You are on page 1of 12

Dolphins

Hamburg-Finkenwerder
Berthing Basin
for Large Vessels
JOB 0185 / 03.02 / TMH
The Hamburg-Finkenwerder berthing basin
for large vessels

An example of the efficient In increasing degree, the port of The waiting berth basin is equipped
combination of flexible steel-pipe Hamburg is also being used by vessels with three berthing dolphins and four
piles with rubber cell fenders on of such draught that they can use the mooring dolphins. Each berthing dol-
berthing dolphins Elbe fairway at high tide only. There is phin is designed for the absorption
a danger of these ships touching the of 330 Mpm, and equipped with a
Over the past few years, the Lower bottom if they are prevented from movable fender panel measuring
Elbe and part of the port of Hamburg reaching their dredged-out berths in 6.10 m x 3.70 m for the transmission
have been dredged to 14.3 m below good time. The berthing basin under of the berthing impact. In addition,
normal sea level. Accordingly, bigger discussion was dredged out to 16.8 m bollards are provided for absorbing
vessels can now enter the port of below normal sea level (2.5 m deeper max. 200 Mp pull from the spring
Hamburg from the open North Sea, than the Elbe fairway) to provide these lines.
approx. 100 km distant. Near Finken- vessels with a suitable berth where
werder, right on the doorstep of they can wait for the next high tide.
Hamburg, a berthing basin for large This depth of water is sufficient for
vessels has been built to permit even empty or partly-laden vessels of up
large tankers to leave the fairway in to 400 000 dwt.
cases where the envisaged berth is
still occupied or low water prevents
further progress.

Fig. 1: The berthing basin for large vessels is located outside the fairway,
immediately in front of the port of Hamburg

2
Fig. 2: Section of the berthing basin at Hamburg-Finkenwerder

The mooring dolphins take the cross


lines and the fore and stern lines.
They are designed to accept a hawser
pull of 400 and 250 Mp. Slip hooks
are provided for holding the hawsers.

All dolphins are equipped with a wor-


king platform, ladders, handrails, and
fendering (Fig. 3).

Fig. 3: Berthing dolphin, designed for an


energy absorption capacity of 330 Mpm

3
Design and construction
of the berthing dolphins

Design work on the berthing dolphins Embedment calculation: Blum method In the initial stage, efforts were made
was based on the following values, Top edge of dolphin pile: +5.7m M.S.L to attain the specified values for
which were determined by the respon- Calculation level: -18.0 m M.S.L. hawser pull and energy absorption
sible authority, the Strom- und Impact point: +2.0m M.S.L. capacity using single-pile elastic dol-
Hafenbau Hamburg (River and Port Point of action, phins. High-tensile fine-grain structural
Construction Authority of Hamburg): hawser pull: +6.0m M.S.L. steel St E 70 was envisaged for the
Coefficient of soil dolphin sections subjected to the
resistance fw: 6.35 Mp/m3 highest stresses. In this context, due
Specified energy consideration had to be given to the
absorption capacity fact that, for this steel grade, a yield
at +2m M.S.L.: 330 Mpm point of 690 N/mm2 (70 kp/mm2) is
Specified hawser pull guaranteed only up to wall thicknesses
at +6m M.S.L.: 200 Mp of 50 mm. The following table shows
Permissible stress: yield point the mechanical properties for high-
tensile fine-grain structural steels D 53
and St E 70.

4
Mechanical properties of high-tensile fine-grain structural steels D 53 and St E 70
Steel grade Wall thickness Tensile strength Yield point Elongation
mm N/mm2 N/mm2 %
(kp/mm2) (kp/mm2)
min. min.

D 53 35 630800 520 14
(6482) (53)

60 630800 510 14
(6482) (52) 14

St E 70* 50 790940 690 12


(8095) (70)
*St E 70 is a water-quenched steel

Fig. 4: The berthing basin for large vessels, with arrangement of the berthing and mooring dolphins

5
Design and construction
of the berthing dolphins (continued)

A review of various pile diameters of material St E 70. However, this been prevented only by using a
(Fig. 5) showed that it is possible to single-pile dolphin would have been very big fender panel designed for
attain the specified energy absorption relatively stiff; it would have had all-round movement to provide load
capacity of 330 Mpm using a single- a high spring constant of about distribution. The pile would have
pile dolphin with a diameter of about 400 Mp/m. Impermissible pressures weighed 85 t.*
2.2 m, a wall thickness of 50 mm, against the ships hull could have

Fig. 5: Comparison of different pipe diameters (heaviest section: 50 mm wall thickness, 70 kp/mm2 yield point)

Fig. 6: Comparison of two different dolphins Fig. 7: Spring characteristic of a rubber cell fender (Bridgestone system)
with the same energy absorption capacity

6
To achieve softer spring reaction, As shown in Fig. 6, the four rubber * At this juncture, attention must be drawn
steel-pipe piles with a diameter of cell fenders make a substantial contri- to the fact that the spring constant must be
viewed together with the depth of water. In
1800 mm and having a more resilient bution towards the overall energy many cases, the water depth exceeds that in
characteristic (spring constant only absorption capacity of the dolphin the Finkenwerder berthing basin under discus-
290 Mp/m instead of 400 Mp/m) were only at an impact load exceeding sion. With very great depths of water and
chosen, and combined with four rub- 240 Mp, or more than 60 Mp per certain soil conditions, pile diameters of 3.0 m
and more can be optimum.
ber cell fenders in each case. Fig. 6 fender element. This is explained by
shows the spring characteristic of this the spring characteristic of the fender
combination, and the spring charac- elements employed (Fig. 7). It can
teristic of a rigid steel-pipe dolphin clearly be seen that once the limit load
with a diameter of 2200 mm. of 71 Mp is exceeded (284 Mp with
four elements) the fender elements
continue to deform without any addi-
tional load being imposed.

Fig. 8: Each longitudinal weld seam is subjec- Fig. 9: Submerged-arc welding of a girth weld
ted to a stringent ultrasonic test using several
probes simultaneously

Fig. 10: X-ray testing of a girth weld Fig. 11: A finished dolphin section ready for
shipment

7
Design and construction
of the berthing dolphins (continued)

Side view

Top view

Fig. 12: Arrangement of the rubber cell fenders between the fender panel and the dolphin pile

8
For economic reasons, the piles 2) It is expendient not to transmit
were assembled from pipe sections the transverse forces acting on
of various steel grades and with the fender panel (vertical and
different wall thicknesses (Fig. 14). parallel to the fender) to the
The overall pile weight was only dolphin pile via the rubber cell
approx. 63 t. elements. With the berthing
dolphins of the Hamburg-Finken-
Various design aspects must be werder berthing basin, these for-
given consideration when using ces must be absorbed by a heavy
rubber cell fenders: steel pin arranged between the
rubber cell elements. This pin
1) Vessels always berth at a certain transmits the forces into the pile
angle. If several rubber cell fen- (Fig. 12). The rubber cell fenders
ders are used as in this case are not capable of transmitting
they are compressed to different these forces on their own.
degrees, and thus make differing
contributions towards the energy
absorption capacity of the dol-
phin. Also, the energy absorp-
tion capacity of the individual
elements must be reduced by
correcting factors for angular
loading, as provided by the rub-
ber manufacturers in their tables.
Fig. 13 shows in schematic form
the varying degrees of compres-
sion of the rubber cell elements
under angular loading.
Fig. 13: Compression of two rubber cell
fenders (Bridgestone system) under
angular loading

Fig. 14: Section arrangement of the


complete dolphin pile

9
Fig. 15: High-capacity tanker in the Hamburg-Finkenwerder berthing basin

10
Notes

11
Thyssen Mannesmann Handel GmbH
Hans-Gnther-Sohl-Strasse 1
D-40235 Dsseldorf
Postal address:
P.O.Box 10 36 51 D-40027 Dsseldorf
Tel.: (*49 211) 9 67-0
Fax: (*49 211) 9 67-78 06
e-mail: offshore@t-mh.com
www.thyssen-mannesmann-handel.de

You might also like