VRV OUTDOOR UNITS

Maintenance Frequency
Description Comment Daily Monthly
1. Compressor Check for undue noise or vibration and
high or low head discharge pressure.

2. Inverter Check frequency steps and linear


control of indoor units.

3. Crankcase Heater Check operation.

4. Solenoid Valve (Balancing Check operation when starting and


pressure, Hot gas bypass) loading/unloading.

5. Outdoor electronic expansion Check control of superheat in relation


valve to the inlet and outlet temperatures of
the heat exchanger.
6. Heat Exchanger Check for damage and/or dust
accumulation. Clean as necessary.

7. Fans and Motors Check bearings and lubricate as


necessary. Inspect and check on fan
guard covers and inspection plates.

8.Solenoid Valves, High Check operation


Pressure Control & Liquid,
Injection
9. Pressure Sensor Check suction pressure for cooling
and discharge pressure for heating.

10. Pressure Switch. High Check for operation.

11. Pressure Switch. Low Check for operation.

12. Thermistors Check readings.


Air/Coil/Discharge/Suction
13. Refrigerant Charge Check for leaks where accessible.

14. Refrigerant Pipework Check for vibration and rectify any


loose or inadequate support/fixing.

15. Insulation Check condition. Repair and reseal as


necessary.
16. Electrical Check for damage to flexible conduits.
Tighten all terminal connections.
Isolate local control panel and inspect
for overheating. Check integrity of
electrical insulation.
quency
Quarterly H Yearly Yearly NOTES
x Check against operating
pressure tables, and record.

x Voltage open no voltage


close.

x 0 pulse close, 2,000 pulse


full open. When cooling stops
200 pulse. When heating stops
0
x Dopulse.
not use CFCs (refrigerant)
for cleaning fins.

x Ensure that all bolts, screws etc


are in place and tight.

x Overheat/overload protection.

x Check fitted securely.

x Opened when the pressure


exceeds 27.5+/- 1.0 kg/cm.
Closed 20.0 +/-1.0 kg/cm2.

x Opened when the pressure


drops below 0+/- 0.2 kg/cm.
Closed 0.6+/- 0.2 kg/cm.

x 3.5 ~ 360k
3.5 ~ 400k
x Pay particular attention to
bolted and flare connected
joints. Any significant shortfall
or frequent topping up may
indicate leakage and should be
reported to client. CFCs must
not be released to atmosphere.

x All pipework joints should be


brazed or welded. To prevent
internal scaling use dry, oxygen
free nitrogen (OFN) during the
jointing process.

x Check all fuses for correct


amperages. Pay particular
attention to contactors and
terminals including thermistor
controls in compressor terminal
box.