You are on page 1of 17

Measurement of Construction Works IV (QSM551)

LIST AND CONTENTS OF ELEMENTS

1. SUBSTRUCTURE

1.A. Piling

All works related to foundation piling including sheet piling left in.

State the system used, whether it is Consultants design or otherwise,


number, average length and size of pile.

1.B. Work Below Lowest Floor Finish

All work below underside of screed or where no screed exists, to the


underside of the lowest floor finish including damp-proof membrane together
with relevant excavations.

This would include column bases, pile caps, ground beams, column stumps,
load-bearing brickwork below lowest floor and ground slabs.
Basement excavations and temporary work supporting sides of excavation
are also included.

2. SUPERSTRUCTURE

2.A. Frame

Load-bearing framework of concrete or steel including columns, floor beams,


roof beams and fascia beams.

Casings to stanchions and beams for structural or protective purposes.

Roof trusses in portal frames shall be included in the Frame element.

2.B. Upper Floors

Upper floors, balconies and structural screeds.

Suspended floors over or in basements.

2.C. Roof

i) Roof Structure: Construction including eaves and verges, plates,


ceiling joists, roof slabs, roof trusses, gable
ends, parapet walls and balustrades at roof level.

ii) Roof coverings: Roof screeds and finishings (e.g. asphalt, roof
tiles, etc.), flashings and roof insulation.

Eaves and verges treatment.

iii) Roof drainage: Gutters, roof outlets and rainwater downpipes.

iv) Roof lights: Roof lights, opening gear, frames, kerbs, glazing
and work to reveals of openings.

1
Measurement of Construction Works IV (QSM551)

2.D. Stairs

i) Stair structure: Construction of ramps and staircases, landings


other than at floor levels, ladders and escape
staircases.

ii) Stair finishes: Finishes to ramps, treads and risers, strings and
soffits of staircases and landings other than at
floor levels.

iii) Stair balustrades: Balustrades and handrails to stairs, landings and


stairwell.
and handrails

2.E. External Walls

External enclosing walls including walls enclosing air wells, basement walls,
retaining walls and diaphragm walls which form part of the external enclosing
walls of the building, skin of brickwork to cladding/curtain walling and damp
proof courses.

Cladding, curtain walling, sheeting rails, non-structural fins and sun screens.

External balustrade walls excluding items included with Stair elements. (refer
2.D.(iii)).

2.F. Windows and External Doors

i) Windows: Sashes, frames, linings and trims.

Ironmongery, glazing and shop fronts.

Lintels, sills, hoods, canopies and work to


reveals of openings and lintels.

ii) Doors: Doors, fanlights and sidelights, frames, linings


and trims, ironmongery and glazing.

Lintels, threshold and work to reveals of


openings.

2.G. Internal Walls and Partitions

Internal walls (including any R.C. walls not included in the Frame or External
Walls element Refer 2.A. and 2.E. respectively), partitions, dam proof
courses and insulation.

Screens, internal fixed lights, moveable space dividing partitions.

Internal balustrade walls excluding items included with Stair element. (refer
2.D.(iii)).

2.H. Internal Doors

Internal Doors, fanlights and sidelights, sliding and folding door, hatches,
frames, linings and trims and work to reveals of openings including lintels and
thresholds.

2
Measurement of Construction Works IV (QSM551)

3. FINISHES

3.A. Internal Wall Finishes

Preparatory work and finishes to surfaces of walls and columns internally.

Surfaces which are self-finished (e.g. self-finished partitions, fairface work,


etc.) shall be included with the appropriate element.

3.B. Internal Floor Finishes

Preparatory work, screeds, skirtings and finishes to floor surfaces excluding


items included with Stair element (refer 2.D.(ii)) and structural screeds
included with Upper Floors element (refer 2.B.).

3.C. Internal Ceiling Finishes

Preparatory work, plastering and finishes to soffits excluding items included


with Stair element (refer 2.D.(ii)) but including sides and soffits of beams not
forming part of wall surfaces.

Suspended ceiling construction and finishes.

Note: where ceilings principally provide ventilation or lighting, they shall be


included with the appropriate Services element, (refer 5.).

3.D. External Finishes

Preparatory work and finishes to outside face of external walls, external floor
and ceiling.

4. FITTINGS AND FURNISHINGS

i) Fittings and Fixtures

Fixed fittings including shelving, cupboards, wardrobes, benches, counters


and the like.

Blinds, blind boxes, curtain tracks and pelmets.

Blackboards, pin boards, notice boards, signs, letering, mirrors (excluding


mirrors in Sanitary Appliances refer 5.A.) and the like.

Ironmongery to fittings.

ii) Furniture and Furnishings

Furniture, curtains, loose carpets and similar soft furnishing material.

iii) Works of Art

Works of art not included in the Finishes element (refer 3.) or elsewhere.

iv) Equipment

Non-mechanical and non-electrical equipment related to the function of the


building (e.g. gymnasium equipment).

3
Measurement of Construction Works IV (QSM551)

5. SERVICES

5.A. Sanitary Appliances

Baths, basins, sinks and the like.

W.C., slop sinks, urinals and the like.

Other bathroom and toilet accessories including toilet roll holder, towel rails,
hand driers, mirrors and the like.

Traps, waste fittings, overflows and taps as appropriate.

5.B. Plumbing Installation

Hot and cold water services, soil, waste and vent pipes, storage tanks,
pumps, valves and taps not included in Sanitary Appliances (refer S.A.).

5.C. Refuse Disposal

Waste compactor, shredders, waste bins, incinerators, skid tanks and the
like.

5.D. Air-Conditioning and Ventilation System

Air-conditioning and mechanical ventilation systems.

5.E. Electrical Installation

Electric supply, electrical fitting and lightning conductors.

5.F. Fire Protection Installation

Fire fighting and warning installations, including wet risers, dry risers,
sprinklers, extinguishers, smoke detectors, alarms and the like.

5.G. Lift and Conveyor Installation

Lifts, escalators, travelators, conveyor belts, dumb waiters and the like.

5.H. Communication Installation

Public address system, telephone installations, PABX, MATV and the like.

5.J. Special Installation

Kitchen equipment, laundry, buildinf automation, security system, gas


installation and the like.

5.K. Builders Work in Connection with Services

Builders work in connection with mechanical and electrical services.

4
Measurement of Construction Works IV (QSM551)

6. EXTERNAL WORKS

6.A. Site Work

Clearance and demolitions.

Preparatory earthworks to form new contours.

Retaining walls, roads and footpaths, car park, turfing, landscaping, fencing
and gates.

Notice boards, flag poles, seats, signs and other external fitting and furniture.

6.B. Drainage

Surface water drainage, foul drainage and sewerage treatment.

6.C. External Services

Water mains, fire mains, gas mains, electrical mains and the like up to the
face of the building.

Fire hydrants, site lighting and the like.

Builders work in connection with external services.

6.D. Ancillary Buildings

Separate minor buildings such as sub-station, stores and the like including
local engineering services.

6.E. Recreational Facilities

Playgrounds, playing fields, outdoor games courts and the like including
necessary equipment.

5
Measurement of Construction Works IV (QSM551)

GENERAL PRINCIPLES OF TAKING-OFF

General Rules
Some of the general principles to be followed in taking-off building quantities are detailed in
the General Rules in Section A of the Malaysian Standard Method of Measurement of
Building Works Second Edition. The following clause is of particular importance:

1. Clause A.2.1 Bills of quantities shall fully describe and accurately represent
the quantity and quality of the works to be carried out. Work which cannot be
measured shall be given as a provisional sum. Work the extent of which is
not known shall be described as provisional or given in a bill of approximate
quantities.
2. Clause A.3.2 Unless otherwise stated, works shall be measured net as
fixed in position and each measurement shall be taken to the nearest 10mm
(i.e. 5mm and over shall be regarded as 10mm and less than 5mm shall be
disregarded).
3. Clause A.3.4 The use of hyphen between two dimensions in a bill of
quantities shall mean a range of dimensions exceeding the first dimension
stated but not exceeding the second.
4. Clause A.4.1 The order of stating dimensions in descriptions shall be
consistent and generally in the sequence of length, width and height. Where
that sequence is not appropriate or where ambiguity could arise, the
dimensions shall be specifically identified.
5. Clauses A.4.4 and A.4.5 Notwithstanding the provisions for labours to be
given as linear items or to be enumerated, such labours may be given in the
description of any linear items or enumerated items of work respectively on
which they occur.
6. Clause A.7.1 Where the unit of billing is the metre, square metre, cubic
metre or kilogramme, quantities shall be billed to the nearest whole unit.
Fractions of a unit less than half shall be disregarded and all other fractions
shall be regarded as a whole unit.
7. Clause A.7.2 Where the unit of billing is in tonne, quantities shall be billed
to the nearest two places of decimals.
8. Where the application of clauses A.7.1 and 2 would cause an entire item to
be eliminated, such item shall be enumerated stating the size or weight as
appropriate.

Dimensions Paper
Each dimension sheet is basically consisting of five main areas as below:

1. Timesing Column in which multiplying figures are entered when there is


more than one of the particular item being measured.
2. Dimension Column in which the actual dimensions, as scaled or taken direct
from the drawings, are entered.
3. Squaring Column in which the length, area or volume obtained by
multiplying together the figures or timesing column and dimension column
is recorded, ready for transfer to the abstract or bill.
4. Description Area in which the written description of each item is entered.
5. Waste Area in which the preliminary calculations, build up of lengths,
explanatory notes, location of measured work, and the like should not be
overlooked.

6
Measurement of Construction Works IV (QSM551)

Dimensioning Items
The following rule must be adhered to when entering, altering or adjusting dimensions:

1. It is essential that ample space is left between all items on the dimension
sheets so that it is possible to follow the dimensions easily and to enable any
items, which may have been omitted when the dimensions were first taken-
off, to be subsequently inserted without cramping the dimensions unduly.
2. Many of the words entered in the description area are abbreviated in order to
save space and time spent in entering the items by highly skilled technical
staff.
3. Where more than one set of dimensions relate to the same description, the
dimensions should be suitably bracketed so that this shall be made clear.
4. The measuring dimensions shall be in black or blue in colour when inserted
in the dimension column whereas red colour is used for deduction the
measured dimensions.
5. If it is necessary to amend figures one procedure is to cross out the original
figures above them, but probably a better approach is to NIL the item as next
described, unless there is insufficient space.
6. Where it is required to omit dimensions which have previously been recorded
the easiest method is to write the word NIL in the squaring column.
7. When taking-off it is most desirable to use figured dimensions on the
drawings in preference to scaling, since drawings are almost invariably in the
form of prints, which are not always true to scale.
8. Each dimension sheet should be suitably needed with the title and taking-off
section of the job and with each sheet numbered consecutively.

Descriptions
Considerable care and skill are required to frame adequate, and yet at the same time, concise
descriptions as in the following:

1. In addition to covering all the matters detailed in the Malaysian Standard


Method of Measurement of Building Works Second Edition, the descriptions
must include all the information which the estimator will require to build up a
realistic price for the item in question.
2. The first few words of a description should clearly indicate the nature of the
item being described.
3. The second description indicates at the outset the nature of the item under
consideration.
4. In some cases it is necessary to give the number of units involved in a
superficial or linear item, in order that the estimator can determine the
average area or length of unit being price.
5. Where an entry on the dimensions paper is to be followed immediately by a
similar item, the use of the words ditto or do., meaning that which has
been said before, will permit the description of the next item to be reduced
considerably.
6. Another practice is to use expressions a.b. (as before) or a.b.d. (as before
described), to refer to a description which has occurred at some earlier point
in the taking-off.
7. When measuring certain types of work they are described as being extra
over another item of work which has been previously measured.
8. In the Malaysian Standard Method of Measurement of Building Works
Second Edition, the expression deemed to be included is used extensively
and indicates that this particular work is covered in the billed item without the
need for specific mention.

7
Measurement of Construction Works IV (QSM551)

Schedule
Schedule is a mean of setting down all relevant information in tabulated form when measuring
a number of items if similar characteristics but varying components.

Uses of Schedule are:

1. To collect together specification information to assist in speedy taking off.


2. For recording measurements and are in effect the taking-off.
3. Combination of both.

Good Practice During Taking-Off


It is expected that the taker off is familiar with the measurement of various elements or
sections and the following are some of the suggestions of good practice and steps to be taken
to reduce errors in taking off:

1. All drawing received for taking off shall be recorded and stamped with date.
Any drawings which are substantially changed by issue of later drawings
should be stamped SUPERSEDED and not be used for taking off. Only
latest drawings to be used for taking off unless it has been agreed that a date
is fixed for the receipt of the last drawings and any drawings issued after that
date would be treated as variation drawings.
2. Colour or strike off all items on the drawings after the items has been
measured to avoid double measurement.
3. After the taking off of an element is completed, go through your taking off
drawings and dimensions to ensure nothing has missed out.
4. On completion of all taking off, the team leader and all the taker offs shall go
through all drawings together to confirm all items have been measured and
not only overlooked but also avoid double measurement.
5. Before taking-off, check overall dimensions against built-up dimensions in
both architectural and structural engineering drawings. Also check the overall
dimensions in architectural against those in the structural drawings.
6. All items must be three dimensional and the booking of dimensions must be
consistent in the order of length, width and height or depth.
7. All dimensions must be annotated to ease post contract administration work.
8. All descriptions and notes on drawings shall be run through and taken into
account.
9. Prepare schedule whenever necessary. The schedules that are normally
required are:

a) Column bases/pile caps


b) Piles of different sizes and lengths
c) Internal finishes
d) Doors and ironmongery
e) Windows and ironmongery
f) Soil/waste manholes
g) Soil/waste drains
h) Sanitary fittings
i) P.C. and provisional sums

10. Never assume any details. In case of doubt, please clarify with the
Architect/Engineers. This can be done by listing all queries on Query List
Forms for confirmation. Any verbal answers to queries must be properly
recorded. At the completion of the bills of quantities preparation, forward a
copy of all queries to the Architect/Engineer for their record.
11. List down all the drawings used for the taking off at the beginning of
dimensions of each element.

8
Measurement of Construction Works IV (QSM551)

12. All dimension sheets must be stamped with job number and title and the
element must be clearly indicated. Each sheet must be serially numbered.

13. During taking off, details of certain sections are not available yet, make To
Take notes on the dimensions so that the sections will not be overlooked
and resulting in non-measurements. Once the details are available and
measurements taken accordingly, the To Take notes shall be lined through
to indicate action has been taken.
14. Do not influence by the B.Q. items in front of you. You may miss new items
required to be measured based on your drawings. Do not assume that
whatever materials specified in previous B.Q. will be used in your present
B.Q. In case of doubt, always seek clarification.
15. During taking off, make notes or sketches on the dimension on items that
have been assumed in the absence of details so that the final accounts can
be prepared with ease.
16. Be careful with taking off especially in the timesing for repetitive items, use
the right set of drawings, booking of dimensions.
17. Once an element is edited, do an overall check on the quantities. Obvious
quantities errors will be detected and corrected before the bill goes to the
tenderers.
18. Once a bill of quantities is prepared and before everything is forgotten, all
dimensions, draft bills, query lists, taking off drawings must be properly
packed in boxes and labeled to avoid any frustrations in locating dimensions,
drawings, etc. in the running of the job by the surveyor who is doing the post
contract work.
19. Do not assume that border line items for any element will be measured by
others. Please check with the other taker off.
20. Any items which need timesing must be noted or done so immediately.
Always check the overall plans for the actual numbers of each items and do
not rely on the details for the number.

Errors in bills of quantities can be originated from any stages in their preparation and as
taking off being the first stage in their preparation, it will definite contribute very much towards
the production of accurate bills of quantities if sufficient care is taken. Always bear in mind
that accurate bills of quantities will greatly save from a lot of embarrassment in explaining
errors, facing litigations and unnecessary worry. On the other hand accurate bills of quantities
will build and maintain a good reputation in the profession.

9
Measurement of Construction Works IV (QSM551)

PILING WORKS

INTRODUCTION

Section E of the Malaysian Standard Method of Building Measurement Second Edition deals
with Piling and Diaphragm Walling.

Basically, the flow of measurement for piling works as stated in the Malaysian Standard
Method of Building Measurement Second Edition as per indicated in the attached Flowchart
of Piling Measurement. The flowchart suggested seven parts of particulars to be inserted in
the Bills of Quantities when measuring Piling Works, namely:

1. Preamble Clauses
2. Types of Piling Operation
3. Plant
4. Main Heading
5. Sub-heading
6. Bodies of Measurement
7. Testing

PREAMBLES CLAUSES

Clauses E.2 and E.3 of the Malaysian Standard Method of Building Measurement Second
Edition deals with Preamble Clauses, which states:

E.2 Soil Description

1. The nature of the ground shall be given in accordance with clause


D.1.1

D.1.1 Particulars of the following shall be given

a. Ground water level and the date when it was


established, hereinafter described as the pre-
contract water level. The ground water level shall be
re-established at the time the various excavation
works are carried out and is described hereinafter as
the post contract water level. Where ground water
levels are subject to periodic changes due to tidal or
similar effects they shall be so described and the
average of the mean high and low levels given.

b. Trial pits or bore holes stating their location.

c. Over or underground services.

2. Where work is to be carried out near canals, rivers, etc. or tidal


waters the levels of the ground in relation to the normal levels of the
canal or river etc. or to the mean levels of high and low tidal waters
shall be stated. Flood levels shall be stated where applicable.

E.3 Starting levels

1. The levels from which the work is expected to begin and from which
measurements have been taken shall be stated. Irregular ground
shall be so described.

10
Measurement of Construction Works IV (QSM551)

Thus, the examples of the Preamble Clauses for Piling Works are as follows:

TYPE OF PILING OPERATION

Clauses E.5.1.a to E.5.1.j of the Malaysian Standard Method of Building Measurement


Second Edition states the various types of piling operation and each shall be given under
separate heading. The types of piling operation are:

1. Bored cast-in-place concrete piles


2. Driven shell cast-in-place concrete piles
3. Pre-formed concrete piles
4. Pre-formed pre-stressed concrete piles
5. Pre-formed concrete sheet piles
6. Timber piles
7. Isolated steel piles
8. Interlocking steel piles
9. Other piles

PLANT

Clause E.4 of the Malaysian Standard Measurement of Building Measurement Second


Edition deals with plant, which states:

E.4 Plant

1. The following items shall be given separately for each type of pile
identified in accordance with clause E.5.1:

a. An item shall be given for bringing to site and removing from


site all plant required for this section of work

b. An item shall be given for maintaining on site all plant


required for this section of the work

11
Measurement of Construction Works IV (QSM551)

Thus, the examples of the description for plants are as follows:

MAIN HEADING

Clauses E.5.1.(i) to E.5.1.(v) of the Malaysian Standard Method of Building Measurement


Second Edition states the various main heading to be inserted within each of the types of
piling operation and each shall be given under separate heading. The classifications of the
main heading are:

1. Preliminary/test piles
2. Working piles
3. Contiguous bored piles
4. Raking piles with 10 inclination angle
5. Raking piles with 20 inclination angle
6. Raking piles with 30 inclination angle
7. Raking piles with 40 inclination angle
8. Piles to be extracted

SUB-HEADING

Clause E.5.2 of the Malaysian Standard Method of Building Measurement Second Edition
states the requirement of sub-heading to be inserted within each of the main heading. The
groups of sub-heading are:

1. nominal cross sectional size


2. the materials of which the piles are composed and in the case of steel piles,
the nominal weight per metre

An example of sub-heading is as follow:

BODIES OF MEASUREMENT

Clauses E.5.3 to E.5.9 together with Clause E.6 are the bodies of measurement that indicate
the items to be measured and to be appeared in the Bills of Quantities within the sub-
heading.

Interlocking Steel Piles

The related clauses in the Malaysian Standard Method of Building Measurement Second
Edition for bodies of measurement for Interlocking Steel Piles are as follows:

E.5 Piling description and measurement

5. In the case of interlocking steel piles, items shall be given for:

a. The total area of piles given in square metres classified into


the following ranges of piles length:

12
Measurement of Construction Works IV (QSM551)

Not exceeding 12.00m


12.00m 24.00m
exceeding 24.00m

b. The total driven area of the piles given in square metres


c. Corner, junction, closure and taper piles, where specifically
required, shall each be given in metres as extra over

7. In the case of pile extensions, items shall be given for:

a. The total number of pile extensions


b. The total length of pile extensions given in metres classified
into the following ranges of pile length:

Not exceeding 3.00m


Exceeding 3.00m

8. The following shall be given in metres:

a. Jetting where specifically required


e. The horizontal length of cutting interlocking piles to remove
tops

9. The following shall be enumerated:

d. Cutting interlocking steel piles to form holes

EXPLANATION ON QUANTITIES
Clause E.8 of the Malaysian Standard Method of Building Measurement Second Edition
states the method of measurement for taking-off quantities for piling works.

The related clauses in the Malaysian Standard Method of Building Measurement Second
Edition for explanation on quantities for Interlocking Steel Piles are as follows:

E.8 Quantities

1. The quantities for piling work shall be calculated as follows:

a. The specified length for pre-formed concrete, timber and


steel piles shall be those which the Contractor is instructed to
provide. Handling, transporting and pitching each length of
pile shall be deemed to be included with the piling items.
b. The driven or bored depth of each pile shall be measured
from the level stated in accordance with Clause E.3 to the
bottom of the toe, to the bottom of the driven casing or to the
bottom of the bored shaft. The measurement for the total
driven depth includes for driving extended piles.
c. The concreted length measured for cast-in-place piles shall
be from cut-off level specifically required to toe level
specifically required and shall include enlarged bases.
d. The areas measured for interlocking steel piling shall be
based on the mean length measured on the centre line of the
piling, over all corner, junction, taper and closure piles.
e. The measurement of pile extensions shall not include length
formed of material arising from cutting off surplus lengths of

13
Measurement of Construction Works IV (QSM551)

other piles. It shall deem to include the work necessary to


attach the extension to the pile
f. Disposal of surplus excavated material including surplus
piles arising from piling operations shall be deemed to be
included with the piling items

SCHEDULE OF PILING WORKS


As mentioned in Lecture Note 1, it is good practice to have the measurement of piling works
of different sizes and length in the form of a schedule. This is because of it is easier and
faster to use the schedule of piling works as the mean of recording measurements in
tabulated form due to measurement a number of items with similar characteristics but varying
components.

The schedule of piling works, therefore, used as the taking off for the relevant piling works
measurement of quantities. Thus, the columns set in the schedule of piling should follow the
taking-off list or the bodies of measurement for piling works.

The attached schedule of piling works is one of the examples for the preparation of the
schedule.

14
Measurement of Construction Works IV (QSM551)

SCHEDULE PAPER
DEPARTMENT OF QUANTITY SURVEYING
FACULTY OF ARCHITECTURE, PLANNING &
SURVEYING
UNIVERSITI TEKNOLOGI MARA, SHAH ALAM

PROJECT: PAGE:
DRAWING NO: DATE:
TAKER OFF:
SCHEDULE OF INTERLOCKING SHEET PILES

Supply Pile (m2) Driving (m2) Acessories (m) Cut-off


Forming
Section Head Remarks
Length Supply n.e. 12m 12m - e. 24m Penetration Holes
Ref. Vertival Raking Corner Junction Closure Taper (m)
length long 24m long long depth (Nos)

15
Measurement of Construction Works IV (QSM551)

MEASUREMENT OF INTERLOCKING SHEET PILE WORKS

Clauses Description Unit

BILL NO. 1 - INTERLOCKING SHEET PILE WORKS (ALL PROVISIONAL)

E2 Preambles Clauses

D1.1a Ground water level

Ground water level was established at 3.00m below existing ground level on 9th
June, 2012 which shall be designated at the pre-contract water level -

D1.1b Trial pits/bore holes

Three numbers bore holes were sunk in positions shown on the location drawings -

D1.1c Existing services

Telephone cables cross over the site of a height of 10.00m on the North side of the
-
site as shown on the location drawing

E2.2 Work near water

The work is to be carried out at a minimum distance of 400.00m from a canal, the
normal level of which is 3.00m below ground level -

E3 Starting level

E3.1 The piling work is expected to starts at and measurement have been taken from
existing ground level -

E5.1h Interlocking Steel Sheet Piles

E4.1a Provision of piling equipment

Allow for bringing to site and removing from site all plant required to this type
of piling Item

E4.1b Maintaining piling equipment

Allow for maintaining on site all plant required for this type of piling Item

E5.1(v) Piles to be extracted/Temporary piles OR Permanent piles

E5.2 Larsen 16W or other equal and approved steel sheet pile including all
necessary strutting and walling (measured nett - no allowance made for laps)

E5.5a Supply steel sheet piles

Total area of piles not exceeding 12.00m long m2


Total area of piles exceeding 12.00m and not exceeding 24.00m long m2
Total area of piles exceeding 24.00m long m2

16
Measurement of Construction Works IV (QSM551)

MEASUREMENT OF INTERLOCKING SHEET PILE WORKS (CONT'D)

Clauses Description Unit

BILL NO. 1 - INTERLOCKING SHEET PILE WORKS (ALL PROVISIONAL) (Cont'd)

Piles to be extracted/Temporary piles OR Permanent piles (Cont'd)

Larsen 16W or other equal and approved steel sheet pile including all
necessary strutting and walling (measured nett - no allowance made for laps)
(Cont'd)

E5.5b Driving

Total driven area m2

Total driven area at a raking ratio of 1 in 5.6715 m2

E5.5c Corner

Extra over for corner piles m

Junction

Extra over for junction piles m

E5.8e Cut-off Head

Horizontal cuttting interlocking piles to remove tops m

E5.9d Forming Holes

Cutting interlocking steel sheet piles to form holes No/Nos

17

You might also like