You are on page 1of 9

SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

PILING WORKS (PROVISIONAL)

PRECAST REINFORCED CONCRETE PILE

PAYLENGTH

Unless otherwise described, pile shall be deemed to be


cast in ordinary portland cement. Price for supply of pile
shall include for casting off site and all necessary
formwork including forming of chamfered corners,
reinforcements, lifting toggles, pile shoes, extension
cap and base plates, mortices for and including
centering bar.

Reinforcement in pile shall include for all necessary


spacer fork.

(i)
The paylength for supply of piles be measured in
linear metre, commencing from cut-off level to toe
of pile when the driven to set. The cut-off level
shall be 75mm above the base of the capping
beam

(ii)
Driving of piles shall be measured and paid for by
linear metre, measured nett from toe of pile when
pitched to the commencing level i.e. toe of pile
when driven. Fractions of a metre will be
measured to the nearest metre. Mark each pile
with its length in linear metre at 1.00m intervals
for each whole length.

(iii) No diesel drop hammer driving equipment is


permissable in the contract and henceforth, the
rate of driving shall be deemed to include
hydraulic driving equipment.

(iv) The Contractor is to aware of the above condition


and allow all costs thereto in adherence to the
requirement.

To Collection : -
J2/1
SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW (cont'd)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

PILING WORKS (PROVISIONAL) (Cont'd)

PRECAST REINFORCED CONCRETE PILE (Cont'd)

It is the obligation of the Contractor before


commencement and after the completion of the piling
works, but before casting of pile caps to engage a
Licensed Surveyor to set out the correct alignment and
eccentricity of each pile strictly in accordance with the
Engineer's layout drawings or any other drawings
subsequently issued by the S.O. during the progress of
the piling works. In the event that deviation from the
correct alignment does occur and eccentricity of any
such pile does not conform to that shown in the said
drawings, the rectification of such pile will have to be
carried out by the Contractor at his own cost to the
entire satisfaction of the S.O.. If any one pile is
damaged and it has to be replaced by one or more
piles, the Contractors will only be paid for ONE
replacement pile and the Contractor shall bear all other
additional costs including the extra costs of enlarging
the capping beam etc. ITEM - - 1,000.00

B Allow for submission of records of all piles in triplicate


duly signed by the Contractor, Site Supervisor and
S.O.'s representative and delivered to the S.O. as the
work proceed. ITEM - - 1,000.00

C
Allow for the provision of all necessary hydraulic
operated piling equipments, plants, tools and ancillary
equipments and for their transportation to site,
handling, assembling, erecting, dismantling and
removal on completion. ITEM - - 5,000.00

Allow for moving and handling hydraulic operated piling


equipments, plants, tools and ancillary equipments
about the site as often and whenever necessary for the
proper execution and completion of the whole piling
operation including any excavation and filling required
for moving the plants, tools and ancillary equipment
from differing level of the site, erection of any staging
required and dismantling and removal on completion. ITEM - - 3,000.00
To Collection : 10,000.00

J2/2
SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW (cont'd)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

PILING WORKS (PROVISIONAL) (Cont'd)

PRECAST REINFORCED CONCRETE PILE (Cont'd)

BANGLO RS1

Supply, deliver and unload on site 300mm x 300mm


precast reinforced concrete Grade 45 as described
piles.

A Initial pile in 12.00m long


(In No. 21) M 252 55.00 13,860.00

B Extension pile in 3.00m long


(In No. 21) M 63 55.00 3,465.00

Handle, transport and pitch 300mm x 300mm precast


reinforced concrete piles

D Pile for driving singly in 12.00m length (initial/extension) NO 21 4.00 84.00

E Ditto in 3.00m length (initial/extension) NO 21 4.00 84.00

Drive only 300mm x 300mm precast reinforced


concrete piles

F To a depth not exceeding 10.00m M 210 5.00 1,050.00

G Ditto exceeding 10.00m and not exceeding 13.00m M 63 5.00 315.00

H Ditto exceeding 13.00m and not exceeding 16.00m M 42 5.00 210.00


______________________________

J
Single V-butt weld connection 1200mm girth between
chamfered edges of head and base plates of piles
including 32mm diameter mild steel bars, 1000mm long
inserted in and including 500mm deep mortices in head
and base of piles NO 21 6.50 136.50
______________________________

K Cut off and remove surplus length of 300mm x 300mm


precast reinforced concrete pile, strip off pile head and
bend back reinforcement for connection as described NO 21 12.00 252.00
To Collection : 19,456.50

J2/3
SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW (cont'd)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

PILING WORKS (PROVISIONAL) (Cont'd)

PRECAST REINFORCED CONCRETE PILE (Cont'd)

BANGLO RS2

Supply, deliver and unload on site 300mm x 300mm


precast reinforced concrete Grade 45 as described
piles.

A Initial pile in 12.00m long


(In No. 40) M 480 55.00 26,400.00

B Extension pile in 3.00m long


(In No. 40) M 120 55.00 6,600.00

Handle, transport and pitch 300mm x 300mm precast


reinforced concrete piles

D Pile for driving singly in 12.00m length (initial/extension) NO 40 4.00 160.00

E Ditto in 3.00m length (initial/extension) NO 40 4.00 160.00

Drive only 300mm x 300mm precast reinforced


concrete piles

F To a depth not exceeding 10.00m M 400 5.00 2,000.00

G Ditto exceeding 10.00m and not exceeding 13.00m M 120 5.00 600.00

H Ditto exceeding 13.00m and not exceeding 16.00m M 80 5.00 400.00


______________________________

J
Single V-butt weld connection 1200mm girth between
chamfered edges of head and base plates of piles
including 32mm diameter mild steel bars, 1000mm long
inserted in and including 500mm deep mortices in head
and base of piles NO 40 6.50 260.00
______________________________

K Cut off and remove surplus length of 300mm x 300mm


precast reinforced concrete pile, strip off pile head and
bend back reinforcement for connection as described NO 40 12.00 480.00
To Collection : 37,060.00

J2/4
SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW (cont'd)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

PILING WORKS (PROVISIONAL) (Cont'd)

A Allow for preliminary test load of 50 KN (twice working


load) on single 300mm x 300mm precast reinforced
concrete piles. NO 2 4,500.00 9,000.00

B To perform dynamic pile testing on piles to be selected


by the Engineer using the Pile Driving Analyser (PDA)
and to carry out computer CASWAP analysis to
stimulate pile/soil model and load settlement behaviour
of tested pile NO 2 500.00 1,000.00
To Collection : 10,000.00

J2/5
SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW (cont'd)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

PILE CAP

BLOK RS 1

Excavate commencing from formation level and get


out, part return, fill in and ram, deposit and spread in
making up levels where directed within the site and
remainder load and cart away from site

A Pile Cap not exceeding 1.50m deep MC 13 8.00 102.96

B Ditto exceeding 1.50m deep and not exceeding 3.00m MC 2 8.50 14.50

Lean concrete Grade 15-38mm aggregate as described

C 50mm Thick ditto under pile cap MS 9 9.75 83.66

Vibrated reinforced concrete Grade 30-20mm


aggregate as described in:-

D Pile Cap MC 5 270.00 1,316.25

High tensile steel reinforcement bar as described in:-

Pile Cap

E 32mm Diameter KG 383 3.20 1,225.03

F 20mm Ditto KG 140 3.20 448.22

G 12mm Ditto KG 113 3.20 360.54

H 10mm Ditto KG 77 3.20 246.01

J 12mm Diameter as binder KG 28 3.20 88.21

K 10mm Ditto KG 39 3.20 124.75

Sawn formwork as described to:-

L Sides of pile cap MS 31 25.00 770.00

'Rentokil' or other equal and approved anti-termite soil


treatment to be executed by soil treatment specialist
to :-
'Rentokil' or other equal and approved anti-termite soil
treatment to be executed by soil treatment specialist
to :-

M Sides and Bottom of pile cap MS 39 4.50 177.21

To Collection : 4,957.33

J2/5
SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW (cont'd)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

PILE CAP (Cont;d)

BLOK RS 2

Excavate commencing from formation level and get


out, part return, fill in and ram, deposit and spread in
making up levels where directed within the site and
remainder load and cart away from site

A Pile Cap not exceeding 1.50m deep MC 25 8.00 203.40

B Ditto exceeding 1.50m deep and not exceeding 3.00m MC 3 8.50 29.56
deep
Lean concrete Grade 15-38mm aggregate as described

C 50mm Thick ditto under pile cap MS 17 9.75 165.26

Vibrated reinforced concrete Grade 30-20mm


aggregate as described in:-

D Pile Cap MC 10 270.00 2,683.13

High tensile steel reinforcement bar as described in:-

Pile Cap

E 32mm Diameter KG 957 3.20 3,062.56

F 20mm Ditto KG 350 3.20 1,120.55

G 12mm Ditto KG 173 3.20 554.68

H 10mm Ditto KG 118 3.20 378.47

J 12mm Diameter as binder KG 42 3.20 135.71

K 10mm Ditto KG 97 3.20 311.87

Sawn formwork as described to:-

L Sides of pile cap MS 31 25.00 770.00


'Rentokil' or other equal and approved anti-termite soil
treatment to be executed by soil treatment specialist
to :-

M Sides and Bottom of pile cap MS 48 4.50 214.88

To Collection : 9,630.07

J2/7
SECTION 'J2' - PILING AND FOUNDATION WORKS FOR BANGLOW (cont'd)

ITEM DESCRIPTION UNIT QTY RATE AMOUNT


NO. (RM) (RM)

COLLECTION

From Page No. J2/1 -

From Page No. J2/2 10,000.00

From Page No. J2/3 19,456.50

From Page No. J2/4 10,000.00

From Page No. J2/5 4,957.33

From Page No. J2/6 9,630.07

From Page No. J2/7 9,630.07


TOTAL CARRIED TO GENERAL SUMMARY ON PAGE E/1: 63,673.97

J2/7

You might also like