with the Employment Agreement dated March 1994. instant petition for review involves only questions of
The CA, in a resolution promulgated on June 20, 1997, denied law and not of fact."24
the motion for partial reconsideration for lack of merit.
We rule against the petitioners.
In compliance with the CA decision, the trial court, on July 18,
1997, rendered a decision declaring the "arbitration clause" in It is error for the petitioners to claim that the case should fall
the Employment Agreement partially void and of no effect. The under the jurisdiction of the Securities and Exchange
dispositive portion of the decision reads: Commission [SEC, for brevity]. The controversy does not in
anyway involve the election/appointment of officers of petitioner
"WHEREFORE, premises considered, judgment is MCHC, as claimed by petitioners in their assignment of errors.
hereby rendered partially declaring the arbitration Respondent Zosa's amended complaint focuses heavily on the
clause of the Employment Agreement void and of no illegality of the Employment Agreement's "Arbitration Clause"
effect, only insofar as it concerns the composition of initially invoked by him in seeking his termination benefits under
the panel of arbitrators, and directing the parties to Section 8 of the employment contract. And under Republic Act
proceed to arbitration in accordance with the No. 876, otherwise known as the "Arbitration Law," it is the
Employment Agreement under the panel of three (3) regional trial court which exercises jurisdiction over questions
arbitrators, one for the plaintiff, one for the defendants, relating to arbitration. We thus advert to the following
and the third to be chosen by both the plaintiff and discussions made by the Court of Appeals, speaking thru Justice
defendants. The other terms, conditions and Minerva P. Gonzaga-Reyes,25 in C.A.-G.R. S.P. No. 43059, viz.
stipulations in the arbitration clause remain in force
and effect."23 "As regards the fourth assigned error, asserting that
jurisdiction lies with the SEC, which is raised for the
In view of the trial court's decision, petitioners filed this petition first time in this petition, suffice it to state that the
for review on certiorari, under Rule 45 of the Rules of Court, Amended Complaint squarely put in issue the question
assigning the following errors for the Court's resolution: whether the Arbitration Clause is valid and effective
between the parties. Although the controversy which
spawned the action concerns the validity of the
"I. The trial court gravely erred when it ruled that the
termination of the service of a corporate officer, the
arbitration clause under the employment agreement is
issue on the validity and effectivity of the arbitration
partially void and of no effect, considering that:
clause is determinable by the regular courts, and do
not fall within the exclusive and original jurisdiction of
"A. The arbitration clause in the employment the SEC.
agreement dated March 1994 between
respondent Zosa and defendants MCHC and
"The determination and validity of the agreement is not
MCMC is valid and binding upon the parties
a matter intrinsically connected with the regulation and
thereto.
internal affairs of corporations (see Pereyra vs. IAC, 181
SCRA 244; Sales vs. SEC, 169 SCRA 121); it is rather an
"B. In view of the fact that there are three ordinary case to be decided in accordance with the
parties to the employment agreement, it is but general laws, and do not require any particular
137
expertise or training to interpret and apply (Viray vs. "But as the defendants [herein petitioner] represent the
CA, 191 SCRA 308)."26 same interest, it could never be expected, in the
arbitration proceedings, that they would not protect
and preserve their own interest, much less, would both
Furthermore, the decision of the Court of Appeals in CA-G.R. SP
or either favor the interest of the plaintiff. The
No. 43059 affirming the trial court's assumption of jurisdiction
arbitration law, as all other laws, is intended for the
over the case has become the "law of the case" which now binds
good and welfare of everybody. In fact, what is being
the petitioners. The "law of the case" doctrine has been defined
challenged by the plaintiff herein is not the law itself
as "a term applied to an established rule that when an appellate
but the provision of the Employment Agreement based
court passes on a question and remands the cause to the lower
on the said law, which is the arbitration clause but only
court for further proceedings, the question there settled
as regards the composition of the panel of arbitrators.
becomes the law of the case upon subsequent appeal." 27 To
The arbitration clause in question provides, thus:
note, the CA's decision in CA-G.R. SP No. 43059 has already
attained finality as evidenced by a Resolution of this Court
ordering entry of judgment of said case, to wit: 'In the event that any dispute, controversy or claim arise out
of or under any provisions of this Agreement, then the
parties hereto agree to submit such dispute, controversy or
"ENTRY OF JUDGMENT
claim to arbitration as set forth in this Section and the
determination to be made in such arbitration shall be final
This is to certify that on September 8, 1997 a and binding. Arbitration shall be effected by a panel of three
decision/resolution rendered in the above-entitled case arbitrators. The Manager, Employee, and Corporation shall
was filed in this Office, the dispositive part of which designate one (1) arbitrator who shall, in turn, nominate and
reads as follows: elect as who among them shall be the chairman of the
committee. Any such arbitration, including the rendering of
'G.R. No. 129615. (Magellan Capital an arbitration award, shall take place in Metro Manila. The
Management Corporation, et al. vs. Court of arbitrators shall interpret this Agreement in accordance with
Appeals, Rolando Zosa, et al.). Considering the the substantive laws of the Republic of the Philippines. The
petitioner's manifestation dated August 11, arbitrators shall have no power to add to, subtract from or
1997 and withdrawal of intention to file otherwise modify the terms of this Agreement or to grant
petition for review on certiorari, the Court injunctive relief of any nature. Any judgment upon the award
Resolved to DECLARE THIS CASE TERMINATED of the arbitrators may be entered in any court having
and DIRECT the Clerk of Court to INFORM the jurisdiction thereof, with costs of the arbitration to be borne
parties that the judgment sought to be equally by the parties, except that each party shall pay the
reviewed has become final and executory, no fees and expenses of its own counsel in the arbitration.'
appeal therefore having been timely (Emphasis supplied).
perfected.'
"From the foregoing arbitration clause, it appears that the
and that the same has, on September 17, 1997, two (2) defendants [petitioners] (MCMC and MCHC) have one
become final and executory and is hereby recorded in (1) arbitrator each to compose the panel of three (3)
the Book of Entries of Judgments."28 arbitrators. As the defendant MCMC is the Manager of
defendant MCHC, its decision or vote in the arbitration
proceeding would naturally and certainly be in favor of its
Petitioners, therefore, are barred from challenging anew, employer and the defendant MCHC would have to protect
through another remedial measure and in any other forum, the and preserve its own interest; hence, the two (2) votes of
authority of the regional trial court to resolve the validity of the both defendants (MCMC and MCHC) would certainly be
arbitration clause, lest they be truly guilty of forum-shopping against the lone arbitrator for the plaintiff [herein
which the courts consistently consider as a contumacious defendant]. Hence, apparently, plaintiff [defendant] would
practice that derails the orderly administration of justice. never get or receive justice and fairness in the arbitration
proceedings from the panel of arbitrators as provided in the
Equally unavailing for the petitioners is the review by this Court, aforequoted arbitration clause. In fairness and justice to the
via the instant petition, of the factual findings made by the trial plaintiff [defendant], the two defendants (MCMC and MCHC)
court that the composition of the panel of arbitrators would, in [herein petitioners] which represent the same interest should
all probability, work injustice to respondent Zosa. We have be considered as one and should be entitled to only one
repeatedly stressed that the jurisdiction of this Court in a arbitrator to represent them in the arbitration proceedings.
petition for review on certiorari under Rule 45 of the Revised Accordingly, the arbitration clause, insofar as the
Rules of Court is limited to reviewing only errors of law, not of composition of the panel of arbitrators is concerned should
fact, unless the factual findings complained of are devoid of be declared void and of no effect, because the law says, "Any
support by the evidence on record, or the assailed judgment is clause giving one of the parties power to choose more
based on misapprehension of facts.29 arbitrators than the other is void and of no effect" (Article
2045, Civil Code).
Even if procedural rules are disregarded, and a scrutiny of the
merits of the case is undertaken, this Court finds the trial court's "The dispute or controversy between the defendants (MCMC
observations on why the composition of the panel of arbitrators and MCHC) [herein petitioners] and the plaintiff [herein
should be voided, incisively correct so as to merit our approval. defendant] should be settled in the arbitration proceeding in
Thus, accordance with the Employment Agreement, but under the
panel of three (3) arbitrators, one (1) arbitrator to represent
the plaintiff, one (1) arbitrator to represent both defendants
"From the memoranda of both sides, the Court is of the
(MCMC and MCHC) [herein petitioners] and the third
view that the defendants [petitioner] MCMC and MCHC
arbitrator to be chosen by the plaintiff [defendant Zosa] and
represent the same interest. There is no quarrel that
defendants [petitioners].
both defendants are entirely two different corporations
with personalities distinct and separate from each other
and that a corporation has a personality distinct and "xxx xxx xxx"30
separate from those persons composing the
corporation as well as from that of any other legal In this connection, petitioners' attempt to put respondent in
entity to which it may be related. estoppel in assailing the arbitration clause must be struck down.
For one, this issue of estoppel, as likewise noted by the Court of
Appeals, found its way for the first time only on appeal. Well-
138
settled is the rule that issues not raised below cannot be have bound themselves to accept the decision of the arbitrator
resolved on review in higher courts. 31 Secondly, employment as final and binding.
agreements such as the one at bar are usually contracts of
adhesion. Any ambiguity in its provisions is generally resolved Arbitration may be classified, on the basis of the obligation on
against the party who drafted the document. Thus, in the which it is based, as either compulsory or voluntary.
relatively recent case of Phil. Federation of Credit Cooperatives,
Inc. (PFCCI) and Fr. Benedicto Jayoma vs. NLRC and Victoria
Abril,32 we had the occasion to stress that "where a contract of Compulsory arbitration is a system whereby the parties to a
employment, being a contract of adhesion, is ambiguous, any dispute are compelled by the government to forego their right to
ambiguity therein should be construed strictly against the party strike and are compelled to accept the resolution of their dispute
who prepared it." And, finally, respondent Zosa never submitted through arbitration by a third party. 1The essence of arbitration
himself to arbitration proceedings (as there was none yet) remains since a resolution of a dispute is arrived at by resort to
before bewailing the composition of the panel of arbitrators. He a disinterested third party whose decision is final and binding on
in fact, lost no time in assailing the "arbitration clause" upon the parties, but in compulsory arbitration, such a third party is
realizing the inequities that may mar the arbitration proceedings normally appointed by the government.
if the existing line-up of arbitrators remained unchecked.
Under voluntary arbitration, on the other hand, referral of a
We need only to emphasize in closing that arbitration dispute by the parties is made, pursuant to a voluntary
proceedings are designed to level the playing field among the arbitration clause in their collective agreement, to an impartial
parties in pursuit of a mutually acceptable solution to their third person for a final and binding resolution. 2Ideally,
conflicting claims. Any arrangement or scheme that would give arbitration awards are supposed to be complied with by both
undue advantage to a party in the negotiating table is anathema parties without delay, such that once an award has been
to the very purpose of arbitration and should, therefore, be rendered by an arbitrator, nothing is left to be done by both
resisted. parties but to comply with the same. After all, they are
presumed to have freely chosen arbitration as the mode of
settlement for that particular dispute. Pursuant thereto, they
WHEREFORE, premises considered, the petition is hereby have chosen a mutually acceptable arbitrator who shall hear
DISMISSED and the decision of the trial court dated July 18, and decide their case. Above all, they have mutually agreed to
1997 is AFFIRMED.SO ORDERED. de bound by said arbitrator's decision.

EN BANCG.R. No. 120319 October 6, 1995 In the Philippine context, the parties to a Collective Bargaining
Agreement (CBA) are required to include therein provisions for a
LUZON DEVELOPMENT BANK, petitioner, machinery for the resolution of grievances arising from the
vs. interpretation or implementation of the CBA or company
ASSOCIATION OF LUZON DEVELOPMENT BANK personnel policies. 3 For this purpose, parties to a CBA shall
EMPLOYEES and ATTY. ESTER S. GARCIA in her capacity name and designate therein a voluntary arbitrator or a panel of
as VOLUNTARY ARBITRATOR, respondents. arbitrators, or include a procedure for their selection, preferably
from those accredited by the National Conciliation and Mediation
Board (NCMB). Article 261 of the Labor Code accordingly
ROMERO, J.:
provides for exclusive original jurisdiction of such voluntary
arbitrator or panel of arbitrators over (1) the interpretation or
From a submission agreement of the Luzon Development Bank implementation of the CBA and (2) the interpretation or
(LDB) and the Association of Luzon Development Bank enforcement of company personnel policies. Article 262
Employees (ALDBE) arose an arbitration case to resolve the authorizes them, but only upon agreement of the parties, to
following issue: exercise jurisdiction over other labor disputes.

Whether or not the company has violated the On the other hand, a labor arbiter under Article 217 of the Labor
Collective Bargaining Agreement provision and Code has jurisdiction over the following enumerated cases:
the Memorandum of Agreement dated April
1994, on promotion.
. . . (a) Except as otherwise provided under this Code the
Labor Arbiters shall have original and exclusive jurisdiction to
At a conference, the parties agreed on the submission of their hear and decide, within thirty (30) calendar days after the
respective Position Papers on December 1-15, 1994. Atty. Ester submission of the case by the parties for decision without
S. Garcia, in her capacity as Voluntary Arbitrator, received extension, even in the absence of stenographic notes, the
ALDBE's Position Paper on January 18, 1995. LDB, on the other following cases involving all workers, whether agricultural or
hand, failed to submit its Position Paper despite a letter from the non-agricultural:
Voluntary Arbitrator reminding them to do so. As of May 23,
1995 no Position Paper had been filed by LDB.
1. Unfair labor practice cases;

On May 24, 1995, without LDB's Position Paper, the Voluntary


2. Termination disputes;
Arbitrator rendered a decision disposing as follows:

3. If accompanied with a claim for reinstatement, those


WHEREFORE, finding is hereby made that the
cases that workers may file involving wages, rates of pay,
Bank has not adhered to the Collective
hours of work and other terms and conditions of
Bargaining Agreement provision nor the
employment;
Memorandum of Agreement on promotion.

4. Claims for actual, moral, exemplary and other forms of


Hence, this petition for certiorari and prohibition seeking to set
damages arising from the employer-employee relations;
aside the decision of the Voluntary Arbitrator and to prohibit her
from enforcing the same.
5. Cases arising from any violation of Article 264 of this
Code, including questions involving the legality of strikes and
In labor law context, arbitration is the reference of a labor
lockouts;
dispute to an impartial third person for determination on the
basis of evidence and arguments presented by such parties who
139
6. Except claims for Employees Compensation, Social very situation presented by the quasi-judicial functions of the
Security, Medicare and maternity benefits, all other claims, voluntary arbitrators here, as well as the subsequent
arising from employer-employee relations, including those of arbitrator/arbitral tribunal operating under the Construction
persons in domestic or household service, involving an Industry Arbitration Commission, 11 that the broader term
amount exceeding five thousand pesos (P5,000.00) "instrumentalities" was purposely included in the above-quoted
regardless of whether accompanied with a claim for provision.
reinstatement.
An "instrumentality" is anything used as a means or
xxx xxx xxx agency. 12 Thus, the terms governmental "agency" or
"instrumentality" are synonymous in the sense that either of
them is a means by which a government acts, or by which a
It will thus be noted that the jurisdiction conferred by law on a
certain government act or function is performed. 13 The word
voluntary arbitrator or a panel of such arbitrators is quite limited
"instrumentality," with respect to a state, contemplates an
compared to the original jurisdiction of the labor arbiter and the
authority to which the state delegates governmental power for
appellate jurisdiction of the National Labor Relations
the performance of a state function. 14 An individual person, like
Commission (NLRC) for that matter. 4 The state of our present
an administrator or executor, is a judicial instrumentality in the
law relating to voluntary arbitration provides that "(t)he award
settling of an estate, 15 in the same manner that a sub-agent
or decision of the Voluntary Arbitrator . . . shall be final and
appointed by a bankruptcy court is an instrumentality of the
executory after ten (10) calendar days from receipt of the copy
court, 16 and a trustee in bankruptcy of a defunct corporation is
of the award or decision by the parties," 5 while the "(d)ecision,
an instrumentality of the state. 17
awards, or orders of the Labor Arbiter are final and executory
unless appealed to the Commission by any or both parties within
ten (10) calendar days from receipt of such decisions, awards, or The voluntary arbitrator no less performs a state function
orders." 6 Hence, while there is an express mode of appeal from pursuant to a governmental power delegated to him under the
the decision of a labor arbiter, Republic Act No. 6715 is silent provisions therefor in the Labor Code and he falls, therefore,
with respect to an appeal from the decision of a voluntary within the contemplation of the term "instrumentality" in the
arbitrator. aforequoted Sec. 9 of B.P. 129. The fact that his functions and
powers are provided for in the Labor Code does not place him
within the exceptions to said Sec. 9 since he is a quasi-judicial
Yet, past practice shows that a decision or award of a voluntary
arbitrator is, more often than not, elevated to the Supreme instrumentality as contemplated therein. It will be noted that,
although the Employees Compensation Commission is also
Court itself on a petition for certiorari, 7 in effect equating the
provided for in the Labor Code, Circular No. 1-91, which is the
voluntary arbitrator with the NLRC or the Court of Appeals. In
forerunner of the present Revised Administrative Circular No. 1-
the view of the Court, this is illogical and imposes an
95, laid down the procedure for the appealability of its decisions
unnecessary burden upon it.
to the Court of Appeals under the foregoing rationalization, and
this was later adopted by Republic Act No. 7902 in amending
In Volkschel Labor Union, et al. v. NLRC, et al., 8 on the settled Sec. 9 of B.P. 129.
premise that the judgments of courts and awards of quasi-
judicial agencies must become final at some definite time, this
A fortiori, the decision or award of the voluntary arbitrator or
Court ruled that the awards of voluntary arbitrators determine
panel of arbitrators should likewise be appealable to the Court of
the rights of parties; hence, their decisions have the same legal
Appeals, in line with the procedure outlined in Revised
effect as judgments of a court. In Oceanic Bic Division (FFW), et
Administrative Circular No. 1-95, just like those of the quasi-
al. v. Romero, et al., 9 this Court ruled that "a voluntary
judicial agencies, boards and commissions enumerated therein.
arbitrator by the nature of her functions acts in a quasi-judicial
capacity." Under these rulings, it follows that the voluntary
arbitrator, whether acting solely or in a panel, enjoys in law the This would be in furtherance of, and consistent with, the original
status of a quasi-judicial agency but independent of, and apart purpose of Circular No. 1-91 to provide a uniform procedure for
from, the NLRC since his decisions are not appealable to the the appellate review of adjudications of all quasi-judicial
latter. 10 entities 18 not expressly excepted from the coverage of Sec. 9 of
B.P. 129 by either the Constitution or another statute. Nor will it
run counter to the legislative intendment that decisions of the
Section 9 of B.P. Blg. 129, as amended by Republic Act No. 7902,
NLRC be reviewable directly by the Supreme Court since,
provides that the Court of Appeals shall exercise:
precisely, the cases within the adjudicative competence of the
voluntary arbitrator are excluded from the jurisdiction of the
xxx xxx xxx NLRC or the labor arbiter.

(B) Exclusive appellate jurisdiction over all In the same vein, it is worth mentioning that under Section 22 of
final judgments, decisions, resolutions, orders or Republic Act No. 876, also known as the Arbitration Law,
awards of Regional Trial Courts and quasi-judicial arbitration is deemed a special proceeding of which the court
agencies, instrumentalities, boards or commissions, specified in the contract or submission, or if none be specified,
including the Securities and Exchange Commission, the the Regional Trial Court for the province or city in which one of
Employees Compensation Commission and the Civil the parties resides or is doing business, or in which the
Service Commission, except those falling within the arbitration is held, shall have jurisdiction. A party to the
appellate jurisdiction of the Supreme Court in controversy may, at any time within one (1) month after an
accordance with the Constitution, the Labor Code of the award is made, apply to the court having jurisdiction for an
Philippines under Presidential Decree No. 442, as order confirming the award and the court must grant such order
amended, the provisions of this Act, and of unless the award is vacated, modified or corrected. 19
subparagraph (1) of the third paragraph and
subparagraph (4) of the fourth paragraph of Section 17
In effect, this equates the award or decision of the voluntary
of the Judiciary Act of 1948.
arbitrator with that of the regional trial court. Consequently, in a
petition for certiorari from that award or decision, the Court of
xxx xxx xxx Appeals must be deemed to have concurrent jurisdiction with
the Supreme Court. As a matter of policy, this Court shall
Assuming arguendo that the voluntary arbitrator or the panel of henceforth remand to the Court of Appeals petitions of this
voluntary arbitrators may not strictly be considered as a quasi- nature for proper disposition.
judicial agency, board or commission, still both he and the panel
are comprehended within the concept of a "quasi-judicial
instrumentality." It may even be stated that it was to meet the
140
ACCORDINGLY, the Court resolved to REFER this case to the effected, one after the other, during the late hours of
Court of Appeals.SO ORDERED. May 16 and the wee hours of May 17, 1996, a time
span of only seven (7) hours.
SECOND DIVISIONA.M. No. RTJ-00-1568 February 15,
2001 Three (3) related informations7 were then filed against Wang,
which were consolidated in Branch 18 of the Regional Trial Court
(RTC, for brevity) of Manila, presided by the respondent judge.
HON. ROBERT Z. BARBERS, Secretary of the Interior and
The charges were docketed as Criminal Case No. 96-149990 (for
Local Government, JUANITO DE GUZMAN and LUCIO
violation of section 16, Article III of Republic Act No. 6425,
MARGALLO IV, petitioners,
otherwise known as the Dangerous Drugs Act, as amended),
vs.
Criminal Case No. 96-149991(for violation of Presidential Decree
JUDGE PERFECTO A.S. LAGUIO, JR., respondent.
No. 1866 [Illegal Possession of Firearms]), and Criminal Case No.
96-149992 (for violation of COMELEC Resolution 2828 in relation
DE LEON, JR., J.: to Republic Act No. 7166 [COMELEC Gun Ban]).

Before us is an administrative complaint for alleged violation of Prior to his arraignment, Wang filed a motion for preliminary
Article 204 (Knowingly Rendering Unjust Judgment) of the investigation dated June 11, 1996 which was granted by the trial
Revised Penal Code, section 3(e) of Republic Act No. 3019 and court in an Order dated June 27, 1996. During the preliminary
sections 4(b) and (c) of Republic Act No. 6713, filed against investigation before the prosecutor, Wang denied that illegal
respondent judge in connection with his acquittal of the accused drugs or unlicensed firearms were found in his possession. The
LAWRENCE WANG y CHEN in Criminal Case Nos. 96-149990, 96- cases were later remanded to the trial court after Assistant City
149991 and 96-149992. Prosecutor Michaela M. Cua submitted a Resolution dated
August 22, 1996 finding probable cause against Wang. Fearing
On April 10, 1997, complainants ROBERT Z. BARBERS,1 JUANITO that his objection to his warrantless arrest and search would be
DE GUZMAN and LUCIO MARGALLO IV filed a joint complaint- waived by his entering a plea, Wang through counsel filed a
affidavit with the Office of the Ombudsman charging respondent Manifestation on November 7, 1996 making of record his
Judge PERFECTO A.S. LAGUIO, JR., of allegedly violating Article continuing objection to his warrantless arrest and praying that
204 of the Revised Penal Code, section 3(e) of Republic Act No. the trial court enter a plea of "not guilty" on his behalf. Acting on
3019,2and section 4, subsections (b) and (c) of Republic Act No. Wang's Manifestation, respondent judge entered a plea of "not
6713.3 Considering the Evaluation Report4 with recommendation guilty" for Wang as reflected in his Order of November 8, 1996.
of its Evaluation and Preliminary Investigation Bureau, the Office
of the Ombudsman endorsed 5the case to the Office of the Court During the trial, the prosecution presented and offered the
Administrator on May 9, 1997. It was pointed out in said testimonies of Insp. Cielito Coronel and Reynaldo Cristobal of the
Evaluation Report "that respondent is primarily accused of PARAC team who arrested Wang, and Felicisima Francisco,
Knowingly Rendering Unjust Judgment." forensic chemist of the National Bureau of Investigation, who
conducted laboratory tests to determine if the confiscated
The administrative complaint stemmed from the acquittal by substance was indeed "shabu", a prohibited drug.
respondent judge of Lawrence Wang, a Hong Kong national who
was apprehended by elements of the Public Assistance and During the hearing on December 6, 1996, the prosecution
Reaction Against Crime or PARAC, DILG, in Malate, Manila in the formally rested its case. In turn, the defense filed a motion for
early morning of May 17, 1996, the particulars of which are leave of court to file a Demurrer to Evidence. The trial court
described in the complainants' Joint Complaint-Affidavit 6 dated granted the defense's motion in an Order of the same date and
April 1, 1997, as follows: gave Wang a period of twenty-five (25) days from receipt
thereof within which to file a Demurrer to Evidence, and the
At about 7 p.m. on May 16, 1996, members of the prosecution a similar period to file its opposition thereto. An
PARAC led by P/Sr. Insp. Lucio Margallo, IV effected the undated Demurrer to Evidence was then filed by Wang through
arrest of SPO1 VERGEL DE DIOS, ROBERTO ANOBLING counsel on January 9, 1997.
and RESTITUTO ARELLANO during an entrapment
operation. This trio then called on their cohorts to bring Subsequently, Assistant City Prosecutor Winnie M. Edad filed a
in additional batch of shabu. After four (4) hours, or at "Manifestation with Motion" stating that the prosecution is
about 11 p.m. of May 16, 1996, PIO REDENTOR TECH resting its case against the accused, Wang, insofar as Criminal
and JOSEPH JUNIO arrived to deliver 150 grams of Case No. 96-149990 only was concerned but excluding the two
shabu. Tech and Junio were likewise arrested at 11 p.m. (2) remaining cases for illegal possession of firearms and
while they were delivering the shabu to de Dios and violation of the COMELEC gun ban, wherein the prosecution
company. When interrogated Tech and Junio disclosed claimed it has not yet rested. Consequently, in an Order dated
that a big transaction of shabu was about to be made January 14, 1997, the trial court set further hearings on the two
at an apartment along Maria Orosa St., Malate, Manila. (2) remaining cases on January 21, February 5, 11 and 12, 1997.
They also admitted that they worked for Lawrence
Wang. Accordingly, the PARAC immediately proceeded
On March 13, 1997, respondent judge issued a Resolution
to said place and conducted surveillance or stake-out
granting Wang's Demurrer to Evidence and acquitting Wang in
operations. After three (3) hours, or about 2:10 a.m. of
the said three (3) closely related cases. Respondent judge
the following day, May 17, 1996, the PARAC agents saw
declared therein and made the finding that:
a man, previously described by TECH as Wang and
identified by a police asset, coming out of the aforesaid
apartment and walking towards a parked BMW car. xxx xxx xxx
After Wang had opened the trunk compartment of the
car, the PARAC agents approached Wang and The threshold issue raised by accused in his
confronted him to ascertain his identity. P/Sr. Insp. Demurrer to Evidence is whether his warrantless
Margallo also prevented Wang from closing the trunk. arrest and search were lawful as argued by the
They then saw the bags of shabu inside the trunk. A prosecution, or unlawful as asserted by the
further search yielded cash amount of P650,000.00 in defense.
small denominations, one (1) mechanical scale and one
(1) electronic scale and two (2) unlicensed firearms,
namely: (1) AMT automatic pistol, cal. 380/9mm and (2) Under Section 5, Rule 113 of the New Rules of Court, a
Daewoo automatic pistol, cal. 9mm. Accordingly, the peace officer may arrest a person without a warrant:
accused was arrested. In all, three (3) arrests were (a) when, in his presence, the person to be arrested has
committed, is actually committing, or is attempting to
141
commit an offense; (b) when an offense has in fact just receipt of the respondent's comment strongly denying and
been committed, and he has personal knowledge of disputing the administrative charges against him and upon the
facts indicating that the person to be arrested has recommendation of OCA, this Court referred the matter to the
committed it, and (c) when the person to be arrested is then Court of Appeals Associate Justice (now Supreme Court
a prisoner who has escaped from a penal establishment Associate Justice) Consuelo Ynares-Santiago for investigation
or place where he is serving final judgment or and report. On September 7, 1998, she submitted her Report
temporarily confined while being transferred from one recommending that respondent judge be reprimanded and
confinement to another. None of these circumstances meted a fine equivalent to six (6) months salary. Her findings
were present when the accused was arrested. The were adopted by the Office of the Court Administrator, per its
accused was merely walking from the Maria Orosa Memorandum9 of December 2, 1999, to wit:
apartment and was about to enter the parked BMW car
when the police officers arrested and frisked him and xxx xxx xxx
searched his car. The accused was not committing any
visible offense at the time of his arrest. Neither was
there an indication that he was about to commit a The conduct of respondent, given the peculiar facts prevailing
crime or that he had just committed an offense. The in this case, leaves much to be desired vis--vis these legal
unlicensed AMT Cal. 380 9mm Automatic Back-up Pistol yardsticks. The abruptness and inordinate haste in which he
[sic] that the accused had in his possession was dismissed the charges against the accused gave rise to the
concealed inside the right front pocket of his pants. And suspicion that he railroaded the proceedings to favor the
the handgun was bantam and slim in size that it would accused.
not give an outward indication of a concealed gun if
placed inside the pants' side pocket as was done by the The records show that two members of the team which
accused. The arresting officers had no information arrested Lawrence Wang, namely P/Insp. Cielito Coronel and
and knowledge that the accused was carrying an SPO3 Reynaldo Cristobal were the only witnesses who
unlicensed handgun, nor did they see him in testified on the facts regarding the warrantless arrest and
possession thereof immediately prior to his seizure. The principal witness and leader of the team, P/Sr.
arrest. Insp. Lucio Margallo IV, who more than anybody else has the
personal knowledge of the circumstances surrounding the
Ditto on the 32 bags of shabu and the other unlicensed arrest of Wang was never presented as a witness. It must be
Daewoo Cal. 9mm Pistol with magazine that were found pointed out in this regard that Margallo, as leader of the
and seized from the car. The contraband items in arresting team could have clarified the circumstances
the car were not in plain view. The 32 bags of surrounding the arrest of Wang and the seizure of the drugs,
shabu were in the trunk compartment, and the firearms and cash found in the car especially the highly
Daewoo handgun was underneath the driver's contentious issue of whether or not the trunk of the car which
seat of the car. The police officers had no contained the "shabu" was already open with said prohibited
information, or knowledge that the banned drug in plain view when he and his team members
articles were inside the car, or that the accused approached. The record, however, discloses that after the
had placed them there. The police officers prosecutor handling the cases conferred with respondent,
searched the car on mere suspicion that there thereafter, Margallo's testimony was dispensed with on the
was shabu therein. dubious ground that it would merely be corroborative. xxx

xxx xxx xxx The record also reveals that Margallo received only one
subpoena to appear in Crim. Case No. 96-149990 (Violation of
Dangerous Drugs Act) on December 6, 1996 xxx.
Respondent judge then issued on the same day an Order dated Unfortunately, he was not able to attend because he was on
March 13, 1997 setting the promulgation of his aforequoted leave at the time xxx and only learned about the hearing after
Resolution on March 20, 1997. December 6, 1996 xxx. Curiously, no other summons were
served on him to testify despite his instructions to SPO3
On the day before the scheduled promulgation, SPO3 Cristobal Cristobal to manifest in Court that he be subpoenaed to testify
claimed that he received a telephone call from a person xxx. As in Crim. Case No. 96-149990, he also received only
claiming to be the branch clerk of court of RTC Manila, Branch one (1) subpoena in the other cases but the reason therefor
18. The caller, according to Cristobal, instructed him to bring to was for the Evidence Custodian namely, SPO3 Cristobal who
court the next day the money confiscated from Wang. Cristobal was under him, to bring the confiscated items in court xxx.
complied. The only other time he received a subpoena was when he was
required to attend the scheduled hearing on March 20, 1997
and he was not aware that said notice requiring his presence
After the Resolution of March 13, 1997 was promulgated by the
on said date was already for the promulgation of the order
trial court, Cristobal was presented with a special power-of-
granting the demurrer to evidence xxx.
attorney8 dated February 12, 1997 executed by Wang
authorizing his counsel, Atty. Oliver Lozano, to receive the
confiscated money. Cristobal handed over the money to Atty. The Resolution granting the demurrer to evidence dismissing
Oliver Lozano, but he first required Atty. Lozano to accomplish a all three (3) cases against Wang is likewise anchored on infirm
receipt written on the special power-of-attorney itself. legal moorings.

Not satisfied with Wang's acquittal, petitioners Barbers et. al., Section 15, Rule 119 of the Revised Rules of Criminal
filed the said Joint Complaint-Affidavit against respondent judge Procedure provides that:
before the Office of the Ombudsman. They also filed an
administrative complaint against the trial prosecutor, Assistant "Sec. 15. Demurrer to evidence. After the prosecution has
City Prosecutor Edad, for alleged gross neglect of duty in his rested its case, the court may dismiss the case on the ground
handling of the Wang cases. However, on September 6, 1999, of insufficiency of evidence: (1) on its own initiate (sic) after
the Department of Justice issued its Resolution dismissing the giving the prosecution an opportunity to be heard; or (2) on
administrative complaint against Edad for lack of merit. motion of the accused with prior leave of court.

After the said Joint Complaint-Affidavit of the complainants If the court denies the motion for dismissal, the accused may
(herein petitioners) against respondent judge was endorsed by adduce evidence in his defense. When the accused files such
the Ombudsman to the Office of the Court Administrator, this motion without the express leave of court, he waives the right
Court required the respondent to comment thereon. After its
142
to present evidence and submits the case for judgment on the document which he required said counsel to sign xxx. The
basis of the evidence for the prosecution." date of the execution of the Special Power of Attorney which
was more than a month prior to the promulgation of the
resolution only fueled Cristobal's suspicion that the
The rule is not applicable if the prosecution has not yet rested
proceedings were already rigged in Wang's favor xxx.
its case xxx.

xxx xxx xxx


In this case, despite the statement in the resolution in
question as well as respondent's claims to the contrary, there
is ample evidence on record that the prosecution had not yet The factual finding of respondent judge that the "shabu" was
rested its case in Criminal Cases Nos. 96-149991 and 96- not in plain view when the accused was arrested becomes
149992 xxx. Particularly revealing on this point is the open to question in the light of the evidence on record that
"Manifestation With Motion to Set Above-Entitled Cases for the compartment of the car containing the "shabu" was
Further Hearing and For Issuance of Subpoena to Prosecution actually already open and the accused attempted to close the
Witnesses" xxx which avers that: same but was prevented from doing so by the arresting
officers xxx much more so taking into consideration the fact
that P/Sr. Insp. Margallo, the principal witness for the
"THE PEOPLE THRU THE UNDERSIGNED TRIAL PROSECUTOR,
prosecution who could have shed light on the circumstances
to this Honorable Court most respectfully manifests that he
of the arrest and seizure, was not given the change (sic) to
rested his case only in so far (sic) as the case of R.A. 6425 is
testify. Considering that the accused is a highly controversial
concerned, and not as regards the charge for violation of P.D.
character on account of his notoriety as a big-time drug lord
L866 (sic) (Crim. Case No. 96-149991) and the case of
not to mention the widespread media attention attracted by
COMELEC Resolution No. 2828 (Crim. Case No. 96-149992);
the case, respondent judge should have proceeded with more
caution and circumspection in the handling thereof.
WHEREFORE, the prosecution respectfully moves this
Honorable Court:
xxx xxx xxx

1. To set Crim. Case Nos. 96-149991-92, for violation of P.D.


However, there is an important aspect to this case which was
1866 and COMELEC Resolution 2828, respectively for further
heretofore not considered. The respondent judge's Resolution in
hearing to enable the prosecution to present its evidence;
question dated March 13, 1997 is one of acquittal. It is well-
settled that acquittal in a criminal case is immediately final and
xxx xxx xxx executory upon its promulgation; accordingly, the State may not
seek its review without placing the accused in double
A circumspect scrutiny of the demurrer to evidence itself xxx jeopardy.10 When the Investigating Justice submitted her Report
will show that the same can only pertain to Criminal Case No. dated September 7, 1998, the questioned Resolution of
96-149990 for violation of the Dangerous Drugs respondent judge acquitting Wang was already the subject of a
Act considering that it was filed on January 9, 1997 and the pending petition for review on certiorari (G.R. No.
prosecution had not yet rested in Criminal Cases Nos. 96- 128587)11 which was filed with this Court. It appeared that after
149991 and 96-149992. In fact, in an Order dated January 14, the State received a copy of the said Resolution of respondent
1997 xxx, respondent set hearings for the two (2) cases on judge on March 20, 1997, the Office of the Solicitor General filed
January 21, February 5, 11 and 12, 1997. It is interesting to a "Manifestation and Motion" on April 3, 1997 with this Court
note in this regard that no demurrer to evidence was filed praying for an extension of thirty (30) days (or until May 4,
after the prosecution had rested its case in Criminal Cases 1997, a Sunday) within which to file a petition for review
Nos. 96-149991 and 96-149992. Neither was the prior on certiorari. The motion was granted by the First Division of this
demurrer filed on January 9, 1997 subsequently amended to Court in a Resolution dated May 7, 1997. The said petition for
include these two cases. Despite all these facts, respondent review on certiorari (G.R. No. 128587) which was filed on May 5,
judge still proceeded to dismiss all three (3) charges against 1997 by the Solicitor General together with the Department of
the accused. Justice, is still pending in this Court. Following established
doctrine, the pendency of the appeal is sufficient cause for the
dismissal of the instant administrative complaint. 12 It has also
xxx xxx xxx been held that the filing of an administrative complaint is not
the proper remedy for the correction of actions of a judge
Furthermore, the factual events surrounding the turnover of perceived to have gone beyond the norms of propriety, where a
the confiscated articles which oddly enough, with the sufficient judicial remedy exists.13 Differently expounded in
exception of the firearms, were not marked in evidence xxx another case,
only increases the dubiousness of the proceedings. As has
been stated earlier, complainants were unaware, upon being As everyone knows, the law provides ample judicial
served with notice to appear on March 20, 1996 that a remedies against errors or irregularities being
Resolution dismissing all three (3) cases on the basis of the committed by a Trial Court in the exercise of its
undated demurrer to evidence would be promulgated xxx. jurisdiction. The ordinary remedies against errors or
Indeed, the document served by the process server made no irregularities which may be regarded as normal in
mention of the fact that the cases were already submitted for nature (i.e., error in appreciation or admission of
resolution and that the same would be promulgated on said evidence, or in construction or application of procedural
date xxx. In fact, SPO3 Cristobal who was Evidence Custodian or substantive law or legal principle) include a motion
of the PARAC-DILG was not served a subpoena commanding for reconsideration (or after rendition of a judgment or
his presence on March 20, 1997. xxx Instead, he received a final order, a motion for new trial), and appeal.
telephone call on March 19, 1997 from a person who identified The extraordinary remedies against error or
herself as the Branch Clerk of respondent judge's sala irregularities which may be deemed extraordinary in
instructing him to bring the confiscated money to court the character (i.e., whimsical, capricious, despotic exercise
next day xxx. Thus, upon appearing the next day, he was of power or neglect of duty, etc.) are inter alia the
surprised to learn that there would be a promulgation. xxx special civil actions of certiorari, prohibition
or mandamus, or a motion for inhibition, a petition for
During the proceedings held March 20, 1997, SPO3 Cristobal change of venue, as the case may be.
was handed a Special Power of Attorney xxx dated February
12, 1997 executed by the accused authorizing his counsel to Now, the established doctrine and policy is that
receive the confiscated money in his behalf xxx. As a disciplinary proceedings and criminal actions
precaution, Cristobal made a handwritten receipt on the said against Judges are not complementary or
143
suppletory of, nor a substitute for, these judicial Corrupt practices of public officers.In addition to acts or
remedies, whether ordinary or extraordinary. omissions of public officers already penalized by existing
Resort to and exhaustion of these judicial law, the following shall constitute corrupt practices of any
remedies, as well as the entry of judgment in the public officer and are hereby declared to be unlawful:
corresponding action or proceeding, are pre-
requisites for the taking of other measures xxx xxx xxx
against the persons of the judges concerned,
whether of civil, administrative, or criminal
nature. It is only after the available judicial (e) Causing any undue injury to any party, including the
remedies have been exhausted and the appellate Government, or giving any private party any unwarranted
tribunals have spoken with finality, that the door benefits, advantage or preference in the discharge of his
to an inquiry into his criminal, civil or official, administrative or judicial functions through
administrative liability may be said to have manifest partiality, evident bad faith or gross inexcusable
opened, or closed. negligence. This provision shall apply to officers and
employees of offices or government corporations charged
with the grant of licenses or permits or other concessions.
xxxx Indeed, since judges must be free to judge,
without pressure or influence from external forces or
factors, they should not be subject to intimidation, the xxx xxx xxx
fear of civil, criminal or administrative sanctions for
acts they may do and disposition they may make in the The other charge is for the alleged violation of section 4,
performance of their duties and functions; and it is subsections (b) and (c) of Republic Act No. 6713 otherwise
sound rule, which must be recognized independently of known as the Code of Conduct and Ethical Standards for
statute, that judges are not generally liable for acts Public Officials and Employees, viz.:
done within the scope of their jurisdiction and in good
faith; and that exceptionally, prosecution of a judge can
Norms of Conduct of Public Officials and Employees. (A)
be had only if "there be a final declaration by a
Every public official and employee shall observe the
competent court in some appropriate proceeding of the
following as standards of personal conduct in the
manifestly unjust character of the challenged judgment
discharge and execution of official duties:
or order, and also evidence of malice or bad faith,
ignorance of inexcusable negligence, on the part of the
judge in rendering said judgment or order" or under the xxx xxx xxx
stringent circumstances set out in Article 32 of the Civil
Code. xxxx14 (b) Professionalism.Public officials and employees shall
perform and discharge their duties with the highest degree
The administrative case at bar involves an acquittal on an of excellence, professionalism, intelligence and skill. They
accused by the respondent judge in three (3) closely related shall enter public service with utmost devotion and
criminal cases which were earlier consolidated in the court dedication to duty. They shall endeavor to discourage
presided by respondent judge. As a rule, acquittal is wrong perceptions of their roles as dispensers or peddlers
immediately final and executory. Consequently, in view of the of undue advantage.
pendency in this Court (First Division) of the petition for review
on certiorari (G.R. No. 128587), supra, we may not, ordinarily, (c) Justness and sincerity.Public officials and employees
review here the said judgment of acquittal in those three (3) shall remain true to the people at all times. They must act
criminal cases, the inquiry in this administrative case being with justness and sincerity and shall not discriminate
limited to the issue of whether the respondent judge is liable for against anyone, especially the poor and the
the charges brought against him.15 However, to resolve those underprivileged. They shall at all times respect the rights
charges in the administrative case, it is indispensable that we of others, and shall refrain from doing acts contrary to law,
consider the respondent Judge's subject Resolution dated March good morals, good customs, public policy, public order,
13, 1997 granting accused Wang's Demurrer to Evidence and public safety and public interest. They shall not dispense
acquitting the latter in the closely related Criminal Cases Nos. or extend undue favors on account of their office to their
96-149990, 96-149991 and 96-149992.1wphi1.nt relatives whether by consanguinity or affinity except with
respect to appointments of such relatives to positions
In appealing Wang's acquittal, the State is relying on a considered strictly confidential or as members of their
recognized exception to the general rule in that where the personal staff whose terms are coterminous with theirs.
assailed judgment is void, no double jeopardy results from the
re-filing of the criminal case.16 In view of the pendency of the xxx xxx xxx
said appeal, we should, ordinarily, be constrained from resolving
the charge of violation of Art. 204 of the Revised Penal Code for
allegedly knowingly rendering an unjust judgment. However, in Respondent judge's alleged transgressions consist principally of:
this administrative case, justice demands that we resolve the (a) resolving the Demurrer to Evidence when the prosecution
basic issue relative to the legality or illegality of Wang's had not yet allegedly rested in all three (3) criminal cases; (b)
warrantless arrest and search, and the issue on the admissibility dismissing all three (3) criminal cases when the Demurrer to
of the bags of "shabu," scales and unlicensed firearms which Evidence allegedly referred only to Criminal Case No. 96-149990
were confiscated during the warrantless search. These are the relative to the drug charges; and (c) propounding questions
very same issues being litigated in the said appeal. 17 Meanwhile, during the clarificatory hearing which revealed his alleged
there is as yet no definitive pronouncement by this Court in G.R. partiality in favor of the accused. After reviewing the records, we
No. 128587, supra, whether respondent's Resolution of acquittal find scant evidence to support the charges as well as the
of Wang is patently erroneous. The jurisprudential rule is that adverse conclusions of the Honorable Investigator.
pendency of an appeal from a questioned judgment renders
the filing of administrative charges premature.18 A close scrutiny of the record does not support the conclusion of
the Investigator that respondent judge prematurely resolved the
Nevertheless, the foregoing considerations do not prevent us Demurrer to Evidence without giving the prosecution ample
from ruling upon the remaining charges brought against opportunity to prove its three (3) cases which were earlier
respondent judge. The first involves an alleged violation of consolidated. The governing rule then, Section 15, Rule 119 of
section 3(e) of the Anti-Graft and Corrupt Practices Act, which the 1985 Rules of Criminal Procedure19 provides that:
provides:
144
Demurrer to evidence.After the prosecution has relevant facts and to bring out the truth."27 Differently stated,
rested its case, the court may dismiss the case on the "questions to clarify points and to elicit additional relevant
ground of insufficiency of evidence (1) on its own evidence are not improper. The judge being the arbiter may
initiative after giving the prosecution an opportunity to properly intervene in the presentation of evidence to expedite
be heard; or (2) on motion of the accused filed with and prevent unnecessary waste of time." 28 The pronouncement
prior leave of court. of this Court in United States v. Hudieres29 is illuminating as
when it was made in 1914:
If the court denies the motion for dismissal, the
accused may adduce evidence in his defense. When The first assignment of error has its basis in the claim
the accused files such motion to dismiss without of counsel that the trial judge went to unjustifiable
express leave of court, he waives the right to present lengths in examining some of the witnesses called for
evidence and submits the case for judgment on the the defense. It is very clear, however, from a review of
basis of the evidence of the prosecution. (Underscoring the whole proceedings that the only object of the trial
supplied) judge in propounding these questions was to endeavor
as far as possible to get at the truth as to the facts
which the witnesses were testifying. The right of a trial
During the hearing held on December 6, 1996, Assistant City
judge to question the witnesses with a view to
Prosecutor Winnie M. Edad stated that he was resting the
satisfying his mind upon any material point which
People's case.20 It was at this time that the defense asked for,
presents itself during the trial of a case over which he
and was given, leave of court to file a Demurrer to Evidence.
presides is too well established to need discussion. The
Perhaps belatedly realizing that it had rested prematurely, the
trial judges in this jurisdiction are judges of both the
prosecution filed a "Manifestation with Motion to Set Above-
law and the facts, and they would be negligent in the
Entitled Cases for Further Hearing and For the Issuance of
performance of their duties if they permitted a
Subpoenas to Prosecution Witnesses"21 on December 19, 1996.
miscarriage of justice as a result of a failure to
Respondent judge, in an Order dated January 14, 199722granted
propound a proper question to a witness which might
that motion and set the two (2) remaining cases (Criminal Case
develop some material fact upon which the judgment in
Nos. 96-149991 and 96-149992) for further hearings. This fact
the case should turn. So in a case where a trial judge
belies the petitioners' claim that they were denied their day in
sees that the degree of credit which he is to give the
court. Significantly, during the hearing held on February
testimony of a given witness may have an important
11, 1997, the prosecution rested in all the three (3)
bearing upon the outcome, there can be no question
cases for the second time,23 including Criminal Case Nos.
that in the exercise of a sound discretion he may put
96-149991 and 96-149992. The prosecution was even able to
such questions to the witness as will enable him to
file an opposition to the Demurrer to Evidence. The record
formulate a sound opinion as to the ability or the
shows that the proceedings were astened when the
willingness of the witness to tell the truth. The
defense filed a Manifestation on February 10, 1997 that
questions asked by the trial judge in the case at bar
it was admitting the existence of the firearms and the
were in our opinion entirely proper, their only purpose
lack of license therefor. Hence, there was not even a
being to clarify certain obscure phases of the case; and
need to amend the Demurrer to Evidence inasmuch as
while we are inclined to agree with counsel that some
the Demurrer to Evidence, as worded, clearly prayed for
of the observations of the trial judge in the course of
the dismissal of all the three (3) cases, namely, Criminal
his examination might well have been omitted, there is
Case Nos. 96-149990, 96-149991 and 96-149992.
no reason whatever to believe that the substantial
rights of the defendants were in anywise prejudiced
Neither do we discern any impropriety when respondent judge thereby.
resolved to dismiss all the three (3) criminal cases filed against
Wang. Petitioners claim that the Demurrer to Evidence could
The transcript of the clarificatory hearing held on February 26,
apply only to Criminal Case No. 96-149990 inasmuch as (1) the
1997 is reproduced below to show that the tenor of respondent
State has rested allegedly only in that case, and (2) the docket
judge's clarificatory questions, though numerous did not really
number stated on the first page of the Demurrer to Evidence
create the impression that respondent judge was biased or that
referred only to Criminal Case No. 96-149990. That claim is
he has practically taken the cudgels for the defense.
erroneous. Even if the caption of the Demurrer to Evidence
stated only Criminal Case No. 96-149990, a plain reading of
the entire Demurrer to Evidence leaves no doubt that it also xxx xxx xxx
covered Criminal Case Nos. 96-149991 and 96-149992. The
principal argument of the defense in those three (3) criminal THE COURT TO THE WITNESS:
cases is that Wang was arrested illegally, without a warrant, Q: You, SPO3 Cristobal, were a member of the police
under circumstances not falling within recognized operatives that effected the arrest of the accused in this case?
exceptions.24 Accordingly, the accompanying search and seizure A: Yes, sir.
which yielded the prohibited articles is also illegal and invalid. Q: From your testimony and that of Police Inspector Cielito
Pursuant to constitutional dictates,25said articles are Coronel, this Court has gathered that prior to the arrest of the
inadmissible in evidence for being "fruits of a poisonous tree." accused there were three 3) men that your team arrested. One of
That defense is unequivocally set forth in the Demurrer to whom is a police officer?
Evidence. The caption of the Demurrer to Evidence which A: Yes, sir.
indicated only Criminal Case No. 96-149990 is not controlling Q: SPO2 Vergel De Dios, Rogelio Anoble and a certain
because the body and prayer of the Demurrer to Evidence refer Arellano?
to all the three (3) closely related cases. A: Yes, sir.
Q: When were they arrested?
A; May 16 on or about 7:00 (interrupted)
Anent the charge that respondent judge displayed bias and Q: P.M.?
partiality during the trial when he asked numerous clarificatory A: P.M., your Honor.
questions, we note that the participation of respondent judge in Q: And on the occasion of the arrest of these three men
the conduct of the trial was not by itself condemnable. He could shabu were confiscated from them?
not be expected to remain an impassive and remote presence A: Yes, sir.
during the proceedings, prohibited from asking questions when Q: And in the course of the investigation of these three men
proper and necessary, yet all these were done without you were able to discover that Redentor Tech and Joseph Junio
necessarily transgressing the boundaries of impartiality decreed were the source of the regulated drug that were confiscated from
the three men that you have arrested?
by judicial ethics. The mere fact that the presiding judge asked
A: Yes, sir.
clarificatory questions during the trial does not make him a
biased judge.26 "He must be accorded a reasonable leeway in
asking questions to witnesses as may be essential to elicit
145
Q: Now, thru entrapment [based] in your testimony you were A: Because of the parked BMW which was described by
able to apprehend also these two men, Redentor Tech and Joseph Redentor as the one used by the accused.
Junio? Q: So there was a BMW car parked in front (sic) of the
A: Yes, sir. apartment?
Q: And that was on the evening of what date? A: Yes, sir.
A: May 16. The same (interrupted) Q: And that was described as the car being used by the
Q: The same date? The same evening? accused?
A: Same evening. About 11:00 p.m. A: Yes, sir.
Q: These two men, Redentor and Joseph they were also Q: Was (sic) Redentor and Joseph with your team when you
investigated by your team? proceeded to the apartment?
A: Yes, sir. A: Initially they were with us but the rest of the members of
Q: You were present when they were investigated? the team brought them to our office.
A: I was the one who investigated them. Q: So when the accused came out from the apartment,
Q: This Redentor, he claimed that he was the talent manager Redentor and Joseph were no longer with your team?
of Glenmore Modelling Agency? A: No, sir.
A: Yes, sir. Q: Now, you stated or testified that when the accused came
Q: And you also stated that the agency was own (sic) by the out from the apartment, he was identified by your team. Who
accused in this case? identified the accused?
A: Yes, sir. A: We have in our company an asset who knows the accused.
Q: How about the other man, Joseph? Did he also say that he Q: When the accused was identified to your team as the
was an employee of the accused? employer mentioned by Redentor you immediately held him
A: He told me that he is a gym instructor. surrounded?
Q: So he was not working for the accused? A: Not immediately. We watched what they were about to do.
A: He is also working for the accused. Q: And what was the accused doing when you saw him
Q: As a gym instructor? coming out from the apartment?
A: Yes. A: They were two. One is supposed to be the driver.
Q: You mean to say that the gym is also own (sic) by the Q: So he has a male companion?
accused? A: Yes, sir.
A: He teaches aerobic. Q: The accused?
Q: In what establishment? A: Yes, sir.
A: In Glenmore. Q: They were walking together when they came out from the
Q: In Glenmore? apartment?
A: Yes. sir. A: The driver, sir, is already beside the car.
Q: These two, Redentor and Joseph at the time of the arrest Q: I see. So the driver was waiting inside the car?
they were in the xxx A: Not inside. Outside.
A: Yes, sir. Q: Outside of the car?
Q: In fact they were in xxx to you the three men which were A: Yes, sir.
previously arrested? Q: But near the car?
A: Yes, sir. A: Yes, sir.
Q: Did you ask Redentor and Joseph the source of shabu that Q: You narrated to this court when you saw the accused
you confiscated from them at the time of the arrest? coming out from the apartment walking where was the bound? To
A: Yes, sir. They refuse (sic) to say the source, however, they what direction was he walking? Towards the car?
told me that they were working for the accused. A: Towards the car.
Q: You also testified that Redentor informed you that there Q: Alright. From the apartment where he came out to the
was another delivery of shabu scheduled that morning of (stop) place where the car was parked, what was the distance? How
was it May 16 or May 17? The other delivery that is scheduled many meters?
on? A: A distance of more or less 15 to 20 meters.
A: On the 17th. Q: What did you observe while the accused was walking from
Q: So it was on the following morning? the apartment to his car which has a distance of about 15 to 20
A: Yes, sir. meters? What did you observe in the nature of the accused while
Q: Did he tell you where the delivery of the shabu was to be he was walking towards his car?
made? A: The accused stopped beside the car. He talked with the
A: No, sir. driver, supposed to be the driver and they talked for a while.
Q: Did he tell you who was to make the delivery? Q: So he walked on the left side of the car. Where (stop) in
A: No, sir. what portion of the car did he approached the driver?
Q: You said that your team decided to see the accused to ask A: Left side, sir.
him to shed light regarding the drug trafficking activities of Q: Left side?
Redentor and Joseph? A: Yes, Your Honor.
A: Yes, Your Honor. That is our initial purpose. Q: And you saw him talked with the driver?
Q: To ask him to shed light? A: Yes, sir.
A: Yes, sir. Q: Then what happened?
Q: At that time when you decided to look for the accused to A: After they talked, we saw them open the compartment of
ask him to shed light on the matter concerning the arrest of the car.
these two employees in possession of shabu. Did you and did Q: At this time your team were observing at the distance?
your team suspect the accused as being involved in the A: Yes, sir.
transaction that led to the arrest of Redentor and Joseph? Q: What was the distance?
A: Yes, sir. We suspected that he was the source of the shabu. A: More or less 15 to 20 meters. We were in a concealed
Q: So you were suspecting the accused as being involved? place.
A: Yes, sir. Q: And you were concealed. You could not be seen by the
Q: In the drug transaction? accused?
A: Yes, sir. A: Yes, sir.
Q: You also testified that you and your team proceeded to Q: What happened when you saw the accused and his driver
Maria Orosa apartment somewhere in Ermita? open the trunk of the car?
A: Yes, sir. A: It was Capt. Margallo and Police Inspector Colonel
Q: And that apartment was pinpointed to you by Redentor as approached them and upon seeing them I also went out of my
the place where the accused could be found? hiding place and the accused was accosted.
A: Yes, sir. Q: So that was the time when you and your team accosted
Q: And when you arrived at the apartment you did not enter the accused when the trunk of his car was open?
the apartment? A: Yes, sir.
A: We conducted a stake out. Q: And after you accosted the accused, what did you do?
Q: You waited outside? A: It was Capt. Margallo and I who prevented them from
A: Yes, sir. closing the compartment.
Q: Why? You were expecting the accused to come out from Q: The trunk?
the apartment? A: Yes, sir.
146
Q: What transpired when you approached the accused at that bias against a party litigant. Thus, there is a case where the
point? When you and your (stop) what is the rank of this Coronel? questions asked of a witness by the judge therein were
A Capt. Margallo. Sr. Inspector Lucio Margallo. adversarial, malicious and hostile in character. 31 There is another
Q: No. No. Yes. He was the one that approached the accused? case where the sheer volume of questions asked by the judge
A: And Lt. Coronel. therein tended to be leading, misleading, if not baseless and
Q: And Police Inspector Coronel? hypothetical.32 It has also been held that clarificatory questions
A: Yes, sir. asked by the trial court must not amount to confrontation,
Q: But you were also nearby?
probing and insinuation, which are characteristics of a cross-
A: Yes, sir.
examination.33
Q: Who talked with the accused?
A: It was Capt. Margallo.
Q: What did he tell to the accused? In administrative proceedings, the complainant bears the onus
A: I was not able to get what they are talking because I of establishing, by substantial evidence, the averments of his
immediately told them that there were shabu at the complaint.34 All told, complainants herein failed to discharge that
compartment. burden. Besides, the charges, subject of the administrative case
Q: Who made that statement? against respondent judge, which were indorsed by the Office of
A: I was the one who told them that there were shabu in the
the Ombudsman to the OCA on May 9, 199735 also appear to be
compartment.
premature in view of the filing on May 5, 1997 and pendency in
Q: You told the accused?
A: No. I told Capt. Margallo that there were shabu inside the this Court of the petition for review on certiorari, entitled
compartment of the car. "People of the Philippines v. Lawrence Wang y Chen and Hon.
Q: Now, in your declaration and from that of the Coronel the Perfecto Laguio, Jr., etc.", docketed as G.R. No. 128587, supra,
accused was frisked? (see note no. 10). It has been held that the pendency of an
A: Yes, sir. appeal from a questioned judgment renders the filing of
Q: And from the pocket of the pants of the accused was taken administrative charges premature.36 Where a sufficient judicial
a back-up pistol? remedy exists, the filing of an administrative complaint is not
A: No, sir. I believe it was a Daewoo caliber pistol. the proper remedy to correct the actions of a judge.37
Q: Daewoo? The one that was taken from the possession of
the accused?
A: The AMT back up pistol was handed to me by Capt. WHEREFORE, the administrative complaint against respondent
Margallo. Judge Perfecto A.S. Laguio, Jr. is hereby DISMISSED.
Q: Yes. From whom it was taken?
A: It was taken from the accused. SO ORDERED.
Q: Correct. So when the accused was frisked what gun was
taken from him and it was discovered inside the pocket of his
pants? FIRST DIVISION[G.R. No. 156259. September 18, 2003]
A: Yes, sir.
Q: Which one occurred first? The bodily search of the accused
GROGUN, INCORPORATED, petitioner, vs. NATIONAL
or the search of the trunk or (sic) the car?
POWER CORPORATION, respondent.
A: I could say it was simultaneously being conducted (sic).
Q: At the same time?
A: Yes, Your Honor because they were here while I was at the DECISION
back.
Q: So while you and your othermembers (sic) of the team
were searching the trunk of the car, Police Inspector Coronel and YNARES-SANTIAGO, J.:
another officer, Capt. Margallo were subjecting the accused to
bodily searched? On August 13, 1992, the National Power Corporation
A: Yes, sir. (NAPOCOR) awarded the project of rehabilitating the Caliraya
Q: And you immediately discovered the shabu inside the Glory Hole Service Spillway (CGHSS) at Caliraya Reservoir,
trunk? Lumban, Laguna to GROGUN INC. (GROGUN). Among several
A: Yes, sir.
contractors, GROGUN offered the most workable and viable
Q: And there was another gun that was taken from the car
design at the lowest price.
and that is underneath the driver's seat?
A: Yes, sir.
Q: When you saw the accused walking towards his car, did The primary purpose of the Caliraya Reservoir was to keep
you know whether he was carrying a gun? the lakes water level within the specified limit not only for the
A: No, sir. It cannot be seen. protection of the dam but also to prevent the flooding of the
Q: It was concealed? towns surrounding the dam. Ever since the Caliraya Reservoir
A: Yes, sir. and the CGHSS were built in 1930, the CGHSS was regularly
Q: So the only time that you and your team learned that he
used to flush down excess water from the lake whenever the
was in possession of the gun is when he was bodily searched?
lakes water level reached critical level. Numerous leaks,
A: Yes, sir. That is the only time that I came to know about
when Capt. Margallo handed to me the gun. however occurred in the vertical shaft of CGHSS.
Q: Other than walking towards the car, the accused was not
doing anything else? It appears that prior to 1992, NAPOCOR engaged ALA
A: None, sir. Industries Corporation to repair the CGHSS. The design and
Q: That would invite your suspicion or give indication that he method, however adopted by ALA Industries Corporation were
was intending to do something unlawful or illegal? not workable. Leaks recurred in the vertical shaft of the CGHSS
A: No, sir.
immediately after the project was accepted by NAPOCOR.
Q: When you searched the car, did the accused protest or try
to prevent your team from searching his car?
A: No, sir.30 NAPOCOR failed to pay for the costs of the rehabilitation
despite the completion of the project. Thus, on March 22, 1994,
xxx xxx xxx GROGUN filed a request for adjudication before the Construction
Industry Arbitration Commission (CIAC), docketed as CIAC Case
No. 06-94,[1] pursuant to the arbitration clause[2] in their
The above-quoted questions propounded by respondent judge Contract.[3] However, finding no stipulation in the contract of the
were necessary for the purpose of determining and clarifying the parties providing for arbitration as a mode of settling disputes,
basis for resolving the all important issue of the legality or CIAC dismissed the case.[4]
illegality of the warrantless arrest of Wang and the warrantless
search of the latter's car. Herein respondent judge's aforequoted
questions contrast favorably against instances in other cases On September 10, 1996, GROGUN filed an action for
wherein it was clearly shown that the judges therein displayed collection of sum of money and damages before the Regional
147
Trial Court of Quezon City, Branch 216, which was docketed as Confirmation of Award.Any time within one month after the
Civil Case No. Q-96-28731.[5] NAPOCOR filed its Answer with award is made, any party to the controversy which was
Counterclaim[6] asserting that the poor quality of GROGUNS arbitrated may apply to the court having jurisdiction, as
workmanship led to numerous defects in the project. provided in section twenty-eight, for an order confirming the
award, and thereupon the court must grant such order unless
the award is vacated, modified or corrected, as prescribed
After the pre-trial conference, the parties filed a Joint
herein. Notice of such motion must be served upon the adverse
Manifestation and Motion[7] submitting their dispute to
party or his attorney as prescribed by law for the service of such
arbitration under Republic Act No. 876[8] taking into
notice upon an attorney in action in the same court. (Italics
consideration the highly technical nature of their contract. The
supplied)
Arbitration Tribunal was composed of Atty. Alfredo F. Tadiar as
Chairman, Engineer Carlito T. Kingkay and Atty. Alejandro A.
Padaen as members. On September 15, 1998, the trial court issued an
Order, viz:
On May 14, 1998, the Arbitration Tribunal rendered a
decision, the decretal portion of which reads: WHEREFORE, the Arbitral Decision dated May 14, 1998 is hereby
ordered modified as follows:
WHEREFORE, judgment is hereby rendered and AWARD is made
as follows: a) the Arbitrators Fees of P420,836.28 shall be shared
by defendant NAPOCOR and plaintiff GROGUN
in proportion to their respective claims, i.e.,
FOR THE PLAINTIFF-CONTRACTOR:
69.94 % and 30.06%, respectively;

Defendant is directed to pay the Plaintiff the following amounts


b) the defendant NAPOCOR is hereby ordered to
on its various claims:
reimburse the plaintiff GROGUN the following
amounts: (1) P294,332.89 representing the
P1,440,000.00 as bonus for early completion of works under Arbitrators Fees; and (2) P25,000.00
Article IV, Clause 6 of their contract. representing the agreed 50% share of
NAPOCOR in the Administrative Costs; and
P 670,369.61 as cost of standby or downtime overhead cost of
skeleton force during the forced work suspension in November, c) the rest of the Arbitral Decision is hereby
1992. confirmed and maintained.[13]

P1,447,670.00 as the value of the accomplished works of the NAPOCORs Motion for Reconsideration of the said
Plaintiff that were destroyed by the waters released by the Order[14] was denied.[15]
opening of the spillway gates.

Thus, NAPOCOR appealed to the Court of Appeals raising


P3,558,039.61 Total claims awarded to the Plaintiff-Contractor. the following errors:

FOR THE DEFENDANT-OWNER I.

Plaintiff is directed to pay the Defendant its counterclaim: THE REGIONAL TRIAL COURT ERRED IN AFFIRMING THE
DECISION OF THE ARBITRAL TRIBUNAL DESPITE THE FACT THAT
P1,047,850.00 as the cost of rectification of the defective works A COPY OF THE ARBITRAL DECISION DATED MAY 14, 1998
performed by Plaintiff SUBMITTED BY GROGUN WAS NOT VERIFIED.

OFFSETTING the two amounts mutually due to each other; II.


Defendant-Owner, National Power Corporation shall pay the net
amount remaining of P2,510,189.61 to the Plaintiff-Contractor, THE REGIONAL TRIAL COURT ERRED IN ADOPTING THE DECISION
GROGUN, INC. [9] OF THE ARBITRAL TRIBUNAL ALTHOUGH THE FINDINGS OF THE
ARBITRAL TRIBUNAL WERE NOT SUBSTANTIATED BY LAW AND
GROGUN submitted a copy of the above decision to the EVIDENCE.[16]
trial court.
Instead of filing an Appellees Brief, GROGUN filed a Motion
On May 20, 1998, GROGUN filed before the trial court to Dismiss[17] the appeal based on the following grounds: (a)
a Manifestation and Motion to Modify the Arbitral NAPOCOR failed to file the record on appeal required in an
Decision,alleging that the Arbitration Tribunal did not include in arbitration proceeding under R.A. No. 876; (b) NAPOCOR failed
its Decision a provision on who should bear the costs of to contest the award before the Arbitration Tribunal or the trial
arbitration pursuant to the parties Agreement on Arbitration court; (c) NAPOCORs two assigned errors were not raised in the
Expenses.[10] trial court and (d) the appeal raised only questions of law.

In its Comment, NAPOCOR argued that the foregoing On March 30, 2001, the Court of Appeals rendered a
Motion is premature because the Arbitration Tribunal had not decision,[18] reversing the Orders of the Regional Trial Court in
submitted its recommendation to the trial court and the same Quezon City, Branch 216 in Civil Case No. Q-96-28731, dated
had not been approved or adopted by the trial court. [11] September 15, 1998 and January 8, 1999 and remanded the
case to the trial court for further proceedings. [19]

In the meantime, GROGUN filed another


Manifestation[12] asking the trial court to grant its Manifestation GROGUN filed a Motion for Reconsideration [20] of the said
and Motion to Modify the Arbitral Award since NAPOCOR did not decision which was denied by the Court of Appeals in its
file a motion to vacate, modify or correct the same within one Resolution dated November 21, 2002.[21]
month from the time it was rendered, pursuant to Section 23 of
the Arbitration Law. Hence, this petition for review on the following assignment
of errors:
148
I 5. DOES NOT AFFECT THE COURT OF ITS JURISDICTION;

THE COURT OF APPEALS PATENTLY ERRED IN NOT 6. SIMPLY AN ASSURANCE AGAINST PRODUCTS OF IMAGINATION;
DISMISSING THE APPEAL, DESPITE:
7. CANNOT BE RAISED AS AN OBJECTION FOR THE FIRST TIME ON
1. THE DEFECT OF NOT HAVING FILED A RECORD ON APPEAL WHICH APPEAL; HAS BEEN COMPLIED WITH BY PETITIONERS
IS REQUIRED IN SPECIAL PROCEEDINGS SUCH AS MOTION TO CONFIRM/ MODIFY THE SAME;
ARBITRATION UNDER REPUBLIC ACT NO. 876;
8. NOT NECESSARY WHERE AN OPPOSITION IS NOT BASED ON
2. THE FILING OF THE BRIEF HAVING BEEN DELAYED FOR MORE FRAUD, ACCIDENT, MISTAKE OR EXCUSABLE
THAN ONE (1) YEAR FROM THE NOTICE OF APPEAL; NEGLIGENCE;

3. IT HAVING FAILED TO REPUDIATE THE ARBITRAL AWARD WITHIN 9. HAS BEEN CURED/ OFFSET BY LACK OF OBJECTION THERETO AT
THE REGLEMENTARY PERIOD OF 30 DAYS UNDER FIRST INSTANCE IN THE COURT BELOW; AND
REPUBLIC ACT NO. 876;
10. DOES NOT BY ITS TECHNICALITY SACRIFICE SUBSTANTIAL
4. THE ARBITRAL DECISION BY VIRTUE OF A JOINT SUBMISSION BY JUSTICE.[22]
THE PARTIES WAS EFFECTIVELY ONE OF A JUDGMENT BY
CONSENT, AS SUCH IT SHOULD HAVE BEEN FIRST The petition lacks merit.
REPUDIATED BEFORE THE ARBITRAL TRIBUNAL. FAILING
TO REPUDIATE THE SAME BEFORE THE ARBITRAL
TRIBUNAL, ITS CONFIRMATION BY THE REGIONAL TRIAL Supreme Court Circular No. 2-90, which is based in a
COURT BECAME MINISTERIAL. THUS THE REGIONAL TRIAL Resolution of the Court En Banc in UDK-9748 (Anacleto Murillo v.
COURTS CONFIRMATION THEREOF IS NOT APPEALABLE; Rodolfo Consul), March 1, 1990, provides in 4(c) thereof:

5. THE ONLY TWO ASSIGNMENT OF ERRORS ARE NOT APPEALABLE c) xxx If an appeal under Rule 41 is taken from the regional trial
AS THEY HAVE NOT BEEN RAISED IN THE REGIONAL TRIAL court to the Court of Appeals and therein the appellant raises
COURT; only questions of law, the appeal shall be dismissed, issues
purely of law not being reviewable by said Court. xxx (Italics
supplied)[23]
6. THE APPEAL, WHICH ULTIMATELY RAISES ONLY QUESTIONS OF
LAW, WAS IMPROPERLY FILED UNDER RULE 41 OF THE
RULES OF COURT; AND This was reproduced in Rule 50, Section 2 of the 1997 Rules of
Civil Procedure.

7. IT APPEARS THAT THERE HAVE ALREADY BEEN A DISMISSAL OF


THE APPEAL FOR FAILURE TO FILE APPELLANTS BRIEF, An appeal under Rule 41 taken from the Regional Trial Court to
AND THE SAME DOES NOT APPEAR TO HAVE BEEN the Court of Appeals raising only questions of law shall be
RECONSIDERED YET. dismissed, issues purely of law not being reviewable by said
court. (Italics supplied)

II
Corollary thereto, in Roman Catholic Archbishop of Manila
v. Court of Appeals, et al.,[24] it was held that there is a question
THE COURT OF APPEALS PATENTLY ERRED IN CAVALIERLY of law when the issue does not call for an examination of the
GRANTING THE RELIEF APPEALED FOR ON THE MERITS probative value of evidence presented, the truth or falsehood of
WITHOUT YET GIVING APPELLEE THE OPPORTUNITY TO facts being admitted and the doubt concerns the correct
FILE ITS BRIEF AND/OR WITHOUT YET THE COURT OF
application of law and jurisprudence on the matter.
APPEALS HAVING RESOLVED THE PENDING INCIDENT
WHICH IS THE MOTION TO DISMISS FILED UNDER RULE 50
OF THE RULES OF COURT. The issues raised by NAPOCOR in its appeal to the Court of
Appeals are not purely questions of law. Specifically, NAPOCORs
arguments assailing the award by the trial court to GROGUN of
III the amount of (a) P1,447,670.00 representing the value of its
accomplished works which were destroyed by the flood waters;
THE COURT OF APPEALS PATENTLY ERRED IN SETTING and (b) P670,369.61 representing the compensation for idle
ASIDE THE ORDER OF THE REGIONAL TRIAL COURT time of manpower and equipment caused by the opening of the
DATED 15 SEPTEMBER 1998 WHICH MODIFIED IN PART CGHSS, raised factual issues. Furthermore, the determination of
AND CONFIRMED THE REST OF THE ARBITRAL DECISION the amount of damages NAPOCOR was entitled to under its
AND THE ORDER DATED 8 JANUARY 1999 WHICH DENIED counterclaim depends on whether the leakages were causally
RESPONDENTS MOTION FOR RECONSIDERATION, linked to any defective work performed by GROGUN.
SUPPOSEDLY BECAUSE THE ARBITRAL DECISION WAS NOT
VERIFIED, WHEN SUCH A LACK OF VERIFICATION: Then, too, the mere filing of the notice of appeal is
sufficient. Rule 41, Section 2 of the 1997 Rule on Civil Procedure
1. UNLIKE FOR AD HOC ARBITRATIONS WHICH ARE CONDUCTED categorically states:
OUTSIDE THE AUSPICES OF THE COURTS, MAY NOT
REQUIRE A VERIFICATION FOR AUTHENTICATING THE (a) Ordinary appeal. The appeal to the Court of Appeals in cases
ARBITRAL AWARD; decided by the Regional Trial Court in the exercise of its original
jurisdiction shall be taken by filing a notice of appeal with the
2. IS MERELY A FORMAL DEFECT THAT IS NEITHER JURISDICTIONAL court which rendered the judgment or final order appealed from
NOR FATAL; and serving a copy thereof upon the adverse party. No record on
appeal shall be required except in special proceedings and other
cases of multiple or separate appeals where the law or these
3. CAN BE DISPENSED WITH OR EXCUSED;
Rules so require. In such cases, the record on appeal shall be
filed and served in like manner.
4. DOES NOT OPERATE TO MAKE THE COURT TO NECESSARILY
COMMIT REVERSIBLE ERROR;
149
This petition originated from an action for collection of a Form and contents of award. The award must be made
sum of money filed with the Regional Trial Court,[25] which is an in writing and signed and acknowledged by a majority of the
ordinary civil action.[26] The decision of the parties to submit arbitrators, if more than one; and by the sole arbitrator, if there
their dispute to arbitration during the proceedings did not is only one. Each party shall be furnished with a copy of the
change the nature of the original action to one of special award. The arbitrators in their award may grant any remedy or
proceeding, under which an appeal shall be by record on appeal. relief which they may deem just and equitable and within the
Section 22 of the Arbitration Law, [27] which provides that scope of the agreement of the parties, which shall include, but
arbitration is in the nature of a special proceeding, is not not be limited to, the specific performance of a contract. (Italics
applicable. supplied)

GROGUN argues that the Court of Appeals should have GROGUN argues that NAPOCOR did not raise as issue the
dismissed the appeal because NAPOCOR filed its Appellants lack of verification of the copy of the arbitral award in the trial
Brief more than one year from the filing of the Notice of Appeal. court. Neither did NAPOCOR repudiate the arbitral award before
the Arbitration Tribunal and the trial court.
The argument is tenuous. Rule 44, Section 7 of the 1997
Rules of Civil Procedure provides that the appellant shall file his The argument is not well-taken. Ordinarily, points of law,
brief within forty-five (45) days from receipt of notice from the theories, issues and arguments not brought to the attention of
Court of Appeals. [28] the lower court cannot be raised for the first time on appeal.[33]

In the case at bar, NAPOCOR received notice from the In the case at bar, however, NAPOCOR could not have
Court of Appeals to file its Brief within 45 days on October 26, raised the lack of verification of the copy of the arbitral award
1999. On December 10, 1999, it filed a Motion for Extension of submitted by GROGUN since it was assailing the authenticity
forty five days, or until January 25, 2000, within which to file its and due execution of the copy itself. It was only after the trial
Brief, which was granted.[29] Hence, NAPOCORs Appellants Brief court upheld the said copy as a valid arbitral award that
filed on January 24, 2000 was on time. NAPOCOR was able to raise the issue, which was during the
filing of its appellants brief before the Court of Appeals.
GROGUN claims that the Court of Appeals had already
dismissed the appeal in its Resolution dated April 18, 2000, GROGUN also argues that the Court of Appeals should
to wit: have first decided the Motion to Dismiss filed by the NAPOCOR
before resolving the merits of the appeal. It also alleges that the
Court of Appeals did not require it to file an Appellees Brief.
In view of the resolution dated March 3, 2000 which considered
the case DISMISSED for failure to file appellants brief, the
motion for extension of time to file brief by the OSG and the The contention is without merit. The grant or denial of the
motion for early resolution filed by plaintiff-appellee Grogun, Inc. Motion to Dismiss was within the sound discretion of the Court of
are merely noted. (Emphasis and italics supplied) Appeals. Its resolution of the appeal on its merits meant that it
found the Motion to Dismiss to be without merit.On the other
hand, Rule 44, Section 8 of the 1997 Rules of Civil Procedure,
GROGUNs reliance is misplaced. In a subsequent [34]
provides that the appellee shall file his brief within forty-five
Resolution, the Court of Appeals corrected itself thus:
days from receipt of the appellants brief. Hence, there was no
need for the Court of Appeals to require GROGUN to file its
Considering that the resolution of this Court dated April 18, 2000 appellees brief.
in CV NO. 62017 was intended for CV NO. 62357, the same is
hereby RECALLED and SET ASIDE.
WHEREFORE, in view of the foregoing, the petition is
DENIED. The Decision of the Court of Appeals dated March 30,
We come now to the issue of whether the copy of the 2001, which set aside the Orders dated September 15, 1998 and
arbitral award submitted by GROGUN to the trial court was valid. January 8, 1999 of the Regional Trial Court of Quezon City,
Branch 216, in Civil Case No. Q-96-28731, and remanded the
GROGUN admits that the copy of the arbitral award it case to the trial court for further proceedings, is AFFIRMED.SO
submitted to the trial court was not verified. However, it argues ORDERED.
that the lack of verification is a formal defect which is not fatal,
and may be waived or dispensed with. It cites cases which, FIRST DIVISIONG.R. No. 94960 March 8, 1993
however, refer to the effect of lack of verification in
the pleadings.
IMPERIAL TEXTILE MILLS, INC., petitioner,
vs.
Verification in general is confirmation of correctness, truth, HON. VLADIMIR P.L. SAMPANG and IMPERIAL TEXTILE
or authenticity by affidavit, oath, or deposition.[30] The MILLS-MONTHLY EMPLOYEES ASSOCIATION (ITM-
verb verify is frequently used in its legal sense in legal MEA), respondents.
proceeding and matters of law, and as used and understood by
lawyers it has a technical signification, and means the swearing
CRUZ, J.:
to an affidavit; to affirm under oath; to confirm and substantiate
by oath; or even by agreement, to confirm by formal oath; to
testify or affirm formally or upon oath; to confirm or establish On March 20, 1987, petitioner Imperial Textile Mills, Inc. (the
the authority of; as by affirmation or competent evidence; to Company, for brevity) and respondent Imperial Textile Mills-
confirm or substantiate by proof; to establish by evidence. [31]The Monthly Employees Association (the Union, for brevity) entered
word verified, in connection with statutory reports, has a settled into a collective bargaining agreement providing across-the-
or well known meaning; and refers to an affidavit attached to board salary increases and other benefits retroactive to
the statement as to the truth of the matters therein set forth, November 1, 1986.
within the personal knowledge of the affiant, and it has been
held that the word means sworn to and ordinarily imports a On August 21, 1987, they executed another agreement on the
verity attested by the sanctity of an oath.[32] job classification and wage standardization plan. This was also
to take effect retroactively on November 1, 1986.
In the case at bar, the copy of the arbitral award did not
meet the requirements of Section 20 of the Arbitration Law, and A dispute subsequently arose in the interpretation of the two
consequently, therefore can not be the basis of the assailed agreements. The parties then submitted it to arbitration and
Orders of the trial court. Specifically, Section 20 provides:
150
designated public respondent Vladimir P.L. Sampang as the In the case of The Consolidated Bank & Trust Corporation
Voluntary Arbitrator. The understanding was that his decision (SOLIDBANK) v. Bureau of Labor Relations, et al., 3this Court held
would be final, executory and inappealable. 1 that the Voluntary Arbitrator lost jurisdiction over the case
submitted to him the moment be rendered his decision.
Therefore, he could no longer entertain a motion for
The Company maintained that the wage of a particular
reconsideration of the decision for its reversal or modification.
employee subject of possible adjustment on base pay should be
Thus:
the pay with the first year CBA increase already integrated
therein.
By modifying the original award, respondent arbitrator
exceeded his authority as such, a fact he was well aware
The Union argued that the CBA increases should not be included
of, as shown by his previous Resolution of Inhibition
in adjusting the wages to the base pay level, as it was separate
wherein he refused to act on the Union's motion for
and distinct from the increases resulting from the job
reconsideration of the award or decision. Thus,
classification and standardization scheme.
respondent arbitrator emphatically ruled:

On July 12, 1988, the Voluntary Arbitrator rendered a decision


It would be well to remind the Parties in this case that the
upholding the formula used by the Company.
arbitration law or jurisprudence on the matter is explicit
in its stand against revocation and amendment of the
The Union filed a motion for reconsideration which was opposed submission agreement and the arbitration award once
by the Company. such has been made. The rationale behind this is that:

On December 14, 1988, after a conference with the parties, the An award should be regarded as the judgment of a court
Voluntary Arbitrator rendered another decision, this time in favor of last resort, so that all reasonable presumptions should
of the Union. be ascertained in its favor and none to overthrow it.
Otherwise, arbitration proceedings, instead of being a
On January 20, 1989, the Company appealed to the NLRC. The quick and easy mode of obtaining justice, would be
appeal was dismissed for lack of jurisdiction. The reason was merely an unnecessary step in the course of litigation,
that the original rule allowing appeal if the Voluntary Arbitrator's causing delay and expenses, but not finally settling
award was more than P100,000.00 had already been repealed anything. Notwithstanding the natural reluctance of the
by BP 130. Moreover, under Article 262-A of the Labor Code, as courts to interfere with matters determined by the
amended, awards or decisions of voluntary arbitrators become arbitrators. they will do so in proper cases where the law
final and executory after calendar 10 days from notice thereof to ordains them. (Arbitration, Manguiat, citing U.S. v.
the parties. Gleason, 175 US 588)

The Company then came to this Court in this petition The power and authority of the Voluntary Arbitrator to act
for certiorari under Rule 65 of the Rules of Court. in the case commences from his appointment and
acceptance to act as such under the submission
agreement of the Parties and terminates upon his
The Court has deliberated on the arguments of the parties in rendition of his decision or award which is accorded the
light of the established facts and the applicable law and finds for benefits of the doctrine of res judicata as in judgments of
the Company. our regular courts of law. Since the power and authority
of the arbitrator to render a valid award, order or
The Union erred in filing a motion for reconsideration of the resolution rest upon the continuing mutual consent of the
decision dated July 12, 1988. So did the respondent Voluntary parties, and there is none shown here, the Voluntary
Arbitrator in entertaining the motion and vacating his first Arbitrator has no choice but to decline to rule on the
decision. pleadings submitted by the parties. (Emphasis supplied)

When the parties submitted their grievance to arbitration, they It is true that the present rule makes the voluntary arbitration
expressly agreed that the decision of the Voluntary Arbitrator award final and executory after ten calendar days from receipt
would be final, executory and inappealable. In fact, even without of the copy of the award or decision by the
this stipulation, the first decision had already become so by parties. 4 Presumably, the decision may still be reconsidered by
virtue of Article 263 of the Labor Code making voluntary the Voluntary Arbitrator on the basis of a motion for
arbitration awards or decisions final and executory. reconsideration duly filed during that period. Such a provision,
being procedural, may be applied retroactively to pending
actions as we have held in a number of cases. 5 However, it
The philosophy underlying this rule was explained by Judge
cannot be applied to a case in which the decision had become
Freedman in the case of La Vale Plaza, Inc., v. R.S. Noonan,
final before the new provision took effect, as in the case at
Inc., 2 thus:
bar. 6 R.A. 6715, which introduced amended Article 262-A of the
Labor Code, became effective on March 21, 1989. The first
It is an equally fundamental common law principle that decision of the Voluntary Arbitrator was rendered on July 12,
once an arbitrator has made and published a final award, his 1988, when the law in force was Article 263 of the Labor Code,
authority is exhausted and be is functus officio and can do which provided that:
nothing more in regard to the subject matter of the arbitration.
The policy which lies behind this is an unwillingness to permit
Voluntary arbitration awards or decisions shall
one who not a is judicial officer and who acts informally and
be final, inappealable, and executory.
sporadically, to re-examine a final decision which he has already
rendered, because of the potential evil of outside
communication and unilateral influence which might affect a The above-quoted provision did not expressly fix the time when
new conclusion. The continuity of judicial office and the tradition the Voluntary Arbitrator's decision or award would become final.
which surround judicial conduct is lacking in the isolated activity We have held, however, that it would assume the attribute of
of an arbitrator, although even here the vast increase in the finality upon its issuance, subject only to judicial review in
arbitration of labor disputes has created the office of the appropriate cases. 7
specialized provisional arbitrator. (Washington-Baltimore N.G.,
Loc. 35 v. Washington Post Co., 442 F. 2d 1234 (1971], pp. 1238- The public respondent exceeded his authority when he acted on
1239) the Union's motion for reconsideration and reversed his original
decision. Corollarily his second decision dated December 14,
151
1988, having been rendered in violation of law, must be 2. The parties mutually agree that the arbitration shall
considered null and void and of no force and effect whatsoever. 8 proceed in accordance with the following terms and
conditions:
WHEREFORE, the decision of the Voluntary Arbitrator dated
December 14, 1988, is SET ASIDE for lack of jurisdiction and his xxx xxx xxx
decision dated July 12, 1988, is REINSTATED.
d. The parties mutually agree that they will abide by the
SO ORDERED. decision of the arbitrator including any amount that may be
awarded to either party as compensation, consequential
damage and/or interest thereon;
THIRD DIVISIONG.R. No. 96283 February 25, 1992

e. The parties mutually agree that the decision of the


CHUNG FU INDUSTRIES (PHILIPPINES) INC., its Directors
arbitrator shall be final and unappealable. Therefore, there
and Officers namely: HUANG KUO-CHANG, HUANG AN-
shall be no further judicial recourse if either party disagrees
CHUNG, JAMES J.R. CHEN, TRISTAN A. CATINDIG, VICENTE
with the whole or any part of the arbitrator's award.
B. AMADOR, ROCK A.C. HUANG, JEM S.C. HUANG, MARIA
TERESA SOLIVEN and VIRGILIO M. DEL
ROSARIO, petitioners,vs.COURT OF APPEALS, HON. f. As an exception to sub-paragraph (e) above, the parties
FRANCISCO X. VELEZ (Presiding Judge, Regional Trail mutually agree that either party is entitled to seek judicial
Court of Makati [Branch 57]) and ROBLECOR assistance for purposes of enforcing the arbitrator's award;
PHILIPPINES, INC., respondents.
4
xxx xxx xxx
ROMERO, J.:
(Emphasis supplied)
This is a special civil action for certiorari seeking to annul the
Resolutions of the Court of Appeals* dated October 22, 1990 Respondent Regional Trial Court approved the arbitration
and December 3, 1990 upholding the Orders of July 31, 1990 agreement thru its Order of May 30, 1990. Thereafter, Engr.
and August 23, 1990 of the Regional Trial Court of Makati, Willardo Asuncion was appointed as the sole arbitrator.
Branch 57, in Civil Case No. 90-1335. Respondent Court of
Appeals affirmed the ruling of the trial court that herein
petitioners, after submitting themselves for arbitration and On June 30, 1990, Arbitrator Asuncion ordered petitioners to
agreeing to the terms and conditions thereof, providing that the immediately pay respondent contractor, the sum of
arbitration award shall be final and unappealable, are precluded P16,108,801.00. He further declared the award as final and
from seeking judicial review of subject arbitration award. unappealable, pursuant to the Arbitration Agreement precluding
judicial review of the award.

It appears that on May 17, 1989, petitioner Chung Fu Industries


(Philippines) (Chung Fu for brevity) and private respondent Consequently, Roblecor moved for the confirmation of said
Roblecor Philippines, Inc. (Roblecor for short) forged a award. On the other hand, Chung Fu moved to remand the case
construction agreement 1 whereby respondent contractor for further hearing and asked for a reconsideration of the
committed to construct and finish on December 31, 1989, judgment award claiming that Arbitrator Asuncion committed
petitioner corporation's industrial/factory complex in Tanawan, twelve (12) instances of grave error by disregarding the
Tanza, Cavite for and in consideration of P42,000,000.00. In the provisions of the parties' contract.
event of disputes arising from the performance of subject
contract, it was stipulated therein that the issue(s) shall be Respondent lower court denied Chung Fu's Motion to Remand
submitted for resolution before a single arbitrator chosen by thus compelling it to seek reconsideration therefrom but to no
both parties. avail. The trial court granted Roblecor's Motion for Confirmation
of Award and accordingly, entered judgment in conformity
Apart from the aforesaid construction agreement, Chung Fu and therewith. Moreover, it granted the motion for the issuance of a
Roblecor entered into two (2) other ancillary contracts, to wit: writ of execution filed by respondent.
one dated June 23, 1989, for the construction of a dormitory and
support facilities with a contract price of P3,875,285.00, to be Chung Fu elevated the case via a petition for certiorari to
completed on or before October 31, 1989; 2 and the other dated respondent Court of Appeals. On October 22,1990 the assailed
August 12, 1989, for the installation of electrical, water and resolution was issued. The respondent appellate court concurred
hydrant systems at the plant site, commanding a price of P12.1 with the findings and conclusions of respondent trial court
million and requiring completion thereof one month after civil resolving that Chung Fu and its officers, as signatories to the
works have been finished. 3 Arbitration Agreement are bound to observe the stipulations
thereof providing for the finality of the award and precluding any
However, respondent Roblecor failed to complete the work appeal therefrom.
despite the extension of time allowed it by Chung Fu.
Subsequently, the latter had to take over the construction when A motion for reconsideration of said resolution was filed by
it had become evident that Roblecor was not in a position to petitioner, but it was similarly denied by respondent Court of
fulfill its obligation. Appeals thru its questioned resolution of December 3, 1990.

Claiming an unsatisfied account of P10,500,000.00 and unpaid Hence, the instant petition anchored on the following grounds:
progress billings of P2,370,179.23, Roblecor on May 18, 1990,
filed a petition for Compulsory Arbitration with prayer for
First
Temporary Restraining Order before respondent Regional Trial
Court, pursuant to the arbitration clause in the construction
agreement. Chung Fu moved to dismiss the petition and further Respondents Court of Appeals and trial Judge gravely
prayed for the quashing of the restraining order. abused their discretion and/or exceeded their jurisdiction,
as well as denied due process and substantial justice to
petitioners, (a) by refusing to exercise their judicial
Subsequent negotiations between the parties eventually led to
authority and legal duty to review the arbitration award,
the formulation of an arbitration agreement which, among
and (b) by declaring that petitioners are estopped from
others, provides:
questioning the arbitration award allegedly in view of the
152
stipulations in the parties' arbitration agreement that "the tended to be time-consuming, costly, and inflexible due to their
decision of the arbitrator shall be final and unappealable" scrupulous observance of the due process of law doctrine and
and that "there shall be no further judicial recourse if their strict adherence to rules of evidence.
either party disagrees with the whole or any part of the
arbitrator's award." As early as the 1920's, this Court declared:

Second In the Philippines fortunately, the attitude of the courts toward


arbitration agreements is slowly crystallizing into definite and
Respondent Court of Appeals and trial Judge gravely workable form. . . . The rule now is that unless the agreement is
abused their discretion and/or exceeded their jurisdiction, such as absolutely to close the doors of the courts against the
as well as denied due process and substantial justice to parties, which agreement would be void, the courts will look with
petitioner, by not vacating and annulling the award dated favor upon such amicable arrangements and will only with great
30 June 1990 of the Arbitrator, on the ground that the reluctance interfere to anticipate or nullify the action of the
Arbitrator grossly departed from the terms of the parties' arbitrator. 10
contracts and misapplied the law, and thereby exceeded
the authority and power delegated to him. (Rollo, p. 17) That there was a growing need for a law regulating arbitration in
general was acknowledged when Republic Act No. 876 (1953),
Allow us to take a leaf from history and briefly trace the otherwise known as the Arbitration Law, was passed. "Said Act
evolution of arbitration as a mode of dispute settlement. was obviously adopted to
supplement not to supplant the New Civil Code on
arbitration. It expressly declares that "the provisions of chapters
Because conflict is inherent in human society, much effort has
one and two, Title XIV, Book IV of the Civil Code shall remain in
been expended by men and institutions in devising ways of
force." 11
resolving the same. With the progress of civilization, physical
combat has been ruled out and instead, more specific means
have been evolved, such as recourse to the good offices of a In recognition of the pressing need for an arbitral machinery for
disinterested third party, whether this be a court or a private the early and expeditious settlement of disputes in the
individual or individuals. construction industry, a Construction Industry Arbitration
Commission (CIAC) was created by Executive Order No. 1008,
enacted on February 4, 1985.
Legal history discloses that "the early judges called upon to
solve private conflicts were primarily the arbiters, persons not
specially trained but in whose morality, probity and good sense In practice nowadays, absent an agreement of the parties to
the parties in conflict reposed full trust. Thus, in Republican resolve their disputes via a particular mode, it is the regular
Rome, arbiter and judge (judex) were synonymous. The courts that remain the fora to resolve such matters. However,
magistrate or praetor, after noting down the conflicting claims of the parties may opt for recourse to third parties, exercising their
litigants, and clarifying the issues, referred them for decision to basic freedom to "establish such stipulation, clauses, terms and
a private person designated by the parties, by common conditions as they may deem convenient, provided they are not
agreement, or selected by them from an apposite listing contrary to law, morals, good customs, public order or public
(the album judicium) or else by having the arbiter chosen by lot. policy." 12 In such a case, resort to the arbitration process may
The judges proper, as specially trained state officials endowed be spelled out by them in a contract in anticipation of disputes
with own power and jurisdiction, and taking cognizance of that may arise between them. Or this may be stipulated in a
litigations from beginning to end, only appeared under the submission agreement when they are actually confronted by a
Empire, by the so-called cognitio extra ordinem." 5 dispute. Whatever be the case, such recourse to an extrajudicial
means of settlement is not intended to completely deprive the
courts of jurisdiction. In fact, the early cases on arbitration
Such means of referring a dispute to a third party has also long
carefully spelled out the prevailing doctrine at the time, thus: ". .
been an accepted alternative to litigation at common law. 6
. a clause in a contract providing that all matters in dispute
between the parties shall be referred to arbitrators and to them
Sparse though the law and jurisprudence may be on the subject alone is contrary to public policy and cannot oust the courts of
of arbitration in the Philippines, it was nonetheless recognized in Jurisdiction." 13
the Spanish Civil Code; specifically, the provisions on
compromises made applicable to arbitrations under Articles
But certainly, the stipulation to refer all future disputes to an
1820 and 1821. 7 Although said provisions were repealed by
arbitrator or to submit an ongoing dispute to one is valid. Being
implication with the repeal of the Spanish Law of Civil
part of a contract between the parties, it is binding and
Procedure, 8 these and additional ones were reinstated in the
enforceable in court in case one of them neglects, fails or
present Civil Code. 9
refuses to arbitrate. Going a step further, in the event that they
declare their intention to refer their differences to arbitration
Arbitration found a fertile field in the resolution of labor- first before taking court action, this constitutes a condition
management disputes in the Philippines. Although early on, precedent, such that where a suit has been instituted
Commonwealth Act 103 (1936) provided for compulsory prematurely, the court shall suspend the same and the parties
arbitration as the state policy to be administered by the Court of shall be directed forthwith to proceed to arbitration. 14
Industrial Relations, in time such a modality gave way to
voluntary arbitration. While not completely supplanting
A court action may likewise be proven where the arbitrator has
compulsory arbitration which until today is practiced by
not been selected by the parties. 15
government officials, the Industrial Peace Act which was passed
in 1953 as Republic Act No. 875, favored the policy of free
collective bargaining, in general, and resort to grievance Under present law, may the parties who agree to submit their
procedure, in particular, as the preferred mode of settling disputes to arbitration further provide that the arbitrators' award
disputes in industry. It was accepted and enunciated more shall be final, unappealable and executory?
explicitly in the Labor Code, which was passed on November 1,
1974 as Presidential Decree No. 442, with the amendments later Article 2044 of the Civil Code recognizes the validity of such
introduced by Republic Act No. 6715 (1989). stipulation, thus:

Whether utilized in business transactions or in employer- Any stipulation that the arbitrators' award or
employee relations, arbitration was gaining wide acceptance. A decision shall be final is valid, without
consensual process, it was preferred to orders imposed by prejudice to Articles 2038, 2039 and 2040.
government upon the disputants. Moreover, court litigations
153
Similarly, the Construction Industry Arbitration Law provides that It should be stressed, too, that voluntary arbitrators, by the
the arbitral award "shall be final and inappealable except on nature of their functions, act in a quasi-judicial capacity. 24 It
questions of law which shall be appealable to the Supreme stands to reason, therefore, that their decisions should not be
Court." 16 beyond the scope of the power of judicial review of this Court.

Under the original Labor Code, voluntary arbitration awards or In the case at bar, petitioners assailed the arbitral award on the
decisions were final, unappealable and executory. "However, following grounds, most of which allege error on the part of the
voluntary arbitration awards or decisions on money claims, arbitrator in granting compensation for various items which
involving an amount exceeding One Hundred Thousand Pesos apparently are disputed by said petitioners:
(P100,000.00) or forty-percent (40%) of the paid-up capital of
the respondent employer, whichever is lower, maybe appealed 1. The Honorable Arbitrator committed grave error in failing
to the National Labor Relations Commission on any of the to apply the terms and conditions of the Construction
following grounds: (a) abuse of discretion; and (b) gross Agreement, Dormitory Contract and Electrical Contract, and
incompetence." 17 It is to be noted that the appeal in the in using instead the "practices" in the construction industry;
instances cited were to be made to the National Labor Relations
Commission and not to the courts.
2. The Honorable Arbitrator committed grave error in
granting extra compensation to Roblecor for loss of
With the subsequent deletion of the above-cited provision from productivity due to adverse weather conditions;
the Labor Code, the voluntary arbitrator is now mandated to
render an award or decision within twenty (20) calendar days
from the date of submission of the dispute and such decision 3. The Honorable Arbitrator committed grave error in
shall be final and executory after ten (10) calendar days from granting extra compensation to Roblecor for loss due to
receipt of the copy of the award or decision by the parties. 18 delayed payment of progress billings;

Where the parties agree that the decision of the arbitrator shall 4. The Honorable Arbitrator committed grave error in
be final and unappealable as in the instant case, the pivotal granting extra compensation to Roblecor for loss of
inquiry is whether subject arbitration award is indeed beyond productivity due to the cement crisis;
the ambit of the court's power of judicial review.
5. The Honorable Arbitrator committed grave error in
We rule in the negative. It is stated explicitly under Art. 2044 of granting extra compensation to Roblecor for losses
the Civil Code that the finality of the arbitrators' award is not allegedly sustained on account of the failed coup d'tat;
absolute and without exceptions. Where the conditions
described in Articles 2038, 2039 and 2040 applicable to both 6. The Honorable Arbitrator committed grave error in
compromises and arbitrations are obtaining, the arbitrators' granting to Roblecor the amount representing the alleged
award may be annulled or rescinded. 19 Additionally, under unpaid billings of Chung Fu;
Sections 24 and 25 of the Arbitration Law, there are grounds for
vacating, modifying or rescinding an arbitrator's award. 20 Thus,
7. The Honorable Arbitrator committed grave error in
if and when the factual circumstances referred to in the above-
granting to Roblecor the amount representing the alleged
cited provisions are present, judicial review of the award is
extended overhead expenses;
properly warranted.

8. The Honorable Arbitrator committed grave error in


What if courts refuse or neglect to inquire into the factual milieu
granting to Roblecor the amount representing expenses for
of an arbitrator's award to determine whether it is in accordance
change order for site development outside the area of
with law or within the scope of his authority? How may the
responsibility of Roblecor;
power of judicial review be invoked?

9. The Honorable Arbitrator committed grave error in


This is where the proper remedy is certiorari under Rule 65 of
granting to Roblecor the cost of warehouse No. 2;
the Revised Rules of Court. It is to be borne in mind, however,
that this action will lie only where a grave abuse of discretion or
an act without or in excess of jurisdiction on the part of the 10. The Honorable Arbitrator committed grave error in
voluntary arbitrator is clearly shown. For "the writ of certiorari is granting to Roblecor extra compensation for airduct change
an extra-ordinary remedy and that certiorari jurisdiction is not to in dimension;
be equated with appellate jurisdiction. In a special civil action
of certiorari, the Court will not engage in a review of the facts 11. The Honorable Arbitrator committed grave error in
found nor even of the law as interpreted or applied by the granting to Roblecor extra compensation for airduct
arbitrator unless the supposed errors of fact or of law are so plastering; and
patent and gross and prejudicial as to amount to a grave abuse
of discretion or an exces de pouvoir on the part of the
arbitrator." 21 12. The Honorable Arbitrator committed grave error in
awarding to Roblecor attorney's fees.

Even decisions of administrative agencies which are declared


"final" by law are not exempt from judicial review when so After closely studying the list of errors, as well as petitioners'
warranted. Thus, in the case of Oceanic Bic Division (FFW), et al. discussion of the same in their Motion to Remand Case For
v. Flerida Ruth P. Romero, et al., 22this Court had occasion to rule Further Hearing and Reconsideration and Opposition to Motion
that: for Confirmation of Award, we find that petitioners have amply
made out a case where the voluntary arbitrator failed to apply
the terms and provisions of the Construction Agreement which
. . . Inspite of statutory provisions making forms part of the law applicable as between the parties, thus
"final" the decisions of certain administrative committing a grave abuse of discretion. Furthermore, in granting
agencies, we have taken cognizance of unjustified extra compensation to respondent for several items,
petitions questioning these decisions where he exceeded his powers all of which would have constituted
want of jurisdiction, grave abuse of discretion, ground for vacating the award under Section 24 (d) of the
violation of due process, denial of substantial Arbitration Law.
justice or erroneous interpretation of the
law were brought to our
attention . . . 23 (Emphasis ours).
154
But the respondent trial court's refusal to look into the merits of institutions to subscribe in MMIC and issue guarantee/s for
the case, despite prima facie showing of the existence of foreign loans or deferred payment arrangements secured from
grounds warranting judicial review, effectively deprived the US Eximbank, Asian Development Bank, Kobe Steel, of
petitioners of their opportunity to prove or substantiate their amount not exceeding US$100 Million. 2
allegations. In so doing, the trial court itself committed grave
abuse of discretion. Likewise, the appellate court, in not giving DBP approved guarantees in favor of MMIC and subsequent
due course to the petition, committed grave abuse of discretion. requests for guarantees were based on the unutilized portion of
Respondent courts should not shirk from exercising their power the Government commitment. Thereafter, the Government
to review, where under the applicable laws and jurisprudence, extended accommodations to MMIC in various amounts.
such power may be rightfully exercised; more so where the
objections raised against an arbitration award may properly
constitute grounds for annulling, vacating or modifying said On July 13, 1981, MMIC, PNB and DBP executed a Mortgage Trust
award under the laws on arbitration. Agreement 3 whereby MMIC, as mortgagor, agreed to constitute
a mortgage in favor or PNB and DBP as mortgagees, over all
MMIC's assets; subject of real estate and chattel mortgage
WHEREFORE, the petition is GRANTED. The Resolutions of the executed by the mortgagor, and additional assets described and
Court of Appeals dated October 22, 1990 and December 3, 1990 identified, including assets of whatever kind, nature or
as well as the Orders of respondent Regional Trial Court dated description, which the mortgagor may acquire whether in
July 31, 1990 and August 23, 1990, including the writ of substitution of, in replenishment, or in addition thereto.
execution issued pursuant thereto, are hereby SET ASIDE.
Accordingly, this case is REMANDED to the court of origin for
further hearing on this matter. All incidents arising therefrom are Article IV of the Mortgage Trust Agreement provides for Events
reverted to the status quo ante until such time as the trial court of Default, which expressly includes the event that the
shall have passed upon the merits of this case. No costs.SO MORTGAGOR shall fail to pay any amount secured by this
ORDERED. Mortgage Trust Agreement when due. 4

THIRD DIVISIONG.R. No. 121171 December 29, 1998 Article V of the Mortgage Trust Agreement prescribes in detail,
and in addition to the enumerated events of defaults,
circumstances by which the mortgagor may be declared in
ASSET PRIVATIZATION TRUST, petitioner, default, the procedure therefor, waiver of period to foreclose,
vs. authority of Trustee before, during and after foreclosure,
COURT OF APPEALS, JESUS S. CABARRUS, SR., JESUS S. including taking possession of the mortgaged properties. 5
CABARRUS, JR., JAIME T. CABARRUS, JOSE MIGUEL
CABARRUS, ALEJANDRO S. PASTOR, JR., ANTONIO U.
MIRANDA, and MIGUEL M. ANTONIO, as Minority Stock- In various requests for advances/remittances of loans if huge
Holders of Marinduque Mining and Industrial amounts, Deeds of Undertaking, Promissory Notes, Loan
Corporation, respondents. Documents, Deeds of Real Estate Mortgages, MMIC invariably
committed to pay either on demand or under certain terms the
loans and accommodations secured from or guaranteed by both
KAPUNAN, J.: DBP and PNB.

The petition for review on certiorari before us seeks to reverse By 1984, DBP and PNB's financial both in loans and in equity in
and set aside the decision of the Court of Appeals which denied MMIC had reached tremendous proportions, and MMIC was
due course to the petition for certiorari filed by the Asset having a difficult time meeting its financial obligations. MMIC
Privatization Trust (APT) assailing the order of the Regional Trial had an outstanding loan with DBP in the amount of
Court (RTC) Branch 62, Makati City. The Makati RTC's order P13,792,607,565.92 as of August 31, 1984 and with PNB in the
upheld and confirmed the award made by the Arbitration amount of P8,789,028,249.38 as July 15, 1984 or a total
Committee in favor of Marinduque Mining and Industrial Government expose of Twenty Two Billion Six Hundred Sixty-
Corporation (MMIC) and against the Government, represented
Eight Million Five Hundred Thirty-Seven Hundred Seventy and
by herein petitioner APT for damages in the amount of P2.5 05/100 (P22, 668,537,770.05), Philippine Currency. 6 Thus, a
BILLION (or approximately P4.5 BILLION, including interest). financial restructuring plan (FRP) designed to reduce MMIC's
interest expense through debt conversion to equity was drafted
Ironically, the staggering amount of damages was imposed on by the Sycip Gorres Velayo accounting firm. 7 On April 30, 1984,
the Government for exercising its legitimate right of foreclosure the FRP was approved by the Board of Directors of the
as creditor against the debtor MMIC as a consequence of the MMIC. 8 However, the proposed FRP had never been formally
latter's failure to pay its overdue and unpaid obligation of P22 adopted, approved or ratified by either PNB or DBP. 9
billion to the Philippine National Bank (PNB) and the
Development Bank of the Philippines (DBP). In August and September 1984, as the various loans and
advances made by DBP and PNB to MMIC had become overdue
The antecedent facts and since any restructuring program relative to the loans was no
of the case. longer feasible, and in compliance with the directive of
Presidential Decree No. 385, DBP and PNB as mortgagees of
MMIC assets, decided to exercise their right to extrajudicially
The development, exploration and utilization of the mineral
foreclose the mortgages in accordance with the Mortgage Trust
deposits in the Surigao Mineral Reservation have been
Agreement. 10
authorized by Republic Act No. 1528, as amended by Republic
Acts Nos. 2077 and 4167, by virtue of which laws, a
Memorandum of Agreement was drawn on July 3, 1968, whereby The foreclosed assets were sold to PNB as the lone bidder and
the Republic of the Philippines thru the Surigao Mineral were assigned to three newly formed corporations, namely,
Reservation Board, granted MMIC the exclusive right to explore, Nonoc Mining Corporation, Maricalum Mining and Industrial
develop and exploit nickel, cobalt and other minerals in the Corporation, and Island Cement Corporation. In 1986, these
Surigao mineral reservation. 1 MMIC is a domestic corporation assets were transferred to the Asset Privatization Trust (APT). 11
engaged in mining with respondent Jesus S. Cabarrus, Sr. as
President and among its original stockholders. On February 28, 1985, Jesus S. Cabarrus, Sr., together with the
other stockholders of MMIC, filed a derivative suit against DBP
The Philippine Government undertook to support the financing and PNB before the RTC of Makati, Branch 62, for Annulment of
of MMIC by purchase of MMIC debenture bonds and extension of Foreclosures, Specific Performance and Damages. 12 The suit,
guarantees. Further, the Philippine Government obtained a firm docketed as Civil Case No. 9900, prayed that the court: (1)
commitment form the DBP and/or other government financing annul the foreclosures, restore the foreclosed assets to MMIC,
155
and require the banks to account for their use and operation in 3. Approving the Transformation of the reliefs prayed for [by]
the interim; (2) direct the banks to honor and perform their the plaintiffs in this case into pure money claims; and
commitments under the alleged FRP; and (3) pay moral and
exemplary damages, attorney's fees, litigation expenses and 15
4. The Complaint is hereby DISMISSED.
costs.

The Arbitration Committee was composed of retired Supreme


In the course of the trial, private respondents and petitioner Court Justice Abraham Sarmiento as Chairman, Atty. Jose C.
APT, as successor of the DBP and the PNB's interest in MMIC, Sison and former Court of Appeals Justice Magdangal Elma as
mutually agreed to submit the case to arbitration by entering Members. On November 24, 1993, after conducting several
into a "Compromise and Arbitration Agreement," hearings, the Arbitration Committee rendered a majority
stipulating, inter alia: decision in favor of MMIC, the pertinent portions of which read
as follows:
NOW THEREFORE, for and in consideration of the foregoing
premises and the mutual covenants contained herein the Since, as this Committee finds, there is no foreclosure at all as
parties agree as follows: it was not legally and validly done, the Committee holds and
so declares that the loans of PNB and DBP to MMIC. for the
1. Withdrawal and Compromise. The parties have agreed to payment and recovery of which the void foreclosure sales
withdraw their respective claims from the Trial Court and to were undertaken, continue to remain outstanding and unpaid.
resolve their dispute through arbitration by praying to the Defendant APT as the successor-in-interest of PNB and DBP to
Trial Court to issue a Compromise Judgment based on this the said loans is therefore entitled and retains the right, to
Compromise and Arbitration Agreement. collect the same from MMIC pursuant to, and based on the
loan documents signed by MMIC, subject to the legal and valid
defenses that the latter may duly and seasonably interpose.
In withdrawing their dispute from the court and in choosing
Such loans shall, however, be reduced by the amount which
to resolve it through arbitration, the parties have agreed
APT may have realized from the sale of the seized assets of
that:
MMIC which by agreement should no longer be returned even
if the foreclosures were found to be null and void.
(a) their respective money claims shall be reduced to purely
money claims; and
The documentary evidence submitted and adopted by the
parties (Exhibits "3", "3-B"; Exhibit "100"; and also Exhibit
(b) as successor and assignee of the PNB and DBP interests "ZZZ") as their exhibits would show that the total outstanding
in MMIC and the MMIC accounts, APT shall likewise succeed obligation due to DBP and PNB as of the date of foreclosure is
to the rights and obligations of PNB and DBP in respect of the P22,668,537,770.05, more or less.
controversy subject of Civil Case No. 9900 to be transferred
to arbitration and any arbitral award/order against either PNB
Therefore defendant APT can, and is still entitled to, collect
and/or DBP shall be the responsibility be discharged by and
the outstanding obligations of MMIC to PNB and DBP
be enforceable against APT, the parties having agreed to
amounting to P22,668,537,770.05, more or less, with interest
drop PNB and DBP from the arbitration.
thereon as stipulated in the loan documents from the date of
foreclosure up to the time they are fully paid less the
2. Submission. The parties hereby agree that (a) the proportionate liability of DBP as owner of 87% of the total
controversy in Civil Case No. 9900 shall be submitted instead capitalization of MMIC under the FRP. Simply put, DBP shall
to arbitration under RA 876 and (b) the reliefs prayed for in share in the award of damages to, and in the obligations of,
Civil Case No. 9900 shall, with the approval of the Trial Court MMIC in proportion to its 87% equity in tile total capital stock
of this Compromise and Arbitration Agreement, be of MMIC.
transferred and reduced to pure pecuniary/money claims
with the parties waiving and foregoing all other forms of
xxx xxx xxx
reliefs which they prayed for or should have prayed for in
Civil Case No. 9900. 13
As this Committee holds that the FRP is valid, DBP's equity in
MMIC is raised to 87%. So pursuant to the above provision of
The Compromise and Arbitration Agreement limited the
the Compromise and Arbitration Agreement, the 87% equity
issues to the following:
of DBP is hereby deducted from the actual damages of
P19,486,118,654.00 resulting in the net actual damages of
5. Issues The issues to be submitted for the Committee's P2,531,635,425.02 plus interest.
resolution shall be (a) Whether PLAINTIFFS have the capacity
or the personality to institute this derivative suit in behalf of
DISPOSITION
the MMIC or its directors, (b) Whether or not the actions
leading to, and including,. the PNB-DBP foreclosure of the
MMIC assets were proper, valid and in good WHEREFORE, premises considered, judgment is hereby
faith. 14 rendered:

This agreement was presented for approval to the trial court. 1. Ordering the defendant to pay to the Marinduque Mining
On October 14, 1992, the Makati RTC, Branch 61, issued an and Industrial Corporation, except the DBP, the sum of
order, to wit: P2,531,635,425.02 with interest thereon at the legal rate of
six per cent (6%) per annum reckoned from August 3, 9, and
24, 1984, pari passu, as and for actual damages. Payment of
WHEREFORE, this Court orders:
these actual damages shall be offset by APT from the
outstanding and unpaid loans of MMIC with DBP and PNB,
1. Substituting PNB and DBP with the Asset Privatization which have not been converted into equity. Should there be
Trust as party defendant. any balance due to MMIC after the offsetting, the same shall
be satisfied from the funds representing the purchase price of
2. Approving the Compromise and Arbitration Agreement the sale of the shares of Island Cement Corporation in the
dated October 6, 1997, attached as Annex "C" of the amount of P503,000,000.00 held under escrow pursuant to
Omnibus Motion. the Escrow Agreement dated April 22, 1988 or to such
subsequent escrow agreement that would supercede [sic] it
156
pursuant to paragraph (9) of the Compromise and Arbitration Private respondents filed a "REPLY AND OPPOSITION" dated
Agreement; November 10, 1984, arguing that a dismissal of Civil Case No.
9900 was merely a "qualified dismissal" to pave the way for the
submission of the controversy to arbitration and operated simply
2. Ordering the defendant to pay to the Marinduque Mining
as "a mere suspension of the proceedings" They denied that the
and Industrial Corporation, except the DBP, the sum of
Arbitration Committee had exceeded its powers.
P13,000.000.00, as and for moral and exemplary damages.
Payment of these moral and exemplary damages shall be
offset by APT from the outstanding and unpaid loans of MMIC In an Order dated November 28, 1993, the trial court confirmed
with DBP and PNB, which have not been converted into equity. the award of the Arbitration Committee. The dispositive portion
Should there be any balance due to MMIC after the offsetting, of said order reads:
the same shall be satisfied from the funds representing the
purchase price of the sale of the shares of Island Cement WHEREFORE, premises considered, and in the light of the
Corporation in the amount of P503,000,000.00 held under parties [sic] Compromise and Arbitration Agreement dated
escrow pursuant to the Escrow Agreement dated April 22, October 6, 1992, the Decision of the Arbitration Committee
1988 or to such subsequent escrow agreement that would promulgated on November 24, 1993, as affirmed in a
supercede [sic] it pursuant to paragraph (9) of the Resolution dated July 26, 1994, and finally settled and
Compromise and Arbitration Agreement; clarified in the Separate Opinion dated September 2, 1994 of
Committee Member Elma, and the pertinent provisions of RA
3. Ordering the defendant to pay to the plaintiff, Jesus S. 876, also known as the Arbitration Law, this Court GRANTS
Cabarrus, Sr., the sum of P10,000,000.00, to be satisfied PLAINTIFFS' APPLICATION AND THUS CONFIRMS THE
likewise from the funds held under escrow pursuant to the ARBITRATION AWARD, AND JUDGMENT IS HEREBY
Escrow Agreement dated April 22, 1988 or to such subsequent RENDERED:
escrow agreement that would supersede it, pursuant to
paragraph (9) of the Compromise and Arbitration Agreement, (a) Ordering the defendant APT to the Marinduque Mining
as and for moral damages; and and Industrial Corporation (MMIC), except the DBP, the sum
of P3,811,757,425.00, as and for actual damages, which
4. Ordering the defendant to pay arbitration costs. shall be partially satisfied from the funds held under escrow
in the amount of P503,000,000.00 pursuant to the Escrow
Agreement dated April 22, 1988. The balance of the award,
This Decision is FINAL and EXECUTORY.
after the escrow funds are fully applied, shall be executed
against the APT;
16
IT IS SO ORDERED.

(b) Ordering the defendant to pay to the MMIC, except the


Motions for reconsideration were filed by both parties, but the DBP, the sum of P13,000,000.00 as and for moral and
same were denied. exemplary damages;

On October 17, 1993, private respondents filed in the same Civil (c) Ordering the defendant to pay to Jesus S. Cabarrus, Sr.,
Case No. 9900 an "Application/Motion for Confirmation of the sum of P10,000,000.00 as and for moral damages; and
Arbitration Award." Petitioner countered with an "Opposition and
Motion to Vacate Judgment" raising the following grounds.
(d) Ordering the defendant to pay the herein
plaintiffs/applicants/movants the sum of P1,705,410.23 as
1. The plaintiffs Application/Motion is improperly filed with arbitration costs.
this branch of the Court, considering that the said motion is
neither a part nor the continuation of the proceedings in
In reiteration of the mandates of Stipulation No. 10 and
Civil Case No. 9900 which was dismissed upon motion of
Stipulation No. 8 paragraph 2 of the Compromise and
the parties. In fact, the defendants in the said Civil Case No.
Arbitration Agreement, and the final edict of the Arbitration
9900 were the Development Bank of the Philippines and the
Committee's decision, and with this Court's Confirmation, the
Philippine National Bank (PNB);
issuance of the Arbitration Committee's Award shall
henceforth be final and executory.
2. Under Section 71 of Rep. Act 876, an arbitration under a
contract or submission shall be deemed a special 18
SO ORDERED.
proceedings and a party to the controversy which was
arbitrated may apply to the court having jurisdiction, (not
necessarily with this Honorable Court) for an order On December 27, 1994, petitioner filed its motion for
confirming the award; reconsideration of the Order dated November 28, 1994. Private
respondents, in turn, submitted their reply and opposition
thereto.
3. The issues submitted for arbitration have been limited to
two: (1) propriety of the plaintiffs filing the derivative suit
and (2) the regularity of the foreclosure proceedings. The On January 18, 1995, the trial court handed down its order
arbitration award sought to be confirmed herein, far denying APT's motion for reconsideration for lack of merit and
exceeded the issues submitted and even granted moral for having been filed out of time. The trial court declared that
damages to one of the herein plaintiffs; "considering that the defendant APT, through counsel, officially
and actually received a copy of the Order of this Court dated
November 28, 1994 on December 6, 1994, the Motion for
4. Under Section 24 of Rep. Act 876, the Court must make
Reconsideration thereof filed by the defendant APT on
an order vacating the award where the arbitrators exceeded
December 27, 1994, or after the lapse of 21 days, was clearly
their powers, or so imperfectly executed them, that a
filed beyond the 15-day reglementary period prescribed
mutual, final and definite award upon the subject matter
or provided for by law for the filing of an appeal from final
submitted to them was not made. 17
orders, resolutions, awards, judgments or decisions of any court
in all cases, and by necessary implication for the filing of a
motion for reconsideration thereof."

On February 7, 1995, petitioner received private respondents'


Motion for Execution and Appointment of Custodian of Proceeds
of Execution dated February 6, 1995.
157
Petitioner thereafter filed with the Court of Appeals a special THE COURT OF APPEALS ERRED IN NOT TREATING
civil action for certiorari with temporary restraining order and/or PETITIONER APT'S PETITION FOR CERTIORARI AS AN APPEAL
preliminary injunction dated February 13, 1996 to annul and TAKEN FROM THE ORDER CONFIRMING THE AWARD.
declare as void the Orders of the RTC-Makati dated November
28, 1994 and January 18, 1995 for having been issued without V
or in excess of jurisdiction and/or with grave abuse of
discretion. 19 As ground therefor, petitioner alleged that:
THE COURT OF APPEALS ERRED IN NOT RULING ON THE
LEGAL ISSUE OF WHEN TO RECKON THE COUNTING OF THE
I PERIOD TO FILE A MOTION FOR RECONSIDERATION. 21

THE RESPONDENT JUDGE HAS NOT VALIDLY ACQUIRED The petition is impressed with merit.
JURISDICTION MUCH LESS, HAS THE COURT AUTHORITY, TO
CONFIRM THE ARBITRAL AWARD CONSIDERING THAT THE
ORIGINAL CASE, CIVIL CASE NO. 9900, HAD PREVIOUSLY BEEN I
DISMISSED.
The RTC of Makati, Branch 62, did not have jurisdiction to
II confirm the arbitral award.

THE RESPONDENT JUDGE COMMITTED GRAVE ABUSE OF The use of the term "dismissed" is not "a mere semantic
DISCRETION AND ACTED WITHOUT OR IN EXCESS OF imperfection". The dispositive portion of the Order of the trial
JURISDICTION, IN ISSUING THE QUESTIONED ORDERS court dated October 14, 1992 stated in no uncertain terms:
CONFIRMING THE ARBITRAL AWARD AND DENYING THE
MOTION FOR RECONSIDERATION OF ORDER OF AWARD. 4. The Complaint is hereby DISMISSED. 22

III The term "dismiss" has a precise definition in law. "To


dispose of an action, suit, or motion without trial on the
THE RESPONDENT JUDGE GROSSLY ABUSED HIS DISCRETION issues involved. Conclude, discontinue, terminate,
AND ACTED WITHOUT OR IN EXCESS OF AND WITHOUT quash." 23
JURISDICTION IN RECKONING THE COUNTING OF THE PERIOD
TO FILE MOTION FOR RECONSIDERATION, NOT FROM THE Admittedly, the correct procedure was for the parties to go back
DATE OF SERVICE OF THE COURT'S COPY CONFIRMING THE to the court where the case was pending to have the award
AWARD, BUT FROM RECEIPT OF A XEROX COPY OF WHAT confirmed by said court. However, Branch 62 made
PRESUMABLY IS THE OPPOSING COUNSEL'S COPY THEREOF. 20 the fatal mistake of issuing a final order dismissing the case.
While Branch 62 should have merely suspended the case and
On July 12, 1995, he Court of Appeals, through its Fifth-Division, not dismissed it, 24 neither of the parties questioned said
denied due course and dismissed the petition for certiorari. dismissal. Thus, both parties as well as said court are bound by
such error.

Hence, the instant petition for review on certiorari imputing to


the Court of Appeals the following errors: It is erroneous then to argue, as private respondents do, that
petitioner APT was charged with the knowledge that the "case
was merely stayed until arbitration finished," as again, the order
ASSIGNMENT OF ERRORS of Branch 62 in very clear terms stated that the "complaint was
dismissed." By its own action, Branch 62 had lost jurisdiction
I over the case. It could not have validly reacquired jurisdiction
over the said case on mere motion of one of the parties. The
Rules of Court is specific on how a new case may be initiated
THE COURT OF APPEALS ERRED IN NOT HOLDING THAT THE
and such is not done by mere motion in a particular branch of
MAKATI REGIONAL TRIAL COURT, BRANCH 62 WHICH HAS
the RTC. Consequently, as there was no "pending action" to
PREVIOUSLY DISMISSED CIVIL CASE NO. 9900 HAD LOST
speak of, the petition to confirm the arbitral award should have
JURISDICTION TO CONFIRM THE ARBITRAL AWARD UNDER
been filed as a new case and raffled accordingly to one of the
THE SAME CIVIL CASE AND NOT RULING THAT THE
branches of the Regional Trial Court.
APPLICATION FOR CONFIRMATION SHOULD HAVE BEEN FILED
AS A NEW CASE TO BE RAFFLED OFF AMONG THE DIFFERENT
BRANCHES OF THE RTC. II

II Petitioner was not estopped from questioning the


jurisdiction of Branch 62 of the RTC of Makati.
THE COURT OF APPEALS LIKEWISE ERRED IN HOLDING THAT
PETITIONER WAS ESTOPPED FROM QUESTIONING THE The Court of Appeals ruled that APT was already estopped to
ARBITRATION AWARD, WHEN PETITIONER QUESTIONED THE question the jurisdiction of the RTC to confirm the arbitral award
JURISDICTION OF THE RTC-MAKATI, BRANCH 62 AND AT THE because it sought affirmative relief in said court by asking that
SAME TIME MOVED TO VACATE THE ARBITRAL AWARD. the arbitral award be vacated.

III The rule is that "Where the court itself clearly has no jurisdiction
over the subject matter or the nature of the action, the
invocation of this defense may be done at any time. It is neither
THE COURT OF APPEALS ERRED IN NOT HOLDING THAT THE
for the courts nor for the parties to violate or disregard that rule,
RESPONDENT TRIAL COURT SHOULD HAVE EITHER
let alone to confer that jurisdiction this matter being legislative
DISMISSED/DENIED PRIVATE RESPONDENTS'
in character." 25 As a rule then, neither waiver nor estoppel shall
MOTION/PETITION FOR CONFIRMATION OF ARBITRATION
apply to confer jurisdiction upon a court barring highly
AWARD AND/OR SHOULD HAVE CONSIDERED THE MERITS OF
meritorious and exceptional circumstances. 26 One such
THE MOTION TO VACATE ARBITRAL AWARD.
exception was enunciated in Tijam vs. Sibonghanoy, 27 where it
was held that "after voluntarily submitting a cause and
IV encountering an adverse decision on the merits, it is too late for
the loser to question the jurisdiction or power of the court."
158
Petitioner's situation is different because from the outset, it has judgment of the arbitrators, are insufficient to invalidate an
consistently held the position that the RTC, Branch 62 had no award fairly and honestly made. 32 Judicial review of an
jurisdiction to confirm the arbitral award; consequently, it arbitration is thus, more limited than judicial review of a trial. 33
cannot be said that it was estopped from questioning the RTC's
jurisdiction. Petitioner's prayer for the setting aside of the Nonetheless, the arbitrators' award is not absolute and without
arbitral award was not inconsistent with its disavowal of the exceptions. The arbitrators cannot resolve issues beyond the
court's jurisdiction. scope of the submission agreement. 34 The parties to such an
agreement are bound by the arbitrators' award only to the
III extent and in the manner prescribed by the contract and only if
the award is rendered in conformity thereto. 35 Thus, Sections 24
and 25 of the Arbitration Law provide grounds for vacating,
Appeal of petitioner to the Court of Appeals thru certiorari under
rescinding or modifying an arbitration award. Where the
Rule 65 was proper.
conditions described in Articles 2038, 36
2039, 37 and 1040 38 of the Civil Code applicable to compromises
The Court of Appeals in dismissing APT's petition and arbitration are attendant, the arbitration award may also be
for certiorari upheld the trial court's denial of APT's motion for annulled.
reconsideration of the trial court's order confirming the arbitral
award, on the ground that said motion was filed beyond the 15- 39
In Chung Fu Industries (Phils.) vs. Court of Appeals, we held:
day reglementary period; consequently, the petition
for certiorari could not be resorted to as substitute to the lost
right of appeal. . . . . It is stated explicitly under Art. 2044 of the Civil Code that
the finality of the arbitrators' award is not absolute and without
exceptions. Where the conditions described in Articles 2038,
We do not agree.
2039 and 2040 applicable to both compromises and arbitrations
are obtaining, the arbitrator's award may be annulled or
28
Section 99 of Republic Act No. 876, provides that: rescended. Additionally, under Sections 24 and 25 of the
Arbitration Law, there are grounds for vacating, modifying or
. . . An appeal may be taken from an order rescinding an arbitrator's award. Thus, if and when the factual
made in a proceeding under this Act, or from a circumstances referred to the above-cited provisions are
judgment entered upon an award present, judicial review of the award is properly warranted.
through certiorari proceedings, but such
appeals shall be limited to questions of According, Section 20 of R.A. 876 provides:
law. . . ..

Sec. 20. Form and contents of award. The award must be


The aforequoted provision, however, does not preclude a party made in writing and signed and acknowledge by a majority of
aggrieved by the arbitral award from resorting to the the arbitrators, if more than one; and by the sole arbitrator, if
extraordinary remedy of certiorari under Rule 65 of the Rules of there is only only. Each party shall be furnished with a copy of
Court where, as in this case, the Regional Trial Court to which the award. The arbitrators in their award may grant any remedy
the award was submitted for confirmation has acted without or relief which they deem just and equitable and within the
jurisdiction or with grave abuse of discretion and there is no scope of the agreement of the parties, which shall include, but
appeal, nor any plain, speedy remedy in the course of law. not be limited to, the specific performance of a contract.

Thus, Section 1 of Rule 65 provides: xxx xxx xxx

Sec 1. Petition for Certiorari: When any tribunal, The arbitrators shall have the power to decide only those
board or officer exercising judicial functions, has acted without matters which have been submitted to them. The terms of the
or in excess of its or his jurisdiction, or with grave abuse of award shall be confined to such disputes. (Emphasis ours).
discretion and there is no appeal, nor any plain, speed, and
adequate remedy in the ordinary course of law, a person
xxx xxx xxx
aggrieved thereby may file a verified petition in the proper court
alleging the facts with certainty and praying that judgment be
rendered annulling or modifying the proceedings, as the law Sec. 24 of the same law enumerating the grounds for vacating
requires, of such tribunal, board or officer. an award states:

In the instant case, the respondent court erred in dismissing the Sec. 24. Grounds for vacating award. In any one of the
special civil action for certiorari, it being clear from the following cases, the court must make an order vacating the
pleadings and the evidence that the trial court lacked award upon the petition of any party to the controversy
jurisdiction and/or committed grave abuse of discretion in taking when such party proves affirmatively that in the arbitration
cognizance of private respondents' motion to confirm the proceeding:
arbitral award and, worse, in confirming said award which is
grossly and patently not in accord with the arbitration (a) The award was procured by corruption, fraud, or other
agreement, as will be hereinafter demonstrated. undue means; or

IVThe nature and limits of the Arbitrators' power. (b) That there was evident partiality or corruption in the
arbitrators or any of them; or
As a rule, the award of an arbitrator cannot be set aside for
mere errors of judgment either as to the law or as to the (c) That the arbitrators were guilty of misconduct in refusing
facts. 29 Courts are without power to amend or overrule merely to postpone the hearing upon sufficient cause shown, or in
because of disagreement with matters of law or facts refusing to hear evidence pertinent and material to the
determined by the arbitrators. 30 They will not review the controversy; that one or more of the arbitrators was
findings of law and fact contained in an award, and will not disqualified to act as such under section nine hereof, and
undertake to substitute their judgment for that of the willfully refrained from disclosing such disqualifications or
arbitrators, since any other rule would make an award the any other misbehavior by which the rights of any party
commencement, not the end, of litigation. 31 Errors of law and have been materially prejudiced; or
fact, or an erroneous decision of matters submitted to the
159
(d) That the arbitrators exceeded their powers, or so foreclosure. Cabarrus, who filed this case supposedly in
imperfectly executed them, that a mutual, final and definite behalf of MMIC should have insisted on the FRP. Yet Cabarrus
award upon the subject matter submitted to them was not himself opposed the FRP;
made. (Emphasis ours)
4. So when PNB-DBP proceeded with the foreclosure, it was
xxx xxx xxx. done without bad faith but with the honest and sincere belief
that foreclosure was the only alternative; a decision further
explained by Dr. Placido Mapa who testified that foreclosure
Section 25 which enumerates the grounds for modifying the
was, in the judgment of PNB, the best move to save MMIC
award provides:
itself.

Sec. 25. Grounds for modifying or correcting award In


Q : Now in this portion of Exh. "L" which was marked as Exh.
anyone of the following cases, the court must make an
"L-1", and we adopted as Exh. 37-A for the respondent, may I
order modifying or correcting the award, upon the
know from you, Dr. Mapa what you meant by "that the
application of any party to the controversy which was
decision to foreclose was neither precipitate nor arbitrary"?
arbitrated:

A : Well, it is not a whimsical decision but rather decision


(a) Where there was an evident miscalculation of figures, or
arrived at after weighty consideration of the information that
an evident mistake in the description of any person, thing or
we have received, and listening to the prospects which
property referred to in the award; or
reported to us that what we had assumed would be the
premises of the financial rehabilitation plan was not
(b) Where the arbitrators have awarded upon a matter not materialized nor expected to materialize.
submitted to them, not affecting the merits of the decision
upon the matter submitted; or
Q : And this statement that "it was premised upon the known
fact" that means, it was referring to the decision to foreclose,
(c) Where the award is imperfect in a matter of form not was premised upon the known fact that the rehabilitation
affecting the merits of the controversy, and if it had been a plan earlier approved by the stockholders was no longer
commissioner's report, the defect could have been feasible, just what is meant "by no longer feasible"?
amended or disregarded by the court.

A : Because the revenue that they were counting on to make


xxx xxx xxx the rehabilitation plan possible, was not anymore expected
to be forthcoming because it will result in a short fall
Finally, it should be stressed that while a court is precluded from compared to the prices that were actually taking place in the
overturning an award for errors in the determination of factual market.
issues, nevertheless, if an examination of the record reveals no
support whatever for the arbitrators determinations, their award Q : And I suppose that was what you were referring to when
must be vacated. 40 in the same manner, an award must be you stated that the production targets and assumed prices of
vacated if it was made in "manifest disregard of the law." 41 MMIC's products, among other projections, used in the
financial reorganization program that will make it viable were
Against the backdrop of the foregoing provisions and principles, not met nor expected to be met?
we find that the arbitrators came out with an award in excess of
their powers and palpably devoid of factual and legal basis. A : Yes.

V xxx xxx xxx

There was no financialM structuring program: foreclosure of Which brings me to my last point in this separate opinion.
mortgage was fully justified. Was PNB and DBP absolutely unjustified in foreclosing the
mortgages?
The point need not be belabored that PNB and DBP had the
legitimate right to foreclose of the mortgages of MMIC whose In this connection, it can readily be seen and it cannot quite
obligations were past due. The foreclosure was not a wrongful be denied that MMIC accounts in PNB-DBP were past due.
act of the banks and, therefore, could not be the basis of any The drawing up of the FRP is the best proof of this. When
award of damages. There was no financial restructuring MMIC adopted a restructuring program for its loan, it only
agreement to speak of that could have constituted an meant that these loans were already due and unpaid. If
impediment to the exercise of the banks' right to foreclose. these loans were restructurable because they were already
due and unpaid, they are likewise "forecloseable". The option
As correctly stated by Mr. Jose C. Sison, a member of the is with the PNB-DBP on what steps to take.
Arbitration Committee who wrote a separate opinion:
The mere fact that MMIC adopted the FRP does not mean
1. The various loans and advances made by DBP and PNB to that DBP-PNB lost the option to foreclose. Neither does it
MMIC have become overdue and remain unpaid. The fact mean that the FRP is legally binding and implementable. It
that a FRP was drawn up is enough to establish that MMIC must be pointed that said FRP will, in effect, supersede the
has not been complying with the terms of the loan existing and past due loans of MMIC with PNB-DBP. It will
agreement. Restructuring simply connotes that the become the new loan agreement between the lenders and
obligations are past due that is why it is "restructurable"; the borrowers. As in all other contracts, there must therefore
be a meeting of minds of the parties; the PNB and DBP must
have to validly adopt and ratify such FRP before they can be
2. When MMIC thru its board and the stockholders agreed bound by it; before it can be implemented. In this case, not
and adopted the FRP, it only means that MMIC had been an iota of proof has been presented by the PLAINTIFFS
informed or notified that its obligations were past due and showing that PNB and DBP ratified and adopted the FRP.
that foreclosure is forthcoming; PLAINTIFFS simply relied on a legal doctrine of promissory
estoppel to support its allegations in this regard. 42
3. At that stage, MMIC also knew that PNB-DBP had the
option of either approving the FRP or proceeding with the
160
Moreover, PNB and DBP had to initiate foreclosure proceedings consider appropriate for the purpose of setting an example
as mandated by P.D. No. 385, which took effect on January 31, for the public good, attorney's fees and litigation expenses in
1974. The decree requires government financial institutions to such amounts as may be proven during the trial, and the
foreclose collaterals for loans where the arrearages amount to costs legally taxable in this litigation.
20% of the total outstanding obligations. The pertinent
provisions of said decree read as follow: Further, plaintiffs pray for such other reliefs as may be just
and equitable in the premises. 44
Sec. 1. It shall be mandatory for government financial
institutions, after the lapse of sixty (60) days from the Upon submission for arbitration, the Compromise and
issuance of this Decree, to foreclose the collaterals and/or Arbitration Agreement of the parties clearly and explicitly
securities for any loan, credit, accommodation, and/or defined and limited the issues to the following:
guarantees granted by them whenever the arrearages on
such account, including accrued interest and other charges,
amount to at least twenty percent (20%) of the total (a) whether PLAINTIFFS have the capacity or the personality
outstanding obligations, including interest and other charges, to institute this derivative suit in behalf of the MMIC or its
as appearing in the books of account and/or related records directors;
of the financial institutions concerned. This shall be without
prejudice to the exercise by the government financial (b) whether or not the actions leading to, and including, the
institutions of such rights and/or remedies available to them PNB-DBP foreclosure of the MMIC assets were proper, valid
under their respective contracts with their debtors, including and in good faith. 45
the right to foreclosure on loans, credits, accommodations
and/or guarantees on which the arrearages are less than
Item No. 8 of the Agreement provides for the period by which
twenty percent (20%).
the Committee was to render its decision, as well as the
nature thereof:
Sec. 2. No restraining order temporary or permanent
injunction shall be issued by the court against any
8. Decision. The committee shall issue a decision on the
government financial institution in any action taken by such
controversy not later than six (6) months from the date of its
institution in compliance with the mandatory foreclosure
constitution.
provided in Section 1 hereof, whether such restraining order,
temporary or permanent injunction is sought by the
borrower(s) or any third party or parties, except after due In the event the committee finds that PLAINTIFFS have the
hearing in which it is established by the borrower and personality to file this suit and the extra-judicial foreclosure
admitted by the government financial institution concerned of the MMIC assets wrongful, it shall make an award in favor
that twenty percent (20%) of the outstanding arrearages has of the PLAINTIFFS (excluding DBP), in an amount as may be
been paid after the filing of foreclosure proceedings. established or warranted by the evidence which shall be
(Emphasis supplied.) payable in Philippine Pesos at the time of the award. Such
award shall be paid by the APT or its successor-in-interest
within sixty (60) days from the date of the award in
Private respondents' thesis that the foreclosure proceedings
accordance with the provisions of par. 9 hereunder. . . . . The
were null and void because of lack of publication in the
PLAINTIFFS' remedies under this Section shall be in addition
newspaper is nothing more than a mere unsubstantiated
to other remedies that may be available to the PLAINTIFFS,
aliegation not borne out by the evidence. In any case, a
all such remedies being cumulative and not exclusive of each
disputable presumption exists in favor of petitioner that official
other.
duty has been regularly performed and ordinary course of
business has been followed. 43
On the other hand, in case the arbitration committee finds
that PLAINTIFFS have no capacity to sue and/or that the
VI
extra-judicial foreclosure is valid and legal, it shall also make
an award in favor of APT based on the counterclaims of DBP
Not only was the foreclosure rightfully exercised by the PNB and and PNB in an amount as may be established or warranted
DBP, but also, from the facts of the case, the arbitrators in by the evidence. This decision of the arbitration committee in
making the award went beyond the arbitration agreement. favor of APT shall likewise finally settle all issues regarding
the foreclosure of the MMIC assets so that the funds held in
In their complaint filed before the trial court, private respondent escrow mentioned in par. 9 hereunder will thus be released
Cabarrus, et al. prayed for judgment in their favor: in full in favor of
APT. 46

1. Declaring the foreclosures effected by the defendants DBP


and PNB on the assets of MMIC null and void and directing The clear and explicit terms of the submission notwithstanding,
said defendants to restore the foreclosed assets to the the Arbitration Committee clearly exceeded its powers or so
possession of MMIC, to render an accounting of their use imperfectly executed them: (a) in ruling on and declaring valid
and/or operation of said assets and to indemnify MMIC for the FRP; (b) in awarding damages to MMIC which was not a
the loss occasioned by its dispossession or the deterioration party to the derivative suit; and (c) in awarding moral damages
thereof; to Jesus S. Cabarrus, Sr.

2. Directing the defendants DBP and PNB to honor and The arbiters overstepped their powers by declaring as valid the
perform their commitments under the financial proposed Financial Restructuring Program.
reorganization plan which was approved at the annual
stockholders' meeting of MMIC on 30 April 1984; The Arbitration Committee went beyond its mandate and thus
acted in excess of its powers when it ruled on the validity of,
3. Condemning the defendants DBP and PNB, jointly and and gave effect to, the proposed FRP.
severally to pay the plaintiffs actual damages consisting of
the loss of value of their investments amounting to not less In submitting the case to arbitration, the parties had mutually
than P80,000,000, the damnum emergens and lucrum agreed to limit the issue to the "validity of the foreclosure" and
cessans in such amount as may be established during the to transform the relief prayed for therein into pure money
trial, moral damages in such amount as this Honorable Court claims.
may deem just and equitable in the premises, exemplary
damages in such amount as this Honorable Court may
161
There is absolutely no evidence that the DBP and PNB agreed, into a debt-for-equity swap. And if they had such authority, there
expressly or impliedly, to the proposed FRP. It cannot be was no showing that the banks, through their board of directors,
overemphasized that a FRP, as a contract, requires the consent had ratified the FRP.
of the parties thereto. 47 The contract must bind both
contracting parties. 48 Private respondents even by their own Further, how could the MMIC be entitled to a big amount of
admission recognized that the FRP had yet not been carried out moral damages when its credit reputation was not exactly
and that the loans of MMIC had not yet been converted into something to be considered sound and wholesome. Under
equity. 49 Article 2217 of the Civil Code, moral damages include
besmirched reputation which a corporation may possibly suffer.
However, the Arbitration Committee not only declared the FRP A corporation whose overdue and unpaid debts to the
valid and effective, but also converted the loans of MMIC into Government alone reached a tremendous amount of P22 Billion
equity raising the equity of DBP to 87%. 50 Pesos cannot certainly have a solid business reputation to brag
about. As Atty. Sison in his separate opinion persuasively put it:
The Arbitration Committee ruled that there was "a commitment
to carry out the FRP" 51 on the ground of promissory estoppel. Besides, it is not yet a well settled jurisprudence that
corporations are entitled to moral damages. While the Supreme
Court may have awarded moral damages to a corporation for
Similarly, the principle of promissory estoppel applies in the
besmirched reputation in Mambulao vs. PNB, 22 SCRA 359, such
present case considering as we observed, the fact that the
ruling cannot find application in this case. It must be pointed out
government (that is, Alfredo Velayo) was the FRP's
that when the supposed wrongful act of foreclosure was done,
proponent. Although the plaintiffs are agreed that the
MMIC's credit reputation was no longer a desirable one. The
government executed no formal agreement, the fact
company then was already suffering from serious financial crisis
remains that the DBP itself which made representations that
which definitely projects an image not compatible with good and
the FRP constituted a "way out" for MMIC. The Committee
wholesome reputation. So it could not be said that there was a
believes that although the DBP did not formally agree
"reputation" besmirched by the act of foreclosure. 55
(assuming that the board and stockholders' approvals were
not formal enough), it is bound nonetheless if only for its
conspicuous representations. The arbiters exceeded their

Although the DBP sat in the board in a dual capacity as authority in awarding damages
holder of 36% of MMIC's equity (at that time) and as MMIC's
creditor the DBP can not validly renege on its to MMIC, which is not impleaded
commitments simply because at the same time, it held
interests against the MMIC.
as a party to the derivative suit.

The fact, of course, is that as APT itself asserted, the FRP


was being "carried out" although apparently, it would Civil Case No. 9900 filed before the RTC being a derivative suit,
supposedly fall short of its targets. Assuming that the FRP MMIC should have been impleaded as a party. It was not joined
would fail to meet its targets, the DBP and so this as a party plaintiff or party defendant at any stage of the
Committee holds can not, in any event, brook any denial proceedings. As it is, the award of damages to MMIC, which was
that it was bound to begin with, and the fact is that not a party before the Arbitration Committee, is a complete
adequate or not (the FRP), the government is still bound by nullity.
virtue of its acts.
Settled is the doctrine that in a derivative suit, the corporation is
The FRP, of course, did not itself promise a resounding the real party in interest while the stockholder filing suit for the
success, although it raised DBP's equity in MMIC to 87%. It corporation's behalf is only a nominal party. The corporation
is not an excuse, however, for the government to deny its should be included as a party in the suit.
commitments. 52
An individual stockholder is permitted to institute a derivative
Atty. Sison, however, did not agree and correctly observed suit on behalf of the corporation wherein he holds stock in
that: order to protect or vindicate corporate rights, whenever the
officials of the corporation refuse to sue, or are the ones to be
sued or hold the control of the corporation. In such actions,
But the doctrine of promissory estoppel can hardly find the suing stockholder is regarded as a nominal party, with the
application here. The nearest that there can be said of any corporation as the real party in interest. . . . . 56
estoppel being present in this case is the fact that the board
of MMIC was, at the time the FRP was adopted, mostly
composed of PNB and DBP representatives. But those It is a condition sine qua non that the corporation be
representatives, singly or collectively, are not themselves impleaded as a party because
PNB or DBP. They are individuals with personalities separate
and distinct from the banks they represent. PNB and DBP . . . Not only is the corporation an indispensable party, but it is
have different boards with different members who may also the present rule that it must be served with process. The
have different decisions. It is unfair to impose upon them reason given is that the judgment must be made binding upon
the decision of the board of another company and thus pin the corporation in order that the corporation may get the
them down on the equitable principle of estoppel. Estoppel benefit of the suit and may not bring a subsequent suit
is a principle based on equity and it is certainly not against the same defendants for the same cause of action. In
equitable to apply it in this particular situation. Otherwise other words the corporation must be joined as party because
the rights of entirely separate distinct and autonomous it is its cause of action that is being litigated and because
legal entities like PNB and DBP with thousands of judgment must be a res ajudicata against it. 57
stockholders will be suppressed and rendered nugatory. 53

The reasons given for not allowing direct individual suit are:
As a rule, a corporation exercises its powers, including the
power to enter into contracts, through its board of directors.
(1) . . . "the universally recognized doctrine that a stockholder
While a corporation may appoint agents to enter into a contract
in a corporation has no title legal or equitable to the corporate
in its behalf, the agent should not exceed his authority. 54 In the
property; that both of these are in the corporation itself for
case at bar, there was no showing that the representatives of
the benefit of the stockholders." In other words, to allow
PNB and DBP in MMIC even had the requisite authority to enter
162
shareholders to sue separately would conflict with the asking for moral damages which he failed to get from the earlier
separate corporate entity principle; case. 62 Worse, private respondents violated the rule against
non-forum shopping.
(2) . . . that the prior rights of the creditors may be prejudiced.
Thus, our Supreme Court held in the case of Evangelista v. It is a basic postulate that a corporation has a personality
Santos, that "the stockholders may not directly claim those separate and distinct from its stockholders. 63 The properties
damages for themselves for that would result in the foreclosed belonged to MMIC, not to its stockholders. Hence, if
appropriation by, and the distribution among them of part of wrong was committed in the foreclosure, it was done against the
the corporate assets before the dissolution of the corporation corporation. Another reason is that Jesus S. Cabarrus, Sr. cannot
and the liquidation of its debts and liabilities, something which directly claim those damages for himself that would result in the
cannot be legally done in view of section 16 of the appropriation by, and the distribution to, him part of the
Corporation Law . . .; corporation's assets before the dissolution of the corporation
and the liquidation of its debts and liabilities. The Arbitration
Committee, therefore, passed upon matters nor submitted to it.
(3) the filing of such suits would conflict with the duty of the
Moreover, said cause of action had already been decided in a
management to sue for the protection of all concerned;
separate case. It is thus quite patent that the arbitration
committee exceeded the authority granted to it by the parties'
(4) it would produce wasteful multiplicity of suits; and Compromise and Arbitration Agreement by awarding moral
damages to Jesus S. Cabarrus, Sr.
(5) it would involve confusion in a ascertaining the effect of
partial recovery by an individual on the damages recoverable Atty. Sison, in his separate opinion, likewise expressed
by the corporation for the same act. 58 befuddlement to the award of moral damages to Jesus S.
Cabarrus, Sr.:
If at all an award was due MMIC, which it was not, the same
should have been given sans deduction, regardless of whether It is clear and it cannot be disputed therefore that based
or not the party liable had equity in the corporation, in view of on these stipulated issues, the parties themselves
the doctrine that a corporation has a personality separate and have agreed that the basic ingredient of the causes of
distinct from its individual stockholders or members. DBP's action in this case is the wrong committed on the
alleged equity, even if it were indeed 87%, did not give it corporation (MMIC) for the alleged illegal foreclosure of its
ownership over any corporate property, including the monetary assets. By agreeing to this
award, its right over said corporate property being a mere stipulation, PLAINTIFFS themselves (Cabarrus, et al.) admit
expectancy or inchoate right. 59 Notably, the stipulation even that the cause of action pertains only to the corporation
had the effect of prejudicing the other creditors of MMIC. (MMIC) and that they are filing this for and in behalf of
MMIC.
The arbiters, likewise, exceeded their authority in awarding
moral damages to Jesus Cabarrus, Sr. Perforce this has to be so because it is the basic rule in
Corporation Law that "the shareholders have no title, legal
It is perplexing how the Arbitration Committee can in one breath or equitable to the property which is owned by the
rule that the case before it is a derivative suit, in which the corporation (13 Am. Jur. 165; Pascual vs. Oresco, 14 Phil.
aggrieved party or the real party in interest is supposedly the 83). In Ganzon & Sons vs. Register of Deeds, 6 SCRA 373,
MMIC, and at the same time award moral damages to an the rule has been reiterated that "a stockholder is not the
individual stockholder, to wit: co-owner of corporate property." Since the property or
assets foreclosed belongs [sic] to MMIC, the wrong
committed, if any, is done against the corporation. There
WHEREFORE, premises considered, judgment is therefore no direct injury or direct violation of the rights
is hereby rendered: of Cabarrus et al. There is no way, legal or equitable, by
which Cabarrus et al. could recover damages in their
xxx xxx xxx personal capacities even assuming or just because the
foreclosure is improper or invalid. The Compromise and
Arbitration Agreement itself and the elementary principles
3. Ordering the defendant to pay to the plaintiff, Jesus S.
of Corporation Law say so. Therefore, I am constrained to
Cabarrus, Sr., the sum of P10,000,000.00, to be satisfied
dissent from the award of moral damages to Cabarrus. 64
likewise from the funds held under escrow pursuant to the
Escrow Agreement dated April 22, 1988 or to such subsequent
escrow agreement that would supersede it, pursuant to From the foregoing discussions, it is evident that, not only did
paragraph (9), Compromise and Arbitration Agreement, as and the arbitration committee exceed its powers or so imperfectly
for moral damages; . . . 60 execute them, but also, its findings and conclusions are palpably
devoid of any factual basis, and in manifest disregard of the law.
The majority decision of the Arbitration Committee sought to
justify its award of moral damages to Jesus S. Cabarrus, Sr. by We do not find it necessary to remand this case to the RTC for
pointing to the fact that among the assets seized by the appropriate action. The pleadings and memoranda filed with this
government were assets belonging to Industrial Enterprise Inc. Court, as well as in the Court of Appeals, raised and extensively
(IEI), of which Cabarrus is the majority stockholder. It then discussed the issues on the merits. Such being the case, there is
acknowledged that Cabarrus had already recovered said assets sufficient basis for us to resolve the controversy between the
in the RTC, but that "he won no more than actual damages. parties anchored on the records and the pleadings before us. 65
While the Committee cannot possibly speak for the RTC, there is
no doubt that Jesus S. Cabarrus, Sr., suffered moral damages on WHEREFORE, the Decision of the Court of Appeals dated July 17,
account of that specific foreclosure, damages the Committee 1995, as well as the Orders of the Regional Trial Court of Makati,
believes and so holds, he, Jesus S. Cabarrus, Sr., may be Branch 62, dated November 28, 1994 and January 19, 1995, is
awarded in this proceeding." 61 hereby REVERSED and SET ASIDE, and the decision of the
Arbitration Committee is hereby VACATED.SO ORDERED.
Cabarrus cause of action for the seizure of the assets belonging
to IEI, of which he is the majority stockholder, having been SECOND DIVISIONG.R. No. 196723 August 28,
ventilated in a complaint he previously filed with the RTC, from 2013
which he obtained actual damages, he was barred by res
judicata from filing a similar case in another court, this time
163
ASIAN CONSTRUCTION AND DEVELOPMENT The Proceedings Before the Arbitral Tribunal
CORPORATION, Petitioner,
vs. On September 2, 2008, Asian Construction filed a
SUMITOMO CORPORATION, Respondent. complaint22 with the CIAC, docketed as CIAC Case No. 28-2008,
seeking payment for its alleged losses and reimbursements
PERLAS-BERNABE, J.: amounting to US$9,501,413.13, plus attorneys fees in the
amount of P2,000,000.00.23 As a matter of course, an Arbitral
Tribunal was constituted, with Alfredo F. Tadiar being designated
Before the Court are consolidated petitions for review on
as Chairman, and Salvador P. Castro and Jesse B. Grove as
certiorari which assail separate issuances of the Court of
Members.24
Appeals (C A) in relation to the partial and final awards rendered
by the Construction Industry Arbitration Commission's (CIAC)
Arbitral Tribunal (Arbitral Tribunal) in CIAC Case No. 28-2008. For its part, Sumitomo filed a Motion to Dismiss,25 questioning
the CIACs jurisdiction over the dispute on the ground that the
arbitration should proceed in accordance with the Commercial
In particular, the petition in G.R. No. 196723 1 filed by Asian
Arbitration Rules of Japan.26 However, the aforesaid motion was
Construction and Development Corporation (Asian Construction)
denied.27 As such, Sumitomo filed an Answer,28 reiterating the
seeks to annul and set aside the CAs Resolutions dated July 23,
CIACs alleged lack of jurisdiction and further asserting that the
20102 and April 18, 20113 in CA-G.R. SP No. 112127 which
claim was already time-barred. It added that had Asian
dismissed its appeal from the Arbitral Tribunals Partial
Construction discharged its obligations under the Agreement to
Award4 dated December 15, 2009 (Partial Award) on the ground
itemize and justify its claims, the same could have been
of forum shopping; while the petition in G.R. No. 196728 5 filed
amicably settled years ago. In this respect, it made a
by Sumitomo Corporation (Sumitomo) seeks to annul and set
counterclaim for the unutilized portion of the advance
aside the CAs Decision6 dated January 26, 2011 and
payments, attorneys fees and costs of litigation in the amount
Resolution7dated April 29, 2011 in CA-G.R. SP No. 113828 which
of at least P10,000,000.00.29
modified the Arbitral Tribunals Final Award 8 dated March 17,
2010 (Final Award) by way of deleting the award of attorneys
fees in Sumitomos favor. Subsequently, the parties signed a TOR,30 stipulating the
admitted facts and defining the issues to be determined in the
arbitration proceedings.
The Facts

On December 15, 2009, the Arbitral Tribunal rendered the Partial


On March 15, 1996, Asian Construction entered into a Civil Work
Award31 which affirmed its jurisdiction over the dispute but held
Agreement9 (Agreement) with Sumitomo for the construction of
that the parties were bound by their Agreement that the
a portion of the Light Rail Transit System along the Epifanio
substantive New York State Law shall apply in the resolution of
Delos Santos Avenue, specifically, from Shaw Boulevard,
the issues.32 It proceeded to dismiss both the claims and
Mandaluyong City to Taft Avenue, Pasay City for a total cost of
counterclaims of the parties on the ground that these had
US$19,982,000.00 (Project).10 The said Agreement provides that
already prescribed under New York State Laws six-year statute
the "validity, interpretation, enforceability, and performance of
of limitations33 and ruled that, in any case, were it to resolve the
the same shall be governed by and construed in accordance
same on the merits, "it would not produce an affirmative
with the law of the State of New York, U.S.A. (New York State
recovery for the claimant." 34
Law), without regard to, or legal effect of, the conflicts of law
provisions thereof"11 and that any dispute, controversy or claim
arising therefrom "shall be solely and finally settled by Aggrieved, Asian Construction filed before the CA, on January 5,
arbitration."12 2010, a Rule 43 Petition for Review,35 docketed as CA-G.R. SP
No. 112127 (First CA Petition), seeking the reversal of the Partial
Award.
In May 1996, Sumitomo paid Asian Construction the amount of
US$2,997,300.00 as advance payment to be recovered in
accordance with the terms of the Agreement. Later, an Meanwhile, notwithstanding its dismissal of the claims and
additional advance payment of US$1,998,200.00 was made in counterclaims, the Arbitral Tribunal further directed the parties
October 1997.13 In all, Asian Construction received from to itemize their respective claims for costs and attorneys fees
Sumitomo the amount of US$9,731,606.62, inclusive of the and to submit factual proof and legal bases for their entitlement
advance payments (before withholding tax of US$97,308.44). 14 thereto.36 Pursuant to this directive, Sumitomo submitted
evidence to prove the costs it had incurred and paid as a result
of the arbitration proceedings.37 Asian Construction, on the other
On September 1, 1998, Sumitomo informed Asian Construction
hand, did not present any statement or document to
that it was terminating the Agreement effective September 5,
substantiate its claims but, instead, submitted an
1998 due to the following reasons: (a) Asian Constructions
Opposition38 dated March 8, 2010 (opposition) to Sumitomos
failure "to perform and complete the civil work for Notice to
claim for costs. The Arbitral Tribunal did not act upon the
Proceed issued construction areas within the duration of the
opposition because it was treated, in effect, as a motion for
Time Schedule in the Contract Specification of Civil and
reconsideration which was prohibited under the CIAC Revised
Architectural Works (Station No. 8 to Station No. 13) x x x"; (b)
Rules of Procedure Governing Construction Arbitration (CIAC
Asian Constructions failure to "provide adequate traffic
Revised Rules).39
management as required in the Scope of Works pursuant to
subparagraph 5.2.4 of the Contract Specification of Civil and
Architectural Work"; and (c) Asian Constructions failure to "pay On March 17, 2010, the Arbitral Tribunal rendered the Final
the suppliers of certain materials and equipment used in the Award40 which granted Sumitomos claim for attorneys fees in
construction of the Project in violation of paragraph 3.1.3, Article the amount of US$200,000.00. It held that while the filing of the
3 of the Agreement." 15 In view of the foregoing, Sumitomo arbitration suit cannot be regarded as "clearly unfounded"
requested Asian Construction to "make the necessary because of the two progress billings that were left unpaid, Asian
arrangements for the proper turnover of the Project x x Constructions disregard of the Agreement to have the dispute
x."16 Asian Construction, however, claimed that the resolved in accordance with New York State Law had forced
accomplishments under Progress Billing No. (PB) 01817 dated Sumitomo to incur attorneys fees in order to defend its
June 10, 1998 and PB 019 18 dated July 6, 1998, as well as other interest.41 It further noted that if Asian Construction had
various claims, were still left unpaid. 19 Hence, on December 22, accepted the settlement offered by Sumitomo, then, the
1998, it sent Sumitomo a letter, 20 demanding payment of the arbitration proceedings would have even been aborted.42On the
total amount of US$6,371,530.89. This was followed by several other hand, a similar claim for attorneys fees made by Asian
correspondences between the parties through 1999 to 2007 but Construction was denied by reason of the latters failure to
no settlement was achieved.21 submit, as directed, proof of its entitlement thereto. 43 As to the
164
matter of costs, the Arbitral Tribunal declared Sumitomo relieved Forum shopping is the act of a litigant who repetitively availed
from sharing pro-rata in the arbitration costs and, consequently, of several judicial remedies in different courts, simultaneously or
directed Asian Construction to shoulder the same costs in full successively, all substantially founded on the same transactions
and reimburse Sumitomo the amount of P849,532.45. However, and the same essential facts and circumstances, and all raising
it ordered Sumitomo to bear all the expenses related to the substantially the same issues, either pending in or already
appointment of the foreign arbitrator considering that such resolved adversely by some other court, to increase his chances
service was secured upon its own initiative and without the of obtaining a favorable decision if not in one court, then in
participation and consent of Asian Construction.44 another. More particularly, forum shopping can be committed in
three ways, namely: (a) by filing multiple cases based on the
same cause of action and with the same prayer, the previous
Dissatisfied with the Arbitral Tribunals ruling, Asian Construction
case not having been resolved yet (where the ground for
filed another Rule 43 Petition for Review45before the CA, on May
dismissal is litis pendentia); (b) by filing multiple cases based on
3, 2010, docketed as CA-G.R. SP No. 113828 (Second CA
the same cause of action and with the same prayer, the
Petition), this time, to set aside the Final Award. In this light, it
previous case having been finally resolved (where the ground for
claimed gross negligence and partiality on the part of the
dismissal is res judicata); and (c) by filing multiple cases based
Arbitral Tribunal and asserted, inter alia, that, apart from being a
on the same cause of action but with different prayers (splitting
non-arbitrable issue, an award of attorneys fees would be
of causes of action, where the ground for dismissal is also either
premature since the prevailing party can only be determined
litis pendentia or res judicata). 52 Forum shopping is treated as an
when the case is decided with finality. Moreover, it maintained
act of malpractice and, in this accord, constitutes a ground for
that both claims of Asian Construction and the counterclaims of
the summary dismissal of the actions involved. 53 To be sure, the
Sumitomo had already been dismissed for being time-barred. 46
rule against forum shopping seeks to prevent the vexation
brought upon the courts and the litigants by a party who asks
The CA Ruling different courts to rule on the same or related causes and grant
the same or substantially the same reliefs and in the process
On July 23, 2010, the CA rendered a Resolution 47 (July 23, 2010 creates the possibility of conflicting decisions being rendered by
Resolution), dismissing Asian Constructions First CA Petition the different fora upon the same issues.54
against the Partial Award on the ground of forum-shopping, after
it was shown that: (a) the aforesaid petition was filed while the In this case, the Court finds that the CA committed no reversible
arbitration case was still pending final resolution before the error in dismissing Asian Constructions First CA Petition on the
Arbitral Tribunal; and (b) Asian Constructions opposition to ground of forum shopping since the relief sought (i.e., the
Sumitomos claim for costs filed before the Arbitral Tribunal had, reconsideration of the Partial Award) and the allegations stated
in fact, effectively sought for the same relief and stated the therein are identical to its opposition to Sumitomos claim for
same allegations as those in its First CA Petition. The CA also costs filed before the Arbitral Tribunal while CIAC Case No. 28-
noted Asian Constructions premature resort to a petition for 2008 was still pending. These circumstances clearly square with
review because what was sought to be nullified was not a final the first kind of forum shopping which thereby impels the
award, but only a partial one. The CA eventually denied Asian dismissal of the First CA Petition on the ground of litis pendentia.
Constructions motion for reconsideration in a Resolution 48 dated
April 18, 2011. Hence, Asian Constructions petition before the
On this score, it is apt to point out that Asian Constructions
Court, docketed as G.R. No. 196723.
argument that it merely complied with the directive of the
Arbitral Tribunal cannot be given any credence since it (as well
Meanwhile, the CA gave due course to Asian Constructions as Sumitomo) was only directed to submit evidence to prove the
Second CA Petition assailing the Final Award and rendered a costs it had incurred and paid as a result of the arbitration
Decision49 on January 26, 2011, upholding the Arbitral Tribunals proceedings. However, at variance with the tribunals directive,
ruling except the award of attorneys fees in favor of Sumitomo. Asian Construction, in its opposition to Sumitomos claim for
The CA held that the fact that Asian Construction initiated an costs, proceeded to seek the reversal of the Partial Award in the
action or refused to compromise its claims cannot be considered same manner as its First CA Petition. It cannot, therefore, be
unjustified or made in bad faith as to entitle Sumitomo to the doubted that it treaded the course of forum shopping,
aforesaid award. Consequently, Sumitomo moved for warranting the dismissal of the aforesaid petition.
reconsideration,50 asserting that Asian Constructions Second CA
Petition should have instead been dismissed in its entirety
In any case, the Court observes that the First CA Petition
considering their Agreement that the Arbitral Tribunals
remains dismissible since the CIAC Revised Rules provides for
decisions and awards would be final and non-appealable.
the resort to the remedy of a petition for review only against a
However, in a Resolution51 dated April 29, 2011, the CA denied
final arbitral award,55 and not a partial award, as in this case.
the motion for reconsideration. Thus, Sumitomos petition before
the Court, docketed as G.R. No. 196728.
In fine, the Court upholds the CAs dismissal of Asian
Constructions petition in CA-G.R. SP No. 112127 (First CA
The Issues Before the Court
Petition) and based on this, denies its petition in G.R. No.
196723.
The essential issues for the Courts resolution are as follows: (a)
in G.R. No. 196723, whether or not the CA erred in dismissing
B. Review and modification of the Final Award.
Asian Constructions First CA Petition on the ground of forum
shopping; and (b) in G.R. No. 196728, whether or not the CA
erred in reviewing and modifying the Final Award which Sumitomo Corporation faults the CA for reviewing and modifying
Sumitomo insists to be final and unappealable. a final and non-appealable arbitral award and insists that the
Asian Constructions Second CA Petition should have been,
instead, dismissed outright. It mainly argues that by entering
The Courts Ruling
into stipulations in the arbitration clause which provides that
"the order or award of the arbitrators will be the sole and
The petitions should be denied. exclusive remedy between the parties regarding any and all
claims and counterclaims with respect to the matter of the
A. Dismissal of Asian arbitrated dispute"56 and that "the order or award rendered in
connection with an arbitration shall be final and binding upon
the parties,"57 Asian Construction effectively waived any and all
Constructions First CA appeals from the Arbitral Tribunals decision or award.

Petition; forum shopping. Sumitomos argument is untenable.


165
A brief exegesis on the development of the procedural rules just or equitable reason to rule otherwise, 68 these incidents are
governing CIAC cases clearly shows that a final award rendered clearly off-tangent with a finding of gross and evident bad faith
by the Arbitral Tribunal is not absolutely insulated from judicial which altogether negates Sumitomos entitlement to attorneys
review. fees.

To begin, Executive Order No. (EO) 1008, 58 which vests upon the Hence, finding the CAs review of the Final Award and its
CIAC original and exclusive jurisdiction over disputes arising consequent deletion of the award of attorneys fees to be
from, or connected with, contracts entered into by parties proper, the Court similarly denies Sumitomos petition in G.R.
involved in construction in the Philippines, plainly states that the No. 196728.
arbitral award "shall be final and inappealable except on
questions of law which shall be appealable to the Court." 59 Later, WHEREFORE, the petitions are DENIED. The Resolutions dated
however, the Court, in Revised Administrative Circular (RAC) No. July 23, 2010 and April 18, 2011 of the Court of Appeals in CA-
1-95,60 modified this rule, directing that the appeals from the G.R. SP No. 112127, as well as its Decision dated January 26,
arbitral award of the CIAC be first brought to the CA on 2011 and Resolution dated April 29, 2011 in CA-G.R. SP No.
"questions of fact, law or mixed questions of fact and law." This 113828 are hereby AFFIRMED.SO ORDERED.
amendment was eventually transposed into the present CIAC
Revised Rules which direct that "a petition for review from a final
award may be taken by any of the parties within fifteen (15) FIRST DIVISION G.R. No. 169332 February 11, 2008
days from receipt thereof in accordance with the provisions of
Rule 43 of the Rules of Court." 61 Notably, the current provision is ABS-CBN BROADCASTING CORPORATION,Petitioner, - v e r
s u s - WORLD INTERACTIVENETWORK SYSTEMS
in harmony with the Courts pronouncement that "despite
(WINS)JAPAN CO., LTD.,Respondent.
statutory provisions making the decisions of certain
x-----------------------------------------
administrative agencies final, the Court still takes cognizance
---------x
of petitions showing want of jurisdiction, grave abuse of CORONA, J.:
discretion, violation of due process, denial of substantial justice
or erroneous interpretation of the law" and that, in particular, This petition for review on certiorari under Rule 45 of the Rules
"voluntary arbitrators, by the nature of their functions, act in a of Court seeks to set aside the February 16, 2005 decision [1] and
quasi-judicial capacity, such that their decisions are within the August 16, 2005 resolution[2] of the Court of Appeals (CA) in CA-
scope of judicial review."62 G.R. SP No. 81940.

On September 27, 1999, petitioner ABS-CBN Broadcasting


In this case, the Court finds that the CA correctly reviewed and
Corporation entered into a licensing agreement with respondent
modified the Arbitral Tribunals Final Award insofar as the award World Interactive Network Systems (WINS) Japan Co., Ltd., a
of attorneys fees in favor of Sumitomo is concerned since the foreign corporation licensed under the laws of Japan. Under the
same arose from an erroneous interpretation of the law.1wphi1 agreement, respondent was granted the exclusive license to
distribute and sublicense the distribution of the television
To elucidate, jurisprudence dictates that in the absence of a service known as The Filipino Channel (TFC) in Japan. By virtue
governing stipulation, attorneys fees may be awarded only in thereof, petitioner undertook to transmit the TFC programming
signals to respondent which the latter received through its
case the plaintiff's action or defendant's stand is so untenable
decoders and distributed to its subscribers.
as to amount to gross and evident bad faith. 63 This is embodied
in Article 2208 of the Civil Code which states: A dispute arose between the parties when petitioner accused
respondent of inserting nine episodes of WINS WEEKLY, a weekly
Article 2208. In the absence of stipulation, attorney's fees and 35-minute community news program for Filipinos in Japan, into
expenses of litigation, other than judicial costs, cannot be the TFC programming from March to May 2002. [3] Petitioner
recovered, except: claimed that these were unauthorized insertions constituting a
material breach of their agreement. Consequently, on May 9,
2002,[4] petitioner notified respondent of its intention to
xxxx terminate the agreement effective June 10, 2002.

Thereafter, respondent filed an arbitration suit pursuant to the


(5) Where the defendant acted in gross and evident bad faith in
arbitration clause of its agreement with petitioner. It contended
refusing to satisfy the plaintiff's64 plainly valid, just and
that the airing of WINS WEEKLY was made with petitioner's prior
demandable claim; approval. It also alleged that petitioner only threatened to
terminate their agreement because it wanted to renegotiate the
xxxx terms thereof to allow it to demand higher fees. Respondent
also prayed for damages for petitioner's alleged grant of an
exclusive distribution license to another entity, NHK (Japan
In this case, the parties agreed that reasonable attorneys fees Broadcasting Corporation).[5]
shall be paid by the defaulting party if it fails to perform any of
its obligations under the Agreement or by the party not The parties appointed Professor Alfredo F. Tadiar to act as sole
prevailing, if any dispute concerning the meaning and arbitrator. They stipulated on the following issues in their terms
interpretation thereto arises.65 However, since the parties of reference (TOR)[6]:
respective claims under the Agreement had already prescribed
pursuant to New York State Law, considering as well that the 1. Was the broadcast of WINS WEEKLY by the
dispute was not regarding the meaning or construction of any claimant duly authorized by the respondent
provision under the Agreement,66 their stipulation on attorneys [herein petitioner]?
fees should remain inoperative. Therefore, discounting the
application of the foregoing stipulation, the Court proceeds to 2. Did such broadcast constitute a material
breach of the agreement that is a ground for
examine the matter under the lens of bad faith pursuant to the
termination of the agreement in accordance
above-discussed rules on attorneys fees.
with Section 13 (a) thereof?

After a careful scrutiny of the records, the Court observes that 3. If so, was the breach seasonably cured under
there was no gross and evident bad faith on the part of Asian the same contractual provision of Section 13
Construction in filing its complaint against Sumitomo since it (a)?
was merely seeking payment of its unpaid works done pursuant
to the Agreement. Neither can its subsequent refusal to accept 4. Which party is entitled to the payment of
damages they claim and to the other reliefs
Sumitomos offered compromise be classified as a badge of bad
prayed for?
faith since it was within its right to either accept or reject the
same owing to its contractual nature.67 Verily, absent any other
166
xxx xxx xxx The issue before us is whether or not an aggrieved
party in a voluntary arbitration dispute may avail of, directly in
the CA, a petition for review under Rule 43 or a petition for
certiorari under Rule 65 of the Rules of Court, instead of filing a
The arbitrator found in favor of respondent.[7] He held that petition to vacate the award in the RTC when the grounds
petitioner gave its approval to respondent for the airing of WINS invoked to overturn the arbitrators decision are other than those
WEEKLY as shown by a series of written exchanges between the for a petition to vacate an arbitral award enumerated under RA
parties. He also ruled that, had there really been a material 876.
breach of the agreement, petitioner should have terminated the
same instead of sending a mere notice to terminate said RA 876 itself mandates that it is the Court of First
agreement. The arbitrator found that petitioner threatened to Instance, now the RTC, which has jurisdiction over questions
terminate the agreement due to its desire to compel respondent relating to arbitration,[9] such as a petition to vacate an arbitral
to re-negotiate the terms thereof for higher fees. He further award.
stated that even if respondent committed a breach of the
agreement, the same was seasonably cured. He then allowed Section 24 of RA 876 provides for the specific grounds for a
respondent to recover temperate damages, attorney's fees and petition to vacate an award made by an arbitrator:
one-half of the amount it paid as arbitrator's fee.
Sec. 24. Grounds for vacating award. - In any one of
Petitioner filed in the CA a petition for review under Rule 43 of the following cases, the court must make an
the Rules of Court or, in the alternative, a petition for certiorari order vacating the award upon the petition of any
under Rule 65 of the same Rules, with application for temporary party to the controversy when such party proves
restraining order and writ of preliminary injunction. It was affirmatively that in the arbitration proceedings:
docketed as CA-G.R. SP No. 81940. It alleged serious errors of
fact and law and/or grave abuse of discretion amounting to lack (a) The award was procured by corruption, fraud, or
or excess of jurisdiction on the part of the arbitrator. other undue means; or

Respondent, on the other hand, filed a petition for confirmation (b) That there was evident partiality or corruption in the
of arbitral award before the Regional Trial Court (RTC) of Quezon arbitrators or any of them; or
City, Branch 93, docketed as Civil Case No. Q-04-51822. (c) That the arbitrators were guilty of misconduct in
refusing to postpone the hearing upon sufficient cause
Consequently, petitioner filed a supplemental petition in the CA shown, or in refusing to hear evidence pertinent and
seeking to enjoin the RTC of Quezon City from further material to the controversy; that one or more of the
proceeding with the hearing of respondent's petition for arbitrators was disqualified to act as such under section
confirmation of arbitral award. After the petition was admitted nine hereof, and willfully refrained from disclosing such
by the appellate court, the RTC of Quezon City issued an order disqualifications or of any other misbehavior by which
holding in abeyance any further action on respondent's petition the rights of any party have been materially prejudiced;
as the assailed decision of the arbitrator had already become or
the subject of an appeal in the CA. Respondent filed a motion for (d) That the arbitrators exceeded their powers, or so
reconsideration but no resolution has been issued by the lower imperfectly executed them, that a mutual, final and
court to date.[8] definite award upon the subject matter submitted to
them was not made.
On February 16, 2005, the CA rendered the assailed decision
dismissing ABS-CBNs petition for lack of jurisdiction. It stated
that as the TOR itself provided that the arbitrator's decision shall
be final and unappealable and that no motion for Based on the foregoing provisions, the law itself clearly
reconsideration shall be filed, then the petition for review must provides that the RTC must issue an order vacating an arbitral
fail. It ruled that it is the RTC which has jurisdiction over award only in any one of the . . . cases enumerated therein.
questions relating to arbitration. It held that the only instance it Under the legal maxim in statutory construction expressio unius
can exercise jurisdiction over an arbitral award is an appeal from est exclusio alterius, the explicit mention of one thing in a
the trial court's decision confirming, vacating or modifying the statute means the elimination of others not specifically
arbitral award. It further stated that a petition for certiorari mentioned. As RA 876 did not expressly provide for errors of fact
under Rule 65 of the Rules of Court is proper in arbitration cases and/or law and grave abuse of discretion (proper grounds for a
only if the courts refuse or neglect to inquire into the facts of an petition for review under Rule 43 and a petition for certiorari
arbitrator's award. The dispositive portion of the CA decision under Rule 65, respectively) as grounds for maintaining a
read: petition to vacate an arbitral award in the RTC, it necessarily
follows that a party may not avail of the latter remedy on the
WHEREFORE, the instant petition is grounds of errors of fact and/or law or grave abuse of discretion
hereby DISMISSED for lack of jurisdiction. The to overturn an arbitral award.
application for a writ of injunction and temporary
restraining order is likewise DENIED. The Regional Trial Adamson v. Court of Appeals [10] gave ample warning that a
Court of Quezon City Branch 93 is directed to proceed petition to vacate filed in the RTC which is not based on the
with the trial for the Petition for Confirmation of Arbitral grounds enumerated in Section 24 of RA 876 should be
Award. dismissed. In that case, the trial court vacated the arbitral award
seemingly based on grounds included in Section 24 of RA 876
SO ORDERED. but a closer reading thereof revealed otherwise. On appeal, the
CA reversed the decision of the trial court and affirmed the
arbitral award. In affirming the CA, we held:

Petitioner moved for reconsideration. The same was denied. The Court of Appeals, in reversing the trial court's
Hence, this petition. decision held that the nullification of the decision of the
Arbitration Committee was not based on the grounds
Petitioner contends that the CA, in effect, ruled that: (a) it provided by the Arbitration Law and that xxx private
should have first filed a petition to vacate the award in the RTC respondents (petitioners herein) have failed to
and only in case of denial could it elevate the matter to the CA substantiate with any evidence their claim of partiality.
via a petition for review under Rule 43 and (b) the assailed Significantly, even as respondent judge ruled against
decision implied that an aggrieved party to an arbitral award the arbitrator's award, he could not find fault with their
does not have the option of directly filing a petition for review impartiality and integrity. Evidently, the nullification
under Rule 43 or a petition for certiorari under Rule 65 with the of the award rendered at the case at bar was not
CA even if the issues raised pertain to errors of fact and law or made on the basis of any of the grounds
grave abuse of discretion, as the case may be, and not provided by law.
dependent upon such grounds as enumerated under Section 24
(petition to vacate an arbitral award) of RA 876 (the Arbitration xxx xxx xxx
Law). Petitioner alleged serious error on the part of the CA.
167
It is clear, therefore, that the award was vacated contention that it may avail of a petition for review under Rule
not because of evident partiality of the 43 under the circumstances of this case is correct.
arbitrators but because the latter interpreted the As to petitioner's arguments that a petition for certiorari under
contract in a way which was not favorable to herein Rule 65 may also be resorted to, we hold the same to be in
petitioners and because it considered that herein accordance with the Constitution and jurisprudence.
private respondents, by submitting the controversy to
arbitration, was seeking to renege on its obligations Section 1 of Article VIII of the 1987 Constitution provides that:
under the contract.
SECTION 1. The judicial power shall be vested in one
xxx xxx xxx Supreme Court and in such lower courts as may be
established by law.
It is clear then that the Court of Appeals reversed
the trial court not because the latter reviewed the Judicial power includes the duty of the courts of
arbitration award involved herein, but because the justice to settle actual controversies involving rights
respondent appellate court found that the trial which are legally demandable and enforceable, and to
court had no legal basis for vacating the determine whether or not there has been a grave
award. (Emphasis supplied). abuse of discretion amounting to lack or excess
of jurisdiction on the part of any branch or
In cases not falling under any of the aforementioned grounds to instrumentality of the Government. (Emphasis
vacate an award, the Court has already made several supplied)
pronouncements that a petition for review under Rule 43 or a As may be gleaned from the above stated provision, it is well
petition for certiorari under Rule 65 may be availed of in the CA. within the power and jurisdiction of the Court to inquire whether
Which one would depend on the grounds relied upon by any instrumentality of the Government, such as a voluntary
petitioner. arbitrator, has gravely abused its discretion in the exercise of its
In Luzon Development Bank v. Association of Luzon functions and prerogatives. Any agreement stipulating that the
Development Bank Employees,[11] the Court held that a decision of the arbitrator shall be final and unappealable and
voluntary arbitrator is properly classified as a quasi-judicial that no further judicial recourse if either party disagrees with the
instrumentality and is, thus, within the ambit of Section 9 (3) of whole or any part of the arbitrator's award may be availed of
the Judiciary Reorganization Act, as amended. Under this cannot be held to preclude in proper cases the power of judicial
section, the Court of Appeals shall exercise: review which is inherent in courts. [16] We will not hesitate to
review a voluntary arbitrator's award where there is a showing
xxx xxx xxx of grave abuse of authority or discretion and such is properly
raised in a petition for certiorari [17] and there is no appeal, nor
(3) Exclusive appellate jurisdiction over all any plain, speedy remedy in the course of law. [18]
final judgments, decisions, resolutions, orders or Significantly, Insular Savings Bank v. Far East Bank and
awards of Regional Trial Courts and quasi-judicial Trust Company[19] definitively outlined several judicial remedies
agencies, instrumentalities, boards or commissions, an aggrieved party to an arbitral award may undertake:
including the Securities and Exchange Commission, the
Employees Compensation Commission and the Civil (1) a petition in the proper RTC to issue an
Service Commission, except those falling within the order to vacate the award on the grounds
appellate jurisdiction of the Supreme Court in provided for in Section 24 of RA 876;
accordance with the Constitution, the Labor Code of the (2) a petition for review in the CA under Rule
Philippines under Presidential Decree No. 442, as 43 of the Rules of Court on questions of fact,
amended, the provisions of this Act and of of law, or mixed questions of fact and law; and
subparagraph (1) of the third paragraph and (3) a petition for certiorari under Rule 65 of the
subparagraph (4) of the fourth paragraph of Section 17 Rules of Court should the arbitrator have acted
of the Judiciary Act of 1948. (Emphasis supplied) without or in excess of his jurisdiction or with
grave abuse of discretion amounting to lack or
excess of jurisdiction.
As such, decisions handed down by voluntary arbitrators fall
within the exclusive appellate jurisdiction of the CA. This Nevertheless, although petitioners position on the judicial
decision was taken into consideration in approving Section 1 of remedies available to it was correct, we sustain the dismissal of
Rule 43 of the Rules of Court.[12] Thus: its petition by the CA. The remedy petitioner availed of,
entitled alternative petition for review under Rule 43 or petition
SECTION 1. Scope. - This Rule shall apply to appeals for certiorari under Rule 65, was wrong.
from judgments or final orders of the Court of Tax
Appeals and from awards, judgments, final orders or Time and again, we have ruled that the remedies of appeal and
resolutions of or authorized by any quasi-judicial certiorari are mutually exclusive and not alternative or
agency in the exercise of its quasi-judicial functions. successive.[20]
Among these agencies are the Civil Service
Commission, Central Board of Assessment Appeals, Proper issues that may be raised in a petition for review under
Securities and Exchange Commission, Office of the Rule 43 pertain to errors of fact, law or mixed questions of fact
President, Land Registration Authority, Social Security and law.[21] While a petition for certiorari under Rule 65 should
Commission, Civil Aeronautics Board, Bureau of only limit itself to errors of jurisdiction, that is, grave abuse of
Patents, Trademarks and Technology Transfer, National discretion amounting to a lack or excess of jurisdiction.
[22]
Electrification Administration, Energy Regulatory Board, Moreover, it cannot be availed of where appeal is the proper
National Telecommunications Commission, Department remedy or as a substitute for a lapsed appeal. [23]
of Agrarian Reform under Republic Act Number 6657,
Government Service Insurance System, Employees In the case at bar, the questions raised by petitioner in
Compensation Commission, Agricultural Inventions its alternative petition before the CA were the following:
Board, Insurance Commission, Philippine Atomic Energy
Commission, Board of Investments, Construction A. THE SOLE ARBITRATOR COMMITTED SERIOUS ERROR
Industry Arbitration Commission, and voluntary AND/OR GRAVELY ABUSED HIS DISCRETION IN RULING
arbitrators authorized by law. (Emphasis supplied) THAT THE BROADCAST OF WINS WEEKLY WAS DULY
AUTHORIZED BY ABS-CBN.

B. THE SOLE ARBITRATOR COMMITTED SERIOUS ERROR


This rule was cited in Sevilla Trading Company v. Semana, AND/OR GRAVELY ABUSED HIS DISCRETION IN RULING
[13]
Manila Midtown Hotel v. Borromeo,[14] and Nippon Paint THAT THE UNAUTHORIZED BROADCAST DID NOT
Employees Union-Olalia v. Court of Appeals.[15] These cases held CONSTITUTE MATERIAL BREACH OF THE AGREEMENT.
that the proper remedy from the adverse decision of a voluntary
arbitrator, if errors of fact and/or law are raised, is a petition for C. THE SOLE ARBITRATOR COMMITTED SERIOUS ERROR
review under Rule 43 of the Rules of Court. Thus, petitioner's AND/OR GRAVELY ABUSED HIS DISCRETION IN RULING
THAT WINS SEASONABLY CURED THE BREACH.
168
D. THE SOLE ARBITRATOR COMMITTED SERIOUS ERROR Petitioner refused to submit to arbitration, however,
AND/OR GRAVELY ABUSED HIS DISCRETION IN RULING prompting respondent to file a Complaint[1] against PEZA for
THAT TEMPERATE DAMAGES IN THE AMOUNT specific performance before the Regional Trial Court (RTC)
OF P1,166,955.00 MAY BE AWARDED TO WINS. of Pasay, alleging that, inter alia:

E. THE SOLE ARBITRATOR COMMITTED SERIOUS ERROR xxxx


AND/OR GRAVELY ABUSED HIS DISCRETION IN
AWARDING ATTORNEY'S FEES IN THE UNREASONABLE 4. Under Clauses 14.1 and 14.2 of the Agreement, the
AMOUNT AND UNCONSCIONABLE AMOUNT dispute shall be resolved through arbitration before an
OF P850,000.00. Arbitration Committee composed of one representative of
each party and a third member who shall be mutually
F. THE ERROR COMMITTED BY THE SOLE ARBITRATOR IS acceptable to the parties: x x x
NOT A SIMPLE ERROR OF JUDGMENT OR ABUSE OF xxx
DISCRETION. IT IS GRAVE ABUSE OF DISCRETION 5. Conformably with the Agreement, plaintiff notified
TANTAMOUNT TO LACK OR EXCESS OF JURISDICTION. defendant in a letter dated September 6, 2004 requesting
that the parties submit their dispute to arbitration. In a
letter dated September 8, 2004, which defendant received
A careful reading of the assigned errors reveals that the real on the same date, defendant unjustifiably refused to
issues calling for the CA's resolution were less the alleged grave comply with the request for arbitration, in violation of its
abuse of discretion exercised by the arbitrator and more about undertaking under the Agreement. Defendant likewise
the arbitrators appreciation of the issues and evidence refused to nominate its representative to the Arbitration
presented by the parties. Therefore, the issues clearly fall under Committee as required by the Agreement.
the classification of errors of fact and law questions which may
be passed upon by the CA via a petition for review under Rule 6. Under Section 8 of Republic Act No. 876 (1953),
43. Petitioner cleverly crafted its assignment of errors in such a otherwise known as the Arbitration Law, (a) if either party
way as to straddle both judicial remedies, that is, by alleging to the contract fails or refuses to name his arbitrator within
serious errors of fact and law (in which case a petition for review 15 days after receipt of the demand for arbitration; or (b) if
under Rule 43 would be proper) and grave abuse of discretion the arbitrators appointed by each party to the contract, or
(because of which a petition for certiorari under Rule 65 would appointed by one party to the contract and by the proper
be permissible). court, shall fail to agree upon or to select the third
arbitrator, then this Honorable Court shall appoint
It must be emphasized that every lawyer should be familiar with the arbitrator or arbitrators.[2] (Emphasis and
the distinctions between the two remedies for it is not the duty underscoring supplied)
of the courts to determine under which rule the
petition should fall.[24] Petitioner's ploy was fatal to its
cause. An appeal taken either to this Court or the CA by the Respondent accordingly prayed for judgment
wrong or inappropriate mode shall be dismissed. [25] Thus,
the alternative petition filed in the CA, being an inappropriate x x x (a) designating (i) an arbitrator to represent
mode of appeal, should have been dismissed outright by the CA. defendant; and (ii) the third arbitrator who shall act as
Chairman of the Arbitration Committee; and (b) referring
WHEREFORE, the petition is hereby DENIED. The February 16, the attached Request for Arbitration to the Arbitration
2005 decision and August 16, 2005 resolution of the Court of Committee to commence the arbitration.[3]
Appeals in CA-G.R. SP No. 81940 directing the Regional Trial
Court of Quezon City, Branch 93 to proceed with the trial of the
petition for confirmation of arbitral award is AFFIRMED. and for other just and equitable reliefs.

Costs against petitioner. In its Answer,[4] PEZA (hereafter petitioner):

SO ORDERED. ADMIT[TED] the allegations in paragraphs 1, 2, 3, 4,


SECOND DIVISION October 23, 2009 G.R. No. 179537 and 6 of the complaint, with the qualification that the
PHILIPPINE ECONOMIC ZONE AUTHORITY,Petitioner- alleged dispute subject of the plaintiffs Request for
versus -EDISON (BATAAN) COGENERATION CORPORATION, Arbitration dated October 20, 2004 is not an arbitrable
Respondent. issue, considering that the provision on pre-termination
fee in the Power Sales and Purchase Agreement (PSPA),
CARPIO MORALES, J.: is gravely onerous, unconscionable, greatly
Petitioner Philippine Economic Zone Authority (PEZA) disadvantageous to the government, against public policy
and Edison (Bataan) Cogeneration Corporation (respondent) and therefore invalid and unenforceable.
entered into a Power Supply and Purchase Agreement (PSPA or
agreement) for a 10-year period effective October 25, 1997 ADMIT[TED] the allegation in paragraph 5 of the
whereby respondent undertook to construct, operate, and complaint with the qualification that the refusal of the
maintain a power plant which would sell, supply and deliver defendant to arbitrate is justified considering that
electricity to PEZA for resale to business locators in the Bataan the provision on the pre-termination fee subject of the
Economic Processing Zone. plaintiffs Request for Arbitration is invalid and
In the course of the discharge of its obligation, unenforceable.Moreover, the pre-termination of the PSPA
respondent requested from PEZA a tariff increase with a is whimsical, has no valid basis and in violation of the
mechanism for adjustment of the cost of fuel and lubricating oil, provisions thereof, constituting breach of contract on the
which request it reiterated on March 5, 2004. part of the plaintiff.[5] (Emphasis and underscoring
supplied)
PEZA did not respond to both requests, however,
drawing respondent to write PEZA on May 3, 2004. Citing a tariff Xxxx
increase which PEZA granted to the East Asia Utilities Respondent thereafter filed a Reply and Motion to
Corporation (EAUC), another supplier of electricity in the Mactan Render Judgment on the Pleadings,[6] contending that since
Economic Zone, respondent informed PEZA of a violation of its petitioner
obligation under Clause 4.9 of the PSPA not to give preferential
treatment to other power suppliers. x x x does not challenge the fact that (a) there
is a dispute between the parties; (b) the dispute must
After the lapse of 90 days, respondent terminated the be resolved through arbitration before a three-member
PSPA, invoking its right thereunder, and arbitration committee; and (c) defendant refused to
demanded P708,691,543.00 as pre-termination fee. PEZA submit the dispute to arbitration by naming its
disputed respondents right to terminate the agreement and representative in the arbitration committee,
refused to pay the pre-termination fee, prompting respondent to
request PEZA to submit the dispute to arbitration pursuant to
the arbitration clause of the PSPA.
169
judgment may be rendered directing the appointment of the two R.A. No. 876 explicitly confines the courts authority
other members to complete the composition of the arbitration only to the determination of whether or not there is an
committee that will resolve the dispute of the parties.[7] agreement in writing providing for arbitration.[15] Given
petitioners admission of the material allegations of respondents
By Order of April 5, 2005, Branch 118 of the Pasay City complaint including the existence of a written agreement to
RTC granted respondents Motion to Render Judgment on the resolve disputes through arbitration, the assailed appellate
Pleadings, disposing as follows: courts affirmance of the trial courts grant of respondents Motion
for Judgment on the Pleadings is in order.
WHEREFORE, all the foregoing considered, this
Court hereby renders judgment in favor of the plaintiff Petitioner argues that it tendered an issue in its Answer
and against the defendant. Pursuant to Section 8 of RA as it disputed the legality of the pre-termination fee clause of
876, also known as the Arbitration Law, and Power the PSPA. Even assuming arguendo that the clause is illegal, it
Sales and Purchase Agreement, this Court would not affect the agreement between petitioner and
hereby appoints, subject to their agreement as respondent to resolve their dispute by arbitration.
arbitrators, retired Supreme Court Chief Justice Andres
Narvasa, as chairman of the committee, and retired The doctrine of separability, or severability as
Supreme Court Justices Hugo Gutierrez, and Justice Jose other writers call it, enunciates that an arbitration
Y. Feria, as defendants and plaintiffs representative, agreement is independent of the main contract. The
respectively, to the arbitration arbitration agreement is to be treated as a separate
committee. Accordingly, let the Request for Arbitration agreement and the arbitration agreement does not
be immediately referred to the Arbitration Committee automatically terminate when the contract of which it is
so that it can commence with the arbitration. a part comes to an end.

SO ORDERED.[8] (Underscoring supplied) The separability of the arbitration agreement


is especially significant to the determination of whether
the invalidity of the main contract also nullifies the
arbitration clause. Indeed, the doctrine denotes that
the invalidity of the main contract, also referred to as
On appeal,[9] the Court of Appeals, by Decision of April the container contract, does not affect the validity of
10, 2007, affirmed the RTC Order.[10] Its Motion for the arbitration agreement.Irrespective of the fact that
Reconsideration[11] having been denied,[12] petitioner filed the the main contract is invalid, the arbitration
present Petition for Review on Certiorari,[13]faulting the appellate clause/agreement still remains valid and enforceable.
[16]
court (Emphasis in the original; underscoring supplied)
Petitioner nevertheless contends that the legality of the
I pre-termination fee clause is not arbitrable, citing Gonzales v.
Climax Mining Ltd. [17] which declared that the therein
. . . WHEN IT DISMISSED PETITIONERS APPEAL AND complaint should be brought before the regular courts, and not
AFFIRMED THE 05 APRIL 2004 ORDER OF THE TRIAL before an arbitral tribunal, as it involved a judicial issue. Held
COURT WHICH RENDERED JUDGMENT ON THE the Court:
PLEADINGS, DESPITE THE FACT THAT PETITIONERS
ANSWER TENDERED AN ISSUE. We agree that the case should not be brought
under the ambit of the Arbitration Law xxx. The
II question of validity of the contract containing the
agreement to submit to arbitration will affect the
. . . WHEN IT AFFIRMED THE ORDER OF THE TRIAL applicability of the arbitration clause itself. A party
COURT WHICH REFERRED RESPONDENTS REQUEST cannot rely on the contract and claim rights or
FOR ARBITRATION DESPITE THE FACT THAT THE ISSUE obligations under it and at the same time impugn its
PRESENTED BY THE RESPONDENT IS NOT AN existence or validity. Indeed, litigants are enjoined from
ARBITRABLE ISSUE.[14] (Underscoring supplied) taking inconsistent positions. As previously discussed,
the complaint should have been filed before the regular
courts as it involved issues which are judicial in nature.
[18]
The petition fails.

The dispute raised by respondent calls for a proceeding


under Section 6 of Republic Act No. 876, AN ACT TO AUTHORIZE The ruling in Gonzales was, on motion for reconsideration filed
THE MAKING OF ARBITRATION AND SUBMISSION AGREEMENTS, by the parties, modified, however, in this wise:
TO PROVIDE FOR THE APPOINTMENT OF ARBITRATORS AND THE
PROCEDURE FOR ARBITRATION IN CIVIL CONTROVERSIES, AND x x x The adjudication of the petition in G.R.
FOR OTHER PURPOSES which reads: No. 167994 effectively modifies part of the Decision
dated 28 February 2005 in G.R. No. 161957. Hence,
SECTION 6. Hearing by court. A party aggrieved by the failure, we now hold that the validity of the
neglect or refusal of another to perform under an agreement in contract containing the agreement to submit to
writing providing for arbitration may petition the court for an arbitration does not affect the applicability of the
order directing that such arbitration proceed in the manner arbitration clause itself. A contrary ruling would
provided for in such agreement. Five days notice in writing of suggest that a partys mere repudiation of the main
the hearing of such application shall be served either personally contract is sufficient to avoid arbitration. That is exactly
or by registered mail upon the party in default. The court shall the situation that the separability doctrine, as well as
hear the parties, and upon being satisfied that the making of the jurisprudence applying it, seeks to avoid. We add that
agreement or such failure to comply therewith is not in issue, when it was declared in G.R. No. 161957 that the
shall make an order directing the parties to proceed to case should not be brought for arbitration, it should be
arbitration in accordance with the terms of the agreement. If the clarified that the case referred to is the case actually
making of the agreement or default be in issue the court shall filed by Gonzales before the DENR Panel of Arbitrators,
proceed to summarily hear such issue. If the finding be that no which was for the nullification of the main
agreement in writing providing for arbitration was made, or that contract on the ground of fraud, as it had already
there is no default in the proceeding thereunder, the proceeding been determined that the case should have been
shall be dismissed. If the finding be that a written provision for brought before the regular courts involving as it did
arbitration was made and there is a default in proceeding judicial issues.[19] (Emphasis and underscoring supplied)
thereunder, an order shall be made summarily directing the
parties to proceed with the arbitration in accordance with the
terms thereof. It bears noting that respondent does not seek to nullify
the main contract. It merely submits these issues for resolution
x x x x (Underscoring supplied) by the arbitration committee, viz:
170
a. Whether or not the interest of Claimant in Under the Performance Bond,[4] the parties agreed on
the project or its economic return in its a time-bar provision which states:
investment was materially reduced as a result
of any laws or regulations of the Philippine Furthermore, it is hereby agreed and understood that
Government or any agency or body under its PRUDENTIAL GUARANTEE AND ASSURANCE INC., shall
control; not be liable for any claim not discovered and
presented to the company within ten days from the
b. Whether or not the parties failed to reach expiration of this bond or from the occurrence of the
an agreement on the amendments to the default or failure of the principal, whichever is the
Agreement within 90 days from notice to earliest, and that the obligee hereby waives his right to
respondent on May 3, 2004 of the material file any claim against the Surety after the termination
reduction in claimants economic return under of the period of ten days above mentioned after which
the Agreement; time this bond shall definitely terminate and be
deemed absolutely cancelled.
c. Whether or not as a result of (a) and (b)
above, Claimant is entitled to terminate the
Agreement;
KRDC then received a notice to proceed on November
d. Whether or not Respondent accorded 24, 1999. On October 16, 2000 or 325 days after KRDC received
preferential treatment to EAUC in violation of the notice to proceed, and 50 days beyond the contract date of
the Agreement; completion, ALI sent PGAI a letter [5] notifying the latter that the
contract with KRDC was terminated due to very serious
e. Whether or not as a result of (d) above, delays. The letter also informed PGAI that ALI may be making
Claimant is entitled to terminate the claims against the said bonds.
Agreement;

f. Whether or not Claimant is entitled to a KRDC, through a letter on October 20, 2000, asked ALI
termination fee equivalent to to reconsider its decision to terminate the contract and
P708,691,543.00; and requested that it be allowed to continue with the
project. On October 27, 2000, ALI replied [6] with regrets that it
g. Who between Claimant and Respondent stands by its earlier decision to terminate the construction
shall bear the cost and expenses of the contract.
arbitration, including arbitrators fees,
administrative expenses and legal fees.[20]
Through a letter[7] dated November 29, 2001, or
In fine, the issues raised by respondent are subject to exactly one (1) year after the expiration date in the performance
arbitration in accordance with the arbitration clause in the bond, ALI reiterated its claim against the performance bond
parties agreement. issued by PGAI amounting to P3,852,800.84. PGAI however did
not respond to the letter.
WHEREFORE, the petition is DENIED.SO ORDERED.
THIRD DIVISION September 8, 2010 G.R. No. 177240
On February 7, 2002, ALI commenced arbitration
PRUDENTIAL GUARANTEE AND ASSURANCE INC.,Petitioner, - proceedings against KRDC and PGAI in the CIAC.PGAI answered
versus - with cross-claim contending that it was not a party to the
ANSCOR LAND, INC.,Respondent. construction contract and that the claim of ALI against the
bonds was filed beyond the expiration period.

VILLARAMA, JR., J.:


On September 2, 2002, the CIAC rendered
judgment[8] awarding a total of P7,552,632.74 to ALI and a total
of P1,292,487.81 to KRDC. CIAC also allowed the offsetting of
This petition for review on certiorari under Rule 45 of the awards to both parties which resulted to a net amount due
the 1997 Rules of Civil Procedure, as amended, assails the to ALI of P6,260,144.93 to be paid by KRDC. Meanwhile, the
[1]
Decision dated April 28, 2006 of the Court of Appeals (CA) in CIAC found PGAI liable for the reimbursement of the
CA-G.R. SP No. 72854 which modified the unliquidated portion of the down payment as a solidary liability
Decision[2] promulgated on September 2, 2002 by the under the surety bond in the amount of P1,771,264.06.[9]
Construction Industry Arbitration Commission (CIAC) to the
effect that herein petitioner Prudential Guarantee and Assurance
Inc. (PGAI) was declared solidarily liable with its principal Kraft In the same judgment, the CIAC absolved PGAI from a
Realty and Development Corporation (KRDC) under the claim against the performance bond. It reasoned that ALI
performance bond. belatedly filed its claim on the performance bond. The CIAC
accepted the view that the November 29, 2001 letter of ALI to
PGAI was the first and only claim on the performance bond,
The facts follow. which was filed unquestionably beyond the allowed period for
filing claims under the contract.

On August 2, 2000, Anscor Land, Inc. (ALI) and KRDC


entered into a Construction Contract [3] for the construction of an The CIAC ruled that the October 16, 2000 letter of ALI
8-unit townhouse (project) located in Capitol Hills, Quezon City. to PGAI did not constitute a proper claim under the performance
bond. In so ruling, the CIAC relied on the tenor of the letter
which used the phrase may be making claims against the said
Under the contract, KRDC was to build and complete bonds. The CIAC interpreted this phrase as tentative at best and
the project within 275 continuous calendar days from the date of far from a positive claim against PGAI. According to the CIAC,
receipt of a notice to proceed for the consideration the letter merely informed PGAI of the termination of the
of P18,800,000.00. construction contract between ALI and KRDC and in no sense did
such letter present a valid claim against the performance bond
As part of its undertaking, KRDC submitted a surety issued by PGAI.
bond amounting to P4,500,000.00 to secure the reimbursement
of the down payment paid by ALI in case of failure to finish the
project and a performance bond amounting to P4,700,000.00 to ALI then filed a petition for review on October 3,
guarantee the supply of labor, materials, tools, equipment, and 2002[10] with the CA questioning the decision of the CIAC to
necessary supervision to complete the project. The said bonds release PGAI from its solidary liability on the performance bond.
were issued in favor of ALI by herein petitioner PGAI.
171
The CA found the petition meritorious in its questioned On the issue of timeliness of the claim, respondent
Decision[11] dated April 28, 2006, to wit: insists that its letter dated October 16, 2000 was for all intents
and purposes a notification of termination of the construction
WHEREFORE, the petition is GRANTED. The contract and at the same time a notice to petitioner that
decretal portion of the decision is MODIFIED to the respondent is in fact making a claim on the performance
effect that PGAI is hereby pronounced solidarily liable bond. Contrary to PGAIs view that the November 29, 2001 letter
with KRDC under the performance bond. was the first and only claim made, respondent asserts that the
said letter was merely a reiteration of its earlier October 16,
2000 claim.
SO ORDERED.[12]

In fine, there are two (2) main issues for this Court to
resolve, to wit:
Petitioner PGAI now comes to this Court to seek relief.
I.
Petitioner argues that the CIAC had no jurisdiction over
the dispute as regards the claim of ALI against the performance Whether or not the CIAC had jurisdiction over the
bond because petitioner was not a party to the construction dispute.
contract. It maintains that Executive Order (EO) No. 1008 [13] did
not vest jurisdiction on the CIAC to settle disputes between a II.
party to a construction contract on one hand and a non-party on
the other. Whether or not the respondent made its claim on the
performance bond within the period allowed by
the time-bar provision.
The petitioner contends that CIACs jurisdiction was
limited to the construction industry and cannot extend to surety First Issue Jurisdiction of the CIAC
or guarantee contracts. By reason of the lack of jurisdiction of
Section 4 of EO No. 1008 defines the jurisdiction of the
the CIAC over the dispute, the September 2,
CIAC:
2002 judgment[14] of the CIAC was void with regard to the
liability of PGAI. Sec. 4. Jurisdiction. The CIAC shall have original and exclusive
jurisdiction over disputes arising from, or connected with,
contracts entered into by parties involved in construction in
As to the award made by the CIAC on ALIs claims, the Philippines, whether the dispute arises before or after the
petitioner maintains that it cannot be held liable under the completion of the contract, or after the abandonment or
performance bond because clearly, under the time-bar breach thereof. These disputes may involve government or
provision in the said bond, the claim made by ALI in its letter to private contracts. For the Board to acquire jurisdiction, the
PGAI dated November 29, 2001 was submitted one (1) year parties to a dispute must agree to submit the same to
late. Petitioner points out that such letter was the first and only voluntary arbitration.
definite claim that ALI made against the performance bond and
unfortunately, it was filed beyond the allowed period. Hence, the The jurisdiction of the CIAC may include but is not limited to
Decision of the CA declaring PGAI solidarily liable with KRDC violation of specifications for materials and workmanship;
under the performance bond is erroneous and should be struck violation of the terms of agreement; interpretation and/or
down. application of contractual time and delays; maintenance and
defects; payment, default of employer or contractor and
changes in contract cost.
On the other hand, respondent avers that the Excluded from the coverage of this law are disputes arising
construction contract itself provided that the performance and from employer-employee relationships which shall continue
surety bond shall be deemed part of the construction contract, to be covered by the Labor Code of the Philippines. (Italics
to wit: supplied.)
Article 1
CONTRACT DOCUMENTS
EO No. 1008 expressly vests in the CIAC original and
1.1 The following shall form part of this Contract and exclusive jurisdiction over disputes arising from or connected
together with this Contract, are known as the with construction contracts entered into by parties that have
Contract Documents: agreed to submit their dispute to voluntary arbitration. Under
the aforequoted provision, it is apparent that a dispute must
a. Bid Proposal
meet two (2) requirements in order to fall under the jurisdiction
xxxx of the CIAC: first, the dispute must be somehow connected to a
construction contract; and second, the parties must have agreed
d. Notice to proceed to submit the dispute to arbitration proceedings.
xxxx
As regards the first requirement, the Performance Bond
j. Appendices A & B (respectively, Surety Bond
issued by the petitioner was meant to guarantee the supply of
for Performance and, Supply of Materials by
labor, materials, tools, equipment, and necessary supervision to
the Developer)[15]
complete the project. A guarantee or a surety contract under
Article 2047[16] of the Civil Code of the Philippines is an
accessory contract because it is dependent for its existence
By reason of this express provision in the construction upon the principal obligation guaranteed by it.[17]
contract, respondent maintains that petitioner PGAI became a
party to such contract when it submitted its Surety and
Performance bonds. Consequently, petitioners argument that In fact, the primary and only reason behind the
CIAC has not acquired jurisdiction over PGAI because the latter acquisition of the performance bond by KRDC was to guarantee
was not a party to the construction contract, is untenable. to ALI that the construction project would proceed in accordance
with the contract terms and conditions. In effect, the
performance bond becomes liable for the completion of the
As to the alleged lack of jurisdiction of CIAC over the construction project in the event KRDC fails in its contractual
dispute arising from the surety contract, respondent cites EO undertaking.
No. 1008, which provides that any dispute connected with a
construction contract comes within the original and exclusive
jurisdiction of the CIAC. The surety bond being an integral part Because of the performance bond, the construction
of the construction contract, it is necessarily connected thereto contract between ALI and KRDC is guaranteed to be performed
which brings it under the jurisdiction of the CIAC. even if KRDC fails in its obligation. In practice, a performance
bond is usually a condition or a necessary component of
construction contracts. In the case at bar, the performance bond
172
was so connected with the construction contract that the former contract. The construction contract breathes life into the
was agreed by the parties to be a condition for the latter to push performance bond. We are not ready to assume that the
through and at the same time, the former is reliant on the latter performance bond contains reservations with regard to some of
for its existence as an accessory contract. the terms and conditions in the construction contract where in
fact it is silent.On the other hand, it is more reasonable to
assume that the party who issued the performance bond
Although not the construction contract itself, the carefully and meticulously studied the construction contract that
performance bond is deemed as an associate of the main it guaranteed, and if it had reservations, it would have and
construction contract that it cannot be separated or severed should have mentioned them in the surety contract.
from its principal. The Performance Bond is significantly and
substantially connected to the construction contract that there
can be no doubt it is the CIAC, under Section 4 of EO No. 1008, Second Issue Petitioners Liability Under the Performance
which has jurisdiction over any dispute arising from or Bond
connected with it. On the second issue, the crux of the controversy revolves upon
a letter dated October 16, 2000 sent by ALI to PGAI. It reads:
On the second requirement that the parties to a dispute
must have previously agreed to submit to arbitration, it is clear xxxx
from Article 24 of the Construction Contract itself that the
parties have indeed agreed to submit their disputes to This pertains to the contract between Kraft Realty
arbitration, to wit: Development Corp. and Anscor Land, Inc., which is
covered by surety and performance bonds by your
Article 24 good company.
DISPUTES AND ARBITRATION
Please be advised that we are now terminating the
All disputes, controversies, or differences between the contract of Kraft due to the breach by Kraft of the
parties arising out of or in connection with this terms and conditions of the construction contract. More
Contract, or arising out of or in connection with the specifically, the project has accumulated very serious
execution of the WORK shall be settled in accordance delays, in spite of the full cooperation that this
with the procedures laid down by the Construction company has extended to Kraft.
Industry Arbitration Commission. The cost of arbitration
shall be borne jointly by both CONTRACTOR and Kindly refer to the attached letter of termination
DEVELOPER on a fifty-fifty (50-50) basis.[18] dated 16 October 2000.

Petitioner however argues that such provision in the Anscor Land [Inc.] may be making claims against the
construction contract does not bind it because it is not a party to said bonds and in this regard, kindly coordinate with
such contract and in effect did not give its consent to submit to the following for any matter with which we can assist
arbitration in case of any dispute on the performance you with.
bond. Such argument is untenable. The Performance Bond
issued by petitioner states that PGAI agreed -- Engr. Teodelito de Vera
Anscor Land, Inc.
To guarantee the supply of labor, materials, tools, Tel. 812-7941 to 48 Fax 813-5301
equipment and necessary supervision to complete the
construction of Proposed Sigma Townhouses of the Thank you for your kind attention.[22] (Italics supplied.)
Obligee as per Notice to Proceed dated November 23,
1999, copy of which is hereto attached and made an
integral part of this bond.[19]
The question really is whether or not the foregoing letter
constituted a valid claim and effectively complied with the time-
bar provision in the performance bond.
When it executed the performance bond, PGAIs
undertaking thereunder was that of a surety to the obligation of
It is clear that ALI communicated two (2) important points to PGAI
KRDC, the principal under the construction contract. PGAI should
in the letter. First, that ALI is terminating the construction contract
not be allowed now to insist that it had nothing to do with the
with KRDC and second, that ALI may be making a claim on the
construction contract and should be viewed as a non-party.
bonds issued by PGAI.
Since the liability of petitioner as surety is solidary with that of
KRDC, it was properly impleaded as it would be the party
ultimately answerable under the bond should KRDC be adjudged The time-bar provision in the Performance Bond provides that
liable for breach of contract. Furthermore, it is well settled that any claim against the bond should be discovered and presented
accessory contracts should not be read independently of the to the company within ten days from the expiration of this bond
main contract. They should be construed together in order to or from the occurrence of the default or failure of the principal,
arrive at their true meaning.[20] In Velasquez v. Court of Appeals, whichever is the earliest. The purpose of this provision in the
[21]
the Court labeled such rule as the complementary contracts performance bond is to give the issuer, in this case PGAI, notice
construed together doctrine. It states: of the claim at the earliest possible time and to afford the issuer
sufficient time to evaluate, and examine the validity of the claim
That the complementary contracts construed together while the evidence or indicators of breach are fresh. In the
doctrine applies in this case finds support in the construction industry, time is precious, delay costs money and
principle that the surety contract is merely an postponement in making a claim could cause additional
accessory contract and must be interpreted with its expenses.
principal contract, which in this case was the loan
agreement. This doctrine closely adheres to the spirit of
Art. 1374 of the Civil Code which states that In line with the rationale behind the time-bar provision, we rule
that the letter dated October 16, 2000 was a sufficient
Art. 1374. The various stipulations of a claim. The tenor of the letter adequately put PGAI on notice that
contract shall be interpreted together, ALI has terminated the contract because of serious delays
attributing to the doubtful ones that sense tantamount to breach by KRDC of its obligations. The letter
which may result from all of them taken jointly. timely informed PGAI that ALI was in fact terminating the
construction contract and thereby giving rise to the obligation of
In the case at bar, the performance bond was silent with regard PGAI under the performance bond. PGAI was informed within
to arbitration. On the other hand, the construction contract was the time-bar provision and had all the opportunity to conduct its
clear as to arbitration in the event of disputes. Applying the said evaluation and examination as to the validity of the termination.
doctrine, we rule that the silence of the accessory contract in
this case could only be construed as acquiescence to the main
173
The CA thus correctly ruled that: The October 16, 2000 letter was the presentation of the
claim. ALIs intent to recover its claim was communicated clearly
The fact of contract termination had been made known to PGAI. By informing PGAI of the termination of the contract
to PGAI as early as October 16, 2000. This with KRDC, ALI in effect presented a situation where PGAI is put
terminationconsequently meant that the principal on notice that ALI in fact has a right to payment by virtue of the
KRDC would no longer be able to supply labor, performance bond and it intends to recover it. Undeniably, ALI
materials, tools, equipment and necessary has substantially complied with the time-bar provision of the
supervision to complete the project. It was at this time, performance bond.
therefore, that PGAIs obligation guaranteeing the
project completion arose, although the amount of
payment was still undetermined. WHEREFORE, the petition is DENIED and the Decision
dated April 28, 2006 of the Court of Appeals in CA-G.R. SP No.
72854 is hereby AFFIRMED.
That ALI merely used the word may in expressing its
intent to proceed against the bond does not make its
claim any less categorical as argued by PGAI. The point
With costs against the petitioner.SO ORDERED.
is the very condition giving rise to the obligation to pay,
i.e. KRDCs default and the resulting contract
termination, was clearly mentioned in the 16 October FIRST DIVISIONG.R. No. 189563 April 7, 2014
2000 letter. The citation of this fact is more than
sufficient to place PGAI in notice that ALI shall be
making claims on the bonds. GILAT SATELLITE NETWORKS, LTD., Petitioner,
vs.
xxxx UNITED COCONUT PLANTERS BANK GENERAL INSURANCE
CO., INC., Respondent.
But the important consideration is that ALI, by its 16
October 2000 letter, was informing PGAI of the contract
SERENO, CJ:
termination, the very condition for its liabilities under
the performance bond to accrue. ALI had no other
purpose in sending the letter than to notify PGAI This is an appeal via a Petition for Review on Certiorari 1 filed 6
that it was intending to proceed against the November 2009 assailing the Decision 2 and Resolution3 of the
performance bond. PGAI makes much out of ALIs Court of Appeals (CA) in CA-G.R. CV No. 89263, which reversed
failure to identify the particular bond against which it the Decision4 of the Regional Trial Court (RTC), Branch 141,
would be claiming. But the contract termination Makati City in Civil Case No. 02-461, ordering respondent to pay
necessarily implies that there would be hiatus in the petitioner a sum of money.
supply of labor and materials.

Surely, no bond would answer for the non- The antecedent facts, as culled from the CA, are as follows:
implementation of contractual provisions other than the
performance bond.Further, the surety bond only
On September 15, 1999, One Virtual placed with GILAT a
guarantees reimbursement of the portion of the
purchase order for various telecommunications equipment (sic),
downpayment and not the supply of labor, materials
and equipment.[23] (Emphasis supplied, italics in the accessories, spares, services and software, at a total purchase
original.) price of Two Million One Hundred Twenty Eight Thousand Two
Hundred Fifty Dollars (US$2,128,250.00). Of the said purchase
price for the goods delivered, One Virtual promised to pay a
In interpreting the time-bar provision, the absence of any portion thereof totalling US$1.2 Million in accordance with the
ambiguity in the words used would lead to the conclusion that payment schedule dated 22 November 1999. To ensure the
the generally accepted meaning of the words shall control. In prompt payment of this amount, it obtained defendant UCPB
the time-bar provision, the word claim does not give rise to any General Insurance Co., Inc.s surety bond dated 3 December
ambiguity in interpretation and does not call for a stretched 1999, in favor of GILAT.
understanding.

During the period between [sic] September 1999 and June 2000,
In Finasia Investments and Finance Corporation v. Court of GILAT shipped and delivered to One Virtual the purchased
Appeals,[24] the Court had the occasion to rule that: products and equipment, as evidenced by airway bills/Bill of
Lading (Exhibits "F", "F-1" to "F-8"). All of the equipment
The word claim is also defined as: (including the software components for which payment was
secured by the surety bond, was shipped by GILAT and duly
Right to payment, whether or not such right is reduced received by One Virtual. Under an endorsement dated
to judgment, liquidated, unliquidated, fixed, contingent, December 23, 1999 (Exhibit "E"), the surety issued, with One
matured, unmatured, disputed, undisputed, legal, Virtuals conformity, an amendment to the surety bond, Annex
equitable, secured, or unsecured; or right to an "A" thereof, correcting its expiry date from May 30, 2001 to July
equitable remedy for breach of performance if such 30, 2001.
breach gives rise to a right to payment, whether or not
such right to an equitable remedy is reduced to
judgment, fixed, contingent, matured, unmatured, One Virtual failed to pay GILAT the amount of Four Hundred
disputed, undisputed, secured, unsecured. Thousand Dollars (US$400,000.00) on the due date of May 30,
2000 in accordance with the payment schedule attached as
In conflicts of law, a receiver may be appointed in any Annex "A" to the surety bond, prompting GILAT to write the
state which has jurisdiction over the defendant who surety defendant UCPB on June 5, 2000, a demand letter
owes a claim.[25] (Italics supplied.) (Exhibit "G") for payment of the said amount of US$400,000.00.
No part of the amount set forth in this demand has been paid to
date by either One Virtual or defendant UCPB. One Virtual
In the case at bar, the claim of ALI against PGAI arose from the likewise failed to pay on the succeeding payment instalment
failure of KRDC to perform its obligation under the construction date of 30 November 2000 as set out in Annex "A" of the surety
contract. ALI therefore already had the claim or right to payment bond, prompting GILAT to send a second demand letter dated
against PGAI in the maximum amount of P4,700,000.00 from the January 24, 2001, for the payment of the full amount of
moment KRDC failed to comply with its obligation. According to US$1,200,000.00 guaranteed under the surety bond, plus
the time-bar provision, in order to enforce such claim or recover interests and expenses (Exhibits "H") and which letter was
the said amount, ALI shall present its claim within ten (10) days
received by the defendant surety on January 25, 2001. However,
from the occurrence of the default or failure of KRDC.
defendant UCPB failed to settle the amount of US$1,200,000.00
174
or a part thereof, hence, the instant complaint." 5 (Emphases in SO ORDERED. (Emphasis in the original)
the original)
The CA ruled that in "enforcing a surety contract, the
On 24 April 2002, petitioner Gilat Satellite Networks, Ltd., filed a complementary-contracts-construed-together doctrine finds
Complaint6 against respondent UCPB General Insurance Co., application." According to this doctrine, the accessory contract
Inc., to recover the amounts supposedly covered by the surety must be construed with the principal agreement. 15In this case,
bond, plus interests and expenses. After due hearing, the RTC the appellate court considered the Purchase Agreement entered
rendered its Decision,7 the dispositive portion of which is herein into between petitioner and One Virtual as the principal
quoted: contract,16 whose stipulations are also binding on the parties to
the suretyship.17 Bearing in mind the arbitration clause
contained in the Purchase Agreement18 and pursuant to the
WHEREFORE, premises considered, the Court hereby renders
policy of the courts to encourage alternative dispute resolution
judgment for the plaintiff, and against the defendant, ordering,
methods,19 the trial courts Decision was vacated; petitioner and
to wit:
One Virtual were ordered to proceed to arbitration.

1. The defendant surety to pay the plaintiff the amount


On 9 September 2008, petitioner filed a Motion for
of One Million Two Hundred Thousand Dollars
Reconsideration with Motion for Oral Argument. The motion was
(US$1,200,000.00) representing the principal debt
denied for lack of merit in a Resolution 20 issued by the CA on 16
under the Surety Bond, with legal interest thereon at
September 2009.
the rate of 12% per annum computed from the time the
judgment becomes final and executory until the
obligation is fully settled; and Hence, the instant Petition.

2. The defendant surety to pay the plaintiff the amount On 31 August 2010, respondent filed a Comment21 on the
of Forty Four Thousand Four Dollars and Four Cents Petition for Review. On 24 November 2010, petitioner filed a
(US$44,004.04) representing attorneys fees and Reply.22
litigation expenses.
ISSUES
Accordingly, defendants counterclaim is hereby dismissed for
want of merit. From the foregoing, we reduce the issues to the following:

SO ORDERED. (Emphasis in the original) 1. Whether or not the CA erred in dismissing the case
and ordering petitioner and One Virtual to arbitrate;
In so ruling, the RTC reasoned that there is "no dispute that and
plaintiff [petitioner] delivered all the subject equipments [sic]
and the same was installed. Even with the delivery and 2. Whether or not petitioner is entitled to legal interest
installation made, One Virtual failed to pay any of the payments due to the delay in the fulfilment by respondent of its
agreed upon. Demand notwithstanding, defendant failed and obligation under the Suretyship Agreement.
refused and continued to fail and refused to settle the
obligation."8
THE COURTS RULING

Considering that its liability was indeed that of a surety, as


"spelled out in the Surety Bond executed by and between One The existence of a suretyship agreement does not give the
Virtual as Principal, UCPB as Surety and GILAT as Creditor/Bond surety the right to intervene in the principal contract, nor can an
Obligee,"9 respondent agreed and bound itself to pay in arbitration clause between the buyer and the seller be invoked
accordance with the Payment Milestones. This obligation was by a non-party such as the surety.
not made dependent on any condition outside the terms and
conditions of the Surety Bond and Payment Milestones.10 Petitioner alleges that arbitration laws mandate that no court
can compel arbitration, unless a party entitled to it applies for
Insofar as the interests were concerned, the RTC denied this relief.23 This referral, however, can only be demanded by
petitioners claim on the premise that while a surety can be held one who is a party to the arbitration agreement.24 Considering
liable for interest even if it becomes more onerous than the that neither petitioner nor One Virtual has asked for a referral,
principal obligation, the surety shall only accrue when the delay there is no basis for the CAs order to arbitrate.
or refusal to pay the principal obligation is without any justifiable
cause.11 Here, respondent failed to pay its surety obligation Moreover, Articles 1216 and 2047 of the Civil Code 25 clearly
because of the advice of its principal (One Virtual) not to provide that the creditor may proceed against the surety without
pay.12 The RTC then obligated respondent to pay petitioner the having first sued the principal debtor.26 Even the Surety
amount of USD1,200,000.00 representing the principal debt Agreement itself states that respondent becomes liable upon
under the Surety Bond, with legal interest at the rate of 12% per "mere failure of the Principal to make such prompt
annum computed from the time the judgment becomes final and payment."27 Thus, petitioner should not be ordered to make a
executory, and USD44,004.04 representing attorneys fees and separate claim against One Virtual (via arbitration) before
litigation expenses. proceeding against respondent.28

On 18 October 2007, respondent appealed to the CA. 13 The On the other hand, respondent maintains that a surety contract
appellate court rendered a Decision14 in the following manner: is merely an accessory contract, which cannot exist without a
valid obligation.29 Thus, the surety may avail itself of all the
WHEREFORE, this appealed case is DISMISSED for lack of defenses available to the principal debtor and inherent in the
jurisdiction. The trial courts Decision dated December 28, 2006 debt30 that is, the right to invoke the arbitration clause in the
is VACATED. Plaintiff-appellant Gilat Satellite Networks Ltd., and Purchase Agreement.
One Virtual are ordered to proceed to arbitration, the outcome of
which shall necessary bind the parties, including the surety, We agree with petitioner.
defendant-appellant United Coconut Planters Bank General
Insurance Co., Inc.
In suretyship, the oft-repeated rule is that a suretys liability is
joint and solidary with that of the principal debtor. This
175
undertaking makes a surety agreement an ancillary contract, as delay in discharging its monetary obligation. 47 Citing Article
it presupposes the existence of a principal 1169 of the Civil Code, petitioner insists that the delay started
contract.31 Nevertheless, although the contract of a surety is in to run from the time it demanded the fulfilment of respondents
essence secondary only to a valid principal obligation, its obligation under the suretyship contract. Significantly,
liability to the creditor or "promise" of the principal is said to be respondent does not contest this point, but instead argues that
direct, primary and absolute; in other words, a surety is directly it is only liable for legal interest of 6% per annum from the date
and equally bound with the principal.32 He becomes liable for the of petitioners last demand on 24 January 2001.
debt and duty of the principal obligor, even without possessing a
direct or personal interest in the obligations constituted by the In rejecting petitioners position, the RTC stated that interests
latter.33Thus, a surety is not entitled to a separate notice of may only accrue when the delay or the refusal of a party to pay
default or to the benefit of excussion. 34 It may in fact be sued is without any justifiable cause.48 In this case, respondents
separately or together with the principal debtor. 35 failure to heed the demand was due to the advice of One Virtual
that petitioner allegedly breached its undertakings as stated in
After a thorough examination of the pieces of evidence the Purchase Agreement.49 The CA, however, made no
presented by both parties,36 the RTC found that petitioner had pronouncement on this matter.
delivered all the goods to One Virtual and installed them.
Despite these compliances, One Virtual still failed to pay its We sustain petitioner.
obligation,37 triggering respondents liability to petitioner as the
formers surety.1wphi1 In other words, the failure of One
Virtual, as the principal debtor, to fulfill its monetary obligation Article 2209 of the Civil Code is clear: "[i]f an obligation consists
to petitioner gave the latter an immediate right to pursue in the payment of a sum of money, and the debtor incurs a
respondent as the surety. delay, the indemnity for damages, there being no stipulation to
the contrary, shall be the payment of the interest agreed upon,
and in the absence of stipulation, the legal interest."
Consequently, we cannot sustain respondents claim that the
Purchase Agreement, being the principal contract to which the
Suretyship Agreement is accessory, must take precedence over Delay arises from the time the obligee judicially or
arbitration as the preferred mode of settling disputes. extrajudicially demands from the obligor the performance of the
obligation, and the latter fails to comply. 50 Delay, as used in
Article 1169, is synonymous with default or mora, which means
First, we have held in Stronghold Insurance Co. Inc. v. Tokyu delay in the fulfilment of obligations.51 It is the nonfulfillment of
Construction Co. Ltd.,38 that "[the] acceptance [of a surety an obligation with respect to time.52 In order for the debtor (in
agreement], however, does not change in any material way the this case, the surety) to be in default, it is necessary that the
creditors relationship with the principal debtor nor does it make following requisites be present: (1) that the obligation be
the surety an active party to the principal creditor-debtor demandable and already liquidated; (2) that the debtor delays
relationship. In other words, the acceptance does not give the performance; and (3) that the creditor requires the performance
surety the right to intervene in the principal contract. The judicially or extrajudicially.53
suretys role arises only upon the debtors default, at which
time, it can be directly held liable by the creditor for payment as
a solidary obligor." Hence, the surety remains a stranger to the Having held that a surety upon demand fails to pay, it can be
Purchase Agreement. We agree with petitioner that respondent held liable for interest, even if in thus paying, its liability
cannot invoke in its favor the arbitration clause in the Purchase becomes more than the principal obligation. 54 The increased
Agreement, because it is not a party to that contract. 39 An liability is not because of the contract, but because of the
arbitration agreement being contractual in nature, 40 it is binding default and the necessity of judicial collection.55
only on the parties thereto, as well as their assigns and heirs.41
However, for delay to merit interest, it must be inexcusable in
Second, Section 24 of Republic Act No. 9285 42 is clear in stating nature. In Guanio v. Makati-Shangri-la Hotel, 56 citing RCPI v.
that a referral to arbitration may only take place "if at least one Verchez,57 we held thus:
party so requests not later than the pre-trial conference, or upon
the request of both parties thereafter." Respondent has not In culpa contractual x x x the mere proof of the existence of the
presented even an iota of evidence to show that either contract and the failure of its compliance justify, prima facie, a
petitioner or One Virtual submitted its contesting claim for corresponding right of relief. The law, recognizing the obligatory
arbitration. force of contracts, will not permit a party to be set free from
liability for any kind of misperformance of the contractual
Third, sureties do not insure the solvency of the debtor, but undertaking or a contravention of the tenor thereof. A breach
rather the debt itself. 43 They are contracted precisely to mitigate upon the contract confers upon the injured party a valid cause
risks of non-performance on the part of the obligor. This for recovering that which may have been lost or suffered. The
responsibility necessarily places a surety on the same level as remedy serves to preserve the interests of the promissee that
that of the principal debtor.44 The effect is that the creditor is may include his "expectation interest," which is his interest in
given the right to directly proceed against either principal debtor having the benefit of his bargain by being put in as good a
or surety. This is the reason why excussion cannot be position as he would have been in had the contract been
invoked.45 To require the creditor to proceed to arbitration would performed, or his "reliance interest," which is his interest in
render the very essence of suretyship nugatory and diminish its being reimbursed for loss caused by reliance on the contract by
value in commerce. At any rate, as we have held in Palmares v. being put in as good a position as he would have been in had
Court of Appeals,46 "if the surety is dissatisfied with the degree the contract not been made; or his "restitution interest," which
of activity displayed by the creditor in the pursuit of his is his interest in having restored to him any benefit that he has
principal, he may pay the debt himself and become subrogated conferred on the other party. Indeed, agreements can
to all the rights and remedies of the creditor." accomplish little, either for their makers or for society, unless
they are made the basis for action. The effect of every infraction
is to create a new duty, that is, to make RECOMPENSE to the
Interest, as a form of indemnity, may be awarded to a creditor one who has been injured by the failure of another to observe
for the delay incurred by a debtor in the payment of the latters his contractual obligation unless he can show extenuating
obligation, provided that the delay is inexcusable. circumstances, like proof of his exercise of due diligence x x x or
of the attendance of fortuitous event, to excuse him from his
Anent the issue of interests, petitioner alleges that it deserves ensuing liability. (Emphasis ours)
to be paid legal interest of 12% per annum from the time of its
first demand on respondent on 5 June 2000 or at most, from the We agree with petitioner that records are bereft of proof to show
second demand on 24 January 2001 because of the latters that respondents delay was indeed justified by the
176
circumstances that is, One Virtuals advice regarding money, the interest due should be that which may have been
petitioners alleged breach of obligations. The lower courts stipulated in writing. Furthermore, the interest due shall itself
Decision itself belied this contention when it said that "plaintiff is earn legal interest from the time it is judicially
not disputing that it did not complete commissioning work on demanded.1wphi1 In the absence of stipulation, the rate of
one of the two systems because One Virtual at that time is interest shall be 6% per annum to be computed from default,
already in default and has not paid GILAT." 58 Assuming arguendo i.e., from judicial or extrajudicial demand under and subject to
that the commissioning work was not completed, respondent the provisions of Article 1169 of the Civil Code.
has no one to blame but its principal, One Virtual; if only it had
paid its obligation on time, petitioner would not have been xxxx
forced to stop operations. Moreover, the deposition of Mr. Erez
Antebi, vice president of Gilat, repeatedly stated that petitioner
had delivered all equipment, including the licensed software; 3. When the judgment of the court awarding a sum of money
and that the equipment had been installed and in fact, gone into becomes final and executory, the rate of legal interest, whether
operation.59 Notwithstanding these compliances, respondent still the case falls under paragraph 1 or paragraph 2, above, shall be
failed to pay. 6% per annum from such finality until its satisfaction, this
interim period being deemed to be by then an equivalent to a
forbearance of credit.
As to the issue of when interest must accrue, our Civil Code is
explicit in stating that it accrues from the time judicial or
extrajudicial demand is made on the surety. This ruling is in Applying the above-discussed concepts and in the absence of an
accordance with the provisions of Article 1169 of the Civil Code agreement as to interests, we are hereby compelled to award
and of the settled rule that where there has been an extra- petitioner legal interest at the rate of 6% per annum from 5 June
judicial demand before an action for performance was filed, 2000, its first date of extra judicial demand, until the satisfaction
interest on the amount due begins to run, not from the date of of the debt in accordance with the revised guidelines enunciated
the filing of the complaint, but from the date of that extra- in Nacar.
judicial demand.60 Considering that respondent failed to pay its
obligation on 30 May 2000 in accordance with the Purchase WHEREFORE, the Petition for Review on Certiorari is hereby
Agreement, and that the extrajudicial demand of petitioner was GRANTED. The assailed Decision and Resolution of the Court of
sent on 5 June 2000,61 we agree with the latter that interest Appeals in CA-G.R. CV No. 89263 are REVERSED. The Decision of
must start to run from the time petitioner sent its first demand the Regional Trial Court, Branch 141, Makati City is REINSTATED,
letter (5 June 2000), because the obligation was already due and with MODIFICATION insofar as the award of legal interest is
demandable at that time. concerned. Respondent is hereby ordered to pay legal interest
at the rate of 6% per annum from 5 June 2000 until the
With regard to the interest rate to be imposed, we take cue from satisfaction of its obligation under the Suretyship Contract and
Nacar v. Gallery Frames,62 which modified the guidelines Purchase Agreement.
established in Eastern Shipping Lines v. CA 63 in relation to
Bangko Sentral-Monetary Board Circular No. 799 (Series of SO ORDERED.
2013), to wit:

1. When the obligation is breached, and it consists in the


payment of a sum of money, i.e., a loan or forbearance of

You might also like