Professional Documents
Culture Documents
Engineering Structures
journal homepage: www.elsevier.com/locate/engstruct
a r t i c l e i n f o a b s t r a c t
Article history: Prestressed steel trusses can offer efcient structural solutions for long span applications such as aircraft
Received 17 March 2014 hangars, stadia and warehouses. In the current study, the tensile behaviour of prestressed steel elements,
Revised 4 August 2014 which comprise tubular steel members with internal prestressing cables, is investigated. The stability of
Accepted 5 August 2014
the elements under prestress and the loaddeformation response of the prestressed elements to the sub-
Available online 1 September 2014
sequent application of tensile loading are examined analytically, numerically and experimentally, with
good correlation achieved between the three approaches. The benets of prestressing, in terms of
Keywords:
increased member strength and stiffness, are demonstrated, and optimal prestress levels are investigated.
Prestress
Steel
2014 Elsevier Ltd. All rights reserved.
Tension
Cable-in-tube system
Truss
Stability
Analytical
Numerical
Experimental
http://dx.doi.org/10.1016/j.engstruct.2014.08.009
0141-0296/ 2014 Elsevier Ltd. All rights reserved.
J. Gosaye et al. / Engineering Structures 79 (2014) 234243 235
in Section 2. Experimental studies are described in Section 3, while 2.2. Stability under prestress
comparisons between the test and analytical results and discus-
sions thereof, are made in Section 4. Note that although previous Previous analytical studies [22,23] have shown prestressing
research provides an insight into the possible inuence of long- elements (i.e. the cables, in the context of the present study) can
term effects, such as creep and shrinkage, on the response of struc- stabilize their compressed counterparts (i.e. the steel tubes hous-
tures [20,21], these have not been addressed in the present study. ing the cables) provided that there are sufcient connection points
Further research is required on this topic. between the two elements. The connection points have been
shown to offer effective lateral restraint and thus reduce the buck-
ling length of the compressed element. If the cable is in constant
2. Analytical modelling and numerical verication
contact with the tube, cable-in-tube systems have innite connec-
tion points, which implies an innite elastic buckling load [23].
In this section, the key behavioural aspects of prestressed steel
Buckling under prestress would not therefore be anticipated in
elements are described, including their response to prestressing
these systems.
and under the subsequent application of tensile load. The stability
To verify the above analytical ndings, a nite element model
of prestressed elements during the prestressing stage, the optimal
was implemented using the commercial nite element (FE) analy-
level of prestress and tensile capacity are also investigated.
sis software, ABAQUS [24]. The tube to cable cross-sectional area ratio
At =Ac and Youngs modulus ratio Et =Ec were 8.96 and 1.58,
2.1. Axial response under prestress respectively. Prestress was introduced through thermal loading
and the coefcient of linear expansion of the cable, ac , was set as
During the prestressing stage of cable-in-tube systems, a tensile 12 106 K1 .
force, P, is applied to the cable and a compression force of equal In the numerical simulation, truss elements were used to model
magnitude is induced in the tube, as depicted in Fig. 1, where Lo the cables since they can only resist axial forces while beam
is the original length of the cable and tube, xc is the extension of elements, which possess both axial and exural stiffness, were
the cable and xt is the shortening of the tube. used to model the tube. The cable and the tube were attached
When the prestressing process is complete the cable and the using tie constraints at the ends and constraint equations were
tube are locked in position at both ends such that there is no rela- applied at various connection points along the length of the tube
tive movement between the two components, as shown in and cable to prevent relative out of plane motion between the
Fig. 1(c). Since the prestressing force, P, of the same magnitude, two components.
but opposite in direction, is applied to the cable and the tube, The number of connection points was varied between one (at
the prestressed element is self-equilibrated when the tube and mid-length) and three (at quarter points). Finite intervals were
cable are attached at both ends. Therefore, provided no out of plane chosen since in the experimental investigation of Section 3, the
displacements (i.e. no buckling) are induced during prestressing cable was signicantly smaller in diameter than the steel tube
the equilibrium condition for the prestressed system can be stated and connections between the cable and the tube were made by
as in Eq. (1). means of collars spaced regularly along the member length. This
is described in Section 3.
Pcable Ptube K c xc K t xt 0; 1 The numerical modelling was conducted in two stages. In the
rst stage, an elastic buckling analysis of the tubular element
where K c and K t are the axial stiffnesses of the cable and the tube
under the prestressing action of the cable was carried out and
respectively. The respective stiffnesses are given by the following
the buckling mode shapes were obtained. In the next stage, a geo-
expressions:
metrically nonlinear analysis utilising the Riks arc-length solution
Ec Ac Et At technique [25], was performed with the rst eigenmode from the
Kc ; Kt ; 2 elastic buckling analysis as an initial imperfection with an ampli-
Lo Lo
tude of Lo =100000. An incremental prestress was applied to the
where Ec and Et are the Youngs moduli of the cable and the tube cable through thermal loading. As illustrated in Fig. 2, the FE
respectively with Ac and At being the cross-sectional areas of the results are in close agreement with the analytical results and show
cable and the tube respectively. that the buckling load N cr with respect to that of the unsupported
member N E , increases in proportion to 1=L2cr , where Lcr is the spac-
ing between the connection points (or collars).
Lo
2.3. Behaviour of prestressed system under tension
(a) P
xc Analytical expressions for the axial load-displacement equilib-
rium paths of prestressed elements under tensile loading are
Lo derived in this section. Three cases are considered in the following
sub-sections: Case I refers to the scenario where the tube yields
(b) P prior to the cable; Case II refers to where the cable yielding prior
to the tube; and Case III considers the two elements yielding simul-
xt taneously. The case which actually arises depends on the geomet-
Lo ric and material properties of the tube and cable, and the level of
prestress, as described in the following sub-sections.
(c)
2.3.1. Case I: Tube yields prior to cable
The three stages of behaviour that occur for Case I are illus-
xc x t
trated in Fig. 3, where the adopted notation is dened. The ratios
Fig. 1. (a) Force diagram of cable during prestress; (b) force diagram of tube during of geometric and material properties between the tube and cable,
prestress; (c) tube and cable locked in position after prestress. as well as the level of applied prestress determine whether the
236 J. Gosaye et al. / Engineering Structures 79 (2014) 234243
18
Analytical: 3 collars
16
Tube
14 FE: 3 collars
N Lcr
12
10 Analytical: 2 collars
N/N E
Cable
8
FE: 2 collars
6 Analytical:1 collar Connection
point
4 (collar)
FE: Tube only FE: 1 collar Analytical:Tube only N Lcr
2
0
0 10 20 30 40 50
Axial displacement (mm)
(a) (b)
Fig. 2. Buckling response of tubular elements under the action of prestressing forces induced through cables connected to the tubular elements at regular intervals along the
length. (a) Analytical and numerical results for buckling behaviour of prestressed element. (b) Buckled conguration of tubular element with one connection point to
prestressing cable.
Start of stage 1: axial force and it will continue to store tensile strain energy, under
Lo-xt Tube increasing N. In the sign convention adopted, positive values
Cable denote tension and elongation and negative values denote com-
(a) Stage 1: N pression and shortening, with the axial displacement x1 measured
from the state of the system at the end of the prestressing process.
x1=xty+xt Stage 1 applies from the onset of loading until the tube yields in
tension at x1 xty xt , as seen in Fig. 3(a). During this stage, both
Start of stage 2: the tube and the cable remain elastic and the total potential energy
Lo+xty function V for the system can be expressed thus:
1 1
V K c x1 xc 2 K t x1 xt 2 Nx1 : 4
(b) Stage 2: N 2 2
An expression for the equilibrium path for this loading stage, Eq. (5),
x2=(xcy-xc)-(xty+xt) is then obtained by differentiating the total potential energy func-
tion V with respect to the axial generalised coordinate, x1 , and sat-
Start of stage 3: isfying the equilibrium condition by setting the resulting expression
Lo+(xcy-xc-xt) to zero:
N K c K t x1 : 5
(c) Stage 3: N
The forces in the tube Nt and cable N c can therefore be expressed as:
x3=xf -(xcy-xc) Nt K t x1 xt ; 6
Nc K c x1 xc : 7
Fig. 3. Generalised coordinate denitions for Case I. Note: displacements in each
stage are expressed with respect to tube deformation.
2.3.1.2. Stage 2: From tube yielding to cable yielding
0 6 x2 6 xcy xc xty xt . In the second stage, as shown in
tube yields before the cable or vice versa. The tube yields prior to Fig. 3(b), the tube has yielded while the cable continues to store elas-
the cable if: tic tensile strain energy as before. This stage continues until the
f cy P f ty P cable yields at an axial displacement relative to the state of
> ; 3 the system at the end of prestressing x1 xcy xc or, relative to
Ec Ac Ec Et At Et
the end of Stage 1, at an axial displacement x2 xcy xc xty xt .
where f cy and f ty are the yield stresses of the cable and the tube The potential energy V now becomes:
respectively. 1 2 1 1
V K c xc xty xt x2 K t x2ty K t xty x2 K st x22 Nx2 8
2 2 2
2.3.1.1. Stage 1: Onset of loading until tube yielding 0 6 x1 6 xty xt .
and the applied load N with the component forces Nt and N c are
The prestressed element, with the tube initially in compression and
given thus:
the cable in tension, both of magnitude P, is subjected to a tensile
load N as shown in Fig. 3. N K c xc xty xt K t xty K c K st x2 ;
The initial compressive axial force in the tube unloads until a
Nt K t xty K st x2 ; 9
tensile displacement of xt is obtained, from which point the tube
is in net tension. The cable, on the other hand, has an initial tensile Nc K c xc xty xt x2 ;
J. Gosaye et al. / Engineering Structures 79 (2014) 234243 237
where K st is the stiffness of the tube after yielding allowing, where Table 1
appropriate, for strain hardening. Analytical solution for tensile response of prestressed elements in Case II.
Stage Onset of loading until cable yielding: 0 6 x1 6 xcy xc
2.3.1.3. Stage 3: From cable yielding to fracture 0 6 x3 6 xf 1
xcy xc . This is the nal stage of loading, in which both the N K c K t x1
N t K t x1 xt
tube and the cable have yielded, and are potentially strain harden- N c K c x1 xc
ing, as shown in Fig. 3(c). The axial displacement x3 is measured
Stage From cable yielding to tube yielding:
from the position at which the cable yields, i.e. at the end of Stage 2
0 6 x2 6 xty xt xcy xc
2. Stage 3 continues until either fracture of the tube or, more likely, N K c xcy K t xt xcy xc K t K sc x2
fracture of the cable at a displacement relative to the state of the
N t K t xt xcy xc x2
system at the end of prestressing being: N c K c xcy K sc x2
P P Stage From tube yielding to fracture: 0 6 x3 6 xf xty xt
xf Lo cf or Lo tf ; 10 3
Ac Ec At E t
N K c xcy K t xty K sc xty xt xcy xc K sc K st x3
where cf and tf are the fracture strain of the cable and tube respec- N t K t xty K st x3
tively. Following similar procedures to the previous loading stage,
N c K c xcy K sc xty xt xcy xc x3
the expression for V is:
1 1 1
V K c x2cy K c xcy x3 K sc x23 K t x2ty K t xty xcy xc
2 2 2
1 2
xty xt x3 K st xcy xc xty xt x3 Nx3 11 Start of stage 1:
2 Lo-xt Tube
and the applied load, together with the component forces, are given Cable
thus: (a) Stage 1: N
N K c xcy K t xty K st xcy xc xty xt K sc K st x3 ;
x1=xcy-xc
Nt K t xty K st xcy xc xty xt x3 ;
Nc K c xcy K sc x3 ;
Start of stage 2:
12 Lo+(xcy-xc-xt )
where K sc is the stiffness of the cable after yielding. Note that post-
fracture of either component (cable or tube), the load is carried by (b) Stage 2: N
the remaining component, with N N c or N N t , depending on
which component fractures rst. x2=(xty+xt)-(xcy-xc)
Force (kN)
the tube and tension in the cable. In the next step, the load was
applied incrementally through displacement control until the ulti- 300
mate load of the prestressed system was reached.
Two levels of preload were considered, both to compare the
200
analytical and numerical results as well as to illustrate the funda- Cable
mental mechanics of the prestressed element under different pre-
stress levels. Fig. 5 shows the results obtained for a system with no 100 Analytical
prestress. Numerical
The numerical and analytical models may be seen to be in very 0
close agreement. For the chosen section properties, the rst reduc- 0 5 10 15 20 25 30
tion in stiffness occurs when the tube yields, while the ultimate Axial displacement (mm)
load is reached once both components have yielded. The tube
yields prior to the cable since the chosen cable has a lower Youngs Fig. 5. Tensile performance of a prestressed element with zero initial prestress.
modulus and a higher yield strength than the tube. The drop in
stiffness of the system due to the yielding of the tube is greater
550 Prestressed system
than the case when the cable yields since the axial stiffness ratio
K t =K c 9:2. Analytical (prestressing )
The results for the second preload condition, where the optimal Analytical (loading ) 450
preload P opt;t determined from Eq. (15) was applied, are shown in Numerical (prestressing)
Tube
Fig. 6. The material and geometrical properties are again as given Numerical (loading) 350
in Table 2, and close agreement between the analytical and numer-
Force (kN)
ical results may be observed. During the prestressing process the 250
cable is subjected to tensile forces and the tube is subjected to
compressive forces of the same magnitude. These preload forces, 150
Cable
along with the corresponding displacements, are plotted in Fig. 6
following the sign conventions dened in Section 2.3.1. 50
For this prestress level, Fig. 6 shows that the initial stiffness of
-15 -10 -5 -50 0 5 10 15
the system is maintained until the ultimate load is reached, at
which point both the cable and the tube yield simultaneously. As
a result of maintaining the initial stiffness, the displacements -150
required to reach the ultimate load are minimised. Increasing pre- Axial displacement (mm)
stress levels beyond Popt;t would have the effect of yielding the
Fig. 6. Tensile performance of a prestressed element with P opt;t initial prestress.
cable prior to that of the tube and thereby increase the displace-
ments at ultimate load, while a lower prestress also results in
higher displacements at ultimate load, but now due to earlier
programme were the prestress level, the presence of grout and
yielding of the tube.
the tube to cable cross-sectional area ratio, At =Ac . The cross-section
used for all specimens was a cold-formed and seam welded
3. Experimental study 60 60 4 square hollow section (SHS) of grade S355 steel. The
cables were 7 wire prestressing strands of grade Y1860S7 steel.
An experimental study was performed in the Structures The adopted test specimen labelling system is explained in Fig. 7
Laboratory at Imperial College London to verify the analytical and a full list of the test specimens and their properties is given
and numerical ndings for the tensile performance of prestressed in Table 3. Note that three target prestress levels were considered:
cable-in-tube systems. Material testing, prestressing operations Pnom ; 12 Popt;t and P opt;t where Pnom is a nominal prestress of 5 kN to
and the tensile member tests are described. ensure that the cables were not slack during grouting and Popt;t is
the optimum prestress described in Section 2.3.3. The achieved
3.1. Introduction (measured) levels of prestress are given in Table 3 and differ
slightly from the target values.
A total of 7 cable-in-tube specimens were tested: 4 being
non-grouted and 3 being grouted. The key variables of the test
3.2. Material tests
Table 2
Properties of prestressed element in the analytical and numerical model. 3.2.1. Tube
Yield strength of tube, f ty 355 N=mm2 Tensile coupon tests were carried out to determine the basic
Yield strength of cable, f cy 1860 N=mm2 engineering stressstrain response of the SHS tubes used to fabri-
Youngs modulus of tube, Et 210 kN=mm2 cate test specimens. Coupons were cut from the at and corner
Youngs modulus of cable, Ec 200 kN=mm2 regions of the cross-section. All at coupons had a parallel necked
Cross-sectional area of tube, At 879 mm2 region of length 150 mm and width 20 mm. The curved corner cou-
Cross-sectional area of cable, Ac 100 mm2 pons were parallel with a nominal length of 320 mm.
Coefcient of linear expansion of cable, ac 12 106 K1 An Instron 8802 250 kN hydraulic machine was used to carry
Initial length of tube and cable, Lo 2000 mm
out the tensile coupon tests in accordance with EN10002-1 [26].
J. Gosaye et al. / Engineering Structures 79 (2014) 234243 239
Specimen Number of cables Grouted (Y/N) Prestress (kN) At =Ac Fig. 8. End plate bolting arrangement for testing of cable-in-tube systems and
cables alone.
T-1-NG-5 1 N 5P nom 8.8
T-1-NG-68 1 N 680:44P opt;t 8.8
T-1-NG-126 1 N 1260:82P opt;t 8.8
T-2-NG-108 2 N 1080:38P opt;t 4.4 and the cable, which reduces reliance on the end anchorages and
T-0-G-0 0 Y serves to protect the cables from corrosion. Note, however, that
T-1-G-68 1 Y 680:44P opt;t 8.8 long-term behaviour of the grout has not been examined herein.
T-1-G-131 1 Y 1310:86P opt;t 8.8 In this study, a Portland cement-based grout, with plasticiser used
to enhance owability, was used. The water to cement ratio was
0:35. Samples were taken from each grout mixture to test strength
The machine was driven under strain control at a rate of 0.001%/s in accordance with EN 12390-3 [28]. The grout was poured into
up to the 0.2% proof stress and at a rate of 0.002%/s beyond the 0.2% 100 mm cube moulds and were left to dry for one day. The samples
proof stress and up to the ultimate tensile stress, from which point were then removed from the mould and cured in water at room
a strain rate of 0.04%/s was applied until fracture. Two linear elec- temperature. The cubes were tested at various time intervals using
trical resistance strain gauges placed on either side of the coupons an Automax5 testing machine under load-control at a constant rate
and used to measure the strain. The applied load and axial dis- of 3 kN/s. Two samples were tested at each time interval and the
placement and other relevant were recorded at 1-s intervals. The average cube strength f cu is reported in Table 5. The cable-in-tube
measured weighted average (based on the cross-sectional areas specimens were tested 7 days after prestressing and grouting.
of the at and corner regions) tensile material properties of the
tube are given in Table 4 in which E is the Youngs modulus, r0:2
is the 0.2% proof stress, ru is the ultimate stress, u is the percent- 3.3. Preparation of specimens and experimental setup
age strain at the ultimate tensile stress, f is the percentage strain
at fracture over the standard gauge length and n and n00:2;u are the The cold-formed 60 60 4 SHS tubes were cut to the required
RambergOsgood parameters [27]. length of two metres, which is a typical length for a bottom chord
element used in the construction of prestressed truss structures.
The tubes were welded onto 20 mm thick end plates and stiffeners
3.2.2. Cable were added, as shown in Fig. 11, to prevent premature failure at
The nonlinear stressstrain curve for the 7-wire strand cable the ends. The end plates had been drilled to allow the specimens
was determined by testing a representative two metre long sam- to be bolted on to the testing machine directly, as illustrated in
ple. The cable was passed through end plates at either end and Fig. 8.
anchored using barrels and wedges. The end plates were bolted To prevent buckling of the tubes during the prestressing pro-
onto the testing machine using M30 socket head cap screws. cess, specimens with initial prestress levels higher than the nomi-
Fig. 8 shows the end connection for the test specimens, although nal prestress level, Pnom (5 kN), had circular connecting collars
the same end plate bolting arrangement was also used in testing tted to the cables at mid-length and at quarter points, as shown
the cable alone. The test was performed using an Instron in Fig. 9.
2000 kN machine. The machine was driven under displacement The circular connecting collars were machined to an external
control with a constant displacement rate of 0.5 mm/min until diameter equal to the inside dimension of the SHS and had a cen-
fracture. The diameter of each strand was measured and the tral hole to accommodate the cable. The cable, with connecting col-
cross-sectional area of the 7-wire strands cable was determined lars attached at Lo =4; Lo =2 and 3Lo =4 from the member ends, was
by summing up the cross-sectional areas of the individual strands. then inserted into the tube. The buckling length of the test speci-
The recorded axial load and displacement were used together with mens under preload were therefore approximately one quarter of
the measured length of sample and its cross-sectional area to their full length, as discussed in Section 2.2.
determine the experimental stressstrain curve. The measured Prior to the prestressing of the specimens, the xed end anchor
material properties of the cable are also reported in Table 4. was seated by applying an initial prestress of 5 kN. The prestress
was then released to t a wedge at the stressing end of the speci-
3.2.3. Grout mens. Once both anchors were in place, the specimens were pre-
Some of the test specimens were grouted to reect common stressed using a T25 stressing jack. After each specimen was
construction practice. The grout provides a bond between the tube prestressed to the appropriate level, the wedge at the stressing
Table 4
Measured weighted average tensile material properties of the tube and cable.
Table 5
Strength of grout with time.
Fig. 9. Test specimen, also showing cable and connecting collar arrangement.
During prestressing, a load cell was used to monitor the applied 3.5. Experimental results
force, while strain gauges, afxed to the four faces of the steel tube,
were used to verify the force in the tube and to monitor any ex- The full set of experimental results are shown in Fig. 13, which
ure, as shown in Fig. 10. gives the tensile loadextension response of the seven specimens.
The tension in the cables was used to stabilize the compressed The gure illustrates that the test specimens exhibit the character-
tubular specimens during prestressing, with the collars used to istic behaviour predicted by the analytical model discussed in Sec-
transfer the lateral resistance provided by the cable to the tube, tion 2, whereby the addition of a cable increases the member
as discussed in Section 2.2. Fig. 12 conrms the stabilizing effect capacity and increasing the level of prestress up to Popt;t reduces
of the cables during the prestressing process. The strain measure- the displacements required to reach the ultimate load, i.e. the ini-
ments (on the primary vertical axis) and the prestress level (on the tial stiffness is maintained over a greater range. Specimen T-0-G-0
secondary vertical axis) of specimen T-1-G-131, during the pre- may be considered as a control specimen, against which the bene-
stressing stage, are plotted against the elapsed time in Fig. 12 cial inuence of the inclusion of cables and prestressing can be
where a and b are the axial and bending strains respectively. assessed. As discussed in Section 4.2, the presence of grout has a
Fig. 12(a) shows that at an applied prestress level of 96 kN, the relatively small inuence on tensile structural behaviour, though
bending strain was only 13% of the axial strain whereas the bend- a less ductile response was typically displayed by these specimens
ing strain was 27% of the axial strain when a tube of the same prop- (see Fig. 13) and the ultimate displacements were generally over-
erties was tested under an externally applied compression of the predicted by the numerical and analytical models; as shown in
same magnitude. A prestress greater than the target level was ini- Figs. 18 and 19. This may be attributed to non-uniformity of strain
tially applied to the specimens to take account of the unavoidable along the cable length, with high concentrations of strain at crack
loss of a small proportion of the prestress upon jack removal. In locations in the grout prompting premature failure. For the non-
some instances, the jack was removed during the prestressing grouted specimens, the cable capacity was lost through the pro-
operation resulting in a temporary drop in load; an example of this gressive fracture of individual strands followed by fracture of the
can be seen in Fig. 12 at approximately 0.04 h. tube, whereas for the grouted specimens simultaneous fracture
Grouting was carried out after prestressing. Specimens that of all cable strands was observed, which was followed closely by
required grouting had holes in the end-plates to allow the grout fracture of the tube.
Table 6
Summary of measured properties of cable-in-tube test specimens.
SG1
0.0007 120
0.0006 100
Strain,
0.0004
60 SG4 SG2
0.0003
SG 1
SG 3 40
0.0002
SG 2
0.0001 SG 4 20
Prestress
0 0
0.00 0.02 0.04 0.06 0.08 0.10
Elapsed time (hrs) SG3
(a) Strain variations for specimen T-1-G-68 (b) Strain gauge locations (SG).
Fig. 12. Prestress level and exural behaviour of specimens during prestressing stage.
700 600
T-2-NG-108 Symbol FE: applied load
ddd definitions: Analytical:
Cable strand
T-1-G-131 fractures applied load
600 T-1-NG-68
Tube fractures 500
Test: applied load
500
400
Axial force (kN)
T-1-G-68
Analytical: force in tube
T-1-NG-126
0 0
0 20 40 60 80 100 120 140 160 -20 0 20 40 60 80 100
Axial displacement (mm) -100
Axial displacement (mm)
Fig. 13. Loaddisplacement response for all grouted and non-grouted test
specimens. Fig. 14. Experimental results with theoretical and numerical model comparisons
for specimen T-1-NG-5.
600 600
Analytical: applied load Analytical: applied load
FE: applied load FE: applied load
500 500
Test: applied load
Test: applied load
400 FE: force in tube 400 FE: force in tube
Analytical: force in tube Analytical: force in tube
-100 -100
Axial displacement (mm) Axial displacement (mm)
Fig. 15. Experimental results with theoretical and numerical model comparisons Fig. 18. Experimental results with theoretical and numerical model comparisons
for specimen T-1-NG-68. for specimen T-1-G-68.
600
Analytical: applied load 600
FE: applied load Test: applied load Analytical: applied load
500
Test: applied load 500 FE: applied load
300
Axial force (kN)
0 0
-20 0 20 40 60 80 100 -20 0 20 40 60 80 100
-100 Prestressing stage -100
Prestressing stage
-200 -200
Axial displacement (mm) Axial displacement (mm)
Fig. 16. Experimental results with theoretical and numerical model comparisons Fig. 19. Experimental results with theoretical and numerical model comparisons
for specimen T-1-NG-126. for specimen T-1-G-131.
700 load carrying capacity than the single cable specimens, are again
Analytical:
applied load well predicted by the analytical and numerical models.
600 Test: applied load FE: applied load
500
4.2. Grouted specimens
Analytical: force in tube Test: force in cable
400 Analytical: force in cable The loaddeection response of the grouted specimens are
Axial force (kN)
experimentally. For the latter, connecting collars between the [4] Madrazo-Aguirre F, Ruiz-Teran AM, Wadee MA. Dynamic behaviour of steel-
concrete composite under-deck cable-stayed bridges under the action of
cable and the tube located at intervals along the member length
moving loads. Eng Struct 2014 [submitted for publication].
were shown to be able to transfer the restraining forces provided [5] Saito D, Wadee MA. Post-buckling behaviour of prestressed steel stayed
by the tensioned cable to the tube and restrict overall buckling. columns. Eng Struct 2008;30:122439.
Hence, provided the cable is in continuous contact with the tube, [6] Saito D, Wadee MA. Buckling behaviour of prestressed steel stayed columns
with imperfections and stress limitation. Eng Struct 2009;31:115.
or a sufcient number of connecting collars are utilised, buckling [7] Saito D, Wadee MA. Numerical studies of interactive buckling in prestressed
under preload is effectively prevented. steel stayed columns. Eng Struct 2009;31:43243.
An analytical model to predict the tensile loaddeection [8] Saito D, Wadee MA. Optimal prestressing and conguration of stayed columns.
Proc Inst Civil Eng Struct Build 2010;163:34355.
response of the prestressed elements was then established, with [9] Wadee MA, Gardner L, Osofero AI. Design of prestressed stayed columns. J
the key controlling parameters being the yield loads of the tube Construct Steel Res 2013;80:8290.
and cable, the pre- and post-yield stiffnesses of the tube and cable, [10] Ayyub BM, Ibrahim A. Post-tensioned trusses: reliability and redundancy. J
Struct Eng, ASCE 1990;116(6):150721.
and the level of preload. An optimum prestress level, correspond- [11] Han KB, Park SK. Parametric study of truss bridges by the post-tensioning
ing to simultaneous yield of the tube and cable was also dened; method. Can J Civil Eng 2005;32:4209.
at this prestress level, the axial deformation corresponding to the [12] Li H, Schmidt L. Post-tensioned and shaped hypar space trusses. J Struct Eng,
ASCE 1997;123(2):1307.
yielding of the system was minimised. The analytical predictions [13] Schmidt LC, Li H. Studies on post-tensioned and shaped space-truss domes.
were veried by comparison with experimental and numerical Struct Eng Mech 1998;6:693710.
results. The full loaddeection curves determined by means of [14] Hancock GJ, Key P, Olsen CJ. Structural behaviour of a stressed arch structural
system. In: Ninth international specialty conference on cold-formed steel
the three approaches (experimental, numerical and analytical)
structures; 1988. p. 55769.
were shown to be in close agreement, and the benets of the inclu- [15] Clarke MJ, Hancock GJ. Finite-element nonlinear analysis of stressed-arch
sion of the cables and their prestressing, in terms of both enhanced frames. J Struct Eng, ASCE 1991;117(10):281937.
strength and stiffness, were demonstrated. The behaviour of pre- [16] Clarke MJ, Hancock GJ. Simple design procedure for cold-formed tubular top
chord of stressed-arch frames. Eng Struct 1994;16(5):37785.
stressed elements in compression as well as the inuence of [17] Clarke MJ, Hancock GJ. Tests and nonlinear analysis of small-scale stressed-
long-term effects such as creep and shrinkage, are currently being arch frames. J Struct Eng, ASCE 1995;121(2):187200.
investigated. [18] Kyoungsoo L, Ziaul H, SangEul H. Analysis of stabilizing process for stress-
erection of strarch frame. Eng Struct 2013;59(2014):4967.
[19] Ellen PE. Post-tensioned steel structure; 1987.
[20] Bazant ZP. Prediction of concrete creep and shrinkage: past, present and
Acknowledgements future. Nucl Eng Des 2001;203:2738.
[21] Gilbert RI, Ranzi G. Time-dependent behaviour of concrete structures. London;
New York: Spon Press; 2011.
The authors are grateful to S2 Space Solutions for their nancial [22] Magnel G. Prestressed concrete. London concrete publications limited; 1948.
and technical contributions to the project, and would also like to [23] Belenya E. Prestressed load-bearing metal structures. Mir; 1977.
thank the Structures Laboratory technicians at Imperial College [24] Dassault Systemes Simulia Corp. ABAQUS/standard: users manual version 6.6.
Hibbitt, Karlsson & Sorensen, Inc.: Pawtucket, USA; 2006.
London. [25] Riks E. An incremental approach to the solution of snapping and buckling
problems. Int J Solids Struct 1979;15(7):52951.
[26] EN 10002-1. Metallic material tensile testing Part 1: Method of test at
References ambient temperature. European Committee for Standardization (CEN):
Brussels; 2001.
[27] Afshan S, Rossi B, Gardner L. Strength enhancements in cold-formed structural
[1] Ellen ME, Gosaye J, Gardner L, Wadee MA. Design and construction of long-
sections part I: Material testing. J Construct Steel Res 2013;83:17788.
span post-tensioned tubular steel structures. In: Gardner L, editor. Tubular
[28] EN 12390-3. Testing hardened concrete Part 3: Compressive strength of test
structures XIV; 2012. p. 68793.
specimens. European Committee for Standardization (CEN): Brussels; 2001.
[2] Magnel G. Prestressed steel structures. Struct Eng 1950;28:28595.
[29] Han LH, He SH, Liao FY. Performance and calculations of concrete lled steel
[3] Belletti B, Gasperi A. Behaviour of prestressed steel beams. J Struct Eng ASCE
tubes (CFST) under axial tension. J Construct Steel Res 2011;67:1699709.
2010;136(9):11319.