Procedure for HSE Risk Assessments

Cairo-HSE-P-09
1.0 Purpose

The purpose of this procedure is to describe how HSE hazard identification and risk
assessments are carried out in SUCO.

2.0 Scope of application

This procedure covers procedures to be followed in hazard identification and risk


assessments applicable to all SUCO operations. For equipment changes a PMC is used
as the main form of risk assessment. In situations where new activities or modified
conditions are proposed, then this procedure should be followed to record the
assessment and provide an overview of risks for training and as the basis for continual
improvement.

3.0 Responsibilities

3.1 Initiator

The Initiator is responsible for raising the proposal to change the operation or activities.

Only staff approved by the Field Manager can initiate work which involves a change of
risk profile.

3.1 Area Authority

Only persons defined as competent by the Field Manager can act as Area Authority.

The Initiator discusses the proposed changes with the Area Authority who then arranges
the risk assessment.

For simple changes in work activities then the Area Authority discusses the risk
assessment with the Safety Department.

For more complex tasks then the Area Authority should raise the risk assessment to the
Field Manager who can request a review from Cairo Operations.

The Area Authority carries out a review of risk assessments every six months to ensure
that all activities have been captured and risk assessments updated.

3.2 Field HSE Department

The field HSE Department advises in risk assessments where necessary.

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 1of 13
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

The Senior HSE person in the Field retains all risk assessment reports for as long as the
risk remains relevant to SUCO operations with a minimum period of five years.

3.3 HSE General Manager (Cairo)

He maintains a central file of relevant correspondence and all documents and reports.
Retention time as long as the risk remains relevant to SUCO operations with a
minimum period of five years.

3.4 Field Manager

The Field Manager reviews any risk assessments carried out at the monthly Field HSE
Committee meeting.

The Field manager is responsible for maintaining a list of all Professional Staff
competent to carry out risk assessments indicating their approval of these staff based on
their qualifications.

4.0 Procedure

4.1 General

There are several techniques possible for Risk Assessment depending on what is
intended to be achieved.

As the facilities are well-established and designed and operated to international oil-
field standards. The main risk issue is the assessment of changes.

When there are changes to established hardware then the Plant Modification Certificate
system is used (PMC). For complex changes other techniques such as HAZOP and
Quantified Risk assessment may be used although these are provided from outside
resources.

For general risk assessment a technique used is the Situational Risk Assessment. A
more formal version of this method, called the SWIFT (Structured What-if Technique),
can also be used if the situation needs a more technical assessment.

In all cases the hazard identification and risk assessment should be carried out using
the technique described below.

4.2 Initiation

A risk assessment can be initiated from several sources.

The identification of any risk relies on the recognition that change takes place in an activity,
product or service that has or could have significant impact. Similarly if any new activity,
product or service is contemplated. This recognition is intended to be pro-active, when planning

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 2of 13
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

the change, although can be reactive, having been discovered during routine operations
monitoring.

4.2.1 Change in Equipment

The procedure for assessing the acceptability of new equipment or facilities (Plant Modification
Certificate) is used to assess whether any changes are made that give rise to different risks. Plant
Modification Certificates are circulated to field HSE for comment.

4.2.2 Change in Purchase Materials/Chemicals

When new chemicals or materials are proposed the approval mechanism includes an evaluation
of the new hazards and risks carried out by the operations and HSE Department staff.

4.2.3 Change in Activity or New method

When it is proposed to change the defined operating procedure or work method involving in-
house or contract staff, an evaluation of the effect on the risk profile is carried out by the relevant
staff involving the HSE Department. This also applies to organisational changes.

4.2.4 Change in Supplier/Contractor

When it is proposed to use a new Supplier or Contractor or to change the existing situation, an
evaluation of the effect on the risk profile is carried out. This is done by relevant staff who also
involve the HSE Department.

4.2.5 Change in External Circumstances

When new information arrives from external sources, such as Cairo Office, Regulators,
Customers, or Interested Parties that has an effect on HSE, the HSE Department Staff assess the
implications and evaluate these as new issues.

4.2.6 Scheduled Review

To ensure that all risks are identified and assessed the Area Authority carries out a review of the
risk assessments every six months to update the records and maintain the information up to date.

4.3 Situation Description

The Initiator should provide sufficient information to carry out initial analysis. The
current situation needs to be described in full enough detail to allow assessment of the
various risk categories to consider.

If the risk assessment is considered to solve a problem then the nature and extent of the
problem needs to be defined.

The initiator should also explain the potential consequences of taking no action.

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 3of 13
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

4.4 Examine Technical Data and Information

The person or team collates and examines all relevant process and equipment technical
data including, drawings, process conditions, locations etc. They also gather supporting
technical information to help risk assessment.

4.5 Hazard Identification

The person or team arranges to complete the Hazard identification and Risk Assessment
as shown in Appendix 1.

The Hazard ID is the code for the hazard type as shown in Appendix 2. For example -
Hydrocarbon Gas is Code S-06.

Hazard Source is the area or equipment where the hazard exists. For example - Gas
Turbine.

4.6 Potential Causes, Events and Consequences

Causes provide a description of what might happen. For example - Flammable Gas
Leak.

The most serious event is included to provide an evaluation of the potential


consequences. For example - Gas Explosion.

The consequences column includes the eventual losses from the most serious event. For
example Multiple Fatality or complete facility loss.

The team identifies all potential scenarios and consequences. Team members need to be
aware of the danger of excluding very unlikely events from their analysis, or of over-
reliance on previous operating history.

In carrying out thewhat if analysis, unlikely events (such as an air crash on to the
facility or earthquake) can be included under terms like catastrophic failure. It is also
necessary to include how long the expected risk situation might last.

4.7 Evaluation of Risk Potential

The next step is to assess the Risk Potential against the various dimensions.

P Personnel Injury
H Health Effects
A Equipment or Asset Damage
E Environmental Harm

The Risk Rating for different scale of effect (from 0 5) is described in Appendix 3 for
each of the above dimensions.

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 4of 13
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

4.8 Probability, Frequency or Likelihood

Having identified the potential scenarios and consequences the next step is to determine
the frequency of events if they already occur or have occurred. For potential events
then the likelihood of the event happening is used as a measure.

The probability ranges from 1 to 10 as shown in Appendix 3.

It is important to be objective in this assessment.

Any measures used to mitigate any loss should be highlighted. For example the hazard
of corrosive chemicals entering the eyes produces an unacceptable risk. The use of
goggles, proper equipment and training reduces the likelihood of a major loss to an
acceptable level.

The provision of existing protection measures such as quenches, spill kits, relief
capability etc. should also be considered.

4.9 Risk assessment

Once the frequency and potential severity or likelihood assessment is done then the
positions can be marked on the Risk Assessment Grid. See Appendix 3.

Those that are considered unacceptable should have a plan to move the risk into the
acceptable region. This is achieved by reducing the potential severity or by reducing
the likelihood.

In loss control terms the options are Terminate, Treat, Transfer, Tolerate.

4.10 Solutions

The various options or solutions should be recorded with a recommendation. In


deciding the optimum approach the effectiveness of the measures should also be
assessed against expected cost.

All the scenarios and the recommended solutions should be listed, including why the
rejected solutions were rejected eg. Take too long, too costly, only provides limited
improvement.

4.11 Implementation and Operational Controls

After competing the risk assessment the expected controls should be marked up on the
form. These include decisions on whether there should be objectives to reduce or
eliminate the risk, any training needs or requirements for emergency procedures.

4.11 Reporting Findings

The person or team updates the register of Risk Assessments for the area.

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 5of 13
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

5.0 Appendices

Appendix 1 - Hazard identification and Risk Assessment Record


Appendix 2 - Hazard ID and codes
Appendix 3 - Risk Consequence and Probability

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 6of 13
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

Department: Location: Risk to: People/Health/Assets/Environment

Job Title: Prepared by: Date: Reference No.:

Ref. Activity Hazard Hazard Source Event and Risk Controls and Preventive Measures
ID Consequences

Consequence
Consider all activities and assess Establish the hazards from the activities. Identify the

Procedures

Procedures
Probability

Emergency
Awareness
Objectives
risks to Injury to People, Health likely events that lead to harm and establish whether they

Induction
Effects, Equipment Damage and will affect people, equipment production or environment.

Rating

Other
Rules
Environmental Harm on

PPE
separate sheets.

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 7 of 13


HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

Appendix 2 - Hazard ID and codes

Category Description Sub-category Code Sub-Category Description


H-01 Hydrocarbons S-01 Crude oil under pressure
H-01 Hydrocarbons S-02 Hydrocarbons in formation
H-01 Hydrocarbons S-03 LPGs
H-01 Hydrocarbons S-04 LNGs
H-01 Hydrocarbons S-05 Condensate. NGL
H-01 Hydrocarbons S-06 Hydrocarbon gas
H-01 Hydrocarbons S-07 Crude oil at low pressure
H-01 Hydrocarbons S-08 Wax
H-02 Flammable Solid S-09 Wood
H-02 Flammable Solid S-10 Coal
H-02 Flammable Solid S-11 Paper
H-02 Flammable Solid S-12 Flammable Metals
H-03 Refined Hydrocarbons S-13 Lube and seal oil
H-03 Refined Hydrocarbons S-14 Hydraulic oil
H-03 Refined Hydrocarbons S-15 Diesel fuel/petrol
H-04 Other Flammable Materials S-16 Cellulose materials
H-04 Other Flammable Materials S-17 Pyrophoric materials
H-04 Other Flammable Materials S-18 Carbon reinforced material
H-04 Other Flammable Materials S-19 Dry vegetation
H-05 Explosives S-20 Detonators
H-05 Explosives S-21 Conventional explosives
H-05 Explosives S-22 Perforating gun charges
H-05 Explosives S-23 Explosive gases
H-05 Explosives S-24 Steam explosion
H-06 Pressure Hazards S-25 Bottled gases under pressure
H-06 Pressure Hazards S-26 Water under pressure
H-06 Pressure Hazards S-27 Non Hydrocarbon gas
H-06 Pressure Hazards S-28 Water above boiling point
H-06 Pressure Hazards S-29 Vessels and Lines
H-06 Pressure Hazards S-30 Air under high pressure
H-06 Pressure Hazards S-31 Diving and Decompression
H-07 Differences in Height S-32 Personnel at height
H-07 Differences in Height S-33 Overhead equipment
H-07 Differences in Height S-34 Working over water
H-07 Differences in Height S-35 Personnel under water
H-07 Differences in Height S-36 Personnel below grade
H-07 Differences in Height S-37 Underground pipes
H-07 Differences in Height S-38 Underground tanks
H-07 Differences in Height S-39 Drips from leaking pipes/joints
H-07 Differences in Height S-40 Objects under Induced Stress
H-07 Differences in Height S-41 Objects under tension
H-07 Differences in Height S-42 Objects under compression
H-08 Vacuum S-43 Air ingress to Flammables
H-08 Vacuum S-44 Vessel collapse
H-08 Vacuum S-45 Physical damage
H-09 Confined Spaces S-46 Vessels
H-09 Confined Spaces S-47 Below Ground
H-09 Confined Spaces S-48 Drains
H-09 Confined Spaces S-49 Floating Roof Tanks

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 8 of 13


HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

H-10 Dynamic Situation Hazards S-50 On land transport (driving)


H-10 Dynamic Situation Hazards S-51 On water transport (boats)
H-10 Dynamic Situation Hazards S-52 In air transport helicopter
H-10 Dynamic Situation Hazards S-53 In air transport aeroplane
H-10 Dynamic Situation Hazards S-54 Boat collision hazard
H-10 Dynamic Situation Hazards S-55 Equipment with moving parts
H-10 Dynamic Situation Hazards S-56 Rotating Equipment
H-10 Dynamic Situation Hazards S-57 Use of hazardous hand tools
H-10 Dynamic Situation Hazards S-58 Use of hazardous power tools
H-10 Dynamic Situation Hazards S-59 Use of knives, machetes. etc.
H-10 Dynamic Situation Hazards S-60 Transfer from boat/ platform
H-10 Dynamic Situation Hazards S-61 Lifting Operations
H-11 Environmental Hazards S-62 Extreme weather conditions
H-11 Environmental Hazards S-63 High wind
H-11 Environmental Hazards S-64 High sea
H-11 Environmental Hazards S-65 Poor visibility
H-11 Environmental Hazards S-66 Sand storm
H-11 Environmental Hazards S-67 River currents
H-11 Environmental Hazards S-68 Earthquake
H-11 Environmental Hazards S-69 Land slip
H-12 Hot Surfaces S-70 Process piping/equipment >60C
H-12 Hot Surfaces S-71 Piping/equipment> 150C
H-12 Hot Surfaces S-72 Engine/ turbine exhaust systems
H-12 Hot Surfaces S-73 Steam piping
H-13 Hot Fluids S-74 Temperature >40C<150C
H-13 Hot Fluids S-75 Temperature >150C
H-14 Cold Surfaces S-76 Process piping -25C to -80C
H-14 Cold Surfaces S-77 Process piping/equipment <-80C
H-15 Cold Fluids S-78 Cold Gases/Liquids between 0 and -30C
H-15 Cold Fluids S-79 Liquified Gases <-30C
H-15 Cold Fluids S-80 Cryogenic Liquids
H-15 Cold Fluids S-81 Oceans, seas and lakes <1OC
H-16 Hazardous Goods S-82 Dangerous goods in storage
H-16 Hazardous Goods S-83 Dangerous goods in transport
H-17 Open Flame S-84 Heaters with fire tube
H-17 Open Flame S-85 Direct fired furnaces
H-17 Open Flame S-86 Flares
H-17 Open Flame S-87 Igniters
H-18 Electricity S-88 Voltage >50-440V in cables
H-18 Electricity S-89 Voltage >50-440V in equipment
H-18 Electricity S-90 Voltage >440V
H-18 Electricity S-91 Lightning discharge
H-18 Electricity S-92 Electrostatic energy/spark
H-18 Electricity S-93 Batteries
H-18 Electricity S-94 High-wattage bulbs
H-18 Electricity S-95 Mobile Generators
H-18 Electricity S-96 Underground cables
H-19 Electromagnetic radiation S-97 Ultraviolet radiation
H-19 Electromagnetic radiation S-98 Infrared radiation
H-19 Electromagnetic radiation S-99 Microwaves
H-19 Electromagnetic radiation S-100 Lasers
H-19 Electromagnetic radiation S-101 Radio/Radar
H-19 Electromagnetic radiation S-102 Strong Magnets

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 9 of 13


HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

H-20 Ionising Radiation - Open S-103 Alpha. Beta- open source


H-20 Ionising Radiation - Open S-104 Gamma rays - open source
H-20 Ionising Radiation - Open S-105 Neutron - open source
H-20 Ionising Radiation - Open S-106 NORM
H-20 Ionising Radiation - Closed S-107 Alpha. Beta - closed source
H-20 Ionising Radiation - Closed S-108 Gamma rays - closed source
H-20 Ionising Radiation - Closed S-109 Neutron - closed source
H-21 Asphyxiates S-110 Insufficient oxygen atmospheres
H-21 Asphyxiates S-111 Drowning
H-21 Asphyxiates S-112 CO2
H-21 Asphyxiates S-113 Halon/CFC
H-22 Toxic Gases S-114 H2S, sour gas
H-22 Toxic Gases S-115 Exhaust fumes
H-22 Toxic Gases S-116 Carbon monoxide
H-22 Toxic Gases S-117 SO2
H-22 Toxic Gases S-118 Benzene
H-22 Toxic Gases S-119 Chlorine
H-22 Toxic Gases S-120 Welding fumes
H-22 Toxic Gases S-121 NOx
H-23 Toxic Liquids S-122 Mercury
H-23 Toxic Liquids S-123 PCBs
H-23 Toxic Liquids S-124 Biocides
H-23 Toxic Liquids S-125 Methanol
H-23 Toxic Liquids S-126 Brines
H-23 Toxic Liquids S-127 Demulsifiers
H-23 Toxic Liquids S-128 Degreasers
H-23 Toxic Liquids S-129 Dermatitis-causing liquids
H-23 Toxic Liquids S-130 Isocyanates
H-23 Toxic Liquids S-131 Sulphanol
H-23 Toxic Liquids S-132 Amines
H-23 Toxic Liquids S-133 Corrosion inhibitors
H-23 Toxic Liquids S-134 Scale inhibitors
H-23 Toxic Liquids S-135 Liquid mud additives
H-23 Toxic Liquids S-136 Odorising additives
H-23 Toxic Liquids S-137 Organic Sulphides/Mercaptans
H-23 Toxic Liquids S-138 Leaded petrol
H-23 Toxic Liquids S-139 Intoxicating substances
H-23 Toxic Liquids S-140 Used engine oils
H-23 Toxic Liquids S-141 Carbon tetrachloride
H-23 Toxic Liquids S-142 Grey and/or black water
H-23 Toxic Liquids S-143 Oxygen scavengers
H-23 Toxic Liquids S-144 Drag reducer

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 10 of 13


HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

H-24 Toxic Solids S-145 Man made mineral fibre


H-24 Toxic Solids S-146 Cement dust
H-24 Toxic Solids S-147 Calcium hypochlorite
H-24 Toxic Solids S-148 Powdered mud additives
H-24 Toxic Solids S-149 Sulphur dust
H-24 Toxic Solids S-150 Oil-based mud
H-24 Toxic Solids S-151 Pseudo oil-based muds
H-24 Toxic Solids S-152 Water-based muds
H-24 Toxic Solids S-153 Cement slurries
H-24 Toxic Solids S-154 Dusts
H-24 Toxic Solids S-155 Heavy metals
H-24 Toxic Solids S-156 Oil-based Sludge
H-24 Toxic Solids S-157 NORM-Contaminated materials
H-25 Carcinogens S-158 Asbestos
H-25 Carcinogens S-159 Benzene
H-25 Carcinogens S-160 VCM
H-25 Carcinogens S-161 NORM
H-25 Carcinogens S-162 Burning Plastics
H-26 Corrosive Substances S-163 Hydrofluoric acid
H-26 Corrosive Substances S-164 Hydrochloric acid
H-26 Corrosive Substances S-165 Sulphuric acid
H-26 Corrosive Substances S-166 Caustic soda
H-26 Corrosive Substances S-167 Sodium Hypochlorite
H-27 Biological Hazards S-168 Medical waste
H-27 Biological Hazards S-169 Used medical equipment
H-27 Biological Hazards S-170 Medicines/Drugs
H-27 Biological Hazards S-171 Pathogens
H-27 Biological Hazards S-172 Food borne bacteria
H-27 Biological Hazards S-173 Water borne bacteria
H-27 Biological Hazards S-174 Parasitic insects
H-27 Biological Hazards S-175 Disease transmitting insects
H-27 Biological Hazards S-176 Cold and flu virus
H-27 Biological Hazards S-177 Poisonous plants
H-27 Biological Hazards S-178 Large animals
H-27 Biological Hazards S-179 Small animals
H-27 Biological Hazards S-180 Poisonous Snakes
H-27 Biological Hazards S-181 Poisonous Scorpions/insects
H-28 Use of Natural Resources S-182 Land take
H-28 Use of Natural Resources S-183 Gravel Water
H-28 Use of Natural Resources S-184 Air
H-28 Use of Natural Resources S-185 Trees, vegetation
H-28 Use of Natural Resources S-186 Aquatic creatures
H-28 Use of Natural Resources S-187 Coral
H-28 Use of Natural Resources S-188 Heritage and antiquities
H-28 Use of Natural Resources S-189 Fuel
H-28 Use of Natural Resources S-190 Energy
H-28 Use of Natural Resources S-191 Minerals
H-28 Use of Natural Resources S-192 Metals
H-29 Medical S-193 Medicines
H-29 Medical S-194 Drugs
H-29 Medical S-195 Medical unfitness
H-29 Medical S-196 Infections
H-29 Medical S-197 Disability

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 11 of 13


HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date

H-30 Ergonomic Hazards S-198 Manual handling operations


H-30 Ergonomic Hazards S-199 Access/Egress/Escape
H-30 Ergonomic Hazards S-200 Ladders and Platforms
H-30 Ergonomic Hazards S-201 Work in harness
H-30 Ergonomic Hazards S-202 Lifting
H-30 Ergonomic Hazards S-203 Slips/Trips/Falls
H-30 Ergonomic Hazards S-204 Trailing cables
H-30 Ergonomic Hazards S-205 Obstructions
H-30 Ergonomic Hazards S-206 Ear-Damaging noise
H-30 Ergonomic Hazards S-207 Loud, steady noises > 85dBA
H-30 Ergonomic Hazards S-208 Heat stress
H-30 Ergonomic Hazards S-209 Work planning issues
H-30 Ergonomic Hazards S-210 High humidity
H-30 Ergonomic Hazards S-211 Vibration
H-30 Ergonomic Hazards S-212 Hand tools
H-30 Ergonomic Hazards S-213 Machine Tools
H-30 Ergonomic Hazards S-214 Work stations
H-30 Ergonomic Hazards S-215 Welding Flash
H-30 Ergonomic Hazards S-216 Inadequate Lighting
H-30 Ergonomic Hazards S-217 Excessive Lighting
H-30 Ergonomic Hazards S-218 Odour/Smell
H-30 Ergonomic Hazards S-219 Incompatible hand controls
H-30 Ergonomic Hazards S-220 Poor location of controls
H-30 Ergonomic Hazards S-221 Physical capability
H-30 Ergonomic Hazards S-222 Cognitive ability
H-30 Ergonomic Hazards S-223 Effects of Colour-blindness
H-30 Ergonomic Hazards S-224 Effects of Deafness
H-30 Ergonomic Hazards S-225 Long working hours
H-30 Ergonomic Hazards S-226 Irregular working hours
H-30 Ergonomic Hazards S-227 Lone working
H-30 Ergonomic Hazards S-228 Poor organisation and job design
H-30 Ergonomic Hazards S-229 Inadequate PPE
H-30 Ergonomic Hazards S-230 Indoor climate
H-30 Ergonomic Hazards S-231 Language barriers
H-30 Ergonomic Hazards S-232 Time pressure or stress
H-30 Ergonomic Hazards S-233 Inadequate Workspace
H-31 Psychological Hazards S-234 Living away from family
H-31 Psychological Hazards S-235 Working and living on live plant
H-31 Psychological Hazards S-236 Post traumatic stress
H-32 Security Related Hazards S-237 Piracy,Theft, pilferage
H-32 Security Related Hazards S-238 Assault
H-32 Security Related Hazards S-239 Sabotage
H-32 Security Related Hazards S-240 External Crisis

Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 12 of 13


HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-09
Paper Copy Valid one month from Print Date
Appendix 3 - Risk Consequence and Probability

Consequence Probability

Risk 10 8 7 5 3 2 1

Rating Injury Health Equipment Environment Continuous Several Several Has Heard of Heard of in Never heard
Times a Times a happened in Oil & other of in general
year in year in before in Gas industry industry
your SUCO SUCO Industry
Code P H A E location

5 Multiple Long term health Extensive Extensive long term harm,


Fatality risk ultimately Damage over considerable area H H H H H/M M M
fatal >50m$

4 Single Long term Major SUCO Extensive harm over


Fatality disability Damage considerable area
recoverable in a few H H H H/M M M M
1m$ 50m$ weeks

3 Major Medium term Major Damage Localised harm requiring


Injury illness Full clean-up. Also non
recovery 50k$ - 1m$ compliance with legal H H H H/M M M L
requirements

2 Minor Short term illness Serious Short term localised effect


Injury Full recovery Damage requiring clean-up
H/M H/M M M M L L
10k$ - 50k$

1 Slight Immediate Slight Damage Minimal harm


Injury Recovery recoverable immediately M M M M L L L
< 10k$

0 No No health effect No damage No harm - could be


Injury beneficial No risk No risk No risk No risk No risk No risk No risk

No risk : 0 Low risk : 4 ( No action ) Medium risk : 5 14 ( Manage ) High medium risk: 15 20 ( Plan ) High risk : 21 ( Immediate action )
Issue 2.2 August 2006 Next Revision Date - 31/12/07 Page 13of 13

You might also like