TRANSPORTATION ENGINEERING GEOMETRIC

DESIGN

Mass Diagram
Given Data:

Free Haul Distance = 50 m


Cost of Borrowing = Php 6.00 per meter-station
Cost of Hauling = Php 0.30 per meter-station

Computations:
Cb 6.00
20 +F .H . D 20 +50
L.E.H. = Ch = 0.30 = 450 m

Free Haul and Over Haul Volumes

From sta. 0+000 to sta 0+230.24, L=230.24m : within the L.E.H.

F.H.V. -1 = 145.64 cu.m.

O.H.V. -1 = 3,209.19 cu.m.

From sta. 0+467.21 to sta 0+630, L=162.79m : within the L.E.H.

F.H.V. -2 = 132.95 cu.m.

O.H.V. -2 = 636.05 cu.m.

From sta. 0+630 to sta 0+827.83, L=197.83m : within the L.E.H.

F.H.V. -3 = 44.64 cu.m.

O.H.V. -3 = 951.82 cu.m.

From sta. 1+239.95 to sta 1+645.51, L=405.56m : within the L.E.H.

F.H.V. -4 = 251.81 cu.m.

O.H.V. -4 = 6,355.7 cu.m.

Waste Volume

From sta. 0+230.24 to sta 0+467.21

W.V. -1 = 10,481.57 cu.m.

From sta. 0+827.83 to sta 1+239.95

W.V. -2 = 24, 277.29cu.m.